1 Porous Asphalt Pavements w/ Stone Recharge Beds Brandon Milar Executive Director California Asphalt Pavement Association SUSTAINABILITY Sustain the quality and quantity of our natural resources for use by future generations History of Porous Asphalt Pavements Porous asphalt mixes developed in 1930 s and 1940 s s by State DOTs Using mixes to reduce runoff in 1970 s Geotextiles developed in 1979 Current design process used since 1980 Projects Using Porous Asphalt Parking Lots Morris Arboretum Philadelphia, PA
2 Granite Curbing Diagram of infiltration bed at Morris Arboretum Access Isle Parking Bay Impervious Parking Bay Porous Asphalt Asphalt Porous Asphalt Granite Paving Paving Paving Curbing Recharge Bed Compacted Filter Fabric Compacted Uncompacted Subgrade Subgrade Subgrade Granite Band Granite Band Shared Medical Systems Malvern, PA 1982 Porous Pavement No maintenance treatments Densegraded Pavement Two maintenance treatments 2
3 University of Rhode Island Used in Low Temperature Environments Goals DuPont Barley Mills Office Complex Preserve Woodlands Porous Pavement w/ Groundwater Recharge Reduce Site Disturbance 3
4 Kaiser Medical Facility Modesto, CA 2005 Details Parking areas constructed using permeable pavements 50 acre site, 4 buildings, & 10 acres of pavements 4,400 tons of permeable asphalt Largest permeable asphalt project west of the Mississippi All runoff from site will be diverted to either permeable pavement parking structure or percolation basin = NO Surface Runoff leaves site Bike/Walking Paths 4
5 Swarthmore College School Yards Penn New School Philadelphia K8K Soccer Field underlain by Infiltration Bed Porous Asphalt Playfield Rain Gardens fed by Roof Leaders Urban setting 43 rd and Locust Roads 5
6 Highway Caltrans Open Graded Asphalt Developed in 30 s Used in CA since 40 s Used as surface for most highways in northern CA It does rain in Arizona Phoenix, AZ Arizona 8 Dense Graded HMA 7 Agg. Base 6 OGFC 6 ATPB 6 Open Graded AB Drainage Trench 18 Years Later 6
7 New Subdivision Pringle Creek Community Salem, OR Homes 32 Acres 5,400 of porous asphalt pavements Anticipate only 10% of normal runoff (roofs, streets, etc) will flow into Pringle Creek Oregon Subdivision Oregon Subdivision Press Release Recordbreaking rainfall throughout the month of November Many regional streets and sidewalks flooded. Subdivision cruised through the month without flooding due to the success of its stateof oftheart porous pavement or green street system Port Facilities 7
8 Port of Portland Auto Warehousing Company s Terminal 6 Port of Portland 35 Acres Infiltrate 100% of the stormwater saved $250,000 reducing permitting eliminated a stormwater system. Oregon APWA Julian Prize for Sustainability Technical Aspects Environmental Site Selection Design Materials Construction Maintenance Environmental Land Development Traditional Stormwater Management Effects on the Hydrologic Cycle Reduces Infiltration Increases Direct Runoff Increases Pollutants Control Peak Rate of Runoff after Development to PreDevelopment Rate Detention Basins Temporary Storage Sediment Control Does Not Address Increase in Volume of Runoff 8
9 BASE FLOW Reduction in Runoff Volume Accounts for stream flow 11 months/yr. Comprises more than 60% of total annual flow 9
10 Flood & Draught Opposite Sides of Same Coin Comparison of Detention vs. Infiltration Design Systems 4 3 PostDev. Inflow Infiltration Bed Discharge PreDevelopment Runoff Detention Basin Discharge Flow (cfs) Time Polutant Removal Effic Site Selection 0 20 Total Phosphorus Soluable Phosphorus Total Nitrogen Nitrate Zinc TSS Infiltration Wetlands Wet Ponds Filtering Swales Dry Ponds 10
11 Project Location Soil permeability/infiltration rate EPA recommends 0.5 /hour 0.1 /hour still OK Depth to bedrock > 2 2 Depth to high water > 3 3 Fill not recommended Frost Pavement section should exceed frost depth? Soils Investigation Borings and/or test pits Test permeability Determine depth to high water table Determine depth to bedrock OpenGraded HMA What are Porous Asphalt Pavements? Design ½ Aggregate Clean Uniformly Graded 2 3 Crushed Agg. (#2) 40% Voids NonWoven Geotextile Uncompacted Subgrade Surface Features Slope limit surface slope to 5% Terrace when necessary Use conventional HMA for steeper slopes Provide alternative way for water to enter bed Stone edge provides alternative path for water to enter bed if pavement sealed or plugged 11
12 Other Runoff Sources Use to infiltrate from other impervious surfaces Avoid piping water long distances Spread infiltration over largest area possible 5:1 Impervious: Infiltration Bottom Must Be Flat Minimize excess stone Recharge Bed Wasted Stone Maximize infiltration area Recharge Bed Stormwater Design Regulations Rainfall Typical designs for 6 month/24 hr storm Conservative design for 20 year/24 hr storm range from 1.4 to 15 in./24 hr. Meet Local & State wastewater mitigation requirements. Less infiltration area at low depths Calculate Detention Basin Required Design Storm: 4 4 / 24 hr. (NOAA) Infiltration Rate: 0.05 / hr. (soil type) Water Table: 10 Total Surface Area: 20 acres Permeable Pavement: 5 acres Available storage: 40% voids in rock bed Design Requirements Infiltration: 1.2 / 24 hr. Detention Required: 4 over 20 acres equals 16 over 5 acres 16 less 1.2 equals 14.8 / 24 hr. Depth of detention basin: 14.8 / 0.4 equals minus equals >
13 Design Considerations Site Plan Mix & Match Pavement Types High traffic areas Loading docks Truck access Entrances Islands/planters Pavement Use Considerations Primary use Parking lots Roads w/ little cut or fill Roads/Highway Challenges Cuts and fills Slope Variable soil conditions Utilities Limited use Materials Clean/Washed 1 ½ 3 grading Passing ¾ sieve < 5% Crushed material Ideally 90% 2 fractured faces CT 205 Consideration for local materials Aggregates Fractured Face A fractured face is an angular, rough or broken surface of an aggregate A fractured face shall be determined a fractured face only if the projected surface area of the fractured face is at least 25 % of the largest crosssectional area of the aggregate. 13
14 Crushed Aggregate? How many fractured faces? Porous Asphalt Open Graded Asphalt Concrete (OGAC) Not ATPB Utilize Caltrans Specification Standard Specification Section 39 ½ or 3/8 Gradation (1 gradation is also available) Method specification for compaction Caltrans Mix Design Procedure CT 368 OBC determination for OGAC Drum Mix Production Drum Drier Batch Plant Production Screen Deck 14
15 Key Mix Properties open gradation Increased permeability >18% air voids OBC = optimum bitumen content Pavement durability Draindown Constructability Maintain proper film thickness Prepare OGAC samples at various binder contents (0.7%, ABR, +0.7%) Place sample in thimble Measure amount of asphalt drained when specimen reaches room temperature Graph results OBC is asphalt content at 4.0g CT 368 Sec 39 Gradation Power 0.45 Curve Sieve ¾ ½ 3/8 #4 #8 #16 #200 ½ Gradation Proposed OR X±4 X±4 X± CC X±7 X±7 X± /8 Gradation Proposed OR X±4 X± CC X±7 X± Open Grade vs. Dense Grade Dense Grade AggAgg Contact Low void content High Stability 15
16 Open Grade AggAgg contact High void content Good stability when confined Binder Selection Conventional (PG xxxx) xx) Standard binders used in most California paving PG 6410 in Central Valley Polymer Modified (PG xxxx PM) Improved performance in cooler climates Improved performance in high traffic Resistance to thermal cracking Improves constructability in cold weather Binders with Ground Tires Asphalt Rubber (RACO) Uses tires Good resistance to cracking Improved durability Rubber Modified (PG xxxx TR) Uses tires Blended at a refinery Performance similar to polymer modified Construction Construction Scheduling Plan to build late in construction process Wait till dirty work is done Wait till vegetation is established Or keep runoff controls in place until established Can excavate bed to about 1 1 above planned elevation and use for SW control Excavate to plan elevation when ready PreConstruction Meeting Include Engineers, Designers, Inspectors, Contractor Personnel, Material Suppliers, Testing Personnel Shared understanding of construction process (minimize failures) 16
17 Protect the Surface Bed Excavation Excavate bed to plan elevation using equipment w/ soft footprint Don t t compact subgrade Nonwoven Geotextile Spread geotextile immediately after fine grading Overlap fabric >16 Install drainage pipes if used Excess fabric (>4 ) folded over agg.. later Stone Recharge Bed Place clean, single size, washed aggregate. Do not drive trucks on fabric Spread and grade with tracked equipment 8 8 lifts. Light compaction static Protect pipes Choker Course Place Choker course ½ clean washed aggregate. Purpose to lock up surface for stable paving platform 1 2 thick Grade and compact Static Fold excess fabric over stone to prevent contamination Paving Recommend track paver Avoid truck movement over agg. Stability may be issue Avoid disturbing agg surface but it will happen Production will be less Mix between 200 F F and 250 F F when placed 17
18 Limit hand work during paving operations Reduces mix temperature Difficult to work with modified binders Can reduce permeability Paving Static compaction 1 to 2 passes 8108 ton steel wheel roller Less stable than thin OGFC May have to let cool some Compaction After Compaction Limit traffic for 24 hours to allow to set up Keep sediment control in place till vegetation established Maintenance Maintenance Strategies Use porous or dense asphalt for patching If using dense, repair should not exceed 10% of total porous pavement paved area Cracks can be repaired using crack sealant Regular cleaning (min twice a year) Flush or jet wash Vacuum sweeping Maintenance DON Ts Do NOT use traditional seal coat treatments Do not use salt or sand for deicing Salt can contaminate groundwater infiltration Sand can reduce permeability 18
19 Absolutely!!! Recycling OGAC can be processed and reused in new pavements Aggregate in bed can be processed and reused OGAC can include recycled asphalt Limit to 15% maximum RAP in total mix Research ongoing to increase % Costs Cost & Availability Asphalt portion similar to conventional HMA Gravel bed costs more than conventional subsurface construction Significant savings when accounting for: Permitting Conventional storm water management techniques Availability Caltrans OGAC regularly available throughout State Considered a specialty mix Aggregate availability can be an issue in certain locations Consideration for local sources Are There Limitations to Porous Asphalt Pavements? 19
20 Where not to use Strategy for Water Quality Slopes greater than 6% Consider terracing Locations where a likelihood of a spill is real Consider a filtration or wetland treatment prior to infiltration 40" 48" TO WATER TABLE DIRECT RAINFALL OPEN EDGE DRAIN H20 RATED CAST RUNOFF IF IMPERVIOUS IRON GRATE 2" x 6" RECTANGULAR EMERGENCY OVERFLOW SLAG RETENTION BED (3) 1" Ø ORIFICE(S) WATER QUALITY SWALE ROOF LEADERS SHOULD BE EXTENDED INTO THE RETENTION BED WHERE POSSIBLE Asphalt Pavement Resources Overview of the asphalt industry Additional information on porous asphalt Electronic copy of today s s presentation Technical publications on asphalt paving Caltrans Specifications Caltrans construction standard specifications Section 39 for OGAC Caltrans test methods CT368 mix design for OGAC CT205 determination of crushed materials m OGAC & RAC Usage Guides 20
Presentation to the 60 th Annual NJ Asphalt Paving Conference March 14, 2017 Ewing, NJ
Presentation to the 60 th Annual NJ Asphalt Paving Conference March 14, 2017 Ewing, NJ James J. Purcell, PE, PMP Technical Director, New Jersey Asphalt Pavement Association Reduce impervious surface Recharge
More information4.8. Subsurface Infiltration
4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration
More information4.8. Subsurface Infiltration
4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration
More informationBRADLEY UNIVERSITY. The Performance and Sustainability of Permeable Pavement Progress Report on the Work Performed Under IAPA Scholarship
BRADLEY UNIVERSITY The Performance and Sustainability of Permeable Pavement Progress Report on the Work Performed Under IAPA Scholarship Anne Riemann 12/19/2016 1 INTRODUCTION Permeable pavement is an
More informationCONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL
CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard
More informationBMP 6.4.4: Infiltration Trench
BMP 6.4.4: Infiltration Trench An Infiltration Trench is a leaky pipe in a stone filled trench with a level bottom. An Infiltration Trench may be used as part of a larger storm sewer system, such as a
More informationReview of State and Federal Stormwater Regulations November 2007
Review of State and Federal Stormwater Regulations November 2007 By: James T. Spaulding, PE, CPESC Joseph M. Ducharme, Jr., PE TTG ENVIRONMENTAL CONSULTANTS, LLC 27 LOCKE ROAD, CONCORD, NH 03301-5301 TELEPHONE:
More informationModule 10b: Gutter and Inlet Designs and Multiple Design Objectives
Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of
More informationPERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers
4.1-a PERVIOUS PAVEMENT Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers DESCRIPTION Pervious pavement is any system comprised of a load bearing surface that allows for movement of
More informationthe 2001 season. Allison brought high winds and street flooding to Houston, after
Module 10b: Gutter and Inlet Designs and Multiple Design Objectives Bob Pitt University of Alabama and Shirley Clark Penn State Harrisburg Evening traffic plows through high water at the intersection of
More informationBoise City Public Works General Drainage Plan Review Requirements Checklist
Boise City Public Works General Drainage Plan Review Requirements Checklist Development Name Bldg. Permit # Drainage Reviewer Site Address Initial Review Date ODI Number Designer Company Name Treated Acres
More informationDRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016
DRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016 INTRODUCTION Storm water management is a challenge facing our ever expanding
More informationA Case for the Design and Modeling of BMP Infiltration and LID Techniques. By: Bob Murdock
A Case for the Design and Modeling of BMP Infiltration and LID Techniques 2009 IAFSM Annual Conference 2009 IAFSM Annual Conference By: Bob Murdock Presentation Outline 1. Runoff Reduction (RR) and Low
More informationSUBSURFACE INFILTRATION SYSTEM DESCRIPTION. Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields
4.1-d SUBSURFACE INFILTRATION SYSTEM Alternative Names: Sump, Drywell, Infiltration Trench, Infiltration Galleries, Leach Fields BMP DESIGN APPROACH Pollutant Source Control Hydrologic Source Control Stormwater
More informationPERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231.
DRIVEWAYS, DRIVEWAYS & PATIOS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - CHARACTERISTICS CSA A231.2 TECHO-BLOC Compressive strength 50 MPa [7200 psi] min. 50 MPa [7200 psi] min. Absorption - 5 % max. Freeze-thaw
More informationPERMEABLE INTERLOCKING PAVERS
PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement
More informationPavement Design. TTP Orientation Seminar 2017
Pavement Design TTP Orientation Seminar 2017 What are Pavements? Engineered structures in contact with the earth's surface built to facilitate movement of people and goods Pedestrians Personal vehicles
More informationPennsylvania Stormwater Best Management Practices Manual
Pennsylvania Stormwater Best Management Practices Manual Presented by the Pennsylvania Department of Environmental Protection Bureau of Watershed Protection In cooperation with: Cahill Associates Environmental
More informationConstruction Best Management Practices Handbook BEST MANAGEMENT PRACTICES
Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN
More informationParaprofessional Training Session 1
Paraprofessional Training Session 1 Part 2: Stormwater Basics November 26, 2012 Rutgers University, Cook Campus Christopher C. Obropta, Ph.D., P.E. Extension Specialist in Water Resources Associate Professor
More informationStanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings
SECTION 32 12 36 SEAL COATS PART 1 GENERAL 1.1 RELATED WORK A. Section 31 10 00: Site Preparation B. Section 32 12 00: Flexible Paving C. Section 32 17 23 01: Traffic Striping and Pavement Markings 1.2
More informationInfiltration Guidelines
Appendix E Infiltration Guidelines As a stormwater management method, infiltration means retaining or detaining water within soils to reduce runoff. Infiltration can be a cost-effective method to manage
More informationStormwaterWise Landscapes: Pervious Surfaces Specifications
StormwaterWise Landscapes: Pervious Surfaces Specifications Purpose & Benefits Stormwater runoff reduction High pollutant removal Control localized drainage problems Attractive alternative for walkways
More informationINTERLOCK BETWEEN PARTICLES AT EACH PERFORATION
for Storm Water Management RUN OFF CONTROLS Porous Parking & Vehicle Access Cellular Confinement Systems (CCS) A Cellular Confinement System (CCS) is an engineered, expandable, polyethylene, honeycomb-like
More information4-07 Asphalt Treated Permeable Base (ATPB)
1 1 0 1 0 1 Supplement Division with the following: (November 0,, APWA GSP) -0 Asphalt Treated Permeable Base (ATPB) -0.1 Description Asphalt treated permeable base (ATPB) consists of a compacted course
More information2.1 Backfill - General
2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately
More informationDefinition of HMA. In simple terms :
Hot Mix Asphalt 101 Definition of HMA In simple terms : A mixture of asphalt binder and graded mineral aggregate, mixed at an elevated temperature and compacted to form a relatively dense pavement layer
More informationA Contractor s Look at the Changing World of Asphalt Technology
Staying Arizona a step Pavements/Asphalt ahead: Conference A Contractor s Look at the Changing World of Asphalt Technology 2012 Arizona Pavement/Materials Conference Adam J.T. Hand, PhD, PE Granite Construction
More informationAt least 2 feet above the seasonal high water table Overflow path or structure provided
General Conditions Map of proposed subwatershed to each subbasin, including total area and CN Design Flow or Design Volume to each STF, as appropriate Operation and Maintenance instructions for each STF
More informationCost Considerations of Asphalt Rubber Hot Mix
Cost Considerations of Asphalt Rubber Hot Mix Gene R. Morris, P.E. International Surfacing, Inc. Kent R. Hansen, P.E. International Surfacing Inc. MATERIAL DESCRIPTION AND PROPERTIES Asphalt-rubber (A-R)
More informationBASE CONSTRUCTION MATERIALS A Aggregate
BASE CONSTRUCTION 2211 AGGREGATE BASE 2211.1 DESCRIPTION This work consists of placing aggregate base. 2211.2 MATERIALS A Aggregate... 3138 Provide the class of aggregate as required by the contract. 2211.3
More informationRhode Island Stormwater Design and Installation Standards Manual
Rhode Island Stormwater Design and Installation Standards Manual Public Workshop Infiltration (Including Permeable Paving) March 24, 2011 Infiltration Section 5.3: Appendix F.3 & H.1 Approved WQ BMPs Infiltration
More informationEvaluation of Structural Performance of Pervious Concrete in Construction
International Journal of Engineering and Technology Volume 2 No. 5, May, 2012 Evaluation of Structural Performance of Pervious Concrete in Construction S.O. Ajamu 1, A.A. Jimoh 2, J.R. Oluremi 1 1 Department
More informationDATE: December 10, 2012 REPORT NO. PW CHAIR AND MEMBERS COMMITTEE OF THE WHOLE OPERATIONS AND ADMINISTRATION
PUBLIC WORKS COMMISSION DATE: December 10, 2012 REPORT NO. PW2012-073 TO: FROM: CHAIR AND MEMBERS COMMITTEE OF THE WHOLE OPERATIONS AND ADMINISTRATION GEOFF RAE, MBA, P.ENG. GENERAL MANAGER, PUBLIC WORKS
More informationMunicipal Stormwater Ordinances Summary Table
APPENDIX F Municipal Ordinances Summary Table Municipality Abington Bryn Athyn Borough Hatboro Borough Ordinance, SALDO Runoff equals pre post Erosion Sediment Control Water Quality Requirements Any which
More informationSECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS
SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS The City of Blue Springs hereby adopts Section 2200 of the Kansas City Metropolitan Chapter of APWA Construction and Material
More informationThin Asphalt Overlays for Pavement Preservation
Thin Asphalt Overlays for Pavement Preservation Mid-Year Asphalt Pavement Technical Seminar Sponsored by Flexible Pavements of Ohio Defining a Thin Asphalt Overlay? Thin overlays are typically 1 ½ inch
More informationPennsylvania Stormwater Best Management Practices Manual. Chapter 3. Stormwater Management Principles and Recommended Control Guidelines
Pennsylvania Stormwater Best Management Practices Manual Chapter 3 Stormwater Management Principles and Recommended Control Guidelines 363-0300-002 / December 30, 2006 Chapter 3 Stormwater Management Principles
More information2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL
SECTION 321200 - PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. The Contractor for this work shall be held to have read all of the Bidding Requirements, the Proposal Forms, the General Conditions of
More information4.2 Permeable Pavement Systems
4.2 Permeable Pavement Systems Permeable Pavement provides the structural support of conventional pavement, but allows stormwater to drain directly through the surface into the underlying stone base and
More informationDRAINAGE DESIGN AND RUTTING PERFORMANACE GUIDELINES FOR PERMEABLE PAVEMENT
DRAINAGE DESIGN AND RUTTING PERFORMANACE GUIDELINES FOR PERMEABLE PAVEMENT by Su Ling Cao Daryl Poduska Graduate Assistants Dan G. Zollinger Associate Professor Sponsored by The Uni-Group U.S.A. The Department
More informationBMP #: Infiltration Basin
Structural BMP Criteria BMP #: Infiltration Basin An Infiltration Basin is a shallow impoundment that stores and infiltrates runoff over a level, subtle, uncompacted, (preferably undisturbed area) with
More informationCATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE
3.33' 3.0' 2.0' 4.33' 4.0' 3.0' 1.00' TO BACK OF CURB LINE TOP OF GRATE ELEV. - SEE PLAN NEENAH CASTING R-3067-V OR AS NOTED ON PLANS. "INFA-SHIELD" SEAL OR EQUAL. RINGS (2 MIN., 1' MAX. OF RINGS AND MORTAR).
More informationE. STORMWATER MANAGEMENT
E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson
More information2011 Guidance Manual for Development Stormwater Quality Control Measures
CITY OF MODESTO STORMWATER MANAGEMENT PROGRAM 2011 Guidance Manual for Development Stormwater Quality Control Measures Prepared for NPDES Permit No. CAS083526; Order R5-2008-0092 This page intentionally
More informationDIVISION 32 EXTERIOR IMPROVMENTS
DIVISION 32 EXTERIOR IMPROVMENTS DIVISION 32 EXTERIOR IMPROVEMENTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
More informationStormwater Volume and Treatment Methods Simplifying the Numbers. IAFSM March 10, Presented by: Tom Powers P.E., CFM, LEED AP, CPESC
Stormwater Volume and Treatment Methods Simplifying the Numbers IAFSM March 10, 2011 Presented by: Tom Powers P.E., CFM, LEED AP, CPESC Introduction GOALS: Improve understanding of Rate and Volume (Quantity)
More informationBIO-AQUIFER STORM SYSTEM
BIO-AQUIFER STORM SYSTEM Specifications for Construction PART 1 GENERAL 1.01 SECTION INCLUDES A. Providing labor, materials, tools and equipment to furnish and install a permeable concrete paving stone
More informationStorm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
More informationCRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING
Guide Specification CRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING COORDINATE WITH DRAWINGS: Show location and extent of stabilized aggregate surfacing. Show details required at adjoining
More informationStorm Drain Inlet Protection for Construction Sites (1060)
Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain
More informationRichland County Department of Public Works Engineering (Land Development) Division
Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or
More informationHydraPressed Slabs. Yorkstone Tan. Wherefunctionmeetsstyle
HydraPressed Slabs Yorkstone Tan Wherefunctionmeetsstyle Texada This series is named after the rugged and beautiful Gulf Islands of the Pacific Northwest. Texada HydraPressed Slabs have a light shot-blast
More informationAsphalt Guidelines. Courtney Rousseau, P.E. Lloyd Consulting Group, LLC
Asphalt Guidelines Courtney Rousseau, P.E. Lloyd Consulting Group, LLC Objectives Review typical asphalt sections and other key components to ensure optimal material usage for your project Review hot mix
More informationN.J.A.C. 7:8 Stormwater Management Rules - Design and Performance Standards. Nonstructural Strategies Assist with Strategy #2; See Page 3
9.3 DRY WELLS Dry wells are subsurface stormwater facilities that are used to collect and temporarily store runoff from clean rooftops; runoff is discharged through infiltration into the subsoil. Dry wells
More informationBackground / Regulatory Requirements
Chapter 2 Background / Regulatory Requirements This Chapter summarizes the impacts of development on stormwater quality and quantity and explains the postconstruction stormwater control requirements for
More informationNova Scotia 2009 Pavement Preservation. Jim Chisholm Highway Construction Services
Nova Scotia 2009 Pavement Preservation Jim Chisholm Highway Construction Services 2009 Construction Overview Pavement Preservation Hot Mix Asphalt Overlays Cold in Place Recycling Pulverization/Graveling/HMA
More informationSECTION EROSION AND SEDIMENTATION CONTROLS
SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL
More informationSECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS
SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS Section Page 19-1 TRENCH EXCAVATION...19.1 19-1.01 Exploratory Excavation...19.1 19-1.02 Trench Width...19.1 19-1.02.A Storm Drain
More informationSand Filter T-6. Description. Site Selection
Description A sand filter is a filtering or infiltrating BMP that consists of a surcharge zone underlain by a sand bed with an underdrain system (when necessary). During a storm, accumulated runoff collects
More informationPorous Pavements in Cold Climates Part 1: Design, Installation, and Maintenance
Porous Pavements in Cold Climates Part 1: Design, Installation, and Maintenance A Green Infrastructure, Green Jobs, and Green Funding Workshop Onondaga Environmental Institute March 2011 Robert Roseen,
More informationSTORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW
SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission
More information6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff
October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design
More informationLS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION
LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete
More informationBioswales, Wetlands, and Trees: How going green can be a part of a Wet Weather Management Plan. Presented by Brian Tornes, PE
Bioswales, Wetlands, and Trees: How going green can be a part of a Wet Weather Management Plan Presented by Brian Tornes, PE Water Management It all Contributes to the Streams Sanitary Sewers Storm Sewers
More informationPennsylvania Stormwater Best Management Practices Manual. Section 3 Stormwater Management Principles, Goals, and a Management Model
Pennsylvania Stormwater Best Management Practices Manual DRAFT - JANUARY 2005 Section 3 Stormwater Management Principles, Goals, and a Management Model This page intentionally left blank. Section 3 Stormwater
More informationSECTION ASPHALT PAVING
SECTION 32 12 16 SPEC WRITER NOTE: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section
More informationMaterials for Civil and Construction Engineers
Materials for Civil and Construction Engineers CHAPTER 9 Asphalt Binders and Asphalt Mixtures Bituminous Materials Asphalt Natural or Refined from petroleum oil Tar Asphalt Cement Cutback Emulsion 2 Source
More information16.0 Water Quality Management Criteria for Developed Land
October 2003, Revised February 2005 Criteria for Developed Land Page 1 16.1 Introduction 16.0 Water Quality Management Criteria for Developed Land Stormwater quality control is an integral part of any
More informationProduct Catalogue. Not intended for design layouts; refer to the appropriate StormTech Design Manual for specific chamber design information.
Product Catalogue Not intended for design layouts; refer to the appropriate Design Manual for specific chamber design information. Subsurface Stomwater Management Specifications and Product Comparison
More informationHighway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination
Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse
More informationA Summary of the International Stormwater BMP Database
A Summary of the International Stormwater Tuesday, February 12, 2013, 1:00PM Presented by: Katie Blansett, Ph.D., P.E. Pennsylvania Housing Research Center www.engr.psu.edu/phrc Objective The objective
More informationOutline of Presentation. Inspecting Construction Site BMPs. Inspector. Back to Basics. Erosion Control. Erosion Control
Inspecting Construction Site BMPs Kristin Kerr EOA, Inc. Outline of Presentation Back to Basics Erosion and Sediment Control Good Site Non-Stormwater Run-on and Run-off Control Construction Inspection
More informationUrban Rainwater Harvesting Systems: Promises and Challenges
TheWaterChannel Webinar #5 Urban Rainwater Harvesting Systems: Promises and Challenges By Vishwanath S Zenrainman@gmail.com www.ircsa.org www.rainwaterclub.org Thanks for coming. The webinar will begin
More informationProject Name: Add a unique name that appropriately identifies the submission
PTAPP Online Municipal Tracking Tool Instructions Project Name: Add a unique name that appropriately identifies the submission Municipal Project: Check this box if the project is part of municipal efforts
More informationTHIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION
THIN ASPHALT OVERLAYS FOR PAVEMENT PRESERVATION Why Thin Asphalt Overlays? Shift from new construction to renewal and preservation Functional improvements for safety and smoothness are needed more than
More informationSECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1
CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1
More informationSECTION AGGREGATES
SECTION 32 05 00 AGGREGATES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Aggregate base 2. Engineered fill 3. Backfill 4. Fine filter aggregate (non-frost susceptible fill) 5. Riprap 6. Recreational
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish
More informationConstruction Specification for Concrete Unit Pavers
Engineering & Construction Services Division Standard Specifications for Road Works TS 3.80 September 2017 for Concrete Unit Pavers Table of Contents TS 3.80.01 SCOPE... 2 TS 3.80.02 REFERENCES... 2 TS
More informationStormwater Pollution: A City Problem with Backyard Solutions
Stormwater Pollution: A City Problem with Backyard Solutions RI Residential Rain Garden Training Program March 31 and April 1, 2011 Roger Williams Park Botanical Center Providence RI Lorraine Joubert URI
More informationStormwater Local Design Manual For Houston County, Georgia
Stormwater Local Design Manual For Houston County, Georgia Adopted November 15, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 2 2.1. DETENTION REQUIREMENTS... 2 2.1.1.
More informationCity of Wheat Ridge Site Drainage Requirements
City of Wheat Ridge Site Drainage Requirements I. INTRODUCTION Purpose The City of Wheat Ridge ( the City ) has specific Site Drainage Requirements that must be followed by proposed developments or re-developments.
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular
More informationHP and RG POLYMERIC SANDS for PAVEMENT JOINTS
TECHNICAL DATA SHEET HP and RG POLYMERIC SANDS for PAVEMENT JOINTS 66 lb. Choice of colors Tan / Ochre Grey UPDATE November 24, 2006 Make sure that you have an up-to-date technical data sheet at hand.
More informationPavement Design. TTP Orientation Seminar 2011
Pavement Design TTP Orientation Seminar 2011 What are Pavements? Engineered structures in contact with the earth's surface built to facilitate movement of people and goods Pedestrians Personal vehicles
More informationPavement Maintenance Best Practices. Thomas J. Wood
Pavement Maintenance Best Practices Thomas J. Wood Agenda Why pavement maintenance / preservation is important Dealing with cracks When to apply a surface treatment Fog Sealing Micro Milling UTBWC Thin
More informationBMP #: Water Quality Inserts
Structural BMP Criteria BMP #: Water Quality Inserts Catch basin inserts are commercially available (manufactured) devices and are generally configured to remove one or more of the following contaminants:
More informationOur Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it?
Our Eastern Shore Groundwater Part IV Groundwater Quality on the Eastern Shore: How safe is our groundwater and are there ways we can protect it? Britt McMillan, Malcolm Pirnie, Inc. Mercury Venus Mars
More informationADOT s Use of RAP in Asphaltic Concrete
ADOT s Use of RAP in Asphaltic Concrete Updated & Presented by: Nye McCarty, P.E. Originally prepared by: Chad Auker & Scott Weinland ADOT Construction-Materials Group Overview ADOT s Existing RAP Specification
More information3/28/2016 APWA-WA CONSTRUCTION MATERIALS COMMITTEE. SPEAKERS: Cody R. Hart, P.E. Jessica Knickerbocker, P.E.
APWA-WA CONSTRUCTION MATERIALS COMMITTEE SPEAKERS: Cody R. Hart, P.E. Jessica Knickerbocker, P.E. 1 Committee Organization The Construction Materials Subcommittee for APWA-WA has two cochairs. Cody R.
More informationA Design Review of Waterproofing Codes
A Design Review of Waterproofing Codes Section 1807 of Chapter 18 of the International Building Code addresses waterproofing under the section title of Dampproofing and Waterproofing. The section defines
More informationUnderstanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More information7/16/2012. Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices
Post Construction Best Management Practices (PCBMPs) Article VIII: Post Construction Best Management Practices Presented by Jennifer Boyer DuPage County DEC Includes BMPs intended to provide volume control
More informationMODEL Stormwater Local Design Manual. City of Centerville
MODEL Stormwater Local Design Manual City of Centerville Adopted December 6, 2005 TABLE OF CONTENTS 1. FORWARD... 1 2. GENERAL LEVEL OF SERVICE STANDARDS... 1 2.1. DETENTION REQUIREMENTS... 1 2.1.1. Discharge
More informationIntegrating Structural and Hydrologic Design in Permeable Pavement David R. Smith Technical Director Interlocking Concrete Pavement Institute
Integrating Structural and Hydrologic Design in Permeable Pavement David R. Smith Technical Director Interlocking Concrete Pavement Institute 2010 Concrete Sustainability Conference 1 National Ready Mixed
More informationConcrete Waste Management
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationStream Channelization, Before and After ACB Installation
An information series from the national authority on concrete masonry technology ARTICULATING CONCRETE BLOCK FOR EROSION CONTROL TEK 11-09B Articulating Concrete Blocks (ACBs) (2011) INTRODUCTION An articulating
More informationUMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist
UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from
More informationAttachment D-1: Civil/Structural Scope of Work
Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,
More information