Automated Demand Response (ADR) Customer Update. August 29, 2013

Size: px
Start display at page:

Download "Automated Demand Response (ADR) Customer Update. August 29, 2013"

Transcription

1 Automated Demand Response (ADR) Customer Update August 29, Today s Agenda Demand response (what, when, why, how) DR strategies (automated DR, enhanced automation) About PG&E s DR programs [Lunch break and exercise] Overview of PG&E s ADR program Getting started DR Automation Server (DRAS) connection, M&V test Wrap up 2 PGE ADR Customer Training Deck 1

2 Objectives After today s session, you should be able to: Describe the features of PG&E's Automated Demand Response (ADR) program Convey benefits of PG&E s Peak Day Pricing Discuss DR load shed strategies Apply ADR program protocols and procedures 3 Today s Presenters David Wylie, P.E., ASW Engineering Kitty Wang, Senior Project Manager, Energy Solutions 4 PGE ADR Customer Training Deck 2

3 Questions? Comments? Ask any time 5 WECC Transmission Grid 6 PGE ADR Customer Training Deck 3

4 What is Demand Response? 7 Characteristics of Demand Response Actions taken only when requested Involves temporary, uncommon activities Programs are voluntary Typically pays incentives 8 PGE ADR Customer Training Deck 4

5 When Demand Meets Supply 50,000 45,000 Megawatts 40,000 35,000 30,000 25, Hour Beginning Supply Demand Forecast Demand Revised Forecast With DR 9 The relationship between weather conditions, demand, and price of electricity Demand on a mild day Demand on a hot day Price of electricity Price on a mild day Price on a hot day Supply Demand for electricity 10 PGE ADR Customer Training Deck 5

6 Lights Keeping Out: the the Price Lights Reasonable: On: Price Demand Price After After Exceeds Additional Demand Supply Demand Response Response Demand Demand after after additional is greater demand than demand supply response = outage Price of electricity after demand response Price of electricity Price of electricity after additional demand response Supply Price of electricity on a mild day Demand for electricity 11 The Cost of Meeting the Peak 12 PGE ADR Customer Training Deck 6

7 Major Factors Affecting Supply Economy Demography Weather Demand Response Interruptibles Major Factors Affecting Supply Demand Target reserve margin Supply adequacy Supply Operating reserve margin Resource additions and retirements Local generation Generator outage Line outage Fuel availability Net import 13 Efficiency and Demand Energy Efficiency A reduction in kwh throughout the year 8,760 hours Daily Load Shift Actions taken to reduce or shift load during summer on-peak hours (kwh and kw) up to 900 hours during the summer Demand Response Reduce load (kw) when requested during unusual events Occasional, called by the utility; 12 to 60 hours 14 PGE ADR Customer Training Deck 7

8 Integrating EE and DR 15 Integrated Demand Side Management (IDSM) IDSM is identified in the CPUC Strategic Plan as an overarching strategy to promote customer-side energy management and achievement of zero net energy goals Can be: Energy efficiency (EE) Demand response (DR) Distributed generation (DG) 16 PGE ADR Customer Training Deck 8

9 Benefits of DR to Utility Companies Helps system reliability Frees up thousands of MW of power at critical times Promotes smart energy, smart grid Benefits of DR to Environment & Society Reduces use of fuels for generation Reduces power plant emissions; improves air quality Reduces greenhouse gases; less global warming PGE ADR Customer Training Deck 9

10 Benefits of DR to Businesses Reduce peak demand energy costs Lower operating costs increased property value Prepare businesses for dynamic pricing Promote a strong California economy Two Sources of Funds for DR DR load shedding participation revenue stream Technology Incentives (TI) funds help pay for hardware and software that enable ADR DR Programs Technology Incentives 20 PGE ADR Customer Training Deck 10

11 Check Your Understanding Think about the term demand response. It means responding to a utility company request to quickly reduce demand for electricity 21 Check Your Understanding Which of the following is a benefit of demand response programs? Helps ensure grid system reliability Earn financial incentives Help reduce the need for building new power plants All of the above 22 PGE ADR Customer Training Deck 11

12 Check Your Understanding How often does the utility company request that a business reduce load for demand response? On hot days Occasionally Hardly ever Once a week 23 Check Your Understanding In your own words, describe the difference between energy efficiency measures and demand response measures. 24 PGE ADR Customer Training Deck 12

13 2013 Operating Reserve Margins Operating Reserve Margin (%) 25% 20% 15% 10% 5% ISO, SP25, and NP26 Operating Reserve Margins (%) for Summer % 23.3% 21.1% 10.4% 6.2% 7.1% ISO SP26 NP26 3% firm load shedding 0% Normal Scenario Extreme Scenario 25 Summer 2013 Outlook 26 PGE ADR Customer Training Deck 13

14 Worst Case Scenario 27 Summer 2013 DR Programs 28 PGE ADR Customer Training Deck 14

15 2013 CA Generation Fuel Resources Renewables mix NDC = Net Dependable Capacity resources RPS = Renewables Portfolio Standard resources 29 Wind and Solar Power and Demand Response Wind and solar are intermittent and stability is more challenging When renewable resources are down, DR can serve as backup In 2012 California installed 1,656 MW of new wind-power capacity, for a total over 5,540 MW California can generate about 7% of its electricity from wind PGE ADR Customer Training Deck 15

16 DR Strategies Control Methods for Achieving DR Manual A person turns off selected equipment Semi-automated A person initiates a control strategy preprogrammed into the Energy Management System (EMS) Automated (ADR) The EMS initiates the control strategy No human intervention EMS receives a signal from PG&E s Demand Response server 32 PGE ADR Customer Training Deck 16

17 Who the Businesses Are the Big Picture People Buildings Process Facilities 33 Potential Demand Response Loads for People Buildings Cooling tower Air-handling units and ductwork Boiler Pumps Chiller 34 PGE ADR Customer Training Deck 17

18 The Top 10 List 1. Dim lights 2. Global Temperature Adjustment (GTA) 3. Limit chiller 4. Reconfigure chillers 5. Cycle package units 6. Reset static pressure 7. Elevators off 8. Fan VFD speed reduction 9. Pre-cool facility 10. Curtail machinery Lighting Strategies EMS Dim some lighting Turn off 1/4 or 1/3 of the lights Dim or shut off perimeter lighting Lighting Room by room notification Locations Private offices Hallways and corridors Lobby Central plant Mechanical rooms Lighting circuits Loading docks Elevator lobbies Bullpens 36 PGE ADR Customer Training Deck 18

19 Office Building HVAC Strategies Air Conditioning Strategies Package Units Cycle package units [Package unit kw] Global temperature adjustment (GTA) [Package unit kw] Central Plant Type of Air System CAV AHU VAV AHU Chiller Global temperature adjustment (GTA) [Chiller kw] Cycle fans [Fan kw + chiller] Reset leaving air temperature (relax humidity control) [Chiller kw] Global temperature adjustment (GTA) [Fan kw + chiller] Limit fan pressure or speed [Fan kw + chiller] Chiller lineup [Chiller kw] Limit speed if VFD is on the chiller [Chiller kw] Limit amps if inlet guide vanes (IGV) are on the chiller [Chiller kw] Where the kw reduction occurs [ in brackets ] 37 Other Machinery Vertical transportation Elevators Escalators Misc. Motors and other loads Manual EMS Pumps Fountains Swimming pools Spas Domestic hot water Fans General exhaust Elevator room Garage exhaust Misc. Machinery Vending machines Laundry room Drinking fountains 38 PGE ADR Customer Training Deck 19

20 DR Strategies: Office Buildings 39 DR Strategies: Hotels and Motels 40 PGE ADR Customer Training Deck 20

21 DR Strategies: Hospitals and Medical Office Buildings 41 DR Strategies: Retail Industry 42 PGE ADR Customer Training Deck 21

22 DR Strategies: Grocery Stores and Supermarkets 43 DR Strategies: Schools 44 PGE ADR Customer Training Deck 22

23 DR Strategies: Manufacturing & Process Facilities 45 DR Strategies: Injection Molding 46 PGE ADR Customer Training Deck 23

24 DR Strategies: Cold Storage & Food Processing 47 DR Strategies: Agricultural & Muni Water Pumping 48 PGE ADR Customer Training Deck 24

25 Focus on Automated Demand Response (ADR) Manual A person turns off selected equipment Semi-automated A person initiates a control strategy preprogrammed into the Energy Management System (EMS) Automated (ADR) The EMS initiates the control strategy No human intervention EMS receives a signal from PG&E s Demand Response server 49 How Does ADR Work? Grid Operator Utility Co. DR Automation Server Communication Pathway or Internet Gateway Business EMS HVAC Lighting Machines ADR enables demand response strategies automatically, without the need for human intervention. 50 PGE ADR Customer Training Deck 25

26 Enhanced Automation Monitoring Weather forecast Dynamic energy/ demand prices Meter information Demand response communication Lighting Occupancy levels HVAC Lighting levels HVAC CO2 Air/water temperature Air/water flow Thermostat setpoints Enhanced Automation EIS EMS Energy Information Systems and Energy Management Systems Controls Lighting Dimmable ballasts Bi-level lighting HVAC Lighting VSDs Ventilation HVAC Thermostat reset Other Chilled water temp. Other Demand limiting Thermal storage Demand response 51 Benefits of Auto-DR Efficiency: Smart, strategic management of energy use helps maximize savings Flexibility: Customers set and always control their own level of Auto-DR participation Ease: Auto-DR makes reducing energy usage automatic PGE ADR Customer Training Deck 26

27 Calculating Load Reductions Calculating Load Reduction What is the DR strategy? What are we calculating? What data? What formulas? 54 PGE ADR Customer Training Deck 27

28 The Nature of Baselines Estimate building load on non-dr days Used to calculate load reduction One baseline methodology does not fit all Baselines are important for: Settlement Resource planning Cost-effectiveness evaluation 55 Important Baselines Customer Specific Summer Baseline (CSSB) Customer Specific Energy Baseline (CSEB) (10-Day Baseline) Day-of Adjustments (calibration) Calibrates the 10-day to the test day 56 PGE ADR Customer Training Deck 28

29 CSSB Example Data Table A: Summer Monthly Average Daily Maximum Demand Month HE 1:00 p.m. HE 2:00 p.m. HE 3:00 p.m. HE 4:00 p.m. HE 5:00 p.m. HE 6:00 p.m. June July August September AVERAGE Example of CSEB Using 10-Day Baseline Methodology Assumes customer agrees to curtail 500 kw per hour from noon - 8:00 p.m. on Friday, August 19 Date Day of Week Day No. Calculation of the 10-day rolling average. HE 1:00 pm HE 2:00 pm HE 3:00 pm HE 4:00 pm HE 5:00 pm HE 6:00 pm HE 7:00 pm HE 8:00 pm Total 8/3 Wed Day 1 1,500 1,300 1,200 1, ,550 8/4 Thur Day 2 1,600 1,400 1, ,700 8/5 Fri Day 3 1,800 1,500 1,100 1, ,200 1,200 1,200 10,300 8/8 Mon Day 4 1,700 1,600 1,200 1, ,520 1,520 1,520 10,910 8/9 Tue Interruption N/A N/A N/A N/A N/A N/A N/A N/A 0 8/10 Wed Day 5 1,300 1,750 1,300 1, ,450 1,450 1,450 10,825 8/11 Thur Day 6 1,400 1,350 1,400 1,500 1,650 1,600 1,600 1,600 12,100 8/12 Fri Interruption N/A N/A N/A N/A N/A N/A N/A N/A 0 8/15 Mon Day 7 1,300 1,150 1,600 1,600 1,800 1,800 1,800 1,800 12,850 8/16 Tue Day 8 1,400 1,200 1,750 1,700 2,000 1,200 1,200 1,200 11,650 8/17 Wed Day 9 1,600 1,500 1,900 1, ,850 1,850 1,850 13,150 8/18 Thur Day 10 1,800 1,600 1,100 1, ,800 1,800 1,800 12,550 Total 15,400 14,350 13,550 14,750 10,675 13,620 13,620 13, day average 1,540 1,435 1,355 1,475 1,068 1,362 1,362 1,362 HE = Hour Ending 58 PGE ADR Customer Training Deck 29

30 10-Day Baseline with Day-of Adjustment 10-Day Baseline 10-Day Baseline Adjusted 59 Calculating Load Reduction Involves: Identifying feasible measures for DR Establishing an energy-use baseline for each DR measure Calculating the potential load reduction based on accepted engineering analysis 60 PGE ADR Customer Training Deck 30

31 Estimate of Demand Reduction When suggesting DR measures, they must adhere to all statutes, regulations, and standards (OSHA, EPA, etc.) Safety first! Consider health, comfort, productivity Use common sense, and be pragmatic! Needs to be sustainable for the facility 61 Check Your Understanding Name some of the most popular DR strategies for lighting Dim some lighting Turn off 1/4 or 1/3 of the lights Dim or shut off perimeter lighting 62 PGE ADR Customer Training Deck 31

32 Check Your Understanding Name some of the most popular DRstrategies for air conditioning Increase space temperature (such as GTA) Make chiller plant adjustments (e.g., reset CHW temperature, limit cooling valve, limit chiller demand) Cycle package units Pre-cool the building 63 Check Your Understanding Name and discuss a couple of DR strategies for constant air volume (CAV) systems Cycle fans Ventilation control (outside air flow) Increase supply air temperature (use with caution) 64 PGE ADR Customer Training Deck 32

33 Check Your Understanding Name and discuss a couple of DR strategies for variable air volume (VAV) systems Reset duct static pressure on fans in VAV HVAC systems Limit fan speed (set CFM /RPM limits) Ventilation control 65 Check Your Understanding Is installing dimming ballasts considered demand response? Maybe. By itself, installing dimming ballasts is not demand response. However, if the dimming ballasts are used to reduce lighting during a called event then it could be demand response. 66 PGE ADR Customer Training Deck 33

34 PG&E s DR Programs Two Sources of Funds for DR DR load shedding participation revenue stream Technology Incentives (TI) funds help pay for hardware and software that enable ADR DR Programs Technology Incentives 68 PGE ADR Customer Training Deck 34

35 DR Load-Shedding Programs Capacity Bidding Program (CBP) Demand Bidding Program (DBP) Aggregator Managed Portfolio (AMP) Peak Day Pricing (PDP) These are the qualifying programs for Technology Incentives 69 Capacity Bidding Program (CBP) May to October, event-based program 11 am 7 pm Monday thru Friday (non-holiday) Bid is placed prior to the beginning of the month Events can be scheduled day-ahead or day-of Two incentive options based on day-ahead or day-of Must enroll with or as third-party aggregator 70 PGE ADR Customer Training Deck 35

36 Demand Bidding Program (DBP) Low-risk, day-ahead DR program Voluntary year-round Internet-based bidding program Can submit load reduction bids on an hourly basis for any event Minimum load reduction 10 kw for two consecutive hours Must have 15-minute interval meter or SmartMeter Eligible for bill credits for reductions from 50% to 150% of bid amount 71 Aggregator Managed Portfolio (AMP) Customers enroll directly with selected DR service providers (aggregators) Individual contracts meet customer s needs See PG&E DR webpage for participating aggregators 72 PGE ADR Customer Training Deck 36

37 Peak Day Pricing (PDP) Smaller accounts receive a discount on all part and on-peak usage on all non-event days of the year Larger accounts get Summer demand (kw) credit Higher usage (kwh) charge during event hours 2 pm 6 pm Monday thru Friday (non-holiday) 12 pm to 6 pm Monday thru Friday for some accounts (see tariff) May 1 thru October 31 9 to 15 events annually 73 Peak Day Pricing (PDP) PGE ADR Customer Training Deck 37

38 Peak Day Pricing Advantages Bill protection lets customers participate risk-free for the first year Maximum potential cost savings Credit if PDP exceeds time-of-use pricing PDP Capacity Reservation Level PGE ADR Customer Training Deck 38

39 InterAct What-If Analysis of Peak Day Pricing (PDP) Participation An average big box store with a peak demand of 238 kw and an average demand of 120 kw during 2012 Energy costs of approximately $142,000 per year 250 Two Weeks of Summer Demand Demand (kw) Two Weeks 77 PDP Participation and Incentive 20% load shed ~ 43 kw for this user ADR incentive would be $8,600 at $200 per kw % Load Shed on Event Day Energy Use (kwh) Midnight to Midnight 78 PGE ADR Customer Training Deck 39

40 Impacts of Switching to PDP Rate Impacts on the utility bill by switching from E-19S rate to E-19S PDP rate Rate Option and Scenario Total Annual Energy Charges Difference from E-19S % Savings for the year Current Rate E-19S $ 142,677 $0 0% Enroll in PDP E-19S PDP $ 142,728 $51 more - 0.1% Participate in 12 DR events E-19S PDP with 20% Load Shed $ 140,605 $2,072* 1.5% Estimated total savings from participating between 9 and 15 PDP events per year 9 Events = $2, Events = $2,072* 15 Events = $1,698 *Assumes Capacity Reservation Level is optimized at 54% of peak. CRL for E-19S current rate and E-19S rate with PDP were also adjusted to increase savings. 79 Lunchtime Exercise PGE ADR Customer Training Deck 40

41 Office - Hourly Demand During Peak Summer Day 81 Office Average On Peak Demand Frequency Distribution 82 PGE ADR Customer Training Deck 41

42 Office - Customer Specific Summer Baseline (CSSB) 83 PG&E s ADR Program PGE ADR Customer Training Deck 42

43 Two Sources of Funds for DR DR load shedding participation revenue stream Technology Incentives (TI) funds help pay for hardware and software that enable ADR DR Programs Technology Incentives 85 Technology Incentives (TI) Funds Auto-DR enables DR programs by reducing electricity usage during period of peak demand without manual intervention Technology incentives (TI) are available for purchasing and installing qualifying DR-enabling equipment, such as EMS or other automated control systems PGE ADR Customer Training Deck 43

44 Introduction to PG&E s ADR Program Objective enable customers to reduce energy usage during times of peak demand with demand response $15.5 million in incentives Program MW goals: 72 MW 7 MW reserved for Advanced Technologies Program runs from September 2012 through December 2014 Provides incentives and technical assistance for medium to large nonresidential customers to install program equipment 87 Intro to PG&E s ADR Program (continued) Program implementers: Energy Solutions ASW Engineering Demand Response Research Center (DRRC) at Lawrence Berkeley National Laboratory (LBNL) Akuacom 88 PGE ADR Customer Training Deck 44

45 PG&E s ADR Program Website A resource for: Program load reduction MW goal and achievement to date Incentive funds available Announcements, and more 89 Program Status The total incentive funding is $15.5 million Currently, the program has $6.08 million available not yet reserved to projects. Of the remaining approximate $6 million, $4.4 million is budgeted for ADR projects for the PDP program. There is approximately $1.1 million allocated for advanced technology ADR projects, and $225,000 for conventional ADR projects in the other eligible DR programs 90 PGE ADR Customer Training Deck 45

46 DR Program Incentive Budget Demand Response Program Incentive Cap* Peak Day Pricing $4,865,000 Aggregator Managed Portfolio (AMP) $3,023,000 Capacity Bidding Program (CBP) $1,511,640 Demand Bidding Program (DBP) $2,000,000 *Updated on 7/10/13 and based on projects under review 91 ADR Program Incentive Availability by Technology Classification Demand Response Program Standard ADR Funding Available* Advanced Tech ADR Funding Available* ADR Funding Available* Peak Day Pricing $3,525,463 $896,716 $4,422,179 Aggregator Managed Portfolio (AMP) $0 $384,856 $384,856 Capacity Bidding Program (CBP) $203,160 $0 $203,160 ADR + Energy Efficiency Projects $1,070,345 Same Cap $1,070,345 Demand Bidding Program (DBP) $24,200 $0 $24,200 * As of 7/10/13 Current values found at: 92 PGE ADR Customer Training Deck 46

47 Program Timeline Program ends December 2014, but projects need to be installed by October 31, 2014 in order to receive incentives. To meet this timeline send in your applications, project proposals, and audit reports by January /31/2014 8/29/2013 (TODAY) Recruit & enroll 1/31/2014 Applications received 5/30/2014 Applications approved Projects installed by this date to be eligible for ADR incentives About 4.5 months 93 Why Consider ADR Incentives Now? It available Use it to add or upgrade facility controls, which benefits both customer and utility Incentives could decrease or disappear as the norm changes: Title 24 standards requirements Smart grid and advanced metering infrastructure Time varying rates (e.g., Peak Day Pricing) 94 PGE ADR Customer Training Deck 47

48 ADR Incentives are Win-Win for customers and the utilities Technology Incentives funds can be used for a variety of enabling technologies Thermostats Lighting control panels Monitoring energy use Title 24 Code Requirements for DR Lighting DR controls for buildings larger than 10,000 square feet, must be capable of lowering lighting by at least 15% HVAC DR controls requires Occupant Controlled Smart Thermostats (OCST); capable of remotely using EMS to increase cooling temperature by 4 degrees or more As DR capable lighting and HVAC controls become baseline requirements in code, they become ineligible for incentives 96 PGE ADR Customer Training Deck 48

49 ADR Eligibility Requirements Requirements to be eligible for ADR program incentives: Non residential customer Electric services from PG&E Interval meter installed Existing account with 24 months billing and usage data Enrolled or eligible to enroll in PG&E DR programs Project is new equipment that provides incremental kw and kwh reductions New equipment or systems not already installed Eligible customers can apply for technology incentives for semi-adr or ADR. 97 Items Not Covered by ADR Incentives Measures that are not covered by ADR incentives include: Metering Distributed generation Permanent load shifting technologies Cameras Solar Software licenses Ongoing maintenance Cloud-based controls Thermal energy storage 98 PGE ADR Customer Training Deck 49

50 ADR Program Incentive Limits Incentive Limits by Demand Response Program Incentive Limits by Technology Category Demand Response Program* ADR Funding Available DBP $2,000,000 CBP $1,511,640 PDP $4,865,000 AMP $3,023,000 PDP Peak Day Pricing AMP Aggregator Managed Portfolio CBP Capacity Bidding Program DBP Demand Bidding Program Technology Category Percent of Incentive Budget Lighting No Cap Non-Advanced HVAC 40% Other Non-Advanced 63% Process 50% Pumping 40% Electric Vehicles and Electric 30% Charging ADR Program Uses Tiered Incentive Structure to Promote Advanced Technologies Technology Category Incentive Rate ($/dispatchable kw) Semi Automated Demand Response $125 Automated Demand Response $200 Advanced Technology HVAC $350 Advanced Technology Lighting $400 Incentive calculation based on dispatchable kw according to the committed load reduction strategy Incentives capped at 100 percent of total project cost: Equipment and installation Construction/project management Sales tax PGE ADR Customer Training Deck 50

51 Additional ADR Program Information Remain on initial DR program for 1 year Remain on any DR program for 3 years Target date for applications before Jan 31, 2014 Projects completed by Oct,31, 2014 Open ADR 2.0b certification Semi-ADR customers must also implement an EE measure 101 Incentives Are Paid In Two Installments 1st installment: 60% after verification of equipment installation and testing of DR strategies 2nd installment: 40% is paid after verification of participant performance PGE ADR Customer Training Deck 51

52 About OpenADR Open Automated Demand Response (OpenADR) An open and standardized protocol Used by electricity providers and system operators to communicate DR signals The standard used by all major CA utilities, including PG&E A common language used over any existing IP-based communications network, such as the Internet The OpenADR Alliance fosters the development, adoption, and compliance of the OpenADR Smart Grid standard 103 What is Advanced Technology? Meets standard ADR eligibility and considered case-by-case Inclusion in a California Emerging Technologies Coordination Council (CA ETCC) DR evaluation Inclusion other recent advanced technology evaluation Wireless or real-time two-way communication within the facility Granularity of control to fixture, zone, or thermostat level Granularity of data reporting and sensing Technologies in early stages of adoption are preferred 104 PGE ADR Customer Training Deck 52

53 Approved Vendors for Advanced Technologies HVAC/R Cypress Envirosystems wireless pneumatic thermostat REGEN Energy wireless devices Lighting Daintree Networks networked, wireless control platform for smart buildings, wireless lighting controls Enlighted, Inc. energy solutions for lighting, HVAC, and data analytics 105 Integrated Demand Side Management (IDSM) IDSM funds: $1.07 million incentives remaining Eligible EE measure is any measure that qualifies for a PG&E EE program incentive Open to new DR customers (not in a DR program for past 12 months) PDP, CBP, DBP only (DBP can be currently enrolled but not participated in last 12 months) Installed at the same site as the ADR measure 106 PGE ADR Customer Training Deck 53

54 Getting Started with PG&E s ADR Program Fill out the 2013 ADR Application 107 CISR Form Customer Information Standard Request (CISR) form Gives a utility account owner s permission to the utility company to release confidential energy usage data to a third party 108 PGE ADR Customer Training Deck 54

55 ADR Project Lifecycle Engineering audit and project application Audit and application review Project installation Installation review and testing First installment payment for 60% of total incentive DR season performance Performance period evaluation Second installment payment up to 40% of total incentive 109 DRAS Connectivity PGE ADR Customer Training Deck 55

56 What is the DRAS? Demand Response Automation Server (DRAS) Automates the interactions between the utilities and their customers for DR programs 111 Customers with Aggregators Utility 112 PGE ADR Customer Training Deck 56

57 Why a DRAS Client Technician (DCT)? ADR may be challenging to implement ADR needs a project facilitator The DCT knows all aspects of the project DCT is project champion and facilitates installation 113 DCT Roles and Responsibilities The DCT: Acts as liaison between facilities and vendors Enables participation in ADR program Provides site support during the entire process Serves as a technical resource coordinates the technical activities required to automate DR load shed at facility sites 114 PGE ADR Customer Training Deck 57

58 Flow Chart: DCT Role / Responsibility Technical Audit (TA) completed; ADR Requested Utility approves potential ADR measures Customer proceeds by reserving Technology Incentive (TI) funds DCT facilitates the project: 1) Reviews steps to enable ADR at customer s site 2) Meets with customer on-site 3) Helps select contractors (if applicable) 4) Prepares scope of work for the site 5) Sets up site on Utility s DRAS 6) Coordinates and manages site work 7) Tests installed ADR system 8) Trains customer on ADR and DRAS 9) Completes DCT verification documents 10) Coordinates formal Utility Verification Test 11) Provides any necessary technical support Utility performs final verification test Customer receives initial 60% payment Utility monitors participation in first DR season Customer receives remaining 40% payment 115 Getting Started in the DRAS If a customer needs to opt-out of a single event they should: Log into the DRAS Click the Events tab Click the Opt-out button This will only be visible if there is an event initiated. Once the Opt-out button has been utilized the event will disappear from the customer interface. 116 PGE ADR Customer Training Deck 58

59 M&V Testing Measure & Verification Test The M&V Test validates the incentive payment M&V test signals are initiated through the DRAS The DRAS client must be online 48 hours prior to the test 118 PGE ADR Customer Training Deck 59

60 Verification Test Scheduling Test Day Schedule a test with site (or vendor) and DCT Site can select date and time Program staff can recommend a time for testing Starts at the site minutes before initiation Verifies installed equipment Witnesses initiation of ADR measures 119 Utility Verification Example #1 Office Building 120 PGE ADR Customer Training Deck 60

61 Utility Verification Example #1 Office Building (continued) Honeywell Jace Client KYZ Pulses for building load 121 Utility Verification Example #1 Office Building (continued) Communications Links EMS Connections 122 PGE ADR Customer Training Deck 61

62 Utility Verification Example #1 Office Building (continued) 123 Utility Verification Example #1 Office Building (continued) 124 PGE ADR Customer Training Deck 62

63 Utility Verification Example #1 Office Building (continued) Pre-Event System Status 125 Utility Verification Example #1 Office Building (continued) Event System Status 126 PGE ADR Customer Training Deck 63

64 Utility Verification Example #1 Office Building (continued) 127 Utility Verification Example #1 Office Building (continued) Pre-Event Fan Status Event Fan Status (ramping down) 128 PGE ADR Customer Training Deck 64

65 Utility Verification Example #1 Office Building (continued) 129 Utility Verification Example #1 Office Building (continued) Pre-Event Status Event Status An apparent 120 kw reduction from the building power readout 130 PGE ADR Customer Training Deck 65

66 Utility Verification Example #1 Office Building (continued) Elevator Curtailment Measure Pre-Event Status Event Status 131 Utility Verification Example #1 Office Building (continued) Corridor Lighting Curtailment Measure Pre-Event Status Event Status 132 PGE ADR Customer Training Deck 66

67 Results Office Building CSSB vs RTE Load Shed = kw kw :00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM Time (Hour Ending) CSSB RTE 600 Adjusted 10 in 10 vs RTE Load Shed = kw kw L :00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM Time (Hour Ending) 1:00 PM2:00 PM3:00 PM4:00 PM5:00 PM6:00 PM7:00 PM8:00 PM Adjusted 10 in 10 RTE 133 Resources Incentives, contact Energy Solutions pge-adr@energy-solution.com Phone: (510) PG&E ADR Website: OpenADR Alliance: Certified devices: PGE ADR Customer Training Deck 67

68 Questions and Comments What questions do you have about Automated Demand Response? What questions do you have about PG&E s PDP program? How do you think you can implement DR at your facility? What ideas do you have for making this work? 135 PGE ADR Customer Training Deck 68

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering Demand Response 2015 Association of Energy Engineers Presenter: David Wylie, P.E. ASWB Engineering National Energy Peak Leveling Program 1977 2 National Energy Peak Leveling Program 1977 3 When Demand

More information

PG&E ADR Incentive Program

PG&E ADR Incentive Program PG&E ADR Incentive Program SVLG Energy Committee 9/25/2014 "PG&E" refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. 2014 Pacific Gas and Electric Company. All rights reserved.

More information

PG&E Automated Demand Response (ADR) Incentives

PG&E Automated Demand Response (ADR) Incentives PG&E Automated Demand Response (ADR) Incentives for Ag Irrigation Pumps Last Updated June 2016 "PG&E" refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. 2016 Pacific Gas and

More information

Working Together to Manage Your Company s Energy Use.

Working Together to Manage Your Company s Energy Use. Energy for What s Ahead SM Working Together to Manage Your Company s Energy Use. Take advantage of one or more of our Demand Response (DR) programs to help lower your energy costs when you actively reduce

More information

PG&E Automated Demand Response (ADR) Incentives

PG&E Automated Demand Response (ADR) Incentives PG&E Automated Demand Response (ADR) Incentives for Ag Irrigation Pumps Last Updated April 2018 "PG&E" refers to Pacific Gas and Electric Company, a subsidiary of PG&E Corporation. 2016 Pacific Gas and

More information

Three Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response

Three Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response Three Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response Yifu Shi Kelly Guiberteau Carlos Yagua, P.E. James Watt, P.E. Energy Systems Laboratory,

More information

The Demand Response Automation Server (DRAS)

The Demand Response Automation Server (DRAS) The Demand Response Automation Server (DRAS) Ed Koch CTO Akuacom Agenda Definition and history of Open Automated Demand Response (OpenADR) concept Empirical results from Automated Demand Response in CA

More information

Demand Response on a. Randy Palombi General Manager CPower, Inc.

Demand Response on a. Randy Palombi General Manager CPower, Inc. Demand Response on a Communications Enabled Grid Randy Palombi General Manager CPower, Inc. What we will cover 1. What is a Smart Grid? 2. What is Demand Response? 3. How does a Smart Grid enable Demand

More information

Section 2: Estimating Energy Savings and Incentives

Section 2: Estimating Energy Savings and Incentives Section 2: Estimating Energy and Incentives 2.1 Estimating Energy and Incentives... 2 2.2 Customized Measures - Estimation Software... 2 2.2.1 AC&R I - High Efficiency Chiller... 4 2.2.2 AC&R I - Split/Packaged

More information

Demand as an Active Actor Day 2, Item 1. Presented by: Flora Flygt XM Medellin, Columbia December 12-13, 2012

Demand as an Active Actor Day 2, Item 1. Presented by: Flora Flygt XM Medellin, Columbia December 12-13, 2012 Demand as an Active Actor Day 2, Item 1 Presented by: Flora Flygt XM Medellin, Columbia December 12-13, 2012 1 Outline Introduction Demand Response Continuum Passive Demand Response Active Demand Response

More information

Open Automated Demand Response

Open Automated Demand Response Open Automated Demand Response Communications Standard Workshop Mary Ann Piette Demand Response Research Center Lawrence Berkeley National Laboratory http://drrc.lbl.gov/ Introduction to OpenADR Agenda

More information

Energy for What s Ahead. Automated Demand Response Technology Incentives 2017 Program Guidelines

Energy for What s Ahead. Automated Demand Response Technology Incentives 2017 Program Guidelines Energy for What s Ahead Automated Demand Response Technology Incentives 2017 Program Guidelines Table of contents 1. Introduction 3 2. Automated Demand Response (Auto-DR) Overview 4 2.1 Auto-DR Programs

More information

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions Strategies for Persistence: Measurement and Verification Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The

More information

design brief energydesignresources Summary CONTENTS

design brief energydesignresources Summary CONTENTS energydesignresources design brief Integrating Demand Responsive Capabilities Into Facility Design Summary Demand response (DR) is an energy management strategy that allows electricity consumers to receive

More information

Load Shift Working Group. https://gridworks.org/initiatives/load-shift-working-group/

Load Shift Working Group. https://gridworks.org/initiatives/load-shift-working-group/ Load Shift Working Group APRIL 18 10AM 2PM PST CPUC GOLDEN GATE ROOM https://gridworks.org/initiatives/load-shift-working-group/ Agenda 10:00 10:20am: Intro and Purpose (Gridworks) 10:20 12:00pm: Grid

More information

Matt Gudorf UCI Energy Manager

Matt Gudorf UCI Energy Manager Matt Gudorf UCI Energy Manager UNIVERSITY OF CALIFORNIA, IRVINE Comprehensive research university 22,216 Undergraduate Students $330 million sponsored research 27 lab buildings operating 24/7 ~7.5 Million

More information

Introduction. The 3 Cost Drivers of Energy

Introduction. The 3 Cost Drivers of Energy Introduction With most commodities, value is determined by two key factors: price and quantity. But when it comes to energy, a third component time plays a big role. When you use energy is just as important

More information

Capacity Performance Training. June 24, 2015

Capacity Performance Training. June 24, 2015 Capacity Performance Training June 24, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems

New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems WHITE PAPER Abstract Grid power demand peaks and increasing supply/ demand inbalances create management

More information

D DAVID PUBLISHING. Optimizing Thermal Energy Storage Systems in the Hospitality Industry. 1. Introduction

D DAVID PUBLISHING. Optimizing Thermal Energy Storage Systems in the Hospitality Industry. 1. Introduction Journal of Energy and Power Engineering 8 (2014) 1991-2000 D DAVID PUBLISHING Optimizing Thermal Energy Storage Systems in the Hospitality Industry Patrick Wilkinson, Jesse Oshiro, Dean Perry and Helen

More information

Custom Application 2018 Retrofit Program

Custom Application 2018 Retrofit Program The Retrofit Program is designed for Commercial and Industrial (C&I) customers to help replace aging and inefficient equipment and systems with more energy efficient technologies. Tailored to a customer's

More information

PJM Demand Response Spring /6/17

PJM Demand Response Spring /6/17 PJM Demand Response Spring 2017 4/6/17 Discussion Topics CPower Introduction (Curtailment Service Provider Role) Demand Response Overview PJM Capacity Market Demand Response Program Capacity Based Program

More information

Participation through Automation: Fully Automated Critical Peak Pricing in Commercial Buildings

Participation through Automation: Fully Automated Critical Peak Pricing in Commercial Buildings Participation through Automation: Fully Automated Critical Peak Pricing in Commercial Buildings Mary Ann Piette, David Watson, Naoya Motegi, Sila Kiliccote Lawrence Berkeley National Laboratory Eric Linkugel,

More information

Permanent Load Shifting Program

Permanent Load Shifting Program 1. Program Description Permanent Load Shifting (PLS) can help reduce system peak load by storing energy produced during off-peak period and shifting electricity use from on-peak to off-peak periods on

More information

PG&E s General Comments on Demand Response Vision Update. January 11, 2008

PG&E s General Comments on Demand Response Vision Update. January 11, 2008 PG&E s General Comments on Demand Response Vision Update January 11, 2008 This document provides PG&E s comments on the draft California Demand Response: A Vision of the Future. The comments are divided

More information

CUSTOMER FACILITY INFORMATION

CUSTOMER FACILITY INFORMATION This Project Information Form provides a template to collect project systems and equipment information and specifications. In addition, this form serves as a general overview of eligibility criteria for

More information

Energy Efficiency in RPM. Adam Keech Director, Market Operations PJM January 13, 2015

Energy Efficiency in RPM. Adam Keech Director, Market Operations PJM January 13, 2015 Energy Efficiency in RPM Adam Keech Director, Market Operations PJM January 13, 2015 PJM Capacity Market PJM Capacity Market Reliability Pricing Model (RPM) PJM secures capacity on behalf of LSEs to satisfy

More information

Critical Peak Pricing Rate Options

Critical Peak Pricing Rate Options Critical Peak Pricing Rate Options (CPP) Questions and Answers PROGRAM OVERVIEW Southern California Edison s (SCE) Critical Peak Pricing (CPP) rate options may benefit commercial and industrial customers

More information

2012 Statewide Load Impact Evaluation of California Aggregator Demand Response Programs Volume 1: Ex post and Ex ante Load Impacts

2012 Statewide Load Impact Evaluation of California Aggregator Demand Response Programs Volume 1: Ex post and Ex ante Load Impacts 2012 Statewide Evaluation of California Aggregator Demand Response Programs Volume 1: Ex post and Ex ante s CALMAC Study ID PGE0318.01 Steven D. Braithwait Daniel G. Hansen David A. Armstrong April 1,

More information

Demand Response in California THE AGGREGATOR MANAGED PORTFOLIO

Demand Response in California THE AGGREGATOR MANAGED PORTFOLIO Demand Response in California THE AGGREGATOR MANAGED PORTFOLIO When it comes to evolving the way we produce and consume energy to preserve our environment for future generations, California is a beacon

More information

Energy Imbalance Market Overview

Energy Imbalance Market Overview Energy Imbalance Market Overview Presentation to: Portland General Electric EIM OATT Stakeholder Meeting David Timson Account Manager CAISO Strategic Alliances October 14, 2016 Topics for Discussion ISO

More information

ISO New England 2003 Demand Response Programs

ISO New England 2003 Demand Response Programs ISO New England 2003 Demand Response Programs Presented at: National Accounts Demand Response Seminar August 19, 2003 Bob Laurita Sr. Program Administrator, Demand Response ISO New England, Inc. New England

More information

NSPM Rate Design Pilot

NSPM Rate Design Pilot NSPM Rate Design Pilot Stakeholder Meeting May 5, 2017 Agenda and Purpose Agenda Introduction of MN Pilot Development A. Liberkowski Concept and Goals Pilot Development Timeline MN Time of Use Rate Option

More information

Reducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE

Reducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE Reducing Hospital Energy Use and Maintaining Savings Glen Anderson, PE AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing

More information

Every building needs an Energy Efficiency Platform.

Every building needs an Energy Efficiency Platform. Every building needs an Energy Efficiency Platform. Persistent commissioning Rule-based controls Advanced analytics Cut energy costs Reduced downtime Optimize energy usage Other Systems Monitor Manage

More information

Centre for Addiction and Mental Health Queen Street Campus Energy Conservation and Demand Management Plan

Centre for Addiction and Mental Health Queen Street Campus Energy Conservation and Demand Management Plan Centre for Addiction and Mental Health Queen Street Campus Energy Conservation and Demand Management Plan In Transition to Sustainable Infrastructure The Centre for Addiction and Mental Health is in the

More information

The OpenADR Primer. An introduction to Automated Demand Response and the OpenADR Standard

The OpenADR Primer. An introduction to Automated Demand Response and the OpenADR Standard The OpenADR Primer An introduction to Automated Demand Response and the OpenADR Standard OpenADR Alliance! +1 408-778-8370! info@openadr.org! www.openadr.org Executive Summary Demand Response (DR) is the

More information

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available?

Customer Benefits. Why Energy Efficiency? Consumers Energy Business Solutions. What Business Solutions Incentives Are Available? Why an Energy Efficiency Program? Business Solutions Energy Efficiency Incentive Program MPSC 21st Century Electric Energy Plan More electricity is needed as soon as practicable. One way of achieving this

More information

Into The Future. Lon W. House, Ph.D ACWA Spring Conference. May 5, 2005 San Jose, CA

Into The Future. Lon W. House, Ph.D ACWA Spring Conference. May 5, 2005 San Jose, CA Into The Future Lon W. House, Ph.D. 530.676.8956 www.waterandenergyconsulting.com ACWA Spring Conference May 5, 2005 San Jose, CA ACWA IEPR Policy Recommendations Generation General - allow aggregation

More information

Demand Response in California The Demand Response Auction Mechanism

Demand Response in California The Demand Response Auction Mechanism Demand Response in California The Demand Response Auction Mechanism When it comes to evolving the way we produce and consume energy to preserve our environment for future generations, California is a beacon

More information

Resource planning and operational requirements for the advanced grid: Demand Response Potential Studies

Resource planning and operational requirements for the advanced grid: Demand Response Potential Studies Resource planning and operational requirements for the advanced grid: Demand Response Potential Studies NASEO EMAP Workshop Presented to the Nevada Governor s Office of Energy Jennifer Potter, Senior Scientific

More information

Case Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency

Case Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency Case Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency Summary Major Fortune 500 Telecom Company Estimated 40% the corporate building portfolio still use pneumatic thermostats

More information

Roundtable I: Energy Markets: The Rise of Community and Institutional Scale Resources

Roundtable I: Energy Markets: The Rise of Community and Institutional Scale Resources Roundtable I: Energy Markets: The Rise of Community and Institutional Scale Resources The Descent of Competition & Ascent of Dynamic Resources Christopher B. Berendt Energy & Sustainability Team Competition

More information

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc. How LEED & The Retro-Commissioning Credits Produce Energy Savings James Vallort Vice President Environmental Systems Design, Inc. Retro-Commissioning Today s session will focus on the following items:

More information

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business FirstEnergy s Pennsylvania Utilities Energy Efficiency Programs for Business 2018 TODAY S AGENDA Introduction to Sodexo Summary of Pennsylvania Act 129 Overview of program website Overview of Application

More information

CHAPTER 6 - Load Forecast & Resource Plan

CHAPTER 6 - Load Forecast & Resource Plan CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching

More information

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144 Demand Response Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Demand Response Module Objectives Upon completion of

More information

Moving on Up(stream) with Automated Demand Response Technologies

Moving on Up(stream) with Automated Demand Response Technologies Moving on Up(stream) with Automated Demand Response Technologies Kitty Wang, Energy Solutions 1 Mark Martinez, Southern California Edison ABSTRACT While the upstream incentive program model is not new,

More information

Opportunities for Demand Response in the National Electricity Market

Opportunities for Demand Response in the National Electricity Market Opportunities for Demand Response in the National Electricity Market Dr David Crossley Managing Director Energy Futures Australia Pty Ltd Embedded Generation and Demand Side Responses Seminar Sydney, 27

More information

PowerDirect Automated Demand Response Pilot Program and Demand Response Overview

PowerDirect Automated Demand Response Pilot Program and Demand Response Overview PowerDirect Automated Demand Response Pilot Program and Demand Response Overview Harlan Coomes Principal Engineer Powering forward. Together. What is Demand Response? Demand Response is a change in customer

More information

2016 Fall Reliability Conference MRO

2016 Fall Reliability Conference MRO 2016 Fall Reliability Conference MRO CAISO s Coordination, Tracking, and Monitoring Distributed Energy Resources Amber Motley; Manager, Short Term Forecasting November 2 nd, 2016 California ISO Overview

More information

Capacity Performance Training. March 16, 2015

Capacity Performance Training. March 16, 2015 Capacity Performance Training March 16, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

Overview NU Conservation Programs & Other Interesting Opportunities: Industrial process sub-metering. Dave McIntosh Justin Marmaras

Overview NU Conservation Programs & Other Interesting Opportunities: Industrial process sub-metering. Dave McIntosh Justin Marmaras Overview NU Conservation Programs & Other Interesting Opportunities: Industrial process sub-metering Dave McIntosh Justin Marmaras AIA Quality Assurance The Building Commissioning Association is a Registered

More information

05/14/2012 THE CRIME OF IMPROPER ENERGY MANAGEMENT AGENDA

05/14/2012 THE CRIME OF IMPROPER ENERGY MANAGEMENT AGENDA THE CRIME OF IMPROPER ENERGY MANAGEMENT COOLING MANAGEMENT SOLUTIONS Dan Mascola AGENDA Promote Background Cooling Management Solutions Case Studies Additional Energy Savings Tips How To Start on Monday

More information

INITIAL ASSESSMENT OF POTENTIAL FOR ACTIVE DEMAND MANAGEMENT (ADM) EEAC Consultants

INITIAL ASSESSMENT OF POTENTIAL FOR ACTIVE DEMAND MANAGEMENT (ADM) EEAC Consultants INITIAL ASSESSMENT OF POTENTIAL FOR ACTIVE DEMAND MANAGEMENT (ADM) EEAC Consultants April 2018 INTRODUCTION Follow-up to energy efficiency assessment of potential, with a focus on demand management Early

More information

Your Path to Energy Savings. New Residential Construction

Your Path to Energy Savings. New Residential Construction Your Path to Energy Savings New Residential Construction Maggie Dimitrova March 1 st, 2011 Agenda PG&E s Integrated Approach California Energy Efficiency Standards Energy Efficiency Incentive Programs

More information

Roadmaps for Demand Response & Storage

Roadmaps for Demand Response & Storage 1 Roadmaps for Demand Response & Storage Jim Price, California ISO Senior Advisor, Market Development & Analysis jprice@caiso.com PSERC Summer Planning Workshop Market Stem July 15, 2015 CAISO markets

More information

2025 California DR Potential Study

2025 California DR Potential Study 2025 California DR Potential Study May 25, 2017 Presented by: Jennifer Potter Study Team: Lawrence Berkeley National Laboratory Peter Alstone, Jennifer Potter, Mary Ann Piette, Peter Schwartz, Michael

More information

Dynamic Price, Product and Messaging Specification

Dynamic Price, Product and Messaging Specification 1 2 3 4 5 6 7 8 Retail Dynamic Price, Product and Messaging Specification (DRAFT) Draft Memo to by Ed Cazalet on Sept 7, 2009. During the August 2nd 2009, OASIS Energy Interoperation Technical Committee

More information

DCAS Energy Management. August 15, 2014 Ellen Ryan & Mike Dipple

DCAS Energy Management. August 15, 2014 Ellen Ryan & Mike Dipple DCAS Energy Management August 15, 2014 Ellen Ryan & Mike Dipple DCAS Energy Management Mission DCAS Energy Management (DEM) serves as the hub for City government s energy management. DEM provides energy

More information

2018 Oakland Clean Energy Initiative Request for Offers Q&A

2018 Oakland Clean Energy Initiative Request for Offers Q&A PG&E may modify the information provided below at any time for any reason. No advance notice is necessary for such modifications to take effect. In the case of differences between this information and

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions 1. What is Demand Response? FERC defines Demand Response (DR) as changes in electric usage by demand-side resources from their normal consumption patterns in response to changes

More information

Project Measurement and Verification Procedures

Project Measurement and Verification Procedures Project and Verification Procedures 1) Introduction The objective of measurement and verification (M&V) activities at the Project level is to confirm that the Measures that are supported by the Retrofit

More information

PUGET SOUND ENERGY DEMAND RESPONSE POTENTIAL ASSESSMENT

PUGET SOUND ENERGY DEMAND RESPONSE POTENTIAL ASSESSMENT PUGET SOUND ENERGY DEMAND RESPONSE POTENTIAL ASSESSMENT DER INTEGRATION INTEREST GROUP 36 TH PLMA CONFERENCE CAMBRIDGE, MA NOVEMBER 13, 2017 1 TOPICS Overview of PSE s Demand-Side Resource Assessment and

More information

NV Energy s Residential HVAC Optimization Program

NV Energy s Residential HVAC Optimization Program Demand Response & Distributed Energy Resources NV Energy s Residential HVAC Optimization Program SWEEP 10 th Annual Southwest Regional Energy Efficiency Workshop November 21-22, 2013 Michael O. Brown Manager,

More information

New Architectures for Interacting with Demand Side Resources in Ancillary Services Markets

New Architectures for Interacting with Demand Side Resources in Ancillary Services Markets New Architectures for Interacting with Demand Side Resources in Ancillary Services Markets Ed Koch, Akuacom/Honeywell Sirajul Chowdhury, CAISO John Hernandez, PG&E San Rafael, CA Folsom, CA San Francisco,

More information

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses SMART HVAC & LIGHTING SYSTEMS Savings From Two Major C&I End Uses September 21, 2016 PRESENTATION OVERVIEW Why this focus? Significant savings potential Smart controls coupled with more efficient technologies

More information

Energy Efficiency in Multi-Tenant Office Buildings

Energy Efficiency in Multi-Tenant Office Buildings Energy Efficiency in Multi-Tenant Office Buildings Presented by David Herman, PE, LEED AP Principal, EnerG Associates, LLC 3/10/2015 1 Learning Objectives 1. List the principal sources and uses of energy

More information

LONG ISLAND LONG ISLAND

LONG ISLAND LONG ISLAND Utility 2.0 Long Range Plan 1 The proposed Utility 2.0 investments are designed to benefit all Long Island customers. Our Utility 2.0 proposal is a component of a broader set of solutions to improve reliability

More information

Energy Savings Made Simple

Energy Savings Made Simple Energy Savings Made Simple SWARM LOGIC FOR DEMAND MANAGEMENT EXCESSIVE COINCIDENCE LEADS TO HIGHER THAN NECESSARY PEAK DEMAND The issue at hand is a lack of system-wide coordination of HVAC loads, which

More information

SMUD s Cutting Edge Utility Programs

SMUD s Cutting Edge Utility Programs . SMUD s Cutting Edge Utility Programs Rob Lechner, Harlan Coomes, Tim Berg, Wade Hughes, Jim Parks Green California Summit Sacramento Convention Center April 8, 2015 Powering forward. Together. About

More information

Reduce your properties energy consumption, keep tenants and residents comfortable, and

Reduce your properties energy consumption, keep tenants and residents comfortable, and YARDI Smart Energy Suite Reduce your properties energy consumption, keep tenants and residents comfortable, and simplify analysis and reporting with automated energy management solutions. YARDI Smart Energy

More information

2019 Commercial and Industrial Demand Reduction Initiative

2019 Commercial and Industrial Demand Reduction Initiative 2019 2019 Commercial and Industrial Demand Reduction Initiative Jointly Submitted by Public Service Company of New Hampshire d/b/a Eversource Energy Unitil Energy Systems, Inc. NHPUC Docket DE 17 136 January

More information

Save with Business Programs and Services

Save with Business Programs and Services Business Programs and Services Change the current way you use energy and make your bill even lower. Save with Business Programs and Services Learn about energy-saving programs, services and rebates available

More information

Minnesota Conservation

Minnesota Conservation Program Information MN Minnesota Conservation Programs Summary We offer solutions for business customers in a suite of energy conservation and energy management products that will help you increase your

More information

Benchmarking of Demand Response Potentials Final Report:

Benchmarking of Demand Response Potentials Final Report: Benchmarking of Demand Response Potentials Final Report: Adaptation of FERC s NADR Model to Xcel Energy s Public Service Company of Colorado Territory Prepared for Xcel Energy May 9, 2012 Table of Contents

More information

National Grid USA Service Company. Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects. Final Report

National Grid USA Service Company. Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects. Final Report National Grid USA Service Company Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects Final Report July 11, 2010 Submitted to: National Grid USA Service Corporation Waltham, MA Submitted

More information

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity

2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity Energy Accounting & Education Energy Managers Kermit King School District of La Crosse John Daily School District of Holmen 1 Topics (Electricity) Creating electricity Defining degree days Customer charges

More information

Entergy Louisiana: Analysis of Long- Term Achievable Demand Response Potential. Draft Report October 12, 2018

Entergy Louisiana: Analysis of Long- Term Achievable Demand Response Potential. Draft Report October 12, 2018 Entergy Louisiana: Analysis of Long- Term Achievable Demand Response Potential Draft Report October 12, 2018 TABLE OF CONTENTS I. EXECUTIVE SUMMARY... 1 II. STUDY APPROACH... 2 Overview... 2 Data Collection

More information

Summary of 60-Day Notice: Smart Thermostat Demand Response

Summary of 60-Day Notice: Smart Thermostat Demand Response Summary of 60-Day Notice: Smart Thermostat Demand Response Public Service Company of Colorado ( Public Service or the Company ) is providing a 60-Day Notice to add a Smart Thermostat measure to the product

More information

Project Information. Measure Description

Project Information. Measure Description Project Information Project ID#: CE07M016 Measure: Multiple Electric : 452,593 kwh, 8.84 kw, 39.26 kw Facility Type School Technology: Multiple Measure Description CH-1 - Chiller Plant Optimization and

More information

Energy Storage for Industrial Buildings. Ankush Halbe October 20 th 2016 NY-BEST Energy Storage Conference Syracuse, NY

Energy Storage for Industrial Buildings. Ankush Halbe October 20 th 2016 NY-BEST Energy Storage Conference Syracuse, NY Energy Storage for Industrial Buildings Ankush Halbe October 20 th 2016 NY-BEST Energy Storage Conference- 2016 Syracuse, NY Agenda Corporate overview Motivation Industrial Facilities Operation Energy

More information

OpenADR DR Program Guide. OpenADR Alliance Webinar July 28, 2015

OpenADR DR Program Guide. OpenADR Alliance Webinar July 28, 2015 OpenADR DR Program Guide OpenADR Alliance Webinar July 28, 2015 Topics The need for a Program Guide DR programs supported DR Template Structure Drill into one program (CPP) Deployment Scenarios Odds and

More information

Building Control Strategies That Work to Improve Your Energy Bottom Line

Building Control Strategies That Work to Improve Your Energy Bottom Line Building Control Strategies That Work to Improve Your Energy Bottom Line William D. (Skip) Milton MBA, CEM, CEA Assistant Director of Facilities Operations Texas Children s Hospital Objective: Learn how

More information

Capacity Performance FAQ Response

Capacity Performance FAQ Response PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum

More information

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC LIBRARY ENERGY WALK- THROUGH Andy Robinson, Training and Education, SEDAC ILLINOIS ENERGY NOW University of Illinois 360 Energy Group 2 WHAT WE DO SEDAC Free Services Outreach and Training Energy Assistance

More information

Commercial Retro-Commissioning Program Manual for 2019 SECTION 1

Commercial Retro-Commissioning Program Manual for 2019 SECTION 1 Commercial Retro-Commissioning Program Manual for 2019 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.

More information

Energy Efficiency A PJM Demand Management Program

Energy Efficiency A PJM Demand Management Program Energy Efficiency A PJM Demand Management Program PJM s Energy Efficiency program pays businesses for permanent load reduction resulting from energy efficiency projects they have completed or will be complete

More information

The energy benefits of View Dynamic Glass

The energy benefits of View Dynamic Glass Workplace demonstration Energy monitoring over a period of 12 months resulted in the commercial office room installed with View Dynamic Glass saving 39 percent of the total energy consumed compared to

More information

2015 Energy Efficiency Program for Business

2015 Energy Efficiency Program for Business ENERGY EFFICIENCY PROGRAM FOR BUSINESS 2015 Energy Efficiency Program for Business Custom Project Training May 20, 2015 1 ENERGY EFFICIENCY PROGRAM FOR BUSINESS Safety First 2 ENERGY EFFICIENCY PROGRAM

More information

Your Trusted Partner in Customer Engagement

Your Trusted Partner in Customer Engagement Your Trusted Partner in Customer Engagement Your Presenter Today: Joel Gilbert BS and MS in Chemical Engineering MS in Operations Research and Statistics Rensselaer Polytechnic Institute Licensed Professional

More information

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Commercial Retro-Commissioning Program Manual for 2015 SECTION 1 Introduction The Commercial Retro-Commissioning Program (RCx) is designed to achieve demand and energy savings in commercial facilities.

More information

THE COMING SMART GRID. Dr. Tom Lawrence, PE, LEED-AP

THE COMING SMART GRID. Dr. Tom Lawrence, PE, LEED-AP BUILDING DEMAND RESPONSE AND THE COMING SMART GRID Dr. Tom Lawrence, PE, LEED-AP lawrence@engr.uga.edu Introductions and Topics Covered What is the smart grid? Demand Response Management Buildings interaction

More information

Outline of Talk. Dynamic vs. Time-of-use pricing. Dynamic vs. Time-of-use pricing

Outline of Talk. Dynamic vs. Time-of-use pricing. Dynamic vs. Time-of-use pricing Symmetric Treatment of Load and Generation: A Necessary Condition for Demand Response to Benefit Wholesale Market Efficiency and Manage Intermittency Frank A. Wolak Director, Program on Energy Sustainable

More information

Demand Response Update

Demand Response Update Demand Response Update Bruce Kaneshiro & David Hungerford California Public Utilities Commission & California Energy Commission November 2, 2006 1 Demand Response in the Energy Action Plan The Energy Action

More information

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT

Energy Assessment Report Clayville Elementary School DRAFT October George Washington Highway, Clayville, RI DRAFT Report Clayville Elementary School October 2016 3 George Washington Highway, Clayville, RI 02815 Clayville Elementary School Summary of Findings On behalf of the School Building Authority at Rhode Island

More information

Statewide Pricing Pilot (SPP)

Statewide Pricing Pilot (SPP) Statewide Pricing Pilot (SPP) Overview and Results 23-24 Should dynamic rates be offered to all customers? 4.5 4. Residential Response to Critical Peak Pricing Control Group CPP Event Total TOU 69% 65%

More information

Demand Response Issues Facing ISO New England. August 2016

Demand Response Issues Facing ISO New England. August 2016 Demand Response Issues Facing ISO New England August 2016 1 Demand Response Issues Facing ISO New England Key Facts and Concerns about the New Market Full implementation of FERC Order 745, with the start

More information

Summary of 60-Day Notice: Smart Thermostat Optimization

Summary of 60-Day Notice: Smart Thermostat Optimization Summary of 60-Day Notice: Smart Thermostat Optimization Public Service Company of Colorado ( Public Service or the Company ) posts this 60- Day Notice to add a Smart Thermostat Optimization Pilot to the

More information

Energy Efficiency Analysis for a Multi-Story Research Office Building (LG Multi V Water IV Heat Recovery VRF System)

Energy Efficiency Analysis for a Multi-Story Research Office Building (LG Multi V Water IV Heat Recovery VRF System) Energy Efficiency Analysis for a Multi-Story Research Office Building (LG Multi V Water IV Heat VRF System) (* Source: http://kr.lgeaircon.com/) Commercial Air-Conditioning Engineering Study ES-MultiVWaterIV_EnergyAnalysis-08-14

More information