REQUIREMENTS FOR INDOOR INSTALLATION OF PADMOUNTED TRANSFORMERS
|
|
- Barrie Riley
- 6 years ago
- Views:
Transcription
1 REQUIREMENTS FOR INDOOR INSTALLATION OF PADMOUNTED TRANSFORMERS Introduction An applicant applying for permanent electric service who opts to have the padmounted transformers installed inside his building shall be required to provide and construct a transformer vault conforming to the standards of Meralco. In view of the difficulties likely to be encountered by the building owner in providing the required location for the transformer vault inside the building once construction has started, he or his authorized representative should consult Meralco regarding this requirement during the initial design stage of the building. Transformer Vault All padmounted transformers to be installed inside customer-owned buildings shall be contained inside a PEC-approved transformer vault to be provided by the customer/building owner and to be used exclusively for the Meralco equipment. The walls and roof shall be constructed using reinforced concrete ( buhos ) not less than 150 mm thick. The floor shall have adequate strength for the load imposed on it and shall be not less than 100 mm thick reinforced concrete when in direct contact with earth or not less than 150 mm thick when located above another storey. Floor finish shall be trowelled smooth and painted with one coat of polyurethane sealer and two coats of epoxy dustproof coating. There shall be a maximum of two (2) padmounted tranformer units in a vault. Generally, the minimum required dimension for the vault shall be 5 m (width) X 4 m (depth) for one (1) three-phase padmounted transformer or 8 m (width) X 4 m (depth) for two (2) three-phase padmounted transformers units. This assumes that a 3-m clear space in front of the equipment for switching operations can be attained when the transformer access door is open. For 2nd floor and 1st basement installations where this is not possible, a 6-m minimum depth for the vault shall be required. [Exception: For 2nd floor transformer vault where a hatchway is used, the depth required is 8 m.] There shall be no openings, e.g., doors, vents, etc., from the transformer vault to any part of the building interior. All openings of the transformer vault shall only lead to the outside of the building. The customer shall be required to provide a concrete pad for the padmounted transformer, 75- mm height. A 150-mm high door sill shall be provided by the customer as part of the transformer vault liquid confinement area. Adequate and permanent ventilation to the outside air in the form of louvered vents shall be required to be provided by the customer as part of the transformer vault design. The vents shall have a combined net area of opening (less the area occupied by the louvers) of not less than 20 sqcm. per kva of the transformer bank capacity installed. For adequate natural air circulation, the intake and exhaust vents shall be located on opposite sides of the padmounted transformer with half of the total area of openings situated near the floor (intake vent) and the other half near the ceiling (exhaust vent). Where the location of the transformer vault will not allow adequate natural circulation of air, or where the minimum required area of ventilation opening cannot be attained, the customer shall be required to provide an exhaust fan per transformer bank installed. In addition, G.I. sheet exhaust
2 duct shall be installed on top of the transformer tank to the exhaust fan. To avoid unnecessary operation, the fan shall be temperature-controlled with switching ON setting of 40-deg. C (104-deg. F). A by-pass switch (test switch) shall be provided in the vault so that Meralco maintenance crew can, from time to time, check the operation of the exhaust fan. Power consumption and maintenance of the fan shall be assumed by the customer. Typical transformer vault layout for one padmounted transformer installed at the ground floor is shown below. For typical transformer vault layout for two padmounted transformers installed at the ground floor, please contact your nearest Meralco s Sales Office. Typical transformer vault layouts for one and two padmounted transformer(s) installed on the 2nd floor and 1st basement are also available.
3
4 LEGEND: EF EXHAUST FAN: FOR FORCED AIR VENTILATION; TEMPERATURE-CONTROLLED; DIRECT DRIVEN BY TOTALLY ENCLOSED MOTOR WITH GRAVITY TYPE DAMPERS. THE FAN SHALL BE RATED ¾ HP, 71 CU.M/MIN ( MM (1/8 IN) STATIC PRESSURE. ED EXHAUST DUCT: MADE OF G.I. SHEET, GAGE 20. DW TA DOORWAY: FOR PERSONNEL ACCESS FROM THE OUTSIDE OF THE BUILDING, 0.8M WIDE X 2.0M HIGH X 3.2 MM THICK STEEL DOOR, OUTWARD SWING WITH 150MM HIGH DOOR SILL. THE DOOR SHALL BE FITTED WITH A LATCH DEVICE FOR MERALCO PADLOCK. IT SHALL BE PROVIDED WITH A PANIC BAR DESIGNED TO OPEN THE DOOR OUTWARD UNDER SIMPLE PRESSURE DURING EMERGENCY. TRANSFORMER ACCESS DOOR: 3.0M WIDE X 2.5M HIGH X 3.2 MM THICK, STEEL DOORS; DOUBLE OUTWARD SWING WITH 150MM HIGH DOOR SILL FOR EQUIPMENT IN AND OUT ACCESS. THE DOORS SHALL BE LOUVERED AT THE LOWER HALF AND SHALL BE FITTED WITH A LATCH DEVICE FOR MERALCO PADLOCK. DS DANGER SIGN: TO BE PAINTED AND/OR POSTED AT THE STEEL DOOR. T GR TRANSFORMER: PADMOUNTED, COMPARTMENTAL TYPE, DEAD FRONT, 3-PH., 60 HZ. LESS-FLAMMABLE LIQUID-FILLED; EQUIPPED WITH PRESSURE-RELIEF DEVICE, EXPULSION FUSES AND CURRENT LIMITING FUSES; BUILT IN ACCORDANCE WITH ANSI C , LATEST REVISION. GROUND ROD: GALVANIZED STEEL ROD, SIZE 25MMØ X 3 M LONG, OR EQUIVALENT. GL GROUND LEAD: SIZE 100MM² (AWG #4/0) BARE, STRANDED, SOFT-DRAWN COPPER, FROM GROUND ROD TO GROUNDING SYSTEM INSIDE THE TRANSFORMER VAULT. GW FD BE CP GROUND WIRE: SIZE 100MM² (AWG #4/0) BARE, STRANDED, SOFT-ANNEALED COPPER, CONNECTING THE TRANSFORMER NEUTRAL TO THE GROUND LEAD INSIDE THE TRANSFORMER VAULT. FLOOR DRAIN: FOR DRAINAGE OF ANY ACCUMULATION OF WATER IN THE TRANSFORMER VAULT; 200 SQUARE X 100 MM DEEP TRAPPED DRAIN WITH STRAINER AND 50MM Ø DRAIN PIPE CONNECTED TO A POSITIVE DRAINAGE SYSTEM OR SUMP FACILITIES. THE FLOOR DRAIN SHALL BE LOCATED WHERE IT SHALL BE VISIBLE AND SAFELY ACCESSIBLE FROM THE DOORWAY. THE DOOR SHALL BE PITCHED TOWARD THE DRAIN. BOLT-EYE: GALVANIZED STEEL, ATLEAST 10,000KG STRENGTH; ANCHORED ON THE WALL 1000MM HIGH. CONCRETE PAD: 75MM HIGH.
5 Location of Transformer Vault The required location for the transformer vault shall be at the ground floor of the building where it can easily be accessed from the outside. This is to ensure ease of installation and future replacement/retirement of the padmounted transformer. In cases where the source of power is coming from networks or underground facilities, 1st basement or 2 nd floor installation may be allowed provided that direct access from the outside of the building for equipment and Meralco personnel can be provided at all times. [Note: Basement location for the transformer vault, i.e., where the building has only one basement, will not be allowed in order to safeguard Meralco s facilities against possible flooding.] For flood-prone areas, padmounted transformer shall only be allowed to be installed on the 2 nd floor. A transformer access doorway shall be provided to be used when conveying the padmounted transformer into the vault. For vaults located on the 2nd floor or 1st basement, a hatchway maybe employed. Transformer access doorways and hatchways shall be readily accessible from the outside of the building at all times. A separate personnel access doorway shall be provided for use exclusively by Meralco crew/contractors conducting regular inspection, vault cleaning, operational switching and maintenance of the padmounted transformer. For vaults located on the 2nd floor and 1st basement, an independent staircase leading to the personnel access doorway shall be provided. The personnel access doorway shall be readily accessible from the outside of the building either directly or by way of the staircase. It shall be provided with a panic bar or a pressure plate or other means that is normally latched but will open the door outward under simple pressure during emergencies. A clear and permanent vehicle access road leading to the transformer vault entrance shall be provided by the customer and available at all times for use of Meralco vehicles. The basic requirement is that during installation or replacement/retirement of the padmounted transformer, the Meralco truck and crane can maneuver and position effectively to load/unload the equipment right outside the transformer vault entrance. A minimum of 6.5-meter road width shall be required. The access road shall meet a minimum 20-ton construction.
6 Hoisting Facility Where the transformer vault is located on the 2nd floor or 1st basement, customers/building owners shall be required to provide and maintain a hoisting facility consisting of an I-beam and chain block with roller with a combined capability of not less than 10 tons. Where the transformer vault is located on the 2nd floor and provided with a transformer access doorway, the hoisting facility shall be installed inside the vault. The I-beam shall extend 1.5 meters outside the doorway. Where the transformer vault is located on the 2nd floor or 1st basement and provided with a hatchway, the hoisting facility shall be installed directly above the hatchway. A clear headroom of 4.0 meters from the bottom of the I-beam shall be required when hoisting facility is provided. This is in order to maintain the desired sling angle of lift of 30 degrees from the vertical when lifting the padmounted transformer at its standard four lifting hooks on top of the tank. A lower headroom will result in a sling angle more than the required which would compress the upper portion of the tank with a force that could compromise the tank s structural integrity. The customer shall submit to Meralco a certification, signed and sealed by a registered structural engineer attesting to the designed lifting capability of the hoisting facility provided. Where the transformer vault is located at the ground floor, customers/building owners shall not be required to provide a hoisting facility inside the vault. Therefore, a 3.0-meter minimum headroom is already adequate for this type of installation. The padmounted transformer shall be rolled to cover the short distance from the vault entrance to the concrete pad using approved type of rollers (i.e., pagong ). Use of any other means for rolling such as steel rods or pipes placed underneath the padmounted transformer is not acceptable. Secondary Main Circuit Breaker The customer shall be required to install a secondary main circuit breaker at the service connection point. This means that direct connection of secondary cables from the transformer to multiple circuit breakers or panel boards of the customer shall not be allowed. In order to limit the length of unprotected secondary cables, the customer shall be required to install his secondary main circuit breaker immediately outside the transformer vault, i.e., in the adjoining room, mounted on the opposite side of the common wall with the transformer vault. Primary and Service Cables Primary cables shall be installed in concrete-encased ducts, 110 mm in diameter, thick-walled, red orange color, made of unplasticized polyvinyl chloride (upvc) in accordance with PNS 14. The thickness of the concrete envelope from the surface of the duct shall be 75 mm. The primary cables shall be supplied, installed and terminated at the primary terminals of the padmounted transformer by Meralco. The service cables shall likewise be installed in concrete-encased ducts, 110 mm in diameter, thickwalled, red orange color, made of unplasticized polyvinyl chloride (upvc) in accordance with PNS 14.
7 Meralco shall supply and install the service cables from the secondary compartment of the padmounted transformer up to the customer s main circuit breaker. The customer s electrical contractor shall be the first to terminate the service cables to their circuit breaker using their own terminal lugs. Meralco shall then terminate the service cables to the secondary terminals of the padmounted transformer.
Electric Service Standards
V: 1 of 6 A. Padmounted Requirements Complete requirements are contained in FPL specifications given to Customers for individual projects. Typical pad mounted transformer requirements include, but are
More informationUNDERGROUND SERVICES SECONDARY
Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-
More informationRESIDENTIAL CONSTRUCTION New Dwellings and Additions
How to Obtain a Building Permit For RESIDENTIAL CONSTRUCTION New Dwellings and Additions MIAMI COUNTY, KANSAS CODE SERVICES DEPARTMENT 201 South Pearl Street, Suite 201 Paola, Kansas 66071-1777 Phone:
More informationCustomer Requirements Customer-owned Transformer Vault Room
Scope This standard documents the requirements for customer-owned vault rooms containing transformers and switches that are owned, operated, and maintained by Tacoma Power. It does not address transformer
More informationMECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement
MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement Draft 11/17/08 Utility transformer issues began surfacing last year with questions of enforcement responsibilities due to utility
More informationDOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES
Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating
More informationRESIDENTIAL BUILDING REQUIREMENTS
RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell
More informationAdvanced Ventilation for Residential applications FBC Res 2010.
Advanced Ventilation for Residential applications FBC Res 2010. Course Description Review of the Residential Ventilation requirements in the Florida Building Code, Residential 2010. I. Introduction Dean
More informationSection BUILDINGS, SHELTERS, ENCLOSURES
Section 13121 BUILDINGS, SHELTERS, ENCLOSURES Part 1 GENERAL 1.1 SECTION INCLUDES 1.2 A. Pre-engineered buildings. B. Pre-engineered shelters. C. Pre-engineered enclosures. D. Electrical wiring and devices
More informationELECTRIC METERING GENERAL
1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 EQUIPMENT 5.0 METER REQUIREMENTS 6.0 METER FACILITIES 7.0 ELECTRICAL CONNECTIONS 2.0 SCOPE This guide covers general requirements and codes for
More information5. AMCA 301 Method of Publishing Sound Ratings for Air Moving Devices. 6. AMCA 500 Test Methods for Louver, Dampers, and Shutters
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationTitle: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards
Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the
More informationRead Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED
Chapter 17 Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.1.1 Applicability The regulations in this chapter apply to any private potable water supply system where plumbing fixtures are
More informationNASHVILLE ELECTRIC SERVICE NON NETWORK VAULT DESIGN GUIDE
NASHVILLE ELECTRIC SERVICE NON NETWORK VAULT DESIGN GUIDE EFFECTIVE JULY 2, 2015 1. PURPOSE...1 2. CUSTOMER RESPONSIBILITY...2 3. DRAWINGS...2 3.1. PRELIMINARY DESIGN DRAWINGS...2 3.2. CONSTRUCTION/APPROVAL
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationSECTION GROUNDING AND BONDING
SECTION 16060 PART 1 GENERAL 1.01 DESCRIPTION A. Section includes requirements for an electrical grounding system, including electrodes, grounding rods, connectors, insulators, equipment grounding and
More informationSECTION COOLING TOWER
PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 26 0526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationDIVISION 11 - EQUIPMENT FOOD SERVICE EQUIPMENT LABORATORY FUME HOODS. A. Design Considerations
DIVISION 11 - EQUIPMENT 11400 FOOD SERVICE EQUIPMENT A. Design Considerations 1. The A/E shall use the services of a food service equipment specialist in preparation of kitchen areas and other food preparation
More informationA. Product Data shall be provided for each type of product indicated.
32 31 13 CHAIN LINK FENCES AND GATES SECTION 1 GENERAL 1.1 SUMMARY This Section includes the following: 1. Chain Link Fences 2. Gates for Chain Link Fences. See electrical specifications for electrical
More informationBasic Service. This Section provides information regarding a. Introduction
Basic Service Introduction This Section provides information regarding a new electric Basic Service for a single phase service less than or equal to 400 amps, and a three phase service less than 50kW.
More informationCommunications Page 1 of 9
Page 1 of 9 Last Update: April 23 rd, 2014 Introduction Design In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a
More informationGENERAL PLAN REVIEW REQUIREMENTS
GENERAL PLAN REVIEW REQUIREMENTS Cover Letter A letter (or an authorized pre-printed form) authorizing CCIS to perform the Plan Review is required. CCIS performs plan reviews for the ICC International
More informationThis guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.
SECTION 14651 FREE STANDING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and industrial
More informationProperty Condition Assessment
Property Condition Assessment Pewaukee, WI 53072 Inspection Date: 1/6/15 Prepared For: Report Number: Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar Dr. Pewaukee, WI 53072
More informationPHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS
1 Introduction 1.1 In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a utility. It should be assumed that all new
More informationBasic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.
Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial
More informationUnderground Service Requirements and Instructions
This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page
More informationSECTION MECHANICAL SPECIFICATION GRIT COLLECTION EQUIPMENT
SECTION 11322 MECHANICAL SPECIFICATION GRIT COLLECTION EQUIPMENT PART 1 GENERAL 1.01 SCOPE There shall be furnished ( ) Grit Separator Mechanism(s) suitable for installation in (a) concrete tank(s) -ft.
More informationDICTATOR Lift Shaft System
DICTATOR Lift Shaft System The Modular Lift Shaft System, also for Retrofitting Certified According to EN 1090 A lift is becoming more and more important for daily life, not only in newly constructed buildings
More informationDiffused Aeration Piping Equipment
1.0 General 1.1. The specifications in this section include all components of the Diffused Aeration System with the exception of the individual diffuser units. Refer to additional specification sections
More informationTelecommunication Spaces
Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137
More informationA-Series Aluminum Gantry Crane
SPANCO PRODUCT SPECIFICATIONS 1 A-Series Aluminum Gantry Crane This guide can be used to prepare a bid specification for the incorporation of an A-Series Gantry Crane into a competitive bid project or
More informationANSI/ ASME HST Performance Standard For Overhead Electric Wire Rope Hoists
SECTION 412213- BRIDGE CRANES Part 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationB. Provide liquid-filled secondary substation transformers as indicated on drawings.
SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED
More informationBASEMENT FINISH CONSTRUCTION PLANS REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS
BASEMENT FINISH REFERENCE: 2015 INTERNATIONAL RESIDENTIAL CODE. PERMITS A construction permit is required. A homeowner may perform the construction work on his own property where he resides, without a
More informationGUIDELINES FOR SANITARY DESIGN AND CONSTRUCTION OF MILK PRODUCTS PLANTS (rev )
Milk and Dairy Food Safety Branch 1220 N Street, Sacramento, CA 95814 GUIDELINES FOR SANITARY DESIGN AND CONSTRUCTION OF MILK PRODUCTS PLANTS (rev. 10-20-2011) The outline below lists sanitary requirements
More informationSECTION CHAIN-LINK FENCES AND GATES 02821/1
SECTION 02821 - CHAIN-LINK FENCES AND GATES 02821/1 PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: 2. Gates: horizontal slide or swing. 3. Fences installed where
More informationCHAPTER 11 CONDUITS AND FITTINGS
CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1
More informationUnderground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11
Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11 Underground Residential Distribution (URD) Index General Discussion... 1-2 Description... 3-7 Drawings (Available
More informationEngineering Design Center. Standard Drawings. 1st Edition -January 2016
Engineering Design Center Standard Drawings 1st Edition -January 2016 Golden State Water Company Standard Drawings 1/11/2016 Table of Contents PART A STANDARD DRAWINGS Section I Pipeline Construction P-1
More informationThis guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.
GORBEL PRODUCT SPECIFICATIONS 2010 Gorbel, Inc., P.O., Box 593, Fisher, New York 14453-0593 PHONE: 800-821-0086, FAX: 585-924-6273; WEBSITE: www.gorbel.com November SECTION 41 22 31PRIVATE FREE STANDING
More informationINTERIOR ENVIRONMENT
CHAPTER 12 INTERIOR ENVIRONMENT > SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern ventilation, temperature control, lighting, yards and courts, sound transmission, room dimensions,
More informationContact Clark Public Utilities Construction Services department at (360) to initiate a request for service.
CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation
More informationInstallation plan. Washer-extractor PW 6107 EL. en - GB M.-Nr / 01
Installation plan Washer-extractor PW 6107 EL en - GB 10.11 M.-Nr. 09 270 450 / 01 M.-Nr. 09 270 450 / 01 2 Technical Datasheet Washer-extractor: Heating: PW 6107 Electric (EL) Legend: Solid circle
More information11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...
Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3
More informationPower Zone Center. Your solution for power distribution and control systems
Power Zone Center Your solution for power distribution and control systems The Strength of One Powerful When you need to install a new power distribution center in your facility, you need it done in fastest
More informationFreight Elevator Series GFM-T
Freight Elevator Series GFM-T Mitsubishi Freight Elevators Can Improve our Goods-Handling Ability Elevator Selection 1. Rated capacity and car size What is the maximum weight or size of goods to be transported
More informationTypical Finished Basement Details
Albemarle County, Virginia Typical Finished Basement Details Based on the 2012 Virginia Residential Code Finished basements must be constructed in conformance with these details. For requirements, details
More informationCardok Sàrl CP37 CH-1295 Tannay Switzerland Phone:
CARDOK CARLIFT with Rigid chains technology Very fast access to underground garages Fast, Silent, Discreet, Design, High-Tech Installation to replace an access ramp on private property Dimensions: (Built
More informationCONDUITS AND FITTINGS
CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit
More informationSECTION SECTIONAL OVERHEAD DOORS
SECTION 08360 SECTIONAL OVERHEAD DOORS PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Doors B. Track and Framing 1.2 RELATED SECTIONS A. Section 04810 - Unit Masonry Assemblies: Prepared opening in masonry.
More informationSECTION PERSONNEL DUTY LOCKERS. 1. FPPL Series Police Personnel Duty Lockers, including the following:
SECTION 10501 PERSONNEL DUTY LOCKERS PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 specifications
More informationALUMINIUM SAND TRAP LOUVER : CONSTRUCTION
ALUMINIUM SAND TRAP LOUVER : CONSTRUCTION RUSKIN sand trap louvers are specially designed to separated the sand and dust from the air. It is effective and necessary to apply for ventilations and inlet
More informationEffective Date: 14-March Table of Contents
Version: 2 Page: 1 of 10 Table of Contents 1.0 Introduction... 2 1.1 Purpose... 2 1.2 Scope... 2 1.3 Definitions... 2 2.0 Guarding of Floor Openings, Wall Openings and Holes... 3 2.1 Stairway Floor Openings...
More informationSECTION AIR DUCT CLEANING
PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Specification Sections, apply to this Section. B. Related Sections:
More informationA/E Design Deliverable Checklist
A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic
More informationSECTION ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING
7160 Krick Rd., Walton Hills, OH 44146 800-321-3827 - Tel 440-439-8650 - Fax 440-439-6889 SECTION 12 48 16 ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING PART 1. GENERAL 1.01 SUMMARY: This section includes
More informationCONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 48-05 Van Dam Street Long Island City, NY 11101 ELECTRIC METER SHOP DEPARTMENT METER ENGINEERING SPECIFICATION MES-350 REVISION 3 June 2016 EFFECTIVE DATE
More informationPASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017
SECTION 10505 - METAL STUDENT LOCKERS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationTraining Certification Categories
Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and
More informationWelcome to Douglas County PUD
Welcome to Douglas County PUD We are committed to providing the best possible utility services at the lowest possible cost consistent with sound business principles. To better serve you, please fill out
More informationWORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00
Description Page No Summary Amount Summary 1/7 230,694.60 22,019.25 22,642.65 2/6 96,801.30 80,150.60 114,056.00 Total Per Unit (MYR) 327,495.90 102,169.85 136,698.65 Total Unit(s) X 1 2 2 Total Per Type
More information2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property
2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical
More informationOne and Two Family Additions
One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri
More informationAnchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi
STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel
More informationSection 2: Underground
Section 2: Underground GENERAL INSTALLATION REQUIREMENTS FOR UNDERGROUND FACILITIES Underground electric service and meter location will be established by NHEC upon site visit. In some instances the type,
More informationBuilding Design Data
Building Design Data.. 1. Building Design The KORE ICF System is designed to meet the requirements of the Building Regulations 1997-2006, in the case of two storeys, single occupancy dwellings. If the
More informationEffective June, Eaton-Durham Model # UTRS223ACH. Siemens, Model # SUAS877-PG. (or Landis & Gyr # UAS877-PG) Milbank. Model # U1980-O.
Siemens, Model # SUAS877-PG (or Landis & Gyr # UAS877-PG) Eaton-Durham Model # UTRS223ACH Milbank Midwest Model # U980-O UTRS223AMEP These are some examples of the single meter sockets we require for underground
More informationSECTION SECTIONAL OVERHEAD DOORS 522 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS. Display hidden notes to specifier. (Don't know how?
SECTION 08360 SECTIONAL OVERHEAD DOORS 522 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Glazed Aluminum
More informationThe Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999
CANADIAN ELECTRICAL CODE 1 The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 Repealed by Chapter E-6.3 Reg 8 (effective June 24, 2003). Formerly Chapter E-6.3 Reg 6 (effective March
More informationInstallation instructions
Installation instructions Holetherm Double-walled flue gas discharge system (DW) 2016 All information in this release is subject to misprints. No liability is accepted for the consequences of misprints.
More informationIntroduction. Disclaimer. Table of contents
Updated July 18, 2012 Introduction The Cambridge Elevating Limited-Use / Limited-Application Elevator is designed to service schools, libraries, low rise, low occupancy commercial buildings, churches and
More informationCITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures
CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person
More informationLarge Basic Service. This Section applies to members requiring new. Introduction. Service Types
Large Basic Service Introduction This Section applies to members requiring new Large Basic electric service installations, greater than 400 amps single phase and greater than 50kW three phase. This Section
More informationBasement Renovation Guide For Residential Dwellings
1 Development Services Department Building Permit & Inspection Services Basement Renovation Guide For Residential Dwellings This document is a guide for home owners and does not cover all possible conditions.
More informationELECTRICAL SERVICE UPGRADE RESIDENTIAL AND COMMERCIAL QUICK INFORMATION REFERENCE
ELECTRICAL SERVICE UPGRADE RESIDENTIAL AND COMMERCIAL QUICK INFORMATION REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2015 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION.
More informationLifting Appliances of Ships and Offshore Installations
CCS Rule Change Notice For: Lifting Appliances of Ships and Offshore Installations Version: May, 2016. RCN No.1 Effective date: 19 May, 2016 Beijing CONTENTS Chapter 3 CRANES, LIFTS, RAMPS AND SELF-LOADING
More informationRESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST
This list is provided as a guide to help you understand the information that must be contained on the construction drawings. This list is not all-inclusive of all building codes but is used as a general
More informationSECTION HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
SECTION 26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and
More informationBILL OF MATERIALS Name of the work: F.T.S Modernisation Work
1 BILL OF MATERIALS Name of the work: F.T.S Modernisation Work Erection,Testing and commissioning of Converter transformer 3 PH,11 KV/2 X 1800 V,4000 KVA outdoor Transformer size of 3150 L X 2800 D X 3200
More informationUFGS (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-26 35 33.00 40 (August 2013) --------------------------------- Preparing Activity: NASA Superseding UFGS-26 35 33.00 40 (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationCentral Dartmouth Section Exterior Envelope Renovations METAL-CLAD WOOD DOORS Page 1 of 5 Dartmouth, NS
Exterior Envelope Renovations METAL-CLAD WOOD DOORS Page 1 of 5 Part 1 General 1. RELATED SECTIONS 1. Section 07 92 10 Joint Sealing 2. Section 08 71 00 Door Hardware 2. REFERENCES 1. American Society
More informationHIGH MAST CAMERA POLE ASSEMBLY GENERAL
10-3.24 HIGH MAST CAMERA POLE ASSEMBLY GENERAL The Contractor must furnish and install the following equipment for high mast camera pole assembly as described herein and as shown on the plans: 1. Camera
More informationFor the 2008 Code, the minimum clear distances were revised to reflect an accurate metric conversion (also known as a soft conversion).
II. 600 Volts, Nominal, or Less 110.26 Spaces About Electrical Equipment. Sufficient access and working space shall be provided and maintained about all electrical equipment to permit ready and safe operation
More informationELM6375DX DRAINABLE ADJUSTABLE LOUVER EXTRUDED ALUMINUM
RUSKIN 3900 Dr. Greaves Rd. Grandview, MO 64030 (816) 761-7476 FAX (816) 966-1655 ELM6375DX DRAINABLE ADJUSTABLE LOUVER EXTRUDED ALUMINUM STANDARD CONSTRUCTION FRAME 6 (152) deep, 6063T5 extruded aluminum
More informatione. Cutouts and Holes for Toilet Accessories: Made to template and edge-reinforced.
TOILET COMPARTMENTS GENERAL INFORMATION 1.1 Unless otherwise directed by CU Facilities toilet compartments shall be floor-supported, and urinal screens shall be wall hung, with anchoring devices and accessories
More informationThree-sided barrier compliant to DIN EN ISO Depending on location, design also as wind protection. Clear height (DH) Three-sided barrier
of 5 Page Car SingleVario 06 Stack Parker 06 50 for vehicle up to 5.00 m = 6 long (50 for vehicle up to 5.0 m 7 long) Depending on location, design also as wind protection. Product Data CONFORMITY 06/06/G63
More information16. Design of Pipeline Structures.
16. Design of Pipeline Structures. a. General. 1) The following guidelines are for the design of structures for water and sewer pipelines including structural concrete and miscellaneous metals design.
More informationSECTION PRE-ENGINEERED MEMBRANE STRUCTURE
SECTION 13125 PART 1 - GENERAL 1.1 SUMMARY A. Section includes the design, engineering, fabrication and erection of a frame-supported, tensilemembrane structure complete with entrance and exit doors and
More informationPRECAST RECTANGULAR CHAMBERS
STANDARD MODELS GENERAL ROUGH SKETCH Available for: Sewer manhole, valve chamber, trouser manhole, and pumping station. Ø60-Ø762 ADJUSTMENT RING 7-00-2-0 20-2 30-60 RING 200-30 60-60 000-220 9ø 6 FLAT
More informationBUILDING CODES & DESIGN CRITERIA
BUILDING CODES & DESIGN CRITERIA Adopted Building Codes: 2006 International Building Code (IBC) 2006 International Residential Code (IRC) 2006 International Mechanical Code (IMC) 2006 International Plumbing
More informationSection SECTIONAL INSULATED STEEL DOORS
1 GENERAL 1.1 GENERAL REQUIREMENTS General Conditions and Division 01 apply to this section. 1.2 RELATED WORK Section 05500: Miscellaneous Metal Fabrication Section 07900: Joint Sealers Section 09900:
More informationCANTILEVER RACK SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE 1.2 APPROVED MANUFACTURER 1.3 REGULATORY ORGANIZATIONS AND GROUPS 1.4 QUALITY ASSURANCE
CANTILEVER RACK SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE This specification is intended to describe the general requirements applicable to a proper structural cantilever rack design. In addition, it is
More informationE-Series Steel Gantry Crane
SPANCO PRODUCT SPECIFICATIONS 1 E-Series Steel Gantry Crane This guide can be used to prepare a bid specification for the incorporation of an E-Series Gantry Crane into a competitive bid project or application.
More informationFairfax County, Virginia
Fairfax County, Virginia Typical Finished Basement Details Based on the 2009 International Residential Code CONTENTS General Requirements... 2 Emergency Escape and Rescue... 2 Wall Construction... 3 Floor/ceiling
More informationPre-Delivery Instructions
Congratulations on your decision to enjoy the finest Aquatic Fitness System available... Welcome to the growing family of ENDLESS POOLS owners. Pre-Delivery Instructions Please take the time to read this
More informationEstimate FOR THE SEPTIC TANK
Estimate FOR THE SEPTIC TANK S.NO ITEM DESCRIPTION. 1 Excavation in soil,soft & hard murum... Qty UNIT Rate Excavation for footing, machine foundation, plinth beams, wall footing, gutters,brick wall, tanks
More informationSECTION VIBRATION ISOLATION FOR PLUMBING PIPING AND EQUIPMENT
SECTION 220550 - VIBRATION ISOLATION FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL REQUIREMENTS 1.1 SUMMARY A. It is the intent of this specification to provide vibration isolation supports for Plumbing
More informationHouston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College
SECTION 323113 - CHAIN LINK FENCES AND GATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More information