Bid Tabulation Report 2011 Pump Station Rehabilitations

Size: px
Start display at page:

Download "Bid Tabulation Report 2011 Pump Station Rehabilitations"

Transcription

1 Bidder No. 1 Bidder No. 2 Bidder No. 3 Bidder No. 4 Bonding Provided 5% 5% 5% 5% Bidder Acknowledges Receipt of Addendums - but only 1 Affadivit of Preferential Bidders Status has has has has Description Scheduled Unit Total Unit Total Unit Total Unit Total Value Unit Price Price Price Price Price Price Price Price 1. Mobilization/Demobilization, insurance, bonds, submittals, existing site documentation, site clean-up and misc. fees. 7, , , , , , , , Furnish and install traffic control at five sites throughout the Truckee Meadows 3, , , , , , , , Caughlin #1 Pump Station HVAC All material 23, , , , , , , , Caughlin #1 Pump Station Vault Electrical/Control Demolish electrical equip./conduit as indicated on the plans. Furnish and install all non-owner provided electrical equipment per the plans and plans and Provide conduit and wiring 5. Caughlin #1 Pump Station Remove MH frames 6. Caughlin #1 Pump Station Abandon existing 1 service line at connection with existing 24 steel main 7. Install 32 pound magnesium anodes to existing steel water mains 8. Caughlin #1 Pump Station Coating Repairs Steel pipe penetrations, A&B pump heads and pump/motor frames and PRVs -coating application per plans/ HVAC vent pipe surface 9. Caughlin #1 Pump Station new sump addition and install 1 PE discharge line and connection to existing discharge. 10. Caughlin #1 Pump Station Electric Meter 11. Caughlin #1 Pump Station Temporary Pavement Patches- Install and maintain 3-inch temporary asphalt patch. 12. Caughlin #1 Pump Station Flow Meter Conduit - Install 2 conduit from pump vault to flow meter MH Includes all trenching, excavation, backfill and conduit 13. Caughlin #1 Pump Station Landscape and Site Restoration Remove sod per plans and replace with DG, repair damaged sprinkler lines as reqd. 14. Caughlin #1 Pump Station steel pipe removal 495 SQ. FT 35 LF 11, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , Page 1 of 5

2 15. Caughlin #2 Pump Station HVAC All material 16. Caughlin #2 Pump Station Vault Electrical/Control Demolish electrical equip./conduit as indicated on the plans. Furnish and install all non- Owner provided electrical equipment per the plans and Install Owner provided equipment as indicated on the plans and Provide conduit and wiring as required for a complete installation. 17. Caughlin #2 Pump Station Remove MH frames 18. Caughlin #2 Pump Station Coating Repairs Steel pipe penetrations, A pump head and motor, PRVs coating application per plans/ HVAC vent pipe surface preparation and coating per plans/ 19. Caughlin #2 Pump Station Temporary Asphalt Patch - Install and maintain 3-inch temporary asphalt patch. 20. Caughlin #2 Pump Station 8-inch By-Pass Regulator Vault Installation Provide all labor and material to install 8-inch regulated by-pass valve in pre-cast concrete vault. Includes excavation/backfill, concrete vault, all internal mechanical/electrical pipe/fittings/supports, ladder, access opening, sump line and pump. Owner shall provide 8-inch regulator valve and sump pump for Contractor install. 21. Caughlin #2 8-inch restrained DIP, fittings and valves for by-pass regulator supply and discharge lines to/from vault. Includes trenching/excavation & backfill, DIP pipe/fittings, poly-wrap, 18 x8 hot-tap saddle/gtvs. 22. Caughlin #2 Pump Station steel pipe removal 570 SQ. FT 60 LF 16, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , Caughlin #2 Pump Station Electric Meter 24. Caughlin #2 Pump Station Landscape and Site Restoration Remove sod per plans and replace with DG, repair damaged sprinkler lines as reqd. 25. Caughlin #2 Pump Station Temporary Sidewalk Pavement Patch Install and maintain 2-inch temporary pavement patch. 26. Caughlin #2 Pump Station Install 32 pound magnesium anodes to existing steel water mains. 290 SQ. FT 2 EA 27. Caughlin #2 Pump Station new sump addition and install 1 PE discharge line and connection to existing discharge. 28. Caughlin #2 Pump base demo and replacement. 2 EA 5, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , Page 2 of 5

3 29. Stoney Brook Pump Station HVAC All material 30. Stoney Brook Pump Station Vault Electrical/Control Demolish electrical equip./conduit as indicated on the plans. Furnish and install all non-owner provided electrical equipment per the plans and Install Owner provided equipment as indicated on the plans and Provide conduit and wiring as required for a complete installation. 31. Stoney Brook Pump Station Remove MH frames and covers, provide/install new MH frame and covers, 32. Stoney Brook Pump Station Remove existing manway opening cover and replace with new access opening within cast in-place collar. 33. Stoney Brook Pump Station Coating Repairs Steel pipe penetrations, A&B pump head and pump/motor frame, PRVs coating application per plans/ HVAC vent pipe surface 34. Stoney Brook Pump Station steel pipe removal 35. Stoney Brook Pump Station Electric Meter 36. Stoney Brook Pump Station - Install 32 pound 37. Stoney Brook Pump Station Temporary Asphalt Patch - Install and maintain 2-inch temporary asphalt patch. 38. Stoney Brook Pump Station new sump addition and 1 PE discharge line install and connection to existing discharge. 39. Stoney Brook Pump Station Landscape removal and Site Restoration Remove shrubs per plans and replace with AB, repair damaged sprinkler lines as reqd. 40. Cashill Pump Station HVAC All material and labor to install the HVAC equipment and controls. Includes the installation of the 8-inch diameter air 41. Cashill Pump Station Vault Electrical/Control Demolish electrical equip./conduit as indicated on the plans. Furnish and install all non-owner provided electrical equipment per the plans and plans and Provide conduit and wiring 1 EA 65 SQ. FT 20, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , Page 3 of 5

4 42. Cashill Pump Station Remove MH frames and covers, provide/install new MH frame and covers, grade rings and concrete collars (note: approx. 48 sq. ft. of concrete slab remove/replace) 43. Cashill Pump Station Remove existing manway opening cover and replace with new access opening within cast in-place collar. 44. Cashill Pump Station Coating Repairs Steel pipe penetrations coating application per plans/ HVAC vent pipe surface 45. Cashill Pump Station steel pipe removal and replacement. Remove/dispose of existing steel 46. CashillPumpbasedemo(A&BPumps)andA pump base replacement 47. Cashill Pump Station - Install 32 pound 48. Cashill Pump Station Temporary Asphalt Patch - Install and maintain 3-inch temporary asphalt patch. 49. Cashill Pump Station Landscape removal and Site Restoration Remove shrubs per plans and replace with decorative rock, place 4 replacement shrubs and repair damaged sprinkler lines as reqd. 50. Brighton Pump Station HVAC All material and labor to install the HVAC equipment and controls. Includes the installation of the 8-inch diameter air 51. Brighton Pump Station Vault Electrical/Control Demolish electrical equip./conduit as indicated on the plans. Furnish and install all non-owner provided electrical equipment per the plans and plans and Provide conduit and wiring 52. Brighton Pump Station Remove MH frames 53. Brighton Pump Station Remove existing manway opening cover and replace with new access opening within cast in-place collar. 54. Brighton Pump Station Coating Repairs Steel pipe penetrations coating application per plans/ HVAC vent pipe surface 55. Brighton Pump Station - Install 32 pound 56. Brighton Pump Station Temporary Asphalt Patch - Install and maintain 3-inch temporary asphalt patch. 57. Brighton Pump Station Landscape removal and Site Restoration Remove shrubs per plans and replace with decorative bark, place 6 replacement shrubs and repair damaged sprinkler lines as reqd. 170 SQ. FT 380 SQ. FT 7, , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , Page 4 of 5

5 58. Brighton Pump Station Electric Meter Relocation Relocate existing electric meter to above grade installation outside of vault as indicated on plans. Includes all conduits, wires, trenching, backfill, surface restoration, concrete pedestal, and electrical equipment for a complete installation. Note: Owner will furnish electric meter cabinet. 4, , , , , , , , Sidewalk & curb/getter demo/replacement 30 LF , , , , Curb/gutter demo/replacement 75 LF , , , , UCA-1: Additive cost to install 4-6-inch degree elbows for vertical offset per alternate bid item #1 on sheet C6 2, , , , , , , , UCA-2: Price for surface preparation and re-coat existing corroded electrical cabinets to remain per system A of Section of the Technical 50 SQ. FT Specifications , , Total Bid Price $478, $534, $527, $651, Total Bid Price Written in Words? y/n total corrected total corrected Bidder Information Provided Licensing Information Provided Disclosure of Principals Provided Referenced Provided Debarment & Safety Information Provided Labor and Equipment Rate Schedules Provided Subcontractors Listed Proposal Summary Executed Page 5 of 5

Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA TMWA Capital Project No.: October 3, 2018

Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA TMWA Capital Project No.: October 3, 2018 Addendum No. 1 GORDON WATER MAIN REPLACEMENT PWP Bid No.: WA-2019-004 TMWA Capital Project No.: 10-0001.053 October 3, 2018 The following information, clarifications, changes and modifications are by reference

More information

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices. SECTION 01220 UNIT PRICES PART 1 GENERAL 1.01 SUMMARY A. This Section specifies administrative and procedural requirements for the unit prices. B. The omission of any unit price description from this Section

More information

DOCUMENT ADDENDA AND MODIFICATIONS

DOCUMENT ADDENDA AND MODIFICATIONS DOCUMENT ADDENDA AND MODIFICATIONS PART 1 1.1 PROCEDURE GENERAL A. For filing purposes, add Addenda and Modifications to the Contract Documents following this page. Modified June 20, 2017 Addenda and Modifications

More information

CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS SECTION 00005B TABLE OF CONTENTS ***CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS***

CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS SECTION 00005B TABLE OF CONTENTS ***CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS*** 00005B *** *** BOLD ITALICIZED Item is bound within this specification manual. Regular non-italicized Item is not bound within this specification manual, however item is part of the contract. Contents

More information

Job Order Sewer Repair Services

Job Order Sewer Repair Services Job Order Sewer Repair Services Bid Addendum No. 1 October 10, 2018 All Contractual Requirements as defined within the Contract Documents shall remain in full force to the extent that they are not modified

More information

Addendum 1. Valve & Valve Vault Replacement. Issued June 13, 2018

Addendum 1. Valve & Valve Vault Replacement. Issued June 13, 2018 155 Corey Avenue St. Pete Beach, FL 33706-1839 www.stpetebeach.org Addendum 1 Valve & Valve Vault Replacement Issued June 13, 2018 Note that this Addendum does not change the bid due date and time as stated

More information

BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of. a Partnership consisting of

BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of. a Partnership consisting of BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of a Partnership consisting of an Individual doing business as. TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instruction

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

SPECIAL SPECIFICATION. Water and Sewer System and Appurtenances

SPECIAL SPECIFICATION. Water and Sewer System and Appurtenances 2004 Specifications CSJ 2250-01-021, etc SPECIAL SPECIFICATION 5243 Water and Sewer System and Appurtenances 1. Description. This Item governs for the furnishing of all equipment, labor and materials to

More information

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered RFB for Wastewater Force Main #3 October 2, 2015 Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered The proposed force main will be required to transmit up to 1000 gallons of wastewater

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 - MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01. BASIS FOR MEASUREMENT AND PAYMENT Measurement and Payment will be made for only those items included in the Schedule of Unit Prices or Contract

More information

General Water Bid Items Item No.

General Water Bid Items Item No. BID PROPOSAL PROPOSAL OF, a corporation organized and existing under the laws of the State of, a partnership consisting of, an individual doing business as. Enclosed with this bid are (1) Bid Bond, and

More information

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL Page 312 VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS-12-01 BID PROPOSAL I/We hereby agree to furnish to the Village of Lombard all necessary materials, equipment, and labor, to complete the IL ROUTE

More information

Statement of Quantities

Statement of Quantities 01-21.26.01 GROUND WATER TREATMENT CONSUMABLES ALLOWANCE 1 A/A 01-52.13 ACCOUNT - PROJECT SPECIAL PROVISIONS TEMPORARY OFFICE FACILITIES 2-1.2a REMOVE 6" CONCRETE CURB AND/OR GUTTER REMOVE 780 LF 2-1.4

More information

City of Naples Utilities Department Wastewater Collections Division

City of Naples Utilities Department Wastewater Collections Division City of Naples Utilities Department Wastewater Collections Division Request for Proposal Reclaimed Water Fire Hydrant & Water Service Installations February 2015 Reclaimed Water Fire Hydrant & Services

More information

CITY AND COUNTY OF DENVER

CITY AND COUNTY OF DENVER 2-1.1b REMOVE COMBINATION CONCRETE CURB, GUTTER AND SIDEWALK (3'-11") 2-1.2a REMOVE 6" CONCRETE CURB AND/OR GUTTER S Holly: See near STA: 25+56 S Poplar 300 LF 25 LF 2-1.4 REMOVE HANDICAP CONCRETE CURB

More information

November 29, CITY OF PLANT CITY Purchasing Division (813)

November 29, CITY OF PLANT CITY Purchasing Division (813) November 29, 2018 CITY OF PLANT CITY Purchasing Division (813) 659-4270 IFB 18-014UM-LG 12-inch Water Transmission Main-Franklin St., Hancock St. and Terrace Drive West ADDENDUM No. 3 *Bidders are required

More information

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule

REVISED PER ADDENDUM No. 1 - Unit Price Bid Schedule 1. Mobilization, Insurance, Bonds, General Requirements, BMPs, Record Drawings, Testing Requirements, Utility Location, Demobilization and Site Maintenance. 1 L.S. 2. Supply and install complete 384,238

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 - PART 1 GENERAL 1.01 THE REQUIREMENT A. Payment for various items of the Bid Schedule, as further specified herein, shall include all compensation to be received by the CONTRACTOR for furnishing

More information

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA BID PROPOSAL PROPOSAL OF, a Corporation organized and existing under the laws of the State of, a Partnership consisting of, an Individual doing business as. Enclosed with this bid are (1) Bid Bond, and

More information

CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE CITY OF BRECKSVILLE,

CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE CITY OF BRECKSVILLE, CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE FOR THE CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS RQ# 41677 BIDS DUE ON: May 1, 2018, at 2:00 p.m. ADDENDUM NUMBER 1, April 25, 2018, Page

More information

CITY OF ALBANY Public Works Department ADDENDUM #1 ST CROCKER LANE RECONSTRUCTION

CITY OF ALBANY Public Works Department ADDENDUM #1 ST CROCKER LANE RECONSTRUCTION CITY OF ALBANY Public Works Department ADDENDUM # ST-6-02 CROCKER LANE RECONSTRUCTION In order to clarify the intent of the Specifications and Drawings, the following provisions are provided and shall

More information

EXHIBIT E SCHEDULE OF UNIT PRICES

EXHIBIT E SCHEDULE OF UNIT PRICES SCHEDULE OF UNIT PRICES TO ACCOMPANY THE BID OF (Bidder/Contractor) ON CALL UTILITY SERVICES AND MISCELLANEOUS CONSTRUCTION FOR SEWER AND WATER LINES SOLICITATION NO.: IFB SA1703 Any bidder who enters

More information

SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6

SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO SOLICITATION NO. CO ADDENDUM-6 SAN ANTONIO WATER SYSTEM C5 & C28 SEWER PROJECT PHASE 3 SAWS PROJECT NO. 18-4501 SOLICITATION NO. CO-00198 ADDENDUM 6 (September 10, 2018) To Respondent of Record: This addendum, applicable to work referenced

More information

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title TABLE OF CONTENTS CONTRACT DOCUMENTS 00001 Inside Title Page 00003 Table of Contents 00004 List of Drawings 00020 Invitation to Bid 00100 Instructions to Bidders 00300 Bid 00500 Agreement 00610 Construction

More information

ADDENDUM NUMBER ONE (1) December 6, The following Addendum shall be incorporated into the Contract Documents for the above referenced project.

ADDENDUM NUMBER ONE (1) December 6, The following Addendum shall be incorporated into the Contract Documents for the above referenced project. TO: ALL HOLDERS OF CONTRACT DOCUMENTS FOR: City of Carlsbad, New Mexico Sanitary Sewer Interceptor 118 Upgrades Phase I Wade M. Chacon P.E. HDR Project Manager/Engineer Bid # 2016-32 ADDENDUM NUMBER ONE

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

ADDENDUM No. 5 TO CONSTRUCTION CONTRACT DOCUMENTS BRIDGEPORT PUBLIC UTILITY DISTRICT (BPUD) Arsenic Removal Project Construction Contract

ADDENDUM No. 5 TO CONSTRUCTION CONTRACT DOCUMENTS BRIDGEPORT PUBLIC UTILITY DISTRICT (BPUD) Arsenic Removal Project Construction Contract ADDENDUM No. 5 TO CONSTRUCTION CONTRACT DOCUMENTS BRIDGEPORT PUBLIC UTILITY DISTRICT (BPUD) Arsenic Removal Project Construction Contract May 15, 2017 THE BIDDER SHALL EXECUTE THE CERTIFICATION WITHIN

More information

CITY OF TACOMA Department of Public Utilities - Water Division

CITY OF TACOMA Department of Public Utilities - Water Division CITY OF TACOMA Department of Public Utilities - Water Division ADDENDUM NO. 1 DATE: October 12, 2015 REVISIONS TO: Request for Bids Specification No. WD15-0133F Water Main Replacement Project No. MRP 2014-27,

More information

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows. 403.01 Section 403. DRAINAGE STRUCTURES 403.01 Description. Adjust, construct, or temporarily lower drainage structures. Clean existing drainage structures and leads as directed by the Engineer. Drainage

More information

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6664 Level (3) Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6664 Level (3) Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Level (3) Communications,

More information

SPECIAL SPECIFICATION 6658 Time Warner Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System 2004 Specifications CSJ 1200-05-014 1. Description. SPECIAL SPECIFICATION 6658 Time Warner Communications System A. This Item will govern the installation of all facilities belonging to Time Warner Cable

More information

IFB # R Blythe Creek Grinder Pump Eliminations

IFB # R Blythe Creek Grinder Pump Eliminations IFB # 2019-015R Blythe Creek Grinder Pump Eliminations ADDENDUM No. 1 ISSUE DATE: October 10, 2018 *******************************************************************************************************************

More information

Addendum No. 2. Pre-Bid Meeting Notes and Scope of Work Clarifications

Addendum No. 2. Pre-Bid Meeting Notes and Scope of Work Clarifications Addendum No. 2 Project No. 2016-01EL West Barbour Street 12kV Underground Reconductoring Revisions to Drawings and Specifications Pre-Bid Meeting Notes and Scope of Work Clarifications Replace Section

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES Section SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL... 39-1 39-2 PRECAST CONCRETE MANHOLES... 39-1 39-2.01 Precast Concrete Storm Drain Manholes... 39-1 39-3 SADDLE MANHOLES... 39-2 39-3.01 Saddle

More information

Fountain Square Renovation Project. Bid # ADDENDUM No. 2. February 14, 2017

Fountain Square Renovation Project. Bid # ADDENDUM No. 2. February 14, 2017 Fountain Square Renovation Project Bid # 17-05 ADDENDUM No. 2 February 14, 2017 Any and all changes to the Contract Document are valid only if they are included by written addendum to all potential respondents,

More information

SPECIAL SPECIFICATION 6666 Charter Communications System

SPECIAL SPECIFICATION 6666 Charter Communications System 2004 Specifications CSJ 1200-05-014 SPECIAL SPECIFICATION 6666 Charter Communications System 1. Description. A. This Item will govern the installation of all facilities belonging to Charter Communications,

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

CULINARY WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix B

CULINARY WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix B CULINARY WATER PROJECT COST ESTIMATES & LOCATION MAPS Appendix B RIVERDALE CITY CAPITAL FACILITIES PLAN CULINARY WATER Engineer's Cost Estimate January 2009 Project Name: Culinary Water Reservoir - Tank

More information

RFB # ADDENDUM NO. 1 ISSUED APRIL 23, 2018 PRE-BID MEETING MINUTES NEW HANOVER COUNTY LANDFILL GAS COLLECTION AND CONTROL SYSTEM CONSTRUCTION

RFB # ADDENDUM NO. 1 ISSUED APRIL 23, 2018 PRE-BID MEETING MINUTES NEW HANOVER COUNTY LANDFILL GAS COLLECTION AND CONTROL SYSTEM CONSTRUCTION RFB # 18-0197 ADDENDUM NO. 1 ISSUED APRIL 23, 2018 PRE-BID MEETING MINUTES NEW HANOVER COUNTY LANDFILL GAS COLLECTION AND CONTROL SYSTEM CONSTRUCTION The following information was conveyed and discussed

More information

BID FORM (LUMP SUM CONTRACT)

BID FORM (LUMP SUM CONTRACT) BID FORM (LUMP SUM CONTRACT) Place County of El Paso Purchasing Department Date Project No. 11-016 Proposal of (hereinafter called Bidder), a corporation organized under the laws of the State of /a partnership/an

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

INVITATION TO BIDDERS. Solicitation No. CO-00157

INVITATION TO BIDDERS. Solicitation No. CO-00157 INVITATION TO BIDDERS Solicitation No. CO-00157 Sealed bids are requested by the San Antonio Water System for the construction of approximately 5,900 LF of 6 to 8-inch of water main and approximately 3,000LF

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 012000 Applies only to Collier County Public Utilities Projects or Works and Utilities Portions of Collier County Transportation Projects, but not to Private Developments PART 1 GENERAL 1.1 SECTION

More information

BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR

BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR BID PROPOSAL FOR TOWN OF HIGHLAND PARK, TEXAS FOR Miscellaneous Concrete Repairs 2014 3600-3900 Blocks of Potomac Avenue and Town Hall, 2014 To: The Honorable Mayor and Town Council Town of Highland Park

More information

For Reference Only - Not For The Purpose Of Bidding BP-1 PROPOSAL. PROPOSAL OF, a corporation a. partnership consisting of

For Reference Only - Not For The Purpose Of Bidding BP-1 PROPOSAL. PROPOSAL OF, a corporation a. partnership consisting of PROPOSAL PROPOSAL OF, a corporation a partnership consisting of and an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instruction and Invitations to Bidders, the undersigned

More information

Addendum 1 City of Portsmouth Bid # Chestnut Street Streetscape Project. Issued: July 21, 2017

Addendum 1 City of Portsmouth Bid # Chestnut Street Streetscape Project. Issued: July 21, 2017 Addendum 1 City of Portsmouth Bid # 61-17 Issued: July 21, 2017 This Addendum forms part of the original document marked: Bid#61-17 Chestnut Street Streetscape Project. Item 1 Clarification Existing gas

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

5820 STONERIDGE MALL RD., #345 * PLEASANTON, CA * (925) * (925) June 29, 2018

5820 STONERIDGE MALL RD., #345 * PLEASANTON, CA * (925) * (925) June 29, 2018 5820 STONERIDGE MALL RD., #345 * PLEASANTON, CA 94588 * (925) 467-1740 * (925) 467-1741 June 29, 2018 Saybrook CLSP, LLC 1800 Ave. of the Stars, 3rd Floor Los Angeles, CA 90067 Attn: Jeff Wilson (310)

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART 1 GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

ADDENDUM #1 MARCH 10, CENTRAL WINDS PARK ROADWAY IMPROVEMENTS Bid # ITB-02/16/BF

ADDENDUM #1 MARCH 10, CENTRAL WINDS PARK ROADWAY IMPROVEMENTS Bid # ITB-02/16/BF ADDENDUM #1 MARCH 10, 2016 CENTRAL WINDS PARK ROADWAY IMPROVEMENTS Bid # ITB-02/16/BF TO: ALL PLAN HOLDERS This Addendum No. 1 to the Contract Documents for City of Winter Springs project "Central Winds

More information

10:00 AM, Wednesday, May 6, Peters Creek Sanitary Sewer Rehabilitation Project

10:00 AM, Wednesday, May 6, Peters Creek Sanitary Sewer Rehabilitation Project NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, May 6, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference

More information

Sample. Bid Proposal. Not Valid for Use

Sample. Bid Proposal. Not Valid for Use BID PROPOSAL PROPOSAL OF, a corporation a partnership consisting of an individual doing business as TO THE SAN ANTONIO WATER SYSTEM: Pursuant to Instructions Invitations to Bidders, the undersigned proposes

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

ADDENDUM NO. 2 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2015 Capital Works 2015-Tender-02

ADDENDUM NO. 2 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2015 Capital Works 2015-Tender-02 ADDENDUM NO. 2 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON April 28, 2015 To All Tenderers: This Addendum is issued prior to the Tender Closing Date April 30, 2015, in accordance

More information

BID SCHEDULE. COMPLETION of this project is expected PURSUANT TO CONTRACT DOCUMENTS. Description Scheduled Unit Total Value Unit Price Price.

BID SCHEDULE. COMPLETION of this project is expected PURSUANT TO CONTRACT DOCUMENTS. Description Scheduled Unit Total Value Unit Price Price. NOTICE: August 24, 2009 No substitution or revision to this Bid Schedule form will be accepted. Truckee Meadows Water Authority will reject any Bid that is received that has changes or alterations to this

More information

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages

TABLE OF CONTENTS VOLUME 1. DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages TABLE OF CONTENTS VOLUME 1 DIVISION 00 - INTRODUCTORY INFORMATION, BIDDING REQUIREMENTS, CONTRACT FORMS & CONDITIONS OF THE CONTRACT Pages SCHEDULE OF DRAWINGS...... 1 PROJECT PERSONNEL & DIRECTORY......

More information

ADDENDUM NO. 1 NOVEMBER 8, 2016

ADDENDUM NO. 1 NOVEMBER 8, 2016 SAN ANTONIO WATER SYSTEM C_13 BROADWAY CORRIDOR PROJECT SEWER REHABILIATION PACKAGE 2.C AND 4.C SAWS JOB NO. 15-45111 (2.C) & 15-4514 (4.C) SOLICITATION NO. CO-00097 ADDENDUM NO. 1 NOVEMBER 8, 2016 TO

More information

SPECIAL SPECIFICATION 2022 Water Mains and Wastwater Main Appurtenances

SPECIAL SPECIFICATION 2022 Water Mains and Wastwater Main Appurtenances 2004 Specifications CSJ 1316-01-034 & 0902-48-502 SPECIAL SPECIFICATION 2022 Water Mains and Wastwater Main Appurtenances 1. Description. Furnish all materials, equipment, labor and incidentals necessary

More information

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section 02540-1 of 10 SECTION 02540 STORM DRAIN REHABILITATION 02540.01 GENERAL A. Description Storm drain rehabilitation shall include, but not necessarily be limited to, pipe joint sealing, inlet and manhole

More information

ADDENDUM NO. 3. Please make note of the following clarifications:

ADDENDUM NO. 3. Please make note of the following clarifications: Purchasing Division ADDENDUM NO. 3 DATE: March 6, 2019 FROM: City of Grand Junction Purchasing Division TO: All Offerors RE: Raw Water Irrigation Supply and Waterline Replacement IFB-4611-19-DH Offerors

More information

CARGO HARDSTAND IMPROVEMENTS. at Seattle-Tacoma International Airport BID PACKAGE. Addendum No. 3

CARGO HARDSTAND IMPROVEMENTS. at Seattle-Tacoma International Airport BID PACKAGE. Addendum No. 3 CARGO HARDSTAND IMPROVEMENTS at Seattle-Tacoma International Airport BID PACKAGE Addendum No. 3 MC-0317700 Primary Work Project #: 104648 Cargo 2 Hardstand Expansion (103801) Cargo 5 Hardstand Construction

More information

CITY OF ALBANY Public Works Department ADDENDUM #1 ST , MAIN STREET REHABILITATION

CITY OF ALBANY Public Works Department ADDENDUM #1 ST , MAIN STREET REHABILITATION CITY OF ALBANY Public Works Department ADDENDUM #1 ST-13-04-2014, MAIN STREET REHABILITATION In order to clarify the intent of the Specifications and Drawings, the following provisions are provided and

More information

COMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO.1 UPPER SKAGIT INDIAN TRIBE PAGE 1

COMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO.1 UPPER SKAGIT INDIAN TRIBE PAGE 1 UPPER SKAGIT INDIAN TRIBE COMMUNITY PLAZA WAY ASPHALT PAVEMENT OVERLAY ADDENDUM NO. 1 (7 pages total) Issue Date: May 11, 2016 General: Recitations of each and every section of the bid documents impacted

More information

ADDENDUM NO. 3 APRIL 9, 2018 CITY OF LUCAS. PARKER ROAD WATER LINE PHASE 2 (Bid ) (FROM LEWIS LANE TO EAST OF SANTA FE TRAIL)

ADDENDUM NO. 3 APRIL 9, 2018 CITY OF LUCAS. PARKER ROAD WATER LINE PHASE 2 (Bid ) (FROM LEWIS LANE TO EAST OF SANTA FE TRAIL) ADDENDUM NO. 3 APRIL 9, 2018 CITY OF LUCAS PARKER ROAD WATER LINE PHASE 2 (Bid 013-18) (FROM LEWIS LANE TO EAST OF SANTA FE TRAIL) This Addendum forms a part of the Contract Documents and Specifications.

More information

TWIN VALLEY PUMP STATION IMPROVEMENTS - CITY OF FARMINGTON FARMINGTON, MI 48335

TWIN VALLEY PUMP STATION IMPROVEMENTS - CITY OF FARMINGTON FARMINGTON, MI 48335 TWIN VALLEY PUMP STATION IMPROVEMENTS - CITY OF FARMINGTON FARMINGTON, MI 48335 BIDS TO BE RECEIVED UNTIL 1:00 P.M., LOCAL TIME, WEDNESDAY, OCTOBER 28, 2015, AT THE OFFICE OF THE CITY CLERK LOCATED AT

More information

BRICK TOWNSHIP MUNICIPAL UTILITIES AUTHORITY BRETON WOODS SECTION 1 WATER MAIN REPLACEMENT ADDENDUM #2

BRICK TOWNSHIP MUNICIPAL UTILITIES AUTHORITY BRETON WOODS SECTION 1 WATER MAIN REPLACEMENT ADDENDUM #2 BRICK TOWNSHIP MUNICIPAL UTILITIES AUTHORITY BRETON WOODS SECTION 1 WATER MAIN REPLACEMENT ADDENDUM #2 The original Contract Documents entitled BRETON WOODS SECTION 1 WATER MAIN REPLACEMENT are amended

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO RA Addendum 2 July 22 nd 2016

CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO RA Addendum 2 July 22 nd 2016 To Respondent of Record: CAMP BULLIS ROAD 12-INCH WATER MAIN PROJECT Solicitation No.: CO-00082-RA Addendum 2 July 22 nd 2016 This addendum, applicable to work referenced above, is an amendment to the

More information

Welcome to Douglas County PUD

Welcome to Douglas County PUD Welcome to Douglas County PUD We are committed to providing the best possible utility services at the lowest possible cost consistent with sound business principles To better serve you, please fill out

More information

The following Specifications of the Special Provisions have been revised and/or added (in red):

The following Specifications of the Special Provisions have been revised and/or added (in red): RE: City of Monrovia Project MR-011 South Area Infrastructure Improvement Project Addendum #1 December 14, 2017 Dear Bidders: The attached information and clarifications constitutes Addendum #1 for the

More information

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83

BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 Item No. BIDDING SCHEDULE SEWER LIFT STATION NO. 2 REPLACEMENT PROJECT CITY OF ALHAMBRA City s Project No. N2M17-83 DESCRIPTION EST. QTY. UNIT UNIT PRICE TOTAL PRICE GENERAL BID ITEMS 1 Per Plans and Specifications

More information

CITY OF TACOMA Department of Public Utilities Tacoma Power

CITY OF TACOMA Department of Public Utilities Tacoma Power CITY OF TACOMA Department of Public Utilities Tacoma Power ADDENDUM NO. 1 DATE: August 4, 2017 REVISIONS TO: Request for Bids Specification No. PG17-0130F TPU Eductor Waste Decant Facility NOTICE TO ALL

More information

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL

SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL SECTION B1 BITUMINOUS CONCRETE PAVING GENERAL This section covers the restoration of roadways and sidewalks, in whole or in part, with bituminous concrete paving. WITHIN 4 DAYS OF BACKFILLING IN AREAS

More information

ATTACHMENT 8 STIPULATED UNIT PRICES

ATTACHMENT 8 STIPULATED UNIT PRICES ATTACHMENT 8 STIPULATED UNIT PRICES 1. Work Package Item Prices (2 pages) 2. General Description of Work Items (3 pages) PQOC SMALL SIDEWALK CONTRACTORS LIST STIPULATED UNIT PRICES City of Los Angeles

More information

DOCUMENT BID DOCUMENT

DOCUMENT BID DOCUMENT DOCUMENT 00 40 00 BID DOCUMENT 1 Submit bids in compliance with Document 00 21 00Instructions to Bidders. Fill in blanks which pertain to the project or indicate N/A. The Owner reserves the right to reject

More information

ADDENDUM NO. 1 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2015 Capital Works 2015-Tender-02

ADDENDUM NO. 1 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON 2015 Capital Works 2015-Tender-02 ADDENDUM NO. 1 TO THE TENDER DOCUMENTS FOR THE CORPORATION OF THE CITY OF PENTICTON April 23, 2015 To All Tenderers: This Addendum is issued prior to the Tender Closing Date April 30, 2015, in accordance

More information

Section 403. DRAINAGE STRUCTURES

Section 403. DRAINAGE STRUCTURES 403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads

More information

ATTACHMENT AA DETAILED SCOPE OF WORK DEMOLITION AND REMOVAL

ATTACHMENT AA DETAILED SCOPE OF WORK DEMOLITION AND REMOVAL ATTACHMENT AA DETAILED SCOPE OF WORK DEMOLITION AND REMOVAL 1.0 Structures Structures are buildings, including attached improvements, which could primarily be used as a residential dwelling or for commercial,

More information

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE14-00XXX Applicant: Job Description:

More information

ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP. ADDENDUM DATE: February 10, BID DATE: February 15, 2017, 11:30 a.m.

ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP. ADDENDUM DATE: February 10, BID DATE: February 15, 2017, 11:30 a.m. ADDENDUM NO. 1 FOR CITY OF CUMMING 900-HP RAW WATER INTAKE PUMP ADDENDUM DATE: February 10, 2017 BID DATE: February 15, 2017, 11:30 a.m. This ADDENDUM is issued to institute the included changes and/or

More information

AD 1-1 ITB U CITATION BLVD./OLD KINGS ROAD TO S.R. 100 WATER MAIN

AD 1-1 ITB U CITATION BLVD./OLD KINGS ROAD TO S.R. 100 WATER MAIN ADDENDUM NO. 1 ITB-U-11-05 CITATION BLVD./OLD KINGS ROAD TO S.R. 100 WATER MAIN ISSUE DATE: February 14, 2011 BID DATE: TO: SUBJECT: INTENT: March 1, 2011 @ 2:00 P.M. All Prospective Bidders and Others

More information

SECTION WASTEWATER FORCE MAINS

SECTION WASTEWATER FORCE MAINS SECTION 02732 WASTEWATER FORCE MAINS PART - GENERAL 1.01 GENERAL: A. This section includes the general requirements for design and installation of force main systems serving wastewater lift stations. B.

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01025 MEASUREMENT AND PAYMENT PART 1 -- GENERAL 1.1 SCOPE A. The Contractor shall receive and accept the compensation as provided in the Bid Form as full payment for furnishing all materials, labor,

More information

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number) EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY

More information

January 18, 2018 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA IFB Y TA, ADDENDUM NO. 1 MALCOLM ROAD WATER SUPPLY FACILITY

January 18, 2018 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA IFB Y TA, ADDENDUM NO. 1 MALCOLM ROAD WATER SUPPLY FACILITY January 8, 208 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA IFB Y8 726-TA, ADDENDUM NO. MALCOLM ROAD WATER SUPPLY FACILITY BID OPENING DATE: January 25, 208 February 5, 208 This Addendum is hereby

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

BID FORM. (Firm) FOR CONSTRUCTION OF

BID FORM. (Firm) FOR CONSTRUCTION OF BID FORM BY Rancho California Water District 42135 Winchester Road Post Office Box 9017 Temecula, CA 92589-9017 (Firm) FOR VIA VISTA GRANDE [PROJECT 20161], AVOCADO MESA [PROJECT 20162], AND CARANCHO WEST

More information

ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB # RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN

ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB # RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB #4320 2014 RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN The following changes, additions, and/or deletions shall be made to the Bid Documents

More information

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel

Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California Tel Public Works Department 305 West Third Street, East Wing, Third Floor Oxnard, California 93030 Tel 805.385.8280 October 24, 2018 ADDENDUM NO. 2 Vineyard Avenue Street Resurfacing Project PW 16-12 SCHEDULED

More information

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630)

C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) Fax: (630) C ITY OF D ARIEN Community Development Department 1702 Plainfield Road Phone: (630) 353-8115 Fax: (630) 852-4709 BUILDING PERMIT INFORMATION PACKET Revised: October 2018 Building Codes: International Residential

More information

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1993 Specifications CSJ 0144-01-060 SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings 1. General. (1) Scope. This Section includes the furnishing, installation, and subsequent

More information

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS)

MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) 00950 - Measurement & Payment Page 00950-1 00950 - MEASUREMENT & PAYMENT (CITY FUNDED PROJECTS) (Last revised 5/20/10) SELECTED LINKS TO SECTIONS WITHIN THIS SPECIFICATION Base Course & Paving Curb & Gutter,

More information

d.p. Consulting Engineers, Inc.

d.p. Consulting Engineers, Inc. d.p. Consulting Engineers, Inc. 3727 Doctors Drive Port Arthur, Tx 77642 Phone: 409-983-6263 Fax : 409-983-6265 Firm Registration No: F-3356 Email : dp@dpengineersinc.com ADDENDUM NO. 1 ADDENDUM ISSUE

More information

Failure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders.

Failure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders. Addendum # Project: Lewis & Clark Regional Water System Bid Date: :00 P.M., Local Time, September 0, 06 Bid Location: Lewis & Clark Regional Water System Office, 46986 Monty Street Tea, SD 57064 Issue

More information

Forsyth County Procurement

Forsyth County Procurement July 7, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 BID 17-63-3150 For: Providing all labor, materials and equipment for the construction of the Brookwood

More information

CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1

CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1 Addendum No. 1 September 26, 2016 Page 1 of 8 CITY OF PORTSMOUTH, NEW HAMPSHIRE GREENLAND WELL PUMP STATION REPLACEMENT ADDENDUM NO. 1 This Addendum forms part of the original contract drawings and specifications

More information

Forsyth County Procurement

Forsyth County Procurement August 1, 2017 Forsyth County Procurement Donna Kukarola, CPPO, CPPB, Procurement Director ADDENDUM #2 Bid 17-72-3340 For: Providing all materials, equipment and labor for the Jot em Down Road Water Tank

More information