Probabilistic Security Assessment in Practice
|
|
- Nigel Daniel
- 6 years ago
- Views:
Transcription
1 Workshop : Increased utilisation of the Nordic Power Transmission System Probabilistic Security Assessment in Practice Idar Gimmestad Kjetil Uhlen STATNETT SINTEF Energiforskning AS 1
2 Background and objective: Development of prototype tools for handling and determination of flexible power transfer limits Results from 2001 Handling congestions between price areas in Elspot (The Flexlast -prototype) Module for calculation of congestion cost Module for calculating Risk Index Results from 2002 Handling internal bottlenecks within price areas Module for estimation of Expected Interruption Cost (EIC) Module for handling of regulating power market (RPM)-costs Objective 2003/2004: Implement a practical tool for Statnett s NCC 2
3 Reliability based operation N-1 criterion (deterministic) Little flexibility, uncertain if the power system capacity is fully utilised The alternative: Reliability based criterion which opens for flexible power transfer corridor (PTC) limits. Weighing between cost and risk Risk = probability x consequence 3
4 Motivation for using flexible reliability based PTC limits Increase utilising of the existing network Allowing increased risk for short interruptions at some places, while Keeping the consequences under control Why: Reduce costs 4
5 Flexible reliability based PTC limits Risk level Increased capacity increased risk level Today Today's situation Today Increased capacity Accept increased risk Increased capacity equal risk level Capacity 5
6 Flexlast - Prototype structure PSS/E-file Nordpool Uploading Data format Congestion cost Assembly of results Contingency analysis 6
7 Summary of project activities in 2002 The project has implemented methods for risk based socio-economic evaluation of power transfer limits as an alternative to deterministic criteria. Prototype software modules has been established. The results have demonstrated that it is possible to implement a practical tool for handling of internal bottlenecks (congestions within price areas) Testing of the prototypes: A few cases are tested as part of the project. Need to carry out more realistic case studies in order to gain experiences. Further development and implementation should be done in close cooperation with control centre staff and the new control centre/ems project. 7
8 Resulting modules from project activities Flexible PTC flow limits Congestion cost between price areas Risk index calculation Assembly of results Decision aid Regulating Power Market costs Expected interruption cost estimation 8
9 Network areas of interest 132 kv 300 kv 420 kv SVELGEN GROV GYLTHALSEN STAKALDEFOSS DALE KOLLSNES FANA STORD FARDAL HOVE MODAL EVANGER HØYANGER REFSDAL LEIR- DØLA SIMA JOSTEDAL FORTUN AURLAND KR.SUND TROLLHEIM ISTAD BRANDHOL DRIVA GRYTTEN AURA ORKDAL GRANA KLÆBU VERDAL STRINDA HÅVIK HUSNES SAMNANGER MAURANGER GISKEMO TAFJORD ØRSKOG SYKKYLVEN BRATTSET NEA BLÅFALLI OKSLA DAGALI HAUGEN HÅHEIM LEIVDAL LITJFOSSEN SAUDA ÅSEN RØLDAL ÅSKÅRA BRYGGJA ULSET NESFLATEN VÅGÅMO SAVALEN HYLEN KVILDAL SONGA VEMORK RJUKAN Ø.VINSTRA RENDALEN SAURDAL VINJE HOLEN TOKKE 9
10 Model for decision-making Decision on operating startegy involves: Transfer limit (Amount of corrective re-dispatch) If and where to split the network Generation & Consumption Deficit network area Security criteria Congestion cost Expected interruption costs System protection Operating strategy 10
11 Operating strategies N-1 Meshed network N-0 Radial network without UFLS?? zero? Congestion cost Interruption cost?? N-1/2 Radial network with UFLS where? Split network where? 11
12 Illustrating example S Consumption forecast P GC = 300 MW P LC = 500 MW PL=min load + (max load -min load)*factor = 1700 MW Local Generation PG = PL PINT = 700 MW Import demand PINT = PL PG = 1000 MW Main Transmission Network λ 4 C limit 600 MW (N-1) interface flow B λ 3 P LB = 400 MW Bids on RPM A B C Thermal limit 600 MW A λ 2 Power [MW] λ 1 Price [NOK/MWh] Last (actual) RPM price 320 NOK/MWh PTC P GA = 400 MW P LA = 800 MW BFK = 500 MW 12
13 Object function Min Cost = Min (Cost corrective redispatch + Cost interruption) Cost corrective redispatch = (RPM local bid RPM current hour) * Ρ Cost interruption = Σ (λn * Pn+1 ) * Rline * KILE * Fv + Σ (λn * Pn UFLS ) * RUFLS * KILE * Fv 13
14 Corrective re-dispatch and flow Operating strategy Regulated power [MW] Interface flow [MW] Meshed network N Split between B and C Split between B and C Split between A and B Split between A and B N-1/2 with UFLS N-0 without UFLS N-1/2 with UFLS N-0 without UFLS
15 Total cost and elements Operating strategy Congestion cost [NOK] Interruption cost [NOK] Total [NOK] Meshed network N Split between B and C N-1/2 with UFLS Split between B and C N-0 without UFLS Split between A and B N-1/2 with UFLS Split between A and B N-0 without UFLS
16 Costs with different strategies N-1/2, w/ufls Split B-C N-0, wo/ufls N-0, 500 Costs [NOK] Joint network N-1 Special regulation cost Interruption cost wo/ufls Split A-B N-1/2, w/ufsl Regulation [MW] Sum cost Regulated power Interface flow 16
17 Total strategy costs Expected Interruption Interruption costs costs Congestion Corrective cost redispatch Costs [NOK/hour] N-1 N-1/2,split B-C, w/ufls N-0,split B-C, wo/ufls N-0,split A-B, wo/ufls N-1/2,split A-B, w/ufls 17
A Probabilistic Security Criterion for Determination of Power Transfer Limits in a Deregulated Environment
A Probabilistic Security riterion for Determination of Power Transfer Limits in a Deregulated Environment Kjetil Uhlen and Gerd H. Kjølle, SINTEF Energy Research Gunnar G. Løvås and Øyvind Breidablik,
More informationPRINCIPLES FOR DETERMINING THE TRANSFER CAPACITIES IN THE NORDIC POWER MARKET
PRINCIPLES FOR DETERMINING THE TRANSFER CAPACITIES IN THE NORDIC POWER MARKET 30.11.2017 Revision Date Summary of updates 3. Final 2010-06-22 New version 4. Final 2011-02-18 Text about Estlink updated.
More informationNorwegian Grid Development Plan 2017 Short version
Norwegian Grid Development Plan Short version Summary The transmission grid is a central part of society's infrastructure. Planning and constructing the grid according to needs and profitability is one
More informationProject: Increased Utilisation of the Nordic Power Transmission System
Workshop: Project: Increased Utilisation of the Nordic Power Transmission System The main aim of the workshop is to establish a meeting place for all project participants to present preliminary results
More informationCapacity Calculation. Tom Tellefsen, Statnett 25.October 2018
Capacity Calculation Tom Tellefsen, Statnett 25.October 2018 Capacity calculation 1. Provide the market with as high market capacities as possible, given the constraints in the grid. N-1 principle No planned
More informationDispatch Signal & Locational Marginal Pricing (LMP)
Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. PJM 2017 Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP PJM 2017 2 Dispatch Rate Definition:
More informationSession 2: Grids: the gateway to power
Session 2: Grids: the gateway to power the TWENTIES project will discuss examples of best practice and Provide their perspectives on future energy systems Latvian Association of Wind Energy (LAWE) 1 Demo
More informationA Nodal Pricing Model for the Nordic Electricity Market
INSTITUTT FOR FORETAKSØKONOMI DEPARTMENT OF BUSINESS AND MANAGEMENT SCIENCE FOR 43 2014 December 2014 Discussion paper A Nodal Pricing Model for the Nordic Electricity Market BY Endre Bjørndal, Mette Bjørndal
More informationNordREG memo to EMG on the price peaks in the NPS market
NordREG memo to EMG on the price peaks in the NPS market September 14th, 2010 1. Introduction The Nordic wholesale power market prices peaked during the winter 2009-2010. For Sweden, Finland, Eastern Denmark,
More informationSystem Integrity Protection Schemes Increasing operational security and system capacity
21, rue d Artois, F-758 PARIS C2-21 CIGRE 212 http : //www.cigre.org System Integrity Protection Schemes Increasing operational security and system capacity E. HILLBERG 1, F. TRENGEREID 2, Ø. BREIDABLIK
More informationMonitoring vulnerability in power systems
Monitoring vulnerability in power systems Extraordinary events, analysis framework and development of indicators Gerd Kjølle, Oddbjørn Gjerde, Matthias Hofmann Electric power systems SINTEF Energy Research
More informationTreatment of Transmission System Bottlenecks - Future Strategies at PreussenElektra Netz
APX International Conference, 16-17 November 1999 Amsterdam, The Netherlands Treatment of Transmission System Bottlenecks - Future Strategies at PreussenElektra Netz Markus Bredow Matthias Luther Germany
More informationCoordination of MRN-NEEM Modeling and High Level Transmission Analysis in Task 5
Coordination of MRN-NEEM Modeling and High Level Transmission Analysis in Task 5 December 30 Revision of the presentation at Macro Future Workshop November 8-9, 2010 Project Objectives Phase I The Roll-Up
More informationComputing Locational Contingency Reserves
Computing Locational Contingency Reserves Simulation and DyMonDs application to Bulk Power System Reliability Jose Fernando Prada 10 th CMU Electricity Conference Pre-conference Workshop March 30, 2015
More informationMarket Based demand Response
Market Based demand Response Results from Norwegian Research Projects IAE/DSM workshop, Trondheim 18 Ove April, S. Grande 2012 Senior Research Scientist SINTEF Energy Research Technology for a better society
More informationAnalysis of Electricity Markets. Lennart Söder
Analysis of Electricity Markets Lennart Söder Electric Power Systems Royal Institute of Technology March 2011 ii Contents 1 Basic electricity market modelling 1 1.1 Demand model...............................
More informationOverview Balance Management project
Overview Balance Management project Ove S. Grande WS Gardermoen 26 January 11 SINTEF Energy Research 0 The Balance Management Project Competence building project in the framework of The Norwegian Research
More informationReliability Coordinator Area System Operating Limit Methodology
Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power
More informationNordic Grid Master Plan 2008
March 28 Nordic Grid Master Plan 28 Organisation for the Nordic Transmission System Operators Table of Contents 1 Summary and recommendation 2 1.1 Background...2 1.2 Approach taken in the analysis...3
More informationAPPENDIX G DISPATCH RELATED DATA
APPENDIX G DISPATCH RELATED DATA G.1 INTRODUCTION G.1.1 The information listed in sections G.2 to G.7 of this Appendix describes the dispatch related data referred to in sections 6.1 and 8.1 of this Chapter
More informationExplanatory document for the Nordic synchronous area proposal for the FRR dimensioning rules in accordance with Article 157(1) of the Commission
Explanatory document for the Nordic synchronous area proposal for the FRR dimensioning rules in accordance with Article 157(1) of the Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing
More informationGrid Development Plan
Grid Development Plan 2005-2020 June 2005 SUMMARY Grid development at a rapid pace Statnett has a leading role in developing an effi cient Norwegian and Nordic electricity market. A key responsibility
More informationKlaus Wewering. ACER Workshop CBA 2.0. Improving the pan-european cost-benefit analysis methodology 10 May 2016
CBA 2.0 Klaus Wewering ACER Workshop Improving the pan-european cost-benefit analysis methodology 10 May 2016 RES integration (B.4) What is measured? Contribution of the project to the usage of RES generation
More informationElectricity Market Design : Experience from the Nordic electricity market NORDPOOL
Electricity Market Design : Experience from the Nordic electricity market NORDPOOL Kurt Jörnsten Department of Business and Management Science, Norwegian School of Economics 1 Objectives for the deregulated
More informationIncreasing Efficiency On The Transmission Grid With Real Time Monitoring
Increasing Efficiency On The Transmission Grid With Real Time Monitoring Joint CEA Transmission Council & Corporate Partners Committee Strategic Workshop February 25, 2009 Presented by: Ron Stelmak The
More informationCARIS Procedure Development and Simulation Model Evaluation
CARIS Procedure Development and Simulation Model Evaluation Bill Lamanna Manager Long Term Planning New York Independent System Operator ESPWG Meeting NYISO September 16, 2009 Draft 1 for discussion only
More informationLess than 20 MW Constraint Reliability Margin Values
Less than 20 MW Constraint Reliability Margin Values David Edelson Manager Operations Performance and Analysis Management Committee August 29, 2018 Rensselear, NY Background NYISO s tariff currently requires
More informationPower Systems Engineering Research Center (PSERC ) An NSF Industry / University Cooperative Research Center. Mission
Power Systems Engineering Research Center ( ) An NSF Industry / University Cooperative Research Center 1 Mission Universities working with industry and government to find innovative solutions to challenges
More informationNational Report Norwegian Water Resources and Energy Directorate (NVE)
National Report Norwegian Water Resources and Energy Directorate (NVE) The data/content refer to 31 December 2011 or the reporting period 2011 unless otherwise stated. 1 Table of Contents Norwegian Water
More informationMID-NORWAY POWER STUDY. A/S Norske Shell E&P
MID-NORWAY POWER STUDY A/S Norske Shell E&P Mid-Norway power study Page 2 of 52 TABLE OF CONTENTS 1 SUMMARY...4 2 INTRODUCTION...5 2.1 BACKGROUND...5 3 REGIONAL BACKGROUND...6 3.1 INTRODUCTION...6 3.2
More information2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool
2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.
More informationSOVN - NEW MARKET MODEL EXPERIENCE AND RESULTS
SOVN - NEW MARKET MODEL EXPERIENCE AND RESULTS Arild Lote Henden, Brukermøte 2017 Agenda Introduction Base method Results Challenges Conclusion 2 Introduction SOVN Stochastic Optimization with individual
More informationLOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals
Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to
More informationLocational Marginal Pricing (LMP): Basics of Nodal Price Calculation
MRTU Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation CRR Educational Class #2 CAISO Market Operations Why are LMPs important to the CRR Allocation & Settlement Process The CRR revenue
More informationDemand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois
1 Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois Zhi Zhou*, Audun Botterud Computational Engineer Argonne National Laboratory
More informationConstraint Specific Transmission Demand Curves
Constraint Specific Transmission Demand Curves Jennifer Boyle Associate Energy Market Design Specialist MIWG December 5, 2017, Krey Corporate Center Today s Agenda Background Project Objectives Scope of
More informationRenewables in Electricity Markets
31761 - Renewables in Electricity Markets Exercise session 1: Day-ahead electricity markets [SOLUTION] The aim of this exercise session is to appraise and better understand the basic structure of electricity
More informationGeneration Deactivation Notification Update
Generation Deactivation Notification Update Transmission Expansion Advisory Committee May 3, 2018 Generation Deactivation 2 Deactivation Status Unit(s) Transmission Zone Requested Deactivation Date PJM
More informationInvestigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection
7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej
More informationCapacity Subscription
Capacity Subscription Gerard Doorman 1 Capacity Subscription Before actual consumption, consumers pay for a fuse that limits demand to fuse size in kw Fuses are centrally controlled and become Load Limiting
More informationSimulation and Optimization of Systems with Multiple Energy Carriers
Simulation and Optimization of Systems with Multiple Energy Carriers Bjørn H. Bakken Arne Haugstad Knut S. Hornnes Sivert Vist Bjørn Gustavsen Jarand Røynstrand SINTEF Energy Research N-7465 Trondheim,
More informationIncidence Matrix-Based LMP Calculation: Algorithm and Applications
Incidence Matrix-Based LMP Calculation: Algorithm and Applications Mohammad Sadegh Javadi Department of Electrical Engineering, Science and Research Branch, Islamic Azad University, Fars, Iran Abstract
More informationResponse 1 (5) Public
Response 1 (5) ACER, Agency for the Cooperation of Energy Regulators consultation2013e04@acer.europa.eu The influence of existing bidding zones on electricity markets FORTUM'S RESPONSE TO PUBLIC CONSULTATION
More informationTechnical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations
Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations
More informationREGIONAL FORECASTING OF GENERATION FROM SMALL HYDROPOWER PLANTS
REGIONAL FORECASTING OF GENERATION FROM SMALL HYDROPOWER PLANTS Professor Ånund Killingtveit NTNU/CEDREN Workshop on Hydro Scheduling in Competitive Electricity Markets Trondheim, Norway, September 17-18
More informationEnergy balances 2011 Power balances 2011/2012
Energy balances 2011 Power balances 2011/2012 May 2008 1 CONTENTS Summary and Conclusions 3-4 Forecast 5-11 Energy balances 12-19 Power balances 20-24 Security of Supply 25-33 Appendices 34-42 1. Energy
More informationMethodology for Calculating Operating Limits for Generators
Page 1 of 6 Methodology for Calculating Operating Limits for Generators I. Generator Operating Limit Definition The Generator Operating Limit (GOL) for a generator establishes a pathspecific, directional,
More informationImpact of large scale wind integration on power system balancing
1 Impact of large scale wind integration on power system balancing S. Jaehnert*, Student Member IEEE, T. Aigner*, Student Member IEEE, G. Doorman, IEEE Senior Member and T. Gjengedal, IEEE Senior Member
More informationThe influence of existing bidding zones on electricity markets
Your reference Our reference Date 30.09.2013 Agency for the cooperation of energy regulators consultation2013e04@acer.europa.eu The influence of existing bidding zones on electricity markets Energy Norway
More informationSSR STUDY REPORT FINAL
System Support Resource Study Escanaba 1 & 2: 25 MW Coal 36 Month Suspension 6/15/2012 6/15/2015 SSR STUDY REPORT FINAL June 21, 2012 Redacted version for January 3, 2013 filing EXECUTIVE SUMMARY An Attachment
More informationDRAFT STUDY PLAN FOR 2018
DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure
More informationGenerator Contingency & RAS Modeling
Generator Contingency & RAS Modeling Revised Issue Paper & Straw Proposal November 15, 2016 Perry Servedio Sr. Market Design & Regulatory Policy Developer Agenda Time Topic Presenter 9:00-9:05 Introduction
More informationMaine Public Service Transmission System Reliability
Maine Public Service Transmission System Reliability Presentation at the Northern Maine Planning Advisory Group 5/15/13 Today s Presentation will cover: Part I Assumptions & Methodology Assumptions used
More informationNordic Power System. Challenges and Opportunities for the Nordic Power System
Challenges and Opportunities for the Nordic Power System This report summarises the shared view of the four Nordic Transmission System Operators (TSOs) Svenska kraftnät, Statnett, Fingrid and Energinet.dk,
More informationTRANSITION OF THE DANISH POWER SYSTEM
TRANSITION OF THE DANISH POWER SYSTEM -from fossil fuels to large scale wind power International Wind & Solar Workshop October 2018 Stockholm, Sweden Peter Børre Eriksen, Chief Engineer, Energinet 1 ENERGINET
More informationWhat s That. Using AURORAxmp to Evaluate Transmission i Expansion. September 10, Electric Market Forecasting Conference Stevenson, WA
What s That Transmission Line Worth? Using AURORAxmp to Evaluate Transmission i Expansion September 10, 2008 2008 Electric Market Forecasting Conference Stevenson, WA Presentation Outline I. Problem Formulation
More informationDispatch Signal & Locational Marginal Pricing (LMP)
Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP Dispatch Rate Economic control signal
More informationDr Emil Hillberg has an international career within the power system area, including previous positions at ABB, SINTEF Energy Research, and STRI, in
Dr Emil Hillberg has an international career within the power system area, including previous positions at ABB, SINTEF Energy Research, and STRI, in Switzerland, Norway and Sweden. Since March 2018 he
More informationPID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation
PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date Description
More information5.4 Post Contingency Local Load Relief Warning
5.4 Post Contingency Local Load Relief Warning Post Contingency Local Load Relief Warning Non-Market Post Contingency Local Load Relief Warning The purpose of the Post Contingency Local Load Relief Warning
More informationReport prepared by. ENERGY INSTITUTE HRVOJE POŽAR, Zagreb, Croatia EKC, Belgrade, Serbia
BLANK PAGE Report prepared by ENERGY INSTITUTE HRVOJE POŽAR, Zagreb, Croatia EKC, Belgrade, Serbia on behalf of SECI PROJECT GROUP ON REGIONAL TRANSMISSION SYSTEM PLANNING with Support From UNITED STATES
More informationTransmission grid tariffs for 2018
Transmission grid tariffs for 2018 Model description and rates Photo: Statnett Tariffs 2018 Changes in the Energy Act were adopted with effect from 1 July 2016. Among other things, the Act defines changes
More informationThe Electric Power System
Country s flag The Electric Power System - Spain - Spanish Power System 1 Basic facts Area: 505 957 km 2 Population: 46 439 864 (2015) Number of TSOs: 1 Number of DSOs: 336 (source: MINETUR) 28 Mio. consumers
More informationCREG PROPOSAL FOR THE ADAPTATION OF THE CBCO SELECTION METHOD AND THE BASE CASE DEFINITION IN THE CWE FLOW BASED MARKET COUPLING
CREG PROPOSAL FOR THE ADAPTATION OF THE CBCO SELECTION METHOD AND THE BASE CASE DEFINITION IN THE CWE FLOW BASED MARKET COUPLING TABLE OF CONTENT 1 Problem description... 2 2 Scope and objective... 3 3
More informationDevelopment of simultaneous energy and reserve dispatch model and corresponding pricing mechanism. Stefanos Delikaraoglou and Yi Ding
Development of simultaneous energy and reserve dispatch model and corresponding pricing mechanism Stefanos Delikaraoglou and Yi Ding DTU CET March 2012 1. Abstract This study aims to develop a market structure
More informationREVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM Tasks 1 and 2 Report Prepared for
More informationImpact of RES on the ancillary services EPCC 11 th International Workshop, Altea Spain
RED ELÉCTRICA DE Impact of RES on the ancillary services EPCC 11 th International Workshop, Altea Spain May 24th 2011 Abril 2007 Dirección de Operación Index Introduction to RES Impact of RES on the ancillary
More informationSituational Awareness Workshop for Management of Wind and Solar Power
Situational Awareness Workshop for Management of Wind and Solar Power Hosted by Southern Company, Atlanta, Georgia Stephen Lee Senior Technical Executive Power Delivery & Utilization December 10, 2009
More informationAbstract Offshore wind farms are gradually being planned and built farther from the shore. The increased integration
1 Analysis of grid alternatives for North Sea offshore wind farms using a flow-based market model Daniel Huertas-Hernando, Harald G. Svendsen, Leif Warland, Thomas Trötscher and Magnus Korpås Abstract
More informationEast Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria
East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission
More informationLMP Implementation in New England
IEEE PES General Meeting, Montreal Eugene Litvinov June, 2006 2006 ISO New England Inc. 1 New England s Electric Power System 14 million people; 6.5 million households and businesses 350+ generators 8,000+
More informationSwedenergy on Thema's report 'Capacity adequacy in the Nordic Electricity märket'
SVENSK ENERGI - SWEDENERGY - AB Marknad/Märkets Magnus Thorstensson +46-8-677 2806, +46-733 925761 magnus.thorstensson@svenskenergi.se YTTRANDE 1 (5) Datum 2015-08-17 NR 041/2015 Elmarknadsgruppen Nordiska
More informationCalculation of system index - Basic idea. Load model Alternative 2. Thermal power station model. Equivalent load. Example 6.8:
System planning, EG2050 Probabilistic production cost simulation of electricity markets lecture 14 Lennart Söder Professor in Electric Power Systems PPC model Assume Perfect competition Perfect information
More informationList of training courses on electrical power system for Cambodia, Laos, Vietnam and Thailand (CLVT) countries
List of training courses on electrical power system for Cambodia, (Responsible and coordinator : Dr. Tuan Nguyen, t.nguyen@ied-sa.fr) 1. TRAINING COURSE 1 CUSTOMER SERVICE METERING AND BILLING 2. TRAINING
More informationManaging Flexibility in MISO Markets
Managing Flexibility in MISO Markets Clean Energy Regulatory Forum November 9, 2012 Outline Impacts of Variable Generation on Ancillary Services Dispatchable Intermittent Resources Introduction to Proposed
More informationExperience of Nordic Region & Recent Developments in Risk Assessment for Electricity Networks
OSCE Expert Workshop: Sharing Best Practices to Protect Electricity Networks from Natural Disasters Experience of Nordic Region & Recent Developments in Risk Assessment for Electricity Networks Farrokh
More informationThe power market. How the power market functions Power trading Price formation International power trading Electricity output un the Nordic countries
The power market How the power market functions Power trading Price formation International power trading Electricity output un the Nordic countries 7 82 The power supply sector in Norway is regulated
More informationDocument title: Project number Document number Principal contact Ove Brattberg
Environment and Transport Plan Classification Open Statnett SF Divisjon Nettutbygging Husebybakken 28B Postboks 5192 Maj. 0302 OSLO Document title: 420 kv power line Ørskog Fardal; Section Ålfoten - Ørskog
More informationIncreasing renewables share in Turkey s power system
Increasing renewables share in Turkey s power system Options for transmission expansion and flexibility System Reliability in Renewables-driven Power Systems 19 April 2018, Agora Energiewende, Berlin Dr
More informationMarket Simulation Structured Scenarios. Energy Imbalance Market Implementation Arizona Public Service and Puget Sound Energy
Market Simulation Structured s Energy Imbalance Market Implementation Arizona Public Service and Puget Sound Energy Version: 1.1 June 1, 2016 Location of Document Link Revision History Date Version Author
More informationLarge-scale Wind Power Integration and Voltage Stability Limits in Regional Networks
Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Magni Þ. Pálsson, Trond Toftevaag, Member IEEE, Kjetil Uhlen, Member IEEE, John Olav Giæver Tande SINTEF Energy Research
More informationRegulating Power Market (RPM) Review Study
Regulating Power Market (RPM) Review Study High-level Summary Bonn / Oosterbeek 07.10.2013 PURPOSE AND SCOPE OF STUDY ANALYSIS OF CURRENT RPM DESIGN REGARDING ATTRACTIVENESS AND EFFICIENCY ANALYSIS OF
More informationBALANCING CODE NO. 1 (BC1)
Paragraph No/Title BALANCING CODE NO. 1 (BC1) PRE GATE CLOSURE PROCESS CONTENTS (This contents page does not form part of the Grid Code) Page Number BC1.1 INTRODUCTION... 1 BC1.2 OBJECTIVE... 1 BC1.3 SCOPE...
More informationPage 1 of 1. NPCC Methodology and Guidelines for Forecasting TTC and ATC
Page 1 of 1 NPCC Methodology and Guidelines for Forecasting TTC and ATC Page 3 of 3 Table of Contents TABLE OF CONTENTS... 3 1. SUMMARY... 5 2. STATUS OF OPEN ACCESS IN NPCC... 6 3. OBJECTIVE OF THE NPCC
More informationCIGRE Working Group (WG) C4.603: Analytical techniques and tools for power balancing assessments
CIGRE Working Group (WG) C4.603: Analytical techniques and tools for power balancing assessments Main objective: Critical assessment of existing modelling methods and tools for analyzing power balancing
More information2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005
2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability
More informationHalf Hour Gate Closure. Issues & Possible Straw Man Solutions
Half Hour Gate Closure Issues & Possible Straw Man Solutions Half Hour Gate Closure National Grid is starting to look at what system operation and the wider market place looks like in 2015 to 2030 High
More informationNERC Reliability Functional Model
NERC Reliability Functional Model Function Definitions and Responsible Entities Version 3 Approved by Standing Committees: Operating Committee: December 6, 2006 Planning Committee: December 6, 2006 Standards
More informationitesla workshop 22 of August
itesla workshop 22 of August Slide show lia Workshop itesla Paris, 22 of August Grégory Meys lia : Who are we? Belgium high voltage transmission system operator (30kV to 380kV) Operating over 8000 km of
More informationIntegrating Wind Power Efficiently into Electricity Markets Poses New Regulatory Challenges
PSERC Webinar, January 19, 2010 Integrating Wind Power Efficiently into Electricity Markets Poses New Regulatory Challenges Tim Mount Department of Applied Economics and Management Cornell University TDM2@cornell.edu
More informationGeneration Dispatch. PJM State & Member Training Dept. PJM /13/2017
Generation Dispatch PJM State & Member Training Dept. PJM 2017 Objectives Explain the difference between Dispatch Rate and LMP PJM 2017 2 Agenda Generation Dispatch PJM 2017 3 Dispatch Rate Definition:
More informationYi-Hsu Chen The Johns Hopkins University, Baltimore, MD. Fieke A.M. Rijkers Dienst Uitvoering en Toezicht Energie (Dte), Den Haag, NL
Applications of Complementarity-Based Models of Transmission-Constrained Power Markets: B-NL Market Integration & Power-NOx Market Interactions in PJM Yi-Hsu Chen The Johns Hopkins University, Baltimore,
More informationMaster Thesis Department of Electrical Engineering. The Effect of a Short- Circuit Current in a High Voltage Installation With a Synchronous Machine.
44 The Effect of a Short- Circuit Current in a High Voltage Installation With a Synchronous Machine. Background Short circuit in a power plant leads to large short-circuit currents and causes large mechanical
More informationNORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2014
NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2014 27.10.2015 REGIONAL GROUP NORDIC Table of Contents 1 SUMMARY... 3 2 INTRODUCTION AND BACKGROUND... 4 3 SCOPE... 5 4 METHODS, DEFINITIONS
More information2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005
2005 Integrated Electricity Plan Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005 2005 IEP Objectives Means Objectives Ends (Fundamental) Objectives Agenda Items No net imports
More informationThe (future) role of the European DSOs - What can we expect? A German perspective
The (future) role of the European DSOs - What can we expect? A German perspective Energi Norge Workshop The role of the DSOs Dr. Jens Büchner Oslo, 6 th June 2018 E-Bridge Competence in Energy Your partner
More informationIDC Regional Congestion Management Training Plan. Revision 0.9. March 22, 2004
IDC Regional Congestion Management Training Plan Revision 0.9 March 22, 2004 Change Record Version Person Date Change Record 0.0 0.9 IDCWG IDCWG February 12, 2004 March 22, 2004 IDCWG Created Document
More informationCapacity allocation and congestion management. Vivi Mathiesen (Ed.)
Capacity allocation and congestion management Vivi Mathiesen (Ed.) 3 2010 R E P O R T Capacity allocation and congestion management A new model for the power market? Norwegian Water Resources and Energy
More informationDesign Wilmar Planning tool
Overview of presentation Design Wilmar Planning tool Peter Meibom PhD course: Energy System Analysis of Large-scale Wind Power Integration, Ålborg University 4 November Risø s mission is to promote environmentally
More informationAlternative Connection Application and Offer Process Proposal
Alternative Connection Application and Offer Process Proposal Decision Paper 31 May 2016 Table of Contents 1. Executive Summary... 4 2. Introduction... 7 2.1 Purpose of the Paper... 7 2.2 Structure of
More information