Foothills Solar and Substation
|
|
- Willis Hunter
- 5 years ago
- Views:
Transcription
1 CITY OF LOVELAND Foothills Solar and Substation MEADOWBROOK RIDGE PUD AMENDMENT & REZONING REQUEST CITY COUNCIL MEETING, OCTOBER 20, 2015 ATTACHMENT B
2 2 Presentation Outline PUD Amendment & Rezoning Request General Description and Background Solar and Substation Facility Conceptual Site Plan Planning Commission/Staff Recommendation and Next Steps CITY OF LOVELAND
3 Property Location and Proposal 3 52 acres purchased by the City Water & Power Department in April 2015 Intent to develop an 18 acre solar facility & 2.4 acre substation, remaining acreage open space Property zoned Meadowbrook Ridge PUD (257 townhomes and single family dwellings) Proposal to remove property from PUD and rezone to Developing Resource
4 Meadowbrook Ridge Planned Unit Development Water Tank 122 acre PUD: 461 residential units 2 Phases Phase 1 south of 22 nd Street, 154 units (SF & Duplex) Phase 2 north of 22 nd Street, 307 units (MF, SF, Duplex) 4
5 Meadowbrook Ridge Planned Unit Development Mehaffey Park 2013 City Parks & Rec purchased 9 acres zoned for 50 duplex units. Rezoned to Public Park. Phase 2 : 52 acres and 257 units 150 MF townhomes, 107 single family detached 5
6 Meadowbrook Ridge Planned Unit Development Mehaffey Park Power Division purchase 52.6 acres Last developable property in PUD Purchased by Power Division Intent is to construct a new substation and solar facility to replace the city s Idylewilde hydroelectric facility GDP Amendment would remove the property from the PUD boundaries. 6
7 7 Rezoning Developing Resource Consistent with property around the existing water tank Special review uses: farming, agriculture, garden uses, public utilities, & extraction of minerals Solar and substation facility requires a special review
8 8 Idylwilde Flood Damage The structure suffered damage and the reservoir filled with silt, sediment and cobbles
9 9 Idylwilde Flood Damage Pipeline Approximately 2,000 feet of the pipe was missing or destroyed
10 West Substation Threat 10
11 Timeline 11
12 Alternate Project Requirements 12 Must be pre-approved by Colorado Office of Emergency Management (COEM) and FEMA Must be located in the declared disaster area Must be owned by the City and the City must maintain legal responsibility Must follow Federal Acquisition Requirements (FARs) for procurement and construction Must comply with Environmental and Historic Preservation requirements Must be permanent and benefit the general public Must be completed in the established time frames by September 2017 Funding cannot be used to provide ongoing O&M or leasing costs
13 Environmental 13 Compliance with the Programmatic Environmental Assessment (PEA) includes: Acquiring necessary permits prior to construction Compliance with stormwater pollution requirements Proper management of hazardous materials Compliance with National Historic Preservation Act (NHPA) Monitoring and controlling construction traffic in accordance with OSHA Completion of the PEA checklist Staff believes final PEA conditions and checklist can be satisfied Completion of PEA anticipated to take 90 days OtterTail Environmental Inc. already working on PEA compliance
14 14 Substation Benefits Expecting to spend $4 Million Near existing transmission lines Reduces West Substation vulnerability Accommodates load growth Benefits entire City Site identified in long term utility plan Dixon Creek Substation Fort Collins, CO Owned by Fort Collins Utilities and PRPA
15 15 Solar Benefits Expecting to spend $5.1 Million Replaces renewable energy source lost from the hydro facility Benefits entire City Renewable Energy Credits count towards the Colorado Renewable Energy Standard (RES) Municipal utilities with 40,000+ customers Requires 10% of renewables in energy mix by 2020 Hangar Solar Field Brighton, CO Owned by United Power 2 MW Solar Field
16 Project Timeline 16
17 Conceptual Site Plan Foothills Solar and Substation Facility 2.4 acre substation 18 acre solar field 18 acres of open space preserved on west side of property Rio Blanco additional parking and access to Mehaffey Park Landscaping, bufferyards & sidewalks along street edges 17
18 Original vs Proposed Development Plans Originally planned for 107 Single Family Homes Originally planned for 150 Multi Family Units. Now a majority of the area is planned as open space. Planned to not be developed in original PUD and substation/solar facility project 18
19 19 Site photos from south & solar panel examples
20 Solar Park and Substation - Conceptual Renderings from Rio Blanco Avenue and W. 22nd Street 20
21 Substation Facility Examples 21
22 Substation Screening Wall 22
23 Solar Field Examples 23
24 24 Process PUD Amendment & Rezoning Neighborhood meeting on September 10 th Staff Recommendation: Approval Planning Commission: Approval recommended 5-3 Special Review Plans Development Plans under review Meetings with neighborhood HOA s Quail Run Meadowbrook Ridge Hunter s Run Future formal neighborhood meeting date not determined Administrative Process does not require public hearings unless through an appeal process CITY OF LOVELAND
25 25 Public Website
26 26 Questions? CITY OF LOVELAND
IDYLWILDE PROJECT FEMA REIMBURSEMENT & POSSIBLE SOLAR PROJECT LOVELAND UTILITIES COMMISSION. July 16, 2014
IDYLWILDE PROJECT FEMA REIMBURSEMENT & POSSIBLE SOLAR PROJECT LOVELAND UTILITIES COMMISSION July 16, 2014 COLORADO RENEWABLE ENERGY STANDARD Applies to municipal utilities serving more than 40k customers
More informationFOOTHILLS SOLAR PARK AND SUBSTATION
SPECIAL REVIEW / SITE DEVELOPMENT PLANS FOR: FOOTHILLS SOLAR PARK AND SUBSTATION 2601-2621 RIO BLANCO AVE SPECIAL REVIEW #915 Civil Engineering & Consulting 1501 Academy Ct. Ste. 203 Fort Collins, CO 80524
More informationLAND USE PBF LDR ZONING PUD PUD. Proposed Maximum Density (DU/Acre) Existing Maximum Intensity (FAR) .30 FAR/ 173 dwelling units.
PROPOSED LARGE SCALE FUTURE LAND USE MAP (FLUM) AMENDMENT OVERVIEW ORDINANCE: 2013-658 APPLICATION: 2013G-001-3-5 APPLICANT: PAUL HARDEN PROPERTY LOCATION: On the south side of Sunbeam Road, at the terminus
More informationKeys Edge Community Development District. Engineer s Report Infrastructure Improvements
Keys Edge Community Development District Engineer s Report Infrastructure Improvements Prepared for Keys Edge Community Development District Board of Supervisors Miami-Dade County, Florida Prepared by
More informationGas Drilling Program Update. Quicksilver Lake Arlington Drill Site
Gas Drilling Program Update Quicksilver Lake Arlington Drill Site City Council Work Session September 13, 2011 Presentation Overview Existing Ordinance Background Proposed Ordinance Discussion Topics Potential
More informationPLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: July 5, 2012
PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: July 5, 2012 APPLICANT NAME DEVELOPMENT NAME LOCATION Gulf Coast Asphalt Gulf Coast Asphalt Company 835 Cochrane Causeway (West side of Cochrane
More informationPLANNED UNIT DEVELOPMENT STAFF REPORT Date: September 7, 2017
PLANNED UNIT DEVELOPMENT STAFF REPORT Date: September 7, 2017 DEVELOPMENT NAME LOCATION Custom Boat Storage 3975 Demetropolis Road (East side of Demetropolis Road, 0.2± miles South of Halls Mill Road.)
More informationFloodplain management uses various tools to
Fort Collins Floodplain Management Program Success Stories from the September 2013 Flood Marsha Hilmes-Robinson, Floodplain Administrator, City of Fort Collins Utilities Chris Lochra, Flood Warning Engineer,
More information3. PUBLIC FACILITIES ELEMENT
3. PUBLIC FACILITIES ELEMENT A. Purpose This Element is intended to identify essential public facilities, buildings, and services and to describe policies and programs that will ensure that the existing
More informationRedwood Heights Stage 2 Update. Citizen s Advisory Committee April 25, 2017
Redwood Heights Stage 2 Update Citizen s Advisory Committee April 25, 2017 Outline Transportation Study Utility Servicing Biodiversity Conservation Strategy Outstanding Items Timeline Water Servicing Limited
More information# 7 ) UN MY PLACE HOTEL SPECIAL USE PERMIT PUBLIC HEARING
# 7 ) UN-53-16 MY PLACE HOTEL SPECIAL USE PERMIT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date: September 14, 2016 Item: UN-53-16 Prepared by: Marc Jordan GENERAL INFORMATION: Applicant:
More informationPlanning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015
Planning Commission Staff Report Project Plan Approval Hearing Date: June 24, 2015 ITEM 4 Provo City s Energy Department requests Final Project Plan approval to rebuild and expand the Energy Department
More informationStormwater Bio-Infiltration Pilot Project Concept Proposal Submitted by
Concept Proposal Submitted by Public Works Department 1947 Center Street, Fourth Floor Berkeley, CA 94704 December 17, 2009 Executive Summary The s Public Works Department submits this concept proposal
More informationlight & power wastewater stormwater water fact book
2015 fact book light & power stormwater wastewater water INSIDE UTILITIES Utilities revenue is fee based, not general fund (sales tax). Our intent: to deliver a level of service our customers expect in
More informationZONING AMENDMENT, PUD & PLANNING APPROAVAL STAFF REPORT Date: May 4, 2006
# 7, 8, & 9 Case ZON2006-00256, ZON2006-00815, & SUB2006-00816 ZONING AMENDMENT, PUD & PLANNING APPROAVAL STAFF REPORT Date: May 4, 2006 NAME SUBDIVISION NAME LOCATION David Hickman Auto Shredding Subdivision
More informationIMPLEMENTATION ACTION & PERFORMANCE MEASURE MONITORING REPORT. Development Services Department City Council Meeting April 11 th, 2017
IMPLEMENTATION ACTION & PERFORMANCE MEASURE MONITORING REPORT 17 Development Services Department City Council Meeting April 11 th, 2017 BACKGROUND adopted in 2015 with the Comprehensive Plan update reported
More informationSite Plan and Subdivision Review
Site Plan and Subdivision Review Municipal Land Use Framework Environmental Resource Inventory Master Plan Zoning Land Use Regulation Ordinance requirements for each zone Lot size, setbacks parking, cluster
More informationAPPENDICES. Table 46: Quantified Objectives (October 2013 to October 2021) New Construction Rehabilitation Conservation/Preservation
VI. APPENDICES APPENDIX A. QUANTIFIED OBJECTIVES The City of Placerville has established quantified (numerical) objectives for several program categories to provide measurable standards for monitoring
More informationRZ-1 LEGEND FUTURE ACCESS TO ALIGN W/ EXISTING HARRIS COVE DRIVE FUTURE ACCESS TO ALIGN WITH PROPOSED ACCESS OPPOSITE COX ROAD
ZONED RU(CD) ZONED RU(CD) LEGEND FUTURE ACCESS TO ALIGN W/ EXISTING HARRIS COVE DRIVE ZONED R-9PUD ZONED R-9PUD ZONED RU(CD) ZONED R-9PUD FUTURE ACCESS TO ALIGN WITH PROPOSED ACCESS OPPOSITE COX ROAD RZ-1
More information1. APPLICANT: RSA Architecture is the applicant for this request.
14. SPECIAL USE PERMIT NO. 2013-5 - 10103 Metcalf Avenue 1. APPLICANT: RSA Architecture is the applicant for this request. 2. REQUESTED ACTION: The applicant is requesting approval of a special use permit,
More informationAmeren Missouri Renewable Initiative
Ameren Missouri Renewable Initiative 09.15 1 EXECUTIVE SUMMARY Missouri Renewable Energy Standard (MoRES) contains both overall (total) renewables and solarspecific requirements. The renewables requirements
More informationReduce, Reuse, Replenish: Stormwater Re-use in the City of Hugo.. Bryan Bear City of Hugo
Reduce, Reuse, Replenish: Stormwater Re-use in the City of Hugo. Bryan Bear City of Hugo Current Situation Current Regulatory Environment USGS study on White Bear Lake Implicate City Wells as at least
More informationCHAPTER AGRICULTURAL ZONES
Agricultural Zones 35.21.020 CHAPTER 35.21 - AGRICULTURAL ZONES Sections: 35.21.010 - Purpose 35.21.020 - Purposes of the Agricultural Zones 35.21.030 - Agricultural Zones Allowable Land Uses 35.21.040
More informationStaff Report MINOR ALTERATIONS
Staff Report To: From: PLANNING DIVISION COMMUNITY & NEIGHBORHOOD DEVELOPMENT Salt Lake City Historic Landmark Commission Michael Maloy, AICP, Senior Planner, michael.maloy@slcgov.com Brittney Topel, Planning
More information# 14 ) ZN AMERICAN DIALYSIS CENTER OF NORTH LAS VEGAS M-2, GENERAL INDUSTRIAL DISTRICT TO M-1, BUSINESS PARK INDUSTRIAL DISTRICT PUBLIC HEARING
# 14 ) ZN-10-16 AMERICAN DIALYSIS CENTER OF NORTH LAS VEGAS M-2, GENERAL INDUSTRIAL DISTRICT TO M-1, BUSINESS PARK INDUSTRIAL DISTRICT PUBLIC HEARING STAFF REPORT To: Planning Commission Meeting date:
More informationWESTERN ENGINEERING CONSULTANTS, Inc LLC
WESTERN ENGINEERING CONSULTANTS, Inc LLC 127 S. Denver Avenue, Ft. Lupton CO 80621 2501 Mill St. Brush, CO 80723 Ph. 303-913-7341, Fax 720-294-1330 Email: firstname.lastname@westerneci.com August 24, 2017
More informationPOLICY FOR NATURAL RESOURCE MANAGEMENT AREAS
POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS I. POLICY STATEMENT Auburn University's (the University's) "Policy for Natural Resource Management Areas" implements the Campus Master Plan Land Use Element
More informationCHAPTER 8: INTERGOVERNMENTAL COOPERATION
CHAPTER 8: INTERGOVERNMENTAL COOPERATION Photos above by Randy Uhl 8.1 Introduction Intergovernmental cooperation involves working with neighboring communities, school districts and agencies to understand
More informationDEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA
DEVELOPMENT REPORT UNION PACIFIC PROPERTY SAN ANTONO INTERMODAL YARD AREA This report was prepared to present development information (Utility availability, Development Regulations, Flood Plain information,
More informationAPPA Joint Action Workshop
APPA Joint Action Workshop Solar, Wind and Distributed Energy: The Role of Joint Action January 12, 2017 Platte River was formed in 1975 as a political subdivision Serves the generation and transmission
More informationC&B Alberta Solar Development ULC
Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by
More informationBOARD OF ZONING ADJUSTMENT STAFF REPORT Date: December 7, 2015
BOARD OF ZONING ADJUSTMENT STAFF REPORT Date: December 7, 2015 CASE NUMBER 6018/5891 APPLICANT NAME LOCATION VARIANCE REQUEST ZONING ORDINANCE REQUIREMENT ZONING AREA OF PROPERTY Garden Design Solutions
More informationRenewable Energy Plan 2013 Biennial Review Lansing Board of Water & Light MSCP Case No. U-16619
Renewable Energy Plan 2013 Biennial Review Lansing Board of Water & Light MSCP Case No. U-16619 This Biennial Review filing by the Lansing Board of Water & Light (LBWL) complies with State of Michigan
More informationPERMITTED USES: Within the MX Mixed Use District the following uses are permitted:
6.24 - MX - MIXED USE DISTRICT 6.24.1 INTENT: The purpose of the MX Mixed Use District is to accommodate the development of a wide-range of residential and compatible non-residential uses (including major
More informationWSU SITE PROJECT BONNEY LAKE DRAFT ENVIRONMENTAL IMPACT STATEMENT
WSU SITE PROJECT BONNEY LAKE DRAFT ENVIRONMENTAL IMPACT STATEMENT August 2009 -?BONNE,Y Community Development Department 8720 Main St. E. POB 7380 Bonney Lake, WA 98391-0944 Phone: 253-447-4356 Fax: 253-826-1921
More informationIndianapolis Characteristics
Indianapolis skyline. AroundIndy.com staff photo, (c) 2011, all rights reserved. Flood of Problems: Modern Urban Watersheds Rachel Wilson, P.E., Indianapolis DPW Kathy Allen, MWH/Stantec Indianapolis Characteristics
More informationPLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013
PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013 NAME LOCATION MAWSS Shelton Beach Road East side of Shelton Beach Road Extension, 2/10± mile North of Moffett Road CITY
More informationIrrigation and Reservoir Companies in the City of Fort Collins Brian Janonis
1 Irrigation and Reservoir Companies in the City of Fort Collins Brian Janonis Bottom Line: Water in Colorado is purchased and sold on the open market. Because water is very limited along the Front Range,
More informationTRANSPORTATION IMPACT FEE
TRANSPORTATION IMPACT FEE City Philosophy for Transportation System Costs The City of Fort Collins sets policy to ensure that safe and sufficient streets will be built and funded. Basic City philosophy
More informationPlanning and Zoning Division Department of Community & Economic Development. Applicant: Pat Milne
HISTORIC LANDMARK COMMISSION STAFF REPORT Pat Milne, Solar Panel Installation, Appeal of Administrative Decision, 470-08-07, 475 E Third Avenue in the Avenues Historic District May 7, 2008 Planning and
More informationTOWN OF STOWE DEVELOPMENT REVIEW BOARD Findings of Fact & Conclusions of Law
TOWN OF STOWE DEVELOPMENT REVIEW BOARD Findings of Fact & Conclusions of Law PROJECT #: 5790 LOCATION: 1199 & 1203 Waterbury Road (#07-309.010) APPLICANT/PROPERTY OWNER: Thomas C. Michelson 87 Farr Hill
More informationContents 8/31/2017 DRAFT REGIONAL IMPACT FEE FACILITIES PLAN & ANALYSIS
Contents Executive Summary... 2 Introduction... 2 Impact Fee Facilities Plan and Impact Fee Analysis... 2 Level of Service... 2 Excess Capacity Used by New Development... 3 Building Facilities for New
More informationHeadwaters Underground Water Conservation. District Hill Country Priority Groundwater Management Area
GW Special Designations Comparison of Water Availability Rules, Hill Country Counties Southeast Trinity Groundwater Conservation Hill Country Priority Groundwater Management Area Hill Country Underground
More informationA Guide to the Municipal Planning Process in Saskatchewan
A Guide to the Municipal Planning Process in Saskatchewan An overview of the municipal planning, development permit and the subdivision approval processes in Saskatchewan July 2016 Prepared By: Community
More informationRUBONIA SUBDIVISION DRAINAGE AND ROADWAY IMPROVMENTS PREPARED BY: MANATEE COUNTY PUBLIC WORKS ENGINEERING SERVICES DIVISION
RUBONIA SUBDIVISION DRAINAGE AND ROADWAY IMPROVMENTS PREPARED BY: MANATEE COUNTY PUBLIC WORKS ENGINEERING SERVICES DIVISION OCTOBER 7, 2016 1 INTRODUCTION Rubonia Neighborhood (Rubonia) is located in northern
More informationCITY OF SALEM. Legislation Text. November 2016 Police Facility General Obligation Bond Measure Resolution
CITY OF SALEM 555 Liberty St SE Salem, OR 97301 Legislation Text File #: 16-117, Version: 1 TO: THROUGH: FROM: Mayor and City Council Steve Powers, City Manager Dan Atchison, City Attorney SUBJECT: November
More informationSection 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS
Section 7.25 REGULATION OF SOLAR FARMS AND SOLAR PANELS This amendment Solar Energy is hereby added to the Montcalm Township Zoning Ordinance to state as follows: A. INTENT AND PURPOSE This section is
More informationPotential Pumped Hydroelectric Energy Storage Sites in Colorado
Potential Pumped Hydroelectric Energy Storage Sites in Colorado University of Colorado at Boulder Department of Electrical Engineering Utility Management Jonah Levine Jonah.Levine@Colorado.edu Dr. Frank
More informationSustainable Design Plan
Draft Jan 2012 4 Contents 4.1 Sustainable Approach to Design and Development 4.1.1 Understanding Sustainability 4.1.2 Response to Context and Location 4.2 Energy 4.2.1 Energy and Transportation 4.2.2 Local
More informationCity of Glendale Stormwater Management Plan Checklist
City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP
More informationCITY OF BOTHELL PUBLIC NOTICE State Environmental Policy Act DETERMINATION OF NON-SIGNIFICANCE
CITY OF BOTHELL PUBLIC NOTICE State Environmental Policy Act DETERMINATION OF NON-SIGNIFICANCE Description of proposal: The applicant proposes a Preliminary Plat to subdivide 6.79 acres into 21 residential
More informationArticle I Development Code Applicability
Article I Development Code Applicability States the purpose, authority, applicability, and rules for interpretation of the zoning regulations. Adopts the Zoning map and includes a matrix showing the relationship
More informationCOUNTY COUNCIL OF BALTIMORE COUNTY, MARYLAND Legislative Session 2017, Legislative Day No. 11. Bill No
COUNTY COUNCIL OF BALTIMORE COUNTY, MARYLAND Legislative Session 0, Legislative Day No. Bill No. - Mrs. Vicki Almond, Councilwoman By the County Council, June, 0 AN ACT concerning Solar Facilities A BILL
More informationCity of Placerville Planning Commission AGENDA
Item 4.2 Placerville, a Unique Historical Past Forging into a Golden Future City of Placerville Planning Commission AGENDA MEETING DATE: January 19, 2016 APPLICATION & NO: 2845 Pleasant Street - Site Plan
More informationThe Port Authority will demolish, remediate, and clear the site for future development by a company or end user.
Who is the Port of Greater Cincinnati Development Authority? The Port of Greater Cincinnati Development Authority (Port Authority) is a quasi-governmental, economic development agency that initiates projects
More informationCase Study: Stearns County, Minnesota
Case Study: Stearns County, Minnesota An early leader in incorporating solar development into local plans and regulations, Stearns County is in a desirable location for solar farm development. Much of
More informationCoastal Hazards Vulnerability and Fiscal Impact Study Report:
Agenda Item B.1 Coastal Hazards Vulnerability and Fiscal Impact Study Report: Vulnerability Assessment and Adaptation Strategies Review October 12, 2015 Planning Commission Meeting Presentation by: Anne
More informationC&B Alberta Solar Development ULC
Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017
More informationPatrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director
DATE: April 26, 2016 TO: FROM: Ron Davis, Interim City Manager Patrick Prescott, Community Development Director By: David L. Kriske, Assistant Community Development Director SUBJECT: Modification of two
More informationINTENT STATEMENT. Division Director Sign-off LDC
INTENT STATEMENT Update the Land Development Code to Implement the Comprehensive Plan s Policies on calculating density for multifamily and intensity for non residential development on constrained parcels.
More information181 State Road 415, New Smyrna Beach. Railey Harding & Allen, P.A. Barcelo Developments, Inc. Scott Ashley, AICP, Planning Manager
GROWTH AND RESOURCE MANAGEMENT DEPARTMENT PLANNING AND DEVELOPMENT SERVICES DIVISION CURRENT PLANNING ACTIVITY 123 W. Indiana Avenue, Room 202, DeLand, FL 32720 (386) 943-7059 PUBLIC HEARING: CASE NO:
More informationVancouver Wharves Diesel Handling Facility Expansion Project
Vancouver Wharves Diesel Handling Facility Expansion Project March 2018 1 Project Information 1. Vancouver Wharves Today 2. Project Rationale 3. Project Overview New Tanks, Railcar and Vessels 4. Project
More informationTrees as part of a Resilient Region
Trees as part of a Resilient Region City of Grand Rapids Suzanne Schulz Design & Development Planning, Managing Director GI Benefits and Practices Why Trees are Important Reduces Stormwater Runoff Increases
More informationDecision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013
Decision 2013-180 13.05-kW Photovoltaic Micro-Generation System May 15, 2013 The Alberta Utilities Commission Decision 2013-180: 13.05-kW Photovoltaic Micro-Generation System Application No. 1609500 Proceeding
More informationAcreage: Acres Requested Action: Current Proposed LAND USE AGR(iv) ROS ZONING PUD & AGR ROS. Existing Maximum Intensity (FAR) 0 SF
PROPOSED SEMI-ANNUAL FUTURE LAND USE MAP (FLUM) AMENDMENT OVERVIEW ORDINANCE: 2010-877 APPLICATION: 2010E-001-6-11-492 APPLICANT: ALEXA GRAF; ENGLAND-THIMS AND MILLER, INC PROPERTY LOCATION: 8517 Cedar
More informationDRAFT Subject to modifications
TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M To: Council Members AGENDA ITEM 7 From: Date: Staff July 17, 2009 Council Meeting Subject: Florida Power and Light Company Riviera Beach Energy
More informationPlanning and Economic Development, City of St. Petersburg, FL
Planning and Economic Development, City of St. Petersburg, FL I. Review of Process June 23, 2011 August 25, 2011 October 20, 2011 January 19, 2012 PS&I Workshop PS&I Workshop City Council Workshop City
More informationSubstitute 1 to Ordinance
Substitute 1 to Ordinance 17-044 Solar Energy Systems - new to our code Minor and Major Utilities - amended Revised: NCC Land Use 09/28/17 Page 1 - SES - SOLAR ENERGY SYSTEM Per State Code, renewable energy
More informationThe City of Red Deer
Decision 2010-148 The City of Red Deer 15-kW Solar Power Plant for City of Red Deer Civic Yards Building April 5, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-148: The City of Red Deer 15-kW Solar Power
More informationORDINANCE NO BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF GRAND FORKS, NORTH DAKOTA, PURSUANT TO ITS HOME RULE CHARTER THAT:
ORDINANCE NO. 4701 An ordinance to amend the zoning map to rezone and exclude from the Columbia Park West PUD (Planned Unit Development), Concept Development Plan, Amendment No. 5 and to include within
More informationYale Hydroelectric Project FERC Project No APPLICATION FOR NEW LICENSE FOR MAJOR PROJECT Volume I
APPLICATION FOR NEW LICENSE FOR MAJOR PROJECT Volume I Executive Summary Initial Statement Exhibit A - Description of the Project Exhibit B - Project Operation and Resource Utilization Exhibit C - Construction
More informationTown of Windham Land Use Ordinance Table of Contents
Town of Windham Land Use Ordinance Table of Contents SECTION 100 GENERAL 101 Title... 1-1 102 Purpose... 1-1 103 Severability Clause... 1-1 104 Conflicts... 1-2 105 Conformance Required... 1-2 106 Rules
More informationDEPARTURE FROM THE NUMBER OF PARKING & LOADING SPACES 289
The Maryland-National Capital Park and Planning Commission Prince George's County Planning Department Development Review Division 301-952-3530 DEPARTURE FROM THE NUMBER OF PARKING & LOADING SPACES 289
More informationCapital Facilities Element
Capital Facilities Element Purpose The Growth Management Act requires cities to prepare a capital facilities element consisting of: 1. An inventory of current capital facilities owned by public entities,
More informationKANKAKEE COUNTY PLANNING DEPARTMENT APPLICATION FOR CLASS I & II GRADING AND DRAINAGE/STOMRWATER PERMIT APPLICATION
KANKAKEE COUNTY PLANNING DEPARTMENT APPLICATION FOR CLASS I & II GRADING AND DRAINAGE/STOMRWATER PERMIT APPLICATION Michael J. Van Mill, AICP Planning Director 189 East Court Street Kankakee, IL 60901
More informationSTAFF REPORT SAUSALITO CITY COUNCIL
STAFF REPORT SAUSALITO CITY COUNCIL MEETING DATE: June 14, 2016 AGENDA TITLE: Approving a Variance from the Elevation Requirements of the Floodplain Management Section of the Sausalito Building Code for
More informationVillage Mixed Use Land Use Designation. Village Mixed Use Zoning District
Vi l l a g e o f P a l m e t t o B a y Village Mixed Use Land Use Designation and Village Mixed Use Zoning District Staff Presentation 19 March 2018 VMU Update O r d i n a n c e t o r e v e r t t o V M
More informationCITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION. Verizon Wireless at 2160 W Drake Road Combined PDP and FP
CITY OF FORT COLLINS TYPE 1 ADMINISTRATIVE HEARING FINDINGS AND DECISION HEARING DATE: November 13, 2013 PROJECT NAME: CASE NUMBER: APPLICANT: OWNER: HEARING OFFICER: Verizon Wireless at 2160 W Drake Road
More informationCity and County of Broomfield, Colorado CITY COUNCIL AGENDA MEMORANDUM. 11f - Page 1
To: From: Prepared by: Agenda Title: CITY COUNCIL AGENDA MEMORANDUM Mayor and City Council Charles Ozaki, City and County Manager Jim Becklenberg, Assistant City and County Manager David Allen, Director
More informationSOLAR ENERGY FARMS AND SOLAR ENERGY SYSTEMS
Chapter XI SOLAR ENERGY FARMS AND SOLAR ENERGY SYSTEMS 1. Purpose Rev. 06-07-17; Ord. 752 A. The purpose of this Chapter is to maintain the City s attractiveness, protect the safety of the people, and
More informationNOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT
Date: September 18, 2017 NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT To: Agencies and Interested Parties Lead Agency: Sacramento Municipal Utility District 6201 S Street, MS H201 Sacramento,
More informationTES Industrial Development SW ¼ SEC Lacombe County Outline Plan
TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1
More informationCypress Waters: TIF Plan and MOU Amendments, Related Service Plan/Development Agreements and Boundary Adjustments
Cypress Waters: TIF Plan and MOU Amendments, Related Service Plan/Development Agreements and Boundary Adjustments Economic Development Committee June 1, 2015 Purpose Update status of Cypress Waters project
More informationDecision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013
Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013
More informationSLOT HOME STRATEGY OVERVIEW
ALLEY ALLEY ALLEY SLOT HOME STRATEGY OVERVIEW In recent years, slot homes have been constructed in many neighborhoods throughout Denver, resulting in a new development pattern that can detract from the
More informationStatement of. Tony Ferguson, USDA Forest Service Director of Minerals and Geology. Management. Before the. House Committee on Natural Resources
Statement of Tony Ferguson, USDA Forest Service Director of Minerals and Geology Management Before the House Committee on Natural Resources Subcommittee on Energy and Mineral Resources Concerning The President
More informationSECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT
SECTION 7 Public Infrastructure, Facilities and Services 8Chapter 8 INFRASTRUCTURE ELEMENT INF-2 CHAPTER 8 Infrastructure Element INTRODUCTION Cupertino s public infrastructure works in tandem with the
More informationH 6062 S T A T E O F R H O D E I S L A N D
LC001 01 -- H 0 S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 01 A N A C T RELATING TO AGRICULTURE AND FORESTRY - FARM CONSERVATION AND RENEWABLE ENERGY Introduced By: Representative
More informationPlease sign in at the front desk and provide your contact information if you would like to receive project updates.
Community Meeting Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If you have
More informationSpecial Use Permit Application Martin Street Property
Special Use Permit Application Martin Street Property Submitted to City of Reno February 08, 2016 Prepared for PCD Asset Group 2760 Camino Diablo Walnut Creek, CA 94597 Prepared by Martin Street Property
More informationMEMORANDUM. Tax map number(s) / total acreage: acres of parcels 12J-5-1, 12J-5-2, 12J-5-3, 12J-5-3A & 12J-5-4A / 12.
MEMORANDUM To: From: Subject: Board of Supervisors Sandra M. Shackelford, Planner SMS Rezoning # PL-15-28 (Timberlake Road) Date: October 27, 2015 BACKGROUND: This request is to rezone 10.76 +/- acres
More informationSection I - Introduction
Section I - Introduction A. Purpose The purpose of this document is to present information to Professional Services Firms that will allow them to design projects, prepare construction documents and provide
More informationTown Board of Trustees December 10, 2013
Town Board of Trustees December 10, 2013 Project Team Abrika Properties LLC Ric Newman & Alan Cohen Planner: Pylman & Associates Edwards, CO 81632 Site Design: DHM Design Carbondale, CO Engineer: Alpine
More informationLynnwood Link Extension 2013 Draft EIS Comments and Responses
Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,
More informationCITY OF ST. MICHAEL WRIGHT COUNTY, MINNESOTA ORDINANCE NO THE CITY COUNCIL OF THE CITY OF ST. MICHAEL HEREBY ORDAINS:
CITY OF ST. MICHAEL WRIGHT COUNTY, MINNESOTA ORDINANCE NO. 1507 AN ORDINANCE AMENDING SECTION 155.073 OF THE ST. MICHAEL CODE TO ADD DEFINITIONS FOR SOLAR ENERGY SYSTEMS, AND ADD COMMUNITY SOLAR GARDEN
More informationEL DORADO COUNTY GENERAL PLAN PUBLIC SERVICES AND UTILITIES ELEMENT PRINCIPLE INTRODUCTION RELATIONSHIP TO OTHER ELEMENTS
EL DORADO COUNTY GENERAL PLAN PUBLIC SERVICES AND UTILITIES ELEMENT PRINCIPLE The Plan must identify the types of governmental services which are necessary to meet residents needs and provide a fiscally
More informationCity of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT
City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT TO: Planning and Zoning Board FROM: Carlos M. Rivero, City Planner DATE: August 10, 2015 RE: Storage Facility P&Z ITEM # 15-010 OWNER
More informationSELF-EVALUATION FORMS. A tool for Michigan communities seeking RRC certification
SELF-EVALUATION FORMS A tool for Michigan communities seeking RRC certification The Redevelopment Ready Communities (RRC) best practices self-evaluations are a tool for communities seeking RRC certification.
More informationREQUEST FOR PLANNING COMMISSION ACTION. 1. Consideration of a Mitigated Negative Declaration.
REQUEST FOR PLANNING COMMISSION ACTION IV.A REDLANDS UNIFIED SCHOOL DISTRICT, APPLICANT (PROJECT PLANNER: MANUEL BAEZA) 1. Consideration of a Mitigated Negative Declaration. 2. PUBLIC HEARING to consider
More informationINITIAL STUDY FOR NEIGHBORHOODS K AND L AT MOUNTAIN HOUSE
INITIAL STUDY FOR NEIGHBORHOODS K AND L AT MOUNTAIN HOUSE Prepared for San Joaquin County Community Development Department September 2011 Prepared by Amy Skewes-Cox, AICP In conjunction with NATALIE MACRIS
More information