Size: px
Start display at page:

Download ""

Transcription

1

2

3

4

5

6

7

8

9

10

11

12

13 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 1 A Preliminary Environmental Policy Review This section briefly outlines the policy framework in relation to the environment for the development of the proposed Corsbie Moor Wind Farm. While it does not contain an in-depth discussion of the specific policies, it does outline the primary policy documents, and their key points, that will need to be taken into consideration. Relevant, specific policies contained within these documents will be fully documented for each of the technical assessments as part of the ES. A separate Planning Statement will also be prepared as part of the overall suite of application documents which will review the extent to which the application complies with relevant national policy and the Development Plan. Under the provisions of Section 25 of the Town and Country Planning (Scotland) Act of 1997, there is a requirement placed on the decision-maker dealing with planning applications whereby the decision has to be made in accordance with the development plan, unless material considerations indicate otherwise. Emerging development plans are examples of material considerations as are national planning policy issued by the Scottish Government. The weight to be given to material considerations against the development plan is a matter for judgement in each individual case. Despite the primacy that legislation gives to the development plan, it is useful to start an assessment of the policy context by looking at the national policy framework, which is the basis under which more local policies will evolve. The assessment of policy context then moves down through the strategic advice in the Structure Plan and finally to the local policy advice in the Local Plan. The National Planning Policy Framework The second National Planning Framework (NPF 2) (approved June 2009) along with the recently approved Scottish Planning Policy (SPP) (February 2010), provides the relevant national planning policy framework for the proposed development. NPF 2 is concerned with Scotland in its wider context and it addresses the major contemporary challenges of global competition, climate change and resource depletion. In regards to energy, it recognises the main challenges as tacking climate change and reducing dependency on fossil fuels. NPF 2 states that the Scottish Government has set high targets for the generation of electricity from renewable means along with other objectives. The SPP recognises that the planning system has a key role in tackling climate change and states that: the need to help mitigate the causes of climate change and the need to adapt to its short and long term impacts should be taken into account in all decisions throughout the planning system. The SPP states that the current (non-capped) target for electricity generation is 50% from renewable sources by 2020 and recognises the current role of onshore wind power. The SPP also states that Development plans should support all scales of development associated with the generation of energy and heat from renewable sources, ensuring that an area s renewable energy potential is realised and optimised in a way that takes account of relevant economic, social, environmental and transport issues and maximises benefits. PAN45 Renewable Energy Technologies, and its two Annexes, is currently being revised in order to reflect the change in the national framework arising from the consolidation of the SPP into one document.

14 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 2 The Development Plan The applicable Development Plan comprises the approved Scottish Borders Structure Plan (2002) with alterations (2005 and 2009) and the Scottish Borders Local Plan, adopted Scottish Borders Structure Plan One of the main aims of the approved Structure Plan is for residents of the area to benefit from new development which makes best use of resources, is well integrated with its surroundings, and is of a high quality, environmentally sensitive design and a high quality, safe and healthy environment. Structure Plan Policies which are directly relevant to the development proposed include: Policy I19 Renewable Energy which provides support for appropriately sited and designed renewable energy development. Policy I20 Wind Energy Developments states criteria against which wind energy developments will be assessed. These include impacts upon amenity and aeronautical safety. The Structure Plan contains a diagram indicating the preferred areas of search for wind energy development. The proposed site is located within a preferred area. In addition to the substantive policies identified above, the Structure Plan contains a number of additional policies which seek to protect the environment and amenity, these include: Principle S1 Environmental Impact Policy N2 International Sites Policy N3 National Sites Policy N4 Precautionary Principle Policy N5 Local Biodiversity Action Policy N6 Environmental Impact Policy N7 Protection of Nature Conservation Interest Policy N8 River Tweed System Policy N9 Maintaining Landscape Character Policy N10 National Scenic Areas Policy N11 Areas of Great Landscape Value Policy N13 Parks and Designed Landscapes Policy N14 National Archaeological Sites Policy N15 Regional and Local Archaeological Sites Policy N16 Archaeological Evaluation, Preservation and Recording

15 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 3 Policy N17 Listed Buildings Policy N18 Conservation Areas Policy N20 Design Policy E22 Protection of the Tourism Industry Policy C8 Access Network Scottish Borders Local Plan Policy D4 Renewable Energy Development within the adopted Local Plan is directly applicable to the proposed development. It is a Development in the Countryside policy which stipulates the Council s support for renewable energy developments where they can be accommodated without unacceptable impacts on the environment. Policy D4 recognises the importance of wider economic and environmental benefits which can be associated with renewable energy developments. It also sets out a number of assessment criteria applicable to commercial scale wind farm developments. The adopted local plan also contains a number of generic policies aim to protect the environment and amenity which are of relevance to the proposed development. Principle 1 Sustainability Policy G1 Quality Standards for New Development Policy BE1 - Listed Buildings Policy BE2 - Archaeological Sites and Ancient Monuments Policy BE3 Gardens and Designed Landscapes Policy NE1 - International Nature Conservation Sites Policy NE2 - National Nature Conservation Sites Policy NE3 - Local Biodiversity Policy NE5 - Development Affecting the Water Environment Policy EP 1 - National Scenic Areas Policy EP2 - Areas of Great Landscape Value. Policy H2 - Protection of Residential Amenity Policy INF 2 Protection of Access Routes Policy INF 6 Development within Exclusion Zones Supplementary Planning Guidance Draft Supplementary Planning Guidance (SPG) relating to Wind Energy was published in May This document includes a Spatial Strategy indicating areas with differing levels of constraints. The Corsbie Moor site is identified as being within an area of Moderate (lower) constraints with pockets of Minor constraints. The area surrounding the site is afforded

16 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 4 significant protection, however the actual site is considered potentially appropriate for the development of wind farm; subject to the findings of relevant assessments. The SPG indicates that proposals in this area should be determined against the requirements of Policy D4 along with the requirements of Section 6.4 of the SPG which relates to impacts upon AGLVs and NSAs, Tourism, Nature Conservation Sites, Shadow Flicker, Noise, Ecology, Ornithology, Biodiversity and Nature Conservation, Aviation, Decommissioning, Communities and Grid. B Archaeology and Cultural Heritage Policy Context Cultural heritage is represented by a wide range of features, both above and below ground that result from past human use of the landscape. These include standing buildings, many still in use, sub-surface archaeological remains, and artefact scatters. It also includes earthwork monuments as well as landscape features such as field boundaries and industrial remains. Certain features that are deemed to be of particular importance are given legal protection as Scheduled Ancient Monuments through the Ancient Monuments and Archaeological Areas Act 1979 (AMAAA). Similarly, the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997 provides for the definition and protection of Listed Buildings and Conservation Areas of architectural and historical interest. This is currently in the process of being amended by the Historic Environment (Amendment) (Scotland) Bill, which is currently before the Scottish Parliament. Further advice on how cultural heritage should be treated is given in SPP and in Planning Advice Note (PAN) 42. PAN42 deals with archaeology, and sets out policy for the protection of features designated under the Ancient Monuments and Archaeological Areas Act The SPP provides the national policy framework for future development, and includes a section on the impacts of development on the historic environment (encompassing Scheduled Monuments and non-designated archaeological sites, Listed Buildings, Conservation Areas, Gardens and Designed Landscapes and World Heritage Sites). Further detail and clarification is provided in the Scottish Historic Environment Policy (SHEP). Regional planning policy relevant to archaeology and cultural heritage is set out above. Baseline Overview Data was obtained on designated features recorded within the site and a 5km envelope surrounding it through GIS datasets downloaded from the Historic Scotland website 1. In addition, data on non-designated cultural heritage features recorded by the National Monuments Record of Scotland (NMRS) and the Scottish Sites and Monuments Records (SSMR) in the surrounding area has been obtained from the Royal Commission on the Ancient and Historical Monuments of Scotland (RCAHMS) on-line Pastmap resource. 1 last accessed on 4th May 2010

17 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 5 Designated Features No designated cultural heritage features have been identified within the site boundary. The nearest Scheduled Monuments to the site are Corsbie Tower (located approximately 900m from the site and 1.6km from the nearest indicative turbine location) and forts at Knock Hill (located approximately 600m from the site boundary). A further eleven Scheduled Monuments lie within 5km of the site boundary. The next nearest of these monuments are at Whitslaid Tower (1.2km west of the site boundary), Houndslow, (2km to the east of the site boundary) and Blythe settlement (2.7km north of the site boundary). Other Scheduled Monuments lie more than 3km from the site, including Black Hill Fort (5.5km south of the site boundary) identified by Historic Scotland as a potential receptor during preliminary consultations. The nearest listed buildings to the site are as follows: Old Bridge Galadean, (Category B), approximately 500m west of the site boundary; Birkhill House (Category B), approximately 500m west of the site boundary; Bassendean House, (Category B), approximately 700m south of the site boundary; Corsbie Farmhouse, (Category B), approximately 800m south of the site boundary; Corsbie Tower, (Category B), approximately 900m south of the site boundary; and Legerwood Church and Churchyard (Category B), approximately 1km south of the site boundary. The nearest Category A listed building is Greenknowe Tower which is located approximately 2.9km south of the site boundary. The closest Garden and Designed Landscapes are Thirlstane Castle, located 4km north-west of the site boundary and Mellerstain, located 4.1km south of the site boundary. The closest World Heritage Site is Edinburgh Old and New Towns, approximately 42km northwest of the site boundary. The Lauder Conservation Area is, at its closest, 4.8km north-west of the site boundary. Preliminary site layouts taking into account potential constraints such as microwave and similar fixed links and proximity to dwellings indicate that turbines will not be located close to the site boundary. The distances of identified features from the nearest turbine will therefore be greater than the distance to the site boundary, and in some cases substantially greater. In particular, features to the west and north-west of the site (e.g. Old Bridge Galadean and Birkhill House) are likely to be up to 2.5km further from the nearest turbine than from the site boundary, while features to the south of the site (e.g. Knock Hill) are likely to be up to 1.5km further from the nearest turbine than from the site boundary. Non-designated Features Several features and areas of archaeological interest are recorded within the site by the NMRS and SSMR. These mostly refer to cropmarks and earthworks identified on aerial photographs, and chance finds of artefacts. The cropmarks and earthworks are indicative of sub-surface archaeology and suggest that the remains of prehistoric settlement may be present within parts of the site. Features and areas of interest currently identified within the site are as follows:

18 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 6 Possible prehistoric enclosures at Eden Burn (SSMR , NMRS NT64NW12, NT64NW13, NT64NW14, NT64NW31, NT64NW42) Dean Brae Burn (NMRS NT64NW42) and Dean Brae (NMRS NT54NW45) and ring-ditch at Eden Burn (NMRS NT64NW41) identified through aerial photography in the south-east corner of the site and forming a discrete group of prehistoric features overlain by later ridge and furrow cultivation; flint arrowhead and stone spindlewhorl (NMRS NT64NW27) found at Corsbie Moor; ridge and furrow cultivation at Corsbie Moor (NMRS NT64NW37) and Cribbs Covert (NMRS NT54SE67); possible prehistoric pit alignment at Legerwood (NMRS NT54SE38); and Boon Black Dyke possible road or trackway at (NMRS NT54SE68, NT54SE66, NT54NE64) is recorded on either side of the site, suggesting it crosses the site from north to south at Stell Wood. Further features within the 500m study area but beyond the site boundary are of similar character, including a pit alignment (NMRS NT54SE60), prehistoric fort (NMRS NT54SE55) and enclosure (NMRS NT54SE34) at Gala Dean, a prehistoric enclosure (NMRS NT54SE32) and medieval mill-lade (NMRS NT54SE36) at Whitslaid, and an enclosed settlement at Boon (NMRS NT54NE47) to the west of the site. To the north, a barbed and tanged arrowhead (NMRS NT64NW25) and stone axehead (NMRS NT64NW26) were found at Hyndsidehill, and to the east, there are further records of ridge and furrow cultivation (NMRS NT64NW35), and prehistoric artefacts (axe-hammer, flint knife and arrowhead) from Bassendean House (NMRS NT64NW16, NT64NW17), and a ring-ditch (NMRS NT64NW45) at Green Knowe. These features indicate the presence of prehistoric settlement and occupation of parts of the site and its environs and are representative of the use of the study area in the medieval and later periods. Proposed Scope of Assessment Direct Effects The small footprint of the built development associated with a wind farm significantly lessens the potential for direct effects on cultural heritage features. Nevertheless there are some known features within the site and the potential for previously unrecorded features to be present within the site remains. As a result, it is possible that archaeological features may be directly affected by the proposed development. The EIA process will identify any known features and attempt to establish the potential for further unrecorded features. Where necessary, this information will be used to inform the wind farm design in order to avoid or reduce effects on identified features. To this end, the following additional sources of information would be consulted during the EIA: Royal Commission on the Ancient and Historical Monuments of Scotland (RCAHMS); Regional Sites and Monuments Record/Historic Environment Record; Registers of designated features within 5 km of the site boundaries; Reports of previous archaeological investigations; and

19 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 7 Review of national and local policy relating to cultural heritage. A study area extending up to 500m from the site boundary will be used to identify known cultural heritage features which might be directly affected by the proposals and to assess the potential presence of previously unrecorded features within the site. A site visit and walkover will also be undertaken, with the aim of identifying any visible cultural heritage features within the site, checking available records and noting general ground conditions. It is anticipated that the appropriate micro-siting of turbines during the process of finalising the wind farm layout design will be used to avoid direct effects on cultural heritage features identified during the EIA. However, where this is not possible measures will be adopted to identify and preserve by record any features which have not previously been recorded. This mitigation is subject to further discussion with relevant consultees, including Scottish Borders Council Archaeological Advisor. Effects on Setting Effects on the setting of designated cultural heritage features and the wider historic landscape will also be considered as part of the EIA. These are normally changes to the setting of a feature, whether permanent or temporary. According to national policy guidance such effects are normally considered more relevant to designated features of national importance, such as scheduled monuments, listed buildings, and registered historic parks and gardens. An initial appraisal of likely cultural heritage receptors undertaken as part of the scoping exercise has identified the following receptors in particular for further assessment in the EIA: Corsbie Tower Scheduled Monument and Listed Building; Knock Hill Fort Scheduled Monument; Black Hill Fort Scheduled Monument; Houndslow Scheduled Monument; and Legerwood Church and Churchyard Listed Buildings. An assessment of potential effects on the setting of the above features will be made through a combination of documentary study, site visits (from publicly accessible areas) and wireframe illustrations. It is additionally proposed that this element of the assessment will be open to consultees, including the relevant planning officer, to encourage ongoing consultation. The aim will be to establish the current setting of the feature and how this might be affected, in consideration of factors such as distance, topography and available screening from vegetation and built development. Where the potential for a significant effect on setting is identified photomontage viewpoints may also be prepared. The assessment will then be made based on professional judgement with reference to a stated methodology, bearing in mind available guidance such as Historic Scotland s Assessment of Impact on the Setting of Historic Environment Resources and any scoping responses or information arising from further consultation. Other designated features within the proposed 5km study area appear unlikely to be significantly affected by the proposed development as a result of their distance from the site and the presence of intervening landform or plantation which provides a degree of screening. However, further research and assessment will be undertaken as part of the EIA and a brief

20 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 8 account of the assessment of effects on all designated cultural heritage features within the ZTV and a distance of 5km of turbines will be presented in the ES. The assessment of effects on the setting of cultural heritage features will be carried out in close consultation with the landscape and visual assessment, with the latter particularly considering the visual amenity aspect of cultural heritage receptors. Confirmation of the proposed scope and any further receptors which consultees may regard as worthy of further assessment, is requested. Assessment Methodology/Approach The EIA would include a description of the research undertaken and results obtained, as well as an assessment of the nature and significance of the likely effects of the proposed development. Consideration would be given to any necessary mitigation, following consultation with E.ON and consultees. All work will be completed in accordance with the Institute for Archaeologists Code of Conduct and Standard and Guidance for Archaeological Desk-Based Assessments (2008). C Landscape, Visual Amenity and Related Issues Policy Context The Landscape and Visual Assessment (LVA) section of the EIA will be undertaken with reference to a number of best practice documents. In particular reference will be made to methodological approaches set out in the following publications: Guidelines on Landscape and Visual Impact Assessment (GLVIA). Second Edition. The Landscape Institute and Institute of Environmental Management and Assessment. 2002; 2 Institute of Environmental Management and Assessment (IEMA) and the Landscape Institute s Guidelines for Landscape and Visual Assessment, second edition (LI/IEMA, 2002); Guidelines on Environmental Impacts of Wind Farms and Small Scale Hydro Electric Schemes. Scottish Natural Heritage. 2001; Siting and Design of windfarms in the landscape Version 1, Scottish Natural Heritage, December 2009; Visual Assessment of Wind Farms: Best Practice. University of Newcastle. Scottish Natural Heritage Report No. F01AA3030A. 2002; Cumulative effects of wind farms a guidance note (SNH, 2005) and the emerging 3rd Version which is currently out to consultation; Visual Representation of Wind Farms Good Practice Guidance (SNH, 2006); 2 We are aware that consultations are underway to revise the GLVIA for a third edition and if this is published during the lifespan of this EIA its contents will be incorporated into the LVA.

21 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 9 Visual Representation of Windfarms: Good Practice Guidance. The Scottish Renewables Forum and the Scottish Society of Directors of Planning, Horner & Maclennan and Envision, 2006; Landscape Character Assessment: Guidance for England and Scotland. University of Sheffield and Land Use Consultants. The Countryside Agency and Scottish Natural Heritage. 2002; Ordnance Survey (OS) Mapping; and Aerial photographs. Baseline Overview The proposed study area for the project will be a 35km radius, based on guidance by Scottish Natural Heritage in relation to proposed turbine size. This is primarily focussed upon the Scottish Borders, although also extends in to East Lothian and Midlothian in the north. The south eastern portion of the study area also extends into the northern extent of Northumberland, England. Landscape Character Landscape Character Typologies within the Scottish Borders area are identified in The Borders Landscape Assessment (ASH Consulting Group, 1998). With regard to the proposed Corsbie Moor Wind Farm, the site is located within the Upland Fringe: Rolling Farmland landscape character type, which is located to the south of the Lammermuir Hills. This character type is characterised by undulating slopes and rolling hills with distinctive mounds and terraces. Land cover is mainly arable and pasture enclosed by mature hedgerows as well as coniferous shelterbelts and plantation forestry. There are also scattered areas of broad-leaved woodland. Landscape Designations Initial research indicates that a number of landscape designations are located within the proposed study area and it may be possible to view the proposed wind turbines from certain vantage points within some of them. These include amongst others: National Scenic Areas (NSA): Eildon Hills. Area of Great Landscape Value (AGLV): Lammermuir Hills; Moorfoot Hills; Eildon and Bowhill. Area of High Landscape Value (AHLV: Tweed Valley. Historic Gardens and Designed Landscapes (HGDL):

22 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 10 Thirlestane Castle; Mellerstain; Priorwood Garden; Bemersyde; Abbotsford. National Trails: Southern Upland Way. Country Parks: The Hirsel Country Park; Bowhill House and Country Park. Proposed Scope of Assessment The LVA chapter will include two related assessments which will look at the effects on the landscape as a whole, as well as those of potential visual receptors located in the vicinity of the site. These are described in more detail below. Landscape Assessment The landscape assessment will include the direct and indirect effects on the landscape resource and various landscape receptors, including landscape character and landscape designations, as well as landscape elements and features. Landscape Character Effects on landscape character areas that have been defined within the local studies 3,4,5 and which are partly or completely located within the Zone of Theoretical Visibility (ZTV) will be assessed. The LVA will focus on those character areas in closest proximity to the application site (i.e. within 10km radius) which are likely to be most affected by the development. This is an approach we have used successfully in previous wind farm LVAs and avoids burdening the LVA with large amounts of erroneous information. Landscape Designations The assessment of landscape designations will also concentrate upon those within the detailed 10km radius study area, where experience indicates that potential significant effects are most likely to occur. Designations which have a cultural heritage dimension, such as listed buildings, scheduled monuments and registered battlefields will be assessed within the cultural heritage 3 Borders Landscape Assessment (ASH Consulting Group, 1998) 4 Lothians Landscape Character Assessment (ASH Consulting Group, 1998) 5 Currently there is no landscape character assessment for the Northumberland area (Northumberland County Council is in the process of producing this) and as a result the National Character Areas described in the North East England Landscape Assessment will be referenced.

23 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 11 chapter. However, the LVA will assess effects upon registered historic gardens and designed landscapes. Landscape Elements The landscape assessment will include direct and indirect effects upon landscape elements and patterns within the application site and immediate context, such as hedgerows and the field boundary pattern. This will include consideration of its condition and capacity. Visual Assessment Visual effects are recognised by the Landscape Institute as being a subset of landscape effects and are concerned wholly with the effect of a proposed development upon the views and the visual amenity of visual receptors: people, who live, work, undertake recreational activities or travel through the study area. Visual receptors are categorised by their visual sensitivity to change in accordance with their principal activity in line with the GLVIA. Some visual assessments are based completely or substantially upon a detailed assessment of a limited number of viewpoints from where the likely effects upon visual receptors are illustrated by photomontages and/or wireframes. Entec s approach, whilst making extensive use of such visualisation techniques, would be to identify a much wider range of visual receptors either as individuals e.g. at individual residential properties within 3km of a turbine, or amalgamated into groups e.g. all the residents of a particular village or hamlet. Once identified, the predicted magnitude of visual change that would be sustained by the visual receptors will be assessed using information gained from site visits, visualisations such as wireframes and the ZTVs. In accordance with the approach set out in the GLVIA the magnitude of visual change will be combined with the sensitivity of the visual receptor (as accorded within the GLVIA) to produce a level of visual effect. There are seven potential levels of visual effect, two of which: substantial and moderate/substantial are assessed as being significant in the context of The Environmental Impact Assessment Regulations (Scotland) Zones of Theoretical Visibility The selection of which visual receptors are to be included within the visual assessment will be guided by a series of ZTVs. These are generated by a computer software programme (generally Resoft Wind Farm Version 4), that uses the tallest model of the potential turbine type and digital terrain model (dtm) data (generally Ordnance Survey Panorama data) to calculate locations from where either the turbines hubs or nacelles or just the upper blade tips would theoretically be visible. In some locations the extent of woodland cover is such that it is likely to have a strong influence upon the availability of receptors views and it is necessary to amend the dtm data to make allowance for this influence. ZTVs will be produced for both the upper blade tip (currently assumed to be 126.5m high) and hub height of the proposed turbines (currently assumed to be 80m high). Initial ZTV analysis indicates that the visibility of the proposed turbines would be relatively fragmented, particularly beyond a 10km radius from the site. Beyond this distance the ZTV becomes increasingly fragmented, being largely restricted to the area s ridgelines and summits. This preliminary ZTV analysis has influenced the selection of the provisional list of visualisation viewpoints (described below). The initial ZTVs will be re-run for any iterations in the turbine layout that arise during the course of the EIA and for the final layout but experience for other wind farm developments indicates that unless these iterations involve a large increase

24 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 12 or decrease in turbine numbers or turbine specification, the distribution of the ZTVs are unlikely to alter greatly. Visualisation Viewpoints It is proposed to provide photomontages for up to ten viewpoints representing the views of key visual receptors within the 10km radius detail study area as well as wireframes from up to a further eight viewpoint locations at distances of between 10km and 35km from the application site. All visualisations will be prepared according to best practice with regard to key considerations such as viewing distance and the angle of view. The provisional viewpoint locations detailed below have been proposed due firstly to their location within the ZTV and then due to the potential sensitivity of the main individual, group or groups of receptors at or close to, that location or because they provide representative views potentially available to large numbers of visual receptors e.g. inhabitants of one of the larger settlements within the study area. It should also be noted that all viewpoints have to be publicly accessible. Proposed Viewpoint Locations Viewpoint No. and Location Grid Reference Approx Distance from Scheme Reason for Selection Photomontage Viewpoints 1) A6089 (north) NT km Representative of views experienced by road users passing the site to the north east. 2) Ledgerwood NT km Nearby settlement to the south, representative of views experienced by local residents. A viewpoint which includes the Ledgerwood Farm Trail would also be desired. 3) Nether Blainslie NT km Nearby settlement to the west, representative of views experienced by local residents. 4) Houndslow NT km Nearby settlement to the east, representative of views experienced by local residents and road users on the A697. 5) A6089 (east) NT km Representative of views at a close proximity from the local road network where there is a direct view of the site 6) Blythe NT km Nearby settlement to the north, representative of views experienced by local residents. Cumulative viewpoint. 7) Lauder NT km Nearby settlement with outstanding conservation area, representative of views experienced by local residents. 8) View from the A6105 NT km Representative of views from the east of the site on the main road network. Cumulative viewpoint. 9) Eildon Hills NSA NT km Representative of views from national level landscape designation. Cumulative viewpoint. 10) Twin Law Cairns NT km Within Lammermuir Hills AGLV, on route of the Southern Upland Way, experienced by recreational receptors. Cumulative viewpoint. Wireframe Viewpoints 11) Maxwellheugh NT km Representative of views experienced by local residents in this settlement to the south east. 12) Lammer Law Nt km Summit within Lammermuir Hills AGLV

25 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 13 Viewpoint No. and Location Grid Reference Approx Distance from Scheme Reason for Selection 13) Broomy Law NT km Within Eildon and BowHill AGLV, on route of the Southern Upland Way, experienced by recreational receptors. 14) Windlestraw Law NT km Elevated vantage point from hill summit to the west. 15) Heart Law NT km Summit within Lammermuir Hills AGLV 16) Cornhill on Tweed NT km Representative of views experienced by local residents within this settlement in the Tweed Valley AHLV. 17) Torfichen Hill NT km Summit within Moorfoot Hills AGLV 18) Black Law (Dunion Hills) NT km Elevated vantage point from hill summit to the south. Consultees are requested to confirm the appropriateness of these proposed viewpoints and advise of any others if this is considered necessary. Residential Amenity In addition to the comprehensive visual assessment, emerging best practice encourages the assessment to also consider the potential for some close by residential visual receptors to sustain adverse effects upon their residential amenity i.e. the manner in which they may wish to use and enjoy their property and garden/grounds as a consequence of the presence of the turbines. For example a sense that turbines are excessively close and/or surround the property could lead to a curtailment of viable activities in particular rooms or parts of the property such as patios or outdoor swimming pools. Hence the assessment will include site surveys using especially developed proformas to ascertain the potential for such effects to arise taking into account variables such as the orientation of a property and its residents principal views, the distribution of windows and the amount of nearby potential screening vegetation. As such effects are most likely to affect properties in close vicinity to the turbines the residential amenity survey will be restricted to individual properties within 3km of any turbine. Also, as with all aspects of the LVA, the amount of information that can be gained in field surveys will be limited by the availability of public access and, in some cases, the relevant information may have to be interpreted from aerial photographs. Cumulative Effects The landscape and visual cumulative assessment will follow the guidelines set out in SNH s Cumulative Effect of Wind Farms: Guidance. In line with these guidelines the cumulative assessment will include all wind farms, clusters and individual turbines that are operational, consented or for which a full planning application has been submitted within 60km radius of any of the proposed turbines at Corsbie Moor. Wind farm proposals at the screening or scoping stages will be excluded on the basis that they may not progress to full applications and subsequently become operational. Identified wind farms will be grouped in accordance with their planning status and geographical distribution to produce a number of cumulative ZTVs which indicate where one or more of these wind farms would theoretically be visible in nominal 360º views. Potential cumulative landscape effects will be assessed as a commentary using the range of headings that are contained in the previously referenced guidance. One of the key issues will be an assessment of the potential cumulative landscape effects of the various wind farms upon

26 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 14 defined landscape character areas and local landscape designations. Visual cumulative effects will utilise a viewpoint based approach using the agreed visualisation viewpoints from the consultation exercise. 360º colour coded cumulative wireframes will be produced from all the visualisation viewpoints from which more than one wind farm could potentially be visible. These will be used to provide an analysis of the overall visual cumulative effect with the proposed Corsbie Moor Wind Farm; without the proposed Corsbie Moor Wind Farm; and the incremental visual effect of the addition of the turbines at the proposed Corsbie Moor Wind Farm. As this is potentially a complex analysis, the results will be summarised in tabular form. Assessment Methodology / Approach The LVA will clearly set out its methodology in its early sections utilising tables wherever possible to maximise its transparency and replicability. Following on from the methodology section, the LVA will present the baseline conditions in a comprehensive but succinct manner using a number of sub-headings to provide an overall analysis of the prevailing landscape and visual conditions within the 35km radius study area, again concentrating upon the 10km radius detailed study area. It should be noted that these radii would be from the nearest proposed turbine as opposed to from the site centre. It will review relevant landscape commentaries, in particular the relevant sections in the landscape character assessments recently produced by Scottish Borders Council. It will also review and list the relevant policies in the Scottish Borders Local Plan and in the Scottish Borders Structure Plan. The baseline will be supported by a number of figures on OS plans and annotated photographs of the application site and its landscape setting. As recommended by the GLVIA, the LVA will consider the potential landscape and visual effects of the proposed wind farm in separate sections. Consultation and Iterative Design A preliminary consultation meeting has already taken place with planning officers from Scottish Borders Council and a landscape architect from SNH. It is currently anticipated that future consultations will be by letter, or phone call. With regard to the detailed design of the turbine layout and ancillary elements of the proposal and the development of mitigation proposals, it is intended to adopt a design led approach through collaboration between the landscape consultant, the project engineers and the developer/landowner. Key design principles with regard to turbine layouts will be used to review and guide the layout design process through a number of layout iterations. Environmental and technical constraints will be mapped, and along with aesthetic considerations, these will be used as a template against which layout options will be reviewed to achieve an appropriate landscape and visual fit. Design issues that will be considered will include the selection criteria for the turbines including their height. In this respect it should be noted that the blade tip height of 126.5m is a worst case scenario. As part of this process it is envisaged wireframes will be produced from some or all of the visualisation viewpoints. These will allow recommendations for the micro-siting of the turbines to minimise the incidences of potentially adverse design features such as the clustering of turbines; the presence of isolated outlier turbines; the formation of an unbalanced turbine array or excessive amounts of blade overlapping. As the LVA proceeds, mitigation proposals will also be developed with regard to variables such as the colour of the turbines, location and detail design of ancillary elements such

27 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 15 as the control building and access routes and any potential for screen planting close to individual sensitive visual receptors. D Nature Conservation Policy Context The assessment will take account of the requirements of, and advice given in: Council Directive 92/43/EEC on the Conservation of Natural Habitats and of Wild Fauna and Flora; Council Directive 79/409/EEC on the conservation of wild birds (the Birds Directive); The Conservation (Natural Habitats, &c) Regulations 1994 (as amended); Wildlife and Countryside Act 1981 (as amended); The Nature Conservation (Scotland) Act 2004; PAN 60: Planning for Natural Heritage (Scottish Govt, 2000), which provides advice on how development and the planning system can improve the natural environment; Institute of Ecology and Environmental Management (IEEM) guidelines on ecological impact assessment (IEEM, 2006); Survey methods for use in assessment of the impact of proposed onshore windfarms on bird communities (SNH 2005); Assessing significance of impacts from onshore windfarms on birds outwith designated areas (SNH 2006); The UK Biodiversity Action Plan (UKBAP); The Scottish Biodiversity List; and The Scottish Borders Local Biodiversity Action Plan. Baseline Overview Good EIA practice includes identification of any statutorily and non-statutorily designated sites of nature conservation interest within a minimum of 2km of the boundaries of a proposed development, though this may be extended if impacts could potentially extend over a wider area (IEA ). Through use of the Scottish Natural Heritage Website 7 it has been determined that there is only one statutorily designated site within this search area, which is the River Tweed Special Area of Conservation (SAC). Information about this site is provided in the table below 8. 6 Institute of Environmental Assessment (1995). Guidelines for Baseline Ecological Assessment. E & FN Spon. London

28 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 16 Statutory Sites for Nature Conservation within 2km of the Site Site Name Grid Ref. Habitat type Area Distance from site River Tweed SAC NT The SAC comprises much of the River Tweed, which drains a large catchment on the east coast of the UK, with subcatchments in both Scotland and England. The River Tweed is the best example in Britain of a large River with strong nutrient grading along its length, with oligotrophic conditions in its headwaters, and nutrient rich lowland conditions just before it enters the sea at Berwick. 3,796ha 400m to the west of the site It is the most species rich example by far of a river with water-crowfoots Ranunculus spp in Scotland, and is the only site selected for this habitat in Scotland. The closest Site of Special Scientific Interest (SSSI) to the site is Gordon Moss SSSI which is located approximately 3.5km to the southeast. This is a remnant of an alluvial flood plain mire and the SSSI is of noted for a variety of habitats, plants and invertebrates. The site is also a Scottish Wildlife Trust reserve. The closest Special Protection Area (SPA) is Greenlaw Moor SPA, located approximately 9km to the northeast, this being designated on the basis of supporting pink-footed geese. Further Desk Study Information on the presence of non-statutory designated sites and protected species will be obtained from Scottish Borders Biological Records Centre. Additional searches will be made for data relating to the site during the EIA and more detailed consultation with individuals with knowledge of the site will be undertaken, as and when such individuals are identified. Proposed Scope of Assessment In assessing the effects of any development on ecology and nature conservation interests it is necessary to define the areas of land cover and the species and habitats that need to be considered in the EIA. In doing this, two inter-related factors need to be considered: A development can affect habitats and species directly (e.g. the land-take required) and indirectly (e.g. disturbance), with the impacts potentially extending beyond the development site boundaries; It is impractical for an ecological assessment to consider every individual species and habitat that may potentially be affected, rather it should focus on valued ecological receptors, i.e. species and habitats that are valued in some way (e.g. designated sites, species protected by specific legislation or species which have economic value) and which could potentially be affected by the proposed development. It is against this background that the scope of this assessment has been defined through preliminary desk study and an extended Phase 1 habitat survey following standard methodology (JNCC, 1993). The assessment will be based on the following surveys that have been undertaken or are currently on-going.

29 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 17 Habitat Survey An Extended Phase 1 Habitat Survey following standard methodology (JNCC, 1993), with particular focus on assessing the potential for habitats to support species of nature conservation interest, for example protected species, as well as mapping habitats and land use. The site is dominated by improved pasture and arable fields and it is not anticipated at this stage that any further habitat surveys will be required. This will be informed by the Extended Phase 1 Habitat Survey. Protected Species Surveys The Extended Phase 1 Habitat survey will inform the need for further protected species surveys such as badger, otter and water vole. An initial desk study and site visit has not identified any suitable ponds for great crested newts and these are thus scoped out. Bats The site contains numerous woodland edge features as well as burns and hedgerows, all of which could provide suitable foraging opportunities for bats. In addition there are numerous farm buildings in the wider area which could provide potential roosting opportunities. Therefore bat activity surveys and roost assessment surveys will be carried out. In respect of bat surveys, the following methodology was discussed with Ann Brown of SNH during a meeting at Scottish Borders Council on 06/07/2010 and, subject to maintaining flexibility to amend the scope in light of survey findings, was agreed as being appropriate for the Corsbie Moor site. Bat activity survey methods will be based upon guidance provided in the JNCC Bat Workers Manual and the Bat Conservation Trust (BCT) Bat Mitigation Guidelines, involving walking around key pre-determined areas of the site (focusing on the proposed turbine area and incorporating potential bat habitats, particularly ditches and woodland edges or hedgerows) between an hour before and 2-3 hours after dusk, listening for bat species using bat detectors (frequency division and heterodyne). Bat calls will be recorded during the survey so that the identity (species) can be subsequently confirmed using Bat Sound analysis software. Four activity surveys will be carried out between May and September. In addition to the activity survey, a roost assessment would be carried out of potential roost habitat such as mature trees and farm buildings within and surrounding the turbine area. Bird Surveys The site supports a range of common and widespread farmland species and initial desk study and survey work suggests it is unlikely that species of high nature conservation value that may potentially be adversely affected by wind farms regularly occur. Vantage point (VP) surveys following the SNH methodology (SNH 2005) have been carried out from two locations over winter and during the breeding season. 42 hours of survey per VP were undertaken between September and March, with a further 36 hours per VP between April to July inclusive. An additional 6 hours of survey per VP have been undertaken in August to complete the 12 month programme. Survey times were varied to ensure that data were collected at a range of times of the day including dawn and dusk. Target species activity over winter was limited, comprising infrequent flights of small flocks of greylag and pink-footed geese passing high (above collision risk height) over the site and a

30 Appendix to Corsbie Moor Wind Farm Request for Scoping Opinion App pg 18 flock of whooper swan were also recorded on a single occasion. Small flocks of lapwing were also recorded. In addition to the winter VP surveys, monthly walkover surveys were undertaken during the autumn and winter. Flocks of common winter farmland passerines such as linnets, yellowhammers and skylarks were recorded during these surveys as well as regular flocks of corvids and wood pigeons. As well as the breeding season VP watches, territory mapping surveys were also undertaken. Given the habitats present, the most appropriate walkover survey for the Corsbie Moor site was a territory mapping survey based on the Common Bird Census (CBC) methodology, which comprised three visits between April and July. Typical species associated with farmland, such as woodpigeon, lapwing, skylark, meadow pipit and yellowhammer were relatively common, as were passerines associated with woodland blocks such as willow warbler, goldcrest, blue tit, coal tit and chaffinch. Curlew was recorded regularly, though in low numbers, and oystercatcher, buzzard, and flocks of rooks and jackdaws were occasionally recorded. Assessment Methodology/Approach The EIA will focus on assessing the potential impact of the proposed development on any relevant designated sites and any species/habitats of nature conservation value on the site and surrounding area that have been identified as having the potential to be affected. This will include an assessment of collision risk to birds of high nature conservation importance and, where necessary, mitigation and enhancement measures will be explored. Along with LVA for wind farms, ornithological impact assessment commonly forms one of the key components of wind farm EIAs which has led to the publication of a number of bird/wind farm guidance documents. The ornithological impact assessment will be prepared in accordance with such best practice documents and in particular, the following publications and guidelines: Survey methods for use in assessment of the impact of proposed onshore windfarms on bird communities (SNH 2005); Assessing significance of impacts from onshore windfarms on birds outwith designated areas (SNH 2006); and Developing field and analytical methods to assess avian collision risk at wind farms (Band et al 2007). The Ecological Impact Assessment will take account of Institute for Ecology and Environmental Management (IEEM) guidelines for Ecological Impact Assessment (IEEM, ). 9 IEEM (2006). Guidelines for Ecological Impact Assessment in the United Kingdom.

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...

More information

5. ENVIRONMENTAL IMPACT ASSESSMENT

5. ENVIRONMENTAL IMPACT ASSESSMENT 5. ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION Environmental Impact Assessment (EIA) is a process that considers how a proposed development will change existing environmental conditions, and what

More information

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4.1 INTRODUCTION This section describes the broad principles of the methodology adopted for the EIA of the Proposed Development. EIA is a procedure required

More information

GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary

GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary 22871-G8.indd greec01 Dec 2009 December 2009 Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty

More information

CPRW Position statement Single and small groups of wind turbines

CPRW Position statement Single and small groups of wind turbines CPRW Position statement Single and small groups of wind turbines April 2014 The purpose of this Position Statement is to guide CPRW Branches in the approach they adopt when considering the acceptability

More information

POLICY CONTEXT Introduction National Energy Policy Documents National Planning Policy Documents

POLICY CONTEXT Introduction National Energy Policy Documents National Planning Policy Documents 5. POLICY CONTEXT Introduction... 5-2 National Energy Policy Documents... 5-2 National Planning Policy Documents... 5-5 Local Planning Policy Documents... 5-14 Conclusions... 5-23 5-1 5. Policy Context

More information

Toddleburn Wind Farm. Environmental Statement Non-technical Summary. I & H Brown Toddleburn Ltd

Toddleburn Wind Farm. Environmental Statement Non-technical Summary. I & H Brown Toddleburn Ltd Toddleburn Wind Farm Environmental Statement Non-technical Summary I & H Brown Toddleburn Ltd July 2004 Introduction I & H Brown Toddleburn Ltd proposes to develop a wind farm near Oxton, in the Scottish

More information

Carscreugh Renewable Energy Park Non-Technical Summary. April 2006

Carscreugh Renewable Energy Park Non-Technical Summary. April 2006 Carscreugh Renewable Energy Park Non-Technical Summary April 2006 PREFACE An Environmental Statement has been prepared to accompany a planning application to Dumfries and Galloway Council for the proposed

More information

Linfairn Wind Farm Addendum Chapter A10: Archaeology

Linfairn Wind Farm Addendum Chapter A10: Archaeology A10. Archaeology and Historic Environment 10.1 Introduction The purpose of this chapter is to review amendments to the Project design and to advise of any consequent alterations to the historic environment

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 12 th June 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

Sandy Knowe Wind Farm. Non-Technical Summary Addendum

Sandy Knowe Wind Farm. Non-Technical Summary Addendum Sandy Knowe Wind Farm Non-Technical Summary Addendum Sandy Knowe Wind Farm Ltd November 2013 SANDY KNOWE WIND FARM ii NON-TECHNICAL SUMMARY Contents 1 Background 1 2 Availability of the ES Addendum 2 3

More information

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories: 5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION The scope of the EIA falls under three broad categories: technical scope; spatial scope; and temporal scope. The scoping process for the

More information

Proposed 40m high 250kw wind turbine to provide electricity for farm yard with excess exported to grid

Proposed 40m high 250kw wind turbine to provide electricity for farm yard with excess exported to grid Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 6 th April 2016 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: J/2012/0377/F Full Proposed 40m

More information

ASSESSING THE CUMULATIVE IMPACT OF ONSHORE WIND ENERGY DEVELOPMENTS

ASSESSING THE CUMULATIVE IMPACT OF ONSHORE WIND ENERGY DEVELOPMENTS Guidance ASSESSING THE CUMULATIVE IMPACT OF ONSHORE WIND ENERGY DEVELOPMENTS March 2012 Contents Page Section 1 INTRODUCTION AND SCOPE OF THE GUIDANCE 3 Background 3 What are cumulative effects 4 Assessing

More information

2. Approach to EIA and project design

2. Approach to EIA and project design 11 2. Approach to EIA and project design 2.1 EIA process Overview of EIA 2.1.1 EIA should be a systematic process that must be followed for certain types of project before a decision can be made on development

More information

Short Life Ministerial Working Group for Onshore Consents Joint position paper by Heads of Planning Scotland and COSLA

Short Life Ministerial Working Group for Onshore Consents Joint position paper by Heads of Planning Scotland and COSLA Introduction Short Life Ministerial Working Group for Onshore Consents Joint position paper by Heads of Planning Scotland and COSLA The Scottish Government s 2020 Renewable Route Map for Scotland, updated

More information

Monitoring the impact of onshore wind farms on birds - January 2009

Monitoring the impact of onshore wind farms on birds - January 2009 Guidance te Monitoring the impact of onshore wind farms on birds - January 2009 Introduction 1. As the number of wind farms constructed in Scotland increases the need to understand the impact that these

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION 6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence;

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence; 14 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 14.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

Wicklow Wind Energy Strategy

Wicklow Wind Energy Strategy Wicklow County Development Plan 2016-2022 Appendix 6 Wicklow Wicklow Wicklow County Development Plan 2016-2022 Appendix 6 2 1. Introduction Wicklow County Council recognises the need to reduce dependence

More information

A site visit to establish the scale of development suitable for your site

A site visit to establish the scale of development suitable for your site Wind Feasibility Study Our wind feasibility study comprises the following: A site visit to establish the scale of development suitable for your site Advice on whether a planning application is likely to

More information

Seneca Wind Cluster. Non Technical Summary May 2013 SENECA GLOBAL ENERGY

Seneca Wind Cluster. Non Technical Summary May 2013 SENECA GLOBAL ENERGY Seneca Wind Cluster Non Technical Summary May 2013 SENECA GLOBAL ENERGY Non-Technical Summary This document presents a Non Technical Summary (NTS) of the Environmental Statement (ES), which has been submitted

More information

Overview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition

Overview. Bhlaraidh and Stronelairg wind farm proposals. SSE Renewables. Site locations. This exhibition and Stronelairg s Overview SSE Renewables SSE Renewables is the renewable energy development division of SSE. The company is responsible for the development of onshore and offshore wind farms in the UK,

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 4 th July 2018 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

Overview. Tangy III Wind Farm Proposal. SSE Renewables. Site location. This exhibition

Overview. Tangy III Wind Farm Proposal. SSE Renewables. Site location. This exhibition Overview SSE Renewables SSE Renewables is the renewable energy division of SSE plc. It is responsible, on behalf of SSE Generation Limited, for the development and construction of SSE group s renewable

More information

Harbourcross Wind Farm Environmental StatementPl. Non-Technical Summary

Harbourcross Wind Farm Environmental StatementPl. Non-Technical Summary Harbourcross Wind Farm Environmental StatementPl April 2013 1 Introduction 1.1 Harbourcross Wind Farm Limited (the Applicant) is seeking planning permission for a proposed wind farm, referred to as Harbourcross,

More information

Wether Hill Windfarm Extension Volume 1: Non-Technical Summary

Wether Hill Windfarm Extension Volume 1: Non-Technical Summary Wether Hill Windfarm Extension Volume 1: November 2015 www.scottishpowerrenewables.com Preface This document is the of the Environmental Statement (ES) and has been prepared to accompany the planning application

More information

Chapter 17 Cumulative Impacts

Chapter 17 Cumulative Impacts Chapter 17 Cumulative Impacts CONTENTS 17. Cumulative Effects... 2 17.1 Introduction... 2 17.2 Summary of Relevant Legislation, Planning Policy and Guidance... 2 17.3 Methods... 5 17.4 Consultation...

More information

Knockendurrick Wind Farm Proposal

Knockendurrick Wind Farm Proposal Knockendurrick Wind Farm Proposal Planning Application and Environmental Statement Non Technical Summary September 2013 Energy for everyone s benefit of the proposed site showing 132m turbines. View from

More information

Fermanagh and Omagh District Council

Fermanagh and Omagh District Council Fermanagh and Omagh District Council Planning Committee Meeting 9 April 2015 Report by Principal Planning Officer K/2014/0186/F: Proposed installation of a wind turbine on a tubular tower with a blade

More information

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,

More information

SP Transmission Ltd SOUTH WEST SCOTLAND RENEWABLES CONNECTION PROJECT: ENVIRONMENTAL STATEMENT

SP Transmission Ltd SOUTH WEST SCOTLAND RENEWABLES CONNECTION PROJECT: ENVIRONMENTAL STATEMENT SP Transmission Ltd SOUTH WEST SCOTLAND RENEWABLES CONNECTION PROJECT: ENVIRONMENTAL STATEMENT Volume 3: Figures December 2008 VOLUME THREE: FIGURES INTRODUCTION 1.1 Location of Wind Farms Requiring Connection

More information

BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION

BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION BLACKWOOD WIND FARM WELCOME TO OUR EXHIBITION Force 9 Energy is seeking to develop a 5 turbine wind farm 1.5km to the east of Auldgirth, approximately 15km north of Dumfries. It is bounded to the north

More information

NON TECHNICAL SUMMARY

NON TECHNICAL SUMMARY CONTENTS Purpose of this Report... 1 The Application Submission Package... 1 Location of the Wind Farm... 1 The Proposed Development... 2 Construction Operations... 2 The EIA Process... 3 Landscape and

More information

Ewe Hill Windfarm. Non-Technical Summary

Ewe Hill Windfarm. Non-Technical Summary Ewe Hill Windfarm Non-Technical Summary October 2009 Contents 1. Introduction... 1 2. Environmental Impact Assessment... 1 3. Windfarm Proposal... 4 4. Legal and Policy Framework... 4 5. Landscape and

More information

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary Norfolk Minerals and Waste Local Plan Minerals Site Specific Allocations Development Plan Document (DPD) Single Issue Silica Sand Review Sustainability Appraisal Report Non-technical summary March 2016

More information

IEMA ES Review Criteria

IEMA ES Review Criteria IEMA ES Review Criteria Structure of the Criteria The criteria are split into three sections and a review report is structured accordingly: Section 1 addresses all of the information contained within an

More information

Bodelith Isaf Wind Farm Non Technical Summary

Bodelith Isaf Wind Farm Non Technical Summary 1 Bodelith Isaf Wind Farm Non Technical Summary 1.1 Introduction This document is the Non Technical Summary (NTS) prepared to accompany the submission of the planning application for the proposed Bodelith

More information

DEUCHRIES WIND FARM Environmental Statement

DEUCHRIES WIND FARM Environmental Statement DEUCHRIES WIND FARM Environmental Statement Volume 4: ES Non-Technical Summary September 2012 NON TECHNICAL SUMMARY Introduction (Force 9 Energy) and EDF Energy Renewables (EDF) are jointly seeking planning

More information

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER Knockskae Wind Farm Environmental Statement Volume 2 Main Report 14-1 14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER 14.1 Introduction 14.1.1 This Chapter has been prepared by. It identifies and

More information

In-combination and Cumulative Effects Assessment

In-combination and Cumulative Effects Assessment P O R T I S H E A D B R A N C H L I N E P R E L I M I N A R Y ENV I R O N M E N T A L I N F O R M A T I O N R E P O R T V O L U M E 2 C H A P T E R 18 In-combination and Cumulative Effects Assessment Table

More information

Ashington Neighbourhood Plan

Ashington Neighbourhood Plan Habitats Regulations Assessment Screening Report for consultation January 2018 Introduction 1.1 This report represents a screening of the need for a Habitats Regulations Assessment (HRA) under Directive

More information

6.0 ASSESSMENT OF LANDSCAPE CAPACITY AND CUMULATIVE CHANGE

6.0 ASSESSMENT OF LANDSCAPE CAPACITY AND CUMULATIVE CHANGE Update of Wind Energy Capacity and Cumulative Impact Study 6.0 ASSESSMENT OF LANDSCAPE CAPACITY AND CUMULATIVE CHANGE 6. Assessment Purpose and Process The purpose of the following assessment is to determine

More information

SgurrEnergy Ltd Linfairn Wind Farm Environmental Statement: Chapter 4

SgurrEnergy Ltd Linfairn Wind Farm Environmental Statement: Chapter 4 4 THE EIA PROCESS 4.1 OVERVIEW The purpose of an EIA is to provide a systematic analysis of the impacts of a project in relation to the existing (baseline) environment. The findings of an EIA are presented

More information

NORTH WESSEX DOWNS AONB POSITION STATEMENT RENEWABLE ENERGY

NORTH WESSEX DOWNS AONB POSITION STATEMENT RENEWABLE ENERGY NORTH WESSEX DOWNS AONB POSITION STATEMENT RENEWABLE ENERGY October 2012 1 NORTH WESSEX DOWNS AONB POSITION STATEMENT RENEWABLE ENERGY October 2012 Position Statement Status The purpose behind this Position

More information

Environmental Statement Volume 1. Non-Technical Summary. Land south of Pendown Farm Cornwall

Environmental Statement Volume 1. Non-Technical Summary. Land south of Pendown Farm Cornwall Environmental Statement Volume 1 Land south of Pendown Farm Cornwall August 2012 1. INTRODUCTION 1.1. Windberry Energy Operations Limited has submitted a planning application to Cornwall Council (CC) for

More information

Welcome to Hoolan Energy s public exhibition for our wind farm proposal

Welcome to Hoolan Energy s public exhibition for our wind farm proposal WELC ME Welcome to Hoolan Energy s public exhibition for our wind farm proposal This exhibition contains information about our plans for a wind development, including visualisations, potential access routes

More information

Introduction. The Need for Wind Energy. Consultation. The Applicant

Introduction. The Need for Wind Energy. Consultation. The Applicant Introduction Peel Wind Farms (UKC) Ltd (Peel) propose to construct a wind farm on an area of land that forms part of the former Asfordby mine and tip site and part of the existing Asfordby Business Park

More information

Detailed Methodology for More Detailed Assessment for Housing Sites. Establishing what capacity re-assessment is required

Detailed Methodology for More Detailed Assessment for Housing Sites. Establishing what capacity re-assessment is required B1.5.3 Detailed Methodology for More Detailed Assessment for Housing Sites Paragraphs 4.31 to 4.33 and 4.78 of the SSM advises that further indicative capacity work will be undertaken on each site identified

More information

GIS data classes used within the November 2013 Environmental Statement Environmental Maps

GIS data classes used within the November 2013 Environmental Statement Environmental Maps LWM-HS2-EV-DAT-000-000006 P01 22 January 2014 GIS data classes used within the November 2013 Environmental Statement Environmental Maps Document No.:LWM-HS2-EV-DAT-000-000006 Revision Author Checked by

More information

ABERARDER WIND FARM. Environmental Statement Volume I Non-Technical Summary

ABERARDER WIND FARM. Environmental Statement Volume I Non-Technical Summary ABERARDER WIND FARM Environmental Statement 2014 Volume I CONTENTS Preface... 2 Introduction... 4 Site Location... 5 Development Plan Policy... 7 Environmental Sensitivity... 9 Site Construction & Decommissioning...

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

ENVIRONMENTAL STATEMENT

ENVIRONMENTAL STATEMENT MIDDLE MUIR WIND FARM Section 36C Variation Application ENVIRONMENTAL STATEMENT The Banks Group. All rights reserved. This document has been provided for your reference by The Banks Group. No material

More information

Linfairn Wind Farm Addendum Chapter A3: Project Description

Linfairn Wind Farm Addendum Chapter A3: Project Description A3. PROJECT DESCRIPTION 3.1 Introduction This chapter provides a description of the changes to the Project since the ES was published. An outline Construction Environmental Management Plan (CEMP) is included

More information

Garvagh Glebe Wind Energy Project County Leitrim

Garvagh Glebe Wind Energy Project County Leitrim HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Proposed development at Stephenson Road, Northacre Trading Estate, Westbury, BA13 4WD Non-technical summary December 2014 Introduction Northacre Renewable Energy Ltd (a company

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

Item 8: Local Plan Preferred Options

Item 8: Local Plan Preferred Options ITEM 8: Local Plan Preferred Options Purpose of Report a. To seek approval from members of the Core Strategy and Development Management Policies Preferred Options Draft Local Plan document for public consultation.

More information

Ironstone Quarry Wind Energy Project Environmental Statement

Ironstone Quarry Wind Energy Project Environmental Statement Ironstone Quarry Wind Energy Project Environmental Statement Non Technical Summary April 2011 Introduction Waste Recycling Group (WRG) Ltd is seeking permission to construct and operate a four turbine

More information

Viridor Waste Management Limited. Energy from Waste with Combined Heat and Power Facility, Oxwellmains. Environmental Statement

Viridor Waste Management Limited. Energy from Waste with Combined Heat and Power Facility, Oxwellmains. Environmental Statement Viridor Waste Management Limited Energy from Waste with Combined Heat and Power Facility, Oxwellmains Environmental Statement (Environmental Impact Assessment Regulations 1999) May 2008 Viridor Waste Management

More information

19. INTERACTION OF IMPACTS

19. INTERACTION OF IMPACTS 19. INTERACTION OF IMPACTS 19.1 INTRODUCTION In addition to the requirement to describe the likely significant effects of the proposed development on the different elements of the environment, it is also

More information

VIRIDOR WASTE MANAGEMENT LTD

VIRIDOR WASTE MANAGEMENT LTD VIRIDOR WASTE MANAGEMENT LTD Proposed re-phasing of landfilling operations; amended restoration levels and aftercare scheme; and provision of a new waste reception building with associated site infrastructure

More information

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands Environmental Statement Non Technical Summary Anthony s Way Frindsbury June 2010 www.wyg.com creative minds safe hands Contents Section A Introduction Part 1 Background Part 2 Environmental Assessment

More information

INTRODUCTION Purpose of this EIA Report The Applicant Site Description Overview of the Proposed Development...

INTRODUCTION Purpose of this EIA Report The Applicant Site Description Overview of the Proposed Development... 1. INTRODUCTION Purpose of this... 1-2 The Applicant... 1-2 Site Description... 1-3 Overview of the Proposed Development... 1-3 EIA Process... 1-5 Structure of the... 1-6 The Environmental Impact Assessment

More information

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT PLANNING APPLICATION TO REMOVE CONDITION 2 OF PLANNING PERMISSION REFERENCE TDC/94/065 TO EXTEND THE OPERATIONAL LIFE OF THE NON-HAZARDOUS AND HAZARDOUS

More information

Prepared by:... Checked by:...

Prepared by:... Checked by:... Hameldon Hill Wind Farm Extension Volume 4 - Non Technical Summary Submitted on behalf of RWE NPower Renewables Limited to Burnley Borough Council December 2009 Prepared by:... Checked by:... Mark Herod

More information

CHAPTER 8 Energy Efficiency, and Renewable Energy. Kildare County Development Plan , Volume 1

CHAPTER 8 Energy Efficiency, and Renewable Energy. Kildare County Development Plan , Volume 1 Chapter 6 Rural Housing Strategy CHAPTER 8 Energy Efficiency, and Renewable Energy 157 8 ENERGY EFFICIENCY AND RENEWABLE ENERGY 8.1 Background The development of renewable energy sources is a priority

More information

Warnham Neighbourhood Plan. Habitats Regulations Assessment Screening Report for consultation

Warnham Neighbourhood Plan. Habitats Regulations Assessment Screening Report for consultation Habitats Regulations Assessment Screening Report for consultation January 2018 Introduction 1.1 This report represents a screening of the need for a Habitats Regulations Assessment (HRA) under Directive

More information

an Inspector appointed by the Secretary of State for Communities and Local Government

an Inspector appointed by the Secretary of State for Communities and Local Government Appeal Decision Site visit made on 20 May 2014 by J M Trask BSc(Hons) CEng MICE an Inspector appointed by the Secretary of State for Communities and Local Government Decision date: 24 July 2014 Appeal

More information

Birneyknowe Wind Farm Proposal

Birneyknowe Wind Farm Proposal Birneyknowe Wind Farm Proposal Planning Application and Environmental Statement Non Technical Summary April 2014 Energy for everyone s benefit Image shows 100m to tip turbines at West Durham Wind Farm

More information

Sheringham Shoal Offshore Wind Farm Onshore Substation Reapplication Environmental Statement Addendum Non-Technical Summary

Sheringham Shoal Offshore Wind Farm Onshore Substation Reapplication Environmental Statement Addendum Non-Technical Summary Sheringham Shoal Offshore Wind Farm Onshore Substation Reapplication Environmental Statement Addendum Non-Technical Summary Scira Offshore Energy Limited 9 April 2009 9R8482 SHERINGHAM SHOAL OFFSHORE WIND

More information

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby. The site comprises the employment element of the South West Rugby allocation

More information

RWE Npower Renewables Ltd. Kirkharle Wind Farm Four Turbine Scheme. Supplementary Environmental Information. Volume 1: Non Technical Summary

RWE Npower Renewables Ltd. Kirkharle Wind Farm Four Turbine Scheme. Supplementary Environmental Information. Volume 1: Non Technical Summary Kirkharle Wind Farm Supplementary Environmental Information Volume : Non Technical Summary Kirkharle Wind Farm Supplementary Environmental Information Volume : Non Technical Summary November 00 Pegasus

More information

Warnham Neighbourhood Plan. Habitats Regulations Assessment Screening Report

Warnham Neighbourhood Plan. Habitats Regulations Assessment Screening Report Habitats Regulations Assessment Screening Report June 2018 Introduction 1.1 This report represents a screening of the need for a Habitats Regulations Assessment (HRA) under Directive 92/43/EEC, also known

More information

Merkins Windfarm Environmental Statement

Merkins Windfarm Environmental Statement Merkins Windfarm Environmental Statement Non Technical Summary October 2011 www.landuse.co.uk PREFACE Copies of the Environmental Statement can be obtained from: Lomond Energy East Cambusmoon Farm Gartocharn

More information

Overcoming Ecological Challenges and Exploring Biodiversity Opportunities Associated with Energy Infrastructure Projects in Scotland

Overcoming Ecological Challenges and Exploring Biodiversity Opportunities Associated with Energy Infrastructure Projects in Scotland Overcoming Ecological Challenges and Exploring Biodiversity Opportunities Associated with Energy Infrastructure Projects in Scotland Kathy Dale EnviroCentre Limited Summary Scotland s renewables targets

More information

PROPOSED ABERDEEN 200MW WIND ENERGY FACILITY IN THE EASTERN CAPE PROVICE VISUAL ASSESSMENT - INPUT FOR SCOPING REPORT

PROPOSED ABERDEEN 200MW WIND ENERGY FACILITY IN THE EASTERN CAPE PROVICE VISUAL ASSESSMENT - INPUT FOR SCOPING REPORT PROPOSED ABERDEEN 200MW WIND ENERGY FACILITY IN THE EASTERN CAPE PROVICE VISUAL ASSESSMENT - INPUT FOR SCOPING REPORT Produced for: Eskom Holdings Limited Produced by: MetroGIS (Pty) Ltd. PO Box 384, La

More information

Rumster Wind Energy Project

Rumster Wind Energy Project Rumster Wind Energy Project Report OSE3525 Appendix D Noise and Shadow Flicker Assessment Orkney Sustainable Energy Limited 6 North End Road Stromness Orkney KW16 3AG Telephone 01856850054 Facsimile 01856851199

More information

Wether Hill Windfarm Extension

Wether Hill Windfarm Extension Wether Hill Windfarm Extension May 2013 May 2013 Wether Hill Windfarm Extension page i 1. Introduction 6 1.1 Background 6 1.2 The Applicant 6 1.3 Purpose of the Document 7 1.4 Structure 8 1.5 Terminology

More information

Contents. Figures. 1. Introduction 1 2. Project Description 2 3. Need for Development 3 4. Planning Policy 5

Contents. Figures. 1. Introduction 1 2. Project Description 2 3. Need for Development 3 4. Planning Policy 5 Non-Technical Summary Cour Windfarm Contents 1. Introduction 1 2. Project Description 2 3. Need for Development 3 4. Planning Policy 5 4.1 The Development Plan... 5 5. Site Selection 7 6. Environmental

More information

7. EIA Assessment Methodology

7. EIA Assessment Methodology 7. EIA Assessment Methodology Introduction 7.1 This Chapter of the PEIR sets out the process and methodology that has been adopted in undertaking the draft EIA. Whilst the overall approach and methodology

More information

Kelda Water Services Graincliffe Wind Turbine Environmental Statement - Non- technical Summary

Kelda Water Services Graincliffe Wind Turbine Environmental Statement - Non- technical Summary Environmental Statement - Non- technical Summary 210238-20 Issue 27 April 2012 This report takes into account the particular instructions and requirements of our client. It is not intended for and should

More information

8 Geology, Hydrology & Hydrogeology

8 Geology, Hydrology & Hydrogeology Inverneill Wind Farm Scoping Report Page 42 8 Geology, Hydrology & Hydrogeology 8.1 Introduction The EIA will consider the potential issues arising from the construction, operation and decommissioning

More information

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT 1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT This Environmental Impact Assessment Report (EIA Report) has been prepared by Environmental Resources Management Ltd

More information

Appendix D: A selection of slides from presentations at local Community Council meetings

Appendix D: A selection of slides from presentations at local Community Council meetings Appendix D: A selection of slides from presentations at local Community Council meetings Hill of Ochiltree Wind Farm Public Consultation Pre-Application Consultation Report Facilitating Change (UK) Limited

More information

Blairadam Forest Wind Farm. Non-Technical Summary

Blairadam Forest Wind Farm. Non-Technical Summary Blairadam Forest Wind Farm Non-Technical Summary January 2014 Non Technical Summary Context This Non Technical Summary (NTS) forms part of the Environmental Statement (ES) that has been prepared by SKM

More information

Clyde Extension Wind Farm Non-Technical Summary

Clyde Extension Wind Farm Non-Technical Summary Clyde Extension Wind Farm Non-Technical Summary Preface This document forms the non-technical summary (NTS) of the to the Environmental Statement (ES) that accompanies an application made by Clyde Windfarm

More information

Birds and Wind Energy Guidance Supporting the transition towards a truly sustainable green energy

Birds and Wind Energy Guidance Supporting the transition towards a truly sustainable green energy Migratory Soaring Birds Project Birds and Wind Energy Guidance Supporting the transition towards a truly sustainable green energy Importance of the sector Energy consumption is rapidly increasing all over

More information

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref: Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by

More information

A 1 5. A15.1 INTRODUCTION A15.2 CONSULTATION RESPONSES. Table A15.1: Objections from Statutory Consultees

A 1 5. A15.1 INTRODUCTION A15.2 CONSULTATION RESPONSES. Table A15.1: Objections from Statutory Consultees A 1 5. ROADS AND TRAFFIC A15.1 INTRODUCTION The design of the proposed Viking Wind Farm has changed since the Section 36 application, and its associated Environmental Statement, were submitted in May 2009.

More information

LINE ONE LINE TWO LINE THREE

LINE ONE LINE TWO LINE THREE LINE ONE LINE TWO LINE THREE Environmental Statement Volume 1: Non-Technical Summary Prepared by This document has been prepared by Limited for the sole use of our client (the Client ) and in accordance

More information

Appendix 12.1: Relevant National and Local Policies and Biodiversity Action Plans

Appendix 12.1: Relevant National and Local Policies and Biodiversity Action Plans Appendix 12.1: Relevant National and Local Policies and Biodiversity Action Plans 1.1 Introduction 1 This Appendix provides an overview of the international, national and local nature conservation policy

More information

Where is the Proposal?

Where is the Proposal? Where is the Proposal? Hapsford Solar Farm Proposed Layout The Hapsford Solar Farm is located on land south of Junction 14 of the M56 near Hapsford and lies to the west of the A5117. The site is located

More information

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement Non Technical Summary Business and Environmental Services A responsive County Council providing excellent and efficient local services

More information

Dean Castle Country Park Development and Management Plan Strategic Environmental Assessment. Environmental Report

Dean Castle Country Park Development and Management Plan Strategic Environmental Assessment. Environmental Report Dean Castle Country Park Development and Management Plan 2011-2016 Strategic Environmental Assessment Environmental Report October 2011 1 1. NON-TECHNICAL SUMMARY Introduction 1.1 Country parks are areas

More information

HAY CLOSE FARM WIND FARM ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY JULY 2014 REPORT NO: 0005-UA NHR-01

HAY CLOSE FARM WIND FARM ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY JULY 2014 REPORT NO: 0005-UA NHR-01 HAY CLOSE FARM WIND FARM ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY JULY 2014 REPORT NO: 0005-UA006631-NHR-01 Not to Scale HAY CLOSE FARM WIND FARM NON TECHNICAL SUMMARY OF THE Environmental Statement

More information

LINE ONE LINE TWO LINE THREE

LINE ONE LINE TWO LINE THREE LINE ONE LINE TWO LINE THREE Hill of Braco Wind Farm Environmental Statement Volume 1: Non Technical Summary January 2013 Preface This Environmental Statement (ES) re ports the results of an Environmental

More information

Consultation. The Approach to Environmental Impact Assessment. Neart na Gaoithe Offshore Wind Farm Environmental Statement. 6.

Consultation. The Approach to Environmental Impact Assessment. Neart na Gaoithe Offshore Wind Farm Environmental Statement. 6. Chapter 6 The Approach to Environmental Impact Assessment 6.1 Introduction 1 Under European legislation, transposed into UK and Scottish law (see Chapter 3: Regulatory and Policy Context for further information),

More information