Embedded Turnouts for the Hiawatha LRT Project. Author: David F. Peterson, PE. Parsons Corporation

Size: px
Start display at page:

Download "Embedded Turnouts for the Hiawatha LRT Project. Author: David F. Peterson, PE. Parsons Corporation"

Transcription

1 Embedded Turnouts for the Hiawatha LRT Project Author: David F. Peterson, PE Parsons Corporation Design Manager, Hiawatha Light Rail Transit Project September 30, 2003

2 ABSTRACT Installation and maintenance of turnouts in paved areas have always been something to avoid for both railroads and transit agencies. For the development of the Hiawatha Light Rail Transit Project, a key element is at-grade rail access to downtown Minneapolis. The present north end in downtown requires crossovers in Fifth Street and Nicollet Mall, a confined area congested with utilities and vehicular traffic. Embedded turnouts turnouts installed in paving are required in this and other locations along the Hiawatha corridor. Minnesota Transit Constructors (MnTC), the design-build contractor for the Hiawatha Project Office, elected to use #6 flexive double tongue switches for paved areas. This European Edgar Allen switch design differs from AREMA standard double tongue turnouts by having a flexible switch point set in a fixed casting, a transit type design also being used in Tampa s new LRT system. For containment of stray electrical current to prevent corrosion of nearby infrastructure, the embedded track is electrically isolated. The turnout is constructed in a concrete tub comprised of concrete and insulating membrane and sealed with elastomeric grout. The turnout and tub are constructed with

3 three concrete pours, with the insulating membrane installed between the first and second pours. In most cases, the turnouts are power operated with switch machines between the switch point castings, and heated with calrod-type electrical resistance heaters. The turnouts were fabricated by Progress Rail Services and will be installed by MnTC s subcontractor Railworks Track Systems in early to mid 2003.

4 1. INTRODUCTION Construction and operation of turnouts in paved areas have always been a lessthan-desired alternative to ballasted designs. These embedded turnouts require closer construction tolerances and higher maintenance and are avoided when possible. The Hiawatha Light Rail Transit project in Minneapolis and Bloomington, Minnesota is currently under construction. Hiawatha is a new system linking downtown Minneapolis with the Minneapolis St. Paul International Airport and the Mall of America in Bloomington. The line is approximately 12 miles in length and includes seventeen stations located in commercial and residential areas. Low floor Bombardier light rail vehicles will operate at up to 55 mph at 7 ½ minute headways at peak travel periods. The system requires six embedded crossovers, primarily at the end points of the system to cross trains over for return movements. The design-build contractor, Minnesota Transit Constructors (MnTC), worked closely with the representatives of the Hiawatha Project Office (HPO) to identify

5 the most appropriate embedded track and turnout system for the Hiawatha LRT system. 2. TURNOUT EVALUATION The HPO s two agencies the Minnesota Department of Transportation and Metro Transit, decided during the design development process to use tee rail in lieu of girder rail for embedded track applications. This in turn led to discussions of alternative types of turnouts. AREMA s Portfolio has two embedded turnout types that in the past have been used both for railroad and light rail transit applications. (See Portfolio Plan No and other referenced plans). These turnouts, using tongue and mate and double tongue switches, would have performed satisfactorily. However, these turnout designs are traditionally intended for railroad use, and considering the lower axle loads of Light Rail Transit (LRT) applications, other options were considered. During the evaluation of turnout options during design development, the HPO and MnTC considered the embedded switches manufactured by Edgar Allen Limited in the United Kingdom. Edgar Allen s switches are currently in use by Tampa, Florida s Hartline system and are being installed in New Orleans streetcar system. They are also in use in Sheffield and Manchester, England

6 and Hong Kong. These flexive tongue designs are ideal for paved track applications and can provide maintenance advantages. Flexive tongue turnouts involve a solid manganese steel body with a flexible manganese tongue, acting as the switch point, fastened to the body by two screws. The tongue is easily removed for maintenance or replacement without removing the entire unit. Electrical resistance heaters (calrods) can be placed along the sides or underneath the manganese castings. 3. METALLURGY Edgar Allen s flexive tongue turnouts were introduced in 1992 for the Sheffield Supertram system in the UK. The Supertram system opened in 1995, and Edgar Allen supplied turnout points and castings for six 25m and three 100m radius turnouts. Both the manganese points and bodies are rated at a Brinell Hardness of approximately 250 at manufacture Edgar Allen reports that in the five years after opening of the Supertram system the bodies and points have work hardened to approximately 400 BHN. The castings and points are manufactured using austenitic manganese steel. 4. TURNOUT DESIGN CONSIDERATIONS

7 The Hiawatha designers evaluated other aspects of the turnout design that would ultimately impact the performance of the turnouts. These factors should be considered for any transit project that requires turnouts in paved areas. a. Paving Depending upon whether vehicles will actually drive upon the turnout, careful consideration should be taken regarding the type of paving to be used around the rails and other turnout components. For Hiawatha, it was decided to use portland cement concrete islands between the rails, with asphalt cement concrete infill to approximately six inches from the rail head. This would give better support to the traffic that could potentially cross the turnout and was considered more aesthetically attractive. Based upon discussions with other transit properties, it was decided that using portland cement concrete against the rail would not perform well due to movement of the rail against the concrete, potentially breaking the concrete. It could also present problems with replacement of rail and turnout components and might not provide satisfactory rail to rail insulating properties. b. Electrical Isolation The embedded track for the Hiawatha system was insulated from the ground to protect adjacent utilities and structures from electrical corrosion by using the

8 rubber boot system manufactured by the Iron Horse Corporation cast in portland cement concrete. The turnouts, however, could not use the boot system due to the irregular size and shape of frogs, switch castings, and plates. As a result, the embedded turnouts were constructed in insulated concrete tubs, which are comprised of reinforced concrete with a rubberized isolation liner with protection board. The rails as they enter the tubs are themselves isolated with bulkheads perpendicular to the track. The turnout materials, including rail, plates, frogs, switch machines, switch castings, and the concrete islands discussed above are installed in the tub. Rail and switch components are mounted on elastomeric grout pads that provide additional insulation and shock resistance. c. Switch Machines The Hiawatha LRT system, as currently designed, has six crossovers in embedded track. Four crossovers are powered using Hanning & Kahl (H&K) switch machines, and the other two crossovers use hand throw turnouts. Spring switches, although common on other systems, were not utilized for operational reasons. The power switches are powered by H&K Model HW(E)61V. The switch machines are located between the switch casting and each switch machine box is drained with non-conducting PVC pipe to the storm drainage system. Power and signal conduit to the switch machine and turnouts run through the isolation

9 membrane and are insulated. Both bonded and poly bar insulated joints are used and are identical to those in standard track applications. Hand throw switch boxes are also located between the switch castings. d. Switch Heaters Since Minnesota winters are long and cold with plenty of snow, the embedded turnouts will be heated using electrical resistance heaters (calrods). There was considerable discussion within the design team regarding whether to install the heaters along the side of the switch castings or underneath. There is no ideal way to heat the switches, since the heaters will be in contact with other materials such as asphaltic concrete or elastomeric grout. Discussions with other transit properties revealed that both methods of heating are used. The Hiawatha designers decided to place two heater rods in metal conduits under each casting, above the concrete and far enough away from the elastomeric grout pads to avoid overheating of the pads. The heater rods can be pulled out of the conduit and replaced without removing the switch casting or conduit. By installing the heater rods underneath, it avoids the inevitable melting of asphalt concrete along the side of the casting, and the dual heater rods provide redundancy. e. Drainage

10 The paved areas in downtown Minneapolis and suburban Bloomington are generally flat and drainage is a challenge. In warm climates, poor drainage in embedded turnouts can be a nuisance in Minnesota, with long periods of subfreezing weather, frozen switch mechanisms could put a turnout out of service for months. The embedded turnout tubs and embedded trackbed are provided surface drainage and the switch machine boxes are also drained. Switch heater rods will be placed in the switch drains to keep them clear during the winter season. 5. CONSTRUCTION METHODS At the time of this writing, the embedded turnouts for the Hiawatha LRT project are under construction. The construction of the turnouts is very time consuming compared to construction of ballasted turnouts and takes several months from start to finish. The construction of the turnouts can be discussed in terms of the three concrete pours, as follows: a. First Pour The Isolation Tub The reinforced concrete isolation tub is constructed on select base material, with conduits in place for drainage and systems (traction power and signal) facilities. The first concrete pour is eight inches thick, with walls up to top of rail longitudinally on the field side of the rails, and with the concrete bulkheads to top of rail between the rails at the ends of the tubs.

11 After placement of the concrete, the isolation liner is placed on the bottom and sides of the tub. The rubberized liner is heat welded and the welds electrically tested. The liner is installed with one-eighth inch thick protection board on both sides of the liner. The following exhibits show the details of the turnout design. The three stages of construction, labeled First Pour, Second Pour, and Final Pour are included. The concrete pour for that phase is cross-hatched in the cross sections. Plan View Isolation Tub for Crossover Hiawatha LRT Design-Build PAVEMENT INFILL TRANSVERSE C OF CROSSING L B CONCRETE 1 MIN C L TRACK NO. 6 TURNOUT WITH DOUBLE TONGUE SWITCH PER SPEC MIN. A SWITCH DRAIN (AT EACH SWITCH) PS C SWITCH AND COVER PLATE FLOW 2-0 MIN. 9º31 38 PITO TUB DRAIN (AT LOW END) CONCRETE 2-0 (MIN.) SWITCH BLOCK OUT C DETAIL A 4-0 MIN. 7 - MAX FLOW POURED POLYMETRIC JOINT SEAL FOR LESS THAN 2 GAP IN RAIL HEAD B CONCRETE PAVEMENT INFILL C L TRACK 38 MAX. A EMBEDDED TRACK SLAB Exhibit I, Plan View, Isolation Tub

12 Hiawatha LRT Design-Build Isolation Tub First Pour PAVEMENT 3-0 MIN. 6 1% 1% #4 REBAR 18 ON CENTER L TRACK ALONG C L TRACK C L TRACK 4 VARIES ½ GAUGE 18 CONCRETE 4-8 ½ GAUGE CONST. IN FILL JOINT LEVEL PCC 2 1/2 CLEAR 3 CLEAR 1% 3-0 MIN. INSET CURB AND GUTTER AND SIDEWALK 1 4 x 4 CHAMPHER 2 ISOLATION MEMBRANE PROTECTION 2 BOARD 3 ISOLATION TUB 1 AGGREGATE BASE, CLASS 5 (02211) NON-FROST SUSCEPTIBLE SOIL ELASTOMER GROUT Exhibit II, Isolation Tub, First Pour Hiawatha LRT Design-Build Section D-D End of Isolation Slab TUB EMBEDDED TRACK SLAB SPECIAL TRACKWORK PLATE WITH E.G. PAD 1 115RE RAIL #5 BETWEEN RAILS BEND UP #6 BAR HORIZ. REINF. 4 x 4 ISOLATION SLAB CHAMFER TOP OF RAIL 2 ELASTOMER GROUT SEAL FOR MEMBRANE EDGE 1 EXPANSION JOINT MATERIAL AND SEALER #6 BETWEEN RAILS TUB REINFORCEMENT PROTECTION BOARD #6 TOTAL 3 EPOXY COATED # ISOLATION MEMBRANE TUB (WORKING SLAB) 9 Exhibit III, End of Isolation Slab b. Second Pour Support for the Rail

13 A strongback system and jacks are used to support the assembled turnout in the proper line and grade prior to the second concrete pour. Anchor bolts and inserts for the turnout plates are placed in the plates in position for embedment in the concrete. Plastic caps are placed over each of the e-clips to prevent fouling during the concrete pour and for protection afterward when asphalt is placed against the rail. Hiawatha LRT Design-Build Isolation Tub Second Pour PAVEMENT 3-0 MIN. 6 1% 1% #4 REBAR 18 ON CENTER L TRACK ALONG C L TRACK C L TRACK 4 VARIES ½ GAUGE 18 CONCRETE 4-8 ½ GAUGE CONST. IN FILL JOINT LEVEL PCC 2 1/2 CLEAR 3 CLEAR 1% 3-0 MIN. INSET CURB AND GUTTER AND SIDEWALK 1 4 x 4 CHAMPHER 2 ISOLATION MEMBRANE PROTECTION 2 BOARD 3 ISOLATION TUB 1 AGGREGATE BASE, CLASS 5 (02211) NON-FROST SUSCEPTIBLE SOIL ELASTOMER GROUT Exhibit IV, Isolation Tub, Second Pour The concrete is placed within the tub to a level one inch below the turnout plates. The one inch vertical gap will be filled with elastomeric grout, which provides electrical isolation and support for the plates, after the second pour concrete is

14 cured. The reinforcement in the second pour is of course separate of the reinforcement in the first pour due to the design of the isolation liner, but hoops of rebar are included in second pour to secure the islands above, which are part of the third pour. c. Third Pour Concrete Islands While elastomeric grout is being poured under the turnout plates, systems work can be done, including bond wires to rails for power feeds and signals, setting and adjusting the switch machines, and installing and testing the insulated joints. The third and last concrete pour brings the concrete between the rails and on the field side of the rail against the isolation liner to top of rail. Hiawatha LRT Design-Build Isolation Tub Final Pour PAVEMENT 3-0 MIN. 6 1% 1% #4 REBAR 18 ON CENTER L TRACK ALONG C L TRACK C L TRACK 4 VARIES ½ GAUGE 18 CONCRETE 4-8 ½ GAUGE CONST. IN FILL JOINT LEVEL PCC 2 1/2 CLEAR 3 CLEAR 1% 3-0 MIN. INSET CURB AND GUTTER AND SIDEWALK 1 4 x 4 CHAMPHER 2 ISOLATION MEMBRANE PROTECTION 2 BOARD 3 ISOLATION TUB 1 AGGREGATE BASE, CLASS 5 (02211) NON-FROST SUSCEPTIBLE SOIL ELASTOMER GROUT Exhibit VI, Isolation Tub, Final Pour

15 The approximately six inch gap between the ball of the rail and the island concrete will be filled in later to top of rail, along with a flangeway, with an asphalt concrete infill to finish the work. 6. SUMMARY The embedded turnouts for the Hiawatha project will be operated in a harsh weather environment and will be critical to the successful operation of the system. The Edgar Allen turnouts, while fairly new to North American transit systems, have been proven to be reliable in Europe and its design should perform well in street conditions in Minneapolis and Bloomington.

SECTION RIGID PAVEMENT

SECTION RIGID PAVEMENT SECTION 02750 PART 1 GENERAL RIGID PAVEMENT 1.1 SUMMARY A. Section Includes: 1. Concrete sidewalks. 2. Concrete stair steps. 3. Concrete integral curbs gutters. 4. Concrete parking areas and roads. B.

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required

More information

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course. SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721

More information

Asphalt on Concrete Base with Waterproofing Membrane

Asphalt on Concrete Base with Waterproofing Membrane CABLES CANNOT BE IN DIRECT CONTACT WITH THE WATERPROOFING MEMBRANE! CABLES WILL BURNOUT, AND THE MEMBRANE WILL MELT. 7 5 4 6 1 2 3 NOTES: 1) CLEAN CONCRETE SURFACE 2) HOT MEMBRANE WATERPROOFING 3) ASPHALTIC

More information

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.

B. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans. SECTION 1400 - CONCRETE PAVEMENT 1401 SCOPE. This section governs the furnishing of all labor, equipment, tools, and materials and the performance of all work necessary to construct concrete pavement.

More information

2004 Specifications CSJ SPECIAL SPECIFICATION DIRECT FIXATION TRACK CONSTRUCTION

2004 Specifications CSJ SPECIAL SPECIFICATION DIRECT FIXATION TRACK CONSTRUCTION 2004 Specifications CSJ 0920-38-250 SPECIAL SPECIFICATION 7660 DIRECT FIXATION TRACK CONSTRUCTION 1. Description. This section specifies the construction of direct fixation (DF) track to the lines and

More information

SECTION CONCRETE PAVING

SECTION CONCRETE PAVING SECTION 32 13 13 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for providing portland cement concrete work and all other incidental concrete improvements for the project

More information

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT PLACE TWO STANDARD CONNECTORS IN EACH UNIT AS SHOWN (VERTICAL ORIENTATION) INSERT TWO CONNECTORS PER HORIZONTALLY ORIENTED BLOCK; INSERT ONE CONNECTOR PER VERTICALLY ORIENTED BLOCK SHIM BETWEEN BLOCK COURSES

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS

More information

Entellus 75 NORTH STREET MERRILL SHERIFF CONSTRUCTION. 181 North 200 West, Suite #4. Bountiful, UT Phone

Entellus 75 NORTH STREET MERRILL SHERIFF CONSTRUCTION. 181 North 200 West, Suite #4. Bountiful, UT Phone Entllus DUMPSTER PAD AND REPLACE WITH NEW BETWEEN THESE TWO POINTS SAWCUT ALONG DEMO LINE REMOVE PARKING SPOTS CURB, GUTTER, ASPHALT AND LANDSCAPING, WITHIN HATCHED AREA FOR NEW ADDITION CURB & GUTTER

More information

SECTION MINOR CONCRETE

SECTION MINOR CONCRETE SECTION 03300 - MINOR CONCRETE CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And Payment...

More information

Structural - Engineering Review Checklist

Structural - Engineering Review Checklist Structural - Engineering Review Checklist Project: List Corridor Criteria ID Review Priority (H,M,L) TOPICS S-_-## Structural Design Codes, Manuals and Specifications 6.1.0 REFERENCES DESIRED Criteria

More information

SECTION EMBEDDED TRACK CONSTRUCTION

SECTION EMBEDDED TRACK CONSTRUCTION CONTRACT SPECIFICATIONS PART 1 - GENERAL 1.01 SUMMARY A. This Section includes specifications for the construction of insulated embedded track as indicated on the Contract Drawings. Embedded track construction

More information

D-1 THE CITY OF HARRISBURG 1 1/2" MIN. ID-2 WEARING COARSE EXISTING STREET SURFACE AC-20 SEALER (ALL AROUND) 1 1/2" MIN. ID-2 BINDER COARSE

D-1 THE CITY OF HARRISBURG 1 1/2 MIN. ID-2 WEARING COARSE EXISTING STREET SURFACE AC-20 SEALER (ALL AROUND) 1 1/2 MIN. ID-2 BINDER COARSE EXISTING STREET SURFACE 1 1/2" MIN. ID-2 BINDER COARSE 1 1/2" MIN. ID-2 WEARING COARSE AC-20 SEALER (ALL AROUND) 8" CLASS A P.C. CONCRETE SAW CUT TOP OF CONCRETE SHALL MEET SURFACE OF EXISTING CONCRETE.

More information

DIVISION 34 TRANSPORTATION SECTION SPECIAL TRACKWORK ADDENDUM NO. 1

DIVISION 34 TRANSPORTATION SECTION SPECIAL TRACKWORK ADDENDUM NO. 1 PART 1 - GENERAL 1.01 RELATED WORK SPECIFIED ELSEWHERE A. The provisions and intent of the Contract, including the General Conditions and General Requirements, apply to this work as if specified in this

More information

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light

More information

SECTION CONCRETE PAVING

SECTION CONCRETE PAVING PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 13 13 CONCRETE PAVING A. Extent of concrete curbs, walks, and paving as show on drawings B. Earthwork and prepared sub-base C. Concrete and related materials

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

CITY OF SAN ANGELO ITEM 360 CONCRETE PAVEMENT

CITY OF SAN ANGELO ITEM 360 CONCRETE PAVEMENT ITEM 360 360.1. DESCRIPTION. CITY OF SAN ANGELO ITEM 360 This item shall govern for the construction of Portland Cement Concrete pavement with or without monolithic curbs on a prepared subgrade or sub-base

More information

SECTION PORTLAND CEMENT CONCRETE

SECTION PORTLAND CEMENT CONCRETE PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the supplemental documents as indicated in the Site Work General Provisions, apply to work of this

More information

Rak Production Technology of Concrete Structures (2015) Concrete Reinforcement

Rak Production Technology of Concrete Structures (2015) Concrete Reinforcement Rak-82-2121 Production Technology of Concrete Structures (2015) Concrete Reinforcement 09.10.2015 1 Learning Outcomes To acquaint the student with concrete reinforcement 2 Reinforcement The of concrete

More information

Wall Panels. Structural wall panel. Architectural wall panel. Cladding wall panel. Sandwich wall panel

Wall Panels. Structural wall panel. Architectural wall panel. Cladding wall panel. Sandwich wall panel Wall Panels Structural wall panel Architectural wall panel Cladding wall panel Sandwich wall panel Wall Panels Assorted styles and colours Reveals and other patterns Painted finish Bolted, welded and knife

More information

A. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork.

A. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork. DIVISION 03 CONCRETE 03 0100 MAINTENANCE OF CONCRETE 03 0505 UNDER SLAB VAPOR BARRIER A. Sheet vapor retarder shall be polyethylene sheet, ASTM D 4397, 10 mils thick minimum. Consult with Facilities Management

More information

lbfoster.com CXT CONCRETE TIES CATALOG

lbfoster.com CXT CONCRETE TIES CATALOG CXT CONCRETE TIES CATALOG L.B. Foster offers a complete line of CXT concrete railroad ties. Our catalog of concrete ties includes standard track, turnout, gantry and specialty ties, such as guard rail,

More information

SECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing.

SECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing. PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 13 34 00 FABRICATED ENGINEERED STRUCTURES A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1

More information

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section

SECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section 02670-1 of 6 SECTION 02670 CURB, COMBINATION CURB AND GUTTER, AND 02670.01 GENERAL A. Description This work shall include, but not necessarily be limited to, the construction of concrete curb, concrete

More information

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES Safety Precautions in the Excavation of a Sentinel Wedge take all necessary steps to make sure the pit is secured. Follow all OSHA requirements for digging

More information

Fundamentals of Jointing for Volume Change in Concrete

Fundamentals of Jointing for Volume Change in Concrete Fundamentals of Jointing for Volume Volume Changes in Concrete Concrete is at its greatest volume when it is freshly placed. As the concrete cures and hardens, water is consumed in the chemical reaction

More information

TABLE OF CONTENTS. Appendices are not a mandatory part of this specification unless invoked by the Owner.

TABLE OF CONTENTS. Appendices are not a mandatory part of this specification unless invoked by the Owner. ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 920 NOVEMBER 2005 CONSTRUCTION SPECIFICATION FOR DECK JOINT ASSEMBLIES, PREFORMED SEALS, JOINT FILLERS, JOINT SEALS, JOINT SEALING COMPOUNDS, AND WATERSTOPS

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete

More information

SECTION CONCRETE REINFORCEMENT

SECTION CONCRETE REINFORCEMENT PART 1 GENERAL 1.01 DESCRIPTION SECTION 03200 CONCRETE REINFORCEMENT A. The work specified in this Section consists of furnishing and installing reinforcement for concrete structures. All reinforcement

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT. A. ASME B31.1 (American Society of Mechanical Engineers) - Power Piping

SECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT. A. ASME B31.1 (American Society of Mechanical Engineers) - Power Piping SECTION 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section includes pipe and equipment supports, hangers, anchors, bases sleeves and the sealing of

More information

SECTION HANGERS AND SUPPORTS FOR PLUMBING

SECTION HANGERS AND SUPPORTS FOR PLUMBING SECTION 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT Page 220548-1 SECTION 220548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT Page 230548-1 SECTION 230548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Public Works Manual. Revised September Concrete & Asphalt

Public Works Manual. Revised September Concrete & Asphalt Public Works Manual Revised September 2015 Concrete & Asphalt Where it must cross domestic it must cross above and with a 1 minimum separation. Nonpotable water tape. 10.00 PORTLAND CEMENT CONCRETE 10.01

More information

Light-Metal Roof Edge, Raised

Light-Metal Roof Edge, Raised NAIL WOOD CANT TO BLOCKING 2 ROWS STAGGERED EACH ROW 24 O.C. 1/2 MIN. 10 0 MAX. FASTEN 18 O.C. WITH NEOPRENE GASKETED FASTENERS 3-1/2 MIN. 4 6 JOINT COVER PLATE SET IN TWO BEADS OF SEALANT 4 MIN. SPECIFIED

More information

DEFENDER. Installation Manual

DEFENDER. Installation Manual DEFENDER Installation Manual 1 DEFENDER SERIES BOLLARDS GENERAL INSTALLATION GUIDELINES (Unless otherwise specified) 1.0 BOLLARD BARRIER FOUNDATION DETERMINE VEHICLE BARRIER LOCATION AND PREPARE EXCAVATION/FOUNDATION

More information

HITT STREET UNIVERSITY PROJECT #: CP REFER TO CP PLANS FOR ELECTRICAL DUCTBANK IN HITT STREET INSTALL:

HITT STREET UNIVERSITY PROJECT #: CP REFER TO CP PLANS FOR ELECTRICAL DUCTBANK IN HITT STREET INSTALL: N 1133521.33 E 1689742.43 STA: 10+53.07 INSTALL: 2-10" 90 BENDS CONNECT TO MIDDLEBUSH HALL INTERIOR PLANT PLUMBING MIDDLEBUSH HALL HW1 HWS HWR 10+00 FREDRICK APARTMENTS FINE ARTS INSTALL 422 LF 10" HWS

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems.

The Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems. The Most Advanced Name in Water Management Solutions TM The most cost-effective slotted and trench surface drain systems. A sensible alternative to metal and concrete Since 1987, Duraslot surface drains

More information

Track & Services Co., Inc.

Track & Services Co., Inc. Track & Services Co., Inc. Company Profile A Joint Venture of With over 80 years of experience, Atlantic Track & Turnout is a major supplier of single source solutions to American railroad and transit

More information

SECTION 12 INDEX CONCRETE CURBS AND GUTTERS

SECTION 12 INDEX CONCRETE CURBS AND GUTTERS SECTION 12 INDEX CONCRETE CURBS AND GUTTERS 1. SCOPE OF WORK. 12-2 2. MATERIALS. 12-2 3. CONSTRUCTION REQUIREMENTS.. 12-2 12-1 SECTION 12 CONCRETE CURBS AND GUTTERS 1. SCOPE OF WORK: This work shall consist

More information

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL

CONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL 13686.00 CONCRETE WALKS AND CURBS 033015-1 1.1 RELATED DOCUMENTS: SECTION 033015 CONCRETE WALKS AND CURBS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General and Supplementary

More information

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT SECTION 230548 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Elastomeric Isolation pads. 2. Elastomeric Isolation mounts. 3. [Freestanding] [Restrained] [Freestanding and restrained]

More information

IN2 Sleeves and Sleeve Seals for Communications Pathways and Cabling

IN2 Sleeves and Sleeve Seals for Communications Pathways and Cabling Illinois Math and Science Academy DigitalCommons@IMSA Project Manuals IN2 2015 IN2 Sleeves and Sleeve Seals for Communications Pathways and Cabling Illinois Mathematics and Science Academy Follow this

More information

Section CONCRETE PAVEMENT

Section CONCRETE PAVEMENT PART 1 GENERAL 1.01 SUMMARY Section 03002 This section includes construction of concrete pavement for roadways, driveways, turnouts, concrete medians, directional islands, sidewalks and curbing when Harris

More information

Current Standard Plates including Transmittal Letters are available on the web at:

Current Standard Plates including Transmittal Letters are available on the web at: MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (6-03) MANUAL: Standard

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE CITY OF TORONTO STANDARD CONSTRUCTION SPECIFICATIONS FOR ROADS TS 3.40 November 2009 CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE INDEX TS 3.40.01 SCOPE... 3 TS 3.40.02 REFERENCES... 3 TS 3.40.03

More information

Light Rail Transit Tracks in Pavement

Light Rail Transit Tracks in Pavement Light Rail Transit Tracks in Pavement ROBERT E. CLEMONS ne of the important features of light rail transit (LRT) is the () ability to locate tracks in downtown streets and transit malls, thus eliminating

More information

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION CHAIN LINK FENCING

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION CHAIN LINK FENCING PART 0 DESIGN STANDARDS 0.01 GENERAL DESIGN GUIDELINES A. Requirements vary. A/E shall consult with DPS project manager to determine extent and type of permanent site fencing to be employed. B. Provide

More information

IN2 Sleeves and Sleeve Seals for Electrical Raceways and Cabling

IN2 Sleeves and Sleeve Seals for Electrical Raceways and Cabling Illinois Math and Science Academy DigitalCommons@IMSA Project Manuals IN2 2015 IN2 Sleeves and Sleeve Seals for Electrical Raceways and Cabling Illinois Mathematics and Science Academy Follow this and

More information

DIVISION 03 CONCRETE. Number CONCRETE

DIVISION 03 CONCRETE. Number CONCRETE 03 00 00 CONCRETE 03 10 00 CONCRETE FORMING AND ACCESSORIES 03 11 00 Concrete Forming 03 11 13 Structural Cast-in-Place Concrete Forming 03 11 16 Architectural Cast-in-Place Concrete Forming 03 15 00 Concrete

More information

CW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS

CW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS December 2012 CW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 0548 - PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms Introduction Scott Reeve, President, Composite Advantage Dayton, Ohio Engineered Solutions and Products for Infrastructure Large parts High

More information

SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017

SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017 SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017 STANDARD SPECIFICATIONS 102.12 Best Value Contracting Partial payments shall be withheld if contractor is working on site and has not satisfied

More information

SECTION CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS

SECTION CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS SECTION 32 05 23 PART 1 - GENERAL 1.1 DESCRIPTION A. This section shall cover site work concrete constructed upon the prepared subgrade and in conformance with the lines, grades, thickness, and cross sections

More information

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five Project Overview Location SR 600 / US 92, Volusia County FPN:

More information

Bitumen Softboard. Applications: Physical Properties: Jolly Bitulex Expansion Joint Fillers conform to the following required standards

Bitumen Softboard. Applications: Physical Properties: Jolly Bitulex Expansion Joint Fillers conform to the following required standards Bitumen Softboard Jolly Bitulex Softboard is processed from cane fibre, the raw material tested and proven to provide the best resilience. Impregnated with Bitumen in various percentages, it is a perfect

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

BLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS

BLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS WOOD TIES 2015 TRACK STANDARDS & SPECIFICATIONS FOR NEW CONSTRUCTION & UPGRADES Ties shall be new 7"x 9" x 8' 6" creosoted grade hardwood. All new ties shall be spiked with four (4) new spikes and box

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT SPECIFICATION EO-1007 REVISION 13 DECEMBER 2013 EFFECTIVE DATE DECEMBER 16,

More information

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of

More information

COUNTY OF BEXAR. Curbed Streets. Residential PUBLIC WORKS DEPARTMENT

COUNTY OF BEXAR. Curbed Streets. Residential PUBLIC WORKS DEPARTMENT COUNTY OF BEXAR PUBLIC WORKS DEPARTMENT 233 N. Pecos La Trinidad, Suite 420 San Antonio, Texas 78207-3188 Main 210-335-6700 DRIVEWAY APPROACH SPECIFICATIONS Curbed Streets Residential Applicability: All

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS. A. Formwork complete with shoring, bracing and anchorage.

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS. A. Formwork complete with shoring, bracing and anchorage. SECTION 02528 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.01 WORK INCLUDED A. Formwork complete with shoring, bracing and anchorage. B. Concrete reinforcement complete with required supports,

More information

ITEM 555 CHAIN LINK FENCING

ITEM 555 CHAIN LINK FENCING ITEM 555 AFTER MARCH 1, 2012 CHAIN LINK FENCING 555.1 Description. This item shall govern for furnishing the quantities of chain link fencing and gates as shown on the plans, including all posts, bracing

More information

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces. PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Handrails and guardrails. 1.2 PERFORMANCE REQUIREMENTS A. General: In engineering railings to withstand structural loads indicated, determine

More information

SPECIAL PROVISION Concrete Pavement

SPECIAL PROVISION Concrete Pavement 1995 Metric CSJ s 0902-48-305, etc. SPECIAL PROVISION 360---036 Concrete Pavement For this project, Item 360, Concrete Pavement, of the Standard Specifications, is hereby amended with respect to the clauses

More information

SECTION HANDRAILS AND RAILINGS. A. Section Metal Fabrications: Associated metal supports.

SECTION HANDRAILS AND RAILINGS. A. Section Metal Fabrications: Associated metal supports. SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Handrails and guardrails B. Guardrails for hatches and openings. C. Safety barriers. D. Roof edge protection. 1.2 RELATED SECTIONS

More information

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report. JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine

More information

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,

More information

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS Underground Electric Distribution Standards I. SCOPE This section includes the standards for concrete, reinforcing steel, formwork, concrete placement, curing, and construction joints. Concrete work for

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Pipe Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in concrete.

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB #

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

Construction Specification for Concrete Bus Pad

Construction Specification for Concrete Bus Pad Engineering & Construction Services Division Standard Specifications for Road Works TS 3.41 June 2017 for Concrete Bus Pad Table of Contents SCOPE... 3 REFERENCES... 3 DEFINITIONS... 3 DESIGN AND SUBMISSION

More information

CONCRETE BARRIER R-49-G TYPE A BARRIER MICHIGAN DEPARTMENT OF TRANSPORTATION 20'-0" MAXIMUM BETWEEN JOINTS 8'-0" TAPERED SECTION (SEE NOTES)

CONCRETE BARRIER R-49-G TYPE A BARRIER MICHIGAN DEPARTMENT OF TRANSPORTATION 20'-0 MAXIMUM BETWEEN JOINTS 8'-0 TAPERED SECTION (SEE NOTES) - SPLIT 8'-0" TAPERED SECTION A B 40" A B " EXPANSION JOINT AT BEGINNING AND END OF SPLIT SECTIONS SEE EXPANSION JOINT DETAIL PLAN CONSTRUCTION STATIONING SHALL BE PLACED ON BOTH SIDES OF THE BARRIER.

More information

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM)

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM) INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM) TABLE OF CONTENTS 1. INTRODUCTION TO THE MODULAR EXPANSION JOINT 1.1 Purpose 1.2 How They Work 1.3 Movement Capacity 1.3.1 Longitudinal Direction

More information

RESTORATION SPECIFICATION

RESTORATION SPECIFICATION In proposed subdivision roadways where other utilities are present, the design plans should illustrate all possible utility line conflicts (crossings). During design and construction, care shall be utilized

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

FOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 3 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS

FOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 3 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS AFTER FEBRUARY 1, 2010 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS 530.1 Description. This item shall govern for curb, gutter, combined curb and gutter, sidewalks and/or driveways,

More information

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! DURA - TRENCH INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation

More information

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific

More information

Ballast Mats ATP-DR Profiled

Ballast Mats ATP-DR Profiled Ballast Mats ATP-DR Profiled Trelleborg ATP-DR Ballast Mat For Transit, Commuter or Railroad use, the Ballast Mat is designed to: Reduce degradation of ballast where depth is restricted By reducing ballast

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 PRECAST CONCRETE PIPE 10.1.1 General This section covers material requirements,

More information

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS

County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS SECTION 27 CURBS, GUTTERS, SIDEWALKS, AND DRAINAGE STRUCTURES 27-1 GENERAL Concrete curbs, gutters, sidewalks,

More information

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

Critical Structures Construction Issues

Critical Structures Construction Issues Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR

More information

ROOF DRAINS TABLE OF CONTENTS

ROOF DRAINS TABLE OF CONTENTS Pictorial Index Product Recommendations Roof Drain Selection Factors Sizing Placement Material & Characteristics Pipe Connection Commonly Specified Options Typical Installations TABLE OF CONTENTS ROOF

More information

LANE ENTERPRISES, INC. STANDARDS & SPECIFICATIONS

LANE ENTERPRISES, INC. STANDARDS & SPECIFICATIONS LANE ENTERPRISES, INC. STANDARDS & SPECIFICATIONS The following pages are an index of standards and specifications associated with Lane products. For quick reference purposes, Lane products are shown below

More information

B. American Society for Testing and Materials: 1. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers.

B. American Society for Testing and Materials: 1. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers. SECTION 230529 - HANGERS AND SUPPORTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe hangers and supports. 2. Hanger rods. 3. Inserts. 4. Flashing. 5. Sleeves. 6. Mechanical sleeve seals. 7. Firestopping

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment

More information

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS

DIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS PART 1 - GENERAL 01.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this Section.

More information

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil

BILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES

More information

Page 1 March 2014 Catholic District School Board of Eastern Ontario C&A Project No

Page 1 March 2014 Catholic District School Board of Eastern Ontario C&A Project No SI. Edwards Catholic School Concrete Formwork Section 03100 Page 1 1 GENERAL 1 RELATED WORK Concrete Reinforcement Cast-in-place Concrete Concrete Curbs and Walks Concrete Floor Finishes Section 03200

More information

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS GENERAL INSTALLATION INSTRUCTIONS 1 Ensure that the trench where the channels are going to be installed has enough room for the appropriate

More information

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN GENERAL NOTES DESIGN TABLE NOTES INDEX OF SHEETS 1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED. U.S. CUSTOMARY UNITS IN ( ) PARENTHESIS.. ALL "DESIGN" METRIC UNITS INDICATED ARE SOFT CONVERTED

More information

SECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT SECTION 230548 - VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information