Black Hills Corp. Overview 8/14/2015 POWER PLANT STORMWATER STABILIZATION THROUGH REVEGETATION, A CASE STUDY. Topics

Size: px
Start display at page:

Download "Black Hills Corp. Overview 8/14/2015 POWER PLANT STORMWATER STABILIZATION THROUGH REVEGETATION, A CASE STUDY. Topics"

Transcription

1 POWER PLANT STORMWATER STABILIZATION THROUGH REVEGETATION, A CASE STUDY AHMP National Conference 2015 Joe Jenkins, PG, CHMM, CPESC Topics Black Hills Corporation Overview Post Construction BMPs and Controls Risk Assessment BMP Repair Engineering Design and BMP Selection Soil Sampling and Amendments Construction Phase One Year Later BMP: Best Management Practice 3 Black Hills Corp. Overview Based in Rapid City, SD, with corporate offices in Denver, CO, and Papillion, NE Utility operations serve 765,000 utility customers in CO, IA, NE, SD, WY Non-regulated businesses generate wholesale electricity, and produce natural gas, crude oil and coal. Utilities Electric Utilities Black Hills Power Cheyenne Light* Colorado Electric Gas Utilities Colorado Gas Kansas Gas Nebraska Gas Iowa Gas Non-Regulated Energy Power Generation Black Hills Electric Generation Coal Mining Wyodak Resources Oil and Gas Black Hills Exploration and Production 4 1

2 Pueblo Airport Generating Station (PAGS) January W. N. Clark Station Canon City, CO 48 MW 255,425 mt CO 2e 24 employees PAGS 380 MW, 29 MW wind 317,683 mt CO 2e 14 employees Replaced 300 MW of coal-based purchased power 6 Impact of PAGS on GHG Emissions Reduction 37% reduction in GHG Emissions 7 2

3 Location of PAGs in Respect to Arkansas River 8 Facility with Respect to Local Topography PAGS Approx. 3.6 miles Arkansas River 9 April

4 Area Designations Site of new turbine unit, construction beginning 2016 Go to master slide > 11 Pueblo County Stormwater Considerations No stormwater retention allowed by County 12 Army Corp Non-Jurisdictional WOTUS 13 4

5 Natural Vegetation in and Around PAGS Shortgrass prairie co-dominant with Greasewood shrubland: Blue Grama Alkali saction grass Galetta grass Sand dropseed Rabbitbrush Cholla 14 Post-Construction BMPs and Controls 15 Engineer s Design

6 Power Block March SE Stockpile and Detention Pond Area March West of Powerblock Culvert 10, 3 ft. round culvert Culvert 9, 4 ft. box culvert 19 6

7 Floodplain Analysis Culvert yr 25 yr 100 yr 20 Culvert yr Flood Level Determination 100 yr FP 10 yr FP July rainfall 21 Culvert yr Flood Level Determination 100 yr FP September rainfall 22 7

8 Rain Event July 15, Pond Slope Design 24 Evaporation Ponds 25 8

9 Laydown Yard March Shale Stockpiles 27 RISK ANALYSIS 28 9

10 Risk Analysis August 2013 Review of existing stormwater restoration practices and BMPs State of Colorado Stormwater Civil Penalty Matrix Determine Base Gravity Penalty Account for Duration of Violation (multi-day penalties) Apply Aggravating or Mitigating Factors Add Economic Benefit Multiple Violations Ability to Pay Multi-Day Penalties Conducting Covered Activities without a Stormwater Permit Failure to Prepare Stormwater Management Plan (SWMP) Deficient Stormwater Management Plan (SWMP) 29 Violation Matrix Multi-Day Penalties Example Day 1 ($ ) = $ 1, Days 2-10 ($ ) X (9 days) X (50%) = $ 4, Days ($ ) X (40 days) X (40%) = $16, Days ($ ) X (50 days) X (30%) = $15, Days ($ ) X (100 days) X (20%) = $20, Days ($ ) X (70 days) X (10%) = $ 7, Multi-Day Base Gravity Penalty = $65, Applicable to each identified violation: Failure to Install, Maintain, or Properly Select BMPs Failure to Perform Inspections of Stormwater Management System Pollution, Contamination, or Degradation of State Waters 30 PAGS at Risk Stormwater Management System Permit expanded in phases but no evidence of communication with State on expansions Initial permit described access road and plant Did not include evaporation ponds or shale stockpiles No post-construction version of the SWMP Inadequate SWMP Site description changes not addressed Site map not updated BMPs not updated Final stabilization practices not described Examples of Recent Violations 2011, Timnah Ranch, $90,223 penalty 2012, Sumo Development, $100,000 penalty 2013, Rock Mt. Materials, $65,

11 PAGS at Risk for Stormwater Management 32 Maintenance and Replacement of Failed BMPs The potential to discharge sediment-laden water from numerous outfalls around the plant site. Each outfall is a separate violation. Stormwater sediment retention basin SE corner of facility Multiple locations along both arroyos on each side of the shale pile All silt fence at the site Partially riprapped channels Slopes along the substation Unstabilized drainage along access road Unstabilized drainage (no controls) along the dirt road west of shale pile Unstabilized slopes (no controls) around evaporation ponds Unstabilized surfaces (no controls) around evaporation ponds Unstabilized surfaces (no controls) around sediment retention basin No perimeter control around stockpile northwest of plant No perimeter control around stockpile southeast of plant No perimeter control around small stockpile by arroyo south of access road No or incomplete perimeter control around shale piles Sediment tracking on roadways at dirt road access west of shale pile Sediment on road east of arroyo where it flows with run off being tracked along roadway above arroyo (potential discharge to state waters) Erosion (rills) on shale pile Erosion (rills) on evaporation pond slopes Erosion (rills) on access road slopes Erosion (rills) on south side of substation Erosion (rills) on sediment retention basin Erosion (rills) on slopes of drainage channels Improperly designed sediment retention basin with direct discharge potential off site Failed controls in laydown yard Failed controls on horizontal surfaces in power block area Lack of weed control 33 INITIAL REPAIR OF FAILED BMPS 34 11

12 Initial Repair of Failed BMPs 35 Initial Repair of Failed BMPs 36 Initial Repair of Failed BMPs Total Cost of repairs $160,

13 Initial Repair of Failed BMPs 5/13/13 South Powerblock Drainage 38 Power Block 4, BMP Maintenance

14 Engineering Design and BMP Selection 41 Engineering Evaluations Control Technology and BMP Selection Available Technologies Revegetation Soil sampling Amend and revegetate Addition of topsoil Rock, riprap, grouted rip rap Manufactured drainage Retaining walls Budgetary Considerations Previously budgeted expense Will raise customer rates Rock versus Vegetation SWOT analysis Cost comparison 42 Soil Sampling South Shale Stockpile (1, 2), Laydown Yard (3) North Shale Stockpile (1), SE Shale Stockpile (2) TDS: Total Dissolved Salts; SAR: Sodium Absorption Ratio; CEC Cation Exchange Capacity 43 14

15 SWOT Analysis Rock Strengths / Opportunities No watering, not affected by drought Potentially low maintenance Immediate results Weaknesses / Threats High Cost Windblown dust may cover riprap over time Potentially high cost to maintain Vegetation Strengths / Opportunities Lower cost Weaknesses / Threats Watering required to support growth Semi/arid conditions accentuated by drought Heavy downpour could impact structures and wash away seeds Greater maintenance anticipated due to time to establish seeds 44 Rock versus Vegetation $1,155,223 for vegetation versus $3,178,261 for primarily rock and riprap cover 45 Final Engineering Design June

16 Amendments and Seed Mixture 47 Construction Phase 48 BMP Construction Began 7/15/

17 Permanent BMP Installation and Revegetation 50 Permanent BMP Installation and Revegetation Complete 9/1/ June 2015 Go to master slide > 52 17

18 Lessons Learned Prior to Project Start Establish effective communication with all parties before construction begins Communicate compliance risk early and effectively Critically evaluate engineering design to determine if effectively addresses site conditions Establish effective communication with federal, state and local agencies as needed During the Project Provide ongoing comprehensive oversite to assure compliance is addressed along with construction activities Carefully manage records Reevaluate compliance as site condition change Do it right the first time! 53 Contact Information Joe Jenkins, PG, CHMM, CPESC Sr. Environmental Professional Black Hills Corporation 1515 Wynkoop St, Denver CO

Re: Erosion Control Report and Drawings Requirements Accompanying Document

Re: Erosion Control Report and Drawings Requirements Accompanying Document Re: Erosion Control Report and Drawings Requirements Accompanying Document This document was created to help engineers and other design staff to better understand, meet and exceed the erosion control requirements

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

Performance Standards Compliance Checklist

Performance Standards Compliance Checklist Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each

More information

STORM WATER POLLUTION PREVENTION PROGRAM SAILOR BAR/ CUTTERS PIT SATELLITE STORAGE YARD

STORM WATER POLLUTION PREVENTION PROGRAM SAILOR BAR/ CUTTERS PIT SATELLITE STORAGE YARD COUNTY OF SACRAMENTO Public Works Agency Department of Transportation STORM WATER POLLUTION PREVENTION PROGRAM SAILOR BAR/ CUTTERS PIT SATELLITE STORAGE YARD SACRAMENTO COUNTY DEPARTMENT OF TRANSPORTATION

More information

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016 Written Closure Plan Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado October 17, 2016 Table of Contents 1.0 General Information... 1 2.0 Description of Closure

More information

D EROSION AND SEDIMENT CONTROL. Table of Contents

D EROSION AND SEDIMENT CONTROL. Table of Contents Table of Contents D1. GENERAL... 1 D2. OBJECTIVE... 1 D3. REFERENCE MATERIAL... 1 D4. REGULATORY REQUIREMENTS... 1 D5. EROSION AND SEDIMENT CONTROL (ESC) PLANS... 2 D5.1 Goals and Objectives:... 2 D5.2

More information

NC2 ASH DISPOSAL AREA

NC2 ASH DISPOSAL AREA POST-CLOSURE PLAN OPPD NEBRASKA CITY GENERATING STATION FOSSIL FUEL COMBUSTION ASH DISPOSAL AREA NC2 ASH DISPOSAL AREA Prepared for: OMAHA PUBLIC POWER DISTRICT NEBRASKA CITY GENERATING STATION OTOE COUNTY,

More information

GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ

GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR PROJECT BEING DEVELOPED

More information

Jim Bridger Power Plant

Jim Bridger Power Plant 2015 Coal Combustion Residuals Annual Inspection Jim Bridger Power Plant Industrial Landfill Prepared for PacifiCorp Energy North Temple Office 1407 West North Temple Salt Lake City, Utah 84116 Final December

More information

A. PROJECT LOCATION. B. PERMITTEE (Responsible party for day to day supervision and control of the MANAGMENT PLAN)

A. PROJECT LOCATION. B. PERMITTEE (Responsible party for day to day supervision and control of the MANAGMENT PLAN) Narrative Report Information Worksheet City and County of Denver, Demolition and Construction Activities Stormwater Management Plan (SWMP) Revised 2/12/2013 as entry form A. PROJECT LOCATION Name of Project

More information

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN SITUATED IN THE SW ¼ OF SECTION 18, T.2S., R.67W., OF THE 6 TH P.M. COUNTY OF ADAMS, STATE OF COLORADO PREPARED FOR: Thornton Cornerstone

More information

1.2 REGULATORY REQUIREMENTS

1.2 REGULATORY REQUIREMENTS Table 1.1. Soil textural classes and general terminology used in soil descriptions (Source: US Environmental Protection Agency 1977). Name Texture Basic soil textural common class names Sandy soils Coarse

More information

VISUAL SITE INSPECTION REPORT 2018

VISUAL SITE INSPECTION REPORT 2018 VISUAL SITE INSPECTION REPORT 2018 SOUTHERN INDIANA GAS AND ELECTRIC A. B. BROWN GENERATING STATION TYPE III RESTRICTED WASTE LANDFILL WEST FRANKLIN, IN ATC PROJECT NO. 170LF00614 January 9, 2019 PREPARED

More information

ES Inspection and Maintenance of MS4 Structural Controls* Document Identification Number Date: March 14, 2018

ES Inspection and Maintenance of MS4 Structural Controls* Document Identification Number Date: March 14, 2018 ES-301-4.08 Inspection and Maintenance of MS4 Structural Controls* Document Identification Number ES-301-4.08 Date: March 14, 2018 Document Owner: Kim Ohlson 1) Activity Description: MS4 Maintenance and

More information

Chapter 2: Selecting Best Management Practices (BMPs)

Chapter 2: Selecting Best Management Practices (BMPs) Chapter 2: Selecting Best Management Practices (BMPs) 2.1 - Temporary versus Permanent BMPs The same level of care should be taken to select both temporary BMPs and permanent BMPs. The same level of care

More information

Construction Site Inspections

Construction Site Inspections Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some

More information

STORM WATER MANAGEMENT PLAN FOR LOT 2 BECKETT AT WOODMEN HILLS FILING NO. 3 SHOPS AT MCLAUGHLIN II 7368 MCLAUGHLIN ROAD PEYTON, CO 80831

STORM WATER MANAGEMENT PLAN FOR LOT 2 BECKETT AT WOODMEN HILLS FILING NO. 3 SHOPS AT MCLAUGHLIN II 7368 MCLAUGHLIN ROAD PEYTON, CO 80831 STORM WATER MANAGEMENT PLAN FOR LOT 2 BECKETT AT WOODMEN HILLS FILING NO. 3 SHOPS AT MCLAUGHLIN II 7368 MCLAUGHLIN ROAD PEYTON, CO 80831 OCTOBER 2017 Revised July 2018 PREPARED FOR: TBONE CONSTRUCTION

More information

EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ

EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ EXAMPLES OF GENERAL SOIL EROSION AND SEDIMENT CONTROL NOTES FOR HUNTERDON COUNTY, NJ *THE BELOW NOTES ARE EXAMPLES OF COMMONLY USED IN SE&SC PLAN APPLICATIONS THE NOTES MAY BE EDITED AS APPROPRIATE FOR

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

Non-Vegetative Stabilization

Non-Vegetative Stabilization Categories EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control NS Non-Stormwater Management Control WM Waste Management and Materials Pollution Control Legend: Primary Category

More information

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture

More information

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY

STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY STATE OF COLORADO GENERAL PERMIT APPLICATION Updated 11/04 STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY This application is for use by all stormwater dischargers engaged in construction

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

A. Each Contractor shall comply with the requirements outlined in these documents.

A. Each Contractor shall comply with the requirements outlined in these documents. Section 000700 Stormwater Management Plan for Aurora Public Schools PART 1 GENERAL 1.0 DESCRIPTION A. Each Contractor shall comply with the requirements outlined in these documents. PART 2 PRODUCTS Not

More information

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station Annual Inspection Report CCR Surface Impoundment MidAmerican Energy Company, Louisa Generating Station Final January 15, 2016 Annual Inspection Report CCR Surface Impoundment Prepared for MidAmerican Energy

More information

Drainage Criteria Manual Review

Drainage Criteria Manual Review City of Colorado Springs Stormwater Management Assessment and Standards Development Drainage Criteria Manual Review March 8, 2013 Springsgov.com/City Agencies/Stormwater/Stormwater Engineering/ Stormwater

More information

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents Site Description A description of construction activity. The proposed sequence for major activities. Estimates of the total

More information

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below.

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below. SEDIMENT CONTROL NOTES 1.0 GENERAL 1.1 The Developer and Contractor shall comply with the requirements of all regulatory authorities, federal, provincial and municipal government departments including

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL () September 2017 Page Chapter 1 Acronyms and Definitions 1.01 Purpose 1 1.02 Acronyms 1 1.03 Definitions 3 Chapter 2 Introduction 2.01 Purpose 1 2.02 Applicability

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

Single Family Residential Construction Erosion/Sediment Control Standards

Single Family Residential Construction Erosion/Sediment Control Standards Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended

More information

Twin Lakes Quarrys, Inc. P.O. Box 705 Mountain Home, AR (870)

Twin Lakes Quarrys, Inc. P.O. Box 705 Mountain Home, AR (870) Twin Lakes Quarrys, Inc. P.O. Box 705 Mountain Home, AR 72654 (870) 425-4510 November 6,2006 Arkansas Department of Environmental Quality Water Division Tony L. Moms P.O. Box 8913 Little Rock, AR 72219-891

More information

Big River Mine Tailings Site St. Francois County, Missouri

Big River Mine Tailings Site St. Francois County, Missouri CASE STUDY Big River Mine Tailings Site St. Francois County, Missouri August 2010 Prepared by The Interstate Technology & Regulatory Council Mining Waste Team Permission is granted to refer to or quote

More information

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station)

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station) Inspection Report To: From: David Burton, Facility Manager (NRG Indian River Generating Station) Richard Southorn, P.E., P.G., CPSWQ Re: Indian River Landfill Annual CCR Unit Inspection Report No. 2 Inspection

More information

Storm Water Pollution Prevention Plan for CES Gravel #3800

Storm Water Pollution Prevention Plan for CES Gravel #3800 David Lewis Cell: (870) 310-2757 Rickey Vaughn Cell: (870) 310-9602 Buddy McAdams Cell: (870) 310-8733 Local (870) 881-8830 Fax: (870) 881-8809 LICENSED, BONDED & INSURED Howard Cupp, Jr. Cell: (870) 314-2877

More information

Soil Erosion and Sedimentation Control (SESC) Information and Application Packet

Soil Erosion and Sedimentation Control (SESC) Information and Application Packet ARENAC COUNTY BUILDING DEPARTMENT SOIL EROSION & SEDIMENT CONTROL P.O. BOX 724 * 120 NORTH GROVE ST * STANDISH, MI 48658 PH. 989-846-9791 FAX: 989-846-9188 This institution is an equal opportunity provider.

More information

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO. 0200-S3N-R2 AFIN 32-00042 OCTOBER 12, 2016 LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT

More information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage

More information

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT

Nonmetallic Mining Reclamation & Operation Plan. Amendment No. 1 (Includes modifications for Wash Plant construction) DRAFT Nonmetallic Mining Reclamation & Operation Plan Amendment No. 1 (Includes modifications for Wash Plant construction) Mondovi Mine Town of Mondovi, Wisconsin Prepared for: Buffalo White Sand, LLC PO Box

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

LAND DISTURBANCE PERMIT

LAND DISTURBANCE PERMIT SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone

More information

Construction Site Runoff Inspections and Enforcement

Construction Site Runoff Inspections and Enforcement Construction Site Runoff Inspections and Enforcement Stormwater Program 12/01/11 Table of Contents Introduction... 1 Purpose of Document... 1 Definition of Terms... 1 Compliance and Inspections... 3 Site

More information

Welcome The purpose of this information is to give you an opportunity to:

Welcome The purpose of this information is to give you an opportunity to: Welcome The purpose of this information is to give you an opportunity to: Learn how the Ada County Highway District (ACHD) is meeting requirements and milestones in our Phase II Stormwater Management Plan,

More information

CROSBY BROOK RESTORATION STUDY BRATTLEBORO, VT

CROSBY BROOK RESTORATION STUDY BRATTLEBORO, VT Key Stakeholders: CROSBY BROOK RESTORATION STUDY BRATTLEBORO, VT Funded By: VT Dept. of Environmental Conservation VT Agency of Transportation (VTrans) Town of Brattleboro NEWEA Spring Meeting Omni Mt.

More information

Stormwater Management. Cayuga County NY 20 July 2016 Presenter : John B. Zepko, CPESC

Stormwater Management. Cayuga County NY 20 July 2016 Presenter : John B. Zepko, CPESC Stormwater Management Cayuga County NY 20 July 2016 Presenter : John B. Zepko, CPESC Agenda What is Stormwater? Why is Stormwater a Problem? NY State Regulations Stormwater Pollution Prevention Plans What

More information

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR

WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR WELCOME TO THE CONSTRUCTION STORMWATER PERMIT WEBINAR All the documents shown today are in the MN Stormwater Manual on the page titled 2018 Construction Stormwater Permit Public Notice and Public Informational

More information

Legal Description Part of the Southwest Quarter of the Southeast Quarter of Section 17, Decoria Township

Legal Description Part of the Southwest Quarter of the Southeast Quarter of Section 17, Decoria Township PC 32-16 Eric & Rande Baker Cut/Fill in Bluff Impact Zone CUP 12/07/2016 Applicants Eric & Rande Baker 17898 578 th Avenue Mankato, MN 56001 Request Request for review and approval of a Conditional Use

More information

Annual Inspection Report North CCR Surface Impoundment. MidAmerican Energy Company, Walter Scott Energy Center

Annual Inspection Report North CCR Surface Impoundment. MidAmerican Energy Company, Walter Scott Energy Center Annual Inspection Report North CCR Surface Impoundment MidAmerican Energy Company, Walter Scott Energy Center Rev 0 July 2018 Annual Inspection Report North CCR Surface Impoundment Prepared for MidAmerican

More information

Hunter Power Plant Coal Combustion Residuals Annual Inspection. Hunter CCR Landfill

Hunter Power Plant Coal Combustion Residuals Annual Inspection. Hunter CCR Landfill 2015 Coal Combustion Residuals Annual Inspection Hunter Power Plant Hunter CCR Landfill Prepared for PacifiCorp Energy North Temple Office 1407 West North Temple Salt Lake City, Utah 84116 Final December

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

ANNUAL INSPECTION REPORT EXISTING COAL COMBUSTION RESIDUE (CCR) LANDFILL MUSCATINE POWER & WATER

ANNUAL INSPECTION REPORT EXISTING COAL COMBUSTION RESIDUE (CCR) LANDFILL MUSCATINE POWER & WATER REPORT DATE: DECEMBER 15, 2017 A. Rule Requirement Federal CCR Rule 257.84(b) Under 257.84(b)(1) existing CCR landfills and any lateral expansion of a CCR landfill must be inspected on a periodic basis

More information

Applying landforming to reclamation: A case study in Central Appalachia

Applying landforming to reclamation: A case study in Central Appalachia Applying landforming to reclamation: A case study in Central Appalachia Leslie Hopkinson, John Quaranta April 12, 2017 Department of Civil and Environmental Engineering West Virginia University WEST VIRGINIA

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill

Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill Prepared for: Westar Energy Jeffrey Energy Center St. Marys, Kansas Prepared by: APTIM Environmental & Infrastructure,

More information

ROADS: OPERATION AND MAINTENANCE

ROADS: OPERATION AND MAINTENANCE ROADS: OPERATION AND MAINTENANCE GEMS Environmental Compliance- ESDM Training Series Kabul July / August 2016 8/1/2016 1 ROADS AND DEVELOPMENT Improved access = benefits across economic sectors Service

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 11: PGGP-EH-SPENV-000018-013 LNG Project Page 2 of 13 CONTENTS 1.0 Objectives... 3 2.0 Legal and Other

More information

Soil Erosion and Sedimentation Control (SESC) Information and Application Packet

Soil Erosion and Sedimentation Control (SESC) Information and Application Packet ARENAC COUNTY BUILDING DEPARTMENT SOIL EROSION & SEDIMENT CONTROL P.O. BOX 724 * 120 NORTH GROVE ST * STANDISH, MI 48658 PH. 989-846-9791 FAX: 989-846-9188 This institution is an equal opportunity provider.

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information

City of Glendale Stormwater Management Plan Checklist

City of Glendale Stormwater Management Plan Checklist City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP

More information

MALAMA I KE KAI - PROTECT OUR HARBOR WATERS. DOT Harbors Construction and Post- Construction Program

MALAMA I KE KAI - PROTECT OUR HARBOR WATERS. DOT Harbors Construction and Post- Construction Program MALAMA I KE KAI - PROTECT OUR HARBOR WATERS DOT Harbors Construction and Post- Construction Program Harbors Program Harbors has NPDES permits for MS4s at: Honolulu Harbor. Kalaeloa Barbers Point Harbor.

More information

Skiver Development of Arkansas, in

Skiver Development of Arkansas, in 0/?2b.r Skiver Development of Arkansas, in January 23,2007 NPDES Enforcement Section Arkansas Department of Environmental Quality P.O. Box 8913 Little Rock, Arkansas 7221 9-891 3 RE: AFIN: 60-04059 NPDES

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information

Good Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions

Good Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions September 18, 2018 Good Housekeeping Phones Weather related emergencies Breaks and facilities Introductions Goals and Objectives 1. Plan Review Process 2. Land Disturbance Permitting 3. Erosion and Sediment

More information

STORMWATER MANAGEMENT PROGRAM. Table of Contents

STORMWATER MANAGEMENT PROGRAM. Table of Contents STORMWATER MANAGEMENT PROGRAM Yakima Valley College March 1st, 0 1 0 1 Table of Contents INTRODUCTION... PROGRAM COMPONENTS... S.D.1: PUBLIC EDUCATION AND OUTREACH... Label Storm Drain Inlets:... Public

More information

Village of Suamico. Appendix D VILLAGE OF SUAMICO STORMWATER REFERENCE GUIDE FOR THE CONSTRUCTION SITE EROSION CONTROL ORDINANCE

Village of Suamico. Appendix D VILLAGE OF SUAMICO STORMWATER REFERENCE GUIDE FOR THE CONSTRUCTION SITE EROSION CONTROL ORDINANCE Appendix D VILLAGE OF SUAMICO STORMWATER REFERENCE GUIDE FOR THE CONSTRUCTION SITE EROSION CONTROL ORDINANCE DATE: May 7, 2008 Executive Summary... 1 Authority... 2 Findings of Fact... 2 Purpose... 2 Applicability

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY In the Matter of the Decision on the Need for an Environmental Impact Statement for the Proposed Remer Wastewater Treatment Facility Expansion FINDINGS

More information

NDDOT Erosion & Sediment Control Construction Course

NDDOT Erosion & Sediment Control Construction Course NDDOT Erosion & Sediment Control Construction Course Module 4: Stormwater Pollution Prevention Plan (SWPPP) 1 What s covered in this module? 1. What is a SWPPP 2. Important initial considerations that

More information

Division of Water Quality (701)

Division of Water Quality (701) Division of Water Quality (701) 328-5210 stormwater@nd.gov March April 2018 1 Construction Permit Permit #: NDR10-0000 Reissued April 1, 2015 Expires March 31, 2020 2 Discharges Covered Stormwater Discharges

More information

This annual inspection report has been prepared to meet the requirements of 40 CFR (b).

This annual inspection report has been prepared to meet the requirements of 40 CFR (b). 2015 ANNUAL INSPECTION REPORT CALEDONIA ASH LANDFILL January 11, 2016 1.0 INTRODUCTION This annual inspection report has been prepared to meet the requirements of 40 CFR 257.84(b). The active area of the

More information

CCSD#1 Stormwater Standards

CCSD#1 Stormwater Standards SECTION 6 EROSION CONTROL STANDARDS 6.1 INTRODUCTION The policies of this section shall apply during construction and until permanent measures are in place following construction as described herein, unless

More information

The Good, The Bad, and The Ugly

The Good, The Bad, and The Ugly Overview The Good, The Bad, and The Ugly Stormwater Regulations for the Construction Industry Seminar March 20, 2012 Wendy Terlizzi Arizona Department of Transportation Office of Environmental Services

More information

Module 1: Construction Site Erosion Control

Module 1: Construction Site Erosion Control Module 1: Construction Site Erosion Control Problems and Regulations Robert Pitt Department of Civil and Environmental Engineering University of Alabama Tuscaloosa, AL Problems Associated with Erosion

More information

Building Better Storm Water Quality

Building Better Storm Water Quality Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction

More information

WAKULLA SITE PLANNING

WAKULLA SITE PLANNING WAKULLA CIVIL SURVEYING SITE PLANNING TRAFFIC CONTROL PLAN WAKULLA ARRAN ROAD WIDENING & RESURFACING UTILITY CONTACT LIST NO. DATE: APPR. REVISION: DATE: CIVIL SURVEYING SITE PLANNING GENERAL NOTES WAKULLA

More information

Technical Data

Technical Data 4906-17-05 Technical Data (A) PROJECT AREA SITE have occurred in this section. (1) Geography and Topography have occurred in this section. (2) Aerial Photography have occurred in this section. (3) Site

More information

SACHSE EROSION CONTROL GUIDELINES

SACHSE EROSION CONTROL GUIDELINES SACHSE EROSION CONTROL GUIDELINES Section I. Definitions The following words, terms, and phrases, when used in this guideline, shall have the meanings ascribed to them in this Section, except where the

More information

INSPECTION REPORTS, WHAT TO LOOK FOR IN THE FIELD & PROPER INSTALLATION OF COMMON BEST MANAGEMENT PRACTICES (BMPS)

INSPECTION REPORTS, WHAT TO LOOK FOR IN THE FIELD & PROPER INSTALLATION OF COMMON BEST MANAGEMENT PRACTICES (BMPS) INSPECTION REPORTS, WHAT TO LOOK FOR IN THE FIELD & PROPER INSTALLATION OF COMMON BEST MANAGEMENT PRACTICES (BMPS) COMMON E&S BEST MANAGEMENT PRACTICES ROCK CONSTRUCTION ENTRANCE (RCE) SILT FENCE (SF)

More information

CITY OF JENKS EARTH CHANGE PERMIT APPLICATION

CITY OF JENKS EARTH CHANGE PERMIT APPLICATION CITY OF JENKS EARTH CHANGE PERMIT APPLICATION Any applicable State or Federal permits must be attached to this application or must be applied for with copies attached to this application if this permit

More information

Stormwater Management Plan Defense Logistics Agency Voorheesville Depot

Stormwater Management Plan Defense Logistics Agency Voorheesville Depot Secretary of Defense Environmental Award Pollution Prevention Non-Industrial Installation Stormwater Management Plan Defense Logistics Agency Voorheesville Depot At Voorheesville Depot, on-site stormwater

More information

Washington State University Pullman Stormwater Management Program Plan 2017

Washington State University Pullman Stormwater Management Program Plan 2017 Washington State University Pullman Stormwater Management Program Plan 2017 The Washington State University (WSU) Pullman Stormwater Management Program (SWMP) Plan has six elements derived from the Eastern

More information

CITY OF CHICO. Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects. Project Address: Building Permit Number:

CITY OF CHICO. Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects. Project Address: Building Permit Number: CITY OF CHICO Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Address: Building Permit Number: What is this document for? The City s Phase II MS4 NPDES General

More information

Post Construction Erosion Controls

Post Construction Erosion Controls Post Construction Erosion Controls Erosion Control Permanent Controls Native Vegetation Preservation Hydroseeding & Soil Stabilizers Soil Roughening Soil Stabilizers Geotextiles Vegetation is the Best

More information

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative

Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Model Poultry Burial E&S Plan (7-2-15) 1. GENERAL INFORMATION Name of project Name of person responsible Erosion and Sedimentation Pollution Control (ESPC) Plan Narrative Address Phone number Municipality

More information

SECTION 11 PART I STORMWATER QUALITY PROTECTION Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES

SECTION 11 PART I STORMWATER QUALITY PROTECTION Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES SECTION 11 PART I STORMWATER QUALITY PROTECTION CONTENTS Page 11-1 Definitions / Acronyms 11-3 PART 1 CONSTRUCTION PRACTICES 11-2 Stormwater Pollution Prevention Plan (SWPPP) 11-3 11-3 Erosion and Sediment

More information

City of West Sacramento Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects

City of West Sacramento Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Name: Page intentionally left blank. - 2 - What is this document for? The City s Phase II MS4 NPDES General Permit

More information

2017 Annual Landfill Inspection Report

2017 Annual Landfill Inspection Report 2017 Annual Landfill Inspection Report Ash Landfill Welsh Plant American Electric Power Service Corporation (SWEPCO) Cason, Texas November 17, 2017 Prepared for: SWEPCO. Prepared by: American Electric

More information

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans) Allen County Stormwater Plan Submittal Checklist The following items must be provided when applying for an Allen County Stormwater

More information

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.) Module 2: Selection of Controls and Site Planning for Construction Site Erosion Prevention Robert Pitt Department of Civil, Construction, and Environmental Engineering University of Alabama Tuscaloosa,

More information

SECTION EROSION AND SEDIMENTATION CONTROL

SECTION EROSION AND SEDIMENTATION CONTROL SECTION 02160 EROSION AND SEDIMENTATION CONTROL PART 1 GENERAL 1.1 RELATED DOCUMENTS A. The Contractor shall be held to have read all Bidding Requirements; all of the General Conditions and Supplementary

More information

General Construction Permit (GCP) Storm Water Inspections. Scott Bulgrin Pueblo of Sandia

General Construction Permit (GCP) Storm Water Inspections. Scott Bulgrin Pueblo of Sandia General Construction Permit (GCP) Storm Water Inspections Scott Bulgrin Pueblo of Sandia Storm Water The 1987 Amendments to the CWA set the process of controlling storm water pollution into motion. In

More information

Review of State and Federal Stormwater Regulations November 2007

Review of State and Federal Stormwater Regulations November 2007 Review of State and Federal Stormwater Regulations November 2007 By: James T. Spaulding, PE, CPESC Joseph M. Ducharme, Jr., PE TTG ENVIRONMENTAL CONSULTANTS, LLC 27 LOCKE ROAD, CONCORD, NH 03301-5301 TELEPHONE:

More information

City of Madison: 2017 Capital Budget Capital Improvement Plan

City of Madison: 2017 Capital Budget Capital Improvement Plan City of Madison: 2017 Capital Budget Capital Improvement Plan Agency: Stormwater Utility Project Summary Backyard Drainage Problems 25,000 25,000 25,000 25,000 25,000 25,000 CIPP Lining Storm Sewer 100,000

More information

SWPPP Inspection Procedures and Form 247 Instructions

SWPPP Inspection Procedures and Form 247 Instructions SWPPP Inspection Procedures and Form 247 Instructions 1. Pre-Construction Conference a. A stormwater pollution pre-construction conference shall be held prior to beginning work on each project. b. The

More information

Detailed Stormwater Management Report David Manchester Road

Detailed Stormwater Management Report David Manchester Road Detailed Stormwater Management Report David Manchester Road Prepared for: Nortrax Canada Inc. 189 Cardevco Road Carp, Ontario K0A 1L0 Prepared by: McIntosh Perry Consulting Engineers Ltd. 115 Walgreen

More information

Chapter 6 Erosion & Stormwater Study Team

Chapter 6 Erosion & Stormwater Study Team Chapter 6 Erosion & Stormwater Study Team Objective How do we stabilize the Las Vegas Wash environment to most effectively reduce erosion and enhance wetlands? Introduction The Las Vegas Wash (Wash) has

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED LESTER PRAIRIE WASTEWATER TREATMENT FACILITY EXPANSION

More information