9.6 Interfield Pipeline Installation and Commissioning and Operation

Size: px
Start display at page:

Download "9.6 Interfield Pipeline Installation and Commissioning and Operation"

Transcription

1 9.6 Interfield Pipeline Installation and Commissioning and Operation As described in the Project Description (Chapter 5.7), Phase 3 will tie-in to the existing Azeri Project marine export pipeline infrastructure to export its oil and gas to the onshore terminal at Sangachal. This will require the installation of three infield pipelines from the offshore facilities and connection to the existing pipelines via pre-installed wye pieces as described in Table 9.17 below. Table 9.17 Phase 3 Infield Export Pipelines Infield line To Length (km) 30 oil line Phase 2 30 oil pipeline oil line Phase 1 30 oil pipeline gas line Phase 1 28 gas pipeline 2.0 The results of the impact assessments of the installation, commissioning and operational activities associated with these Phase 3 infield pipelines are described below Environmental Impacts The results of the environmental impact assessment are summarised in Table Pipeline installation and commissioning will be conducted over a relatively short period of time. It is anticipated that installation, tie-in and commissioning activities will not exceed 50 days, 20 days and 30 days respectively for all three infield pipelines. Furthermore, once installed, the pipelines will cover only a small area of the seabed. As such the residual environmental impacts associated with these activities are ranked low and are not predicted to be significant ACG Phase 3 ESIA Chapter 9 9/55

2 Table 9.18 Summary of Environmental Impact Assessment for Interfield Pipeline Installation Commissioning and Operation ID Activity Environmental Aspects Environmental Mitigation Cumulative Contribution Environmental Impact Significance Justification / Comments Residual Environmental Issues to be Addressed E Infield Pipeline Installation, Commissioning and Operation E1. Installation and commissioning pipelay vessel and vessel support Atmospheric emissions, noise, wastes, liquid discharges. Bilge water, sewage water standards and control; All wastes shipped to shore; Waste management planning and implementation; L As B1. As B1 Refer to Section Lay barge anchoring procedure plan. E2. Installation and tie-in of pipelines, flowlines and umbilicals Physical seabed disturbance, physical presence. As E1; Structural frames installed to protect wyes for tie-in. L As B1 Narrow pipeline corridor used. Concern over the disturbance of the benthic habitat raised during consultation. Benthic sensitivity Refer to Section E3. Rectification of freespans and crossing existing lines Physical seabed disturbance, physical presence. As E2; Crossing supports installed to protect existing lines. L As E2 As E2. E4. Testing and commissioning (hydrotesting) Liquid wastes. Interfield oil lines hydrotest waters transferred to terminal for treatment and disposal; Gas line hydrotest water to be discharged offshore careful selection of chemical additives using Chemical Selection Management system; L Discharge from gas line only and relatively low volume offshore, will disperse rapidly. Regulator concern over discharges to the Caspian. Assurance of chemical selection management Refer to Section The use of chemical additives to hydrotesting water will be challenged in line with the Project HSE Standards; E5. Pigging of pipelines Solid wastes, liquid wastes Pigging required for oil lines only. Pigging wastes sent to shore for incorporation into process or treatment/disposal as per the Waste Management Plan; Material selection and chemical use for the water injection flowlines removes the requirement for routine pigging. Use of wax inhibitor to prohibit wax build up L Low residual impacts but cumulative waste generation issue across AzBU activities. Issue of waste management raised during consultation. Waste treatment & disposal Refer to Section and Section ACG Phase 3 ESIA Chapter 9 9/56

3 Vessel emissions and discharges Up to 10 vessels will be present at the installation location during the installation and commissioning programme including the pipelay barge, anchor handling vessels, pipe haul barges and other attendant vessels. This will result in additional emissions to the atmosphere from vessel engines and exhausts and discharges to the sea of treated sewage waters and bilge waters. With respect to effluent discharges all of these vessels will be subject to the same operational controls as described in Section above in that effluents will be treated to the required project standards prior to discharge. Where vessels do not have effluent treatment facilities the effluents will be containerised then transferred to shore for disposal. The volumes of sewage waters that will be generated are shown in Table It is assumed that each person will produce 0.22 m 3 grey water and 0.1 m 3 black water per day. Table 9.19 Estimated Volume of Sewage During Interfield Pipeline Installation and Commissioning (m 3 ) Activity Vessels Number Of Vessels POB Duration (Days) Grey Water (m 3 ) Black Water (m 3 ) Lay-barge ,310 1,050 Anchor handling vessel Pipeline installation Pipe-haul barges & tugs Diving Support vessel Survey vessel Pipeline tie-in Lay-barge Diving Support vessel Pipeline commissioning Tugs TOTALS 5,513 2,506 Total emissions to the atmosphere that will be released from all vessel activity for the pipeline installation and commissioning programme, based on predicted diesel consumption rates and the duration of the activities are shown in Table Table 9.20 Estimated Emissions to the Atmosphere during Interfield Pipeline Installation and Commissioning (tonnes) Activity Duration (Days) Emission species CO 2 CH 4 CO NO x SO x 1 PM NMVOC Pipeline installation 50 9, Pipeline tie-in 20 2, Pipeline commissioning 30 2, TOTALS 14, PM Particulate Matter NMVOC Non-Methane Volatile Organic Compounds 1 Based on an H 2 S content in diesel of 0.8% (marine diesel) Other vessel solid and liquid wastes will be transported to shore for disposal in accordance with the AzBU waste management plan, excluding food waste, which will be macerated and discharged overboard. Overall the total volumes of vessel emissions and discharges during pipeline installation and commissioning activities are relatively small and will occur over a short time period. Once released in the open offshore environment they will be rapidly dispersed and diluted to ACG Phase 3 ESIA Chapter 9 9/57

4 ambient levels. Environmental impacts associated with discharges to sea during offshore vessel activities are therefore considered to be insignificant Benthic Disturbance As with the installation of the offshore platforms and other subsea facilities (Section 9.3.1), the installation of the pipelines will also result in some disturbance to the seabed during installation and the presence of the pipelines will result in a permanent loss of seabed habitat. The pipe-laying operation is continuous with the lay-barge moving progressively forward as sections of pipe are welded, inspected, coated on board the lay-barge and then deployed to the seabed. The barge is held in position by up to eight anchors which also provide the mechanism by which the lay-barge moves forward along the pipeline installation route. As pipe-laying proceeds, the anchors are periodically moved by two anchor handling tugs (with one more on standby). The interval at which this occurs varies but is typically between every 500 m to 600 m of pipeline length laid. The lateral anchor spread of the pipe-lay barge is typically between 600 m to 700 m either side of the pipeline. Anchoring during pipeline installation will disturb the seabed and potentially create anchor mounds in the seabed sediments. Anchor, wire and chain drag disturbance to the seabed will be reduced by adherence to an Anchoring Management Plan that will be prepared for the installation programme. The plan will minimise the total number of anchor drops and lifts. Further, during installation the anchors will be positioned using positioning survey equipment so that correct position is achieved at first drop thereby avoiding unnecessary drops and lifts. The plan will also address the risks of damage to an existing and operating pipeline cables during lay-barge anchor handling activities. Prior to pipeline installation a pre-lay survey will be conducted using side scan sonar and ROV to assist with the planning of the installation activities, as well as to confirm seabed data including sediment type, bathymetry and topography. The survey will also ensure that the target lay area is free of any obstacles, will map all identified subsea hazards and will confirm the position and status of all existing seabed pipelines and other subsea cables. The pipeline routes will be selected to optimise line spacing and to minimise lay-barge anchor pattern interference and risk of damage to existing lines. The Phase 3 pipelines will need to cross existing pipelines on route to the connection point on the main Phase 1 / Phase 2 export pipelines. Concrete or steel crossing structures will be placed along the flanks of the existing pipelines so that sufficient spacing between the individual lines is provided. An acoustic transponder array will be installed at each crossing to provide positioning control during protection mattress and pipeline installation activities. As described in Section 9.3.1, no areas of seabed sensitivity have been identified in the Phase 3 offshore location. Furthermore, the infield pipelines will not be buried which will reduce seabed disturbance and once installed will only cover a relatively small area of the seabed. These measures, along with the careful operational management designed to minimise disturbance during the installation programme, indicates that only low residual environmental impacts to the seabed will result from these infield pipelines. The surfaces of the unburied pipelines will provide a new hard substrate for colonisation by organisms in areas where they previously would be unlikely to occur. This implies that a slight structural change in the marine faunal assemblage will result in the offshore environment through which the infield pipelines pass. The relatively short length of these pipelines would mean however, that the total new hard surface that is available for colonisation is not large and therefore, this change in faunal assemblage would not be significant Hydrotesting Once in place, each pipeline will be flooded with seawater drawn from the open sea in order to test for damage and to ensure the pipeline s integrity. This pressure testing with water is ACG Phase 3 ESIA Chapter 9 9/58

5 known as hydrotesting. The water will be treated with chemicals, which are added in order to avoid any internal corrosion of the pipe whilst the seawater is in the line. The Phase 3 30" oil export lines will be laid, flooded and tested during early 2006 and they will be dewatered by first oil in early 2008, equating to a period of two years where the lines will contain dosed water. The water will be sent to Sangachal in the Azeri 30" oil export lines. The Phase3 28" gas export line will be dewatered and dried offshore, prior to gas export. The dosed hydrotest water will also stay in the line for two years as above. The Phase 3 water injection flowlines will be laid and hydrotested during 2007 and dewatered in early 2008 soon after first oil. The water will be injected downhole into the water injection wells. The time water would be present in these flowlines is from 2 to 18 months. The chemicals to be used are the same as were used in Phase 1 and are included in Table 9.20 below, together with their dose rates. Table 9.21 Pipeline Hydrotest Water Chemicals Chemical Dose rate ppm Function Composition OCNS Category 1 D TROSKILL 88 Biocide THPS (tetrakishydroxymethylphosphonium sulphate) and 100 quaternary ammonium TROS TC Oxygen Scavenger Ammonium bisulphite E TROS SEADYE 100 Tracer Dye Fluorescein E 1 Offshore Chemical Notification Scheme. OCNS Category E is the lowest rating. Category E chemicals are of low toxicity, readily biodegradable and non-bioaccumulative. The components of the hydrotest water have the following characteristics: Oxygen scavenger: reacts with the oxygen in the water to form sulphates. The chemical can only react with oxygen once and once the reaction is complete, the residues are harmless. The main ingredient, ammonium bisulphite has a very low toxicity and is considered to pose no risk to the environment. Tracer dye: fluorescein dye that is poorly degradable but that is highly water-soluble and does not bioaccumulate. Although it is moderately persistent, it does not present any long-term environmental hazard. Biocide: readily biodegradable product that is also not bioaccumulative. Test results have shown that THPS completely hydrolyses in seven days at ph 9. Seawater typically has a ph of 8.1. The active ingredient in the biocide, THPS, will degrade in the pipeline prior to discharge, hence discharge concentrations will be significantly lower than the dosage concentration. This is supported by evidence published by Baker Petrolite (January 2000), which indicated that only 12% of the original concentration of THPS remained in the pipeline after 80 days. The oxygen scavenger and biocide chemicals hydrolyse and degrade almost entirely within in the pipeline, with a proportion being adsorbed on the pipeline surfaces. Used hydrotest water contains very little active oxygen scavenger and biocide. On completion of hydrotesting the pipelines will be tied into the connector wyes and platform and subsequently dewatered. The oil pipelines will be dewatered by launching a pig from the platform driven by the Phase 3 produced oil. The water will be pushed along the pipeline and on into the Phase 1 and 2 pipelines via the connector wyes, where it will continue on to the onshore terminal, and routed with the produced water for disposal. The infield gas pipeline will also be dewatered by launching a pig from the platform. The pig will be driven by produced gas and a glycol slug will follow the pig in front of the flowing gas. Unlike the oil pipeline, hydrotest water from the gas pipeline will be discharged to sea via a 4 valve at the connector wye on the 28 gas export pipeline. The gas will continue to flow into the Phase 1 and 2 gas pipelines and onto the onshore terminal. The total volume of hydrotest water to be discharged will be approximately 1000 m ACG Phase 3 ESIA Chapter 9 9/59

6 The discharged hydrotest water will contain residues of oxygen scavenger and biocide, and tracer die. Upon discharge the chemicals will disperse, not persisting in the environment in any potential harmful form. The chemicals to be used for dosing the hydrotest water were carefully selected using a Chemical Selection Management System to ensure that the chemicals selected on the basis of lowest toxicity, using the OCNS. The chemical components were also subjected to Caspian specific toxicity tests, as follows: The hydrolysis, adsorption or degradation of the individual chemicals were tested over 24 hours; The hydrolysis, adsorption or degradation of mixtures of the selected chemicals in seawater, at the actual doses to be used, were tested over 24 hours. The results of the tests are presented below in Tables Table 9.22 Hydrotest Water Single Chemical Tests (EC/LC 50, mg.l -1 ) Type Name Zooplankton Phytoplankton Standard WAF 11 Standard WAF 1 Dye TROS Seadye Fluoroscein >5,600 1, ,007.3 Oxygen scavenger TROS Oxygen Scavenger > Biocide TROSKIL 88 Biocide THPS Approx Table 9.23 Hydrotest Package, Zooplankton Toxicity Tests (LC 50, mg.l -1 ) Name Dose 2 Standard WAF LC50 (%) 3 Equivalent LC50 (%) Equivalent TROS Oxygen Scavenger TROSKIL 88 Biocide THPS TROS Seadye Table 9.24 Hydrotest Package, Phytoplankton Toxicity Tests (EC 50, mg.l -1 ) Name Dose 2 Standard WAF EC50 (%) Equivalent EC50 (%) Equivalent TROS Oxygen Scavenger TROSKIL 88 Biocide THPS TROS Seadye WAF refers to test preparations where the chemical or mixture was added to the sea water and allowed to equilibrate for 24 hours before the commencement of the toxicity tests. 2 Dose refers to the manufacturer s recommended concentration in the hydrotest package. The tests were carried out on a series of percentage dilutions of this package. The equivalent concentration of biocide is estimated from the dose and the 50% effects concentration. 3 Toxicity value as a concentration of the entire fluid in seawater expressed as a percentage. The single chemical test results show very low toxicity to both zooplankton and phytoplankton from the tracer dye and the oxygen scavenger. Phytoplankton were more sensitive than the zooplankton to the biocide: phytoplankton gave results with EC 50 values ranging between 1 and 2.1 mg.l -1 and zooplankton LC 50 values of approximately 13 mg.l -1. The tests on the whole hydrotest package (chemicals in seawater at the specified dosage) also indicated that the phytoplankton were the more sensitive: tests on standard and WAF preparations, under fresh and aged conditions, produced very consistent results, with the EC 50 values for all four variants in the range of about 3.4% to 4.8%; that is, the percentage concentration of the whole package in seawater. The above evidence confirms that no significant impact on the receiving environment will result from the discharge of the hydrotest water package tracer dye or oxygen scavenger. While phytoplankton show a higher sensitivity to the biocide, they live in the upper thermal layers of the sea whereas the hydrotest water will be released in deep water, thus avoiding contact with phytoplantkon. These factors along with the low biocide dosage rates in the hydrotest waters and the relatively small volume to be discharged from only one of the infield lines indicates that any residual impacts associated with this discharge would be low ACG Phase 3 ESIA Chapter 9 9/60

7 Pigging Wastes During operation, the Phase 3 oil pipelines will be pigged on a regular basis to remove waxes (and sands) accumulating on the internal surfaces. Pigging will be based on experience from the Chirag platform. Each line will be pigged every 3 days. That equates to 122 times per year for each pipeline. It is calculated that the ACG lines will produce 1 te of wax and sand each, or around 250 te per year. Pigging will be from offshore to onshore via the export lines and the wax, sand and any other materials received at the terminal will be handled in accordance with the AzBU Waste Management Strategy and Azeri Project Waste Management Plan. The AzBU waste management programme is further discussed in Section ACG Phase 3 ESIA Chapter 9 9/61

8 This page is intentionally blank ACG Phase 3 ESIA Chapter 9 9/62

10 Construction, Installation and HUC Environmental Impact Assessment, Mitigation and Monitoring

10 Construction, Installation and HUC Environmental Impact Assessment, Mitigation and Monitoring 0 Construction, Installation and HUC Environmental Impact Assessment, Contents 0. Introduction... 4 0.2 Scoping Assessment... 4 0.3 Impacts to the Atmosphere... 3 0.3. Mitigation... 3 0.3.2 Construction

More information

URS- EIA- REP Date of Issue 19th November 2012

URS- EIA- REP Date of Issue 19th November 2012 DocID: External DocID: URS-EIA-REP-201040 46369085_Doc020_REP_Rev03 Date of Issue 19th November 2012 This report has been prepared by URS Infrastructure & Environment UK Limited on behalf of South Stream

More information

Company Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran

Company Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran Company Profile Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran +98 21 88774544 +98 21 88790572 Table of Contents About US........ 2 Our Capabilities.. 3 Work shop / Storage... 4 EPC Services

More information

9.5 Offshore Facilities Platform Drilling, Production, Facilities Operations and Maintenance

9.5 Offshore Facilities Platform Drilling, Production, Facilities Operations and Maintenance 9.5 Offshore Facilities Platform Drilling, Production, Facilities Operations and Maintenance The main offshore activities for Phase 3 will be hydrocarbon extraction and partial processing. These are described

More information

Abate on Site This involves adding something to the design to abate the impact eg pollution controls.

Abate on Site This involves adding something to the design to abate the impact eg pollution controls. 6 MITIGATION AND MANAGEMENT MEASURES 6.1 INTRODUCTION A key objective of the EIA is to develop and describe practical, commensurate and cost effective mitigation measures that avoid, reduce, control, remedy

More information

Integrity Management of Submarine Pipeline Systems. B.H.Leinum, Det Norske Veritas

Integrity Management of Submarine Pipeline Systems. B.H.Leinum, Det Norske Veritas Integrity Management of Submarine Pipeline Systems B.H.Leinum, Det Norske Veritas PSA Stavanger 9 December 2009 Presentation - Content Introduction to DNV RP-F116 on Integrity Management of Submarine Pipeline

More information

APPENDIX 5B. Shah Deniz 2 Project Composition and Function of Key SD2 Chemicals with Potential for Discharge

APPENDIX 5B. Shah Deniz 2 Project Composition and Function of Key SD2 Chemicals with Potential for Discharge APPENDIX 5B Shah Deniz 2 Project Composition and Function of Key SD2 Chemicals with Potential for Discharge Environmental & Socio-Economic Impact Assessment The tables in this Appendix provide a list

More information

INTECNA srl REFERENCES LIST AND APPROVALS HYDRO-TESTING PROCEDURES

INTECNA srl REFERENCES LIST AND APPROVALS HYDRO-TESTING PROCEDURES INTECNA srl Via Stella del Sud, 4 20060 Mediglia (MI) I Tel +39 02 90601175 Fax +39 02 90601191 E mail intecna@libero.it HYDRO-TESTING PROCEDURES REFERENCES LIST AND APPROVALS Case History n 1 Year : 1996

More information

Route Survey and Intervention Works for the Nord Stream Pipeline. Dredging and the Environment Seminar, Tallinn, 15 Oct. 2008

Route Survey and Intervention Works for the Nord Stream Pipeline. Dredging and the Environment Seminar, Tallinn, 15 Oct. 2008 Route Survey and Intervention Works for the Nord Stream Pipeline Dredging and the Environment Seminar, Tallinn, 15 Oct. 2008 Agenda 1. Nord Stream Project 2. Routing Optimisation and Route Survey 3. Types

More information

APPLICATION OF THE CHARM MODEL FOR THE DISCHARGE CONTROL OF PRODUCTION CHEMICALS

APPLICATION OF THE CHARM MODEL FOR THE DISCHARGE CONTROL OF PRODUCTION CHEMICALS APPLICATION OF THE CHARM MODEL FOR THE DISCHARGE CONTROL OF PRODUCTION CHEMICALS Graham Payne, EOSCA, c/o Briar Technical Services Ltd Melanie Thatcher, EOSCA, c/o Baker Hughes INTEQ 1 INTRODUCTION The

More information

Nord Stream Extension Project >

Nord Stream Extension Project > Nord Stream Extension Project > Public Hearing on the Finnish Environmental Impact Assessment Programme Helsinki 16.4.2013, Turku 17.4.2013, Hanko 18.4.2013, Kotka 22.4.2013, Mariehamn 24.4.2013 1 Project

More information

Inland Technologies Inc

Inland Technologies Inc Inc Evaluation of the Mono-ethylene Glycol [MEG] Concentrator to Recycle MEG used in Hydrate Prevention March 2007 Document Nr 0035_INL-OPT-REP-001 Client : Inland Technologies Inc Project : Evaluation

More information

CP DESIGN OF A SUPER 13% CR FLOWLINE. Are Sjaastad and Harald Osvoll FORCE Technology Norway AS Hornebergveien Trondheim Norway

CP DESIGN OF A SUPER 13% CR FLOWLINE. Are Sjaastad and Harald Osvoll FORCE Technology Norway AS Hornebergveien Trondheim Norway CP DESIGN OF A SUPER 13% CR FLOWLINE Are Sjaastad and Harald Osvoll FORCE Technology Norway AS Hornebergveien 7 7038 Trondheim Norway Olav Jan Hauge and Rolf E. Lye Norsk Hydro ASA Norway Guy Bärs Technip

More information

Tomakomai CCS Demonstration Project

Tomakomai CCS Demonstration Project 1 Tomakomai CCS Demonstration Project CSLF TECHNICAL GROUP MEETING October 4, 2016 Japan CCS Co., Ltd. (JCCS) 2 Overview of Tomakomai Demonstration Project Hokkaido Is. Tomakomai TOKYO Tomakomai CCS Demonstration

More information

TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum

TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum FGP-WPMP Major Construction Scope Overview Jorge Calvo 30 January 2017 Atyrau, Kazakhstan Tengizchevroil

More information

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT The health of the world s oceans and marine life is degrading rapidly as a result of excess human activities.

More information

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure Additional Information Regarding The Implementation Programme

More information

Marine Growth Management during Decommissioning

Marine Growth Management during Decommissioning Marine Growth Management during Decommissioning Annual Environment Seminar Oil & Gas UK 28 November 2013 David Sell Ben Bryant Joe Ferris Content Characteristics of marine growth in situ offshore and as

More information

Offshore installation operations in Arctic waters. Igor Kopsov, Region Manger SURF Russia and Kazakhstan

Offshore installation operations in Arctic waters. Igor Kopsov, Region Manger SURF Russia and Kazakhstan Offshore installation operations in Arctic waters Igor Kopsov, Region Manger SURF Russia and Kazakhstan Table of contents 1. Offshore operations in remote and harsh environment Snow White (Norway) 2. Offshore

More information

Mitigating Environmental Impacts in the Offshore Oil and Gas Industry

Mitigating Environmental Impacts in the Offshore Oil and Gas Industry Mitigating Environmental Impacts in the Offshore Oil and Gas Industry Paul Barnes, Manager - Atlantic Canada & Arctic NOTES 2015 St. John s, NL April 27, 2015 Overview Who is CAPP? Oil and Gas Lifecycle

More information

Global Oilfield Solutions. Basolon GL 40 and Basolon IN 40: H 2 S scavengers for the oilfield application

Global Oilfield Solutions. Basolon GL 40 and Basolon IN 40: H 2 S scavengers for the oilfield application Basolon GL 40 and Basolon IN 40: H 2 S scavengers for the oilfield application Hydrogen sulfide (H 2 S) occurs naturally and is frequently encountered in the oil and gas industry. Natural gas or crude

More information

Background story: Coating and Logistics. Nord Stream 2 AG Jul-17

Background story: Coating and Logistics. Nord Stream 2 AG Jul-17 Nord Stream 2 AG Jul-17 Table of Contents Introduction... 3 1. What is concrete weight coating, and why is it necessary?... 4 How it works... 4 Why it s necessary... 6 2. Nord Stream 2 partners with Wasco...

More information

Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events)

Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events) Chapter 12 Hazard Analysis and Risk Assessment (Unplanned Events) TABLE OF CONTENTS 12 HAZARD ANALYSIS AND RISK ASSESSMENT... 12-1 12.1 Introduction... 12-1 12.2 Pipeline Design and Risk... 12-1 12.2.1

More information

AQUCAR 742 Water Treatment Microbiocide for the Oilfield (NA, LA, Europe)

AQUCAR 742 Water Treatment Microbiocide for the Oilfield (NA, LA, Europe) Product Information AQUCAR 742 Water Treatment Microbiocide for the ilfield (NA, LA, Europe) CAS Reg. No. 111-30-8 General The AQUCAR family of oilfield microbiocides are glutaraldehyde-based biocides

More information

DP Conference MTS Symposium. Flow Assurance. Elijah Kempton Tommy Golczynski

DP Conference MTS Symposium. Flow Assurance. Elijah Kempton Tommy Golczynski DP Conference MTS Symposium Flow Assurance Elijah Kempton Tommy Golczynski Marine Technology Society September 30, 2004 Session Outline Flow Assurance Overview Key Flow Assurance Issues Wax Hydrates Slugging

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

DRAFT FOR CONSULTATION

DRAFT FOR CONSULTATION DRAFT FOR CONSULTATION Exclusive Economic Zone and Continental Shelf (Environmental Effects Discharge and Dumping) Regulations 2014 Governor-General Order in Council At Wellington this day of 2014 Present:

More information

Emergency Telephone Number: Within Australia Outside Australia

Emergency Telephone Number: Within Australia Outside Australia 1. IDENTIFICATION OF THE MATERIAL AND SUPPLIER 1.1 Product Details Product Name: Other Name: Aquatain AMF Liquid Mosquito Film Recommended Use: Mosquito control on water bodies 1.2 Company Details Manufacturer/Supplier:

More information

MATERIAL SAFETY DATA SHEET

MATERIAL SAFETY DATA SHEET MATERIAL SAFETY DATA SHEET 1. IDENTIFICATION OF THE MATERIAL AND SUPPLIER 1.1 Product Details: Product name: Chemical name of main ingredient: Recommended Use: AQUATAIN AMF Silicone Fluid (Polydimethylsiloxane)

More information

A Comparison between. commercial Pipeline Fluid-dynamic Codes. OLGA vs. LEDAFLOW

A Comparison between. commercial Pipeline Fluid-dynamic Codes. OLGA vs. LEDAFLOW A Comparison between commercial Pipeline Fluid-dynamic Codes OLGA vs. LEDAFLOW Presentation Content Scope Analyzed Pipeline System and Basic Data Steady State Simulation Results and Summary Transient Simulation

More information

Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013

Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17) Floating LNG: The Challenges of production systems and well fluids management By: Frederic MOLLARD, TECHNIP France 04/19/2013

More information

5 Emissions, discharges and wastes

5 Emissions, discharges and wastes 5 Emissions, discharges and wastes 5 5 Emissions, Discharges and Wastes 5.1 Introduction Over the lifetime of the Ichthys Gas Field Development Project (the Project) a range of emissions, discharges and

More information

Nord Stream 2. Espoo Report Non-Technical Summary

Nord Stream 2. Espoo Report Non-Technical Summary Nord Stream 2 Espoo Report Non-Technical Summary Nord Stream 2 Espoo Report Non-Technical Summary Transporting Natural Gas to the EU Nord Stream 2 is an infrastructure project comprising a natural gas

More information

1) 2) 3) 4) 5) The oil and gas cycle. Life cycle of oil and gas (time) Potential requirement on ground

1) 2) 3) 4) 5) The oil and gas cycle. Life cycle of oil and gas (time) Potential requirement on ground The oil and gas cycle Life cycle of oil and gas (time) 1) 2) 3) 4) 5) 6) Activity Desk study and get licens: Find areas with favorable geological conditions Seismic survey: Provide detailed information

More information

Admiralty Inlet Pilot Tidal Project FERC No Appendix D. Water Quality Monitoring Plan

Admiralty Inlet Pilot Tidal Project FERC No Appendix D. Water Quality Monitoring Plan Appendix D Water Quality Monitoring Plan ADMIRALTY INLET PILOT TIDAL PROJECT FERC PROJECT NO. 12690 WATER QUALITY MONITORING PLAN (submitted with the Final Application for a New Pilot Project License)

More information

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009 Portbury Dock Renewable Energy Plant Cumulative Impact Assessment Non-Technical Summary September 2009 INTRODUCTION On 28 th August 2009 E.ON Climate & Renewables UK Developments Limited (EC&R) submitted

More information

/ Production.

/ Production. / Production www.exprogroup.com A global leader in fast-track, cost-effective and enhanced production solutions. The production solutions we provide allow our customers to plan the optimal exploitation

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

OIL RECORD BOOK INSTRUCTIONS

OIL RECORD BOOK INSTRUCTIONS OIL RECORD BOOK INSTRUCTIONS Oil Record Book, Part I - Machinery space operations (All Ships) The following pages of this section show a comprehensive list of items of machinery space operations which

More information

Timothy Cornelius CEO, Atlantis Resources Limited. Atlantis Resources: November

Timothy Cornelius CEO, Atlantis Resources Limited. Atlantis Resources: November Timothy Cornelius CEO, Atlantis Resources Limited Atlantis Resources: November 2014 0 Atlantis Turbine Systems 1.5MW turbine system AR1500 detailed design contract with Lockheed Martin formally commenced

More information

CASBEE (Comprehensive Assessment System for Building Environmental Efficiency)

CASBEE (Comprehensive Assessment System for Building Environmental Efficiency) Japan CASBEE (Comprehensive Assessment System for Building Environmental Efficiency) CASBEE is a Japanese green rating tool used for evaluating environmental building performance, developed under the guidance

More information

ES 1 Introduction. ES 1.1 Project outline

ES 1 Introduction. ES 1.1 Project outline ES 1 Introduction ES 1.1 Project outline The Shah Deniz Stage 1 Project is the first stage in the development of the Shah Deniz gas field. The Stage 1 project comprises an Upstream component consisting

More information

ESIA Albania Section 4 Project Description

ESIA Albania Section 4 Project Description ESIA Albania Section 4 Project Description Page 2 of 108 TABLE OF CONTENTS 4 PROJECT DESCRIPTION 7 4.1 TAP Project Overview 7 4.1.1 Purpose of the Project Description 7 4.1.2 TAP Project Scope and Location

More information

Platform Construction and Installation

Platform Construction and Installation Platform Construction and Installation Platform Construction and Installation UK Construction Yards. Worldwide Construction. Construction Quality and Safety. Construction Risks. Offshore Installation.

More information

Appendix A: Project Characteristics

Appendix A: Project Characteristics Gorgon Fourth Train Expansion Proposal Appendix A: Project Characteristics Appendices Project Characteristics A Key Characteristics table has been prepared to describe the elements of the Foundation Project

More information

Dry and Liquefied Gas to European Markets

Dry and Liquefied Gas to European Markets Dry and Liquefied Gas to European Markets Competing or Complementary? Graham Bennett Outline Introduction Supply/Demand changes affecting the gas market Innovations impacting gas import/export options

More information

Technical Note FlexSteel Pipe Transport, Installation, and Handling

Technical Note FlexSteel Pipe Transport, Installation, and Handling Technical Note FlexSteel Pipe Transport, Installation, and Handling Tech Note No. : TN_FlexSteel_113, Rev 0 Date : 20 February 2006 Prepared By : David Lenzer Approved By : Michael Case This technical

More information

The Importance of Pipeline Cleaning: Risks, Gains, Benefits, Peace of Mind

The Importance of Pipeline Cleaning: Risks, Gains, Benefits, Peace of Mind The Importance of Pipeline Cleaning: Risks, Gains, Benefits, Peace of Mind André van der Werff Brenntag Nederland B.V. Netherlands 1. Increased pipeline failures Time, deterioration and corrosion of the

More information

BASICS OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA)

BASICS OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) BASICS OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) HSE specialists, environmental engineers, design engineers, project managers and senior project managers involved in conceptual design, Front-End

More information

Application of the AGF (Anoxic Gas Flotation) Process

Application of the AGF (Anoxic Gas Flotation) Process Application of the AGF (Anoxic Gas Flotation) Process Dennis A. Burke Environmental Energy Company, 6007 Hill Road NE, Olympia, WA 98516 USA (E-mail: dennis@makingenergy.com http//www.makingenergy.com)

More information

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate Project Overview Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate a natural gas-tomethanol production plant and storage facilities, and a new marine terminal, in the

More information

Integrity management and operational experiences of flexible risers

Integrity management and operational experiences of flexible risers Integrity management and operational experiences of flexible risers Stavanger - November 26 th 2013 Flexible risers Management of Integrity, learning, sharing of experiences and continuous improvement

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

ESIA Italy Annex 11 Summary of Impacts and Mitigation Measures

ESIA Italy Annex 11 Summary of Impacts and Mitigation Measures ESIA Italy Annex 11 Summary of s and Page 2 of 42 1 SUMMARY OF IMPACTS AND MITIGATION MEASURES [* NOTE: Mitigation measures in italics will be developed in a further stage of the Project.] Offshore Physical

More information

METAL PRODUCTS PIPELINE ENGINEERING. Engineered Products for the Pipeline Pigging and Flow Assurance Industry

METAL PRODUCTS PIPELINE ENGINEERING. Engineered Products for the Pipeline Pigging and Flow Assurance Industry METAL PRODUCTS 1 2 3 PIPELINE ENGINEERING Engineered Products for the Pipeline Pigging and Flow Assurance Industry Engineered Products for the Pipeline Pigging and Flow Assurance Industry Pipeline Engineering

More information

The Future of the Ocean Economy - Offshore Wind

The Future of the Ocean Economy - Offshore Wind The Future of the Ocean Economy - Offshore Wind Workshop on Shipping and the Offshore Industry Monday 24 th November, 2014 OECD, Paris Key data sources EWEA Background Projections Technology Finance IEA

More information

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , & TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed

More information

South Stream Offshore Pipeline Russian Sector Environmental and Social Impact Assessment (ESIA) July 2014

South Stream Offshore Pipeline Russian Sector Environmental and Social Impact Assessment (ESIA) July 2014 South Stream Offshore Pipeline Russian Sector Environmental and Social Impact Assessment (ESIA) July 2014 This report has been prepared by URS Infrastructure & Environment UK Limited on behalf of South

More information

SAFETY DATA SHEET Kresto Kolor ULTRA

SAFETY DATA SHEET Kresto Kolor ULTRA SAFETY DATA SHEET SECTION 1: Identification of the substance/mixture and of the company/undertaking 1.1. Product identifier Product name Product number KKU30ML,KKU250ML,KKU2LT 1.2. Relevant identified

More information

Module 12: Oceanography Topic 6 Content: Ocean Pollution Notes. Ocean Pollution

Module 12: Oceanography Topic 6 Content: Ocean Pollution Notes. Ocean Pollution Ocean Pollution 1 Ocean pollution is an important modern-day environmental issue. Pollution occurs when chemical, physical, and/or biological agents are introduced into an environment and cause undesirable

More information

Development of large-diameter line pipe for offshore applications

Development of large-diameter line pipe for offshore applications Development of large-diameter line pipe for offshore applications Dr. Michael Gräf Europipe Deutschland GmbH, Muelheim, Germany Dr. Hans-Georg Hillenbrand Europipe GmbH, Ratingen, Germany EUROPIPE. The

More information

Material Safety Data Sheet (MSDS)

Material Safety Data Sheet (MSDS) Page: 1 of 7 1. IDENTIFICATION OF THE SUBSTANCE/PREPARATION AND THE COMPANY/ UNDERTAKING Identification of the substance or preparation: Linear alkyl benzene CAS Number: 67774-74-7 Synonyms: Linear Alkyl

More information

THE REPUBLIC OF LIBERIA Bureau Of Maritime Affairs

THE REPUBLIC OF LIBERIA Bureau Of Maritime Affairs THE REPUBLIC OF LIBERIA Bureau Of Maritime Affairs 8619 Westwood Center Dr Suite 300 Vienna, VA USA 22182 Telephone: (703) 790-3434 Fax: (703) 790-5655 December 13, 2006 MARINE OPERATIONS NOTE 9/2006 -

More information

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT Final Scoping Report - Non-Technical Summary Presentation Structure of the Presentation Introduction to the Tema LNG Project

More information

5. MONITORING ACTIVITIES

5. MONITORING ACTIVITIES 34 5. MONITORING ACTIVITIES This chapter describes the environmental monitoring activities performed during 21. Monitoring was performed related to the following construction activities: munitions clearance,

More information

Detailed Air Quality Modelling and Analysis

Detailed Air Quality Modelling and Analysis Page 1 of 22 Ser. No. Via San Gregorio, 38 20124 Milan - Italy IAL00-ERM-643-Y-TAE-1021 Proponent: Author: Project Title: Trans Adriatic Pipeline AG Environmental Resources Management Trans Adriatic Pipeline

More information

Material Safety Data Sheet

Material Safety Data Sheet Section 1. Chemical Product and Company Identification Material Safety Data Sheet Product Name: Propylene Glycol 50% Version: V3 Effective Date: 15 January, 2013 Supplier / Manufacturer: Chemfax Products

More information

Material Safety Data Sheet Maxcare Pine Disinfectant Crescent Brands

Material Safety Data Sheet Maxcare Pine Disinfectant Crescent Brands Page: 1 of 6 1. IDENTIFICATION OF THE SUBSTANCE AND COMPANY DETAILS 1.1 BRAND NAME Maxcare 1.2 PRODUCT CATEGORY Detergent.Disinfectant. Washing and cleaning. 1.3 COMPANY NAME UK 1.4 COMPANY CONTACT DETAILS

More information

Without having Cost Estimation Model you are putting your Project on a Big RISK

Without having Cost Estimation Model you are putting your Project on a Big RISK July 2014 Without having Cost Estimation Model you are putting your Project on a Big RISK Drive your project with a appropriate Cost Estimation System to mitigate Risks Plug your project to Our NoDoC Database

More information

High performance polypropylene thermal insulation for high temperature and deep water applications

High performance polypropylene thermal insulation for high temperature and deep water applications High performance polypropylene thermal insulation for high temperature and deep water applications Allan Boye Hansen and Adam Jackson Bredero Shaw Norway AS, div. Thermotite ABSTRACT Flow assurance including

More information

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval

APPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval APPENDIX 2 Nova Scotia Department of Environment and Labour Terms and Conditions for Approval Approval Approval Date: March 14, 2007 Keltic Petrochemicals Inc. LNG and Petrochemical Plant Facilities Keltic

More information

Environmentally Acceptable Lubricants (EALs): Choosing the right EAL type for your application

Environmentally Acceptable Lubricants (EALs): Choosing the right EAL type for your application Environmentally Acceptable Lubricants (EALs): Choosing the right EAL type for your application There is a wide range of performance levels among both readily biodegradable and petroleum based lubricants.

More information

Safety Data Sheet (1907/2006/EC)

Safety Data Sheet (1907/2006/EC) 1 Identification of the substance/preparation and company 1.1 Name of substance/preparation Commercial product name: LIQUIDSEAL for fruit citrus post harvest 1.2 Use of substance/preparation: Agricultural

More information

INPEX Ichthys LNG Project

INPEX Ichthys LNG Project INPEX Ichthys LNG Project INPEX Ichthys LNG Project McDermott is delivering an engineering, procurement, construction and installation (EPCI) solution for one of the world s largest subsea gas field developments

More information

SAFETY DATA SHEET 46V PAG OIL WITH UV DYE

SAFETY DATA SHEET 46V PAG OIL WITH UV DYE Supersedes: February 10, 2012 Section 1 Identification of the Substance/Mixture and of the Company/Undertaking Product Name: Part Number(s): 511046 Product Class: Automotive Refrigerant Lubrication Oil

More information

Environmental Authorization Application to the EPA for Offshore 2D Seismic, Multibeam and Coring Acquisition Survey

Environmental Authorization Application to the EPA for Offshore 2D Seismic, Multibeam and Coring Acquisition Survey TGS GEOPHYSICAL COMPANY (UK), LTD. PROJECT SUMMARY for Environmental Authorization Application to the EPA for Offshore 2D Seismic, Multibeam and Coring Acquisition Survey Project Title TGS Guyana Offshore

More information

Electric Paint Safety Data Sheet

Electric Paint Safety Data Sheet Electric Paint Safety Data Sheet ACCORDING TO EC-REGULATIONS 1907/2006 (REACH) & 1272/2008 (CLP) 1. IDENTIFICATION OF THE SUBSTANCE / MIXTURE AND OF THE COMPANY / UNDERTAKING 1.1 Product identifier GHS

More information

Down Hole Flow Assurance

Down Hole Flow Assurance Down Hole Flow Assurance Ferhat Erdal Senior Advisor - Flow Assurance Steve Cochran Senior Advisor - Flow Assurance SPE GCS Annual Drilling Symposium Spring, TX April 13, 2017 Flow Assurance Key Words

More information

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED Chapter 17 Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.1.1 Applicability The regulations in this chapter apply to any private potable water supply system where plumbing fixtures are

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

UCON Lubricant LB-XY Products

UCON Lubricant LB-XY Products Product Safety Assessment UCON Lubricant LB-XY Products Product Safety Assessment documents are available at www.dow.com/productsafety/assess/finder. Select a Topic: Names Product Overview Manufacture

More information

Examples of Studies conducted by

Examples of Studies conducted by Examples of Studies conducted by Page Oxygen Uptake Rate (OUR) Fingerprints 1 Toxicity Assessment Using a Dilution Series 4 Assessment of Acute Toxicity to Treatment Plants 5 Biodegradation Tests for Wastewater

More information

SAFETY DATA SHEET EVERFRESH - POT POURRI

SAFETY DATA SHEET EVERFRESH - POT POURRI SAFETY DATA SHEET SECTION 1: Identification of the substance/mixture and of the company/undertaking 1.1. Product identifier Product name Product number Internal identification A102 EV Janitorial 1.2. Relevant

More information

Drilling Waste and Well Site Restoration

Drilling Waste and Well Site Restoration Drilling Waste and Well Site Restoration Geoff Silcox CH EN 6158 Energy and Society Chemical Engineering, University of Utah Drilling Waste: Introduction Mud controls subsurface pressures, lubricates drill

More information

DP INNOVATION. Dynamic Positioning of Underwater Vehicles - Tethered or Not

DP INNOVATION. Dynamic Positioning of Underwater Vehicles - Tethered or Not DP INNOVATION Dynamic Positioning of Underwater Vehicles - Tethered or Not Jonathan Davis BP America Dr. Ioseba Tena Seebyte, Ltd October 7-8, 2008 Return to Session Directory Dynamic Positioning of Underwater

More information

LONE STAR PIPE TRACKING SYSTEM

LONE STAR PIPE TRACKING SYSTEM LONE STAR PIPE TRACKING SYSTEM PIPE TRACKING SYSTEM PRESENTATION ONSHORE/OFFSHORE PIPE TRACKING TECHNOLOGY/Material Management System LONE STAR PIPE TRACKING SYSTEM REAL TIME WEB BASED TRACKING SYSTEM

More information

Environmental Impact Assessment for Drilling of Three Exploration Wells in the Mayaro-Guayaguayare Block, Offshore Trinidad

Environmental Impact Assessment for Drilling of Three Exploration Wells in the Mayaro-Guayaguayare Block, Offshore Trinidad Environmental Impact Assessment for Drilling of Three Exploration Wells in the Mayaro-Guayaguayare Block, Offshore Trinidad February 2013 Prepared for: Voyager Energy (Trinidad) Ltd. Princes Court, Level

More information

Product No: BiologiQ AG201090, AG202080, AG203070, AG204060, AG Revision Date: 08 December 2016

Product No: BiologiQ AG201090, AG202080, AG203070, AG204060, AG Revision Date: 08 December 2016 SECTION 1. PRODUCT AND COMPANY IDENTIFICATION Product Name Common Names BiologiQ AG Eco Starch Polymer Resin BiologiQ Starch Resin BiologiQ Eco Starch Resin Product Use Manufacturer BiologiQ ESR Resin

More information

9 Socio-Economic Impact Assessment, Mitigation and Management

9 Socio-Economic Impact Assessment, Mitigation and Management 9 Mitigation and Management Table of Contents 9.1 Introduction... 9-2 9.2 Scoping... 9-3 9.3 Socio Economic Impacts... 9-9 9.3.1 Onshore Impacts Associated with Physical Presence of Seismic Vehicles and

More information

Production Chemistry & Microbiology Materials Consultancy & Testing Corrosion Management & Monitoring. Production & Integrity Assurance

Production Chemistry & Microbiology Materials Consultancy & Testing Corrosion Management & Monitoring. Production & Integrity Assurance Production Chemistry & Microbiology Materials Consultancy & Testing Corrosion Management & Monitoring Production & Integrity Assurance A strong commitment to meeting our clients needs and expectations

More information

SAFETY DATA SHEET FRESH FLORAL BOUQUET

SAFETY DATA SHEET FRESH FLORAL BOUQUET Page: 1 Compilation date: 01/08/2008 Revision date: 20/08/2014 Revision No: 5 Section 1: Identification of the substance/mixture and of the company/undertaking 1.1. Product identifier Product name: Hospifresh

More information

Providing clear solutions with innovative design

Providing clear solutions with innovative design Alderley Alderley Shaping the future of produced water treatment solutions Produced Water Treatment Solutions Providing clear solutions with innovative design Produced Water Treatment Solutions Solutions

More information

LNG Plant Overview. Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen

LNG Plant Overview. Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen LNG Plant Overview Seminar with Supplier Association Murmanshelf Murmansk, 15 May 2012 Jostein Pettersen Table of Content Part 1 : LNG plant overview (Jostein) Part 2 : Main equipment units (Jostein) Part

More information

Identification of the substance and the company

Identification of the substance and the company Ne silica. 1 1.1 Product identifier Name of the substance Identification of the substance and the company Calcium sulphate Registration number 01-2119444918-26-0054 EC-No. 231-900-3 CAS-No. 7778-18-9 1.2

More information

Environmental Management Plan (EMP)

Environmental Management Plan (EMP) SE DELI GS DRIFT MI E ORA GE RIVER MI ES MI I G ACTIVITIES A D PROPOSED EW I PIT SLIMES DISPOSAL Environmental Management Plan (EMP) Compiled for: Namdeb Diamond Corporation (Pty) Ltd Compiled by: Unit

More information

La Taboada (Lima-Peru) outfall

La Taboada (Lima-Peru) outfall La Taboada (Lima-Peru) outfall E. Pita (1), I. Sierra (2) 1. Civil Engineer and General Manager, Ingeniería Creativa Pita, S.L..(INCREA), calle Buganvilla 6, p1, 1ºA. Madrid 28036-Spain (E-mail: epita@increa.eu;

More information

SAFETY DATA SHEET ILFOSTOP 1+19

SAFETY DATA SHEET ILFOSTOP 1+19 Revision Date 19/10/2015 Revision 3 Supersedes date 17/09/2012 SAFETY DATA SHEET SECTION 1: IDENTIFICATION OF THE SUBSTANCE/MIXTURE AND OF THE COMPANY/UNDERTAKING 1.1. Product identifier Product name Internal

More information

Discussion of the Environmental Impacts of the Solwara 1 Copper Concentration and Smelting Processes

Discussion of the Environmental Impacts of the Solwara 1 Copper Concentration and Smelting Processes 89 90 Discussion of the Environmental Impacts of the Solwara 1 Copper Concentration and Smelting Processes Tongling Non-Ferrous Metals Group copper smelter Image credit: nerin.com 91 Analysis IV Environmental

More information

Ambient Air Quality Monitoring Baseline Report, Kirby Misperton A Wellsite, KM8 Production Well

Ambient Air Quality Monitoring Baseline Report, Kirby Misperton A Wellsite, KM8 Production Well Ambient Air Quality Monitoring Baseline Report, Kirby Misperton A Wellsite, KM8 Production Well. Prepared for: Third Energy UK Gas Ltd. Document Control Page Client Third Energy UK Gas Ltd. Document Title

More information

No Dig renovation and installation of systems using polyolefin pipes

No Dig renovation and installation of systems using polyolefin pipes No Dig renovation and installation of systems using polyolefin pipes MEMBER OF Why use No Dig technology with polyolefin pipes? In many of the major cities of the world, the underground pipeline systems

More information