Construction of the Superstructure of Major Sea Crossings

Size: px
Start display at page:

Download "Construction of the Superstructure of Major Sea Crossings"

Transcription

1 Construction of the Superstructure of Major Sea Crossings Matt Carter Associate Director 2 nd International Seminar on Design & Construction of Second Penang Bridge

2 2 Second Penang Bridge

3 Donghai Bridge Incheon Bridge Penang Bridge Shenzhen Western Corridor 3 Typical Sea Crossing Bridges

4 4 Long Section Scale H:V = 10:1 Maximum water depth = 10m Typical water depth = 2 to 3m

5 5 Stonecutters Bridge, Hong Kong

6 6 Second Penang Bridge, Malaysia

7 Substructure is typically around one third of the total cost Innovative design gives substantial savings Depends on ground conditions Innovations: - Construction methods - Lateral pile load tests - Articulation - Seismic isolation 7 Substructure optimization

8 Typical Superstructure

9 Quality Production line casting in a controlled environment Economy Repetitive operations, re-use of equipment Safety Minimise working at height and over water 9 Advantages of precast construction

10 Quality Cost Speed of Construction Durability Safety Environmental Impact Aesthetics 10 Design Drivers

11 Quality Cost Speed of Construction Durability Safety Environmental Impact Aesthetics 11 Design Drivers

12 Cost High elevation / deep water Low elevation / shallow water Span For given site conditions there will be an optimum economic span With current technologies in shallow seas without navigation requirements this is typically around 50m to 55m 12

13 Economic Comparison of First Penang Bridge Based on prevailing costs and available technologies in July 1977 Source: The Penang Bridge, Planning Design and Construction by Tan Sri Datuk Professor Ir. Chin Fung Kee

14 Asia s first precast segmental bridge Design & Build contract Opened 1991 Balanced cantilever segment erection Completed project next to the old Kai Tak Airport Overhead gantry weighted 400 tonnes and was 130m long 14 Kwun Tong Bypass Phase 2

15 15

16 Comparison between First and Second Penang Penang Bridge (1985) 40m PC beam and slab Second Penang Bridge (2013) 55m precast segmental box girders

17 Typical Cross Section Typically 10 16m Typically 10 16m 16m is enough for a three lane highway with full width breakdown land

18 Precast Segmental Span by Span

19 19 Span by Span Erection

20 20 Erection Sequence

21 21 Erection Gantry

22 22

23 23

24 24 Srtuctural Completion

25 Precast Segmental Balanced Cantilever

26 Span-by-span segmental needs all of the segments in a span to be simultaneously supported by the gantry Under some design conditions this could lead to a very expensive gantry: - Long spans - Tight radius curves Deep Bay Link Shorter projects may not justify investment West Tsing Yi Viaducts 26 Why balanced cantilever?

27 27 Shenzhen Western Corridor

28 Fast Track Design & Construction Feasibility Study (incl. Conceptual Design & EIA) Aug 2001 Sep 2002 Detailed Design Jul 2002 Jul 2003 Construction (Gammon-Skanska-MBEC JV) Aug 2003 Dec 2005 (28 months) Total only ~ 4 ½ years 28

29 29

30 30 Segment erection

31 Cantilever tip derricks Segment delivery by barge Segment storage Short line segment match casting 31

32 End Spans Expansion joints are needed at regular intervals which interfere with balanced cantilever erection Options - Short end spans interrupt the rhythm of the bridge - Temporary fixity of joints - Mid span hinge - SWC hybrid solution

33 33 End span erection

34 Hong Kong Zhuhai Macau Bridge HKSAR Zhuhai 43.6 km bridge over Pearl River Estuary 1st major combined bridge & tunnel sea-crossing in China reduce travel time to 0.5 hour from HK and Pearl River West Macau 34

35 Qingzhou navigation channel HKBCF HK Section Zhuhai West Artificial Island Tunnel East Artificial Island Lantau Lantau Island Island Macau 35

36 36

37 12km long highway Including 9.4km sea crossing viaduct 37 Hong Kong Section

38 38 Hong Kong Section

39 39 75m precast segmental balanced cantilever

40 Full Span Launching Method

41 41

42 Project Overview 42 Project Overview

43 43 Incheon Bridge

44 44 Full Span Launching Method

45 45 Launching gantry

46 46 Full Span Casting Factory

47 47

48 48 Pretensioning

49 49 Erection of first segment

50 Delivery of segments in deep water which is accessible by floating crane Transportation along the already erected deck by a mutli-wheeled transporter 50

51 Segment transportation is governing load 1,300 tonne segment and 950 tonne transporter unit Spread onto four girders 51

52 52 Erection equipment

53 Full Span Launching Method Contractor was experienced with the method Very long viaduct justifies investment in bespoke launching gantry to achieve very fast construction No variations in deck width, no tight radius curves in highway alignment Marine environment and availability of large capacity floating cranes Low level viaduct makes moderate span length (50m) economical

54 Comparison of Sea Crossing Construction Methods

55 Project Deck Type Procurement Method Contractor Construction Method Second Penang Bridge Incheon Bridge Precast Concrete Box Girder Shenzhen Western Corridor Design & Build Design & Build Engineers Design UEM Builders Span by span precast segmental Samsung Construction JV Full span precast launching Gammon-Skanska- MBEC Joint Venture Balanced cantilever precast segmental Status Under Construction Completed 2009 Completed 2006 Total Length 16.9 km 12.3 km 5.5 km Viaduct Length 16.5 km 9.0 km 4.7 km Width 2 x 14.0 m 2 x 15.7 m 12 x m Typical Span 55 m 50 m 75 m Typical Bridge Unit Length 330 m 250 m 590 m 55 Three sea crossings constructed in shallow water in East Asia

56 8092 segments 3 lines of 7 moulds per line (different fabricators) Storage capacity for 780 segments (2 months supply) Typical segment 1 per day 56 Second Penang Bridge Precast Yard

57 360 segments 1 mould Storage capacity for six segments (<2 weeks production) One segment every 2 days 57 Incheon Bridge Precast Yard

58 Casting yard in mainland China 1,879 segments 6 moulds Segment casting started well in advance of erection 58 Shenzhen Western Corridor

59 Project Second Penang Bridge Incheon Bridge Number of Spans Number of Gantries 4 2 Shenzhen Western Corridor 90 (Hong Kong section) 1 overhead gantry + 4 pairs of cantilever derricks Spans Per Gantry Number of Segments 8, ,879 Number of Moulds 3 x 7 = Segments Per Mould Target Cycle Time Theoretical Duration at Target Productivity days per span per gantry 2 days per span per mould 1 week per span per gantry 20 months 24 months 4.5 months 59 Three sea crossings constructed in shallow water in East Asia

60 Second Penang Bridge Design & Build contractor can tailor method Contractor had previous experience of span by span segmental Environmental impacts acceptable with a 55m span Incheon Bridge Design & Build contractor can tailor method Contractor had previous experience of full span launching Large number of spans justifies investment in bespoke gantry Shenzhen Western Corridor Very fast track project - needs multiple gantries Limited number of spans hard to justify bespoke investment Engineers design needs flexible method Environmentally sensitive mud flats needs longer spans (75m) 60 ard

61 Conclusions With constant width and gentle plan curvature a typical span length of 50m to 55m can be constructed by any one of the three methods Speed of construction depends on number of construction fronts so the cycle time for a single gantry may not dictate project duration Span by span segmental construction is a versatile method but span is limited to around 55m Span by span segmental can be significantly accelerated if required once construction team has gone through learning curve Balanced cantilever will be more economical at longer spans Full span launching will only be economical for very large projects which tends to limit the number of contractors who will adopt it Harder to accelerate full span launching

62 Emerging Trends

63 Extension of Design Life Asset Management Structural Health Monitoring Threat and Vulnerability Assessment 63 Stainless steel reinforcement

64 Thank You

Construction of Bridges

Construction of Bridges Construction of Bridges Materials suitable for the Construction of Long-span Bridges 1. Stone in arch masonry 2. Steel in girder or box-section constructed in steel plates and standard sections 3. Steel

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series www.thestructuralengineer.org 41 CBDC series July 2014 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote

More information

POSTER PAPER PROCEEDINGS

POSTER PAPER PROCEEDINGS ITA - AITES WORLD TUNNEL CONGRESS 21-26 April 2018 Dubai International Convention & Exhibition Centre, UAE POSTER PAPER PROCEEDINGS Advanced Developments in Steel and RC Immersed Tunnels Hideki Sakaeda

More information

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure C.Y. Shao Shanghai Municipal Engineering Design & Research General Institute (Group) Co. Ltd.,

More information

LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG. Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong

LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG. Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong 1. ABSTRACT Accompanying with the construction of the new Hong

More information

Innovative solutions in Hong Kong Zhuhai Macao Bridge (HZMB) Hong Kong Link Road Project

Innovative solutions in Hong Kong Zhuhai Macao Bridge (HZMB) Hong Kong Link Road Project Innovative solutions in Hong Kong Zhuhai Macao Bridge (HZMB) Hong Kong Link Road Project Man Chan Dragages Hong Kong Limited, Hong Kong Donald S.H. Chan China Harbour Engineering Company Limited (Hong

More information

Bridge Construction Methods

Bridge Construction Methods Bridge Construction Methods Mr. K F TAM, MHKIE, MCIHT Gammon Construction Limited Abstract In Hong Kong, bridge is one of the main transportation accesses. Gammon has responded with resourcefulness, innovation

More information

Smart System Design Competition

Smart System Design Competition Young Engineer Workshop 2016 Smart System Design Competition Using Hong Kong Zhuhai Macau Bridge, Guangzhou, China Seeking Intelligent Solutions Organized by Young Engineer Program of IABSE Chinese Group

More information

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES Massachusetts Department of Transportation Highway Division I-95 / Whittier Bridge Replacement Type Study Report 6. Evaluation of

More information

Creating Solutions Together The Construction Of The Waiwera Viaduct

Creating Solutions Together The Construction Of The Waiwera Viaduct Waiwera bridge The Construction Of The Waiwera Viaduct Solving the Construction Of Waiwera Bridge Using Balanced Cantilever and Matched Precast Segmental Erection Via Overhead Gantry By David Trayner VSL

More information

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES J. E. Erdoğan 1 and Ö. Özkul 2 ABSTRACT Despite its widespread use around the world, constructing

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series 40 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote excellence in the design, construction and management

More information

Concrete. from Grey to Green. Concrete Technology

Concrete. from Grey to Green. Concrete Technology Concrete from Grey to Green Concrete Technology Gammon Construction Limited has been involved in a wide range of construction projects in Asia for over 50 years. We are the marketleading construction contractor

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch Warwick Triangle Viaduct: Outbound INTRODUCTION The Warwick Triangle Precinct in Durban is one of the busiest trading and transport hubs in Africa. Major traffic conflict resulted from the movement of

More information

Introduction -- Tsing Ma Bridge

Introduction -- Tsing Ma Bridge Introduction The Lantau Fixed Crossing, or sometimes called the Lantau Link, is one of the Airport Core Projects for the construction of the new international airport of Hong Kong located in Chek Lap Kok.

More information

Construction and design features of the Bridge over the Danube River. Bulgaria

Construction and design features of the Bridge over the Danube River. Bulgaria Construction and design features of the Bridge over the Danube River. Bulgaria Javier MANTEROLA Pr. Dr. jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. amartinez@cfcsl.com Juan Antonio NAVARRO janavarro@cfcsl.com

More information

Design of Izmir Bay Crossing Bridge

Design of Izmir Bay Crossing Bridge Design of Izmir Bay Crossing Bridge Burak Kurtman Dpt. Manager of Bridge Group, Yüksel Project International, Ankara, Turkey Tel: +90 (312) 4957000 E-mail: bkurtman@yukselproje.com.tr Abstract The Izmir

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

MARTA Rapid Transit Bridges

MARTA Rapid Transit Bridges MARTA Rapid Transit Bridges his precast segmental post-tensioned concrete project for the T Metropolitan Atlanta Rapid Transit Authority demonstrates the ability of the segmental technique to economically

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update July 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The entails the construction of a cast in place

More information

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change

More information

MATERIAL QUANTITIES FOR BALANCED CANTILEVER BRIDGES. FANI ANTONIOU Egnatia Odos A.E., 6th km Thessaloniki - Thermi, GREECE

MATERIAL QUANTITIES FOR BALANCED CANTILEVER BRIDGES. FANI ANTONIOU Egnatia Odos A.E., 6th km Thessaloniki - Thermi, GREECE MATERIAL QUANTITIES FOR BALANCED CANTILEVER BRIDGES DIMITRIOS KONSTANTINIDIS Department of Civil Infrastructure Engineering, Alexander Technical Institute of Thessaloniki, 574, GREECE FANI ANTONIOU Egnatia

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE Paul Gauvreau University of Toronto, Canada (formerly J. Muller International) Thomas E. Kelly, Jr. Earth Tech/J.

More information

Progressive Erection Applied to Box Girder with Strutted Wing Slab

Progressive Erection Applied to Box Girder with Strutted Wing Slab Progressive Erection Applied to Box Girder with Strutted Wing Slab Koji Osada 1, Taketo Kanamoto 1, Kimito Saito 2, Takahiro Arai 2 1 Introduction The Uchimaki Viaduct is a multi-span continuous box girder

More information

Project Reference Catalogue. Bridge Design Services

Project Reference Catalogue. Bridge Design Services 1 www.wiecon.com.tw High Speed Rail s 2 List - Taiwan high speed rail project, contract C250. Composite launched bridge, design unit DU 11.01. - Taiwan high speed rail project. Warren truss steel bridges.

More information

Possible solution to past CM examination question. Question 3 - April Footbridge over a waterfall. by Saprava Bhattacharya

Possible solution to past CM examination question. Question 3 - April Footbridge over a waterfall. by Saprava Bhattacharya Possible solution to past CM examination question Question 3 - April 2013 Footbridge over a waterfall by Saprava Bhattacharya The information provided should be seen as an interpretation of the brief and

More information

AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS

AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS AN INNOVATIVE ERECTION TECHNIQUE FOR REDUCING TWO- THIRD OF CONSTRUCTIONAL BRIDGE DEFLECTIONS Assist. Prof. Ala a M. Darwish Dr. Wameedh G. Abdul-Hussein Nawal D. Salman Building and Construction Engineering

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update September 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: September

More information

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng. SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical

More information

Precast segmental design and construction in China

Precast segmental design and construction in China Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Precast segmental design and construction in China Dong, Xu, Huichi Li & Chao Liu

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Project Reference Catalogue

Project Reference Catalogue Bridge Bridge Taiwan High Speed Rail, Advancing Shoring Method Taiwan High Speed Rail Corporation. Over 127 km of 13 wide prestressed concrete viaducts were constructed; and 9 contractors designed and

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

More information

Pushing the Envelope For 100 Years

Pushing the Envelope For 100 Years Pushing the Envelope For 100 Years Tunneling under the Chesapeake Bay The Parallel Thimble Shoal Highway Tunnel Presented by: Kevin Abt, PE Chesepeake Bay Bridge and Tunnel District Mike Kling, PE, PTOE

More information

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia.

New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia. New Pumarejo Bridge over the river Magdalena in Barranquilla. Colombia. J. Manterola S. Fernández S. Fuente J. Muñoz-Rojas J. A. Navarro ABSTRACT The overall length of the new bridge over the River Magdalena

More information

Seismic Design of a Railway Viaduct in a High Seismic Zone

Seismic Design of a Railway Viaduct in a High Seismic Zone Seismic Design of a Railway Viaduct in a High Seismic Zone 9 th Small Bridges Conference, Australia 2019 Seismic Design of a Railway Viaduct in a High Seismic Zone 1. Project Overview 2. Typical Project

More information

RESILIENT INFRASTRUCTURE June 1 4, 2016

RESILIENT INFRASTRUCTURE June 1 4, 2016 RESILIENT INFRASTRUCTURE June 1 4, 2016 WESTMINSTER DRIVE UNDERPASS ACCELERATED BRIDGE CONSTRUCTION USING GIGO (GET IN-GET OUT) BRIDGE CONCEPT Mark D Andrea, M.Sc., P.Eng. Stantec Consulting Ltd., Canada

More information

GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY

GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY Introduction Authors Jarrod Hitchcox Associate Technical Director Arcadis Australia Pacific jarrod.hitchcox@arcadis.com

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Design of continuity slabs and the 020 Gajanan Chaudhari Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE Anand Panpate Senior Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

More information

BRIDGES WITH PROGRESSIVELY ERECTED DECKS

BRIDGES WITH PROGRESSIVELY ERECTED DECKS Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey BRIDGES WITH PROGRESSIVELY ERECTED DECKS P. Novotny 1, P. Svoboda 2 and J. Strasky 3 ABSTRACT Two types of bridges with progressively erected

More information

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge)

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge) Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge) Chodai Co., Ltd., Nippon Engineering Consultants Co., Ltd., IHI Infrastructure Systems Co,. Ltd., and Sumitomo Mitsui Construction

More information

DOCUMENT STATUS. Details of Revision:

DOCUMENT STATUS. Details of Revision: (I) DOCUMENT STATUS Details of Revision: Revision Rev. Date Sections Amendment Source and/or Details A 30 Aug 2013 All Issued for Approval B 23 Sep 2013 All Revised for Approval C 24 Sep 2013 4, 5 D 8

More information

2016 ACEC/PA ANNUAL MEETING

2016 ACEC/PA ANNUAL MEETING 2016 ACEC/PA ANNUAL MEETING z I-49 North, Segment K (I-220 to Martin Luther King Drive) Interchange Project Durk Krone, P.E., TRC Engineers Inc., Baton Rouge, La 1 I-49 North Segment K Project 2 AGENDA

More information

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation STANDARDIZED CONCRETE BRIDGES IN TEXAS John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation ABSTRACT Standardized concrete bridge plans are used extensively

More information

The Aizhai Suspension Bridge is

The Aizhai Suspension Bridge is INTERNATIONAL DESIGN & CONSTRUCTION: BRIDGES Mountain grown Hilly terrain contributes mightily to China bridge By Yinbo Liu, Ph.D., P.E., Guoping Chen, Shulong He and Yongjian Zhang, Ph.D. Contributing

More information

Design Challenges and Construction Benefits of Precast Segmental Rail Bridges

Design Challenges and Construction Benefits of Precast Segmental Rail Bridges Design Challenges and Construction Benefits of Precast Segmental Rail Bridges by Amy R. Kohls, P.E., S.E. Director Texas Office Figg Bridge Engineers, Inc. 10000 North Central Expressway Suite 1300 Dallas,

More information

Feasibility of Peljesac Bridge Variants

Feasibility of Peljesac Bridge Variants Davorin Kolic, Mohammad Irshad Neuron Zagreb Ltd. IDC Washington Ltd. Feasibility of Peljesac Bridge Variants 1. CCC Symposium on Graz, September 8-9, 2005 Concrete Engineering Content Strait crossing

More information

creative engineering solutions

creative engineering solutions creative engineering solutions milestones 1980 Robert Benaim established Robert Benaim and Associates and quickly developed an international reputation for excellence in the design of bridges and heavy

More information

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal

SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal SHRP 2 - R04 Innovative Bridge Designs for Rapid Renewal FEHRL Long Life Bridges SQUARE (Brussels) Thursday June 10, 2010 Objective RAPID RENEWAL Bridge Systems WHAT IS THE BIG IDEA? Manufactured Bridges

More information

Recent Major Cable-Stayed Bridges in Shanghai

Recent Major Cable-Stayed Bridges in Shanghai 34 Recent Major Cable-Stayed Bridges in Shanghai Q.E. Deng, C.Y. Shao Shanghai Municipal Engineering Design General Institute, China ABSTRACT: This paper presents three major cable-stayed bridges completed

More information

Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge

Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge Innovative Bridge Designs in Colorado by Pete Chomsrimake, P.E. ABC Project SME, CDOT Staff Bridge ABC History in Colorado 1. Promote Using Prefabricated Bridge & CBC Members since Early 1990 (Partnership

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

Equipment Design Heavy Lifting

Equipment Design Heavy Lifting Equipment Design Heavy Lifting 1 www.wiecon.com.tw COMPANY PROFILE Wiecon is an internationally active consulting company with technology driven expertise. The design of bridge structures represents a

More information

A THEORETICAL ATTEMPT TO REDUCE THE CONSTRUCTIONAL DEFLECTIONS OF UN-SHORED REINFORCED CONCRETE DECK-GIRDER BRIDGES

A THEORETICAL ATTEMPT TO REDUCE THE CONSTRUCTIONAL DEFLECTIONS OF UN-SHORED REINFORCED CONCRETE DECK-GIRDER BRIDGES . Ala a M. DARWISH, 2. Wameedh G. ABDUL-HUSSEIN,. Nawal D. SALMAN A THEORETICAL ATTEMPT TO REDUCE THE CONSTRUCTIONAL DEFLECTIONS OF UN-SHORED REINFORCED CONCRETE DECK-GIRDER BRIDGES,2,. BUILDING AND CONSTRUCTION

More information

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN

More information

STONECUTTERS BRIDGE, HONG KONG DESIGN AND CONSTRUCTION

STONECUTTERS BRIDGE, HONG KONG DESIGN AND CONSTRUCTION STONECUTTERS BRIDGE, HONG KONG DESIGN AND CONSTRUCTION HUSSAIN, Naeem Director, Arup, Hong Kong naeem.hussain@arup.com CARTER, Matt Associate Director, Arup, Hong Kong matt.carter@arup.com KITE, Steve

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series 42 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG) The group aims to promote excellence in the design, construction and management

More information

Precast Prestressed Segmental Elevated Urban Motorway in Italy

Precast Prestressed Segmental Elevated Urban Motorway in Italy Precast Prestressed Segmental Elevated Urban Motorway in Italy Bruno Gentilini Lino Gentilini Consulting Engineers Trento, Italy Bruno Gentilini Lino Gentilini The authors, who were responsible for the

More information

Basarab Cable Stayed Bridge in Bucharest

Basarab Cable Stayed Bridge in Bucharest Basarab Cable Stayed Bridge in Bucharest Javier MANTEROLA Pr. Dr. Civil Engineer Carlos Fernández Casado,S.L. Madrid, SPAIN jmanterola@cfcsl.com Antonio MARTÍNEZ Dr. Civil Engineer Carlos Fernández Casado,S.L.

More information

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION

STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION STATE OF NEW JERSEY DEPARTMENT OF TRANSPORTATION PRELIMINARY DESIGN SUBMISSION REPORT For U.S. Route 130 Over Raccoon Creek Bridge Township of Logan Gloucester County, New Jersey Prepared By: Structural

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

Structural Steelwork. Bridge Structures Building Structures Marine Structures Temporary Works structures Bulk Construction Materials

Structural Steelwork. Bridge Structures Building Structures Marine Structures Temporary Works structures Bulk Construction Materials Structural Steelwork Bridge Structures Building Structures Marine Structures Temporary Works structures Bulk Construction Materials 1 Who We Are 3 Overview 4 Fabricated Steelworks 6 Modular and Pre-Assembled

More information

DESIGN AND ERECTION OF INCHEON BRIDGE

DESIGN AND ERECTION OF INCHEON BRIDGE DESIGN AND ERECTION OF INCHEON BRIDGE Man-Geun, Yun, Ph.D., PE Executive, Vice President, mgy.52@samsung.com Hyun-Yang, Shin, Ph.D., S.E. Bridge Division, shynis@samsung.com Jai-Beom, Shim, PE Executive

More information

PROPOSED BEAM STABILITY SUBMITTAL REQUIREMENTS March 3, 2017

PROPOSED BEAM STABILITY SUBMITTAL REQUIREMENTS March 3, 2017 PROPOSED BEAM STABILITY SUBMITTAL REQUIREMENTS March 3, 2017 Virginia J. Epperly, PE Complex Structures Engineer Structure & Bridge Division Andrew M. Zickler, PE ABC Support & Complex Str. Program Manager

More information

MIDAS Training Series

MIDAS Training Series MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session

More information

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE Design of the Main Spans of the Chongqing Caiyuanba Bridge ARCH 04 M.C. Tang and J. Sun @CIMNE, Barcelona, 2004 DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE Man-Chung Tang* and John Sun+

More information

Development Island Vehicle Access

Development Island Vehicle Access Elizabeth Quay Water Front Development Island Vehicle Access Bridge Small Bridges Conference - 23 rd November 2015 Presentation Outline Project Overview Key Challenges Description of Island Vehicle Access

More information

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE Keith Donington, P.E. October 2012 1 Sibley Pond - Bridge Elevation 2 Bridge Open to Traffic November 2011 3 Bridge Highlights

More information

The HKIE Structural Examination Written Examination 2017

The HKIE Structural Examination Written Examination 2017 The HKIE Structural Examination Written Examination 2017 Section 2: Design Questions (80% of the Written Examination) Date: 5 December 2017 (Tuesday) Time: 12:00 nn 06:00 pm (Duration: 6 hours) Question

More information

Gautrain construction update

Gautrain construction update Month end 30 April 2008 Gautrain construction update SOUTHERN SECTION Underground section Park Station Excavation of the single-track rail tunnel towards Emergency Shaft 2 in Houghton has reached approximately

More information

Launching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008

Launching Bridges in to the Future. CBDG Annual Conference. Simon Bourne Managing Director. 26 June 2008 Launching Bridges in to the Future CBDG Annual Conference 26 June 2008 Simon Bourne Managing Director WWW.BENAIMGROUP.COM Use of Incremental Launching Deck lengths of more than 200m 30-70m spans, typically

More information

CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS

CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS WJ Martin 17.1 SCOPE Specialist construction systems refer to the construction systems falling outside of the normal reinforced and prestressed bridges that

More information

Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL

Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL Design and Construction Folsom Lake Crossing by Hans Strandgaard, Alex Harrison, Jeff Aldrich, and Jeff Thomure, CH2M HILL View of the Folsom Dam and the canyon just upstream of construction. The area

More information

Over the years, the use of precast concrete has taken giant

Over the years, the use of precast concrete has taken giant Precast Concrete Bridge Deck - Design, Transportation and Erection: A Designer s Overview Debabrata Mukherjee 1, Manju Balaji 2 1 Group Engineer, Atkins 2 Engineer, Atkins 76 Over the years, the use of

More information

Finite Element Simulation of Cantilever Construction Structure

Finite Element Simulation of Cantilever Construction Structure Finite Element Simulation of Cantilever Construction Structure Baofeng Pan 1, Gang Li 2 Abstract In order to realize the control ultimate goal, it is necessary to predict and control the deformation and

More information

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE

CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE CONSTRUCTION OF BALANCE CANTILEVER APPROACH SURAMADU BRIDGE By Masakazu Matsubara Resident Engineer for Approach & Main Bridge Suramadu Bridge Project 1. DESIGN 1.1. Concept of Design of Cantilever Erection

More information

Design of Idemli Bridges in Landslide Areas

Design of Idemli Bridges in Landslide Areas Design of Idemli Bridges in Landslide Areas C. Ozkaya, G. Cetin & F. Tulumtas Yuksel Proje Uluslararası Co., Ankara, Turkey ABSTRACT: In this paper, design of a highway viaduct located in a landslide area

More information

MIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating

MIDAS Civil 2016 v2.1 Release Webinar. PSC Composite Design Check / Load rating 2016 v2.1 Release Webinar PSC Composite Design Check / Load rating What is Composite Girder Module? Wizard-modeling - Steel Composite Bridge - PSC Composite Bridge Report Generation for Design & Load Rating

More information

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts... Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts... LECTURE 13 May 17, 2005 May 17, 2005 1 Where we have been Basics Allowable Stress Ultimate Strength Shear Camber

More information

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1 LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE Mark S. Mahan 1 Abstract The newly approved AASHTO Guide Specification for LRFD Seismic Bridge Design (referred to as LRFD Seismic Guide Spec), July 2007,

More information

MOH AND ASSOCIATES, INC., TAIWAN Design of Taiwan Friendship Bridge River Tempisque, Costa Rica

MOH AND ASSOCIATES, INC., TAIWAN Design of Taiwan Friendship Bridge River Tempisque, Costa Rica Design of Taiwan Friendship Bridge River Tempisque, Costa Rica Huat-Yoo Chua Moh And Associates, Inc. Taiwan Jack Chang RSEA Engineering Corporation Taiwan 1. Introduction Taiwan Friendship Bridge spans

More information

PAN PAC PULPMILL TREATMENT TANK

PAN PAC PULPMILL TREATMENT TANK PAN PAC PULPMILL TREATMENT TANK B. PENG 1, M. ROMANES 2, P. GABY 1 1 Holmes Consulting Group 2 Concrete Structures (NZ) Ltd ABSTRACT The recently completed MBBR and AS tank is part of a multi-million dollar

More information

4 th Annual Bridges Asia Conference, Hong Kong February 2013

4 th Annual Bridges Asia Conference, Hong Kong February 2013 GOVERNMENT OF MALAYSIA MALAYSIAN HIGHWAY AUTHORITY JAMBATAN KEDUA PTD. LTD. 4 th Annual Bridges Asia Conference, Hong Kong 26-27 February 2013 Sustainable Bridge Construction Practices Case Study: Second

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Construction of the Asset Polymer Composite Bridge for Heavy Traffic Loads

Construction of the Asset Polymer Composite Bridge for Heavy Traffic Loads Construction of the Asset Polymer Composite Bridge for Heavy Traffic Loads Björn Täljsten Professor, Technical University of Denmark, Lyngby, Denmark and Luleå University of Technology, Luleå, Sweden 1

More information

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables J. Manterola A. Martínez Carlos Fernández Casado S.L., Spain B. Martín J.A. Navarro M. A:

More information

Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities

Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities Acoustic Decoupling Measures Plan 12 September 2012 Main

More information

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG CONCRETE SPLICED GIRDERS IN TEXAS Nicholas Nemec, P.E. TxDOT-BRG October 15, 2014 What is a Concrete Spliced Girder? 2 What is a Concrete Spliced Girder? What it is NOT : Continuous For Live Load 3 What

More information

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction

Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction Boeing North Bridge: Lessons Learned in Accelerated Bridge Construction Gregory A. Banks, Myles Parrish, Charles W. Spry WSDOT ABC Workshop April 2015 Project Overview Location Located in Renton, WA PROJECT

More information

COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO. C.Sankarlingam Vice President L & T Ltd.

COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO. C.Sankarlingam Vice President L & T Ltd. COMPLICATIONS IN CONSTRUCTION OF METROS IN URBAN AREAS A CASE STUDY OF HYDERABAD METRO 2 0 1 7 C.Sankarlingam Vice President L & T Ltd. Abstract Project Brief: Hyderabad is located in the state of Telangana

More information

Dan Eckenrode Executive Director

Dan Eckenrode Executive Director Dan Eckenrode Executive Director pcigulfsouth1@att.net www.pcigulfsouth.org PCI Gulf South Became a chapter of PCI in May 2016 12 Precast producers Covers 3 states, AL, MS, & LA Work with DOT s on Transportation

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

CASE STUDIES FOR STEEL BRIDGE ERECTION: CONVENTIONAL, LATERAL SLIDES, AND INCREMENTAL LAUNCHING

CASE STUDIES FOR STEEL BRIDGE ERECTION: CONVENTIONAL, LATERAL SLIDES, AND INCREMENTAL LAUNCHING CASE STUDIES FOR STEEL BRIDGE ERECTION: CONVENTIONAL, LATERAL SLIDES, AND INCREMENTAL LAUNCHING MATTHEW BOWSER DOUG DIXON BIOGRAPHY Matthew works as a Project Engineer in the bridge division of MMM Group

More information

Nutrient Response to Sewage Abatement in Hong Kong

Nutrient Response to Sewage Abatement in Hong Kong Nutrient Response to Sewage Abatement in Hong Kong Prof. Paul J. Harrison Atmospheric, Marine & Coastal Environment Program Institute for the Environment HK University of Science & Technology Outline Background

More information

CONSTRUCTABILITY IMPROVEMENT OF BRIDGES USING STEPPING FORMWORK

CONSTRUCTABILITY IMPROVEMENT OF BRIDGES USING STEPPING FORMWORK CONSTRUCTABILITY IMPROVEMENT OF BRIDGES USING STEPPING FORMWORK By Mohamed Emam Abd El-Razek, 1 and Ismail M. Basha 2 ABSTRACT: Many construction systems have been used to build several highway bridges

More information

REPORT Condition D19 Permanent Noise Barriers

REPORT Condition D19 Permanent Noise Barriers REPORT Condition D19 Permanent Noise Barriers Project Name: WestConnex New M5 Project number: 15.7020.2597 Revision date: 19/08/2016 Revision: 1 Document Approval Rev. Prepared by Reviewed by Recommended

More information