COLUMBIA & COWLITZ RAILWAY BRIDGE #7 SPIN FIN PILES IN PRACTICE
|
|
- Ralf Heath
- 6 years ago
- Views:
Transcription
1 COLUMBIA & COWLITZ RAILWAY BRIDGE #7 SPIN FIN PILES IN PRACTICE Todd Nottingham, P.E. Peratrovich, Nottingham & Drage Inc. 811 First Avenue, Suite 260 Seattle, Washington, Phone: , Fax: Mike Hartley, P.E. Peratrovich, Nottingham & Drage Inc. 811 First Avenue, Suite 260 Seattle, Washington Phone: , Fax:
2 ABSTRACT COLUMBIA & COWLITZ BRIDGE #7 - SPIN FIN PILES IN PRACTICE The Columbia & Cowlitz Railway Bridge #7 was severely damaged by fire in the summer of 2001, effectively destroying 900-feet of the structure. The bridge was part of the railway line that transported a significant amount of Weyerhaeuser timber product. The loss of the bridge forced Weyerhaeuser to absorb alternate transportation costs and affected the employment of many; therefore, it was important to quickly repair the bridge. Weyerhaeuser solicited bids from a number of firms to reconstruct the bridge under a design/build scenario on November 2, with bids due November 30, The team of Hurlen Construction and Peratrovich, Nottingham & Drage, Inc. was selected and was awarded a contract on December 17, The bridge was substantially complete and allowed traffic on March 20, 2002, an elapsed time of just 93 days. The bridge structure crosses a paved county road, elevated approximately 35-feet above the ground and is on a curve and grade. Soil conditions at the site consisted of loose to medium dense alluvial deposits over bedrock at various depths. The pile foundation for the bridge utilized spin fin tips, which substantially increases both compressive and tensile strengths of the piles. The increased capacity allowed longer spans and fewer piles and simplified longitudinal load resistance, thus saving time and reducing costs for the project. Key words: Railroad, Bridge, Spin Fin Pile Word count: 2,866
3 COLUMBIA & COWLITZ BRIDGE #7 - SPIN FIN PILES IN PRACTICE INTRODUCTION Overview The original Columbia & Cowlitz Railway Bridge #7 consisted of a combination of steel and timber construction. A 700-foot timber trestle section of the bridge was entirely destroyed and another 200-feet of bridge was severely damaged during a fire in the summer of 2001 (figure I). The loss of the bridge significantly affected the operations of Weyerhaeuser Company who owns and operates the line which is used to transport wood products in the area. The need to replace the bridge became apparent relatively soon after the fire when alternate transportation means failed to provide a cost affective solution. Weyerhaeuser hired the design/build team of Hurlen Construction and Peratrovich, Nottingham & Drage, Inc. (PND) through a design/build bidding process to reconstruct the C&C Railway Bridge #7 (figure II). The team was selected from a group of other highly qualified teams because it offered several cost saving solutions and provided the most timely construction schedule. Following the bid process that lasted from November 2 to November 30, 2001, Weyerhaeuser proceeded to negotiate with Hurlen/PND to provide an accelerated schedule. On December 17, 2001, a notice to proceed was issued with a substantial completion requirement of March 20, 2002.
4 Structure Description The selected concept featured relatively long spans using rolled steel girders. The girders were supported by two pile moment frame bents that utilized the driven pile as the column. The 700- foot main bridge replacement was divided into three independent bridge sections with a central four-pile bent utilizing batter piles that resisted longitudinal loads (figure III & IV). An open deck with timber ties and standard rail sections completed the superstructure. Reduced project time and lower cost was achieved by minimizing the number of driven piles, reducing the number of field installed components, and maximizing the use of locally available and existing materials (piles and pile caps). The design of Bridge #7 followed AREMA (American Railway Engineering and Maintenance of Way Association) guidelines. Design loading included standard E80 live load, wind, seismic, impact, and longitudinal loads. This bridge, with a 14-degree horizontal curve, needed to resist a significant centrifugal loading component. The selected 50-foot girder spans were the maximum that could be achieved with the available rolled steel girders and still meet roadway and other clearances. The bridge girders along the curved section were kept straight, but were positioned to provide optimal load balancing between all girders.
5 Project Implementation Work began concurrently on preliminary design, surveys, geotechnical investigation, and material acquisition for long lead items. Close coordination between all parties was necessary. Thirty-inch diameter pipe piles were initially selected based upon the anticipated height of the bridge. A mill order was not possible because of the long lead time. Existing material was found and put on hold in sufficient quantity to match preliminary pile estimates. However, four different pile wall thicknesses and grades of steel were required to meet the anticipated demand. Heavier wall piles and higher grade materials were used on pile bents that were subject to higher loads such as the longitudinally braced bents. Thinner wall piles were used at shorter spans and end bents which were subject to smaller loads. Ordered pile lengths were established after the geotechnical investigation was completed with sufficient quantity reserved for overruns. Final completion of pile driving showed a 7% overrun based upon preliminary pile estimates. Surveyors were mobilized to the site upon notice to proceed and continued to work through the holiday season. A final topographic survey was completed in late December that provided enough information to perform detailed design. The survey effort identified a significant quantity and variety of utilities along the west side of the road that apparently extended outside of the right of way. Based upon the locates, it was determined that special pile spacing would be needed in that area. Pile locations were established in the field and potholes were dug (soil vacuumed out to expose utility without damage) to verify that utility conflicts were avoided. The pile bent configuration at bent 8 was designed to allow the pile cap to span the majority of the utilities with one pile actually threaded between a power line and a water line.
6 A field geotechnical investigation performed by PND was initiated and completed by December 23, The program consisted of drilling four holes across the proposed alignment. Variable conditions were encountered, but generally consisted of variable depths of sand and silt over bedrock. Bedrock depths in some areas were excessive and it was determined that the pile foundation would need to be designed as friction piles in most instances. The steel superstructure for the bridge required a mill rolling for the main girders that met grade and charpy requirements. The two largest domestically rolled beam shapes were picked to be used on the project. The largest, W40 x 324, was used to span the main roadway while the other W40 x 230 was used throughout the remaining bridge. The initial mill order for the girders was placed on December 15, 2001 for the estimated steel lengths and rolling scheduled on January 2, The steel was rolled and trucked to Jesse Engineering in Tacoma, Washington where it was fabricated and sub-assembled to ensure the desired curvature and fit-up were obtained. Field construction began on January 15, 2002, with completion of demolition of the damaged trestle bridge (figures V & VI) followed by pile driving. Piles were driven with an impact hammer to desired pile capacities. Spin-fin pile tips were utilized on piles that were subject to tension loads located at longitudinal force resisting bents (figure VII). Tie placement, rail installation (figure VIII), and completion of the superstructure all went smoothly and allowed the first train to cross the bridge on March 20, 2002 (figure IX).
7 SPIN FIN PILE General Highly loaded tensile capacity piles, often over 100-tons, are being used with a greater frequency and in more diverse applications. Conventional piles are often unable to resist these tension loads. An innovative pile dubbed the Spin Fin with tension characteristics superior to those of usual piles does not usually require increasing the pile length, or require heavier driving equipment. A spin fin pile is a pipe with steel fins welded at a batter, giving the pile a screw-like appearance and characteristics at the pile tip. Fins can be readily shop or field fabricated and attached. Because of their unique deformation characteristics, these piles allow substantial pile movement without catastrophic failure. The result is a more predictable and reliable tension pile. End bearing or pile compression is also markedly improved. Spin fin piles were originally utilized in 1984 for a bulkhead tension tieback for a coal loading system, following in-house testing of model piles in Subsequent full scale model testing under a grant from the State of Alaska and Federal Highway Administration ( Use of Spin Fin Piles for Increased Tension Capacity, unpublished report for the State of Alaska Department of Transportation and Public Facilities; Campbell, Christopherson, Nottingham, 1987) and Caltrans ( Colton Interchange Spin Fin Pile Tension Load Test; Nottingham, Unpublished, 1991) established initial design parameter for sandy and silty soils. Practical installation and testing in a variety of structures have progressed from 1984 with thousands of spin fin piles now in place.
8 Pile Configuration Spin-fin piles differ from conventional piles in tip configuration only. Spin-fin pile connection to substructure components must usually be made to develop the pile strength and to resist torsion. Strong details at this interface assure development of the redundant aspects (i.e. large overload and energy absorbing capacity) of the spin fin piles. Conventional interface details such as short concrete embedment or penetration through piles by footing reinforcing steel are not acceptable. Spin-Fin Pile Action Spin-fin piles develop strength in two primary ways. Basically, this strength is derived through the pile skin friction as is a conventional pile, plus modified end bearing on the projected fin area resulting from fin/soil interface. Figure X shows an idealized tension pile. A compression pile would act similarly, except end bearing and shaft friction would be reversed. End bearing is engaged when the pile attains maximum skin friction, usually after a short primarily elastic movement for tension piles. Typical load deflection curves are graphically described in figures XI and XII. As pile movement continues, spin fin piles continue to gain strength in comparison to smooth piles. P u = P O + P f = Pile ultimate capacity P f =(k f N+c) A e, Where:
9 P f = Pile ultimate frictional capacity k f = A constant N = Standard split-spoon value for soil strata c = Cohesion A e = Effective pile friction area P O = A O k O d e, Where: P O = Pile ultimate spin-fin capacity k O = A constant that varies for compressive or tensile capacity and soil types A O = Projected plan area of fins d e = Depth to fin layer Limited by maximum or minimum depth. Note: Minimum depth must be adequate to develop a conical soil mass with greater weight than the pile tension.
10 Pile Load Tests Spin fin pile load tests require some special features, specifically, the pile must be restrained against rotating. Since the pile drives with a rotating screw-like action, this characteristic must be resisted during testing to achieve accurate results. Tests generally follow ASTM Quick Load Tests Procedures, often times extended to failure. Testing has shown large strength gain by simply modifying the pipe pile tips with slanted steel plates. Results in similar soils show some variation due to fin size, pitch, length, and time elapsed to testing and driving, and other variables. Without going into lengthy discussion, the most critical spin fin characteristic is the guarantee of predictable performance. Conventional smooth friction pipe piles seem to fail rapidly once shaft friction resistance is exceeded and may even be extracted at decreasing load. On the other hand similar spin fin piles move with increasing load after frictional resistance is surpassed and seem to produce predictable failure patterns. The pile elastic limit should not be exceeded under operating conditions (i.e. no permanent set) which is normally less than the limit of the shaft friction or approximately ½-inch of load test deformation. However, unusual loads such as maximum contingency loads should not exceed pile resistance at some acceptable pile set such as 1-inch. Using this philosophy the structure will never exceed permanent set during operational conditions and will experience only limited deformation after contingency events.
11 Geotechnical Information The following discusses one driven pile that was installed at the Bridge #7 Bent 9 left vertical (Pile 9LV). This vertical pile was positioned in the middle third of the replacement trestle and was subject to various loadings that were significantly larger than other typical bents. A spin fin pile tip was installed on the pile (figure VII). Initial geotechnical work was completed in the early stages of the projects. Figure XIII shows a generalized soil profile and two partial drill logs adjacent to Pile 9LV. The logs indicated the near surface material to be soft clays and silts down to 20-feet. This is followed with a medium dense sand layer from 20 to 60-feet. A dense sand layer with gravel extends from 60-feet to bedrock which is greater than 130-feet below grade. Pile Loads Loads to Pile 9LV consist of various components including dead, live, longitudinal, and centrifugal. These loads are visually described in Figure III. These loads are combined as follows: Compression Primary: Secondary: Dead + Live = 330 kip Longitudinal = 250-kips
12 Tension Maximum tension load is minimal due to configuration for this pile with maximum anticipated tension load less than 50-kips. However, the adjacent batter pile (Pile 9LB) could see as much as 280-kips in tension. Pile Analysis As previously discussed, spin-fin pile capacity is derived from two components skin friction and a type of end bearing. Pile 9LV was driven with an initial length of 140-feet to an embedment of 130-feet. It is a 30- inch diameter pile with inch wall thickness equipped with an 8-plate spin fin. A pile driving log is shown in Figure XIV. The ultimate elastic skin friction component of the pile was estimated as follows: Depth Material properties Skin Friction 0-20 feet clay/silt C=500 psf 80-kips feet Sand friction = 30*25=750 psf 240 kips feet Sand/gravel friction = 35*25=875 psf 480-kips Total estimated skin friction 780-kips The estimated ultimate skin friction was confirmed after driving by two methods a modified ENR formula which estimated the pile capacity at 950-kips and also by a wave equation method which estimated the pile capacity at 900-kips.
13 The ultimate capacities for the pile for both tension and compression were calculated using the wave evaluation as the ultimate skin friction capacity, P f, and P o = A o K o D e for the bearing component. Ultimate Pile Compressive Capacity P UC = P OC + P f = 900+1,600 = 2,500 kips Ultimate Pile Tensile Capacity P UT = P Ot + P f = = 1,500 kips In hind sight, pile embedment depths could have been substantially reduced with estimated embedment 20 to 30 feet less than was actually installed for this pile. However, some conservatism was justified due to the speed of construction. CONCLUSION Bridge #7 has been in operation since March, Spin fin piles provided assurance that tensile and compressive capacities would be met on the project that standard smooth piles could not. The completed structure utilized a minimum number of piles that allowed for an accelerated construction schedule (figures XV & XVI).
14 REFERENCES 1. Nottingham, D., Spin Fin Pile Performance, International Conference on Design and Construction of Deep Foundations, Orlando, Florida December 6-8, 1994.
15 TABLES AND FIGURES Figures I. Original Bridge - Fire II. New Bridge III. Pile Cap 9 IV. Typical Batter Pile Bent V. Fire Damaged Bridge VI. Existing / Remaining Bridge VII. Spin Fin Pile Tip VIII. Steel Superstructure IX. First Crossing X. Pile Tension Load Action XI. Typical Compression Pile Test XII. Typical Comparative Repetitious Tension Pile Test XIII. Soil Profile XIV. Pile Driving Record XV. Product Crossing XVI. Finished Bridge
16 ORIGINAL BRIDGE FIRE FIGURE I
17 NEW BRIDGE FIGURE II
18 PILE CAP 9 FIGURE III
19 TYPICAL BATTER PILE BENT FIGURE IV
20 FIRE DAMAGED BRIDGE FIGURE V
21 EXISTING / REMAINING BRIDGE FIGURE VI
22 SPIN FIN PILE TIP FIGURE VII
23 STEEL SUPERSTRUCTURE FIGURE VIII
24 FIRST CROSSING FIGURE IX
25 PILE TENSION LOAD ACTION FIGURE X
26 TYPICAL COMPRESSION PILE TEST IN SAND FIGURE XI
27 TYPICAL COMPARATIVE REPITITIOUS TENSION PILE TEST FIGURE XII
28 SOIL PROFILE FIGURE XIII
29 Project: Columbia & Cowlitz Bridge #7 Project No: Pile Designation: 9LV Ground Elev.: +29-ft Pile Type: 30-Inch Diameter Tip Elev.: -101-ft Foreman: Terry McConnville Pile Wall Thickness: inches Cutoff Elev.: ft Vibratory Hammer Type: NA Pile Tip Type: Spin Fin Initial Length:140-ft Impact Hammer Type: ICE 120S Req. Comp. Cap.: 500-kips Final Length: 170-ft Rated Energy: 120,000 ft-lbs Req. Tensile Cap.: 100-kips Full Stroke: 12,000 10ft Penetration Blows/ Foot Blow/ Minute Est. Energy Pile Rotation Notes 1 to Soft driving not recorded to ft-kips 90 degree at 30-ft to ft-kip 180 degree at 70-ft Splice and redrive at 100-feet degree at 88-ft 100 to ft-kip ft-kip Reduced energy for final driving ft-kip ft-kip ft-kip ft-kip ft-kip final rotation not recorded PILE DRIVING RECORD (Condensed from original) FIGURE XIV
30 PRODUCT CROSSING FIGURE XV
31 FINISHED BRIDGE FIGURE XVI
OPEN CELL. (800) SWC 120. SWC Weld-on. Charts and Pictures courtesy of: 120 o
OPEN CELL The OPEN CELL bulkhead, used primarily on docks and similar structures, is a cellular flat sheet pile structure in which each cell s sheet piles are driven in the shape of a U when viewed from
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationConstruction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT
CHAPTER Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 19 By Dr. Ibrahim
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More informationDIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: GEOTECH ENTERPRISES, INC.
0 Most Widely Accepted and Trusted ICC ES Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3623 Reissued 04/2017 This report is subject to renewal 04/2018. DIVISION: 31 00 00 EARTHWORK
More informationFoundation Innovations Ensure Successful Bridge Replacement
COVER STORY Foundation Innovations Ensure Successful Bridge Replacement Rhode Island s new $163.7 million, 2,265 ft (690 m) long, fourlane Sakonnet River Bridge sits just south of the existing bridge in
More informationSUPPLEMENTAL TECHNICAL SPECIFICATION
July 14, 2015 HIGH STRAIN DYNAMIC LOAD TESTING OF DRILLED SHAFTS 1.0 GENERAL This work shall consist of performing high-strain dynamic testing using a drop weight loading system on a test drilled shaft
More informationUNDERPINNING A CRANE FOUNDATION
UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New
More informationContents. Tables. Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters. Foreword.
Tables x Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters xii xiv xvi xvi Foreword xviii 1 Introduction 1 1.1 Aims of the Manual 1 1.2 Eurocode
More informationRapid Axial Load Testing of Drilled Shafts
Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial
More informationHURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX B-2 FLOODWALL PILE ANALYSES EAST WALLS
HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX B-2 FLOODWALL PILE ANALYSES EAST WALLS Revised March 2015 Preliminary Flood Wall Pile Analysis
More informationINTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICE EVALUATION CRITERIA FOR
INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS UNIFORM EVALUATION SERVICE EVALUATION CRITERIA FOR HELICAL PILES FOR USE UNDER THE INTERNATIONAL RESIDENTIAL CODE EC027-2017 (Adopted November
More informationSPECIAL SPECIFICATION 4385 Railroad Bridge Construction
2004 Specifications CSJ 0912-71-622 SPECIAL SPECIFICATION 4385 Railroad Bridge Construction 1. Description. Construct Railroad bridges following the recommendations in the applicable Chapters of the current
More informationBi-Directional Static Load Testing of Drilled Shafts
Supplemental Technical Specification for Bi-Directional Static Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (01/18) 1.0 GENERAL This work shall consist of furnishing all materials, equipment,
More informationBijan Khaleghi, Ph, D. P.E., S.E.
0 Submission date: July, 0 Word count: 0 Author Name: Bijan Khaleghi Affiliations: Washington State D.O.T. Address: Linderson Way SW, Tumwater WA 0 INTEGRAL BENT CAP FOR CONTINUOUS PRECAST PRESTRESSED
More information1 Exam Prep Placing Reinforcing Bars Tabs and Highlights
1 Exam Prep Placing Reinforcing Bars Tabs and s These 1 Exam Prep Tabs are based on the CRSI Placing Reinforcing Bars Recommended Practices, 9 th Edition. Each 1 Exam Prep tabs sheet has five rows of tabs.
More informationITEM 404 DRIVING STEEL PILING
AFTER MARCH 1, 2012 ITEM 404 DRIVING STEEL PILING 404.1 Description. This Item shall govern the driving of steel piling. The piling shall be of the size and weight shown on the plans and shall be in accordance
More informationBRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.
BRIDGE DESIGN MANUAL UPDATES Jamie F. Farris, P.E. October 2015 Table of Contents 1 BDM Chapter 2 Limit States and Loads 2 BDM Chapter 3 Superstructure Design 3 BDM Chapter 4 Substructure Design 4 Questions
More informationSteel Railway Bridge Fatigue and the Evolution of Railway Car Loadings
1 Steel Railway Bridge Fatigue and the Evolution of Railway Car Loadings The Current State and Future Challenges of Railway Bridges Stephen M. Dick, PE, SE, Ph.D. Hanson Professional Services 2 Discussion
More informationDesign of Steel-Concrete Composite Bridges
Design of Steel-Concrete Composite Bridges to Eurocodes Ioannis Vayas and Aristidis Iliopoulos CRC Press Taylor & Francis Croup Boca Raton London New York CRC Press is an imprint of the Taylor & Francis
More informationSPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS PREFACE
SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS Standard ADOPTED 1939; ADVANCED TO STANDARD, 1945. PREFACE The specifications have been prepared on the basis that they will be used
More informationOFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION
Supplemental Specification 901-S-803-1 LFRD Driven Pile Specifications. DATE: May 24, 2010 OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION SUBJECT: LRFD Driven Pile Specifications
More informationOver the last decade, drilled and postgrouted micropile foundations have
Seismic Design of Micropile Foundation Systems Leo Panian, S.E., and Mike Korolyk, S.E. Over the last decade, drilled and postgrouted micropile foundations have come to be increasingly relied on for resisting
More informationADDENDUM No. 6. ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1
ADDENDUM No. 6 ITB No. 4424: W.R. Wheeler (Swift Run) Service Center PUD Non-motorized Improvements Phase 1 Due: June 9, 2016 at 2:00 p.m. (local time) The following changes, additions, and/or deletions
More informationImplementation of this Special Provision requires a complete understanding of the following documents:
VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR Quality Assurance/Quality Control (QA/QC) for the Construction of Deep Foundation Systems for Design-Build and PPTA Contracts November 10, 2009
More informationSTATNAMIC LOAD TESTING OF HIGH CAPACITY MARINE FOUNDATIONS
STATNAMIC LOAD TESTING OF HIGH CAPACITY MARINE FOUNDATIONS Mike Muchard, P.E., Applied Foundation Testing, Inc., Tampa, FL, USA STATNAMIC load testing augmented with embedded instrumentation has been successfully
More informationCase History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River
DEEP FOUNDATIONS 207 Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River W. Robert Thompson, III, 1 M.ASCE, P.E., Jeffrey R. Hill, 2 M.ASCE, P.E., and J. Erik Loehr,
More informationTesting Methods of Driven Piles on INDOT Demonstration Projects
66 Testing Methods of Driven Piles on INDOT Demonstration Projects by Firooz Zandi, P.E. Chief Geotechnical Engineer Division of Materials & Tests, I NDOT INTRODUCTION: This paper provides an overview
More informationDESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK
ABSTRACT DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK James Barron 1, P.E., Thomas Hattala 2, P.E.,
More informationUse of Grade 80 Reinforcement in Oregon
Use of Grade 80 Reinforcement in Oregon Craig Shike, PE Bridge Operations & Standards Managing Engineer PRESENTATION OUTLINE Material Properties of High Strength Reinforcement Recent Grade 80 Research
More informationLATITUDE FOR HANDLING LONGITUDINAL FORCES. By:
Small, Berry and Jenkins 1 LATITUDE FOR HANDLING LONGITUDINAL FORCES By: Gregory Small, P.Eng. UMA Engineering Ltd. 2540 Kensington Rd NW Calgary, AB T2N 3S3 Phone 403-270-9200 Fax 403-270-2865 Ronald
More informationSECTION DUCTILE IRON PILES
SECTION 31 66 13 DUCTILE IRON PILES PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS A. Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents. B.
More informationInterior Hangers. Application
Application Interior bridge deck hangers are typically fabricated using two heavy duty sheet metal end clips that have been electrically resistance welded to an appropriate sized wire or formed metal connecting
More informationNORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA
NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA PURPOSE AND SCOPE These criteria modify and supplement the applicable sections of the AREMA Manual of Recommended Practice in connection
More informationSection Steel H-Piling Tender No. [ ] Page 1
Tender No. [ ] Page 1 1.0 GENREAL 1.1 DEFINITIONS.1 Refusal is attained when the resistance to pile penetration for the last 150 mm of driving is not less than [ blows/mm] with a final set of [ blows]
More informationBridge articulation No. 1.04
Bridge articulation Scope This Guidance Note gives advice on the selection of the articulation arrangements, the choice of bearing types and dispositions of bearings, for bridges where relative movement
More informationRECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS
RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS Chris Nickel, P.E. LA DOTD Pavement & Geotechnical Services 2011 Louisiana Engineering Conference TOPIC OUTLINE Driven Piles Definitions and Data table
More informationDIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: HELICAL ANCHORS, INC BOONE AVENUE, NORTH MINNEAPOLIS, MINNESOTA 55428
0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-3982 Reissued 09/2017 This report is subject to renewal 09/2019. DIVISION: 31 00
More informationSEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2
ABSTRACT SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR Robert Small 1, Rob Jameson 2 Seismic Upgrade of the University Mound Reservoir North Basin included 542 micropiles with 1335 KN (300 kip) design capacity
More informationBi-Directional Static Load Testing of Driven Piles
Bi-Directional Static Load Testing of Driven Piles Paul J. Bullock, PhD Fugro Consultants Inc. Loadtest Bi-Directional Osterberg Cell Testing Specialized jack in pile uses bearing to mobilize side shear
More informationENGN 1380 Design Project
ENGN 1380 Design Project The Indy Residence Hall and Parking Garage at Brown University Knowledge District Campus Pikanstruction Inc. Arnold and Ives Street Providence, RI 02912 T 4018156955 pokemon@pikanstruction.edu
More informationSECTION 552 HELICAL ANCHORS AND HELICAL PILES
SECTION 552 HELICAL ANCHORS AND HELICAL PILES DESCRIPTION 552.01 This work pertains to furnishing and installing helical anchors and helical piles shown in the Contract in accordance with the Drawings
More informationSJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series
SJI Updates Expanded Load Tables for Noncomposite Joists / Joist Girders and Development of New Composite Joist Series SUMMARY David Samuelson Steel joists are growing in recognition as being a very economical
More informationDesigning for Longitudinal Force
AREMA Annual Technical Conference Structures Session Tuesday, September 19, 2006 KICC, Louisville, KY Designing for Longitudinal Force Design of Steel Bridges for Longitudinal Force John F. Unsworth, P.Eng.
More informationSAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS
SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS 1.0 DESCRIPTION This work shall consist of furnishing all materials and labor necessary for conducting an Osterberg Cell (O-cell)
More informationINNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT
INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT Tracy Brettmann, P.E., D.GE, Vice President, A. H. Beck Foundation Company, Houston, Texas, (713) 413-3800, tracy.brettmann@ahbeck.com
More informationWe have engaged Beacon Construction Consultants to act as the price estimate reviewer.
Stantec Consulting Ltd. 400-655 Tyee Road Victoria BC V9A 6X5 Tel: (250) 388-9161 Fax: (250) 382-0514 June 10, 2010 File: 1123-10987 (rev) City of Victoria #1 Centennial Square Victoria, BC V8W 1P6 Attention:
More informationTHE BRACE CONNECTION THE BOLTED OPTION FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING)
Comparative Study of Bolted versus Welded SCBF Connections Authors: Robert P. Krumpen III P.E., Bechtel Corporation, rpkrumpe@bechtel.com Dr. Peter J. Carrato P.E. S.E., Bechtel Corporation, pcarrato@bechtel.com
More information1970 s and. Site Location Map. and shed transform the. Gateway Project.
Bayview Gateway and Tulare Park Improvements Project August 2013 Page 2 of 10 Tulare Park Improvement Project Tulare Park is an existing 8,000 square foot park that is located within the Port s portion
More informationSUNSHINE SKYWAY BRIDGE
SUNSHINE SKYWAY BRIDGE Retrofit of the Post-Tensioned Precast Transition Pier Columns on the Sunshine Skyway Bridge Presented by: Antonio Ledesma, P.E. May 7, 2012 SUNSHINE SKYWAY BRIDGE, FLORIDA Presentation
More informationI-74 over the Mississippi River
I-74 over the Mississippi River Design and Construction of Arch Foundations 104 th Transportation and Highway Engineering Conference Presented by: Andrew J. Keaschall, PE, SE, Alfred Benesch & Company
More informationWELCOME TO THE PILE DRIVING INSPECTOR COURSE
Lesson 1 WELCOME TO THE PILE DRIVING INSPECTOR COURSE 1-1 Welcome to the Pile Driving Inspector Course. This is a course designed to assist students to understand the specifications and inspection practices
More informationStrain Limits for Concrete Filled Steel Tubes in AASHTO Seismic Provisions. PIs: Mervyn Kowalsky and James Nau RA: Nicole King
Strain Limits for Concrete Filled Steel Tubes in AASHTO Seismic Provisions PIs: Mervyn Kowalsky and James Nau RA: Nicole King Project Overview Seismic behavior of reinforced concrete filled steel pipe
More informationIntroduction to Structural Analysis TYPES OF STRUCTURES LOADS AND
AND Introduction to Structural Analysis TYPES OF STRUCTURES LOADS INTRODUCTION What is the role of structural analysis in structural engineering projects? Structural engineering is the science and art
More informationSensitivity Analysis of Rail-Structure Interaction Force Effects for Direct-Fixation. Bridges
Sensitivity Analysis of Rail-Structure Interaction Force Effects for Direct-Fixation Bridges Authors: Daniel Baxter, P.E., S.E. (Michael Baker Jr. Inc.), David Nemovitz, P.E. (Michael Baker Jr. Inc.) Number
More informationSeismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction. Bijan Khaleghi 1
Seismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction Bijan Khaleghi 1 Abstract Ductility of precast prestressed girder bridges can be achieved by proper detailing of pier
More informationBRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)
SPECIAL PROVISION August 31, 2009 PROJECT # S-R399(42) PROJECT # S-R399(59) PIN # 6697/7236 SECTION 03253S BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT) Add Section 03253S: PART
More information1. Cast-in-place concrete is specified in Section
SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record
More informationRehabilitation of Masonry Piers at Nipigon, Ontario
Rehabilitation of Masonry Piers at Nipigon, Ontario Daniel E. J. Adamson, P. Eng. Canadian Pacific Railway 2881 Alyth Road SE Calgary, AB Canada, T2G 5S3 Phone (403) 303-8835 Fax (403) 303-8830 ABSTRACT
More informationTECH FACTS. Formulas for Success Innovative Ways to Reinforce Slabs-On-Ground
TF 705-R-03 Formulas for Success Innovative Ways to Reinforce Slabs-On-Ground BACKGROUND With nearly a century of experience in designing slabs-on-ground, both with and without welded wire reinforcement
More informationABRAHAM LINCOLN BRIDGE
ABRAHAM LINCOLN BRIDGE PROJECT LOCATION: CONNECTING LOUISVILLE, KY WITH JEFFERSON, IN ACROSS THE OHIO RIVER. CATEGORY B: TRANSPORTATION PROJECT OWNER: KENTUCKY TRANSPORTATION CABINET COWI North America
More informationSteven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates
LA Transportation Conference: 10 Jan 2011 Drilled Shaft Foundations For Two Mississippi River Bridges in Louisiana Dan Brown and Associates Projects John James Audubon Bridge, St. Francisville New Construction
More informationProject Address: Name of Person Completing Form:
Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties
More informationThe designer shall also submit additional information required by the University as described and underlined below.
I. Structural Engineering Submissions The designer shall submit all information required by the State Construction Office (SCO) as described in the State Construction Manual Chapter 300 - Project Design
More informationStatement of Special Inspections Michigan Building Code 2012 (MBC 2012)
Gaines Charter Township 8555 Kalamazoo Ave SE Caledonia MI 49316 PH: 616 698-6640 Fax: 616 698-2490 www.gainestownship.org Building Department Statement of Special Inspections Michigan Building Code 2012
More informationDIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK
DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,
More informationStructural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)
Inspection of Fabricators (1704.2) Furnish inspection reports (1704.2.1) - Fabricators that have not been approved Provide a Certificate of Compliance (1704.2.2) - Approved Fabricators Steel Construction
More informationDIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: EMPIRE PIERS 2656 EAST HWY 47 WINFIELD, MO EVALUATION SUBJECT:
0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-4050 Issued 12/2017 This report is subject to renewal 12/2018. DIVISION: 31 00 00
More informationENGINEERED POWER SOLUTIONS
Date: May 2, 2017 Subject: To: From: Structural Overview of Earth Anchors For PV Ground Mounted Arrays Brian Boguess Nuance Energy Group, Inc. Matthew Gilliss Engineered Power Solutions (EPS) INTRODUCTION
More informationChapter 21 GEOTECHNICAL REPORTS
Chapter 21 GEOTECHNICAL REPORTS Final SCDOT GEOTECHNICAL DESIGN MANUAL June 2010 Table of Contents Section Page 21.1 Introduction... 21-1 21.2 Geotechnical Base Line Report... 21-1 21.3 Bridge Geotechnical
More informationNONLINER STIFFNESS MATRIX MODELING FOR COMPLEX PILE GROUP FOUNDATION OF THE ANCHORAGE PORT ACCESS BRIDGE
10NCEE Tenth U.S. National Conference on Earthquake Engineering Frontiers of Earthquake Engineering July 21-25, 2014 Anchorage, Alaska NONLINER STIFFNESS MATRIX MODELING FOR COMPLEX PILE GROUP FOUNDATION
More informationxiii Preface to the Fifth Edition Preface to the Second Edition Factors for Conversion to SI Units of
Structural Steel Designer's Handbook Table Of Contents: Contributors xiii Preface to the Fifth Edition xv Preface to the Second Edition xvii Factors for Conversion to SI Units of xix Measurement Chapter
More informationContinuous for Live Load: A Texas Historical Perspective
Continuous for Live Load: A Texas Historical Perspective Scott Walton, M.S.C.E., E.I.T. 1, and Timothy E. Bradberry, M.S.E., P.E. 2 Abstract A significant number of engineers in the United States have
More information3.5 Tier 1 Analysis Overview Seismic Shear Forces
Chapter 3.0 - Screening Phase (Tier ) 3.5 Tier Analysis 3.5. Overview Analyses performed as part of Tier of the Evaluation Process are limited to Quick Checks. Quick Checks shall be used to calculate the
More informationItem 442 Metal for Structures
Item 442 Metal for Structures 1. DESCRIPTION 2. MATERIALS Provide structural steel, high-strength bolts, forgings, steel castings, iron castings, wrought iron, steel pipe and tubing, aluminum castings
More informationOHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO
OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 July 21, 2017 To: Users of the Bridge Design Manual From: Tim Keller, Administrator, Office of Structural
More information2008 Bridge Load Rating Class 101
2008 Bridge Load Rating Class 101 Workshop Agenda VIII. Load Rating Example #2 IX. Simple Span Nail Laminated Timber Deck (without distress) Class Exercise Simple Span Nail Laminated Timber Deck (with
More informationCTP STITCH-TIE AGAIN! Quick and easy way to re-anchor existing veneers to back-up structures.
Helical Wall Tie System for Stabilizing Veneers and Structural Repair AGAIN! ANOTHER CTP SOLUTION! CTP STITCH-TIE Quick and easy way to re-anchor existing veneers to back-up structures. Brick to Concrete
More informationPREPARED BY: ALBERT NEUMANN E.I. PROJECT MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION, DISTRICT 5
SR 19 OVER LITTLE LAKE HARRIS BRIDGE 110026 SUBSTRUCTURE REPAIR LAKE COUNTY, FL PREPARED BY: ALBERT NEUMANN E.I. PROJECT MANAGER FLORIDA DEPARTMENT OF TRANSPORTATION, DISTRICT 5 DAVID THOMPSON P.E. ENGINEER
More informationPulaski County, Virginia
Pulaski County, Virginia Typical Retaining Wall Details Based on the 2009 International Residential Code CONTENTS Timber Retaining Wall... 2 General Requirements... 2 Wall Construction... 2 Deadmen...
More informationBrace Badger Helical Anchor System. MB Badger Advantages Installation Requirements MB Super Braces Brace Attachment Criteria.
Brace Badger Helical Anchor System MB Badger Advantages Installation Requirements MB Super Braces Brace Attachment Criteria MB BRACE BADGER HELICAL ANCHOR SYSTEM There are times in tilt-up construction
More informationAlberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.
STANDARD BRIDGE & CULVERT COMPONENTS Alberta Bridge Inventory In Alberta there are about 13,300 bridges. Types of bridges in Alberta: Standard bridges 3521 (26%) Bridge size culverts 8348 (63%) Major bridges
More informationAPPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system.
APPENDIX B. LOAD FRAME This Appendix will describe the philosophy in the design and operation of the loading system. LOAD FRAME The large-scale gusset plate testing required a unique loading fixture. A
More informationSAMPLE SPECIFICATION for HIGH STRAIN DYNAMIC TESTING of DRIVEN PILES
SAMPLE SPECIFICATION for HIGH STRAIN DYNAMIC TESTING of DRIVEN PILES October 2014 In using this sample specification, it should be recognized that each site and structure is unique. Therefore, geotechnical
More informationSupplemental Structural Correction Sheet Steel Moment Frame Design (2017 LABC)
Supplemental Structural Correction Sheet Steel Moment Frame Design (2017 LABC) Plan Check/PCIS Application No.: Checked By: Your feedback is important, please visit our website to complete a Custom Survey
More informationMarina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle
Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle Overall Information Location: Singapore Date of Completion: 2010 Cost: $5.7 billion Architect: Moshe Safdie Executive Architect: Aedas, Pte
More informationMinimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08
Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced
More informationDIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: GOLIATHTECH INCORPORATED 175B RUE PELADEAU MAGOG, QUEBEC J1X 5G9 CANADA
0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-3726 Issued 10/2017 This report is subject to renewal 10/2018. DIVISION: 31 00 00
More informationLRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1
LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE Mark S. Mahan 1 Abstract The newly approved AASHTO Guide Specification for LRFD Seismic Bridge Design (referred to as LRFD Seismic Guide Spec), July 2007,
More informationDIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: CANTSINK MANUFACTURING, INC. 71 FIRST AVENUE LILBURN, GEORGIA 30047
0 Most Widely Accepted and Trusted ICC-ES Evaluation Report ICC-ES 000 (800) 423-6587 (562) 699-0543 www.icc-es.org ESR-1559 Reissued 12/2016 This report is subject to renewal 12/2018. DIVISION: 31 00
More informationAluminum Beam Gang System
Aluminum Beam Gang Aluminum Beam Gang System Symons Aluminum Beam Gang Forming System offers computer-optimized aluminum beams with an extremely high strength-toweight ratio. The unique beam attachment
More informationSTATE UNIVERSITY CONSTRUCTION FUND. UNIVERSITY CON DIRECTIVE 5-1 Issue date: October 2014
STATE STRUCTION FUND DIRECTIVE 5-1 Issue date: October 2014 STRUCTURAL STEEL 1. General: It is the Fund's policy that the design of the structural steel is the prime responsibility of the project's Structural
More informationSTEEL DECKS FOR RAIL BRIDGES
STEEL DECKS FOR RAIL BRIDGES Duncan Paterson PE PhD HDR Inc. 9987 Carver Rd Cincinnati OH 513-984-7500 duncan.paterson@hdrinc.com Steve Lorek, PE HDR Inc. 9987 Carver Rd Cincinnati OH 513-984-7500 Steve.Lorek@hdrinc.com
More informationDUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS
DUCTILE IRON PILES DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS Designed to resist both compression and tension loads in either end-bearing or friction,
More informationAppendix D.1. Redundancy Analysis of Composite Spread Box Girder Superstructures under Vertical Loads
Appendix D.1 Redundancy Analysis of Composite Spread Box Girder Superstructures under Vertical Loads By Jian Yang, Feng Miao and Michel Ghosn Contents 1. Introduction...1 2. Structural Modeling...3 2.1
More informationSmarter. Safer. Leaner.
Smarter. Safer. Leaner. Fast Installation and Removal Decrease Leading Edge Exposure by 87% OSHA Compliant Versatile and Reusable Use Perimeter Protection Posts During Construction: At Building Perimeter
More informationJohn James Audubon Bridge
John James Audubon Bridge Cable-Stayed Main Span Over the Mississippi River Johns Hopkins University Whiting School of Engineering September 10, 2008 The Project Scheduled Time to Complete Estimated Number
More information