Winter Readiness Workshop. November 6, 2017

Size: px
Start display at page:

Download "Winter Readiness Workshop. November 6, 2017"

Transcription

1 Winter Readiness Workshop November 6,

2 2 Emergency Preparedness - Planning

3 Reminders FERC Order Energy Offer Cap Reference Levels CROW Outage Cause Codes Replaces the current hard energy offer cap of $1,000/MWh, with a soft cap of $1,000 and a hard cap of $2,000/MWh Offers will be verified by the IMM after market close and before market processes run MISO and IMM are working to ensure system and software readiness for implementation on December 1, 2017 (Additional details at Nov 9 MSC Meeting) Request consultation with IMM if reference levels aren t reflective of costs or unit capabilities Mandatory and based on outage priority Essential to implement MISO s unit commitment plan and conduct postevent analysis Use specific codes in place of 115 Other 3

4 Resource Assessment: Generation Darius Monson

5 MISO projects adequate resources to reliably meet demand for Winter MISO Preliminary 2017 Winter Forecast MISO Wide Reserve Margin Target 15.8% Base Reserve Margin* 35.7% Winter is forecasted to be warmer than normal in the Central and South, and normal to below normal in the North Projected Reserve Margin* Probable Reserves after Outages* Winter Peak Forecast Total Projected Available Capacity All-time Winter Peak: 109 GW - January 6, % to 37.3% 6.7% to 19.3% GW GW 5 *Range of projections reflect the uncertainty of parameters, such as resource outages, load, and limited transmission, that can t be known ahead of time

6 Winter Resource Assessment Process Generation Load Reserves Various forced outage scenarios studied Load Modifying Resource (LMR) availability based on historical winter performance Regional transmission path contracts considered 6

7 Investigation of 3 winter resource and load scenarios show sufficient level of planning reserves GW GW * Total Capacity Coincident Peak Forecast Base Reserves (Pre-Outage) Total Probable Capacity Coincident Peak Forecast Probable Reserves (Pre-Outage) * Total Probable Capacity includes 1.7 GW of MISO-North resources with Energy Resource Interconnection Service without a firm point-topoint Transmission Service Request. These are Energy Only resources not counted as capacity, but still are available to serve local load in real-time operations. GW * Total Probable Capacity 90/10 Coincident Peak Forecast High Load Reserves (Pre-Outage)

8 Planned and Maintenance Outages are a significant portion of the total outages during past winters 35,000 30,000 GADS Mntnce Outages GADS Planned Outages GADS Forced Outages 25,000 20,000 MW 15,000 10,000 5,000 0 Dec- 12 Jan- 13 Feb- 13 Dec- 13 Jan- 14 Feb- 14 Dec- 14 Jan- 15 Feb- 15 Dec- 15 Jan- 16 Feb- 16 Dec- 16 Jan- 17 Feb- 17 Forced Out [MW] Total Out [MW] Average of 15 monthly peak hours 12,942 (Dec-12~Feb-17 23,339 (Dec-12~Feb-17) Max seasonal average of 5 seasons 15,850 (Dec-12~Feb-17) 25,469(Dec-12~Feb-17) Maximum peak day 21,409 (Jan-14) 28,738 (Dec-16) 8

9 Total Outage Predictions based on 5-year winter outage data from GADS 160 Base Reserve Margin Scenario Probable Reserve Margin Scenario 16.8% Reserve Margin with Outages % Reserve Margin with Outages * *^ Base Capacity (w/out S-N Limit) Coincident Peak Forecast Base Reserves (Pre-Outage) Total Outages (Forced, Mntnce, Planned) Base Reserves (Post-Outage) Probable Capacity (w/out S-N limit) Coincident Peak Forecast Probable Reserves (Pre-Outage) Total Outages (Forced, Mntnce, Planned) Probable Reserves (Post-Outage) *Capacity which was assumed non-transferrable from planning analysis is included in MISO-wide outage results, to reflect total outage impact seen by operations. ^There is 0.9 GW of additional Energy Only resources in the MISO-S region which can be expected to serve local load in real time operations. 9

10 160 Under high load and extreme outage scenarios, like the Polar Vortex, MISO would need to rely on Maximum Generation procedures High Load High Outage Scenario 9.6% Reserve Margin with Outages 160 High Load Extreme Outage Scenario 6.7% Reserve Margin with Outages *^ *^ Probable Capacity (w/out S-N Limit) 90/10 Coincident Peak Forecast High Load Reserves (Pre-Outage) High Outages (Forced, Mntnce, Planned) High Load Reserves (Post-Outage) Probable Capacity (w/out S-N Limit) 90/10 Coincident Peak Forecast High Load Reserves (Pre-Outage) Extr. Outages (Forced, Mntnce, Planned) Extreme Reserves (Post-Outage) *Capacity which was assumed non-transferrable from planning analysis is included in MISO-wide outage results, to reflect total outage impact seen by operations. ^There is 0.9 GW of additional Energy Only resources in the MISO-S region which can be expected to serve local load in real time operations. 10

11 In high load and extreme outage scenarios, MISO may need to rely on Behind-the-Meter and Demand Response to meet peak demand Probable Outage Scenario % Reserve Margin with Outages BTMG+DR 30% Operating Reserves 12% Generation 58% GW Probable Reserves Emergency only resources (Steps 2b and above) Total Outages Generation BTMG+DR Operating Reserves Extreme Outage Scenario Generation 0% Operating Reserves 33% BTMG+DR 67% GW High Load Reserves 6.7% Reserve Margin with Outages 28.7 Extreme Total Outages 0.0 Emergency only resources (Steps 2b and above) Generation BTMG+DR Operating Reserves 11

12

13 Contact Info Darius Monson Resource Adequacy Coordination (651) Ryan Westphal Resource Adequacy Coordination (651)

14 Generation Resource Assessment Appendix

15 Base Scenario 15

16 Base Scenario GVTC: Generation Verification Test Capacity TIS: Total Interconnection Service ER: Energy Resources TSR: Transmission Service Request BTMG: Behind The Meter Generation DR: Demand Response GW

17 Resource Assessment: Transmission Katie Hulet

18 Overview Overview Why perform the Coordinated Seasonal Assessment (CSA)? Evaluate a variety of stressed conditions across the MISO footprint Inform Real-Time Operations of potential limitations and issues on the system for the upcoming winter Coordinate with other entities No outstanding issues were identified for this upcoming winter 18

19 Overview CSA Analyses Steady-State AC Contingency Analysis First Contingent Incremental Transfer Capability (FCITC) Analysis Critical Interface Voltage Stability (PV) Analysis Phase Angle Analysis Evaluates the effect of simple and complex contingencies on the MISO footprint and Tier-1 areas IROL review Evaluates the impact of high MW transfers and identifies key flowgates and interfaces that may limit transfers 3 transfer analyses and Wind Generation Sensitivity studied Analyzes high transfers in combination with transmission and generator outages which can cause stability issues across the footprint 4 PV interfaces studied Identifies large phase angle differences associated with reclosing a transmission line 19

20 Steady-State AC Contingency Analysis Contingencies Category P0 (Cat A) system intact Category P1 (Cat B) P1.1 (B1) fault generator P1.2 (B2) fault transmission circuit P1.3 (B3) fault transformer P1.4 single shunt device P1.5 (B4) block single dc pole Stakeholders provided additional P2, P3, P6 and P7 contingencies they deemed beneficial to run for their areas Results No outstanding thermal or voltage issues identified Interconnection Reliability Operating Limit (IROL) Screening: No new IROLs identified Nuclear Plant contingencies: No constraints identified 20

21 Transfer (FCITC) Analysis Analysis Wilton Center to Dumont Transfer Dumont to Wilton Center Transfer MISO Midwest (North & Central) to MISO South FCITC (MW) >5000 > * Constraint [AEP] Tanners Creek - [DEO&K] Miami Fort 345 kv ckt 1 for the loss of [DEO&K] Terminal - [DEO&K] East Bend 345 kv ckt 1 [ITCT] Monroe [ATSI] Lallendorf 345 kv ckt 1 for the loss of [METC] Morocco [ATSI] Allen Jct 345 kv ckt 1 [EES-EMI] Franklin - [EES] Bogalusa 500 kv ckt 1 for the loss of [EES] McKnight - [EES-EMI] Franklin 500 kv ckt 1 *The Regional Directional Transfer Limit for real-time flows from MISO Midwest to MISO South is 3000 MW 21

22 CSA Transfer (FCITC) Historical Trend MW Wilton Center to Dumont Dumont to Wilton Center MISO Midwest to South Not Studied

23 Wind Generation Sensitivity MISO North Region Wind MISO Central Region Non-Wind Limiting Constraint: [ITCM] Ottumwa - [ITCM] Wapello 161 kv ckt 2 for the loss of [ITCM] Ottumwa - [ITCM] Wapello 161 kv ckt 1 FCITC: 3,469 MW 23

24 Critical Interface Voltage Stability (PV) Analysis Interfaces Evaluated Grand Gulf Stability Guide Down Stream of Gypsy (DSG) HV Interface Western HV Interface West of Atchafalaya Basin (WOTAB) Interface Scenarios and Results Each Interface was evaluated with a variety of scenarios ranging from system intact to applying a known outage with the most severe contingency Results indicate that the system voltages behave as expected for the entire spectrum of scenarios 24

25 Phase Angle Analysis MISO North to South Biased Case MISO Operating Region Delta Bus Angle Contingency English Name Stakeholder Comment CENTRAL NORTH 54.4 NORTH 35.2 NORTH SOUTH [WEC] Charter Steel Industrial 138 kv [WEC] CedarSauk 138 kv ckt 1 [XEL] Mallard 115 kv [WAPA] CPEC-Rutheville 115 kv ckt 1 [MP] Zemple 230 kv [OTP] Cass Lake 230 kv ckt 1 [MP] Zemple 230 kv [MP] CLAY BOSWELL 230 kv ckt 1 [EES] Mcknight 500 kv [SOCO] Daniel 500 kv ckt 1 Mitigated by Under Voltage Load Shed at Charter Steel Increase AC injection around Coal Creek/Center Reduce generation to reduce phase angle Reduce generation to reduce phase angle Reduce generation to reduce phase angle 25

26 Contact Info Katherine Hulet (651) Benny Relucio (317) Winter CSA Results on the MISO Extranet (CEII NDA, UNDA Appendix A, & Reliability Authority Approval Required): Winter CSA Results on the MISO Public Site:

27 27 Emergency Preparedness - Readiness

28 Extreme conditions can challenge MISO operations Polar Vortex January 2014 Tropical Storm Cindy June 2017 Solar Eclipse August 2017 Hurricane Harvey August 2017 Freezing Tested Hurricane Effectively MISO used components and Action Plan and managed a Hurricane Action fuel restrictions led provided an decrease in solar Plan developed with to improved electric- opportunity to energy and drop in members to gas coordination, practice lessons load, driven by successfully outage reporting, learned from human behavior manage this rain and winter readiness Hurricane and weather and flooding event preparations Readiness Drills patterns 28

29 but operators are well prepared to make quick and complex decisions when handling all operating situations Gas-Electric Coordination Initiatives Enhanced Operational Tools Gas-Electric Market Alignment Generation Fuel Survey MISO Winterization Guidelines Operational Situational Awareness Generation Portfolio Diverse generation pool to ensure reliability Planning and collaboration with members and gas industry for wind and natural gas utilization Emergency Preparedness FERC Winter Readiness Technical Conference MISO EOP & Winter Readiness Workshops Emergency Response & Power System Restoration Drill Operational Readiness Simulator training, Certification, and Continuing Education Strong Situational Awareness Robust Operational Tools and Procedures Operational & Market Enhancements 29

30 Operational and market enhancements also improve MISO s preparedness Coordinated Transaction Scheduling Improves transactions between MISO and PJM Oct 2017 Pricing Ramp Product May 2016 Provides transparent price signals to help manage ramp constraints that could lead to short-term reserve scarcity events Emergency Pricing Phase II Jul 2017 Off-line fast start resources amortized over minimum run time Available Maximum Emergency units allowed to move down below their Economic Minimum limits FERC Order 809 Nov 2016 MISO implemented changes to its Day Ahead Market to align with the Gas industry Gas-Electric Coordination Data Sharing with gas system operators Aug 2017 Enhances MISO s ability to coordinate with pipelines, especially during constrained operating conditions Gas Usage Profiles Target Nov 2017 Share Day-Ahead gas burn estimates with pipelines connected to MISO generators 30

31 MISO continues to conduct monthly Operation Drills MONDAY FRIDAY LMR DRILL: 2 nd Tuesday of each 10:00 EST MPs only LMM Drill: 2 nd Tuesday of each 10:00 EST LBAs only XML DRILL: Last Wednesday of each 13:00 EST LBAs only Firm Load Shed Drill: 1 st Wednesday of each 13:00 EST LBAs only EDR Drill: 2 nd Thursday of each 10:00 EST Power Restoration Drills: Two Drills held each Fall. 31

32 Electric-Gas Coordination Mark Thomas

33 Executive Summary National Storage Levels are near last year s, but slightly below 5 year average New gas supply heading into MISO, but could be cut if scheduled on interruptible transportation contracts MISO has implemented operational tools and strategic initiatives to increase situational awareness MISO is releasing Winterization Guidelines to promote generator winter preparedness 33

34 Strong Storage Levels Should Support Winter Operations Storage expected to peak just below 5-year average around 3.8 Tcf Unseasonably high injections during weeks surrounding hurricanes Harvey and Irma due to lower levels of power generation demand Even though injection season has lagged, NYMEX gas prices have remained under $3.00/MMBtu going into winter 34

35 Winter Outlook Increased Competition for Natural Gas in Winter Local Distribution Companies (LDCs) & Firm Shippers utilizing reserved firm transportation capacity contracts Potential limits on Interruptible transportation and flexible services Increase in gas-fired generation competing for same transportation space Pipeline Supply New expansions, such as Rover Pipeline, bringing gas to MISO New pipeline capacity is approved and built on Firm Transportation commitments Cold weather increases risk of production freeze-offs and compressor de-rates, threatening supply Rover Pipeline, Energy Transfer 35

36 Electric Gas Operations Tools

37 MISO actively monitors the Pipeline Network and Gas Industry activities MISO s Gas Pipeline Notifications Website provides regional insight into pipeline operating conditions Scrapes 35 MISO Pipeline EBB s for Critical Postings Useful for Market Participants and MISO Staff One Location, Regional Insight Critical Postings are issued if supply, capacity, or operational flexibility is impacted > Markets and Operations > Gas Pipelines ions/pages/gaspipeline.aspx 37

38 Fuel Impact Report: At Risk Units Internally, MISO will be monitoring the Pipeline Notification Website daily and will be translating relevant Critical Notices MISO will attempt to identify units that may be impacted and classify them as At Risk based on available information Internal classification will not impact unit status or Market Participant s portal submissions

39 Control Room Electric/Gas Pipeline Real Time Display Further interpretation and Leveraging of: Pipeline Notification Website Fuel Impact Report Pipeline Map Display with Additional Generator data included Daily Interpretation of pipeline conditions Pipeline Critical Notices will be translated and visually interpreted on Display - Serve as quick reference for Operators - Provide visual of restrictions - Additional Tool for insight into potential fuel limitations - Improves Awareness

40 Recent Initiatives

41 Generator-Pipeline Database Upgrade MISO commercial model updated with information provided by Market Participants holding natural gas generation Coordinated market participant outreach with Customer & Asset Registration Services MISO now has complete database of pipeline connections and dual fuel capability for all gas generators 41

42 Gas Usage Profiles Project Gas system operators will receive customized daily summaries of usage forecasts based on the MISO day-ahead clearings of interconnected generators Forecasted daily totals and hourly profiles MISO will coordinate with participating gas pipelines/local Distribution Companies (LDCs) to develop the most effective gas usage aggregations for each system 42

43 MISO Winter Generator Survey 4th annual implementation of the survey which was made available from October 2 nd November 3 rd, 2017 The highest participation rate of 87% (63,600 MW of capacity reporting) was reached during last year s survey survey was more user friendly, no significant changes to questions 43

44 MISO Winterization Guidelines Extreme cold temperatures can contribute to significant losses of electric generation MISO generators can protect against losing capacity by preparing for potential freeze offs of equipment Evaluation of Potential Problem Areas Detailed and Tested Winterization Plan Critical Instrument and Equipment Protection Fuel Availability Considerations 44

45 MISO urges asset owners to weatherize their generating units Follow the recommendations of North American Electric Reliability Corporation (NERC) Reliability Guideline: Generating Unit Winter Weather Readiness Review A Message from MISO on Weatherization on the MISO Website MISO Winterization Guidelines 45

46 Contact Info Mark Thomas Gas/Electric Operations Coordinator Please complete the Winter Generator Fuel Survey by November 4 th

47 Market Participant Winterization Presentation Duke Energy Bill Luke General Manager - Cayuga Generation Station Brian Wininger Technical Manager Cayuga Generation Station Jason Myers Operations Superintendent Cayuga Generation Station 47

48 48 Emergency Preparedness - Application

49 Each winter brings challenges that have to be closely monitored Sustained cold temperatures Fuel Limitations Frozen Equipment Insufficient Preparation Rapid Load Pickups Severe weather conditions Forced Generation Outages Wind Generation Solar Generation 49

50 Real-Time operating procedures are followed to efficiently provide least cost energy and maintain reliability of the Bulk Electric System Normal Operating Procedures Anticipate and plan ahead for "normal" system conditions Abnormal Operating Procedures Infrastructure or software system problems that affect MISO or its members Emergency Operating Procedures Emergency conditions that negatively impact system reliability 50

51 Emergency operating procedures preserve the system and gain access to certain resources during emergency or abnormal operating situations Emergency Operating Procedures guide operator actions when an event has the potential to, or actually does, negatively impact system reliability Maximum Generation Emergency Procedures Conservative System Operations Geo-Magnetic Disturbance Warning Severe Weather Alert Tier I Emergency Price Offer Floor Cold Weather Alert Hot Weather Alert Tier II Emergency Price Offer Floor 51 For more information - MISO Operating Procedures One-Pager and Appendix

52 Operators used emergency procedures to reliably manage the heat wave experienced in late September 52 Operating Day 09/21/ o F 09/22/ o F 09/23/ o F 09/24/ o F 09/25/ o F Peak Load GW GW GW GW GW Wind at Peak 8.8 GW 9.2 GW 4.8 GW 5.4 GW 1.9 GW NSI at Peak (Imports) 9.7 GW 11.8 GW 9.5 GW 7.2 GW 7.2 GW Cons Ops 11:00 EST Terminated 09/26 20:00 EST Max Gen Alert 12:00 20:00 EST 12:30 18:15 EST 13:00 17:15 EST 13:00 19:00 EST Max Gen Warning Max Gen Event 1a Max Gen Event 1bc 14:00 18:15 EST 14:30 18:15 EST 14:00 17:15 EST Record temperatures, high load, and seasonal and forced outages were contributing factors to the challenging conditions

53 Additional enhancements to tools and processes will better position MISO to manage extreme circumstances Improvement Area Transmission Load Relief (TLRs) Mitigation Issue Summary Other solutions are available to locally manage congestion, without the far-reaching impacts of TLRs. MISO is drafting a white paper v suggesting that for FERC re-examine the use of TLRs to manage congestion. Outage vanalysis Mid-Term: Generator Outage Capacity Tool Enhance Long-Term: Weather Tools Import and application processes to are include not designed more weather for parameters, this level of which uncertainty. are currently The Market available System from weather vendors, Enhancement into load includes forecasting projects system that IT will Agile be able backlog to serve as the foundation for improvements to address this issue. Generation Outage v Tariff Authority Enhance Work with Weather Stakeholders Import application to evaluate to include Tariff changes more weather to parameters, remove restrictions which are on currently MISO s available ability to from move weather generation vendors, outages into based load on forecasting capacity system and risk IT level. Agile backlog Forecasting Enhancements v Enhance Weather Weather Import Import application application to include to include more more weather weather parameters, parameters, which are currently look into available probabilistic from (90/10) weather forecast information, vendors, into and load Scenario forecasting analysis system with IT Agile Forecast backlog Monitor software 53

54 MISO plans for, monitors, and responds to changing system conditions throughout the day Obligations are successfully met through expertise, collaboration, and communication 54

55 Contact Info Rick Stachowicz Shift Operations Trevor Hines Shift Operations

56 Appendix

57 One-Pagers 57

58 MAXIMUM GENERATION EMERGENCY DETAILS PAGERS/ONE%20PAGER%20-%20MISO%20OPERATING%20PROCEDURES.PDF

59 Conservative System Operations Procedure SO-P-NOP sitory/procedure/so-p-nop %20rev%200%20conservative%20 System%20Operations.pdf MISO Market Capacity Emergency SO-P-EOP tory/procedure/so-p-eop %20rev%203%20miso%20market% 20Capacity%20Emergency.pdf

60 MISO s operating procedures ensure reliability during emergency or abnormal operating situations Conservative Operations: If conditions warrant, MISO will transition from normal operating conditions to Conservative Operations to prepare local operating personnel for a potential event, and to prevent a situation or event from deteriorating Emergency Operations: Emergency Operating Procedures (EOPs) guide system operator actions when an event occurs on the electric system that has the potential to, or actually does, negatively impact system reliability. EOPs are communicated in escalating order as alerts, warnings, and events Cold Weather Alert Severe Weather Alert Conservative Operations Declarations Maximum Generation Alert Maximum Generation Warning Maximum Generation Event (Step 1) / EEA*1 Maximum Generation Event (Steps 2, 3, 4) / EEA*2 Maximum Generation Event (Step 5) / EEA*3 Extreme temperatures forecasted Adverse weather conditions within the area Reliability issues may be possible MISO forecasts a potential capacity shortage Preparing for a possible event Taking steps to preserve operating reserves Taking steps to preserve firm load Actual event occurring - shed firm load and/or perform rolling brownouts or blackouts for defined area 60 *NERC Emergency Energy Alert (EEA)

61 Conservative System Operations MISO is responsible for determining, declaring, coordinating (when time permits) and communicating Conservative System Operations for the purpose of maximizing MISO s ability to operate the Bulk Electric System (BES) reliably during periods of extreme weather conditions and other abnormal circumstances that pose an imminent threat to the power grid. Five declarations are used to prepare operating personnel and facilities for extreme weather conditions or abnormal conditions that will, or have the potential to, impact the Bulk Electric System (BES): Conservative System Operations Severe Weather Alert Hot Weather Alert Cold Weather Alert Geo-Magnetic Disturbance Warning 61

62 Cold Weather Alert Cold Weather Alert may or may not coincide with a Conservative System Operations declaration, and can be for any portion of the MISO system. Cold Weather Alert TOPs and GOPs review plans to determine if any scheduled or in process maintenance or testing on monitoring, control, transmission, or generating equipment can be deferred or cancelled GOPs shall report and provide updates to the MISO Regional Generation Dispatcher (RGD) concerning all fuel/environmental limited resources for the duration of the Alert 62

63 To gain access to certain resources, MISO must progress through its Maximum Generation Emergency Procedures Tier I Offer Floor Event - Step 1: a) Commit AME b) Implement Emergency Max Limits c) Declare NERC Energy Emergency Alert (EEA) 1 - All available non-emergency resources in use Tier II Offer Floor Event Step 2: a) Declare NERC EEA 2 - Load Mgmt procedures in effect b) Implement LMR (BTMG & DR) & Load Management Measures (LMM) Stage 1 c) Commit Emergency Demand Response (EDR) d) Implement Emergency Energy Purchases Event - Step 3: a) Utilize Operating Reserves b) Instruct load reduction of Load Management Measures (LMM) Stage 2 63 For more information - MISO Operating Procedures One-Pager and Appendix

64 Maximum Generation Emergency - Alert Level The purpose of the Max Gen Alert is to communicate system conditions for Operational Awareness. Steps in this level are designed to prepare entities for actions during subsequent levels of the Max Gen process. Each level/step actions are exhausted, time permitting, prior to going to next step. Define boundaries of Alert Area and start and end time of Alert period Declare or update Conservative System Operations as appropriate Identify the amount of available External Resources that can be scheduled into the Alert area Identify the amount of non-firm Export Schedules from Alert area available for curtailment during a Warning declaration MPs to ensure energy interchange transactions sourcing or sinking in the MISO Balancing Authority Area (MBAA) are accurate 64

65 Maximum Generation Emergency - Alert Level Communicate! Determine amount of increased transfer capability and/or amount of transmission constraint stranded generation that can be made available MPs and LBAs ensure LMR availability data, self-scheduled LMR and LMM information in the MCS-LMR Tool is updated and accurate Coordinate with TOs to determine the availability of any transmission system reconfiguration options in the shortage area Issue any projections, declarations, or specific instructions via MCS 65

66 Maximum Generation Emergency - Warning Level Max Gen Warning indicates that Operating Reserve requirements may not be met in the near future without taking actions Collect and review LMR availability via the MCS LMR Tool Ensure use of Economic Maximum Limits by MISO processes (MPs to review limits and ensure all ranges are offered) Review Emergency Demand Response (EDR) offers to determine availability. MPs to ensure correct availability data is entered in the Tool LBAs may issue public conservation announcements and/or public appeals 66

67 Maximum Generation Emergency - Warning Level Step 1: Instruct available External Resources (Module E registered Capacity Resources) to be scheduled into the MBAA in the amount required to relieve the shortage condition. Step 2: Curtail non-firm Export Schedules from the Warning Area in the amounts required to relieve the shortage condition. Step 3: Instruct TOs to implement reconfiguration options expected to increase transfer capability into the Warning Area and/or make transmission constraint stranded generation available in the amount required to relieve the shortage condition. 67

68 Maximum Generation Emergency - Event Level When MISO cannot meet forecasted Energy and Operating Reserve requirements with Economic Maximum Limits Commit Generation Resources, DRR Type 1 and DRR Type 2 that are Available Max Emergency (AME) Implement Emergency Generation Limits Declare NERC Energy Emergency Alert (EEA) Level 1 All available Resources are in use 68

69 Maximum Generation Emergency - Event Level Max Gen Event Step 2 is the implementation of Load Management actions. These resources include LMRs, LMMs, EDRs Declare NERC EEA Level 2 Load Management in effect Instruct Load to be reduced via Module E Load Modifying Resources (LMRs) and reduction via Load Management Measures Stage 1 Commit EDR offers, available in the event area, in merit order Emergency purchases from neighboring BAs (excess energy) Instruct LBAs to issue public appeals to reduce demand 69

70 Maximum Generation Emergency - Event Level Operating Reserves have been depleted. Use Load Management Measures Stage 2 Supplemental, then spinning reserves are utilized as cooptimized by Unit Dispatch System (UDS) Instruct Load to be reduced by Load Management Measures Stage 2 by LBAs - Reduction by LBA will be determined by prorated of total amount of resources available in Event Area - Includes voltage reductions 70

71 Maximum Generation Emergency - Event Level Implement Reserve Call from Contingency Reserve Sharing Group Implement additional Emergency energy purchases (typically from neighboring Balancing Authority's Operating Reserves) 71

72 Maximum Generation Emergency - Event Level Firm Load Shed in progress or imminent Declare NERC EEA Level 3 Firm Load interruption imminent or in progress Direct Firm Load Shedding in the defined Event Area by LBA 72

73 Maximum Generation Emergency - Termination Steps taken during Maximum Generation Emergency will be restored in the reverse order from implementation Short-term forecasted Load returned below (and continuing below) the sum of the economic maximums of online Resources plus scheduled interchange Maximum Generation Event is terminated Generation Resources should verify they have returned to normal economic operating ranges 73

74 LMR Process & Steps taken by MISO & Market Participants (MPs) / Asset Owners (AOs) 74

Winter Readiness Workshop. October 29, 2018

Winter Readiness Workshop. October 29, 2018 2018-19 Winter Readiness Workshop October 29, 2018 1 Agenda 1. Introduction/Opening Remarks R. Benbow 2. Preparedness a. Winter 2017-18 Lessons Learned R. Benbow b. Offer Cap Status C. Hansen c. Winter

More information

Capacity Shortages RE Module. Interconnection Training Program PJM State & Member Training Dept.

Capacity Shortages RE Module. Interconnection Training Program PJM State & Member Training Dept. Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 Project 2014-03 Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014 This mapping document showing the translation of Requirements in the following currently-enforceable

More information

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The 1 2 3 4 LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The Transmission Provider will calculate and post the Planning

More information

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization - 1 - Introduction The North American Electric Reliability Council (NERC) requires every

More information

NERC Reliability Functional Model

NERC Reliability Functional Model NERC Reliability Functional Model Function Definitions and Responsible Entities Version 3 Approved by Standing Committees: Operating Committee: December 6, 2006 Planning Committee: December 6, 2006 Standards

More information

Proposed Definitions for the NERC Glossary of Terms Project : Emergency Operations

Proposed Definitions for the NERC Glossary of Terms Project : Emergency Operations Proposed Definitions for the NERC Glossary of Terms Project 2009-03: Emergency Operations The Emergency Operations Standards Drafting (EOP SDT) proposes revisions to a defined term in the NERC Glossary

More information

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering 2017 ITPNT 2 0 1 7 I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e June 15, 2016 Engineering Revision History Date or Version Number Author Change Description Comments

More information

Outage Coordination Training MISO Training

Outage Coordination Training MISO Training MISO Last material update: 05/19/2015 Course Content and Disclaimer 2 1 2 3 4 Course Description This course will review MISO's outage study processes and the coordination opportunities with TOs and MPs.

More information

5.4 Post Contingency Local Load Relief Warning

5.4 Post Contingency Local Load Relief Warning 5.4 Post Contingency Local Load Relief Warning Post Contingency Local Load Relief Warning Non-Market Post Contingency Local Load Relief Warning The purpose of the Post Contingency Local Load Relief Warning

More information

Implementation Plan IRO Reliability Coordination Current Day Operations

Implementation Plan IRO Reliability Coordination Current Day Operations Implementation Plan IRO-005-4 Reliability Coordination Current Day Operations Approvals Required IRO-005-4 Reliability Coordination Current Day Operations Prerequisite Approvals None Revisions to Glossary

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

Resource Availability and Need

Resource Availability and Need Resource Availability and Need Issues Statement Whitepaper March 30, 2018 Table of Contents 1. Executive Summary... 2 2. Aging and Retirement of the Portfolio s Generating Units... 5 2.1. Retirements reduce

More information

Load Modifying Resources. Capacity Instruments affecting Resource Availability and Need

Load Modifying Resources. Capacity Instruments affecting Resource Availability and Need Capacity Instruments affecting Resource Availability and Need May 25, 2018 Purpose Statement Review the participation and historic performance of Load Modifying Resources (LMRs) in MISO s Capacity and

More information

SPP Emergency Operations: 2016 Summer Preparedness Workshop

SPP Emergency Operations: 2016 Summer Preparedness Workshop SPP Emergency Operations: 2016 Summer Preparedness Workshop AGENDA 9:00 9:15 Welcome.. CJ Brown 9:20 9:30 EOP Update Process... Kim Gorter 1. Review 2. Posting Red-line Version 3. Stakeholder Interaction

More information

Gas-Electric System Needs and Reliability

Gas-Electric System Needs and Reliability Gas-Electric System Needs and Reliability Mike Nygaard Engineer, Policy Studies, MISO Geographically, MISO is the largest Independent System Operator in North America Transmission: ~66,000 miles Peak load:

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b

Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b Appendix 9C1 Transmission Loading Relief Procedure Eastern Interconnection Version 2b [Appendix 9C1B, Interchange Transaction Reallocation During TLR Levels 3a and 5a ] [Appendix 9C1C, Interchange Transaction

More information

NERC Reliability Functional Model Technical Document Version 5

NERC Reliability Functional Model Technical Document Version 5 Reliability Functional Model Technical Document Version 5 Prepared by the Functional Model Working Group This document is a companion to Version 5 of the Functional Model. It provides context, explanations,

More information

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005 2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

Standard IRO Reliability Coordination Transmission Loading Relief

Standard IRO Reliability Coordination Transmission Loading Relief Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 Evolution of the Grid in MISO Region Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017 1 MISO s mission is to ensure reliable delivery of low-cost energy through efficient,

More information

Functional Entity Roles and Responsibilities

Functional Entity Roles and Responsibilities Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...

More information

Transmission Loading Relief Eastern Interconnection

Transmission Loading Relief Eastern Interconnection Transmission Loading Relief Eastern Interconnection Purpose: This standard defines procedures for curtailment and reloading of Interchange Transactions to relieve overloads on transmission facilities modeled

More information

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to

More information

Standard EOP Capacity and Energy Emergencies

Standard EOP Capacity and Energy Emergencies A. Introduction 1. Title: Capacity and Energy Emergencies 2. Number: EOP-002-2 3. Purpose: To ensure Reliability Coordinators and Balancing Authorities are prepared for capacity and energy emergencies.

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 11 Congestion and Marginal Losses Congestion and Marginal Losses The locational marginal price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018 Operations Report Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average

More information

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012 Wind Update Renewable Energy Integration Lessons Learned March 28, 212 Contents Summary Review of Historical Wind Growth and Output Impact of Wind on Operations Wind Curtailments Dispatchable Intermittent

More information

PJM Cold Snap Performance Dec. 28, 2017 to Jan. 7, 2018

PJM Cold Snap Performance Dec. 28, 2017 to Jan. 7, 2018 PJM Cold Snap Performance PJM Interconnection Feb. 26, 2018 Note: On February 27, 2018, this paper was updated to correct minor clerical errors. On March 3, 2018, Figure 22 was updated to correct the colors

More information

Energy Market. Table 3 1 The Energy Market results were competitive

Energy Market. Table 3 1 The Energy Market results were competitive Section 3 Energy Market Energy Market The PJM Energy Market comprises all types of energy transactions, including the sale or purchase of energy in PJM s Day-Ahead and Real-Time Energy Markets, bilateral

More information

Ensuring Resource Availability meets Need (RAN) in MISO. MRO Spring Reliability Conference May 23, 2018 Kevin Vannoy, Director Market Design

Ensuring Resource Availability meets Need (RAN) in MISO. MRO Spring Reliability Conference May 23, 2018 Kevin Vannoy, Director Market Design Ensuring Resource Availability meets Need (RAN) in MISO MRO Spring Reliability Conference May 23, 2018 Kevin Vannoy, Director Market Design Purpose & Key Takeaways Purpose: Discuss MISO s Resource Availability

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information

MIDWEST ISO UPDATE. Sherman Elliott Manager State Regulatory Affairs

MIDWEST ISO UPDATE. Sherman Elliott Manager State Regulatory Affairs MIDWEST ISO UPDATE Sherman Elliott Manager State Regulatory Affairs June 2, 2006 RTO Services Monitor flow of power over the high voltage transmission system Schedule transmission service Security analysis

More information

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018 Operations Report Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 5.0 4.5 4.0 On-Peak Average

More information

Energy Market. Highlights

Energy Market. Highlights Section 2 Energy Market Energy Market The PJM Energy Market comprises all types of energy transactions, including the sale or purchase of energy in PJM s Day-Ahead and Real-Time Energy Markets, bilateral

More information

The Year to Date in PJM: Operations and Markets

The Year to Date in PJM: Operations and Markets The Year to Date in PJM: Operations and Markets Kerry Stroup Manager, State Government Policy PJM Interconnection OMA Energy Committee July 30, 2014 OMA Energy Committee Presentation Outline PJM s mission:

More information

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 3 3.1. Order of Steps... 3 3.2. Restricted

More information

JCM Drill Down Report. February 19, 2015

JCM Drill Down Report. February 19, 2015 JCM Drill Down Report February 19, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

Coordination Between the Gas and Electric Industries: Understanding the Problem and Assessing the Solutions

Coordination Between the Gas and Electric Industries: Understanding the Problem and Assessing the Solutions Coordination Between the Gas and Electric Industries: Understanding the Problem and Assessing the Solutions Floyd L. Norton IV J. Daniel Skees December 5, 2012 www.morganlewis.com Presentation Overview

More information

Summary of M-13 Rev. 66 Changes

Summary of M-13 Rev. 66 Changes Summary of M-13 Rev. 66 Changes Dean Manno SOS-Joint meeting September 6 th, 2018 M-13, Rev. 66 Changes Overview of Changes: Cover to Cover Periodic Review Section 3.2 added Production System Freeze Change

More information

Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective

Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective Mark Lauby, Senior Vice President and Chief Reliability Officer North American Electric Reliability Corporation

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

Approved by Standing Committees Approved by Board of Trustees

Approved by Standing Committees Approved by Board of Trustees Reliability Functional Model Function Definitions and Responsible Entities Prepared by the Functional Model Working Group Version 4 Approved by Standing Committees Approved by Board of Trustees August

More information

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool 2016 Probabilistic Assessment December 5, 2016 Southwest Power Pool Table of Contents 1. Summary...2 a. SPP Planning Coordinator Footprint...2 b. Seasonal Capacity Totals... Error! Bookmark not defined.

More information

JCM Drill Down Report -- Draft. March 21, 2014

JCM Drill Down Report -- Draft. March 21, 2014 JCM Drill Down Report -- Draft March 21, 2014 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill

More information

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report

Contents. DRAFT Capacity Deliverability Fact Finding Summary Report DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system

More information

IMM Quarterly Report: Fall 2017

IMM Quarterly Report: Fall 2017 IMM Quarterly Report: Fall 2017 MISO Independent Market Monitor David Patton, Ph.D. Potomac Economics December 5, 2017 Highlights and Findings: Fall 2017 The MISO markets performed competitively this fall,

More information

Energy Uplift (Operating Reserves)

Energy Uplift (Operating Reserves) Section 4 Energy Uplift Energy Uplift (Operating Reserves) Energy uplift is paid to market participants under specified conditions in order to ensure that resources are not required to operate for the

More information

Third Incremental Auction shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates.

Third Incremental Auction shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates. Definitions T U - V Tangible Net Worth: Tangible Net Worth shall mean all assets (not including any intangible assets such as goodwill) less all liabilities. Any such calculation may be reduced by PJMSettlement

More information

Attachment 1-IRO Transmission Loading Relief Procedure Eastern Interconnection

Attachment 1-IRO Transmission Loading Relief Procedure Eastern Interconnection Standard IRO-006-0 Reliability Coordination Transmission Loading Relief Attachment 1-IRO-006-0 Transmission Loading Relief Procedure Eastern Interconnection Purpose This standard defines procedures for

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING December 22, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

Broader Regional Markets

Broader Regional Markets Attachment B Broader Regional Markets, Long-Term Solutions to Lake Erie Loop Flow Slide Presentation from the December 15, 2009 Technical Conference Held in Carmel, Indiana LAKE SUPERIOR LAKE SUPERIOR

More information

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria 5/1/2018 OC Meeting PJM Manual M36 System Restoration A.1 Critical Black Start Criteria A.1.1 Goal PJM and its stakeholders have developed requirements for the amount and redundancy of Black Start generation

More information

Joint and Common Market ITEM 4 PSEUDO TIES

Joint and Common Market ITEM 4 PSEUDO TIES Joint and Common Market ITEM 4 PSEUDO TIES Agenda 1. Overview 2. Background 3. Common Issues 4. PJM Update 5. MISO Update 6. Double-Counting 7. Next Steps 2 Overview Purpose Provide a status update on

More information

Adequate Summer Electricity Supplies Projected

Adequate Summer Electricity Supplies Projected Adequate Summer Electricity Supplies Projected Summer 2017 Reliability Assessment Overview The comprehensive reliability assessment conducted by the Northeast Power Coordinating Council, Inc. (NPCC) projects

More information

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Agenda Item 3.b.i ORS Meeting September 7-8, 2016 RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016 Introduction The Southern Company Services is the Southeastern

More information

Reliability Coordinator Area System Operating Limit Methodology

Reliability Coordinator Area System Operating Limit Methodology Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power

More information

Northwest Power Pool Processes

Northwest Power Pool Processes Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 11 Congestion and Marginal Losses Congestion and Marginal Losses The locational marginal price (LMP) is the incremental price of energy at a bus. The LMP at a bus is the sum of three components:

More information

Ancillary Service Markets

Ancillary Service Markets Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Energy Markets - The Basics

Energy Markets - The Basics Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

Dispatchable Intermittent Resource (DIR) Workshop

Dispatchable Intermittent Resource (DIR) Workshop Dispatchable Intermittent Resource (DIR) Workshop April 13, 2011 DIR Registration April Peterson 1 Market Participant v. Asset Owner Market Participant represents the highestlevel data component of Commercial

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. SOUTHWEST POWER POOL, INC.'s REPORT REGARDING FUEL ASSURANCE ISSUES

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. SOUTHWEST POWER POOL, INC.'s REPORT REGARDING FUEL ASSURANCE ISSUES UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Centralized Capacity Markets in Regional Transmission Organizations and Independent System Operators Winter 2013-2014 Operations

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report February 28, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan

More information

Independent Transmission Organization. Stakeholder s Meeting December 2006

Independent Transmission Organization. Stakeholder s Meeting December 2006 SPP Presentation Independent Transmission Organization Stakeholder s Meeting December 2006 2 Introduction Participants Agenda Facilities 3 ITO Overview EON US (LG&E/KU) Overview EON US Tariff vs MISO Tariff

More information

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper

Toward Ensuring Reliability: Reliability Performance Metrics. A NERC Staff White Paper Toward Ensuring Reliability: Reliability Performance Metrics A NERC Staff White Paper Table of Contents Table of Contents Table of Contents... 2 Executive Summary... 3 Metrics Objective... 5 Metrics Background...

More information

Gas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI

Gas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI Gas-Electric Infrastructure Challenges WPUI Gas Program September 17, 2012 MISO EPA/Gas related efforts - Timeline EPA Rules & Regulations MISO EPA Impact Study, Oct 2011 Gas Consultant Phase 1 Study,

More information

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION Rock Island Clean Line LLC ) ) Petition for an Order granting Rock Island ) Clean Line a Certificate of Public Convenience ) and Necessity pursuant to Section

More information

Summary of 2016 MISO State of the Market Report

Summary of 2016 MISO State of the Market Report Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor

More information

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists

More information

April 27, Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6546 Mercantile Way P.O. Box Lansing, MI 48909

April 27, Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6546 Mercantile Way P.O. Box Lansing, MI 48909 Matthew R. Dorsett Corporate Counsel Direct Dial: 317-249-5299 E-mail: mdorsett@misoenergy.org April 27, 2011 Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6546 Mercantile Way

More information

PJM Manual 29: Billing. Revision: 23 Effective Date: January 1, Prepared by Strategic Market Services Department

PJM Manual 29: Billing. Revision: 23 Effective Date: January 1, Prepared by Strategic Market Services Department PJM Manual 29: Billing Revision: 23 Effective Date: January 1, 2012 Prepared by Strategic Market Services Department PJM 2012 Table of Contents PJM Manual 29: Billing Table of Contents Table of Contents...

More information

JCM Drill Down Report. May 27, 2015

JCM Drill Down Report. May 27, 2015 JCM Drill Down Report May 27, 2015 The purpose of this document is to provide a brief description of each component listed on the JCM Work Plan Timeline compiled by PJM and MISO. This Drill Down Report

More information

Interface Pricing Approach Whitepaper May 2015

Interface Pricing Approach Whitepaper May 2015 Interface Pricing Approach Whitepaper May 2015 This white paper represents MISO's current progress and assessment on the Interface Pricing issue. Additional analysis is underway and will be shared with

More information

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents

More information

Overview. IEEE Boston Chapter ISO New England Inc.

Overview. IEEE Boston Chapter ISO New England Inc. Overview New England s power system will undergo major changes in the coming years to integrate renewables, demand response, smart grid and other new technologies Good planning helps overcome integration

More information

Reliability Coordinator Transition Coordination Group Update

Reliability Coordinator Transition Coordination Group Update Reliability Coordinator Transition Coordination Group Update WECC RC Forum 1/24/19 Presented by Jim Shetler / Eric Whitley - RCTCG Agenda RC Transition Project Roll-Out Update Update on Activities to Date

More information

Energy Uplift (Operating Reserves)

Energy Uplift (Operating Reserves) Section 4 Energy Uplift Energy Uplift (Operating Reserves) Energy uplift is paid to market participants under specified conditions in order to ensure that resources are not required to operate for the

More information

Capacity Performance Training. March 16, 2015

Capacity Performance Training. March 16, 2015 Capacity Performance Training March 16, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

2750 Monroe Blvd Audubon, PA

2750 Monroe Blvd Audubon, PA 2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018 Operations Report Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, 2019 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average Off-Peak

More information

NERC Probabilistic Assessments Overview & Future Improvements

NERC Probabilistic Assessments Overview & Future Improvements NERC Probabilistic Assessments Overview & Future Improvements Noha Abdel-Karim, PhD. NERC IEEE LOLEWG Meeting July 31, 2015 Overview NERC Probabilistic Assessment (ProbA) reports extend the LTRA data with

More information

MISO-PJM Joint and Common Market Drill Down Report

MISO-PJM Joint and Common Market Drill Down Report MISO-PJM Joint and Common Market Drill Down Report August 22, 2017 The purpose of this document is to provide a brief description of each component listed on the Joint and Common Market (JCM) Work Plan

More information

Weather and Environmental Emergencies RE Module. Interconnection Training Program PJM State & Member Training Dept.

Weather and Environmental Emergencies RE Module. Interconnection Training Program PJM State & Member Training Dept. Disclaimer This training presentation is provided as a reference for preparing for the PJM Certification Exam. Note that the following information may not reflect current PJM rules and operating procedures.

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

2007 State of the Market Report

2007 State of the Market Report Volume 2: Detailed Analysis Market Monitoring Unit March 11, 2008 printed: 04/24/08 Preface The Market Monitoring Unit of PJM Interconnection publishes an annual state of the market report that assesses

More information

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology Executive Summary Deliverability is an essential element of any resource adequacy requirement. Specifically, Load

More information

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Last Revised: May 25, 26 Disclaimer: "MIDWEST ISO MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND, EXPRESS

More information