1 AFTER NOVEMBER 1, 2008 ITEM 706 PIPE SLOPE DRAIN Description. This work shall consist of the installation of temporary erosion protection and sediment control pipe slope drains, utilized during construction operations and prior to final stabilization, in accordance with these specifications and construction drawings, and as directed by the Engineer Materials. Rip-rap shall consist of 6-inch diameter stone and shall be open graded with most of the fines removed. Stone shall be composed of clean, hard, durable material free from adherent coatings, salt, alkali, dirt, clay, loam, shale, soft or flaky materials, or organic and injurious matter. Galvanized steel pipe shall be full circle pipe conforming to AASHTO Designation M245. It may be fabricated with corrugations, lap joint construction with riveted seams, or it may be fabricated with helical lock seams. Gaskets are to be O ring type meeting the requirements of ASTM C 361. Diameter to be 13/16-inch for 1/2-inch deep corrugations. Gasket lengths shall be in accordance with the pipe manufacturer's recommendations. Coupling bands shall conform to the requirements of AASHTO M36. Width of connecting bands shall be in accordance with Texas Department of Transportation's specification titled "Corrugated Metal Pipe-Coupling Bands". Dimple bands will not be accepted Construction Methods. No clearing and grubbing or rough cutting, other than as specifically directed by the Engineer to allow for soil testing, surveying and installation of erosion protection and sediment control measures, shall be permitted until sediment control and erosion protection systems are in-place. Slope drains shall be installed at the locations shown on the construction drawings, in accordance with the drawing attached to this
2 Page -2- AFTER NOVEMBER 1, 2008 specification, and as directed by the Engineer. Pipe slope drains shall be constructed in accordance with an approved schedule that clearly describes the timing during the construction process that the various erosion control measures will be implemented. Soil around and under the entrance section shall be hand-tamped in maximum 8-inch lifts, to the top of the embankment. Subgrade shall be constructed to the required elevations. All soft sections and unsuitable material shall be removed and replaced. The subgrade shall be thoroughly shaped to a smooth uniform surface. The fill material for the embankment shall be free of roots, woody vegetation, oversized stones or rocks, or organic or other objectionable matter. The area under the embankment shall be cleared, grubbed, and stripped of vegetation and root material. The inlet pipe shall have a slope of 3-percent or greater. The pipe drain diameter shall be as indicated on the construction drawings. The top of embankment over the inlet pipe and other pipes carrying water to the inlet pipe shall be at least 1-foot higher, at all points, over the top of the inlet pipe. See the attached drawing. Compaction of embankments, excavations and trenches shall be by tamping and rolling soil to a minimum of 90% of standard proctor density (ASTM Method D 698). Embankments shall be compacted in maximum 8-inch lifts. The pipe shall be secured with hold-down grommets spaced 10-feet on center. The depth of the rip-rap apron shall be equal to the diameter of the pipe drain, with 2:1 side slopes. Rip-rap shall be placed in minimum 12-inch thick layers. The Contractor shall inspect slope drains at least once every fourteen calendar days and within 24-hours of the end of a storm event of 0.5 inches rainfall or greater. The Contractor shall repair damaged slope drain sections. The Contractor shall redress the outlet as needed and replace the stone at the outlet to replace depleted stone. The Contractor shall redress and restabilize stone as needed to maintain the specified
3 Page -3- AFTER NOVEMBER 1, 2008 thickness, height, and width. The Contractor shall remove sediment from the rip-rap apron, when the sediment has accumulated to one-half the pipe diameter or one foot, whichever is less, for the pipe slope drain. All erosion protection and sediment control systems shall be maintained by the Contractor, until final stabilization. Damage caused to erosion protection and sediment control systems shall be repaired immediately. Upon removal of the pipe slope drain, the area shall be graded as per the construction drawings and stabilized with vegetation. The Contractor is responsible for removal and disposal of sediment and debris from the pipe slope drain and as directed by the Engineer. Sediment shall not be allowed to flush into the storm sewer system, waterways, jurisdictional wetlands, or onto adjacent properties. Uncontaminated sediment can be placed at the project spoil site or, if properly handled spread out to supplement fill requirements. The Engineer will designate how the sediment deposits are to be handled. Uncontaminated sediment shall not be laced in waterways or jurisdictional wetlands, unless as approved by the Engineer. If sediment has been contaminated, then it shall be disposed of in accordance with the applicable federal, state and local regulations. Off-site disposal shall be the responsibility of the Contractor. After final stabilization and at the direction of the Engineer, the Contractor, when required, shall be responsible for removing all erosion protection and sediment control systems, that are not permanent, from the project Quality Assurance. The Contractor is responsible for the control of the quality of materials incorporated into the construction and quality of completed construction. The County will engage materials engineering services to provide quality assurance testing and inspection to assist the County Engineer in determining the acceptability of materials and completed construction. Quality assurance services provided by the County do not relieve the Contractor of his responsibility for quality control. The Materials Engineer shall not have control of the means, methods, techniques, sequences or procedures of construction selected by the Contractor.
4 Page -4- AFTER NOVEMBER 1, 2008 The Materials Engineer will determine the in-place density in accordance with ASTM D 2922 or ASTM D The minimum level of testing shall be one test per 500 linear feet of embankment Measurement and Payment. When paid for separately as a pay item, measurement and payment shall be paid for at the unit price bid for each pipe slope drain, complete in place. Payment for pipe slope drain will include and be full compensation for all labor, equipment, materials, supervision and for all incidental expenses for the construction of these items, complete in-place, including but not limited to embankment and excavation, protection of trees, maintenance requirements, repair and replacement of damaged sections, removal of sediment deposits, redressing of stones, and removal of erosion protection and sediment control systems after final stabilization. There are line code(s), description(s), and unit(s) for this item. Note: This specification requires a drawing. END OF ITEM 706
5 Page -5- AFTER NOVEMBER 1, 2008
6 Page -6- AFTER NOVEMBER 1, 2008
7 Page -7- AFTER NOVEMBER 1, 2008 SUMMARY SHEET ITEM PIPE SLOPE DRAIN Other Specifications Required: Item 725, General Source Controls Reference Standards: AASHTO M 245 ASTM C 361 AASHTO M 36 Description: Describes the method for constructing pipe slope drains. Payment: If paid for separately, paid for by each unit of pipe slope drain. DO NOT INCLUDE THIS SHEET IN CONTRACT SPECIFICATIONS.
ITEM 750 ROCK FILTER DAMS
AFTER MARCH 1, 2012 ITEM 750 ROCK FILTER DAMS 750.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control rock filter dams utilized during construction
More informationTECHNICAL SPECIFICATION
TECHNICAL SPECIFICATION ITEM 04821 TEMPORARY VEHICLE AND EQUIPMENT FUELING AREA PART 1 - GENERAL 1.01 Description Installation of erosion and sediment control for a temporary vehicle and equipment fueling
More informationITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS
ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing
More informationDIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012
2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include
More informationEROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY
31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed
More informationSECTION 18 - EARTHWORK TABLE OF CONTENTS
SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL...18.1 18-2 ROADWAY EXCAVATION...18.1 18-2.01 General...18.1 18-2.02 Unsuitable Roadway Excavation and Backfill...18.1 18-2.03 Surplus
More informationINDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1
March 2002 No. 400 INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS 400. 1 SCOPE... 1 400. 2 REMOVING CULVERTS AND TIMBER STRUCTURES 2.1 Concrete and Metal Pipe Culverts... 1 2.2 Structural
More informationSTANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL Section Number Title 801 GENERAL 802 STANDARD METHODS OF EROSION AND SEDIMENT
More informationSECTION 18 - EARTHWORK TABLE OF CONTENTS
SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL... 18.1 18-2 ROADWAY EXCAVATION... 18.1 18-2.01 General... 18.1 18-2.02 Unsuitable Roadway Excavation and Backfill... 18.1 18-2.03 Surplus
More informationItem 460 Corrugated Metal Pipe
Item 460 Corrugated Metal Pipe 1. DESCRIPTION 2. MATERIALS Furnish and install corrugated metal pipes, materials for constructing corrugated metal pipe culverts, or corrugated metal storm drain mains,
More informationSECTION EROSION CONTROL DEVICES
SECTION 02374 PART 1 GENERAL EROSION CONTROL DEVICES 1.1 SUMMARY A. Section Includes: 1. Diversion Channels. 2. Rock Energy Dissipator. 3. Paved Energy Dissipator. 4. Rock Basin. 5. Rock Barriers. 6. Sediment
More informationSECTION TRENCHING & BACKFILLING
SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications
More informationSPECIAL SPECIFICATION 4425 Thermoplastic Pipe
2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm
More informationSPECIAL SPECIFICATION 4653 Polypropylene Pipe
2004 Specifications CSJ 2158-01-013, Etc. SPECIAL SPECIFICATION 4653 Polypropylene Pipe 1. Description. Furnish and install polypropylene pipe for constructing polypropylene pipe culverts or polypropylene
More informationSECTION 18 - EARTHWORK TABLE OF CONTENTS
SECTION 18 - EARTHWORK TABLE OF CONTENTS Section Page 18-1 GENERAL... 18-2 18-2 ROADWAY EXCAVATION... 18-2 18-2.01 General... 18-2 18-2.02 Unsuitable Roadway Excavation and Backfill... 18-2 18-2.03 Surplus
More informationDIVISION 4100 SITEWORK
DIVISION 4100 SITEWORK SECTION 4115 EARTHWORK PART 1 - GENERAL 1.01 SCOPE This section covers the grading and compaction of excavations, embankments, structural foundations, and planted areas. 1.02 REFERENCES
More informationSPECIFICATION FOR PIPE CULVERT CONSTRUCTION
SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.
More informationSTANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING Section Number Title 301 GENERAL 302 MATERIALS SPECIFICATIONS 303 CLEARING
More information17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS
17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.1 Description The work covered by this section of the specifications consists of furnishing all labor, the construction and installation of open storm drain
More information378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE
378-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION 378 - POND I. SCOPE The work shall consist of constructing an earthfill embankment and appurtenances to the lines, grades,
More informationSECTION GENERAL EXCAVATION
02210-1 of 11 SECTION 02210 GENERAL EXCAVATION 02210.01 GENERAL A. Description 1. General excavation shall include but not necessarily be limited to, excavation and grading for general site work, roadways,
More informationSECTION UNDERDRAINS. 1. Protection of the environment; Section Trench excavation, backfill, and compaction; Section
02510-1 of 7 SECTION 02510 UNDERDRAINS 02510.01 GENERAL A. Description Underdrain installation shall include, but not necessarily be limited to, constructing underdrains using pipe, filter fabric, and
More informationB. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.
SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution
More informationSECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING
SECTION 334701 - WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. The Contractor shall provide all labor, materials, tools, and equipment required
More informationItem Name Description Unit of Measure Mobilization Per WSDOT Lump Sum
Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of
More informationConstruction Inspection Checklists
III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments
More informationSECTION 14 EMBANKMENT
SECTION 14 EMBANKMENT 14.1 DESCRIPTION A. General: This work consists of constructing roadway embankments, including preparation of the areas upon which embankments are to be placed; the construction of
More informationITEM P-156 TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTATION CONTROL DESCRIPTION
ITEM P-156 TEMPORARY AIR AND WATER POLLUTION, SOIL EROSION, AND SILTATION CONTROL DESCRIPTION 156-1.1 This item shall consist of temporary control measures as shown on the plans or as ordered by the Engineer
More informationEXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.
CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 02315-1 PART 1 GENERAL 1.1 Description of Work.1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto. 1.2 Related
More informationSECTION CURB, COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN. 1. Bituminous concrete pavement; Section
02670-1 of 6 SECTION 02670 CURB, COMBINATION CURB AND GUTTER, AND 02670.01 GENERAL A. Description This work shall include, but not necessarily be limited to, the construction of concrete curb, concrete
More informationCITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS
TEXAS STANDARD CONSTRUCTION NOTES DRWN. BY: DSGN. BY: KJW 1 of 2 *Place geotextile fabric as a permeable seperator to prevent mixing of coarse aggregate and underlying soil. (as needed). 1. GEOTEXTILE
More informationINDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2
INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...
More information1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK
1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for
More informationSECTION 303 CULVERTS
303.01 Scope - This section covers the construction of pipe culverts. 303.01.01 Definitions for the purposes of this section, the following general terms are defined as follows: a) Backfilling means the
More informationSECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.
PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and
More informationSECTION EROSION CONTROLS
SECTION 31 25 13 EROSION CONTROLS PART 1 GENERAL 1.1 SUMMARY A. Section Includes installing, maintaining and removing: 1. Silt Fence. 2. Temporary Construction Entrances. 3. Diversion Channels. 4. Sediment
More informationSECTION UNCLASSIFIED EXCAVATION AND GRADING
SECTION 02210 UNCLASSIFIED EXCAVATION AND GRADING PART 1 GENERAL 1.1 DESCRIPTION Work in this section includes the excavation, undercut excavating, grading, earthwork and compaction required as shown on
More informationSECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.
SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationSECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.
SECTION 02720 STORM DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-place Concrete. 1.02 REFERENCES
More informationSECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...
SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...
More informationPART 1 GENERAL REQUIREMENTS
PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...
More informationSOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO.
SOUTH GRANVILLE WATER AND SEWER AUTHORITY GENERAL DESCRIPTION OF COST ITEMS AND BID ITEMS FOR H STREET BY-PASS WATERLINE CONTRACT NO. 2017-1 43 SOUTH GRANVILLE WATER AND SEWER AUTHORITY H STREET BY-PASS
More informationCITY OF FARGO SPECIFICATIONS REMOVALS
REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation
More information***************************************************************************************************************
02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************
More informationCITY OF FARGO SPECIFICATIONS REMOVALS
REMOVALS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary to perform vegetation
More informationBase Course Design and Construction
Part I General A. This information is to be used as a guideline in construction a dynamic aggregate base and drainage system. Project conditions may vary based on overall scope of work and location. Any
More informationDiversion Dikes. Fe=0.95
2.2 Diversion Dike Erosion Control Description: A diversion dike is a compacted soil mound, which redirects runoff to a desired location. The dike is typically stabilized with natural grass for low velocities
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES
Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle
More informationDEPARTMENT OF TRANSPORTATION STATE OF GEORGIA SPECIAL PROVISION. Section 550 Storm Drain Pipe, Pipe-Arch Culverts, and Side Drain Pipe
Revised: October 25, 2007 Revised: June 11, 2010 DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA SPECIAL PROVISION Section 550 Storm Drain Pipe, Pipe-Arch Culverts, and Side Drain Pipe Delete Section 550
More informationExcavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.
Item Excavation and Backfill for Structures 1. DESCRIPTION 2. MATERIALS Excavate for placement and construction of structures and backfill structures. Cut and restore pavement. Use materials that meet
More informationCITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL
CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL 13.01 GENERAL The work included in this section shall consist of furnishing all materials and equipment and performing all labor
More informationITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219.
ITEM 461 STRUCTURAL PLATE STRUCTURES 461.1. Description. This Item shall govern for the furnishing and installing of structural plate pipes, pipe arches, arches, underpasses, box culverts and special shapes
More information2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1
2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1 There are three ways to accomplish urban soil erosion and sedimentation control: Allow erosion to take place and then control sediment
More informationSection 1I-3 - Bioswales
BIOSWALES (Numbering pending) These specifications compliment the bioswale design portion of the Iowa Stormwater Management Manual in Chapter 2, Section 2I-3. Sections of the following documents, as referenced
More informationFOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 REVISION 7 ITEM 516 INSTALLATION OF FLEX BEAM GUARDRAIL
AFTER NOVEMBER 1, 2008 ITEM 516 INSTALLATION OF FLEX BEAM GUARDRAIL 516.1 Description. This item shall govern for furnishing and placing 10 or 12 gauge galvanized flex beam guardrail, complete with timber
More informationSECTION 10 - TRENCHING AND BACKFILLING
SECTION 10 - TRENCHING AND BACKFILLING 10.1 General A. Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 10.1.1 Related requirements
More informationSECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.
SECTION 1100 GRADING 1101 SCOPE. This section covers the performance of all work required for grading the project in coordination with all previous work performed at the locations shown on the contract
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationREGIONAL CONSTRUCTION STANDARDS
REGIONAL CONSTRUCTION STANDARDS SIXTH EDITION Publication Update 6.5 (Full Committee Approved Proposed Revision 6.5 Storm Sewer Joint Wrap - Section 302 As Publication Update 6.5) March 27, 2018 Copyright
More information1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1
1.01 GENERAL A. The Contractor shall perform all excavation, backfilling, grubbing and grading required for construction and installation of pipelines, structures and appurtenances. Excavation shall include
More informationConstruction Specification for General Excavation
Engineering & Construction Services Division Standard Specifications for Road Works TS 2.10 September 2018 for General Excavation Table of Contents TS 2.10.01 SCOPE... 2 TS 2.10.02 REFERENCES... 2 TS 2.10.03
More informationSECTION STORM SEWER PIPE
SECTION 4200 - STORM SEWER PIPE 4200.1 SCOPE: This section covers the requirements for all labor, equipment and materials for the installation of storm sewers pipes. Trenching guidelines are provided in
More informationCITY OF URBANA CLASS 2 EROSION CONTROL PERMIT STANDARD DETAILS
CITY OF URBANA CLASS 2 EROSION CONTROL PERMIT STANDARD DETAILS CLASS 2 EROSION CONTROL PERMIT STANDARDS TABLE OF CONTENTS EROSION CONTROL PRACTICES FLOW CHART 1 EROSION CONTROL PERMIT FORM 2 EXAMPLE EROSION
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...
More informationSECTION 1 GENERAL NOTES
ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE 44-1 44-1.01 Description 44-1 44-1.02 Materials 44-1 44-1.03 Proportions 44-1 44-1.04
More informationTown of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL
CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with
More information1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods
SECTION 2000- EARTHWORK PART 1- GENERAL 1.01 SCOPE: This Section covers excavation, fill, and compaction of earth and rock for roadway, embankments, structural foundations, and planted areas. Topics include
More informationINDEX DESCRIPTION MATERIALS APPROVAL FOR BASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6
03005_Jan31_2018.pdf Page 1 of 6 INDEX Page 03005-1 DESCRIPTION 2 03005-2 MATERIALS 2 03005-3 APPROVAL FOR BASE COURSE 3 03005-4 CONSTRUCTION 3 03005-5 MEASUREMENT 6 03005-6 PAYMENT 6 03005_Jan31_2018.pdf
More information901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL
SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID
More informationENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION
NEW CASTLE COUNTY DEPARTMENT OF LAND USE ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION For Permanent Structures, pursuant to Delaware Pond Code 378 and Delaware Sediment and
More informationSECTION FLEXIBLE PAVING
SECTION 321200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Include GENERAL CONDITIONS and applicable parts of Division 1 as part of this Section. B. Examine all Drawings and other Sections of the Specifications
More informationROLLED EROSION CONTROL PRODUCTS (RECP)
Supplemental Technical Specification for ROLLED EROSION CONTROL PRODUCTS (RECP) SCDOT Designation: SC-M-815-9 (07/17) 1.0 Rolled Erosion Control Products (RECP) This Supplemental Specification replaces
More informationGWINNETT COUNTY STORM SEWER PIPE STANDARDS
1.0 Standard Specifications GWINNETT COUNTY STORM SEWER PIPE STANDARDS 1.1 Unless otherwise specifically set forth herein or in the Gwinnett County Standard Drawings, all of the materials, methods of the
More informationSITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013
WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown
More informationSECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS
SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS Section Page 44-1 SHOTCRETE... 44.1 44-1.01 Description... 44.1 44-1.02 Materials... 44.1 44-1.03 Proportions...
More informationC. This project shall be designed to meet LEED Silver design criteria. Construction activity pollution prevention is a mandatory requirement.
SECTION 31 25 13 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the provisions for the control of erosion in the construction area and in stockpile areas
More informationSECTION EROSION AND SEDIMENTATION CONTROLS
SECTION 312500 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made
More informationSECTION STORM DRAINAGE AND STORMWATER MANAGEMENT
SECTION 322 - STORM DRAINAGE AND STORMWATER MANAGEMENT 322.01 DESCRIPTION Work includes all labor, material and equipment to construct storm drain systems and stormwater management facilities, including
More informationSECTION EROSION AND SEDIMENTATION CONTROLS
SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL
More informationCONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02
More informationSECTION 2831 ITEM F-162 CHAIN-LINK FENCES
SECTION 2831 ITEM F-162 CHAIN-LINK FENCES PART 1 - GENERAL 1.1 DESCRIPTION. This item shall consist of furnishing and erecting a chain-link fence in accordance with these specifications and the details
More informationSECTION BORING AND/OR JACKING PIPE
02910-1 of 6 SECTION 02910 BORING AND/OR JACKING PIPE 02910.01 GENERAL A. Description Boring and/or jacking pipe shall include, but not necessarily be limited to, furnishing and installing carrier pipe
More informationTips with Creation of your Erosion and Sediment Control Plan
Tips with Creation of your Erosion and Sediment Control Plan By Chris Droste, CESCO Senior Erosion Control Specialist Westmoreland Conservation District Forming Your Narrative Use the DEP checklist. Page
More informationSECTION TRENCHING, BACKFILL AND COMPACTION
SECTION 312333 TRENCHING, BACKFILL AND COMPACTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. Native Backfill Material 2. Crushed Stone Bedding 3. Select Backfill Material 4. Shoring and Bracing
More informationSECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL 36.1 36-2 PIPEMAKING EQUIPMENT 36.1 36-3 TRENCH EXCAVATION 36.1 36-4 SPECIAL FOUNDATION TREATMENT 36.1 36-5
More informationSECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS
SECTION 13100 MECHANICALLY STABILIZED EARTH RETAINING WALLS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. Includes all labor, material, equipment, testing and submittals required to design and complete construction
More informationSECTION STRUCTURAL EXCAVATION FOR STRUCTURES
1 1 1 0 1 0 1 0 1 SECTION 1. STRUCTURAL EXCAVATION FOR STRUCTURES BASED ON DFD MASTER SPECIFICATION DATED /1/1 P A R T 1 - G E N E R A L SCOPE The work under this section shall consist of providing all
More informationAppendix B.2. Construction Specifications for Infiltration Practices
Appendix B.2 Construction Specifications for Infiltration Practices B.2.A Infiltration Trench General Notes and Specifications An infiltration trench may not receive run-off until the entire contributing
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION
Sheet 1 of 8 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION Note: This Special Provision is generally written in the imperative mood. The subject, the
More informationStandards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition
STANDARD FOR SLOPE PROTECTION STRUCTURES Definition Structures to safely conduct surface runoff from the top of a slope to the bottom of the slope. Purpose The purpose of this practice is to convey storm
More information1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork.
PAGE 334000-1 SECTION 334000 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More informationTABLE OF CONTENTS
DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes
More informationAPPENDIX A MEASUREMENT AND PAYMENT
P-150 DEMOLITION 4.01 Removal of pavement shall be measured per square yard based on the area shown on the plans. Any pavement removed outside the designed limits of removal because the pavement was damaged
More informationHYDROLOGIC RESTORATION OF THE CASH CREEK BASIN IN TATE'S HELL STATE FOREST
HYDROLOGIC RESTORATION OF THE CASH CREEK BASIN IN TATE'S HELL STATE FOREST CONSTRUCTION PLAN BID SET PREPARED FOR: LOCATION MAP CARRABELLE US ROUTE 319/98 EASTPOINT Prepared By Plan Design Enable CORPORATE
More informationSECTION 300 STORM SEWER TABLE OF CONTENTS
SECTION 300 STORM SEWER TABLE OF CONTENTS Starts on Page 300 GENERAL... 2 301 MATERIALS... 2 302 CONSTRUCTION PROCEDURES... 5 303 TESTING... 5 304 ABANDONMENT OF EXISTING STORM SEWER FACILITIES... 6 305
More informationSECTION 503 TEMPORARY PAVEMENT RESTORATION
SECTION 503 TEMPORARY PAVEMENT RESTORATION 503-1 DESCRIPTION: This work consists of furnishing, placing, compacting, and maintaining a temporary pavement surface suitable for driving in accordance with
More informationSPECIAL SPECIFICATION 2093 LIME/CEMENT STABALIZED SUBGRADE
2004 Specifications CSJ 0902-48-838 SPECIAL SPECIFICATION 2093 LIME/CEMENT STABALIZED SUBGRADE This item shall consist of treating the subgrade by scarifying, adding lime slurry, initial mixing and curing,
More information