1 Environmental Monitoring Report VIE: Strengthening Water Management and Irrigation Systems Rehabilitation Project (ADB5) The Fifth Quarterly Environment Monitoring Report (From March to May ) COMPONENTS 2: CONSTRUCTION AND REHABILITATION OF BAC HUNG HAI IRRIGATION AND DRAINAGE INFRASTRUCTURE Prepared by Southeast Asia Institute for Water Resources and Environment for the Central Project Office (CPO) MARD and the Asian Development Bank

2 MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT CENTRAL PROJECT OFFICE (CPO) Strengthening water management and irrigation systems rehabilitation project (ADB5) PACKAGE 14 MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN FOR THE WHOLE PROJECT THE FIFTH QUARTERLY ENVIRONMENT MONITORING REPORT (From March to May ) COMPONENTS 2: CONSTRUCTION AND REHABILITATION OF BAC HUNG HAI IRRIGATION AND DRAINAGE INFRASTRUCTURE Central Project Office (CPO) Consultant firm Southeast Asia Institute for Water Resources and Environment Ha Noi, 05/

3 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage CURRENCY EQUIVALENTS (1 st June 2013) Currency unit Viet Nam Dong (VND) VND 1,00 = $ $1.00 = VND ABBREVIATIONS ADB Asian Development Bank AFD Agence Francaise Development PMU Projects Management Unit BHH Bac Hung Hai irrigation and drainage system CBOs Community Based Organizations CEMP Community Environmental Management Program CPMU Central Project Management Unit CPO Central Project Office EMP Environmental Management Plan GOV Government M&E Monitoring & Evaluation PPMU Provincial Project Management Unit PRA Public Relative Assessment EM Environmental Management SEMP Site Environmental Management Program TOR Term of References DONRE Department of Natural Resources and Environment IEE Initial Environmental Examination QCVN Vietnam National Environmental Standards ADB Asian Development Bank AFD Agence Francaise Development PMU Projects Management Unit BHH Bac Hung Hai irrigation and drainage system MEASURES UNIT ha Hectare kg Kilogram km Kilometer m Meter t Ton NOTES In this report, "$" refers to US dollars otherwise state This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. i Package 14 Monitoring the implementation of environmental management plan for the

4 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage TABLE OF CONTENTS LIST OF TABLES... iii LIST OF FIGURES... iii CHAPTER 1: SUMMARY OF PROJECT INTRODUCTION OF PROJECT Objectives of components Main works items of project Implementation location of components CHAPTER 2: IMPLEMENTATION PROGRESS OF PROJECT... 4 CHAPTETR 3: RESULTS OF THE FIFTH MONITORING FOR THE IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN The results of community based monitoring Implemented contents Results of community based monitoring The results of environmental monitoring of construction supervision consultant Implementation contents On site inspection results Contents of On site inspection Analysis results of environmental samples in the fifth monitoring Analysis results of air samples Analysis results of surface - water sample in the fifth monitoring Synthesing results of the fifth monitoring CHAPTER 4: CONCLUSION AND RECOMMENDATION Conclusion Achieved results Pending issues Recommendations Plan for next 6 months monitoring APPENDIX Appendix 1: Location of sub - projects Appendix 2: Some photos in the fifth monitoring Appendix 3: Analysis results of environmental samples ii Package 14 Monitoring the implementation of environmental management plan for the

5 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage Appendix 4: The fifth monitoring minutes and list of community consultation in the fifth monitoring Appendix 5: The monitoring forms LIST OF TABLES Table 1.1: Sub projects in BHH system...2 Table 2.1: Implementation progress of sub - projects... 6 Table 3. 1: Comments of community about project s impact on environment, society Table 3. 2: Number of environmental monitoring forms implemented by construction supervision consultant in the fifth monitoring Table 3. 3: Synthesizing the assessment based on score given by construction supervision consultant Table 3. 4: Assessment results of construction supervision consultant Table 3. 5: Locations of on site inspection of sub - projects Table 3. 6: Summary the results of on site inspection in the fifth monitoring Table 3. 7: Synthesizing the pending issues of sub projects Table 3. 8: Description of air sampling location Table 3. 9: Description of surface - water sampling location Table 3. 10: Synthesis of the fifth monitoring LIST OF FIGURES Figure 1.1: Diagram of sub- projects... 3 Figure 3.1: DO concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.2: SS concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.3: COD concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.4: BOD5 concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.5: NH 4 + concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.6: NO 2 - concentration in surface water at monitoring location HP2 the fifth monitoring iii Package 14 Monitoring the implementation of environmental management plan for the

6 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage CHAPTER 1: SUMMARY OF PROJECT 1.1 INTRODUCTION OF PROJECT Project Strengthening water management and irrigation systems rehabilitation, invested by ADB and AFD, includes three components: (i) Components 1: of New Educational Facilities for Water Resources University. (ii) Components 2: and rehabilitation of Bac Hung Hai irrigation and drainage system infrastructure. (iii) Components 3: Strengthening capacity of BHH Service Providers Objectives of components 2 Long term objectives: To improve water supply and drainage for: Transforming cropping-pattern by irrigation and drainages solutions to ensure a stable production and water supply for 100 % residents in the Bac Hung Hai in 2020; agricultural production with drought frequency of 85% in 2020; reducing damages caused by flood in the region, mostly in the area of lowlying agricultural land of Hung Yen and Hai Duong provinces in order to stabilize human life and production activities to push forward an sustainable socio - economic development, protect ecological environmental, and prevent pollution and deterioration of water resources. Short term objectives: - Providing sufficient water for agricultural, aquaculture activities; meet the water supply demand for industrial zone, residential areas and remedy environmental pollution situation by development and rehabilition activities of irrigation infrastructure of project region; - Modernizing and improving irrigation-system performance; - Innovating management practices and improving service quality; - Strengthening institution for sustainable exploitation of the system to achieve proposed targets; - Establishing, strengthening and developing institution for the regional management and exploitation agencies in appropriate, effective and sustainable way; - Strengthening management and operation practices with community s participation through education, communication and public consultation. Main works items of project The works items relate to environmental assessment including (Table 1.1): - Constructing 8 new pumping stations, in which 1 irrigation pumping station and 7 drain pumping stations; - Rehabilitating and upgrading 2 drain pumping stations. 1 Package 14 Monitoring the implementation of environmental management plan for the

7 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Name of Sub project 1 Phu My irrigation pump-station Table 1.1: Sub projects in BHH system New construction / upgrade/ Rehabilitati on New construction Capacity ( m 3 /s) Location 13.2 Dinh To commue - Thuan Thanh district Bac Ninh province Remark Taking water from Duong river 2 Lien Nghia drain pumpstation 3 Nghi Xuyen drain pumpstation 4 Chua Tong drain pumpstation 5 Kenh Vang II drain pumpstation 6 Nhat Trai drain pumpstation 7 Co Ngua pump-station 8 Cau Dua drained pumpstation New construction New construction New construction Rehabilitatio n (change machine) New construction New construction New construction 25 Lien Nghia commue - Van Giang district - Hung Yen province. 55 Thanh Cong provincr - Khoai Chau district - Hung Yen province 11 Trung Hung commune - Yen My district Hung Yen province 44 Trung Kenh commune - Luong Tai district - Bac Ninh province 30 Minh Tan commune - Luong Tai district - Bac Ninh province 7 Van Giang commune - Ninh Giang district - Hai Duong province 17 Van To commune - Tu Ky district - Hai Duong province Draining water to Red river of one regulating works in Cuu An river to enclose the drainage catchment. - Draining water to Red river - Draining water to Kim Son river - Replace pumps and the auxiliary electric-mechanic equipment - Restore pumping capacity to 44 m 3 /s Draining water to Thai Binh river Draining water to Luoc river Draining water to Thai Binh river 9 Doan Thuong drain pump - station 10 My Dong drain pumpstation New construction Upgrading (change machine) 15.6 Doan Thuong commune - Gia Loc district - Hai Duong province 22 Tien Phong commune - Thanh Mien district - Hai Draining water to Dinh Dao river Draining water to Luoc river 2 Package 14 Monitoring the implementation of environmental management plan for the

8 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Name of Sub project New construction / upgrade/ Rehabilitati on Implementation location of components 2 Capacity ( m 3 /s) Location Duong province Remark Bac Hung Hai System (BHH) is located in the center of the Red River Delta, in the administrative boundaries of four provinces: 2 districts on the southeast of Hanoi, the entire of Hung Yen Province, 7 districts of Hai Duong and 3 districts of Bac Ninh province. BHH system is enclosed by four major rivers: Duong river in the north, Luoc river in the south, Red river in the western and Thai Binh River in the east. The total irrigation area of the system is 192,045 ha, of which, 142,479 ha is agricultural land. The total population in the region is 2.8 million people, in which, 2.2 million people working in agricultural production. BHH system is divided into 10 sub-regions: Gia Lam, Gia Thuan, Chau Giang, Bac Kim Son, Cam Giang - Hai Duong city, An Thi. Binh Giang - Bac Thanh Mien, Tu Loc (Gia Loc-Tu Ky), Southwest of Cuu An, Southeast of Cuu An. The locations of 10 subprojects are shown in figure 1.1. The location for each sub- project can be seen in figures from Figure 1.1 to Appendix 1. Figure 1.1: Diagram of sub- projects 3 Package 14 Monitoring the implementation of environmental management plan for the

9 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage CHAPTER 2: IMPLEMENTATION PROGRESS OF PROJECT Updating to 5/5/, there were 9/10 sub - projects which have been in construction; Particularly Co Ngua sub project has been being in process of preparing commencement. Implementation progress of sub projects has been synthesized in Table 2.1. In which: - Sub projects in goodconstruction progress are Kenh Vang, Cau Dua, Doan Thuong, and Lien Nghia,. - Sub projects in delayed construction progress compared are Chua Tong, My Dong, Nghi Xuyen and Co Ngua. Reasons for the delaying for each sub project as following: - Phu My pumping station sub project has been delayed according construction progress for 3 months due to rainy weather that causing difficulties for construction of outer dyke pumping station. PMU has directed construction contractor to speed up progress at thedelayed items and to commit to finishing work as proposed progress. - Chua Tong pumping station sub project has been delayed according to construction progress for 2 months due to the narrow road of material transportation, difficulties for transportation of sheeting pile and concrete. At the same time, during excavation of foundation, it has impacted on local people s house; there are signs of crack and break between road and local people s house, for which, the PMU has requested contractor to stop construction to resolve problem, ensuring safety for local people house. - My Dong pumping station sub project constructing culvert caused cracking wall and yard of ancillary construction so that construction has been stopped for 1 month in order to insurance company verifies damage and compensate for people. - Co Ngua pumping station sub project, commencement has delayed for 2 months compared with plan because procudures for land acquisition have to finish according to the new regulations. Here is summary of main actitivities of sub projects: (i) Phu My pumping station sub project: construction of basic part has been finished; foundation of pumping house and management house have been completing, discharge canal has been constructing (section from discharge tank to culvert under dyke). volume approximately achieved 26%. (ii) Kenh Vang pumping station sub- project : management house, pumping house, center controlling house and sewer grates system, intake tank, retaining dam which belong to head- works. volume appoximately achieved 75%, construction progress achieved plan. (iii) Nhat Trai pumping station sub project: construction volume approximately achieved 2% ( ensure proposed plan). + Lot A: making road for construction, forming testing pile and excavating foundation of pumping house. + Lot B: forming beams for retaining canal slope and constructing diversion canal. (iv) Chua Tong pumping station sub - project: Constructing retaining dam at upstream. volume approximately achieved 30%, construction progress has delayed in 4 Package 14 Monitoring the implementation of environmental management plan for the

10 The fifth monitoring report - Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage comparison with plan. (v) Lien Nghia pumping station sub - project: + Lot A has finished retaining dam, construction road at field side, forming pile in large scale, excavating foundation to design altitude(-4,1m). Foundation and wall of pumping house; foundation and side wall of intake tank have been constructing. Returning filled soil around pumping house has been done. + Lot B has been excavating discharge canal and preparing raft for construction of discharge canal s gate. Value of implemeted volume approximately achieved 40%, construction progress achieved plan. (vi) Cau Dua pumping station sub - project: discharge culvert under dyke and basic parts of management house have been constructed completely. Pumping house and intake tank has been constructing. volume approximately achieved 50%, construction progress achieved plan. (vii) Doan Thuong pumping station sub - project: volume approximately achieved 60%, construction progress achieved plan. + Lot A has constructed completely concreted foundation, wall of pumping house, discharge tank and intake tank. Concreted engine floor of pumping house, pumping house has been constructing. + Lot B has constructed completely gravity drainage culvert; dreged, consolidated canal and constructing 4 brideges on canal. (viii) Co Ngua pumping station sub - project: site plan and campsite for workers have been preparing, construction progress delayed in comparision with plan. (ix) My Dong pumping station sub - project:management house, pumping house, culvert under dyke and discharge canal have been constructing. volume approximately achieved 80%, construction progress delayed in comparison with plan. (x) Nghi Xuyen pumping station sub project: construction progress delayed in comparison with plan. + Lot A: Processed, installed formworks, reinforced foundation, pumping house s wall, concreted foundation; installed the stop log gains of pumping house and sewer grate. Transition yard has been constructing. + Lot B: Processed, installed formwork, reinforced steel of foundation and wall; culvert section no.3-5 has been poured with concrete, culvert foundation has been filled by soil to altitude +3,6 m; Gate of culvert under dyke has been processing and installing. 5 Package 14 Monitoring the implementation of environmental management plan for the

11 2013 No. Name 1 Phu My pumping station 2 Kenh Vang II pumping station Name of contractor Cooperation between Dong A International Joint Stock Company Anh Phuong construction JSC Ha Tay Irrigation JSC Cooperation between Ninh Giang Company Ltd - Tan Thinh Date of Signing Contract and Commenc e cement Date signing contract: 1/4/2013 of Date commence ment: 19/4/2013 of Date of signing contract: 4/3/2013 Date of commence Table 2.1: Implementation progress of sub - projects Imple men - ting time 24 month s 24 months In monitoring period (from 1/3/ to 30/4/) - Basic part has been constructed completely and pumping house has been finishing. - Pumping house, discharge tank, intake tank, discharge canal (section from discharge tank to culvert under dyke) has been constructing. Sewer grates system and intake tank of head works and management house, pumping Constructed items Cumulative work to 30/4/ - Driving pile has been tested completely. - Pumping house has been finishing. Pumping house, discharge tank, intake tank, discharge canal (section from discharge tank to culvert under dyke) has been constructing. - Driving pile has been tested. - Headworks have been constructing: discharge tank, Constructed volume In monitoring period (from 1/3/ to 30/4/) - Basic part of management house has been constructed completely. - Discharge canal which section is from discharge tank to culvert under dyke (100m) has been completed. - Retaining dam has been constructed by soil: 2500m 3 - Management Cumulative work to 30/4/ - Basic part of management house has been constructed completely (374.5m 2 ). - Discharge canal has been constructing (earthworking of 1,569 m 3 soil of discharge canal), pumping house, discharge tank: Excavation and transportation of 2,400m 3 of soil. - Concrete piles have been drived by 700m, bamboo piles by 3000m; Excavation, transportation of Assessment of construction progress compared with shedule - Approximately achieved 26% value of contract (9.5 billion VND). - progress has been delayed for 3 months due to much rain. - Achieved 15 billion VND (75%) of contract value -Achieved 6 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

12 2013 No. Name Name of contractor Company Ltd - Irrigation Joint Stock Company Date of Signing Contract and Commenc e cement ment: 19/4/2013 Imple men - ting time In monitoring period (from 1/3/ to 30/4/) house and centre controlling house have been constructing. Constructed items Cumulative work to 30/4/ sewer grate system, intake tank, retaining dam. - Management house, pumping house, centre controlling house has been finishing. Constructed volume In monitoring period (from 1/3/ to 30/4/) house has been plastering with plastering volume: 3350m 2 - Pumping house has been painting with area of 2900m 2 Cumulative work to 30/4/ mud, soil: more than 5000 m 3 ; Pouring concrete: 500m 3 - Being complete plastering the mangement house with area of 3350 m 2 ; The Station is being painted with area of 2900 m 2. Assessment of construction progress compared with shedule construction progress in comparison with proposed plan 3 Nhat Trai pumping station Lot A: Association between Song Hong irrigation construction JSC ; and Development JSC; A Chau industrial Engineering JSC - Date of signing contract 6/12/ Date of commence ment 19/02/ 36 months Completed soil excavation stage 1 and completed production of testing concrete piles. Completed soil excavation stage 1 and completed production of testing concrete piles. - Completed soil excavation stage 1 to altitude of - 1.0m, completed production of testing concrete piles (269.5m) for 11 positions. Completed soil excavation stage 1 to altitude of - 1.0m, completed production of testing concrete piles (269.5m) for 11 positions. - Approximately achieved 2 billion VND (3%) of contract value. - Achieved construction progress in comparison with proposed plan. 7 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

13 2013 No. Name Name of contractor Date of Signing Contract and Commenc e cement Imple men - ting time In monitoring period (from 1/3/ to 30/4/) Constructed items Cumulative work to 30/4/ Constructed volume In monitoring period (from 1/3/ to 30/4/) Cumulative work to 30/4/ Assessment of construction progress compared with shedule 4 Chua Tong pumping station Lot B: An Binh construction corporation Hung Yen Irrigation and Dyke JSC - Date of signing contract 25/12/2013 -Date of commence ment 19/02/ - Date of signing contract: 27/1/ Date of commence ment: 18/4/ months 28 months - Diversion canal :excavating canal, processing steel, pouring concrete beams - Works on canal: Processing reinforcement steel, pouring concrete pile. - Retaining dam at upstream has been constructing - Excavating canal, processing steel, pouring concrete beams - Processing reinforcement steel, pouring concrete pile. - Testing pile has been done. - Pumping house, intake tank, discharge tank have been constructing. - Retaining dam at upstream has been constructing. Forming beams for retaining canal slope and constructing diversion canal with length of 780.4m. - Forming piles and driving piles have been done in large scale, earthwork of retaining dam at upstream has been done. - Retaining dam at upstream has been Forming beams for retaining canal slope and constructing diversion canal with length of 780.4m. - of road base has been finished: 680m; Levelling ground volume : 70%; - Earthwork of 250m of diverson canal has been done. - Approximately achieved 1.24 billion VND (3%) of contract value. - progress has delayed in comparison with proposed plan due to high level underground. progress has delayed in comparison with proposed plan due to narrow road for material transportation, causing difficulties for material 8 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

14 2013 No. Name Name of contractor Date of Signing Contract and Commenc e cement Imple men - ting time In monitoring period (from 1/3/ to 30/4/) Constructed items Cumulative work to 30/4/ Constructed volume In monitoring period (from 1/3/ to 30/4/) constructing. Cumulative work to 30/4/ Assessment of construction progress compared with shedule transportation and overcoming the problem of house cracking. 5 Lien Nghia pumping station Hai Phong Irrigation Joint Stock Company Hung Yen Irrigation Company - Date of signing contract: 20/9/ Date of commence ment: 8/10/ months - Lot A: construction of retanining dam, construction road at field side, forming piles in large scale, excavation of foundation have been finished. + Lot B: discharge canal has been constructing and and raft has been preparing for construction of discharge canal s gate. - Testing pile has been done - Intake tank, discharge tank, pumping house have been constructing; - Raft has been preparing for construction of discharge canal s gate. - of retanining dam, construction road at field side, forming piles in large scale, excavation of foundation to designed altitude have been finished (- 4.1m). - Discharge canal has been excavating. Raft has been preparing for construction of discharge canal s gate. - of retanining dam, construction road at field side, forming piles in large scale, excavation of foundation to designed altitude have been finished (- 4.1m). - Pumping house s wall, side wall to +2.1m have been constructing; Canal of puming house, side wall have been excavating; Raft - Approximately achieved 40% of contract value. - progress has ensured in comparison with plan 9 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

15 2013 No. Name Name of contractor Date of Signing Contract and Commenc e cement Imple men - ting time In monitoring period (from 1/3/ to 30/4/) Constructed items Cumulative work to 30/4/ Constructed volume In monitoring period (from 1/3/ to 30/4/) Cumulative work to 30/4/ has been preparing for construction of discharge canal s gate. Assessment of construction progress compared with shedule 6 Cau Dua pumping station Cooperation between Thanh Hoa Agricultural and Rural Development Company - Thai Binh Irrigation Joint Stock Company - Date of signing contract: 25/4/2013 -Date commence ment: 1/6/2013 of 24 months - Foundation of management house has been treated and poured concrete pumping house to engine floor. - Pumping house has been constructing and discharge canal has been pouring concrete. - Poured concrete pumping house to engine floor; Poured concrete intake tank s foundation - Discharge canal and management house have been constructing. - Pouring concrete:1.100m 3 ; brick masonry of 180 m 3, - Plastering wall 2,200 m 2. -Levelling ground stage 1 has been done: 13,971m 3 ; Driving concreted pille with 546 piles;earthworkin g has been done with: 41,000m 3 of soil. - Driving sheeting pile has been done: T; brick masonry of 180m 3 - Approximately achieved 47% of contract value - progress has been ensured in comparison with approved plan - Plastering wall 2,200 m 2 7 Doan Thuong lot A: Cooperation - Date of signing 24 months - Foundation of management - Foundation of management house - Processing reinforcement - Processing reinforcement - Approximately achieved 60% of 10 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

16 2013 No. Name pumping station Name of contractor between Hai Duong Irrigation and Electrical Installation Company Lot B: Thao Nguyen Company Ltd Date of Signing Contract and Commenc e cement contract: 10/4/ Date of commence ment: 1/6/ Date of signing contract: 10/4/ Date of commence ment: 1/6/2013 Imple men - ting time 24 months In monitoring period (from 1/3/ to 30/4/) house has been treated and poured concrete, discharge canal, pumping house to engine floor. - Pumping house has been constructing, high voltage transmission line tower has been installing. - 4 bridges for local people have been constructing; of discharge culvert under dyke; construction of Duong Gung temporary pumping station. Constructed items Cumulative work to 30/4/ - Discharge canal has been pouring with concrete; poured concrete, pumping house to pump - floor and constructing pumping house. Constructed volume In monitoring period (from 1/3/ to 30/4/) has been treated; steel has been high voltage finished T; transmission line Form steel: tower has been 4.069T; brick installed. masonry: 30.0m 3. - of drainage culvert, gravity canal, dredging canal, strengthening canal slope have been finished. - 4 bridges for local people, Duong Gung temporary pumping station and - Pouring concretes 278.1m 3 - Processing of reinfrocement steel has been finished with 10T; form steel: 4.069T; Stone masonry : m 3 ; excavated soil: 4,317m 3 ; filled soil: 3,084m 3 Cumulative work to 30/4/ steel has been finished 201.9T; Form steel: T; brick masonry: 30.0m 3 - Pouring concretes m 3 - Dredging canal has been done with102,702.8m 3, Strengthened canal slope by stone: 1,695.3m 3 ; Processing of round steel bar has been done: T; form steel with Assessment of construction progress compared with shedule contract value. - progress has exceeded in comparison with approved plan. - Approximately achieved 60% of contract value - progress has been ensured in comparison with approved plan 11 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

17 2013 No. Name 8 Co Ngua pumping station 9 My Dong pumping station Name of contractor Association between JSC no.12 and Thai Binh irrigation construction consultant JSC and Hai Duong pump manufacture JSC Cooperation between Dai An Investment and Date of Signing Contract and Commenc e cement - Date of signing contract: 05/4/ Date of commence ment: not available - Date of signing contract: 6/5/2013 Imple men - ting time 24 months In monitoring period (from 1/3/ to 30/4/) - Canal has been dredged, canal slope has been strengthened for canal section K2,2-K2,6 volume has not been available. Pumping station house, culvert, roller bridge of intake tank; gate Constructed items Cumulative work to 30/4/ discharge culvert under dyke have been constructing;. volume has not been available. Pumping station house, culvert, roller bridge of intake tank; gate of Constructed volume In monitoring period (from 1/3/ to 30/4/) Cumulative work to 30/4/ - Reinforced T; filled concretes:260.3m 3 soil: 22,097m 3 ; Reinforced concrete piles with 120 piles volume has not been available. - Excavated and filled with 6,053 m 3 of soil; - Pouring concrete: -Pouring concrete: 1, m 3 volume has not been available. Excavated and filled with 16,483 m 3 of soil and transported Assessment of construction progress compared with shedule Commencement has been delayed in comparison with plan because the procedures of land acquisition based on new regulations have to complete. progress has delayed in comparison with 12 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

18 2013 No. Name 10 Nghi Xuyen Pumping station Name of contractor Joint Stock Company and Joint Stock Company No. 12 Lot A: cooperation between Song Hong JSC Thanh Date of Signing Contract and Commenc e cement - Date of commence ment: 11/6/ Date of signing contract: 21/08/ Date of commence Imple men - ting time 36 months In monitoring period (from 1/3/ to 30/4/) of culvert under dyke have been constructing. - Processing and installing of formwork, reinforcement steel for foundation, wall Constructed items Cumulative work to 30/4/ culvert under dyke have been constructing. - Camps for workers has been done; Excavation of foundation stage 1, 2 has been finished; Work item of Constructed volume In monitoring period (from 1/3/ to 30/4/) Cumulative work to 30/4/ m 3 refuse: 171,680 m 3 - Formwork for pumping house has been done: 10,000m 2 ; Reinforcement -Pouring concrete: m 3 - Excavated 24,000m 3 of soil; Pour concrete for preformed pile m 3 ; Driving pile for Assessment of construction progress compared with shedule plan because of the following reasons: - Survey data of diversion canal are different from design in process of wating redesign. - contractor who construct culvert caused crack of wall and ancillary construction of local people. -Implementation value approximately achieved 42.0 billions 13 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

19 2013 No. Name Name of contractor Hoa Agriculture and Rural Development Company 6.3 Joint Stock Company Date of Signing Contract and Commenc e cement ment: 12/9/2013 Imple men - ting time In monitoring period (from 1/3/ to 30/4/) of pumping house have been done. - Foundation and wall of pumping house has been pouring with concrete; Install the stop log gians and sewer grate. of transition yard. Constructed items Cumulative work to 30/4/ foundation treatment; construction road; Base treatment and pouring concrete for bottom slab of management house; - Foundation of pumping station house has been pouring with concrete; Install the stop log gians of pumping house and sewer grate. Constructed volume In monitoring period (from 1/3/ to 30/4/) steel: 400 tons - Foundation and wall of pumping house has been pouring with reinforced concrete:1,600m 3. Cumulative work to 30/4/ base treatment 12,144.25m; Driving Lasen sheeting pile 8,280m; pile steel tons; - Foundation of pumping house has been pouring with reinforced concrete 1.600m 3. Assessment of construction progress compared with shedule - progress meets the approved plan; some work items exceed construction progress such as construction of electrical line, management house. Lot B: Hai Phong irrigation construction JSC and Mien Bac electrical investment and development Company - Date of signing contract: 21/08/ Date of commence ment: 12/9/ months - Processing and installing of formwork, reinforcement steel of foundation and wall have been done; culvert with section - Camps, base treatment, soil excavation for culvert under sky, soil excavation for discharge canal have been done; Processing and installing of - Formwork volume has been done with 1,700 m 2 ; reinforced steel of 130 (tons); filled soil volume for culvert foundation: 1,400m 3. - Excavated 23,000m 3 of soil; Driving pile for base treatment with 5,920m; Driving Larsen sheeting pile with 3,216m; steel tons; filled - Implementation value approximately achieved 23.3 billion VND. -Ensure approved plan. 14 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

20 2013 No. Name Name of contractor Date of Signing Contract and Commenc e cement Imple men - ting time In monitoring period (from 1/3/ to 30/4/) no.3,4 and 5 have been poured with concrete and foundation of culvert has been filled with soil to altitude +3.6 m - Gate of culvert under dyke has been processing and installing. Constructed items Cumulative work to 30/4/ formwork, reinforcement steel of foundation and wall have been done; culvert with section no.3,4 and 5 have been poured with concrete and foundation of culvert has been filled with soil to altitude +3.6 Constructed volume In monitoring period (from 1/3/ to 30/4/) Pouring concrete of 1,000 m 3 Cumulative work to 30/4/ soil volume for culvert foundation: 1,400m 3 - Pouring concrete of 1,729 m 3 Assessment of construction progress compared with shedule - Gate of culvert under dyke has been processing and installing. 15 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

21 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage CHAPTETR 3: RESULTS OF THE FIFTH MONITORING FOR THE IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN The fifth monitoring time: - On 29th April : Worked with CPO regarding on the contents in the fifth monitoring and collecting the relevant documents of components 2 - From 5/5 to 15/5/: On site visit at construction site of sub projects of components 2 ( in Bac Ninh, Hai Duong and Hung Yen province) 3.1 The results of community based monitoring Implemented contents Interviewing local authorities and local people about construction s impacts on environment, society and resolving conflicts which have been arised during construction. Numbers of interviewee include 180 people, in which: - Classification based on gender: 148 males and 32 females - Classification based on position: 4 Chairmans of commune, 5 Vice chairmans of commune, 3 land administration staffs, 1 village s leader and 167 local people in affected area. Detailed list of interviwees in the fifth monitoring can be seen in Appendix Results of community based monitoring Table 3. 1: Comments of community about project s impact on environment, society No. Sub project s name 1 Phu My pumping station 2 Kenh Vang II pumping station 3 Nhat Trai pumping station 4 Chua Tong pumping station Comments of community Environmental sanitation, occupational safety have been done well; got on well with local authority and local people - Good collaboration with commune local authority in ensuring traffic safety and security in region. - Local people have no comment about impacts of construction activities. People s committe of Minh Tan commune assessed that although being complicated area sub project has implemented well worker management, ensuring security at construction site and locality. However, People s Committee of commune has some recommendations: - Road through construction site is narrow; material and waste soil transportation means need to be covered and arising dust in transportation. - In case of arising problems, collaboration with local authority and relevant parties to thoroughly resolve - Sanitation at construction site has been relatively clean. People s Committee of Trung Hung commune highly apprecited environmental protection and ensuring occupational safety for 16 Package 14 Monitoring the implementation of environmental management plan for the

22 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name 5 Lien Nghia pumping station 6 Cau Dua pumping station 7 Doan Thuong pumping station 8 Co Ngua pumping station 9 My Dong pumping station 10 Nghi Xuyen pumping station workers. Comments of community - Contractor need to have sign board and warning sign boar for local people and water holes near construction site especially for children. - contractor has implemented well collecting domestic waste and ensuring environmental sanitation requirement at construction site. - Local people always support and desire project to complete on time. - There is no impact on environment and people s living because construction site is far from residential area. - Contractors have implemented well the issues of ensuring traffic safety, occupational safety at construction site and getting on well with locality. Lot A: has not impacted on people s living. Lot B : - Road surface in front of People s Committee office of Doan Thuong commune is muddy in case of rain and dusty in case of sun. Need to speed up construction progress to return road surface. - PMU needs solution (building temporary pumping station) for irrigation water supply to whole cultivable land areas which have been affected by landslide canal leading to no irrgation water. - Commune authority has bot received EMP report and information of package s progress. PMU of sub project has been requested to collaborate with People s Committee of commune when construction is commenced. - Contractor has implemented seriously the issues of environmental sanitation protection. They provide support in retaining bank for irrigation canal in order to provide irrigataion water supply for agricultural production of locality. - Contractor and insurance company have recalculate the damage for the affected household ( contractor has paid for this household 50million VND in total damage value of 80million VND based on calculation of insurance company). Presently, this household has satisfied and there is no more complaint. - Security at construction site has been ensured. Workers are aware of environmental protection at construction stie as well as surrounding environment. - Get on well with locality and local people. - Local authorities and local people assessed that most of construction contractor have collaborated well with local authorities during construction process, and supported and 17 Package 14 Monitoring the implementation of environmental management plan for the

23 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage created favourable conditions by authorities and people. activities have not impact significantly on environment and society. - The sub projects assessed by community have implemented well Environmental management plan including: Phu My, Kenh Vang II, Lien Nghia and Nghi Xuyen. - The sub projects assessed by community have not implemeneted well the environmental impact mitigation measures such as: Contractor contracting Lot B ( Doan Thuong sub - project ) has not thoroughly done the issues of returing road surface which is in front of school and People s Committee office that leading to upset of locality. Nhat Trai sub project has not paid attention on watering road surface that leading to arising dust at road section across construction site. 3.2 The results of environmental monitoring of construction supervision consultant Implementation contents (i) Collecting from PMU environmental monitoring froms implemented by construction supervision consultant. Numbers of collected forms in the fifth monitoring are listed in Table 3.2 as following: Table 3. 2: Number of environmental monitoring forms implemented by construction supervision consultant in the fifth monitoring No. Sub project s name Number of environmental monitoring forms implemented by construction supervision consultant in the fifth monitoring Form no.1 Form no.2 1 Phu My pumping station Kenh Vang II pumping station 3 Nhat Trai pumping station - Lot A 2 - Lot B 2 4 Chua Tong pumping station 5 Lien Nghia pumping station Cau Dua pumping station Doan Thuong pumping station - Lot A Lot B Co Ngua pumping station 0 9 My Dong pumping station Nghi Xuyen pumping 18 Package 14 Monitoring the implementation of environmental management plan for the

24 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name station Number of environmental monitoring forms implemented by construction supervision consultant in the fifth monitoring Form no.1 Form no.2 - Lot A Lot B 2 0 Total + Form no. 1: Forms of collecting environmental monitoring information (24 forms). supervision consultant has assessed the implementation measures to mitigate the construction impact on environment, society by giving score with the following assessment scale: Score of 1: no implementation Score of 2: sketchy implementation Score of 3 : fully implementation Score of 4 : very good implementation + Form no. 2: Monitor, manage arising risk: At sub projects of Chua Tong pumpings station (cracked people shouse), Doan Thuong (landslide of irrgation canal) but construction supervision consultant did not fill in the from no. 2. For remaining of 8/10 sub projects, because of no arising risk, there is no form no.2. (i) Interviewed construction supervision consultant to record their comments in implementation of environmental management plan of construction contractors Environmental monitoring results of construction supervision consultant According to the assessment of construction supervision consultant, there are 8/10 sub projects with more than 11 contents achieved average score of 3. In which, sub projects of Kenh Vang II, Nhat Trai, Cau Dua and Nghi Xuyen have 12/12 contents achieved average score of 3. My Dong sub project has 8 contents achieved average score of 3; 4 remaining contents achieved avevrage score of < 3. Synthesis results of forms assessed by construction supervision consultant in Table 3.4. Table 3. 3: Synthesizing the assessment based on score given by construction supervision consultant The fourth monitoring No. Sub project s name Number of contents with score < 3 Number of contents with score 3 1 Phu My Kenh Vang II Nhat Trai Lot A 0 12 Lot B Package 14 Monitoring the implementation of environmental management plan for the

25 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage 4 Chua Tong Lien Nghia Cau Dua Doan Thuong Lot A 0 12 Lot B Co Ngua My Dong Nghi Xuyen Lot A 1 11 Lot B 0 12 supervision consultant assessed that some sub projects have not thoroughly overcome comments of previous monitoring such as sub project of Doan Thuong, Chua Tong and My dong ( table 3.5). The pending issues are following: - Wheel washing station at entrance point of construction site has not been set up: sub project of Phu My, Chua Tong and Doan Thuong. - Recycle bin and mobile toilets have not been available at construction site for workers: sub projects of Chua Tong and Phu My. - Location of material storage is adjacent to local people s house and traffic road without being covered. Falling rock and soil during transportation have not been cleaned (My Dong sub - project). - Temporary fence to separate construction area from people s house and manufacture area has not been set up (Sub -projects of Phu My, Chua Tong and Nhat Trai). sign board as well as light signal at night have not been installed (Nhat Trai sub - project). No. Table 3. 4: Assessment results of construction supervision consultant Sub project s name 1 Phu My pumping station 2 Kenh Vang II pumping station 3 Nhat Trai pumping station 4 Tong Chua pumping station Pending issues in the fifth monitoring - Wheel washing station has not been set up at the entrance point of construction site - Mobile toilet at construction site was not available Workers working at construction site have not fully worn labour protection - Temporary fence to separate construction area from people s house and manufacture area has not been set up - sign board as well as light signal at night have not been installed - Recycle bin and mobile toilets were not available at construction site for workers 20 Package 14 Monitoring the implementation of environmental management plan for the

26 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name 5 Lien Nghia pumping station 6 Cau Dua pumping station 7 Doan Thuong pumping station 8 Co Ngua pumping station 9 My Dong pumping station 10 Nghi Xuyen pumping station 3.3 On site inspection results Contents of On site inspection Pending issues in the fifth monitoring - Wheel washing station was not set up at the entrance point of construction site There is no pending issues There is no pending issues There is no wheel washing station at the entrance point of construction site. has not been started - Material storage has been located too close to people s house (< 50m) - Falling rock and soil during transportation have not been cleaned There is no pending issues The on site inspection has been done by real observation at construction site, directly interviewing workers and professional staff and taking photographs, filling information in th eforms; making minutes to confirm the pending issues and responsibilities of parties. The contents of on site inspection includes: - Inspecting the implementation of environmental mitigation measures; - Inspecting the implementation of social mitigation measures; - Inspecting the implementation of occupational safety; - Inspecting the implementation of traffic safety measures. - Collecting form no. 3 (Monitoring workers health participating construction): None of contractor implement this content Locations of on site inspection are listed in table 3.5: No. Sub project s name 1 Phu My pumping station 2 Kenh Vang II pumping station 3 Nhat Trai pumping station Table 3. 5: Locations of on site inspection of sub - projects Locations of on site inspection in the fifth monitoring area of management house, pumping house, discharge tank, intake tank and campsite of workers area of management house, pumping house, central controlling house, sewer grates system and intake tank Worker s campsite at construction area of pumping station, diversion canal and area of forming testing pile 21 Package 14 Monitoring the implementation of environmental management plan for the

27 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage 4 Chua Tong pumping station 5 Lien Nghia pumping station 6 Cau Dua pumping station 7 Doan Thuong pumping station 8 Co Ngua pumping station 9 My Dong pumping station 10 Nghi Xuyen pumping station Area of retaining dam, worker s campsite, pumping house and surrounding area of construction site Area of excavating discharge canal, excavating foundation of pumping house area of management house s foundation, intake tank, culvert under dyke and worker s campsite Lot A: construction area of pumping house, intake tank, discharge tank Lot B:area of dredging and embankment for Thach Khoi canal in front of People s Committee office of Doan Thuong commune, gravity culvert and bridge across canal Site plan area for preparing construction of pumping station and workers campsite Area of reparing pumping house, culvert and surrounding area area of culvert under dyke; management house, pumping house and workers campsite Results of on site inspection No. The results of on site inspection have been synthesized in table 3.6 Table 3. 6: Summary the results of on site inspection in the fifth monitoring Sub project s name Recommendation in the last monitoring period. I Recommendations of environmental monitoring consultant 1 Phu My pumping station 2 Kenh Vang II pumping station 3 Nhat Trai pumping station 4 Chua Tong pumping station 5 Lien Nghia pumping station Immediately make fence to separate, warning construction works from fields area of local people Immediately make fence to separate, warn construction works from fields area of local people Need to make package s information board, traffic sign board, construction sign board There is no recommendation Need to sign contract with local collecting group to collect domestic waste Need to make sign board at construction area of management house (field side) Implemented x x Not implemented yet x x x 22 Package 14 Monitoring the implementation of environmental management plan for the

28 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name 6 Cau Dua pumping station 7 Doan Thuong pumping station 8 Co Ngua pumping station 9 My Dong pumping station 10 Nghi Xuyen pumping station Recommendation in the last monitoring period. Recycle bins and mobile toilets need to be provided at construction site for workers Labour protection needs to be equipped for workers at construction site during construction Protection fence need to be made along dredged canal section to ensure safety for traffic user. Road section in front of school and People s Committee office affected by construction need to be cleaned PMU of Co Ngua needs to send EMP report and progress information of package to People s Committee of Van Giang commune, Division of Natural Resources and Environment of Ninh Giang district Package s information board, traffic sign board and construction sign board need to be made - PMU of My dong sub project need to collaborate with local authority in order to thoroughly overcome situation of cracking wall and yard of ancillary construction of a family s house.speed up construction progress to return road surface for local people - Material storage need to be replaced to appropriate location and far from people s house at least 50 m - Prohibition sign board need to be placed out side of construction site Labour protection for workers need to be fully equipped during construction Labour protection for workers need to be fully equipped during construction II Recommendations of the ADB s mission 1 TB. Chùa Tổng Pay for renting house for affected household Implemented x x x x Not implemented yet x x x x x x 23 Package 14 Monitoring the implementation of environmental management plan for the

29 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name Recommendation in the last monitoring period. Engage the professional agency to certify the damages after construction finished. Implemented x Not implemented yet Adequately compensate to the damages house if any Make the temporary wall to separating construction works from the residential area x Increase water spraying for reducing dust generated fromm construction transport and cleaning leaked soil from transport on the road x 2 Cau Dua pumping station Confirm and agree the situation of the dyke before construction. The Constructor commits to take compensation for the damages after construction finished if any x install sign boards on the road at two sites of construction works showing times during a day for dyke road blocking x Project transport on the dyke road need to be done before raining season x 3 Doan Thuong pumping station Make the fence to separate construction work from agriculture and living areas x Install sufficient project information, warning boards x Strengthen the section of the enlarged canal bank near the complained house in order to prevent the damage to this house x Strengthen the damaged irrigation canal section caused by construction of enlarging drainage canal x 4 My Dong pumping station Process payment for the damaged house x Remove excavated soil and installation of project information and x 24 Package 14 Monitoring the implementation of environmental management plan for the

30 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name Recommendation in the last monitoring period. warning boards at the right locations Implemented Not implemented yet 5 Nghi Xuyen Pumping station Assign sufficient safety staff to supervise construction safety issues x Remove excavated soil to the proper sites for management x install sufficient project information/ warning boards, especially transport safety on the dyke road x Return broken dyke to the original quality before raining season x a- Achieved results: (i) Overcoming the pending issues in the fourth monitoring based on comments of construction supervision consultant including : - PMU of Nhat Trai sub project has sent EMP report to construction contractor and construction supervision consultant. At the same time, PMU has informed to Division of Natural Resources and Environment of Luong Tai district; People s Committee of Nhat Trai commune in project area about construction progress, Environmental Impact Assessmentand approved decision of Ministry of Natural Resources and Environment. - PMUs of sub projects Co Ngua and Nhat Trai have placed information board of Sub projects at construction site - Sub projects of Nhat Trai and Co Ngua have made traffic sign board and construction sign board - Lien Nghi sub - project: construction contractor has made a contract with local collecting group to collect domestic waste - contractor of My Dong pumping station : + Collaborated with insurance company to determine impact degree and compensate damage for affected household (when verification result of insurance company has not been available, contractor has paid in advance 50 million VND in total of approximately of 80million VND). Presently, there is no complaint, contractor has constructing again from 26/4/. + Material storage has been replaced to appropriate location and far from people s house at least 50m + Prohibition sign board has been placed at out side of construction site (ii) Overcoming the pending issues in the middle monitoring of ADB including : + Cau Dua sub project has verification minutes of dyke s status before construction, in which, they commit to take compensation for the damages after construction finished if any. Installed sign boards on the road at two sites of construction works showing construction times. 25 Package 14 Monitoring the implementation of environmental management plan for the

31 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage + Doan Thuong sub - project has fully installed warning sign board, package s information board. Presently, status of affected house of Mr. Doan household has been stable and safe because contractor has temporaryly strengthened canal bank by bamboo piles (before monitoring of ADB s the Mission ). Presently, Mr. Doan household has temporaryly satisfied and had no more complaint. + My Dong sub - project:contractor and insurance company has calculated damage for affected household (contractor has paid in advance 50 million VND in total of approximately of 80million VND). Presently, people has satisfied and had no more complaint. Contractor has placed warning sign board, information board of project at appropriate location. + Chua Tong sub - project: Has paid monthly rent for affected household (2 million VND/month). At the same time, commit to compensate damage (if any) after construction finished. Presently, there is no complaint from local people. + Nghi Xuyen sub - project: Project s information board and warning sign board for ensuring traffic safety at dyke road have been fully installed. At the monitoring time, according to the explaination of contractor, for excavated soil gathering at construction site, contractor did not move to dumping site; it s used to fill pumping house s foundation. b- The pending issues need to be resolved The pending issues of sub prorject have been synthesized in table 3.7 No. Sub project s name 1 Phu My pumping station 2 Kenh Vang II pumping station 3 Nhat Trai pumping station Table 3. 7: Synthesizing the pending issues of sub projects Pending issues in the fifth monitoring The pending issues in the fourth monitoring have not been solved: - There is no fence to separating construction works from field of local people (figure appendix 3) - Workers in working hours did not wear labour protection (Figure Appendix 3) - Fence for separating, warning construction site from paddy filed of local people has not been made - Sign board for occupational safety is wrong specification (Figure Appendix 3) - Waste soil has not been transported promptly, still stored at construction site (Figure Appendix 3) - Road surface has not been cleaned and sprayed water to reduce dust for road section going through construction site (Figure Appendix3) - There is no fence to separate construction works from road and paddy field of local people (Figure Appendix 3) - Minutes has not been made to verify road surface status before construction for section going through construction site 26 Package 14 Monitoring the implementation of environmental management plan for the

32 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name 4 Chua Tong pumping station 5 Lien Nghia pumping station 6 Cau Dua pumping station 7 Doan Thuong pumping station 8 Co Ngua pumping station 9 My Dong pumping station 10 Nghi Xuyen pumping station Pending issues in the fifth monitoring - Temporary fence for separating construction site from residential area has not been made - The sign of wall cracking and separating between road and local people s house adjacent to construction site impacted by excavation of foundation (Figure Appendix 3) - The pending issues of the fourth monitoring have not been overcome such as: Did not make construction sign board at construction area of management house (field side). This is area of high density of population and high traffic volume - Recycle bins and mobile toilets at construction site for workers have not been provided - Dyke surface section going through construction site with falling waste soil during transportation has not been cleaned promptly (Figure Appendix 3) - Waste soilt has not been transported to dumping site (Figure Appendix 3) Lot A: - Temporary fence for separating construction site from residential area and agricultural area has not been made Lot B: - The pending issues of the second and the third monitoring have not been overcome thoroughly like installing fence for warning danger when Thach Khoi canal is constructed (Figure appendix 3) - Landslide of local irrigation canal occured at Thach Khoi canal (distance of 300m from People s Committee office of Doan Thuong commune toward Hai Duong city), by dredged canal. Impact on cultivation of farmer due to lack of irrigation water (Figure Appendix 3) has not been commenced - Labour protection for workers in working hours has not been fully equipped - Waste soil has not been promptly transported and still stored at construction site (Figure appendix 3). - Workers who poured concrete have not fully worn labour protection in working hours (Figure appendix 3). - Dyke cut for construction of culvert under dyke has been licensed with document no. 2111/UBND-KT1 dated 22/11/ 2013 of People s 27 Package 14 Monitoring the implementation of environmental management plan for the

33 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub project s name Pending issues in the fifth monitoring Committee of Hung Yen province. In which, construction is regulated to finish before 30/4/ for flood protection. However, due to much rain, contractor has not filled to return dyke to original altitude (+11,83m) - Safety staff to monitor construction safety has not been assigned - Excavated soil has not been removed to dumping site - Occupational safety for workers has not been trained 3.4 Analysis results of environmental samples in the fifth monitoring According to regulation, taking samples to evaluate environmental quality is conducted 2 times/ year in monitoring time in March and November. Thus, in the fifth monitoring, additional taking samples have been implemted at sub projects which have not been fully taken samples in 2nd monitoring in 2013 because construction has not been commenced. Numbers of analysed samples in the fifth monitoring include: 3 surface water samples and 4 air samples. Consultant surveyed sampling locations; Describle weather conditions, surrounding environment landscape of sampling location (dust level, vibration, noise and emission resources...), flow state; Describle the factors which affect environmental quality such as: construction activities, people s living activities, traffic...); Sampling method, sample preservation, sample analysis in laboratory and assessment method for environmental quality comly with Vietnam s regulations (QCVN): - For air quality: dust is assessed based on QCVN 05: 2009/BTNMT, noise assessment is based on QCVN 26: 2010/BTNMT, vibration assessment is based on QCVN 27: 2010/ BTNMT. - Surface water quality assessment is based on QCVN 08: 2008/BTNMT Analysis results of air samples a) Describe the location of air sampling Air samples were taken on 5/5/ to 7/5/ in weather condition of slight sunny, no wind. Location description of air sampling is in Table 3.8. Table 3. 8: Description of air sampling location No. Symbol Sampling location 1 HP2-KK3 Nhat Trai pumping station 2 HP2-KK5 Lien Nghia pumping station Site description in the fifth monitoring Sampling location at construction site near road. Workers were processing steel at construction area of pumping house, less dust Sampling location at construction site, far from road.workers were processing steel at construction area of pumping house, less 28 Package 14 Monitoring the implementation of environmental management plan for the

34 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage 3 HP2-KK8 Co Ngua pumping station 4 HP2-KK10 Nghi Xuyen pumping station dust. Sampling location at construction site, no construction activities and no dust Sampling location at construction site, far from road, in sampling time.workers were pouring concrete of culvert under dyke, no dust. b- Analysis results of air sample The analysis results of air sample quality (Table 3.1, Appendix 3) showed that the parameters of noise, vibration and dust at taking sample location are below the allowable value accordance with QCVN 05:2009, QCVN 26:2010. activities did not impact on air environment quality because of processing steel and pouring concrete and there is no transportation means, At Co Ngua sub project, there is no construction activities. However, at sampling location of Nhat Trai pumping station sub project, dust concentration is 0.28 mg/m3 (approximate allowable value in QCVN 05:2009) because contractor did not regularly spray water road surface. Thus, construction contractor need to pay attention on dust mitigation measures to avoid its impact on environment Analysis results of surface - water sample in the fifth monitoring a- Describle the location of surface - water sampling Surface - water samples were taken from 5/5/ to 7/5/ in weather condition of slight sunny, no wind. The description of surface water sampling is in table 3.9. Table 3. 9: Description of surface - water sampling location No. Symbol Sampling location 1 HP2- NM3 Lien Nghia pumping station 2 HP2- NM6 Co Ngua pumping station 3 HP2-NM7 Nghi Xuyen pumping station Site description in the fifth monitoring - Taking sample in Dong Que river near pumping station s construction, wrokers were cutting steel for constructing pumping house in sampling time. - No flow, dark green water, slight ordour, less garbage - Taking water sample at Co Ngua pumping station, no construction activities in sampling time. - No flow, brown water colour, slight smell, less garbage. - Taking sample in Cuu An river near excavation of foundation position, no construction activities in sampling times. - No flow, green water colour, slight smell, no garbage, much weeds. 29 Package 14 Monitoring the implementation of environmental management plan for the

35 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage b- Analysis results of surface water sample The analysis results of surface water quality of the fifth monitoring are listed in table 3.2 and Appendix 3; comparison between appendixs and figures from3.1 to 3.6 shows that: - At sampling location of Lien Nghia pumping station sub project (HP2-NM3): COD, NH + - 4, NO 2 are the main pollutants. COD concentration is 32.6 mg/l exceeding irrigation water standard 1.09 times; NH + 4 (0.96 mg/l) concentration exceeds 1.92 times; NO - 2 (0,05 mg/l) concentration exceeds 1.25 times. According to the obsevation of consultant and locality s feedback, water quality at sampling location has been mainly polluted from residential area, construction activities did not impact on river water quality. - At sampling location of Co Ngua pumping station sub project (HP2-NM6): there are 3 concentration parameters excced standards including: SS (59.32 mg/l) exceeds 1.19 times, NH 4 + (0.78 mg/l) exceeds 1.56 times and NO 2 - (0.06 mg/l) exceeds 1.5 times. These poll;utions must be caused by domestic wastewater of residential area living along river because during sampling time there is no construction activities at construction site. - At sampling location of Nghi Xuyen pumping station sub project (HP2-NM7): there are 4 indicators exceeding limited value at column B1 QCVN 08:2008 including: SS (52.16 mg/l); COD (42.18 mg/l), NH (1.46 mg/l), NO 2 (0.08 mg/l) exceed allowable standard representively 1.04 times; 1.21 times; 1.01 times and 1.28 times. activities have not impacted on surface water quality because of far from water resources. River water has been polluted due to impact of domestic wastewater of residential area living along river. DO (mg/l) HP2-NM3 HP2-NM6 HP2-NM7 DO (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu SS (mg/l) HP2-NM3 HP2-NM6 HP2-NM7 SS (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu Figure 3.1: DO concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.2: SS concentration in surface water at monitoring location HP2 the fifth monitoring 40 15,5 COD (mg/l) BOD5 (mg/l) 15 14, HP2-NM3 HP2-NM6 HP2-NM7 13,5 HP2-NM3 HP2-NM6 HP2-NM7 COD (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu BOD5 (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu Figure 3.3: COD concentration in surface water at monitoring location HP2 the fifth monitoring Figure 3.4: BOD5 concentration in surface water at monitoring location HP2 the fifth 30 Package 14 Monitoring the implementation of environmental management plan for the

36 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage monitoring NH4+ (mg/l) 1,2 1 0,8 0,6 0,4 0,2 0 HP2-NM3 HP2-NM6 HP2-NM7 NH4+ (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu NO2- (mg/l) 0,07 0,06 0,05 0,04 0,03 0,02 0,01 0 HP2-NM3 HP2-NM6 HP2-NM7 NO2- (mg/l) QCVN 08:2008 B1 Kí hiệu mẫu Figure 3.5: NH 4 + concentration in surface water at monitoring location HP2 the fifth monitoring 3.5 Synthesing results of the fifth monitoring Figure 3.6: NO 2 - concentration in surface water at monitoring location HP2 the fifth monitoring The pending issues in the fifth monitoring, implementation responsibility and implementation time are synthesized in Table Package 14 Monitoring the implementation of environmental management plan for the

37 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub - project Pending issues and recommendation 1 Phu My - Set up wheel washing station at entrance point of construction site to mitigate dust 2 Kenh Vang II - Provide more recycle bins and 4 mobile toilets at construction site for workers - Make fence to separate construction works from paddy field of local people - Replace occupational safety sign board according specification at construction - Transport waste soil according regulation 3 Nhat Trai - Regularly spray water on road surface for section going through construction site to mitigate dust 4 Chua Tong - Cover material and waste soil transportation means - Install construction sign board as well as sign light at night - Make fence to separat construction works from paddy field of local people Need to make fence separating construction works from residental area Table 3. 10: Synthesis of the fifth monitoring Agency/individual take responsibility contractor of Phu My sub - project contractor of Kenh Vang I sub - project contractor of Nhat Trai sub - project contractor of Chua Tong sub - project Supervision/ monitoring Bac Ninh PMU with support of construction supervision consultant and environmental monitoring consultant Bac Ninh PMU with support of construction supervision consultant and environmental monitoring consultant Bac Ninh PMU with support of construction supervision consultant and environmental monitoring consultant Hung Yen PMU with support of construction supervision consultant and environmental monitoring consultant Time 5/ 5/ 5/ 15/5/ 32 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

38 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub - project Pending issues and recommendation Fully compensate the damage for household after construction is finished (if any) Agency/individual take responsibility contractor of Chua Tong sub - project Supervision/ monitoring Hung Yen PMU and CPO Time when construction finished - Install warning sign board for people especially for children about deep holes at construction site - Set up wheel washing station at entrance point of construction site to mitigate dust contractor of Chua Tong sub - project Hung Yen PMU with support of construction supervision consultant and environmental monitoring consultant 5/ 5 Lien Nghia Install sign board at construction area of pumping house ( filed side ) contractor of Lien Nghia subproject Hung Yen PMU with support of construction supervision consultant and environmental monitoring consultant 5/ 6 Cau Dua - Transport waste soil according regulation -Clean falling roack, soil during transportation construction contractor of Cau Dua sub project Hai Duong PMU with support of construction supervision consultant and environmental monitoring consultant 6/ 7 Doan Thuong Make fence to separate construction works from residential area and agricultural production area - contractor of lot A Doan Thuong sub - project Hai Duong PMU with support of construction supervision consultant and environmental monitoring consultant 15/5/ - Speed up construction progress to return road surface in front of school and Doan Thuong s People s Committee office. - Immediately make protection fence contractor of lot B Doan Thuong sub - project Hai Duong PMU with support of construction supervision consultant and environmental monitoring consultant 15/5/ 33 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

39 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub - project Pending issues and recommendation during construction of Thach Khoi canal to ensure safety for traffic users - Set up wheel washing station at entrance point of construction site to mitigate dust - Build temporary pumping station for irrgation water supply for whole agricultural area which have been affected by landslide of local irrgation canal (currently lack of irrgation water) 8 Co Ngua Sent EMP report, information of construction progress to People s Committee of Van Giang commune and Division of Natural Resources and Environment ofninh Giang district 9 My Dong Transport excavated soilt to dumping site as regulation 10 Nghi Xuyen -Clean leaked rock, soil during transportation - Fully equip labour protection for workers during construction time Assign staff to monitor construction safety issue and train occupational safety for workers Agency/individual take responsibility Supervision/ monitoring PMU of Hai Duong Environmental monitoring consultant PMU of Hai Duong Environmental monitoring consultant contractor of My Dong sub - project contractor of My Dong sub - project contractor of Nghi Xuyen sub - project BHH s PMU with support of construction supervision consultant and environmental monitoring consultant BHH s PMU with support of construction supervision consultant and environmental monitoring consultant CPO with support of construction supervision consultant and environmental monitoring consultant Time 15/5/ 10/5/ 15/5/ 10/5/ From1/5/ 34 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

40 The fifth monitoring report Components 2 and rehabilitation of Bac Hung Hai irrigation and drainage No. Sub - project Pending issues and recommendation Return dyke section which is cut for construction of culvert under dyke befor rainy season Agency/individual take responsibility contractor of Nghi Xuyen sub - project Supervision/ monitoring CPO with support of construction supervision consultant and environmental monitoring consultant Time 6/ 11 All sub - project Fully equip labour protection for workers during construction time Periodical medical examination for workers at construction site need to be implemented (6 months/ times) contractor of Nghi Xuyen sub - project All construction contractors CPO with support of construction supervision consultant and environmental monitoring consultant CPO with support of construction supervision consultant and environmental monitoring consultant 10/5/ 10/5/ 35 Package 14 Monitoring the implementation of environmental management plan for the whole project - Project Strengthening water management and irrigation systems

41 4.1 Conclusion CHAPTER 4: CONCLUSION AND RECOMMENDATION Achieved results - contractors have collaborated with local authorities and PMU in resolving arsing problems. activities have not much impacted on environment, society in region. The sub projects which are assessed well implematation of EMP include: Phu My, Kenh Vang II, Lien Nghia and Nghi Xuyen. - supervision consultant has fully recorded and submitted monitoring forms to PMUs of sub projects. They have given fully and exactly feedback the implemtation of mitigation measures for environmental impact, occupational safety, traffic and arising problems at construction site - People s Commitee of communes in project area have taken right their responsibility to monitor community, regularly inspect, give feedback to PMU about construction s impact on environment, society. They support PMUs and construction contractors to manage worker and resolve arising problems - Regarding construction s impact on environmental quality, based on analysis results, there has not significantly impacted on air quality and surface water environment in region Pending issues - PMU of Co Ngua pumping station sub project has not sent EMP report and construction progress of package to People s Committee of Van Giang commune - contractor have not overcome completely recommendations of Environmental monitoring consultant in the previous monitoring and recommendatios of the Mission of ADB (Table 3.10). the pending issues are following: + Environmental sanitation : Sub projects of Cau Dua, Phu My have not fully provided recycle bins and mobile toilets at construction site; Sub projects of Chua Tong, Doan Thuong have not set up wheel washing station at entrance point of construction site; Nhat Trai sub project has not regularly sprayed water on road surface;sub- projects of My Dong and Nghi Xuyen have not transported excavated soil to dumping site as regulations. + Occupational safety: fence for separating construction works from residential area and production area is not available( sub-projects of Phu My, Kenh Vang, Chua Tong and Doan Thuong); Warning sign board for deep holes at construction site has not been available (Chua Tong sub project); Labour protection for workers during construction time has not fully equipped( sub projects of My Dong and Nghi Xuyen); Workers has not been trained for occupational safety ( Nghi Xuyen). All construction contractors have not implemented periodical medical examination for workers at construction site (6 months/ time). + Traffic safety: Nhat Trai sub project has not installed construction sign board as well as sign light at night + Community safety: Nhi Xuyen sub project has not returned dyke to origional altitute (before cutting dyke to construction culvert under dyke) - For construction supervision consultant of Doan Thuong sub project (lot B) and Chua Tong sub - project in case of arsing problems did not fill in the form no.2( in case of arising problems) 36 Package 14 Monitoring the implementation of environmental management plan for the

42 4.2. Recommendations - For PMUs of sub projects need measures to force construction contractor into implementing recommendations and implementation time for regulations in table 3.10 and minutes have been made while on site inspection (appendix 4). PMU of Doan Thuong sub project need to collaborate with local authorities and construction contractor of lot B in order to thoroughly resolve environmental consultant s recommendations in previous monitorings and recommendations of The Mission (ADB), pending issues should not be extented that causing upset for local people. - For construction contractor need to overcome the pending issues of the previous monitoring, the fifth monitoring and the Mission of ADB (according to table 3.10). - For construction supervision consultant, beside filling in form no. 1, monitor the implementation of recommendations in the previous monitoring; arising problems need to be filled in form no.2 and promptly reflect to PMU, especially for construction supervision consultant for sub projects of Doan Thuong, Chua Tong and My Dong - People s Committee of Doan Thuong commune need to promptly reflect the pending issues of construction contractor, avoid extending the pending issues Plan for next 6 months monitoring The next monitoring plan of Environmental monitoring consultant will be implemented in August and November with the following contents: - Implement on site inspection - Synthesize monitoring forms of construction supervision consultant - Implement community based monitoring - Implement sampling to evaluate environmental quality 37 Package 14 Monitoring the implementation of environmental management plan for the

43 APPENDIX Appendix 1: Location of sub - projects Appendix 2: Some photos in the fifth monitoring Appendix 3: Analysis results of environmental samples Appendix 4: The fifth monitoring minutes and list of community consultation Appendix 5: The monitoring forms 38 Package 14 Monitoring the implementation of environmental management plan for the

44 Appendix 1: Location of sub - projects Figure 2.1: Location of Phu My sub - project Figure 2.2: Location of Kenh Vang II sub - project Figure 2.3: Location of Nhat Trai sub - project Figure 2.4: Location of Chua Tong sub - project Figure 2.5: Location of Lien Nghia sub - project Figure 2.6: Location of Cau Dua sub - project 39 Package 14 Monitoring the implementation of environmental management plan for the

45 Figure 2.7: Location of Doan Thuong sub - project Figure 2.8: :Location of Co Ngua sub - project Figure 2.9: Location of My Dong sub - project Figure 2.10: Location of Nghi Xuyen sub - project 40 Package 14 Monitoring the implementation of environmental management plan for the

46 Appendix 2: Some photos in the fifth monitoring Figure 3.1: There was no fence separating construction site from paddy field of people Phu My sub - project Figure 3.2: Workers did not wear labour protection in working hours - Phu My sub - project Figure 3.3: Sketchy sign board Kenh Vang II sub - project Figure 3.4: Waste soil has not been transported to dumping site Kenh Vang II sub-project Figure 3.5: Road section going through construction site was dirty Nhat Trai sub - Figure 3.6: There was no fence separating construction site from paddy field of people 41 Package 14 Monitoring the implementation of environmental management plan for the

47 project Nhat Trai sub - project Figure 3.7: Sign of crack between yard and pavement Chua Tong sub - project Figure 3.8: Sign of crack between road and house Chua Tong sub - project Figure 3.9: Dyke surface going through construction site was dirty because of falling rock, soil Cau Dua sub - project Figure 3.10: Waste soil was gathered at construction site, it has not transported to dumping site as regulation Cau Dua sub - project Figure 3.11: There was no protection barrier and sign board when Thach Khoi canal has been constructed with section going through school at Lot B Doan Thuong sub - project Figure 3.12: Location of collapsed irrigation canal Doan Thuong sub - project (Lot B) 42 Package 14 Monitoring the implementation of environmental management plan for the

48 Figure 3.13: Waste soil was gathered at construction site and has not transported to dumping site My Dong sub - project Figure 3.14: Workers who were pouring concrete did not wear fully labour protection Nghi Xuyen sub - project Figure 3.15: Taking air sample - Nghi Xuyen sub - project Figure 3.16:Authority leader speeched at meeting between consultant group and My Dong sub project 43 Package 14 Monitoring the implementation of environmental management plan for the

49 Appendix 3: Analysis results of environmental samples 1. Phú Mỹ PS 2. Liên Nghĩa PS 3. Nghi Xuyên PS 4. Chùa Tổng PS 5. Kênh Vàng II PS 6. Nhất Trai PS Figure 3.1: Diagram of sampling locations in the fifth monitoring 44 Package 14 Monitoring the implementation of environmental management plan for the

LIST OF CONSTRUCTION MATERIALS COMPANIES IN VIETNAM

LIST OF CONSTRUCTION MATERIALS COMPANIES IN VIETNAM LIST OF CONSTRUCTION MATERIALS COMPANIES IN VIETNAM 1 COSEVSO 19 - Cement Company / Midland Construction Corporation Add: Hoa Khuong Commune, Hoa Vang District, Da Nang City Phone: 84-511-378 0329 Fax:

More information

ANNEX 6 PUBLIC CONSULTATION

ANNEX 6 PUBLIC CONSULTATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Environmental Assessment (EA) A6.1. Objective and Methodology A6.2. Identification of

More information

The Current State of River Basins in Vietnam Pollution and Solution

The Current State of River Basins in Vietnam Pollution and Solution The Third WEPA International Forum on Water Environmental Governance 23-24 October 2008, Malaysia The Current State of River Basins in Vietnam Pollution and Solution Hoang Duc Hanh 1, Nguyen The Dong 2

More information

Overview of Water Environmental Pollution in Vietnam

Overview of Water Environmental Pollution in Vietnam Overview of Water Environmental Pollution in Vietnam Nguyen Thi Hue Institute of Environmental Technology (IET), Vietnamese Academy of Science and Technology(VSAT). 18-Hoang Quoc Viet R., Caugiay distr.,hanoi,vietnam

More information

Briefing on Drought on Mekong Delta

Briefing on Drought on Mekong Delta 2016/SOM3/EPWG/016 Agenda Item: 9.3 Briefing on Drought on Mekong Delta Purpose: Information Submitted by: Viet Nam 10 th Emergency Preparedness Working Group Meeting Lima, Peru 15-16 August 2016 THE 10

More information

VIET NAM LOSSES CAUSED BY TYPICAL DISASTERS FROM 1978 TO 2005 TYPICAL DISASTERS IN VIET NAM ECONOMIC LOSS RECORDED FROM

VIET NAM LOSSES CAUSED BY TYPICAL DISASTERS FROM 1978 TO 2005 TYPICAL DISASTERS IN VIET NAM ECONOMIC LOSS RECORDED FROM VIET NAM Việt Nam is located at the Southeast of Asia, with 333. km 2 of the total natural area and 32km of coastline. Population: 84 million (24 s statistics) Population density: 226 capitas/km2 Urban

More information

Lessons Learned: NAMA development in Vietnam

Lessons Learned: NAMA development in Vietnam Lessons Learned: NAMA development in Vietnam Dr. Huynh Thi Lan Huong Director of Climate Change Research Center Institute of Meteorology, Hydrology and Environment Ministry of Natural Resources and Environment,

More information

Title Action Plan toward Effective Flood Hazard Mapping in My Country

Title Action Plan toward Effective Flood Hazard Mapping in My Country Title Action Plan toward Effective Flood Hazard Mapping in My Country JICA region focused training course on flood hazard mapping Sep 2006 LAI TUAN ANH Division of Geodesy Department of Planning and Management

More information

University of Agriculture & Forestry - Hue University. Châu Thành court, Cai Lậy court & Sắc Tứ pagoda, Tiền Giang

University of Agriculture & Forestry - Hue University. Châu Thành court, Cai Lậy court & Sắc Tứ pagoda, Tiền Giang No. PN Project title Implementing agency 1 6 2 8 3 10 4 18 5 22 6 34 7 40 8 44 9 47 Reducing greenhouse gases by promoting the use of "Advanced cooking table" model Development of environment-friendly

More information

Ex-ante Project Evaluation

Ex-ante Project Evaluation Ex-ante Project Evaluation 1. Name of project Country: Socialist Republic of Vietnam Name of project: Hai Phong City Environmental Improvement Project (II) L/A signing date: March 31, 2009 Loan amount:

More information

Oxfam America (VIE 034/07): System of Rice Intensification -- Advancing Small Farmers in Mekong Region

Oxfam America (VIE 034/07): System of Rice Intensification -- Advancing Small Farmers in Mekong Region DRAFT Oxfam America (VIE 034/07): System of Rice Intensification -- Advancing Small Farmers in Mekong Region Background Under a 3-year grant, SRI promotion is being implemented through a partnership among

More information

REGULATIONS OF ENVIRONMENTAL MANAGEMENT OF THE CONSTRUCTION PROJECTS Dr. Pham Van Bo Vice president Academy of Managers for Construction and Cities Ministry of Construction - Vietnam List of abbreviations

More information

# Group STT COMPANY / ORGAN BUSINESS SCOPES / OBLIGATIONS. Vietnam Chamber of Commerce and Industry

# Group STT COMPANY / ORGAN BUSINESS SCOPES / OBLIGATIONS. Vietnam Chamber of Commerce and Industry # STT COMPANY / ORGAN BUSINESS SCOPES / OBLIGATIONS 1 Vietnam Chamber of Commerce and Industry www.vcci.com.vn E-commerce, Business training programs, Trade & Investment promotion, Linking enterprises

More information

CURRENT STATUS OF WATER-RELATED SANITATION CONDITIONS IN HUE CITY, VIETNAM

CURRENT STATUS OF WATER-RELATED SANITATION CONDITIONS IN HUE CITY, VIETNAM CURRENT STATUS OF WATER-RELATED SANITATION CONDITIONS IN HUE CITY, VIETNAM Pham Khac Lieu, D.Eng. Department of Environmental Science College of Sciences, Hue University, Vietnam Contents 1. Hue city at

More information

Research and Proposal on the Irrigation Modernization Framework in Red River Delta, Vietnam

Research and Proposal on the Irrigation Modernization Framework in Red River Delta, Vietnam Research and Proposal on the Irrigation Modernization Framework in Red River Delta, Vietnam Vu Hai Nam Abstract The purpose of this research to develop an Irrigation Modernization Frame (IMF) for irrigation

More information

Drought Situations and Management in Vietnam

Drought Situations and Management in Vietnam Drought Situations and Management in Vietnam Background: In Vietnam, drought is one of the most frequent natural disasters, only after flood and storm, and has been becoming more severe due to the impact

More information

VIKING PROFILE VIKING PROFILE

VIKING PROFILE VIKING PROFILE VIKING PROFILE Hanoi - 2015 GENERAL INFORMATION Business name in Vietnamese Business name in English: Abbreviated name: Address of head office Công Ty Cổ Phần Viking Việt Nam VIKING VIET NAM JOINT STOCK

More information

Statement at East Asian and Middle-South American Conference on Environmental Industry

Statement at East Asian and Middle-South American Conference on Environmental Industry Mr. LÊ VĂN DỤC Vice Director Department of Construction Hanoi, Vietnam Statement at East Asian and Middle-South American Conference on Environmental Industry Subject: Sanitation of Water Source and Treatment

More information

THE CURRENT STATE OF WATER SUPPLY AND DRAINAGE SYSTEMS INSIDE THE CIVIL BUILDINGS IN DANANG CITY

THE CURRENT STATE OF WATER SUPPLY AND DRAINAGE SYSTEMS INSIDE THE CIVIL BUILDINGS IN DANANG CITY THE UNIVERSITY OF DANANG UNIVERSITY OF SCIENCE AND TECHNOLOGY THE CURRENT STATE OF WATER SUPPLY AND DRAINAGE SYSTEMS INSIDE THE CIVIL BUILDINGS IN DANANG CITY KICK-OFF SYMPOSIUM ON REDUCING GHG THROUGH

More information

JOBS AROUND THE WORLD

JOBS AROUND THE WORLD PILE DRIVERS AND THE U.S. SUPREME COURT: A STORIED FOUNDATION OF CONSTRUCTION LAW EST. 1984 THE INTERNATIONAL PILE DRIVERS, DEEP FOUNDATIONS & MARINE CONTRACTOR S MAGAZINE PILE BUCK PRESENTS 2013 VOLUME

More information

Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871)

Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871) losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Vietnam Second Transmission and Distribution Project

More information

Vietnamese Real Estate - The potential market

Vietnamese Real Estate - The potential market Vietnamese Real Estate - The potential market Currently, Vietnam is one of the fastest growing countries in the world. The investment trend is showing positively as the government continues to support

More information

Performance Assessment of Irrigation Schemes and Water Pollution Issues Raised in the Red River, Vietnam

Performance Assessment of Irrigation Schemes and Water Pollution Issues Raised in the Red River, Vietnam International Journal of Environmental Protection and Policy 2018; 6(1): 1-8 http://www.sciencepublishinggroup.com/j/ijepp doi: 10.11648/j.ijepp.20180601.11 ISSN: 2330-7528 (Print); ISSN: 2330-7536 (Online)

More information

PPP in Vietnam- Current Status & Prospect VFCEA. Prof. Dr(sr). PHAM HONG GIANG Vietnam Federation of Civil Engineering Associations

PPP in Vietnam- Current Status & Prospect VFCEA. Prof. Dr(sr). PHAM HONG GIANG Vietnam Federation of Civil Engineering Associations PPP in Vietnam- Current Status & Prospect VFCEA Prof. Dr(sr). PHAM HONG GIANG Vietnam Federation of Civil Engineering Associations PPP What is it? It s a cooperative venture between the government & the

More information

CURRICULUM VITAE NAME NGUYEN HAI HOA. Living address: House N0. 24B, Group I, Tan Xuan, Xuan Mai town, Chuong My

CURRICULUM VITAE NAME NGUYEN HAI HOA. Living address: House N0. 24B, Group I, Tan Xuan, Xuan Mai town, Chuong My CURRICULUM VITAE NAME NGUYEN HAI HOA Sex: Male. Day of birth: 02 February 1974. Place of birth: Phuc Tho district, Ha Noi. Living address: House N0. 24B, Group I, Tan Xuan, Xuan Mai town, Chuong My District,

More information

Factors influencing the Vietnam Provincial Governance and Public Administration Performance Index (PAPI)

Factors influencing the Vietnam Provincial Governance and Public Administration Performance Index (PAPI) Factors influencing the Vietnam Provincial Governance and Public Administration Performance Index (PAPI) By: Le Van Chien HCM National Academy of Politics and Public Administration, Vietnam This paper

More information

Initial Environmental Examination (Final Review) MFF 0054-VIE: Water Sector Investment Program Tranche 2

Initial Environmental Examination (Final Review) MFF 0054-VIE: Water Sector Investment Program Tranche 2 Initial Environmental Examination (Final Review) Project Number: 41456-033 April 2012 MFF 0054-VIE: Water Sector Investment Program Tranche 2 This initial environmental examination is a document of the

More information

Climate Change: Impacts and Opportunities for the Red River Basin and Delta, Vietnam

Climate Change: Impacts and Opportunities for the Red River Basin and Delta, Vietnam Climate Change: Impacts and Opportunities for the Red River Basin and Delta, Vietnam Do Minh Duc*, Mai Trong Nhuan, Pham Van Cu * Associate Professor, Dr. Eng. Hanoi University of Science Content Introduction

More information

Meeting Vietnam s Energy Demands in a Sustainable Way

Meeting Vietnam s Energy Demands in a Sustainable Way TRUNG SON HYDROPOWER PROJECT Meeting Vietnam s Energy Demands in a Sustainable Way Photo by: World Bank 1 Photo by: Mai Ky/World Bank, 2012 OVERVIEW Trung Son Hydropower Project (TSHPP) is a US$411.57

More information

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water The diversion works for the Cua Dat CFRD in Vietnam Michel Ho Ta Khanh, Dinh Sy Quat, Prof Pham Hong Giang VNCOLD No 95/10 Chua Boc Street Dong Da District Hanoi Vietnam Abstract The Cua Dat CFRD is constructed

More information

To: AGRICULTURAL PROJECTS MANAGEMENT BOARD LOW CARBON AGRICULTURAL SUPPORT PROJECT. SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness

To: AGRICULTURAL PROJECTS MANAGEMENT BOARD LOW CARBON AGRICULTURAL SUPPORT PROJECT. SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness AGRICULTURAL PROJECTS MANAGEMENT BOARD LOW CARBON AGRICULTURAL SUPPORT PROJECT No: /DANN-LCASP Re: Report on project implementation progress to the Mid-term Mission SOCIALIST REPUBLIC OF VIETNAM Independence

More information

The matter of environmental pollution in domestic waterway transportation in Vietnam

The matter of environmental pollution in domestic waterway transportation in Vietnam The matter of environmental pollution in domestic waterway transportation in Vietnam X. Phuong Nguyen, V. Huong Dong, P. Q. Phong Nguyen Ho Chi Minh University of Transport No.2, D3 Road, Binh Thanh District,

More information

Assessment of Flood Hazard in Hanoi City

Assessment of Flood Hazard in Hanoi City VNU Journal of Earth and Environmental Sciences, Vol. 29, No. 1 (2013) 26-37 Assessment of Flood Hazard in Hanoi City Nguyễn Hiệu *, Đỗ Trung Hiếu, Đặng Kinh Bắc, Đoàn Thu Phương * Faculty of Geography,

More information

Environmental and Social Monitoring Report. Viet Nam: Central Regions Rural Water Supply and Sanitation Sector Project

Environmental and Social Monitoring Report. Viet Nam: Central Regions Rural Water Supply and Sanitation Sector Project Environmental and Social Monitoring Report Semi-Annual Report December 2016 Viet Nam: Central Regions Rural Water Supply and Sanitation Sector Project WATER SUPPLY AND SANITATION OF TIEN LOC COMMUNE, HAU

More information

MID TERM REPORT. Completion of Pilot Investment Project Improved Cook Stove Use in Viet Nam. Revision: 01. Submitted to: Landell Mills Ltd.

MID TERM REPORT. Completion of Pilot Investment Project Improved Cook Stove Use in Viet Nam. Revision: 01. Submitted to: Landell Mills Ltd. EPRO CONSULTING JSC CENTRE FOR SOCIAL INNITIATIVES PROMOTION MID TERM REPORT Completion of Pilot Investment Project Improved Cook Stove Use in Viet Nam Revision: 01 Submitted to: Landell Mills Ltd. Hanoi

More information

INFORMATION ON PFR2 SUB-PROJECTS:

INFORMATION ON PFR2 SUB-PROJECTS: INFORMATION ON PFR2 SUB-PROJECTS: Appendix 1: Da Nang Appendix 2: Hue Appendix 3: Hai Phong Appendix 4: Buon Ma Thuot Appendix 5: Quang Tri The second tranche of the Multitranche Financing Facility (MFF)

More information

CONSUMPTION OF FOODSTUFF FROM ANIMAL ORIGIN AND CONSUMERS UNDERSTANDING ON FOOD SAFETY: CASE STUDY IN RED RIVER DELTA

CONSUMPTION OF FOODSTUFF FROM ANIMAL ORIGIN AND CONSUMERS UNDERSTANDING ON FOOD SAFETY: CASE STUDY IN RED RIVER DELTA CONSUMPTION OF FOODSTUFF FROM ANIMAL ORIGIN AND CONSUMERS UNDERSTANDING ON FOOD SAFETY: CASE STUDY IN RED RIVER DELTA Vu Dinh Ton 1, Pham Kim Dang 2 et al 1 Center for Interdisciplinary Research on Rural

More information

Viet Nam: Comprehensive Socioeconomic Urban Development Project in Viet Tri, Hung Yen and Dong Dang

Viet Nam: Comprehensive Socioeconomic Urban Development Project in Viet Tri, Hung Yen and Dong Dang Environmental Monitoring Report Inception Report July 2015 Viet Nam: Comprehensive Socioeconomic Urban Development Project in Viet Tri, Hung Yen and Dong Dang Prepared by Environment Analyzing and Technique

More information

Vietnam Agriculture- Pillar of Economy

Vietnam Agriculture- Pillar of Economy AGRICULTURE AND RURAL DEVELOPMENT MINISTRY DEPARTMENT OF CROPS PRODUCTION Vietnam Agriculture- Pillar of Economy Tran Xuan Dinh Over View Vietnam located in the southeastern of Indochina, the distance

More information

REPORT ON ENVIRONMENTAL MONITORING

REPORT ON ENVIRONMENTAL MONITORING VIETNAM INFRASTRUCTURE DEVELOPMENT AND FINANCE INVESTMENT JOINT STOCK COMPANY REPORT ON ENVIRONMENTAL MONITORING THE EXPRESSWAY HANOI- HAl PHONG PROJECT The 6th monitoring of locations of packages EX-2.

More information

Irrigation and Flood Protection Rehabilitation Project (Loan 1259-VIE[SF]) in Viet Nam

Irrigation and Flood Protection Rehabilitation Project (Loan 1259-VIE[SF]) in Viet Nam Project Performance Audit Report PPA:VIE 25019 Irrigation and Flood Protection Rehabilitation Project (Loan 1259-VIE[SF]) in Viet Nam September 2005 Operations Evaluation Department Asian Development Bank

More information

SOME SOLUTIONS TO RESPOND CLIMATE CHANGE FOR THE MEKONG DELTA, VIET NAM

SOME SOLUTIONS TO RESPOND CLIMATE CHANGE FOR THE MEKONG DELTA, VIET NAM 18 SOME SOLUTIONS TO RESPOND CLIMATE CHANGE FOR THE MEKONG DELTA, VIET NAM Nguyen Thuy Lan CHI 1, Phan DAO 1, Miroslav KYNCL 2 1 Trường Đại học Tôn Đức Thắng, Việt Nam e-mail: nguyenthuylanchi@tdt.edu.vn

More information

The role of UNICEF in Rural Water Supply & Environmental Sanitation

The role of UNICEF in Rural Water Supply & Environmental Sanitation The role of UNICEF in Rural Water Supply & Environmental Sanitation ADB Journalists Workshop on Water Policy Issues in Vietnam 9-12 November 2003 The views expressed in this paper are the views of the

More information

environment assessment subproject: in dong gia-hai duong

environment assessment subproject: in dong gia-hai duong Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E1060, vol. 6 Ministry of Agriculture and Rural Development Project Preparation Unit

More information

COOPERATION IN HOCHIMINH CITY

COOPERATION IN HOCHIMINH CITY DEPARMENT OF NATURAL RESOURCES AND ENVIRONMENT DONRE & INTERNATIONAL CITY TO CITY COOPERATION IN HOCHIMINH CITY TOKYO, JAPAN 1 st 3 rd FEB., 2012 MAP OF HO CHI MINH CITY HOCHIMINH CITY - Overview - Geographical

More information

environment assessment subproject: in chi lang bac-hai duong

environment assessment subproject: in chi lang bac-hai duong Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E1060, vol. 5 Ministry of Agriculture and Rural Development Project Preparation Unit

More information

BASELINE STUDY FOR COMMUNITY BASED WATER MANAGEMENT PROJECT (CWMPs)

BASELINE STUDY FOR COMMUNITY BASED WATER MANAGEMENT PROJECT (CWMPs) Inclusion Project/Mekong Water Governance Program Vietnam BASELINE STUDY FOR (CWMPs) TECHNICAL REPORT Prepared by Le Anh Tuan - Huynh Vuong Thu Minh Dinh Diep Anh Tuan - Nguyen Thi Phuong Thao Can Tho,

More information

DEPARTMENT OF AGRICULTURE AND RURAL DEVELOPMENT THANH HOA PROVINCIAL PROJECT MANAGEMENT UNIT ENVIRONMENTAL MANAGEMENT PLAN

DEPARTMENT OF AGRICULTURE AND RURAL DEVELOPMENT THANH HOA PROVINCIAL PROJECT MANAGEMENT UNIT ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DEPARTMENT OF AGRICULTURE AND RURAL DEVELOPMENT THANH HOA PROVINCIAL PROJECT MANAGEMENT

More information

Vietnam s Water Sector Outlook and Engineering Opportunities. Planned Expenditure Per Annum up to 2020

Vietnam s Water Sector Outlook and Engineering Opportunities. Planned Expenditure Per Annum up to 2020 Vietnam s Water Sector Outlook and Engineering Opportunities Water Sector Targets Water supply and sanitation (WS&S) sector seeks investments to total 2.5% of GDP by 2020 Planned Expenditure Per Annum

More information

If member of farmer group. 5c. Do you desire a recommendation for a rice field you will manage in selected month? O No O Yes

If member of farmer group. 5c. Do you desire a recommendation for a rice field you will manage in selected month? O No O Yes 1 Rice Crop Manager Mekong Delta Beta Version 1. Where is the field? O Mekong Delta O Red River Delta If Mekong Delta, Rice Crop Manager is for use with modern rice varieties and Tai Nguyen rice. It is

More information

Decentralized Trade Support Services for Strengthening the Competitiveness of Vietnamese SMEs

Decentralized Trade Support Services for Strengthening the Competitiveness of Vietnamese SMEs Decentralized Trade Support Services for Strengthening the Competitiveness of Vietnamese SMEs NGUYỄN T. MINH THÚY Deputy National Program Director 6/2016 Content Introduction Figures Highlighted/Lessons

More information

POTENTIAL IMPACTS OF THE SUPER SEA DYKE (SSD) AT RACH GIA BAY ON THE VALUES OF MANGROVES IN KIEN GIANG PROVINCE - MEKONG DELTA, VIETNAM

POTENTIAL IMPACTS OF THE SUPER SEA DYKE (SSD) AT RACH GIA BAY ON THE VALUES OF MANGROVES IN KIEN GIANG PROVINCE - MEKONG DELTA, VIETNAM 1 POTENTIAL IMPACTS OF THE SUPER SEA DYKE (SSD) AT RACH GIA BAY ON THE VALUES OF MANGROVES IN KIEN GIANG PROVINCE - MEKONG DELTA, VIETNAM Dr. Trinh Thi Long SOUTHERN INSTITUTE OF WATER RESOURCES RESEARCH

More information

PROCUREMENT PLAN. Consulting Services

PROCUREMENT PLAN. Consulting Services PROCUREMENT PLAN Basic Data Project Name: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Project : 46391-001 Approval : 3161/8286 Country: Viet Nam, Socialist Republic of Executing Agency:

More information

ASSESSMENT OF SALINITY INTRUSION IN THE RED RIVER UNDER THE EFFECT OF CLIMATE CHANGE

ASSESSMENT OF SALINITY INTRUSION IN THE RED RIVER UNDER THE EFFECT OF CLIMATE CHANGE ASSESSMENT OF SALINITY INTRUSION IN THE RED RIVER UNDER THE EFFECT OF CLIMATE CHANGE Presented by NGUYEN Trung Viet Water Resources University, Vietnam March 2-4, 2011 Introduction Red River System is

More information

Land Acquisition and Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report Land Acquisition and Resettlement Due Diligence Report Document stage: Draft Project number: July 2017 IND: Kolkata Environmental Improvement Investment Program Construction of Sewage Treatment Plant at

More information

The KUND System: A sustainable way to ensure drinking water supply in the rural Mekong Delta under flood conditions

The KUND System: A sustainable way to ensure drinking water supply in the rural Mekong Delta under flood conditions A Project Proposal under the theme of Infrastructure development under increased flooding/storm intensity The KUND System: A sustainable way to ensure drinking water supply in the rural Mekong Delta under

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

VIE: Power Transmission Investment Program Multi- Tranche Financing Facility Tranche 3

VIE: Power Transmission Investment Program Multi- Tranche Financing Facility Tranche 3 Initial Environmental Examination December 2015 VIE: Power Transmission Investment Program Multi- Tranche Financing Facility Tranche 3 Subproject: 500kV My Tho Duc Hoa Transmission Line Prepared by National

More information

PART-III. Present Condition and Pre-F/S level Development Plan for Each Irrigation Scheme

PART-III. Present Condition and Pre-F/S level Development Plan for Each Irrigation Scheme PART-III Present and Pre-F/S level Development Plan for Each Irrigation Scheme Location of District N CENTRAL SULAWESI SINJAI DISTRICT SOUTHEAST SULAWESI Kassi PARE-PARE UJUNG PANDANG SOUTH SULAWESI PROVINCE

More information

Japanese ODA Loan. Ex-Ante Evaluation

Japanese ODA Loan. Ex-Ante Evaluation Japanese ODA Loan Ex-Ante Evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Haor Flood Management and Livelihood Improvement Project Loan Agreement: June 16, 2014 Loan

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

Prepared by Ministry of Mahaweli Development and Environment for the Asian Development Bank.

Prepared by Ministry of Mahaweli Development and Environment for the Asian Development Bank. Initial Environmental Examination April 2016 Project Number: 47381-002 SRI: Proposed Raising of the Minipe Anicut and Rehabilitation of the Minipe Left Bank Canal Project in Kandy District Addendum to

More information

SFG2372 REV. CORRIDOR 3 Day Ninh Co junction Canal and crossing bridge (DNC) ESIA Environment and Social Impact Assessment Executive Summary

SFG2372 REV. CORRIDOR 3 Day Ninh Co junction Canal and crossing bridge (DNC) ESIA Environment and Social Impact Assessment Executive Summary Public Disclosure Authorized THE SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT OF WATERWAYS SFG2372 REV Public Disclosure Authorized NORTHERN DELTA TRANSPORT DEVELOPMENT PROJECT

More information

Lower Mattagami River Project

Lower Mattagami River Project Lower Mattagami River Project 2016 Canadian Consulting Engineering Awards Project summary Ontario Power Generation s (OPG) Lower Mattagami River (LMR) project, its largest hydro project in 40 years, added

More information

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT AND INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT PAPER ON A PROPOSED ADDITIONAL LOAN

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT AND INTERNATIONAL DEVELOPMENT ASSOCIATION PROJECT PAPER ON A PROPOSED ADDITIONAL LOAN Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: PAD1724 INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT AND INTERNATIONAL DEVELOPMENT

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Public Disclosure Copy Date ISDS Prepared/Updated: 04-Apr-2014

More information

Vietnam Baseline Perspective. Key issues and trends in the Mekong Delta

Vietnam Baseline Perspective. Key issues and trends in the Mekong Delta Vietnam Baseline Perspective Key issues and trends in the Mekong Delta Structure of presentation National macro-economics - Total national GDP trend - Key growing sector - Drivers of the trend - Government

More information

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani DESCRIPTION OF

More information

Development of a study area Case study: Day River basin. H.P. Hagedooren L.M. Keyzer

Development of a study area Case study: Day River basin. H.P. Hagedooren L.M. Keyzer Development of a study area Case study: Day River basin H.P. Hagedooren L.M. Keyzer 2 Development of a study area Case study: Day River Basin By H.P. Hagedooren L.M. Keyzer in partial fulfilment of the

More information

D DAVID PUBLISHING. 2. The Approach and Methodology. 1. Introduction

D DAVID PUBLISHING. 2. The Approach and Methodology. 1. Introduction Journal of Environmental Science and Engineering B 5 (2016) 161-166 doi:10.17265/2162-5263/2016.04.001 D DAVID PUBLISHING Experimental Model to Treat BOD 5, COD in Wastewater by Eichhornia Crassipes Raft,

More information

VALUE CHAIN INITIATIVES FOR DRAGON FRUIT (PITAYA) MARKET DEVELOPMENT

VALUE CHAIN INITIATIVES FOR DRAGON FRUIT (PITAYA) MARKET DEVELOPMENT VALUE CHAIN INITIATIVES FOR DRAGON FRUIT (PITAYA) MARKET DEVELOPMENT John Malcolm Campbell 1 Nguyen Van Hoa 2, Nguyen Minh Chau 2, and Nguyen Huu Hoang 2 1 New Zealand Institute of Plant and Food Research

More information

CDM IMPLEMENTATION IN VIETNAM and OPPORTUNITIES FOR INVESTMENT

CDM IMPLEMENTATION IN VIETNAM and OPPORTUNITIES FOR INVESTMENT The Kyoto Mechanism - Japan Carbon Investors Forum Tokyo, 14-15 March 2006 CDM IMPLEMENTATION IN VIETNAM and OPPORTUNITIES FOR INVESTMENT Tran Thi Minh Ha, Director General International Cooperation Department

More information

Presentation -- Three Gorges Dam (TGD) on the Yangtze River

Presentation -- Three Gorges Dam (TGD) on the Yangtze River Presentation -- Three Gorges Dam (TGD) on the Yangtze River Alex Buchanan Rudy Koester Ali Elahi Michael Jane It is in the Yichang city, Hubei province in China C O N S T R U T I O N S I T E Brief Introduction

More information

Domestic Biogas in Africa

Domestic Biogas in Africa Domestic Biogas in Africa Lessons from SNV & HIVOS biogas programs in Vietnam, Tanzania & Burkina Faso Bruno Verbist With inputs from Vu Dinh Ton Idrissa Kaboré Hezron Makundi Introduction Biogas: Popular

More information

VIETNAM NATIONAL COAL-MINERAL INDUSTRIES. Dr. Trần Xuân Hòa CEO OF VINACOMIN

VIETNAM NATIONAL COAL-MINERAL INDUSTRIES. Dr. Trần Xuân Hòa CEO OF VINACOMIN VIETNAM NATIONAL COAL-MINERAL INDUSTRIES HOLDING CORPORATION LTD. COAL EXPORT AND THE FUTURE IN VIETNAM Dr. Trần Xuân Hòa CEO OF VINACOMIN 1 Brief Introduction to VINACOMIN Vietnam National Coal-Mineral

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

CLIMATE CHANGE AND FLOOD RISK IN THE MEKONG DELTA ADAPTATION AND COEXISTENCE IN FLOOD-PRONE RICE AREA

CLIMATE CHANGE AND FLOOD RISK IN THE MEKONG DELTA ADAPTATION AND COEXISTENCE IN FLOOD-PRONE RICE AREA CLIMATE CHANGE AND FLOOD RISK IN THE MEKONG DELTA ADAPTATION AND COEXISTENCE IN FLOOD-PRONE RICE AREA Hideto Fujii Japan International Research Center for Agricultural Sciences 1-1 Ohwashi, Tsukuba, Ibaraki

More information

Adaptation to Sea Level Rise in the Vietnamese Mekong River Delta: Should a Sea Dike be Built? Vo Thanh Danh

Adaptation to Sea Level Rise in the Vietnamese Mekong River Delta: Should a Sea Dike be Built? Vo Thanh Danh Adaptation to Sea Level Rise in the Vietnamese Mekong River Delta: Should a Sea Dike be Built? Vo Thanh Danh March 2012 Comments should be sent to: Vo Thanh Danh, School of Economic and Business Administration,

More information

institutional framework in Vietnam

institutional framework in Vietnam Mangrove-related policy and institutional framework in Vietnam MFF -FAO Final workshop for Income for Coastal Communities for Mangrove Protection Project December 2016 Dr. Mai Sy Tuan, MFF Vietnam NCB

More information

NORTHERN DELTA TRANSPORT DEVELOPMENT PROJECT (NDTDP) CORRIDOR 3 Day Ninh Co junction Canal and crossing bridge (DNC)

NORTHERN DELTA TRANSPORT DEVELOPMENT PROJECT (NDTDP) CORRIDOR 3 Day Ninh Co junction Canal and crossing bridge (DNC) Public Disclosure Authorized THE SOCIALIST REPUBLIC OF VIETNAM MINISTRY OF TRANSPORT PROJECT MANAGEMENT UNIT OF WATERWAYS SFG2325 REV Public Disclosure Authorized NORTHERN DELTA TRANSPORT DEVELOPMENT PROJECT

More information

Lady and Gentlemen I am Bui Duc Dien and from Viet Nam, I am very happy to this forum here. Now, I will read summary report about bioenergy

Lady and Gentlemen I am Bui Duc Dien and from Viet Nam, I am very happy to this forum here. Now, I will read summary report about bioenergy Lady and Gentlemen I am Bui Duc Dien and from Viet Nam, I am very happy to this forum here. Now, I will read summary report about bioenergy development of Viet Nam 1. Biomass technology in Vietnam: Now

More information

Secondary Evaluation Report on Dai Ninh Hydropower Project (1)(2)(3) in the Socialist Republic of Vietnam

Secondary Evaluation Report on Dai Ninh Hydropower Project (1)(2)(3) in the Socialist Republic of Vietnam Secondary Evaluation Report on Dai Ninh Hydropower Project (1)(2)(3) in the Socialist Republic of Vietnam Takako Haraguchi, International Development Associates Profile of the Project for the Primary Evaluation

More information

Water & Wastewater Industry in Vietnam

Water & Wastewater Industry in Vietnam Water & Wastewater Industry in Vietnam Assoc. Prof. Dr. Viet-Anh Nguyen Director, Institute of Environmental Science and Engineering (IESE), Hanoi University of Civil Engineering. Head of Science and Technology

More information

Your reliable investment location

Your reliable investment location DEEP C INDUSTRIAL CLUSTER Your reliable investment location Hanoi Haiphong Expressway Tan Vu Lach Huyen Road & Bridge Lach Huyen Deep Sea Port New Cat Bi International Airport Dinh Vu Industrial Zone Overview

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan 1.Name of the Project Country: The Republic of Indonesia Project: Upper Citarum Basin Flood Management Sector Loan Loan Agreement: March 28,

More information

MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT (MARD) CENTRAL PROJECT OFFICE (CPO) VIETNAM MANAGING NATURAL HAZARDS PROJECT (VN-Haz Project)

MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT (MARD) CENTRAL PROJECT OFFICE (CPO) VIETNAM MANAGING NATURAL HAZARDS PROJECT (VN-Haz Project) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT (MARD) CENTRAL PROJECT OFFICE (CPO) VIETNAM

More information

Industrial Estate Market Update A challenging 2012 & 2013 Outlook. Presented by: Hieu Le, Senior Manager, Industrial & Logistics Services March, 2013

Industrial Estate Market Update A challenging 2012 & 2013 Outlook. Presented by: Hieu Le, Senior Manager, Industrial & Logistics Services March, 2013 Industrial Estate Market Update A challenging 2012 & 2013 Outlook Presented by: Hieu Le, Senior Manager, Industrial & Logistics Services March, 2013 CBRE Market View March 2013 AGENDA A LOOK BACK A CHALLENGING

More information

Building the Market Chain Coconut in Vietnam

Building the Market Chain Coconut in Vietnam Building the Market Chain Coconut in Vietnam Midrib baskets: The art of giving In Vietnam, special occasions like the Tet Festival and Mother s Day are not complete without the traditional gift-giving.

More information

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2008. Study on the Improvement Project of Rail Freight

Study on Private-Initiative Infrastructure Projects. in Developing Countries in FY2008. Study on the Improvement Project of Rail Freight Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2008 Study on the Improvement Project of Rail Freight Transport for Hanoi - Hai Phong in the Socialist Republic of Viet

More information

ADB TA8102-VIE: Promoting Climate Resilient Rural Infrastructure in Northern Viet Nam ICEM TR-18 Slope Protection Designs and Specifications

ADB TA8102-VIE: Promoting Climate Resilient Rural Infrastructure in Northern Viet Nam ICEM TR-18 Slope Protection Designs and Specifications 1 This report is one of a series of technical reports prepared by ICEM as part of the Asian Development Bank (ADB) capacity development technical assistance (CDTA) project Promoting Climate Resilient Rural

More information

Development of Climate-Related Risk Maps and Adaptation Plans (Climate Smart MAP) for Rice Production in Vietnam s Mekong River Delta

Development of Climate-Related Risk Maps and Adaptation Plans (Climate Smart MAP) for Rice Production in Vietnam s Mekong River Delta Development of Climate-Related Risk Maps and Adaptation Plans (Climate Smart MAP) for Rice Production in Vietnam s Mekong River Delta Working Paper No. 220 CGIAR Research Program on Climate Change, Agriculture

More information

ENVIRONMENTAL IMPACTS ASSESSMENT REPORT

ENVIRONMENTAL IMPACTS ASSESSMENT REPORT SOCIALIST REPUBLIC OF VIETNAM BENTRE PROVINCIAL PEOPLE'S COMMITTEE BEN TRE WATER MANAGEMENT PROJECT (B-SWAMP) ENVIRONMENTAL IMPACTS ASSESSMENT REPORT 2016 SOCIALIST REPUBLIC OF VIETNAM BENTRE PROVINCIAL

More information

Climate Change on the Vietnam, Mekong Delta

Climate Change on the Vietnam, Mekong Delta Climate Change on the Vietnam, Mekong Delta Expected impacts and adaptations Toru Konishi World Bank East Asia Infrastructure Overview 1. The Mekong and the Mekong Delta 2. Expected Climate Change Impacts

More information

ROLE OF ODA IN PROMOTING INTEGRATED COASTAL ZONE MANAGEMENT IN VIETNAM THE CASE OF THUA THIEN HUE PROVINCE

ROLE OF ODA IN PROMOTING INTEGRATED COASTAL ZONE MANAGEMENT IN VIETNAM THE CASE OF THUA THIEN HUE PROVINCE ROLE OF ODA IN PROMOTING INTEGRATED COASTAL ZONE MANAGEMENT IN VIETNAM THE CASE OF THUA THIEN HUE PROVINCE Prepared by Vu Canh Toan 1 Hanoi, September 2012 ABBREVIATIONS ADB: AusAid: CCA: DANIDA: DARD

More information

HO CHI MINH CITY ENVIRONMENTAL SANITATION PHASE 2

HO CHI MINH CITY ENVIRONMENTAL SANITATION PHASE 2 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized THE PEOPLE S COMMITTEE OF HO CHI MINH CITY ENVIRONMENT SANITATION PROJECT INVESTMENT

More information

Current Status of Energy in Viet Nam: Tran Thuc

Current Status of Energy in Viet Nam: Tran Thuc Current Status of Energy in Viet Nam: Tran Thuc 1. Overview Located in SE Asia, Country has a long shape and long coastline Area: about 330,000 km 2, Population: more than 83 million people Climate and

More information

Environmental and Social Review Summary. Hoi Xuan Hydropower Project

Environmental and Social Review Summary. Hoi Xuan Hydropower Project Environmental and Social Review Summary Hoi Xuan Hydropower Project This Environmental and Social Review Summary (ESRS) is prepared by MIGA staff and disclosed prior to the date on which MIGA s Board of

More information

This guide only applies for sewer assets up to and including 225mm diameter.

This guide only applies for sewer assets up to and including 225mm diameter. INTRODUCTION This guide only applies for sewer assets up to and including 225mm diameter. These guidelines (subject to change) provide an outline of the requirements which need to be considered when planning

More information

Water diversions in the lower Mekong basin current status and issues

Water diversions in the lower Mekong basin current status and issues Water diversions in the lower Mekong basin current status and issues Mekong river basin Nguyen Nhan QUANG River Basin Management expert 1 2 Longitudinal Profile of Mekong from source to sea Brief on the

More information