Utah Compressed Air Energy Storage (CAES) Project Phase 1 Economic Evaluation using PLEXOS

Size: px
Start display at page:

Download "Utah Compressed Air Energy Storage (CAES) Project Phase 1 Economic Evaluation using PLEXOS"

Transcription

1 Utah Compressed Air Energy Storage () Project Phase 1 Economic Evaluation using PLEXOS Tao Guo, Ph.D., Regional Director, WEST Coast - USA Guangjuan Liu, Ph.D., Senior Consultant Xiaolong Wang, Consultant Yannick Degeilh, Ph.D., Consultant Energy Exemplar, LLC 3013 Douglas Blvd, Suite 120 Roseville, CA U.S.A. Prepared for City of Burbank Water and Power 164 W. Magnolia Blvd. Burbank, CA Schulte Associates LLC 2236 Coley Forest Place Raleigh, NC P a g e

2 List of Acronyms ANL Argonne National Laboratory AS PSH Adjustable Speed Pumped-storage Hydro Generator AS Ancillary Services BA Balancing Area BAA Balancing Authority Area BPA Bonneville Power Administration BWP City of Burbank Water and Power Compressed Air Energy Storage CAISO California Independent System Operator COI California-Oregon Interface DA Day-Ahead DOE US Department of Energy FS PSH Fixed Speed Pumped-storage Hydro Generator GWh Gigawatt-hours HA Hour-Ahead LTPP Long Term Procurement Plan NREL National Renewable Energy Laboratory OPF Optimal Power Flow PACW Pacific Corps West PNNL Pacific Northwest National Laboratory PSH Pumped-storage Hydro Generator RPS Renewable Portfolio Standards RT Real Time SCED Security Constrained Economic Dispatch SCUC Security Constrained Unit Commitment TEPPC Transmission Expansion Planning and Policy Committee WI Western Interconnection WECC Western Electricity Coordinating Council WWSIS Western Wind and Solar Integration Study 2 P a g e

3 Executive Summary Energy Exemplar was engaged by Schulte Associates LLC, consultant for the City of Burbank Water and Power (BWP), for the economic evaluation of the Utah Project using PLEXOS, an integrated power market simulation software suite. The Utah Project Phase 1 is proposed to be a 300 MW generation facility located at Delta, Utah and connected to the Intermountain Power Project (IPP) substation. This project has transmission access to Southern California through the DC-Tie from the Intermountain substation to the Adelanto substation close to the Los Angeles Basin. Phase I is an initial effort leading to a larger, 1200 MW /renewable energy combination project to follow. In order to capture the benefit of this Utah project in detail, a WECC database with the nodal transmission representation was prepared and configured to be as close to reality as possible. The WECC system is simulated for years 2020 to Assumptions The database prepared for this study was originally from the WECC TEPPC 2024 Common Case database version [1]. It has been converted to a PLEXOS database and further updated with California-specific assumptions, and renewable generation profiles and flexibility reserve requirements. The TEPPC 2024 database covers the entire footprint of the Western Interconnection (WI), including the provinces of British Columbia and Alberta in Canada, and Comision Federal de Electricidad (CFE) in northern Mexico. The additional assumption updates include California low frequency modeling. In the California transmission operation, certain low frequency reliability requirements are modeled for BANC, TID, SCE, SDGE, and IID. 25% of the area loads are covered by the local generations with moving mass such as thermal or hydro generators. Renewable Generation Profiles. The simulations are performed at the hourly interval. The hour-ahead wind and solar generation profile forecasts are derivated from the 5-minute actual wind and solar generation profiles. The 5- minute actual wind and solar generation profiles in year 2024 were received from NREL [6] based on year 2006 for the entire WECC footprint. The one-hour persistency forecast technique is used to generate the hour-ahead wind and solar generation profiles. The solar generators include the solar generators with and without the tracking system. Regional loads. The Hour-Ahead (HA) regional load profiles in year 2020 were received from Pacific Northwest National Laboratory (PNNL) for the WECC VGS 1 There was no release note published for TEPPC 2024 Common Case version P a g e

4 study [5]. The load profiles in year 2020 were updated for year 2024 for the given annual peaks and load energies using the PLEXOS time series build function. Contingency, Flexibility and Regulation Reserves. The contingency, flexibility and regulation reserve requirements were generated based on the 5-minute actual net loads and the HA net loads in BAAs (a BAA net load is the BAA load less the solar and wind generation in the BAA). Modeling Approach and Scope The study is performed using the PLEXOS Energy-Ancillary Service-DC-OPF cooptimization capability. The simulations are performed for each of the years 2022 to 2025 for the cases without and with the Utah project. All cases included the existing, 1900 MW IPP coal plant in operation. Results and Findings The findings of this study are summarized below. All the results mentioned here are based on the annual measurement from the simulations for years 2020 to The cost and revenue values are measured based on real, 2014 US dollars including real escalation to the year shown, but excluding general inflation. WECC Production Cost The WECC total production cost saving by year due to the Utah project, including the reserve provision shortfall cost reductions (i.e., ancillary services ), are listed in the following chart. In addition to reserve provisions, production costs include fuel, variable operating and maintenance (O&M) costs, startup costs, and carbon emissions (CO2) costs for resources in and serving California. 35,000 30,000 25,000 20,000 15,000 10,000 5,000 WECC Total Production Cost Savings in 000$ due to Utah Project (Including Reserve Shortfall Cost Reduction) - 4 P a g e Production Cost Savings

5 It is noticed that, when the renewable energies reach 20% in WECC and 37% in California (including the OOS renewables) in year 2023, the WECC production cost savings due to the Utah project sharply increase to nearly 20 million dollars. This step change is not due to a year-to-year discontinuity in Plexos model input assumptions. Instead, it appears to represent a tipping point inflection in the WECC system s needs for storage as the California RPS approaches 38% to 40%. Utah Project Operation Performance Utah Project earns energy arbitrage revenue and AS revenues. The following charts display the Utah project operation, operating costs, energy and AS revenues, and net operating revenues. 1,400 1,200 1, Generation and Total Reserve Provisions (GWh) by Year Generation Reserve Provision 5 P a g e

6 Operating Cost (000$) by Year 25,000 20,000 15,000 10,000 5, Generation Cost Pumping Cost Operating Revenue (000$) by Year 25,000 20,000 15,000 10,000 5, Energy Revenue AS Revenue 6 P a g e

7 Net Operating Revenue (000$) by Year 12,000 10,000 8,000 6,000 4,000 2, Net Revenue The Utah project net operating revenue is calculated as Net Revenue = Energy Revenue (LMP x Generation) + Reserve Revenue (Reserve Shadow Price x Reserve Provision) Fuel and VO&M Cost Pumping Cost (LMP x Pumping Load) Usually, the net revenue represents the profit of the project that is operated as an Independent Power Producer (IPP) in a power market. One can notice that the net revenue increases from 3 million dollars in year 2020 to 11 million dollars in year Size of the Storage Cavern Thourgh the storage size of the Utah Project is defined as 7.2 GWh, the max compressing energy is 0.54 GWh the represents nearly 2 consecutive hours full capacity (300 MW) compressing; the max discharging energy is 1.22GWh that represents nearly 4 consecutive hours full capacity (300 MW) discharging. Impact on Other Generators The following table shows the generation changes in WECC by generator type due to the Utah project. The following can be observed. 1. With the Utah project, the Coal generation ( COAL in the table) in WECC is reduced with the Utah project in years 2020 and 2021, but increased from year 2022 to year P a g e

8 2. With the Utah Project, the CC and CT generation 2 ( CC and CT in the table) in WECC is increased in years 2020 and 2021, but reduced from year 2022 to year From the observation point 1, the CO2 production in WECC is reduced in years 2020 and 2021 but increased in years 2022 to With the renewable generation increase from year 2020 to year 2025 and due to the Utah project, the activities of the pumped storage generators ( PSH in the table) and the energy storage generators ( ES in the table) are increased. The Utah project shares the reserve provisions from the PSH and ES facilities so that the PSH and ES facilities can generate more energy. 2 In the WECC TEPPC database, the CT generator category includes co-generation facilities. 8 P a g e

9 WECC Generation in GWh by Generator Type Generator Type (- ) (- ) (- ) (- ) (- ) (- ) - 84 (84) (109) (124) (172) (208) (233) Coal 234, , , , , ,159 (276) 232, ,360 (364) 232, ,552 (93) 231, ,208 (542) Hydro 239, ,605 (31) 239, ,591 (2) 239, , , , , ,563 (32) 239, ,580 2 Nuclear 56,561 56,561-56,561 56,561-56,561 56,561 (0) 56,561 56,561 (0) 56,561 56,561 (0) 56,561 56,561 (0) Others 5,328 5,381 (52) 5,307 5,358 (51) 5,267 5,310 (42) 5,296 5,313 (17) 5,311 5,332 (22) 5,354 5,379 (25) ST 2,266 2,317 (51) 2,343 2, ,330 2,351 (22) 2,359 2, ,426 2,466 (40) 2,478 2,502 (23) Bio 18,351 18,414 (63) 18,300 18,349 (49) 18,197 18,236 (38) 18,120 18,166 (46) 18,018 18,083 (65) 17,961 18,000 (39) CC 253, , , ,505 (403) 253, , , , , , , , CT 35,663 35,756 (93) 36,937 36, ,563 37,807 (244) 39,104 39, ,412 40, ,698 41, DR-EE 3,099 3,099-3,409 3,409-3,750 3,750-4,125 4,125-4,537 4,537-4,990 4,990 - ES 1,387 1,449 (62) 1,449 1,502 (53) 1,504 1,552 (48) 1,542 1,589 (47) 1,587 1,616 (29) 1,603 1,645 (42) Geo 27,222 27,222 (0) 27,211 27, ,199 27,200 (1) 27,187 27,188 (2) 27,183 27,183 (0) 27,172 27,179 (7) Small Hydro 4,278 4,278-4,278 4,278-4,278 4,278-4,278 4,278-4,278 4,278-4,278 4,278 - PSH 3,846 4,003 (158) 3,972 4,108 (136) 3,983 4,137 (155) 4,056 4,214 (157) 4,122 4,256 (134) 4,196 4,347 (151) PV-BTM 15,677 15,677-17,145 17,145-18,613 18,613-20,081 20,081-21,549 21,549-23,017 23,017 - Solar 40,031 40,031-43,780 43,780 (0) 47,527 47,527 (0) 51,268 51, ,001 55,002 (0) 58,722 58,723 (1) Wind 60,083 60,083-65,709 65,709-71,336 71,336-76,962 76,962-82,583 82,588 (5) 88,208 88,213 (4) Total 1,001,362 1,001,699 (337) 1,013,456 1,013,779 (323) 1,025,550 1,025,898 (347) 1,037,842 1,038,236 (394) 1,050,292 1,050,661 (369) 1,062,860 1,063,282 (422) The following table shows the generation changes in California by generator type due to the Utah project. The followings can be observed. 1. With the Utah project, the Coal generation ( COAL in the table) in California is increased slightly in years 2020 and 2025; 9 P a g e

10 2. With the Utah Project, the CC and CT generation 3 ( CC and CT in the table) in California is increased in years 2020 and 2021, but reduced from year 2022 to year California Net Import reduced gradually from year 2020 to year 2025 due to the renewable generation increases in California. However, with the Utah Project, the California net import is reduced in year 2020 and 2021 but increased in years 2022 to 2025 as opposed to the cases without the Utah Project. 4. With the renewable generation increase from year 2020 to year 2025 and due to the Utah project, the activities of the pumped storage generators ( PSH in the table) and the energy storage generators ( ES in the table) are increased. The Utah project shares the reserve provisions from the PSH and ES facilities so that the PSH and ES facilities can generate more energy. Combining the observations of points 2 and 3, the CO2 production in California is increased in year 2020 and 2021 and is reduced in years 2022 to That is opposite to the trend of the CO2 production in WECC. These trends go in opposite directions over time because as load increases gradually and renewables increase over the study period, higher-cost natural gas-fired generation in California (compared to elselwhere in WECC) is at the margin more often later in the planning period. As a result, natural gas-fired generation in California is more likely to be offset by generation during the latter part of the study period. 3 In the WECC TEPPC database, the CT generator category includes co-generation facilities. 10 P a g e

11 California Generation in GWh by Generator Type Generator Type (- ) (- ) (- ) (- ) (- ) (- ) - 84 (84) (109) (124) (172) (208) (233) Coal 11,198 11,265 (68) 11,094 11,147 (53) 10,971 11,005 (34) 10,816 10,849 (33) 10,702 10,730 (29) 10,586 10,622 (35) Hydro 35,016 34, ,993 34,996 (3) 34,973 34,991 (17) 34,928 34,934 (6) 34,927 34, ,928 34,929 (1) Nuclear 17,114 17,114-17,114 17,114-17,114 17,114 (0) 17,114 17,114 (0) 17,114 17,114 (0) 17,113 17,113 (0) Others (18) (22) (16) (5) (8) (8) ST 1,580 1,627 (47) 1,642 1, ,607 1,627 (20) 1,596 1,611 (14) 1,594 1,640 (46) 1,598 1,611 (13) Bio 9,891 9,909 (18) 9,798 9,815 (17) 9,667 9,699 (32) 9,553 9,577 (23) 9,414 9,434 (20) 9,283 9,317 (34) CC 83,535 83,569 (34) 82,211 82,386 (176) 81,109 80, ,392 80, ,509 79, ,032 77, CT 9,462 9,480 (18) 9,593 9, ,631 9, ,689 9,722 (33) 9,768 9, ,829 9, DR-EE 3,099 3, ,409 3,409-3,750 3,750-4,124 4,124-4,537 4,537-4,990 4,990 0 ES 1,387 1,449 (62) 1,449 1,502 (53) 1,504 1,552 (48) 1,542 1,589 (47) 1,587 1,616 (29) 1,603 1,645 (42) Geo 14,476 14, ,466 14, ,455 14, ,443 14,443 (0) 14,441 14, ,431 14,436 (5) Small Hydro 4,206 4, ,206 4, ,206 4, ,206 4, ,206 4, ,206 4,206 0 PSH 3,393 3,551 (159) 3,531 3,660 (129) 3,556 3,705 (149) 3,644 3,789 (145) 3,711 3,836 (126) 3,769 3,913 (143) PV-BTM 12,022 12,022-13,147 13,147-14,273 14,273-15,399 15,399-16,524 16,524-17,650 17,650 - Solar 34,361 34, ,579 37,579 (0) 40,794 40,795 (0) 44,005 44, ,207 47,207 (0) 50,397 50,398 (1) Wind 16,203 16,203 (0) 17,721 17,721-19,238 19,238-20,756 20,756 (0) 22,273 22, ,790 23,790 - CA Total Gen 257, ,698 (486) 262, ,715 (485) 267, ,397 (268) 272, ,626 (123) 277, ,917 (92) 282, , Net Import 63,018 62, ,962 61, ,933 61,003 (70) 59,524 59,774 (250) 58,203 58,470 (266) 57,496 58,060 (564) Total 320, ,566 (336) 324, ,505 (313) 328, ,399 (338) 332, ,400 (373) 336, ,386 (358) 340, ,437 (411) 11 P a g e

12 Contributions to emission reductions With the Utah Project, due to the Coal generation reduction in WECC in years 2020 and 2021 but increase in years 2022 to 2025, the CO2 production in WECC is reduced in years 2020 and 2021 but increased in years 2022 to With the Utah Project, the coal generation in California is increased slightly for all years. This happens in part because the IPP Coal facility, whose generation increases with, is included in the California totals. However, due to the CC and CT generation increase in California in years 2020 and 2021 but reduction in years 2022 to 2025, the CO2 production in California is increased in years 2020 and 2021 but reduced in years 2022 to Year WECC CO 2 Production (1000 ton) CO 2 Reduct ion CO 2 Reducti on (%) CO 2 Cost ($000) only in CA CO2 Cost Reduct ion CO2 Cost Reducti on (%) , , % 1,286,122 1,288,657 (2,535) -0.20% , , % 1,273,065 1,275,707 (2,642) -0.21% , ,750 (185) -0.05% 1,261,043 1,260, % , ,156 (178) -0.05% 1,252,827 1,250,945 1, % , ,723 (21) -0.01% 1,244,758 1,242,042 2, % , ,634 (287) -0.08% 1,229,569 1,224,093 5, % Contribution to Renewable Generation Integration The pumping mode of the Utah project operation can absorb over-generation from the solar and wind generation. The Utah Project helps reduce solar and wind generation curtailment from 0 GWh in year 2020 to 5.11 GWh (0.61 GWh Solar generation curtailment reduction and 4.5 GWh wind generation curtailment reduction) in year P a g e

13 WECC Solar and Wind Generation Curtailment (GWh) without and with Utah Project Solar Curtailment in Wind Curtailment in Solar Curtailment in Wind Curtailment in Changes in STS Transmission Line Constraints Though the flow in STS transmission line (IPPDC-Tie) is always from North (Utah) to South (Southern California), one can observe that, at the hourly level, In most compressing hours, the flow from North to South is decreased as opposed to the flow in the Case. This indicates that some generation flows from Southern California to Utah to provide compressing energy for the Utah project. In most generating hours, the flow from North to South is increased as opposed to the flow in the Case. This indicates that some generation from the Utah flows to Southern California. 13 P a g e

14 Table of Contents 1 Introduction Database Preparation and Assumption Revisions Database Preparation Assumptions Updates California Low Frequency Modeling Renewable Generation Profiles Regional Loads Renewable Portfolio Standard Contingency, Flexibility and Regulation Reserves Utah Project Representation Gas Forecast Emission Market Modeling for California CAISO Export Transmission Charge Modeling Approaches PLEXOS SCUC/ED Algorithm Simulation Results Total WECC System Production Cost Utah Project Performance as Independent Power Producer (IPP) Total Generation and Generation Cost Changes by Generator Type Solar and Wind Generation Curtailment Emissions Production Intermountain Power Plant Production Intermountain Power Plant DC-Tie Findings WECC Production Cost Utah Project Operation Performance Impact on Other Generators Contributions to Emission Reductions Contribution to Renewable Generation Integration Storage Cavern Capacity References P a g e

15 List of Figures Figure 1-1 Utah Project Site Figure 2-1 Diagram of WECC Load Regions (Source: WECC) Figure 2-2 Illustration of a operation Figure 2-3 Compressing Mode Representation Figure 2-4 Generating Mode Representation Figure 3-1 PLEXOS Security Constrained Unit Commitment and Economic Dispatch Algorithm 45 Figure 4-1 STS Flow versus Utah Project Operation in a Typical Day of May, Figure 5-1 WECC Retail Loads and Renewable Generation Figure 5-2 WECC RPS % Figure 5-3 California Retail Load and Renewable Generation Figure 5-4 California RPS in % Figure 5-5 WECC Total Production Cost Saving due to Utah Project Figure 5-6 Utah Project Generation and Total Reserve Provision (GWh) Figure 5-7 Utah Operating Costs Figure 5-8 Utah Energy and AS Revenues Figure 5-9 Utah Project Net Operating Revenue Figure 5-10 WECC Renewable Generation Curtailment without and with Utah Project P a g e

16 List of Tables Table 2-1 Total Annual Energy Demand for BAAs in WECC for Year 2024 (GWh) Table 2-2 RPS by Technology and BAA for Year Table 2-3 RPS by Technology and BAA for Year Table 2-4 RPS by Technology and BAA for Year Table 2-5 RPS by Technology and BAA for Year Table 2-6 RPS by Technology and BAA for Year Table 2-7 RPS by Technology and BAA for Year Table 2-8 Mapping of Load Regions and Contingency Reserve Sharing Groups Table 2-9 Characteristics of Utah Project Representation in PLEXOS Table 2-10 Gas Price Forecast for Year 2024 by Month Table 2-11 Thresholds for Tiered CO2 Allowance Charge for Energy Import from NW into California Table 4-1 Penalty Prices for Reserve Provision Shortfall Table 4-2 WECC Production Cost Savings due to Utah Project Table 4-3 Utah Project Value as an Independent Power Producer Table 4-4 WECC Generation and Generation Cost Changes Due to Utah Project Table 4-6 California Generation and Generation Cost Changes Due to Utah Project Table 4-7 WECC Renewable Curtailment Reduction Due to Utah Project Table 4-8 WECC CO2 Reduction and CA CO2 Cost Reduction Due to Utah Project Table 4-9 Intermountain Power Plant Generation and AS Service Table 4-10 IPP DC-Tie flows with and without Utah Project Table 5-1 WECC Generation Changes by Generator Type due Utah Project Table 5-2 California Generation Changes by Generator Type Due to Utah Project Table 5-3 WECC CO2 Reduction and CA CO2 Cost Reduction Due to Utah Project P a g e

17 1 Introduction Energy Exemplar was engaged by Schulte Associates LLC for the Utah Compressed Air Energy Storage () project economic evaluation on behalf of the City of Burbank Water and Power, using PLEXOS, the Integrated Energy Model 4. This report presents the study assumptions, simulation solutions and analysis. As shown in Figure 1-1, the Utah Project Phase 1 is proposed to be a 300 MW generation, 300 MW compression facility located at Delta, Utah and connected to the Intermountain Power Project (IPP) substation. This project has transmission access to Southern California through the DC-Tie from the IPP substation to the Adelanto substation close to the Los Angeles Basin. In order to capture the benefit of the Utah project in detail, a WECC database with the nodal transmission representation was prepared and configured to be as realistic as possible. In this study, Energy Exemplar performed a Case study from year 2020 to year 2025 to better understand the Utah project s value for those years. The Case for these years and the case with the Utah project for these years are simulated to quantify the Utah project benefit to the WECC system. Figure 1-1 Utah Project Site 4 For more information about PLEXOS, visit 17 P a g e

18 For the rest of the report, Section 2 describes Database Preparation and Assumption Revisions; Section 0 describes Emission Market Modeling for California The California CO2 Market is modeled in this study. The CO2 price is $/lb (or about $25/ton) and the commitment and dispatch price of the thermal generators in California includes the CO2 cost component. The import energy from outside of California is charged with the GHG allowance as well. The energy imported from Northwest is charged at the tiered rate: at $0.523/MWh below the thresholds and $11.97/MWh above the thresholds. The thresholds follow the following patterns. Thresholds for the Tiered CO 2 Allowance Charge for Energy Import from NW into California Threshold (MW) Time Period 1120 M M M M04,D M04,D M M M M08,D M08,D M09 1 M10 97 M11 1 M12 Table 2-11 Thresholds for Tiered CO2 Allowance Charge for Energy Import from NW into California The GHG allowance charge for the energy import from Southwest to California is constant of $11.97/MWh CAISO Export Transmission Charge Any energy export from CAISO is charged at $10.83/MWh for the transmission usage. 18 P a g e

19 Modeling Approaches; Section 4 presents Simulation Results; Section 5 summarizes Findings. 19 P a g e

20 2 Database Preparation and Assumption Revisions 2.1 Database Preparation The database prepared for this study was originally from the WECC TEPPC 2024 Common Case database version [1]. It has been converted to a PLEXOS database and further updated with California-specific assumptions, and renewable generation profiles and contingency, flexibility and regulation reserve requirements. The TEPPC 2024 database covers the entire footprint of the Western Interconnection (WI). As shown in Figure 2-1, there are total of 43 load regions in this footprint, representing the Balance Authority Areas (BAAs), trading hubs, and/or the BAA s sub-regions in the United States, plus the provinces of British Columbia and Alberta in Canada, and Comision Federal de Electricidad (CFE) in northern Mexico. Figure 2-1 Diagram of WECC Load Regions (Source: WECC) 5 There was no release note published for TEPPC 2024 Common Case version P a g e

21 The entire WI network consists of over 19,000 buses, over 25,000 transmission lines and over 5,300 generators (including the renewables). For the detailed descriptions of the TEPPC 2024 Common Case database, please refer to reference [1]. 2.2 Assumptions Updates There are further assumption updates in the areas of California low frequency reliability requirements, WECC renewable generation profiles, and flexibility reserve requirements. This section provides some highlights of the major assumption updates California Low Frequency Modeling In the California transmission operation, certain low frequency reliability requirements are modeled for BANC, TID, SCE, SDGE, and IID. 25% of these area loads are covered by the local generation with moving mass such as thermal or hydro generators Renewable Generation Profiles The 5-minute actual wind and solar generation profiles in year 2024 were received from NREL [6] based on year 2006 for the entire WECC footprint. The one-hour persistency forecast technique is used to generate the hour-ahead wind and solar generation profiles. The solar generators include solar generators with and without tracking systems Regional Loads The Day-Ahead (DA) and Hour-Ahead (HA) load forecasts and 5-minute Real Time (RT) actual loads in year 2020 were received from Pacific Northwest National Laboratory (PNNL) for the WECC VGS study [5]. d on the three sets of loads in year 2020, the three sets of loads are built for year 2024 for the given annual peaks and load energies using the PLEXOS time series build function. The BAA s annual peak and load energies are from [1]. A summary of the total annual energy demand for the BAAs in WECC are listed in the following table 6. 6 Please refer to Figure 2-1 for the load area acronyms 21 P a g e

22 Demand Energy by BAAs in Year 2024 Gross Load in GWh (Including Transmission Load Regions and Distribution losses) Retail Load in GWh AESO 113, ,631 AZPS 36,149 32,751 AVA 14,592 13,220 BCHA 68,475 62,038 BPAT 60,903 55,178 CFE 14,475 13,114 CHPD 4,231 3,833 DOPD 1,829 1,657 EPE 10,814 9,798 IPFE 2,815 2,551 GCPD 5,253 4,759 IID 4,756 4,309 LDWP 35,296 31,978 IPMV 5,461 4,948 NEVP 29,213 26,467 NWMT 12,004 10,876 PAID 7,138 6,467 PAUT 32,078 29,063 PAWY 11,152 10,104 PACW 23,826 21,586 CIPB 52,500 47,565 CIPV 65,779 59,596 PGE 24,946 22,601 PNM 16,248 14,721 PSCO 43,025 38,980 PSEI 27,001 24,463 CISC 115, ,633 SCL 10,528 9,538 CISD 25,953 22,756 BANC 18,321 16,599 SPPC 15,336 13,895 SRP 40,145 36,371 TEPC 15,498 14,041 TIDC 3,045 2,759 TPWR 5,427 4,916 IPTV 11,865 10,750 WACM 32,164 29,141 WALC 5,380 4,874 WAUW P a g e

23 Demand Energy by BAAs in Year 2024 Gross Load in GWh (Including Transmission Load Regions and Distribution losses) Retail Load in GWh VEA WECC Total 1,023, ,694 CA Total 321, ,695 CAISO Total 260, ,050 Table 2-1 Total Annual Energy Demand for BAAs in WECC for Year 2024 (GWh) When generating the BAA loads for other years, the load growth rate is assumed 1.231% as stated in [9] in the State of California. The same load growth rate is assumed for other BAAs as an approximation Renewable Portfolio Standard The Renewable Portfolio Standard (RPS) in each BAA is obtained from variety of sources [1], [7], and [8]. The RPS percentage of a BAA is calculated as follows RPS% = RPS(GWh) PV_BTM(GWh) Load(GWh) PV_BTM(GWh) Where PV_BTM is the solar and distributed generation behind the meter. The RPS percentage in California is growing from 33% in year 2020 to 42% in year 2025, assuming 3% to 4% of RPS from Out Of State (OOS). In years 2020 to 2025, only the wind and solar generation are assumed to grow in the WECC. The renewable energy and load energy for years 2020 to 2025 by BAA and by technology are listed in the following tables. 23 P a g e

24 RPS in GWh by Technology and BAA in Year 2020 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% AESO 2, ,371 8,139 8,139 97,799 97,799 8% AVA 1, ,761 1,748 12,598 12,585 14% AZPS ,410 3,884 3,168 31,209 30,493 10% BANC , ,850 1,521 15,817 15,488 10% BCHA 2, ,429 4,351 4,351 59,117 59,117 7% BPAT 3, ,724 16,689 16,584 52,580 52,475 32% CFE - 5, ,679 5,679 12,497 12,497 45% CHPD ,653 3,650 0% CIPB ,226 1, ,607 2,381 45,326 43,100 6% CIPV 6,064 8,080 2,639 2,791 9, ,348 32,479 29,688 56,790 53,999 55% CISC 2,938 2, ,227 12,251 2,782 9,563 35,769 30,542 95,895 90,667 34% CISD ,158 4, ,376 7,452 6,294 21,685 20,527 31% DOPD ,579 1,578 0% EPE ,336 9,315 2% GCPD ,535 4,532 0% IID 860 3, , ,461 5,366 4,106 4, % IPFE ,431 2,421 6% IPMV ,715 4,706 18% IPTV ,244 10,231 8% LDWP ,523-1,137 5,085 4,463 30,472 29,851 15% NEVP ,221 25,040 3% NWMT ,277 1,343 1,320 10,364 10,341 13% 24 P a g e

25 RPS in GWh by Technology and BAA in Year 2020 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% PACW ,417 1,355 20,570 20,508 7% PAID ,163 6,155 8% PAUT ,756 1,650 27,694 27,589 6% PAWY ,905 2,925 2,905 9,628 9,609 30% PGE , ,537 21,479 5% PNM ,939 2,258 2,105 14,028 13,875 15% PSCO ,038 5,692 5,188 37,145 36,640 14% PSEI ,289 1,537 1,520 23,311 23,295 7% SCL ,089 9,083 0% SPPC 26 6, ,471 8,519 8,426 13,240 13,147 64% SRP , ,659 33,878 2% TEPC ,380 13,058 3% TH_Mea d % TH_PV % TIDC ,629 2,573 1% TPWR ,685 4,681 4% WACM ,769 27,526 2% WALC , ,645 4,423 20% WAUW % VEA % WECC Total 22,930 27,535 4,296 16,199 35,795 5,430 56, , , , ,051 18% CA 10,496 14,079 4,224 12,503 32,460 3,054 15,966 92,782 80, , ,693 31% 25 P a g e

26 RPS in GWh by Technology and BAA in Year 2020 Small Hydro PV-BTM Solar Solar Thermal Total RPS Total RPS w/o PV-BTM Retail Load Retail load after PV-BTM Region Bio Geo Wind RPS% Total CAISO Total 9,526 10,842 3,186 11,402 27,540 3,038 14,774 80,307 68, , ,769 33% Table 2-2 RPS by Technology and BAA for Year 2020 RPS in GWh by Technology and BAA in Year 2021 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% AESO 2, ,874 8,642 8,642 98,985 98,985 9% AVA 1, ,790 1,776 12,750 12,736 14% AZPS ,636 4,243 3,460 31,588 30,804 11% BANC , ,991 1,631 16,009 15,649 10% BCHA 2, ,563 4,485 4,485 59,834 59,834 7% BPAT 3, ,916 17,894 17,780 53,218 53,103 33% CFE - 5, ,681 5,681 12,649 12,649 45% CHPD ,697 3,694 0% CIPB ,434 1, ,010 2,575 45,876 43,441 6% CIPV 6,064 8,080 2,639 3,052 10, ,662 33,949 30,896 57,479 54,426 57% CISC 2,938 2, ,717 13,398 3,043 10,459 38,562 32,845 97,058 91,341 36% CISD ,266 4, ,505 8,102 6,835 21,948 20,682 33% DOPD ,598 1,597 0% EPE ,450 9,426 3% 26 P a g e

27 RPS in GWh by Technology and BAA in Year 2021 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% GCPD ,590 4,587 0% IID 860 3, , ,591 5,487 4,156 4, % IPFE ,460 2,450 6% IPMV ,772 4,762 20% IPTV ,368 10,354 8% LDWP ,759-1,243 5,486 4,806 30,842 30,162 16% NEVP ,527 25,329 3% NWMT ,397 1,465 1,440 10,490 10,465 14% PACW ,067 1,514 1,447 20,819 20,752 7% PAID ,237 6,229 8% PAUT ,841 1,725 28,030 27,915 6% PAWY ,177 3,199 3,177 9,745 9,724 33% PGE ,122 1,058 21,798 21,735 5% PNM ,120 2,469 2,302 14,198 14,031 16% PSCO ,510 6,223 5,670 37,596 37,044 15% PSEI ,410 1,659 1,641 23,594 23,576 7% SCL ,199 9,192 0% SPPC 26 6, ,609 8,699 8,597 13,401 13,299 65% SRP , ,079 34,226 2% TEPC ,543 13,190 3% TH_Mea d % TH_PV % TIDC ,661 2,600 1% 27 P a g e

28 RPS in GWh by Technology and BAA in Year 2021 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% TPWR ,742 4,738 3% WACM ,105 27,840 2% WALC , ,701 4,458 22% WAUW % VEA % WECC Total 22,930 27,535 4,296 17,716 39,147 5,939 61, , , , ,200 19% CA Total 10,496 14,079 4,224 13,674 35,500 3,340 17,461 98,773 85, , ,836 32% CAISO Total 9,526 10,842 3,186 12,470 30,119 3,322 16,158 85,622 73, , ,372 35% Table 2-3 RPS by Technology and BAA for Year 2021 RPS in GWh by Technology and BAA in Year 2022 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% AESO 2, ,377 9,145 9, , ,186 9% AVA 1, ,819 1,803 12,905 12,890 14% AZPS ,862 4,602 3,752 31,971 31,120 12% BANC , ,132 1,741 16,204 15,813 11% BCHA 2, ,697 4,619 4,619 60,560 60,560 8% BPAT 3, ,107 19,100 18,976 53,863 53,739 35% CFE - 5, ,684 5,684 12,802 12,802 44% 28 P a g e

29 RPS in GWh by Technology and BAA in Year 2022 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% CHPD ,742 3,739 0% CIPB ,643 1, ,412 2,769 46,432 43,789 6% CIPV 6,064 8,080 2,639 3,314 11, ,975 35,419 32,105 58,176 54,862 59% CISC 2,938 2, ,206 14,546 3,303 11,354 41,355 35,149 98,235 92,029 38% CISD ,375 4, ,633 8,751 7,377 22,214 20,839 35% DOPD ,618 1,616 0% EPE ,564 9,539 3% GCPD ,646 4,642 0% IID 860 3, , ,721 5,608 4,206 4, % IPFE ,490 2,479 7% IPMV ,014 1,004 4,830 4,819 21% IPTV ,494 10,479 8% LDWP ,996-1,350 5,887 5,149 31,216 30,478 17% NEVP ,836 25,621 3% NWMT ,516 1,586 1,559 10,617 10,590 15% PACW ,158 1,611 1,538 21,072 20,999 7% PAID ,313 6,304 9% PAUT ,926 1,801 28,370 28,245 6% PAWY ,449 3,472 3,449 9,863 9,840 35% PGE ,029 1,209 1,140 22,063 21,994 5% PNM ,302 2,680 2,499 14,370 14,189 18% PSCO ,982 6,753 6,153 38,052 37,452 16% PSEI ,530 1,781 1,762 23,880 23,861 7% SCL ,311 9,303 0% 29 P a g e

30 RPS in GWh by Technology and BAA in Year 2022 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% SPPC 26 6, ,747 8,878 8,768 13,564 13,453 65% SRP , ,505 34,578 2% TEPC ,707 13,324 3% TH_Mea d % TH_PV % TIDC ,693 2,627 1% TPWR ,799 4,795 3% WACM ,446 28,158 2% WALC ,049-1,313 1,049 4,758 4,494 23% WAUW % VEA % WECC Total 22,930 27,535 4,296 19,233 42,499 6,447 66, , , , ,477 19% CA Total 10,496 14,079 4,224 14,845 38,539 3,626 18, ,765 89, , ,019 34% CAISO Total 9,526 10,842 3,186 13,537 32,698 3,606 17,541 90,937 77, , ,007 37% Table 2-4 RPS by Technology and BAA for Year 2022 RPS in GWh by Technology and BAA in Year 2023 Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Total RPS w/o PV-BTM Retail Load Retail load after PV-BTM RPS% 30 P a g e

31 RPS in GWh by Technology and BAA in Year 2023 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% AESO 2, ,880 9,648 9, , ,401 10% AVA 1, ,847 1,831 13,062 13,045 14% AZPS ,088 4,961 4,044 32,359 31,441 13% BANC , ,272 1,851 16,400 15,979 12% BCHA 2, ,830 4,753 4,753 61,294 61,294 8% BPAT 3, ,299 20,306 20,171 54,517 54,382 37% CFE - 5, ,686 5,686 12,957 12,957 44% CHPD ,787 3,784 0% CIPB ,851 2, ,814 2,963 46,995 44,144 7% CIPV 6,064 8,080 2,639 3,575 12, ,289 36,888 33,313 58,881 55,306 60% CISC 2,938 2, ,696 15,693 3,564 12,250 44,148 37,452 99,427 92,731 40% CISD ,483 5, ,762 9,401 7,918 22,484 21,000 38% DOPD ,637 1,636 0% EPE ,680 9,653 3% GCPD ,702 4,698 0% IID 860 3, , ,851 5,730 4,257 4, % IPFE ,520 2,508 7% IPMV ,084 1,072 4,888 4,877 22% IPTV ,621 10,605 8% LDWP ,232-1,456 6,288 5,492 31,595 30,798 18% NEVP , ,150 25,918 3% NWMT ,636 1,708 1,679 10,746 10,717 16% PACW ,249 1,708 1,629 21,327 21,249 8% PAID ,390 6,380 10% 31 P a g e

32 RPS in GWh by Technology and BAA in Year 2023 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% PAUT , ,011 1,876 28,714 28,579 7% PAWY ,721 3,746 3,721 9,983 9,958 37% PGE ,110 1,296 1,221 22,331 22,256 5% PNM ,483 2,892 2,696 14,545 14,349 19% PSCO ,454 7,283 6,636 38,513 37,867 18% PSEI ,651 1,903 1,883 24,170 24,149 8% SCL ,424 9,415 0% SPPC 26 6, ,885 9,058 8,939 13,728 13,609 66% SRP , , ,935 34,936 2% TEPC ,873 13,460 3% TH_Mea d % TH_PV % TIDC ,726 2,655 1% TPWR ,858 4,853 3% WACM ,791 28,481 2% WALC ,132-1,417 1,132 4,816 4,531 25% WAUW % VEA % WECC Total 22,930 27,535 4,296 20,750 45,851 6,956 72, , , , ,886 20% CA Total 10,496 14,079 4,224 16,016 41,579 3,912 20, ,757 94, , ,243 35% CAISO 9,526 10,842 3,186 14,605 35,277 3,891 18,925 96,251 81, , ,675 38% 32 P a g e

33 RPS in GWh by Technology and BAA in Year 2023 Region Bio Geo Total Table 2-5 RPS by Technology and BAA for Year 2023 Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Total RPS w/o PV-BTM Retail Load Retail load after PV-BTM RPS% RPS in GWh by Technology and BAA in Year 2024 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% AESO 2, ,383 10,151 10, , ,631 10% AVA 1, ,876 1,858 13,220 13,202 14% AZPS ,313 5,320 4,336 32,751 31,767 14% BANC , ,413 1,961 16,599 16,147 12% BCHA 2, ,964 4,886 4,886 62,038 62,038 8% BPAT 3, ,490 21,511 21,367 55,178 55,034 39% CFE - 5, ,689 5,689 13,114 13,114 43% CHPD ,833 3,830 0% CIPB ,060 2, ,217 3,157 47,565 44,506 7% CIPV 6,064 8,080 2,639 3,836 13, ,602 38,358 34,522 59,596 55,759 62% CISC 2,938 2, ,185 16,840 3,824 13,145 46,940 39, ,633 93,448 43% CISD ,592 5, ,891 10,051 8,459 22,756 21,165 40% DOPD ,657 1,655 0% EPE ,798 9,768 3% GCPD ,759 4,755 0% IID 860 3, , ,981 5,851 4,309 4, % 33 P a g e

34 RPS in GWh by Technology and BAA in Year 2024 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% IPFE ,551 2,538 8% IPMV ,005 1,153 1,141 4,948 4,935 23% IPTV ,750 10,732 9% LDWP ,468-1,563 6,689 5,834 31,978 31,123 19% NEVP , ,467 26,218 3% NWMT ,756 1,830 1,799 10,876 10,845 17% PACW ,341 1,805 1,721 21,586 21,502 8% PAID ,467 6,457 10% PAUT , ,096 1,951 29,063 28,918 7% PAWY ,993 4,020 3,993 10,104 10,077 40% PGE ,191 1,383 1,303 22,601 22,521 6% PNM ,665 3,103 2,893 14,721 14,511 20% PSCO ,926 7,813 7,119 38,980 38,286 19% PSEI ,772 2,026 2,003 24,463 24,441 8% SCL ,538 9,529 0% SPPC 26 6, ,023 9,237 9,110 13,895 13,767 66% SRP , , ,371 35,298 2% TEPC ,041 13,598 3% TH_Mea d % TH_PV , ,069 1, % TIDC ,759 2,682 1% TPWR ,916 4,912 3% WACM ,141 28,807 2% 34 P a g e

35 RPS in GWh by Technology and BAA in Year 2024 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% WALC ,215-1,520 1,215 4,874 4,569 27% WAUW % VEA % WECC Total 22,930 27,535 4,296 22,267 49,203 7,464 77, , , , ,928 21% CA Total 10,496 14,079 4,224 17,187 44,619 4,198 21, ,748 99, , ,008 37% CAISO Total 9,526 10,842 3,186 15,673 37,856 4,175 20, ,566 85, , ,877 40% Table 2-6 RPS by Technology and BAA for Year 2024 RPS in GWh by Technology and BAA in Year 2025 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% AESO 2, ,886 10,654 10, , ,876 10% AVA 1, ,905 1,885 13,380 13,361 14% AZPS ,052-1,038 3,539 5,679 4,627 33,148 32,097 14% BANC , ,554 2,071 16,800 16,317 13% BCHA 2, ,098 5,020 5,020 62,791 62,791 8% BPAT 3, ,682 22,717 22,563 55,847 55,693 41% CFE - 5, ,691 5,691 13,274 13,274 43% 35 P a g e

36 RPS in GWh by Technology and BAA in Year 2025 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% CHPD ,880 3,876 0% CIPB ,268 2, ,619 3,351 48,142 44,874 7% CIPV 6,064 8,080 2,639 4,098 14, ,916 39,828 35,730 60,319 56,221 64% CISC 2,938 2, ,675 17,987 4,085 14,041 49,733 42, ,853 94,179 45% CISD ,700 6, ,020 10,700 9,000 23,032 21,332 42% DOPD ,677 1,675 0% EPE ,917 9,885 3% GCPD ,817 4,812 0% IID 860 3, , ,110 5,972 4,361 4, % IPFE ,582 2,568 8% IPMV ,074 1,222 1,209 5,008 4,994 24% IPTV ,880 10,862 9% LDWP ,705-1,669 7,090 6,177 32,366 31,453 20% NEVP , ,788 26,522 4% NWMT ,875 1,951 1,918 11,008 10,975 17% PACW ,432 1,902 1,812 21,848 21,758 8% PAID ,545 6,534 11% PAUT , ,182 2,027 29,415 29,260 7% PAWY ,265 4,294 4,265 10,226 10,198 42% PGE ,273 1,469 1,384 22,876 22,790 6% PNM ,846 3,315 3,090 14,900 14,675 21% PSCO ,397 8,343 7,602 39,453 38,712 20% PSEI ,892 2,148 2,124 24,760 24,736 9% SCL ,654 9,644 0% 36 P a g e

37 RPS in GWh by Technology and BAA in Year 2025 Total RPS w/o PV-BTM Retail load after PV-BTM Region Bio Geo Small Hydro PV-BTM Solar Solar Thermal Wind Total RPS Retail Load RPS% SPPC 26 6, ,160 9,417 9,281 14,063 13,927 67% SRP , , ,812 35,666 3% TEPC ,212 13,738 4% TH_Mea d % TH_PV , ,141 1, % TIDC ,793 2,711 1% TPWR ,976 4,971 3% WACM ,494 29,138 2% WALC ,298-1,624 1,298 4,934 4,607 28% WAUW % VEA % WECC Total 22,930 27,535 4,296 23,784 52,555 7,973 82, , , , ,103 22% CA Total 10,496 14,079 4,224 18,358 47,658 4,484 23, , , , ,815 38% CAISO Total 9,526 10,842 3,186 16,741 40,434 4,460 21, ,880 90, , ,112 42% Table 2-7 RPS by Technology and BAA for Year P a g e

38 2.2.5 Contingency, Flexibility and Regulation Reserves 38 P a g e Contingency Reserves The requirements for contingency reserves, i.e. spinning and non-spinning reserves, are defined for 28 reserve regions. The mapping between the reserve regions and the load regions is specified in the following table. Reserve Region AESO APS AVA BCTC BPA Burbank CAISO CFE EPE Glendale IID IPC LDWP NVE NWMT PAC PGN PNM PSC PSE Load Region AESO AZPS AVA BCHA BPAT CHPD DOPD GCPD SCL TPWR Burbank CIPB CIPV CISC CISD VEA CFE EPE Glendale IID IPFE IPMV IPTV LDWP NEVP SPPC NWMT PAID PAUT PAWY PACW PGE PNM PSCO PSEI

39 Reserve Region SMUD SRP TEP TIDC WACM WALC WAUW Load Region BANC SRP TEPC TIDC WACM WALC WAUW Table 2-8 Mapping of Load Regions and Contingency Reserve Sharing Groups The spinning reserve requirement of a reserve region is 3% of the loads of the load regions in the reserve region. The spinning reserve is provided by the eligible on-line generators in the regions. The non-spinning reserve requirement of a reserve region is 3% of the loads of the load regions in the reserve region. The non-spinning reserve is provided by the eligible on-line generators and the off-line quick startup generators in the region [3] Regulation up and Regulation Down Reserves The requirements of the regulation up and regulation down reserves are defined as 1% of the loads of the load regions in the reserve region. The regulation up and regulation down reserves are provided by the eligible on-line generators in the regions Flexibility Up and Flexibility Down Reserves The requirements of the hourly flexibility up and flexibility down reserve for a reserve region are calculated based on the distribution of the 5-minute net load (load less solar and wind generation) less the hourly net load forecast in the reserve region [6]. The flexibility up and down reserve requirements are determined at 95 percent of the distribution Utah Project Representation A Compressed Air Energy System () operation can be illustrated in the following diagram. 39 P a g e

40 Figure 2-2 Illustration of a operation In the Utah Project Phase 1, two trains of equipment will be built with each train including 150 MW of both compressing and generating capacity. The storage cavern size for each train is 7.2 GWh (representing 48 hours of storage at full 150 MW generation output). A is modeled in PLEXOS as a pumped storage generator with 80% cycle efficiency and a CT generator. For purposes of the Plexos modeling, the compressing mode and generating mode are illustrated in the following diagrams. in Compressing Mode Gen=120 MWh Gen=150 MWh Storage Fuel=0 Btu ~ Gen=150 MWh 40 P a g e ~ Gen=0 MWh

41 Figure 2-3 Compressing Mode Representation in Generating Mode Gen=100 MWh Gen=100 MWh Storage Fuel= mm Btu ~ Gen=150 MWh Figure 2-4 Generating Mode Representation The following table summarizes the characteristics of the project. 41 P a g e ~ Gen=50 MWh Heat Rate=13,125 Btu/kWh Utah Properties Value Trains 2 Max Cap per Train (MW) 150 Min Cap per Train (MW) 20 Max Ramp Rate per Train (MW/min) 30 Fuel Burned at Max Capacity per Train(mmBtu) Heat Rate at CT Max Capacity of 50 MW per Train (Btu/kWh) 13,125 Heat Rate at Max Capacity of 150 MW per Train (Btu/kWh) 4,375 Max Compressing Load per Train (MW) 150 Min Compressing Load per Train (MW) 90 Storage (GWh) 7.2 Cycle Efficiency 80% Table 2-9 Characteristics of Utah Project Representation in PLEXOS The generation heat rate of 13,125 Btu/kWh shown in the above figure is based on the assumption that natural gas input to the facility provides about one-third of the

42 energy for generation (the rest coming from the stored energy). For Plexos modeling purposes, the 13,125 Btu/kWh figure is calculated by taking three times the actual heat rate of a facility (i.e., 4,375 Btu/kWh applicable to 100% of the generation ouput energy 7 ). The Plexos model then uses the 13,125 Btu/kWh figure for one-third of the generation output energy to determine fuel costs. The project is capable of providing contingency reserves, regulation up and down reserves, and flex up and down reserves, in both compressing mode and generating mode. Each 150 MW train was assumed to be capable of compressing at the same time that the other train was generating, and vice versa. The Plexos results showed this would happen only occasionally and typically during ramping events when the needs for compression or generation would toggle from one to the other. Energy Exemplar also initially tested the results of allowing the compressor mode and the generation mode of an individual train to operate at the same time. The Plexos results in this test showed this approach of operating significantly decreased the economic benefits of the facility. As a result, for the balance of of the study it was assumed that each train would either be in compression mode or generation mode in a particular time period but not both at the same time Gas Forecast The gas price assumption was originally from CEC IEPR 2013 [2]. The following table lists the Gas Price Forecast by Month for the year 2024 in real 2014 dollars. 7 Lessons from Iowa: Development of a 270 Megawatt Compressed Air Energy Storage Projecy in Midwest Independent System Operator A Study for the DOE Energy Storage Systems Program, Robert H. Schulte, Nicholas Critelli, Hr., Kent Holst, and Georgianne Huff. Sandia Report, SAND , January P a g e

43 2024 Gas Price Forecast ($/mmbtu in Real 2014 dollars) BAA or Region M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12 AESO Arizona North Arizona South Baja Baja California BC Hydro California Blythe California Kern River California Mojave California PG&E BB California PG&E LT California San Juan Valley California SDGE California SoCal Gas California SoCal Gas B California SoCal Gas B Other Colorado Gas to Idaho North Idaho South Montana Nevada North Nevada South Nevada South California P a g e

44 2024 Gas Price Forecast ($/mmbtu in Real 2014 dollars) BAA or Region M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12 New Mexico North New Mexico South Oregon Oregon Malin Synthetic Gas Texas West Utah Washington Wyoming Table 2-10 Gas Price Forecast for Year 2024 by Month 44 P a g e

45 2.2.8 Emission Market Modeling for California The California CO2 Market is modeled in this study. The CO2 price is $/lb (or about $25/ton) and the commitment and dispatch price of the thermal generators in California includes the CO2 cost component. The import energy from outside of California is charged with the GHG allowance as well. The energy imported from Northwest is charged at the tiered rate: at $0.523/MWh below the thresholds and $11.97/MWh above the thresholds. The thresholds follow the following patterns. Thresholds for the Tiered CO 2 Allowance Charge for Energy Import from NW into California Threshold (MW) Time Period 1120 M M M M04,D M04,D M M M M08,D M08,D M09 1 M10 97 M11 1 M12 Table 2-11 Thresholds for Tiered CO2 Allowance Charge for Energy Import from NW into California The GHG allowance charge for the energy import from Southwest to California is constant of $11.97/MWh CAISO Export Transmission Charge Any energy export from CAISO is charged at $10.83/MWh for the transmission usage. 45 P a g e

46 3 Modeling Approaches 3.1 PLEXOS SCUC/ED Algorithm PLEXOS Security Constrained Unit Commitment (SCUC) algorithm consists of two major logics: Unit Commitment using Mixed Integer Programming and Network Applications. The SCUC/ED simulation algorithm is illustrated in the following figure. Figure 3-1 PLEXOS Security Constrained Unit Commitment and Economic Dispatch Algorithm The unit commitment and economic dispatch (UC/ED) logic performs the Energy-AS cooptimization using Mixed Integer Programming enforcing all resource and operation constraints. The UC/ED logic commits and dispatches resources to balance the system energy demand and meet the system reserve requirements. The resource schedules from the UC/ED are passed to the Network Applications logic. The Network Applications logic solves the DC-OPF to enforce the power flow limits and nomograms. The Network Applications logic also performs the contingency analysis if the contingencies are defined. If there are any transmission limit violations, these transmission limits are passed to the UC/ED logic for the re-run of UC/ED. The iteration continues until all transmission limit violations are resolved. Thus the co-optimization solution of Energy-AS-DC-OPF is reached. The same algorithm for the SCUC/ED is used by many ISO market scheduling software (some ISO market scheduling software may use AC-OPF in the Network Applications). 46 P a g e

GridView Review 2026 Common Case Version 2.0

GridView Review 2026 Common Case Version 2.0 GridView Review 2026 Common Case Version 2.0 Colby Johnson Staff Engineer December 14, 2017 2 Overview GridView Review What is it/what does it do? Inputs and Outputs 2026 Common Case Version 2.0 Changes

More information

Energy. Roseville, CA U.S.A. Argonne, IL USA. Technical Report. October 30, DOE Contract No. ANL Contract No. 2F-3110.

Energy. Roseville, CA U.S.A. Argonne, IL USA. Technical Report. October 30, DOE Contract No. ANL Contract No. 2F-3110. Technical Report Energy Exemplar EE-2013-10-30-01 October 30, 2013 DOE Contract No. DE-FOA-0000486 ANL Contract No. 2F-3110 Adjustable Speed Pumped-Storage Hydro- Generator ( PSH) Evaluation by PLEXOS

More information

Transmission and Renewable Energy

Transmission and Renewable Energy Transmission and Renewable Energy Yale Conference on the Environment Presented by Richard Sedano February 28, 2015 The Regulatory Assistance Project 50 State Street, Suite 3 Montpelier, VT 05602 Phone:

More information

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions Shucheng Liu Principal, Market Development 2016-2017 Transmission Planning Process Stakeholder Meeting February 28, 2017 Page

More information

NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC)

NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC) NORTHWEST POWER POOL Reliability through Cooperation 2006 2 NORTH AMERICAN ELECTRIC RELIABILITY COUNCIL (NERC) NERC is a not-for-profit company formed as a result of the Northeast blackout in 1965 to promote

More information

Modeling the 1-Step and 2-Step Dispatch Approaches to Account for GHG Emissions from EIM Transfers to Serve CAISO Load

Modeling the 1-Step and 2-Step Dispatch Approaches to Account for GHG Emissions from EIM Transfers to Serve CAISO Load Modeling the 1-Step and 2-Step Dispatch Approaches to Account for GHG Emissions from EIM Transfers to Serve CAISO Load P R E P A R E D B Y : Judy Chang Johannes Pfeifenberger Kai Van Horn Onur Aydin Mariko

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Continue Implementation and Administration, and Consider Further Development of, California Renewables

More information

Beyond LCOE: The Value of CSP with Thermal Energy Storage

Beyond LCOE: The Value of CSP with Thermal Energy Storage CSP Beyond LCOE: The Value of CSP with Thermal Energy Storage energy.gov/sunshot Mark S. Mehos, Program Manager, CSP NREL Discussion SunShot and LCOE Understanding the Value of CSP with Thermal Energy

More information

Reduced Network Modeling of WECC as a Market Design Prototype

Reduced Network Modeling of WECC as a Market Design Prototype PAPER 2011GM0942 1 Reduced Network Modeling of WECC as a Market Design Prototype James E. Price, Member, IEEE, and John Goodin Abstract California s administration, legislature, and energy regulators have

More information

Procurement Under GHG Regulation

Procurement Under GHG Regulation Procurement Under GHG Regulation Pedro J. Pizarro Senior Vice President, Power Procurement Southern California Edison IEP Annual Meeting September 25, 2007 Existing GHG-Related Procurement Rules Loading

More information

Low Carbon Grid Study: SWIP North Economic Benefits

Low Carbon Grid Study: SWIP North Economic Benefits Low Carbon Grid Study: SWIP North Economic Benefits Center for Energy Efficiency and Renewable Technologies 1100 11 th Street, Suite 300 Sacramento, CA, 95814 James H. Caldwell Dr. Liz Anthony March 2016

More information

Western EIM Benefits Report Fourth Quarter 2017

Western EIM Benefits Report Fourth Quarter 2017 Western EIM Benefits Report Fourth Quarter 2017 January 30, 2018 Contents EXECUTIVE SUMMARY... 3 EIM BENEFITS IN Q4 2017... 4 INTER-REGIONAL TRANSFERS... 4 WHEEL THROUGH TRANSFERS... 8 REDUCED RENEWABLE

More information

Western EIM Benefits Report Second Quarter 2017

Western EIM Benefits Report Second Quarter 2017 Western EIM Benefits Report Second Quarter 2017 July 31, 2017 www.westerneim.com Table of Contents EXECUTIVE SUMMARY... 3 EIM BENEFITS IN Q2 2017... 4 INTER-REGIONAL TRANSFERS... 4 REDUCED RENEWABLE CURTAILMENT

More information

Western Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group

Western Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group Western Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group Demand Analysis of 215 Scenarios To Explore the Range of Need for a Canada/Pacific Northwest

More information

Economic Planning Study. May 13, 2014

Economic Planning Study. May 13, 2014 Economic Planning Study May 13, 2014 In this presentation Review of the draft 2014 study results Potential issues Proposed improvements Status of 2019 and 2024 studies Next steps 1 Review of the draft

More information

Benefits for Participating in EIM February 1, 2016

Benefits for Participating in EIM February 1, 2016 Benefits for Participating in EIM February 1, 2016 www.caiso.com Revision History Date Version Description Author 01/27/2016 1.0 Lin Xu 02/02/2016 1.1 Corrects the November benefit amount referenced in

More information

California Grid Operations: Current Conditions and Future Needs

California Grid Operations: Current Conditions and Future Needs California Grid Operations: Current Conditions and Future Needs Jim Detmers Vice President, Operations Global Climate & Energy Project November 1, 2007 STANFORD UNIVERSITY Our objective today is identify

More information

Latest Computational and Mathematical Tools for Transmission Expansion

Latest Computational and Mathematical Tools for Transmission Expansion Latest Computational and Mathematical Tools for Transmission Expansion IEEE PES T&D Meeting, Chicago IL Clayton Barrows, PhD April 15, 2014 NREL is a national laboratory of the U.S. Department of Energy,

More information

Analysis of Benefits of an Energy Imbalance Market in the NWPP

Analysis of Benefits of an Energy Imbalance Market in the NWPP PNNL-22877 Prepared for the U.S. Department of Energy under Contract DE-AC05-76RL01830 Analysis of Benefits of an Energy Imbalance Market in the NWPP NA Samaan R Schellberg D Warady S Williams R Bayless

More information

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024

A Bulk Energy Storage Resource Case Study with 40% RPS in 2024 A Bulk Energy Storage Resource Case Study with 40% RPS in 2024 Shucheng Liu Principal, Market Development 2015-2016 Transmission Planning Process Stakeholder Meeting February 18, 2016 California ISO Public

More information

California s Solar Buildout: Implications for Electricity Markets in the West

California s Solar Buildout: Implications for Electricity Markets in the West California s Solar Buildout: Implications for Electricity Markets in the West EPIS Electric Market Forecasting Conference Las Vegas, Nevada September 7, 2017 Arne Olson, Partner Agenda Report From the

More information

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage ISO 2016-2017 Transmission Planning Process Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage January 4, 2018 Contents 1. Introduction... 1 2. Background... 1 3. Objectives of

More information

2026 PC18 CAES Double Capacity

2026 PC18 CAES Double Capacity 2026 PC18 CAES Double Capacity Colby Johnson, Staff Engineer 2 Modeling Logic Production Cost Model Scope Scope Key Questions Assumptions Added generation Removed generation Added transmission Results

More information

Jan Strack and Huang Lin March 14, 2017

Jan Strack and Huang Lin March 14, 2017 SDG&E Request for Economic Planning Study of the Renewable Energy Express Transmission Project as part of CAISO s 2017-2018 Transmission Planning Process (TPP) Jan Strack (jstrack@semprautilities.com)

More information

EIM Settlements Load Customer Training September 13, 2016

EIM Settlements Load Customer Training September 13, 2016 EIM Settlements Load Customer Training September 13, 2016 EIM Settlements Customer Training Review EIM 101 EIM terminology Participating / Non-Participating Base Schedules and etags Settlements and Disputes

More information

January 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND:

January 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND: Henry Lorenzen Chair Oregon Bill Bradbury Oregon Guy Norman Washington Tom Karier Washington W. Bill Booth Vice Chair Idaho James Yost Idaho Jennifer Anders Montana Tim Baker Montana January 3, 2018 MEMORANDUM

More information

DOE Funded Pumped Storage Study

DOE Funded Pumped Storage Study DOE Funded Pumped Storage Study Greg Brownell Manager, Resource Planning and Commodity Budget Feb, 2016 Powering forward. Together. Presentation Outline SMUD Overview DOE Funded Iowa Hill Study Overview

More information

Loads and Resources Methods and Assumptions

Loads and Resources Methods and Assumptions Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1

More information

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q1 2017 Report on Market Issues and Performance July 10, 2017 Prepared by: Department of Market Monitoring TABLE OF CONTENTS Executive

More information

Energy Imbalance Market Overview

Energy Imbalance Market Overview Energy Imbalance Market Overview Presentation to: Portland General Electric EIM OATT Stakeholder Meeting David Timson Account Manager CAISO Strategic Alliances October 14, 2016 Topics for Discussion ISO

More information

1. It s architecturally unique 2. It has unique features

1. It s architecturally unique 2. It has unique features 1. It s architecturally unique 2. It has unique features 1. Transparent 2. Customisable 3. Integrated Architecturally unique Architecturally unique Architecturally unique 1. Time 2. Stochastic Optimisation

More information

Senate Bill 350 Study

Senate Bill 350 Study Senate Bill 350 Study Volume VII: Ratepayer Impact Analysis PREPARED FOR PREPARED BY July 8, 2016 Senate Bill 350 Study The Impacts of a Regional ISO-Operated Power Market on California List of Report

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. September 24, 2014

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. September 24, 2014 Rulemaking: --0 Witness: Exhibit No.: Dr. Jimmy Nelson Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. Rulemaking --0 (Filed December,

More information

Clean Energy and Pollution Reduction Act Senate Bill 350 Early Release Material. April 14, 2016

Clean Energy and Pollution Reduction Act Senate Bill 350 Early Release Material. April 14, 2016 Clean Energy and Pollution Reduction Act Senate Bill 350 Early Release Material April 14, 2016 April 14, 2016 Call Agenda Time Topic Presenter 9:00 9:05 Introduction Kristina Osborne 9:05 9:10 Overview

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J. Investigation No. -0-0 Exhibit No. Witnesses: Joseph P. Hoerner and Shayleah J. LaBray BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP Chapter Direct Testimony of Joseph P.

More information

Open Access Technology International, Inc. (OATI)

Open Access Technology International, Inc. (OATI) 1 Incentive-Compatible Solutions for Efficient Energy Consumption and Reliable Power System Operation Farrokh Rahimi, Ph.D. Vice President, Market Design & Consulting Open Access Technology International,

More information

Pacific Northwest Low Carbon Scenario Analysis

Pacific Northwest Low Carbon Scenario Analysis Pacific Northwest Low Carbon Scenario Analysis 2018 Scenarios and Sensitivities June 2018 Arne Olson, Senior Partner Kush Patel, Partner Nick Schlag, Director Kiran Chawla, Consultant Femi Sawyerr, Associate

More information

Power Integrated Resource Plan PWP Presentation

Power Integrated Resource Plan PWP Presentation Power Integrated Resource Plan PWP Presentation Community Meeting #1 Pasadena Central Library July 18, 2018 POWER INTEGRATED RESOURCES PLAN: PWP PWP ACCOMPLISHMENTS & PROGRAMS 2 Renewable and Coal Annual

More information

APS Stakeholder Meeting. September 9 th 2016

APS Stakeholder Meeting. September 9 th 2016 APS Stakeholder Meeting September 9 th 2016 APS: EIM Implementation & Customer Impact Review 9/9/2016 Emerging Market Opportunity CAISO: Energy Imbalance Market Existing Markets 3 Changing Electrical Grid

More information

Renewable Resource Procurement by Western Utilities

Renewable Resource Procurement by Western Utilities Renewable Resource Procurement by Western Utilities Preliminary Findings: Western Renewable Energy Zones Survey Committee for Regional Electric Power Cooperation Presented by Lisa Schwartz April 12, 2011

More information

Analyzing the Value of Storage and Demand Response in a Wholesale Market

Analyzing the Value of Storage and Demand Response in a Wholesale Market Analyzing the Value of Storage and Demand Response in a Wholesale Market Marissa Hummon National Summit on Smart Grid & Climate Change - 2014 Washington, D.C. NREL is a national laboratory of the U.S.

More information

Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration

Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration Technical Appendix October 2015 Regional Coordination in the West: Benefits of PacifiCorp and California ISO Integration

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long Term Procurement Plans Rulemaking 13 12 010

More information

the most promising locations for new renewables in the Imperial CREZ.

the most promising locations for new renewables in the Imperial CREZ. March 3, 2016 Imperial Irrigation District (IID) appreciates the opportunity to comment on the California Independent System Operator (CAISO) presentation during its 2/18/16 Stakeholder meeting discussing

More information

2007 PWP Integrated Resource Plan. April 17, 2007

2007 PWP Integrated Resource Plan. April 17, 2007 2007 PWP Integrated Resource Plan April 17, 2007 1 Planning Objectives Reliable Power Competitive Power Rates Stable Power Rates Environmentally Responsible 2 Planning Objectives Reliable and Dependable

More information

Pacific Northwest Low Carbon Scenario Analysis

Pacific Northwest Low Carbon Scenario Analysis Pacific Northwest Low Carbon Scenario Analysis Achieving Least-Cost Carbon Emissions Reductions in the Electricity Sector November 8, 2017 Arne Olson, Partner Nick Schlag, Sr. Managing Consultant Jasmine

More information

Valuing Energy Storage as a Flexible Resource. Final Phase 1 Report for Consideration in CPUC A

Valuing Energy Storage as a Flexible Resource. Final Phase 1 Report for Consideration in CPUC A Valuing Energy Storage as a Flexible Resource Final Phase 1 Report for Consideration in CPUC A. 14-02-006 June 19, 2014 Valuing Energy Storage as a Flexible Resource Final Phase 1 Report for Consideration

More information

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator

Energy Storage Integration in Alberta s Energy Only Market. Kevin Dawson Director, Market Design Alberta Electric System Operator Energy Storage Integration in Alberta s Energy Only Market Kevin Dawson Director, Market Design Alberta Electric System Operator Outline The AESO and Alberta s Wholesale Electricity Market About the AESO

More information

POWER SYSTEM OPTIMIZATION FLEXIBLE POWER SYMPOSIUM, VAIL COLORADO

POWER SYSTEM OPTIMIZATION FLEXIBLE POWER SYMPOSIUM, VAIL COLORADO POWER SYSTEM OPTIMIZATION FLEXIBLE POWER SYMPOSIUM, VAIL COLORADO Mikael Backman Director, Market Development Americas Wartsila Power Plants The Value of Smart Power Generation Smart Power Generation can

More information

Low Carbon Grid Study Phase II Results

Low Carbon Grid Study Phase II Results Phase II Results CEERT Sacramento, CA February 2016 "This Power Point is a "master" presentation file that contains all of the slides that are used in formal presentations of the Phase II results. The

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions... 8 Load... 8 Fuel Prices... 9 Resources... 9 Pacific

More information

California ISO Preparing California for a Greener and Smarter Grid

California ISO Preparing California for a Greener and Smarter Grid California ISO Preparing California for a Greener and Smarter Grid Presented by Jim McIntosh Director Operations Executive Advisor California ISO Agenda CAISO Overview Current & Future Challenges Renewables

More information

2017 Study Program PC02: High Wind

2017 Study Program PC02: High Wind 2017 Study Program PC02: High Wind Bhavana Katyal 2 PC02: Modeling Logic Production Cost Model Scope Scope Key Questions Assumptions Increased Wind Generation Results Generation Mix/ Curtailment Dump Energy

More information

Navajo Generation Station Phase 2 Study

Navajo Generation Station Phase 2 Study Navajo Generation Station Phase 2 Study Stakeholder outreach Kevin Black, USBR Scott Hasse, NREL David Hurlbut, NREL NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency

More information

Net Demand Variability (NDV) Summary

Net Demand Variability (NDV) Summary Net Demand Variability (NDV) Summary Executive Summary: This document provides a summary of the Net Demand Variability (NDV) work presented to the Energy and Ancillary Service (EAS) workgroup in WG meetings

More information

Impacts of High Variable Renewable Energy (VRE) Futures on Electric-Sector Decision Making

Impacts of High Variable Renewable Energy (VRE) Futures on Electric-Sector Decision Making Impacts of High Variable Renewable Energy (VRE) Futures on Joachim Seel, Andrew Mills, Ryan Wiser Lawrence Berkeley National Laboratory Presentation at International Conference on Energy Systems Integration

More information

2016 Fall Reliability Conference MRO

2016 Fall Reliability Conference MRO 2016 Fall Reliability Conference MRO CAISO s Coordination, Tracking, and Monitoring Distributed Energy Resources Amber Motley; Manager, Short Term Forecasting November 2 nd, 2016 California ISO Overview

More information

Pacific Northwest Low Carbon Scenario Analysis

Pacific Northwest Low Carbon Scenario Analysis Pacific Northwest Low Carbon Scenario Analysis Achieving Least-Cost Carbon Emissions Reductions in the Electricity Sector November 8, 2017 Arne Olson, Partner Nick Schlag, Sr. Managing Consultant Jasmine

More information

Pacific Northwest Low Carbon Scenario Analysis

Pacific Northwest Low Carbon Scenario Analysis Pacific Northwest Low Carbon Scenario Analysis 2018 Scenarios and Sensitivities June 2018 Arne Olson, Senior Partner Kush Patel, Partner Nick Schlag, Director Kiran Chawla, Consultant Femi Sawyerr, Associate

More information

100% Fossil Free Electricity. June 27, 2018

100% Fossil Free Electricity. June 27, 2018 100% Fossil Free Electricity June 27, 2018 Current Washington Emissions Levels 100 90 +7% 80 70 60 50-82% 40 30 20 10 0 1990 2013 2050 (goal) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

More information

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo

More information

Advancements in Grid Integration of Wind and Solar Power in the Western Interconnect

Advancements in Grid Integration of Wind and Solar Power in the Western Interconnect Advancements in Grid Integration of Wind and Solar Power in the Western Interconnect World Renewable Energy Forum Forum Moderator, Brian Parsons May 17, 1:15 2:30 NREL is a national laboratory of the U.S.

More information

TESTIMONY OF MARK ROTHLEDER ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

TESTIMONY OF MARK ROTHLEDER ON BEHALF OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Application No.: Exhibit No.: Witness: Mark Rothleder Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long-Term Procurement Plans. TESTIMONY OF MARK ROTHLEDER BEFORE

More information

Low Carbon Grid Study: Analysis of a 50% Emission Reduction in California

Low Carbon Grid Study: Analysis of a 50% Emission Reduction in California Low Carbon Grid Study: Analysis of a 50% Emission Reduction in California Executive Summary Gregory Brinkman and Jennie Jorgenson National Renewable Energy Laboratory Ali Ehlen and James H. Caldwell Center

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted John Hu Los Angeles Department of Water and Power System Planning Office: 213-367-0506 E-mail: gang-kung.hu@ladwp.com Los Angeles Department

More information

Carbon Charge Proposal Evaluation PREPARED BY: PREPARED FOR: DATE:

Carbon Charge Proposal Evaluation PREPARED BY: PREPARED FOR: DATE: Carbon Charge Proposal Evaluation PREPARED BY: PREPARED FOR: DATE: MARC D MONTALVO & MATTHEW LOIACONO IPPTF MEETING AUGUST 20, 2018 Overview Background Work Plan Methodology Input Assumptions Results Questions

More information

Common Case Process. Jon Jensen Staff Engineer System Adequacy Planning

Common Case Process. Jon Jensen Staff Engineer System Adequacy Planning Common Case Process Jon Jensen Staff Engineer System Adequacy Planning 2 Introduction: 2026 Common Case What is it? Year 10 focused Production Cost/Economic Dispatch (SCED) Model (GridView); 8760 hours

More information

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering Demand Response 2015 Association of Energy Engineers Presenter: David Wylie, P.E. ASWB Engineering National Energy Peak Leveling Program 1977 2 National Energy Peak Leveling Program 1977 3 When Demand

More information

MISO Energy Storage Study DRAFT Scope

MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope MISO Energy Storage Study DRAFT Scope July 19, 2011 MISO Page 1 Table of Contents 1. Introduction... 3 2. Study Objectives... 3 3. Study Drivers... 4 4. Study Description...

More information

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2013 Report on Market Issues and Performance February 10, 2014 Prepared by: Department of Market Monitoring Department of Market Monitoring

More information

Regulation Energy Management Draft Final Proposal

Regulation Energy Management Draft Final Proposal Regulation Energy Management Draft Final Proposal January 13, 2011 Renewable Integration: Market and Product Review Phase 1 Regulation Energy Management (REM) Revised Draft Final Proposal Table of Contents

More information

New England States Committee on Electricity

New England States Committee on Electricity Renewable and Clean Mechanisms 2.0 Study Phase I: Scenario Analysis Winter 2017 New England States Committee on Electricity Overview Context Analytical Approach and Modeling Assumptions Scenario Analysis

More information

PJM s Clean Power Plan Modeling Reference Model and Sensitivities

PJM s Clean Power Plan Modeling Reference Model and Sensitivities PJM s Clean Power Plan Modeling Reference Model and Sensitivities Muhsin K. Abdur-Rahman Senior Market Strategist MC Webinar April 25, 2016 What it is Reference Model Robust modeling representation of

More information

CAISO s Plan for Integration of Renewable Resources

CAISO s Plan for Integration of Renewable Resources CAISO s Plan for Integration of Renewable Resources July 21, 2008 CEC 33% Renewables Workshop Presented by David Hawkins Program Tracks 2008-9 CAISO Work Plan Track 1 - Develop Operational Tools Wind and

More information

Generation Technology Assessment & Production Cost Analysis

Generation Technology Assessment & Production Cost Analysis SPO Planning Analysis Generation Technology Assessment & Production Cost Analysis EAI Stakeholder Meeting July 31, 212 Technology Life Cycle Technology Deployment Over Time Conceptual Research & Development

More information

Seattle City Light: GHG Impacts of EIM Participation

Seattle City Light: GHG Impacts of EIM Participation Seattle City Light: GHG Impacts of EIM Participation February 10, 2017 Arne Olson, Partner Nick Schlag, Managing Consultant Jack Moore, Director Alison Ong, Associate Outline This presentation is a supplement

More information

Flexible Ramping Products

Flexible Ramping Products Flexible Ramping Products Revised Draft Final Proposal August 16, 2012 Lin Xu, Ph.D. Senior Market Development Engineer Don Tretheway Senior Market Design and Policy Specialist Agenda Time Topic Presenter

More information

Making Sense of U.S. Energy Markets

Making Sense of U.S. Energy Markets Making Sense of U.S. Energy Markets National Conference of State Legislators Task Force on Energy Supply Philip Pettingill, Director Regional Integration January 14, 2017 Two-thirds of the United States

More information

PREPARED DIRECT TESTIMONY OF JEFF HUANG SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY

PREPARED DIRECT TESTIMONY OF JEFF HUANG SAN DIEGO GAS & ELECTRIC COMPANY AND SOUTHERN CALIFORNIA GAS COMPANY Application No: A.1-0- Exhibit No.: Witness: Jeff Huang Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Natural Gas Rates

More information

July 5, 2018 MEMORANDUM. Power Committee. John Ollis, Power System Analyst. SUBJECT: Wholesale Electricity Price Forecast BACKGROUND:

July 5, 2018 MEMORANDUM. Power Committee. John Ollis, Power System Analyst. SUBJECT: Wholesale Electricity Price Forecast BACKGROUND: James Yost Chair Idaho W. Bill Booth Idaho Guy Norman Washington Tom Karier Washington Jennifer Anders Vice Chair Montana Tim Baker Montana Ted Ferrioli Oregon Richard Devlin Oregon July 5, 2018 MEMORANDUM

More information

2011 IRP Public Input Meeting. December 15, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. December 15, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting December 15, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda 2011 IRP schedule update and next steps Resource portfolio development status Supply Side Resources

More information

Integrating Renewables into the Power Grid

Integrating Renewables into the Power Grid Integrating Renewables into the Power Grid An Overview by Barney Speckman November 2010 Energy Solutions Overview Why do we have to integrate renewables What is meant by integrating renewables How does

More information

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1 NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN CHAPTER 1. EXECUTIVE SUMMARY STRAWMAN 1 1. Load Service Requirements a. Peaking Capacity (Planning Reserve Margin) b. Dispatchable Capacity

More information

Baja California Sur Renewable Integration Study

Baja California Sur Renewable Integration Study Baja California Sur Renewable Integration Study Carlo Brancucci, Riccardo Bracho, Greg Brinkman, and Bri-Mathias Hodge National Renewable Energy Laboratory Produced under direction of the 21st Century

More information

Executive Summary MQRI-OPS 2

Executive Summary MQRI-OPS 2 MQRI-OPS 1 Executive Summary On August 21, 2017 the ISO system experienced a solar eclipse with obscuration ranging from 58 percent in Southern California to 76 percent in Northern California. The eclipse

More information

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development

With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development With funding provided by the US Department of Energy, NREL, and the Utah Office of Energy Development www.fourcornerswind.org Photo courtesy of Avangrid Renewables, LLC UNDERSTANDING REGIONAL ELECTRICITY

More information

PJM Renewable Integration Study. Ken Schuyler Renewable Energy in West Virginia June 5, 2014

PJM Renewable Integration Study. Ken Schuyler Renewable Energy in West Virginia June 5, 2014 PJM Renewable Integration Study Ken Schuyler Renewable Energy in West Virginia June 5, 2014 PJM as Part of the Eastern Interconnection 27% of generation in Eastern Interconnection 28% of load in Eastern

More information

2018 Summer Loads and Resources Assessment

2018 Summer Loads and Resources Assessment May 9, 2018 Table of Contents I. EXECUTIVE SUMMARY... 2 II. SUMMER 2017 REVIEW... 11 Demand... 11 Generation... 12 Interchange... 12 III. SUMMER 2018 ASSESSMENT... 14 CAISO Loads... 14 Hydro Generation...

More information

Models for Integration of HPSP in Power System Needs and Posibilities for PSHP Construction in Croatia

Models for Integration of HPSP in Power System Needs and Posibilities for PSHP Construction in Croatia Models for Integration of HPSP in Power System Needs and Posibilities for PSHP Construction in Croatia Mladen Zeljko, Ph.D. Energetski institut Hrvoje Požar (mzeljko@eihp.hr) Some existing PSHP Content

More information

On the Path to SunShot: Emerging Issues and Challenges in Integrating High Levels of Solar into the Electrical Generation and Transmission System

On the Path to SunShot: Emerging Issues and Challenges in Integrating High Levels of Solar into the Electrical Generation and Transmission System On the Path to SunShot: Emerging Issues and Challenges in Integrating High Levels of Solar into the Electrical Generation and Transmission System Paul Denholm, Kara Clark, and Matt O Connell National Renewable

More information

PJM Reserve Market. PJM State & Member Training Dept. PJM /27/2015

PJM Reserve Market. PJM State & Member Training Dept. PJM /27/2015 PJM Reserve Market PJM State & Member Training Dept. Objectives Students will be able to: Identify the process and procedures for participating in the Real Time Reserve Market Reserves Overview What are

More information

State-Federal RPS Collaborative

State-Federal RPS Collaborative State-Federal RPS Collaborative Solar Valuation in Utility Planning Studies Presentation by Andrew Mills, LBNL Hosted by Todd Olinsky-Paul, Project Director, CESA January 16, 2013 Housekeeping All participants

More information

CAISO-IOU Technical Design Session

CAISO-IOU Technical Design Session CAISO-IOU Technical Design Session Farrokh Rahimi, Ph.D. Vice President, Market Design and Consulting Open Access Technology International, Inc. (OATI) John Goodin Lead, Demand Response California ISO

More information

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - CAISO 2008-2013 Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - Purpose The purpose of this document is to provide an initial high-level scoping and program plan for the CAISO

More information

An Analysis of Concentrating Solar Power with Thermal Energy Storage in a California 33% Renewable Scenario

An Analysis of Concentrating Solar Power with Thermal Energy Storage in a California 33% Renewable Scenario An Analysis of Concentrating Solar Power with Thermal Energy Storage in a California 33% Renewable Scenario Paul Denholm, Yih-Huei Wan, Marissa Hummon, and Mark Mehos NREL is a national laboratory of the

More information

Contingency Modeling Enhancements

Contingency Modeling Enhancements Contingency Modeling Enhancements Straw Proposal Discussion May 22, 2013 Delphine Hou Senior Market Design and Policy Specialist and Lin Xu, Ph.D. Senior Market Development Engineer Agenda Time Topic Presenter

More information

California ISO Summer Loads and Resources Operations Assessment April 10, Grid Assets California ISO Version 3.0.

California ISO Summer Loads and Resources Operations Assessment April 10, Grid Assets California ISO Version 3.0. California Independent System Operator Corporation 2006 Summer Loads and Resources Operations Assessment April 10, 2006 Grid Assets Version 3.0 Table of Contents I. Executive Summary...2 Table 1 2006 ISO

More information

Pacific Northwest Low Carbon Scenario Analysis

Pacific Northwest Low Carbon Scenario Analysis Pacific Northwest Low Carbon Scenario Analysis 2018 Scenarios and Sensitivities June 2018 Arne Olson, Senior Partner Kush Patel, Partner Nick Schlag, Director Kiran Chawla, Consultant Femi Sawyerr, Associate

More information

Energy and Environmental Economics, Inc. Energy Efficiency Avoided Costs 2011 Update

Energy and Environmental Economics, Inc. Energy Efficiency Avoided Costs 2011 Update Energy and Environmental Economics, Inc Energy Efficiency Avoided Costs 2011 Update Brian Horii, Eric Cutter December 19, 2011 Table of Contents Overview... 2 Natural Gas Avoided Cost Updates... 4 Overview

More information

Agenda. Project Overview Important Trends Summary of Findings Key Uncertainties Review of the Modeling Techniques. April 4, /3/2014

Agenda. Project Overview Important Trends Summary of Findings Key Uncertainties Review of the Modeling Techniques. April 4, /3/2014 April 4, 2014 Tim Belden tbelden@energygps.com 1 Agenda Project Overview Important Trends Summary of Findings Key Uncertainties Review of the Modeling Techniques 2 1 Project Overview Objectives: Estimate

More information