Cavity Barriers: Final Factual Report of the Experimental Programme

Size: px
Start display at page:

Download "Cavity Barriers: Final Factual Report of the Experimental Programme"

Transcription

1 Cavity Barriers: Final Factual Report of the Experimental Programme The authors of this report are employed by BRE. The work reported herein was carried out under a Contract placed by the ODPM. Any views expressed are not necessarily those of the ODPM.

2 Executive Summary This report brings together the data and findings from the experimental programme undertaken to support the review of the guidance, currently provided, in Approved Document B (AD(B)) on cavity barriers. The work was undertaken to provide data to support the current ongoing review of Approved Document B. The information presented in this report covers five discrete work packages which have been undertaken to address areas identified as requiring investigation. The topics identified were : 1. Three cavity barrier scenarios: Floor voids Plenum spaces Cavity closures 2. Data from the floor voids and plenum space programmes were used to develop an existing validated model based on the BRE Jasmine computational fluid dynamics model, for use with both floor voids and variations to plenum space designs. 3. Consideration of the standard test methods for assessing the fire resistance performance of the cavity barrier systems. These topics were addressed using experimental programmes designed to investigate the key issues and provide practical solutions. The key findings from this work were : Confirmation that cavity barriers, when appropriately designed and installed offer a means by which unseen smoke and fire spread may be mitigated. The issues of installation design and methods must be considered in the application and use of these systems. Modelling of these types of systems may offer potential options for expansion of current design solutions.

3 Contents Introduction 1 Project Summary 2 Floor voids Annex A 2 Plenum spaces Annex B 2 Cavity closures Annex C 2 Computer modelling - Annex D 2 Fire Resistance testing Annex E 3 General Discussions and Recommendations 4 Annex A Floor Voids 5 General 5 Experimental 5 Phase One: Commercial Floor system. 5 Phase Two: Timber Floor 5 Phase Three: Ignition Scenario 6 Experimental Setup - Floor Voids 6 Instrumentation 6 Ignition Source 6 Smoke measurement 7 Cavity Barrier 7 Scenarios 7 Discussion and Recommendations 8 Heating by Exposure to a radiant heat source 31 Instrumentation 31 Results 33 Conclusion 33 Annex B Plenum Spaces 34 Introduction 34 Test Facility 34 Extract system 35 Suspended ceiling 35 Cable support 35 Gas analysis and measurements 35 Gas velocity 35 Gas analysis 36 Ladder assembly loading and withdrawal 36 Experimental 36 Thermocouples 36

4 Room thermocouples 37 Ceiling Void thermocouples 37 Cable thermocouples 37 Cable loading 37 Cavity barrier installation 38 Fire stopping description 38 Data logging 38 Photographic and video recording 38 Gas Burner 39 Results 39 Test 1 - Control test with no cavity barrier installed. 39 Test 2 - Test with cavity barrier installed - no fire stopping. 40 Test 3 Test with cavity barrier and fire stopping installed. 41 Discussion 42 Recommendation 42 Photographs 55 Annex C Cavity Closures 62 Experimental 62 Room enclosure 62 Fuel Load 63 Instrumentation 64 Results 65 Discussion and Recommendations 65 Graphs 66 Photographs 70 Annex D CFD modelling of Cavity Barrier Scenarios 77 Introduction 77 Mathematical Description of the CFD Modelling 77 Combustion modelling 78 Radiation modelling 78 Turbulence modelling 78 Modelling flame spread 78 Modelling temperature dependent material properties 79 Floor cavity barrier 80 Floor Test 3 80 Floor Test 4 81 Plenum space (ceiling void) scenario 88 Experimental Details 88 Details of computer modelling of the fire tests 89 Modelling the Geometry, Cavity Barrier and Extraction System 89 Thermal Properties of the materials 90 Flame spread modelling of the PVC communication cable 90 Numerical details 92 Results and discussion 92 References Annex D 93

5 Annex E - Fire Resistance Test 98 General 98 Barriers 98 Test Frame 98 Instrumentation 98 Table E1 Visual observations from Test Table E2 Visual observations from Test Table E3 Visual observations from Test Table E4 Visual observations from Test Table E5. Summary of Performance based on failure criteria set in BS 476: Part Discussion and Recommendations 103 Temperature time curves for Tests 1 to Test Test Test Test Photographs. 112 Test Test Test Test 4 117

6 Introduction This report brings together the data and findings from the experimental programme undertaken to support the review of the guidance, currently provided, in Approved Document B (AD(B)) on cavity barriers. The specific objectives of the experimental programme were identified as a result of a review exercise to establish the background and development of the current guidance. The findings from this study suggested that there appeared to be only a limited amount of directly relevant data in this area and therefore additional supporting experimental work would be required. The key topic areas identified several areas for further investigation into the potential for unseen smoke and fire spread through voids and cavities, based on experience gained from users of the current guidance and changes in building construction methods. The topics identified were : 1. Three cavity barrier scenarios: Floor voids Plenum spaces Cavity closures 2. Data from the floor voids and plenum space programmes were used to develop an existing validated model based on the BRE Jasmine computational fluid dynamics model, for use with both floor voids and variations to plenum space designs. 3. Consideration of the standard test methods for assessing the fire resistance performance of the cavity barrier systems. 1

7 Project Summary As these topics were completed as discrete work packages, this report has been prepared as a summary document with detailed Annexes addressing each of the work areas as follows: Floor voids Annex A In order to investigate the potential for unseen fire spread to occur through the voids in suspended floor systems, a series of experiments have been undertaken utilising a commercially designed and installed suspended floor system. Work has also been undertaken to look at potential fire risks from standard timber floor systems and also potential transmission routes for fire spread from radiated heat from the room of fire origin into the floor void. The work was completed in three phases which are presented in Annex A. The results from this work confirmed that cavity barriers, when effectively designed and installed appeared to offer a suitable means of mitigating potential fire and smoke spread through unseen floor voids. Plenum spaces Annex B Considerable work has been undertaken in characterising fire travel through plenum spaces via cables and this work was undertaken to investigate the effect of cavity stopping at preventing fire spread through void spaces. Three scenarios were considered and the results are presented and discussed in Annex B. Again one of the key findings from this work was to confirm that whilst combustible materials passing through voids may offer a potential fire transmission route, appropriately designed and installed cavity barriers can provide a means a mitigate any fire and smoke spread risk. Cavity closures Annex C The objective of this study was to investigate the effectiveness of different types of window frame constructions at mitigating the entry of fire into a timber frame cavity. The experimental scenario selected for this study was based upon a post flashover fire within an enclosure, breaking out through a window opening which is set within a timber frame cavity wall construction. Four systems were investigated and the findings are discussed in detail in Annex C. These findings suggest that, as has been seen as a common theme throughout this work, that the interface detail between the cavity closure and the primary substrate is as critical to the overall performance of the system as the ability of the material involved to withstand the imposed fire load. Computer modelling - Annex D BRE work on fire modelling research and development has culminated in the development of its own computational fluid dynamics (CFD) fire models JASMINE and SOFIE. These models have been used to complement the experimental programmes, for assessing the performance of cavity barriers installed in floor voids and plenum 2

8 spaces. The findings are discussed in detail in Annex D where the main conclusions showed that the models may provide a reasonable basis for assessing the overall fire performance of potential design solutions using these types of scenarios. Fire Resistance testing Annex E In order to assist in the development of an appropriate fire resistance test for assessing the performance of cavity barrier systems, four typical cavity closure systems were subjected to an adhoc fire resistance scenario based upon a standard fire performance temperature-time curve using a 1.5m adhoc test furnace. The scenario adopted was designed to consider the influence of installation details on the performance of the systems when tested to the adhoc scenario and to therefore provide a practical approach to assessing these types of systems, whilst recognising the need for a standardised test method. The results from this work again raised issues regarding performance in service in relation to the ease of installation and hence associated workmanship related to the end use of the system. 3

9 General Discussions and Recommendations The primary findings from this work are: Confirmation that the cavity barriers can provide an effective means to mitigate smoke and fire spread if they are designed to meet the service requirements expected in practice. This must include provision for jointing details, as shown in the adhoc fire resistance tests. The interface between the barrier and the primary structures must also be addressed, as illustrated by the failure mode of the timber window frames in the cavity closure tests. The key factor in the performance of the systems appears to be the ability to install and repair the systems simply, this can be affected by a number of issues, which lie outside the scope of this study. However, this issue must be considered in the context of the performance requirements placed upon these products when in service. This includes addressing the control of openings and services passing through any barrier, as shown by the plenum tests, Annex B. The findings from the plenum tests suggest that appropriately installed cavity barriers may provide a useful means of controlling potential unseen smoke and fire spread through voids and cavities in scenarios such as floors where combustible services may be present, without the redress to significant controls on the materials passing through the voids. The results of the window closure work suggest that where excessive movement or consumption of the frame material during the fire allow flames spread into the timber cavity, the use of the robust design details for timber frame systems appears to offer a potential mitigating option. The work also showed that whilst the frame work may not be consumed or displaced in the fire, if the fixing to or robustness of the primary structure is not adequate, breach of the cavity can still occur and in such cases, the robust design detail still provides an additional mitigating effect. The modelling work has been shown to be a potentially useful tool for assessing the performance of these systems in practice. 4

Annex C Cavity Closures

Annex C Cavity Closures Annex C Cavity Closures Introduction The objective of this study was to investigate the effectiveness of different types of window frame constructions at mitigating the entry of fire into a timber frame

More information

Fire Engineering, the BCA (NCC) & Bushfire Calculator. Keith Nicholls - Manager Product Testing and Assessments (Australia) Exova Group Limited

Fire Engineering, the BCA (NCC) & Bushfire Calculator. Keith Nicholls - Manager Product Testing and Assessments (Australia) Exova Group Limited Fire Engineering, the BCA (NCC) & Bushfire Calculator Keith Nicholls - Manager Product Testing and Assessments (Australia) Exova Group Limited Presentation Topics Current Building Code (fire safety) design

More information

european fire standards and national legislation

european fire standards and national legislation 1 european fire standards and national legislation An Introduction Current testing and standards In the past, manufacturers, designers and specifiers in the Internal Market had to cope with a lack of meaningful

More information

EUROPEAN ORGANISATION FOR TECHNICAL APPROVALS

EUROPEAN ORGANISATION FOR TECHNICAL APPROVALS E TA TECHNICAL REPORT Fire Resistance Tests for Cavity Barriers TR 31 Edition October 2008 EUROPEAN ORGANISATION FOR TECHNICAL APPROVALS EOTA TECHNICAL REPORT TR 031 Fire Resistance Tests for Cavity Barriers

More information

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II

Fire Inspection and Code Enforcement, 7 th Edition. Chapter 6 Building Construction: Components Inspector II Fire Inspection and Code Enforcement, 7 th Edition Chapter 6 Building Construction: Components Today we will Discuss fire walls, party walls, fire partitions, and curtain walls Discuss roof types and coverings

More information

INTERIOR FINISHES CHAPTER 8

INTERIOR FINISHES CHAPTER 8 CHAPTER 8 INTERIOR FINISHES SECTION 801 GENERAL 801.1 Scope. Provisions of this chapter shall govern the use of materials used as interior finishes, trim and decorative materials. 801.1.1 Interior finishes.

More information

MP-400. The most thermally efficient, robust and reliable medical incinerators on the market. Simply Built Better!

MP-400. The most thermally efficient, robust and reliable medical incinerators on the market. Simply Built Better! The most thermally efficient, robust and reliable medical incinerators on the market Simply Built Better! Specifically designed for medical waste. MP-400 The MP medical hot hearth Incinerators designed

More information

The Integrity of Compartmentation in Buildings During a Fire

The Integrity of Compartmentation in Buildings During a Fire The Integrity of Compartmentation in Buildings During a Fire The authors of this report are employed by BRE. The work reported herein was carried out under a Contract placed by the ODPM. Any views expressed

More information

REFLECTIVE TECHNOLOGY CONSTRUCTION MEMBRANES

REFLECTIVE TECHNOLOGY CONSTRUCTION MEMBRANES CI/SfB (47) Ln6 Uniclass Pr_25_57_10_68 January 2018 REFLECTIVE TECHNOLOGY CONSTRUCTION MEMBRANES................................ ........................................................ REFLECTIVE TECHNOLOGY

More information

Load testing of a PVC coated handrail system. 25 th March Test report number

Load testing of a PVC coated handrail system. 25 th March Test report number Load testing of a PVC coated handrail system 25 th March 2010 Tested on behalf of BRE by Names Julian Pettifer and Felix Ahatty Position Senior Technician and Junior Engineer, Actions, Building Technology

More information

Design guide to separating distances during construction, Part 4

Design guide to separating distances during construction, Part 4 TRUCTURAL TIMBER ASSOCIATION Building solutions in timber Design guide to separating distances during construction, Part 4 For CLT type frame buildings Version. - November 204 Thanks to KLH and Binderholz

More information

MP-300. The most thermally efficient, robust and reliable medical incinerators on the market. Simply Built Better!

MP-300. The most thermally efficient, robust and reliable medical incinerators on the market. Simply Built Better! The most thermally efficient, robust and reliable medical incinerators on the market Simply Built Better! Specifically designed for medical waste. MP-300 The MP medical hot hearth Incinerators The Addfield

More information

Evaluation Report. for. Empire West, Inc Graton Road Post Office Box 511 Graton, California 95444

Evaluation Report. for. Empire West, Inc Graton Road Post Office Box 511 Graton, California 95444 for Empire West, Inc. 9270 Graton Road Post Office Box 511 Graton, California 95444 CertMark International Pty Ltd (CMI) has awarded this Certification to the company named above for the Product/system

More information

Computer Models For Fire and Smoke

Computer Models For Fire and Smoke Computer Models For Fire and Smoke Model Name: KAMELEON FIREEX KFX Version: KAMELEON FIREEX KFX 2010 Date: August 6 th, 2013 Classification: Very Short Description: Field model KAMELEON FIREEX KFX is an

More information

Predicted Heat Strain (PHS)

Predicted Heat Strain (PHS) Predicted Heat Strain (PHS) User Guide Version 1: August 2016 Page 1 of 16 Contents page 1 OVERVIEW... 3 1.1 Purpose... 3 1.2 Scope... 3 2 BACKGROUND... 3 2.1 Predicted heat strain... 3 2.2 Ranges of Validity...

More information

BRE Global Test Report

BRE Global Test Report BRE Global Test Report Classification of fire performance in accordance with BR 135: 2013 Annex B. Prepared for: Date: 02 July 2014 Report Number: 287129 Iso Systems and Aquarian Cladding Systems BRE Global

More information

The extra strong, extra durable, sound resistant system that you can direct fix to

The extra strong, extra durable, sound resistant system that you can direct fix to C0 Partitions The extra strong, extra durable, sound resistant system that you can direct fix to All our systems are covered by SpecSure when using genuine Gyproc and Isover products gyproc.ie Utilising

More information

ASTATT1 Prepare to carry out air tightness testing

ASTATT1 Prepare to carry out air tightness testing ASTATT1 Prepare to carry out air tightness testing Overview This standard is for those who carry out air tightness and/or air change rate testing of buildings of any size or complexity. It covers those

More information

INTERIOR FINISHES CHAPTER 8

INTERIOR FINISHES CHAPTER 8 CHAPTER 8 INTERIOR FINISHES SECTION 801 GENERAL 801.1 Scope. Provisions of this chapter shall govern the use of materials used as interior finishes, trim and decorative materials. 801.2 Interior wall and

More information

to a medium range machine. Our Mini Plus machine is capable of a burn rate of up to 50kg per hour cleanly We also manufacture high capacity burn rate

to a medium range machine. Our Mini Plus machine is capable of a burn rate of up to 50kg per hour cleanly We also manufacture high capacity burn rate The most thermally efficient, robust and reliable animal incinerators on the market Simply Built Better! MINI+ Our Mini+ incinerator features a robust 10mm steel periphery, along with a top loading design.

More information

INTERIOR FINISHES CHAPTER 8

INTERIOR FINISHES CHAPTER 8 CHAPTER 8 INTERIOR FINISHES SECTION 801 GENERAL 801.1 Scope. Provisions of this chapter shall govern the use of materials used as interior finishes, trim and decorative materials. 801.2 Interior wall and

More information

Definition of Wall. A continuous, vertical structure Thin relatively to its length and height

Definition of Wall. A continuous, vertical structure Thin relatively to its length and height Walls & Partition Learning Objectives Briefly explain the functions & functional requirements of walls Differentiate and compare between load bearing and non-load bearing walls Briefly describe the characteristics,

More information

PASSIVE FIRE PROTECTION Specialists for the construction, infrastructure, transport, energy, industrial and commercial sectors.

PASSIVE FIRE PROTECTION Specialists for the construction, infrastructure, transport, energy, industrial and commercial sectors. Uniclass L68111:P91 Ry November 2017 Epic F811 Passive Fire Protection Solutions Alternative product choices in the critical areas of fire protection and fire stopping to provide protection to life and

More information

Application of a Generalised Engineering Methodology for Thermal Analysis of Structural Members in Fire

Application of a Generalised Engineering Methodology for Thermal Analysis of Structural Members in Fire Application of a Generalised Engineering Methodology for Thermal Analysis of Structural Members in Fire Liang, H., Welch, S. 1 School of Engineering and Electronics, University of Edinburgh, EH9 3JL, Edinburgh,

More information

Loss Prevention Standard

Loss Prevention Standard Loss Prevention Standard LPS 1208: Issue 2.2 This Loss Prevention Standard is the property of BRE Global Ltd. and is made publicly available for information purposes only. Its use for testing, assessment,

More information

6/16/2016. A FORENSIC EXAMINATION OF TALL BUILDING FACADE FIRES l Building Envelope Fires in Dubai Skyscrapers. Martin Edwards. The Address (Atkins)

6/16/2016. A FORENSIC EXAMINATION OF TALL BUILDING FACADE FIRES l Building Envelope Fires in Dubai Skyscrapers. Martin Edwards. The Address (Atkins) A FORENSIC EXAMINATION OF TALL BUILDING FACADE FIRES l Building Envelope Fires in Dubai Skyscrapers Martin Edwards The Address (Atkins) 2016 - Probyn Miers 2010 Ltd ProbhynMiers Ltd 1 The Address Downtown

More information

BRE Global Ltd Watford, Herts WD25 9XX. d+b facades (UK) Ltd. The Packway, Larkhill, Salisbury, SP4 8PY. Customer Services

BRE Global Ltd Watford, Herts WD25 9XX. d+b facades (UK) Ltd. The Packway, Larkhill, Salisbury, SP4 8PY. Customer Services BRE Global Test Report BS 8414-1:2015 + A1:2017 test on d+b facades rain screen cladding system with 100mm-thick Rockwool insulation and aluminium cassette panels. Prepared for: d+b facades (UK) Ltd. Date:

More information

nderfloor heating Order a complete wet underfloor system instantly, up to 112m 2, using one single code.

nderfloor heating  Order a complete wet underfloor system instantly, up to 112m 2, using one single code. nderfloor heating Order a complete wet underfloor system instantly, up to 112m 2, using one single code. The simple route to a professional solution. www.one-pack.co.uk Uponor Housing Solutions work to

More information

RAINSCREEN DUO SLAB. Non-combustible thermal insulation

RAINSCREEN DUO SLAB. Non-combustible thermal insulation RAINSCREEN DUO SLAB Non-combustible thermal insulation RAINSCREEN DUO SLAB Effective, non-combustible thermal insulation for ventilated rainscreen and overcladding applications RAINSCREEN DUO SLAB is a

More information

Eclipse Energy Guard. Product Information & Installation Manual General Installation Requirements

Eclipse Energy Guard. Product Information & Installation Manual General Installation Requirements Product Information & Installation Manual 01 Important Notice to Buyers and Users of RoyOMartin wall system These instructions are not intended to cover every installation requirement, application, detail

More information

GypLyner UNIVERSAL Metal framed wall lining system

GypLyner UNIVERSAL Metal framed wall lining system Metal framed wall lining system Pizza Express, York 30 Metal framed wall lining system wall lining system is a cost-effective, virtually independent metal frame drylining. It is a general purpose system

More information

Floors Walls Roofs. Jablite Premium board Jablite board. APPLICATION: Internally Lined Pitched Roof PRODUCTS: Vencel Resil Limited

Floors Walls Roofs. Jablite Premium board Jablite board. APPLICATION: Internally Lined Pitched Roof PRODUCTS: Vencel Resil Limited Floors Walls Roofs APPLICATION: Internally Lined Pitched Roof PRODUCTS: Jablite Premium board Jablite board Vencel Resil Limited Head Office: Infinity House, Anderson Way, Belvedere, Kent DA17 6BG Tel:

More information

Underfloor Heating System

Underfloor Heating System More than just an Underfloor Heating System including More than just an Underfloor Heating System underfloor heating + acoustic flooring + integrated control technology Performance Technology Integrated

More information

Building Design Data

Building Design Data Building Design Data.. 1. Building Design The KORE ICF System is designed to meet the requirements of the Building Regulations 1997-2006, in the case of two storeys, single occupancy dwellings. If the

More information

Thermal Performance of Plasterboard Lined Steel Stud Walls

Thermal Performance of Plasterboard Lined Steel Stud Walls Missouri University of Science and Technology Scholars' Mine International Specialty Conference on Cold- Formed Steel Structures (28) - 19th International Specialty Conference on Cold-Formed Steel Structures

More information

Dow Building Solutions. Insulating floors with STYROFOAM Solutions: basic principles

Dow Building Solutions. Insulating floors with STYROFOAM Solutions: basic principles Dow Building Solutions Insulating floors with STYROFOAM Solutions: basic principles Introduction STYROFOAM -A Dow Building Solutions STYROFOAM -A products include FLOORMATE -A materials for flooring applications.

More information

Changes to California s Building Code for Construction in Wildfire Prone Areas: Impact on Wood and Wood-based Materials

Changes to California s Building Code for Construction in Wildfire Prone Areas: Impact on Wood and Wood-based Materials Changes to California s Building Code for Construction in Wildfire Prone Areas: Impact on Wood and Wood-based Materials Stephen L. Quarles, Ph.D. University of California Cooperative Extension Richmond,

More information

TYVEK CONSTRUCTION MEMBRANES DUPONT AIRGUARD REFLECTIVE

TYVEK CONSTRUCTION MEMBRANES DUPONT AIRGUARD REFLECTIVE DuPont de Nemours (Luxembourg) S.à r.l. Rue General Patton L-2984 Luxembourg Tel: 01275 337660 Fax: 01275 879773 e-mail: tyvek.construction@lux.dupont.com website: www.tyvekhome.com APPROVAL INSPECTION

More information

COMPUTATIONAL FLUID DYNAMIC COMBUSTION MODELLING OF A BAGASSE BOILER

COMPUTATIONAL FLUID DYNAMIC COMBUSTION MODELLING OF A BAGASSE BOILER REFEREED PAPER COMPUTATIONAL FLUID DYNAMIC COMBUSTION MODELLING OF A BAGASSE BOILER DU TOIT P AND VAN DER MERWE SW John Thompson, Sacks Circle, Bellville South, 7530, South Africa philipd@johnthompson.co.za

More information

TRIDENT SEC 04 SECTION SAFETY AND SECURITY FILMS

TRIDENT SEC 04 SECTION SAFETY AND SECURITY FILMS TRIDENT SEC 04 SECTION 08 87 23 SAFETY AND SECURITY FILMS PART 1 GENERAL 1.1 SUMMARY A. Optically clear, anti-fragmentation protective polymeric film for glass hazard mitigation. 1.2 RELATED SECTIONS A.

More information

ISOPA. Prüfungsanstalt (MFPA), Leipzig, on a polyurethane. rigid foam insulated roof construction.

ISOPA. Prüfungsanstalt (MFPA), Leipzig, on a polyurethane. rigid foam insulated roof construction. F I R E P E R F O R M A N C E O F P O L Y U R E T H A N E S T E E L D E C K R O O F I N G F I R E P E R F O R M A N C E O F P O L Y U R E T H A N E S T E E L D E C K R O O F I N G has funded a series of

More information

Architecture Building, Delft University of Technology: Data Collection and Preliminary Analyses

Architecture Building, Delft University of Technology: Data Collection and Preliminary Analyses Fire and Collapse, Faculty of Architecture Building, Delft University of Technology: Data Collection and Preliminary Analyses Brian J. Meacham, PhD, PE, FSFPE Associate Professor Worcester Polytechnic

More information

UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS

UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS Mandatory Fire Safety Instruction UCL ESTATES & FIRE STANDARD - GENERAL PERFORMANCE FOR SITE HOARDING AND CONTRACTOR CABINS UCL general hoardings details - what you need to know: Prohibited Note Prior

More information

Report on First Revision June 2014 NFPA 5000

Report on First Revision June 2014 NFPA 5000 5000 FR520 BLD-FUR (10.1 and 10.2) 10.1* General. 10.1.1 Application. Interior finish for buildings shall comply with this chapter. 10.1.2 Automatic Sprinkler Systems. Where another provision of this chapter

More information

Material and Structural Response through Fire Experiments A Way Forward

Material and Structural Response through Fire Experiments A Way Forward Material and Structural Response through Fire Experiments A Way Forward Venkatesh Kodur Michigan State University 1 Outline Background Fire Resistance Assessment Elemental / System Tests Test Methods Drawbacks

More information

Floors Walls Roofs. Jablite Premium board Jablite board. APPLICATION: Internal Wall PRODUCTS: Vencel Resil Limited

Floors Walls Roofs. Jablite Premium board Jablite board. APPLICATION: Internal Wall PRODUCTS: Vencel Resil Limited Floors Walls Roofs APPLICATION: Internal Wall PRODUCTS: Jablite Premium board Jablite board Vencel Resil Limited Head Office: Infinity House, Anderson Way, Belvedere, Kent DA17 6BG Tel: 020 8320 9100 Fax:

More information

Reflective Insulation Specification & Application Guide for Post Frame and Metal Building Construction

Reflective Insulation Specification & Application Guide for Post Frame and Metal Building Construction Reflective Insulation Specification & Application Guide for Post Frame and Metal Building Construction WHAT IS PLY-FOIL? Ply-Foil is a multilayer, reflective insulation which comes in rolls consisting

More information

ICFs. Insulating Concrete Forms. Shorten Construction Schedule Enhance Comfort and Safety Reduce Energy Costs

ICFs. Insulating Concrete Forms. Shorten Construction Schedule Enhance Comfort and Safety Reduce Energy Costs ICFs Shorten Construction Schedule Enhance Comfort and Safety Reduce Energy Costs Build An Environmentally Friendly Home Add up residential heating and cooling, lighting, appliances and other electronic

More information

BRE Global Assessment Report

BRE Global Assessment Report BRE Global Assessment Report An assessment of the fire performance of the Gebrik Insulating Brick Cladding System against BR 135, Third Edition Prepared for: Date: 13 April 2016 Aquarian Cladding Systems

More information

A Comparative Analysis of the Use of Different External Fire Spread Calculation Methods

A Comparative Analysis of the Use of Different External Fire Spread Calculation Methods A Comparative Analysis of the Use of Different External Fire Spread Calculation Methods (1) Declan Thomson, (2) Paul Currie, and (2) Jianqiang Mai (1) Hoare Lea and Partners (6 th Floor Royal Exchange,

More information

Fire safety issues with balconies

Fire safety issues with balconies Fire safety issues with balconies By Ciara Holland, Martin Shipp and David Crowder of BRE Global Introduction BRE Global carries out fire investigation activities on behalf of the Department for Communities

More information

HPW Protocol Reference Manual

HPW Protocol Reference Manual 1 HPW Protocol Reference Manual Change Log: UPDATED BY DATE UPDATED VERSION UPDATE DETAILS 2 Table of Contents: HIGH PERFORMANCE WALL ASSEMBLY... 4 THERMAL SPECIFICATION... 4 REQUIREMENTS FOR HPW INSULATION...

More information

1 Product. 2 Scope of Use. IGNIS PERFORMANCE SOLUTION No I01R01. Ritek XL Thermal Wall System

1 Product. 2 Scope of Use. IGNIS PERFORMANCE SOLUTION No I01R01. Ritek XL Thermal Wall System IGNIS PERFORMANCE SOLUTION Evaluation No.4214 [2016] 1 Product Ignis Solutions has been engaged by Ritek Building Solutions to evaluate compliance of their Ritek XL Thermal Wall System against the Building

More information

RMF Intercell. NBS Specification 2013 K41

RMF Intercell. NBS Specification 2013 K41 RMF Intercell NBS Specification 2013 K41 InterfaceFLOR BV. K41 Specification 40mm, 60mm, 80mm, 90mm and 110mm K41 Raised access floors To be read with Preliminaries/ General conditions. TYPES OF RAISED

More information

v2. 13/06/2016 Technical Solutions Applications of Extreme Heat in FIREPLACES

v2. 13/06/2016 Technical Solutions Applications of Extreme Heat in FIREPLACES v2. 13/06/2016 Technical Solutions Applications of Extreme Heat in FIREPLACES INDEX 1. Basic concepts about extreme heat 2. Fireplace tipologies 2.1. Classification according to the form in which heat

More information

REPORT NUMBER: SAT-004A ORIGINAL ISSUE DATE: April 13, 2017 REVISED DATE:

REPORT NUMBER: SAT-004A ORIGINAL ISSUE DATE: April 13, 2017 REVISED DATE: Page 1 of 9 REPORT NUMBER: 102951522SAT-004A ORIGINAL ISSUE DATE: April 13, 2017 REVISED DATE: EVALUATION CENTER Intertek Testing Services NA Inc. 16015 Shady Falls Road Elmendorf, TX 78112 TEST REPORT

More information

Honeywell UOP Callidus Solutions

Honeywell UOP Callidus Solutions Alex Norris Sales Manager, EMEA Callidus Technologies May 15, 2017 May 17, 2017 Honeywell UOP Callidus Solutions Efficient and Clean Combustion 2017 Honeywell Oil & Gas Technologies Symposium Cairo, Egypt

More information

Local Temperature Measurements on Full-Size Systems in the Laboratory: Insight into the Extent of Thermal Bridges in Building Envelope Components

Local Temperature Measurements on Full-Size Systems in the Laboratory: Insight into the Extent of Thermal Bridges in Building Envelope Components Local Temperature Measurements on Full-Size Systems in the Laboratory: Insight into the Extent of Thermal Bridges in Building Envelope Components Thomas W. Petrie, Jan Ko ny, Jerald A. Atchley and André

More information

John Thompson Boilers and latest developments

John Thompson Boilers and latest developments John Thompson Boilers and latest developments Etienne de Villiers 19 September 2013 Alstom John Thompson Packaged fir Packaged Firetube Boilers Firetube Boilers Produce saturated steam for process Capacities:

More information

GypLyner. GypLyner. Metal framed wall lining system. All our systems are covered by SpecSure when using genuine Gyproc and Isover products.

GypLyner. GypLyner. Metal framed wall lining system. All our systems are covered by SpecSure when using genuine Gyproc and Isover products. GypLyner GypLyner Metal framed wall lining system All our systems are covered by SpecSure when using genuine Gyproc and Isover products Linings GypLyner GypLyner is a cost-effective, virtually independent

More information

First Revision No NFPA [ Section No ]

First Revision No NFPA [ Section No ] First Revision No. 1001-NFPA 5000-2015 [ Section No. 7.2.5.6.8 ] Global FR-6108 7.2.5.6.8 Exterior Nonbearing Walls. Exterior nonbearing walls tested shall be permitted when tested in accordance with,

More information

Environmental Testing of an Advanced Flare Tip for a Low-Profile Flare Burning Ethylene

Environmental Testing of an Advanced Flare Tip for a Low-Profile Flare Burning Ethylene American-Japanese Flame Research Committee Joint International Symposium Advances in CombustionTechnology: Improving the Environment and Energy Efficiency Marriott Waikoloa, Hawaii October 22-24, 2007

More information

PROMATECT -S Smoke & Fire Barrier

PROMATECT -S Smoke & Fire Barrier PROMATECT -S Smoke & Fire Barrier Introduction The purpose of a cavity barrier is to prevent the spread of smoke and flame from penetrating and/or moving within a concealed space in a fire compartment.

More information

URSA MINERAL WOOL URSA Acoustic Roll

URSA MINERAL WOOL URSA Acoustic Roll - 073_Layout 1 02/10/2017 10:19 Page 1 URSA UK LTD Crest House 102-104 Church Road Teddington, Middlesex TW11 8PY United Kingdom Tel : 020 8977 96 97 Fax : 020 8977 94 56 Web : www.ursa-uk.co.uk E-mail

More information

PERFORMANCE BASED EVALUATION OF FIRE SCENARIOS USING FLUENT

PERFORMANCE BASED EVALUATION OF FIRE SCENARIOS USING FLUENT PERFORMANCE BASED EVALUATION OF FIRE SCENARIOS USING FLUENT Shyam Dayanandan, Dan Chong Computational Engineering Solutions LLP E-mail: shyam@ce-sol.com Website: www.ce-sol.com ABSTRACT The Fire and Engineering

More information

BRE Global Test Report

BRE Global Test Report BRE Global Test Report BS 6853: 1999 Incorporating Amendment No. 1 tests to specific requirements of Table 5 on Controltac 180 on 3mm Aluminium coated with EP300/Hydro Topcoat (Axalta, dft 100µm) Prepared

More information

Thermablok Aerogel Insulation Blanket Thermablok Aerogel Blanket

Thermablok Aerogel Insulation Blanket Thermablok Aerogel Blanket Uniclass 68152 Thermablok Aerogel Insulation Blanket Thermablok Aerogel Blanket Ultra Thin Internal Solid Wall, Ceiling & Floor Insulation Systems for New Build & Refurbishment Unique insulation with the

More information

TW50. Insulation STANDARD DETAILS FOR 50 MM INSULATION BOARD IN A 100 MM CAVITY. Low Energy Low Carbon Buildings. Wall lining. Inner leaf blockwork

TW50. Insulation STANDARD DETAILS FOR 50 MM INSULATION BOARD IN A 100 MM CAVITY. Low Energy Low Carbon Buildings. Wall lining. Inner leaf blockwork Insulation CI/SfB (21.9) Rn7 M2 First Issue May 2017 e with retaining clip TW50 STANDARD DETAILS FOR 50 MM INSULATION BOARD IN A 100 MM CAVITY 25 mm / 50 mm residual cavity Kingspan Thermawall TW50 Outer

More information

Insight. The Hollow Building. By Joseph W. Lstiburek, Ph.D., P.Eng., Fellow ASHRAE

Insight. The Hollow Building. By Joseph W. Lstiburek, Ph.D., P.Eng., Fellow ASHRAE Insight The Hollow Building An edited version of this Insight first appeared in the ASHRAE Journal. By Joseph W. Lstiburek, Ph.D., P.Eng., Fellow ASHRAE Buildings today are hollow and multilayered with

More information

REPORT HOLDER: THE DOW CHEMICAL COMPANY 1501 LARKIN CENTER DRIVE MIDLAND, MICHIGAN EVALUATION SUBJECT:

REPORT HOLDER: THE DOW CHEMICAL COMPANY 1501 LARKIN CENTER DRIVE MIDLAND, MICHIGAN EVALUATION SUBJECT: 0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-3089 Reissued 07/2016 This report is subject to renewal 07/2018. DIVISION: 07 00

More information

Fire Pattern Repeatability: A Study in Uncertainty

Fire Pattern Repeatability: A Study in Uncertainty Fire Pattern Repeatability: A Study in Uncertainty Daniel Madrzykowski National Institute of Standards and Technology Gaithersburg, MD., USA Charles Fleischmann, PhD Department of Civil and Natural Resources

More information

ENERGETIC EVENT IN FUEL-COOLANT INTERACTION TEST FARO L-33

ENERGETIC EVENT IN FUEL-COOLANT INTERACTION TEST FARO L-33 FR0108109 ENERGETIC EVENT IN FUEL-COOLANT INTERACTION TEST FARO L-33 D. MAGALLON*, I.HUHTINIEMI European Commission, Institute for Systems, Informatics and Safety, 21020 Ispra (VA), Italy Key words : FCI,

More information

Fire Safety and Performance of Wood in Multi-Residential and Commercial Buildings. Boris Iskra Forest & Wood Products Australia

Fire Safety and Performance of Wood in Multi-Residential and Commercial Buildings. Boris Iskra Forest & Wood Products Australia Fire Safety and Performance of Wood in Multi-Residential and Commercial Buildings Boris Iskra Forest & Wood Products Australia This Presentation 1. Fire Hazard Properties Building Code of Australia Volume

More information

Recommended Amendments to the 2012 International Residential Code (IRC)

Recommended Amendments to the 2012 International Residential Code (IRC) Issue: Insulation Requirements by Components- Basement Wall R-value and U-value 2012 IECC Section: Table N1102.1.1 and Table N1102.1.3 Modify the Tables as shown below: (Delete data, add new data) CLIMATE

More information

The Importance of Slab Edge & Balcony Thermal Bridges

The Importance of Slab Edge & Balcony Thermal Bridges Exterior Exterior Thermal Break Prepared by Date RDH Building Engineering Ltd. September 24, 2013 Interior 18.6 C Interior 18.6 C Report # 2: Impact of Slab Thermal Breaks on Thermal Comfort and Condensation

More information

July 23, 2010 PARTIES INTERESTED IN REFLECTIVE FOIL INSULATION

July 23, 2010 PARTIES INTERESTED IN REFLECTIVE FOIL INSULATION July 23, 2010 TO: SUBJECT: PARTIES INTERESTED IN REFLECTIVE FOIL INSULATION Revisions to the Acceptance Criteria for Reflective Foil Insulation, Subject AC02-0610-R1 (LS/RB) Dear Madam or Sir: In June

More information

Rainscreen Ventilated Fire Barrier

Rainscreen Ventilated Fire Barrier An intumescent FR barrier for slab edge, curtain wall and façade applications Technical Data Sheet KEY BENEFITS - Allows air movement in building design whilst providing superior fire rating - Fire Resistance

More information

CHAPTER 3: Modern Methods of Construction (MMC)

CHAPTER 3: Modern Methods of Construction (MMC) CONTENTS 3.1.1 INTRODUCTION 3.1.2 SUITABILITY OF SYSTEMS AND COMPONENTS 3.1.3 TYPES OF MODERN METHODS OF CONSTRUCTION (MMC) 3.1.4 SUITABILITY OF SYSTEMS TO MEET WARRANTY REQUIREMENTS 3.1.5 INSULATED CONCRETE

More information

The Passive Fire Protection Handbook

The Passive Fire Protection Handbook The Passive Fire Protection Handbook The UK s comprehensive guide to passive fire protection Chapter Ceilings, Floors and Roofs AUGUST 0 The Passive Fire Protection Handbook Contents Chapter : Introduction

More information

Technical Guidance Note

Technical Guidance Note Technical Guidance Note THE BUILDING REGULATIONS 2004 EDITION ENGLAND AND WALES REQUIREMENT A3 DISPROPORTIONATE COLLAPSE 1. INTRODUCTION (a) This technical guidance note outlines NHBC s interpretation

More information

THERMAL BARRIERS AND IGNITION BARRIERS FOR THE SPRAY POLYURETHANE FOAM INDUSTRY

THERMAL BARRIERS AND IGNITION BARRIERS FOR THE SPRAY POLYURETHANE FOAM INDUSTRY THERMAL BARRIERS AND IGNITION BARRIERS FOR THE SPRAY POLYURETHANE FOAM Copyright: 2011 Distributed by permission of Spray Polyurethane Foam Alliance Page 2 TECHNICAL OVERSIGHT COMMITTEE Participating Members

More information

CLT The new use of timber in Australia Prepared for AIRAH Victoria Division Meeting, February 2014

CLT The new use of timber in Australia Prepared for AIRAH Victoria Division Meeting, February 2014 CLT The new use of timber in Australia Prepared for AIRAH Victoria Division Meeting, February 2014 Jonathan Barnett, PhD, FIEAust, CPEng Technical Director Is Timber the Future? 2 What is CLT Cross-Laminated

More information

Simulation of Flameless Combustion of Natural Gas in a Laboratory Scale Furnace

Simulation of Flameless Combustion of Natural Gas in a Laboratory Scale Furnace Turkish J. Eng. Env. Sci. 30 (2006), 135 143. c TÜBİTAK Simulation of Flameless Combustion of Natural Gas in a Laboratory Scale Furnace Sébastien MURER, Barbara PESENTI and Paul LYBAERT Thermal Engineering

More information

CLIMAVER ductwork system. Saves valuable space, reduces installation time and is more cost-effective

CLIMAVER ductwork system. Saves valuable space, reduces installation time and is more cost-effective CLIMAVER ductwork system Saves valuable space, reduces installation time and is more cost-effective The CLIMAVER pre-insulated ductwork system solution enables you to meet the thermal, acoustic and fire

More information

CFD modeling of airflows and contaminant transport in an aircraft cabin

CFD modeling of airflows and contaminant transport in an aircraft cabin 20th International Congress on Modelling and Simulation, Adelaide, Australia, 1 6 December 2013 www.mssanz.org.au/modsim2013 CFD modeling of airflows and contaminant transport in an aircraft cabin Jiuzhou

More information

Quantification of Green Building Features on Firefighter Safety

Quantification of Green Building Features on Firefighter Safety 2017 NFPA Conference & Expo Quantification of Green Building Features on Firefighter Safety Handout Material Selected Presentation Slides Presented by: Praveen Kamath, WPI Brian Meacham, WPI Michael Gollner,

More information

TRIDENT S8 DN 35 SECTION SAFETY AND SECURITY FILMS

TRIDENT S8 DN 35 SECTION SAFETY AND SECURITY FILMS TRIDENT S8 DN 35 SECTION 08 87 23 SAFETY AND SECURITY FILMS PART 1 GENERAL 1.1 SUMMARY A. Optically clear, anti-fragmentation protective polymeric film for glass hazard mitigation. 1.2 RELATED SECTIONS

More information

June 25, 2012 PARTIES INTERESTED IN SPRAY-APPLIED FOAM PLASTIC INSULATION

June 25, 2012 PARTIES INTERESTED IN SPRAY-APPLIED FOAM PLASTIC INSULATION June 25, 2012 TO: PARTIES INTERESTED IN SPRAY-APPLIED FOAM PLASTIC INSULATION SUBJECT: Revisions to the Acceptance Criteria for Spray-applied Foam Plastic Insulation, Subject AC377-0612-R1 (SF/MB) Dear

More information

Technical Solutions Fireplaces DEKTON MANUAL

Technical Solutions Fireplaces DEKTON MANUAL Technical Solutions Fireplaces DEKTON MANUAL INDEX BASIC CONCEPTS ABOUT EXTREME HEAT FIREPLACE TIPOLOGIES Classification according to the form in which heat is generated Classification according to the

More information

CFD Modeling Study of a 500 MW Gas-Fired Utility Boiler

CFD Modeling Study of a 500 MW Gas-Fired Utility Boiler CFD Modeling Study of a 500 MW Gas-Fired Utility Boiler E.H. Chui, A. Runstedtler, A. Majeski CANMET Energy Technology Centre, Natural Resources Canada, Ottawa, Canada I. Leach OPG Lennox Generating Station,

More information

FIRESTOP 101: An Introduction to Firestopping

FIRESTOP 101: An Introduction to Firestopping FIRESTOP 101: An Introduction to Firestopping Role of Firestop What is Firestopping? A process whereby certain materials, some of them specially manufactured, are used to resist (or stop) the spread of

More information

June 1, 2010 PARTIES INTERESTED IN EVALUATION REPORTS ON REFLECTIVE FOIL INSULATION

June 1, 2010 PARTIES INTERESTED IN EVALUATION REPORTS ON REFLECTIVE FOIL INSULATION June 1, 2010 TO: PARTIES INTERESTED IN EVALUATION REPORTS ON REFLECTIVE FOIL INSULATION SUBJECT: Proposed Revisions to the Acceptance Criteria for Reflective Foil Insulation, Subject AC02-0610-R1 (LS/RB)

More information

Xtratherm Thin-R Thermal Liner (XT/TL Grade)

Xtratherm Thin-R Thermal Liner (XT/TL Grade) CERTIFICATE NO. 03/0183 DETAIL SHEET 4 Xtratherm Thin-R Thermal Liner (XT/TL Grade) PRODUCT DESCRIPTION: This Detail Sheet relates to Xtratherm Thin-R Thermal Liner, as defined in NSAI Agrément Certificate

More information

Acceptable Construction Details, Thermal Bridging and Air Permeability. Sean Armstrong, Technical Adviser, Building Standards, DEHLG

Acceptable Construction Details, Thermal Bridging and Air Permeability. Sean Armstrong, Technical Adviser, Building Standards, DEHLG Acceptable Construction Details, Thermal Bridging and Air Permeability Sean Armstrong, Technical Adviser, Building Standards, DEHLG Outline Overview of TGD L Overview of Guidance wrt Airtightness and Thermal

More information

Charring rate determination of wood pine profiles submitted to high temperatures

Charring rate determination of wood pine profiles submitted to high temperatures Charring rate determination of wood pine profiles submitted to high temperatures Fonseca, E.M.M. 1 and Barreira, L.M.S. 1 1 Polytechnic Institute of Bragança, Portugal Abstract The wood material presents

More information

2012 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs

2012 IBC Inspection of Fire-Resistance Rated Floors, Ceilings and Roofs Class Outline Inspection of Fire-resistance-Rated Floors, Ceilings and Roofs Based on 2012 International Building Code (IBC) Introduction Determining fire resistance Test standards Definitions Alternate

More information