DISTRIBUTION STORM HARDENING AND RESILIENCY. Matt Shellenberger, P.E. American Electric Power
|
|
- Phebe Horton
- 6 years ago
- Views:
Transcription
1 DISTRIBUTION STORM HARDENING AND RESILIENCY Matt Shellenberger, P.E. American Electric Power
2 AMERICAN ELECTRIC POWER
3 DEFINITIONS» Hardening: improves the durability and stability of infrastructure to withstand the impacts of severe weather events with minimal damage EEI Before and After the Storm, January 2013» Resiliency: measures do not prevent damage; rather they enable facilities to continue operating despite damage and/or promote a rapid return to normal operations EEI Before and After the Storm, January 2013
4 THE CURRENT REALITY» High customer expectations for good reliability and short duration outages» Regulatory / political scrutiny has increased» Increased frequency of the biggest storm we ve ever had» Significant direct and societal costs for storm outages
5 EVENT TYPES TO HARDEN AGAINST» Wind above 60 mph Wind blows trees into line causing: conductor and pole failure Aeolian vibrations; galloping conductor; Tropical Storms and Category 1 Hurricanes (74-95 mph) Straight line winds (i.e. Derecho; down bursts ; etc.)» Ice & Snow precipitation Ice and heavy wet snows cause loads exceeding design criteria Ice load breaks conductors and poles, as well causing trees to fall onto the system Snow load primarily impacts trees near the system (and to the system, by extension)
6 SYSTEM LEVEL ACTIONS» Execute basic reliability / asset programs Cyclic vegetation management program in all locations Asset / Reliability Programs Circuit inspection & repair of deteriorated material & equipment Visual, EMF, Infrared inspection methods Sectionalizing improvement on all single & three phase Cyclic pole inspection / treatment / replacement Target aged poles Replacement of small wire (#4 and smaller) Basic infrastructure maintenance programs, consistently executed improve reliability.
7 DESIGNING BEYOND NESC» Increase the ice load (NESC rule 250 B) while holding the design tension fixed.» Grade B overload factors vs. increase ice loading.
8 LD-PRO 10 BUTTON MODE» Used Phase 2 to define the new Zone load conditions (NESC 250B).» Determine limiting spans in Phase 5 and Phase 6.» Design in Phase 9p and determine costs in Phase 10.» Trial and error method to find equivalent wind load for a given design criteria.
9 COMPARING THE OPTIONS I could see for miles and miles, I could see for miles and miles.. The Who Extreme ice wind 3ph new per mile 556AAC using max span % Loading pole Heavy NESC Zone, 250C 100mph, 250D 1" ice 40mph 96% 40' cl4 tangent pole (280' span) Medium NESC Zone, 250C 100mph, 250D.75" ice 40mph 100% 40' cl5 tangent pole (265' span) Light NESC Zone, 250C 100mph, 250D.75"ice 30mph 82% 40' cl 4 tangent pole (260' span) Corrosive Zone, 250C 150MPH wind, 250D.5" ice 30mph 95% 40' cl 2 tangent (180' span) Heavy NESC Zone, 250B- B Grade 90% 40' cl 3 tangent pole Medium NESC Zone, 250B- B Grade 86% 40' cl 4 tangent pole Light NESC Zone, 250B B-Grade 95% 40' cl 3 tangent pole Corrosive Zone, 250B B-Grade 95% 40' cl 2 tangent Heavy NESC Zone, 250B- C Grade 95% 40' cl 4 tangent pole Medium NESC Zone, 250B- C Grade 79% 40' cl 5 tangent pole Light NESC Zone, 250B C-Grade 82% 40' cl 4 tangent pole Corrosive Zone, 250B C-Grade 95% 40' cl2 tangent Light Plus, 100mph wind, 250B C-Grade 98% 40' cl2 tangent Heavy Plus, 1" ice, 250B C-Grade 91% 40' cl 2 tangent, 60" heavy braces on tangent Heavy Plus, 1.5" ice, 250B C-Grade 82% 40' cl 2 tangent, 60" heavy braces on tangent
10 NORMALIZING THE RESULTS (NO OLF) NESC Table values Grade B Grade C Strength factors for 250B Wood » NESC Heavy Grade C 28lbs/ft 2 ~ 107mph wind» NESC Heavy Grade B 35lbs/ft 2 ~117mph wind» AEP Heavy Plus (1 ice) Grade C 45lbs/ft 2 ~133mph wind
11 SAG AND TENSION.» Same tension with more ice = more sag, shorter spans, more vertical load, etc.» Deadends and anchoring are about the same.
12 INTERNAL AEP RECOMMENDATIONS» Heavy loading district (1/2 ice 40mph wind) upgrade to 1 ice / 40mph wind Equivalent to 0 ice / 133 mph wind 25%+ Increased structure strength 5% - 15% avg. increase in capital cost per structure Based on worst case as defined by ASCE ice/wind map applied in all locations (except light loading district).» Medium loading district (1/4 ice/ 40mph wind): upgrade to 1 ice / 40mph wind.» Light loading district (0 ice / 60mph wind): upgrade to 0 ice / 90mph wind. Note: Texas coastal region designed for 150 mph wind 12
13 CIRCUIT LEVEL ACTIONS» Target specific circuits Prioritize circuits using criticality algorithm Apply options by zone» Increase Automated Circuit Reconfiguration, Sectionalizing, Station Breaker capabilities» Expand Distribution SCADA
14 EPRI RESILIENCY STUDY» Three year project to determine ways to strategically design components of the distribution system to fail in a certain order to prevent the most time consuming repairs to be prevented.» Items being evaluated: Spacer Cable Construction Third party attachment impact Conductor slippage Pole Impact Loading Insulator Pin tests Crossarms and braces (tangents and deadends) Neutral attachment test.
15 DECIDING ON A FAILURE ORDER Possible order of failure 1. Insulator ties slip or swing to relieve impact load. Similar to transmission swinging suspension insulator. 2. Break the deadend crossarm. 3. Break inline crossarms / shear post insulators. 4. Break the pole Equipment must still meet NESC minimums» Design poles to AEP Heavy Plus (1 of ice)» Design remaining equipment to NESC minimums» How to prevent pre-mature failure of mechanically fused components under day to day loading.
16 RISKS» Doing nothing may lead to increased regulatory scrutiny» Corporate focus / commitment must be long term» Additional regulatory support may be needed for funding» Culture beats strategy, every time It s worked OK this way before Non-standard materials and practices are prevalent» Resources are necessary for large scale implementation» Customer may resist facility location and maintenance requirements» Joint-users may resist additional costs
17 MEASURING RESULTS» Comparative analysis of storm performance between improved and non-improved circuits» Historic vs. post-improvement performance» Overall system reliability change
18 NEXT STEPS» Develop final design rules Keeps maximum design tensions same? Apply new design rules in Distribution Design Studio» Decision: Implement hardening design criteria for all new and replacement facilities system-wide - 25% increase in 5%-15% increase in cost - Next Step: Evaluate alternative materials
19 QUESTIONS????
20 THANK YOU
Distribution Line Storm Hardening Presenter: Tim Cashman Cashman Engineering
Distribution Line Storm Hardening Presenter: Tim Cashman Cashman Engineering PLS-CADD Advanced Training and User Group Meeting Madison, WI July 16 18, 2013 Introduction Due to the frequency and severity
More informationATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES
ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES The National Electrical Safety Code (NESC) is a set of rules to safeguard people during the installation, operation,
More informationStrength & Loading. Of Wood Utility Poles. Webinar
Strength & Loading Of Wood Utility Poles. Webinar Overview Benefits of Wood as a Utility Pole Material Defining Wood Pole Strength Loading Criteria In-Service Analysis Upcoming NESC 2017 Changes Pole Material
More informationNip / Tuck Method A Solution to Providing Additional Conductor-to-Ground Clearances for Transmission Lines
Nip / Tuck Method A Solution to Providing Additional Conductor-to-Ground Clearances for Transmission Lines Michael E Belanger, P.E., M.ASCE Garrett E Luszczki, E.I., A.M.ASCE TRC Augusta, Maine Presented
More informationV. Design, Application, Maintenance & Operation Technical Requirements
V. Design, Application, Maintenance & Operation Technical Requirements V.A PJM Design & Application of Overhead Transmission Lines 69 kv & Above These design criteria have been established to assure acceptable
More informationACCR. More Amps. More Confidence. Glenmar E. Cambri, REE Senior Applications Engineer
TM ACCR More Amps More Confidence Glenmar E. Cambri, REE Senior Applications Engineer What is 3M ACCR? A high voltage, overhead transmission conductor designed as a drop-in replacement for ACSR and other
More informationKissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2006
Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2006 1) Introduction This report is filed in response to the
More informationGRU Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Calendar Year 2014
1) Introduction GRU Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. Calendar Year 2014 a) Gainesville Regional Utilities (GRU) b) 4747 N. Main Street
More informationREGULATORY CHANGE FOR UTILITY VEGETATION MANAGEMENT IN THE US
REGULATORY CHANGE FOR UTILITY VEGETATION MANAGEMENT IN THE US WILL PORTER DIRECTOR OF CONSULTING RULES AND REGULATIONS CHANGE TO MEET SOCIETAL NEEDS State regulators commissions Customer Needs Electric
More informationExtreme Weather Event Analysis & System Hardening Qualifications
Prepared by: Quanta Technology, LLC Contact: Carl L. Wilkins, P.E. cwilkins@quanta-technology.com 4020 Westchase Blvd., Suite 300 Raleigh, NC 27607 (919) 334-3092 office (919) 279-5848 cell Quanta Technology
More informationWood Pole Design Considerations
NORTH AMERICAN WOOD POLE COUNCIL TECHNICAL BULLETIN No. 17-D-202 Wood Pole Design Considerations Prepared by: W. Richard Lovelace Executive Consultant Hi-Line Engineering a GDS Company About NAWPC The
More informationCHAPTER 7. ERRATA. 1) Chapter 1 Introduction and Summary:
7 Errata CHAPTER 7. ERRATA This chapter addresses errors and corrections to the text of the Phase 1 Draft EIS and is organized by Draft EIS chapter, section, and page number. 1) Chapter 1 Introduction
More informationMinimum Transmission Design Standards f or Competitive Upgrades Rev 2
Minimum Transmission Design Standards f or Competitive Upgrades Rev 2 December, 2016 Minimum Design Standards Task Force Revision History Date or Version Number 12/17/2014 Revision IR Author Change Description
More informationSurvey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST
Survey and Summary of Best Practices for Distribution Reliability Improvement December 8, 2016 2 3 p.m. EST Webinar Overview Moderator: Speaker: Michele Suddleson DEED Program Director American Public
More informationHPC-9DJ
Manual Distribution Design Manual Volume 2: Low Voltage Aerial Bundle Cable Standard Number: HPC-5DC-07-0002-2014 Document Control Author Name: Anthony Seneviratne Position: Standards Engineer Document
More informationHi-Tension News Spring/Summer Arresters. Introduction. Shield Wires EU1413-H
Polymer Arresters as an Alternative to Shield Wire This article is taken from a paper presented at the 24th Annual Transmission & Substation Design and Operation Symposium. by Jim Sanders and Kevin Newman
More informationThe Value of Customer Reliability to the Utility
The Value of Customer Reliability to the Utility Interviewing Lee Taylor, Consulting Engineer Presentation to IEEE Working Group on Distribution Reliability June 20, 2006 Montreal Canada Overview Service
More informationBasic Reliability Analysis of Electrical Power Systems
Basic Reliability Analysis of Electrical Power Systems Course No: E03-020 Credit: 3 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980
More informationPREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES
2013 PREPARING FOR & RESPONDING TO EXTREME WEATHER & EXTENDED OUTAGES Forward-Looking Statement Readers are cautioned that statements contained in this presentation about our and our subsidiaries' future
More informationStay-Cable Replacement Design
Stay-Cable Replacement Design Mississippi River Bridge Luling, Louisiana Christopher Ligozio CTLGroup Copyright Post-Tensioning Institute all rights reserved. Page 1 of 35 Luling Bridge Copyright Post-Tensioning
More informationVegetation Management Takes to the Air BC Hydro pilots the use of LIDAR and PLS-CADD to identify vegetation encroaching on transmission lines.
Vegetation Management Takes to the Air BC Hydro pilots the use of LIDAR and PLS-CADD to identify vegetation encroaching on transmission lines. By Bryan Hooper, British Columbia Hydro Currently, BC Hydro
More informationPractical Checklists of Best Practices Frank Donovan, W3LPL
Design, Construction and Maintenance of Antennas and Towers for Storm Survival and Long Term Reliability Practical Checklists of Best Practices Frank Donovan, W3LPL Typical A Typical Guyed Guyed Tower
More informationRequirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014
Requirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014 1040 O Street, P.O. Box 80869 p: 402.475.4211 Lincoln, NE 68501-0869 www.les.com
More informationElectric Service Handbook
Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated
More informationNORTH AMERICAN WOOD POLE COALITION. A Discussion of Wood Equivalent Poles and the 2002 National Electrical Safety Code
NORTH AMERICAN WOOD POLE COALITION A Discussion of Wood Equivalent Poles and the 2002 National Electrical Safety Code TABLE OF CONTENTS INTRODUCTION...1 DISCUSSION... 2 SUMMARY AND CONCLUSIONS... 4 LIST
More informationSubstation Bus Design: Current Methods Compared with Field Results
Electrical Transmission and Substation Structures Conference 2009 ASCE 143 Substation Bus Design: Current Methods Compared with Field Results Keith Malmedal Ph.D. P.E. P.Eng. 1 and John Wendelburg P.E.
More informationDynamic Analysis of Transmission Tower
Dynamic Analysis of Transmission Tower Sk.Musthafa Department of Civil Engineering, Amara Institute of Engineering and Technology. Sk.Yusuf Basha Department of Civil Engineering, Amara Institute of Engineering
More informationPepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure
1 Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure General Meeting of the IEEE Power Engineering Society Panel Discussion Predictive Reliability
More informationAsset Risk Assessment Through Advanced Analytics. Cop yri g h t 2014 OSIso f t, LLC.
Asset Risk Assessment Through Advanced Analytics Presented by Richard Wernsing Contacts Public Service Electric & Gas Richard Wernsing Cell: 973-303-889 Email: Richard.wernsing@pseg.com OSIsoft Kevin Walsh
More informationSECTION 4 - SECONDARY CONSTRUCTION OVERHEAD TABLE OF CONTENTS
4. GENERAL SECONDARIES & SERVICES 4.- INDIVIDUAL PHASE SECONDARY OVERHEAD LINE EXTENSIONS 4.- SECONDARY AND SERVICE CABLE SPLICES 4.- INSULATED SERVICE ENTRANCE COMPRESSION CONNECTORS 4.- 4. POLE ATTACHMENTS
More informationJoint Use Pole Overloading
Florida Public Service Commission Staff Workshop on Electric Utility Infrastructure Joint Use Pole Overloading new stratagem consulting Tallahassee, FL July 8, 25 Factors Contributing to Pole Failures
More informationELECTRICAL SERVICE UPGRADE RESIDENTIAL AND COMMERCIAL QUICK INFORMATION REFERENCE
ELECTRICAL SERVICE UPGRADE RESIDENTIAL AND COMMERCIAL QUICK INFORMATION REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2015 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION.
More informationAnalysis of distribution system reliability and outage rates
Reclosers Technical Data TD280026EN Supersedes pril 2003 (R280-90-7) COOPER POWER SERIES nalysis of distribution system reliability and outage rates Recloser Technical Data TD280026EN nalysis of distribution
More informationSafety on Heights: Our Policy
11/17/14 Safety on Heights: Our Policy Only volunteers over the age of 18 are allowed to work on heights of more than six feet off the ground. This includes all work on scaffolds. Only volunteers who are
More informationSuojatuote PROxA Weather Protection System Installation Manual. Suojatuote Pro Oy Rastaansiipi 15 D Oulu Suomi
Suojatuote PROxA Weather Protection System Installation Manual Suojatuote Pro Oy Rastaansiipi 15 D 10 90650 Oulu Suomi General The Weather Protection System is a temporary roof system that protects from
More informationVegetation Management Plan
Vegetation Management Plan TABLE OF CONTENTS SECTION TITLE PAGE NUMBER 1. INTRODUCTION 2 2. SAFETY 3 3. RELIABILITY 3 4. VEGETATION MANAGEMENT GUIDELINES 4 5. NEW RIGHT OF WAY GUIDELINES 6 6. VEGETATION
More informationBP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7
Safety Manual Page 1 of 7 Scaffolds 1. Purpose This policy establishes the basic safety requirements and safe work practices for the erection, use, inspection, movement, and dismantling of scaffolding.
More informationTransmission Owner Asset Management
Transmission Owner Asset Management Pieces of Asset Management New customers, load growth, repairs, maintenance, operational issues, etc. All the pieces make up the asset management plan for repair or
More informationWork Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines
Work Performed On or Near Overhead Lines Work Performed On or Near Overhead Lines 1910.269(p) and (q) of Electric Power Generation, Transmission, and Distribution Note: The below information applies only
More informationDesignated Entity Design Standards Task Force Minimum Required Standards
Designated Entity Design Standards Task Force Minimum Required Standards Developed by the DEDSTF Version 2.0.3 2 Table of Contents Introduction...3 Applicability...3 Transmission Lines Minimum Required
More informationUSER S MANUAL 400W and 600W
USER S MANUAL 400W and 600W 1108 Summit Avenue, Suite 8 Plano, TX 75074 866-WND-PWRD www.acgreenenergy.com CONTENTS 1. WIND TURBINE INTRODUCTION 2. SITING 3. CHOOSING A SUITABLE WIND TURBINE 4. YOUR WIND
More informationScaffolding Safety. Scaffolding
Scaffolding Safety Scaffolding 1926.450 - Scope, Application Covers all scaffolds used in workplaces Does not apply to crane or derrick suspended personnel platforms, which are covered by 1926.550(g) Aerial
More informationTESTING PTE EARTHING
1 SCOPE This section of the Power Systems Live Working Manual details the procedures to be followed to achieve Safety from the System when carrying out examination, testing and remedial work on PTE (Pole
More informationNova Scotia Utility and Review Board
Nova Scotia Utility and Review Board IN THE MATTER OF The Public Utilities Act, R.S.N.S., c.0, as amended Post-Tropical Storm Arthur Review of Nova Scotia Power s Storm Response September, 0 0 TABLE OF
More informationWhy do Transmission Asset Owners Need a Transmission Restoration System (ERS)? Transmission Line Emergencies Do Occur
Sabotage of a critical 500 kv DC transmission line necessitated the erection of this Lindsey Emergency Restoration Structure. Total erection time was 5-1/2 hours. Why do Transmission Asset Owners Need
More informationCONTACT ELECTRICAL CHARACTERISTICS TIGER CLAW CONTACT TESTING. A. Gas Tight
CONTACT ELECTRICAL CHARACTERISTICS TIGER CLAW CONTACT TESTING A. Gas Tight 1. Purpose - To evaluate the integrity of the contact interface by assessment of the gas tight characteristics of the contacting
More informationExtreme Weather Events and State DOTs
Extreme Weather Events and State DOTs Date: August 25, 2014 Committee: Presenter: SASHTO Michael Meyer, Parsons Brinckerhoff AASHTO EXTREME WEATHER EVENTS SYMPOSIUM Best Practices for Extreme Weather Management
More informationA Study on Analysis of Transmission Line Tower and Design of Foundation
A Study on Analysis of Transmission Line Tower and Design of Foundation 1 B. Bharath Kumar Reddy, 2 K. Rasagnya, 3 V. Sanjay Gokul 1,2 Under Graduates, 3 Assistant Professor Abstract - The Transmission
More informationOSHA Rules for Scaffolding
OSHA Rules for Scaffolding A) Objectives: 1. 2. 3. Don t let the scaffold fall. Don t fall off the scaffold. Don t let the material fall off the scaffold. Name of Competent Person: Name of Qualified Person:
More informationXXXXXXXXXXX Solar (XXX) Generation Interconnection
Facility Study For XXXXXXXXXXX Solar (XXX) Generation Interconnection Prepared For: Randy Harlas, Substation Manager El Paso Electric Company El Paso, TX September 2010 Table of Contents 1. GENERAL...
More informationBenefit-Cost Analysis Summary Report
Benefit-Cost Analysis Summary Report Site 74 City of Syracuse PROJECT OVERVIEW As part of NYSERDA s NY Prize community microgrid competition, the CNY RPDB has proposed development of a microgrid that would
More informationNAU Challenge Course Climbing Wall Design. Austin Hopper Project Manager Kelsey Deckert Structural Engineer Stephanie Sarty Materials Engineer
NAU Challenge Course Climbing Wall Design Austin Hopper Project Manager Kelsey Deckert Structural Engineer Stephanie Sarty Materials Engineer Design Climbing Wall for NAU Challenge Course Location Flagstaff,
More informationTECHNICAL SPECIFICATION FOR PRESTRESSED CEMENT CONCRETE POLES ( F.O.S. 2.5) FOR 11 KV AND LT LINES ( REC SPECIFICATION NO.
TECHNICAL SPECIFICATION FOR PRESTRESSED CEMENT CONCRETE POLES ( F.O.S. 2.5) FOR 11 KV AND LT LINES ( REC SPECIFICATION NO. 15 / 1979) MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. PAGE 1 OF 7
More informationVegetation Management Plan
Page 1 of 23 The United Illuminating Company Vegetation Management Plan Distribution Planned Cycle 11/01/2013 Page 2 of 23 Table of Contents EXECUTIVE SUMMARY... 3 Distribution Line Clearance Implementation
More informationCircuit Reliability Review
Circuit Reliability Review Hidden Hills January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationCompany Replaces previous document Document ID Issue E.ON Elnät Sverige AB Ny engelsk utgåva D
Document type Page Verksamhetsstyrande 1 (5) Company Replaces previous document Document ID Issue E.ON Elnät Sverige AB Ny engelsk utgåva D17-0008968 1.0 Organisation Valid from Valid until Regionnätsaffärer
More informationP.G student, Civil Engineering department, Saraswati College of Engineering, Maharashtra, India 1
International Journal of Scientific & Engineering Research, Volume 6, Issue 1, December-15 145 Analysis and Design of kv transmission line tower with hot rolled and cold formed section Supriya Khedkar1,
More informationUndergrounding: Hidden Lines, Hidden Costs
NORTH AMERICAN WOOD POLE COUNCIL TECHNICAL BULLETIN No. 17-U-102 Undergrounding: Hidden Lines, Hidden Costs Prepared by: North American Wood Pole Council About NAWPC The North American Wood Pole Council
More informationSteel Pole Research. Professor Jeffrey Packer. American Iron and Steel Institute. University of Toronto
Steel Pole Research Professor Jeffrey Packer American Iron and Steel Institute Wood Poles Environmentalists are opposing logging & non-replacement. Long, straight poles are becoming difficult to obtain.
More informationMark L. Reno, P.E. September 11, 2015
Ogden Ogden Siphon Canyon Pipe Siphon Suspension Structural Assessment Bridge Mark L. Reno, P.E. September 11, 2015 Seismic Retrofit of Designed in 1936 by U.S. Bureau of Reclamation 1,044 feet of 31.25
More informationTower Site Inspection Procedures
Engineering, Manufacturing, Construction & Erection Specializing in Radio & TV Communication Towers 6037 S. Industrial Rd. 918-789-9020 Office 918-789-9922 Fax www.belltowercorp.com bob@belltowercorp.com
More informationAmeren Illinois Electric Quality Assurance Program Keith Lowry Superintendent, Electric Quality Assurance
Ameren Illinois Electric Quality Assurance Program Keith Lowry Superintendent, Electric Quality Assurance May 15, 2015 Development of Quality Assurance Process Illinois Commerce Commission Reliability
More informationToronto Hydro s Climate Adaptation Actions
s Climate Adaptation Actions Rob McKeown Engineer, Standards & Policy Planning Engineering & Construction Division OCCIAR Webinar March 1, 2017 2 March 1, 2017 3 March 1, 2017 Generation In Ontario, 70%
More informationGEOS / ENST Problem set #Grid Due: Tues. May 18
GEOS 24705 / ENST 24705 Problem set #Grid Due: Tues. May 18 Problem 1: Three-phase power transmission The standard means by which electricity is transmitted in the U.S. is as 3-phase AC power. Each of
More informationTree Risk Assessment Recognizing and Evaluating Potential Hazards
Davey Resource Group Tree Risk Assessment Recognizing and Evaluating Potential Hazards Great Lakes Park Training Institute Why Do We Care? Personal safety Safety of crew Safety of citizens Recognizing
More informationHeel Blocking Requirements and Capacity Analysis. Overview Revised 3/22/2017
Heel Blocking Requirements and Capacity Analysis Overview Revised 3/22/2017 SBCA has been the voice of the structural building components industry since 1983, providing educational programs and technical
More informationPanel Jack Pro System BRACING, ALIGNMENT AND SCAFFOLDING EQUIPMENT
IMPORTANT SAFETY INFORMATION FOR USERS OF THE REECHCRAFT, BRACING SYSTEM PLEASE READ BEFORE USE Panel Jack Pro System BRACING, ALIGNMENT AND SCAFFOLDING EQUIPMENT UK Edition 1.3 26/11/2012 1 TABLE OF CONTENTS
More informationAMI information. for improved outage management
Utilities the way we see it AMI information for improved outage management The information contained in this document is proprietary. 2013 Capgemini. All rights reserved. Rightshore is a trademark belonging
More informationUnderstanding New IEC Mechanical Test Requirements of Arresters
Understanding New IEC Mechanical Test Requirements of Arresters ArresterFacts 007 Understanding New IEC Mechanical Test Requirements of Arresters New Cyclic Load Test (1000 cycles) 1 cycle every 2 seconds
More informationTEMPORARY METER POLE INSTALLATION
TEMPARY METER POLE INSTALLATION MEMBER PROVIDED Location to be made by REMC within 50' of our transformer or existing service Temporary pole to be properly braced 24" 3 wire weatherhead (located 24" from
More informationCircuit Reliability Review
Circuit Reliability Review Agoura Hills January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationENVIRONMENTAL MANAGEMENT PLAN
Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Azerbaijan: Power Transmission Project Transmission Lines Rehabilitation sub-projects
More informationSeries IEEE 1070 ERS
Series IEEE 1070 ERS Quality and innovations in Q UESTION: WHY DO TRANSMISSION ASSET OWNERS NEED AN EMERGENCY RESTORATION SYSTEM (ERS)? A NSWER: Transmission line emergencies do occur. Whether caused by
More informationOVERHEAD CONSTRUCTION MANUAL L.V. CONSTRUCTION
OVERHEAD CONSTRUCTION MANUAL Back to MAIN INDEX Go to SECTION INDEX CONSTRUCTION DWG CONSTRUCTION DWG Construction Code guide - 06/ Pole top LVABC and Open wire Construction Code Guide - 06/2 Normal Bridge
More informationDOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES
Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating
More informationCantilever Racking Store Any Size, Any Shape
Cantilever Racking Store Any Size, Any Shape Cantilever Racking Applications Cantilever Racking for Metal Tube & Piping Storage - 4 Very Narrow Aisle (VNA) Cantilever Racking - 5 Cantilever Roofs for Four-Season
More informationPOST FRAME BUILDING STANDARDS
CASS COUNTY, MISSOURI BUILDING CODES, ENVIRONMENTAL HEALTH AND ZONING DEPARTMENT 30508 S. West Outer Road, Harrisonville, MO 64701 P- (816) 380-8134 F- (816) 380-8130 POST FRAME BUILDING STANDARDS 201.3
More informationTechnical Specifications of 8 M and 9 M PCC Poles (F.O.S.-2.5) with working load 200 Kg.
DAKSHIN HARYANA BIJLI VITRAN NIGAM LIMITED Specification No. S-95/DD-177 Technical Specifications of 8 M and 9 M PCC Poles (F.O.S.-2.5) with working load 200 Kg. Chief Engineer/P&D, DHBVN, Hisar. Issue
More informationCVEN 483. Structural System Overview
CVEN 483 Structural System Overview Dr. J. Bracci Fall 2001 Semester Presentation Overview 1. Building system primary function 2. Types of load 3. Building materials 4. Structural members 5. Structural
More informationThe Impact of the Changing Climate on Prince Edward Island s Infrastructure: Adaptation Options
The Impact of the Changing Climate on Prince Edward Island s Infrastructure: Adaptation Options Heather Auld Principal Climate Scientist Risk Sciences International (RSI) Adapting Infrastructure to What???
More informationTechnical Specification for LV ABC Fuse Switch Disconnectors
Ergon Energy Corporation Limited Technical Specification for LV ABC Fuse ETS-06-02-02 Check this is the latest Process Zone version before use. Specification ETS 06-02-02 Ver 3 Contents 1. Purpose and
More informationOperational efficiency
Operational efficiency OPERATIONAL EFFICIENCY G4-DMA Last year, the company invested BRL 791.5 million in services to consumers, expansion of the system, operational reliability, recovery of losses, information
More informationSAFETY BARRIER SYSTEM
SAFETY BARRIER SYSTEM Attractive, Durable Composite Utility Walls Non-conductive perimeter fencing provides safety, security. Ideal for substations, transformer yards, and other utility-asset properties.
More informationEing adequate levels of safety
Pole Testing Ensures High Reliability and Long Life Hydro-Québec pilot project verifies results of field-test methods. By Lee A. Renforth, IPEC Ltd., and André Taras, Hydro-Québec lectric utilities are
More informationSTONE OAK DAM: TO BREACH OR NOT TO BREACH, THAT IS THE QUESTION. TFMA Spring Conference 2013
STONE OAK DAM: TO BREACH OR NOT TO BREACH, THAT IS THE QUESTION TFMA Spring Conference May 23, 2013T F M A Spring Conference 2013 INTRODUCTIONS ALYSHA GIRARD, P.E., CFM Storm Water Program Manager City
More informationDesign and Optimization of Overhead Transmission Lines using PLS-CADD and TOWER software
Design and Optimization of Overhead Transmission Lines using PLS-CADD and TOWER software Dates Theoretical and Practical Training Course PLS-CADD training: Dec. 9 to 12, 2017 TOWER/PLS-POLE training Dec.
More informationTechnical Specification for Live Line Tap Connectors
Ergon Energy Corporation Limited Technical Specification for Live Line Tap ETS-06-01-01 Check this is the latest Process Zone version before use. Specification ETS 06-01-01 Ver 1 Contents 1. Purpose and
More informationPresentation: Paul van Lieshout - Jacobs Consultancy Extreme Weather Events and Wind Energy Production Analysis
Presentation: Paul van Lieshout - Jacobs Consultancy Extreme Weather Events and Wind Energy Production Analysis www.jacobsconsultancy.com Introductions and Objective The IPCC concludes that small changes
More informationTechnical Specification for Aluminium Castings, Pole Caps and Pressed Symbols
Ergon Energy Corporation Limited Technical Specification for Aluminium Castings, Pole Caps and Pressed Symbols ETS-01-05-01 Check this is the latest Process Zone version before use. Specification ETS 01-05-01
More informationComposite Poles for Electric Utility & Communication Applications
Composite Poles for Electric Utility & Communication Applications Technical Specification (USA) INFRASTRUCTURE FOR LIFE RS Technologies www.rstandard.com Email Toll Free Phone Fax info@grouprsi.com +1
More informationStudy Committee B2 Technical Advisory Group B2-AG-06
Study Committee B2 Technical Advisory Group B2-AG-06 Cigré AG06 Seminar Bangkok Types and Uses of High Brian Wareing Brian Wareing.Tech Ltd Chester, UK Convenor Cigré AG06 WG48 Experience with the Mechanical
More informationElectricity Safety (Electric Line Clearance) Regulations 2010
Version No. 001 Electricity Safety (Electric Line Clearance) Regulations 2010 Version as at 29 June 2010 TABLE OF PROVISIONS Regulation Page 1 Objectives 1 2 Authorising provisions 1 3 Commencement 2 4
More informationOrdinance No July 1, 2016
(Insert Facing Page 3 IRC) 2.02.540 Amendment to IRC Section R105.2 Work Exempt From Permit, Building and Electrical Sections. The following additional exception shall be added to R105.2 Building: Building:
More informationDUQUESNE UNIVERSITY SAFETY PROGRAM FOR WORKING AT ELEVATED HEIGHTS
DUQUESNE UNIVERSITY SAFETY PROGRAM FOR WORKING AT ELEVATED HEIGHTS Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Responsibilities 1 Scaffolding 2 Ladders
More informationResponse of Metal Roofs to Uniform Static and True Hurricane Wind Loads
Missouri University of Science and Technology Scholars' Mine International Specialty Conference on Cold- Formed Steel Structures (2008) - 19th International Specialty Conference on Cold-Formed Steel Structures
More informationTRANSMISSION & DISTRIBUTION SILICONE INSULATORS InterPhase Spacers 15 kv to 400 kv
K-LINE INSULATORS LIMITED Catalogue TD-IPS TORONTO, ONTARIO, CANADA TRANSMISSION & DISTRIBUTION SILICONE INSULATORS InterPhase Spacers 15 kv to 400 kv ISO9001 SAI GLOBAL FILE No. 000117 Transmission &
More information3M Cold Shrink Silicone Rubber Connector Insulators 8440 Series
3M Cold Shrink Silicone Rubber Connector Insulators 8440 Series Data Sheet May 2014 Product Description 3M Cold Shrink Connector Insulators 8440 Series are open-ended, silicone rubber, tubular sleeves.
More informationPROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014
PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 The United States Forest Service (USFS), Shawnee National Forest (SNF), is analyzing a request from Ameren Services (Ameren), a group
More informationEEI written comments 83 pages long. Proposal issued in Author has been rewriting for the last 2 years. Preamble for final rule will be 1,000
April 2011 EEI written comments 83 pages long. Proposal issued in 2005. Author has been rewriting for the last 2 years. Preamble for final rule will be 1,000 pages. It is very technical and very detailed.
More informationCITY OF RICHMOND PINE CAMP COMMUNITY CENTER ROOF REPLACEMENT PROJECT RCS PROJECT NO
SECTION 07220 - ROOF INSULATION PART 1 - GENERAL 1.01 DESCRIPTION A. Work included: The Roofing Contractor will provide all polyisocyanurate insulation and high density wood fiber roof insulation (tapered
More information