Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

Size: px
Start display at page:

Download "Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014"

Transcription

1 Decision Syncrude Canada Ltd. Mildred Lake Power Plant July 17, 2014

2 Decision : Syncrude Canada Ltd. Mildred Lake Power Plant Application No Proceeding No July 17, 2014 Published by The Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 Calgary, Alberta Decision Syncrude Canada Ltd. Application No Mildred Lake Power Plant Proceeding No Introduction and background 1. On February 11, 2014, Syncrude Canada Ltd. (Syncrude) filed an application with the Alberta Utilities Commission (AUC or the Commission), pursuant to sections 4, 11 and 18 of the Hydro and Electric Energy Act, requesting approval to: Construct and operate a 92-megawatt (MW) power plant (the proposed power plant or the project). Connect the proposed power plant to the Alberta Interconnected Electric System (AIES). Amend the existing Industrial System Designation, within its Mildred Lake facility. 2. The application was registered as Application No and assigned Proceeding No The proposed power plant would be located in the northwest quarter of Section 6, Township 93, Range 10, west of the Fourth Meridian, approximately 30 kilometres north of Fort McMurray. 4. The proposed power plant is intended to provide additional electrical and thermal energy, to offset increased energy demands affiliated with the current Mildred Lake oilsands operation. 5. The Commission issued an information request to Syncrude on February 27, Syncrude responded on March 20, On April 4, 2014, the Commission issued a notice of application, with a deadline of April 25, 2014, to file submissions or statements of intent to participate in relation to the application. 7. On May 16, 2014, the Commission received a letter from the Mikisew Cree First Nation (MCFN) in response to the notice. The MCFN explained that it had not been consulted by Syncrude and had recently learned of the project. In its letter, the MCFN requested, among other things, that the Commission extend the deadline to allow it to file a submission. The Commission extended the deadline for submissions until May 26, On May 23, 2014, the Commission received a letter from the Athabasca Chipewyan First Nation (ACFN) requesting an extension to file its statement of intent to participate. The ACFN explained that it had not been consulted by Syncrude and learned of the project after the deadline for filing statements of intent to participate had passed. By letter dated May 26, 2014, the Commission granted the ACFN s request. 9. The Commission received three submissions in response to its notice of application. AUC Decision (July 17, 2014) 1

4 Mildred Lake Power Plant Syncrude Canada Ltd. 10. TransCanada Energy Ltd. (TransCanada), by letter dated April 25, 2014, stated that it is the owner of the MacKay River power plant located near the project. TransCanada indicated that the information provided regarding the proposed power plant was insufficient to determine the impact on TransCanada. By letter dated May 16, 2014, TransCanada advised that it received additional information from Syncrude and no longer had any concern with the proposed power plant. 11. ATCO Power Canada Ltd. (ATCO Power), by letter dated April 25, 2014, requested that the Commission provide it with an opportunity to review studies referred to by Syncrude in the application. On May 15, 2014, ATCO Power advised that it had an opportunity to review this additional information and no longer requested further process. 12. On June 2, 2014, the ACFN submitted a statement of intent to participate on behalf of its members. The ACFN submitted that the proposed power plant is located within its traditional lands. It contended that the project may affect the ACFN members ability to exercise their treaty rights in the immediate vicinity and downstream of the proposed power plant site. 13. The Commission did not receive further submissions from the MCFN. 14. Syncrude, by letter dated June 10, 2014, responded to the ACFN s submission. Syncrude stated that there is no evidence that the ACFN may be directly and adversely affected by the construction and operation of the proposed power plant. 15. In its June 19, 2014 ruling, the Commission denied standing to the ACFN for the reasons set out in its ruling on standing which is attached as Appendix 1. As there was not a person with standing in relation to the application, the Commission did not hold a hearing before making its decision on the application. 2 Discussion 16. Syncrude is the holder of Order No. U which is an approval to operate an industrial system at its Mildred Lake oilsands facility. The industrial system includes a number of generating units, transmission lines and substations. The development of the proposed power plant was included in the Mildred Lake Upgrader expansion project approved by Alberta Environment, a predecessor to Alberta Environment and Sustainable Resource Development (AESRD), in Three turbines were contemplated in the 2005 Alberta Environment application. Only two turbines were installed and the unit applied for in this application is the third turbine. 17. Syncrude indicated that the proposed power plant is located within the boundaries of the Lower Athabasca Regional Plan. Syncrude noted however that the proposed power plant is located on an existing disturbed industrial site and requires no additional clearing: the proposed power plant would be located within Syncrude s Mildred Lake facilities which extend over 2,000 metres around the proposed power plant. Syncrude submitted that no new land use dispositions would be required under the Public Lands Act. Syncrude also indicated that the nearest community is Fort McKay, located approximately 15 kilometres north of the project. 1 Order No. U : Syncrude Canada Ltd. Industrial System Designation, Application No , April 22, AUC Decision (July 17, 2014)

5 Mildred Lake Power Plant Syncrude Canada Ltd. 18. Syncrude submitted that, if approved, the proposed power plant would connect to the Alberta Interconnected Electric System (AIES) at the ATCO Electric Ltd. Ruth Lake substation through the existing Syncrude 260 kilovolt transmission lines. The Alberta Electric System Operator, in a letter dated December 2, 2013, indicated that the proposed connection would not adversely impact the AIES. 19. AESRD issued Approval No under the Environmental Protection and Enhancement Act for the Mildred Lake oilsands facility. Syncrude applied to AESRD in December 2013 to amend this approval to permit the construction, operation and reclamation of the proposed power plant. 20. Syncrude indicated that regional drainage is not affected by the project. Existing site runoff plans would be unaffected by the addition of the proposed power plant and no watercourse would be significantly impacted. Also, Syncrude advised that the water withdrawals for the proposed power plant were approved by AESRD for its current oilsands operations. Total water withdrawals would remain below Syncrude s licenced limit and the annual total intake would be less than 0.2 per cent of the annual flow on the Athabasca River. Syncrude submitted that utilizing water from the Athabasca River would not impact navigation on the river. 21. In a letter dated January 21, 2013, AESRD advised Syncrude that pursuant to Section 44 of the Environmental Protection and Enhancement Act the proposed power plant is not a mandatory activity for the purposes of an environmental assessment. Having regard to Section 44(3) of the Environmental Protection and Enhancement Act, AESRD decided that further assessment of the proposed power plant was not required and, as such, it was unnecessary for Syncrude to submit a screening report. 22. Also, Syncrude conducted an air quality assessment as part of its application to AESRD. Dispersion modelling was done for Nitrogen Dioxide (NO 2 ), Carbon Monoxide (CO) and Ammonia (NH 3 ) which indicated that baseline concentrations (i.e. concentrations resulting from other existing and approved sources in the area) exceed the Alberta Ambient Air Quality Objectives. Syncrude indicated that when the contribution of the proposed power plant is added to the baseline results, the maximum concentrations are essentially unchanged. Syncrude submitted that these results demonstrate that the proposed power plant would result in minimal changes to air quality. 23. Syncrude indicated that over 80 per cent of the power provided by the project is required to support tailings management and emissions reduction initiatives. These include the Sulphur Emissions Reduction project approved in the Environmental Protection and Enhancement Act approval and the Mature Fine Tailings Centrifuge projects previously approved. 24. Furthermore, Syncrude indicated that the proposed power plant would supply the largest air emission reduction project undertaken in the oilsands region. Syncrude stated that approval of the project would decrease SO x and NO x emissions by routing exhaust through the best available control technology, as opposed to flaring or routing through less effective emissions control technologies. 25. Syncrude stated that the anticipated noise levels would be within the permissible sound levels in AUC Rule 012: Noise Control (AUC Rule 12). 26. Further, Syncrude obtained a Historical Resource Act clearance from Alberta Culture and Community Spirit on January 7, AUC Decision (July 17, 2014) 3

6 Mildred Lake Power Plant Syncrude Canada Ltd. 27. Syncrude submitted that it conducted a participant involvement and consultation program for the project which included notification to all occupants, residents, and landowners within 2,000 metres of the proposed power plant site boundary and personally consulted all occupants, residents, and landowners within 800 metres of the proposed power plant site boundary. Syncrude indicated that it also consulted with various government agencies and that none of these government agencies raised any concern with respect to the project. Further, Syncrude submitted that AESRD was involved at an early stage in the participant involvement program and that AESRD advised Syncrude that the First Nation consultation guidelines were not triggered by this project. 28. Syncrude also indicated that power generated by the existing facility is designated as an Industrial System pursuant to Section 4 of the Hydro and Electric Energy Act, and that the conditions of this designation will be unaffected by the addition of the proposed power plant. 3 Findings 29. The Commission considers that the application meets the information requirements stipulated in AUC Rule 007: Applications for Power Plants, Substations, Transmission Lines and Industrial System Designations and Hydro Development (AUC Rule 007). Also, the Commission has reviewed the participant involvement and consultation program conducted by Syncrude, and finds that it meets the requirements of AUC Rule 007. In assessing the adequacy of Syncrude s participant involvement and consultation program, the Commission observes that there were efforts made by Syncrude to identify parties, including First Nations, which may be directly and adversely affected by the project. 30. With respect to the siting of the proposed power plant, the Commission recognizes that the proposed power plant would be located on disturbed land surrounded by Syncrude s oilsands facilities in an area covered by the Lower Athabasca Regional Plan and the proposed power plant is in accordance with the plan. In making its decision on the application, the Commission took into account that no additional clearing and no new land use dispositions are required. The Commission understands that the nearest community is located approximately 15 kilometres north of the proposed power plant. As the project is proposed to be constructed on a previously developed site, the Commission considers that potential impacts to soil, vegetation and wildlife are minimal. 31. Further, the Commission has taken into account that water withdrawals for the proposed power plant are to be made under Syncrude s water licence issued by AESRD for its current oilsands operations. Total water withdrawals would remain below Syncrude s licenced limit. Also, the Commission accepts that regional drainage would not be affected by the project and the addition of the proposed power plant would not affect existing run off plans for the oilsands site. 32. Regarding air emissions, the Commission is aware that Syncrude has applied to AESRD in relation to the proposed power plant for an amendment of its Alberta Environment approval for the Mildred Lake oilsands facility. The Commission observes that AESRD has advised Syncrude that the proposed power plant is not a mandatory activity for the purposes of an environmental assessment and that further assessment of the project is not required. 33. The Commission recognizes that Syncrude conducted an air quality assessment and that the baseline concentrations of emissions, from other existing and approved sources in the area, 4 AUC Decision (July 17, 2014)

7 Mildred Lake Power Plant Syncrude Canada Ltd. exceeded the Alberta Ambient Air Quality Objectives. These results were submitted to AESRD as part of the requested amendment of its environmental approval. However, the Commission notes that when the contribution of the proposed power plant is added to the baseline results, the maximum concentrations remain essentially unchanged; the project s contribution to air emissions would be relatively small. The proposed power plant would also incorporate a catalytic reduction for post-combustion emissions control which would further reduce emissions of NO x and SO x. The Commission finds that the environmental benefits from emissions mitigation and tailings management are significant. 34. Based on the foregoing, the Commission finds that the potential overall adverse environmental impacts of the project are minimal. As a result, the Commission concludes that the construction and operation of the proposed power plant is in the public interest from an environmental perspective. 35. The Commission also finds that the predicted noise levels are in compliance with AUC Rule Based on the foregoing, in accordance with Section 17 of the Alberta Utilities Commission Act, the Commission finds that construction and operation of the proposed power plant is in the public interest, having regard to the social and economic effects of the proposed power plant and its effects on the environment. 37. In making its decision whether to amend Syncrude s Industrial System Designation, the Commission has considered the applicable principles and criteria contained in Section 4 of the Hydro and Electric Energy Act. Accordingly, the Commission finds that each of the criteria contained in sections 4(3)(a), (b), (c), (d), (e), (f) and (g) of the Hydro and Electric Energy Act has been met to warrant inclusion of the proposed power plant as part of Syncrude s Industrial System Designation. The Commission grants the applied for connection order based on the technical specifications provided in the application and the AESO s opinion that the proposed connection would not adversely impact the AIES. AUC Decision (July 17, 2014) 5

8 Mildred Lake Power Plant Syncrude Canada Ltd. 4. Decision 38. Pursuant to sections 4, 11 and 18 of the Hydro and Electric Energy Act the Commission approves the application and grants Syncrude: Approval No. U July 17, 2014 to construct the Mildred Lake power plant as set out in Appendix 1 (Appendix 1 will be distributed separately). Order No. U July 17, 2014 to alter Syncrude s ISD as set out in Appendix 2 (Appendix 2 will be distributed separately). Order No. U July 17, 2014 to connect Syncrude s power plant to the AIES as set out in Appendix 3 (Appendix 3 will be distributed separately). Dated on July 17, The Alberta Utilities Commission (original signed by) Neil Jamieson Commission Member 6 AUC Decision (July 17, 2014)

9 Mildred Lake Power Plant Syncrude Canada Ltd. Appendix 1 Standing letter AUC Decision (July 17, 2014) 7

10 June 19, 2014 To: Interested parties Syncrude Canada Ltd. Proposed 92-MW Generator at Mildred Lake Facility Application No Proceeding No Ruling on standing 1 Introduction 1. In this ruling, the Commission must decide if the persons who filed a submission with respect to the above-referenced application have demonstrated that they have rights that may be directly and adversely affected by the Commission s decision on the proposed project application. A person who demonstrates the potential for direct and adverse effect is said to have standing. 2. The Commission asked me to write to you to provide its ruling and reasons for its ruling on the standing of the party that filed a statement of intent to participate in this proceeding. 2 Background 3. The applicant, Syncrude Canada Ltd. (Syncrude) owns and operates the existing oilsands mining, extraction and upgrading facilities known as the Mildred Lake Plant located approximately 30 kilometers north of Fort McMurray, Alberta. Proceeding No is an application to construct a gas turbine generator with a capacity of 92 megawatts (MW) (the proposed power plant or the proposed project) on the Mildred Lake Plant site. 4. The proposed power plant is surrounded by Syncrude s mine and tailings facilities, and other oilsands operations. The proposed project is located on disturbed Crown land within a heavily industrialized site; no new land use dispositions would be required under the Public Lands Act for the proposed power plant. 5. On April 4, 2014, the Commission issued a notice of application for the above-referenced proceeding. In the notice of application, the Commission directed any person who had concerns or objections to the application, or who wished to support the application to file a submission by April 25, On May 16, 2014, the Commission received a letter from the Mikisew Cree First Nation asserting that it has rights that may be directly and adversely affected by the application and indicating that it learned of the application, after the deadline for submissions had past. The

11 June 19, 2014 Page 2 of 8 Mikisew Cree First Nation requested, among other things, that the Commission extend the deadline to allow it to file a statement of intent to participate. 7. The Commission extended the deadline for submissions until May 26, 2014, to accommodate parties, including the Mikisew Cree First Nation, who had not received the original notice. 8. On May 23, 2014, the Commission received a motion from the Athabasca Chipewyan First Nation (ACFN) requesting an extension to file its statement of intent to participate on June 2, By letter dated May 26, 2014, the Commission granted the ACFN s request. 10. The Commission received three submissions from interested parties in response to the notice of application. 3 Views of interested parties 3.1 Objections and statements of intent to participate 11. By letter dated April 25, 2014, TransCanada Energy Ltd. (TransCanada) stated that it is the owner of the MacKay River power plant located in the vicinity of the proposed project. TransCanada indicated that it may be directly and adversely affected by the operation of the proposed power plant and the impact its operation would have on the Alberta Interconnected Electric System. TransCanada indicated that information provided was insufficient to determine the impact on TransCanada. Therefore, it requested that it be given an opportunity to review information necessary to determine that Syncrude s plant expansion would not adversely impact TransCanada s operations. On May 16, 2014, TransCanada wrote to the Commission stating that it had received additional information from the applicant and had no concern with the proposed power plant. 12. By letter dated April 25, 2014, ATCO Power Canada Ltd. (ATCO Power) requested that the Commission establish a process for the consideration of Syncrude s application for the proposed power plant, and provide interested parties with an opportunity to review studies that had been referred to by the applicant. On May 15, 2014, ATCO Power advised that it had an opportunity to review this additional information and no longer requested further process. 13. The Commission did not receive any further submissions from the Mikisew Cree First Nation. 14. The ACFN submitted a statement of intent to participate on behalf of its members. The ACFN explained that it is a signatory to Treaty 8 which guaranteed the ACFN s hunting, gathering, fishing, and trapping rights in support of sustaining its traditional livelihood. Accordingly, the ACFN asserted constitutionally protected aboriginal and treaty rights pursuant to Section 35 of the Constitution Act, 1982.

12 June 19, 2014 Page 3 of In its statement of intent to participate, the ACFN explained that eight reserves are set aside for the use and benefit of its members, all of which are located downstream of the proposed project and that the nearest reserve is Fort McKay, located approximately 15 kilometres north of the proposed project. 16. The ACFN submitted that the proposed power plant is located within its traditional lands and that its members continue to exercise their constitutional treaty rights in the vicinity of and downstream of the proposed project. It contended that the proposed project may directly and adversely affect the ACFN members ability to exercise their treaty rights in the immediate vicinity of, and downstream of the proposed power plant site. The Athabasca River is the most proximate water body to the proposed project, and is within 2,000 metres of the boundary of the existing Mildred Lake Plant site. The ACFN submitted several documents in support of the rights it had asserted The ACFN stated that it was concerned with the implications of the proposed project and how this will result in increased use of water from the Athabasca River, and increased air emissions including acidifying emissions, particulate matter, and polycyclic aromatic hydrocarbons (PAH). According to the ACFN, the proposed project may directly and adversely impact the ACFN s treaty rights by way of the use of water from the Athabasca River, and from the air emissions that will extend well beyond the proposed power plant s site boundaries. Specifically, the ACFN stated that the Project - including the withdrawal of water, and chemicals released by the Project into the airshed may directly and adversely affect the constitutional rights of ACFN The ACFN submitted affidavits from several of its members and other reports in support of its statement of intent to participate. 3 In their respective affidavits, the ACFN members stated that they utilized a portion of the Athabasca River corridor which is located within 2,000 metres of the existing site and that navigation is already difficult in that portion of the Athabasca River. The members also indicated that any further water withdrawals would make it more difficult or impossible to exercise their rights. In addition, one member anticipated that there may be increased garbage in the Athabasca River should the proposed project proceed. 19. In its submission, the ACFN stated that an oral hearing is the appropriate forum that would allow the ACFN to lead evidence regarding Syncrude s July, 1999 Environmental Mitigation Agreement with the ACFN (the mitigation agreement) in relation to Syncrude s Including Exhibit No McCormack ACFN Ethnohistory, Exhibit No Royal Commission on aboriginal Peoples Excerpt, Exhibit No As Long as the River Flows, Bruce MacLean Community Based Monitoring, Exhibit No Index of Case law. Exhibit No Jenny Biem letter to AUC at page 4. Exhibit No Affidavit of Michael Mercredi June 1, Exhibit No Affidavit of Lisa King June 1, Exhibit No Affidavit of Amanda Annand May 31, Exhibit No Jack Pine Mine Expansion Hearing. Exhibit No Carver Presentation Nov Exhibit No Syncrude and ACFN Environmental Mitigation Agreement Exhibit No Kurek et al Athabasca Oil Sands Legacy. Exhibit No Kindzeirski et al study. Exhibit No Effects of Acid Rain Surface Waters and Aquatic Animals.

13 June 19, 2014 Page 4 of 8 acidifying emissions, as well as of the extent and nature of potential impacts of the Syncrude application on the continued exercise of the ACFN s treaty rights. 20. Syncrude, by letter dated June 10, 2014, commented upon the standing request of the ACFN. In its submission, Syncrude stated that there is no evidence that the ACFN may be directly and adversely affected by the proposed power plant. In response to the ACFN s assertion that water withdrawals may adversely affect the ACFN s aboriginal and treaty rights, Syncrude advised that the water withdrawals for the proposed project were approved by Alberta Environment Sustainable Resource Development under Syncrude s Athabasca River Water Diversion License in relation to its current oilsands operations. The total water withdrawals would remain well below Syncrude s licensed limit and would be within water withdrawal volumes contemplated in the Lower Athabasca Water Management Framework. Further, Syncrude s annual total intake is less than 0.2 per cent of the annual flow on the Athabasca River, and water withdrawal for the proposed project, relative to annual flow, would be negligible. Syncrude stated that while it understands that use of the Athabasca River is important to the ACFN, it is simply not possible for water withdrawal for the proposed project to impact that use, or the ACFN s ability to navigate the river. 21. With respect to the ACFN s concern about air emissions, Syncrude stated that the proposed project does not have the potential to directly and adversely affect the ACFN s treaty and aboriginal rights due to air emissions; to the contrary, the proposed project provides the power necessary for one of the largest air emission reduction projects undertaken in the oilsands region. Syncrude indicated that it completed a detailed air quality assessment and, based on the results of this assessment, the potential adverse changes to the air quality from the proposed power plant are expected to be minimal. In response to the ACFN s concern about increased particulate and PAH and their impact on the ACFN, Syncrude submitted that there is no evidence that particulate emissions or PAH emissions will increase as a result of the proposed project. Syncrude also noted the proposed project, if approved, would allow Syncrude to significantly reduce sulphur oxide (SOx) and nitrogen oxide (NOx) emissions. 22. With respect to the concern expressed about increased garbage, Syncrude stated that there is no evidence to support the ACFN s allegation that the proposed project will result in more garbage in the Athabasca River. 23. With respect to the ACFN s assertion that Syncrude had acknowledged in the mitigation agreement that the ACFN would be impacted by the proposed project, Syncrude stated that this agreement has nothing to do with the proposed project and that the mitigation agreement referred to by the ACFN addresses impacts from the its oilsands upgrader expansion project. 4 The Commission s ruling on standing 4.1 How the Commission determines standing 24. Standing before the Commission is determined in accordance with subsection 9(2) of the Alberta Utilities Commission Act, which states: (2) If it appears to the Commission that its decision or order on an application may directly and adversely affect the rights of a person, the Commission shall

14 June 19, 2014 Page 5 of 8 (a) give notice of the application in accordance with the Commission rules, (b) give the person a reasonable opportunity of learning the facts bearing on the application as presented to the Commission by the applicant and other parties to the application, and (c) hold a hearing. 25. In Cheyne v. Alberta (Utilities Commission), the Alberta Court of Appeal characterized section 9(2) as the equivalent of section 26(2) of the Energy Resources Conservation Act and confirmed that the two-part test for standing under section 26(2) applies to subsection 9(2). In an earlier decision, Dene Tha v. Alberta (Energy and Utilities Board), the Alberta Court of Appeal described that two-part test as follows: s. 26(2) has two branches. First is a legal test, and second is a factual one. The legal test asks whether the claim right or interest being asserted by the person is one known to the law. The second branch asks whether the Board has information which shows that the application before the Board may directly and adversely affect those interests or rights. The second test is factual In its description of the factual test in the Dene Tha decision, the Alberta Court of Appeal stated that: It was argued before us that more recent case law on prima facie infringement of aboriginal or treaty rights changed things. But the Board still needed some facts to go on. It is not compelled by this legislation to order intervention and a hearing whenever anyone anywhere in Alberta merely asserts a possible aboriginal or treaty right. Some degree of location or connection between the work proposed and the right asserted is reasonable. What degree is a question of fact for the Board In Sawyer v. Alberta (Energy and Utilities Board), the Alberta Court of Appeal commented further on the factual component of the standing test and stated that in considering the location or connection, the Board is entitled to look at factors such as residence, the presence or absence of other wells in the area, and the frequency and duration of the applicant s use of the area near the proposed site. 28. In Decision , 6 the Commission considered an application by Maxim Power Corp. to construct and operate a new 500-MW coal-fired generating unit at the existing H.R. Milner generation station. The Commission received submissions on standing from individuals who owned or occupied lands approximately 20 kilometres from the proposed plant. The persons seeking standing raised issues relating to greenhouse gas emissions criteria, air contaminants and mercury, climate change and the impacts to water quantity and quality and fish in the Smoky River. The Commission found as follows with respect to standing in that case:.the Commission would consider that person to have standing and the Commission would proceed with a public hearing at which that person would be able to participate Dene Tha' First Nation v. Alberta (Energy and Utilities Board), 2005 ABCA 68, at paragraph 10. Ibid, at paragraph 14. AUC Decision : Maxim Power Corp. H.R. Milner Power Plant Expansion, Application No , Proceeding ID No. 203, August 10, 2011.

15 June 19, 2014 Page 6 of 8 Typically, this test is met by a person who owns or occupies land in proximity to a proposed development, and who substantiates an interest, with a direct bearing on his or her lands or other right known to law, which could be directly and adversely impacted by a decision of the Commission with respect to the application. This is the essence of the test for standing as set out in the Cheyne case and Section 9(2) of the Alberta Utilities Commission Act. Matters of interest to parties living some distance from a proposed project and matters of general interest to persons in Alberta do not typically meet the statutory test for standing unless they are able to show that their rights may be directly and adversely impacted by a decision of the Commission with respect to the application If the Commission finds that a person has standing pursuant to Section 9(2) of the Alberta Utilities Commission Act, it must hold a hearing to consider the person s concerns about the subject application. Further, persons with standing have the right to fully participate in the hearing, including the right to file evidence in support of their position, the right to question or cross-examine the applicant(s) on its evidence and the right to make argument. 4.2 Ruling on standing 30. In making its ruling, the Commission reviewed and considered the submissions received from the ACFN and Syncrude in light of the proposed project Mikisew Cree First Nation 31. As stated above, the Commission did not receive a statement of intent to participate or other submission from the Mikisew Cree First Nation after it submitted its letter dated May 16, In its letter, the Mikisew Cree First Nation stated that it holds Treaty 8 rights on unoccupied Crown lands located near or downstream from Syncrude s operations, including lands within the Athabasca River Corridor located within 2000 metres of the plant site and that it believed that the proposed project may directly and adversely impact its treaty rights and interests. 32. For the purposes of this ruling, the Commission is prepared to assume, without deciding, that the Mikisew Cree First Nation is entitled to exercise the rights it has asserted in its submission. 9 However, based on the information provided by the Mikisew Cree First Nation, the Commission finds that it has not established, on a factual basis, how it may be directly and adversely affected by the Commission s decision on the application. As a result, the Commission is not satisfied that Mikisew Cree First Nation has standing in relation to this application AUC Decision , at paragraph 20. Exhibit No Mikisew Cree First Nation correspondence to AUC re: Syncrude application Exhibit No Affidavit of Michael Mercredi June 1, 2014, Exhibit Affidavit of Lisa King June 1, Exhibit No Affidavit of Amanda Annand May 31, 2014, Exhibit McCormack ACFN Ethnohistory, Exhibit No Royal Commission on aboriginal Peoples Excerpt, Exhibit No As Long as the River Flows, Bruce MacLean Community Based Monitoring, Exhibit Jack Pine Mine Expansion Hearing, Exhibit No Carver Presentation Nov , Exhibit No Syncrude and ACFN Environmental Mitigation Agreement 1999, Exhibit No Kurek et al Athabasca Oil Sands Legacy, Exhibit No Kindzeirski et al study, Exhibit No Effects of Acid Rain Surface Waters and Aquatic Animals, Exhibit No Jenny Biem letter to AUC, and Exhibit No Index of Caselaw.

16 June 19, 2014 Page 7 of The ACFN 33. For the purposes of this ruling, the Commission is prepared to assume, without deciding, that the ACFN is entitled to exercise the rights it has asserted in its submissions The Commission finds, for the reasons that follow, that the ACFN has failed to demonstrate how the rights it has asserted may be directly and adversely affected by the Commission s decision on the proposed project. 35. The Commission has considered the ACFN s submission that its members live in Fort MacKay, 15 kilometres away from the proposed project, that one of its members works in a school located approximately three and a half kilometres away from the proposed project, and that its members exercise their aboriginal and treaty rights in the Athabasca River located two kilometres away from the Mildred Lake Plant site. The Commission also considers that the proposed power plant site is a 100 metre by 200 metre area in the middle of the Mildred Lake oilsands development, which extends approximately five kilometres from the boundary of the proposed power plant. Based on its review of the application, the Commission understands that the proposed power plant, if approved, would be more than five kilometres away from the Athabasca River and approximately 15 kilometers from residences. 36. While proximity to a project is not the only factor that the Commission will consider when reviewing an application for standing, it is an important one. Another important factor is the nature of the proposed project itself. In this case, the proposed project, would be constructed on pre-disturbed Crown land on the existing Mildred Lake Plant site. Also, the Commission notes that electrical power from the proposed project would be used to support environmental units and sustainment projects. Specifically, the Commission points to the applicant s submission that over 80 per cent of the proposed project s electricity output would support tailings management and emissions reduction. 11 Accordingly, given the nature of the proposed project and the distance from the proposed project to the areas where the ACFN has stated that its members exercise their rights, the Commission finds that the ACFN has not established a sufficient connection between approval of the proposed project and a potential adverse impact on its rights. 37. As the Commission understands it, the ACFN is not asserting the right to pursue treaty rights on the existing Mildred Lake Plant site but, rather it is asserting those rights in association with the locations outside of the proposed project site, the closest location being the Athabasca River Exhibit No Affidavit of Michael Mercredi June 1, 2014, Exhibit Affidavit of Lisa King June 1, Exhibit No Affidavit of Amanda Annand May 31, 2014, Exhibit McCormack ACFN Ethnohistory, Exhibit No Royal Commission on aboriginal Peoples Excerpt, Exhibit No As Long as the River Flows, Bruce MacLean Community Based Monitoring, Exhibit No Jack Pine Mine Expansion Hearing, Exhibit No Carver Presentation Nov , Exhibit Syncrude and ACFN Environmental Mitigation Agreement 1999, Exhibit No Kurek et al Athabasca Oil Sands Legacy, Exhibit No Kindzeirski et al study, Exhibit No Effects of Acid Rain Surface Waters and Aquatic Animals, Exhibit No Jenny Biem letter to AUC, and Exhibit No Index of Caselaw. Exhibit No Response to ACFN concerns with Syncrude's SUSP application, page 2.

17 June 19, 2014 Page 8 of The ACFN also expressed concerns that were more general in nature and related to the proposed project s potential impact to area water and air that it claimed would impact the exercise of its members treaty rights. The Commission understands that, if approved, the proposed project s water withdrawals would be minimal and within Syncrude s existing licenses, and the proposed project would not increase the volume of wastewater generated or added to wastewater streams. Also, air emissions generated by the proposed project would be negligible compared to other facility and regional emissions. 12 Further, the proposed project would incorporate post-combustion technology to reduce NO x emissions from the proposed project and would decrease area SOx emissions by allowing Syncrude s sulphur emissions reduction project to operate at full capacity. 13 While the ACFN listed a number of general concerns about the proposed project, it failed to demonstrate how the Commission s decision on the application may directly and adversely affect the rights it asserted at the locations identified by its members as important for the carrying out of traditional activities. The Commission therefore finds that the ACFN has not demonstrated, on a factual basis, that it may be directly and adversely affected by the construction and operation of the proposed power plant. 39. Based on the information presented by the ACFN and taking into account the nature of the proposed project, it is the Commission s view that the ACFN has not demonstrated that its treaty rights exercised in and around the Athabasca River would be affected by the proposed power plant as the Athabasca River is far enough away to prevent direct and adverse effects. 40. Based on the forgoing, the Commission is not satisfied that the ACFN has standing in relation to this application. 5 Conclusion 41. The Commission considers that a hearing is not required as the Commission s decision or order regarding this application will not directly and adversely affect the rights of a person pursuant to Section 9 of the Alberta Utilities Commission Act. Yours truly, Shanelle Sinclair Commission Counsel Exhibit No Response to ACFN concerns with Syncrude's SUSP application page 4. Exhibit No Response to ACFN concerns with Syncrude's SUSP application page 4.

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment Decision 2011-523 (Errata) Errata to Decision 2011-523 Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment January 10, 2012 The Alberta Utilities Commission Decision

More information

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document Decision 3476-D01-2015 Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document ATCO Electric Ltd. Yeo Substation Project Facility Application February 18, 2015 Alberta Utilities

More information

NaturEner Wild Rose 1 Energy Inc.

NaturEner Wild Rose 1 Energy Inc. Decision 2013-348 Amendment to Wild Rose 1 Wind Power Plant September 13, 2013 The Alberta Utilities Commission Decision 2013-348: Amendment to Wild Rose 1 Wind Power Plant Application No. 1609685 Proceeding

More information

Connacher Oil and Gas Limited

Connacher Oil and Gas Limited Decision 2010-094 Cogeneration Plant and Industrial System Designation March 2, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-094: Cogeneration Plant and Industrial System Designation Application No.

More information

Seven Generations Energy Ltd.

Seven Generations Energy Ltd. Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant January 17, 2018 Alberta Utilities Commission Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant Proceeding 22976

More information

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011 Decision 2011-496 December 15, 2011 The Alberta Utilities Commission Decision 2011-496: Application No. 1607774 Proceeding ID No. 1505 December 15, 2011 Published by The Alberta Utilities Commission Fifth

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 23468-D01-2018 Margie 1034S Substation May 28, 2018 Alberta Utilities Commission Decision 23468-D01-2018 Margie 1034S Substation Proceeding 23468 Application 23468-A001 May 28, 2018 Published

More information

Harvest Operations Corp.

Harvest Operations Corp. Decision 2014-214 Six-MW Power Plant Exemption July 21, 2014 The Alberta Utilities Commission Decision 2014-214: Six-MW Power Plant Exemption Application No. 1610444 Proceeding No. 3153 July 21, 2014 Published

More information

NOVA Chemicals Corporation

NOVA Chemicals Corporation Decision 2013-426 NOVA Chemicals Corporation Industrial System Designation Amendment November 29, 2013 The Alberta Utilities Commission Decision 2013-426: NOVA Chemicals Corporation Industrial System Designation

More information

Decision Cenovus FCCL Ltd.

Decision Cenovus FCCL Ltd. Decision 2012-196 Construct and Operate a 95-MW Cogeneration Power Plant, Construct and Operate Sunday Creek 539S Substation, Industrial System Designation and Interconnection of the Christina Lake Industrial

More information

Nexen Inc. and CNOOC Canada Inc.

Nexen Inc. and CNOOC Canada Inc. Decision 2012-330 Long Lake Project December 6, 2012 The Alberta Utilities Commission Decision 2012-330: Long Lake Project Application No. 1608729 Proceeding ID No. 2074 December 6, 2012 Published by The

More information

Aquatera Utilities Inc.

Aquatera Utilities Inc. Decision 2014-194 Aquatera Utilities Inc. 2.85-MW Power Plant June 26, 2014 The Alberta Utilities Commission Decision 2014-194: Aquatera Utilities Inc. 2.85-MW Power Plant Application No. 1610366 Proceeding

More information

Grande Prairie Generation, Inc.

Grande Prairie Generation, Inc. Decision 20292-D01-2015 Northern Prairie Power Plant November 27, 2015 Alberta Utilities Commission Decision 20292-D01-2015 Northern Prairie Power Plant Proceeding 20292 Application 20292-A001 November

More information

TransAlta Corporation

TransAlta Corporation Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant Units 1 and 2 December 21, 2018 Alberta Utilities Commission Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant

More information

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013 Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013

More information

Alberta Electric System Operator Needs Identification Document Application

Alberta Electric System Operator Needs Identification Document Application Decision 22618-D01-2017 Alberta Electric System Operator Needs Identification Document Application Facility Applications June 22, 2017 Alberta Utilities Commission Decision 22618-D01-2017: Alberta Electric

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions December 19, 2016 Alberta Utilities Commission Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions Proceeding 22229 Application

More information

Pembina NGL Corporation

Pembina NGL Corporation Decision 22928-D01-2018 45-Megawatt Cogeneration Power Plant, Alteration to Scoria 318S Substation and Amendment to the Redwater Industrial System Designation January 9, 2018 Alberta Utilities Commission

More information

Alberta Power (2000) Ltd.

Alberta Power (2000) Ltd. Decision 23558-D01-2018 Battle River Power Plant Alterations August 27, 2018 Alberta Utilities Commission Decision 23558-D01-2018 Battle River Power Plant Alterations Proceeding 23558 Application 23558-A001

More information

SunEEarth Alberta Solar Development Inc.

SunEEarth Alberta Solar Development Inc. Decision 22422-D01-2017 Yellow Lake Solar Project September 26, 2017 Alberta Utilities Commission Decision 22422-D01-2017 Yellow Lake Solar Project Proceeding 22422 Application 22422-A001 September 26,

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Signalta Resources Limited

Signalta Resources Limited Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station June 1, 2017 Alberta Utilities Commission Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station Proceeding 22388 Application

More information

Pteragen Canada Inc.

Pteragen Canada Inc. Decision 2013-171 May 7, 2013 The Alberta Utilities Commission Decision 2013-171: Application No. 1608907 Proceeding ID No. 2181 May 7, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place,

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration May 25, 2017 Alberta Utilities Commission Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration Proceeding 22562 Application 22562-A001 May

More information

Consultation Protocol of the Mikisew Cree First Nation

Consultation Protocol of the Mikisew Cree First Nation November 24, 2009 In our every deliberation we must consider the impact of our decisions on the next seven generations - author unknown Consultation Protocol of the Mikisew Cree First Nation ( the Protocol

More information

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018 Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project May 17, 2018 Alberta Utilities Commission Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project Proceeding 22711 Application

More information

Nexen Inc. OPTI Canada Inc.

Nexen Inc. OPTI Canada Inc. Decision 2010-006 Nexen Inc. OPTI Canada Inc. Long Lake South Phase 1 Cogeneration Power Plant January 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-006: Nexen Inc. and OPTI Canada Inc. Long Lake

More information

Pengrowth Energy Corporation

Pengrowth Energy Corporation Decision 2013-308 Lindberg SAGD Industrial System Designation August 20, 2013 The Alberta Utilities Commission Decision 2013-308: Lindberg SAGD Industrial System Designation Application No. 1609200 Proceeding

More information

Greengate Power Corporation

Greengate Power Corporation Decision 2011-085 Blackspring Ridge Wind Project March 9, 2011 The Alberta Utilities Commission Decision 2011-085: Blackspring Ridge Wind Project Application No. 1604777 Proceeding ID No. 190 March 9,

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22499-D01-2017 June 7, 2017 Decision 22499-D01-2017 Proceeding 22499 Application 22499-A001 June 7, 2017 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

The City of Red Deer

The City of Red Deer Decision 2010-148 The City of Red Deer 15-kW Solar Power Plant for City of Red Deer Civic Yards Building April 5, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-148: The City of Red Deer 15-kW Solar Power

More information

Grizzly Oil Sands ULC

Grizzly Oil Sands ULC Decision 2013-124 Algar Lake Project Distribution System Exemption March 28, 2013 The Alberta Utilities Commission Decision 2013-124: Algar Lake Project Distribution System Exemption Application No. 1609370

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on March

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation Mackenzie County October 11, 2018 Alberta Utilities Commission Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation

More information

Burdett Solar GP Corp.

Burdett Solar GP Corp. Decision 23364-D01-2018 Burdett Solar Project Time Extension October 3, 2018 Alberta Utilities Commission Decision 23364-D01-2018 Burdett Solar Project Time Extension Proceeding 23364 Application 23364-A001

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by

More information

Solar Krafte Utilities Inc.

Solar Krafte Utilities Inc. Decision 23323-D01-2018 August 21, 2018 Alberta Utilities Commission Decision 23323-D01-2018 Proceeding 23323 Application 23323-A001 August 21, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018 Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and Salvage November 8, 2018 Alberta Utilities Commission Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and

More information

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013 Decision 2013-180 13.05-kW Photovoltaic Micro-Generation System May 15, 2013 The Alberta Utilities Commission Decision 2013-180: 13.05-kW Photovoltaic Micro-Generation System Application No. 1609500 Proceeding

More information

Proposed Traditional Land Use (TLU) Assessment Methodology for Teck Frontier Project Update

Proposed Traditional Land Use (TLU) Assessment Methodology for Teck Frontier Project Update Teck Resources Limited Suite 1000, 205 9 th Ave. S.E. Calgary, AB Canada T2G 0R3 +1 000 000 0000 Dir +1 403 767 8500 Tel +1 403 265 8835 Fax +1 000 000 0000 Mobile www.teck.com December 4, 2014 Mikisew

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 22706-D01-2017 Spring 2017 Comprehensive Sound Survey at Receptors R and S August 25, 2017 Alberta Utilities Commission Decision 22706-D01-2017 Proceeding 22706 Application 22706-A001 August 25,

More information

IMPLEMENTATION OF THE METIS SETTLEMENTS CONSULTATION POLICY

IMPLEMENTATION OF THE METIS SETTLEMENTS CONSULTATION POLICY 1 IMPLEMENTATION OF THE METIS SETTLEMENTS CONSULTATION POLICY BACKGROUND The Government of Alberta s Policy on Consultation with Metis Settlements on Land and Natural Resource Management, 2015 (Policy)

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23713-D01-2018 August 28, 2018 Alberta Utilities Commission Decision 23713-D01-2018 Proceeding 23713 Application 23713-A001 August 28, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

Re: Teck Frontier Oils Sands Mine Project: Responses to Supplemental Information Requests (SIRs)

Re: Teck Frontier Oils Sands Mine Project: Responses to Supplemental Information Requests (SIRs) Fort Chipewyan Métis Local 125 Métis Nation of Alberta February 27, 2013 Carolyn Dunn Crown Consultation Coordinator Canadian Environmental Assessment Agency Email: Carolyn.Dunn@ceaa-acee.gc.ca Re: Teck

More information

HORIZON NORTH PIT EXTENSION PROJECT

HORIZON NORTH PIT EXTENSION PROJECT HORIZON NORTH PIT EXTENSION PROJECT Plain Language Project Package File Number for Consultation: FNC201706486 Page 0 WHO IS CANADIAN NATURAL? Canadian Natural Resources Limited (Canadian Natural) is a

More information

Notice of Technical Meeting

Notice of Technical Meeting Notice of Technical Meeting Amendments to three wind energy projects in the Pincher Creek area proposed by Welsch Wind Power Inc., Windy Point Wind Park Ltd. and NextEra Canada Development & Acquisitions,

More information

Citation: Decision 2011 ABERCB 005. Published by

Citation: Decision 2011 ABERCB 005. Published by REPORT OF THE JOINT REVIEW PANEL ESTABLISHED BY THE FEDERAL MINISTER OF THE ENVIRONMENT AND THE ENERGY RESOURCES CONSERVATION BOARD Decision 2011-005: Total E&P Joslyn Ltd., Application for the Joslyn

More information

EDF EN Canada Development Inc.

EDF EN Canada Development Inc. Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant March 2, 2016 Alberta Utilities Commission Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant Proceeding 21203 Application 21203-A001

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22447-D01-2017 Vauxhall Solar Power Plant July 4, 2017 Alberta Utilities Commission Decision 22447-D01-2017 Vauxhall Solar Power Plant Proceeding 22447 Application 22447-A001 July 4, 2017 Published

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited 20171218A Canadian Natural Resources Limited Application for Horizon Oil Sands Processing Plant and Mine Tailings Management Plan December 18, 2017 Alberta Energy Regulator Decision 20171218A: Canadian

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

Frontier Oil Sands Mine Project Joint Review Panel

Frontier Oil Sands Mine Project Joint Review Panel Frontier Oil Sands Mine Project Joint Review Panel December 16, 2016 Teck Resources Limited Attention: Sheila Risbud, Regulatory Manager, Energy Subject: Additional Information Required from Teck Resources

More information

The Government of Saskatchewan Guidelines for Consultation with First Nations and Métis People: A Guide for Decision Makers.

The Government of Saskatchewan Guidelines for Consultation with First Nations and Métis People: A Guide for Decision Makers. The Government of Saskatchewan Guidelines for Consultation with First Nations and Métis People: A Guide for Decision Makers May 2006 This document sets out the approach to be used by all Government of

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2009-126 Needs Identification Document Application Southern Alberta Transmission System Reinforcement September 8, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-126: Needs Identification Document

More information

Renewable Energy Services Ltd.

Renewable Energy Services Ltd. Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation February 23, 2018 Alberta Utilities Commission Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation Proceeding 1976 Applications

More information

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc.

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Decision 2010-612 Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Needs Identification Document, Transmission Line, Substation and Power Plant Al-Pac Pulp

More information

EOG Resources Canada Inc.

EOG Resources Canada Inc. Decision 2008-061 Application for a Pipeline Licence Provost Field July 15, 2008 ENERGY RESOURCES CONSERVATION BOARD Decision 2008-061:, Application for a Pipeline Licence, Provost Field July 15, 2008

More information

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008 Decision 2008-132 FortisAlberta Inc. Micro-Generation Determination December 16, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-132: FortisAlberta Inc. Micro-Generation Determination Application No. 1594619

More information

October 30, 2012 Our File:

October 30, 2012 Our File: October 30, 2012 Our File: 5000-510-5120 Minister of Environment and Sustainable Resource Development 204 Legislature Building 10800 97 Avenue Edmonton, AB T5K 2B6 Attention: Honourable Diana McQueen at

More information

Proponent Handbook. Voluntary Engagement with First Nations and Métis Communities to Inform Government s Duty to Consult Process

Proponent Handbook. Voluntary Engagement with First Nations and Métis Communities to Inform Government s Duty to Consult Process Proponent Handbook Voluntary Engagement with First Nations and Métis Communities to Inform Government s Duty to Consult Process November 2013 TABLE OF CONTENTS 3 Introduction 3 What is the Duty to Consult?

More information

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement. Environmental Impact Assessment Technical Review Comments on the Environmental Impact Statement as submitted by Claude Resources Inc. Saskatchewan Ministry of Environment December, 2009 1. INTRODUCTION

More information

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT Notice NOTICE OF APPLICATIONS SHELL CANADA LIMITED QUEST CARBON CAPTURE AND STORAGE RADWAY FIELD ENERGY RESOURCES CONSERVATION BOARD APPLICATIONS NO. 1689376, 1670112, AND 1671615 ALBERTA ENVIRONMENT ENVIRONMENTAL

More information

SUMMARY LOUISIANA-PACIFIC CANADA LTD. - TEN YEAR FOREST MANAGEMENT PLAN (CLIENT FILE NO.: )

SUMMARY LOUISIANA-PACIFIC CANADA LTD. - TEN YEAR FOREST MANAGEMENT PLAN (CLIENT FILE NO.: ) SUMMARY LOUISIANA-PACIFIC CANADA LTD. - TEN YEAR FOREST MANAGEMENT PLAN - 1996-2005 (CLIENT FILE NO.: 3893.00) Louisiana-Pacific Canada Ltd. had applied for a Environment Act Licence of a Ten Year Forest

More information

to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street, 1 st Floor Quebec, Quebec G1K 3X2

to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street, 1 st Floor Quebec, Quebec G1K 3X2 Decision Statement Issued under Section 54 of the Canadian Environmental Assessment Act, 2012 to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street,

More information

Canadian Natural Upgrading Limited

Canadian Natural Upgrading Limited 20180523A Canadian Natural Upgrading Limited Application for Muskeg River Mine Tailings Management Plan May 23, 2018 Alberta Energy Regulator Decision 20180523A: Canadian Natural Upgrading Limited; Application

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2014-126 South and West Edmonton Area Transmission System Reinforcement Needs Identification Document May 5, 2014 The Alberta Utilities Commission Decision 2014-126: South and West Edmonton Area

More information

SemCAMS Area Project Description

SemCAMS Area Project Description REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory

More information

PROCEDURE FOR PREPARING AN EMISSION SUMMARY AND DISPERSION MODELLING REPORT [GUIDELINE A-10]

PROCEDURE FOR PREPARING AN EMISSION SUMMARY AND DISPERSION MODELLING REPORT [GUIDELINE A-10] February 2017 PROCEDURE FOR PREPARING AN EMISSION SUMMARY AND DISPERSION MODELLING REPORT [GUIDELINE A-10] Version 4.0 Guidance for Emission Summary and Dispersion Modelling Reports under Ontario Regulation

More information

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints Decision 22493-D01-2018 1646658 Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints January 17, 2018 Alberta Utilities Commission Decision 22493-D01-2018 1646658 Alberta Ltd. (BluEarth)

More information

Proponent Handbook. Voluntary Engagement with First Nations and Métis Communities to Inform Government s Duty to Consult Process

Proponent Handbook. Voluntary Engagement with First Nations and Métis Communities to Inform Government s Duty to Consult Process Proponent Handbook Voluntary Engagement with First Nations and Métis Communities to Inform Government s Duty to Consult Process November, 2013 TABLE OF CONTENTS 3 Introduction 3 What is the Duty to Consult?

More information

Fort Hills Energy Corporation

Fort Hills Energy Corporation 20190225A Fort Hills Energy Corporation Application for Fort Hills Tailings Management Plan February 25, 2019 Alberta Energy Regulator Decision 20190225A: Fort Hills Energy Corporation; Application for

More information

Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association

Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association Ministry of the Environment Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association Review prepared pursuant to subsection 7(1) of the Environmental Assessment

More information

Environmental Assessment Program

Environmental Assessment Program Environmental Assessment Program Frequently Asked Questions Updated February 2010 Introduction The following is a list of questions that are commonly asked by both project Proponents and the public regarding

More information

FORT MCMURRAY AREA Applications No and

FORT MCMURRAY AREA Applications No and KEARL OIL SANDS PROJECT JOINT REVIEW PANEL Calgary Alberta IMPERIAL OIL RESOURCES VENTURES LIMITED APPLICATION FOR AN OIL SANDS MINE AND BITUMEN PROCESSING FACILITY (KEARL OIL SANDS PROJECT) Decision 2007-013

More information

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc.

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc. Regulatory Audit Report #2008-001 ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc. Inter-Affiliate Code

More information

Canadian Natural Upgrading Limited

Canadian Natural Upgrading Limited 20180523B Canadian Natural Upgrading Limited Application for Jackpine Mine Tailings Management Plan May 23, 2018 Alberta Energy Regulator Decision 20180523B: Canadian Natural Upgrading Limited; Application

More information

Imperial Oil Resources Limited

Imperial Oil Resources Limited 20180716A Imperial Oil Resources Limited Application for Kearl Mine s Tailings Management Plan July 16, 2018 Alberta Energy Regulator Decision 20180716A: Imperial Oil Resources Limited; Application for

More information

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries

More information

Site C Dam The Crown s approach to Treaty 8 First Nations consultation SITE C PROJECT BC S PROPOSED PROCESS TO APPROVE SITE C. Legal backgrounder:

Site C Dam The Crown s approach to Treaty 8 First Nations consultation SITE C PROJECT BC S PROPOSED PROCESS TO APPROVE SITE C. Legal backgrounder: Legal backgrounder: Site C Dam The Crown s approach to Treaty 8 First Nations consultation Summary: The Site C Dam project proposal engages the jurisdiction and lawful authority of Treaty 8 First Nations.

More information

Project Summary Table BlackPearl Resources Inc Blackrod Commercial SAGD Project Proponent Name: BlackPearl Resources Inc. Date: November, 2011

Project Summary Table BlackPearl Resources Inc Blackrod Commercial SAGD Project Proponent Name: BlackPearl Resources Inc. Date: November, 2011 Project Summary Table BlackPearl Resources Inc Blackrod Commercial SAGD Project Proponent Name: BlackPearl Resources Inc. Date: vember, 2011 Project Name: Blackrod Commercial SAGD Project Company Contact

More information

Preliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and

Preliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and Information required by EUB Guide G-23 1.0 GENERAL INFORMATION 1.1 INTRODUCTION The application should include: a brief project summary, objectives, approvals requested, technical and economic details,

More information

Ellerslie Substation Expansion

Ellerslie Substation Expansion Ellerslie Substation Expansion Volume 2 UV 2 North Saskatchewan River EDMONTON UV 216 UV 14 ") ELLERSLIE 89S Bretona!! Trevithick March 2010 Why are you receiving this newsletter? You are receiving this

More information

December 2, 2016 EAB File #: Transaction #:

December 2, 2016 EAB File #: Transaction #: Ministry of Environment Environmental Assessment and Stewardship Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: (306) 787-6132 Fax: (306) 787-0930 December 2, 2016 EAB File #:

More information

AND WHEREAS the Minister is satisfied that all the requirements of the Act have been met, including those required of Premier Tech;

AND WHEREAS the Minister is satisfied that all the requirements of the Act have been met, including those required of Premier Tech; PROVINCE OF SASKATCHEWAN MINISTRY OF ENVIRONMENT MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT PREMIER TECH HORTICULTURE LTD. SMOKEY RIDGE PEAT HARVESTING PROJECT WHEREAS

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 22274-D01-2018 Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement January 12, 2018 Alberta Utilities Commission Decision 22274-D01-2018 Provost to Edgerton and Nilrem

More information

BEFORE THE PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter:

BEFORE THE PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter: BEFORE THE PUBLIC SERVICE COMMISSION In re: Petition for determination of need for Glades Power Park Units 1 and 2 electrical power plants in Glades County, by Florida Power & Light Company. ORDER NO.

More information

HYDRO AND ELECTRIC ENERGY REGULATION

HYDRO AND ELECTRIC ENERGY REGULATION Province of Alberta HYDRO AND ELECTRIC ENERGY ACT HYDRO AND ELECTRIC ENERGY REGULATION Alberta Regulation 409/1983 With amendments up to and including Alberta Regulation 136/2015 Office Consolidation Published

More information

Lower Athabasca Region Air Zone Canadian Ambient Air Quality Standards Response Government of Alberta Action Plan

Lower Athabasca Region Air Zone Canadian Ambient Air Quality Standards Response Government of Alberta Action Plan Lower Athabasca Region Air Zone Canadian Ambient Air Quality Standards Response Government of Alberta Plan September 2017 Any comments or questions regarding the content of this document may be directed

More information

CROWN CONSULTATION AND ACCOMMODATION REPORT for the 2017 NGTL SYSTEM EXPANSION PROJECT (NOVA GAS TRANSMISSION LTD.) (GH )

CROWN CONSULTATION AND ACCOMMODATION REPORT for the 2017 NGTL SYSTEM EXPANSION PROJECT (NOVA GAS TRANSMISSION LTD.) (GH ) CROWN CONSULTATION AND ACCOMMODATION REPORT for the 2017 NGTL SYSTEM EXPANSION PROJECT (NOVA GAS TRANSMISSION LTD.) (GH-002-2015) Prepared by the Major Projects Management Office October 14, 2016 Disclaimer

More information

GENERAL PERMISSIONS, AUTHORIZATIONS and CONDITIONS

GENERAL PERMISSIONS, AUTHORIZATIONS and CONDITIONS Non OGAA v 4.0 April 30, 2018 Coastal GasLink Pipeline Ltd. 450 1St Street SW Calgary, AB T2P 5H1 Attention: Coastal GasLink Pipeline Ltd. RE: Permit Replacement for Application Determination Number 100084244,

More information

Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017

Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017 Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach October 2017 (Simulated FPF) INTRODUCTION Noront is proposing to develop a Ferrochrome Production Facility (FPF) in Northern

More information

THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL

THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL Alberta Municipal Affairs February 1997 Updated March 2002 1.0 INTRODUCTION The authority for municipal planning,

More information

LNG Canada Development Inc.

LNG Canada Development Inc. LNG Canada Development Inc. Shell Centre 32 nd Floor 400 4 th Avenue SW PO Box 100, Station M Calgary AB T2P 2H5 Canada Submitted electronically to: compliance.conformite@ceaa-acee.gc.ca April 20, 2016

More information

Remediation Certificate Application for Upstream Oil and Gas Sites

Remediation Certificate Application for Upstream Oil and Gas Sites Remediation Certificate Application for Upstream Oil and Gas Sites 1.0 SITE IDENTIFICATION Site Name: Land type: Private Special Area Crown, specify disposition number if applicable County/M.D/I.D./S.A:

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 2008-012 Application for a Pipeline Licence Taber Field February 12, 2008 ALBERTA ENERGY AND UTILITIES BOARD Decision 2008-012:, Application for a Pipeline Licence, Taber Field February 12, 2008

More information