Construction Regulations 2014 vs Construction Regulations 2003
|
|
- Abel Fields
- 6 years ago
- Views:
Transcription
1 Construction Regulations 2014 vs Construction Regulations 2003 By Mark Winter Safe Working Practice Tel: / mwinter@safepractice.co.za
2 Why the new Construction Regulations? What are the Main differences between the 2003 and 2014 Construction Regs?
3 Where physical construction work started after 7 th February 2014 itwill fall under the 2003 regs until 7 th August 2014, ie: 6 month lead in. Where physical construction started on or before 7 th February 2014 it will fall under the 2003 regs until 6 th August, 2015, ie: 18 month lead in.
4 2003 Regs an Agent means any person who acts as a representative for a client in managing overall construction work 2014 Regs An Agent means a competent person who acts as representative for the client Competent person must have training, knowledge and experience and, where applicable, qualifications specific to task SAQA registration of training and qualifications and must be familiar with the Act and applicable Regs
5 New Position Introduced: Construction Manager Is a competent person to manage physical construction processes and co-ordinate resources on site No existing SAQA unit standards for training yet Definition of Construction Supervisor now added Is a competent person to supervise construction activities on site
6 Under 2003 Regs was any person who prepared a design, checked and approved a design, arranged for an employee (or person at work under his control) to prepare a design, architects and engineers contributing to (or overall responsibility) for design, surveyors, contractors doing design work, designs temporary work, interior designer, shop fitter or landscape architect Under 2014 Regs must be a competent person
7 Definition of method statement removed in 2014 regs Batching plant now called bulk mixing plant Explosive Powered Tool has been changed to Explosive Actuated Fastening Device Body belts removed from fall prevention equipment definition in 2o14 regs
8 Not much in the way of changes: Medical certs of fitness for all Appointment of Construction Manager, Construction Supervisors No requirement to carry proof of induction anymore, just records on site Site specific safety plans
9 Prepare a baseline risk assessment for the intended construction project Prepare a suitable, sufficiently documented and coherent site specific health and safety specification based on the baseline risk assessment Provide the designer with the health and safety specification Ensure designer takes safety specification into consideration during the design stage Ensure that the designer carries out all responsibilities in Reg 6 Include the safety specification in the tender documents Inspect site at least once every 30 days Copy of safety audit report must be issued to Principal Contractor within 7 days of the audit
10 When there is a fatality or permanent disabling injury on site ensure contractor reports it to DOL and that the report includes measures taken by contractor to make site safer Where more than one Principal Contractor appointed, client must ensure co-operation between Principal Contractor and contractors ref these regs. Client may appoint competent person as agent where notification other than Construction Work Permit application to DOL is required (ie: under reg 4(1)). Note that decision of DOL final if there is a question over whether an agent is required or not
11 Assume responsibility for legal safety obligations of the client. Agent MUST manage h&s on site for the client Agent MUST be registered with SACPCMP this requirement commences August 7, 2015
12 Construction Health and Safety Officer (CHSO) Construction Health and Safety Manager (CHSM) Construction Health and Safety Agent (CHSA) Provision made for candidates in each category
13 Reg 34 only makes mention of Reg 3 and 5(7)(b) which is about the permit and client/agent must be registered in 18 months what about safety officers? do they also have 18 months because Reg 34 does not include them?
14 Experience and qualifications and referrals Professional Registration vs Membership of safety associations Professional Indemnity Insurance Price important but not the deciding factor quality vs price
15 Duties formerly under Reg 9 Structures of 2003 Regs. New section for2014 Regs 1 Incorporate all applicable safety standards into design 2 Take h&s specs into consideration 3 Before tender, make available in a report to client (a) all health and safety information of the design that may effect pricing of the construction work, (b) the geotechnical-science aspects and (c) the loading structure can withstand 4 Inform client in writing of any anticipated dangers or hazards relating to construction, make available all info for safe execution of work upon being designed or when design altered 5 Refrain from including dangerous procedures or materials hazardous to people
16 When mandated by the client: Carry out inspections at appropriate stages to verify construction carried out as per design Stop works not in accordance with design s h&s aspects In final inspection of completed structure, include h&s aspects, declare structure safe for use and issue completion certificate Take ergonomic related hazards into account in design If designer not mandated by the client then client agent must do the above
17 Still requirement for owner to do safety audits once every 6 months for first 2 years, thereafter annually
18 Contractor must notify DOL at least 7 days before work starts, on Annexure 2 if work includes: Excavation work Working at height where there is a risk of falling demolition of structure, or Use of explosives Where contractor constructs single storey dwelling for client who will reside in building, contractor must notify DOL at least 7 days before start of work on Annexure 2
19 The Client must apply for permit within 30 days or more before the start of the construction for a permit if the work: 1. Exceeds 180 days 2. Involve more than 1800 person days 3. Value of contract equals or is higher than R , or has a CIDB grading of level 6 4. This requirement will be in force 18 months from February 10, NOTE: Client MUST appoint a competent person in writing as an agent where a Construction Permit is required
20 Must use a form similar to Annexure 1 A site specific number must be assigned within 30 days of application for permit by Department of Labour This number must be displayed clearly visible at the entrance of the specific site The Principal Contractor must keep a copy of the permit in the safety file. No construction can be performed without the permit. Not transferrable Client must appoint a competent person in writing as an agent where a Construction Permit is required.
21 What documentation needs to accompany the application? Baseline risk assessment Health and Safety Specification Health Safety Plan Proof in writing that an agent has been appointed Proof in writing of letter of good standing Workmen s Comp of P/C Proof that designer has received specs Proof that designer has complied with all the duties in Reg 6 Proof that designer took specs in consideration for design Proof P/C made adequate provision for health & safety Proof P/C is competent and have necessary resources
22 The Principal Contractor must appoint in writing 1 full time competent person as construction manager could this be the site agent? Contractor not required to have this appointment, just the Principal Contractor. The Construction Manager is responsible to manage all construction work on a single site and to ensure h&s compliance In the absence of the Construction Manager the Principal Contractor must appoint an alternate Construction Manager Depending on the size of the project the Principal Contractor can appoint Assistant Construction Managers for different sections, the Construction Manager is however still personal accountable to manage the site The Construction Manager can only manage the 1 site he/she is appointed for
23 A contractor must, after consulting with the client appoint in writing a full time or part time construction health and safety officer (CHSO) The contractor must make sure that the CHSO is registered with SACPCMP and has the necessary competencies and resources A Construction Manager can appoint construction supervisors responsible for construction activities and h&s compliance Competent Assistant supervisors can be appointed by the contractor to assist the Construction Supervisor but the Construction Supervisor stays personally accountable for supervision A Construction Supervisor can only supervise the site for which he/she is appointed unless sufficient amount of construction supervisors have been designated on all the relevant construction sites There are SAQA unit standards available for Con Sups and Ass Sups
24 Risk Assessment: 1 A contractor must consult with h&s committee or trade union or representatives of employees on the monitoring and review of assessment 2 Contractor must review assessment where changes are affected to the design or when an incident occurs Fall Protection: 1 No longer physical or psychological fit but medically fit 2 Must include a rescue plan detailing the necessary procedure, personnel and suitable equipment required to affect a rescue
25 Under 2003 Regs this was a certificate valid for one year issued by an occupational health practitioner for plant operators and persons working at height. Under 2014 Regs this is a certificate specific to the construction work being performed issued by occupational health practitioner in form of Annex 3 (see next slide for example). No certificate validity mentioned. Must a certificate be issued for each site? All contractor s employees on site must have this certificate
26
27 Contractor must: 1 appoint competent person as rope access supervisor with duty to supervise all rope access work and ensure h&s compliance BUT the C/M is not relieved from personal accountability 2 ensure all rope access operators are competent and licensed No rope access work allowed unless: 1 design, selection, use of equipment, anchors complies with SANS 2 there is a site specific fall protection plan by a competent person which includes records for inspection and maintenance of equipment
28 Suspended Scaffold - A contractor must submit a copy of the certificate of system design for every new project. Cranes must now be designed and erected under the supervision of a competent person. A risk assessment and method statement must be developed and applied. A wind speed device must be fitted to the crane to provide the operator with an audible warning when wind speeds are too high
29 Note change in regs: formerly depending on no of workers and duration of work that has been removed as a pre-condition. (a) Shower facilities after consultation with the employees or employees representatives, or at least one shower facility for every 15 persons; (b) at least one sanitary facility for each sex and for every 30 workers; (c) changing facilities for each sex; and (d) sheltered eating areas.
30 Construction vehicles must be inspected daily by the operator or driver, 2003 regs previously required this to be done by a competent person However requirement for workers to wear reflective vests when next to or in road has been removed as a requirement Construction vehicles on public roads must comply with provisions of the Nat Road Traffic Act Tools, materials, etc must be secured and separated by a physical barrier to prevent movement
31 Temporary Works now defined in definitions of new Con Regs 2014 as falsework, formwork, support work, scaffold, shoring or other temporary structures designed to provide support or means of access during construction work Must all scaffolds now have a design by a temporary works designer?
32 Old Formwork and Support work section replaced by Temporary Works section. New requirements for Contractor - Must: Appoint a temporary works designer in writing to design, inspect and approve the erected temporary works on site before use. Note Scaffold is temporary work!! Ensure that: Detailed activity specific drawings kept on site for inspection Temp works design drawings are kept on site Authorisation given by competent person in writing before concrete can be cast Temp works drawing or other relevant document includes construction sequences and method statements Temp works design and drawing only used for its intended purpose and specific portion of site Temp works drawings approved by the temp works designer before erection of any temp works
33 Must ensure: All temp works are adequately designed Designs done with close reference to structural design drawings issued by the contractor Drawings and calcs re the temporary works design are kept at office of the temp works designed Loads of temp works and imposed loads are indicated in the design
34 A Construction Health and Safety Technical Committee has been established consisting of members from DOL, DPW (designated by Built Environment Council and CIDB), Higher Education, SA Property Owners Assoc, Employers Associations, Unions, consultants involved in construction industry and coopted members = 11 + co-opted members
35 Challenges Ahead Very few Safety Agents will qualify as Agents under SACPCMP unless qualifying criteria are relaxed. DOL will be focussing more on role of clients in h&s on site Costs will increase but so will quality and safety standards on sites How to implement the new Regulations on site What to expect from client agents, DOL, project clients. There will be a two tier system for a time - two lead in periods
36 Appoint client agent early in design process to guide you and the client Only issue site specific specifications containing the new 2014 requirements Use Safety Agents who are professionally registered with a voluntary association (eg: Institute of Safety Management) and with verifiable construction experience
(7 February 2014 to date) OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993
(7 February 2014 to date) OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (Gazette No. 14918, Notice No. 1158, dated 2 July 1993. Commencement date: 1 January 1994, except section 1(3): to be proclaimed)
More informationHEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE
HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE The purpose of the health and safety questionnaire is to provide Clients with assurances that all companies on
More informationThe safe management and control of Temporary Works
The safe management and control of Temporary Works What are TW s? The HSE describe Temporary Works (TW s) as; an engineered solution that may include any structure, provision for access, item or technique
More informationWork Health and Safety Management Systems and Auditing Guidelines
Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a
More informationOPTUS SUPPLIER WORK HEALTH & SAFETY POLICY
OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height
More informationClaire Deacon Pr.CHSA MCur (UPE) BSc Med (Hons) Biomedical Eng (UCT) B.Tech OH (Pen Tech) SACPCMP 4 th term Council Member
Claire Deacon Pr.CHSA MCur (UPE) BSc Med (Hons) Biomedical Eng (UCT) B.Tech OH (Pen Tech) SACPCMP 4 th term Council Member United States Department of Labour, 2012) Latest SA CHS statistics 2013-2014 (Furter,
More informationCHAPTER 1 RIGHTS AND RESPONSIBILITIES 1 RIGHTS AND RESPONSIBILITIES. Duties of an Employer. Duties of a Constructor
CHAPTER 1 RIGHTS AND RESPONSIBILITIES 1 RIGHTS AND RESPONSIBILITIES An essential part of Ontario s health and safety legislation is the importance of having a strong "Internal Responsibility System" (IRS).
More informationACT Scaffolding Services LTD METHOD STATEMENT Scaffold erection
Address: 20 Bole Close, Wombwell, Barnsley, South Yorkshire. S73 8AZ Tel: 07883 780704 Email: enquiries@actscaffold.co.uk Web: www.actscaffold.co.uk Project/Contract Boiler Scaffolding Client Example Comp
More informationA2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT:
A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V.2 10.5.17) PROJECT: Oakdale Primary School, Peterborough Extension, Refurbishments and Associated Works.
More informationCHAS Assessment Standards
CHAS Assessment Standards Section 1 - All Prosecutions or Enforcement Notices The Supplier has provided details of any enforcement notices or prosecutions served on them in the last three years by the
More informationH&S007 Level 2 and 3 Risk Health and Safety Contractor Approval Request
Private Bag 9023 Whangarei 0148 New Zealand T: 09 430 4200 0800 WDC INFO 0800 932 463 F: 09 438 7632 W: www.wdc.govt.nz E: mailroom@wdc.govt.nz H&S007 Level 2 and 3 Risk Health and Safety Contractor Approval
More informationSHORT COURSES. Industry Training New Zealand
SHORT COURSES Industry Training New Zealand 2 CONTENTS About Tai Poutini Polytechnic About Training for Industry Short Courses Cranes Truck Mounted Crane Pendant Crane Lifting Loads Telehandler Scaffolding
More informationSITE SAFETY RULES - SILVERSTONE CLASSIC 2018
SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 The following is an outline of the Safe Working Requirements for all Companies, staff and any other persons for this event. Please note that the terms Company
More informationDesigner and CDM Co-ordinator Guidance
Designer and CDM Co-ordinator Guidance Five or more employees 1 CONTENTS INTRODUCTION...4 Further reading / additional resources...4 QUESTION 1: POLICY AND ORGANISATION...5 Guidance...5 What you need to
More informationCampbell Arnott s Contractor Management
Campbell Arnott s Contractor Management Registration process The Campbell Arnott s Contractor Management process is completed in two parts: online company registration and online employee registration
More informationInformation about Administrative Penalties
Information about Administrative Penalties Workplace health and safety is a shared responsibility. What you need to know about Nova Scotia's occupational health and safety administrative penalties On January
More informationMini Tender PART B External Wall Insulation, Mechanical and Electrical Installation
Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation Mini Tender Questionnaire for Subcontractors Section B involves a questionnaire oriented around the provision of key
More informationEDUCATION SUPPORT OFFICER Cardijn College Position Information Document
EDUCATION SUPPORT OFFICER Cardijn College Position Information Document Name: Position Title: Maintenance Officer Employment: Permanent Replacement Temporary x Commencement date: / / 2016 Full Time/Part-time
More informationARBORIST. Job Description
ARBORIST Job Description Employer: City Suburban Tree Surgeons Limited Title of Job: Arborist Grade: A1 A4 Person reports to: Crew Leader / Team Leader / Contract Supervisor Supervises: Ground Persons,
More informationGUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08
CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date
More informationST AUGUSTINE S PARISH SCHOOL
2014 ST AUGUSTINE S PARISH SCHOOL Position: MARKETING & COMMUNICATIONS OFFICER / WHS CO-ORDINATOR Non-Teaching (Permanent) - 35 Hours per Week Subject(s): ESO Grade 4-42 weeks Commencing: 25 Aug 2014 Role
More informationJK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE
THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main
More informationGeneral Installation Conditions
Page 1 of 14 General Installation Conditions AMB 2012 E / Rev 2 Page 2 of 14 Table of Contents 1 General Information 1.1 Terms 1.2 Deviating contractual arrangements 1.3 No validity of deviating conditions
More informationAdelaide Airport Limited
Induction Pack for Contractors Site Rules and Conditions for Contractors Revision: 7 November 2015 Site Rules and Conditions-Adelaide:Legal 42723757_1 1. GENERAL 1 2. BUILDING CONSENT AND APPROVAL 1 3.
More information3: CONTRACTOR HSMS COMPLIANCE AUDIT TOOL
Title: This compliance tool is to be performed on Contractor HSMS plans. It can be used throughout the duration when the contractor submits the generic/specific WHS plan prior to arrival and desktop audit
More informationStandards of Performance. Mariane Ewbank Chairperson Standards and Customs WG
Standards of Performance Mariane Ewbank Chairperson Standards and Customs WG Please hold for instructions to open packs 1 and 2 Can we consider this an official doc???? Second version And this invoice?
More informationMandatory Building Inspection Scheme (MBIS) and Mandatory Window Inspection Scheme (MWIS)
1 Mandatory Building Inspection Scheme (MBIS) and Mandatory Window Inspection Scheme (MWIS) 2 Content Purpose Legislation Key Features of MBIS & MWIS Duties of Registered Inspector Code of Practice for
More informationCorporate Health and Safety Policy July 2012
Corporate Health and Safety Policy July 2012 Contents Page General Statement of Health and Safety Policy and Intent 2 1. ORGANISATION 3 1.1 Elected Members 3 1.2 Cabinet Members 3 1.3 Governing Bodies
More informationNational Road Traffic Act 93 of 96 and its amendments
National Road Traffic Act 93 of 96 and its amendments National Road Traffic Regulations CHAPTER VIII: TRANSPORTATION OF DANGEROUS GOODS AND SUBSTANCES BY ROAD This legislation became effective from 3 August
More informationClick on the relevant state and open the OHS authority website.
Copyright 2011 - OnGuard Safety Training Pty Ltd 1 of 7 Introduction Overview OHS Acts National Codes Codes of Practice Duty of Care Overview Occupational health and safety (OHS) legislation varies in
More informationContractor Management and Purchasing
company workers at risk. Contractors play a significant role in safety and health management at facilities whether there are contract miners or contractors performing project work. They often face very
More informationHFM Asset Management Contractor Induction Queens Riverside Apartments
HFM Asset Management Contractor Induction Queens Riverside Apartments Contents Purpose About HFM Asset Management HFM Asset Management s Responsibilities Contractors Responsibilities Commencing Work Working
More informationDesigner and CDM Co-ordinator Guidance
Designer and CDM Co-ordinator Guidance Fewer than five employees Health and Safety 1 CONTENTS INTRODUCTION...5 Further reading / additional resources...5 Note to suppliers...6 QUESTION 1: POLICY AND ORGANISATION...8
More informationContractor Selection & Management Guideline Rev01. Revision 00. April 2011
Contractor Selection and Management Guideline Revision 00 April 2011 Document Details and Issue Record Rev No. Details Date Author 00 Draft 10/04/2011 CJMD Checked Text Calcs Approved Document Reference:
More informationPosition Description: Client Services Coordinator. headspace Bairnsdale General Manager Operations Date effective October 2016
Position Description: Client Services Coordinator Location headspace Bairnsdale Approval General Manager Operations Date effective October 2016 POSITION SUMMARY The Client Services Coordinator provides
More informationGuidance Note: CSCS Cards
Guidance Note: CSCS Cards Most major contractors and homebuilders require their workforce to hold a valid CSCS card as a demonstration of their commitment to safe and efficient working. To attain a CSCS
More informationTOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:
TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be
More informationCorporate Social Responsibility Policy Statement
Health and Safety Policy Statement Environmental Policy Statement Corporate Social Responsibility Policy Statement Organisation and Arrangements Created Oct 2012 BT/WS Issue 21, Sept 2017 BT/AT Page 1
More informationCONTRACTOR WHS HAZARD STANDARD TRAFFIC MANAGEMENT EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD TRAFFIC MANAGEMENT EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationABIOSH INTERNATIONAL CERTIFICATE IN OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT (ICERT)
ABIOSH INTERNATIONAL CERTIFICATE IN OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT (ICERT) Introduction The International Certificate in Health and Safety was developed because of the need to provide a qualification
More informationSKILLS DEVELOPMENT ACT, 1998 (ACT NO. 97 of 1998) LEARNERSHIP REGULATIONS, 2007
STAATSKOERANT, 29 JUNlE 2007 No. 30010 3 No. R. 519 DEPARTMENT OF LABOUR 29June2007 SKILLS DEVELOPMENT ACT, 1998 (ACT NO. 97 of 1998) LEARNERSHIP REGULATIONS, 2007 I, Membathisi Mphumzi Shepherd Mdladlana,
More informationSubcontractor Project Management Plan
Subcontractor Project Management Plan FOR LAYTON PROJECT: COMPANY: CONTACT NAME: ACTIVITY: Signed Date Written by: Reviewed by: Accepted by: Issue Date Description of Revisions Change Introduced by Change
More informationINJURY AND ILLNESS PREVENTION PROGRAM. Adopted June 25, 1991 by Board Resolution 91-95
INJURY AND ILLNESS PREVENTION PROGRAM Adopted June 25, 1991 by Board Resolution 91-95 Latest Annual Review/Revision December, 2012 TABLE OF CONTENTS 1.0 Introduction... 1 2.0 Definitions... 1 3.0 Policy...
More informationGovernment Decree on the Transport of Dangerous Goods by Air (210/1997; amendments up to 659/2009 included) Section 1 Scope of application (659/2009)
NB: Unofficial translation; legally binding only in Finnish and Swedish Government Decree on the Transport of Dangerous Goods by Air (210/1997; amendments up to 659/2009 included) Section 1 Scope of application
More informationBUILDING ACTIVITY APPLICATION PACKAGE
BUILDING ACTIVITY APPLICATION PACKAGE ADELAIDE and PARAFIELD AIRPORTS FEBRUARY 2016 O:\E&AS\3-93 Page i Contents Page INTRODUCTION 1 SUBMISSION OF APPLICATION 1 Application Information 2 Supporting Documentation
More informationHazardous. Scheme. the power behind your business
Hazardous Areas Scheme YOUR GUIDE TO REGISTRATION the power behind your business GUIDE TO REGISTRATION REQUIREMENTS Electrical work in potentially explosive atmospheres (hazardous areas) is not included
More information9.1 Introduction Legislative requirements for JOHS Committees Composition of JOHS Committee and Safety Sub-committees...
Table of Contents 9.1 Introduction... 2 9.2 Legislative requirements for JOHS Committees... 2 9.3 Composition of JOHS Committee and Safety Sub-committees... 2 9.4 Functions of JOHS Committee... 3 9.5 Roles
More informationSECTION 1: APPLICANT INFORMATION. 1. Have you contacted your local Chapter regarding their established submission process or procedure?
2018 CONSTRUCTION SAFETY EXCELLENCE AWARDS APPLICATION INSTRUCTION STEPS: 1. DOWNLOAD FORM 2. FILL OUT 3. SUBMIT DEADLINE FEBRUARY 2, 2018 SECTION 1: APPLICANT INFORMATION 1. Have you contacted your local
More informationEstablish health and safety requirements
16. 1for Establish health and safety requirements projects The Health and Safety at Work Act (Section 2 (2) (a)) requires that employers should provide and maintain plant and systems of work that are,
More informationImplementing EC Regulation 1071/2009 Rules Concerning the Occupation of Road Transport Operator
Implementing EC Regulation 1071/2009 Rules Concerning the Occupation of Road Transport Operator This is the response of the Royal Society for the Prevention of Accidents (RoSPA) to the Department for Transport
More informationCONTRACTOR SAFETY MANAGEMENT PROGRAM (CSMP) PRE-QUALIFICATION SAFETY QUESTIONNAIRE
CONTRACTOR SAFETY MANAGEMENT PROGRAM (CSMP) PRE-QUALIFICATION SAFETY QUESTIONNAIRE Omitting or reporting false information on this questionnaire could result in disqualification or removal from the Supplier
More informationGUIDELINES FOR DESIGN, FABRICATION AND INSTALLATION OF TENSION MEMBRANE AND SHADE STRUCTURES
GUIDELINES FOR DESIGN, FABRICATION AND INSTALLATION OF TENSION MEMBRANE AND SHADE STRUCTURES First Edition Aug.1986 Revised March 2009, 2010, October 2011 with minor editorial changes in May 2012. This
More informationFACILITY AND GROUNDS MANAGER
CITY OF CITRUS HEIGHTS FACILITY AND GROUNDS MANAGER DEFINITION To plan, organize, direct and coordinate the activities of the Facilities and Grounds Division within the General Services Department including
More informationHealth, Safety and Environmental Manager
Health, Safety and Environmental Manager External Vacancy Post Ref 5881. 37 hours, Permanent. 30,603.00-32,463.42 per annum Sunderland College is seeking to appoint an experienced Health, Safety & Environmental
More informationConstruction OS&H Project planning and control for safe OS&H
Construction OS&H Project planning and control for safe OS&H Summary General principles of project planning and control OS&H by design as a key element of project planning and control OS&H performance
More informationTOWN OF WAYLAND POSITION DESCRIPTION. DPW Water Working Foreman. Department of Public Works. Public Works Director. Teamsters
TOWN OF WAYLAND POSITION DESCRIPTION Title: Department: Appointing Authority: Affiliation: DPW Water Working Foreman Department of Public Works Public Works Director Teamsters Grade: D-11 Personnel Board
More information2016 Port of San Francisco Building Code
PORT CODE PROCEDURE NO. : DATE : December 5, 2012 SUBJECT : Permit Process; Inspection TITLE : Special Inspection and Structural Observation Procedures PURPOSE : The purpose of this Port Code Procedure
More informationCITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application
CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application Good for 90 days from the Date Issued This permit is only required if the work location is owned or controlled by the City of Homestead and
More informationAPPLICATION FORM FOR FILMING IN THE PUBLIC DOMAIN IN THE ADMINISTRATIVE AREA OF DUBLIN CITY COUNCIL
APPLICATION FORM FOR FILMING IN THE PUBLIC DOMAIN IN THE ADMINISTRATIVE AREA OF DUBLIN CITY COUNCIL APPLICATIONS MUST BE RECEIVED AT LEAST 10 WORKING DAYS IN ADVANCE OF THE DATE PERMISSION IS REQUIRED
More informationKane County Deputy Registrar s Handbook Issued by: Kane County Clerk
Kane County Deputy Registrar s Handbook Issued by: John A. Cunningham Kane County Clerk COUNTY OF KANE John A. Cunningham Kane County Clerk 719 S. Batavia Ave., Bldg. B Geneva, IL 60134 Phone: (630) 232-5990
More informationEmployers' Guide to Road Safety Requirements
Employers' Guide to Road Safety Requirements The Occupational Health and Safety Regulation (OHSR) sets out requirements that apply to road safety and workrelated driving. Tables below identify measures
More information9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:
SECTION 9. COMMERCIAL WIND ENERGY FACILITIES 9.1 Purpose. The purpose of this Section 9 of the Zoning Bylaw is to provide by special permit for the construction and operation of commercial wind facilities
More informationFOR THE SELF-CERTIFICATION PERMIT PROGRAM ISSUED BY THE DEPARTMENT OF BUILDINGS
FOR THE SELF-CERTIFICATION PERMIT PROGRAM ISSUED BY THE DEPARTMENT OF BUILDINGS CONTENTS Overview... 2 Part I: General Provisions... 2 A. Definitions... 2 B. Scope and Effect... 4 Part II: General Self-Certification
More informationQuality, Health, Safety & Environment Manual
Page 1 of 14 DOCUMENT RELEASE AUTHORIZATION Prepared, Reviewed and Issued by: Management Representative: ( ) Approved by: Chairman and Managing Director ( ) Issued as: CONTROLLED COPY / UNCONTROLLED COPY
More informationSocial Sector Accreditation Standards Level 4
Social Sector Accreditation Standards Level 4 Introduction These standards for accreditation are produced by the New Zealand Government for the accreditation of providers funded to deliver social services.
More informationControl of Equipment on Masts, Towers and Rooftops BOP018.8
Control of Equipment on Masts, Towers and Rooftops BOP018.8 1.0 Introduction This document defines the rules to be followed for all works on Arqiva owned or managed sites/structures that have a structural
More information2014Construction Code: Chapter 33 Key Revisions
Robert D Alessio Department of Buildings Senior Executive Director Engineering and Safety Operations New York University-Kimmel Center Tuesday, March 24, 2015 2014Construction Code: Chapter 33 Key Revision
More informationABOUT US. We operate on a nationwide basis and have built up an impressive portfolio of clients in the public and private sectors.
ASBESTOS MANAGEMENT ABOUT US Clifford Devlin has been providing specialist services to manage asbestos for over 25 years. The company is licensed by the Health & Safety Executive (HSE) to remove and dispose
More informationDIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT
DIEMERSFONTEIN WINE & COUNTRY ESTATE BUILDING CONTRACTORS CODE OF CONDUCT 1. CODE OF CONDUCT AGREEMENT The building contractor is a builder/contractor ( the contractor ) appointed by the owner ( the employer
More informationINDUSTRIALIZED HOUSING AND BUILDINGS Administrative Rules of the Texas Department of Licensing and Regulation 16 Texas Administrative Code, Chapter 70
INDUSTRIALIZED HOUSING AND BUILDINGS Administrative Rules of the Texas Department of Licensing and Regulation 16 Texas Administrative Code, Chapter 70 TABLE OF CONTENTS 70.1. Authority... 1 70.10. Definitions...
More informationLearning Exchange: Training Programmes Guide Table of Contents
Learning Exchange: Training Programmes Guide Table of Contents Frequently Asked Questions... 2 1. Which legislation guides driver and operator training?... 2 2. How does TETA fit into the picture?... 2
More informationINTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol
INTERNATIONAL CYANIDE MANAGEMENT INSTITUTE Cyanide Transportation Verification Protocol For The International Cyanide Management Code www.cyanidecode.org December 2016 The International Cyanide Management
More informationCONTINENTAL FERRY PORT SITE INDUCTION
CONTINENTAL FERRY PORT SITE INDUCTION Port activities As landlord of the Commercial Port, the Port Authority must be informed of all works conducted on these premises The Authority is committed to the
More informationPermit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:
Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,
More informationContingent Workforce Solution (CWS) Programme
Contingent Workforce Solution (CWS) Programme United Kingdom November 2017 Introduction 3M recognises the flexibility that can be gained through the engagement of temporary workers and how important they
More informationWinstone Aggregates. Page 2 of 14
Attachment 1 to Fletcher Building Submission Submission to the Ministry of Business, Innovation and Employment on Government s Proposed Changes to the Health and Safety in the New Zealand Mining Industry
More informationBox Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments
Box Clever Consulting Executive Summary Project Report July 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 05/08/17 Strand Plaza - Liverpool Status Report @ End of
More informationCDM-C Guidance. Five or more employees. Health and Safety 1. CMD-C Guidance Notes V
CDM-C Guidance Five or more employees Health and Safety 1 CONTENTS INTRODUCTION...4 Further reading / additional resources...4 QUESTION 1: POLICY AND ORGANISATION...5 Guidance...5 What you need to provide...6
More informationSee revision section. Resources, Roles, Responsibility, Accountability, and Authority. Section in OHSAS 18001:2007
1. PURPOSE The purpose of this document is to identify occupational health and safety roles and responsibilities at each function and level within the City of Dallas in accordance with the requirements
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER
More informationYour Checklist Guide for Effortless Crane Hire
Your Checklist Guide for Effortless Crane Hire (Plus Frequently Asked Questions) There are 6 key Processes that can make your Crane Hire experience effortless if we work together to manage them efficiently:
More informationGUIDELINES FOR DESIGN, FABRICATION AND INSTALLATION OF TENSION MEMBRANE AND SHADE STRUCTURES
GUIDELINES FOR DESIGN, FABRICATION AND INSTALLATION OF TENSION MEMBRANE AND SHADE STRUCTURES First Edition Aug.1986 Revised March 2009, 2010, October 2011 with minor editorial changes in May 2012. This
More informationElectrical Safety Management Plan (ESMP)
Electrical Safety Management Plan (ESMP) CONTENTS 1 INTRODUCTION 4 1.1 Purpose 4 1.2 Background 4 2 OBJECTIVES OF THE ESMP 2.1 Electrical Safety Policy 2.2 Electrical Safety Goals 2.3 Objectives 5 5 5
More informationLevel 2 NVQ Certificate in Erection of Precast Concrete (Construction)
Level 2 NVQ Certificate in Erection of Precast Concrete (Construction) Qualification Specification ProQual 2016 Contents Introduction 3 Qualification profile 3 Qualification Structure 4 Pathway 1 Flooring
More informationNATIONAL BUILDING REGULATIONS AND BUILDING STANDARDS ACT, 1977 (Act No. 103 of 1977)
FORM 1 To: NATIONAL BUILDING REGULATIONS AND BUILDING STANDARDS ACT, 1977 (Act No. 103 of 1977) DECLARATION BY PERSON RESPONSIBLE FOR PREPARING AN APPLICATION FOR APPROVAL OF THE ERECTION OF THE BUILDING
More informationARTICLE 38: AIR QUALITY ASSESSMENT AND VENTILATION REQUIREMENT FOR URBAN INFILL RESIDENTIAL DEVELOPMENTS
San Francisco Health Code ARTICLE 38: AIR QUALITY ASSESSMENT AND VENTILATION REQUIREMENT FOR URBAN INFILL RESIDENTIAL DEVELOPMENTS Sec. 3801. Sec. 3802. Sec. 3803. Sec. 3804. Sec. 3805. Sec. 3806. Sec.
More informationGUIDE FOR APPLICANTS
GUIDE FOR APPLICANTS This guide has been prepared to assist you in applying for a position with Port of Newcastle. Prior to completing your application, please read the following information to gain an
More informationVerify Category A Audit Content
Verify Category A Audit Content V10.0 Achilles Group Limited, 2014. All rights reserved. Objective The objective of this document is to provide suppliers who have registered for a Verify Category A (V10.0)
More informationSupplier handbook Solaris Bus & Coach S.A.
Solaris Bus & Coach S.A. This handbook is the property of Solaris Bus & Coach S.A. Any modification or distribution without written permission is prohibited. Table of Contents 1. Introduction...2 1.1.
More informationTransport Sector Portfolio
Transport Sector Portfolio Rehabilitation of 4.476 Kms of Asphalt Road in Shindand District, Herat Province, Afghanistan. United Nations Office for Project Services ( UNOPS ) -and- Name of Contractor Site
More informationOffice. Recruitment activities are performed in compliance with Federal and State Equal Employment
CHAPTER 2 - RECRUITMENT AND EMPLOYMENT Section 2.10 - Recruitment: All Administrator/Staff recruitment activities are to be conducted through the Human Resources Office. Recruitment activities are performed
More informationPolicy Work Health and Safety (WHS) RCPA Introduction WHS legislation
Policy Subject: Work Health and Safety (WHS) Approval Date: July 2011, December 2014 Review Date: July 2018 Review By: Board of Directors Number: 1/2011 The Royal College of Pathologists of Australasia
More informationHSE statement on radiation protection advisers
HSE statement on radiation protection advisers The requirements of this Statement came into effect on 31 March 2007 Purpose Introduction Criteria of core competence Assessing bodies Suitable RPA's Annex
More informationEARLY START PERMITS. Site cleaning, including removal of any existing asphalt, and/or concrete slab, Excavation work under the building footprint,
INFORMATION BULLETIN / PUBLIC - BUILDING CODE REFERENCE NO.: LAMC 91.106.4 Effective: 01-01-2017 DOCUMENT NO.: P/BC 2017-097 Revised: Previously Issued As: P/BC 2014-097 EARLY START PERMITS Los Angeles
More informationUNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN
UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 1 July 2014 Approved Plan Jon Fahie This, the University
More informationBHC-P-03.1 Training, Competence and Induction
BHC-P-03.1 Training, Competence and Induction Contents 1.0 Purpose 2.0 Scope 3.0 Definitions 4.0 Main requirements 5.0 Guidance documents and references 6.0 Appendices Revision register Date Version Description
More informationHOUSING COORDINATOR (HOUSING REPRESENTATIVE)
DEFINITION: To perform a variety of duties involved in assisting low income persons in locating and maintaining decent, safe and sanitary housing in the private rental market. SUPERVISION RECEIVED: Receives
More informationAsbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22
Page 1 of 22 Asbestos Survey Project Summary Pursuant to your request; Environmental, Inc., has performed an Asbestos Building Survey on 8/13/2014 and limited to the above referenced location. The Interior/Exterior/Roof
More informationHealth and Safety Policy
Health and Safety Policy Policy Volume Policy Chapter Responsible Committee/Unit/Division/Faculty Responsible Chairperson/Director/Manager E: General Institutional Policies & Protocols E.1 RU Safety Health
More information