Precast segmental design and construction in China

Size: px
Start display at page:

Download "Precast segmental design and construction in China"

Transcription

1 Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN Precast segmental design and construction in China Dong, Xu, Huichi Li & Chao Liu Dept. of Bridge Engineering, Tongji University, Shanghai, China ABSTRACT: In 2001, Liuhe River Bridge in Shanghai was the first span-by-span precast segmental bridge constructed by a launching gantry in China. In 2003, Humin Viaduct in Shanghai was the first project using short line segment casting for urban elevated viaducts. The biggest PC beam bridge using balanced cantilever precast segmental construction in China is Jiujiang Bridge in Guangdong province, which has two 160 m main spans and was completed in In July 2001, the first 4-span cable-stayed bridge in China, Yiling Bridge in Hubei province, using precast segmental PC box girder construction, was completed. Although China has these successful references, the precast segmental construction, originated from the contractor system, was not well followed in time by design codes. Lack of specified design codes in China usually causes owners and even designers hesitate to use this construction method. Longitudinal mild reinforcing bars do not continue through the joints. The new concept of making closed horizontal shear reinforcement, with the addition of normally arranged vertical stirrups, to carry the horizontal and vertical components of the diagonal tensile stress was proposed in the reinforcement design of precast segments for the approach bridges of the Sutong Bridge. 1 INSTRUCTIONS Precast segmental construction for prestressed concrete bridges has been widely used in the world. This method has many advantages, such as qualityguaranteed standard precast segments, fast speed construction time and the least site work. Lots of prestressed concrete bridges in the world were built by precast segmental construction method in recent 20 years [1]. Although more and more precast segmental bridges have been successfully built in China, this construction method is still relatively new to Chinese engineers. One reason is that the precise control of the dimensions of the bridge makes the construction much more complicated. Another reason is that the precast segmental construction method, originated from the contractor system, is not well followed in time by design codes. This construction method even well influences the structural design including the profiles of internal and external prestressing tendons, the detail dimensions of segments and the arrangements of segments and deviators, etc. Due to these reasons, lack of the regarding specified design codes usually causes owners and even designers to hesitate to use this construction method. 2 RECENT CONSTRUCTION REFERENCES IN CHINA 2.1 Precast segmental span by span construction New Liuhe Bridge in Shanghai The new Liuhe Bridge in Shanghai consisted of 3 42 m single spans. The bridge had dual carriageways, each of which included 3 lanes of traffic. The upward bridge was m in width, while the downward bridge was m. In order to be familiar with the design method of segmental construction with external prestressing, the precast segmental construction was adopted. The upward and downward bridges consisted of two parallel single-cell box girders, respectively. Each box girder was longitudinally divided into 13 segments. The weight of a single span was 515 tons, and the weight of a 3.33 m standard segment was 40 tons. The bridge segments were precasted with long-line method. A launching gantry was used to carry and install all the segments into a span. This bridge was the first span-by-span precast segmental bridge constructed by a launching gantry in China, as shown in Figure 1. Mixed tendons were used for the longitudinal prestressing in the bridge. Most 795

2 Figure 1. New Liuhe River Bridge, installation of precast segments. Figure 3. Humin Viaduct, installation of precast segments. Figure 2. New Liuhe River Bridge, external tendons. of the prestressing tendons were internal bonded tendons, while four 19T15 external unbonded tendons were used in each span, occupying 24% of the whole prestressing in a single span, as shown in Figure 2. The bridge was completed in Oct Humin Elevated Viaduct in Shanghai Humin Elevated Viaduct in Shanghai was the second bridge using span-by-span precast segmental construction using launching gantry in China, as shown in Figure 3. The total length of the viaduct was 5.56 km and the average span was m. The 30 m spans were made of 11 precast segmental box girders, while the 35 m spans were made of 13 ones. The girder segments were 25 m in width, 2.1 m in height, 2 m, 2.5 m and 3 m in length. The weight of the precast segments at pier tops was up to 130 tons and the standard segments were about 110 tons. The segments were short line precasted. Figure 4 shows the external tendons and deviators in this bridge. Although half of the 5.56 km viaduct was designed to adopt this method, most of the spans were built by the traditional monolithic scaffolding construction because of the restricted construction period. Only Figure 4. Humin Viaduct, external tendons and deviators. Figure 5. Second Jiujiang Bridge. two sections were left to use precast segmental construction, one in the main viaduct and another in a ramp. Each section included ten spans. The whole viaduct, which has an appealing arc bottom shape, was completed in the end of

3 Figure 8. Launching gantry to assemble the segments. Figure 6. Approach bridges in deep water. Figure 9. Installation of the deviator segment. Figure 7. Precast segments storage yard. 2.2 Precast segmental balanced cantilever construction Second Jiujiang Bridge At present, the biggest bridge using precast segmental balanced cantilever construction in China was the Second Jiujiang Bridge, completed in 1996 and located in Guangdong Province, as shown in Figure 5. The main bridge had 6 spans (50 m m m m + 50 m), including the two biggest 160 m precast segmental spans. In this bridge, the maximum cantilever length reached to 78.5 m, leaving a 3 m cast-in-situ closure. The width of the deck segments was m. All the prestressing system was internally arranged Deep water approach bridges of the Sutong cable-stayed bridge Sutong Bridge, with a total length of 8146 m over the Yangtze River including a 1088 m cable stayed main span, was completed on June 28, 2007 and will open to traffic at the end of April this year. The approach spans were wholly prestressed concrete continuous beams including about 25 spans of 75 meters in deep water (Fig. 6). Short line segment precasting and balanced cantilever construction were adopted (Fig. 7). Launching gantry was used to assemble the cantilever segments, as shown in Figure 8. The bridge is the largest bridge project using precast segmental cantilever construction, launching gantry assembling and short line precasting in China. Special segments, including the anchorage segments and deviator segments (Fig. 9) were carefully designed and precasted. In order to keep the weight of all segments within 150 tons, the anchorage cross beam, which occupies half of the weight of the pier segment, is casted in-situ. Each span consists of six 25T15 external tendons. A new external prestressing system was adopted in this bridge. The adopted external prestressing system was developed by the joint R&D center supported by OVM (Liuzhou) Machinery Co. Ltd. and Tongji University, as shown in Figure 10 and Figure 11.The system uses unbonded monostrands and has two features. The first is the deviator device, which can comb the individual monostrands and guide 797

4 Figure 10. External prestressing tendons. Figure 13. Profile of the deviator after testing. Figure 11. External prestressing tendons. Figure 14. Connection of the deviator and the straight part. Figure 12. Detail of the deviator of the system. them one by one in deferent vertical and lateral curvatures (Figs 12 13). The second feature is that the straight part of the tendon profile does not need to be grouted (Fig. 14). It significantly reduces the self weight of the tendons and facilitates the inspection and monitoring of the strands during service time (Fig. 15). 2.3 Precast segmental cable-stayed bridge Yunyang Bridge over the Hanjiang River Yunyang Bridge, completed in 1993 and located in Hubei Province, was a P.C. cable-stayed bridge with double pylons. The bridge was the first long span earth anchored prestressed concrete cable stayed bridges in Figure 15. Easy inspection of the tendons. China, with 3 spans (86 m m + 86 m). The concrete girder was box-section with three cells, using three-dimension prestress technology. The length of the segments were 3.7 m and 4.3 m and the maximum weight of the precast segments was around 100 tons. (Fig. 16) Yiling Bridge over the Yangtze River Yiling Bridge, crossing Yangtze River in Yichang City in Sichuan Province, was a 4-span cable-stayed bridge 798

5 Figure 16. Figure 17. Yunyang Bridge under construction. Yiling Bridge. with 2 main spans of 348 m and side spans of 120 m with a total length of 936 m. The concrete girder was three cells box-girder, which was 23 m in width. The precast segments were 3 m in length. The cast-in-situ length of the main girder was 131 m on both side spans and 22 m around the central pylons; the two 324 m main spans were precasted and erected using the balanced cantilever method. (Fig. 17) 3 SOME TECHNICAL CONSIDERATIONS 3.1 Flexural behavior For externally prestressed concrete structure, the flexural resistance in ultimate stage has relationship with many factors, including span depth ratio, the distance between deviators, the type of external prestressing strands, i.e., bonded or unbonded, etc. Joint is also a major factor influencing the flexural behavior of precast segmental structures. Although FEM method has become popular for analysis, the numerical model for joints is difficult to make. Meanwhile, designers used to get a quick estimation of the flexural ultimate carrying capacity of the bridges, especially in preliminary stage. As a matter of fact, section equilibrium method can be borrowed from the calculation of internally prestressed concrete structures to calculate the flexural ultimate carrying capacity of externally unbonded prestressed concrete structures. The key factor to use this simplified method is to get the ultimate stress increment of external prestressing tendons at the ultimate stage. Although many codes in the world include those equations, they are quite different because many parameters that have influences on the ultimate stress of external prestressing tendon cannot be totally simulated in experiments. Zero ultimate stress increment was recommended for the external tendons in Sutong approach bridges. Although a little bit conservative, it was practical and not a controlling factor in this case because the unbonded monostrands external system were adopted and much more internal tendons than external tendons were used in the mixed tendon arrangement in the design. In China, there are already some theoretical and experimental achievements in the design theories of the flexural behavior for monolithic and precast segmental construction. Some numerical analysis models considering the geometric and material nonlinear, as well as the joint mechanism have been developed. In order to create more precise numerical models, which can reflect the mechanism of joints between segments, further research and experimental tests are still being made. The technical guides are hopefully to be issued based on these researches in the following years. 3.2 Reinforcement design near joints of the precast segments in Sutong Bridge Although dry joints between precast segments have been used in a lot of bridges around the world, the mechanism of this kind of construction is still not very clear, especially the shear strength. Fortunately, if the glued and multiple-key joints are used between precast segments, the web crack pattern will be the same as that in the monolithic structures in ultimate stage [3]. Nevertheless, there is still a concern that because longitudinal mild reinforcing bars do not continue through the joints in precast segmental bridges, minor deficiency of shear resistance might happen in the local areas along the joints. In order to minimize the uncertain area as much as possible, in the design of the reinforcement near joints of the precast segments in the Sutong approach spans, horizontal reinforcements were suggested to be made closed so as to get enough development length similar to the vertical stirrups as in Figure

6 Bridge, made Chinese Engineers to be more familiar with this construction method. At the same time, the theoretical and experimental research achievements will further accelerate the establishment of the detailed specifications for the design and construction of precast segmental bridges. REFERENCES Figure 18. Reinforcement arrangement in a web near joints of the precast segments. 4 CONCLUSIONS [1] Naaman, A.E. & Breen, J.E External prestressing in bridge. ACI Detroit: SP 120. [2] Xiang Hanfan Major Bridges in China, Compilation Board of Major Bridges in China. Beijing, China: The People s Transportation Press. [3] Podolny, W. & Muller, J.M Construction and Design of Prestressed Concrete Segmental Bridges. New York, USA. Practical experiences gained from major engineering projects, especially in the approach spans of Sutong 800

SECTION 1 INTRODUCTION TO POST-TENSIONED CONCRETE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE

SECTION 1 INTRODUCTION TO POST-TENSIONED CONCRETE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE SECTION 1 INTRODUCTION TO POST-TENSIONED CONCRETE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE NOTE: MOMENT DIAGRAM CONVENTION In PT design, it is preferable to draw moment diagrams to the tensile

More information

Behavior of a multiple spans cable-stayed bridge

Behavior of a multiple spans cable-stayed bridge Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Behavior of a multiple spans cable-stayed bridge S. Arnaud, N. Matsunaga, S. Nagano

More information

The Europe Bridge in Portugal: concept and structural design

The Europe Bridge in Portugal: concept and structural design Journal of Constructional Steel Research 60 (2004) 363 372 www.elsevier.com/locate/jcsr The Europe Bridge in Portugal: concept and structural design A.J. Reis a,b,, J.J. Oliveira Pedro a,b a GRID-Consulting

More information

THE EUROPE BRIDGE, IN PORTUGAL: THE CONCEPT AND STRUCTURAL DESIGN

THE EUROPE BRIDGE, IN PORTUGAL: THE CONCEPT AND STRUCTURAL DESIGN THE EUROPE BRIDGE, IN PORTUGAL: THE CONCEPT AND STRUCTURAL DESIGN A.J.Reis 1,J.J.Oliveira Pedro 2 ABSTRACT The Europe bridge is a cable stayed bridge with a main span of 186m. A 3D stay cable arrangement

More information

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1 Department of Civil Engineering Lecture 2.1 Methods of Prestressing Advantages of Prestressing Section remains uncracked under service loads Reduction of steel corrosion (increase durability) Full section

More information

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

More information

MIDAS Training Series

MIDAS Training Series MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session

More information

ULTIMATE LOAD-CARRYING CAPACITY OF SELF-ANCHORED CONCRETE SUSPENSION BRIDGE

ULTIMATE LOAD-CARRYING CAPACITY OF SELF-ANCHORED CONCRETE SUSPENSION BRIDGE ULTIMATE LOAD-CARRYING CAPACITY OF SELF-ANCHORED CONCRETE SUSPENSION BRIDGE Meng Jiang*, University of Technology Dalian, P. R. China Wenliang Qiu, University of Technology Dalian, P. R. China Lihua Han,

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

In-plane testing of precast concrete wall panels with grouted sleeve

In-plane testing of precast concrete wall panels with grouted sleeve In-plane testing of precast concrete wall panels with grouted sleeve P. Seifi, R.S. Henry & J.M. Ingham Department of Civil Engineering, University of Auckland, Auckland. 2017 NZSEE Conference ABSTRACT:

More information

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG CONCRETE SPLICED GIRDERS IN TEXAS Nicholas Nemec, P.E. TxDOT-BRG October 15, 2014 What is a Concrete Spliced Girder? 2 What is a Concrete Spliced Girder? What it is NOT : Continuous For Live Load 3 What

More information

DEVELOPMENT OF ACCELERATED BRIDGE CONSTRUCTION DETAIL FOR SEISMIC REGIONS. W. Phillip Yen 1 and Amjad Aref 2

DEVELOPMENT OF ACCELERATED BRIDGE CONSTRUCTION DETAIL FOR SEISMIC REGIONS. W. Phillip Yen 1 and Amjad Aref 2 DEVELOPMENT OF ACCELERATED BRIDGE CONSTRUCTION DETAIL FOR SEISMIC REGIONS Abstract W. Phillip Yen 1 and Amjad Aref 2 This paper provides an overview of current research in development of the seismic detailing

More information

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE By Masakazu Matsubara Resident Engineer for Approach & Main Bridge Suramadu Bridge Project 1. DESIGN 1.1. Concept of Design of Cantilever Erection

More information

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Design of continuity slabs and the 020 Gajanan Chaudhari Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Anand Panpate Senior Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

More information

Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey

Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey International Symposium on Industrial Chimneys and Cooling Towers, Prague, Oct 8-11, 2014 Construction Techniques of The 3 rd Bosphorus Bridge in Istanbul, Turkey M. Orçun TOKUÇ 1 and Tamer TUNCA 2 1 Engineer

More information

Design strategies for the future

Design strategies for the future Design strategies for the future Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Expansion joints with low noise emission T. Spuler,

More information

Project Reference Catalogue

Project Reference Catalogue Bridge Bridge Taiwan High Speed Rail, Advancing Shoring Method Taiwan High Speed Rail Corporation. Over 127 km of 13 wide prestressed concrete viaducts were constructed; and 9 contractors designed and

More information

Construction of the Superstructure of Major Sea Crossings

Construction of the Superstructure of Major Sea Crossings Construction of the Superstructure of Major Sea Crossings Matt Carter Associate Director 2 nd International Seminar on Design & Construction of Second Penang Bridge 2 Second Penang Bridge Donghai Bridge

More information

Executive Summary. Champlain Bridge Approach Spans Edge Girder Condition Assessment and Rehabilitation Requirements.

Executive Summary. Champlain Bridge Approach Spans Edge Girder Condition Assessment and Rehabilitation Requirements. Executive Summary "Les Ponts Jacques Cartier et Champlain Incorporée" (PJCCI) requested that Buckland & Taylor (B&T) study the overall condition of the approach span edge girders of the Champlain Bridge

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES

REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES Benjamin Raison R; Freeda Christy C PG student, School of Civil Engineering, Karunya University. Associate Professor, School of Civil Engineering, Karunya

More information

Service life extension of existing precast concrete girders

Service life extension of existing precast concrete girders Concrete Repair, Rehabilitation and Retrofitting II Alexander et al (eds) 29 Taylor & Francis Group, London, ISBN 978--415-4685-3 Service life extension of existing precast concrete girders D.I. Banic,

More information

Parametric Study of Continuous Concrete Beam Prestressed with External Tendon

Parametric Study of Continuous Concrete Beam Prestressed with External Tendon Parametric Study of Continuous Concrete Beam Prestressed with External Tendon Assistant Professor, College of Engineering, Diyala University, Iraq ABSTRACT This paper presents the results of a parametric

More information

French bridges experiences from prefabricated deck elements. Stockholm, march 4th, 2009

French bridges experiences from prefabricated deck elements. Stockholm, march 4th, 2009 French bridges experiences from prefabricated deck elements. Stockholm, march 4th, 2009 Born 1957, TPE civil engineering degree 1979. He joined SETRA in 1980. Experience in steel bridges, and their pathology.

More information

2. Strelasund Crossing

2. Strelasund Crossing 2. Strelasund Crossing Objektplanung Eisenbahnprojekte 2. Strelasund Crossing The new section of the Baltic motorway A20 from Lübeck to Stettin also included construction of the Rügen link road B96n Stralsund/Rügen

More information

Bijan Khaleghi, Ph, D. P.E., S.E.

Bijan Khaleghi, Ph, D. P.E., S.E. 0 Submission date: July, 0 Word count: 0 Author Name: Bijan Khaleghi Affiliations: Washington State D.O.T. Address: Linderson Way SW, Tumwater WA 0 INTEGRAL BENT CAP FOR CONTINUOUS PRECAST PRESTRESSED

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority

Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority Management of Half Joints in RTA Bridges Amie Nicholas, Project Engineer, NSW Roads and Traffic Authority SYNOPSIS In recent years, there has been heightened concern over the performance of half joints

More information

CRACKING BEHAVIOR AND CRACK WIDTH PREDICTIONS OF CONCRETE BEAMS PRESTRESSED WITH BONDED FRP TENDONS

CRACKING BEHAVIOR AND CRACK WIDTH PREDICTIONS OF CONCRETE BEAMS PRESTRESSED WITH BONDED FRP TENDONS CRACKING BEHAVIOR AND CRACK WIDTH PREDICTIONS OF CONCRETE BEAMS PRESTRESSED WITH BONDED FRP TENDONS Weichen XUE Professor Tongji University Siping Road 1239#, Shanghai 200092, China xuewc@tongji.edu.cn*

More information

7.1 Transmission of Prestress (Part I)

7.1 Transmission of Prestress (Part I) 7.1 Transmission of Prestress (Part I) This section covers the following topics. Pre-tensioned Members 7.1.1 Pre-tensioned Members The stretched tendons transfer the prestress to the concrete leading to

More information

THE RION ANTIRION BRIDGE DESIGN AND CONSTRUCTION

THE RION ANTIRION BRIDGE DESIGN AND CONSTRUCTION THE RION ANTIRION BRIDGE DESIGN AND CONSTRUCTION Jean-Paul TEYSSANDIER 1, Jacques COMBAULT 2 And Pierre MORAND 3 SUMMARY The RION-ANTIRION Bridge (Greece) is located in a zone of difficult environmental

More information

UHPC Connection of Precast Bridge Deck

UHPC Connection of Precast Bridge Deck Jan L. Vitek, Metrostav, a.s. and CTU in Prague Jiri Kolisko, CTU in Prague, Klokner Institute David Citek, CTU in Prague, Klokner Institute Stanislav Rehacek, CTU in Prague, Klokner Institute Robert Coufal,

More information

Creep and Shrinkage Analysis of Composite Truss Bridge with Double Decks

Creep and Shrinkage Analysis of Composite Truss Bridge with Double Decks Abstract Creep and Shrinkage Analysis of Composite Truss Bridge with Double Decks XIN Haohui; LIU Yuqing; Zheng Shuangjie Tongji University,Shanghai, China 2011xinhaohui@tongji.edu.cn; yql@tongji.edu.cn;

More information

Mechanical Performance of Composite Truss Bridge with Double Decks

Mechanical Performance of Composite Truss Bridge with Double Decks Mechanical Performance of Composite Truss Bridge with Double Decks Jun HE PH.D Tongji University Shanghai, China frankhejun@gmail.com Biao MA Civil Engineer Shanghai Municipal Engineering Design General

More information

JULY 2014 LRFD BRIDGE DESIGN 5-1

JULY 2014 LRFD BRIDGE DESIGN 5-1 JULY 014 LRFD BRIDGE DESIGN 5-1 5. CONCRETE STRUCTURES Reinforced and prestressed concrete are used extensively in bridge projects. In addition to general design guidance and information on detailing practices,

More information

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung POST-TENSIONING APPLICATION AND TECHNOLOGY Moe Kyaw Aung Overview 1. Background 2. Basic Design Concept 3. Application and Benefits 4. Components of Post-tensioning System 5. Installation Process 6. Construction

More information

The Aizhai Suspension Bridge is

The Aizhai Suspension Bridge is INTERNATIONAL DESIGN & CONSTRUCTION: BRIDGES Mountain grown Hilly terrain contributes mightily to China bridge By Yinbo Liu, Ph.D., P.E., Guoping Chen, Shulong He and Yongjian Zhang, Ph.D. Contributing

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Structural assessment of the integrated steel fly-overs widening the historic multiple-arch concrete viaduct over the Pede valley

Structural assessment of the integrated steel fly-overs widening the historic multiple-arch concrete viaduct over the Pede valley Structural assessment of the integrated steel fly-overs widening the historic multiple-arch concrete viaduct over the Pede valley Ken SCHOTTE PhD Student, Researcher Ken.Schotte@UGent.be Bart DE PAUW Researcher

More information

Effect of excessive cement in prestressed concrete girder

Effect of excessive cement in prestressed concrete girder Effect of excessive cement in prestressed concrete girder C.V. Kand, T.P. Thite and S.M. Litake DETAILS OF FLYOVER AND METHOD OF CONSTRUCTION This flyover was on an important road with heavy traffic, had

More information

HARRY H. EDWARDS INDUSTRY ADVANCEMENT AWARD. The Chesapeake and Delaware Canal Bridge Design-Construction Highlights

HARRY H. EDWARDS INDUSTRY ADVANCEMENT AWARD. The Chesapeake and Delaware Canal Bridge Design-Construction Highlights HARRY H. EDWARDS INDUSTRY ADVANCEMENT AWARD The Chesapeake and Delaware Canal Bridge Design-Construction Highlights Denney Pate, P.E. Regional Bridge Engineer Figg Engineering Group Tallahassee, Florida

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico Roberto Gómez, Raul Sánchez-García, J.A. Escobar and Luis M. Arenas-García Abstract In this paper we study the

More information

Effects of construction sequences on a continuous bridge

Effects of construction sequences on a continuous bridge IABSE-JSCE Joint Conference on Advances in Bridge Engineering-II, August 8-10, 010, Dhaka, Bangladesh. ISBN: 978-98--189-0 Amin, Okui, Bhuiyan (eds.) www.iabse-bd.org Effects of construction sequences

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2016 to December 31, 2016 Period Year 1 Project Development and Seismic Evaluation of Pier Systems w/ Pocket Connections and Square

More information

LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG. Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong

LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG. Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong 1. ABSTRACT Accompanying with the construction of the new Hong

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Inverted Double T BEAMS and SLABS Applications

Inverted Double T BEAMS and SLABS Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Inverted Double T BEAMS and SLABS Applications Inverted Double T Beams U Panels Inverted Double T Slabs Inverted Triple

More information

Efficient Mathematical Model for Prestressing Cables and Its Implementation in Computer Analysis

Efficient Mathematical Model for Prestressing Cables and Its Implementation in Computer Analysis IOSR Journal of Mathematics (IOSR-JM) e-issn: 2278-5728, p-issn: 2319 765X. Volume 10, Issue 3 Ver. V (May-Jun. 2014), PP 32-38 Efficient Mathematical Model for Prestressing Cables and Its Implementation

More information

Equipment Design Heavy Lifting

Equipment Design Heavy Lifting Equipment Design Heavy Lifting 1 www.wiecon.com.tw COMPANY PROFILE Wiecon is an internationally active consulting company with technology driven expertise. The design of bridge structures represents a

More information

Do It Right The First Time, Every Time And On Time. An Introduction to HERCULES LMK PT. Website:

Do It Right The First Time, Every Time And On Time. An Introduction to HERCULES LMK PT. Website: Do It Right The First Time, Every Time And On Time An Introduction to HERCULES LMK PT Content 1.Introduction 2.Post-Tensioning System 3.Typical Stressing Procedure 4.Typical Preliminary Design 5.PT Slab

More information

REPAIR OF PRECAST PRE-TENSIONED GIRDERS USING EXTERNAL POST-TENSIONING ASIT N. BAXI BAXI ENGINEERING MIGUEL FORERO SUNCOAST POST-TENSION

REPAIR OF PRECAST PRE-TENSIONED GIRDERS USING EXTERNAL POST-TENSIONING ASIT N. BAXI BAXI ENGINEERING MIGUEL FORERO SUNCOAST POST-TENSION REPAIR OF PRECAST PRE-TENSIONED GIRDERS USING EXTERNAL POST-TENSIONING ASIT N. BAXI BAXI ENGINEERING MIGUEL FORERO SUNCOAST POST-TENSION PROJECT INFORMATION Project name: Laketown Wharf Retrofit Location:

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT Oct. 1, 2015 to December 31, 2015 Period Submitted by M. Saiidi, A. Itani, and A. Mohebbi Department of Civil and Environmental Engineering

More information

Get In, Get Out, Stay Out!

Get In, Get Out, Stay Out! Get In, Get Out, Stay Out! FHWA Accelerated Bridge Construction Program By Gary Jakovich, P.E. Senior Bridge Engineer, FHWA Virginia Concrete Conference Richmond, VA March 6-7, 2007 Federal Highway Administration

More information

ACCELERATED BRIDGE CONSTRUCTION IN TEXAS. Michael D. Hyzak, PE 1 Gregg A. Freeby, PE 2 Lloyd M. Wolf, PE 3 David P. Hohmann, PE 4 John M.

ACCELERATED BRIDGE CONSTRUCTION IN TEXAS. Michael D. Hyzak, PE 1 Gregg A. Freeby, PE 2 Lloyd M. Wolf, PE 3 David P. Hohmann, PE 4 John M. ACCELERATED BRIDGE CONSTRUCTION IN TEXAS Michael D. Hyzak, PE 1 Gregg A. Freeby, PE 2 Lloyd M. Wolf, PE 3 David P. Hohmann, PE 4 John M. Holt, PE 5 ABSTRACT The Texas Department of Transportation (TxDOT)

More information

Fundamentals of Post-Tensioned Concrete Design for Buildings

Fundamentals of Post-Tensioned Concrete Design for Buildings Fundamentals of Post-Tensioned Concrete Design for Buildings Part One by John P. Miller www.suncam.com Copyright 2012 John P. Miller Page 1 of 49 Overview of This Course This is Part One of a three-part

More information

Design and construction of an immersed concrete tunnel using an integrated dock facility

Design and construction of an immersed concrete tunnel using an integrated dock facility Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Design and construction of an immersed concrete tunnel using an integrated dock facility

More information

Deformation Analysis of Prestressed Continuous Steel-Concrete Composite Beams

Deformation Analysis of Prestressed Continuous Steel-Concrete Composite Beams Deformation Analysis of Prestressed Continuous Steel-Concrete Composite Beams Jianguo Nie 1 ; Muxuan Tao 2 ;C.S.Cai 3 ; and Shaojing Li 4 Abstract: Deformation calculation of prestressed continuous steel-concrete

More information

Special Reinforced Concrete Structural Walls

Special Reinforced Concrete Structural Walls 135 Special Reinforced Concrete Structural Walls The requirements of this section apply to special reinforced concrete structural walls serving as part of the earthquake force-resisting system. Shear Strength:

More information

Continuous for Live Load: A Texas Historical Perspective

Continuous for Live Load: A Texas Historical Perspective Continuous for Live Load: A Texas Historical Perspective Scott Walton, M.S.C.E., E.I.T. 1, and Timothy E. Bradberry, M.S.E., P.E. 2 Abstract A significant number of engineers in the United States have

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT January 1, 2017 to March 31, 2017 Period Year 1 Project Development and Seismic Evaluation of Pier Systems w/ Pocket Connections and Square

More information

Application of Tensioned CFRP Strip Method to an Existing Bridge

Application of Tensioned CFRP Strip Method to an Existing Bridge SP-230 66 Application of Tensioned CFRP Strip Method to an Existing Bridge by A. Tateishi, A. Kobayashi, Y. Hamada, T. Takahashi, and H. Yasumori Synop nopsis: s: Tensioned carbon fiber reinforced polymer

More information

Sabah Shawkat Cabinet of Structural Engineering 2017

Sabah Shawkat Cabinet of Structural Engineering 2017 3.1-1 Continuous beams Every building, whether it is large or small, must have a structural system capable of carrying all kinds of loads - vertical, horizontal, temperature, etc. In principle, the entire

More information

Strength Design of Reinforced Concrete Structures

Strength Design of Reinforced Concrete Structures Chapter 6 Strength Design of Reinforced Concrete Structures 6.1 Analysis and Design General Considerations 6.1.1 Convention and Notation Unless otherwise explicitly stated, the following units shall be

More information

Seismic response of corroded r.c. structures

Seismic response of corroded r.c. structures Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Seismic response of corroded r.c. structures Anna Saetta & Paola Simioni Department

More information

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 1, No 3, 2010

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 1, No 3, 2010 ABSTRACT Economics of Alternative Structural Schemes of Prestressed Concrete Bridges : Few Case Studies Kishore kumar.m 1,Ch Hanumantha Rao 2 1 M Kishore Kumar, Executive Engineer (Civil), Border Roads

More information

Shaking Table Test of Controlled Rocking Reinforced Concrete Frames

Shaking Table Test of Controlled Rocking Reinforced Concrete Frames 6 th International Conference on Advances in Experimental Structural Engineering th International Workshop on Advanced Smart Materials and Smart Structures Technology August -, 5, University of Illinois,

More information

Fragility Curves for Seismically Retrofitted Concrete Bridges

Fragility Curves for Seismically Retrofitted Concrete Bridges Fragility Curves for Seismically Retrofitted Concrete Bridges S.-H. Kim Department of Civil and Environmental Engineering, University of California, Irvine, USA. ABSTRACT: This study presents the development

More information

Hybrid prestressed concrete bridges with steel truss webs-sarutagawa bridge and Tomoegawa bridge

Hybrid prestressed concrete bridges with steel truss webs-sarutagawa bridge and Tomoegawa bridge IABSE-JSCE Joint Conference on Advances in Bridge Engineering-III, August 21-22, 2015, Dhaka, Bangladesh. ISBN: 978-984-33-9313-5 Amin, Okui, Bhuiyan, Ueda (eds.) www.iabse-bd.org Hybrid prestressed concrete

More information

FINITE ELEMENT ANALYSIS AND PARAMETRIC STUDY OF CURVED CONCRETE BOX GIRDER USING ABAQUS SOFTWARE

FINITE ELEMENT ANALYSIS AND PARAMETRIC STUDY OF CURVED CONCRETE BOX GIRDER USING ABAQUS SOFTWARE IJRET: International Journal of Research in Engineering and Technology eissn: 9-6 pissn: -78 FINITE ELEMENT ANALYSIS AND PARAMETRIC STUDY OF CURVED CONCRETE BOX GIRDER USING ABAQUS SOFTWARE Nila P Sasidharan,

More information

5.4 Analysis for Torsion

5.4 Analysis for Torsion 5.4 Analysis for Torsion This section covers the following topics. Stresses in an Uncracked Beam Crack Pattern Under Pure Torsion Components of Resistance for Pure Torsion Modes of Failure Effect of Prestressing

More information

New Troja Bridge in Prague Structural Solution of Steel Parts

New Troja Bridge in Prague Structural Solution of Steel Parts Available online at www.sciencedirect.com Procedia Engineering 40 (2012 ) 159 164 Steel Structures and Bridges 2012 New Troja Bridge in Prague Structural Solution of Steel Parts V. Janata a*, D. Gregor

More information

Development of extradosed structures in the bridge construction

Development of extradosed structures in the bridge construction Development of extradosed structures in the bridge construction S keda, Yokohama National University, Japan A Kasuga, Sumitomo Construction Co. Ltd, Japan 25th Conference on OUR WORLD N CONCRETE & STRUCTURES:

More information

Seismic Analysis of Monolithic Coupling Beams of Symmetrical Coupled Shear Wall System

Seismic Analysis of Monolithic Coupling Beams of Symmetrical Coupled Shear Wall System Research Article International Journal of Current Engineering and Technology ISSN 2277-4106 2012 INPRESSCO. All Rights Reserved. Available at http://inpressco.com/category/ijcet Seismic Analysis of Monolithic

More information

Inventory Inspection and Load Rating of a Complex Segmental Concrete Bridge. Presented by Matthew J. Lengyel, PE, SE

Inventory Inspection and Load Rating of a Complex Segmental Concrete Bridge. Presented by Matthew J. Lengyel, PE, SE Inventory Inspection and Load Rating of a Complex Segmental Concrete Bridge Presented by Matthew J. Lengyel, PE, SE Introduction Project Overview Parallel Segmental Bridges (1F 763 and 3F 763) Number of

More information

Section A A: Slab & Beam Elevation

Section A A: Slab & Beam Elevation CE 331, Spring 2011 Flexure Strength of Reinforced Concrete s 1 / 5 A typical reinforced concrete floor system is shown in the sketches below. The floor is supported by the beams, which in turn are supported

More information

CHAPTER 9 STAIR CASES 9.1 GENERAL FEATURES 9.2 TYPES OF STAIR CASES

CHAPTER 9 STAIR CASES 9.1 GENERAL FEATURES 9.2 TYPES OF STAIR CASES CHAPTER 9 STAIR CASES 9.1 GENERAL FEATURES Stair cases are provided for connecting successive floors. It is comprised with flights of steps with inter mediate landings which provides rest to the user and

More information

Modelling of RC moment resisting frames with precast-prestressed flooring system

Modelling of RC moment resisting frames with precast-prestressed flooring system Modelling of RC moment resisting frames with precast-prestressed flooring system B.H.H. Peng, R.P. Dhakal, R.C. Fenwick & A.J. Carr Department of Civil Engineering, University of Canterbury, Christchurch.

More information

MOH AND ASSOCIATES, INC., TAIWAN Design of Taiwan Friendship Bridge River Tempisque, Costa Rica

MOH AND ASSOCIATES, INC., TAIWAN Design of Taiwan Friendship Bridge River Tempisque, Costa Rica Design of Taiwan Friendship Bridge River Tempisque, Costa Rica Huat-Yoo Chua Moh And Associates, Inc. Taiwan Jack Chang RSEA Engineering Corporation Taiwan 1. Introduction Taiwan Friendship Bridge spans

More information

Strengthening Effect on Prestressed Concrete members Affected by Alkali-Silica Reaction(ASR)

Strengthening Effect on Prestressed Concrete members Affected by Alkali-Silica Reaction(ASR) Strengthening Effect on Prestressed Concrete members Affected by Alkali-Silica Reaction(ASR) Yukio Takebe 1, Takanobu Yokoyama 2, Hideshige Yonekawa 3, Kenichi Nakamura 4, Toyoaki Miyagawa 5 1 DPS Bridge

More information

Cast in-situ Balanced Cantilever for Building a Bridge

Cast in-situ Balanced Cantilever for Building a Bridge 2013, TextRoad Publication ISSN 2090-4304 Journal of Basic and Applied Scientific Research www.textroad.com Cast in-situ Balanced Cantilever for Building a Bridge Hamid Aadal, Pejman Ghasemipoor Sabet,

More information

TWO-WAY POST-TENSIONED SLABS WITH BONDED TENDONS

TWO-WAY POST-TENSIONED SLABS WITH BONDED TENDONS PTI JOURNAL TECHNICAL PAPER TWO-WAY POST-TENSIONED SLABS WITH BONDED TENDONS By Kenneth B. Bondy Authorized reprint from: December 2012 issue of the PTI Journal Copyrighted 2012, Post-Tensioning Institute

More information

ANSYS Customization for Bridges and Prestressed Concrete Structures Analysis and Design

ANSYS Customization for Bridges and Prestressed Concrete Structures Analysis and Design ANSYS Customization for Bridges and Prestressed Concrete Structures Analysis and Design Javier Aparicio Ingeciber, S.A. Isabella Maia Ingeciber, S.A. Eduardo Salete Ingeciber, S.A. Abstract This paper

More information

CHAPTER 11: PRESTRESSED CONCRETE

CHAPTER 11: PRESTRESSED CONCRETE CHAPTER 11: PRESTRESSED CONCRETE 11.1 GENERAL (1) This chapter gives general guidelines required for the design of prestressed concrete structures or members with CFRM tendons or CFRM tendons in conjunction

More information

Design, fabrication and construction of Railway Bridge over Södertälje canal

Design, fabrication and construction of Railway Bridge over Södertälje canal NSCC2009 Design, fabrication and construction of Railway Bridge over Södertälje canal Michael B. Thulstrup 1, Mattias Nilsson 2, Robert Hällmark 3 & Jens P. Nielsen 4 1 Project Manager, MT Højgaard a/s,

More information

Work methodology for replacement of expansion joints of Meghna bridge in 2008

Work methodology for replacement of expansion joints of Meghna bridge in 2008 IABSE-JSCE Joint Conference on Advances in Bridge Engineering-III, August 21-22, 2015, Dhaka, Bangladesh. ISBN: 978-984-33-9313-5 Amin, Okui, Bhuiyan, Ueda (eds.) www.iabse-bd.org Work methodology for

More information

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015 Tolerances for Concrete Construction Thomas J Downs P.E., FACI President Forensic Experts Minneapolis, MN What is it? Tolerances for Concrete Construction When did we start this anyway? Who said we needed

More information

LATERAL LOAD BEHAVIOR OF UNBONDED POST-TENSIONED HYBRID COUPLED WALLS. Qiang SHEN Graduate Research Assistant. Yahya C. KURAMA Assistant Professor

LATERAL LOAD BEHAVIOR OF UNBONDED POST-TENSIONED HYBRID COUPLED WALLS. Qiang SHEN Graduate Research Assistant. Yahya C. KURAMA Assistant Professor LATERAL LOAD BEHAVIOR OF UNBONDED POST-TENSIONED HYBRID COUPLED WALLS Qiang SHEN Graduate Research Assistant Yahya C. KURAMA Assistant Professor University of Notre Dame, Civil Engineering and Geological

More information

Hyperstatic (Secondary) Actions In Prestressing and Their Computation

Hyperstatic (Secondary) Actions In Prestressing and Their Computation 5.5 Hyperstatic (Secondary) Actions In Prestressing and Their Computation Bijan O Aalami 1 SYNOPSIS This Technical Note describes the definition, computation, and the significance of hyperstatic (secondary)

More information

Full-Depth Precast Concrete Bridge Deck Construction

Full-Depth Precast Concrete Bridge Deck Construction Full-Depth Precast Concrete Bridge Deck Construction John R. Fowler, P.Eng., President Canadian Precast/Prestressed Concrete Institute Paper prepared for presentation at the Bridges Links to a Sustainable

More information

Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System

Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System Design studies of the Castle Bridge over Wislok River in Rzeszow with application of CAD System Author: Dariusz Alterman Superviser: Dr. Tomasz Siwowski, Civ. Eng. Chairman of the examination committee:

More information

Supporting economical bridge construction the central hinge bearings of the 2 nd Shitalakshya Bridge

Supporting economical bridge construction the central hinge bearings of the 2 nd Shitalakshya Bridge IABSE-JSCE Joint Conference on Advances in Bridge Engineering-II, August 8-10, 2010, Dhaka, Bangladesh. ISBN: 978-984-33-1893-0 Amin, Okui, Bhuiyan (eds.) www.iabse-bd.org Supporting economical bridge

More information

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT ATHABASCA RIVER BRIDGE REHABILITATION PROJECT PROJECT INFORMATION Project Name Athabasca River Bridge Rehabilitation Project Location Highway 40 (over the Athabasca River), Entrance, Alberta Year Completed

More information

Pile to Slab Bridge Connections

Pile to Slab Bridge Connections Pile to Slab Bridge Connections Mohamed I. Ayoub 1, David H. Sanders 2 and Ahmed Ibrahim 3 Abstract Slab bridges are a common bridge type, where the pile extends directly from the ground to the superstructure.

More information

Experimental investigation on the shear capacity of RC dapped end beams and design recommendations

Experimental investigation on the shear capacity of RC dapped end beams and design recommendations Structural Engineering and Mechanics, Vol. 21, No. 2 (2005) 221-235 221 Experimental investigation on the shear capacity of RC dapped end beams and design recommendations Quanfeng Wang and Zixiong Guo

More information

THE NEW AASHTO MANUAL FOR BRIDGE EVALUATION 2008

THE NEW AASHTO MANUAL FOR BRIDGE EVALUATION 2008 LOAD & RESISTANCE FACTOR RATING OF HIGHWAY BRIDGES FHWA LRFR Seminar SESSION 5 THE NEW AASHTO MANUAL FOR BRIDGE EVALUATION 2008 Bala Sivakumar, P.E. HNTB Corp. 2005 AASHTO BRIDGE MEETING AASHTO Adopted

More information

DEVELOPMENT OF THE STRUCTURAL DESIGN AND CONSTRUCTION GUIDELINE FOR HIGH-RISE PC BUILDINGS - JAPANESE PC PROJECT

DEVELOPMENT OF THE STRUCTURAL DESIGN AND CONSTRUCTION GUIDELINE FOR HIGH-RISE PC BUILDINGS - JAPANESE PC PROJECT 16 DEVELOPMENT OF THE STRUCTURAL DESIGN AND CONSTRUCTION GUIDELINE FOR HIGH-RISE PC BUILDINGS - JAPANESE PC PROJECT Fumio WATANABE 1, Shin OKAMOTO And Hisahiro HIRAISHI 3 SUMMARY Prestressed concrete has

More information

Substructure systems, specifically retaining walls

Substructure systems, specifically retaining walls Design principles of totally prefabricated counterfort retaining wall system compared with existing cast-in-place concrete structures Maen Farhat and Mohsen Issa An alternative to cast-in-place concrete

More information

Field application of FRP material in Kentucky

Field application of FRP material in Kentucky Field application of FRP material in Kentucky Abheetha Peiris, University of Kentucky (email: abheetha@engr.uky.edu) Issam Harik, University of Kentucky (email: iharik@engr.uky.edu) Abstract Repair and

More information