Consolidating Systems for a Greener Future:

Size: px
Start display at page:

Download "Consolidating Systems for a Greener Future:"

Transcription

1 FEATURE Consolidating Systems for a Greener Future: Trinity University s thermal utility upgrade Bradley A. Pankow, PE, Principal Engineer and Project Manager, Stanley Consultants; and Jesse Cabrera, PE, Senior Mechanical Engineer and Project Manager, Stanley Consultants T rinity University, founded in 1869, is a private liberal arts college set on a 117-acre hillside campus overlooking downtown San Antonio, Texas. A signatory to the American College & University Presidents Climate Commitment, Trinity has instituted numerous initiatives, under the banner of its Red Bricks/Green Campus sustainability program, aimed at reducing its environmental impact. These initiatives include the construction of new buildings to LEED (Leadership in Energy and Environmental Design) standards. The newest of these is the $127 million Center for the Sciences and Innovation, which opened in December 2013 and is the largest development ever undertaken on campus. In 2010, the impending science center construction and the campus s aging thermal utility system prompted Trinity University to look at its thermal utility infrastructure. Trinity hired Stanley Consultants to provide a comprehensive utility master plan that was closely coordinated with proposed campus expansion and improvements. This plan included a study of the merits of consolidating the campus s existing thermal utility plants and distribution systems in light of the science center s construction on the property occupied by the main plant. The three campus utility plants Bell, East and Main plants each Courtesy Trinity University. Photo Robert Benson. Trinity University s 280,000-sq-ft Center for the Sciences and Innovation is the latest of several new campus buildings to be built to LEED guidelines. Construction of the new center was an impetus for upgrading campus thermal utility systems. contained multiple chillers and hot water boilers with associated pumps. This arrangement delivered excess redundant capacity for the heating and cooling loads on campus. The completed utility master plan provided Trinity with thermal utility generation options and distribution system alternatives. It recommended consolidating the heating hot water generation into the East Plant and the chilled-water generation into the Bell Plant. Ultimately selected as the preferred course of action, this consolidation coupled with distribution system upgrades have already resulted in significant energy savings for Trinity University. 25

2 ENGINEERING DESIGN Design for the project kicked off in fall Stanley Consultants was selected to perform a comprehensive, multidisciplined engineering design of the utility plant consolidation that included the interconnection of the thermal utility loops into one distribution loop for chilled and heating hot water. The interconnection of the thermal utility distribution systems required hydraulic modeling of the entire campus distribution system to ensure adequate supply at each campus building. Consolidation also required an upgrade of the campus electrical distribution system. Twothirds of the campus electrical system was recabled to provide adequate capacity for the new chillers as well as to upgrade the campus for longterm sustainability. The natural gas line feeding the East Plant was similarly upgraded in size. An expedited design was critical, as the Main Plant needed to be off line and ready for demolition by January 2012 to make room for the new science center and to minimize disruption to the campus while students were present. In order to ensure that equipment would be available for installation during construction, equipment procurement packages were issued for the new chillers, cooling towers and heating hot water boilers. The preprocurement of equipment allowed the design team to prepare drawings for the installation of known equipment, reducing the time required for shop drawing review and eliminating the need for redesign of piping and electrical layouts. RVK Architects provided architectural services to the project, ensuring that the exteriors of the new East Plant addition, the renovated Bell Plant and the new cooling tower screen wall blended with existing campus architecture. Design drawings were completed for the East and Bell plants simultaneously to accommodate the phases required during construction. Having phased drawings in the construction 26 package provided clarity to contractors bidding on the project, which helped to reduce bid package review time and speed up the project award. The notice to proceed for design was given in September 2010, and 100 percent construction documents were completed in February Construction of both the chilled- and hot water plants commenced in April 2011, proceeding in seven phases to completion Jan. 5, BELL PLANT: CHILLED-WATER GENERATION The consolidation of the campus chilled-water generation systems into the Bell Plant included the installation of four new high-efficiency variablespeed 1,350-ton chillers and related cooling towers. This provided a total capacity of 5,400 tons at a delta T of 10 degrees F. The chilled-water pumping scheme consisted of direct primary design with variable-speed distribution pumps. The existing distribution systems were combined to provide a single variable-flow chilled-water loop served by the Bell Plant. The distribution pumps were equipped with variable-frequency drives to vary the chilled-water flow within the system to meet operating conditions. Construction phasing of the Bell Plant was critical to project execution, since chilled-water production needed to remain active throughout the process. Launched in April and May 2011, respectively, phases 1 and 2 consisted of preparing the existing Bell Plant for the new mechanical and electrical equipment. This included the excavation and expansion of the Bell Plant yard and construction of the retaining wall foundation. Next, underground electrical duct banks, equipment pads, unit switchgear, transformers and motor control centers were installed in phase 3. Additionally, the underground domestic water piping and headers for the chilled- and heating hot water systems were installed, as were the building and auxiliary heating hot water pumps once the existing boiler No. 2 in the Bell Plant was demolished. Begun in August 2011, phase 4 followed with the demolition of the existing boiler No. 1 and the remaining heating hot water system. Phase Four new high-efficiency variable-speed chillers like this one were purchased and installed as part of the Bell Plant redesign.

3 5 added chiller No. 1, including the balance of plant equipment necessary for operation. Later that fall, phase 6 demolished the existing chillers and electrical switchgear in the Bell Plant. New cooling towers and pumps were subsequently installed in the expanded yard. Ultimately, phase 7 added chillers Nos. 2, 3 and 4 and the balance of plant equipment for operation. EAST PLANT: HOT WATER GENERATION The consolidation of the hot water generation systems on campus into the East Plant entailed the installation of two new hot water boilers and the relocation of one hot water boiler from the Main Plant. Phasing of the East Plant construction was critical to project execution since heating hot water production needed to remain uninterrupted. Phase 1, launched in spring 2011 concurrently with the chilledwater plant project, consisted of the construction of a new larger building encompassing the existing East Plant. A new gas line and metering station were completed to supply Hot and chilled-water distribution piping was installed in an open-cut trench in King Street to connect buildings to the Bell Plant. natural gas to the new boiler systems. Also included was installation of a temporary boiler at the Bell Plant with variable-frequency drive distribution pumps to provide interim heating hot water for the East Campus during demolition of the existing hot water systems at the Bell and East plants. Phase 2 followed with the installation of new distribution piping between the East and Bell plants, to be connected during the initial stages of phase 3. The new header piping included connections for the temporary boiler system. Two new heating hot water boilers were then installed and connected to the distribution system. Later in the summer, phase 4 included the removal of the temporary boiler system and final tie-in of all heating hot water piping within the East Plant. Phases 5 and 6 did not include any work at the East Plant. After the Upper Campus tie-ins were complete to the thermal distribution system, phase 7 allowed for the Main Plant to be shut down and for the third heating hot water boiler to be relocated into the East Plant. As completed, the expanded East Plant delivers N+1 redundant capacity via three 13,390-Mlb/hr heating hot water boilers utilizing a primarysecondary pumping system to provide heating hot water to campus. During the winter months, the heating hot water system supplies 180 F to campus with a return temperature of 160 F. During shoulder and summer months, the supply temperature is reduced to 160 F to conserve energy. THERMAL DISTRIBUTION SYSTEMS As previously described, Trinity had been served by three independent thermal utility plants Main, East and Bell. The distribution systems were not interconnected, and each utility plant provided hot or chilled-water service to a dedicated set of buildings on its respective distribution system. Existing piping materials in the distribution systems included PVC, steel and Transite, some of which was insulated and jacketed in PVC. Thermal utility plant consolidation required that each distribution system be upgraded to include a main trunk line allowing for heating and cooling service supply throughout campus. The upgraded system was designed to accommodate future building expansion and to provide ease of connection to existing building branch piping. Flow modeling of the interconnected distribution system was completed to ensure flow requirements were met to each building and to determine plant pump head requirements. A major design and construction consideration for the project was a very short window for underground piping installation to minimize disruptions to the campus and the surrounding community. The design of the thermal distribution system started with a 3D laser scan survey of the planned piping routes. This allowed the design team to locate protected trees, light poles, sidewalks, retaining walls and buildings electronically. Using the 3D scan and modeling software, the design team was able to determine piping alignments that minimized surface damage and the need for tree restoration. After routings were selected, underground storm and sanitary sewers and potable water piping systems were studied from campus maps and site surveys as necessary. The resulting main trunk routing minimized surface restoration and installation time. The thermal energy distribution systems were designed with external insulation to conserve energy and minimize lifecycle costs. Carrier pipe materials (carbon steel, polyethylene, PVC and ductile iron) were evaluated based on life expectancy, installation time, durability and the need for thermal expansion compensation. Ductile iron pipe was selected as the most beneficial across the evaluation criteria. Additionally, ductile iron was chosen since it could be used for both chilled and heating hot water and required the least amount of installation labor for both systems com- 27

4 bined. Restrained joint connections were selected to eliminate the need for thrust blocks at directional changes and to allow for multiple installation options. Also, restrained joints installed with the spigot end pulled back against the retaining ring (fig. 1) allowed for a design free of expansion loops on the heating hot Figure 1. Restraining Ring. Restrained joint pipe allows for pullback against restraining ring to provide for pipe expansion. Restraining Ring Source: Stanley Consultants and American Cast Iron Pipe Co. water system, further reducing the system cost. Additional design considerations included future distribution system isolation and interim thermal utility supply to campus while the Bell and East Plant modifications were under construction. Historically, the Main Plant served the Upper Campus buildings with thermal utilities. Logistics dictated that the Main Plant remain in service as long as possible to keep the buildings conditioned. The Lower and East Campus thermal utilities were addressed early in construction by installing the main trunk piping between the East and Bell plants. Once the main trunk piping was installed, thermal utilities were supplied from the two plants. Thermal utility tie-ins to buildings were made during late summer and early fall Upper Campus installation was completed after the Lower Campus piping was brought on line. Isolation valves between the Upper and Lower campuses allowed the installation phasing to be completed. The transition to the new piping mains on Upper Campus was completed during the break between fall and spring semesters. The main trunk piping was filled, flushed, rinsed and energized with a one-day outage allowed at each building to make the connection to the new main. The thermal distribution systems each include a dirt/air/water separator to keep the piping systems free of sediment accumulation. Once thermal utilities were supplied to the buildings on the Upper Campus, the Main Plant was taken off line. OUTSTANDING RESULTS Although the project was incredibly complex, installation contractor Harvey-Cleary Builders and Stanley Consultants successfully completed the design and construction within a tight time frame with minimal interference to the campus activities. According to John W. Greene, Trinity University s director of campus planning and sustainability, the results System Snapshot: Trinity University Startup Year Number of Buildings Served Total Square Footage Served Plant Capacity Number of Boilers/Chillers Fuel Types Distribution Network Length Distribution Piping Type Piping Diameter Range System Pressure System Temperatures System Water Volume Hot Water System million sq ft East Plant: 40,170 Mlb/hr 3 boilers Natural gas 6,600 ft piping Restrained-joint ductile iron with urethane foam insulation and HDPE jacket 4 to 14 inches 55 psig 180 F supply/160 F return (winter) 160 F supply/140 F return (shoulder and summer months) 82,300 gal Chilled-Water System million sq ft Bell Plant: 5,400 tons 4 chillers Electric 6,600 ft piping Cement-lined, restrained-joint ductile iron with urethane foam insulation and HDPE jacket 4 to 20 inches 60 psig 42 F supply/52 F return 125,600 gal Source: Stanley Consultants. 28

5 have been outstanding. He explains: The project has allowed Trinity to move forward with the construction of an equally outstanding Center for the Sciences and Innovation. The systems are working flawlessly. Greene adds that the campuswide electrical consumption has been reduced by around 10 percent and has not been this low since more than 10 years ago when the university had less square footage to air condition. With their inherent efficiencies and the energy savings they make possible, Trinity University s upgraded thermal utility systems are now more than ever prepared to help the institution achieve its goal of making tomorrow greener than today. Bradley A. Pankow, PE, is principal mechanical engineer and project manager for Stanley Consultants, focusing on educational and institutional steam, hot water and chilled-water generation and distribution systems. He was formerly factory manager and operations manager with H.J. Heinz, lead mechanical engineer for Raytheon Engineers and Constructors, and engineering manager for Rovanco Piping Systems Inc. Pankow holds Bachelor of Science in Mechanical Engineering and Master of Science in Engineering degrees from the University of Wisconsin-Platteville. He can be contacted at pankowbradley@stanleygroup.com. Jesse Cabrera, PE, senior mechanical engineer and project manager for Stanley Consultants, is experienced in large central heating and chilledwater facilities and distribution systems, and electric generating and combined-cycle plants. Previously, he was a project engineer for El Paso Electric Co. and Houston Lighting & Power Co. Cabrera earned a Bachelor of Science in Mechanical Engineering degree from The University of Texas at Austin and a Master of Business Administration degree from Texas State UniversitySan Marcos. He may be reached at cabrerajesse@stanleygroup.com. INSTALLATION COSTS REDUCED WITH VALUE ENGINEERING Applying value engineering in the thermal utility project, Trinity University, Stanley Consultants and installation contractor Harvey-Cleary Builders reduced project costs and preserved the construction schedule, while minimizing student and campus interruptions. Initial project bids had come in on the project with unfavorable results due to the compressed installation schedule, area subsurface rock, underground utilities and surface restoration costs. Working with the installation contractor and the university, the engineering team reviewed installation techniques that would bring down installation costs. These techniques required vetting of the piping material and the manufacturer s installation instructions against the system design and the proposed directional boring installation. Directional boring allowed the contractor to install the piping below existing underground utilities, reducing utility interruptions and relocations and subsequently reducing the amount of surface damage and restoration to be completed. Harvey-Cleary Builders enlisted an underground piping subcontractor experienced in installing direct-buried systems to handle this job. The use of restrained joint piping, mechanical joint fittings and valves, and transition couplings allowed the installation to be completed on time. Building connections from the main trunk piping were made on a building-by-building basis. Valve boxes placed at each branch connection allowed for building isolation in the event of future underground piping issues and for switching between chilled- and heating hot water service for those buildings not served by a four-pipe system. The valve switching areas for two-pipe systems at three buildings were designed and installed such that a future switch to a four-pipe system could be completed with relative ease. Directional boring, including under existing utilities, reduced surface restoration and minimized utility reroutes and conflicts. Shown here is the valve and directional-bore receiving pit on Upper Campus. 29

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES. David Payne, P.E Interim Associate Director October 16, 2012

DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES. David Payne, P.E Interim Associate Director October 16, 2012 DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES David Payne, P.E Interim Associate Director October 16, 2012 Agenda - Production System Overview - Distributions Systems Overview - Recently Completed

More information

Re-envisioning district energy at Sheridan College

Re-envisioning district energy at Sheridan College FEATURE Re-envisioning district energy at Sheridan College Systems on two campuses are being implemented and optimized according to European standards. Pernille M. Overbye, Managing Director, Ramboll Inc.;

More information

CHILLED WATER DISTRIBUTION SYSTEM

CHILLED WATER DISTRIBUTION SYSTEM Campus-Wide System: A campus-wide central chilled water system has been developed in recent years and is being expanded to serve additional cooling loads as need arises and opportunity affords. This system

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and

More information

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL Page 312 VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS-12-01 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the IL ROUTE

More information

MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011

MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011 MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011 The Building Committee for the SDSU Central Heating Plant Boiler Replacement and Plant Upgrades met

More information

CHILLED WATER SUB-ELEMENT Goal 1 To provide heating water and chilled water to satisfy the building demands to support the mission of the University.

CHILLED WATER SUB-ELEMENT Goal 1 To provide heating water and chilled water to satisfy the building demands to support the mission of the University. ELEMENT 10 UTILITIES ELEMENT INCLUDING SUB-ELEMENTS: Chilled Water and Reheat Water Electrical Power and Other Fuels Telecommunications Systems UTILITIES ELEMENT CHILLED WATER SUB-ELEMENT Goal 1 To provide

More information

STANDARD DETAILS. Revised January Bonita Springs Utilities, Inc East Terry Street (239)

STANDARD DETAILS. Revised January Bonita Springs Utilities, Inc East Terry Street (239) STANDARD DETAILS Revised January 2018 Bonita Springs Utilities, Inc. 11900 East Terry Street Bonita Springs, FL 34135 (239) 992-0711 DETAIL SHEET INDEX WATER DETAILS W-1 CONSTRUCTION JUMPER ASSEMBLY W-2

More information

Moving Toward Greater Sustainability: Oklahoma State University Builds a New Central Plant

Moving Toward Greater Sustainability: Oklahoma State University Builds a New Central Plant Moving Toward Greater Sustainability: Oklahoma State University Builds a New Central Plant June 21, 2016 Introductions James Rosner, PE, CEM (james.rosner@okstate.edu) - Director of Energy Services, Oklahoma

More information

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested. Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure

More information

Utilities Infrastructure Master Plan UK JANUARY 2016 FINAL DRAFT

Utilities Infrastructure Master Plan UK JANUARY 2016 FINAL DRAFT FINAL DRAFT Utilities Infrastructure Master Plan UK-1553-15 JANUARY 2016 Executive Summary Please contact Jeff Zumwalt (jeff.zumwalt@uky.edu) for more information 1. EXECUTIVE SUMMARY 1.1 Goals and Objectives

More information

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS 1 33 63 00 - Underground Steam and Condensate Distribution System 1. Introduction A. Steam is distributed to University and Medical Center buildings through an underground piping system year-round at a

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

University of Massachusetts Procurement Department 140 Hicks Way 407 Goodell Building Amherst, MA 01003

University of Massachusetts Procurement Department 140 Hicks Way 407 Goodell Building Amherst, MA 01003 University of Massachusetts Procurement Department 140 Hicks Way 407 Goodell Building Amherst, MA 01003 May 16, 2016 Addendum #1 Contract Number: UMA16-25 Project Number: 1000730 Speedtype: 157194 Title:

More information

REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System

REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System Issued by the City of Montpelier, Vermont Department of Planning and Community Development Responses Due: August 12, 2011,

More information

SECTION WATER DISTRIBUTION SYSTEM

SECTION WATER DISTRIBUTION SYSTEM Conditions of Use/ Responsibility of Data Montgomery County Public Schools Facilities Guide DIVISION 2 - SITE WORK These guideline specifications are to be used by the A/E as a base document in the development

More information

ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE CAPITOL IDEA CAMPUS ENERGY CONFERENCE MARCH 8, 2018

ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE CAPITOL IDEA CAMPUS ENERGY CONFERENCE MARCH 8, 2018 WWW.AOC.GOV 1 ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE CAPITOL IDEA CAMPUS ENERGY CONFERENCE MARCH 8, 2018 ACCOMPLISHMENTS IN ENERGY REDUCTION EFFORTS AT THE ARCHITECT OF THE

More information

TEXAS A&M ENGINEERING

TEXAS A&M ENGINEERING TEXAS A&M ENGINEERING 312 Jack K. Williams Administration Building I 3126 TAMU I College Station, Texas 77843-3126 M. Katherine Banks, Ph.D., P.E. Vice Chancellor and Dean of Engineering Director, Texas

More information

District Energy YALE UNIVERSITY S COGENERATION SYSTEM UPGRADE SCOTTSDALE CONFERENCE REVIEW Q&A WITH IDEA S NEW CHAIR REUSING DATA CENTER WASTE HEAT

District Energy YALE UNIVERSITY S COGENERATION SYSTEM UPGRADE SCOTTSDALE CONFERENCE REVIEW Q&A WITH IDEA S NEW CHAIR REUSING DATA CENTER WASTE HEAT District Energy 10 YALE UNIVERSITY S COGENERATION SYSTEM UPGRADE 6 19 22 30 THIRD QUARTER 2017 REUSING DATA CENTER WASTE HEAT Q&A WITH IDEA S NEW CHAIR SCOTTSDALE CONFERENCE REVIEW TELLING THE GREEN STEAM

More information

PVC. System Specifications TABLE 1 TABLE 2

PVC. System Specifications TABLE 1 TABLE 2 TRICON PVC TABLE 1 Pipe Size Minimum Insulation Thickness PVC Jacket O.D. PVC Jacket Wall 2 1.81 6.14.070 3 1.25 6.14.070 4 1.75 8.16.080 6 1.69 10.20.100 8 1.69 12.24.120 10 1.65 14.32.140 12 1.47 16.00.160

More information

LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN. APPENDIX N - Campus Utilities Assessment Findings

LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN. APPENDIX N - Campus Utilities Assessment Findings LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN APPENDIX N - Campus Utilities Assessment Findings Louisiana State University Campus Master Plan Campus Utilities Introduction Based

More information

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

GENERAL UTILITIES REQUIREMENTS

GENERAL UTILITIES REQUIREMENTS 33 00 00 GENERAL UTILITIES REQUIREMENTS i. 01 41 26.02 Local Utility Information & Locate ii. 23 05 19 Meters and Gages iii. 33 10 00 Water Utilities Public Water Distribution System iv. 33 12 13.13 Water

More information

SECTION 1 GENERAL NOTES

SECTION 1 GENERAL NOTES ISSUE DATE NOVEMBER 1st, 2011 SECTION 1 Page List Page Number Page Title COVER COVER GN-01 PAGE 1 GN-02 PAGE 2 GN-03 PAGE 3 GN-04 PAGE 4 GN-05 PAGE 5 GN-06 PAGE 6 GN-07 PAGE 7 : 1. (CCU) STANDARD SPECIFICATIONS

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

STEAM TO HOT WATER CONVERSION

STEAM TO HOT WATER CONVERSION STEAM TO HOT WATER CONVERSION Steam to Hot Water Conversion Toronto 300-3901 Highway #7 Vaughan, ON L4L 8L5 (905) 265-9777 Vancouver 210-4180 Lougheed Highway Burnaby, BC V5C 6A7 (604) 689-3410 www.fvbenergy.com

More information

SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6

SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6 SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO. 18-4501 SOLICITATION NO. CO-00198 ADDENDUM 6 (September 10, 2018) To Respondent of Record: This addendum, applicable to work referenced

More information

E. CONSTRUCTION PROCEDURES

E. CONSTRUCTION PROCEDURES E. CONSTRUCTION PROCEDURES The Project facilities would be constructed in accordance with established electric utility practices, best management practices, final engineering plans, CL&P s specifications

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

EADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel Mechanical Option

EADQUARTERS. Thesis Revised Proposal. Stephanie Kunkel  Mechanical Option EADQUARTERS 707 N. Calvert St. Mechanical System Renovation Construction Management & Lighting/Electrical Breadths Stephanie Kunkel www.engr.psu.edu/ae/thesis/portfolios/2011/slk5061 Mechanical Option

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

KEY ELEMENTARY SCHOOL

KEY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1925 BUILDING AREA 52,000 SF CURRENT PROGRAM CAPACITY 320 ENROLLMENT 2008 328 WARD 3 PROPOSED PROGRAM CAPACITY 325 Site Plan KEY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018 PART 1 - GENERAL... 2 1.1 Work Included... 2 1.2 Related Sections... 2 1.3 Reference Standards... 2 1.4 Shop Drawings... 3 1.5 Certificates...

More information

STATE UNIVERPROGRAM DIRECTIVES

STATE UNIVERPROGRAM DIRECTIVES DIRECTIVE 15H-10 PIPING TYPES AND MATERIALS Issue date: September 2017 Steam & Condensate Piping Service & Location Pipe Size Pipe Material & Weight Joint Type Fitting Material Insulation Material Low

More information

Brown University Updated March 11, 2013 Facilities Design & Construction Standards

Brown University Updated March 11, 2013 Facilities Design & Construction Standards SECTION 01 17 90 UTILITY & CRITICAL SYSTEM CONNECTIONS AND INTERRUPTIONS PART 1 - GENERAL 1.1 SUMMARY: A. Brown University operates and maintains extensive campus and building utilities and distribution

More information

UVM Central Utility Plant: A Half Century of Growth, Innovation, & Efficiency

UVM Central Utility Plant: A Half Century of Growth, Innovation, & Efficiency UVM Central Utility Plant: A Half Century of Growth, Innovation, & Efficiency IDEA Campus Energy 2018 Baltimore, MD Presenters: Sal Chiarelli, UVM, Mike Pelletier, UVM, Bill Mahoney, RMF Time: 10:30 AM

More information

CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS SECTION 00005B TABLE OF CONTENTS ***CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS***

CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS SECTION 00005B TABLE OF CONTENTS ***CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS*** 00005B *** *** BOLD ITALICIZED Item is bound within this specification manual. Regular non-italicized Item is not bound within this specification manual, however item is part of the contract. Contents

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

GENERAL NOTES FOR FORCE MAINS: *CONTACTOR SHALL HAVE RICHMOND UTILITIES PERSONNEL ON SITE WHEN DIGGING OVER OR AROUND UTILITY LINES AND PUMP STATIONS. CONTRACTOR SHALL SCHEDULE EXCAVATION WITH RICHMOND

More information

General Water Bid Items Item No.

General Water Bid Items Item No. BID PROPOSAL PROPOSAL OF, a corporation organized and existing under the laws of the State of, a partnership consisting of, an individual doing business as. Enclosed with this bid are (1) Bid Bond, and

More information

Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal.

Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal. ACKNOWLEDGEMENT BY RESPONDENT Each Respondent shall acknowledge receipt of this Addendum No. 1 by noting such and signing the Bid Proposal. This undersigned acknowledges receipt of this Addendum No. 1

More information

Carleton College Utility Master Plan. Martha M. Larson, CEM Manager of Campus Energy & Sustainability

Carleton College Utility Master Plan. Martha M. Larson, CEM Manager of Campus Energy & Sustainability Carleton College Utility Master Plan Martha M. Larson, CEM Manager of Campus Energy & Sustainability June 15, 2018 Planning Progression Carleton s utility plan is part of a 10-year planning progression.

More information

CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO RA Addendum 2 July 22 nd 2016

CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO RA Addendum 2 July 22 nd 2016 To Respondent of Record: CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO-00082-RA Addendum 2 July 22 nd 2016 This addendum, applicable to work referenced above, is an amendment to the

More information

Business Partner Whitepaper Series Wake Forest University An Investment Renewed

Business Partner Whitepaper Series Wake Forest University An Investment Renewed Business Partner Whitepaper Series Wake Forest University An Investment Renewed By Gregory A. Carnathan, PE, CEM, LEED AP Mechanical Project Manager / Associate at RMF Engineering Business Partner Whitepaper

More information

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CHAPTER 3 WATER SYSTEM DESIGN 3.1 WATER SYSTEM DESIGN GENERAL 3.1.1 Criteria for the design of water service and water distribution lines

More information

SPECIAL SPECIFICATION. Water and Sewer System and Appurtenances

SPECIAL SPECIFICATION. Water and Sewer System and Appurtenances 2004 Specifications CSJ 2250-01-021, etc SPECIAL SPECIFICATION 5243 Water and Sewer System and Appurtenances 1. Description. This Item governs for the furnishing of all equipment, labor and materials to

More information

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION 33 11 13.24 POLYETHYLENE PRESSURE PIPE PART 1 GENERAL... 2 1.1 Description... 2 1.2 Reference Specification... 2 1.3

More information

POWER ENGINEERS We Help You Succeed

POWER ENGINEERS We Help You Succeed POWER ENGINEERS We Help You Succeed POWER FACTS»» Founded in 1976»» 2,300+ employees»» Offices nationwide & overseas»» Employee-owned ENERGY»» Transmission & Distribution Line Design Overhead & Underground

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE

CHARLES COUNTY GOVERNMENT ITB NO WAKEFIELD PUMPING STATION UPGRADE CHARLES COUNTY GOVERNMENT Department of Fiscal and Administrative Services Purchasing Division Telephone: 301-645-0656 February 27, 2014 ITB NO. 14-33 WAKEFIELD PUMPING STATION UPGRADE ADDENDUM NUMBER

More information

Division 33. Utilities

Division 33. Utilities See Section 32 for requirements on Utility Plan Preparation. 33 10 00. Water Utilities 33 11 00. Water Utility Distribution Piping 1. All underground pipe material, 4 inch diameter and larger shall be

More information

Session: Date: Thursday, October 2, :00 am 11:00 am

Session: Date: Thursday, October 2, :00 am 11:00 am Session: 100205 Date: Thursday, October 2, 2014 Time: 10:00 am 11:00 am Serving a New Medical District The Utility Plant Challenge Presented by: Juan Ontiveros Executive Director Utilities and Energy Management

More information

University Medical Center at. Healthy Success: Hospital energy system showcases best practices. Feature Story

University Medical Center at. Healthy Success: Hospital energy system showcases best practices. Feature Story Feature Story Healthy Success: Hospital energy system showcases best practices Guy Molinari, PE, LEED AP, Senior Vice President, Concord Engineering Group; Thomas Batten, PE, Project Manager and Lead Mechanical

More information

Applying Geothermal Technology for Large Scale Projects

Applying Geothermal Technology for Large Scale Projects Jeff Urlaub, PE MEP Associates, LLC jeffu@mepassociats.com 715.832.5680 Engineering Future Focused Solutions Applying Geothermal Technology for Large Scale Projects Breakout Session Category (e.g. Residential)

More information

TECHNICAL SPECIAL PROVISION PIPE BURSTING BISCAYNE ISLAND DRAINAGE IMPROVEMENTS PROJECT NO.: B-30588

TECHNICAL SPECIAL PROVISION PIPE BURSTING BISCAYNE ISLAND DRAINAGE IMPROVEMENTS PROJECT NO.: B-30588 TECHNICAL SPECIAL PROVISION PIPE BURSTING BISCAYNE ISLAND DRAINAGE IMPROVEMENTS PROJECT NO.: B-30588 Mayor Tomas P. Regalado Commissioner Wilfredo Willy Gort, District 1 Commissioner Marc Sarnoff, District

More information

SECTION 2100 WATER MAIN

SECTION 2100 WATER MAIN SECTION 2100 WATER MAIN WATER MAIN PART 1 GENERAL 1.01 Section Summary A. This section includes product and installation requirements for water main pipe, gate valves, hydrants, fittings, and miscellaneous

More information

[THESIS PROPOSAL] North Hall American University Washington, D.C.

[THESIS PROPOSAL] North Hall American University Washington, D.C. 2013 Brandon Tezak, LEED Green Associate Construction Management Option Faculty Advisor: Dr. Anumba January 9, 2013 [THESIS PROPOSAL] North Hall American University Washington, D.C. Executive Summary After

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT AND MANAGER that offers comprehensive management throughout the project, from concept to completion, yielding the greatest possible benefit to the owner. IPS will offer uncolored

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 5100 - SANITARY SEWER MAIN PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of sanitary sewer mains and services. Topics include permits and fees, record drawings, pipe materials,

More information

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction. General: 1. Construct utilities in accordance to TWA approved plans and shop drawings. Any deviation from the approved plans shall be approved by the DEVELOPER S ENGINEER and TWA 2. A preconstruction meeting

More information

1. Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1. Section Temporary Facilities and Controls for limitations and procedures governing temporary use of Owner's facilities. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

McDuff WTP High Service Pump Replacement

McDuff WTP High Service Pump Replacement T E C H N I C A L M E M O R A N D U M 642-03 MCDUFF WTP HIGH SERVICE PUMP REPLACEMENT 642-03 McDuff WTP High Service Pump Replacement PREPARED FOR: PREPARED BY: Capital Budget Planning Craig Jones DATE:

More information

RESOLUTION WHEREAS,

RESOLUTION WHEREAS, APPROVAL TO PROCEED WITH CONSTRUCTION FOR ALDEN LIBRARY ROOF REPLACEMENT - CONSTRUCTION PHASE, BACK SOUTH DEMOLITION - CONSTRUCTION PHASE AND BUDGET AMENDMENT, COLLEGE OF FINE ARTS (LIN HALL) INFRASTRUCTURE

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract

More information

APPA Institute, Dallas TX, February

APPA Institute, Dallas TX, February Heating System Distribution EU 332 Jay W. Becker, PE Key Points Take Aways Planning is vital Build for the future Know Campus layout Reliability meeting needs Economics / options / trade offs Good Design

More information

SECTION PLUMBING PIPING SYSTEMS

SECTION PLUMBING PIPING SYSTEMS SECTION 15300 PLUMBING PIPING SYSTEMS PART 1 - GENERAL 1.01 SPECIAL NOTICE A. Each contractor shall read all relevant documents, become familiar with the job, the scope of work, type of general construction,

More information

Sample. Bid Proposal. Not Valid for Use

Sample. Bid Proposal. Not Valid for Use BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions Invitations to Bidders, the undersigned proposes

More information

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal

Broad Institute Expansion: Cambridge, Massachusetts. Mechanical Thesis Proposal Broad Institute Expansion: Cambridge, Massachusetts Mechanical Thesis Proposal Table of Contents Executive Summary... 2 Building Overview... 3 Mechanical System Overview... 4 Mechanical System Design Objectives...

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

Revision Date: February 28,

Revision Date: February 28, FACILITY SERVICES - REQUIREMENTS FOR PLUMBING, FIRE PROTECTION, HVAC, AND ELECTRIC DOCUMENTS 2007 Edition, Published April, 2007, Revision Date: February 28, 2018 FS-1. SEPARATE DOCUMENTS REQUIRED.2 SEPARATION

More information

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Applications for New Installations There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Note that some specifications

More information

NEW MIDDLE SCHOOL PROJECT

NEW MIDDLE SCHOOL PROJECT Monthly Report May 2017 2 INTRODUCTION P.J. Dick Incorporated is pleased to present to the Chartiers Valley Board of School Directors the following Construction Report for the Chartiers Valley Middle School

More information

DIVISION 33 UTILITIES

DIVISION 33 UTILITIES DIVISION 33 UTILITIES This Article on Codes, Regulation and Standards shall apply to all Divisions of the Building Standards Table of Contents 33 05 13 MANHOLES AND STRUCTURES... 3 33 10 00 WATER UTILITIES...

More information

THESIS PROPOSAL UNIVERSITY RIDGE AT EAST STROUDSBURG UNIVERSITY EAST STROUDSBURG, PA PREPARED FOR: JAMES FREIHAUT, PH.D.

THESIS PROPOSAL UNIVERSITY RIDGE AT EAST STROUDSBURG UNIVERSITY EAST STROUDSBURG, PA PREPARED FOR: JAMES FREIHAUT, PH.D. THESIS PROPOSAL UNIVERSITY RIDGE AT EAST STROUDSBURG UNIVERSITY EAST STROUDSBURG, PA PREPARED FOR: JAMES FREIHAUT, PH.D. BY: MATTHEW CARR MECHANICAL OPTION JANUARY 22, 2007 Table of Contents Executive

More information

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES This article was published in ASHRAE Journal, January 2014. Copyright 2014 ASHRAE. Posted at www. ashrae.org. This article may not be copied and/or distributed electronically or in paper form without permission

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS ITEM NO. 848 SANITARY SEWERS 848.1 DESCRIPTION: This item shall govern the furnishing, installation and jointing of sanitary sewer pipe of the size and type specified by the project's plans and specifications.

More information

PRESENTED BY: BRAD SWEARINGEN JIM NONNENMANN, PE

PRESENTED BY: BRAD SWEARINGEN JIM NONNENMANN, PE IDEA CAMPUS ENERGY 2016 : THE CHANGING LANDSCAPE PRVN CONSULTANTS, INC. PRESENTED BY: BRAD SWEARINGEN JIM NONNENMANN, PE AGENDA Research Campus Utilities Overview Chilled Water Need and Project Goals Project

More information

Bid Tabulation Report 2011 Pump Station Rehabilitations

Bid Tabulation Report 2011 Pump Station Rehabilitations Bidder No. 1 Bidder No. 2 Bidder No. 3 Bidder No. 4 Bonding Provided 5% 5% 5% 5% Bidder Acknowledges Receipt of Addendums - but only 1 Affadivit of Preferential Bidders Status has has has has Description

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

San Francisco Distribution System Seismic Reliability using Earthquake- Resistant Ductile Iron Pipe. Part I: Procurement and Design

San Francisco Distribution System Seismic Reliability using Earthquake- Resistant Ductile Iron Pipe. Part I: Procurement and Design San Francisco Distribution System Seismic Reliability using Earthquake- Resistant Ductile Iron Pipe Part I: Procurement and Design CA-NV AWWA Fall Conference 2014 Katie Miller, P.E. Manager, City Distribution

More information

Agenda. About UTMB 9/24/2013

Agenda. About UTMB 9/24/2013 THE UNIVERSITY OF TEXAS MEDICAL BRANCH (UTMB) AT GALVESTON Energy Security on a Barrier Island Presented to CAPPA 2013 - Annual Conference Tuesday, Oct. 1, 2013 Agenda About UTMB Galveston Hurricane Ike

More information

INVITATION TO BIDDERS. Solicitation No. CO-00157

INVITATION TO BIDDERS. Solicitation No. CO-00157 INVITATION TO BIDDERS Solicitation No. CO-00157 Sealed bids are requested by the San Antonio Water System for the construction of approximately 5,900 LF of 6 to 8-inch of water main and approximately 3,000LF

More information

GAPPA News. GAPPA 2011 Leading in Lean Time LEADING IN LEAN TIMES

GAPPA News. GAPPA 2011 Leading in Lean Time LEADING IN LEAN TIMES August 2011 GAPPA 2011 Leading in Lean Time The 2011 GAPPA annual meeting at Jekyll Island was a success. We had 102 booths and plenty of attendees. The facilities were nice and accommodating. 26 members

More information

Case Studies and Approach

Case Studies and Approach Incorporating Renewable Energy into Performance Contracts Case Studies and Approach Steven Spanbauer Energy Systems Group August 10, 2016 Rhode Island Convention Center Providence, Rhode Island Agenda

More information

Honorable Mayor and City Council, Project Management Team c/o Jeff Hulsether, PE City Engineer

Honorable Mayor and City Council, Project Management Team c/o Jeff Hulsether, PE City Engineer MEMORANDUM TO: FROM: Honorable Mayor and City Council, Project Management Team c/o Jeff Hulsether, PE City Engineer Scott D. Hedlund, PE, PMP DATE: RE: Monthly Project Status Update SEH No. BRDMN 131759

More information

REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County

REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County REQUEST FOR PROPOSALS Garfield Charter Township Hall Sidewalk Snowmelt Heating System Repairs Garfield Township, Grand Traverse County Proposals Due: 10:00 A.M., Thursday, March 28, 2019 Address Proposals

More information

Project Case Study. Motor City DCP. Project: District Cooling Plant, Motor City Start Date: 2007 Completion Date: 2010

Project Case Study. Motor City DCP. Project: District Cooling Plant, Motor City Start Date: 2007 Completion Date: 2010 Project: District Cooling Plant, Motor City Start Date: 2007 Completion Date: 2010 Location: Dubai, UAE Industry: District Cooling Developer: Emicool Consultant/Architect: DC Pro Engineering Value: US

More information

Ground Source Heat Pump System Design and Permitting AWWA Pacific Northwest Section Conference, May 6-8, 2009 Salem, Oregon

Ground Source Heat Pump System Design and Permitting AWWA Pacific Northwest Section Conference, May 6-8, 2009 Salem, Oregon Paul D. Stull III, P.E. Paul.Stull@amec.com Tyler Clary, PE Tyler.Clary@ci.vancouver.wa.us City of Vancouver Vancouver, WA 360.487.7169 Ground Source Heat Pump System Design and Permitting AWWA Pacific

More information

Mission Critical Commissioning for Healthcare Facilities

Mission Critical Commissioning for Healthcare Facilities Mission Critical Commissioning for Healthcare Facilities Steven R. Rusty Ross SSRCx, LLC Synopsis Healthcare Facilities serve a critical and unique mission. Few facilities delivered by the construction

More information

Program Update. Chino Health Science Parking Lot

Program Update. Chino Health Science Parking Lot Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction

More information

Chilled Water Plant Assessment & Criteria Design

Chilled Water Plant Assessment & Criteria Design Chilled Water Plant Assessment & Criteria Design Prepared for: Cleveland Airport System November 14, 2016 PREPARED BY: 1100 Superior Avenue Cleveland, Ohio 44114 (216)681-2020 TABLE OF CONTENTS SECTION

More information

DUO-THERM 505 Specification Guide

DUO-THERM 505 Specification Guide STANDARD SPECIFICATION 3.101 7.01.08 Part 1 - General Duo - Therm 505 Steel Piping Systems suitable for Steam, High Temperature Hot Water, Gravity and Pumped Condensate. 1.1 Pre-insulated Piping - Furnish

More information