2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005
|
|
- Hilary Bridges
- 5 years ago
- Views:
Transcription
1 2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005
2 2005 IEP Objectives Means Objectives Ends (Fundamental) Objectives Agenda Items No net imports Supply > Demand No dependence on US No loss of control to US companies Continued public ownership of resources Diversity of supply (including coal) Security * Cost - Average Risk A) Planning Criteria B) Financial Analysis C) Employment & Economic Development Flexibility to import green power Increase the number of communities integrated into the system Distributed Generation Diverse Generation Open and fast review process Recognition for BC Hydro Minimize environmental Impacts And/or increase positive environmental impact Reliability for consumers D) Role of Public and Private Sectors E) Clean and Green Definitions F) Measuring Environmental Impacts Minimize risk of transmission failures Air, Land and Water G) Diversity/Distributed Generation Increase/decrease private sector involvement * H) Other topics Maintain/increase regional equity * New research and development in BC Increase employment 3/31/05 Page 2 NEW - Regional workshops
3 Objectives of this session Understand industry standards for reliability and BC Hydro s Planning Criteria Understand how reliability is currently treated in portfolios Confirm committee is satisfied these criteria will allow BC Hydro to meet the reliability objective 3/31/05 Page 3
4 Reliability - definition Adequacy The ability of the electric system to supply the aggregate electrical demand and energy requirements of their customers at all times, taking into account scheduled and reasonably expected unscheduled outages of system elements Security The ability of the electric system to withstand sudden disturbances such as electric short circuits or unanticipated loss of system elements. 3/31/05 Page 4
5 Why Planning Criteria and how are they used? Ensure BC Hydro has a reliable system Requirement to meet certain planning criteria to be connected to western North America grid Dictate when new resources or upgrades are needed for reliability 3/31/05 Page 5
6 Reliability : Customers and BCH perspectives Generation Transmission Distribution CHL zero 15% 85% Consequence -severe - severe -local - system wide - wide spread -outages problems blackouts - economic - economic - local impacts impacts impacts Customers Customer Hours Lost (CHL) Time to Restore frequency Duration 3/31/05 Page 6
7 Agenda for Presentation Review industry reliability standards Explain BC Hydro s current planning criteria for Generation, Transmission, and Distribution 3/31/05 Page 7
8 Regulatory and Reliability groups 3/31/05 Page 8
9 Regulatory Authority BC Utilities Commission (BCUC) BCUC has regulatory authority over BC Hydro, and approves BC Hydro s reliability standards. NERC (National Electricity Reliability Council) NERC is a voluntary organization that is responsibility for Transmission reliability standards in the US NERC is promoting the development of a new mandatory system of reliability standards and compliance, backstopped in the United States by the Federal Energy Regulatory Commission 3/31/05 Page 9
10 Regional Reliability Councils Western Electricity Coordinating Council (WECC) Establishes mandatory operation standards and guidelines that describe good planning practices Required by NERC to establish a resource adequacy processes 3/31/05 Page 10
11 Western Interstate Board and CREPP Western Interstate Board is an organization of 3 provinces (including BC) and 12 western states Committee on Regional Electric Power Cooperation (CREPC) Concentrating on resource assessment 3/31/05 Page 11
12 Conclusions for Regulatory All regulatory agencies and governments at all levels are interested in Reliability Due to the interconnection of the bulk electric system, joint planning and co-ordination is required. 3/31/05 Page 12
13 Reliability : Customers and BCH perspectives Generation Transmission Distribution CHL zero 15% 85% Consequence -severe - severe -local - system wide - wide spread -outages problems blackouts - economic - economic - local impacts impacts impacts Customers Customer Hours Lost (CHL) Time to Restore frequency Duration 3/31/05 Page 13
14 Generation Reliability Planning Capacity Criteria 3/31/05 Page 14
15 Constraints in Generation Systems Energy Constrained Capacity Constrained System Hydro Systems Thermal Systems Adequacy Annual Reserve Margin Metric Load/Resource Balance Constraint Fuel Limited Machine limited 3/31/05 Page 15
16 Constraints in BC Hydro s System BC Hydro historically was energy constrained, but now capacity requirements are often driving new resource acquisitions. Both energy and capacity reliability metrics are required and used by BC Hydro Peak Load (MW) 6,816 7,513 8,646 10,143 Capacity Reserve 33% 26% 25% 15% 3/31/05 Page 16
17 Capacity Reliability Planning Methods Deterministic Planning Reserve Margin Probabilistic Loss of Load Probability (LOLP) [probability] Hourly Loss of Load Expectation (LOLE) [probability] Expected Unserved Energy (EUE) [kwh/year] Economic reliability planning (Shortage Value) 3/31/05 Page 17
18 Generation Capacity Adequacy Metrics Increasing computation complexity Adequacy Aspect Frequency Duration Magnitude Value Shortage LOLP LOLE EUE Value!!!!!!!!!! 3/31/05 Page 18
19 Target Planning Reserve Margins Reserve Margin 20% 18% 16% 14% 12% 10% 8% 6% 4% 2% 0% BC Hydro CPUC Avista Pacificorp Idaho Power Portland General Electirc Puget Sound Electirc Hydro Quebec 3/31/05 Page 19
20 BC Hydro s Capacity Planning Criterion 14% planning reserve calculated from LOLP analysis Criterion is 1-day-in-10-years Peak Load Forecast 1:2 Design Temperature Duration curve for daily values Resource Counting Dependable capacity Forced outage rates LOLP Analysis Output 14% reserve margin (includes 400 MW from intertie) Peak load carrying capability of system 3/31/05 Page 20
21 How is Capacity Planning Criteria used? Dictates when new capacity resources are required in order to maintain reliability L/R Balance Peak Load Forecast 1:2 Design Temperature 12,000 11,000 10,000 Output from LOLP 14% reserve margin 400 MW (intertie) 9,000 8,000 7,000 Existing Supply Heritage Contract IPPs and contracts 6,000 F2005 F2006 F2007 F2008 F2009 F2010 F2011 F2012 F2013 F2014 3/31/05 Page 21
22 Example 3/31/05 Page 22 Note: From Pacificore public information sessions
23 Generation Reliability Planning Energy Criteria 3/31/05 Page 23
24 Energy Planning Criteria in hydro systems Account for annual hydro variability Hydro Generation Firm energy capability of Heritage hydro assets based on critical low flow period : 43,000 GWh Critical Period /31/05 Page 24
25 Energy Planning Criteria for Heritage Assets Critical Water Firm Energy Heritage Hydro 43,000 GWh Firm Energy Burrard 6,000 GWh 49,000 GWh Average Water Year Heritage Hydro 47,000 GWh Average Burrard usage or imports 2,000 GWh 49,000 GWh 3/31/05 Page 25
26 BC Hydro Long term goal for Reliability of Energy Supply BC Hydro will plan to have sufficient generation capability in BC to be able to meet domestic demand in any given year. 3/31/05 Page 26
27 5,000 4,800 4,600 4, IEP results Self Sufficiency Gas & Electricity Price Forecast High NEB EIA Alt HR Confer NPV ($Millions) 4,200 4,000 3,800 3,600 3,400 3,200 3,000 EA1 Non-Firm Imports for Incremental Demand EA2 3,000 GWh per year Non-Firm Imports (CCGTs) EA3 Energy Self- Sufficiency (CCGTs) EA4 3,000 GWh per year Energy Surplus (CCGTs) 3/31/05 Page 27 EA5 3,000 GWh per year Non-Firm Imports (Fixed Cost Resources) EA6 Energy Self- Sufficiency (Fixed Cost Resources) EA7 3,000 GWh per year Energy Surplus (Fixed Cost Resources)
28 Transmission Reliability Planning 3/31/05 Page 28
29 WECC/NERC Planning Standards (Revised April 10, 2003) Includes mandatory standards and guidelines that describe good planning practices Requirements are primarily to avoid cascading outages and affecting the control area s neighbour. Minimum operating reliability general system instability, uncontrolled separation, cascading outages, or voltage collapse will not occur as a result of any single contingency or multiple contingency of sufficiently high likelyhood Single contingencies (N-1) should not lead to loss of demand or curtailed firm transfers (although interruptions to local network customers connected to the faulted element may occur) 3/31/05 Page 29
30 WECC Mandatory Operating Reserves Greater of - single contingency - sum of 5% (hydro) and 7% (thermal) of load WECC also sets requirements for spinning reserve BC Hydro is part of Northwest Power Pool, which has a reserve sharing agreement. 3/31/05 Page 30
31 Transmission Planning and IEP BC Hydro gives portfolios to BCTC, who indicate what reinforcements are required to meet N-1 contingency and other stability requirements. 3/31/05 Page 31
32 Distribution Planning 3/31/05 Page 32
33 Distribution Distribution Reliability is currently undertaken based on historical performance of the distribution system combined with performance targets for improvement or maintenance of current performance. The system performance is measured in terms of frequency and duration of outages including the resulting Customer Hours Lost (CHL) metric. Based on actual performance and economics, Distribution targets areas where frequent, long and high number of customers impacted outages have occurred. 3/31/05 Page 33
34 Distributed Generation and Reliability Distributed Generation may have some benefit in local area and affect CHL metric. This is not measured in our portfolio analysis. Distributed Generation could have some cost savings in Distribution Lines that is not accounted for in our portfolio analysis. May be able to apply general rules of thumb for cost savings. 3/31/05 Page 34
35 Reliability - Summary Objective of Reliability met by: 14% capacity planning reserve MW interie Firm energy to meet load under critical water N-1 contingency for transmission planning 3/31/05 Page 35
36 3/31/05 Page 36
37 WECC sub-regions Sub-regions actively developing their own resource adequacy standards California 90% of peak load + 15% reserve covered by forward commitments 1-year ahead 5% reliance on spot market Northwest Planning and Conservation Council (NWPCC) System as many similarities to BCH 3/31/05 Page 37
38 Criteria and method behind reserve margin Criteria Probablistic Method BC Hydro 1-in-10 LOLP CPUC deterministic Avista deterministic Pacificorp 1-in-10 & economic LOLP and EUE Portland General Electirc deterministic (based on FERCS SMD) Puget Sound Electirc deterministic & economic Hydro Quebec 2.4 hr per year BPA 3/31/05 Page 38
39 Example 3/31/05 Page 39 Note: From Pacificore public information sessions
40 BC Hydro Proposed Next Steps for Capacity Criteria 1) use existing models and information to develop LOLP vs planning margin graph Graph of increasing costs vs planning margin A graph similar to first graph will be presented to PIEPC in March 3/31/05 Page 40
2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005
2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability
More informationNORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC)
NORTHWEST POWER POOL Reliability through Cooperation 2006 2 NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC) NERC is a not-for-profit company formed as a result of the Northeast blackout in 1965 to promote
More informationEnergy Supply Costs. BCUC Workshop
Energy Supply Costs BCUC Workshop 15 January 2004 Outline Electricity Planning/Supply Requirements Context Approach to Planning for New Supply Cost Versus Risk Management Projected Electricity Demand/Supply
More information2012 Grid of the Future Symposium. Innovations in Bulk Power System Reliability Assessment: A North American View
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium Innovations in Bulk Power System Reliability Assessment: A North American View M.G.
More informationPacific Northwest Power Supply Adequacy Assessment for 2019 Final Report
Pacific Northwest Power Supply Adequacy Assessment for 2019 Final Report May 7, 2014 Council Document Number 2014-04 1 Executive Summary The Pacific Northwest s power supply is expected to be close to
More informationTTC/ATC 1.0 DEFINITIONS
TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule
More informationCapacity and Flexibility Needs under Higher Renewables
Capacity and Flexibility Needs under Higher Renewables Project Deliverable October 1, 2015 Arne Olson, Partner Ana Mileva, Senior Consultant Elaine Hart, Managing Consultant Defining today s planning problem
More informationJune 5, 2018 MEMORANDUM. Council Members. John Fazio, Senior Systems Analyst. SUBJECT: Briefing on Adequacy Analysis and Report BACKGROUND:
James Yost Chair Idaho W. Bill Booth Idaho Guy Norman Washington Tom Karier Washington Jennifer Anders Vice Chair Montana Tim Baker Montana Ted Ferrioli Oregon Richard Devlin Oregon June 5, 208 MEMORANDUM
More informationA Probabilistic Method to Assess Power Supply Adequacy for the Pacific Northwest
NW POWER AND CONSERVATION COUNCIL A Probabilistic Method to Assess Power Supply Adequacy for the Pacific Northwest John Fazio, Senior Systems Analyst 12/22/2011 A Probabilistic Method to Assess Power Supply
More informationTransmission Reliability. BCUC Workshop 15 January 2004
Transmission Reliability BCUC Workshop 15 January 2004 Overview British Columbia Transmission Corporation (BCTC) is responsible for planning, operating and managing BC Hydro s transmission system pursuant
More informationCONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 8
CONTENTS Forward... 4 Executive Summary... 5 The Council s Resource Adequacy Standard... 7 Recent Adequacy Assessments... 8 2023 Resource Adequacy Assessment...10 Sensitivity Analysis...10 Monthly Analysis...12
More informationA Revised Resource Adequacy Standard for the Pacific Northwest. NERC LOLE Work Group November 7-8, 2011 Austin, TX
A Revised Resource Adequacy Standard for the Pacific Northwest NERC LOLE Work Group November 7-8, 2011 Austin, TX OUTLINE Makeup of the PNW s Power Supply NERC Definition for Adequacy PNW s Approach Sample
More informationAPPENDIX I PLANNING RESERVE MARGIN STUDY
APPENDIX I PLANNING RESERVE MARGIN STUDY Introduction The planning reserve margin (), measured as a percentage of coincident system peak load, is a parameter used in resource planning to ensure there are
More informationToward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper
Toward Ensuring Reliability: Reliability Performance Metrics A NERC Staff White Paper Table of Contents Table of Contents Table of Contents... 2 Executive Summary... 3 Metrics Objective... 5 Metrics Background...
More informationReliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective
Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective Mark Lauby, Senior Vice President and Chief Reliability Officer North American Electric Reliability Corporation
More information2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool
2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.
More informationAppendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT
Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology Executive Summary Deliverability is an essential element of any resource adequacy requirement. Specifically, Load
More informationINTEGRATED RESOURCE PLAN
INTEGRATED RESOURCE PLAN 2016 Public Meeting #3 Thursday, August 13, 2015 2015 Portland General Electric. All rights reserved. Welcome: Meeting Logistics August 13, 2015 Slide 2 Local Participants: DoubleTree
More informationCONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 9
CONTENTS Forward... 4 Executive Summary... 5 The Council s Resource Adequacy Standard... 7 Recent Adequacy Assessments... 9 2021 Resource Adequacy Assessment...10 2022 Resource Adequacy Assessment...11
More informationRegional Resource Adequacy Studies
Appendix F: Resource Adequacy F 2017 PSE Integrated Resource Plan Regional Resource Adequacy Studies The results and data from these three studies of regional load/resource balance were used in the preparation
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3
More informationDefinition of Adequate Level of Reliability. Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET
Definition of Adequate Level of Reliability Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET Outline Background Definition and Reliability Objectives Supporting Documents Industry Feedback Next Steps Questions
More informationCAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)
Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC
More informationIntegrating High Levels of Variable Renewable Energy Sources
Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning
More informationTable of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.
Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6
More informationMaking Sense of U.S. Energy Markets
Making Sense of U.S. Energy Markets National Conference of State Legislators Task Force on Energy Supply Philip Pettingill, Director Regional Integration January 14, 2017 Two-thirds of the United States
More informationOverview. IEEE Boston Chapter ISO New England Inc.
Overview New England s power system will undergo major changes in the coming years to integrate renewables, demand response, smart grid and other new technologies Good planning helps overcome integration
More informationSystem Needs: An Energy Planning Perspective. Randy Reimann
System Needs: An Energy Planning Perspective Randy Reimann TOPICS BCUC 2006 IEP/LTAP Decision 2008 LTAP Workplan Resource Options Update System Planning and Criteria 2 BCUC IEP/LTAP DECISION Key findings:
More informationINTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID
CEYLON ELECTRICITY BOARD INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID 2018-2028 Dr. H.M Wijekoon Chief Engineer (Transmission Planning) Randika Wijekoon Electrical Engineer (Generation
More informationCalifornia Independent System Operator Corporation Fifth Replacement Tariff
Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing
More informationCalifornia Independent System Operator Corporation Fifth Replacement Tariff
Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing
More informationSeasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014
Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the
More informationStandards de planification du NERC
Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council
More informationCAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)
Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC
More informationRELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES
RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES Evangelos Dialynas Professor in the National Technical University of Athens Greece dialynas@power.ece.ntua.gr
More informationEast Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria
East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission
More informationReliability Issues White Paper. Accommodating High Levels of Variable Generation
Reliability Issues White Paper Accommodating High Levels of Variable Generation April 7, 2008 Table of Contents Table of Contents Introduction...Error! Bookmark not defined. Introduction... 1 NERC s Mission...
More informationDefinition of Adequate Level of Reliability
Definition approved by Operating Committee and Planning Committee at their December 2007 OC and PC meetings Definition of Adequate Level of Reliability 116-390 Village Boulevard, Princeton, New Jersey
More informationCritical Importance and Role of Power Generation Planning in the Power System
Critical Importance and Role of Power Generation Planning in the Power System By Hassan Jafar Zaidi, CEO Power Planners Int. (PPI), Pakistan Training Workshop Identification, Comparison and Scenario Based
More informationPOWER SYSTEM OPTIMIZATION FLEXIBLE POWER SYMPOSIUM, VAIL COLORADO
POWER SYSTEM OPTIMIZATION FLEXIBLE POWER SYMPOSIUM, VAIL COLORADO Mikael Backman Director, Market Development Americas Wartsila Power Plants The Value of Smart Power Generation Smart Power Generation can
More informationINFORMATION RELEASE. TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates
INFORMATION RELEASE TRANSMISSION SYSTEM TRANSFER CAPABILITY LIMITS Upgrade Options & Cost Estimates OVERVIEW This Information Release is intended to provide an overview of the transmission constraints
More informationLoads and Resources Methods and Assumptions
Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1
More informationMid-C Seminar July 16 th, 2014
NWPP Members Market Assessment and Coordination Initiative Mid-C Seminar July 16 th, 2014 Dan Williams, LC Chair, Portland General Electric Slides not reviewed or approved by MC Members 1 Agenda History
More informationPOTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More information2005 Integrated Electricity Plan Modelling Approach IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005
2005 Integrated Electricity Plan Modelling Approach 2005 IEP Provincial IEP Committee Meeting #4 May 31/June 1, 2005 IEP Road Map Part 2 Key Input Assumptions Part 1 Planning Objectives and Principles
More informationWholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission
Wholesale Electricity Markets and New England Independent System Operator Commissioner Mark Vannoy Maine Public Utilities Commission March 26, 2014 Overview and Background 2 Wholesale Electricity Markets
More informationGlossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004
Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)
More informationEnergy Imbalance Market Overview
Energy Imbalance Market Overview Presentation to: Portland General Electric EIM OATT Stakeholder Meeting David Timson Account Manager CAISO Strategic Alliances October 14, 2016 Topics for Discussion ISO
More informationCalifornia Grid Operations: Current Conditions and Future Needs
California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify
More informationFrequently Asked Questions August 2013
Frequently Asked Questions August 2013 General What is the Bulk-Power System or Bulk Electric System? NERC defines the Bulk-Power System as the electricity power generation facilities combined with the
More informationSpecial Assessment: Bulk Power System Impacts Due to Severe Disruptions on the Natural Gas System
Special Assessment: Bulk Power System Impacts Due to Severe Disruptions on the Natural Gas System John Moura, Director, Reliability Assessment and System Analysis Natural Gas Supply Association Annual
More informationPJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia
PJM Wholesale Markets Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM RTO Functions Grid Operation Non-discriminatory treatment Monitoring transmission system Reliability
More informationCHAPTER 6 - Load Forecast & Resource Plan
CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service
More information1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY
1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY Prof. Michael W. Golay Nuclear Engineering Dept. 1 Energy Supply, Demand, and Storage Planning The Example of Electricity PRESENTATION
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More informationElectric Analysis PSE Integrated Resource Plan. Contents. Chapter 6: Electric Analysis
6 2017 PSE Integrated Resource Plan Electric Analysis This chapter presents the results of the electric analysis. Contents 1. ANALYSIS OVERVIEW 6-3 2. RESOURCE NEED 6-5 Components of Physical (Peak) Need
More informationCONTENTS LIST OF TABLES LIST OF FIGURES
CONTENTS 1.0 PURPOSE OF ACTION AND NEED FOR POWER... 1-1 1.1 PURPOSE OF THE ACTION... 1-1 1.2 NEED FOR PROJECTS... 1-3 1.2.1 PacifiCorp Operations... 1-3 1.2.2 Cowlitz PUD Operations... 1-5 1.2.3 Regional
More informationNorthwest Power Pool Processes
Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed
More informationLessons Learned in Wind Integration
Lessons Learned in Wind Integration 2009 Southwest Renewable Energy Conference Flagstaff, AZ September 11, 2009 J. Charles Smith Executive Director UWIG What is UWIG? Non-profit corporation established
More informationElectricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)
For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold
More informationERCOT Public LTRA Probabilistic Reliability Assessment. Final Report
ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response
More informationSUMMARY OF TRANSMISSION BUSINESS
Filed: September, 0 EB-0-00 Schedule Page of SUMMARY OF TRANSMISSION BUSINESS.0 INTRODUCTION 0 Hydro One Networks Inc. is licensed by the Ontario Energy Board (the OEB or the Board ) to own, operate and
More informationNERC PLANNING STANDARDS
NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More information4 Calculation of Demand Curve Parameters
4 Calculation of Demand Curve Parameters This section addresses the demand curve for the Alberta capacity market, including the calculations for the components of the demand curve. 4.1 Resource adequacy
More informationSenate Bill 350 Study
Senate Bill 350 Study Volume VII: Ratepayer Impact Analysis PREPARED FOR PREPARED BY July 8, 2016 Senate Bill 350 Study The Impacts of a Regional ISO-Operated Power Market on California List of Report
More informationOptimizing the Generation Capacity Expansion. Cost in the German Electricity Market
Optimizing the Generation Capacity Expansion Cost in the German Electricity Market Hamid Aghaie Research Scientist, AIT Austrian Institute of Technology Novemebr 2017 1 Motivation Energy-only Market Generators
More informationEnergy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator
Energy Storage Integration in Alberta s Energy Only Market Kevin Dawson Director, Market Design Alberta Electric System Operator Outline The AESO and Alberta s Wholesale Electricity Market About the AESO
More informationUpdated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations
Updated October 2, 2014 System Operator Transmission - Senior interconnected system. Maintains the Western Electricity Coordinating Council (WECC) Coordinated Outage System (COS), documents standardized
More informationKey Issues and Consideration in Market Design, Operational and Oversight
Key Issues and Consideration in Market Design, Operational and Oversight Patrick Donlon Amanda Gordon Kathryn Sophy Kenneth Villwock Public Utilities Commission of Ohio & Pennsylvania Public Utilities
More informationBPA Comments on Appendix H. Pacific Northwest California Transfer Increase Informational Special Study
BPA Comments on Appendix H Pacific Northwest California Transfer Increase Informational Special Study February 28, 2019 On February 4, 2019, the California ISO (CAISO) released the 2018 2019 Transmission
More informationBriefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area
Briefing on How Resource Adequacy Works in ISO s Current Balancing Authority Area Regional Resource Adequacy Meeting December 16, 2015 Salt Lake City, Utah Keith Johnson Manager, Infrastructure Policy
More informationMay 9, The Honorable Rick Perry Secretary U.S. Department of Energy 1000 Independence Avenue Washington, DC Dear Secretary Perry:
Gerry Cauley President and Chief Executive Officer May 9, 2017 The Honorable Rick Perry Secretary U.S. Department of Energy 1000 Independence Avenue Washington, DC 20585-1000 Dear Secretary Perry: The
More informationTransmission System Long-term View Alberta Power Industry Consortium
Transmission System Long-term View Alberta Power Industry Consortium Jerry Mossing Vice-President Transmission Planning and Performance November 6, 2013 Power Industry Structure in Alberta Minister of
More informationReliability Modelling: Review Process & Methodology
Reliability Modelling: Review Process & Methodology Adequacy and Demand Curve Workgroup Sept 20 th, 2017 Public Reliability Modelling Background Per SAM 2.0: AESO is the responsible party for modelling
More informationTable of Contents Page i
2012 Integrated Resource Plan Table of Contents I. Executive Summary... 1 II. Recent Trends in Electrical Load Growth... 4 III. System Load Forecast... 7 IV. Current Resources... 12 V. Load/Resource Balance
More informationMay 5, Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426
May 5, 2008 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 RE: Definition of Adequate Level of Reliability Dear Secretary Bose: The
More informationBenjamin F. Hobbs. I. Resilience: Engineer s definition. IV. Multiple stressors. II. Traditional resource adequacy (independent
Benjamin F. Hobbs Theodore K. and Kay W. Schad Professor of Environmental Management Whiting School of Engineering, JHU Founding Director, E 2 SHI Chair, CAISO Market Surveillance Committee bhobbs@jhu.edu
More informationPrepared Remarks of. David N. Cook, General Counsel North American Electric Reliability Council
Prepared Remarks of David N. Cook, General Counsel North American Electric Reliability Council Hearing Before the United States Senate Committee on Energy and Natural Resources Summary The North American
More informationRecent Development in Reliable Energy Market in the US and Singapore
Recent Development in Reliable Energy Market in the US and Singapore 18-19 th June 2008 Electrical Engineering and Maintenance Forum World Engineering Congress, Bangkok, Thailand Dr. Panida Jirutitijaroen
More informationFor Bandon Utilities Commission
For Bandon Utilities Commission July 12, 2017 Profile BPA, a component of the U.S. Department of Energy, is a non-profit and self-funded power marketing administration in the Pacific Northwest. Congress
More information2012 Integrated Resource Plan. Appendix. Wind Integration Study Phase II
Appendix 6E Wind Integration Study Phase II Table of Contents 1 Executive Summary... 1 2 Introduction... 3 3 Objectives... 4 4 Wind Integration Study Methodology... 5 4.1 Study Scenarios... 6 4.2 Study
More informationApproved RMWG Discussion was held. ??? John Simpson need to assign SMART rating
ALR1-1 Generator Reactive Limit Metric:Voltage schedules How many times did generators encounter var limits associated with holding voltage schedule. 10 3 2 1 1 3 1 Initial pilot effort completed, reaching
More informationTransmission Reliability Margins. Table of Contents. Purpose. Operating Procedure
Table of Contents Purpose... 1 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 3 3. Detail... 3 3.1 TRM Value Determination... 3 3.2 TRM Instructions...
More informationDRAFT STUDY PLAN FOR 2018
DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure
More informationReliability Challenges of the Clean Power Plan
Reliability Challenges of the Clean Power Plan Branden Sudduth Director, Reliability Planning 2 Outline WECC Role in the Western Interconnection Uniqueness of the Western Interconnection WECC efforts related
More informationLOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals
Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to
More informationCalifornia ISO Preparing California for a Greener and Smarter Grid
California ISO Preparing California for a Greener and Smarter Grid Presented by Jim McIntosh Director Operations Executive Advisor California ISO Agenda CAISO Overview Current & Future Challenges Renewables
More informationTEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY
TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for
More informationElectrical energy GHG emission factors for BC
October 2011 Electrical energy GHG emission factors for BC Calculating greenhouse gas (GHG) emissions in the process of generating electrical energy is a problem. The energy comes from many different sources,
More informationColorado PUC E-Filings System
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO PROCEEDING NO. A- E IN THE MATTER OF THE APPLICATION OF BLACK HILLS/COLORADO ELECTRIC UTILITY COMPANY, LP FOR () APPROVAL OF ITS 0 ELECTRIC
More informationElliot Mainzer, BPA. NW Wind Integration Forum SC Meeting June 6, 2011
Elliot Mainzer, BPA Ken Dragoon, g NWPCC NW Wind Integration Forum SC Meeting June 6, 2011 1. Review the fundamentals concerning our current wind fleet and the regulatory demand for renewables by 2020.
More informationNERC Probabilistic Assessments Overview & Future Improvements
NERC Probabilistic Assessments Overview & Future Improvements Noha Abdel-Karim, PhD. NERC IEEE LOLEWG Meeting July 31, 2015 Overview NERC Probabilistic Assessment (ProbA) reports extend the LTRA data with
More informationNational Council on Electricity Policy Annual Meeting & Workshop Denver, CO. May 8, Jeff Bladen Executive Director Market Development
National Council on Electricity Policy Annual Meeting & Workshop Denver, CO May 8, 2018 Jeff Bladen Executive Director Market Development Assessing the Challenge MISO region is undergoing rapid and substantial
More informationAn Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004
Independent Electricity Market Operator : An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004 January 6, 2003 Public This page intentionally left blank. IMO_REP_0093v1.1
More informationAdequate Summer Electricity Supplies Projected
Adequate Summer Electricity Supplies Projected Summer 2017 Reliability Assessment Overview The comprehensive reliability assessment conducted by the Northeast Power Coordinating Council, Inc. (NPCC) projects
More information2011 Probabilistic Assessment. 11JAN12 Interregional Coordination
The 2011 Probabilistic Assessment was a pilot study performed by SPP at NERC s request to voluntarily conduct an assessment to determine reliability indices using probabilistic methods. The majority of
More informationReview of Utility Resource Plans in the West
Review of Utility Resource Plans in the West Charles Goldman Nicole Hopper Lawrence Berkeley National Laboratory New Mexico PRC IRP Workshop Santa Fe, NM June 8, 2006 Overview of Presentation Project overview:
More informationReference Document. Interconnected Operations Services
N ORTH A MERICAN ELECTRIC RELIABILITY COUNCIL Princeton Forrestal Village, 116-390 Village Boulevard, Princeton, New Jersey 08540-5731 Reference Document Prepared by the Subcommittee Version 1.1 with Proposed
More information