Grizzly Oil Sands ULC

Size: px
Start display at page:

Download "Grizzly Oil Sands ULC"

Transcription

1 Decision Algar Lake Project Distribution System Exemption March 28, 2013

2 The Alberta Utilities Commission Decision : Algar Lake Project Distribution System Exemption Application No Proceeding ID No March 28, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: Fax: Website:

3 The Alberta Utilities Commission Calgary, Alberta Decision Application No Algar Lake Project Distribution System Exemption Proceeding ID No Application 1. (GOS), by Application No , registered on March 8, 2013, filed a letter of enquiry with the Alberta Utilities Commission (AUC or the Commission) under Section 11 of the Hydro and Electric Energy Regulation. GOS requested that the previously granted exemption, pursuant to Section 24 the Hydro And Electric Energy Act, for its Algar Lake Steam Assisted Gravity Drainage (SAGD) Project site in the Fort McMurray area, be extended in scope to include the following: Extension and construction of a 4,160-volt (V) cable along the north perimeter of the main production facility (MPF). Relocation of a 4,160/600-V, 500-kilovolt-ampere (kva) transformer to the northeast corner of the MPF. 2 Background 2. GOS is in the process of developing the Algar Lake SAGD Project (the Algar project), located approximately 40 kilometres southwest of Fort McMurray. GOS has approval, by Approval No. U , 1 to construct and operate a 15-megawatt power cogeneration facility. The power will be used solely for the Algar project and an exemption was granted to GOS, in Decision , 2 to operate the associated 600-V distribution lines that will serve the electrical requirements both on-site and at four nearby well pads. 3. The decision specified the following details: The proposed power plant and the nearby off-site load are located on lands which GOS has been granted surface rights, under Miscellaneous Lease, thus showing tenancy within the lease area where distribution facilities will be located. 3 There are no dwellings within 2,500 metres of the proposed development. 4 The noise impact assessment was completed for the entire Algar project which included the proposed power plant and two backup diesel generators. Results indicated that the Power Plant Approval No. U , Application No , Proceeding ID No. 1870, August 31, Decision : Algar Lake 15-MW Cogeneration Power Plant, Application No , Proceeding ID No. 1870, August 31, Decision , paragraphs 10 and 26. Decision , paragraph 11. AUC Decision (March 28, 2013) 1

4 Algar Lake Project Distribution System Exemption projected noise levels will comply with the requirements of AUC Rule 012: Noise Control (AUC Rule 012). 5 The Commission accepted that the proposed development is expected to have minimal environmental impacts (as the gas turbines would be installed within the MPF buildings at the Algar project site) and will meet Alberta Ambient Air Quality Objectives. 6 The Commission found that GOS had provided information to indicate there is no public highway on the lands over which the electric energy will be distributed. 7 Exemption, pursuant to Section 24 of the Hydro and Electric Energy Act, was granted to GOS to own and operate the proposed 600-V distribution system. 8 3 Discussion 4. GOS stated that during the detailed engineering phase it was recognized that, by extending the MPF internal 4,160-V distribution system to a location immediately adjacent to the MPF and close to the well site loads, an improvement to the distribution system could be achieved. The improvement areas would be as follows: Reduced voltage drop on the system to the well pad sites. Reduced operating losses on the system to the well pad sites. Reduced voltage sag during motor start. 5. GOS submitted that the construction of the 4,160-V cable and the relocation of the transformer (the alterations) would occur within the originally approved site boundaries and would be installed in accordance with standard industry practice. Specifically, the proposed 4,160-V cable would be installed in a common tray with the already approved 600-V cable system and the 500-kVA transformer would be relocated adjacent to the MPF. 6. GOS also submitted that no incremental environmental impact will result from the proposed alterations as no new lands would be impacted. 7. The 500-kVA transformer which was originally proposed to be located within the MPF, was not identified as a major noise source in the noise impact assessment in the original application 9 and thus it is not considered a significant noise source within the approved project. The relocation of the transformer to its proposed location is therefore not expected to alter the predicted noise levels. 8. There is no change to the site location or the ownership of the land over which the electric energy will be distributed Decision , paragraph 17. Decision , paragraph 19. Decision , paragraph 27. Decision , paragraphs 28 and 30. Proceeding ID 1870, Exhibit AUC Decision (March 28, 2013)

5 Algar Lake Project Distribution System Exemption 4 Findings 9. Based on the information submitted by GOS, the Commission finds: No other persons would be directly affected by the proposed alterations as there are no dwellings within 2,500 metres of the Algar project site. The proposed alterations do not include additional sources of emissions and, therefore, will not alter the air quality assessment. The proposed alterations will not alter the predicted noise levels and, thus, the project remains in compliance with the requirements set out in AUC Rule 012. No adverse environmental impacts will be caused by the proposed alterations. 10. As there is no change to the site location or the ownership of the land over which the electric energy will be distributed, the exemption, pursuant to Section 24 of the Hydro and Electric Energy Act, granted to GOS in Decision , remains valid. 5 Decision 11. The Commission approves the application and grants the exemption, pursuant to Section 24 the Hydro And Electric Energy Act, which is extended in scope to include the 4,160-V electric distribution system. 12. The Commission may cancel or suspend this exemption, in whole or in part, in accordance with Section 41 of the Hydro and Electric Energy Act or may review this exemption, in whole or in part, upon its own motion or upon an application by an interested party, in accordance with Section 10 of the Alberta Utilities Commission Act. Dated on March 28, The Alberta Utilities Commission (original signed by) Tudor Beattie, Q.C. Commission Member AUC Decision (March 28, 2013) 3

Pengrowth Energy Corporation

Pengrowth Energy Corporation Decision 2013-308 Lindberg SAGD Industrial System Designation August 20, 2013 The Alberta Utilities Commission Decision 2013-308: Lindberg SAGD Industrial System Designation Application No. 1609200 Proceeding

More information

Nexen Inc. OPTI Canada Inc.

Nexen Inc. OPTI Canada Inc. Decision 2010-006 Nexen Inc. OPTI Canada Inc. Long Lake South Phase 1 Cogeneration Power Plant January 15, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-006: Nexen Inc. and OPTI Canada Inc. Long Lake

More information

Harvest Operations Corp.

Harvest Operations Corp. Decision 2014-214 Six-MW Power Plant Exemption July 21, 2014 The Alberta Utilities Commission Decision 2014-214: Six-MW Power Plant Exemption Application No. 1610444 Proceeding No. 3153 July 21, 2014 Published

More information

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011 Decision 2011-496 December 15, 2011 The Alberta Utilities Commission Decision 2011-496: Application No. 1607774 Proceeding ID No. 1505 December 15, 2011 Published by The Alberta Utilities Commission Fifth

More information

Seven Generations Energy Ltd.

Seven Generations Energy Ltd. Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant January 17, 2018 Alberta Utilities Commission Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant Proceeding 22976

More information

Connacher Oil and Gas Limited

Connacher Oil and Gas Limited Decision 2010-094 Cogeneration Plant and Industrial System Designation March 2, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-094: Cogeneration Plant and Industrial System Designation Application No.

More information

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment Decision 2011-523 (Errata) Errata to Decision 2011-523 Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment January 10, 2012 The Alberta Utilities Commission Decision

More information

Nexen Inc. and CNOOC Canada Inc.

Nexen Inc. and CNOOC Canada Inc. Decision 2012-330 Long Lake Project December 6, 2012 The Alberta Utilities Commission Decision 2012-330: Long Lake Project Application No. 1608729 Proceeding ID No. 2074 December 6, 2012 Published by The

More information

The City of Red Deer

The City of Red Deer Decision 2010-148 The City of Red Deer 15-kW Solar Power Plant for City of Red Deer Civic Yards Building April 5, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-148: The City of Red Deer 15-kW Solar Power

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 23468-D01-2018 Margie 1034S Substation May 28, 2018 Alberta Utilities Commission Decision 23468-D01-2018 Margie 1034S Substation Proceeding 23468 Application 23468-A001 May 28, 2018 Published

More information

Decision Cenovus FCCL Ltd.

Decision Cenovus FCCL Ltd. Decision 2012-196 Construct and Operate a 95-MW Cogeneration Power Plant, Construct and Operate Sunday Creek 539S Substation, Industrial System Designation and Interconnection of the Christina Lake Industrial

More information

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013 Decision 2013-180 13.05-kW Photovoltaic Micro-Generation System May 15, 2013 The Alberta Utilities Commission Decision 2013-180: 13.05-kW Photovoltaic Micro-Generation System Application No. 1609500 Proceeding

More information

NOVA Chemicals Corporation

NOVA Chemicals Corporation Decision 2013-426 NOVA Chemicals Corporation Industrial System Designation Amendment November 29, 2013 The Alberta Utilities Commission Decision 2013-426: NOVA Chemicals Corporation Industrial System Designation

More information

Pembina NGL Corporation

Pembina NGL Corporation Decision 22928-D01-2018 45-Megawatt Cogeneration Power Plant, Alteration to Scoria 318S Substation and Amendment to the Redwater Industrial System Designation January 9, 2018 Alberta Utilities Commission

More information

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013 Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013

More information

NaturEner Wild Rose 1 Energy Inc.

NaturEner Wild Rose 1 Energy Inc. Decision 2013-348 Amendment to Wild Rose 1 Wind Power Plant September 13, 2013 The Alberta Utilities Commission Decision 2013-348: Amendment to Wild Rose 1 Wind Power Plant Application No. 1609685 Proceeding

More information

Signalta Resources Limited

Signalta Resources Limited Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station June 1, 2017 Alberta Utilities Commission Decision 22388-D01-2017 Coaldale 6.4-Megawatt Cogeneration Station Proceeding 22388 Application

More information

Grande Prairie Generation, Inc.

Grande Prairie Generation, Inc. Decision 20292-D01-2015 Northern Prairie Power Plant November 27, 2015 Alberta Utilities Commission Decision 20292-D01-2015 Northern Prairie Power Plant Proceeding 20292 Application 20292-A001 November

More information

Aquatera Utilities Inc.

Aquatera Utilities Inc. Decision 2014-194 Aquatera Utilities Inc. 2.85-MW Power Plant June 26, 2014 The Alberta Utilities Commission Decision 2014-194: Aquatera Utilities Inc. 2.85-MW Power Plant Application No. 1610366 Proceeding

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration May 25, 2017 Alberta Utilities Commission Decision 22562-D01-2017 ENMAX No. 31 Substation Alteration Proceeding 22562 Application 22562-A001 May

More information

SunEEarth Alberta Solar Development Inc.

SunEEarth Alberta Solar Development Inc. Decision 22422-D01-2017 Yellow Lake Solar Project September 26, 2017 Alberta Utilities Commission Decision 22422-D01-2017 Yellow Lake Solar Project Proceeding 22422 Application 22422-A001 September 26,

More information

Burdett Solar GP Corp.

Burdett Solar GP Corp. Decision 23364-D01-2018 Burdett Solar Project Time Extension October 3, 2018 Alberta Utilities Commission Decision 23364-D01-2018 Burdett Solar Project Time Extension Proceeding 23364 Application 23364-A001

More information

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018 Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project May 17, 2018 Alberta Utilities Commission Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project Proceeding 22711 Application

More information

Pteragen Canada Inc.

Pteragen Canada Inc. Decision 2013-171 May 7, 2013 The Alberta Utilities Commission Decision 2013-171: Application No. 1608907 Proceeding ID No. 2181 May 7, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place,

More information

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document Decision 3476-D01-2015 Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document ATCO Electric Ltd. Yeo Substation Project Facility Application February 18, 2015 Alberta Utilities

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions December 19, 2016 Alberta Utilities Commission Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions Proceeding 22229 Application

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

Alberta Electric System Operator Needs Identification Document Application

Alberta Electric System Operator Needs Identification Document Application Decision 22618-D01-2017 Alberta Electric System Operator Needs Identification Document Application Facility Applications June 22, 2017 Alberta Utilities Commission Decision 22618-D01-2017: Alberta Electric

More information

EDF EN Canada Development Inc.

EDF EN Canada Development Inc. Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant March 2, 2016 Alberta Utilities Commission Decision 21203-D01-2016 Blackspring Ridge Wind Power Plant Proceeding 21203 Application 21203-A001

More information

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018 Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and Salvage November 8, 2018 Alberta Utilities Commission Decision 23890-D01-2018 Swan Hills F.P.L. 744S Substation Decommission and

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22499-D01-2017 June 7, 2017 Decision 22499-D01-2017 Proceeding 22499 Application 22499-A001 June 7, 2017 Published by the: Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta

More information

Alberta Power (2000) Ltd.

Alberta Power (2000) Ltd. Decision 23558-D01-2018 Battle River Power Plant Alterations August 27, 2018 Alberta Utilities Commission Decision 23558-D01-2018 Battle River Power Plant Alterations Proceeding 23558 Application 23558-A001

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by

More information

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008 Decision 2008-132 FortisAlberta Inc. Micro-Generation Determination December 16, 2008 ALBERTA UTILITIES COMMISSION Decision 2008-132: FortisAlberta Inc. Micro-Generation Determination Application No. 1594619

More information

TransAlta Corporation

TransAlta Corporation Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant Units 1 and 2 December 21, 2018 Alberta Utilities Commission Decision 23808-D01-2018 Coal-to-Gas Conversion of Keephills Power Plant

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on March

More information

Meadow Creek West. Project overview:

Meadow Creek West. Project overview: Project overview: Meadow Creek West will be a steam assisted gravity drainage (SAGD) oil sands development in northeast Alberta. Meadow Creek West is an additional phase to our Meadow Creek project and

More information

Greengate Power Corporation

Greengate Power Corporation Decision 2011-085 Blackspring Ridge Wind Project March 9, 2011 The Alberta Utilities Commission Decision 2011-085: Blackspring Ridge Wind Project Application No. 1604777 Proceeding ID No. 190 March 9,

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 22706-D01-2017 Spring 2017 Comprehensive Sound Survey at Receptors R and S August 25, 2017 Alberta Utilities Commission Decision 22706-D01-2017 Proceeding 22706 Application 22706-A001 August 25,

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation Mackenzie County October 11, 2018 Alberta Utilities Commission Decision 23918-D01-2018 Paddle Prairie Compressor Station Installation

More information

Solar Krafte Utilities Inc.

Solar Krafte Utilities Inc. Decision 23323-D01-2018 August 21, 2018 Alberta Utilities Commission Decision 23323-D01-2018 Proceeding 23323 Application 23323-A001 August 21, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

HYDRO AND ELECTRIC ENERGY REGULATION

HYDRO AND ELECTRIC ENERGY REGULATION Province of Alberta HYDRO AND ELECTRIC ENERGY ACT HYDRO AND ELECTRIC ENERGY REGULATION Alberta Regulation 409/1983 With amendments up to and including Alberta Regulation 136/2015 Office Consolidation Published

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22447-D01-2017 Vauxhall Solar Power Plant July 4, 2017 Alberta Utilities Commission Decision 22447-D01-2017 Vauxhall Solar Power Plant Proceeding 22447 Application 22447-A001 July 4, 2017 Published

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

Section 1 - Introduction

Section 1 - Introduction Section 1 - Introduction Algar Lake SAGD Project Section 1 Project Introduction TABLE OF CONTENTS 1. PROJECT INTRODUCTION... 1 1.1 PROJECT BACKGROUND... 1 1.2 PROJECT PROPONENT... 1 1.3 PROJECT OVERVIEW...

More information

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014 Decision 2014-212 Syncrude Canada Ltd. Mildred Lake Power Plant July 17, 2014 Decision 2014-212: Syncrude Canada Ltd. Mildred Lake Power Plant Application No. 1610311 Proceeding No. 3068 July 17, 2014

More information

AltaGas Utilities Inc.

AltaGas Utilities Inc. Decision 23713-D01-2018 August 28, 2018 Alberta Utilities Commission Decision 23713-D01-2018 Proceeding 23713 Application 23713-A001 August 28, 2018 Published by the: Alberta Utilities Commission Eau Claire

More information

RULE 302 Permit Fee Schedules - Adopted 04/18/72; Amended 06/20/78; 12/15/80; 06/29/81; 04/25/83; 06/29/87; 03/01/88; 06/01/93; 03/13/08, 11/13/08.

RULE 302 Permit Fee Schedules - Adopted 04/18/72; Amended 06/20/78; 12/15/80; 06/29/81; 04/25/83; 06/29/87; 03/01/88; 06/01/93; 03/13/08, 11/13/08. RULE 302 Permit Fee Schedules - Adopted 04/18/72; Amended 06/20/78; 12/15/80; 06/29/81; 04/25/83; 06/29/87; 03/01/88; 06/01/93; 03/13/08, 11/13/08. It is hereby determined the cost of issuing permits,

More information

Renewable Energy Services Ltd.

Renewable Energy Services Ltd. Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation February 23, 2018 Alberta Utilities Commission Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation Proceeding 1976 Applications

More information

Notice of Technical Meeting

Notice of Technical Meeting Notice of Technical Meeting Amendments to three wind energy projects in the Pincher Creek area proposed by Welsch Wind Power Inc., Windy Point Wind Park Ltd. and NextEra Canada Development & Acquisitions,

More information

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT Notice NOTICE OF APPLICATIONS SHELL CANADA LIMITED QUEST CARBON CAPTURE AND STORAGE RADWAY FIELD ENERGY RESOURCES CONSERVATION BOARD APPLICATIONS NO. 1689376, 1670112, AND 1671615 ALBERTA ENVIRONMENT ENVIRONMENTAL

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 22274-D01-2018 Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement January 12, 2018 Alberta Utilities Commission Decision 22274-D01-2018 Provost to Edgerton and Nilrem

More information

JAPAN CANADA OIL SANDS HANGINGSTONE SAGD PROJECT

JAPAN CANADA OIL SANDS HANGINGSTONE SAGD PROJECT Public Disclosure Document for the proposed JAPAN CANADA OIL SANDS HANGINGSTONE SAGD PROJECT May 7 th, 2008 I. INTRODUCTION Japan Canada Oil Sands Limited (JACOS) continues to evaluate the development

More information

Telephone Lake project

Telephone Lake project Telephone Lake project Cenovus Energy Inc. is a Canadian oil company. We re committed to applying fresh, progressive thinking to safely and responsibly unlock energy resources the world needs. Our operations

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

October 2, 2015 EAB File #: Transaction #:

October 2, 2015 EAB File #: Transaction #: Ministry of Environment Environmental Assessment Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: 306.787 5971 Fax: 306 787 0930 October 2, 2015 EAB File #: 2015-013 Transaction

More information

Understanding Bill 50

Understanding Bill 50 1 Understanding Bill 50 Major Players: Energy Utilities Board (EUB): Prior to 2008, the EUB was the governing body responsible for regulating the entire energy industry in Alberta, including transmission

More information

ATCO HEARTLAND GENERATING STATION PHASE 2

ATCO HEARTLAND GENERATING STATION PHASE 2 ATCO HARTLAND GNRATING STATION PHAS 2 Project Information Package August 2015 Conceptual drawing of ATCO Heartland Generating Station with Phase 2 on the upper left Project Overview ATCO Power is proposing

More information

Jackfish 2 Project. Public Disclosure Document. August 2005

Jackfish 2 Project. Public Disclosure Document. August 2005 Jackfish 2 Project Public Disclosure Document August 2005 Table of Contents Introduction...1 Company Profile...2 Preliminary Project Description...2 The Plan...2 The Process...3 Facilities...3 Physical

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2014-126 South and West Edmonton Area Transmission System Reinforcement Needs Identification Document May 5, 2014 The Alberta Utilities Commission Decision 2014-126: South and West Edmonton Area

More information

ATCO Gas and Pipelines Ltd.

ATCO Gas and Pipelines Ltd. Decision 22889-D01-2017 ATCO Gas and Pipelines Ltd. 2017-2018 Unaccounted-For Gas Rider D October 13, 2017 Alberta Utilities Commission Decision 22889-D01-2017 ATCO Gas and Pipelines Ltd. 2017-2018 Unaccounted-For

More information

Cold Lake expansion project

Cold Lake expansion project Cold expansion project Initial project description Plain language summary March 2016 Our commitment Imperial Oil Limited s success depends on our ability to maintain an open dialogue with, and ongoing

More information

LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012

LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012 LARICINA ENERGY LTD. STONY MOUNTAIN PIPELINE PROJECT DESCRIPTION DOCUMENT FEBRUARY 2012 01 STONY MOUNTAIN PIPELINE Laricina will develop and follow an environmental protection plan that meets or exceeds

More information

GROUSE GROUSE IN SITU OIL SANDS PROJECT. Proposed Development Plan. Plain Language Project Summary

GROUSE GROUSE IN SITU OIL SANDS PROJECT. Proposed Development Plan. Plain Language Project Summary GROUSE Proposed Development Plan GROUSE IN SITU OIL SANDS PROJECT Plain Language Project Summary ABOUT CANADIAN NATURAL WHO WE ARE Canadian Natural Resources Limited (Canadian Natural) is a senior independent

More information

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc.

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Decision 2010-612 Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc. Needs Identification Document, Transmission Line, Substation and Power Plant Al-Pac Pulp

More information

Project Location. The CEC is a 320 MW combined-cycle power generation

Project Location. The CEC is a 320 MW combined-cycle power generation ENMAX Corporation ENMAX, through its subsidiaries, makes, moves and sells electricity to residential, small business and large commercial customers and is headquartered in Calgary, Alberta, with offices

More information

[] Brochure, picture, drawing, etc., of the use to be conducted (if applicable).

[] Brochure, picture, drawing, etc., of the use to be conducted (if applicable). TEMPORARY USE PERMIT APPLICATION ACCOUNT # 4232 Temporary Use Permit procedures are contained in Section 83.030705 of the Yucaipa Development Code. Temporary Use Permits shall be first issued for a period

More information

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report Prepared for: Grand Valley 2 Limited Partnership 222 3rd Avenue Southwest, Suite 900 Livingston Place, South Tower Calgary

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 2014-313 Sarcee Trail S.W. Pipeline Replacement Southwest Calgary November 14, 2014 The Alberta Utilities Commission Decision 2014-313: Sarcee Trail S.W. Pipeline Replacement Southwest Calgary

More information

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints Decision 22493-D01-2018 1646658 Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints January 17, 2018 Alberta Utilities Commission Decision 22493-D01-2018 1646658 Alberta Ltd. (BluEarth)

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

Section 1 Project Introduction

Section 1 Project Introduction Section 1 Project Introduction TABLE OF CONTENTS Page 1 PROJECT INTRODUCTION... 1 1.1 PROJECT BACKGROUND... 2 1.2 PROJECT PROPONENT... 3 1.3 PROJECT OVERVIEW... 4 1.4 PROJECT REGULATORY APPROVAL PROCESS...

More information

October 30, 2012 Our File:

October 30, 2012 Our File: October 30, 2012 Our File: 5000-510-5120 Minister of Environment and Sustainable Resource Development 204 Legislature Building 10800 97 Avenue Edmonton, AB T5K 2B6 Attention: Honourable Diana McQueen at

More information

Form B GENERATION INTERCONNECTION APPLICATION (Non-Inverter Based Generation and Inverter Based Generation > 25 kw)

Form B GENERATION INTERCONNECTION APPLICATION (Non-Inverter Based Generation and Inverter Based Generation > 25 kw) Form B GENERATION INTERCONNECTION APPLICATION (Non-Inverter Based Generation and Inverter Based Generation > 25 kw) Preface: This Facility Connection Standard applies to any connection to Westar Energy's

More information

Cogeneration & Carbon Management Key Issues in the Design of Carbon Management Policies and Regulations in Alberta

Cogeneration & Carbon Management Key Issues in the Design of Carbon Management Policies and Regulations in Alberta Cogeneration & Carbon Management Key Issues in the Design of Carbon Management Policies and Regulations in Alberta Paula McGarrigle Managing Director Solas Energy Consulting Inc. Suite 119, 2137 33 Avenue

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 2008-012 Application for a Pipeline Licence Taber Field February 12, 2008 ALBERTA ENERGY AND UTILITIES BOARD Decision 2008-012:, Application for a Pipeline Licence, Taber Field February 12, 2008

More information

SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT. Attachment D. Property Line Setback Assessment

SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT. Attachment D. Property Line Setback Assessment SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT Attachment D Property Line Setback Assessment SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT

More information

THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL

THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL Alberta Municipal Affairs February 1997 Updated March 2002 1.0 INTRODUCTION The authority for municipal planning,

More information

MICRO-GENERATION NOTICE SUBMISSION GUIDELINE

MICRO-GENERATION NOTICE SUBMISSION GUIDELINE www.auc.ab.ca MICRO-GENERATION NOTICE SUBMISSION GUIDELINE ( V e r s i o n 2. 0 ) September 20, 2017 T a b l e o f C o n t e n t s 1. Introduction...2 2. Purpose...2 3. Differences between micro-generation

More information

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc.

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc. Regulatory Audit Report #2008-001 ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc. Inter-Affiliate Code

More information

ADMINISTRATION RECOMMENDATION(S) 2017 May 04. That Calgary Planning Commission recommends APPROVAL of the proposed Land Use Amendment.

ADMINISTRATION RECOMMENDATION(S) 2017 May 04. That Calgary Planning Commission recommends APPROVAL of the proposed Land Use Amendment. Page 1 of 17 EXECUTIVE SUMMARY This land use amendment application seeks to redesignate 214 lots, comprising approximately 11.59 hectares (28.63 acres), from DC Direct Control District to DC Direct Control

More information

The current note, approved by the County Commission on August 11, 2015 (INSTR # ) reads as follows:

The current note, approved by the County Commission on August 11, 2015 (INSTR # ) reads as follows: Page 1 of 16 STAFF REPORT Palm Aire Cypress Course Estates 4 th Section 126-MP-81 A request to amend the note on the plat has been filed with the Planning and Development Management Division. This plat

More information

Suspension Requirements for Wells

Suspension Requirements for Wells Directive 01 Suspension Requirements for Wells July 24, 2007 Effective January 1, 2008, the Alberta Energy and Utilities Board (EUB) has been realigned into two separate regulatory bodies, the Energy Resources

More information

The Standards referred to shall be the most recent edition.

The Standards referred to shall be the most recent edition. Page 1 of 7 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described hereunder shall consist of the excavation of trenches and tunnels; the supply and installation of pipe and/or encasement pipe; the

More information

Capital Power Generation Services Inc.

Capital Power Generation Services Inc. Decision 22563-D01-2018 Halkirk 2 Wind Power Project April 11, 2018 Alberta Utilities Commission Decision 22563-D01-2018 Halkirk 2 Wind Power Project Proceeding 22563 Applications 22563-A001 and 22563-A002

More information

May 8, 2017 EASB File #: Transaction #:

May 8, 2017 EASB File #: Transaction #: Ministry of Environment Environmental Assessment and Stewardship Branch 4 th floor, 3211 Albert Street Regina, Saskatchewan S4S 5W6 Phone: (306) 787-6132 Fax: (306) 787-0930 May 8, 2017 EASB File #: 2016-022

More information

ALBERTA QUEEN ELIZABETH II HIGHWAY (HWY 2) STONEY TRAIL. To Edmonton. Calgary International Airport EDMONTON CALGARY. To the U.S.

ALBERTA QUEEN ELIZABETH II HIGHWAY (HWY 2) STONEY TRAIL. To Edmonton. Calgary International Airport EDMONTON CALGARY. To the U.S. Nose Creek Business Park is a 5.5 million square foot master-planned, mixed use commercial development situated on 324 acres along the Queen Elizabeth II Highway, just north of Stoney Trail ring road and

More information

Ellerslie Substation Expansion

Ellerslie Substation Expansion Ellerslie Substation Expansion Volume 2 UV 2 North Saskatchewan River EDMONTON UV 216 UV 14 ") ELLERSLIE 89S Bretona!! Trevithick March 2010 Why are you receiving this newsletter? You are receiving this

More information

Garvagh Glebe Wind Energy Project County Leitrim

Garvagh Glebe Wind Energy Project County Leitrim HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's

More information

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement Your guide to the SOUTHERN ALBERTA Transmission Reinforcement OUR TRANSMISSION LINES TRANSPORT THE POWER YOU USE EVERY DAY. Edmonton Red Deer Calgary Lethbridge 85% AltaLink s transmission system efficiently

More information

Order. -AI1ta. Energy Regulator. MADE at the City of Fort McMurray, in the Province of Alberta, on

Order. -AI1ta. Energy Regulator. MADE at the City of Fort McMurray, in the Province of Alberta, on -AI1ta Order Energy Regulator MADE at the City of Fort McMurray, in the Province of Alberta, on August 11 2015 ALBERTA ENERGY REGULATOR Under Sections 113 and 156 of the Environmental Protection and Enhancement

More information

GARKANE ENERGY COOPERATIVE SMALL GENERATOR QUALIFIED FACILITY INTERCONNECTION APPLICATION

GARKANE ENERGY COOPERATIVE SMALL GENERATOR QUALIFIED FACILITY INTERCONNECTION APPLICATION Designated Contact Person: Mike Avant, Engineering Manager Address (for U.S. Mail Deliveries): Garkane Energy 1802 S Highway 89A Kanab, UT 84741 Telephone Number: (435) 644-5-26 E-Mail Address: mike.avant@garkane.com

More information

Decision (Errata) Alberta Ltd. Errata to Decision Bull Creek Wind Project. March 10, 2014

Decision (Errata) Alberta Ltd. Errata to Decision Bull Creek Wind Project. March 10, 2014 Decision 2014-040 (Errata) Errata to Decision 2014-040 Bull Creek Wind Project March 10, 2014 The Alberta Utilities Commission Decision 2014-040 (Errata): Bull Creek Wind Project Application No. 1608556

More information

nine (9) pad-mounted tranformers each approximately 75 kilovolt-ampere (kva), designated as sound sources ID: BC-63 to BC-71;

nine (9) pad-mounted tranformers each approximately 75 kilovolt-ampere (kva), designated as sound sources ID: BC-63 to BC-71; Ministry of the Environment Ministère de l Environnement RENEWABLE ENERGY APPROVAL NUMBER 2895-8QCJVX Issue Date: February 9, 2012 Injasuti Developments Ltd. 2650 Spruce Needle Dr Mississauga, Ontario

More information

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance Project: East Hampton Temporary Generation Facility Expansion Date: May 17, 2018 This notice is issued

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 20581-D02-2016 Rossdale Substation Building Expansion May 13, 2016 Alberta Utilities Commission Decision 20581-D02-2016 Rossdale Substation Building Expansion Proceeding 20581 Application 20581-A001

More information

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,

More information