Urban Pipeline. Replacement Program A NATURAL GAS PIPELINE INITIATIVE. Southwest Calgary Connector & South Glenmore Lateral. Safety First. Always.

Size: px
Start display at page:

Download "Urban Pipeline. Replacement Program A NATURAL GAS PIPELINE INITIATIVE. Southwest Calgary Connector & South Glenmore Lateral. Safety First. Always."

Transcription

1 Urban Pipeline Replacement Program A NATURAL GAS PIPELINE INITIATIVE Southwest Calgary Connector & South Glenmore Lateral Safety First. Always.

2 ATCO s Urban Pipeline Replacement Program In January 2014, ATCO received approval from the Alberta Utilities Commission (AUC) to proceed with its Urban Pipeline Replacement (UPR) Program. The Program will see the high-pressure natural gas transmission pipelines in Calgary and Edmonton neighbourhoods recommissioned to lower-pressure natural gas distribution service or abandoned and new, modern high-pressure natural gas transmission pipelines installed primarily within the Transportation/Utility Corridors (TUCs) that surround the cities. By doing this, ATCO will modernize the natural gas transmission network and add the capacity needed to meet the growing demand for natural gas in the two cities. A large factor in the approval of the UPR Program was the extensive public consultation activities that ATCO engaged in as part of the application process. This information package is part of ATCO s ongoing commitment to ensuring homeowners and businesses living along the pipeline route are aware of the project, the process, and ATCO s approach to constructing these pipelines. For more information, please visit ATCOPipelines.com/upr. If you have any questions or concerns, please contact us directly at Project Overview In the fall of 2017, ATCO proposes to begin construction on the Southwest Calgary Connector (SWCC). This project will include: The installation of a 508 mm (20 ) natural gas transmission pipeline that will run 14 km within the Transportation/Utility Corridor from the Sarcee Trail SW/Glenmore Trail SW interchange to Spruce Meadows Trail (HWY 22X). The installation of the South Glenmore Lateral, which is a 324 mm (12 ) natural gas transmission pipeline that runs 1.9 km within the Transportation/Utility Corridor along the extension of 90th Ave SW. The installation of above ground facilities (examples and general description of the above ground facilities are shown below and specific locations for this project can be seen on the map provided.) ATCO Gate Stations ATCO Gate Stations occupy a fenced footprint that is generally 60 m by 60 m. The purpose of these facilities is to reduce the pressure from ATCO s high-pressure transmission lines to ATCO Gas lower pressure distribution pipelines. The gas then feeds into the distribution system, which delivers it to homes and businesses. These facilities also provide measurement of gas volumes flowing through the station. ATCO Control Facilities ATCO Control Facilities occupy a fenced footprint that typically ranges in size from 25 m by 25 m to 50 m by 75 m. The purpose of these facilities is to enable ATCO to control major connection points on the system. The facilities can also include odourant injection, maximum operating pressure protection, pressure and flow control components.

3 Highly-trained staff in our Control Centre monitor our system 24/7. Safety & Construction AT ATCO, safety is paramount. The new pipelines will be designed and constructed to exceed industry standards including materials, construction practices, and inspection capabilities. ATCO meets all applicable pipelines standards and exceeds code requirements by performing non-destructive inspection on 100% of welds made during construction. A significant portion of the new pipeline will be constructed using the open trench method; however, horizontal directional drilling will be used to install pipe under existing roads to minimize the impact on traffic and the excavation of environmentally sensitive areas and water course crossings. Community ATCO builds and maintains a safe and reliable natural gas pipeline network, to provide service to Albertans and Alberta-based companies while developing strong community relationships. ATCO will work and communicate with interested parties throughout the UPR Program to minimize construction inconvenience. ATCO is committed to: Working cooperatively with the community by incorporating feedback into project design and construction. Clearly marking and fencing work areas to control access during construction. Utilizing the appropriate signage and flag persons to safely direct local traffic, as necessary. Circulating notifications to affected communities to provide up-to-date information on nearby construction activities. Project Preparations Over the next couple of months, ATCO personnel will meet with directly affected landowners, businesses, the City of Calgary, and other interested parties along the pipeline route to discuss project details. ATCO personnel will ensure that all required approvals from Alberta Environment, the AUC, and Alberta Infrastructure are in place prior to beginning construction. We will also continue working with the applicable authorities regarding any potential traffic impacts during the project. What You Will See ATCO has a well-defined process in place for pipeline installations. Typical construction activities you will see when construction begins are: Pre-installation Activities (Summer 2017): Surveying the pipeline alignment and workspace (horizontal directional drills) to establish and mark construction limits and to locate other underground utilities (pipelines, cables, etc.). Removing and stockpiling topsoil in layers to protect the soil for future use. Grading and preparing land for construction. Pipeline Installation Activities (Fall 2017 to Summer 2018): Excavation of trenches to install pipelines. Set up of horizontal directional drilling rigs and support trailers at road crossing locations. Stringing and welding of pipe sections. Non-destructive inspection on 100% of welds. Lowering the pipeline into trenches. Hydro-static pressure testing new pipe sections. Connecting the new pipeline to the existing system. Commissioning of the pipeline for natural gas transmission services. Restoring temporary working space and other affected land areas back to original conditions once all work is completed.

4 Open House: February 2, 2017 Highlights What Why Replacing aging natural gas pipeline infrastructure within the City of Calgary. The installation of ~14 km of 508 (20 ) and ~1.9 km of 324 mm (12 ) natural gas transmission pipelines. To modernize the natural gas system and to add capacity to meet the growing demand for safe and reliable natural gas service. Highlights When Construction planned from September 2017 to March Where Along the proposed SW Calgary Ring Road between Sarcee Trail SW/Glenmore Trail SW and Spruce Meadows Trail (HWY 22X). We welcome the opportunity for open dialogue about this and any of our projects Frederic De Caigny Project Manager Frederic.DeCaigny@ATCO.com Kyle Wig Supervisor, Land Acquisition Kyle.Wig@ATCO.com ATCO Pipelines is part of the ATCO Group of Companies. With approximately 7,000 employees and assets of $20 billion, ATCO is a diversified global corporation delivering service excellence and innovative business solutions in Structures & Logistics (workforce housing, innovative modular facilities, construction, site support services, and logistics and operations management); Electricity (electricity generation, transmission, and distribution); Pipelines & Liquids (natural gas transmission, distribution and infrastructure development, energy storage, and industrial water solutions); and Retail Energy (electricity and natural gas retail sales). Safety First. Always. ATCOPipelines.com

5

6 Urban Pipeline Replacement Program Calgary

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 21591-D01-2017 West Calgary Connector Pipelines Project February 21, 2017 Alberta Utilities Commission Decision 21591-D01-2017 West Calgary Connector Pipelines Project Proceeding 21591 Application

More information

Investor Presentation September 2016

Investor Presentation September 2016 Investor Presentation September 2016 1 LEGAL DISCLAIMER Statements made by representatives for ATCO Ltd. and information provided in this presentation may be considered forward-looking statements. By their

More information

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project Welcome Metro North Transmission Project Burnaby Community Information Open House March 8, 207 Thank you for attending this Community Information Open House about the Metro North Transmission Project.

More information

ATCO Gas and Pipelines Ltd. (South)

ATCO Gas and Pipelines Ltd. (South) Decision 20512-D01-2016 Southwest Edmonton Connector Pipeline January 14, 2016 Alberta Utilities Commission Decision 20512-D01-2016 Southwest Edmonton Connector Pipeline Proceeding 20512 Applications 20512-A001

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

INDUSTRIAL FORT SASKATCHEWAN S. fortsask.ca/business LOCATION CONNECTIONS GROWTH

INDUSTRIAL FORT SASKATCHEWAN S. fortsask.ca/business LOCATION CONNECTIONS GROWTH INDUSTRIAL FORT SASKATCHEWAN S L E A D I N Gedge LOCATION CONNECTIONS GROWTH fortsask.ca/business Fort Saskatchewan is a major industrial and commercial centre in northern Alberta. We are the largest urban

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

Field Instruction. All Horizon Power workers who work in and around excavations.

Field Instruction. All Horizon Power workers who work in and around excavations. 6.4 Excavation work and directional drilling Purpose This instruction provides the minimum requirements for: All Horizon Power workers who work in and around excavations. All Horizon Power workers who

More information

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement Your guide to the SOUTHERN ALBERTA Transmission Reinforcement OUR TRANSMISSION LINES TRANSPORT THE POWER YOU USE EVERY DAY. Edmonton Red Deer Calgary Lethbridge 85% AltaLink s transmission system efficiently

More information

ADDISON NATURAL GAS PROJECT Phase 2 Middlebury Community Meeting. February 27, 2013 Middlebury VFW Post 7823

ADDISON NATURAL GAS PROJECT Phase 2 Middlebury Community Meeting. February 27, 2013 Middlebury VFW Post 7823 ADDISON NATURAL GAS PROJECT Phase 2 Middlebury Community Meeting February 27, 2013 Middlebury VFW Post 7823 0 Agenda Vermont Gas Natural Gas Economics Review of the Addison Natural Gas Project Discuss

More information

Nexen Inc. and CNOOC Canada Inc.

Nexen Inc. and CNOOC Canada Inc. Decision 2012-330 Long Lake Project December 6, 2012 The Alberta Utilities Commission Decision 2012-330: Long Lake Project Application No. 1608729 Proceeding ID No. 2074 December 6, 2012 Published by The

More information

Canadian Solar Developers Ltd.

Canadian Solar Developers Ltd. Canadian Solar Developers Ltd. Type of Document Draft Report Project Name Proposed Ground Mount Solar Facility L.P #5 8338 Scotchmere Drive, Strathroy, ON OPA FIT Program: FIT-FL67GB5 Project Number V00002250-00

More information

SUNDANCE 7 January 2014

SUNDANCE 7 January 2014 Artist rendering of a combined-cycle natural gas power plant. SUNDANCE 7 January 2014 Project Information Booklet Table of Contents Introduction to Sundance 7 1 TransAlta and MidAmerican 1 Project location

More information

Roadrunner Gas Transmission Pipeline. Frequently Asked Questions Summer 2015

Roadrunner Gas Transmission Pipeline. Frequently Asked Questions Summer 2015 Roadrunner Gas Transmission Pipeline Frequently Asked Questions Summer 2015 Will the pipeline provide gas service to communities along the route? No. The Roadrunner pipeline is a natural gas transmission

More information

INVESTING IN OUR ECONOMY: NORTH-SOUTH CORRIDOR TRANSMISSION REINFORCEMENT

INVESTING IN OUR ECONOMY: NORTH-SOUTH CORRIDOR TRANSMISSION REINFORCEMENT INVESTING IN OUR ECONOMY: NORTH-SOUTH CORRIDOR TRANSMISSION REINFORCEMENT Government of Alberta Response to the Critical Transmission Review Committee Report February 23, 2012 Alberta s Electricity Transmission

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

Excavation Marking and Dig Safely NY Procedure

Excavation Marking and Dig Safely NY Procedure 6 Environment, Health & Safety Services Excavation Marking and Dig Safely NY Procedure Document No: SA-024-A Revision No: 00 Date: 6/2/08 Approved By: See Page 6 Table of Contents 1.0 Purpose... 1 2.0

More information

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE14-00XXX Applicant: Job Description:

More information

[ sample ] Copyright 2014 by PEC Safety, Inc. First Edition, revised October 23, 2014

[ sample ] Copyright 2014 by PEC Safety, Inc. First Edition, revised October 23, 2014 Copyright 2014 by PEC Safety, Inc. First Edition, revised October 23, 2014 All rights reserved. Printed in the United States of America. Per the United States Copyright Act of 1976, no part of this publication

More information

EPCOR Distribution & Transmission Inc.

EPCOR Distribution & Transmission Inc. Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions December 19, 2016 Alberta Utilities Commission Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions Proceeding 22229 Application

More information

Our Shared Boundary. An Intermunicipal Development Plan for the Municipal District of Foothills and The City of Calgary

Our Shared Boundary. An Intermunicipal Development Plan for the Municipal District of Foothills and The City of Calgary Our Shared Boundary An Intermunicipal Development Plan for the Municipal District of Foothills and The City of Calgary Title: Our Shared Boundary - An Intermunicipal Development Plan for the Municipal

More information

Natural Gas Transmission Line SAFETY BULLETIN

Natural Gas Transmission Line SAFETY BULLETIN Natural Gas Transmission Line SAFETY BULLETIN At New Jersey Natural Gas (NJNG), safety is our top priority. Make it yours too. Join us as a Partner in Safety by following the important information in this

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Harvest Operations Corp.

Harvest Operations Corp. Decision 2014-214 Six-MW Power Plant Exemption July 21, 2014 The Alberta Utilities Commission Decision 2014-214: Six-MW Power Plant Exemption Application No. 1610444 Proceeding No. 3153 July 21, 2014 Published

More information

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan TES Industrial Development Lacombe County Outline Plan 112849297 June 2012 am v:\1128\active\112849297\07_reports_studies\rpt_tes_20120508.doc i Table of Contents 1.0 INTRODUCTION... 1 1.1 PURPOSE... 1

More information

Addison Natural Gas Project

Addison Natural Gas Project 0 Addison Natural Gas Project Addison County Regional Planning Commission November 14, 2012 Outline Vermont Gas The Addison Natural Gas Project Overview Route Design Town Benefits Route Sections ACRPC

More information

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013 Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013

More information

Accompanying this letter are three documents with further information about the project and BowArk s public involvement:

Accompanying this letter are three documents with further information about the project and BowArk s public involvement: BowArk Energy Ltd. Suite 0 Devon Tower 00 Ave SW Calgary, Alberta, TP H (0 - www.bowark.com March 0, 0 RE: Lanfine Wind Power Project Dear neighbour, My name is Keith Knudsen, and I am the lead developer

More information

ATCO HEARTLAND GENERATING STATION PHASE 2

ATCO HEARTLAND GENERATING STATION PHASE 2 ATCO HARTLAND GNRATING STATION PHAS 2 Project Information Package August 2015 Conceptual drawing of ATCO Heartland Generating Station with Phase 2 on the upper left Project Overview ATCO Power is proposing

More information

Jackfish 2 Project. Public Disclosure Document. August 2005

Jackfish 2 Project. Public Disclosure Document. August 2005 Jackfish 2 Project Public Disclosure Document August 2005 Table of Contents Introduction...1 Company Profile...2 Preliminary Project Description...2 The Plan...2 The Process...3 Facilities...3 Physical

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

ComEd Customer Requirements for An Underground Service

ComEd Customer Requirements for An Underground Service 1 st Edition /\n 1:xclon Company ComEd Customer Requirements for An Underground Service Thank you for your recent interest in new or revised underground electrical service. If you proceed with this project,

More information

SPRINGBANK Phase 1 Background Report

SPRINGBANK Phase 1 Background Report Phase 1 Background Report Table of Contents 1.0 CONTEXT... 4 CENTRAL ASP... 4 NORTH ASP... 4 MODDLE ASP... 5 2.0 PROJECT SCOPE... 5 3.0 PLANNING POLICY FRAMEWORK... 6 COUNTY PLAN (BYLAW C-7280-2013)...

More information

Works, services and infrastructure code

Works, services and infrastructure code 9.4.11 Works, services infrastructure code 9.4.11.1 Application (1) This code applies to assessable development identified as requiring assessment against the Works, services infrastructure code by the

More information

Aquatera Utilities Inc.

Aquatera Utilities Inc. Decision 2014-194 Aquatera Utilities Inc. 2.85-MW Power Plant June 26, 2014 The Alberta Utilities Commission Decision 2014-194: Aquatera Utilities Inc. 2.85-MW Power Plant Application No. 1610366 Proceeding

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

ESTIMATING THE COST OF PIPELINE TRANSPORTATION IN CANADA Eugène Karangwa, Transport Canada

ESTIMATING THE COST OF PIPELINE TRANSPORTATION IN CANADA Eugène Karangwa, Transport Canada ESTIMATING THE COST OF PIPELINE TRANSPORTATION IN CANADA, Transport Canada INTRODUCTION Pipeline transportation is an important sector in the Canadian economy. Canada is a major energy producer in the

More information

The Corporation of The City of London

The Corporation of The City of London The Corporation of The City of London Legislative Health and Safety Requirements The following is a health and safety guide for those providing a tender to assist in determining legislative health and

More information

Policy Direction for Alberta s Capacity Market Framework

Policy Direction for Alberta s Capacity Market Framework Policy Direction for Alberta s Capacity Market Framework August 15, 2017 Alberta Department of Energy Table of Contents Executive Summary... 1 1 Introduction... 2 2 Policy Direction for Alberta s Capacity

More information

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards

More information

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings G U I D E L I N E S F O R L A N D O W N E R S, D E V E L O P E R S A N D C O N T R A C T O R S T A B L E O F C O N T E N T S 1 Introduction 2 Office Locations/Map 3 General Requirements 4 Structures and

More information

Controlled Corporations

Controlled Corporations Controlled Corporations This technical document is part of a series of draft discussion papers created by Municipal Affairs staff and stakeholders to prepare for the Municipal Government Act Review. It

More information

PIPELINE EMERGENCY RESPONSE GUIDELINES

PIPELINE EMERGENCY RESPONSE GUIDELINES PIPELINE EMERGENCY RESPONSE GUIDELINES FOR SCHOOLS In the event of an actual or suspected pipeline release call 911 and Kinder Morgan Canada at 1.888.876.6711 If you see someone working or digging near

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Galore Creek Project Update Minerals North Conference April 2006

Galore Creek Project Update Minerals North Conference April 2006 NovaGold Resources Inc. Galore Creek Project Update Minerals North Conference April 2006 Drilling the Southwest Zone NovaGold Resources Inc. Galore Creek: Premier Cu-Au-Ag Porphyry in North America Demonstrated

More information

Auckland Transport Code of Practice 2013

Auckland Transport Code of Practice 2013 26 Corridor Access Management 26.1 Background Auckland Transport is the Road Controlling Authority and Corridor Manager for all public roads within the Auckland Region (except motorways and state highways

More information

GUIDE SPECIFICATION Los Angeles World Airports. xx xx xx CALM Review Procedures. CALM Element Background

GUIDE SPECIFICATION Los Angeles World Airports. xx xx xx CALM Review Procedures. CALM Element Background xx xx xx CALM Review Procedures CALM Element Background The CALM (Coordination and Logistics Management) Team s goal is to minimize construction-related impacts to passenger service and tenants while maintaining

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

Utility Locating Policy (Complying with Dig Safely NY)

Utility Locating Policy (Complying with Dig Safely NY) 6 Environment, Health & Safety Services Utility Locating Policy (Complying with Dig Safely NY) Document No: SA-024-A Revision No: 01 Date: 4/26//12 Approved By: See Page 5 Table of Contents 1.0 Purpose...

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Acoustic Monitoring of Large Diameter Water Transmission Mains - City of Ottawa Case Study

Acoustic Monitoring of Large Diameter Water Transmission Mains - City of Ottawa Case Study Acoustic Monitoring of Large Diameter Water Transmission Mains - City of Ottawa Case Study CERIU - INFRA - 2011 Stewart Day, PURE Technologies, Regional Manager- Canada Shelley McDonald, City of Ottawa,

More information

Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009

Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009 Alberta Transportation Gas Tax Fund and Public Transit Fund Outcomes Report December 2009 FINAL 1 Table of Contents Slide Number Executive Summary 3 Understanding the Outcomes Report 5 Measuring results

More information

Filing Plans and Specifications

Filing Plans and Specifications Upcoming Utilities Department Projects Anticipated To Have Plans and Specifications Filed August, September, October Report for Council Infrastructure Committee on 7-19-2016 Water and WPC Plant Projects

More information

ENVIRONMENTAL SCREENING REPORT

ENVIRONMENTAL SCREENING REPORT ENVIRONMENTAL SCREENING REPORT Pursuant to the Canadian Environmental Assessment Act (CEA Act) SCREENING SUMMARY TransCanada PipeLines Limited (TransCanada) is proposing to conduct a contaminant sampling

More information

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit 7.1 E-Permit and U-Permit Permit Description and Purpose The Excavation Permit (E-Permit) and the Utility Permit (U-Permit) are issued to allow construction,

More information

MOUNTAINEER XPRESS. Columbia Pipeline Group

MOUNTAINEER XPRESS. Columbia Pipeline Group MOUNTAINEER XPRESS Columbia Pipeline Group C169566.indd 1 TABLE OF CONTENTS CPG AT A GLANCE THE PLAN/PROJECT COMPONENTS COMMITMENT TO KEEPING YOU INFORMED PROJECT BENEFITS SAFETY FREQUENTLY ASKED QUESTIONS

More information

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS MARCH 2017 SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS 1.0 General A. All work activities within the SCRRA operating corridor and right-of-way, or work activities that

More information

NZQA registered unit standard version 3 Page 1 of 5

NZQA registered unit standard version 3 Page 1 of 5 Page 1 of 5 Title Operate the drill rig for horizontal directional drilling Level 3 Credits 15 Purpose People credited with this unit standard are able to: care for and maintain horizontal directional

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

SASKENERGY/TRANSGAS FORECAST FOR 2017 AND BEYOND THE SASKATCHEWAN OIL & GAS SUPPLY CHAIN FORUM

SASKENERGY/TRANSGAS FORECAST FOR 2017 AND BEYOND THE SASKATCHEWAN OIL & GAS SUPPLY CHAIN FORUM SASKENERGY/TRANSGAS FORECAST FOR 2017 AND BEYOND THE SASKATCHEWAN OIL & GAS SUPPLY CHAIN FORUM NOVEMBER 15, 2016 Derrick R. Mann, P.Eng. (Acting) Vice President Engineering, Integrity and Construction

More information

E.L. Smith Solar Farm Project Open House. Lower Level

E.L. Smith Solar Farm Project Open House. Lower Level E.L. Smith Solar Farm Project Open House Lower Level We are consulting you to share feedback and perspectives that we will consider in the planning and execution of this project. Who is epcor? Powering

More information

STATE OF VERMONT PUBLIC SERVICE BOARD

STATE OF VERMONT PUBLIC SERVICE BOARD STATE OF VERMONT PUBLIC SERVICE BOARD Docket No. 7970 Petition of Vermont Gas Systems, Inc., requesting a Certificate of Public Good pursuant to 30 V.S.A. 248, authorizing the construction of the Addison

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

Welcome. Public Information Event. Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study

Welcome. Public Information Event. Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study Welcome Public Information Event Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study Please sign in to be added to the study mailing list and receive

More information

ENVIRONMENT INDUCTION. Section 5

ENVIRONMENT INDUCTION. Section 5 ENVIRONMENT INDUCTION Section 5 1 Overview Environmental Legal Obligations Environment Policy Environmental Commitment InSitu Recovery (ISR) Mining Low Environmental Impact Monitoring and Reporting Environmental

More information

News and Views, by Anne Burke

News and Views, by Anne Burke News and Views, by Anne Burke Fluorescent Signs and Speed Bumps for School Zones There was a discussion between the City General Manager and Council about possibly replacing the signs on playgrounds areas

More information

Pipeline Rehabilitation

Pipeline Rehabilitation Pipeline Rehabilitation Profile The Velosi Group was formed in 1982 and has grown to become one of the world s most trusted specialists in Asset Integrity and HSE Solutions providing a comprehensive range

More information

STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA) FOR ENERGY SECTOR: CASE STUDY OF OLKARIA GEOTHERMAL EXPANSION PROGRAMME IN NAKURU COUNTY, KENYA.

STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA) FOR ENERGY SECTOR: CASE STUDY OF OLKARIA GEOTHERMAL EXPANSION PROGRAMME IN NAKURU COUNTY, KENYA. STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA) FOR ENERGY SECTOR: CASE STUDY OF OLKARIA GEOTHERMAL EXPANSION PROGRAMME IN NAKURU COUNTY, KENYA. Philip.J. Barasa Environmental Scientist Kenya Electricity Generating

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

Central Washington University

Central Washington University Central Washington University Excavation, Trenching and Shoring Program Plan prepared by: Central Washington University Office of Environmental Health & Safety 400 East University Way Ellensburg, WA 98926

More information

WELCOME! Mill Creek Daylighting Technical Feasibility Study. Thank you! Open House December Please sign in and get a comment form.

WELCOME! Mill Creek Daylighting Technical Feasibility Study. Thank you! Open House December Please sign in and get a comment form. WELCOME! Daylighting Technical Feasibility Study Open House December 2016 Please sign in and get a comment form. Thank you! WHAT IS DAYLIGHTING? Daylighting refers to the process of re-establishing creeks

More information

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling) INDEX 2 Company Profile 4 Technical Description 13 Organization Chart 6 Quality & HSE 19 Services Offered 8 Certification 22 COMPANY PROFILE Company Profile 4 Thrustboring Technology Contracting Company

More information

Presentation for Roads Australia Miller Street, Sydney 3 April creating public Pacific Highway delivering value for money

Presentation for Roads Australia Miller Street, Sydney 3 April creating public Pacific Highway delivering value for money Presentation for Roads Australia Miller Street, Sydney 3 April 2014 Legitimacy & Support creating public Pacific Highway delivering value for money Real sustainable development solutions in practice Public

More information

Bonnie Doon Grade Separation

Bonnie Doon Grade Separation 6. 2 Bonnie Doon Grade Separation Recommendation: That the April 18, 2017, Integrated Infrastructure Services report CR_4461, be received for information. Report Summary This report provides information

More information

VIRGINIA UTILITY PROTECTION SERVICE, INC. Title: Ticket Entry - Work Type List Working Document

VIRGINIA UTILITY PROTECTION SERVICE, INC. Title: Ticket Entry - Work Type List Working Document Printed copies are for reference only. Please refer to the electronic copy for the latest version. Purpose: To provide instructions for editing the work type list through Newtin administrator accounts

More information

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Electrical Work. NOV Embankments Over Swamps and Compressible Soils GENERAL & CONSTRUCTION S OPS GENERAL CONDITIONS OF CONTRACT NOV 2006 100 OPS General Conditions of Contract DIVISION 1 - GENERAL S 106 Electrical Work 120 180 The Use of Explosives General Specification

More information

development services strategic plan

development services strategic plan development services strategic plan 2016 2018 contents 4 Branch manager s message 6 what we do 12 role of the strategic plan 14 city vision 15 corporate strategy: the way ahead 16 department & branch

More information

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12 SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and

More information

192GasCatalog.

192GasCatalog. 192GasCatalog www.energyu.org www.midwestenergy.org 192-Abnormal Operating Conditions... 4 192-0101 Characteristics and Hazards of Natural Gas... 4 192-0201 Gas Detection and Alarm System Maintenance...

More information

Review Haelok District Heating Distribution Line WV Illighausen, Thurgau, Switzerland December 2015

Review Haelok District Heating Distribution Line WV Illighausen, Thurgau, Switzerland December 2015 Review Haelok District Heating Distribution Line WV Illighausen, Thurgau, Switzerland December 2015 Background: The dairy in Illighausen is to be supplied steadily with 95 C flow temperature hot water

More information

Bill 36, the Alberta Land Stewardship Act sets the bar for responsible regional planning

Bill 36, the Alberta Land Stewardship Act sets the bar for responsible regional planning April 27, 2009 Bill 36, the Alberta Land Stewardship Act sets the bar for responsible regional planning Proposed Act respects property rights and local decision-making Edmonton... Future development in

More information

Basic Service. This Section provides information regarding a. Introduction

Basic Service. This Section provides information regarding a. Introduction Basic Service Introduction This Section provides information regarding a new electric Basic Service for a single phase service less than or equal to 400 amps, and a three phase service less than 50kW.

More information

SITE WORK PRE-PLANNING AND SAFETY CHECKLIST

SITE WORK PRE-PLANNING AND SAFETY CHECKLIST Page 1 of 17 SITE WORK PRE-PLANNING AND SAFETY CHECKLIST Job No Project Name Date Company Representative(s) Other Representative(s) Safety and General Items Existing Site Conditions 1. Has existing site

More information

Telephone Lake project

Telephone Lake project Telephone Lake project Cenovus Energy Inc. is a Canadian oil company. We re committed to applying fresh, progressive thinking to safely and responsibly unlock energy resources the world needs. Our operations

More information

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55

John Hart Generating Station Replacement Project. January 2018 Community Construction Update Report #55 John Hart Generating Station Replacement Project January 2018 Community Construction Update Report #55 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email:

More information

NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE

NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE NATIONAL ENERGY BOARD PIPELINE PERFORMANCE MEASURES REPORTING GUIDANCE Amended November 2014 PIPELINE PERFORMANCE MEASURES - OVERVIEW Introduction The National Energy Board (Board) took action in March

More information

GTA West Transportation Corridor Planning and Environmental Assessment Study Stage 2. Community Workshop #2 June 2015

GTA West Transportation Corridor Planning and Environmental Assessment Study Stage 2. Community Workshop #2 June 2015 GTA West Transportation Corridor Planning and Environmental Assessment Study Stage 2 Community Workshop #2 June 2015 1 TODAY S AGENDA Study overview Update on project activities since PIC #1 Breakout sessions:

More information

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION INTRODUCTION By Dawn Tattle, P. Eng. Anchor Shoring & Caissons Ltd. TTC Yonge Station is the largest and most complicated of the

More information

Metro North Transmission Project Project Update October 2017

Metro North Transmission Project Project Update October 2017 Metro orth Transmission Project Project Update October 2017 Project Update Since October 2016, our focus has been on completing the necessary field work to help develop our preliminary design and preferred

More information

TECHNICAL PROCEDURE TABLE OF CONTENTS

TECHNICAL PROCEDURE TABLE OF CONTENTS TECHNICAL PROCEDURE No. Page DATE: 07/3/5 CATEGORY UNDERGROUND STRUCTURES SUBJECT OF SMUD s UNDERGROUND TRANSMISSION TABLE OF CONTENTS PURPOSE... 2 2 REFERENCES... 2 3 MINIMUM REQUIREMENTS... 2 4 RELATED

More information

PART 1: ROUTING UPDATE

PART 1: ROUTING UPDATE PART 1: ROUTING UPDATE TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PIPELINE CORRIDOR... 2 Page 2.1 Overview of Pipeline Corridor Selection and Optimization Process... 2 2.2 Environmental, Socio-Economic

More information

Grizzly Oil Sands ULC

Grizzly Oil Sands ULC Decision 2013-124 Algar Lake Project Distribution System Exemption March 28, 2013 The Alberta Utilities Commission Decision 2013-124: Algar Lake Project Distribution System Exemption Application No. 1609370

More information

Managing Growth and Development

Managing Growth and Development Managing Growth and Development This technical document is part of a series of draft discussion papers created by Municipal Affairs staff and stakeholders to prepare for the Municipal Government Act Review.

More information

ATCO PIPELINES APPLICATION TO CONSTRUCT AND OPERATE A NATURAL GAS PIPELINE Decision EDMONTON AREA Application No

ATCO PIPELINES APPLICATION TO CONSTRUCT AND OPERATE A NATURAL GAS PIPELINE Decision EDMONTON AREA Application No ALBERTA ENERGY AND UTILITIES BOARD Calgary Alberta ATCO PIPELINES APPLICATION TO CONSTRUCT AND OPERATE A NATURAL GAS PIPELINE Decision 2001-34 EDMONTON AREA Application No. 1055407 1 DECISION The Board

More information

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update United States Army Corps of Engineers Addicks and Barker Dam Safety Update COL Richard P. Pannell District Commander, Galveston District U.S. Army Corps of Engineers March 9, 2016 US Army Corps of Engineers

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS SECTION 334100 - STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY Section Includes: 1. Pipe and fittings. 2. Drain Basin. 3. De-chlorination tablet feeder. 4. Non-pressure transition couplings.

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD) ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING

More information

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT Notice NOTICE OF APPLICATIONS SHELL CANADA LIMITED QUEST CARBON CAPTURE AND STORAGE RADWAY FIELD ENERGY RESOURCES CONSERVATION BOARD APPLICATIONS NO. 1689376, 1670112, AND 1671615 ALBERTA ENVIRONMENT ENVIRONMENTAL

More information

Oil and Gas Development in Greeley, Colorado

Oil and Gas Development in Greeley, Colorado Oil and Gas Development in Greeley, Colorado Brad.Mueller@greeleygov.com Director, Community Development Department Location of Greeley Population 103,000 Same as Boulder County seat is Weld County Weld

More information