Guidelines for Multi-Point Suspended Scaffolds (MPSS)

Size: px
Start display at page:

Download "Guidelines for Multi-Point Suspended Scaffolds (MPSS)"

Transcription

1 Guidelines for Multi-Point Suspended Scaffolds (MPSS)

2 For more copies, please contact Publications Section Ministry of Labour 655 Bay St., 14th Floor Toronto ON M7A 1T7 (416) Toll-free: Fax: (416) Web: Published January Queen's Printer for Ontario, 2006 ISBN X

3 Guidelines for Multi-Point Suspended Scaffolds (MPSS) Occupational Health and Safety Branch Ministry of Labour January 2006

4

5 TABLE OF CONTENTS Section 1 Introduction... Page 1 Section 2 Purpose of the Guideline... Page 2 Section 3 Definitions... Page 3 Section 4 Multi-Point Suspended Scaffolds (MPSS) Overview... Page 5 Sec Platform Uses... Page 5 Sec Description of Major Components... Page 5 Section 5 Design Requirements... Page 3 Sec Load Considerations... Page 8 Sec Methods for Designing MPSS... Page 11 Sec Redundancy of the System Design... Page 14 Sec Other Design Considerations... Page 15 Section 6 General Requirements... Page 16 Sec Engineering Drawing Requirments... Page 16 Sec Specific Duties: Professional Engineer, Constructor, Employer, Worker and Supervisor... Page 17 Appendix A Typical Components of MPSS... Page 22

6

7 1. INTRODUCTION The Regulations for Construction Projects (Ontario Regulation 213/91) were amended by Ontario Regulation 85/04, which added specific requirements for the design, construction and use of multi-point suspended scaffolds (MPSS) in subsections to 142.8, along with the definitions for multi-point suspended scaffold, safety factor, and traverse in subsection 1(1) These amendments came into effect October 1, Sections 137 to 142 of Ontario Regulation 213/91 are no longer applicable to MPSS. This guideline is intended to provide assistance to professional engineers, constructors, employers, supervisors and workers with an overview of the design, construction and use of multi-point suspended scaffolds. The information contained in this guideline is not intended to be all-inclusive. The requirements of the Occupational Health and Safety Act and the Regulations for Construction Projects (the Regulation) must be complied with and should be referred to when using this guideline. 1

8 2. PURPOSE OF THE GUIDELINE The purpose of this guideline is to clarify the requirements for MPSSs in sections to of the Regulations for Construction Projects. The guideline highlights the major components of an MPSS, design methods, design loads, load factors and safety factors to be considered in the design, system redundancy, design drawings and what they should include. Not withstanding the requirements made under the Occupational Health and Safety Act, the guideline explains the sections of the regulations for MPSS that deal with the responsibilities of the professional engineer and responsibilities of the constructor, employer, supervisor and worker. In designing an MPSS, a professional engineer must ensure that the minimum design criteria set out in the Regulations are met when following other applicable codes and standards. 2

9 3. DEFINITIONS 3.1 TERMS DEFINED IN SUBSECTION 1(1) OF THE ACT AND SUBSECTION 1(1) OF THE REGULATION The following definitions have been extracted from section 1(1) of the Occupational Health and Safety Act, 1990 and Section 1(1) of the Regulations for Construction Projects and are provided below for reference in this guideline: multi-point suspended scaffold (MPSS), means a suspended scaffold or suspended work platform or a system of suspended scaffolds or suspended work platforms, each scaffold or platform being more than 750 millimetres in width, that is supported from an overhead support system by at least three primary load- carrying means of suspension to maintain the system s stability. Building Code, means Ontario Regulation 403/97 made under the Building Code Act, competent person, means a person who, (a) (b) (c) is qualified because of knowledge, training and experience to organize the work and its performance, is familiar with the Act and the regulations that apply to the work, and has knowledge of any potential or actual danger to health or safety in the workplace; competent worker, in relation to specific work, means a worker who, (a) (b) (c) is qualified because of knowledge, training and experience to perform the work, is familiar with the Occupational Health and Safety Act and with the provisions of the regulations that apply to the work, has knowledge of all potential or actual danger to health or safety in the work; constructor, means a person who undertakes a project for an owner and includes an owner who undertakes all or part of a project by himself or by more than one employer; 3

10 employer, means a person who employs one or more workers or contracts for the services of one or more workers and includes a contractor or subcontractor who performs work or supplies services and a contractor or subcontractor who undertakes with an owner, constructor, contractor or subcontractor to perform work or supply services; professional engineer, means a person who is a professional engineer within the meaning of the Professional Engineers Act; safety factor, means the ratio of the failure load to the specified load or rated load; traverse, when used in relation to a multi-point suspended scaffold, means to move the scaffold horizontally, in a controlled manner along the building or structure to which it is attached; worker, means a person who performs work or supplies services for monetary compensation but does not include an inmate of a correctional institution or like institution or facility who participates inside the institution or facility in a work project or rehabilitation program. 4

11 4. MULTI-POINT SUSPENDED SCAFFOLDS (MPSS) OVERVIEW 4.1 USE OF MPSS Multi-point suspended scaffolds are suspended from a permanent building or structure and are used as a work platform for a variety of tasks on construction projects and industrial workplaces. Multi-point suspended scaffolds vary in size and capacity depending on their application.they range from large area MPSS commonly used for bridge repair and restoration work to small scaffolds used for access and inspection applications. MPSS are also used for masonry work particularly in high-rise building construction.

12 4.2.2 Suspension System The suspension system contains the following: 1- Suspension assembly includes wire ropes, chains or cables and rigging hardware to connect the platform to the overhead structure, which is normally a permanent structure; 2- Hoisting mechanism, where the scaffold is to be raised or lowered; and 3- Anchorage system, which includes outrigger beams, beam clamps, cross tubes, trolley mechanism and other related hardware Suspension assembly The suspension assemblies are the primary support system for Multi-Point Suspended Scaffolds. The suspension system assembly connects the platform structure to the overhead structure. The suspension assembly consists of wire ropes, chains or cables. Wire Ropes and Chains The most common type of suspension system assembly is steel wire rope or chains to support or suspend the platform from a permanent or temporary structure. Threaded steel rods and steel tubes are also commonly used. This type of assembly normally includes the wire rope or chain, the appropriate rigging hardware, the stirrups or clamps used to attach the wire rope or chain to the main support beams of the platform, and the beam clamps or outrigger beams. The beam clamps and outrigger beams are part of the anchorage system and are attached directly to the permanent structure Hoisting Mechanism A hoisting mechanism is connected to the suspension system when the MPSS is designed to move vertically. The two main categories of hoists are manually operated and power operated hoists. Manually Operated Hoists The most common hoists are traction type, which are used with a wire ropes suspension system. 6

13 Power Operated Hoists Power Hoists are operated by electric, hydraulic, or pneumatic power. Most of these units use a motor driven sheave or drum assembly Anchorage System The anchorage system for the MPSS includes the following: Trolley and Rollers Trolley and rollers are used when the platform is designed to traverse or move horizontally. When the trolley mechanisms are attached to the permanent structure, they are considered part of the anchorage system. Trolley mechanisms are sometimes used at the platform level and as such are considered part of the suspension assembly. The use of movement-limiting devices would ensure that trolley movement is controlled. Outrigger Beams Outrigger beams may be used as anchorage for an MPSS and are part of the suspension system. They are generally supported on the permanent structure and over hang the edge to provide an attachment for the wire rope or chains of the suspension assembly. 7

14 5. DESIGN REQUIREMENTS Section 142.2(1) requires that a professional engineer design the MPSS. The professional engineer must be licensed in Ontario and must have the necessary knowledge and experience to design MPSSs and their components. Note: Subsection 142.2(14) requires that the constructor have the professional engineer, responsible for the structural integrity of the permanent building or structure from which the scaffold is suspended, provide a written report on the suitability of the supporting structure to support the design loads imposed by the MPSS. In order to do this, the MPSS design engineer must provide the loading information to the engineer responsible for the permanent building or structure. The information should contain but is not limited to the following: The loading imparted by the MPSS, including wind loads on the MPSS, localized loading caused by a failure in a suspension point, etc. The fall arrest forces for workers on the platform In the case of bridges, traffic movement, possibility of lane closures that may cause imbalanced loading Any other loading that in the opinion of the professional engineer may affect the supporting structure 5.1 LOADING CONSIDERATIONS: Section (2) indicates both the live loads, dead loads and wind loads that must be used in the design of the MPSS Dead loads: Dead loads are the weight of the MPSS and its components including the loads imposed by the guardrail system. Fixed scaffold and ancillary structures that are constructed as part of the MPSS may be considered as part of the dead load. 8

15 5.1.2 Live Loads: The live loads to be taken into consideration when designing an MPSS are, but are not limited to: construction material equipment debris from demolition, including grit from abrasive (sand) blasting workers loads from traversing or otherwise moving the MPSS. The minimum uniformly distributed live loading that the MPSS is to be designed to is dependent on its intended use. The MPSS must be designed for a minimum live load of 1.2 kn/m 2 uniformly distributed over the platform surface, except: if the MPSS is intended for masonry work, it shall be designed for a live load of at least 2.4 kn/m 2 excluding storage of masonry units; if the MPSS is used for heavy-duty work such as demolition or storage of masonry units or other related material or equipment, it shall be designed for a live load of at least 3.6 kn/m 2 uniformly distributed over the platform surface Additional Live Load Considerations Subsection 142.2(3) requires in addition to the loads specified in subsection (2), a multi-point suspended scaffold shall be able to support or resist the following concentrated loads and wind loads Concentrated Loads Subsection 142.2(3) requires that in addition to the uniformly distributed live and dead loads, the MPSS must be able to support or resist a concentrated load of 1.1 kn on an area measuring 0.3 metres by 0.3 metres located on the platform at a position having the most adverse effect on the component under consideration. This concentrated load will be factored with a live load factor of 3.0 for MPSS and structural members and 4.0 for suspension systems. 9

16 Loads due to Abrasive (Sand) Blasting operations If the MPSS is to be used for abrasive blasting operations, then an additional live load allowance for 25 mm grit accumulation across the entire platform area must be included. It is recommended that the unit weight of the grit be specified and verified during field inspection Wind Loads Subsection 142.2(3)(b) indicates that the MPSS shall be designed for wind loads determined in accordance with Table (Design Data for Selected Locations in Ontario) as per section of the Building Code, assuming a probability factor of at least one in ten. The effect of wind loading on any environmental enclosures on the MPSS must be taken into account Special consideration for the wind loading The wind load derived from Table of the Building Code, may be reduced by up to 30% if the professional engineer who designs the MPSS determines it appropriate to do so. If the professional engineer does reduce the wind load, he/she must provide the rational for doing so in writing Any Other Applied Loads Subsection 142.2(3)(c) indicates that in addition to the above loads, the MPSS shall be designed for any other loads likely to be applied to it. Examples include: Stock piling or storage of material Dynamic effects of moving equipment Material receiving areas 10

17 5.2 METHODS FOR DESIGNING THE MPSS The regulation offers alternative design methods which may be used for the design of the MPSS: Limit States Design Working Stress Design Ultimate Strength Design (Testing to failure for components) Limit States Design Subsections 142.2(2),(3),(4),(5),(6),(7) and (8) of the Regulation set out the design and load criteria of an MPSS, based on the Limit States Design method in section of the Building Code. The values of the load factors stated in subsections 142.2(7) and (8) of the Regulation replace the values of the load factors described in section of the Building Code and must be used instead. The live load factors for the MPSS are different from those of the Building Code as the MPSS is a temporary structure while the Building Code addresses permanent structures. The MPSS must be designed to have sufficient strength and stability so that the factored resistance is greater than or equal to the factored loads as presented in section of the Building Code. The equation below (see section of the Building Code) was modified for the design of the MPSS by not considering the factored loads due to the effect of temperature change (α T )T. φr effect of: α D D + γψ[ (α L )L + (α W )W ] Where φ = Resistance factor applied to the specified material property or to the resistance of a member, connection, structure or foundation, which for the limit state under consideration takes into account the variability of dimensions and material properties, workmanship, type of failure and uncertainty in the prediction of resistance. The value of φ shall not be more than 0.9 and in some cases it may be less. R = Resistance of a member, connection, structure or foundation, based on the dimensions and on the specified properties of the structural materials. 11

18 (α D ) = Dead load factor (refer to Table 1). D = Anticipated dead load of MPSS and its components. γ = Importance factor applied to factored loads other than dead load which takes into account the consequences of collapse or failure as they relate to the use of the structure (refer to section of the Building Code). The value of γ shall not be less than 1.0 and may be increased greater than 1.0 in some cases for critical components. ψ = Load combination factor applied to factored loads other than dead load to take into account the reduced probability of a number of loads from different sources acting simultaneously (refer to section of the Building Code). (α L ) = Live load factor (refer to Table 1) L = Specified live load for platform surface. (α W ) = Wind load factor (refer to Table 1). W = Wind load in accordance with section of the Building Code using the probability factor of at least one in ten for temporary structures. Note: The above definitions have been modified to reflect the terms related to Multi-point Suspended Scaffolds. Table 1 provides a comparison of the load factors for the design of an MPSS. 12

19 Table 1 Load Factors Structure/component α L α D α W MPSS and structural members (platform structure) Suspension and Anchorage system Working Stress Design Subsection 142.2(9) of the Regulation allows the designer the option to design the MPSS and its components using Working Stress Design. However, the safety factors for the scaffold and its structural members are required to be at least equal to what would otherwise be provided under the Limit States Design Ultimate Strength Design (Determination Of Failure Load By Testing) Subsection 142.2(10) of the Regulation indicates that if a component is tested to failure, then a suitable safety factor may be applied to the failure load to determine the capacity of the component. Where the failure load of a component has been determined by testing and verified in writing by a professional engineer, the minimum safety factors listed in Table 2 shall be used. 13

20 Table 2 Minimum Safety Factors for Testing MPSS Component/structure Minimum Safety Factor Component of the MPSS (Platform Structure) Components of the Suspension and Anchorage System Hoisting system (wire ropes, chains or cables used for hoisting) REDUNDANCY OF THE SYSTEM DESIGN Subsection 142.2(12) of the Regulation requires that an MPSS be designed, constructed and maintained in such a way that the failure of one means of support or suspension will not cause any part of the scaffold to collapse or fail under the most adverse loading conditions as determined by the professional engineer who designs the scaffold in compliance with section This requirement means that the suspension system and its components must be designed such that if a suspender or a suspension component fails under any loading condition, the remaining suspension system shall continue to support the platform with the load factors and safety factors specified in subsections (7)(8)(9)(10). A failure mode analysis is normally required to be carried out to determine this design requirement. The above suspension system redundant design feature is required where the MPSS is both stationary or when it is being moved or traversed to another anchorage position. 14

21 5.4 OTHER DESIGN CONSIDERATIONS Fall Arrest System Section requires a worker on an MPSS to use a fall arrest system when the MPSS is being erected, dismantled, traversed or otherwise moved. The fall arrest system is independent of the MPSS and must be designed in accordance with subsections 26.1, 26.6, 26.7 and 26.9 of the Regulation such that the worker is protected at all times. The design and layout of the fall arrest system must take into consideration the design of the MPSS. It is recommended that the design engineer of the MPSS evaluate the loads induced by the fall arrest system on the permanent structure Movement limiting devices

22 6.0 General Requirements 6.1 ENGINEERING DRAWINGS In accordance with subsection 142.2(15). the design drawings of the MPSS shall include: a statement by the professional engineer who designs the MPSS indicating that the design meets the requirements of this Regulation; the size and specifications of all components, including the type and grade of all materials to be used (for specific products this may be supplemented by listing the product name, model and size, i.e. beams, trolleys, tensioning devices); the load factors and safety factors for the scaffold and all its components; all the specified loads, including the loads during erection, dismantling, traversing and otherwise moving. Load patterns and location of concentrated loads should also be included; the procedures for erection, dismantling, traversing and otherwise moving Additional Considerations For Engineering Drawings It is recommended that the professional engineer who designs the MPSS show the following requirements on the design drawings: the maximum wind speed as referenced in Part of the guideline should also be on the drawing; the professional engineer specify the wind load at which work on the MPSS shall stop; movement-limiting devices as referenced in Part of the guideline; procedures to be followed where the MPSS becomes skewed or jammed during traversing or moving; a checklist of the items including the critical components to be inspected, to assist the competent worker during the inspection of the MPSS; where proprietary components are used for the MPSS, the professional engineer who designs the scaffold must ensure that appropriate testing and certifications of components have been done. 16

23 6.2 SPECIFIC DUTIES The following are specific duties imposed by the Regulation on professional engineers and other workplace parties related to the design, erection, use, moving, traversing, maintenance, and dismantling of MPSS Professional Engineer s Duties In addition to designing the MPSS in accordance with Parts 6.1 and of the guidelines and the requirements of section and subsections 142.3(2),(3),(4) and (5) of the Regulation, the professional engineer shall prepare, sign and seal design drawings of the MPSS Constructor s Duties In addition to the general duties and responsibilities as per section 23 of the Occupational Health and Safety Act, R.R.O. 1990, c. O.1, the constructor has additional duties related to MPSS: Section that the MPSS is designed by a Professional Engineer the design drawings are signed and sealed by the Professional Engineer the drawings include written procedures for the erection, dismantling and traversing the MPSS any deviations from the drawings are approved by a Professional Engineer in writing Professional Engineer responsible for the structural integrity of the permanent structure from which an MPSS is suspended provides written report approving the design loads on the permanent structure by the MPSS 17

24 Section to notify the Ministry of Labour that the MPSS is to be erected or dismantled ensure that a Professional Engineer inspects the MPSS after it is erected and before it is first used (including inspection when MPSS is moved to Canada and before it is first used on a project in Ontario), and after it has been moved to a new anchorage that the Professional Engineer provides a written report that the MPSS complies with the drawings subject to any deviations and states whether or not all components are in adequate condition before erecting or dismantling a multi-point suspended scaffold, the constructor shall give notice, in person, by telephone, by fax or by electronic means, to the Ministry office located nearest the project. Section keep all written reports and drawings regarding the MPSS at the project Section keep, at the project, a written record of all inspections, tests, repairs, modifications and maintenance performed on the MPSS while the MPSS is at the project Additional elements to be considered by Constructor It is recommended that the MPSS is equipped with a wind speedmeasuring device and that work is stopped if the wind speed specified in the Professional Engineer s drawing is reached. A copy of the written records of inspection under section are maintained with the MPSS when it is moved off site. 18

25 6.2.3 Employer s Duties In addition to the general duties and responsibilities as per sections 25 and 26 of the Occupational Health and Safety Act, R.R.O. 1990, c. O.1, the employer has additional duties related to MPSS: Section that the MPSS is designed by a Professional Engineer the design drawings are signed and sealed by the Professional Engineer the drawings include written procedures for the erection, dismantling and traversing the MPSS any deviations from the drawings are approved by a Professional Engineer in writing Section ensure that a Professional Engineer inspects the MPSS after it is erected and before it is first used (including inspection when the MPSS is moved to Canada and before it is first used on a project in Ontario), and after it has been moved to a new anchorage position ensure the Professional Engineer provides a written report that the MPSS complies with the drawings and that all components are in adequate condition ensure that the MPSS is equipped with a wind speed-measuring device and that work is stopped if the wind speed specified in the Professional Engineer s drawing is reached. appoint a competent worker to inspect the MPSS prior to each day s use and ensure that the inspection is done. Section ensure that the MPSS is erected, dismantled and traversed by a competent worker under the supervision of a competent person in accordance with all design drawings, provide adequate oral and written instruction to the workers working on the MPSS on the use and limitations of the scaffold 19

26 provide adequate oral and written instruction for the workers engaged in the erection, dismantling and traversing of the MPSS provide the constructor with the drawings, reports and approvals for the MPSS Section ensure the MPSS is not overloaded post signs on the MPSS indicating the loading of the platform Section during erection, dismantling, traversing or otherwise moving, a worker shall use personal fall protection equipment at all times. provide written instruction to workers on operation procedures when MPSS is jammed or skewed Additional consideration foremployer It is recommended that the competent worker inspects the MPSS based on a check-list prepared by the design engineer or by the manufacturer Worker s Duties In addition to the general duties and responsibilities as per section 28 of the Occupational Health and Safety Act, R.R.O. 1990, c. O.1, the worker has additional duties related to MPSS: Section the competent worker shall inspect the MPSS daily, prior to its use. Section work in accordance with the manufacturer s or Professional Engineer s instruction for the MPSS 20

27 Section use appropriate fall arrest equipment while the MPSS is being erected, dismantled or traversed. The workers shall use double lanyards or equivalent to ensure 100% protection where needed Supervisor s Duties In addition to the general duties and responsibilities as per section 27 of the Occupational Health and Safety Act, R.R.O. 1990, c. O.1, the supervisor has additional duties related to MPSS Section under his or her supervision, only a competent worker or workers shall erect, dismantle, or otherwise move an MPSS 21

28 Appendix A Sketch 1, Multi-point suspended scaffold assemblies 22

29

30 ISBN January 2006

Comparison of the two proposals developed by the Ministry of Labour (MOL) and the SAE Working Group (SAE WG)

Comparison of the two proposals developed by the Ministry of Labour (MOL) and the SAE Working Group (SAE WG) to Ontario Regulation 213/91 (Construction Projects) under the Occupational Health and Safety Act (OHSA) related to Suspended Access Equipment (SAE) Comparison of the two proposals developed by the Ministry

More information

RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 November 2016

RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 November 2016 RMM 307 Scaffolds/Suspended Scaffolds and Powered Elevated Platforms Safety Program Page 2 3.3 Canadian Standards Association, Z271-10 (R2015): Safety Code for Suspended Elevating Platforms. 3.4 National

More information

FALLS: Model Scaffold & Work Platforms Policy (Ontario Version)

FALLS: Model Scaffold & Work Platforms Policy (Ontario Version) FALLS: Model Scaffold & Work Platforms Policy (Ontario Version) INTRODUCTION If you use scaffolds, suspension platforms, boatswain s chairs or other work platforms suspended high above the floor or work

More information

Scaffolding Procedures

Scaffolding Procedures Procedures Purpose It is the purpose of this company in issuing these procedures to further ensure a safe workplace based on the following formal, written procedures for scaffold work. Application This

More information

Corporate Policy and Procedure

Corporate Policy and Procedure Corporate Policy and Procedure POLICY CATEGORY AUTHORITY RELATED POLICIES APPROVED BY Safety Management When Outside Contractors are Retained (Contractor Safety Management Program) (the Policy ) Health

More information

The following is Copyright 2009 The Queen s Printer, Saskatchewan

The following is Copyright 2009 The Queen s Printer, Saskatchewan Saskatchewan Elevated Work Platform This material has been extracted from the Regulations and Acts of the Province as an aid to help students better understand the subject. This is not an official source

More information

Sample Written Program. For. Scaffolds

Sample Written Program. For. Scaffolds Sample Written Program For Scaffolds 1 Scaffold Safety Program (COMPANY NAME) Purpose The purpose of this safety policy and procedure is to establish guidelines for the protection of {COMPANY} employees

More information

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7 Safety Manual Page 1 of 7 Scaffolds 1. Purpose This policy establishes the basic safety requirements and safe work practices for the erection, use, inspection, movement, and dismantling of scaffolding.

More information

OCCUPATIONAL HEALTH AND SAFETY ACT SCAFFOLDING REGULATIONS

OCCUPATIONAL HEALTH AND SAFETY ACT SCAFFOLDING REGULATIONS c t OCCUPATIONAL HEALTH AND SAFETY ACT SCAFFOLDING REGULATIONS PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current to October 28,

More information

ANID GROUP SARL. For. Scaffolds

ANID GROUP SARL. For. Scaffolds ANID GROUP SARL For Scaffolds 1 Scaffold Safety Program Anid Group SARL Purpose The purpose of this safety policy and procedure is to establish guidelines for the protection of Anid Group employees who

More information

Copies of the written program may be obtained at Where are copies of this written plan kept? (Insert building/room, etc.).

Copies of the written program may be obtained at Where are copies of this written plan kept? (Insert building/room, etc.). Scaffolding Safety Procedures for Construction Purpose It is this company's purpose in issuing these procedures to further ensure a safe workplace based on the following formal, written procedures for

More information

Scaffolding. Safety Guide. STOP! Before you climb

Scaffolding. Safety Guide. STOP! Before you climb Scaffolding Safety Guide Printed FEB 2015 rebr. AUG 2016 Contents Safety Guide Disclaimer... 1 Safety Guide Objectives... 2 Roles & Responsibilities of Workplace Parties Employers, Supervisors, Workers...

More information

Title: Scaffolding Safety Policy. University Division/Department: Environmental Health & Safety Effective Date: October 6, 2017 Page: 1 of 15

Title: Scaffolding Safety Policy. University Division/Department: Environmental Health & Safety Effective Date: October 6, 2017 Page: 1 of 15 Page: 1 of 15 Table of Contents I. Purpose 2 II. Scope & Application 2 III. Definitions 2 IV. Policy 3 V. Procedures 3 a. Roles & Responsibilities 3 b. Safe Scaffold Erection and Use 5 c. Types of Scaffolds

More information

Scaffolding Safety Procedures

Scaffolding Safety Procedures Safety & Health Program 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 Scaffolding Safety Procedures Purpose It is this company's purpose in issuing these procedures

More information

Consultation on Proposed Miscellaneous Amendments to the Construction Projects Regulation (O. Reg. 213/91)

Consultation on Proposed Miscellaneous Amendments to the Construction Projects Regulation (O. Reg. 213/91) Consultation on Proposed Miscellaneous Amendments to the Construction Projects Regulation (O. Reg. 213/91) Summary of Proposal The Ministry of Labour (MOL) is proposing to make miscellaneous amendments

More information

Scaffolding Safety. Scaffolding

Scaffolding Safety. Scaffolding Scaffolding Safety Scaffolding 1926.450 - Scope, Application Covers all scaffolds used in workplaces Does not apply to crane or derrick suspended personnel platforms, which are covered by 1926.550(g) Aerial

More information

SafeDeck Supported Scaffold System

SafeDeck Supported Scaffold System SafeDeck Supported Scaffold System Table of Contents Origination 1 Range of Motion 1 Installation Efficiency 2 Third-Party Testimonial 2 SafeDeck Specifications 3 Competent Person 4 Tools Required 4 Components

More information

SCAFFOLDING PROCEDURE

SCAFFOLDING PROCEDURE SCAFFOLDING PROCEDURE 1 Table of Contents 1 PURPOSE... 3 2 PROGRAM COMPLIANCE... 3 3 SCOPE... 3 4 DEFINITIONS... 3 5 RESPONSIBILITES... 4 6 SCAFFOLD INSPECTION... 5 7 SCAFFOLD USE... 5 8 SCAFFOLD REQUIREMENTS...

More information

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT Construction Safety Education Forum 6 March 2013 Scaffolding Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT SRWSD in confidence 1 Presentation Outline Introduction

More information

Fall Protection Program For Working on Flat Roofs

Fall Protection Program For Working on Flat Roofs Fall Protection Program For Working on Flat Roofs Policy Sponsor: Responsible Unit: Facilities Management Approval Date: Revisions: January 2016 1. Introduction Facilities Management employees are required

More information

As a scaffold user, Mr Scaffold recommends Method 1, but both options are suitable.

As a scaffold user, Mr Scaffold recommends Method 1, but both options are suitable. 20 EASYSCAF t TM The Next Level 1300 MR SCAFFOLD (1300 677 223) 12 Lagana Place Wetherill Park NSW 2164 Fax: (02)9725 5214 ABN: 65 088 652 144 Re: Workcover Update Feb 2011 Thankyou for purchasing your

More information

Occupational Health & Safety: Cranes and Construction

Occupational Health & Safety: Cranes and Construction Occupational Health & Safety: Cranes and Construction Mark E. Geiger Melanie I. Francis 416.593.3926 416.597.4895 mgeiger@blaney.com mifrancis@blaney.com Blaney McMurtry LLP - 2 Queen Street East, Suite

More information

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 539 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS

More information

DEPAUL UNIVERSITY. Scaffolding Program. Environmental Health & Safety. April 2017

DEPAUL UNIVERSITY. Scaffolding Program. Environmental Health & Safety. April 2017 DEPAUL UNIVERSITY Scaffolding Program Environmental Health & Safety April 2017 1 TABLE OF CONTENTS SECTION PAGE NO. 1.0 PURPOSE 2 2.0 SCOPE 2 3.0 SCAFFOLDING ERECTOR 2 4.0 GENERAL 2 5.0 WOOD SCAFFOLDING

More information

Document Number: HSE Created: February 21, 2013 SCAFFOLDING. Author: A Holland

Document Number: HSE Created: February 21, 2013 SCAFFOLDING. Author: A Holland Document Number: HSE33-001 Created: February 21, 2013 SCAFFOLDING Author: A Holland MAPP Construction - Corporate 344 Third Street Baton Rouge, LA 70801 (225) 757-0111 MAPP Construction - Houston 11511

More information

Reliant Holdings Ltd Safety Management System

Reliant Holdings Ltd Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 Purpose The purpose of this program is to prevent injuries due to falls from elevated work areas and ensure employees

More information

Installing metal decking, curtain walls, window walls, siding systems, miscellaneous metals, ornamental iron, and similar materials; and

Installing metal decking, curtain walls, window walls, siding systems, miscellaneous metals, ornamental iron, and similar materials; and Steel Erection Plan for Construction Purpose Company Name must meet the requirements of OSHA's Steel Erection standard (29 CFR 1926, Subpart R). This Steel Erection Plan for Construction is our company's

More information

QUORUM MINING & RELINING SERVICES HEALTH AND SAFETY MANAGEMENT

QUORUM MINING & RELINING SERVICES HEALTH AND SAFETY MANAGEMENT SCAFFOLDING AND ELEVATED WORK PROCEDURE STATEMENT OF PROCEDURE: This procedure reviews the hazards associated with the use of scaffolds and how to control or minimize those hazards. This procedure also

More information

SCOPE OF WORK AND GENERAL INSTRUCTIONS

SCOPE OF WORK AND GENERAL INSTRUCTIONS SCOPE OF WORK AND GENERAL INSTRUCTIONS SCOPE OF WORK SUMMARY FOR PROJECT CONSTRUCTION SERVICES Project: IRB Planned Renovation for 16 th, 17 th and 18 th Floors Project No.: GOC1238936 Location: 300 West

More information

NZQA registered unit standard 9184 version 6 Page 1 of 5

NZQA registered unit standard 9184 version 6 Page 1 of 5 Page 1 of 5 Title Erect and dismantle non-notifiable prefabricated frame scaffolding up to five metres in height Level 3 Credits 5 Purpose People credited with this unit standard are able to: demonstrate

More information

WHAT YOU NEED TO KNOW ABOUT SUSPENDED SCAFFOLDS ISSUED FEBRUARY 2004, REVISION 1 OCTOBER 2005

WHAT YOU NEED TO KNOW ABOUT SUSPENDED SCAFFOLDS ISSUED FEBRUARY 2004, REVISION 1 OCTOBER 2005 WHAT YOU NEED TO KNOW ABOUT SUSPENDED SCAFFOLDS ISSUED FEBRUARY 2004, REVISION 1 OCTOBER 2005 Construction & Utilities Program WorkSafe Victoria What you need to know about Suspended Scaffolds, Revised

More information

Fall Protection - Part 3

Fall Protection - Part 3 Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Fall Protection - Part 3 Self Inspection Checklist Instructions: This checklist covers fall

More information

Scaffold Safety

Scaffold Safety Scaffold Safety 6800-2.0 Associated OHS Process: General Industry and Construction Safety The master copy of this document resides in electronic format. Printed copies of this document are for convenience

More information

STANDARD PRACTICE INSTRUCTION

STANDARD PRACTICE INSTRUCTION STANDARD PRACTICE INSTRUCTION DATE: March 1, 2001 SUBJECT: Scaffolding Safety Program. REGULATORY STANDARDS: 29 CFR 1910.28 Safety Requirements For Scaffolding. 29 CFR 1910.29 Manually Propelled Mobile

More information

The Edge Protection Federation Containment Systems Product Specification, Test Methods

The Edge Protection Federation Containment Systems Product Specification, Test Methods The Edge Protection Federation Containment Systems Product Specification, Test Methods Revision 2 August 2016 This Standard defines how the Edge Protection Federation defines Containment. This document

More information

Technical Guideline for. Section 8. Inspection and Approval of Construction

Technical Guideline for. Section 8. Inspection and Approval of Construction Technical Guideline for Section 8. Inspection and Approval of Construction Ontario Regulation 22/04 Electrical Distribution Safety January 12, 2005 Technical Guideline Section 8 General Legal Disclaimer

More information

Load Handling (Hoisting) Policy

Load Handling (Hoisting) Policy 1.0 PURPOSE This policy is to promote safe load handling (hoisting) practices and reduce the frequency and severity of incidents. The purpose is to protect personnel from injury, the environment from harm,

More information

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely.

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely. INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. Trade King 730 mobile aluminium towers are light-weight scaffold towers used throughout the

More information

Joint Structural Division. Standard for. Structural Engineering Services. 2nd Edition

Joint Structural Division. Standard for. Structural Engineering Services. 2nd Edition Joint Structural Division Standard for Structural Engineering Services 2nd Edition SSES2.indd 1 7/20/16 9:39:16 AM Joint Structural Division Second Edition June 2016 Preface The Institution of Structural

More information

LEGAL SUPPLEMENT 43. to the Government Gazette of Mauritius No. 13 of 8 February 2014

LEGAL SUPPLEMENT 43. to the Government Gazette of Mauritius No. 13 of 8 February 2014 LEGAL SUPPLEMENT 43 to the Government Gazette of Mauritius No. 13 of 8 February 2014 Government Notice No. 16 of 2014 THE OCCUPATIONAL SAFETY AND HEALTH ACT Regulations made by the Minister under section

More information

Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR , 23, 66 App.C; 29 CFR ) ISD #535

Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR , 23, 66 App.C; 29 CFR ) ISD #535 Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR 1910.22, 23, 66 App.C; 29 CFR 1926.502) ISD #535 Health & Safety Office Maintenance Service Building 10 SE 9½ Street Rochester, MN

More information

The following is Queen's Printer for Ontario, Occupational Health and Safety Act - R.R.O. 1990, Reg. 851

The following is Queen's Printer for Ontario, Occupational Health and Safety Act - R.R.O. 1990, Reg. 851 Ontario Lift Truck - Chariot de levage industriel This material has been extracted from the Acts and Regulations of the Province to help students understand the subject. It is not an official source of

More information

BECx Construction Phase Safety

BECx Construction Phase Safety BECx Construction Phase Safety What is the Number One Priority in Construction? Building Enclosure Commissioning: Train the Trainer Iowa State University, Ames Iowa May 10 12, 2016 Presented by William

More information

2014Construction Code: Chapter 33 Key Revisions

2014Construction Code: Chapter 33 Key Revisions Robert D Alessio Department of Buildings Senior Executive Director Engineering and Safety Operations New York University-Kimmel Center Tuesday, March 24, 2015 2014Construction Code: Chapter 33 Key Revision

More information

Construction Regulations

Construction Regulations 2014 = Added; modified; unchanged 2003 = Modified; deleted; unchanged GOVERNMENT NOTICE DEPARTMENT OF LABOUR No. GNR 84 FEBRUARY 2014 OCCUPATIONAL HEALTH AND SAFETY ACT, Act 85 of 1993, As Amended CONSTRUCTION

More information

Supported Scaffold Inspections

Supported Scaffold Inspections Supported Scaffold Inspections May 2016 Inspect scaffolds and scaffold parts daily, before each work shift, and after any event that may have caused damage. Check to see if power lines near scaffolds are

More information

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities

HEALTH & SAFETY MANUAL Legislated Duties and Responsibilities CONTRACTOR SAFETY PROGRAM PURPOSE: The Contractor Safety Program (CSP) establishes that contractors are required to work in compliance with legislation, regulations and the Town of Caledon health and safety

More information

ELEVATOR CONSTRUCTOR TRADE REGULATION

ELEVATOR CONSTRUCTOR TRADE REGULATION Province of Alberta APPRENTICESHIP AND INDUSTRY TRAINING ACT ELEVATOR CONSTRUCTOR TRADE REGULATION Alberta Regulation 276/2000 With amendments up to and including Alberta Regulation 131/2016 Office Consolidation

More information

Construction Regulations 2014 vs Construction Regulations 2003

Construction Regulations 2014 vs Construction Regulations 2003 Construction Regulations 2014 vs Construction Regulations 2003 By Mark Winter Safe Working Practice Tel: 071 6032213 / 021 7121643 mwinter@safepractice.co.za Why the new Construction Regulations? What

More information

ONTARIO PROVINCIAL STANDARD SPECIFICATION

ONTARIO PROVINCIAL STANDARD SPECIFICATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 539 NOVEMBER 2003 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS 539.04

More information

CONSTRUCTION HEALTH AND SAFETY, AND INJURY PREVENTION Prevent hazards when working with cranes, lifting appliances and rigging on construction sites

CONSTRUCTION HEALTH AND SAFETY, AND INJURY PREVENTION Prevent hazards when working with cranes, lifting appliances and rigging on construction sites 1 of 7 level: 4 credit: 4 planned review date: December 2003 sub-field: purpose: Construction People credited with this unit standard are able to: identify different types of rigging and lifting work for

More information

SECTION 616 TEMPORARY TRAFFIC CONTROL

SECTION 616 TEMPORARY TRAFFIC CONTROL SECTION 616 TEMPORARY TRAFFIC CONTROL 616.1 Description. This work shall consist of furnishing, installing, operating, maintaining, cleaning, relocating and removing temporary traffic control devices and

More information

Mobile Tower 3T Method (Through The Trapdoor) Please read this guide carefully. Please note that diagrams are for illustrative purposes only.

Mobile Tower 3T Method (Through The Trapdoor) Please read this guide carefully. Please note that diagrams are for illustrative purposes only. Mobile Tower 3T Method (Through The Trapdoor) INTRODUCTION Please read this guide carefully. Please note that diagrams are for illustrative purposes only. LOYAL mobile aluminium towers are light-weight

More information

Temporary Structures. Shoring and Scaffolding ATCE--II. Advanced Topics in Civil Engineering. Shoring and Scaffolding ATCE-II

Temporary Structures. Shoring and Scaffolding ATCE--II. Advanced Topics in Civil Engineering. Shoring and Scaffolding ATCE-II Temporary Structures and In multistory work, The shoring which supports freshly placed concrete is necessarily supported by lower floors which may not yet have attained their their full strength, and which

More information

Marina Bay Sands Guidelines for Rigging Service

Marina Bay Sands Guidelines for Rigging Service Marina Bay Sands Guidelines for Rigging Service 1) Rigging and hanging of points in the licensed area of the event is an exclusive service offered by MBS. 2) It is the responsibility of the Licensee to

More information

MOBILE ACCESS TOWER INSTRUCTION MANUAL SHALLOW BRACE. Incorporating the 3T method of assembly

MOBILE ACCESS TOWER INSTRUCTION MANUAL SHALLOW BRACE. Incorporating the 3T method of assembly MOBILE ACCESS TOWER Incorporating the 3T method of assembly SHALLOW BRACE INSTRUCTION MANUAL 2 INTRODUCTION This instruction manual contains all the information required to correctly assemble the OCTO

More information

Scaffolding Safety Guidelines

Scaffolding Safety Guidelines Scaffolding Safety Guidelines Occupational Safety & Health Bureau Montana Department of Labor & Industry Prepared for Montana Employers by the Occupational Safety & Health Bureau Department of Labor and

More information

SECTION SUSPENDED MAINTENANCE ANCHORAGE SYSTEM

SECTION SUSPENDED MAINTENANCE ANCHORAGE SYSTEM SECTION 112423 SUSPENDED MAINTENANCE ANCHORAGE SYSTEM PART 1 GENERAL 1.1 SECTION INCLUDES A. Suspended Access Anchorage Systems: 1. System design and certification. 2. Fall protection roof anchors. 3.

More information

SECTION SECTIONAL OVERHEAD DOORS

SECTION SECTIONAL OVERHEAD DOORS SECTION 08360 SECTIONAL OVERHEAD DOORS PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Doors B. Track and Framing 1.2 RELATED SECTIONS A. Section 04810 - Unit Masonry Assemblies: Prepared opening in masonry.

More information

SECTION STAINLESS STEEL FLEXIBLE CABLE MESH. Show hidden Specifier Notes for best results

SECTION STAINLESS STEEL FLEXIBLE CABLE MESH. Show hidden Specifier Notes for best results SECTION 05700 STAINLESS STEEL FLEXIBLE CABLE MESH Show hidden Specifier Notes for best results PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Stainless Steel Flexible Cable Mesh B. Related Sections:

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

Scaffolds. OSHA Office of Training & Education 1

Scaffolds. OSHA Office of Training & Education 1 Scaffolds OSHA Office of Training & Education 1 What Is A Scaffold? An elevated, temporary work platform Three basic types: Supported scaffolds -- platforms supported by rigid, load bearing members, such

More information

Scaffolds. OSHA Office of Training & Education 1

Scaffolds. OSHA Office of Training & Education 1 Scaffolds OSHA Office of Training & Education 1 What Is A Scaffold? An elevated, temporary work platform Three basic types: Supported scaffolds -- platforms supported by rigid, load bearing members, such

More information

SCOPE OF WORK AND GENERAL INSTRUCTIONS

SCOPE OF WORK AND GENERAL INSTRUCTIONS SCOPE OF WORK AND GENERAL INSTRUCTIONS SCOPE OF WORK SUMMARY FOR PROJECT CONSTRUCTION SERVICES Project: ECCC Space Optimization Project No.: GOC504787 Location: 401 Burrard Street, Vancouver The purpose

More information

Health, Safety and Environment

Health, Safety and Environment Health, Safety and Environment SOP-06 Working at Height Produced by HSSE Facilities & GS Department Table of Contents 1 Overview... 1 1.1 Purpose... 1 1.2 Hazards and Risks... 1 1.3 Key Terminology...

More information

Scaffolder On-the-Job Training Guide

Scaffolder On-the-Job Training Guide Scaffolder On-the-Job Training Guide Scaffolders lay out, assemble, erect, use, maintain and dismantle scaffolding including access scaffold, shoring, falsework, bleachers and stages. Training Requirements:

More information

Safe Schools: A Health and Safety Check New Jersey Safe Schools Program/New Jersey Department of Education 473

Safe Schools: A Health and Safety Check New Jersey Safe Schools Program/New Jersey Department of Education 473 Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Scaffolding - Part 1 Self Inspection Checklist Instructions: This checklist covers some

More information

No. S 518 WORKPLACE SAFETY AND HEALTH ACT (CHAPTER 354A) WORKPLACE SAFETY AND HEALTH (SCAFFOLDS) REGULATIONS 2011

No. S 518 WORKPLACE SAFETY AND HEALTH ACT (CHAPTER 354A) WORKPLACE SAFETY AND HEALTH (SCAFFOLDS) REGULATIONS 2011 1 First published in the Government Gazette, Electronic Edition, on 9th September 2011 at 5:00 pm. No. S 518 WORKPLACE SAFETY AND HEALTH ACT (CHAPTER 354A) WORKPLACE SAFETY AND HEALTH (SCAFFOLDS) REGULATIONS

More information

Uniscaff User Guide. Uniscaff. George Roberts Total Reliability of Supply. George Roberts Total Reliability of Supply

Uniscaff User Guide. Uniscaff.   George Roberts Total Reliability of Supply. George Roberts Total Reliability of Supply George Roberts Total Reliability of Supply User Guide George Roberts Total Reliability of Supply www.scaffoldingsales.co.uk Tubes Scaffold Staircases Beams Formwork Fencing K-Lok User Guide Contents Introduction

More information

SAULT COLLEGE OF APPLIED ARTS AND TECHNOLOGY SAULT STE. MARIE, ONTARIO COURSE OUTLINE SCAFFOLDING, EARTHWORK BARRIERS AND CONTROLS

SAULT COLLEGE OF APPLIED ARTS AND TECHNOLOGY SAULT STE. MARIE, ONTARIO COURSE OUTLINE SCAFFOLDING, EARTHWORK BARRIERS AND CONTROLS SAULT COLLEGE OF APPLIED ARTS AND TECHNOLOGY SAULT STE. MARIE, ONTARIO COURSE TITLE: COURSE OUTLINE SCAFFOLDING, EARTHWORK BARRIERS AND CONTROLS CODE NO. : SEMESTER: TWO PROGRAM: AUTHOR: INSTRUCTOR: CONSTRUCTION

More information

Section Re-employment in the Construction Industry

Section Re-employment in the Construction Industry Construction employers are required to offer to re-employ their injured construction workers who have been unable to work due to a work-related injury/disease. A construction employer's obligation to re-employ

More information

Fall Protection Plan for Construction

Fall Protection Plan for Construction Safety & Health Program 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 Fall Protection Plan for Construction OSHA currently regulates fall protection for construction

More information

REFURBISHMENT DEMOLITION

REFURBISHMENT DEMOLITION CONTRACTOR WHS HAZARD STANDARD REFURBISHMENT DEMOLITION EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

FrameSAFE Site-Specific Fall Protection Plan Template. Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL SAMPLE

FrameSAFE Site-Specific Fall Protection Plan Template. Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL SAMPLE FrameSAFE Site-Specific Fall Protection Plan Template Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL Step 1: Complete Site-Specific Form Enter the site-specific information in the form on

More information

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2 Purpose This procedure provides guidance to the Diocese of Maitland Newcastle (DoMN), principal contractors and other persons conducting a business or undertaking (PCBU) who commission or carry out construction,

More information

LADDERSPAN AGR. BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE

LADDERSPAN AGR. BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE LADDERSPAN AGR BoSS Camlock Advance Guardrail Mobile Aluminium Tower 1450/850 Frames USER GUIDE Contents Safety First Safety Checklist Quantity Schedules Assembly and Dismantling Procedure Toe Boards Stabilisers

More information

Effective Date: 10-January Table of Contents

Effective Date: 10-January Table of Contents Version: 3 Page: 1 of 8 Table of Contents 1.0 Introduction... 2 1.1 Purpose... 2 1.2 Scope... 2 1.3 Definitions... 2 1.4 Responsibilities... 2 Environmental Health and Safety Office (EHSO) and Emory Healthcare

More information

SCAFFOLDS Revision No: 3

SCAFFOLDS Revision No: 3 PAGE 1 OF 6 1.0 PURPOSE/ SCOPE To communicate the safety requirements for the erection, inspection and safe use of scaffolds. Compliance with these requirements will assure employee safety while working

More information

Issue Date: 3.2. Bearer: A horizontal member of a scaffold upon which the platform rests and which may be supported by ledgers.

Issue Date: 3.2. Bearer: A horizontal member of a scaffold upon which the platform rests and which may be supported by ledgers. 1.0 Policy It is the Company s policy to follow national and corporate standards and guidelines for scaffold safety. This policy shall apply to all site employees and contractors. 2.0 Purpose The purpose

More information

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

COMPENDIUM OF TYPICAL HAZARDS ASSOCIATED WITH USE OF SCAFFOLDS AND THEIR CONTROL MEASURES IN THE CONSTRUCTION INDUSTRY USE OF SCAFFOLDS

COMPENDIUM OF TYPICAL HAZARDS ASSOCIATED WITH USE OF SCAFFOLDS AND THEIR CONTROL MEASURES IN THE CONSTRUCTION INDUSTRY USE OF SCAFFOLDS COMPENDIUM OF TYPICAL HAZARDS ASSOCIATED WITH USE OF SCAFFOLDS AND THEIR CONTROL MEASURES IN THE CONSTRUCTION INDUSTRY USE OF SCAFFOLDS Refer to Technical Advisory for Scaffolds 1 No. Hazards Possible

More information

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

OSH5063EP(PRS3607) Workplace and Work Equipment Hazard. Session 9. Working at Height

OSH5063EP(PRS3607) Workplace and Work Equipment Hazard. Session 9. Working at Height OSH5063EP(PRS3607) Workplace and Work Equipment Hazard Session 9 Working at Height 1 Introduction The most common fatal type of accident in construction remains falling from a height 2 Introduction Where

More information

CANDIDATE HANDBOOK. Boom Truck Operator

CANDIDATE HANDBOOK. Boom Truck Operator CANDIDATE HANDBOOK Boom Truck Operator Stiff Boom Unlimited Tonnage Stiff Boom 40 Tonnes and Under Stiff Boom 20 Tonnes and Under Folding Boom Unlimited Tonnage Folding Boom 22 Tonnes and Under Folding

More information

DRAFT APPENDIX B TO SUBPART L October 6, 1998

DRAFT APPENDIX B TO SUBPART L October 6, 1998 ACCOSH Workgroup-scafapxb. 1 DRAFT APPENDIX B TO SUBPART L October 6, 1998 This Appendix B is provided to serve as a guide for evaluating the feasibility of providing safe access and fall protection for

More information

MOBILE CRANE OPERATOR

MOBILE CRANE OPERATOR To qualify to challenge certification in this trade, you must: Have experience performing job tasks listed as per Section E; and Have worked a minimum of 5,400 documented hours of which 1,600 hours must

More information

RESPONSIBILITIES IN THE DESIGN PROCESS INVOLVING METAL PLATE CONNECTED WOOD TRUSSES

RESPONSIBILITIES IN THE DESIGN PROCESS INVOLVING METAL PLATE CONNECTED WOOD TRUSSES CHAPTER 2 RESPONSIBILITIES IN THE DESIGN PROCESS INVOLVING METAL PLATE CONNECTED WOOD TRUSSES 2.1 PURPOSE The purpose of this chapter is as follows: 2.1.1 To define and draw attention to the typical duties

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

WHS Change Management

WHS Change Management Page 1 of 6 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons in the mission / ministry

More information

AVON MAITLAND DISTRICT SCHOOL BOARD

AVON MAITLAND DISTRICT SCHOOL BOARD AVON MAITLAND DISTRICT SCHOOL BOARD Create Positive, Inclusive Learning Environments, and Maximize Outcomes for Students DIRECTOR S ACTION REPORT TO: Regular Board Meeting Tuesday, May 9, 2017 AGENDA ITEM:

More information

MOBILE CRANE OPERATOR

MOBILE CRANE OPERATOR To qualify to challenge certification in this trade, you must: Have experience performing job tasks listed as per Section D; and Have worked a minimum of 5,400 documented hours of which 1,600 hours must

More information

Scaffolding. This Section shall also apply to all GWC Sub-Contractors Introduction:

Scaffolding. This Section shall also apply to all GWC Sub-Contractors Introduction: Scaffolding This Section shall also apply to all GWC Sub-Contractors 3.19.1 Introduction: All types of scaffold will be used throughout construction activities. Suitable scaffold will be erected, modified,

More information

CORPORATE POLICY C3.H17

CORPORATE POLICY C3.H17 Page 1 of 6 DEVELOPED BY: APPROVED BY: APPROVAL DATE: Corporate Services Department CMT TBD EFFECTIVE DATE: September 1, 2013 LATEST REVISON: NEXT REVIEW: Definitions...2 Scope...2 Purpose...3 Legislative

More information

SCAFFOLDS AND SCAFFOLDING WORK

SCAFFOLDS AND SCAFFOLDING WORK SCAFFOLDS AND SCAFFOLDING WORK Code of Practice TABLE OF CONTENTS FOREWORD... 4 SCOPE AND APPLICATION... 4 1. INTRODUCTION... 5 1.1 What is a scaffold and scaffolding work?... 5 1.2 Who has health and

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SWMS 002 Erect / Dismantle Single Bay Towers and/or Multiple Bay Towers Page of 9 ABN: 40 088 478 399 This SWMS has been prepared and authorised by OLDFIELDS ACCESS PTY LTD ACN: 088 478 399 Date: Issue

More information

SCAFFOLDING SAFETY PROGRAM

SCAFFOLDING SAFETY PROGRAM SCAFFOLDING SAFETY PROGRAM Introduction Gay Construction Company has instituted plans and procedures to provide a stable, sound, secure and adequately constructed scaffold system on each job that requires

More information

"WORKING SAFELY WITH SUSPENDED SCAFFOLDING"

WORKING SAFELY WITH SUSPENDED SCAFFOLDING MAJOR PROGRAM POINTS "WORKING SAFELY WITH SUSPENDED SCAFFOLDING" Training for the OSHA SCAFFOLDING STANDARD "Quality Safety and Health Products, for Today...and Tomorrow" OUTLINE OF MAJOR PROGRAM POINTS

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 928 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL TABLE OF CONTENTS 928.01 SCOPE 928.02 REFERENCES 928.03

More information

Construction (Design & Management) Regulations 2015 Briefing Note

Construction (Design & Management) Regulations 2015 Briefing Note construction Construction (Design & Management) Regulations 2015 Briefing Note Introduction The Construction (Design & Management) Regulations 2015 ("CDM 2015") are in force on 6 April 2015 (Regulation

More information

Approved By: R. Keen Date: March 6, 2014 Rev. No Scaffolding Procedure

Approved By: R. Keen Date: March 6, 2014 Rev. No Scaffolding Procedure Scaffolding Procedure A CONTROL DOCUMENT 1. PURPOSE The purpose of this section is to protect employees from harm by providing guidelines to ensure scaffolding is erected inspected, dismantled, used and

More information