PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE

Size: px
Start display at page:

Download "PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE"

Transcription

1 PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE

2 Overview 1. Project Objectives 2. Bridge Data 3. Timeline 4. Existing Condition 5. Sequence of Coating and Repair Operations 6. Major Repair Items 7. Environmental Monitoring 8. Special Challenges 9. Rehabilitated Condition 10. Closing / Questions

3 Huey P Long US-190 Mississippi River Bridge The Huey P. Long Bridge is a continuous steel cantilever truss bridge over the Mississippi River carrying US 190 (Airline Highway) and one rail line between East Baton Rouge Parish, Louisiana and West Baton Rouge Parish, Louisiana View of the bridge from the Capital Building Observatory looking South

4 Project Objectives 1. To clean and paint the steel bridge substructure and superstructure components 2. To evaluate and repair or replace deteriorated steel truss span and deck girder span members, as well as steel and concrete substructure components 3. To repair or replace deteriorated or damaged roadway components within the bridge right-of-way 4. To preserve the bridge for continued usage in the 21st century with minimal disruption to roadway, rail, and river traffic

5 Bridge / Project Data 1. Bridge Type: Continuous Steel Cantilever Truss 2. Location: Mississippi River Milepost Year Completed: 1940, widened in Clearance: 111 feet AMSL 5. Traffic: ADT is 28,388; Rail carries 5-6 trains per day

6 Project Data 1. Total length of project: ½ from East highway abutment to West highway abutment 2. Estimated Square Feet for Cleaning and Painting: 3,675,420 from East highway abutment to West highway abutment 3. Total Original Project Cost: $74,849, Current Project Cost: $78,371, Current Project Completion: 98% 6. Current Overrun: 4.71%

7 Timeline

8 Timeline Project start: Notice to Proceed June 28, Day Assembly Period. Construction began September 24, Project completion date projected for April Working Days: 858 (began as 520 before construction) Calendar days: 3 years and 8 months to date

9 Existing Condition Bridge was last painted in the 1980 s. Existing coating was lead containing. Extensive pack rust, crevice, and pitting corrosion, resulting in areas of significantly reduced metalwork section to member components and fasteners. General coating breakdown and surface corrosion. Significant dirt and debris accumulations within some members. Poor roadway joint conditions. Concrete was in relatively good condition in most locations.

10 Existing Condition

11 Existing Condition

12 Existing Condition

13 Existing Condition

14 Sequence of Coating and Repair Operations 1. Containment (Class 1A) 2. Pressure washing (5,000 psi) 3. Chloride, Sulphate and Nitrate (CSN) testing for Surface Contaminants 4. Blast Cleaning to SSPC SP-10 and Hand & Power Tool Removal of Areas of Pack Rust 5. Prime Coat Application (Organic Zinc Rich) 6. Prime Coat Touch-up 7. Post-Blast Structural Inspections 8. Structural Repairs 9. Post-Structural Repairs Sequence of Painting

15 Project Clean & Paint Cost Breakdown Cleaning and Painting of approximately 3.6 million square feet. Lump Sum Bid Price for Painting of approximately 50 million dollars. Approximately $13.45 per square foot for painting.

16 Project Clean & Paint Cost Breakdown

17 Containments - Approaches

18 Girder Containments Approaches Platform Cables, Metal Decking over Roadways

19 Girder Containments Approaches Platform Cables, Fencing and Tarps

20 Tower Containments Approaches Temporary Traffic Barriers Anchored Cables for Tarps

21 Containment

22 Containment

23 Containment

24 Containment Entryway

25 Inside the Tower Containment

26 Containments - Main Bridge

27 Containments - Main Bridge

28 Containments - Main Bridge

29 Containments - Main Bridge

30 Containments - Main Bridge

31 Pressure Washing

32 Pressure Washing

33 Chloride, Sulphate and Nitrate (CSN) Testing

34 Abrasive testing Oil testing Conductivity testing

35 Blast Cleaning

36 Blast Cleaning

37 Blast Cleaning

38 Blast Cleaning

39 Prime Coat Application

40 Post-Blast Structural Inspections Used to determine if additional repairs were required due to section losses after corrosion removal Also used to determine required deteriorated rivet replacement that was necessary (per rivet) Each was conducted jointly with the Contractor after prime coat application Quantities of items were recorded and agreed upon daily, then compared to bid items Final document was produced for record, altered quantities were captured in periodic change orders

41 Post-Blast Structural Inspections

42 Structural Repairs Clean and prime coat existing metalwork and faying surfaces to receive repairs Install or conduct repairs i.e. gusset plate clips, replace rivets, full or partial member replacement, etc. Install mechanically galvanized fasteners at repairs.

43 Major Repair Items

44 Approach Bent Anchor Bolt Replacement Boh Bros conducted concrete pedestal expansion work and anchor bolt installation, American Bridge conducted steel bracket installation and connection to the bent columns. Required 1908 CY of excavation, 585 CY of concrete, 288 anchor bolts, and 144 brackets.

45 Approach Bent Anchor Bolt Replacement

46 Approach Bent Anchor Bolt Replacement

47 Approach Bent Anchor Bolt Replacement

48 Rivet Removal and HS Bolt Replacement 106,000 projected, 47,346 conducted Replacement criteria was agreed upon prior to work beginning (MM created, all parties consented) American Bridge conducted this work. Required reconsideration once approach work was complete (differing conditions on main truss) Tracked and agreed upon daily between AB and MM Savings was used to pay for fabrication and installation of bottom chord perforation covers to mitigate future section loss

49 Rivet Removal and HS Bolt Replacement

50 Rivet Removal and HS Bolt Replacement

51 RR Stringer Stirrup Bearing Repairs 40 projected, 40 conducted American Bridge conducted this work Required evaluation after railroad closure, stringer jacking, and dismantling to determine if all repair types would be conducted Faying surfaces had to be prepped and coated during closure 14-hour rail closure agreed upon in advance, none went over 13 Final closure only lasted 7 hours

52 RR Stringer Stirrup Bearing Repairs

53 RR Stringer Stirrup Bearing Repairs

54 RR Stringer Stirrup Bearing Repairs

55 RR Stringer Stirrup Bearing Repairs

56 Power tool cleaning of faying surfaces and prime coating

57 RR Stringer Stirrup Bearing Repairs

58 RR Stringer Stirrup Bearing Repairs

59 RR Tower Bent Member Replacement 201 projected, 237 conducted American Bridge conducted this work Most required temporary bracing and had to be completed during the RR closure (members not allowed to be removed during rail traffic)

60 RR Tower Bent Member Replacement

61 RR Tower Bent Member Replacement

62 Post Structural Repairs Clean primed steel of dust, dirt and debris from repair activities Solvent clean to remove any oil, grease or grime deposits and solvent and hand tool clean mechanically galvanized fasteners to roughen the surface Prime coat touch-up areas of damaged primer and galvanizing of the installed fasteners.

63 Post Structural Repairs Sequence of Painting Clean and apply penetrating sealer to any areas of irremovable crevice corrosion Apply red tinted prime stripe coat Apply grey tinted epoxy intermediate stripe coat Apply white epoxy intermediate coat and touch-up Apply caulking to all gaps between plates ½ or less Apply Louisiana Grey polyurethane topcoat and touch-up

64 Penetrating Sealer Application

65 Cleaning of Galvanized Fasteners

66 Prime Stripe Coat Application

67 Intermediate Stripe Coat

68 Intermediate Coat Application

69 Topcoat Application Main Bridge

70 Topcoat Application - Approaches

71 Touch-up of Containment Contact Points

72 Environmental Monitoring

73 KGC Environmental Services Inc. Scope of Services Perform TSP-Lead high volume air monitoring during lead emission generating activities. Conduct visible emission and visible accumulation assessments in order to measure the containment system efficacy. Mitigate environmental risk by identifying potential issues before they occur. Ensure compliance with all laws, regulations and contract specifications pertaining to hazardous waste management, ambient air quality and protection of the environment. Conduct pre-job and post-job soil sampling. Provide detailed and legally defensible environmental data.

74 TSP-Lead Ambient Air Monitoring

75 TSP-Lead Ambient Air Monitoring

76 KGC Summary of Environmental Data Suspected Cause of (TSP-Lead)Air Quality Project Limit Exceedance Structural Repairs, Rivet Busting, Plate Clipping & Grinding Number of Exceedances 40 Blowing Down Without Full Containment & Ventilation Abrasive Blasting, Vacuuming & Recycling 14 Containment Dismantling 4 Site Clean-Up & Moving Equipment 2 17

77 Hazardous Waste Management

78 Hazardous Waste Management Number of Hazardous Waste Shipments 25 Number of 55 Gallon Waste Drums Used 1,085 Pounds of Hazardous Waste Recycled/Disposed 837,135 pounds

79 Challenges & Lessons Learned Sensitive Receptor Areas- multiple businesses and residences were extremely close to the bridge. In order to mitigate the risk associated with abrasive blasting a coating system that contained lead and chromium next to sensitive receptors, the contractor instituted special containment and housekeeping procedures. KGC performed 24 hour high volume sampling to confirm that the sensitive receptors were not being negatively impacted as a result of the contractor s activities. Structural Repairs including rivet busting, plate clipping and grinding disturbed lead coated faying surfaces. The majority of the TSP-lead air samples that were over the project limit were a result of the aforementioned activities. Engineering controls and high volume air monitoring should be considered when LADOTD performs repairs and maintenance on other projects where the existing coating system contains heavy metals. Housekeeping is Paramount - thorough vacuuming of lead dust and abrasives from steel members and containment tarps prior to containment dismantling is essential to keeping a safe work environment. As the blasting and painting crews progressed down the bridge, iron workers moved in to perform the necessary structural repairs. At times they worked in less than ideal work conditions.

80 Challenges & Lessons Learned Equipment Storage Yards Require the contractor to store all blasting and painting equipment and materials used on the project on state property. Otherwise, heavy metals that are invariably present on these items could be released onto public property opening the LADOTD to potential litigation and remedial efforts.

81 Special Challenges Water Ponding in Past Pitting Corrosion Lower Chord Horizontal Diaphragms

82 Special Challenges Slurry Blasting Tower Column Base Repairs

83 Special Challenges Slurry Blasting Tower Column Base Repairs

84 Special Challenges Slurry Blasting Outboard Roadway Railings

85 Containments- Bridge Rail

86 Special Challenges Slurry Blasting and Painting Outboard Roadway Railings

87 Special Challenges RR Coordination

88 Special Challenges Steel Repair and Inspection Access

89 Special Challenges Steel Repair and Inspection Access

90 Special Challenges - Snooper used for Final Touch-up of Platform Contact Points

91 Rehabilitated Condition

92 Rehabilitated Condition

93 Rehabilitated Condition

94 Rehabilitated Condition

95 Rehabilitated Condition

96

97 Closing / Questions

Rehabilitation Design and Construction for the US 190 Mississippi River Bridge Cleaning, Painting, and Repair Project

Rehabilitation Design and Construction for the US 190 Mississippi River Bridge Cleaning, Painting, and Repair Project Rehabilitation Design and Construction for the US 190 Mississippi River Bridge Cleaning, Painting, and Repair Project 2013 Louisiana Transportation Conference Session 13 Durk Krone, P.E., TRC Engineers,

More information

Table of Contents. List of Drawings

Table of Contents. List of Drawings SCOPE OF WORK Hastings Stadium Exhibition Park, 81 London Road, Guelph, Ontario Structural and Maintenance Remedial Work Prepared For City of Guelph City Hall, 1 Carden Street, Guelph, ON N1H 3A1 Prepared

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Sheet 1 of 9 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION SECTION STRUCTURAL STEEL CONSTRUCTION Page 392, subsection.01. Add the following bid items:

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9080 - Concrete Steps, Handrails, and Safety Rail CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL PART - GENERAL.0 SECTION INCLUDES

More information

ESTIMATE OF QUANTITIES

ESTIMATE OF QUANTITIES ESTIMATE QUANTITIES STATE S.D. SHEET NO. TOTAL SHEETS 2 12 SPECIFICATIONS TEMPORARY PAVEMENT MARKING, Continued STATE S.D. SHEET NO. TOTAL SHEETS 3 12 South Dakota Standard Specifications for Roads and

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

Stay-Cable Replacement Design

Stay-Cable Replacement Design Stay-Cable Replacement Design Mississippi River Bridge Luling, Louisiana Christopher Ligozio CTLGroup Copyright Post-Tensioning Institute all rights reserved. Page 1 of 35 Luling Bridge Copyright Post-Tensioning

More information

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25 General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO

More information

Evaluation of Rehabilitation Alternatives for the Cedar Avenue Bridge

Evaluation of Rehabilitation Alternatives for the Cedar Avenue Bridge Evaluation of Rehabilitation Alternatives for the Cedar Avenue Bridge Mn/DOT Bridge No. 3145 Prepared for Minnesota Department of Transportation and City of Bloomington, Minnesota Prepared by www.meadhunt.com

More information

SECTION High Performance Coatings Field Applied Acrylic Urethanes (Solid Color, Pearl and Metallic Finishes)

SECTION High Performance Coatings Field Applied Acrylic Urethanes (Solid Color, Pearl and Metallic Finishes) - 1 - SECTION 099600 High Performance Coatings Field Applied Acrylic Urethanes (Solid Color, Pearl and Metallic Finishes) PART 1 GENERAL 1.1 SECTION INCLUDES A. Systems for field applied acrylic urethane

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

PREFABRICATED STEEL TRUSS SPECIFICATIONS

PREFABRICATED STEEL TRUSS SPECIFICATIONS PREFABRICATED STEEL TRUSS SPECIFICATIONS 1. GENERAL 1.1 Scope All engineering design and related detailing of the bridge(s) shall be provided by the supplier. The design and detailing shall conform to

More information

SUPERIOR PRODUCTS INTERNATIONAL LEAD-BASED PAINT ABATEMENT ENCAPSULATION METHOD THAT ELIMINATES SANDBLASTING FOR STEEL STRUCTURES

SUPERIOR PRODUCTS INTERNATIONAL LEAD-BASED PAINT ABATEMENT ENCAPSULATION METHOD THAT ELIMINATES SANDBLASTING FOR STEEL STRUCTURES SUPERIOR PRODUCTS INTERNATIONAL INTRODUCES A LEAD-BASED PAINT ABATEMENT ENCAPSULATION METHOD THAT ELIMINATES SANDBLASTING FOR STEEL STRUCTURES Superior Products RUST GRIP and ENAMO GRIP Before 1 LEAD-BASED

More information

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , & TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed

More information

D R A F T Field Inspection and Condition Report

D R A F T Field Inspection and Condition Report D R A F T Field Inspection and Condition Report for UNION STREET RAILROAD BRIDGE (Rails-to-Trails Conversion) Key No. 11085 ODOT, Region 2 Local Agency On-Call ATA 23456 WOC 1 City of Salem, Urban Development

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes

More information

KENTUCKY TRANSPORTATION CENTER

KENTUCKY TRANSPORTATION CENTER Research Report KTC-08-20/FR155-06-1F KENTUCKY TRANSPORTATION CENTER EXPERIMENTAL CONCRETE COATING APPLICATION ON THE MEDIAN BARRIER OF I-65 IN LOUISVILLE OUR MISSION We provide services to the transportation

More information

Society of Women Engineers Region H Conference

Society of Women Engineers Region H Conference Society of Women Engineers Region H Conference Faith Duncan, PE & Greg Hasbrouck, PE Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Project Overview US 52 / IL 64 over the Mississippi

More information

PRODUCT GUIDE: ZINC-RICH COATINGS. Version:

PRODUCT GUIDE: ZINC-RICH COATINGS. Version: PRODUCT GUIDE: ZINC-RICH COATINGS Version: 08.07.17 305 Zinc Rich Epoxy Polyamide Primer Description: 305 is a user friendly zinc-rich epoxy primer formulated for use as a primer under acrylic, epoxy,

More information

Transmission Tower Maintenance Bottom Line Savings Through Active Maintenance

Transmission Tower Maintenance Bottom Line Savings Through Active Maintenance Transmission Tower Maintenance Bottom Line Savings Through Active Maintenance Introduction Transmission towers/poles are among an electrical utility s largest and most important commercial assets. Unfortunately,

More information

Port of Lake Charles RE: 3501 Bayou D Inde Road 200,000 Gallon EWT

Port of Lake Charles RE: 3501 Bayou D Inde Road 200,000 Gallon EWT P.O. Box 3753 Lake Charles, LA 70602 July 21, 2016 Mr. Nick Pestello Assistant Director of Engineering (337) 794-3687 Job No. 316288 If you would like to speak with Patrick Heltsley concerning this report,

More information

A. Types of lightgauge metal framing units include the following: 1. C-shaped structural steel studs Uniform Building Code.

A. Types of lightgauge metal framing units include the following: 1. C-shaped structural steel studs Uniform Building Code. SECTION 05400 COLD-FORMED METAL FRAMING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification

More information

Property Test/Standard Description. US EPA method 24 (tested) (CARB(SCM)2007, SCAQMD rule 1113, Hong Kong)

Property Test/Standard Description. US EPA method 24 (tested) (CARB(SCM)2007, SCAQMD rule 1113, Hong Kong) Approved 402;2522 1,2 2522 zinc epoxy ^(ValidationDate) 1 Product description This is a two component polyamide cured zinc rich epoxy coating. It is a high zinc dust containing product. It conforms to

More information

A STRUCTURAL ASSESSMENT STUDY ON THE SUSTAINABILITY OF SULTAN ISKANDAR BRIDGE KUALA KANGSAR PERAK MALAYSIA

A STRUCTURAL ASSESSMENT STUDY ON THE SUSTAINABILITY OF SULTAN ISKANDAR BRIDGE KUALA KANGSAR PERAK MALAYSIA A STRUCTURAL ASSESSMENT STUDY ON THE SUSTAINABILITY OF SULTAN ISKANDAR BRIDGE KUALA KANGSAR PERAK MALAYSIA Lim Char Ching Public Works Department, Malaysia Email: cclim.jkr@1govuc.gov.my, Tel: 012-238

More information

I-94/I-69 Interchange Bridge Construction

I-94/I-69 Interchange Bridge Construction I-94/I-69 Interchange Bridge Construction General Project Information Let in August 2013 Cost of $76 million Prime Contractor Walter Toebe Construction Company Reconstruction of I-94 from Griswold to Lapeer

More information

SURFACE PREPARATION BEFORE PAINTING

SURFACE PREPARATION BEFORE PAINTING SURFACE PREPARATION: For any given paint system, surface preparation is the single important factor which would determine its performance. Various surface preparation methods are adopted depending on the

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT ATHABASCA RIVER BRIDGE REHABILITATION PROJECT PROJECT INFORMATION Project Name Athabasca River Bridge Rehabilitation Project Location Highway 40 (over the Athabasca River), Entrance, Alberta Year Completed

More information

SECTION PREFABRICATED PIPE BRIDGE(s)

SECTION PREFABRICATED PIPE BRIDGE(s) SECTION 13135 - PREFABRICATED PIPE BRIDGE(s) PART 1 - GENERAL 1.01 Scope A. The Contractor is responsible for all engineering design, detailing, fabricating, installation including foundations for the

More information

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

ROOF SUBSTRATE PREP MANUAL

ROOF SUBSTRATE PREP MANUAL ROOF SUBSTRATE PREP MANUAL ALDOCOAT Liquid Applied Roof Restoration Systems AFTER BEFORE JULY 2016 1604 N. Main St. Kannapolis, NC 28081 (800) 474-6019 www.aldoproducts.com ROOF SUBSTRATE PREPARATION Preparation

More information

Section 2 Supplemental Specification 2.11 High Tension Cable Barrier

Section 2 Supplemental Specification 2.11 High Tension Cable Barrier 2.11 HIGH TENSION CABLE BARRIER 2.11.1 GENERAL This Work consists of the supply, installation, removal, disposal and reinstallation of High Tension Cable Barrier (HTCB) system. 2.11.2 DEFINITIONS AND INTERPRETATION

More information

Florock Seamless Flooring Systems

Florock Seamless Flooring Systems Architectural Specification FloroCrete RT Rake/Trowel Urethane Mortar 3/16-1/4 (4.5-6.0 mm) Floor Resurfacing System Part 1: General 1.01 System Description A. System I Skid-Resistant Finish Resurfacing

More information

Structural Evaluation Report. Johnson Street Bridge Rehabilitation. Victoria, British Columbia

Structural Evaluation Report. Johnson Street Bridge Rehabilitation. Victoria, British Columbia Structural Evaluation Report Johnson Street Bridge Rehabilitation Victoria, British Columbia Prepared for MMM Group Limited Vancouver, BC May 2010 Table of Contents Page 1.0 Introduction 1 2.0 Seismic

More information

HYDROJETTING INFORMATION. a six page issue October 1999

HYDROJETTING INFORMATION. a six page issue October 1999 a six page issue Hydrojetting is the surface preparation of steel using high-energy water to remove coatings, corrosion products and other surface contamination such as oil/grease etc. It relies totally

More information

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS BRIDGE PREVENTIVE MAINTENANCE STRATEGY Approved January 3, 2007 BLANK Purpose To maximize the non-deficient service life of local bridges in the Erie-Niagara region, members of the Greater Buffalo-Niagara

More information

Chapter 2. Basic practices. Topics. 7 Basic practices. Notes. 2.5 Existing flooring and adhesive residue Job site conditions 8

Chapter 2. Basic practices. Topics. 7 Basic practices. Notes. 2.5 Existing flooring and adhesive residue Job site conditions 8 7 Basic practices Chapter 2 Basic practices Topics 2.1 Job site conditions 8 2.2 Wood subfloors 9 2.3 Concrete subfloors 10 2.5 Existing flooring and adhesive residue 11 2.6 Radiant heat subfloors 11 2.7

More information

Fine-Tune Your Knowledge On The Metallizing Process

Fine-Tune Your Knowledge On The Metallizing Process Fine-Tune Your Knowledge On The Metallizing Process 1. What is Metallizing? Metallizing is a common term used to describe thermal sprayed metal coatings. For corrosion protection of steel elements, it

More information

The Design of the New Portageville Bridge

The Design of the New Portageville Bridge The Design of the New Portageville Bridge Daniel B. Irwin, P.E. Modjeski and Masters, Inc 100 Sterling Parkway, Suite 302 Mechanicsburg, PA 17050 (717)790-9565 dbirwin@modjeski.com Kevin W. Johns, P.E.

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014

More information

Designing Bridges for Inspectability

Designing Bridges for Inspectability Designing Bridges for Inspectability Sreenivas Alampalli 1 and Arthur P. Yannotti 2 1 New York State Department of Transportation 50 Wolf Road, Albany, NY 12232 (518) 457-5498; salampalli@dot.state.ny.us

More information

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements

More information

Rust-Oleum Industrial Brands Specification

Rust-Oleum Industrial Brands Specification Rust-Oleum Industrial Brands Specification Coating Specification for Rust-Oleum Virtual Solutions Coating Solution 2 A solvent based coating system High Performance 9100/9800 System DTM Epoxy Mastic/DTM

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 11/21/2014 Project 140560 Addendum No. 2 PID No. 82972 HAM IR 275

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2013 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Frank D. Rea Director of Coatings Services / Chief Chemist

Frank D. Rea Director of Coatings Services / Chief Chemist State of the Union Cleaning and Painting Steel Bridges Frank D. Rea Director of Coatings Services / Chief Chemist CURRENT PRACTICES AND MATERIALS LESSONS LEARNED THE LATEST CURRENT PRACTICES AND MATERIALS

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-05 51 33 (February 2016) Change 2-02/18 ----------------------------- Preparing Activity: NAVFAC Superseding UFGS-05 51 33 (May 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE Bridge Manual - Part I - June 2007 5-1 CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE 5.1 GENERAL This chapter is intended to instruct the Designer in the preparation and submission of Special Provisions and

More information

D D TYPE A1, A2 & B MICHIGAN DEPARTMENT OF TRANSPORTATION 5-40 CONNECTION. L4" x 4" x 3/8" Brace. C8 x 4.25 Strut. WT9 x 17.5.

D D TYPE A1, A2 & B MICHIGAN DEPARTMENT OF TRANSPORTATION 5-40 CONNECTION. L4 x 4 x 3/8 Brace. C8 x 4.25 Strut. WT9 x 17.5. Sign length minus Adjust to avoid interference with sign legend A Deck fascia A 6" Equal Equal 6" Sign length (L) varies 6 to 12 PLAN 0 CONNECTION (DECK FASCIA) Angle connection assembly F Face of concrete

More information

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

SECTION BASIC ELECTRICAL MATERIALS AND METHODS SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:

More information

Tate Access Floors, Inc. ConCore 1250 Access Floor Panel Bolted Stringer Understructure System

Tate Access Floors, Inc. ConCore 1250 Access Floor Panel Bolted Stringer Understructure System Notice: Tate Access Floors, Inc. ConCore 1250 Access Floor Panel Bolted Stringer Understructure System If you are using MasterFormat 2004 Edition, the proper section number to use is Section 09 69 00,

More information

Pigeon Forge, Tennessee City Hall and Thurman Lift Station Coating Rehabilitation. Contract Documents

Pigeon Forge, Tennessee City Hall and Thurman Lift Station Coating Rehabilitation. Contract Documents Pigeon Forge, Tennessee City Hall and Thurman Lift Station Coating Rehabilitation April 21, 2017 Contract Documents Prepared By: Veolia Water North America For the City of Pigeon Forge, Tennessee P.O.

More information

PERFORMANCE OF COATINGS OVER WATERJETTED SURFACES J. PETER AULT, P.E. ELZLY TECHNOLOGY CORPORATION

PERFORMANCE OF COATINGS OVER WATERJETTED SURFACES J. PETER AULT, P.E. ELZLY TECHNOLOGY CORPORATION PERFORMANCE OF COATINGS OVER WATERJETTED SURFACES J. PETER AULT, P.E. ELZLY TECHNOLOGY CORPORATION LEARNING OBJECTIVES THIS WEBINAR WILL EXPLORE ISSUES ASSOCIATED WITH WATERJETTING SURFACE PREPARATION

More information

BEARING METAL STUD FRAMING

BEARING METAL STUD FRAMING L-1 Section 05410 Long Form Specification LOAD BEARING METAL STUD FRAMING This section includes axially loaded steel studs, with unique slotted top channels, usually of 0.91, 1.2 and 1.5 mm (16, 18, or

More information

Short Span Steel Bridges

Short Span Steel Bridges Short Span Steel Bridges MINK 2015 Michael Barker, PE University of Wyoming & SSSBA Bridge Technology Center Outline of Today s Presentation SSSBA & espan140 Design Competitiveness of Steel Bridges Economics

More information

DUGOUT MODEL (4 POST) 10 x 24 SPECIFICATIONS

DUGOUT MODEL (4 POST) 10 x 24 SPECIFICATIONS DUGOUT MODEL (4 POST) 10 x 24 SPECIFICATIONS Dimensions: Roof Dimensions 10-0 x 24 Column Dimensions (center to center) 6-7 x 22-9 Minimum Clearance 7-6 Minimum Clearance @ Front ±9-2 Roof Pitch 2:12 pitch

More information

I-74 Corridor in the Quad Cities A State of the Art Design

I-74 Corridor in the Quad Cities A State of the Art Design I-74 Corridor in the Quad Cities A State of the Art Design Mid-Continent Transportation Research Symposium August 16-17, 2017 Presented By: Norm McDonald, Iowa DOT State Bridge Engineer PRESENTATION OUTLINE

More information

Chapter 4 Bridge Program Drawings

Chapter 4 Bridge Program Drawings Chapter 4 Bridge Program Drawings Section 4.10-Bridge Railing Introduction Steel bridge railing and concrete bridge barrier rail are installed along the edge of the bridge roadway to keep errant vehicles

More information

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014

STATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014 STATE STRUCTION FUND DIRECTIVE 5-1 Issue date: October 2014 STRUCTURAL STEEL 1. General: It is the Fund's policy that the design of the structural steel is the prime responsibility of the project's Structural

More information

NXT SUBSTRATE PREPARATION AND PRIMER GUIDE TDS 230N

NXT SUBSTRATE PREPARATION AND PRIMER GUIDE TDS 230N NXT SUBSTRATE PREPARATION AND PRIMER GUIDE TDS 230N Substrate preparation is the most important factor to successful NXT self-leveling underlayment (SLU) and NXT Vapor Reduction Coating installations.

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

SECTION 1043 FENCE MATERIAL

SECTION 1043 FENCE MATERIAL SECTION 1043 FENCE MATERIAL 1043.1 Scope. This specification covers the material required in the construction of chainlink fence and woven wire fence. 1043.2 Basis of Acceptance. The basis of acceptance

More information

Carboguard 890 PRODUCT DATA SHEET SELECTION & SPECIFICATION DATA. Generic Type. Cycloaliphatic Amine Epoxy

Carboguard 890 PRODUCT DATA SHEET SELECTION & SPECIFICATION DATA. Generic Type. Cycloaliphatic Amine Epoxy SELECTION & SPECIFICATION DATA Generic Type Description Features Color Finish Primer Cycloaliphatic Amine Epoxy Highly chemical resistant epoxy mastic coating with exceptionally versatile uses in all industrial

More information

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents

Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Accelerated Bridge Construction (ABC) webinar Thursday, October 24, 2013 ABC Center at Florida International University (FIU) presents Washington State s Skagit River Bridge Emergency Slide Bijan Khaleghi

More information

A. Section Metal Decking. (05300 in MF95) B. Section Cold Formed Metal Framing. (05400 in MF95)

A. Section Metal Decking. (05300 in MF95) B. Section Cold Formed Metal Framing. (05400 in MF95) SECTION 05 44 00 - PRE-ENGINEERED PRE-FABRICATED COLD-FORMED STEEL TRUSSES (Section 05425 in MasterFormat 1995) PART 1 GENERAL 1.1 SECTION INCLUDES A. Pre-engineered cold-formed steel trusses. B. Cold-formed

More information

US 278 East Bound and West Bound. MacKay Creek and Skull Creek. Cursory Above Water and Underwater Investigation Of. Over

US 278 East Bound and West Bound. MacKay Creek and Skull Creek. Cursory Above Water and Underwater Investigation Of. Over Cursory Above Water and Underwater Investigation Of US 278 East Bound and West Bound Over MacKay Creek and Skull Creek In Hilton Head, South Carolina Bridges over MacKay Creek Bridges over Skull Creek

More information

CHAIN LINK FENCES AND GATES

CHAIN LINK FENCES AND GATES SECTION 02831 CHAIN LINK FENCES AND GATES PART 1 GENERAL 1.01 SUMMARY A. Alternate Material for Fence Post and Framing Material: Where schedule 40 galvanized steel is specified, the following will be accepted:

More information

Deck Joints and Bearings

Deck Joints and Bearings Deck Joints Deck Joints and Purpose is to: bridge the gap between spans protect the ends of the girders allow for expansion, contraction and rotational movement prevent water and salt from leakage Most

More information

Preserva on Assessment

Preserva on Assessment Preserva on Assessment For Ftorkowski Road Bridge over Hun ngton Creek BMS # 40 7217 0482 6006 Luzerne County PennDOT Engineering District 4 0 Final Report June 2016 Prepared by TranSystems for the Pennsylvania

More information

Bridge Deck Preservation Treatment Options

Bridge Deck Preservation Treatment Options Western Bridge Preservation Partnership May 17-18, 2016 Salt Lake City, Utah Bridge Deck Preservation Treatment Options Gregg Freeman - Kwikbond Polymers Rob Johnson - Transpo Industries Clay Christiansen

More information

Ballast Water Tanks Repair Guide for Crew

Ballast Water Tanks Repair Guide for Crew January 2011 Ballast Water Tanks Repair Guide for Crew This brief introduction is only intended as a guide for crew repairs with CHEMCO products Epo-chem RS 500P and RA 500M. This is a guideline for how

More information

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects The Chief Estimator Software Item Cost Summary Bridge & Overpass Projects Elevated Transit Guideways Precast Girder Elevated Guideway 10 Abutment Excavation & Backfill 1,500.00 m3 222 10,368 8,634 1,309

More information

STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Bridge Project/Plan Authorization and Approval Authority SPECIFIC SUBJECT:

More information

FACT SHEET #2 DECK INFORMATION

FACT SHEET #2 DECK INFORMATION Borough of Doylestown Building and Zoning Department 57 West Court Street, Doylestown, PA 18901 215.345.4140 FACT SHEET #2 DECK INFORMATION BACKGROUND The provisions of the PAUCC. ICC Property Maintenance

More information

Stay Cable Replacement of the Luling Bridge Armin Mehrabi Bridge Engineering Solutions

Stay Cable Replacement of the Luling Bridge Armin Mehrabi Bridge Engineering Solutions Stay Cable Replacement of the Luling Bridge Armin Mehrabi Bridge Engineering Solutions AMehrabi@BESbridge.com 2013 Louisiana Transportation Conference February 20, 2013, Baton Rouge, LA Hale Boggs (Luling)

More information

SECTION EPOXY FLOORING SYSTEMS

SECTION EPOXY FLOORING SYSTEMS SECTION 09800 EPOXY FLOORING SYSTEMS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

ITEM 458 WATERPROOFING FOR STRUCTURES

ITEM 458 WATERPROOFING FOR STRUCTURES ITEM 458 WATERPROOFING FOR STRUCTURES 458.1. Description. This Item shall govern for the furnishing and placing of waterproofing on concrete and steel bridge decks of railroad structures and on other structures

More information

Gusset Plate Retrofit in Illinois

Gusset Plate Retrofit in Illinois Gusset Plate Retrofit in Illinois Jayme F. Schiff, P.E., S.E. Repair Plans Unit Chief Illinois Department of Transportation October, 2010 1 Illinois DOT s Guidelines for Rating Gusset Plates by the Load

More information

Refer to Substrates & Surface Preparation.

Refer to Substrates & Surface Preparation. SELECTION & SPECIFICATION DATA Generic Type Description Features Color Finish Primer Dry Film Thickness Aliphatic Acrylic Polyurethane Thin film, high gloss finish with exceptional weathering performance

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Open-Web Truss Long Span Installation Guidelines

Open-Web Truss Long Span Installation Guidelines TECHNICAL BULLETIN #301 Open-Web Truss Long Span Installation Guidelines RedBuilt has maintained a policy of manufacturing and marketing products of the highest quality to our customers. We guarantee the

More information

Tested in accordance with ISO , high expected durability in corrosivity category C5-I. Property Test/Standard Description

Tested in accordance with ISO , high expected durability in corrosivity category C5-I. Property Test/Standard Description Approved 7461;7680 1,2 7680 zinc epoxy ^(ValidationDate) 1 Product description This is a two component polyamide cured zinc rich epoxy coating. It is a high solids, high zinc dust containing product. It

More information

1.1 This Section includes surface preparation and the application of base coats, intermediate and topcoats.

1.1 This Section includes surface preparation and the application of base coats, intermediate and topcoats. PAINTING GENERAL INFORMATION 1.1 This Section includes surface preparation and the application of base coats, intermediate and topcoats. DESIGN REQUIREMENTS 2.1 Material Compatibility: a. Provide materials

More information

To ensure warranty eligibility, each job must be approved by American WeatherStar before it begins.

To ensure warranty eligibility, each job must be approved by American WeatherStar before it begins. SPRAY POLURETHANE FOAM & COATINGover metal roof deck SPF To ensure warranty eligibility, each job must be approved by American WeatherStar before it begins. PART 1 GENERAL 1.01 DESCRIPTION A. The intention

More information

SECTION PLATE CONNECTED WOOD TRUSSES

SECTION PLATE CONNECTED WOOD TRUSSES SECTION 06173 PLATE CONNECTED WOOD TRUSSES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Shop fabricated wood trusses for roof and floor framing. 2. Bridging, bracing, and anchorage. B. Related Sections:

More information

Smarter. Safer. Leaner.

Smarter. Safer. Leaner. Smarter. Safer. Leaner. Fast Installation and Removal Decrease Leading Edge Exposure by 87% OSHA Compliant Versatile and Reusable Use Perimeter Protection Posts During Construction: At Building Perimeter

More information

A. Section includes surface preparation and the application of high-performance coating systems on the following substrates:

A. Section includes surface preparation and the application of high-performance coating systems on the following substrates: ILLINOIS STATE UNIVERSITY CORDOGAN, CLARK & ASSOCIATES, INC. WATTERSON DINING EXPANSION PROJECT 960 RIDGEWAY AVENUE NORMAL, ILLINOIS AURORA, ILLINOIS CCA PROJECT NUMBER: 14362 630-896-4678 BID SET JULY

More information

MINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM

MINNESOTA ARCHITECTURE - HISTORY INVENTORY FORM Identification Historic Name Bridge 5388 Current Name Bridge R0529 Field # Address State Highway 2 over the Little Iowa River City/Twp LeRoy Township County Mower Legal Desc. Twp 101N Range 14W Sec 21

More information

Addendum # 1 Perdue Stadium Seating Bowl Improvements Date of Addendum: 09/07/16

Addendum # 1 Perdue Stadium Seating Bowl Improvements Date of Addendum: 09/07/16 Wicomico County Purchasing 125 N. Division St. Room B-3 Salisbury, MD 21801 Ph. 410-548-4805 Fax 410-334-3130 Email: purchasing@wicomicocounty.org Addendum # 1 Perdue Stadium Seating Bowl Improvements

More information

American Railway Engineering & Maintenance-of-Way Association Letter Ballot

American Railway Engineering & Maintenance-of-Way Association Letter Ballot Assignment: At the January 2017 meeting in Ft. Myers, FL ballot 15-17-01 was proposed by the subcommittee and general committee to combine Sections 4.11 and 4.13 into a single Section and add Commentary.

More information

Joint Surface Preparation Standard. NACE No. 3/SSPC-SP 6 Commercial Blast Cleaning

Joint Surface Preparation Standard. NACE No. 3/SSPC-SP 6 Commercial Blast Cleaning Item No. 21067 Joint Surface Preparation Standard NACE No. 3/SSPC-SP 6 Commercial Blast Cleaning This NACE International (NACE)/SSPC: The Society for Protective Coatings standard represents a consensus

More information

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT

More information

The Contractor is responsible for quality control, including workmanship and materials furnished by his subcontractors and suppliers.

The Contractor is responsible for quality control, including workmanship and materials furnished by his subcontractors and suppliers. SECTION 05 31 33 - STEEL FORM DECKING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the contract, including General and Supplementary Conditions and Division 01 - Specification

More information

Anti-Graffiti Coatings Guide

Anti-Graffiti Coatings Guide Green Coatings in any colour Anti-Graffiti Coatings Guide Envirochoice Graffiti Protection 1st EDITION August 2012 contents about us About Us Page 3 s for Various Substrates Page 4 Product Overview Page

More information

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT PROJECT ROUTE 2, CANAAN/PITTSFIELD, MAINE G. Keith Donington, PE, Parsons Brinckerhoff, Manchester, NH Hany L. Riad, PhD, PE, Parsons Brinckerhoff, Boston, MA

More information