3rd Brazilian Congress on Tunnels and Underground Structures. International Seminar "South American Tunnelling - SAT 2012.

Size: px
Start display at page:

Download "3rd Brazilian Congress on Tunnels and Underground Structures. International Seminar "South American Tunnelling - SAT 2012."

Transcription

1 3rd Brazilian Congress on Tunnels and Underground Structures International Seminar "South American Tunnelling - SAT 2012 Júlio César Bueno

2 General Aspects

3

4

5 Acts of Good Third Party Employer Contractor

6 Acts of Good Third Party Employer Contractor

7 Acts of Good Third Party Employer Contractor

8 Acts of Good Third Party Employer Contractor

9 Acts of Good Third Party Employer Contractor

10 Acts of Good Third Party Employer Designer Contractor Subcontractor

11 Acts of Good Third Party Employer Designer Contractor Subcontractor

12 Acts of Good Third Party Employer Contractor Subcontractor Designer

13 Acts of Good Third Party Employer Contractor

14 International Approach: Two opposing views

15 The general rule: contractor s liability If a contractor has promised - in unqualified terms - to construct a building or other structure for a lump sum price, no excuse for late performance or nonperformance that the site conditions were worse than anticipated Agreed price is all that the contractor is entitled to be paid for doing so The risk of adverse site conditions, whether they be known or latent, is with the contractor

16 The general rule: contractor s liability US case law United States v Spearin (1918), 248 U.S. 132 Where one agrees to do, for a fixed sum, a thing possible to be performed, he will not be excused or become entitled to additional compensation, because unforeseen difficulties are encountered. Thus, one who undertakes to erect a structure upon a particular site, ordinarily assumes the risk of subsidence of soil. UK case law Bottoms v York Corporation (1892), Hudson Fourth Edition, Vol 2 Table of Cases; Workshop Tarmacadam Co Ltd v Hannaby (1995) 66 Con LR 105, CA

17 The If otherwise general rule: expected, contractor s contract liability should have an specific contractual release for the contractor Unless a contract makes specific provision for a contractor to be entitled to an extension of time for completion, additional compensation, or both, in the event of adverse conditions being encountered, the risk of those conditions will remain with the contractor Clauses dealing with force majeure or exceptionally weather conditions ARE NOT sufficiente as they ARE NOT to be considered the same as unforeseen bad ground

18 The general rule: contractor s liability Enhancing the general rule s application? Contractor has knowledge of the site Contractor has inspected the site or shall be deemed to have inspected it Contractor has satisfied itself on the form and nature of the site, including the soil and subsurface How far can these provisions go? Need to qualify reasonable knowledge or inspection Was the contractor really able to get to know the site, inspected it and to be satisfied?

19 A contract rule: risk with the owner Many standard forms give contractors extension of time and price increase in case of unforeseen ground conditions ICE - Institute of Civil Engineers (clause 12) NEC - Engineering and Construction Contract (clause 60.1) FIDIC - International Federation of Consulting Engineers (clause 4.12, of the new Red Book )

20 In those standard forms, owner may be excluded from A contract liability rule: when risk contractor with the owner ought to have anticipated such conditions Such forms apply the concept of imputed knowledge in opposition to actual knowledge What site investigations an experienced contractor ought to have conducted? What information an experienced contractor would have gleaned? How an experienced contractor ought to have interpreted the information?

21 A contract rule: risk with the owner In contrast, some US State legislatures provides a baseline of expected ground conditions and seek potential distinctions only A differing site condition clause entitles the contractor to additional time for completion and compensation No need for inquiry on what site conditions the contractor ought to have anticipated

22 About the information provided to contractor

23 1) Owner does not provide any information to contractor - No Information System 2) Owner provides information to contractor but does not warrant the accuracy of such information Disclaimer System 3) Owner provides information to contractor and warrants the accuracy and/or the completeness of such information DSC System

24 Disclaimer System Some special considerations for public owners Stenerson v City of Kalispell, (1981) 629 P.2d 773 Mont. Public entity either knew or should have known that the information would be relied on by bidders Is it fair to make such distinction?

25 DSC System The owner may find that shifting risk to the contractor is not in the owner s best interest In such a case, the owner may choose to accept the risk of unforeseen site and subsurface conditions The owner may be taken to warranty contractually, either expressly or by necessary implication, that the information provided to the contractor is accurate and should be followed Bacal Construction (Midlands) Ltd v Northampton Development Corporation (1975), 8 BLR 88, CA

26 DSC System Type I DSC Requires that there be an actual physical condition encountered at the site that differs materially from the conditions indicated in the contract document Type II DSC Requires a variance between the site condition actually encountered and that which would be reasonably expected at the time the contract was made

27 DSC System The applicability of the Spearin Doctrine in the USA United States v Spearin (1918), 248 U.S. 132 If the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications. (...) This responsibility of the owner is not overcome by the usual clauses requiring builders to visit the site, to check the plans, and to inform themselves of the requirements of the work.

28 DSC System Confront with UK case law Under English law, an owner who provides plans or specifications to a contractor does not warrant that the work described in the plans and specifications is capable of being performed at all, or that is capable of being performed in a particular manner Thorn v The Mayor and Commonalty of London (1876), LR 1 HL 120

29 DSC System Misrepresentation When erroneous information is provided to a tenderer, and the tenderer, in reliance upon it, enters into a building or engineering contract, there may be an actionable misrepresentation, sounding in damages Possible distinction between innocent misrepresentation (an erroneuous statment) and a fraudulentmisrepresentation

30

31

32 Ground s elements and related risk types Information Interpretation (subjective) Information (objective) Incorrect Incomplete

33 Ground s elements and related risk types Probability Foreseen Unforeseen Aparent Real

34 Specific issues in Brazil

35 Specific issues in Brazil Importance of the management of the contract The day-by-day in opposition to the pacta sunt servanda principle Possible change in the allocation of responsibility

36 Specific The theory issues in of Brazil unpredictability or rebus sic stantibus clause in the new Civil Code The absolute unpredictability concept Complete change in the conditions of the contract Extreme burdensome A clear benefit to the other party

37 Specific issues in Brazil Continuous obligation of the parties to mitigate the risks during the contract Simply allocation of risk does not prevent the application of good-faith rules

38 DBB / DESIGN-BID-BUILD

39 EPCM / ENGINEERING PROCUREMENT CONSTRUCTION MANAGEMENT

40 EC+P / EPC HÍBRIDO / SPLIT EPC

41 EPC / ENGINEERING PROCUREMENT CONSTRUCTION

42 EPC / ENGINEERING PROCUREMENT CONSTRUCTION

43 O QUE É UMA ALIANÇA? EPCM Contratado 1 Engineering DBB Engineering VALE Construction VALE Procurement EPCM Contratado 2 Procurement VALE Engineering Construction Alianza Procurement Contratado 1 Engineering Contratado Construction Engineering VALE Construction VALE Contratado Procurement Contratado 2 Procurement Split EPC Construction EPC

44 SOLUÇÃO DE CONFLITOS

45 Conclusion

46 Conclusions Ground Risks, in the form of unforeseen geological and/or geotechnical conditions, are a serious factor in cost and schedule control on all major civil engineering projects The amounts of money, involved in claims arising from these geotechnical problems, is enormous and needs to be taken very seriously by financing agencies and all players in the construction industry

47 Conclusions Inadequate site investigations rank as one of the major contributors to ground risk. More realistic allocations of time and money have to be made to these site investigation programs It is also important that geologists and geotechnical engineers make more efficient use of the resources allocated for site investigation

48 Contact information Júlio César Bueno LL.M (Cantab) Ph.D (USP) Pinheiro Neto Advogados Rua Hungria, São Paulo - SP Brazil Tel: +55 (11) Fax: +55 (11) juliobueno@pinheironeto.com.br

49

Project Owners, especially in the public sector, are. Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions

Project Owners, especially in the public sector, are. Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions Design-Build and Public-Private Partnerships: Risk Allocation of Subsurface Conditions By David J. Hatem, Esq. Project Owners, especially in the public sector, are exploring and utilizing alternative project

More information

How do FIDIC contracts work

How do FIDIC contracts work How do FIDIC contracts work Zoltán Záhonyi (MSc civil engineer, postgraduate in law) FIDIC Contracts Committee member FIDIC Accredited Trainer Z&Partners Consulting Engineers Ltd. Leading Partner, managing

More information

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, 2013 11:00 a.m. 12:00 p.m. Introduction

More information

The table below sets out the main features of the Yellow and Silver Books and highlight their key differences 1.

The table below sets out the main features of the Yellow and Silver Books and highlight their key differences 1. Page 1 sur 8 United Kingdom: Use And Misuse Of FIDIC Forms Of Contract In Central And Eastern Europe: The Worrying Trend Of Silver Book Provisions In Public Works Contracts 14 June 2012 Article by Frederick

More information

Geotechnical baseline reports

Geotechnical baseline reports Geotechnical baseline reports Darren Page OTB Engineering Ltd BONUS What is a GBR? A single source contract document containing measurable contractual descriptions of the geotechnical conditions to be

More information

New developments in best practice for plant and design-build contracts

New developments in best practice for plant and design-build contracts CAPEC Business Opportunities Seminar New developments in best practice for plant and design-build contracts CAPEC Business Opportunities Seminar Xining - September 2015 Peter Boswell Plant contracts huge,

More information

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 PATRIZIA PALMITESSA-SAVRIC BSc Arch Eng MArch Arch.BW RIBA MAAB FCIArb FAArb FBIArb Head Contracts & Dispute Resolution GINDER PALMITESSA PTY LTD T: +267

More information

Legal Issues Related to Design Build

Legal Issues Related to Design Build Legal Issues Related to Design Build Presented by Aaron O. Martin CLARK, MIZE & LINVILLE, CHARTERED 129 S. 8 th, St. Salina, KS 67401 Telephone: (785) 823 6325 Facsimile: (785) 823 1868 aomartin@cml law.com

More information

Use of FIDIC Red Book on International Road Projects

Use of FIDIC Red Book on International Road Projects Use of FIDIC Red Book on International Road Projects Ellis Baker Partner & Global Head, Construction & Engineering Email: ebaker@whitecase.com Phone: +44 (0) 207 532 1601 29 Sept 2015 Key features of the

More information

*Corresponding author:k Shobana

*Corresponding author:k Shobana Int. J. Struct. & Civil Engg. Res. 2014 Jayant Damodar Supe and M K Gupta, 2014 Research Paper MANAGING THE RISKS IN CONSTRUCTION PROJECT BY COMPARING MOSPI AND FIDIC K Shobana 1 *, D Pradeep Kumar 2 and

More information

Is It Time for Design-Build?

Is It Time for Design-Build? Is It Time for Design-Build? NASTT Pacific NW Chapter January 24, 2013 John Parnass Davis Wright Tremaine LLP Seattle, Washington Where Are We Now? Trenchless market still dominated in Washington by traditional

More information

PUBLIC-PRIVATE PARTNERSHIP

PUBLIC-PRIVATE PARTNERSHIP PUBLIC-PRIVATE PARTNERSHIP Law firm Sajic GP Banja Luka Bulevar vojvode Zivojina Misica 49B, Banja Luka Bosnia and Herzegovina Tel: +387 51 227 620 Fax: +387 51 227 623 e-mail: info@afsajic.com www.advokatskafirmasajic.com

More information

Procurement Department PROCUREMENT POLICY

Procurement Department PROCUREMENT POLICY Procurement Department PROCUREMENT POLICY Document Number: CR/QMS/PROC/POL/1101 Documentum Number: Document History: Revision: Date: Prepared by: Checked by: Authorised by: Reason for Issue: 8.0 15.04.10

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

PITFALLS & TIPS OF DEALING WITH SUBCONTRACT NOMINATION UNDER FIDIC & UAE CIVIL LAW

PITFALLS & TIPS OF DEALING WITH SUBCONTRACT NOMINATION UNDER FIDIC & UAE CIVIL LAW Technical Event Jointly Hosted by AACEI and Construction Management Guide PITFALLS & TIPS OF DEALING WITH SUBCONTRACT NOMINATION UNDER FIDIC & UAE CIVIL LAW 1 Speaker: Samer H. Skaik BEng, MSc (W/D), PMP,

More information

Course List 2008 Civil Engineering Commercial Training

Course List 2008 Civil Engineering Commercial Training Course List 2008 Civil Engineering Commercial Training From SURCO, the trading company of the Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Institution of CIVIL ENGINEERING SURVEYORS Dominion

More information

How Construction Contracts Cause Litigation. By: Robert C. Epstein, Esq. 1

How Construction Contracts Cause Litigation. By: Robert C. Epstein, Esq. 1 How Construction Contracts Cause Litigation By: Robert C. Epstein, Esq. 1 We live in a litigious society, and construction contributes its fair share of disputes. Conflicts, disputes and claims seem to

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It Jim Mallorey, P.E. Metro Wastewater Reclamation District Chris Harper - University of Colorado Boulder January 23, 2014 1

More information

1913 Lausanne, Switzerland

1913 Lausanne, Switzerland FIDIC What is FIDIC? An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the

More information

Fundamentals of Construction Contract & Contractual Risks: Design Risks

Fundamentals of Construction Contract & Contractual Risks: Design Risks Fundamentals of Construction Contract & Contractual Risks: Design Risks Categories of Contracts Design and Build Build Only NSC (Specialist) Design & Build Design & Build Duty to ensure that design meets

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS Pedro d Aça Castel-Branco ST Division Civil Engineering Group (ST/CE) CERN, Geneva, Switzerland Abstract The contracts for the civil

More information

The Changing Face of Quantity Surveying Practices in Construction Industry

The Changing Face of Quantity Surveying Practices in Construction Industry The Changing Face of Quantity Surveying Practices in Construction Industry YESHWANTH BABU REDDY School of Architecture and Building Deakin University Table of Contents: 1.1 Background... 2 1.2 Introduction...

More information

WEBINAR. The FIDIC 2017 Suite of Agreements. Presenter: Vincent Leloup FIDIC Contracts Committee. Exequatur, 2017

WEBINAR. The FIDIC 2017 Suite of Agreements. Presenter: Vincent Leloup FIDIC Contracts Committee. Exequatur, 2017 WEBINAR The FIDIC 2017 Suite of Agreements Presenter: Vincent Leloup FIDIC Contracts Committee Exequatur, 2017 PROGRAMME 1. FIDIC 2017 SUITE OF AGREEMENTS ROOTS & HISTORY 2. FIDIC 2017 WHITE BOOK MAIN

More information

Giorgiana Teccuci Aisha Nadar

Giorgiana Teccuci Aisha Nadar Giorgiana Teccuci Aisha Nadar Role of the Consulting Engineer in the Context of the New Yellow Book & its Dispute Board Provisions Agenda The FIDIC Contracts The Consulting Engineer and their role What

More information

Maintenance for Building Services

Maintenance for Building Services A BSRIA Guide www.bsria.co.uk Maintenance for Building Services How to acquire maintenance services contracts By Jo Harris BG 3/2008 BG 3-2008 (Maintenance contracts) cover 6.p653 06/06/2008, 09:26 ACKNOWLEDGEMENTS

More information

RUB-EIC Seminar. The EIC View on the FIDIC New Books. by Hakan Broman, NCC Interational St. Petersburg, Russia, 17 April 2008

RUB-EIC Seminar. The EIC View on the FIDIC New Books. by Hakan Broman, NCC Interational St. Petersburg, Russia, 17 April 2008 RUB-EIC Seminar The EIC View on the FIDIC New Books by Hakan Broman, NCC Interational St. Petersburg, Russia, Structure of the Presentation FDIC New Books 1999 EIC Contractor s Guide to the FIDIC Red/Yellow/Silver

More information

NTA Metropolitan Mass Transit System. To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project. Addendum No.

NTA Metropolitan Mass Transit System. To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project. Addendum No. Date: 12 th July 2017 #1069265 To: All Bidders Re: Tender 055/2017 for the Signaling and Train Control of the Red Line Project Addendum No. 5 Addendum no. 5 is issued for inclusion into the tender documents.

More information

Blue List. Green List. Civil Engineering Commercial Training Courses

Blue List. Green List. Civil Engineering Commercial Training Courses Blue List Green List Civil Engineering Commercial Training Courses From SURCO, the information business of the Chartered Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Chartered Institution of

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

Contract notice utilities

Contract notice utilities Business Opportunity Title: United Kingdom-Warrington: CHP Schemes servicing and repair and maintenance and provision of spares and consumables Document Type: Contract Notice Published By: United Utilities

More information

STUDY ON THE MANAGEMENT OF EPC PROJECTS

STUDY ON THE MANAGEMENT OF EPC PROJECTS International Journal of Civil, Structural, Environmental and Infrastructure Engineering Research and Development (IJCSEIERD) ISSN(P): 2249-6866; ISSN(E): 2249-7978 Vol. 5, Issue 3, Jun 2015, 11-22 TJPRC

More information

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order [Introductory Note to User: The following text as published describes

More information

Please read the Notes below before using the BIM Particular Conditions.

Please read the Notes below before using the BIM Particular Conditions. BIM Particular Conditions Version 1.0 The BIM Particular Conditions Version 1.0 on the following pages may be attached to the Principal Agreement when incorporating the use of BIM into the project, as

More information

BONUS PAYMENT TERMS AND CONDITIONS

BONUS PAYMENT TERMS AND CONDITIONS DEFINITIONS 1. Unless the contrary intention appears, in these terms and conditions the following words and phrases have the following meaning: 1.1 Account means the account provided by the Designated

More information

The Case For QUALIFICATIONS-BASED SELECTION

The Case For QUALIFICATIONS-BASED SELECTION AMERICAN COUNCIL OF ENGINEERING COMPANIES OF OKLAHOMA 201 N.E. 27TH STREET SUITE 135 OKLAHOMA CITY OK 73105-2740 405.525.7696 FAX 405.557.1820 E-MAIL: jsullins@acecok.org WEBSITE: www.acecok.org The Case

More information

The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents

The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents CCDC Standard Construction Documents CCDC 2-1994 Stipulated Price Contract Standard prime contract between

More information

Present Contract Courses on:

Present Contract Courses on: y International Federation of Consulting Engineers Uganda Association of Consulting Engineers Present Contract Courses on: The Practical Use of the 1999 FIDIC Conditions of Contract for Construction &

More information

SEFI. DB/DBO in emerging economies and LDCs: A practical answer to address the infrastructure challenge with improved governance

SEFI. DB/DBO in emerging economies and LDCs: A practical answer to address the infrastructure challenge with improved governance DB / DBO Workshop March 31st 2015 Paris SEFI DB/DBO in emerging economies and LDCs: A practical answer to address the infrastructure challenge with improved governance Marc Frilet Managing Partner «Frilet

More information

Turnkey contracting under the FIDIC Silver Book: What do owners want? What do they get? by Jonathan Hosie November 2007

Turnkey contracting under the FIDIC Silver Book: What do owners want? What do they get? by Jonathan Hosie November 2007 Turnkey contracting under the FIDIC Silver Book: What do owners want? What do they get? by Jonathan Hosie November 2007 Turnkey contracting under the FIDIC Silver Book: What do owners want? What do they

More information

What Every APPA Member Needs To Know About Construction Contracts

What Every APPA Member Needs To Know About Construction Contracts 2 What Every APPA Member Needs To Know About Construction Contracts June 18, 2018 Judah Lifschitz, Esq. Principal & Co-President Shapiro, Lifschitz & Schram P.C. lifschitz@slslaw.com (202) 689-1900 3 What

More information

The letter of expression of interest (EOI) should provide information of the company s technical qualifications and experience in the Annex B.

The letter of expression of interest (EOI) should provide information of the company s technical qualifications and experience in the Annex B. Request for Expression of Interest of Initial, Intermediate and Final Technical Review Support Missions/ Technical Audit for the Project of Gujarat Rural Roads Funding source: Sector: Asian Infrastructure

More information

Common Myths and Best Practices. By Gr e g o r y A. Ga r r e t t

Common Myths and Best Practices. By Gr e g o r y A. Ga r r e t t Common Myths and Best Practices By Gr e g o r y A. Ga r r e t t 16 Contract Management October 2009 Examining 10 common myths and several best practices of risk management can help you apply an effective

More information

FIDIC Workshops. Amman, Jordan January :00 am 05:00 pm. Engineers Training Center is a FIDIC Accredited Training Supplier

FIDIC Workshops. Amman, Jordan January :00 am 05:00 pm. Engineers Training Center is a FIDIC Accredited Training Supplier FIDIC Workshops Amman, Jordan 26-29 January 2014 09:00 am 05:00 pm Engineers Training Center is a FIDIC Accredited Training Supplier About these workshops These special two-day events have been designed

More information

DfE wishes to appoint Commissioners to deliver intervention and improvement support in the following LAs:

DfE wishes to appoint Commissioners to deliver intervention and improvement support in the following LAs: s ECSC Dynamic Purchasing System - Request for Quotation (RFQ) Supplier notice Please note that responses to this RFQ need to be made electronically through Redimo2 by completing evaluation sections and

More information

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts)

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts) Volume (5) Number (8) August 2015 J. Appl. Environ. Biol. Sci., 5(8)55-69, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Commencement

More information

International Experience with PPP Programs: Success, Failure and Key Lessons. 22 February 2012

International Experience with PPP Programs: Success, Failure and Key Lessons. 22 February 2012 International Experience with PPP Programs: Success, Failure and Key Lessons Delivering Public-Private Private Partnerships in PNG 22 February 2012 Why PPPs? Value for Money Synergies between design, construction,

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical experience in how to organize the contract administration

More information

Introduction to FIDIC Conditions of contract OUTLINE. What is FIDIC? Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor

Introduction to FIDIC Conditions of contract OUTLINE. What is FIDIC? Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor New tendency in contracts worldwide Introduction to FIDIC Conditions of contract Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor 1 2 OUTLINE 1. What is FIDIC? 2. Characteristics of FIDIC Conditions

More information

PROCUREMENT: TIPS AND PITFALLS. Jeremy Taitinger Sean Ward

PROCUREMENT: TIPS AND PITFALLS. Jeremy Taitinger Sean Ward PROCUREMENT: TIPS AND PITFALLS Jeremy Taitinger Sean Ward Procurement Procurement is an important process for municipalities to ensure they obtain competitive bids and proposals representing the best available

More information

PRESENTERS. Paul James. Senior Vice Vice President, Risk Risk Management & & General Counsel. Bond Brothers, Inc.

PRESENTERS. Paul James. Senior Vice Vice President, Risk Risk Management & & General Counsel. Bond Brothers, Inc. Senior Vice Vice President, Risk Risk Management & & General Counsel PRESENTERS Paul James Senior Vice President, Risk Management & General Counsel Bond Brothers, Inc. Kenneth Rubinstein Co-Chair of Construction

More information

The Role of FIDIC contracts in the construction industry

The Role of FIDIC contracts in the construction industry The Role of FIDIC contracts in the construction industry Kaj Möller (M. Sc. C. E., Exec. MBA) FIDIC Executive Committee member since 2011 Liaison with FIDIC Contracts Committee Head of Export @ Sweco Group

More information

COMMERCIAL MANAGEMENT. Construction Law Competencies

COMMERCIAL MANAGEMENT. Construction Law Competencies COMMERCIAL MANAGEMENT Construction Law Competencies To exhibit an understanding of contract and civil engineering construction law, to support and recommend appropriate strategies to other members of the

More information

Community Workshop October 17, 2015

Community Workshop October 17, 2015 Community Workshop October 17, 2015 Goals for Workshop Education for attendees How City builds projects now Why a different method is being pursued for WRF Other workshops (not today) Architecture Treatment

More information

BIM: Risks & Responsibilities: Can a BIM Protocol provide the solutions?

BIM: Risks & Responsibilities: Can a BIM Protocol provide the solutions? BIM: Risks & Responsibilities: Can a BIM Protocol provide the solutions? CIC/BIM Pro (2013) Overview Background: Personal / BIM BIM Protocol: Purpose / Scope USA Precedents Protocols: AIA: Document E202

More information

EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENTS

EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENTS EPC/TURNKEY CONTRACT, LUMPSUM FIXED PRICE SUBJECT TO ADJUSTMENTS Oleh : Sarwono Hardjomuljadi sarwonohm2@yahoo.co.id Civil Engineering Department,Faculty of Engineering, University of Mercu Buana Jakarta,

More information

Inquiry no 1/12/2017/3.2

Inquiry no 1/12/2017/3.2 Knurów, 04.12.2017y. Inquiry no 1/12/2017/3.2 Bud Expert Sp. z o.o. with address: Jęczmienna 4, Knurów, VAT No. 9691624534, invites to submit water cutting machine detailed description of the order the

More information

CHALLENGING SITES & HYDRO TUNNELLING CHOICE OF TECHNOLOGIES AND CONTRACT IMPLICATIONS

CHALLENGING SITES & HYDRO TUNNELLING CHOICE OF TECHNOLOGIES AND CONTRACT IMPLICATIONS CHALLENGING SITES & HYDRO TUNNELLING CHOICE OF TECHNOLOGIES AND CONTRACT IMPLICATIONS Harald Wagner, Consulting Engineer & ITA EXCO Expert, Bangkok/Vienna Key Words: Innovative Flexible Contracting, Standards

More information

NEC3 Contracts explained

NEC3 Contracts explained ICE London Graduates & Students NEC3 Contracts explained Monday 21 April 2008 Peter Higgins, pd Consult former Chairman of NEC Panel Purpose and development of NEC3 Contracts State of the Construction

More information

Public tendering and legal aspects of project business in Romania

Public tendering and legal aspects of project business in Romania Public tendering and legal aspects of project business in Romania Ligia Cecilia Popescu/Fabiola Meister Wolf Theiss Bucharest, Romania April 9, 2013 Public Procurement plays key role in new Government

More information

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016

Contracts and Risk. Building blocks for success. Miami, November 14 th, 2016 Contracts and Risk Building blocks for success Miami, November 14 th, 2016 Risk, what risk? Heathrow 100% Cost Overrun 6 month delay Channel Tunnel 80% cost overrun Hallandsas 300% Cost overrun 10+ years

More information

Contracting Methods and Risk Management

Contracting Methods and Risk Management Contracting Methods and Risk Management In Tunneling and Underground Construction Michael S Schultz Senior Vice President CDM Smith Boston, Massachusetts September 12, 2016 Topics What is a Contract and

More information

Present FIDIC Contract Courses on:

Present FIDIC Contract Courses on: y International Federation of Consulting Engineers Uganda Association of Consulting Engineers Present FIDIC Contract Courses on: The Practical Use of the 1999 FIDIC Conditions of Contract for Construction

More information

Meeting the Standard of Care in an Evolving Project Delivery Environment

Meeting the Standard of Care in an Evolving Project Delivery Environment Meeting the Standard of Care in an Evolving Project Delivery Environment Russell Jumper & Tim Fandrey Gray Reed & McGraw Texas Society of Professional Engineers Denton Chapter March 9, 2018 Gray Reed &

More information

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS Randall J. Essex, PE Executive Vice President Tunnels Practice Breakthroughs in Tunneling Short Course September 12-15, 2016 University of Colorado,

More information

Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group

Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group Stephane Giraud Director Dams & River Works FIDIC Accredited Trainer & Adjudicator Egis Group INTRODUCTION EMPLOYER S CORE PRINCIPLES OF PROCUREMENT Value for money / Economy Efficiency / Fit for purpose

More information

58 th UIA CONGRESS Florence / Italy October 29 November 2, 2014 LABOUR LAW COMMISSION OUTSOURCING, SUBCONTRACTING AND STAFF LEASING

58 th UIA CONGRESS Florence / Italy October 29 November 2, 2014 LABOUR LAW COMMISSION OUTSOURCING, SUBCONTRACTING AND STAFF LEASING 58 th UIA CONGRESS Florence / Italy October 29 November 2, 2014 LABOUR LAW COMMISSION Saturday, November 1, 2014 OUTSOURCING, SUBCONTRACTING AND STAFF LEASING OUTSOURCING IN PORTUGAL Acácio Pita Negrão

More information

New rules on public procurement have come into force on January 2018

New rules on public procurement have come into force on January 2018 May 2018 New rules on public procurement have come into force on January 2018 What changed for contracting authorities and economic players with the entry into force of the last review of the Portuguese

More information

DEPARTMENT OF PUBLIC WORKS ROAD OPERATIONS DIVISION REVIEW OF CONTRACT (A/B-118) ASPHALT RECYCLING, INC. APRIL 2000

DEPARTMENT OF PUBLIC WORKS ROAD OPERATIONS DIVISION REVIEW OF CONTRACT (A/B-118) ASPHALT RECYCLING, INC. APRIL 2000 DEPARTMENT OF PUBLIC WORKS ROAD OPERATIONS DIVISION REVIEW OF CONTRACT (A/B-118) ASPHALT RECYCLING, INC. APRIL 2000 Prepared by: April 24, 2000 The Honorable Carlton Henley Chairman The Board of County

More information

New York City Transit (NYCT) DATE: July 19, 2018 CONSTRUCTION/ARCHITECTURAL & ENGINEERING CONTRACT SOLICITATION NOTICE/PROJECT OVERVIEW MTA-NYCT IS NOW ADVERTISING FOR THE FOLLOWING: SSE #: 0000226381

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

Bangalore International Airport Limited REQUEST FOR QUOTATION (RFQ) FOR. SITC of Standalone Fire Alarm for exit doors at BIAL project office

Bangalore International Airport Limited REQUEST FOR QUOTATION (RFQ) FOR. SITC of Standalone Fire Alarm for exit doors at BIAL project office Bangalore International Airport Limited REQUEST FOR QUOTATION (RFQ) FOR SITC of Standalone Fire Alarm for exit doors at BIAL project office Bangalore International Airport Limited Kempegowda International

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

Building Terms & Construction Jargon Explained. CLPM Glossary of Terms

Building Terms & Construction Jargon Explained. CLPM Glossary of Terms Building Terms & Construction Jargon Explained Building terms and construction jargon can be bewildering! If you are busy carrying out research for your building project, you ve probably already been bombarded

More information

LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP

LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PMO-RALG ENHANCEMENT OF PROCUREMENT CAPACITY OF LOCAL GOVERNMENT AUTHORITIES PROJECT (EPC LGAP) LGA PROCUREMENT CAPACITY BUILDING STRATEGY FORMULATION WORKSHOP PROCUREMENT COMPLIANCE & PERFORMANCE AS PER

More information

CIVIL AND STRUCTURAL ENGINEERING SERVICES TENDER

CIVIL AND STRUCTURAL ENGINEERING SERVICES TENDER CIVIL AND STRUCTURAL ENGINEERING SERVICES TENDER 14 HYBRID OFFICE/INDUSTRIAL UNITS At Plots 11 & 12,Cornwall Business Park (West) For JAD Developments (Redruth) Ltd 1 Introduction 1.1 Project Information

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

Application of FIDIC CC for EU- Funded Projects in Bulgaria

Application of FIDIC CC for EU- Funded Projects in Bulgaria Application of FIDIC CC for EU- Funded Projects in Bulgaria Assen Antov Transport Engineer Advisor to the Minister of Regional Development and Public Works EFCA Annual Conference 2016, 02 04 June 2016,

More information

Sealed tenders are invited from experienced and reputed Bidders for the Development of Courseware for the CFP CM Certification.

Sealed tenders are invited from experienced and reputed Bidders for the Development of Courseware for the CFP CM Certification. TENDER NOTICE NO. 2013-14/MUM/01 DATED: 25 th June 2013 Tender for Development of Courseware for the CFP CM Certification Program Due date: 13 th July, 2013 up to 5.30 p.m. Sealed tenders are invited from

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

Managing the Bid Process

Managing the Bid Process Managing the Bid Process This document is concerned with the process suppliers of goods and services will typically go through when they are asked to submit a price for undertaking a piece of work. In

More information

Code of Conduct for Suppliers

Code of Conduct for Suppliers Code of Conduct for Suppliers This Code of Conduct has been developed in recognition of the importance of the ten principles of the UN Global Compact and is viewed as an important means of integrating

More information

International Federation of Consulting Engineers

International Federation of Consulting Engineers International Federation of Consulting Engineers Italo Goyzueta, Deputy Director, FIDIC Convention Engineering as Engine for Growth: Opportunities and Constraints Rome June 5, 2014 Procurement & Business

More information

LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA

LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA Article 1 This Law regulates the scope, principles, manner, and forms of public-private partnership, requirements for the establishment of a

More information

Agenda Part 1 (up to break)

Agenda Part 1 (up to break) Welcome to the Use of the NEC3 Engineering Construction Contract as a project management tool Presenter : Jon Broome leading edge projects consulting ltd jon@leadingedgeprojects.co.uk +44(0)7970 428 929

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER

BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER January 2012 This Primer was produced for the United States Agency for International Development (USAID). It was prepared

More information

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018 PLANNING CORE COMPETENCIES 2018 The competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific standard,

More information

Delays in Construction Projects: Causes and Mitigation

Delays in Construction Projects: Causes and Mitigation Delays in Construction Projects: Causes and Mitigation Aleksander Srdić, Ph.D. University of Ljubljana, Faculty of Civil and Geodetic Engineering, Slovenia aleksander.srdic@fgg.uni-lj.si Assoc. Prof. Jana

More information

Serbia: Belgrade Water Project - Project Implementation Unit Support for Tranche 1

Serbia: Belgrade Water Project - Project Implementation Unit Support for Tranche 1 Serbia: Belgrade Water Project - Project Implementation Unit Support for Tranche 1 Country: Serbia Business sector: Municipal and environmental infrastructure Project number: 44630 Funding source: Austrian

More information

SOUTH AFRICAN NATIONAL STANDARD

SOUTH AFRICAN NATIONAL STANDARD ISBN 978-0-626-27661-4 SOUTH AFRICAN NATIONAL STANDARD Construction and management requirements for works contracts Part 1: General engineering and construction works Published by SABS Standards Division

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Bidding Conditions Attachment C

Bidding Conditions Attachment C Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives

More information

Supply chain management theory, NQF level 6, Credits 10

Supply chain management theory, NQF level 6, Credits 10 SUPPLY CHAIN MANAGER Knowledge modules 132401-001-01-00 KM-01 Supply chain theory, NQF level 6, Credits 10 132401-001-01-00 KM-02 Supply chain service delivery operational planning, NQF level 6, Credits

More information