Non-Technical Summary

Size: px
Start display at page:

Download "Non-Technical Summary"

Transcription

1 RIVERSIDE RESOURCE RECOVERY FACILITY, BEXLEY SECTION 36C VARIATION APPLICATION PROPOSED OPERATIONAL EFFICIENCY IMPROVEMENTS NON-TECHNICAL SUMMARY RIVERSIDE RESOURCE RECOVERY LIMITED SEPTEMBER 2014

2 Introduction NTS.1 NTS.2 NTS.3 NTS.4 NTS.5 NTS.6 NTS.7 NTS.8 Riverside Resource Recovery Limited s RRRL ) Energy from Waste Facility hereafter the Facility ) is located on Norman Road, Belvedere Figure NTS1) in the London Borough of Bexley LBB ). The Facility became fully operational in 2013 following a period of commissioning which began in It recovers energy from both Municipal Waste MW) and Commercial and Industrial Waste C&I) and is an important strategic river-served waste management facility for London, helping the capital to manage its own waste, keeping over 100,000 Heavy Goods Vehicles HGVs) off the capital's roads. The Facility processes 670,000 tonnes per annum tpa) of waste from across London and exports approximately 480,000 Mega Watt hours MWh) of electricity to the National Grid. An application for consent to construct and operate an Energy from Waste generating station was submitted by RRRL to the Secretary of State for the Department of Trade and Industry in September 1999 under Section 36 of the Electricity Act The application incorporated improvements to Norman Road and the development of a dedicated jetty. A variation to the application was subsequently submitted in August 2002 and was accompanied by an Environmental Statement ES) hereafter the 2002 ES ). Following two public inquiries in 2003 and 2005, the Secretary of State granted the Section 36 Consent and associated Deemed Planning Permission needed to build the Facility in June 2006 reference GDBC/003/00001C-06). Both the Section 36 Consent and the associated Deemed Planning Permission impose a restriction on waste inputs to the Facility of 670,000tpa. This reflected the assumptions adopted at the time of the application in 2002 relating to the Net Calorific Value NCV) of the waste anticipated to be delivered to the Facility and the number of days per annum over which the Facility was expected to operate. It was, however, acknowledged at the time of the application that this was an estimate, based on best available information in existence at that time. A worst case scenario was also tested in the 2002 ES, which assessed the likely impact of a throughput of 835,000tpa of waste. RRRL is seeking to improve the operational efficiency of its existing Facility through increasing the total waste throughput from 670,000tpa to 785,000tpa, and including the option for adding the Port of Tilbury to its network of riparian waste transfer stations these two elements comprise the Proposed Changes ). Further details on the Proposed Changes are provided below see NTS 14 to NTS 24). An Environmental Impact Assessment EIA ) has been undertaken, in accordance with Schedule 2 of the Electricity Works Environmental Impact Assessment) England and Wales) Regulations 2000 as amended), to consider the potential for significant environmental effects resulting from the Proposed Changes. An ES has been prepared to report the findings and its key elements are summarised in this document: The. Riverside Resource Recovery Limited NTS-1

3 Site Description NTS.9 The Facility is located on Norman Road, Belvedere the Site ) in the LBB. It lies to the north of the A2016 and on the south bank of the River Thames. Bexleyheath is to the south and the Dartford River Crossing lies some 8km to the east. A map showing the location of the Site is provided on Figure NTS1. NTS.10 The Facility is located on a site of approximately 6 hectares; this includes the main Energy from Waste building including the stack, air-cooled condensers and other smaller scale ancillary plant and structures as approved by the existing Section 36 Consent and Deemed Planning Permission. An aerial photograph of the Facility is provided at Figure NTS2. NTS.11 The application boundary remains the same as submitted as part of the original Section 36 application. A copy of the application site boundary plan replicating approved plan D1.2) is provided as Figure NTS3. Existing Operations NTS.12 The Facility is an important waste management facility treating London s waste in a sustainable way. Over 85% of the waste currently delivered to the Facility arrives on barges along the River Thames from four riparian waste transfer stations located in Wandsworth, Battersea, the City of London and Tower Hamlets. NTS.13 The primary residue of the Energy from Waste process is Incinerator Bottom Ash IBA ). This is transported by barge from the Site to the Port of Tilbury where any remaining recyclables e.g. metals) are separated and removed and the residue is then processed to form aggregate for use in the construction industry. A map showing the location of the Facility relative to the existing riparian wharves and the Port of Tilbury is provided at Figure NTS4. The Proposed Changes NTS.14 Based on the commissioning and operational data, RRRL is aware that the Facility is capable of operating with a higher throughput and greater degree of operational efficiency than is currently permitted. This is as a result of improved operational efficiency and variations in the NCV of the waste from the assumptions applied at the time of the original application. NTS.15 The Proposed Changes comprise two main elements: The increase in waste throughput to the Facility from 670,000tpa to 785,000tpa; and Allowing the potential for river borne waste to be transported to the Facility from the Port of Tilbury in addition to riparian waste transfer stations in Greater London. NTS.16 There is no built development or physical modification of the Facility that would be required as a consequence of the Proposed Changes. NTS.17 Full details of what is proposed can be found in the Planning Supporting Statement and the ES. An explanation by way of a summary is provided here. Riverside Resource Recovery Limited NTS-2

4 a) Increasing the waste throughput of the Facility from 670,000tpa to 785,000tpa NTS.18 Both the Section 36 Consent and a condition of the Deemed Planning Permission impose a restriction on waste inputs to the Facility of 670,000tpa. The Facility has been designed and constructed making use of available technologies to maximise plant availability, including the incorporation of online boiler cleaning and the provision of standby equipment to allow maintenance of plant without affecting the operation of the Facility. NTS.19 Together with advances in reliability, this has led to higher levels of plant availability than anticipated in the original 2002 application. Based on the operational performance of the Facility to date, an annual plant availability of 94% is considered realistic. This contrasts with a figure of 89% availability used at the time of the original Section 36 application to define the throughput of 670,000tpa. NTS.20 In respect of the NCV of the waste, the range considered at the time of the original Section 36 application was 9 13MJ/kg. Operating data obtained for the Facility shows a monthly average NCV ranging from 9MJ/kg to 10MJ/kg. This NCV level falls below the predicted average NCV of 10.2MJ/kg used to define the throughput of 670,000tpa in the 2002 ES. The lower NCV of the waste results in more waste being processed in order to generate the same amount of power as waste of a higher calorific value. NTS.21 Applying both parameters 94% availability and an NCV for the waste of 9MJ/kg) gives a maximum potential throughput at the Facility of 785,000tpa. This is considered to represent the maximum throughput that is appropriate for the purposes of setting a potential future maximum waste throughput in the application. This can be achieved without any change to the physical structure or footprint of the Facility and with the fundamental character of the operation remaining unchanged. b) Permitting the option for river borne waste to be transported to the Facility from the Port of Tilbury in addition to the existing riparian waste transfer stations in Greater London NTS.22 Another operational improvement, for which consent is sought, is the potential use of the Port of Tilbury for the transport of waste to the Facility. The Port of Tilbury is currently utilised by RRRL for the handling and processing of IBA generated by the Facility. However, both the river transport and IBA handling operations have the potential to be used more efficiently and to allow greater throughput. NTS.23 There will be no additional tug movements as a result of the Proposed Changes. The existing tugs that currently transport waste from the riparian wharves or IBA to the Port of Tilbury, would tow a limited number of additional barges. NTS.24 Finally, in addition, the Proposed Changes also include minor re-wording of some of the conditions set out in the original Deemed Planning Permission to bring them in to line with subsequent planning permissions granted by the LBB. Riverside Resource Recovery Limited NTS-3

5 Alternatives NTS.25 Given that the Proposed Changes involve increasing throughput at the existing Facility i.e. they relate to operational efficiency and not to any new built development), the consideration of alternative sites and processes is not considered relevant. Assessment Methodology NTS.26 The initial stage of the EIA was the production of an Outline Environmental Report OER) that identified the potential environmental effects that were proposed to be addressed in the EIA. The scope of the EIA is limited to potentially significant effects only, in respect of the Proposed Changes this relates principally to the potential increase in pollutant concentrations released from the Facility. The baseline assumed for assessment purposes includes the Facility operating as it does currently, at its consented throughput capacity of 670,000tpa of waste. NTS.27 The OER was issued to a range of consultees for comment including the Department for Energy and Climate Change, the LBB, the Greater London Authority, the Port of London Authority, Natural England and the Environment Agency. The issues raised by consultees on environmental matters have been addressed where necessary within the ES. These comprised predominantly information requests that did not require the scope of the EIA to be widened. NTS.28 The assessments included in the EIA are: Air quality assessment, including an assessment of the potential impact of any changes to air quality on human health and on natural heritage; and Cumulative effects assessment. NTS.29 The specialist assessments, discussed in more detail below, followed generally similar assessment methodologies. Desk studies were undertaken to establish the existing situation the baseline). The effects of the Proposed Changes were established using a method that compares the sensitivity and importance of receptors with the likely magnitude of change to establish the degree of the effects. If the degree of effect is moderate or above then the effect is considered to be significant. Slight or negligible effects are not considered to be significant. NTS.30 The degree of an effect determines the resources that should, where required, be put in place to avoid or reduce mitigate) an adverse effect and identifies the actual value of a beneficial effect. Environmental Effects Air Quality NTS.31 The Proposed Changes will increase the concentrations of pollutants emitted from the Facility, which were identified as having potential effects on ambient air quality. NTS.32 A desk study was undertaken to determine the current baseline) conditions, the Facility operating at the current maximum throughput of 670,000tpa. The Riverside Resource Recovery Limited NTS-4

6 baseline conditions relating to ambient air quality were obtained from local authorities. NTS.33 An air quality dispersion model was created following best practice guidance and was used to determine the increase in emissions from the Proposed Changes. The model assessed both the impact of processing an additional 115,000tpa of waste and the impact of the Facility operating at 785,000tpa. The effects of the Proposed Changes on air quality at sensitive receptors selected representative residential locations and schools) in proximity to the Facility relative to national air quality objectives were then assessed. NTS.34 The significance of the effects have been determined with reference to the criteria produced by the Institute of Air Quality Management IAQM). NTS.35 The assessment demonstrates that the Proposed Changes will result in a small increase in the amount of gases released from the Facility. The change in local air quality will be very small and will not result in a significant effect as defined by the IAQM. NTS.36 The assessment has concluded that the Proposed Changes will not have a significant effect on air quality. Health Effects NTS.37 A health effects assessment was undertaken using the modelling results from the air quality assessment to provide concentrations of the additional quantity of pollutants emitted as a result of the Proposed Changes. NTS.38 A specific health assessment modelling exercise was then undertaken to determine where any pollutants emitted to the air go. Estimates of the potential exposure of individuals to these substances were then made. NTS.39 It has been demonstrated that even the most exposed individual is not subject to a significant health hazard, arising from exposures via both inhalation and from local edible foods. NTS.40 The Proposed Changes have therefore been assessed and will not have a significant effect on human health. Natural Heritage NTS.41 The increased concentrations of emissions have the potential to increase the deposition of nutrient nitrogen and acid as well as other compounds such as sulphur dioxide on designated sites of biological importance at a range of distances from the Facility, which could in turn have the potential to lead to adverse effects on these ecosystems. NTS.42 A desk study was undertaken to establish the baseline environmental conditions on internationally and nationally designated sites within 15km of the Facility and local sites of conservation interest within 2km, in order to understand any likely impact of the Proposed Changes on the integrity of these sites. NTS.43 The air quality dispersion model was utilised to determine the contribution of the Proposed Changes to pollutant concentrations and deposition rates at the identified designated sites. The percentage contribution of the Proposed Riverside Resource Recovery Limited NTS-5

7 Changes to site specific thresholds was then calculated in order to determine the level of significance of any effect. NTS.44 The percentage contribution from the Proposed Changes on all European and nationally designated sites within 15km and local nature reserves within 2km was substantially below the significance criteria produced by the Environment Agency and Natural England. NTS.45 The Proposed Changes have therefore been assessed and will not have a significant effect on natural heritage. Cumulative Effects NTS.46 Consideration has also been given to the effect of the Proposed Changes in combination with other schemes that are consented or for which permissions are currently being sought i.e. the cumulative effects). In agreement with consultees, the EIA has considered the potential for air quality effects from other relevant developments within the vicinity of the Facility, in combination with the Proposed Changes to give rise to significant cumulative effects in relation to air quality, and the potential for consequential impacts on health and natural heritage. NTS.47 For the purposes of assessing the effects of the Proposed Changes with other proposed schemes, the following were agreed with consultees for inclusion within the ES: Thames Gateway Waste to Energy Ltd TGW2E) a proposal for the development of an energy generation facility on a site known as Plot 2 in the London Sustainable Industries Park in Dagenham. East London Sustainable Energy Facility, Biossence East London) Limited Rainham) proposes to develop an advanced gasification project, known as the East London Sustainable Energy Facility in Dagenham, East London, for the purpose of generating renewable energy and heat and power from solid recovered fuel. Beckton and Crossness sewage treatment works associated with the improvement works of the Thames Tideway Tunnels Project to increase treatment capacity by 20% and construction of a thermal hydrolysis plant at Beckton. NTS.48 The results of the human health and natural heritage assessments show that the effect from the Proposed Changes is so small that under the relevant guidance the significance of the effect alone does not necessitate the need for a cumulative assessment. NTS.49 In relation to air quality, the results identify that the impact of the Proposed Changes relative to the identified four planned sources is zero or negligible for local residents. Therefore, the cumulative effect of the Proposed Changes will not be significant. Riverside Resource Recovery Limited NTS-6

8 Conclusion NTS.50 This provides an outline of the findings of the ES, which accompanies this application to the Department of Energy and Climate Change. The findings of the ES demonstrate that the Proposed Changes applied for as part of this application will result in a limited number of negligible to small changes to the local air quality, none of which would give rise to significant adverse effects. Further Information NTS.51 Further information on the variation application and a copy of the supporting material including the Planning Supporting Statement and ES can be found on the application website at: NTS.52 Copies of the ES and its appendices have been distributed to the Department for Energy and Climate Change, the LBB and consultees. The documents are available for inspection during the consultation period at the following addresses below: National Infrastructure Consents Department for Energy and Climate Change 2nd Floor King s Buildings c/o 3 Whitehall Place London SW1A 2AW London Borough of Bexley Civic Offices 2 Watling Street Bexleyheath Kent DA6 7AT NTS.53 Hard copies of the variation application and the ES may be obtained for 175 for a paper copy and/or 10 for a CD in order to cover printing / copying and distribution costs. Please contact: Terence O Rourke Ltd Everdene House Deansleigh Road Bournemouth Dorset BH7 7DU Tel: maildesk@torltd.co.uk Riverside Resource Recovery Limited NTS-7

9 RIVERSIDE RESOURCE RECOVERY LIMITED Site location RRRF) RRRF Figure 1.1: Site location RRRF RRRL 0 I 3,800 m Revision Dwgno/ 12 Drawn by: Checked by: JC TS Scale: Based upon the 2013 Ordnance Survey 1:50,000 colour raster map with the permission of the Ordnance Survey on behalf of Her Majesty's Stationery Office, Crown copyright. Terence O'Rourke Ltd. Licence No Copyright Terence O'Rourke Ltd, 2014 RIVERSIDE RESOURCE RECOVERY FACILITY, BEXLEY PROPOSED OPERATIONAL EFFICIENCY IMPROVEMENTS ENVIRONMENTAL STATEMENT NTS. NON-TECHNICAL SUMMARY London 3 Whitcomb Street London WC2H 7HA Figure NTS1 Site location RRRF) Bournemouth Everdene House Deansleigh Road Bournemouth BH7 7DU enquiries@torltd.co.uk

10 RIVERSIDE RESOURCE RECOVERY LIMITED RIVERSIDE RESOURCE RECOVERY FACILITY, BEXLEY PROPOSED OPERATIONAL EFFICIENCY IMPROVEMENTS ENVIRONMENTAL STATEMENT NTS. NON-TECHNICAL SUMMARY Figure NTS2 Aerial photo of RRRF looking eastwards)

11 Steps Tarmac Footpath Steps Embankment Certificate FS RIVERSIDE RESOURCE RECOVERY LIMITED Concrete Path Embankment Tarmac Footpath Gravel Footpath 100m 0 100m Crown copyright, All rights reserved Licence number AL RIVERSIDE RESOURCE RECOVERY FACILITY, BEXLEY PROPOSED OPERATIONAL EFFICIENCY IMPROVEMENTS ENVIRONMENTAL STATEMENT NTS. NON-TECHNICAL SUMMARY Figure NTS3 Section 36 application site boundary replicating approved plan D1.2)

12 RIVERSIDE RESOURCE RECOVERY LIMITED Site location RRRF) Walbrook Wharf, Cannon Street Northumberland wharf Riparian waste transfer stations Tilbury IBA processing operation RRRF Cringle Dock, Battersea Smugglers Way, Wandsworth Tilbury Docks Site and dock locations Riverside EFW Cory 0 I 3,250 m Revision Dwgno/ 12 Drawn by: Checked by: JC JB Scale: Based upon the 2013 Ordnance Survey 1:50,000 colour raster map with the permission of the Ordnance Survey on behalf of Her Majesty's Stationery Office, Crown copyright. Terence O'Rourke Ltd. Licence No Copyright Terence O'Rourke Ltd, 2014 RIVERSIDE RESOURCE RECOVERY FACILITY, BEXLEY PROPOSED OPERATIONAL EFFICIENCY IMPROVEMENTS ENVIRONMENTAL STATEMENT NTS. NON-TECHNICAL SUMMARY London Figure NTS4 The four existing riparian waste 3 Whitcomb Street London WC2H 7HA transfer stations situated along the River Thames and Tilbury Docks Bournemouth Everdene House Deansleigh Road Bournemouth BH7 7DU enquiries@torltd.co.uk

Cory Riverside Energy. Riverside Resource Recovery Facility

Cory Riverside Energy. Riverside Resource Recovery Facility Cory Riverside Energy Riverside Resource Recovery Facility Annual Performance Report: 2016 Environmental Permit: BK0825IU Riverside Resource Recovery Ltd Norman Road Belvedere DA17 6JY 1 1. Introduction

More information

Cory Environmental. Riverside Resource Recovery Facility

Cory Environmental. Riverside Resource Recovery Facility Cory Environmental Riverside Resource Recovery Facility Annual Performance Report: 2014 Environmental Permit: BK0825IU Riverside Resource Recovery Ltd Norman Road Belvedere DA17 6JY 1 1. Introduction The

More information

Cory Environmental. Riverside Resource Recovery Facility

Cory Environmental. Riverside Resource Recovery Facility Cory Environmental Riverside Resource Recovery Facility Annual Performance Report: 2015 Environmental Permit: BK0825IU Riverside Resource Recovery Ltd Norman Road Belvedere DA17 6JY 1 1. Introduction The

More information

5. Environmental issues and methodology

5. Environmental issues and methodology 5. Environmental issues and methodology 5 Environmental issues and methodology Introduction 5.1 The methodology used to carry out the environmental impact assessment (EIA) is set out in this chapter. This

More information

Non-technical summary. Canford. Extension of composting facility. Non-technical summary

Non-technical summary. Canford. Extension of composting facility. Non-technical summary Canford Extension of composting facility Introduction NTS1 NTS2 NTS3 NTS4 (NESG) and WH White Ltd submitted a planning application to the Borough of Poole Council (BPC) which was registered on 9 May 2008

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Revision of the layout and design of the Advanced Thermal Treatment Facility permitted under consent 14/12003/WCM at Stephenson Road, Northacre Trading Estate, Westbury, BA13

More information

Beddington Lane Energy Recycling Facility and Revisions to Landfill Restoration Environmental Impact Assessment Update

Beddington Lane Energy Recycling Facility and Revisions to Landfill Restoration Environmental Impact Assessment Update Jim Redwood Planning Department London Borough of Sutton 24 Denmark Road Carshalton Surrey, SM5 2JG 15th March 2012 Our Reference: TOR 227701B Dear Jim Beddington Lane Energy Recycling Facility and Revisions

More information

Northacre Renewable Energy

Northacre Renewable Energy Northacre Renewable Energy Proposed development at Stephenson Road, Northacre Trading Estate, Westbury, BA13 4WD Non-technical summary December 2014 Introduction Northacre Renewable Energy Ltd (a company

More information

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary Viridor Energy from Waste Facility Environmental Statement Non-Technical Summary September 2012 Viridor Energy from Waste Facility Environmental Statement Non-Technical Summary Introduction Viridor has

More information

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary Environmental Impact Assessment Report prepared by: Ecus Ltd. Brook Holt 3 Blackburn Road Sheffield S61 2DW 0114 266 9292 September 2013 Page Left Intentionally Blank 2 INTRODUCTION This Non Technical

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY S1014-0340-0008MPW NTS Rev1.doc Print Date 19 February 2009 ISSUE NUMBER 1 DATE 19/02/09 AUTHOR CHECKED MPW SMO Title Page

More information

A10 Electronic Interference: Application 1 - RBKC

A10 Electronic Interference: Application 1 - RBKC A10 Electronic Interference: Application 1 - RBKC Addendum to the Environmental Statement Volume I January 2012 Introduction A10.1 This Chapter of the Addendum to the June 2011 Environmental Statement

More information

Preliminary Environmental Information Report

Preliminary Environmental Information Report Riverside Energy Park Preliminary Environmental Information Report CHAPTER: 02 PLANNING INSPECTORATE REFERENCE NUMBER: EN010093 REGULATORY AND POLICY BACKGROUND June 2018 Revision 0 Planning Act 2008 Infrastructure

More information

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands Environmental Statement Non Technical Summary Anthony s Way Frindsbury June 2010 www.wyg.com creative minds safe hands Contents Section A Introduction Part 1 Background Part 2 Environmental Assessment

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION SEVERN ROAD RESOURCE RECOVERY CENTRE CHAPTER 1 INTRODUCTION SLR REF 402.0036.00374 September 2009 CONTENTS Introduction 2 Surrounding Area 3 Access 3 The Applicant 3 Summary of Development 4 Traffic and

More information

Energy from Waste Facility Environmental Statement Volume 1: Non-Technical Summary. July 2016

Energy from Waste Facility Environmental Statement Volume 1: Non-Technical Summary. July 2016 Energy from Waste Facility Environmental Statement Volume 1: Non-Technical Summary July 2016 This Environmental Statement has been prepared by Turley Planning on behalf of This is Protos with contributions

More information

7. EIA Assessment Methodology

7. EIA Assessment Methodology 7. EIA Assessment Methodology Introduction 7.1 This Chapter of the PEIR sets out the process and methodology that has been adopted in undertaking the draft EIA. Whilst the overall approach and methodology

More information

Ferrybridge Multifuel 2 (FM2) Power Station

Ferrybridge Multifuel 2 (FM2) Power Station Welcome Multifuel Energy Ltd is proposing to build a second multifuel power station at Ferrybridge (FM2). This formal consultation is an opportunity for you to provide feedback and comment on the Proposed

More information

GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary

GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary GlaxoSmithKline Wind Project Environmental Statement Non-Technical Summary 22871-G8.indd greec01 Dec 2009 December 2009 Based upon the Ordnance Survey Map with the permission of the Controller of Her Majesty

More information

PROPOSED ENERGY RECOVERY FACILITY Whistleberry Road, Hamilton

PROPOSED ENERGY RECOVERY FACILITY Whistleberry Road, Hamilton PROPOSED ENERGY RECOVERY FACILITY Whistleberry Road, Hamilton Clean Power owns a 4.5ha site at Whistleberry Road, Hamilton - the site of the former Craighead School. This site, which neighbours the East

More information

Chapter 8 LAND USE AND AGRICULTURE 8

Chapter 8 LAND USE AND AGRICULTURE 8 Chapter 8 LAND USE AND AGRICULTURE 8 8 Land use and agriculture Introduction 8.1 Terence O Rourke Ltd undertook the assessment of overall land use impacts and Richard Stock undertook the assessment of

More information

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY

ECO2 LINCS LTD SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY SLEAFORD RENEWABLE ENERGY PLANT IPPC APPLICATION - NON TECHNICAL SUMMARY ISSUE NUMBER 1 DATE 16/11/07 AUTHOR CHECKED SMO TME Title Page ISSUE NUMBER 1 DATE 16/11/07 AUTHOR CHECKED SMO TME Title Page TABLE

More information

LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY

LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 1 LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY Document Production &

More information

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT PLANNING APPLICATION TO REMOVE CONDITION 2 OF PLANNING PERMISSION REFERENCE TDC/94/065 TO EXTEND THE OPERATIONAL LIFE OF THE NON-HAZARDOUS AND HAZARDOUS

More information

Welcome to this exhibition by DS Smith Paper Ltd regarding the Kemsley Paper Mill (K4) CHP Plant project.

Welcome to this exhibition by DS Smith Paper Ltd regarding the Kemsley Paper Mill (K4) CHP Plant project. DS Smith Paper Ltd Welcome to this exhibition by DS Smith Paper Ltd regarding the Kemsley Paper Mill (K4) CHP Plant project. We will be applying to the Secretary of State for permission to build a new

More information

Ardley Waste Management Facility. Non Technical Summary

Ardley Waste Management Facility. Non Technical Summary Non Technical Summary CONTENTS 1.0 Introduction 2.0 Site Description 3.0 The Development 4.0 Alternatives 5.0 Potential Environmental Effects 6.0 Conclusions 1.0 Introduction 1.1 The Applicant 1.2 The

More information

Sustainability Statement

Sustainability Statement Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Sustainability Statement Doc Ref: 7.07 Appendix B.21 Greenwich Pumping Station

More information

How to determine if an EIA is of a good quality?

How to determine if an EIA is of a good quality? How to determine if an EIA is of a good quality? Paul McQuillan Principal Consultant 13 th April 2011 IEMA EIA Quality Mark scheme IEMA = Institute of Environmental Management & Assessment IEMA will launch

More information

A proposed new gas-fired power station on the Wilton International site

A proposed new gas-fired power station on the Wilton International site TEES CCPP PROJECT A proposed new gas-fired power station on the Wilton International site Welcome This event is intended to provide you with information about the proposed Tees Combined Cycle Power Plant

More information

NORTH LONDON WASTE AUTHORITY

NORTH LONDON WASTE AUTHORITY NORTH LONDON WASTE AUTHORITY REPORT TITLE: DEVELOPMENT CONSENT ORDER APPLICATION REPORT OF: Managing Director FOR SUBMISSION TO: NORTH LONDON WASTE AUTHORITY DATE: 25 SEPTEMBER 2015 SUMMARY OF REPORT:

More information

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories: 5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT 5.1 INTRODUCTION The scope of the EIA falls under three broad categories: technical scope; spatial scope; and temporal scope. The scoping process for the

More information

SgurrEnergy Ltd Linfairn Wind Farm Environmental Statement: Chapter 4

SgurrEnergy Ltd Linfairn Wind Farm Environmental Statement: Chapter 4 4 THE EIA PROCESS 4.1 OVERVIEW The purpose of an EIA is to provide a systematic analysis of the impacts of a project in relation to the existing (baseline) environment. The findings of an EIA are presented

More information

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION 6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

Land at KEMSLEY PAPER MILL (K4) CHP PLANT, SITTINGBOURNE, KENT. Preliminary Environmental Information

Land at KEMSLEY PAPER MILL (K4) CHP PLANT, SITTINGBOURNE, KENT. Preliminary Environmental Information Land at KEMSLEY PAPER MILL (K4) CHP PLANT, SITTINGBOURNE, KENT Preliminary Environmental Information November 2017 Introduction DS Smith Paper Limited ( the Applicant ) proposes to seek permission to decommission

More information

NON TECHNICAL SUMMARY

NON TECHNICAL SUMMARY INTRODUCTION 1. This document comprises a Non Technical Summary (NTS) and has been prepared by (SLR) on behalf of SITA UK (the applicant). 2. The NTS is part of a package of documents being submitted to

More information

Open vehicle storage Former Paper Mill Site Purfleet

Open vehicle storage Former Paper Mill Site Purfleet Open vehicle storage Former Paper Mill Site Purfleet Environmental statement Introduction NTS.1 NTS.2 NTS.3 NTS.4 NTS.5 (PRE) is applying to Thurrock Council (TC) for full planning permission for surface

More information

Welcome. from waste to resource. Millerhill Recycling and Energy Recovery Centre

Welcome. from waste to resource.   Millerhill Recycling and Energy Recovery Centre Welcome This exhibition is part of FCC Environment s commitment to inform and consult with local stakeholders on proposals for the Millerhill Recycling and Energy Recovery Centre (RERC). In December 2014,

More information

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT 1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT This Environmental Impact Assessment Report (EIA Report) has been prepared by Environmental Resources Management Ltd

More information

Proposed Multi Fuel Power Station. Environmental Statement. Non Technical Summary. October Prepared on behalf of

Proposed Multi Fuel Power Station. Environmental Statement. Non Technical Summary. October Prepared on behalf of Proposed Multi Fuel Power Station Environmental Statement Non Technical Summary October 2009 Prepared on behalf of Project Title: Report Title: Ferrybridge Multi Fuel Power Station Project No: 49307965

More information

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until 2035 Non Technical Summary SLR Consulting Limited Project Ref: 403.00079.00474

More information

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009 Introduction Viridor Waste Management

More information

Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE

Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE Mercia EnviRecover PROPOSED DEVELOPMENT OF A RENEWABLE ENERGY PLANT ON LAND AT HARTLEBURY TRADING ESTATE, HARTLEBURY, WORCESTERSHIRE Environmental Statement Regulation 19 Submission (3a) Other Information

More information

Preface. Gaia Power Ltd 71A High Street Yarm TS15 9BG. Tel: Web:

Preface. Gaia Power Ltd 71A High Street Yarm TS15 9BG. Tel: Web: Preface This document comprises the Environmental Statement and its Non- Technical Summary, which have been prepared in support of an application for planning consent for the construction of a biomass

More information

Cory Riverside Energy: A Carbon Case

Cory Riverside Energy: A Carbon Case Cory Riverside Energy: A Carbon Case [Type here] PAGE 2 Carbon Trust Peer Review Co r y Ri v e r s i d e E n e r g y: A Ca r b o n Ca s e The Carbon Trust has conducted a peer-review on the report Cory

More information

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT 4.1 INTRODUCTION This section describes the broad principles of the methodology adopted for the EIA of the Proposed Development. EIA is a procedure required

More information

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices Crossrail Environmental Statement Volume 9c Appendices Westbourne Park Bus Garage Extension Environmental Statement Volume 2 Appendices 9c If you would like information about Crossrail in your language,

More information

Viridor (Cardiff Energy Recovery Facility) Substantial Variation

Viridor (Cardiff Energy Recovery Facility) Substantial Variation Natural Resources Wales permitting decisions Viridor (Cardiff Energy Recovery Facility) Substantial Variation www.naturalresourceswales.gov.uk Issued 2 nd March 2017 Page 1 of 14 Contents Variation...

More information

THE ELECTRICITY ACT 1989 (AS AMENDED) - SECTION 36C VARIATION OF CONSENTS UNDER SECTION 36 - CONSENT REQUIRED FOR THE CONSTRUCTION ETC

THE ELECTRICITY ACT 1989 (AS AMENDED) - SECTION 36C VARIATION OF CONSENTS UNDER SECTION 36 - CONSENT REQUIRED FOR THE CONSTRUCTION ETC 21 Garlick Hill, London, EC4V 2AU T: 020 7489 0213 F: 020 7248 4743 E: info@dwdllp.com W: dwdllp.com Date: 25 July 2017 Your Ref: - Our Ref: 2941E The Secretary of State for Business, Energy and Industrial

More information

Mineral Products in London. Safeguarding London s Wharves and Rail Depots for future Prosperity and Sustainability

Mineral Products in London. Safeguarding London s Wharves and Rail Depots for future Prosperity and Sustainability Mineral Products in London Safeguarding London s Wharves and Rail Depots for future Prosperity and Sustainability Mineral Products in London Did you know? London s housing, building and infrastructure

More information

2013 No ENVIRONMENTAL PROTECTION ELECTRICITY. The Carbon Capture Readiness (Electricity Generating Stations) Regulations 2013

2013 No ENVIRONMENTAL PROTECTION ELECTRICITY. The Carbon Capture Readiness (Electricity Generating Stations) Regulations 2013 S T A T U T O R Y I N S T R U M E N T S 2013 No. 2696 ENVIRONMENTAL PROTECTION ELECTRICITY The Carbon Capture Readiness (Electricity Generating Stations) Regulations 2013 Made - - - - 17th October 2013

More information

Nobel Way, The Hub, off Witton Road, Perry Barr, Birmingham, B6 7EU

Nobel Way, The Hub, off Witton Road, Perry Barr, Birmingham, B6 7EU Committee Date: 11/06/2015 Application Number: 2015/02541/PA Accepted: 22/04/2015 Application Type: Reserved Matters Target Date: 22/07/2015 Development Ward: Perry Barr Nobel Way, The Hub, off Witton

More information

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref: Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell Volume 2 NON TECHNICAL SUMMARY December 2012 SLR Ref: 419.00034.00473 INTRODUCTION 1. This Non Technical Summary (NTS) has been produced by

More information

EXECUTIVE SUMMARY RESOURCES MERSEYSIDE A place where nothing is wasted. The Joint Recycling and Waste Management Strategy for Merseyside

EXECUTIVE SUMMARY RESOURCES MERSEYSIDE A place where nothing is wasted. The Joint Recycling and Waste Management Strategy for Merseyside EXECUTIVE SUMMARY RESOURCES MERSEYSIDE 2011-2041 A place where nothing is wasted The Joint Recycling and Waste Management Strategy for Merseyside Foreword We are pleased to present this Joint Recycling

More information

10.0 AIR QUALITY AND CLIMATIC FACTORS

10.0 AIR QUALITY AND CLIMATIC FACTORS .0 AIR QUALITY AND CLIMATIC FACTORS.1 ASSESSMENT METHODOLOGY.1.1 General Section 39 (2) (b) (ii) of the Transport (Railway Infrastructure) Act 2001, requires that proposed developments are examined in

More information

E.ON Climate & Renewables UK Developments Limited Portbury Dock Renewable Energy Plant Carbon Dioxide Emissions Study

E.ON Climate & Renewables UK Developments Limited Portbury Dock Renewable Energy Plant Carbon Dioxide Emissions Study E.ON Climate & Renewables UK Developments Limited Portbury Dock Renewable Energy Plant Carbon Dioxide Emissions Study August 2009 This report takes into account the particular instructions and requirements

More information

Environmental strategies

Environmental strategies Vauxhall Nine Elms Battersea Opportunity Area Planning Framework Chapter 9 Environmental strategies Mayor of London 131 new energy network for the OA strategic links to nearby energy networks Chapter 9

More information

Longbridge Town Centre Planning Application

Longbridge Town Centre Planning Application Longbridge Town Centre Planning Application Non-Technical Summary of the Environmental Statement January 2011 Introduction An application for Planning Permission has been submitted to Birmingham City Council

More information

4. Approach to the Phase 1B (North) Further Information Report

4. Approach to the Phase 1B (North) Further Information Report 4. Approach to the Phase 1B (North) Further Information Report Introduction 4.1.1 This Chapter sets out the general approach to the EIA process of the Phase 1B (North) RMA. The aims of the Report are set

More information

Non-Technical Summary

Non-Technical Summary 1. Introduction and Background 1.1 Following consultation Barwood Land and Estates Limited (Barwood Land) is making a number of minor amendments to and providing related additional information for the

More information

Greatmoor Energy from Waste Facility. Carbon Footprint Assessment

Greatmoor Energy from Waste Facility. Carbon Footprint Assessment Greatmoor Energy from Waste Facility Carbon Footprint Assessment 411-0197-00783 August 2010 WRG i 411-0197-00783 CONTENTS 1.0 INTRODUCTION... 1 2.0 METHODOLOGY... 1 3.0 RESULTS... 3 3.1 Characterising

More information

Pyrolysis is the thermal degradation of residual municipal waste in the absence of air to produce a solid fraction and syngas.

Pyrolysis is the thermal degradation of residual municipal waste in the absence of air to produce a solid fraction and syngas. Option 7: Pyrolysis/Gasification (with fuel preparation) The residual municipal waste in this option is firstly put through a mechanical treatment process, which prepares the waste for use as a fuel, typically

More information

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence;

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence; 14 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 14.1 INTRODUCTION Cumulative and indirect effects result from the combined impacts of multiple projects / plans. Their consideration is important as the impacts

More information

Chapter 4 Environmental Impact Assessment

Chapter 4 Environmental Impact Assessment Chapter 4 Environmental Impact Assessment Legacy Communities Scheme: Environmental Statement Chapter 4: Environmental Impact Assessment 4-1 4 Environmental Impact Assessment 4.1 Introduction This chapter

More information

REVISED NON-TECHNICAL SUMMARY INTEGRATED WASTE MANAGEMENT FACILITY, RIVENHALL AIRFIELD

REVISED NON-TECHNICAL SUMMARY INTEGRATED WASTE MANAGEMENT FACILITY, RIVENHALL AIRFIELD REVISED NON-TECHNICAL SUMMARY 1.0 Introduction This Revised Non-Technical Summary (NTS 2015) relates to the most recent and detailed proposals to construct the integrated waste management facility (IWMF)

More information

Berth 9 Quay Extension Environmental Statement Non-Technical Summary

Berth 9 Quay Extension Environmental Statement Non-Technical Summary Berth 9 Quay Extension Hutchison Ports UK Ltd July 2013 Final Report 9Y0150 CONTENTS Page 1 PROJECT BACKGROUND 1 2 NEED FOR THE PROPOSED SCHEME 4 3 DESCRIPTION OF THE CONSTRUCTION PHASE 4 4 DESCRIPTION

More information

IEMA ES Review Criteria

IEMA ES Review Criteria IEMA ES Review Criteria Structure of the Criteria The criteria are split into three sections and a review report is structured accordingly: Section 1 addresses all of the information contained within an

More information

Submarine Dismantling Project

Submarine Dismantling Project Title of document Submarine Dismantling Project The decision on the application to carry out a decommissioning project at Rosyth Royal Dockyard under the Nuclear Reactors (Environmental Impact Assessment

More information

Thorpe Marsh CCGT Power Station ENVIRONMENTAL STATEMENT SUPPLEMENTARY INFORMATION

Thorpe Marsh CCGT Power Station ENVIRONMENTAL STATEMENT SUPPLEMENTARY INFORMATION Thorpe Marsh CCGT Power Station ENVIRONMENTAL STATEMENT SUPPLEMENTARY INFORMATION Final June 2011 Thorpe Marsh CCGT Power Station ENVIRONMENTAL STATEMENT SUPPLEMENTARY INFORMATION Final June 2011 SKM Enviros

More information

It will be of particular interest to those potentially affected by the Government s proposals for high speed rail.

It will be of particular interest to those potentially affected by the Government s proposals for high speed rail. HIGH SPEED TWO INFORMATION PAPER E8: ARCHAEOLOGY This paper outlines HS2 Ltd's approach to assess and reduce as far as reasonably practicable the impact on archaeological remains that could result from

More information

Non-Technical Summary

Non-Technical Summary Tilbury Green Power Facility Environmental Statement Non-Technical Summary February 2008 3 Brindleyplace Birmingham B1 2JB Tilbury Green Power Facility Environmental Statement: Non-Technical Summary February

More information

CHP Ready Guidance for Combustion and Energy from Waste Power Plants

CHP Ready Guidance for Combustion and Energy from Waste Power Plants CHP Ready Guidance for Combustion and Energy from Waste Power Plants i Document Owner: National Services/ Knowledge, Strategy & Planning (KSP) Version History: Document Date Published Summary of Changes

More information

Ravenhead Quarry. Environment Act Application for Determination of Conditions (ROMP) Environmental Statement Non Technical Summary

Ravenhead Quarry. Environment Act Application for Determination of Conditions (ROMP) Environmental Statement Non Technical Summary Ravenhead Quarry I Environment Act 1995 Application for Determination of Conditions (ROMP) Environmental Statement Non Technical Summary November 2013 Prepared for: Ibstock Bricks (1996) Limited UNITED

More information

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening;

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; 5 TRAFFIC AND TRANSPORT 5.1 SUMMARY OF RESIDUAL IMPACTS The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening; be outside of the

More information

ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY

ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY PHASE 2 SECTION 73 AMENDMENTS ENVIRONMENTAL STATEMENT NON-TECHNICAL SUMMARY DECEMBER 2013 Battersea Power Station Phase 2 Amendment ES Non-Technical Summary Background This document provides a non-technical

More information

Environmental. Environmental Permits (EP) are required to operate an energy from waste facility within England and Wales. Guide page 32.

Environmental. Environmental Permits (EP) are required to operate an energy from waste facility within England and Wales. Guide page 32. Environmental Permitting Environmental Permits (EP) are required to operate an energy from waste facility within England and Wales. 1.0 Environmental Permitting 2.0 Waste inputs 3.0 Process control 4.0

More information

Phase 3 Section 73 Amendments ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY

Phase 3 Section 73 Amendments ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY Phase 3 Section 73 Amendments ENVIRONMENTAL STATEMENT: NON-TECHNICAL SUMMARY May 2014 Architects and Masterplanning Rafael Viñoly Architects 2-4 Exmoor Street, London W10 6BD T. +44 (0)20 8206 6200 F.

More information

Welcome To Our Exhibition

Welcome To Our Exhibition Welcome To Our Exhibition Welcome to the exhibition of our proposals for a Waste Recycling and Renewable Energy Facility Distributed Renewable Energy Networks Ltd (DRENL) propose to develop a 10MW Waste

More information

npower who we are Tilbury Power Station

npower who we are Tilbury Power Station npower who we are npower who we are RWE npower, part of the RWE Group, is the leading UK energy company committed to conducting its business with a sense of responsibility for the environment, its customers

More information

Air Quality. Executive Summary

Air Quality. Executive Summary Air Quality Executive Summary Air quality adjacent to the Scheme is currently good with low background concentrations of air pollutants. However, there are areas within Cambridge city centre which currently

More information

E3: EXCAVATED MATERIAL AND WASTE MANAGEMENT

E3: EXCAVATED MATERIAL AND WASTE MANAGEMENT HIGH SPEED TWO INFORMATION PAPER E3: EXCAVATED MATERIAL AND WASTE MANAGEMENT This paper outlines the approach for managing excavated material and waste that will arise from the construction of Phase One

More information

Harewood Whin Waste Transfer Station Environmental Statement

Harewood Whin Waste Transfer Station Environmental Statement Harewood Whin Waste Transfer Station Environmental Statement This document is the Environmental Statement for the proposed Waste Transfer Station at the site of the Harewood Whin Resource Recovery Facility,

More information

In-combination and Cumulative Effects Assessment

In-combination and Cumulative Effects Assessment P O R T I S H E A D B R A N C H L I N E P R E L I M I N A R Y ENV I R O N M E N T A L I N F O R M A T I O N R E P O R T V O L U M E 2 C H A P T E R 18 In-combination and Cumulative Effects Assessment Table

More information

Tunnel Vision Jobs for your future

Tunnel Vision Jobs for your future Tunnel Vision Jobs for your future Thames Tideway Tunnel aims to: Thames Tideway Tunnel What it means for local people Contractors will employ at least one apprentice for every 50 site employees at all

More information

Planning, Transport, Regeneration Overview and Scrutiny Committee

Planning, Transport, Regeneration Overview and Scrutiny Committee 4 March 2014 ITEM: 5 Planning, Transport, Regeneration Overview and Scrutiny Committee London Gateway Report of: Matthew Gallagher, Principal Planner (Major Applications) Wards and communities affected:

More information

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS 23 rd International Congress on Sound & Vibration Athens, Greece 10-14 July 2016 ICSV23 USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS Chris Skinner, Paul Shields and Yuyou Liu AECOM,

More information

Coire Glas Pumped Storage Scheme

Coire Glas Pumped Storage Scheme About SSE SSE is one of the UK s largest energy companies and is headquartered in Perth. Our purpose is to provide the energy people need in a reliable and sustainable way. We're involved in producing,

More information

NON-TECHNICAL SUMMARY

NON-TECHNICAL SUMMARY CONTENTS Introduction... 1 Planning and EIA... 2 The SIte... 2 Proposed Development... 3 AD Plant... 3 Revised Restoration... 3 Planning Policy... 4 Hydrogeology and Hydrology... 4 Landscape and Visual

More information

TIMARU DISTRICT COUNCIL HEARINGS COMMITTEE. To rezone land from Residential 4 to Industrial L. SITE: 8 Doncaster Street, Timaru - Pt Lot 33 DP 3363

TIMARU DISTRICT COUNCIL HEARINGS COMMITTEE. To rezone land from Residential 4 to Industrial L. SITE: 8 Doncaster Street, Timaru - Pt Lot 33 DP 3363 TIMARU DISTRICT COUNCIL HEARINGS COMMITTEE DECISION ON PROPOSED PLAN CHANGE NO. 8 APPLICANT: PROPOSAL: Alexander Sutherland Hogg To rezone land from Residential 4 to Industrial L SITE: 8 Doncaster Street,

More information

Environmental Impact Assessment. Volume 2: Environmental Statement

Environmental Impact Assessment. Volume 2: Environmental Statement Energy from Waste Facility Plot 8, Protos Environmental Impact Assessment Volume 2: Environmental Statement April 2018 This Environmental Statement has been prepared by Turley Planning on behalf of This

More information

New Earth Energy Ltd

New Earth Energy Ltd New Earth Energy Ltd Biomass Renewable Energy Facility at Dorset Green Technology Park, Winfrith Presentation to Dorset Energy Group District Heating Seminar 13 October 2009 Robert Asquith Planning Director

More information

ENVIRONMENTAL STATEMENT ADDENDUM Air Quality STAMBRIDGE MILLS ENVIRONMENTAL STATEMENT ADDENDUM OCTOBER 2010 PLANNING APPLICATION REFERENCE

ENVIRONMENTAL STATEMENT ADDENDUM Air Quality STAMBRIDGE MILLS ENVIRONMENTAL STATEMENT ADDENDUM OCTOBER 2010 PLANNING APPLICATION REFERENCE STAMBRIDGE MILLS ENVIRONMENTAL STATEMENT ADDENDUM OCTOBER 2010 PLANNING APPLICATION REFERENCE 11/00494/FUL An Environmental Statement was submitted to Rochford District Council (RDC) in August 2011 accompanying

More information

DEVELOPMENT OF A SUSTAINABLE ENERGY PLANT. KEMSLEY PAPER MILL, SITTINGBOURNE, KENT ST REGIS PAPER COMPANY LIMITED & E.ON ENERGY FROM WASTE UK LIMITED

DEVELOPMENT OF A SUSTAINABLE ENERGY PLANT. KEMSLEY PAPER MILL, SITTINGBOURNE, KENT ST REGIS PAPER COMPANY LIMITED & E.ON ENERGY FROM WASTE UK LIMITED DEVELOPMENT OF A SUSTAINABLE ENERGY PLANT. KEMSLEY PAPER MILL, SITTINGBOURNE, KENT ST REGIS PAPER COMPANY LIMITED & E.ON ENERGY FROM WASTE UK LIMITED ENVIRONMENTAL STATEMENT CHAPTER 1: INTRODUCTION Prepared

More information

Use of long term monitoring data for defining baseline sound levels

Use of long term monitoring data for defining baseline sound levels Use of long term monitoring data for defining baseline sound levels Chris SKINNER 1 ; Sue THOMAS 2 ; Paul SHIELDS 3 1 AECOM, UK 2 Tideway/Amec Foster Wheeler, UK 3 AECOM, UK ABSTRACT With the trend towards

More information

Newhurst Energy Recovery Facility, Shepshed, Leicestershire. Proposed modifications to the approved design. Volume 3 NON TECHNICAL SUMMARY

Newhurst Energy Recovery Facility, Shepshed, Leicestershire. Proposed modifications to the approved design. Volume 3 NON TECHNICAL SUMMARY Newhurst Energy Recovery Facility, Shepshed, Leicestershire Proposed modifications to the approved design Volume 3 NON TECHNICAL SUMMARY July 2014 SLR Ref: 403.04097.00005 Biffa Waste Services Limited

More information

PROPOSED MIXED USE DEVELOPMENT

PROPOSED MIXED USE DEVELOPMENT J Routledge & Sons PROPOSED MIXED USE DEVELOPMENT Land at Tanhouse Lane, Widnes Environmental Statement: Non-Technical Summary Planning Application: 05/00057/OUTEIA Tanhouse Lane Environmental Statement

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT ATTACHMENT 1 STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DETERMINATION OF ADEQUACY OF THE ENVIRONMENTAL IMPACT STATEMENT FOR THE OLMSTED WASTE-TO-ENERGY FACILITY: MUNICIPAL

More information

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary Sizewell B Dry Fuel Store Environmental Statement Non-Technical Summary NON TECHNICAL SUMMARY 1 INTRODUCTION This Non Technical Summary (NTS) is submitted as part of the application to extend the existing

More information

Sandy Knowe Wind Farm. Non-Technical Summary Addendum

Sandy Knowe Wind Farm. Non-Technical Summary Addendum Sandy Knowe Wind Farm Non-Technical Summary Addendum Sandy Knowe Wind Farm Ltd November 2013 SANDY KNOWE WIND FARM ii NON-TECHNICAL SUMMARY Contents 1 Background 1 2 Availability of the ES Addendum 2 3

More information