CONSULTANT SCOPE OF WORK

Size: px
Start display at page:

Download "CONSULTANT SCOPE OF WORK"

Transcription

1 Consultant Services CONSULTANT SCOPE OF WORK ENVIRONMENTAL DOCUMENT LA 23 RAILWAY RELOCATION PE/NEPA PROJECT JEFFERSON AND PLAQUEMINES PARISHES, LOUISIANA RPC Task LA23RR1 RPC/ The Regional Planning Commission for Jefferson, Orleans, Plaquemines, St. Bernard, St. Tammany and Tangipahoa Parishes (RPC) and the Federal Railroad Administration (FRA) have entered into a Cooperative Agreement to conduct an Environmental Review and prepare an environmental document for the relocation of the New Orleans Gulf Coast Railway (NOGC) that serves Jefferson and Plaquemines Parishes in the New Orleans region of Southeast Louisiana. The FRA is the lead federal agency in the preparation and oversight of the environmental documentation. Funding, however, originated with FHWA and certain additional traffic analysis is required by FHWA to fulfill FHWA and LADOTD thresholds. The RPC will complete all tasks outlined in the Statement of Work between the FRA and RPC. The RPC seeks qualified consultant teams to assist RPC in fulfillment of all required FRA and FHWA deliverables. The consultant team will prepare and summarize all technical information and analytical findings in accordance with requirements of the National Environmental Policy Act (NEPA), as amended, the Council on Environmental Quality s regulations implementing NEPA, and the FRA s procedures for the Consideration of Environmental Impacts (Environmental Procedures). In addition, the Consultant will be responsible to ensure dialogue and coordination with LADOTD and FHWA are performed so that the process and final product(s) also satisfy any LADOTD and FHWA concerns for roadway implications. The consultant, in partnership with RPC, is expected to coordinate with FRA on a continuous basis through bi-weekly or monthly coordination calls that will be outlined more fully in the Project Management Plan. Work performed under this grant is a programmatic FRA action. Work is being undertaken with the reasonable intent of an Environmental Assessment resulting in a Finding of No Significant Impact (FONSI). If it is determined that the project has significant impacts and requires an Environmental Impact Statement (EIS), the EIS could be performed under this contract via a supplemental agreement and only if sufficient additional funding is available. The General Objective The general objective of this Project will be to identify and develop a preferred alternative to the current NOGC railway alignment, or to identify transportation systems safety improvements along the existing NOGC rail corridor that could be implemented to address existing transportation, safety and quality of life needs. Study Area Location The boundaries of the study area are the Harvey Canal on the west, the Mississippi River on the north, the Jefferson/Orleans Parish line on the east, and Walker Road on the south. The portion of the NOGC

2 that is the subject of the Project runs from the western side of the Harvey Canal, in Harvey, LA, to near the intersection of LA 23/Belle Chasse Highway and Walker Road in Belle Chasse, LA. In Gretna, the railway corridor parallels 4 th Street and runs down the center of Madison Street, both classified as urban collectors and in densely developed neighborhoods populated by residences, schools, and churches. The portion of the railway that runs parallel to LA 23 is similarly developed, and intersects with several major west bank arterials, including US 90B, Terry Parkway, and Behrman Highway (LA 428). The railway crosses two major water bodies on moveable bridges: the Harvey Canal near 4 th Street in Harvey and the Intracoastal Waterway near LA 23 in Belle Chasse. Although the area is protected by levees and flood protection walls, most of the area is mapped within the 100-year floodplain. The area is primarily developed for industrial, commercial, and residential uses, but does contain some undeveloped areas vegetated with trees and navigation and transportation of goods. The project area spans the Gulf Intracoastal Waterway (GIWW), a channel used for commercial navigation and transportation of goods. The project area also contains other waterways and wetlands development activities. The project area lies within the Mississippi River deltaic plain and the Louisiana Coastal Zone. The Naval Air Station Joint Reserve Base New Orleans, a Navy airport with a main runway oriented southwest to northeast, is located east of the project area. The Proposed Action will require Federal Railroad Administration involvement and permits from multiple federal, state, and local entities. The consultant team shall provide the services described below for the LA 23 Rail Relocation Project PE/NEPA. All products will be reviewed and approved by the RPC project manager prior to submission to FRA. Phase I Project Background and Management, Data Collection and Scoping 1. Previous Studies The consultant will be responsible for reviewing previous studies or documents relevant to the proposed rail line relocation and related improvements, including but not limited to the following: - Plaquemines Parish Intermodal Feasibility Study December, 2002: RPC - Peters Road Supplemental EA with FONSI December, 2009: RPC RPC will provide these two documents. Other items to be researched by the consultant include Jefferson and Plaquemines Parish planning studies influencing the study area and any economic development reports for undeveloped areas in the project vicinity. The Peters Road roadway corridor is currently in final design and the consultant will be responsible for coordinating the proposed alternative railway alignment(s) with this effort. The consultant will be responsible for reviewing the findings and recommendations from the previous studies and preparing a summary Memorandum of key issues. Task 1 Deliverables: Compendium of previous studies; Summary Memorandum of key issues 2. Detailed Project Work Plan, Project Management Plan and Project Agreements The FRA requires RPC to submit a Detailed Project Work Plan, which consists of the activities and steps necessary to complete all tasks in the Grantor (FRA)/Grantee (RPC) agreement and an

3 executed agreement with the host railroad to access the railroad s property to perform the preliminary engineering and/or environmental work. FRA also requires the submission of a Project Management Plan which describes the approach for team organization, team decision-making, roles and responsibilities and interaction with FRA. These required documents will be created as one submission by RPC. RPC will be responsible for organizing and submitting the above documents to FRA. The selected consultant is required to provide RPC with any needed supporting documentation for the above reports and to work with the RPC to come to resolution on management issues and identify any interdependencies among tasks. Supporting documentation includes the consultant budget and schedule, the host railroad agreement between the consultant and the NOGC RR, graphics for all organizational charts. The consultant will work with RPC as necessary to advise and provide additional information as needed for submission of these documents. All information, unless preapproved, will go through and be submitted to the FRA by the RPC Project Manager. Task 2 Deliverables: Consultant Budget and Schedule Host Railroad Agreement Organizational Chart graphics Consultant and subconsultant task descriptions 3. Agency and Stakeholder Involvement Plan Due to the intensive nature of the NEPA process to facilitate communication and coordination to accomplish key milestones and engage an array of stakeholders, the Consultant, working closely with the RPC Project Manager, will develop an Agency and Stakeholder Involvement Plan after the Detailed Project Work, Schedule and Project Management Plan are approved by FRA. The Agency and Stakeholder Involvement Plan will create a plan of meeting and outreach activities. It will identify stakeholders and groups to be engaged in the range of activities within the Environmental Review process and work to develop a stakeholder database and an invitation list for each meeting. The consultant will establish the number of meetings, the preparation and resources (manpower and materials) needed for each meeting or outreach activity, and establish a schedule with potential locations. The plan will set out a blueprint for creation and management of sign-in sheets, signage, agendas, minutes, comment forms, transcriptions, mapping and photography, exhibits, handouts and distribution of the information to be shared or collected at each activity, task or milestone. The plan will also detail advertisements, required periods of advertisement, timing of meeting notifications, required comment periods, confidentiality, storage of materials, number of copies and the process to update contacts. The consultant will demonstrate how public involvement activities will be linked to key milestones in the planning /engineering and NEPA process. The Agency and Public Involvement Plan will at a minimum include planning for the following meetings or tasks and the consultant will allow for adequate contingency for additional, unplanned meetings: Project Management Committee Scoping meetings/process defined Solicitation of Views packets and distribution Agency and Local Officials Meetings Alternative Outreach Meetings Informational Meetings

4 Public Meetings Public Hearings (see items 14 and 15) Agency Review of Technical Information Draft Environmental Document Review Final Environmental Document Review Draft FONSI Final Environmental Document Distribution Task 3 Deliverables: An Agency and Stakeholder Involvement Plan Report including a schedule, a spreadsheet of required elements for each meeting and a descriptive narrative with sufficient detail to reflect all requirements for each meeting or task listed above. 4. Scoping, Purpose and Need Statement The consultant shall develop a Scoping process to identify the affected public and agency concerns and define the issues and alternatives that will be examined. They will follow the approved Agency and Stakeholder Involvement Plan for outreach and communication. The consultant will prepare a Purpose and Need (P&N) statement that forms the basis against which the alternatives are evaluated, including the no build option. The P&N clearly identifies the problem to be solved by the proposed action and the elements contributing to the problem that must be addressed by proposed solutions. The P&N statement draws on existing and projected conditions, proposed improvements, environmental quality concerns, and community characteristics in the Study Area. The consultant will undertake the following activities to develop the statement of Purpose and Need: - Review the goals and objectives in previous studies documents. - Assess the need for the rail facilities relocation and extension and other improvements considering the Study Area limits; existing and proposed facilities and services; level of train service; growth in local, national, and international trade; local transportation goals and objectives; identified problems along the rail corridors; and other goals. Identify and analyze system improvements to meet annunciated project goals. - Identify opportunities and constraints in addressing identified needs to help further define alternatives and to take advantage of existing and planned transportation improvements (including improvements to Peters Rd. and SR 23) and economic development potential and job growth opportunities. Following RPC/DOTD and FRA approval, the consultant will distribute the P&N statement to federal, state and local agencies, Native American tribes, and the railroads. The P&N statement will be made available to the public through the Public Involvement Plan. Task 4 Deliverables: Scoping Report Draft Purpose and Need Statement Final Purpose and Need Statement 5. Traffic and Grade Crossing Delay Analysis The consultant will develop a baseline scenario for existing rail, vehicular, and marine transportation operating within the study area. The consultant will work with the RPC, DOTD, the Coast Guard,

5 NOGC and other agencies to collect existing data on the number and characteristics of existing modal operations, including historical growth rates, rail data, vehicle traffic counts, turning movement counts, marine traffic on the Gulf Intracoastal Waterway (GIWW) and vehicle delay measurements at key grade crossing locations, to establish the baseline scenario, for use in analyzing both the no build and build alternative(s). Per arrangements with Federal Highway Administration (FHWA), congestion and delay data collection tasks will be completed as described below. Train crossings interrupt roadway traffic flow for a period of time that is dependent on the speed and length of the train. The proposed changes in train volume as a result of the future No Build and Build Alternatives would cause increased vehicle delay at those at-grade crossings where train traffic increases and an improvement in vehicle delay at those at-grade crossings where train traffic decreases. Factors in the vehicle delay analysis include: The number of trains per day before and after the proposed project, The estimated time it takes for a train to pass the highway/rail at-grade crossing; and Existing and projected roadway traffic volumes. Several values for each highway/rail at-grade crossing will be calculated and included in the analysis. All new and existing at-grade crossings will be evaluated and results will be summarized in a technical memorandum. Existing conditions, No-Build, No-Build with highway TSM Alternatives, and conditions under the Build Alternatives will be examined for the following parameters: Blocked crossing time per train Average delay per delayed roadway vehicle Vehicle queue length Average delay for all vehicles Total vehicle traffic delay Traffic LOS The following sections briefly describe the parameters that will be used to measure the roadway and rail operational conditions at highway/rail at-grade crossings. 5.1 Blocked Crossing Time per Train (Dc) The time required for a train to cross the intersecting roadway will be estimated. This time is called the blocked crossing time. This value is used to determine the length of time drivers wait when trains pass through a highway/rail at-grade crossing. Average train speed is a major factor in this calculation. This speed is dependent not only on track conditions and train operating characteristics, but also on intersecting commuter and freight rail traffic. 5.2 Average Delay per Delayed Vehicle (Da) The average delay per delayed vehicle is the average amount of time that a driver would be delayed at a highway/rail at-grade crossing as a result of a single train crossing. It assumes a uniform arrival of vehicles. Vehicles arrive at a constant rate. When the blocked crossing period begins, vehicles begin to queue. When the blocked crossing period ends, queued vehicles begin

6 to depart at the constant vehicle departure rate. The departure rate continues until the departure curve intersects the arrival curve, signifying the dissipation of the queue. 5.3 Vehicle Queue Length (Q) The vehicle queue is the estimated number of vehicles in line at the end of the blocked crossing time of a single train event. The vehicle queue is equal to the number of vehicles that arrive during the blocked crossing time (Dc). The vehicle queue during the peak hour of roadway traffic will be estimated. The peak-hour traffic will be assumed to be 10 percent of the ADT volume a typical assumption used by traffic engineers. The vehicle queue at the end of the blocked crossing time will be calculated. 5.4 Average Delay for All Vehicles (Dv) The average delay per vehicle is the average amount of time that a vehicle is delayed at that intersection. 5.5 Average Number of Vehicles Delayed Per Day (Td) The average number of vehicles delayed per day equals the number of drivers in a 24-hour period that would be stopped for trains at highway/rail at-grade crossings. The average number of vehicles delayed per day per crossing will be estimated. 5.6 Traffic Level of Service The vehicle delay effects at highway/rail at-grade crossings using the LOS concept at signalized intersections, as documented in the 2010 Highway Capacity Manual (HCM) (Transportation Research Board [TRB] 2010) will also be estimated. Use of the HCM procedures for signalized intersections is acceptable for the following reasons: the absence of a similar measure of efficiency for highway/rail at-grade crossings, and similarities between signalized intersection operation and highway/rail at-grade crossing operation. 5.7 Total Daily Average Vehicle Traffic Delay The total average vehicle delay will be calculated for each crossing over a 24-hour period and multiplied by the number of vehicles delayed to estimate the total daily average vehicle traffic delay. All of the above factors will be calculated based on existing and proposed values for the number of trains (N), average train speed (V), length of trains (L), and the number of traffic lanes (NL) for the highway/rail at-grade crossing. The existing LOS for each highway/rail at-grade crossing will be determined. The LOS refers to the efficiency at which a highway/rail at-grade crossing operates when a train passes through. To analyze the existing and future year traffic delays at crossings, data will be compiled from several sources, including consultant collected traffic data for major roadway as determined by the Project Management Committee (PMC) and the following: FRA location and inventory databases, which include information about highway/rail at-grade crossings, such as ADT data NOGC Railway databases for number of trains per day, train lengths and speeds LADOTD roadway ADT data

7 NOGC s Operating Plan The consultant will analyze existing railroad operating conditions in consultation with NOGC and other railroads operating in the study area. Conduct one meeting with the railroads to obtain the latest railroad infrastructure and operational data such as valuation maps, track diagrams, timetables, yard plans, schedules, interchange procedures, and operating statistics, etc. The consultant will survey the NOGC about railroad traffic growth forecasts over the next thirty years. The consultant will establish the base year and forecast years in consultation with the Project Management Committee (PMC). Some data supplied by NOGC and other railroads may be confidential and may not be released, unless approved for release by NOGC or the American Association of Railroads (AAR). The consultant will discuss the requirements of the Traffic Analyses for all transportation modes with RPC prior to initiating data collection activities. RPC s Transportation Model will be used to assist in establishing horizon year traffic forecasts in coordination with the New Orleans Gulf Coast Railroad (NOGC). The consultant will prepare a draft Traffic Analyses Report for submission to RPC for review and comment prior to finalization. Upon approval, the consultant will prepare the final Traffic Analyses Report and provide five copies along with an electronic version in.pdf format to RPC. Task 5 Deliverables: Traffic Analysis Report (rail (freight and passenger), vehicular and marine traffic data) Baseline and Forecast Findings Phase II Alternatives Studies The objective of this phase is to develop all reasonable alternatives consistent with the purpose and need for the project, including the no build alternative and those introduced through the public process. A project-based Geographic Information System (ArcGIS Project) will be used throughout the project to help identify physical and environmental constraints, evaluate potential environmental impacts, and to clearly present findings for stakeholder review and comment in the development and comparison of alternatives. All data will be provided for all Alternatives considered. This study phase concludes with a recommendation of a Preferred Alternative. 6. Geographic Information System/Environmental Inventory In cooperation with RPC, the consultant will develop geo-referenced data sets that inform engineering alternatives. All data will be stored in a File GeoDatabase compatible with ESRI s ArcGIS All vector data will be provided in the same coordinate system within the geodatabase. Raster data can be forwarded in its original projection. All map products, views and layouts will be set to view in the local State Plane LA South NAD83 feet coordinate system. The consultant will collect existing data from any source necessary and prepare an inventory of social, economic, environmental, physical and cultural resources potentially impacted by the project alternatives and enter this information into an ArcGIS Project for subsequent review, analysis, and screening of alternatives. This information will be supplemented with field data, as appropriate, or as may be requested by RPC/DOTD/FRA.

8 6.0 GIS Metadata The consultant will develop and maintain metadata for all GIS layers. The consultant will adhere to Federal Geographic Data Committee (FGDC) standards for newly created data layers. All data layers included in any map product will be cited with a minimum of data provider and year of the data. The consultant will maintain and update the ArcGIS Project throughout the duration of the project. At project completion, the consultant will deliver the ArcGIS Project containing all data and metadata within a geodatabase to RPC and DOTD as a Map Package file on one or more DVDs as a series of self-extracting files. 6.1 Project Mapping The consultant will make use of available aerial imagery and vector data for producing exhibits for the Study Area. These will include but are not limited to: o The most current as well as the highest resolution digital orthophotography available. o The most current and highest resolution lidar available. o Digital parish roadway data layers obtained from Jefferson Parish and Plaquemines Parish and LA DOTD. Roadway data will be edited within the LADOTD geodatabase. If there are discrepancies between the local data and LADOTD data, the verified linework will be entered (or edited) within the LADOTD geodatabase. o Displays will be reviewed prior to meetings to review appropriate seals, citations, disclaimers etc. All data layers included in any map product will be cited with a minimum of data provider and year of the data. 6.2 Environmental Inventory shall include but not be limited to: Waters of the U.S., including Wetlands The project study area lies adjacent to the Mississippi River and within portions of the 100-year floodplain. The project study area contains the GIWW, Harvey Canal No.1, Bayou Barataria, Bayou Barriere, and numerous canals and ditches. Undeveloped portions of the project study area appear to contain various types of freshwater wetland (e.g., forested, shrub, emergent) with a range of hydrologic conditions (e.g., permanent to seasonal inundation/saturation). The consultant will review aerial photography, National Wetland Inventory (NWI) digital data, the National Hydrography Dataset, U.S. Geological Survey (USGS) topographic maps, the US Army Corps of Engineers Navigable Waterways dataset, and information from the U.S. Fish & Wildlife Service (FWS) and the Natural Resources Conservation Service (NRCS) to identify potential waters of the U.S., including wetlands, within the study area and potentially impacted by the proposed action. Acreage of wetlands impacted and their value will be calculated and exhibits suitable for

9 reproduction will be developed by the consultant indicating the limits of wetlands in the study area and the areas to be impacted by the project. The consultant will conduct a preliminary wetland delineation in accordance with guidelines found in the Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Atlantic and Gulf Coast Plan Region (United States Army Corps of Engineers, Wetland Regulatory Assistance Program, 2010) for the preferred alternative. Subsequent to the wetland delineation, the consultant will prepare a wetland data report, using the latest federal criteria, for submittal to the U.S. Army Corps of Engineers, New Orleans District. Photographs of each soil sample with the appropriate Munsell soil chart in the same photograph will be included in the wetland data report. Each wetland area will be located on a quadrangle sheet as well as a site plan with the station numbers depicted. Five copies of the draft and final wetland data report and accompanying data will be produced by the consultant and made available to for distribution as directed by RPC Streams, Scenic Streams and Water Bodies The consultant will obtain information on streams and water bodies for the study area from the USGS National Hydrography dataset. Information will also be obtained for any rivers within the study area designated as Wild and Scenic by the National Wild and Scenic Rivers Act or as Scenic Streams by the State of Louisiana Water Quality The consultant will obtain and review water quality information for the study area from the Louisiana Department of Environmental Quality Coastal Zones The consultant will obtain and review coastal zone and coastal conservation plan (CCP) boundaries as they may pertain to the study area from the Louisiana Department of Natural Resources, Coastal Management Division as well as all projects through local coastal management programs and the Louisiana Coastal Protection and Restoration Authority Protected Species Plants and animals with federal classifications of Endangered, Threatened, Proposed Endangered, and Proposed Threatened species are protected under the provisions of Sections 7 and 9 of the Endangered Species Act (ESA), as amended. The consultant will acquire federal and state-listed species and critical habitat locations from the FWS and the Louisiana Department of Wildlife and Fisheries, Natural Heritage Program (NHP). The consultant will need to execute a data sharing agreement with the NHP for data usage. Because of the sensitivity of the endangered and threatened species data, the site locations will not be made available to the public.

10 6.2.6 Cultural Resources The National Environmental Policy Act (NEPA) requires consideration of important historic and cultural aspects of our national heritage, while Section 106 of the National Historic Preservation Act, as amended, requires federal agencies to take into account the effect that an undertaking will have on historic properties. Historic properties are those included in or eligible for inclusion in the National Register of Historic Places (NRHP) or within local historic districts and may include structures, buildings, districts, objects, and sites. The consultant will obtain and enter into the ArcGIS Project database archaeological sites and architectural resources within the study area, as obtained from the Louisiana Division of Archaeology (DA) and the Division of Historic Preservation (DHP). If the proposed action would potentially affect any site eligible for the NRHP, then consultation with the Louisiana SHPO would be required. Because of the sensitivity of the archaeological data, the site locations will not be made available to the public Floodplains The Federal Emergency Management Agency (FEMA) issues Flood Insurance Rate Maps as part of the National Flood Insurance Program (NFIP) which designate the Special Flood Hazard Area (SFHA) in land areas covered by the floodwaters of the one percent annual chance flood, or 100-year flood. The project study area may contain areas within designated 100-year floodplains. The consultant will acquire current and proposed FEMA Digital Flood Insurance Rate Maps (DFIRM) for the study area from FEMA for input into the ArcGIS Project database. Potential impacts to floodplains as a result of the proposed action may include filling, grading, channel relocation, new bridges and culverts, and other activities. Impacts to the 100-year floodplain typically require coordination and approval from the local floodplain administrator(s) and FEMA, and may require flood damage reduction or mitigation measures Levees and Flood Protection Projects The project study area contains or is adjacent to levees which serve as flood control and hurricane protection risk reduction along the Mississippi River and portions of the GIWW. It is anticipated, therefore, that the Proposed Action would require a flood control permit from one or more levee districts and reviewed by Louisiana Office of Coastal Activites and the Louisiana Coastal Protection and Restoration Authority, DOTD, and the U.S. Army Corps of Engineers (USACE). The levee districts with jurisdiction in the project study area are the West Jefferson Levee District and Algiers Levee District, which make up the Southeast Louisiana Flood Protection Authority West, and the Plaquemines Parish Government. If the Proposed Action would alter, use, or occupy a levee from a federal flood control project, then it must be demonstrated that this will not be injurious to the public interest and will not impair the usefulness of the federal project in order to obtain approval from the Secretary of the Army through the USACE.

11 6.2.9 Air Quality The Clean Air Act (CAA) of 1970 and EPA regulatory programs govern air pollution assessment and control. In Louisiana, EPA and LDEQ are responsible for air quality protection. Under authority of the CAA, EPA establishes primary and secondary pollutant criteria called the National Ambient Air Quality Standards (NAAQS). Jefferson and Plaquemines Parishes are presently in attainment of ozone standards. There is currently no model for project level ozone. Railroad emissions from locomotives and railroad ancillary activities are analyzed under EPA s general conformity rules in non-attainment areas. It is anticipated, therefore, that the consultant will need to perform a general conformity analysis for the ozone precursor pollutants. Emissions can also be calculated from proposed project fuel consumption, if available. If the Proposed Action has the potential to emit air contaminants, it shall be further evaluated for the applicability of exemptions and air permitting requirements. For instance, construction activities for the Proposed Action should meet ambient air quality, visibility, odor and opacity standards and implement reasonable particulate matter control. An air quality evaluation related to the potential movement of coal by rail and resultant air contaminants is required in this task. Task 6.11 Deliverables: Air Quality Impact Assessment Summary Noise and Vibration The consultant will submit a noise protocol for DOTD approval (following Federal Transit Administration guidance Transit Noise and Vibration Impact Assessment, May, 2006, as referenced in Environmental Impact and Related Procedures, FHWA and FTA, effective April 23, The consultant will follow FTA guidance, Appendix D: Determining Existing Noise, to obtain ambient noise measurements for the existing exterior sound environment Navigation The project study area crosses the GIWW, a channel used for extensive commercial navigation along the Gulf Coast. The project study area also crosses the Harvey Canal which connects to the Mississippi River. Both of these channels are navigable waterways subject to U.S. Coast Guard jurisdiction. Any bridge or causeway proposed across a navigable waterway of the U.S. requires a Coast Guard bridge permit under Section 9 of the Rivers and harbors Act. The Coast Guard will impose any necessary conditions on the location and plans for bridges to ensure they are constructed, maintained, and operated in the interest of public navigation. The Proposed Action may require a Coast Guard bridge permit and be subject to requirements that it not hinder navigation, such as using a lift bridge with a tower on either side of the waterway Water Wells The consultant will obtain water well information for the study area from the DOTD (Now DNRs) Water Well Registry website for use in the ArcGIS Project.

12 6.3.5 Oil and Gas Wells The consultant will obtain oil and gas well information for the study area from the Louisiana Department of Natural Resources for use in the ArcGIS Project Hazardous Materials Sites The consultant will obtain hazardous materials site locations for the study area from Environmental Data Resources (EDR) risk management information reports, Sanborn maps, local data sources such as emergency response agencies, GOHSEP, and historic aerial photography and enter this data into the ArcGIS Project Existing and Future Land Use & Zoning The consultant will obtain existing and future land use and zoning information for the study area from Jefferson Parish and Plaquemines Parish for the ArcGIS Project Parks, Community Facilities & Recreational Sources All public facilities, including recreational and public park land, will be identified and delineated for the study area. Research, analysis, and documentation of compliance with Section 4(f) of the USDOT Transportation Act will be done by the consultant. The consultant will identify the locations where Land and Water Conservation Act Funds or any other fund affecting park and recreational lands are being used. The consultant will prepare all documentation for coordination with the appropriate agencies. The above information will be included in the ArcGIS Project Standing Structures The consultant will identify structures within 100 feet of the rail corridor on the most current digital orthophotography as being residential, business/commercial, church, community center, fire station, police station, school, or other and input this information into the ArcGIS Project. 6.4 Major Utilities The consultant will enter major utility information into the ArcGIS Project along the proposed rail corridors as obtained from the major utility companies, Jefferson Parish, Plaquemines, and Louisiana One Call Existing Railroad Network The consultant will obtain existing railroad network data for the study area from the National Transportation Atlas database, the LADOTD and any source available to improve local accuracy. These data will be overlaid with the highest resolution and most current digital orthophotography available and verified and edited for recent rail line changes. The rail lines, rail yards and intermodal terminals and ownership information will be layers within the ArcGIS Project.

13 6.4.2 Census/Demographic/Economic Data The consultant will utilize 2010 Bureau of Census and the latest American Community Survey data (block group/parish) or other approved data sources deemed superior by the project team for describing study area characteristics. As a minimum the consultant will enter data on population, age, race, ethnicity, income, housing tenure, housing characteristics (value, renter/owner, vacancy, etc.) and journey to work information. Locally obtained applicable data will be reviewed to improve the study accuracy which may include blighted/adjudicated properties, new construction and renovation permits, businesses, economic tax incentive zones, and any other local layers that may prove useful to the team Political Boundaries The consultant will obtain all pertinent political boundaries for the study area including state, parish, and municipal representatives; planning districts, and neighborhood boundaries. Contact information such as name, address, telephone numbers, website address, etc. will be obtained, as applicable Additional items as determined in the public process. Task 6 Deliverables: ArcGIS Project including social, economic, environmental, cultural and physical data, with alternative layers and metadata. 7. Define Relocation Alignment Alternatives Working in coordination with the NOGC and the Project Management Committee, the consultant will determine the boundaries for feasible railroad corridor alignments between the Harvey Canal and Walker Road. Various relocation alignments will be sought that meet the goals and objectives set through scoping the project, the purpose and need statement and stakeholder involvement. The consultant will conduct three meetings with the Project Management Committee to refine assumptions and establish design and performance criteria/standards to be used in alternatives evaluation and refinement, and coordinate those assumptions with participating agencies. Examples of design criteria include: design speed, typical section, curvature, clearances, switch locations, etc. Performance criteria examples include: mobility improvements, environmental benefits, operating efficiencies, cost-effectiveness, job creation, compatibility and support of existing land use policies, etc. The consultant will develop preliminary drawings, schematics, and initial geometrics to evaluate the alternatives in sufficient detail to show track alignment, switch locations, potential yards and sidings, minimal right-of-way width, roadway and bridge crossings, and other information necessary to compare the no build and build alternatives. The consultant will estimate residential and commercial displacements, including disproportionate impacts to minority and low income populations. The consultant will design modifications to reduce or alleviate potential impacts or to provide project enhancements for the impacted areas.

14 Each alternative will be studied in sufficient detail to develop preliminary capital cost estimates. Schematic plans and profiles for the various alternatives will be developed (1 =200 or 1 =400 or larger scale, as appropriate), identifying necessary structural modifications of existing transportation facilities, permits required, utility relocation, and rights-of-way requirements. The consultant will complete the engineering to a level of detail necessary to support the evaluation of the transportation system in satisfying the stated purpose and need, accepting anticipated growth, and disclosing the effects on the social, economic, and natural environment as required under NEPA. This analysis will be developed on base maps using geo-referenced, controlled, aerial photography. Plans and profiles will be developed showing alignments, potential property acquisition, yards, and ancillary support facilities. Identify necessary highway modifications including impacts to DOTD and Parish streets. Task 7 Deliverables: -Preliminary drawings, schematics and initial geometrics for each alternative (road, rail and Highway TSM) -Summary and/or map of commercial and residential displacement, land use policies 8. Cost Estimates The consultant will prepare capital cost estimates based on per-foot construction costs for typical railroad and roadbeds and per-square-foot costs for bridge facilities. In addition, utilities relocation costs will be developed for any major utilities that have to be modified or moved on a comparable basis. Right-of-way acquisition costs will be developed for properties which need to be acquired based on local real estate values and probable requirement for relocation assistance. The consultant will use information available from public sources to estimate the number and type of properties which may be needed. The consultant will prepare construction costs estimates for each alternative under detailed development, including utility relocation costs and mitigation costs. The consultant will provide the supporting analysis for all utilities to be relocated, including water, gas, electric, telephone, and sewer. Right-of-way requirements, impacts, and costs will be developed for each detailed alternative, including displacements and access requirements. In consultation with NOGCRR, the consultant will evaluate the requirements, rights-of-way impacts, and associated costs for train control and signalizing elements. Task 8 Deliverables: Cost Estimates for capital improvements, utilities relocation, rights-of-way, and commercial and residential displacements for each alternative under detailed development 9. Alternatives Analysis and Screening Prepare a preliminary Alternatives Summary in a concise format describing the various alternatives, including the no build alternative, and making use of tables, exhibits, data sheets and text to describe and compare each option. The Summary should objectively evaluate all reasonable alternatives and include estimated project costs, qualitatively evaluate construction of rail and roadway traffic affects, and quantitatively analyze potential environmental impacts of each alternative, based on the ArcGIS Project. Briefly discuss alternatives eliminated from detailed

15 study, including the reasons for their elimination. Identify the preliminary alternatives operating benefits and indicate how well those improvements satisfy the stated Purpose and Need. Identify the types of benefits that may accrue to the railroad and to the public as a result of all proposed improvements, particularly those associated with operating over the new route(s). The Summary should also include the following: o o o o o Updated Study Area Map showing the preliminary alternatives Typical Section(s) Location and Environmental Resources maps. Display the preliminary alternatives and the identified social, economic, natural and cultural resources on the Project Base Map. Illustrate the alternatives and their relationship to the resources. Color maps are preferred because they assist in visualizing the resources and clarifying the area of potential effect. Preliminary Alternatives Impact Summary showing the comparative impacts for each of the alternatives developed Preliminary cost estimates for each alternative Task 9 Deliverables: Preliminary Alternatives Summary 10. Refine Alternatives and Identify Preferred Alternative Summarize the alternatives outreach meetings and responses based on comments received from the agencies, Native American tribes, local officials and the public. Revise the preliminary alternatives and cost estimates based on the comments received; enter the revised alternatives into the ArcGIS Project for re-evaluation of environmental impacts. Expand the Preliminary Alternatives Summary to reflect the stakeholder input. Discuss the revisions made and why, objectively evaluate the revised alignments and update the estimated project cost and quantitative analysis of potential environmental impacts based on the ArcGIS Project. Present the additional information in a concise format relying on tables, exhibits, and data summaries. Include the following additional exhibits, if applicable: - Updated Study Area Map showing the revised preliminary alternatives - Revised Typical Section(s) - Revised Location and Environmental Resources maps. Display the revised preliminary alternatives, the Preferred Alternative, and the social, economic, natural, and cultural resources identified within the Study Area on the Project base map. - Revised Preliminary Alternatives Impact Summary showing the comparative impacts for each of the revised preliminary alternatives developed - Revised cost estimates. In consultation with RPC, DOTD, FRA, and NOGC, identify a Preferred Alternative using a balanced transportation decision-making approach that takes into account the potential impacts on the human and natural resources; the public s need for safe and efficient transportation improvements; and the least environmentally damaging practicable alternative in accordance with NEPA and the Clean Water Act (CWA) Section 404(b)(1) guidelines.

16 Task 10 Deliverables: Alternatives outreach meetings comments and responses; Revised and Expanded Preliminary Alternatives Summary with preferred alternative recommendations; and Concurrence on Preferred Alternative identified in the draft environmental document. Phase III Environmental Documentation The consultant will summarize all studies and analyses conducted per section 6 to assess the beneficial and adverse effects of the Project on the social, economic, natural and cultural environment in accordance with FRA Procedures for Considering Environmental Impacts (64 FR 28545, May 26, 1999). 11. Items to be addressed in Environmental Document Preparation The EA will be prepared in accordance with FRA s technical advisory and shall contain the latest environmental checklist and summary of mitigation, permits, and commitment sheet. Below is a list of the major topics to be included in the environmental report document DOTD Environmental Determination Checklist The Consultant will prepare DOTD s Environmental Determination Checklist for eligible federal aid roadways impacted by the project for inclusion in the document. Additional sheets will be added as necessary to explain or expand responses to the checklist categories Summary Section A Summary will be prepared that adequately and accurately summarizes the environmental findings and documentation, identifying major conclusions, areas of concern, and issues raised by federal agencies and the public, issues to be resolved, and comparative analysis of the alternatives Summary of Mitigation and Permits A summary of mitigation and permits shall be placed at the beginning of the document. All potential permits and their requirements to implement the project will be identified. Any mitigation measure or enhancement committed to by Jefferson Parish, Plaquemines Parish, DOTD, or the railroad will be listed in this summary Purpose and Need for Action The purpose and need statement will be refined to address the comments received as a result of agency and public coordination or through advances in the Project s development. The P & N for the proposed action shall be discussed in the environmental document. It will identify the problems that the proposed action is intended to correct, including the no-build alternative Alternatives All reasonable alternatives considered shall be discussed in the document, including alternatives introduced through the public process. If any alternative was dismissed at an early

17 stage, the reasons for dismissal shall be discussed in the document. The alternatives shall address the purpose and need of the project. These alternatives, including the no build alternative, will be described and analyzed in the document. The estimated costs associated with each alternative will be documented in the report. Summary tables will be prepared to compare impacts of the build and no-build alternatives. The Consultant will summarize operational issues pertinent to operating scenarios, operating and maintenance costs. Capital cost estimates will be prepared utilizing unit price information obtained from the railroad Impacts Analysis of each alternative, including the no-build will be made. Items to consider include, but are not limited to, traffic patterns, permits, land use, community/social, economic, historic, cultural, recreational, archaeological, noise, air, wetlands, floodplains, farmland, and endangered or threatened species and/or their habitat. Information will be based on GIS-based and field data developed as part of this effort. Previous and on-going studies obtained through secondary sources, directly in the field, or through meetings and discussions with public agencies, the public, organizations, individuals and elected officials may also be used. Some of these items may require the production of a separate report in addition to the analysis in the environmental document. Potential mitigation measures designed to reduce or alleviate environmental consequences or impacts will be discussed in the environmental document Wetlands The consultant will conduct a wetland delineation in accordance with guidelines found in the Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Atlantic and Gulf Coast Plain Region (United States Army Corps of Engineers, Wetland Regulatory Assistance Program, 2010) for the preferred alternative. Subsequent to the wetland delineation, the consultant will prepare a wetland data report using the latest federal criteria, for submittal to the U.S. Army Corps of Engineers, New Orleans District. Prior to conducting the site visit, the consultant will review in house data including, but limited to infrared photography, National Wetlands Inventory (NWI) maps, quadrangle maps, and soil maps. Acreage of wetlands impacted and their value will be calculated and exhibits suitable for reproduction indicating the limits of wetlands in the area affected by the project and the areas to be impacted will be made. All paperwork necessary for the permit application will be prepared by the consultant for DOTD s use in obtaining the necessary permits. Photographs of each soil sample with the appropriate Munsell soil chart in the same photograph will be included in the wetland data report. Each wetland area will be located on a quadrangle sheet as well as a site plan with the station numbers depicted. Five (5) copies of the draft and final wetland data report will be produced and made available for distribution by RPC (see 6.2.1) Environmental Site Assessment If right-of-way is required for the preferred alternative, the consultant shall perform a Phase I Environmental Site Assessment on the site in accordance with the recommendations and requirements of the United States Environmental Protection Agency (USEPA) in the American Society for Testing and Materials (ASTM) Standard practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process, ASTM E and the All Appropriate Inquiry (AAI) Standard (40CFR 312) and will include a review and summary of the following:

18 (1) State and federal regulatory agency databases that house environmental information relative to discerning the presence or absence of recognized environmental conditions (2) Historical aerial photography (3) Soil and land use information (4) Oil and gas well data (5) Water well data (6) U. S. Geological Survey 7.5 minute topographic maps (7) Historical topographic maps (8) City directory information (if available, of targeted properties based upon site reconnaissance, and regulatory agency databases) (9) Sanborn Maps (if available) The Phase I Environmental Site Assessment (ESA) will also involve interviews with personnel associated with the subject property, and a field visit to the subject property to conduct a reconnaissance of the site and immediate adjoining properties with the purpose of identifying potential areas of environmental concern. The consultant will not assume the User s Responsibility as set forth in Section 6 of the ASTM Standard, and 40 CFR , of engaging the services of a title company or title professional to review recorded land title records for environmental liens and activity/use limitations recorded against or relating to the property. Five (5) copies of the draft and final Phase I assessment shall be produced and made available for distribution as directed by RPC Air Quality Assessment The consultant will perform air quality modeling for the proposed alternatives as required by current EPA general conformity regulations and guidelines. A discussion of the anticipated impact to project level and regional air quality is required. An Air Quality study for CO2 may be prepared using CAL3QHC or MOBILE 6, or latest FHWA criterion. There is no model for project-level ozone. Railroad emissions from locomotives and railroad ancillary activities are analyzed under general conformity rules in non-attainment areas. Therefore, the consultant will perform a general conformity analysis for the ozone precursor pollutants. Conduct calculations with either the MOVES or NONROADS models, as applicable. Emissions can also be calculated from proposed project fuel consumption, if available. Five (5) copies of the draft and final Air Quality Study will be produced and made available for distribution as directed by RPC Noise and Vibration Assess noise and vibration, inclusive of before and after conditions and with and without the Proposed Action, following federal guidance Transit Noise and Vibration Impact Assessment, May, 2006, as referenced in Environmental Impact and Related Procedures, FHWA and FTA, effective April 23, The consultant will collect various data sources to predict train sound levels such as operating train speeds/locomotive power, equipment type, track configuration or condition, and source of receiver distances. Appropriate modeling tools and procedures will be used to identify noise sensitive receptors along the proposed routes. Identify locations where noise barriers would be both technically beneficial in terms of reducing impacts and feasible in that sufficient numbers of

I. PROJECT INITIATION

I. PROJECT INITIATION REPLACE BELLE CHASSE TUNNEL AND BRIDGE STAGE 1 - ENVIRONMENTAL ASSESSMENT PLAQUEMINES PARISH, LOUISIANA (State Project No. 700-38-0108) / H.004791 Background This is a scope of services for the preparation

More information

LA 23 NOGC Railway Relocation PE/NEPA Project

LA 23 NOGC Railway Relocation PE/NEPA Project LA 23 NOGC Railway Relocation PE/NEPA Project LA 23/New Orleans & Gulf Coast Railway Relocation Preliminary Engineering (PE) / National Environmental Policy Act (NEPA) Project Kevin Keller, PE HDR Engineering,

More information

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting LA 23 NOGC Railway Relocation PE/NEPA Project Public Meeting LA 23 New Orleans & Gulf Coast Railway (NOGC) Relocation Preliminary Engineering (PE) / National Environmental Policy Act (NEPA) Project RPC/FRA

More information

Exhibit A Mn/DOT Contract No

Exhibit A Mn/DOT Contract No Exhibit A Mn/DOT Contract No. 98142 SCOPE OF WORK AND DELIVERABLES Preliminary Design Red Wing US 63 Bridge and Approach Roadways State Project (SP) 2515-21 SCOPE OVERVIEW... 2 SCHEDULE... 2 PROJECT TASK

More information

2.1.1 Traffic Noise Analysis

2.1.1 Traffic Noise Analysis 2.1.1 Traffic Noise Analysis Number: 2.1.1 2.1.1 Name: Traffic Noise Analysis Traffic Noise Analysis Description: This category includes the performance of a traffic This category includes the performance

More information

Scope of Work. Land Use, Transportation, and Resilience: Scenario Planning Study East Tangipahoa Area State Project No. H RPC Task: ETangi

Scope of Work. Land Use, Transportation, and Resilience: Scenario Planning Study East Tangipahoa Area State Project No. H RPC Task: ETangi Scope of Work Land Use, Transportation, and Resilience: Scenario Planning Study East Tangipahoa Area State Project No. H.013576 RPC Task: ETangi Project Description The Regional Planning Commission is

More information

Appendix. Sample EA/EIS Scope of Work

Appendix. Sample EA/EIS Scope of Work Appendix K Sample EA/EIS Scope of Work EA/EIS Sample Scope of Work The purpose of this Scope of Work (SOW) is to prepare an EA document pursuant to the National Environmental Policy Act (NEPA) to analyze

More information

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination

Interstate 73 FEIS: I-95 to the Myrtle Beach Region Chapter 4. Public Involvement and Agency Coordination 4-65 Interstate 73 FEIS: I-95 to the Myrtle Beach Region 4-66 Comment noted. The use of existing roadways was considered during alternative development (refer to Chapter 2, Section 2.1, page 2-1 and the

More information

The Caltrans Contract Manager will assign specific projects to the Consultant through the issuance of Task Orders.

The Caltrans Contract Manager will assign specific projects to the Consultant through the issuance of Task Orders. Scope of Work/Deliverables Environmental Services for Project Specific High Desert Corridor Area of Los Angeles and San Bernardino Counties (District 7 & 8) Attachment 1 Page 1 of 11 A. Project Description

More information

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.0 PRELIMINARY ENVIRONMENTAL REVIEW 5.1 INTRODUCTION A preliminary environmental review was performed on the proposed freeway improvements that form Concept C, which encompasses the three freeway corridors

More information

TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING

TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING TIER 2 EIS OVERVIEW SOUTH SUBURBAN INAUGURAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT The proposed, (SSA) will require

More information

REGIONAL PLANNING COMMISSION

REGIONAL PLANNING COMMISSION PURPOSE & PROJECT DESCRIPTION REGIONAL PLANNING COMMISSION STAGE 0 FEASIBILITY STUDY Traffic Signal Timing and Coordination Study Veterans Boulevard Corridor Jefferson Parish, LA RPC Project VetCor1 State

More information

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform

More information

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT Public Notice U.S. Army Corps Permit Application No: SWG-2008-00106 Of Engineers Date Issued: 11 April 2017 Galveston District Comments Due: 11 May 2017 U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

More information

CESAM-RD-N May 29, 2014 PUBLIC NOTICE NO. SAM JSC

CESAM-RD-N May 29, 2014 PUBLIC NOTICE NO. SAM JSC DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS MOBILE DISTRICT MONTGOMERY FIELD OFFICE 605 MAPLE STREET BUILDING 1429, ROOM 105 MAXWELL AFB, AL 36112 CESAM-RD-N May 29, 2014 PUBLIC NOTICE NO. SAM-2014-00173-JSC

More information

Work Breakdown Structure Element Dictionary Preliminary Engineering

Work Breakdown Structure Element Dictionary Preliminary Engineering Element Name Initiation PE 3.1 Initiation includes the implementation of the project s funding and notification of the consultant or in-house design staff to commence work, the Kickoff Meeting with the

More information

GENERAL OVERVIEW MEETING JANUARY 10, 2019

GENERAL OVERVIEW MEETING JANUARY 10, 2019 Upper Barataria Basin Coastal Storm Risk Management and The Amite River and Tributaries-Comprehensive Study East of the Mississippi River, Louisiana Feasibility Studies GENERAL OVERVIEW MEETING JANUARY

More information

Procedure for NEPA for County or City Projects

Procedure for NEPA for County or City Projects Procedure for NEPA for County or City Projects I. County or City Projects with any Federal Highway funding or action shall be submitted to Environmental Program Division (EPD) with a request to start studies

More information

Agency Scoping. May 31, :00 a.m. 1:00 p.m. Environmental Impact Statement Port Columbus International Airport

Agency Scoping. May 31, :00 a.m. 1:00 p.m. Environmental Impact Statement Port Columbus International Airport Agency Scoping Meeting 10:00 a.m. 1:00 p.m. Environmental Impact Statement Port Columbus International Airport Presented to: CMH EIS Agencies By: FAA Consultant, Landrum & Brown Date: Agenda I. History,

More information

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:

More information

Interstate 66 Tier 1 Environmental Impact Statement Public Hearing

Interstate 66 Tier 1 Environmental Impact Statement Public Hearing Interstate 66 Tier 1 Environmental Impact Statement Public Hearing 1 Project Corridor Study Process / Tiering Approach Tier 1 EIS focuses on broad issues - Purpose and need - Mode / Technology choice -

More information

PUBLIC NOTICE REQUEST FOR PERMISSION TO ALTER A U.S. ARMY CORPS OF ENGINEERS PROJECT PURSUANT TO 33 U.S.C. SECTION 408

PUBLIC NOTICE REQUEST FOR PERMISSION TO ALTER A U.S. ARMY CORPS OF ENGINEERS PROJECT PURSUANT TO 33 U.S.C. SECTION 408 DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, NEW ORLEANS DISTRICT 7400 LEAKE AVENUE NEW ORLEANS, LOUISIANA 70118 REPLY TO ATTENTION OF Regional Planning and Environmental Division South Environmental Compliance

More information

Section 7 Environmental Constraints

Section 7 Environmental Constraints Section 7 Environmental Constraints i Yakima Valley Metropolitan and Regional Transportation Plan Public Comment DRAFT 1/27/2016 Environmental Constraints Analysis A programmatic-level review of potential

More information

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: June 17, 2014 Comment Deadline: July 17, 2014 Corps Action ID#: SAW-2009-00655 NC DOT TIP: R-4903 The Wilmington District, Corps

More information

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: May 30, 2013 Comment Deadline: June 30, 2013 Corps Action ID Number: SAW-2005-11122 The Wilmington District, Corps of Engineers

More information

Traffic Impact Study Requirements

Traffic Impact Study Requirements [TYPE THE COMPANY NAME] Traffic Impact Study Requirements County of San Mateo Department of Public Works Roadway Services 9/1/2013 I. Introduction The County of San Mateo (County), Department of Public

More information

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY Public Notice U.S. Army Corps Permit Application No: SWG-2016-00959 Of Engineers Date Issued: 28 November 2017 Galveston District Comments Due: 13 December 2017 U.S. ARMY CORPS OF ENGINEERS, GALVESTON

More information

US Army Corps of Engineers

US Army Corps of Engineers I I I ' A I US Army Corps of Engineers LA River Ecosystem Restoration, CA Preconstruction Engineering and Design Phase 104791 LOS ANGELES DISTRICT SOUTH PACIFIC DIVISION August 15, 2017 1 Table of Contents

More information

An Overview and Comparison of the Tennessee Department of Transportation s Environmental Evaluation Process

An Overview and Comparison of the Tennessee Department of Transportation s Environmental Evaluation Process Introduction This document provides a brief overview of the policy and procedures that govern the environmental evaluation process that the Tennessee Department of Transportation (TDOT) must follow for

More information

Traffic Impact Analysis (TIA) POLICY

Traffic Impact Analysis (TIA) POLICY Ascension Parish Planning Commission Traffic Impact Analysis (TIA) POLICY This policy establishes requirements for studies that provide information on traffic projected to be generated by all proposed

More information

Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District

Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District Public Notice October 21, 2016 U.S. Army Corps of Engineers Charleston District Notice of Intent to Prepare a Draft Environmental Impact Statement for the Proposed Jasper Ocean Terminal in Jasper County,

More information

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES

5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES 5.D.1 HISTORIC, ARCHITECTURAL, ARCHEOLOGICAL, AND CULTURAL RESOURCES Section 106 of the National Historic Preservation Act (NHPA) of 1966, as amended (16 U.S.C. Section 470(f)) protects properties that

More information

Public Notice. Permit Application No.: SWF Date: December 20, 2012

Public Notice. Permit Application No.: SWF Date: December 20, 2012 Public Notice Applicant: The City of The Colony Permit Application No.: SWF-2012-00231 Date: December 20, 2012 The purpose of this public notice is to inform you of a proposal for work in which you might

More information

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies APPENDIX B Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies Revised December 7, 2010 via Resolution # 100991 Reformatted March 18, 2011 TABLE OF CONTENTS

More information

Categorical Exclusion (CE)

Categorical Exclusion (CE) Categorical Exclusion (CE) Project Information Project Name: Federal Project#: Project Number: 0029-002-135, D624, P101 Project Type: Construction UPC: 77383 Charge Number: Route Number: 29 Route Type:

More information

Chapter 2 Table of Contents 2.1 PROJECT DEVELOPMENT PROCESS

Chapter 2 Table of Contents 2.1 PROJECT DEVELOPMENT PROCESS Chapter 2 Table of Contents Section Page 2.1 PROJECT DEVELOPMENT PROCESS... 2.2 Activity No. 1: Planning... 2.2 Activity No. 2: Identification of Appropriate Level of NEPA Compliance....2.2 Activity No.

More information

APPENDIX A. NEPA Assessment Checklist

APPENDIX A. NEPA Assessment Checklist APPENDI A NEPA Assessment Checklist NEPA CHECKLIST DATE: January 12, 2009 PREPARER: Frederick Wells, RLA PIN and Project Title: Surplus Property Request Wilder Balter Partners Marketplace Town of Newburgh,

More information

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY?

Northern Intermodal Transit Facility WHAT IS AN INTERMODAL TRANSIT FACILITY? WHAT IS AN INTERMODAL TRANSIT FACILITY? An intermodal transit facility gathers many modes of transportation together and is strategically located to increase destination alternatives. Intermodal facilities

More information

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS).

Environmental Impact Statement for the Green Line to the Airport Project. ACTION: Notice of Intent to Prepare an Environmental Impact Statement (EIS). This document is scheduled to be published in the Federal Register on 11/18/2015 and available online at http://federalregister.gov/a/2015-29418, and on FDsys.gov DEPARTMENT OF TRANSPORTATION Federal Transit

More information

Governor s Transportation Task Force. MEGAPROJECT NEEDS RPC Freight Roundtable Executive Director: Walter Brooks

Governor s Transportation Task Force. MEGAPROJECT NEEDS RPC Freight Roundtable Executive Director: Walter Brooks Governor s Transportation Task Force MEGAPROJECT NEEDS RPC Freight Roundtable Executive Director: Walter Brooks April 26, 2017 RPC Transportation Investments 2010-2015 Transit, $253.6M (20.3%) Safety &

More information

Clearview Parkway LA 3152 Stage 0 Feasibility Study and Environmental Inventory

Clearview Parkway LA 3152 Stage 0 Feasibility Study and Environmental Inventory Clearview Parkway LA 3152 Stage 0 Feasibility Study and Environmental Inventory Public Information Meeting Thursday, February 21, 2008 6:30 p.m., Eastbank Council Chambers, Yenni Building Project Sponsors

More information

Three copies (one original and two copies) of your completed NOI should be submitted to:

Three copies (one original and two copies) of your completed NOI should be submitted to: To: Prospective Applicants for a Stormwater General Permit Associated with Construction Activity Greater than 5 Acres Attached is a Stormwater General Permit Associated with Construction Activity Greater

More information

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS MOBILE DISTRICT MONTGOMERY FIELD OFFICE 105 SOUTH TURNER BOULEVARD MONTGOMERY, ALABAMA 36114

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS MOBILE DISTRICT MONTGOMERY FIELD OFFICE 105 SOUTH TURNER BOULEVARD MONTGOMERY, ALABAMA 36114 DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS MOBILE DISTRICT MONTGOMERY FIELD OFFICE 105 SOUTH TURNER BOULEVARD MONTGOMERY, ALABAMA 36114 CESAM-RD-N May 21, 2018 PUBLIC NOTICE NO. SAM-2006-01867-JAP

More information

APPENDIX M CEQA Initial Study Checklist

APPENDIX M CEQA Initial Study Checklist APPENDIX M CEQA Initial Study Checklist Appendix G ENVIRONMENTAL CHECKLIST FORM (To be Completed by Applicant) 1. Project title: 2. Lead agency name and address: 3. Contact person and phone number: 4.

More information

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures

Table Table 7.2 Potential Environmental Impacts and Mitigation Measures 7.2 Natural Environment/Environmental Planning Executive Summary/Key Points The Environmental Consultation and Mitigation Plan establishes: o A process for consultation with environmental resource agencies

More information

CESAM-RD-N February 10, 2017 PUBLIC NOTICE NO. SAM CMS

CESAM-RD-N February 10, 2017 PUBLIC NOTICE NO. SAM CMS DEPARTMENT OF THE ARMY MOBILE DISTRICT, CORPS OF ENGINEERS BIRMINGHAM FIELD OFFICE 218 SUMMIT PARKWAY, SUITE 222 HOMEWOOD, ALABAMA 3529 CESAM-RD-N February 1, 217 PUBLIC NOTICE NO. SAM-211-59-CMS JOINT

More information

Wyandanch Intermodal Transit Facility

Wyandanch Intermodal Transit Facility Wyandanch Intermodal Transit Facility Environmental Assessment July 2010 Prepared by: The United States Department of Transportation Federal Transit Administration in cooperation with The Town of Babylon

More information

TIER 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT. 7. Affected Environment, Environmental Consequences, and Mitigation Strategies

TIER 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT. 7. Affected Environment, Environmental Consequences, and Mitigation Strategies TIER 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT 7. Affected Environment, Environmental Consequences, and Mitigation Strategies Table of Contents Chapter 7 7 Affected Environment, Environmental Consequences,

More information

SECTION VII TRAFFIC IMPACT ANALYSIS GUIDELINES

SECTION VII TRAFFIC IMPACT ANALYSIS GUIDELINES SECTION VII TRAFFIC IMPACT ANALYSIS GUIDELINES A. GENERAL Traffic Impact Analyses (TIAs) are tools that have historically been utilized to evaluate the interaction between existing transportation infrastructures

More information

Chapter 3 FEDERAL POLICIES SOUTH DAKOTA DRAINAGE MANUAL

Chapter 3 FEDERAL POLICIES SOUTH DAKOTA DRAINAGE MANUAL Chapter 3 FEDERAL POLICIES SOUTH DAKOTA DRAINAGE MANUAL October 2011 Table of Contents Section Page 3.1 ENVIRONMENTAL...3-1 3.2 HEALTH...3-3 3.3 HISTORIC AND ARCHEOLOGICAL PRESERVATION...3-4 3.4 LAND

More information

Public Notice. Applicant: BNSF Railway Company Project No.: SWF Date: November 27, 2018

Public Notice. Applicant: BNSF Railway Company Project No.: SWF Date: November 27, 2018 Public Notice Applicant: BNSF Railway Company Project No.: SWF-2018-00246 Date: November 27, 2018 The purpose of this public notice is to inform you of a proposal for work in which you might be interested.

More information

12 Evaluation of Alternatives

12 Evaluation of Alternatives 12 Evaluation of Alternatives This chapter evaluates the effectiveness of the No-Build Alternative and the proposed METRO Blue Line Light Rail Transit (BLRT) Extension project based on the information

More information

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION AUGUST 2015 Table of Contents 1 Decision... 1 1.1 Project Description... 2 1.2 Basis for the FHWA Decision... 7 1.2.1

More information

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX

Environmental Impact Statement; Lone Star Regional Rail Project Williamson, Travis, Bastrop, Hays, Caldwell, Comal, Guadalupe, and Bexar Counties, TX This document is scheduled to be published in the Federal Register on 10/06/2014 and available online at http://federalregister.gov/a/2014-23711, and on FDsys.gov [4910-22] DEPARTMENT OF TRANSPORTATION

More information

PROGRAMMATIC AGREEMENT

PROGRAMMATIC AGREEMENT PROGRAMMATIC AGREEMENT CATEGORICAL EXCLUSION APPROVALS NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION & FEDERAL HIGHWAY ADMINISTRATION FEBRUARY 2000 PREAMBLE This Agreement establishes the procedures of the

More information

Transportation Conformity Guidance for Qualitative Hot-spot Analyses in PM 2.5 and PM 10 Nonattainment and Maintenance Areas

Transportation Conformity Guidance for Qualitative Hot-spot Analyses in PM 2.5 and PM 10 Nonattainment and Maintenance Areas Transportation Conformity Guidance for Qualitative Hot-spot Analyses in PM 2.5 and PM 10 Nonattainment and Maintenance Areas United States Environmental Protection Agency Federal Highway Administration

More information

Public Notice. Applicant: Lennar Homes Project No.: SWF Date: October 29, Name: Mr. Darvin Messer Phone Number:

Public Notice. Applicant: Lennar Homes Project No.: SWF Date: October 29, Name: Mr. Darvin Messer Phone Number: Public Notice Applicant: Lennar Homes Project No.: SWF-2013-00265 Date: October 29, 2013 The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It is

More information

Comprehensive Transportation Study for Glencoe, MN

Comprehensive Transportation Study for Glencoe, MN Comprehensive Transportation Study for Glencoe, MN Introduction and Project Information Introduction There have been a number of planning and preliminary engineering studies completed in the Glencoe area

More information

Categorical Exclusion (CE)

Categorical Exclusion (CE) Categorical Exclusion (CE) Project Information Project Name: Rte 130 Bridge Replacement over Pedlar River Federal Project#: BR-005-3(116) Project Number: 0130-005-643, B650, C501, P101, R201 Project Type:

More information

11 Joint Development Regulatory Context and Methodology

11 Joint Development Regulatory Context and Methodology 11 Joint Development This chapter describes the long-term direct and potential indirect impacts, and short-term direct and potential indirect impacts, of the proposed METRO Blue Line Light Rail Transit

More information

JOINT PUBLIC NOTICE. April 4, 2016

JOINT PUBLIC NOTICE. April 4, 2016 JOINT PUBLIC NOTICE April 4, 2016 United States Army State of Louisiana Corps of Engineers Department of Environmental Quality New Orleans District Attn: Water Quality Certification Sec. Attn: Regulatory

More information

U.S. Army Corps of Engineers (USACE) Galveston District

U.S. Army Corps of Engineers (USACE) Galveston District Appendix II U.S. Army Corps of Engineers (USACE) Galveston District SWG MITIGATION BANK PROSPECTUS TEMPLATE This Template includes the information required for a mitigation bank prospectus as outlined

More information

Chapter 5 - Transportation

Chapter 5 - Transportation Chapter 5 - Transportation Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the residents

More information

Environmental Impact Statement for the California High-Speed Rail System Burbank to Los Angeles Section, CA

Environmental Impact Statement for the California High-Speed Rail System Burbank to Los Angeles Section, CA This document is scheduled to be published in the Federal Register on 07/24/2014 and available online at http://federalregister.gov/a/2014-17384, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY THE COMMONWEALTH OF MASSACHUSETTS Number: P-92-010 Date: 10-08-92 - ) HIGHWAY DEPARTMENT FROM: NON-NHS BRIDGE R&R POLICY The purpose of this Engineering Directive is to formally notify Department Personnel

More information

State Route 8 Bridge Replacement Project

State Route 8 Bridge Replacement Project OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel

More information

Chapter 5 Transportation Draft

Chapter 5 Transportation Draft Chapter 5 Transportation Draft Discussion Similar to the other elements in the Comprehensive Plan, the transportation element impacts the quality of life, economic development and public safety of the

More information

TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA

TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA TOWN OF MOORESVILLE TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL TOWN OF MOORESVILLE, NORTH CAROLINA Effective August 1, 2007 Amended March 4, 2013, December 1, 2014, May 1, 2017 TOWN OF MOORESVILLE,

More information

Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010

Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010 Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010 The U.S. Army Corps of Engineers (Corps) and U.S. Environmental Protection

More information

Appendix E-1. FDOT MPO Program Management Handbook. (Excerpts)

Appendix E-1. FDOT MPO Program Management Handbook. (Excerpts) Appendix E-1 FDOT MPO Program Management Handbook (Excerpts) TABLE OF CONTENTS Chapter 4 Long-Range Transportation Plan Section Page 4.1 PURPOSE... 4-2 4.2 AUTHORITY... 4-2 4.3 SCOPE... 4-2 4.4 REFERENCES...

More information

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT Public Notice U.S. Army Corps Permit Application No: SWG-2015-00114 Of Engineers Date Issued: 18 October 2018 Galveston District Comments Due: 19 November 2018 U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

More information

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number:

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number: Public Notice Applicant: City of Dallas Project No.: SWF- 2014-00151 Date: April 18, 2014 The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It

More information

Willmar Wye Public Open House #4 and Public Hearing

Willmar Wye Public Open House #4 and Public Hearing Willmar Wye Public Open House #4 and Public Hearing February 23, 2017 www.dot.state.mn.us/d8/willmarwye Agenda Time Topic 5:00 pm Open House Opportunity for the public to ask questions of project staff

More information

16.1 Significant and Unavoidable Impacts

16.1 Significant and Unavoidable Impacts Chapter 16 NEPA requires an EIS and CEQA requires an EIR to evaluate a number of other types of environmental impacts in addition to those already addressed in the resource chapters. The analysis required

More information

INFORMATION REQUIRED FOR PROBABLE CATEGORICAL EXCLUSION (SECTION (d))

INFORMATION REQUIRED FOR PROBABLE CATEGORICAL EXCLUSION (SECTION (d)) Grant Applicant: Proposed Project: Date: August 03, 2010 Northern Virginia Transportation Commission, Arlington County Government, and Washington Metropolitan Area Transit Authority Crystal City/Potomac

More information

Public Notice. Applicant: TXI Operating, LP Project No.: SWF Date: April 2, Name: Mr. Darvin Messer Phone Number:

Public Notice. Applicant: TXI Operating, LP Project No.: SWF Date: April 2, Name: Mr. Darvin Messer Phone Number: Public Notice Applicant: TXI Operating, LP Project No.: SWF-2012-00125 Date: April 2, 2013 The purpose of this public notice is to inform you of a proposal for work in which you might be interested. It

More information

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES 1 PURPOSE... 3 2 PROJECT DESCRIPTION... 5 3 PROJECT COMMON AND PROJECT GENERAL TASKS... 6 4 ROADWAY

More information

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION SECTION 2B 1 - GROUND SURVEYS Survey Authorization... 2B-1 Interstate... 2B-1 Principal / Minor Arterial... 2B-1 Urban...

More information

Final Design Guideline

Final Design Guideline Final Design Guideline May, 2016 July, 2011 Check the Capital Project Delivery website to ensure this is the current version Table of Contents Purpose... 1 Introduction... 1 FD Support... 1 Roadway and

More information

Public Notice US Army Corps of Engineers Fort Worth District

Public Notice US Army Corps of Engineers Fort Worth District Public Notice US Army Corps of Engineers Fort Worth District Applicant: Dolet Hills Lignite Company Permit Application No.: SWF-2014-00282 Date: August 28, 2014 The purpose of this public notice is to

More information

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Lynnwood Link Extension 2013 Draft EIS Comments and Responses Page 157 C-001-001 Sound Transit acknowledges your opposition to Alternative C1 due to its residential impacts and impacts to Scriber Creek Park and wetlands. Page 158 C-002-001 Following the Draft EIS,

More information

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No EXHIBIT A TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No. 429768-4-12-01 This Exhibit forms an integral part of the Agreement between the DEPARTMENT and, the CONSULTANT,

More information

City of Bishop. Environmental Checklist Form

City of Bishop. Environmental Checklist Form City of Bishop Environmental Checklist Form 1. Project title: Environmental Review / 2007 California Building Codes 2. Lead agency name and address: City of Bishop 377 W. Line Street Bishop, Ca 93514 3.

More information

GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES

GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES Adopted by Town Council on November 25, 2008 Prepared By: HNTB Engineering Department Planning Department TABLE OF CONTENTS I. INTRODUCTION... 1 II.

More information

Oklahoma Department of Transportation Environmental Programs Division Office Fax

Oklahoma Department of Transportation Environmental Programs Division Office Fax Oklahoma Department of Transportation Environmental Programs Division Office 521-3050 Fax 522-5193 Documented Categorical Exclusion (DCE) for I-40: Pavement Reconstruction and Added Lanes from the Douglas

More information

Final Quiet Zone Work Plan

Final Quiet Zone Work Plan Executive Summary Recognizing the impacts of commuter train horns on the communities they serve, RTD will assist and facilitate the local jurisdictions Quiet Zone applications along the Gold Line, Northwest

More information

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R October 26, 2018

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R October 26, 2018 THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2018-822 October 26, 2018 Application

More information

TRANSPORTATION PLAN Donald Vary

TRANSPORTATION PLAN Donald Vary LOUISIANA STATEWIDE TRANSPORTATION PLAN Donald Vary March 2, 2016 AGENDA Plan Development Decision-Making Process Outreach Activities Vision and Goals Transportation Needs Financial Analysis (revenue scenarios

More information

DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, MOBILE DISTRICT CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA

DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, MOBILE DISTRICT CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA REPLV TO ATTENTION OF: DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, MOBILE DISTRICT CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 CESAM-RD-M April15, 2014 PUBLIC NOTICE NO. SAM-2014-00275-TMZ

More information

JOINT PUBLIC NOTICE May 16, 2016

JOINT PUBLIC NOTICE May 16, 2016 JOINT PUBLIC NOTICE May 16, 2016 United States Army State of Louisiana Corps of Engineers Department of Environmental Quality New Orleans District Water Quality Certification Section Regulatory Branch

More information

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY Public Notice U.S. Army Corps Permit Application No: SWG-2007-00247 Of Engineers Date Issued: 26 September 2017 Galveston District Comments Due: 26 October 2017 U.S. ARMY CORPS OF ENGINEERS, GALVESTON

More information

Programmatic Categorical Exclusions

Programmatic Categorical Exclusions Memorandum of Agreement for Approval of Categorical Exclusions between the Federal Highway Administration and the Wyoming Department of Transportation. February 12, 2014 The Federal Highway Administration,

More information

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018 What is the Carolina Crossroads Project? The South Carolina Department of Transportation (SCDOT), in cooperation with the Federal Highway Administration (FHWA), is proposing to upgrade and redesign a key

More information

FEDERAL TRANSIT ADMINISTRATION REGION 8. Finding of No Significant Impact (FONSI) for the Central Bus Operations and Maintenance Facility

FEDERAL TRANSIT ADMINISTRATION REGION 8. Finding of No Significant Impact (FONSI) for the Central Bus Operations and Maintenance Facility FEDERAL TRANSIT ADMINISTRATION REGION 8 Finding of No Significant Impact (FONSI) for the Central Bus Operations and Maintenance Facility Applicant: Utah Transit Authority Project Location: Salt Lake City,

More information

EXHIBIT A SCOPE OF SERVICES FOR MODAL DEVELOPMENT (MD) SUPPORT - CONTINUING. Financial Project Nos

EXHIBIT A SCOPE OF SERVICES FOR MODAL DEVELOPMENT (MD) SUPPORT - CONTINUING. Financial Project Nos EXHIBIT A SCOPE OF SERVICES FOR MODAL DEVELOPMENT (MD) SUPPORT - CONTINUING Financial Project Nos. 411461-1-12-10 422799-2-12-12 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT SEVEN Revised: 07/16/18 07/10/18

More information

Public Notice. Public Notice No. Date: Closing Date: US Army Corps LRL mad 6 Apr May 2018 of Engineers Louisville District

Public Notice. Public Notice No. Date: Closing Date: US Army Corps LRL mad 6 Apr May 2018 of Engineers Louisville District Public Notice Public Notice No. Date: Closing Date: US Army Corps LRL-2016-1083-mad 6 Apr 2018 7 May 2018 of Engineers Louisville District Please address all comments and inquiries to: U.S. Army Corps

More information

NEW YORK NEW JERSEY HARBOR AND TRIBUTARIES COASTAL STORM RISK MANAGEMENT

NEW YORK NEW JERSEY HARBOR AND TRIBUTARIES COASTAL STORM RISK MANAGEMENT NEW YORK NEW JERSEY HARBOR AND TRIBUTARIES COASTAL STORM RISK MANAGEMENT 237 217 200 80 237 217 200 119 FEASIBILITY 237 217 200 STUDY 27 255 0 163 131 239 110 112 62 102 130 National Environmental Policy

More information

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE FINAL ENVIRONMENTAL IMPACT STATEMENT Project Name: Project Location: Lead Agency & Contact Person: SEQRA Classification: Project Sponsors:

More information

O Street Arterial Corridor Study

O Street Arterial Corridor Study Prepared for: Weld County Public Works Department P.O. Box 758 1111 H Street Greeley, Colorado 80631 Prepared by: Felsburg Holt & Ullevig 6300 South Syracuse Way, Suite 600 Centennial, CO 80111 303-721-1440

More information

Qualitative Hot Spot Analysis for PM2.5 February 4, 2008

Qualitative Hot Spot Analysis for PM2.5 February 4, 2008 Technical Guidance for TG-POL-01-08 Qualitative Hot Spot Analysis for PM2.5 February 4, 2008 This technical guidance provides general guidelines for performance of a qualitative hot spot analysis for particulate

More information