Embedded Turnouts for the Hiawatha LRT Project. Author: David F. Peterson, PE. Parsons Corporation
|
|
- Antonia Greer
- 5 years ago
- Views:
Transcription
1 Embedded Turnouts for the Hiawatha LRT Project Author: David F. Peterson, PE Parsons Corporation Design Manager, Hiawatha Light Rail Transit Project September 30, 2003
2 ABSTRACT Installation and maintenance of turnouts in paved areas have always been something to avoid for both railroads and transit agencies. For the development of the Hiawatha Light Rail Transit Project, a key element is at-grade rail access to downtown Minneapolis. The present north end in downtown requires crossovers in Fifth Street and Nicollet Mall, a confined area congested with utilities and vehicular traffic. Embedded turnouts turnouts installed in paving are required in this and other locations along the Hiawatha corridor. Minnesota Transit Constructors (MnTC), the design-build contractor for the Hiawatha Project Office, elected to use #6 flexive double tongue switches for paved areas. This European Edgar Allen switch design differs from AREMA standard double tongue turnouts by having a flexible switch point set in a fixed casting, a transit type design also being used in Tampa s new LRT system. For containment of stray electrical current to prevent corrosion of nearby infrastructure, the embedded track is electrically isolated. The turnout is constructed in a concrete tub comprised of concrete and insulating membrane and sealed with elastomeric grout. The turnout and tub are constructed with
3 three concrete pours, with the insulating membrane installed between the first and second pours. In most cases, the turnouts are power operated with switch machines between the switch point castings, and heated with calrod-type electrical resistance heaters. The turnouts were fabricated by Progress Rail Services and will be installed by MnTC s subcontractor Railworks Track Systems in early to mid 2003.
4 1. INTRODUCTION Construction and operation of turnouts in paved areas have always been a lessthan-desired alternative to ballasted designs. These embedded turnouts require closer construction tolerances and higher maintenance and are avoided when possible. The Hiawatha Light Rail Transit project in Minneapolis and Bloomington, Minnesota is currently under construction. Hiawatha is a new system linking downtown Minneapolis with the Minneapolis St. Paul International Airport and the Mall of America in Bloomington. The line is approximately 12 miles in length and includes seventeen stations located in commercial and residential areas. Low floor Bombardier light rail vehicles will operate at up to 55 mph at 7 ½ minute headways at peak travel periods. The system requires six embedded crossovers, primarily at the end points of the system to cross trains over for return movements. The design-build contractor, Minnesota Transit Constructors (MnTC), worked closely with the representatives of the Hiawatha Project Office (HPO) to identify
5 the most appropriate embedded track and turnout system for the Hiawatha LRT system. 2. TURNOUT EVALUATION The HPO s two agencies the Minnesota Department of Transportation and Metro Transit, decided during the design development process to use tee rail in lieu of girder rail for embedded track applications. This in turn led to discussions of alternative types of turnouts. AREMA s Portfolio has two embedded turnout types that in the past have been used both for railroad and light rail transit applications. (See Portfolio Plan No and other referenced plans). These turnouts, using tongue and mate and double tongue switches, would have performed satisfactorily. However, these turnout designs are traditionally intended for railroad use, and considering the lower axle loads of Light Rail Transit (LRT) applications, other options were considered. During the evaluation of turnout options during design development, the HPO and MnTC considered the embedded switches manufactured by Edgar Allen Limited in the United Kingdom. Edgar Allen s switches are currently in use by Tampa, Florida s Hartline system and are being installed in New Orleans streetcar system. They are also in use in Sheffield and Manchester, England
6 and Hong Kong. These flexive tongue designs are ideal for paved track applications and can provide maintenance advantages. Flexive tongue turnouts involve a solid manganese steel body with a flexible manganese tongue, acting as the switch point, fastened to the body by two screws. The tongue is easily removed for maintenance or replacement without removing the entire unit. Electrical resistance heaters (calrods) can be placed along the sides or underneath the manganese castings. 3. METALLURGY Edgar Allen s flexive tongue turnouts were introduced in 1992 for the Sheffield Supertram system in the UK. The Supertram system opened in 1995, and Edgar Allen supplied turnout points and castings for six 25m and three 100m radius turnouts. Both the manganese points and bodies are rated at a Brinell Hardness of approximately 250 at manufacture Edgar Allen reports that in the five years after opening of the Supertram system the bodies and points have work hardened to approximately 400 BHN. The castings and points are manufactured using austenitic manganese steel. 4. TURNOUT DESIGN CONSIDERATIONS
7 The Hiawatha designers evaluated other aspects of the turnout design that would ultimately impact the performance of the turnouts. These factors should be considered for any transit project that requires turnouts in paved areas. a. Paving Depending upon whether vehicles will actually drive upon the turnout, careful consideration should be taken regarding the type of paving to be used around the rails and other turnout components. For Hiawatha, it was decided to use portland cement concrete islands between the rails, with asphalt cement concrete infill to approximately six inches from the rail head. This would give better support to the traffic that could potentially cross the turnout and was considered more aesthetically attractive. Based upon discussions with other transit properties, it was decided that using portland cement concrete against the rail would not perform well due to movement of the rail against the concrete, potentially breaking the concrete. It could also present problems with replacement of rail and turnout components and might not provide satisfactory rail to rail insulating properties. b. Electrical Isolation The embedded track for the Hiawatha system was insulated from the ground to protect adjacent utilities and structures from electrical corrosion by using the
8 rubber boot system manufactured by the Iron Horse Corporation cast in portland cement concrete. The turnouts, however, could not use the boot system due to the irregular size and shape of frogs, switch castings, and plates. As a result, the embedded turnouts were constructed in insulated concrete tubs, which are comprised of reinforced concrete with a rubberized isolation liner with protection board. The rails as they enter the tubs are themselves isolated with bulkheads perpendicular to the track. The turnout materials, including rail, plates, frogs, switch machines, switch castings, and the concrete islands discussed above are installed in the tub. Rail and switch components are mounted on elastomeric grout pads that provide additional insulation and shock resistance. c. Switch Machines The Hiawatha LRT system, as currently designed, has six crossovers in embedded track. Four crossovers are powered using Hanning & Kahl (H&K) switch machines, and the other two crossovers use hand throw turnouts. Spring switches, although common on other systems, were not utilized for operational reasons. The power switches are powered by H&K Model HW(E)61V. The switch machines are located between the switch casting and each switch machine box is drained with non-conducting PVC pipe to the storm drainage system. Power and signal conduit to the switch machine and turnouts run through the isolation
9 membrane and are insulated. Both bonded and poly bar insulated joints are used and are identical to those in standard track applications. Hand throw switch boxes are also located between the switch castings. d. Switch Heaters Since Minnesota winters are long and cold with plenty of snow, the embedded turnouts will be heated using electrical resistance heaters (calrods). There was considerable discussion within the design team regarding whether to install the heaters along the side of the switch castings or underneath. There is no ideal way to heat the switches, since the heaters will be in contact with other materials such as asphaltic concrete or elastomeric grout. Discussions with other transit properties revealed that both methods of heating are used. The Hiawatha designers decided to place two heater rods in metal conduits under each casting, above the concrete and far enough away from the elastomeric grout pads to avoid overheating of the pads. The heater rods can be pulled out of the conduit and replaced without removing the switch casting or conduit. By installing the heater rods underneath, it avoids the inevitable melting of asphalt concrete along the side of the casting, and the dual heater rods provide redundancy. e. Drainage
10 The paved areas in downtown Minneapolis and suburban Bloomington are generally flat and drainage is a challenge. In warm climates, poor drainage in embedded turnouts can be a nuisance in Minnesota, with long periods of subfreezing weather, frozen switch mechanisms could put a turnout out of service for months. The embedded turnout tubs and embedded trackbed are provided surface drainage and the switch machine boxes are also drained. Switch heater rods will be placed in the switch drains to keep them clear during the winter season. 5. CONSTRUCTION METHODS At the time of this writing, the embedded turnouts for the Hiawatha LRT project are under construction. The construction of the turnouts is very time consuming compared to construction of ballasted turnouts and takes several months from start to finish. The construction of the turnouts can be discussed in terms of the three concrete pours, as follows: a. First Pour The Isolation Tub The reinforced concrete isolation tub is constructed on select base material, with conduits in place for drainage and systems (traction power and signal) facilities. The first concrete pour is eight inches thick, with walls up to top of rail longitudinally on the field side of the rails, and with the concrete bulkheads to top of rail between the rails at the ends of the tubs.
11 After placement of the concrete, the isolation liner is placed on the bottom and sides of the tub. The rubberized liner is heat welded and the welds electrically tested. The liner is installed with one-eighth inch thick protection board on both sides of the liner. The following exhibits show the details of the turnout design. The three stages of construction, labeled First Pour, Second Pour, and Final Pour are included. The concrete pour for that phase is cross-hatched in the cross sections. Plan View Isolation Tub for Crossover Hiawatha LRT Design-Build PAVEMENT INFILL TRANSVERSE C OF CROSSING L B CONCRETE 1 MIN C L TRACK NO. 6 TURNOUT WITH DOUBLE TONGUE SWITCH PER SPEC MIN. A SWITCH DRAIN (AT EACH SWITCH) PS C SWITCH AND COVER PLATE FLOW 2-0 MIN. 9º31 38 PITO TUB DRAIN (AT LOW END) CONCRETE 2-0 (MIN.) SWITCH BLOCK OUT C DETAIL A 4-0 MIN. 7 - MAX FLOW POURED POLYMETRIC JOINT SEAL FOR LESS THAN 2 GAP IN RAIL HEAD B CONCRETE PAVEMENT INFILL C L TRACK 38 MAX. A EMBEDDED TRACK SLAB Exhibit I, Plan View, Isolation Tub
12 Hiawatha LRT Design-Build Isolation Tub First Pour PAVEMENT 3-0 MIN. 6 1% 1% #4 REBAR 18 ON CENTER L TRACK ALONG C L TRACK C L TRACK 4 VARIES ½ GAUGE 18 CONCRETE 4-8 ½ GAUGE CONST. IN FILL JOINT LEVEL PCC 2 1/2 CLEAR 3 CLEAR 1% 3-0 MIN. INSET CURB AND GUTTER AND SIDEWALK 1 4 x 4 CHAMPHER 2 ISOLATION MEMBRANE PROTECTION 2 BOARD 3 ISOLATION TUB 1 AGGREGATE BASE, CLASS 5 (02211) NON-FROST SUSCEPTIBLE SOIL ELASTOMER GROUT Exhibit II, Isolation Tub, First Pour Hiawatha LRT Design-Build Section D-D End of Isolation Slab TUB EMBEDDED TRACK SLAB SPECIAL TRACKWORK PLATE WITH E.G. PAD 1 115RE RAIL #5 BETWEEN RAILS BEND UP #6 BAR HORIZ. REINF. 4 x 4 ISOLATION SLAB CHAMFER TOP OF RAIL 2 ELASTOMER GROUT SEAL FOR MEMBRANE EDGE 1 EXPANSION JOINT MATERIAL AND SEALER #6 BETWEEN RAILS TUB REINFORCEMENT PROTECTION BOARD #6 TOTAL 3 EPOXY COATED # ISOLATION MEMBRANE TUB (WORKING SLAB) 9 Exhibit III, End of Isolation Slab b. Second Pour Support for the Rail
13 A strongback system and jacks are used to support the assembled turnout in the proper line and grade prior to the second concrete pour. Anchor bolts and inserts for the turnout plates are placed in the plates in position for embedment in the concrete. Plastic caps are placed over each of the e-clips to prevent fouling during the concrete pour and for protection afterward when asphalt is placed against the rail. Hiawatha LRT Design-Build Isolation Tub Second Pour PAVEMENT 3-0 MIN. 6 1% 1% #4 REBAR 18 ON CENTER L TRACK ALONG C L TRACK C L TRACK 4 VARIES ½ GAUGE 18 CONCRETE 4-8 ½ GAUGE CONST. IN FILL JOINT LEVEL PCC 2 1/2 CLEAR 3 CLEAR 1% 3-0 MIN. INSET CURB AND GUTTER AND SIDEWALK 1 4 x 4 CHAMPHER 2 ISOLATION MEMBRANE PROTECTION 2 BOARD 3 ISOLATION TUB 1 AGGREGATE BASE, CLASS 5 (02211) NON-FROST SUSCEPTIBLE SOIL ELASTOMER GROUT Exhibit IV, Isolation Tub, Second Pour The concrete is placed within the tub to a level one inch below the turnout plates. The one inch vertical gap will be filled with elastomeric grout, which provides electrical isolation and support for the plates, after the second pour concrete is
14 cured. The reinforcement in the second pour is of course separate of the reinforcement in the first pour due to the design of the isolation liner, but hoops of rebar are included in second pour to secure the islands above, which are part of the third pour. c. Third Pour Concrete Islands While elastomeric grout is being poured under the turnout plates, systems work can be done, including bond wires to rails for power feeds and signals, setting and adjusting the switch machines, and installing and testing the insulated joints. The third and last concrete pour brings the concrete between the rails and on the field side of the rail against the isolation liner to top of rail. Hiawatha LRT Design-Build Isolation Tub Final Pour PAVEMENT 3-0 MIN. 6 1% 1% #4 REBAR 18 ON CENTER L TRACK ALONG C L TRACK C L TRACK 4 VARIES ½ GAUGE 18 CONCRETE 4-8 ½ GAUGE CONST. IN FILL JOINT LEVEL PCC 2 1/2 CLEAR 3 CLEAR 1% 3-0 MIN. INSET CURB AND GUTTER AND SIDEWALK 1 4 x 4 CHAMPHER 2 ISOLATION MEMBRANE PROTECTION 2 BOARD 3 ISOLATION TUB 1 AGGREGATE BASE, CLASS 5 (02211) NON-FROST SUSCEPTIBLE SOIL ELASTOMER GROUT Exhibit VI, Isolation Tub, Final Pour
15 The approximately six inch gap between the ball of the rail and the island concrete will be filled in later to top of rail, along with a flangeway, with an asphalt concrete infill to finish the work. 6. SUMMARY The embedded turnouts for the Hiawatha project will be operated in a harsh weather environment and will be critical to the successful operation of the system. The Edgar Allen turnouts, while fairly new to North American transit systems, have been proven to be reliable in Europe and its design should perform well in street conditions in Minneapolis and Bloomington.
SECTION RIGID PAVEMENT
SECTION 02750 PART 1 GENERAL RIGID PAVEMENT 1.1 SUMMARY A. Section Includes: 1. Concrete sidewalks. 2. Concrete stair steps. 3. Concrete integral curbs gutters. 4. Concrete parking areas and roads. B.
More informationSECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS
SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More informationAsphalt on Concrete Base with Waterproofing Membrane
CABLES CANNOT BE IN DIRECT CONTACT WITH THE WATERPROOFING MEMBRANE! CABLES WILL BURNOUT, AND THE MEMBRANE WILL MELT. 7 5 4 6 1 2 3 NOTES: 1) CLEAN CONCRETE SURFACE 2) HOT MEMBRANE WATERPROOFING 3) ASPHALTIC
More informationB. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.
SECTION 1400 - CONCRETE PAVEMENT 1401 SCOPE. This section governs the furnishing of all labor, equipment, tools, and materials and the performance of all work necessary to construct concrete pavement.
More information2004 Specifications CSJ SPECIAL SPECIFICATION DIRECT FIXATION TRACK CONSTRUCTION
2004 Specifications CSJ 0920-38-250 SPECIAL SPECIFICATION 7660 DIRECT FIXATION TRACK CONSTRUCTION 1. Description. This section specifies the construction of direct fixation (DF) track to the lines and
More informationSECTION CONCRETE PAVING
SECTION 32 13 13 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for providing portland cement concrete work and all other incidental concrete improvements for the project
More informationGEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT
PLACE TWO STANDARD CONNECTORS IN EACH UNIT AS SHOWN (VERTICAL ORIENTATION) INSERT TWO CONNECTORS PER HORIZONTALLY ORIENTED BLOCK; INSERT ONE CONNECTOR PER VERTICALLY ORIENTED BLOCK SHIM BETWEEN BLOCK COURSES
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS
More informationEntellus 75 NORTH STREET MERRILL SHERIFF CONSTRUCTION. 181 North 200 West, Suite #4. Bountiful, UT Phone
Entllus DUMPSTER PAD AND REPLACE WITH NEW BETWEEN THESE TWO POINTS SAWCUT ALONG DEMO LINE REMOVE PARKING SPOTS CURB, GUTTER, ASPHALT AND LANDSCAPING, WITHIN HATCHED AREA FOR NEW ADDITION CURB & GUTTER
More informationSECTION MINOR CONCRETE
SECTION 03300 - MINOR CONCRETE CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And Payment...
More informationStructural - Engineering Review Checklist
Structural - Engineering Review Checklist Project: List Corridor Criteria ID Review Priority (H,M,L) TOPICS S-_-## Structural Design Codes, Manuals and Specifications 6.1.0 REFERENCES DESIRED Criteria
More informationSECTION EMBEDDED TRACK CONSTRUCTION
CONTRACT SPECIFICATIONS PART 1 - GENERAL 1.01 SUMMARY A. This Section includes specifications for the construction of insulated embedded track as indicated on the Contract Drawings. Embedded track construction
More informationD-1 THE CITY OF HARRISBURG 1 1/2" MIN. ID-2 WEARING COARSE EXISTING STREET SURFACE AC-20 SEALER (ALL AROUND) 1 1/2" MIN. ID-2 BINDER COARSE
EXISTING STREET SURFACE 1 1/2" MIN. ID-2 BINDER COARSE 1 1/2" MIN. ID-2 WEARING COARSE AC-20 SEALER (ALL AROUND) 8" CLASS A P.C. CONCRETE SAW CUT TOP OF CONCRETE SHALL MEET SURFACE OF EXISTING CONCRETE.
More informationDIVISION 34 TRANSPORTATION SECTION SPECIAL TRACKWORK ADDENDUM NO. 1
PART 1 - GENERAL 1.01 RELATED WORK SPECIFIED ELSEWHERE A. The provisions and intent of the Contract, including the General Conditions and General Requirements, apply to this work as if specified in this
More informationPART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER
PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER COMMUNICATIONS LIGHTING Street Lighting Plan 710 Riser... 287 730 Collar for street light pole... 289 731 Pull box... 291 732 Trench for street light
More informationSECTION CONCRETE PAVING
PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 13 13 CONCRETE PAVING A. Extent of concrete curbs, walks, and paving as show on drawings B. Earthwork and prepared sub-base C. Concrete and related materials
More informationSECTION STORM DRAINAGE
SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation
More informationCITY OF SAN ANGELO ITEM 360 CONCRETE PAVEMENT
ITEM 360 360.1. DESCRIPTION. CITY OF SAN ANGELO ITEM 360 This item shall govern for the construction of Portland Cement Concrete pavement with or without monolithic curbs on a prepared subgrade or sub-base
More informationSECTION PORTLAND CEMENT CONCRETE
PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including the supplemental documents as indicated in the Site Work General Provisions, apply to work of this
More informationRak Production Technology of Concrete Structures (2015) Concrete Reinforcement
Rak-82-2121 Production Technology of Concrete Structures (2015) Concrete Reinforcement 09.10.2015 1 Learning Outcomes To acquaint the student with concrete reinforcement 2 Reinforcement The of concrete
More informationWall Panels. Structural wall panel. Architectural wall panel. Cladding wall panel. Sandwich wall panel
Wall Panels Structural wall panel Architectural wall panel Cladding wall panel Sandwich wall panel Wall Panels Assorted styles and colours Reveals and other patterns Painted finish Bolted, welded and knife
More informationA. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork.
DIVISION 03 CONCRETE 03 0100 MAINTENANCE OF CONCRETE 03 0505 UNDER SLAB VAPOR BARRIER A. Sheet vapor retarder shall be polyethylene sheet, ASTM D 4397, 10 mils thick minimum. Consult with Facilities Management
More informationlbfoster.com CXT CONCRETE TIES CATALOG
CXT CONCRETE TIES CATALOG L.B. Foster offers a complete line of CXT concrete railroad ties. Our catalog of concrete ties includes standard track, turnout, gantry and specialty ties, such as guard rail,
More informationSECTION FABRICATED ENGINEERED STRUCTURES. A. Pre-engineered, shop-fabricated structural steel building with formed purlin framing.
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 13 34 00 FABRICATED ENGINEERED STRUCTURES A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1
More informationSECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section
02670-1 of 6 SECTION 02670 CURB, COMBINATION CURB AND GUTTER, AND 02670.01 GENERAL A. Description This work shall include, but not necessarily be limited to, the construction of concrete curb, concrete
More informationSENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES
SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES Safety Precautions in the Excavation of a Sentinel Wedge take all necessary steps to make sure the pit is secured. Follow all OSHA requirements for digging
More informationFundamentals of Jointing for Volume Change in Concrete
Fundamentals of Jointing for Volume Volume Changes in Concrete Concrete is at its greatest volume when it is freshly placed. As the concrete cures and hardens, water is consumed in the chemical reaction
More informationTABLE OF CONTENTS. Appendices are not a mandatory part of this specification unless invoked by the Owner.
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 920 NOVEMBER 2005 CONSTRUCTION SPECIFICATION FOR DECK JOINT ASSEMBLIES, PREFORMED SEALS, JOINT FILLERS, JOINT SEALS, JOINT SEALING COMPOUNDS, AND WATERSTOPS
More information1.02 RELATED WORK: Refer to the following sections for related work:
SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete
More informationSECTION CONCRETE REINFORCEMENT
PART 1 GENERAL 1.01 DESCRIPTION SECTION 03200 CONCRETE REINFORCEMENT A. The work specified in this Section consists of furnishing and installing reinforcement for concrete structures. All reinforcement
More informationSECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT. A. ASME B31.1 (American Society of Mechanical Engineers) - Power Piping
SECTION 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section includes pipe and equipment supports, hangers, anchors, bases sleeves and the sealing of
More informationSECTION HANGERS AND SUPPORTS FOR PLUMBING
SECTION 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationSECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT
Page 220548-1 SECTION 220548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationSECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT
Page 230548-1 SECTION 230548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationPublic Works Manual. Revised September Concrete & Asphalt
Public Works Manual Revised September 2015 Concrete & Asphalt Where it must cross domestic it must cross above and with a 1 minimum separation. Nonpotable water tape. 10.00 PORTLAND CEMENT CONCRETE 10.01
More informationLight-Metal Roof Edge, Raised
NAIL WOOD CANT TO BLOCKING 2 ROWS STAGGERED EACH ROW 24 O.C. 1/2 MIN. 10 0 MAX. FASTEN 18 O.C. WITH NEOPRENE GASKETED FASTENERS 3-1/2 MIN. 4 6 JOINT COVER PLATE SET IN TWO BEADS OF SEALANT 4 MIN. SPECIFIED
More informationDEFENDER. Installation Manual
DEFENDER Installation Manual 1 DEFENDER SERIES BOLLARDS GENERAL INSTALLATION GUIDELINES (Unless otherwise specified) 1.0 BOLLARD BARRIER FOUNDATION DETERMINE VEHICLE BARRIER LOCATION AND PREPARE EXCAVATION/FOUNDATION
More informationHITT STREET UNIVERSITY PROJECT #: CP REFER TO CP PLANS FOR ELECTRICAL DUCTBANK IN HITT STREET INSTALL:
N 1133521.33 E 1689742.43 STA: 10+53.07 INSTALL: 2-10" 90 BENDS CONNECT TO MIDDLEBUSH HALL INTERIOR PLANT PLUMBING MIDDLEBUSH HALL HW1 HWS HWR 10+00 FREDRICK APARTMENTS FINE ARTS INSTALL 422 LF 10" HWS
More informationTECHNICAL SPECIFICATION
TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing
More informationThe Most Advanced Name in Water Management Solutions TM. The most cost-effective slotted and trench surface drain systems.
The Most Advanced Name in Water Management Solutions TM The most cost-effective slotted and trench surface drain systems. A sensible alternative to metal and concrete Since 1987, Duraslot surface drains
More informationTrack & Services Co., Inc.
Track & Services Co., Inc. Company Profile A Joint Venture of With over 80 years of experience, Atlantic Track & Turnout is a major supplier of single source solutions to American railroad and transit
More informationSECTION 12 INDEX CONCRETE CURBS AND GUTTERS
SECTION 12 INDEX CONCRETE CURBS AND GUTTERS 1. SCOPE OF WORK. 12-2 2. MATERIALS. 12-2 3. CONSTRUCTION REQUIREMENTS.. 12-2 12-1 SECTION 12 CONCRETE CURBS AND GUTTERS 1. SCOPE OF WORK: This work shall consist
More informationCONCRETE WALKS AND CURBS SECTION CONCRETE WALKS AND CURBS PART 1 - GENERAL
13686.00 CONCRETE WALKS AND CURBS 033015-1 1.1 RELATED DOCUMENTS: SECTION 033015 CONCRETE WALKS AND CURBS PART 1 - GENERAL A. Drawings and general provisions of Contract, including General and Supplementary
More informationSECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT
SECTION 230548 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Elastomeric Isolation pads. 2. Elastomeric Isolation mounts. 3. [Freestanding] [Restrained] [Freestanding and restrained]
More informationIN2 Sleeves and Sleeve Seals for Communications Pathways and Cabling
Illinois Math and Science Academy DigitalCommons@IMSA Project Manuals IN2 2015 IN2 Sleeves and Sleeve Seals for Communications Pathways and Cabling Illinois Mathematics and Science Academy Follow this
More informationSection CONCRETE PAVEMENT
PART 1 GENERAL 1.01 SUMMARY Section 03002 This section includes construction of concrete pavement for roadways, driveways, turnouts, concrete medians, directional islands, sidewalks and curbing when Harris
More informationCurrent Standard Plates including Transmittal Letters are available on the web at:
MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards ISSUED BY: Office of Project Management and Technical Support, Design Support Section TRANSMITTAL LETTER NO. (6-03) MANUAL: Standard
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE
CITY OF TORONTO STANDARD CONSTRUCTION SPECIFICATIONS FOR ROADS TS 3.40 November 2009 CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE INDEX TS 3.40.01 SCOPE... 3 TS 3.40.02 REFERENCES... 3 TS 3.40.03
More informationLight Rail Transit Tracks in Pavement
Light Rail Transit Tracks in Pavement ROBERT E. CLEMONS ne of the important features of light rail transit (LRT) is the () ability to locate tracks in downtown streets and transit malls, thus eliminating
More informationDENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION CHAIN LINK FENCING
PART 0 DESIGN STANDARDS 0.01 GENERAL DESIGN GUIDELINES A. Requirements vary. A/E shall consult with DPS project manager to determine extent and type of permanent site fencing to be employed. B. Provide
More informationIN2 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
Illinois Math and Science Academy DigitalCommons@IMSA Project Manuals IN2 2015 IN2 Sleeves and Sleeve Seals for Electrical Raceways and Cabling Illinois Mathematics and Science Academy Follow this and
More informationDIVISION 03 CONCRETE. Number CONCRETE
03 00 00 CONCRETE 03 10 00 CONCRETE FORMING AND ACCESSORIES 03 11 00 Concrete Forming 03 11 13 Structural Cast-in-Place Concrete Forming 03 11 16 Architectural Cast-in-Place Concrete Forming 03 15 00 Concrete
More informationCW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS
December 2012 CW 3240 RENEWAL OF EXISTING CURBS TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications... 1 1.4 Referenced Standard
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 22 0548 - PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationFiber Reinforced Polymer (FRP) Panels for Rail Station Platforms
Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms Introduction Scott Reeve, President, Composite Advantage Dayton, Ohio Engineered Solutions and Products for Infrastructure Large parts High
More informationSUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017
SUMMARY OF PUBLIC WORK STANDARD SPECIFICATION REVISIONS 2017 STANDARD SPECIFICATIONS 102.12 Best Value Contracting Partial payments shall be withheld if contractor is working on site and has not satisfied
More informationSECTION CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS
SECTION 32 05 23 PART 1 - GENERAL 1.1 DESCRIPTION A. This section shall cover site work concrete constructed upon the prepared subgrade and in conformance with the lines, grades, thickness, and cross sections
More informationSR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five
SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed Florida Department of Transportation District Five Project Overview Location SR 600 / US 92, Volusia County FPN:
More informationBitumen Softboard. Applications: Physical Properties: Jolly Bitulex Expansion Joint Fillers conform to the following required standards
Bitumen Softboard Jolly Bitulex Softboard is processed from cane fibre, the raw material tested and proven to provide the best resilience. Impregnated with Bitumen in various percentages, it is a perfect
More informationCONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS
More informationBLACK RIVER RAILROAD SYSTEM 2015 TRACK STANDARDS & SPECIFICATIONS
WOOD TIES 2015 TRACK STANDARDS & SPECIFICATIONS FOR NEW CONSTRUCTION & UPGRADES Ties shall be new 7"x 9" x 8' 6" creosoted grade hardwood. All new ties shall be spiked with four (4) new spikes and box
More informationCONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT SPECIFICATION EO-1007 REVISION 13 DECEMBER 2013 EFFECTIVE DATE DECEMBER 16,
More information2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL
SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of
More informationCOUNTY OF BEXAR. Curbed Streets. Residential PUBLIC WORKS DEPARTMENT
COUNTY OF BEXAR PUBLIC WORKS DEPARTMENT 233 N. Pecos La Trinidad, Suite 420 San Antonio, Texas 78207-3188 Main 210-335-6700 DRIVEWAY APPROACH SPECIFICATIONS Curbed Streets Residential Applicability: All
More informationSECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS. A. Formwork complete with shoring, bracing and anchorage.
SECTION 02528 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.01 WORK INCLUDED A. Formwork complete with shoring, bracing and anchorage. B. Concrete reinforcement complete with required supports,
More informationITEM 555 CHAIN LINK FENCING
ITEM 555 AFTER MARCH 1, 2012 CHAIN LINK FENCING 555.1 Description. This item shall govern for furnishing the quantities of chain link fencing and gates as shown on the plans, including all posts, bracing
More informationSECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.
PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Handrails and guardrails. 1.2 PERFORMANCE REQUIREMENTS A. General: In engineering railings to withstand structural loads indicated, determine
More informationSPECIAL PROVISION Concrete Pavement
1995 Metric CSJ s 0902-48-305, etc. SPECIAL PROVISION 360---036 Concrete Pavement For this project, Item 360, Concrete Pavement, of the Standard Specifications, is hereby amended with respect to the clauses
More informationSECTION HANDRAILS AND RAILINGS. A. Section Metal Fabrications: Associated metal supports.
SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Handrails and guardrails B. Guardrails for hatches and openings. C. Safety barriers. D. Roof edge protection. 1.2 RELATED SECTIONS
More information2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.
JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine
More informationDIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK
DIVISION 03 CONCRETE SPECIFICATION 031000: FORMS AND FORMWORK PART 1.0 GENERAL 1.1 DESCRIPTION The work of this specification includes furnishing of all labor, materials, equipment and incidentals to install,
More informationCONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS
Underground Electric Distribution Standards I. SCOPE This section includes the standards for concrete, reinforcing steel, formwork, concrete placement, curing, and construction joints. Concrete work for
More informationSECTION ORNAMENTAL ALUMINUM RAILING
SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Pipe Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in concrete.
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB #
SECTION 26 0529 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
More informationConstruction Specification for Concrete Bus Pad
Engineering & Construction Services Division Standard Specifications for Road Works TS 3.41 June 2017 for Concrete Bus Pad Table of Contents SCOPE... 3 REFERENCES... 3 DEFINITIONS... 3 DESIGN AND SUBMISSION
More informationCONCRETE BARRIER R-49-G TYPE A BARRIER MICHIGAN DEPARTMENT OF TRANSPORTATION 20'-0" MAXIMUM BETWEEN JOINTS 8'-0" TAPERED SECTION (SEE NOTES)
- SPLIT 8'-0" TAPERED SECTION A B 40" A B " EXPANSION JOINT AT BEGINNING AND END OF SPLIT SECTIONS SEE EXPANSION JOINT DETAIL PLAN CONSTRUCTION STATIONING SHALL BE PLACED ON BOTH SIDES OF THE BARRIER.
More informationINSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM)
INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM) TABLE OF CONTENTS 1. INTRODUCTION TO THE MODULAR EXPANSION JOINT 1.1 Purpose 1.2 How They Work 1.3 Movement Capacity 1.3.1 Longitudinal Direction
More informationRESTORATION SPECIFICATION
In proposed subdivision roadways where other utilities are present, the design plans should illustrate all possible utility line conflicts (crossings). During design and construction, care shall be utilized
More informationPASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017
SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationFOR PROJECTS INITIATED AFTER FEBRUARY 1, 2010 REVISION 3 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS
AFTER FEBRUARY 1, 2010 ITEM 530 CONCRETE CURB, GUTTER, CURB AND GUTTER SIDEWALKS AND DRIVEWAYS 530.1 Description. This item shall govern for curb, gutter, combined curb and gutter, sidewalks and/or driveways,
More informationINSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!
DURA - TRENCH INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation
More informationGUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410
GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific
More informationBallast Mats ATP-DR Profiled
Ballast Mats ATP-DR Profiled Trelleborg ATP-DR Ballast Mat For Transit, Commuter or Railroad use, the Ballast Mat is designed to: Reduce degradation of ballast where depth is restricted By reducing ballast
More informationWastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 PRECAST CONCRETE PIPE 10.1.1 General This section covers material requirements,
More informationCounty of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS
County of Sacramento Standard Construction Specifications January 1, 2008 TECHNICAL PROVISIONS SECTION 27 CURBS, GUTTERS, SIDEWALKS, AND DRAINAGE STRUCTURES 27-1 GENERAL Concrete curbs, gutters, sidewalks,
More informationTILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:
PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral
More informationITEM 432 TUNNEL CONSTRUCTION
AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.
More informationCritical Structures Construction Issues
Critical Structures Construction Issues FLORIDA DEPARTMENT OF TRANSPORTATION STATE CONSTRUCTION OFFICE Specification 1-3: Definitions Contractor s Engineer of Record Specialty Engineer CLASS OF CONTRACTOR
More informationROOF DRAINS TABLE OF CONTENTS
Pictorial Index Product Recommendations Roof Drain Selection Factors Sizing Placement Material & Characteristics Pipe Connection Commonly Specified Options Typical Installations TABLE OF CONTENTS ROOF
More informationLANE ENTERPRISES, INC. STANDARDS & SPECIFICATIONS
LANE ENTERPRISES, INC. STANDARDS & SPECIFICATIONS The following pages are an index of standards and specifications associated with Lane products. For quick reference purposes, Lane products are shown below
More informationB. American Society for Testing and Materials: 1. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe Hangers.
SECTION 230529 - HANGERS AND SUPPORTS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe hangers and supports. 2. Hanger rods. 3. Inserts. 4. Flashing. 5. Sleeves. 6. Mechanical sleeve seals. 7. Firestopping
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS
PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment
More informationDIVISION 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 - GENERAL RELATED DOCUMENTS
PART 1 - GENERAL 01.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this Section.
More informationBILL OF QUANTITIES. Construction and Rehabilitation of wadi Gaza Bridges PAL Funded by Government of Brazil
United Nations Development Programme Programme of Assistance to the Palestinian People-PAPP Construction and Rehabilitation of wadi Gaza Bridges PAL10-00054031 Funded by Government of Brazil BILL OF QUANTITIES
More informationPage 1 March 2014 Catholic District School Board of Eastern Ontario C&A Project No
SI. Edwards Catholic School Concrete Formwork Section 03100 Page 1 1 GENERAL 1 RELATED WORK Concrete Reinforcement Cast-in-place Concrete Concrete Curbs and Walks Concrete Floor Finishes Section 03200
More informationPrecast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS
Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS GENERAL INSTALLATION INSTRUCTIONS 1 Ensure that the trench where the channels are going to be installed has enough room for the appropriate
More informationCOMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN
GENERAL NOTES DESIGN TABLE NOTES INDEX OF SHEETS 1. ALL DIMENSIONS ARE IN MILLIMETERS UNLESS OTHERWISE NOTED. U.S. CUSTOMARY UNITS IN ( ) PARENTHESIS.. ALL "DESIGN" METRIC UNITS INDICATED ARE SOFT CONVERTED
More informationSECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT
SECTION 230548 - VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
More information