CVE 471 WATER RESOURCES ENGINEERING DAMS. Assist. Prof. Dr. Bertuğ Akıntuğ

Size: px
Start display at page:

Download "CVE 471 WATER RESOURCES ENGINEERING DAMS. Assist. Prof. Dr. Bertuğ Akıntuğ"

Transcription

1 CVE 471 WATER RESOURCES ENGINEERING DAMS Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE 471 Water Resources Engineering 1/101

2 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 2/101

3 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 3/101

4 Classification of Dams A dam is an impervious barrier built across a watercourse to store water for several purposes: water supply, creating head (energy generation), forming a lake, sediment control, flood control, recharging of groundwater, etc. There are disadvantages of dams as well: imbalance of ecosystem, decrease amount of downstream water, reduction in the fertility of farmlands, etc. Therefore, detailed survey should be carried out to ensure that the relative weights of advantages over disadvantages are higher. CVE 471 Water Resources Engineering 4/101

5 Classification of Dams Dams can be classified into a number of different categories depending upon the purpose of classifications. A classification based on the type and materials of construction: Gravity Dams Concrete gravity dams Prestressed concrete gravity dams Roller compacted concrete (RCC) gravity dams Arch Dams Constant-angle arch dams Constant-center arch dams Variable-angel, variable-cemter arch dams Buttress Dams Flat-slab buttress dams Multiple-arch buttress dams Embankment (Fill) Dams CVE 471 Water Resources Engineering 5/101

6 Classification of Dams Gravity Dams Concrete gravity dams Pre-stressed concrete gravity dams Roller compacted concrete (RCC) gravity dams Karun Dam, Iran Shasta Dam, California, USA CVE 471 Water Resources Engineering 6/101

7 Classification of Dams Arch Dams Constant-angle arch dams Constant-center arch dams Variable-angel arch dams Variable-center arch dams Monticello Dam, California, USA Gordon Dam, Tasmania CVE 471 Water Resources Engineering 7/101

8 Classification of Dams Buttress Dams Used mainly in wide valleys, it consists of an impermeable wall, which is shored up by a series of buttresses to transmit the thrust of the water to the foundation. Flat-slab buttress dams Multiple-arch buttress dams CVE 471 Water Resources Engineering 8/101

9 Classification of Dams Buttress Dams Flat-slab buttress dams Lake Tahoe Dam, California, USA CVE 471 Water Resources Engineering 9/101

10 Classification of Dams Buttress Dams Multiple-arch buttress dams Bartlett Dam, Phoenix, Arizona, USA CVE 471 Water Resources Engineering 10/101

11 Classification of Dams Embankment (Fill) Dams Earth-fill dams Simple embankment Zoned embankment Diaphragm type embankment Upstream of Ataturk Dam, Turkey Embankment (Fill) Dams Rock-fill dams Downstream of Ataturk Dam, Turkey Impermeable-face Impermeable-earth core CVE 471 Water Resources Engineering 11/101

12 Classification of Dams A classifications based on purpose, such as storage diversion flood control hydropower generation A classification based on hydraulic design such as overflow dams, non-overflow dams Gilboa Dam, New York State, USA CVE 471 Water Resources Engineering 12/101

13 Classification of Dams A timber crib dam in Michigan, USA Liberty Dam, USA CVE 471 Water Resources Engineering 13/101

14 Classification of Dams A classification based on dam height: According to the International Commission on Large Dams (ICOLD): Large Dam if height > 15 m Large Dam if 10 m < height < 15 m reservoir storage > 10 6 m 3 crest length > 500 m High Dam height > 50 m Small Dam height < 10 m Distribution of dam heights in Turkey as of CVE 471 Water Resources Engineering 14/101

15 Classification of Dams Percent distribution of dams in Turkey according to purpose CVE 471 Water Resources Engineering 15/101

16 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 16/101

17 Parts of Dams A dam is composed of the following structural components Body forms the main part of a dam as an impervious barrier. Reservoir is the artificial lake behind a dam body. Spillway is that part of a dam to evacuate the flood wave from the reservoir. Water intake is a facility to withdraw water from a reservoir. Outlet facilities are those appurtenances to withdraw water from the reservoir to meet the demands or to discharge the excess water in the reservoir to the downstream during high flows. sluiceways, penstocks, diversion tunnels, bottom outlets, and water intake structures Others: Hydropower station, site installations, roads, ship locks, fish passages, etc. CVE 471 Water Resources Engineering 17/101

18 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 18/101

19 Planning of Dams There are commonly three steps in the planning and design: reconnaissance survey, feasibility study, and planning study. In reconnaissance surveys, the alternatives, which seem infeasible without performing intensive study, are eliminated. Feasibility Study: Estimation of water demand Determination of water potential Optimal plans Determination of dam site Topography Geologic information Foundation conditions Flood hazard CVE 471 Water Resources Engineering 19/101

20 Planning of Dams Feasibility Study: Determination of dam site (cont d) Spillway location and possibility Climate Diversion facilities Sediment problem Water quality Transportation facilities Right of way cost Determination of type of dams Project design Hydrologic design Hydraulic design Structural design CVE 471 Water Resources Engineering 20/101

21 Planning of Dams Planning Study: Topographic surveys Foundation studies Details on materials and constructional facilities Hydrologic study Reservoir operation study CVE 471 Water Resources Engineering 21/101

22 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 22/101

23 Construction of Dams Details of dam construction are beyond the scope of this course. The principal steps to be followed during the construction of any type of dam briefly: Evaluation of time schedule and required equipment. Diversion of river flow Foundation treatment Evaluation of Time Schedule and Required Equipment. Items to be considered: the characteristics of dam site the approximate quantities of work the preservation of construction equipment and materials diversion facilities and urgency of work CVE 471 Water Resources Engineering 23/101

24 Construction of Dams Diversion of River Flow Diversion of the river flow is may be accomplished in one of the following ways 1. Water is diverted through a side tunnel or channel. (Applicable for low flow depths ~1.5 m) Diversion by side tunnel or channel CVE 471 Water Resources Engineering 24/101

25 Construction of Dams Diversion of River Flow (cont d) Typical cross-section of earth cofferdams f: free board f=0.2(1+h) h: flow depth (meters) G=z/5 + 3 (meters) Cofferdams should be constructed during the low flow season. For fill type dams, embankment cofferdam may be kept in place as part of the embankment (e.g. Keban Dam and Ataturk Dam). For concrete dams, embankment cofferdam should be demolished after the dam has been constructed. Earth cofferdam on impervious foundation Earth cofferdam on pervious foundation CVE 471 Water Resources Engineering 25/101

26 Construction of Dams Diversion of River Flow (cont d) Hoover Dam, USA CVE 471 Water Resources Engineering 26/101

27 Construction of Dams Diversion of River Flow (cont d) Hoover Dam Overflow Tunnels (spillways), USA CVE 471 Water Resources Engineering 27/101

28 Construction of Dams Diversion of River Flow (cont d) Hoover Dam Overflow Tunnels (spillways), USA CVE 471 Water Resources Engineering 28/101

29 Diversion of River Flow (cont d) Construction of Dams Hoover Dam Overflow Tunnels (spillways), USA CVE 471 Water Resources Engineering 29/101

30 Construction of Dams Diversion of River Flow (cont d) 2. Water is discharged through the construction, which takes place in two stages. This type of diversion is normally practiced in wider valleys. Two-stage diversion CVE 471 Water Resources Engineering 30/101

31 Construction of Dams Diversion of River Flow (cont d) Two-stage diversion CVE 471 Water Resources Engineering 31/101

32 Construction of Dams Diversion of River Flow (cont d) A cofferdam on the Ohio River, Illinois, USA, built for the purpose of constructing the lock and dam. CVE 471 Water Resources Engineering 32/101

33 Construction of Dams Diversion of River Flow (cont d) Selection of a proper diversion scheme is based on the joint consideration of hydrologic characteristics of river flow, type of dam and its height, availability of materials, characteristics of spilling arrangements. The optimum design is based on cost minimization. The cost analysis is carried out for various sizes of diversion tunnels or channels to determine the corresponding total costs. The optimum tunnel diameter or bottom width of a lined trapezoidal channel is then determined according to the minimum total cost of the facility. CVE 471 Water Resources Engineering 33/101

34 Construction of Dams Foundation Treatment Foundation treatment for dams is essential to achieve less deformation under high loads, to decrease permeability and seepage, to increase shearing strength, and to satisfy slope stability for the side hills. Highly porous foundation material causes excessive seepage, uplift and considerable settlement. Such problems can be improved by a grouting operation. In this operation, the grout mix is injected under pressure to decrease the porosity, and hence to solidify the formations underlying the dam and reservoir. CVE 471 Water Resources Engineering 34/101

35 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 35/101

36 Gravity Dams Gravity dams are satisfactorily adopted for narrow valleys having stiff geological formations. Their own weight resists the forces exerted upon them. They must have sufficient weight against overturning tendency about the toe. The base width of gravity dams must be large enough to prevent sliding. These types of dams are susceptible to settlement, overturning, sliding and severe earthquake shocks. CVE 471 Water Resources Engineering 36/101

37 Gravity Dams Concrete Gravity Dams Concrete gravity dams area built of mainly plain concrete to take compressive stresses. Shasta Dam, California, USA CVE 471 Water Resources Engineering 37/101

38 Gravity Dams Concrete Gravity Dams (cont d) Concrete gravity dams have lower maintenance and operation costs compared to the other types of dams. In the design of these structures, the following criteria should be satisfied: Dimensions of the dam are chosen such that only compressive stresses develop under all loading conditions. The dam must be safe against overturning, shear and sliding. CVE 471 Water Resources Engineering 38/101

39 Gravity Dams Concrete Gravity Dams (cont d) In the construction of concrete gravity dams special care is required for the problems due to shrinkage and expansion. Formation of the body of the concrete gravity dam CVE 471 Water Resources Engineering 39/101

40 Gravity Dams Concrete Gravity Dams (cont d) Forces Acting on Gravity Dams The weight: W c = dead load Hydrostatic forces: Uplift Force: φ: uplift reduction coefficient Moment arm of F u =B(2h 1 +3h 2 ) / 3(h 1 +h 2 ) Actual uplift pressures are determined by pressure gauges installed at the bottom of the dam. Free body diagram. Forces acting on a concrete gravity dam CVE 471 Water Resources Engineering 40/101

41 Gravity Dams Concrete Gravity Dams (cont d) Forces Acting on Gravity Dams Sediment Force: γ s : submerged specific weight of soil K a : active earth pressure coefficient according to the Rankine theory. K a = (1-sinθ)/(1+sinθ) Ice Load (F i ): Free body diagram. Forces acting on a concrete gravity dam CVE 471 Water Resources Engineering 41/101

42 Gravity Dams Concrete Gravity Dams (cont d) Forces Acting on Gravity Dams Earthquake Force: F d = kw c k: earthquake coefficient Dynamic Force in the reservoir induced by earthquake F w = 0.726Ckγh 2 1 θ C = Dynamic Force acting on a spillways ΣF = ρq u obtained using momentum equation Free body diagram. Forces acting on a concrete gravity dam CVE 471 Water Resources Engineering 42/101

43 Gravity Dams Concrete Gravity Dams (cont d) Forces Acting on Gravity Dams Wave Force may be considered for wide and long reservoirs. Temperature Loads may be severe during construction because of hydration reactions Free body diagram. Forces acting on a concrete gravity dam CVE 471 Water Resources Engineering 43/101

44 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria Stability analyses are performed for various loading conditions The structure must prove its safety and stability under all loading conditions. Since the probability of occurrence of extreme events is relatively small, the joint probability of the independent extreme events is negligible. In other word, the probability that two extreme events occur at the same time is relatively very low. Therefore, combination of extreme events are not considered in the stability criteria. Floods (spring and summer) Ice load (winter). No need to consider these two forces at the same time. CVE 471 Water Resources Engineering 44/101

45 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria Usual Loading Hydrostatic force (normal operating level) Uplift force Temperature stress (normal temperature) Dead loads Ice loads Silt load Unusual Loading Hydrostatic force (reservoir full) Uplift force Stress produced by minimum temperature at full level Dead loads Silt load Extreme (severe) Loading Forces in Usual Loading and earthquake forces CVE 471 Water Resources Engineering 45/101

46 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The ability of a dam to resist the applied loads is measured by some safety factors. To offset the uncertainties in the loads, safety criteria are chosen sufficiently beyond the static equilibrium condition. Recommended safety factors: (USBR, 1976 and 1987) F.S 0 : Safety factor against overturning. F.S s : Safety factor against sliding. F.S ss : Safety factor against shear and sliding. However, since each dam site has unique features, different safety factors may be derived considering the local condition. CVE 471 Water Resources Engineering 46/101

47 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The factor of safety against overturning: F. S 0 = M M r 0 where ΣM r : total resisting moment about the toe. ΣM 0 : total overturning moment about the toe. The factor of safety against sliding: F. S s = f V H where f: coefficient of friction between any two planes ΣV: vectorial summation of vertical forces. ΣH: vectorial summation of horizontal forces. CVE 471 Water Resources Engineering 47/101

48 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The factor of safety against sliding and shear: f V + raτ s F. Sss = (in the dam) H F. S ss = f V + ca H (at foundation level) where A: Area of the shear plane, τ s : shear strength of concrete r: factor to express max allowable average shear stress r=0.33, 0.50, and 1.0 for usual, unusual, and extreme loading, respectively. f: coefficient of friction between any two planes ΣV: vectorial summation of vertical forces. ΣH: vectorial summation of horizontal forces. CVE 471 Water Resources Engineering 48/101

49 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The contact stress between the foundation and the dam or the internal stress in the dam body must be compressive: V σ = ± A Mc I Normal stress Bending or flexural stress Base pressure distribution where σ : vertical normal base pressure A: Area of the shear plane, M: net moment about the centerline of the base (M = ΣV.e) e: eccentricity ( B / 2 x) c: B/2 I : Moment of inertia (B 3 /12) ΣV: vectorial summation of vertical forces. CVE 471 Water Resources Engineering 49/101

50 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The contact stress between the foundation and the dam or the internal stress in the dam body must be compressive: In order to maintain compressive stresses in the dam or at the foundation level, the minimum pressure σ min 0. This can be achieved with a certain range of eccentricity. σ = ΣV ± A Mc I for a unit width σ min = ΣV A ΣV e B / 2 B 3 /12 = ΣV B 1 6e B 0 σ min 0 can be achieved if e B/6 Full reservoir σ max at the downstream face Empty reservoir σ max at the upstream face Base pressure distribution CVE 471 Water Resources Engineering 50/101

51 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The contact stress between the foundation and the dam or the internal stress in the dam body must be compressive: Tension along the upstream face of a gravity dam is possible under reservoir operating conditions. z = 1.0 (if there is no drainage in the dam body) z = 0.4 (if drains are used) P: hydrostatic pressure at the level under consideration CVE 471 Water Resources Engineering 51/101

52 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria Concrete gravity dams have varying thickness. Hence the inclined compressive stresses parallel to the face of the dam need to be computed. For a concrete gravity dam with slopes of 1V:mH at the upstream face and 1V:nH at the down stream face, the major principle compressive stresses, σ iu (parallel to the upstream face) and σ id (parallel to the downstream face) are obtained from the static equilibrium of forces in the vertical direction as: (ΣF y =0) where σ u and σ d vertical normal compressive stresses and p u and p d hydrostatic pressures CVE 471 Water Resources Engineering at the upstream and downstream faces, respectively. 52/101

53 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria Internal horizontal and vertical shear stresses at the upstream and downstream faces are obtained by equating the total moment to zero as (ΣM A =0, ΣM B =0): where τ hu, τ hd, τ vu, and τ vd are the horizontal and vertical internal shear stresses at the upstream and downstream faces, respectively. CVE 471 Water Resources Engineering 53/101

54 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria The maximum compressive stress, σ max,must be smaller than a certain fraction of the compressive strength of concrete, σ c, and foundation material, σ f. Safety criteria for concrete gravity dams Unconfined compressive strength, σ f for foundation materials CVE 471 Water Resources Engineering 54/101

55 Gravity Dams Concrete Gravity Dams (cont d) Stability Criteria Excessive care must be taken during the filling of the reservoir. Initially 1/3 of the dam height may be filled first. After waiting for several weeks and assuring that the dam is safe, further filling is performed. Since safety levels change with respect to upstream water depth, gravity dams must be analyzed for various operating levels and empty reservoir cases, separately. For the empty reservoir case, the overturning tendency must be checked with respect to the toe and heel, separately. The stability against sliding may be improved by providing a cut off wall in the foundation at the upstream side. CVE 471 Water Resources Engineering 55/101

56 Gravity Dams Prestressed Concrete Gravity Dams In a prestress concrete dam, forces are applied to the dam before the reservoir is filled in order to counter undesirable stress that would develop in the absence of the prestressing forces. For prestressing, either small-diameter high-tensile wires or hightensile steel bars can be used. Roller Compacted Concrete (RCC) Gravity Dams RCC dam is constructed using cement, water, fine and course aggregates, and fly ash which are mixed in certain proportions to have a no-slump, rather dry composition. Construction is based on the compaction of this mixture by heavy static or vibrating rollers. Construction period of RCC dams is shorter than that of conventional concrete gravity dams. CVE 471 Water Resources Engineering 56/101

57 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 57/101

58 Arch Dams Arch dams are thin concrete structures. Gokcekaya, Oymapinar, Karakaya, Gezende, and Berke dams in Turkey. Gokcekaya Dam Berke Dam Karakaya Dam CVE 471 Water Resources Engineering 58/101

59 Arch Dams Arch dams: Oymapinar Dam, Turkey CVE 471 Water Resources Engineering 59/101

60 Arch Dams Hoover Dam, USA CVE 471 Water Resources Engineering 60/101

61 Arch Dams Arch dams are thin concrete structures. Stability of an arch dam is based on its self weight and its ability to transmit most of the imposed water loads into the valley walls. At the sites of arch dams, the side formations and foundations should be very stiff to resist the applied load. For effective arching action, the radius of the arch should be as small as possible. They are formed by concrete blocks having base dimensions of approximately 15 m by 15 m and height of 1.5 m Reinforcement is not generally required in thick arch dams because it increases the cost drastically. Arch dams have normally higher structural safety than conventional gravity dams. CVE 471 Water Resources Engineering 61/101

62 Arch Dams Types of Arch Dams Arch dams are classified according to geometric characteristics of the valley where they are adopted. Arch dams are classified according to the location of the center and magnitude of the central angle Constant-center (variable angle) arch dams are suitable for medium-high dams in U-shape valleys. They have single curvature in plan with vertical upstream face. CVE 471 Water Resources Engineering 62/101

63 Arch Dams Types of Arch Dams Variable-center (constant angle) arch dams are suitable for V-shape valleys. Radius of the arc reduces with respect to depth. So arching action is more pronounced at low depths. Since these types of dams are normally thinner than constant-center dams, they are more elastic and safer. Variable-center (constant angle) arch dams CVE 471 Water Resources Engineering 63/101

64 Arch Dams Types of Arch Dams Variable-center (variable angle) arch dams are composed of the combination of two types described above. Load distribution in vertical direction governs the cross-sectional shape of the dam. This type has a pronounced double curvature They utilized the concrete strength more compared the other types resulting in thinner and more efficient structure. However, tensile stresses may develop in the dam body. Variable-center (variable angle) arch dams Gokcekaya Dam CVE 471 Water Resources Engineering 64/101

65 Arch Dams Types of Arch Dams Variable-center (variable angle) arch dams Gokcekaya Dam Cross-section of Gokcekaya Dam CVE 471 Water Resources Engineering 65/101

66 Arch Dams Design of Arch Dams Structural design of an arch dam requires the determination of load distribution in the dam body using the trial load method and applications of the theory of elasticity and the theory of shells. Structural design is beyond the scope of this course. Simplified design: The determination of the thickness at any elevation of an arch dam whose crest elevation has already been determined in the hydrologic design step. In the arch dams, the total load is shared by arch and cantilever actions and transmitted to the sides and foundation, respectively. Therefore, the base width of arch dams is usually much narrower than that of concrete gravity dams having almost the same height. Hence, the effect of uplift pressure can be ignored. CVE 471 Water Resources Engineering 66/101

67 Arch Dams Design of Arch Dams However, effect of temperature stresses should be checked to ensure that they are smaller than tensile strength. Near the crest of the dam, most of the loads taken by arches and transmitted to the side abutments. Near the bottom of the dam, cantilevers take most of the load and transmit to the foundation. Gokcekaya Dam CVE 471 Water Resources Engineering 67/101

68 Arch Dams Design of Arch Dams In the following analysis, the water thrust induced by hydrostatic pressure is assumed to be taken by arch action only and transmitted to the sides. The differential force acting on a differential element having a central angle of dφ is df v = P r dφ The vertical component of this force is df' v = P r dφ sinφ Free-body diagram for arch dam analysis CVE 471 Water Resources Engineering 68/101

69 Arch Dams Design of Arch Dams Integration of this force along the arc length gives the total horizontal force, H h. H h π 2 π = 2 γhr sinφ dφ = 2γhr cos 2 π θ a 2 2 π θ cos a 2 2 θ = 2γhr sin a 2 Free-body diagram for arch dam analysis where h: the height of the arch rib relative to the reservoir surface r: the radius of arch θ a : the central angle CVE 471 Water Resources Engineering 69/101

70 Arch Dams Design of Arch Dams The equilibrium of forces in y- direction involves where Therefore H h = 2R y θ R R a y = sin 2 θ hr a θ 2γ sin = R a 2 sin 2 2 R = γhr where R: the reaction offered by the sides against the transmission of water thrust. Free-body diagram for arch dam analysis As observed from the R = γhr, the reaction at the sides is directly proportional to the arc radius at a given height. Therefore, narrow valleys having stiff geological formations and small r-values are suitable for arch dams. CVE 471 Water Resources Engineering 70/101

71 Arch Dams Design of Arch Dams If the thickness of the arch rib, t, is relatively small as compared with r, there is small difference between the average and maximum compressive stresses in the rib and σ R/t. The required thickness of the rib is then t γhr σ = (the thickness varies linearly with depth.) all where σ all : the allowable working stress for concrete in compression. CVE 471 Water Resources Engineering 71/101

72 Arch Dams Design of Arch Dams The volume of concrete per unit height of a single arch rib across a canyon of width of B a is V=Lt where L is the arch length which is equal to rθ a (θ a in radians). Inserting the values of L and t into the equation above V h = σ γ 2 all r θ a CVE 471 Water Resources Engineering 72/101

73 Arch Dams Design of Arch Dams The optimum central angle θ a for a minimum volume of arch rib can be determined as 133º34 by differentiating V with respect to θ a and equating the result to zero. This is the reason why a constant-angle arch dam can be design to require less concrete than a constant-center dam. In practice, the central angles of arch dams vary from 100º to 140º. However, the formwork of a constant-angle dam is more difficult. CVE 471 Water Resources Engineering 73/101

74 Arch Dams Design of Arch Dams The optimum central angle θ a for a minimum volume of arch rib can be determined as 133º34 by differentiating V with respect to θ a and equating the result to zero. This is the reason why a constant-angle arch dam can be design to require less concrete than a constant-center dam. In practice, the central angles of arch dams vary from 100º to 140º. However, the formwork of a constant-angle dam is more difficult. CVE 471 Water Resources Engineering 74/101

75 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 75/101

76 Buttress Dams A buttress dam consists of a sloping slab. Depending on the orientation of slab, a buttress dam may be classified as flat-slab buttress dam multiple-arch buttress dam Elmali Dam construction, Istanbul, 1941 A typical buttress dam. CVE 471 Water Resources Engineering Elmali Dam 76/101

77 Buttress Dams Flat-slab buttress dams Lake Tahoe Dam, California, USA CVE 471 Water Resources Engineering 77/101

78 Buttress Dams Multiple-arch buttress dams Bartlett Dam, Phoenix, Arizona, USA CVE 471 Water Resources Engineering 78/101

79 Buttress Dams Some advantages of buttress dams over conventional gravity dams: They can be constructed on foundations having smaller bearing capacity then required for gravity dams. Since they have thinner slabs, possibility of development of vertical cracks is less. Problems encountered during the setting of concrete are reduced. Unless a mat foundation is used, uplift forces are negligibly small because of hollow spaces provided between the buttresses. Ice pressures are also small as the ice sheet slides up the inclined slab. Main disadvantage of buttress dams: May have comparable costs, because of increased formwork and reinforcement. There is only one buttress dam in Turkey (Elmali 2 Dam). Elmali 2 Dam CVE 471 Water Resources Engineering 79/101

80 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 80/101

81 Embankment (Fill) Dams They composed of fill of suitable earth materials at the dam site. Coarse-grained soils (gravel and coarse sand) relatively pervious, easily compacted, resistant to moisture, Clay is considered as a core material (impermeable) unstable when saturated (expands due to wetting, hard to compact) Therefore, clay mixed with sand and fine gravel is used as a core. Core must be compacted in thinner layers with fairly accurate moisture control. Compacted asphalt may also be used as an economical core material in case of loose foundations. Asphalt can absorb earthquake shocks effectively. CVE 471 Water Resources Engineering 81/101

82 Embankment (Fill) Dams Embankment dams are usually safer against deformations and settlements. Embankment dams Earth-fill dams Rock-fill dams (More than 50% of the total material is of rock.) Earth-fill dams in Turkey Seyhan Dam Demirkopru Dam Cubuk 2 Dam Bayindir Dam Rock-fill dams in Turkey Keban Dam Ataturk Dam Hasan Ugurlu Dam Hasan Ugurlu Dam CVE 471 Water Resources Engineering 82/101

83 Embankment (Fill) Dams Body volume of embankment dams is relatively greater than the other types of dams. Normally cheaper than the other types where there is enough fill material in the close vicinity. Fill dams comprise more than 70% of the dams in the world and 90% in Turkey. Keban Dam CVE 471 Water Resources Engineering 83/101

84 Embankment (Fill) Dams Earth-fill Dams Construction: Placement of selected material on layers of 50 cm thick and compaction. Non-organic and non-plastic soils are needed. The embankment soil is usually irrigated at the borrow area. Piezometers can be placed in the embankment at various depths during the construction to measure the pore water pressure. A typical earth-fill dam is constructed in a multi-layer formation. CVE 471 Water Resources Engineering 84/101

85 Embankment (Fill) Dams Earth-fill Dams A typical earth-fill dam is constructed in a multi-layer formation. Earth dam on pervious foundation CVE 471 Water Resources Engineering 85/101

86 Embankment (Fill) Dams Earth-fill Dams Seepage through an earth-fill dam. The flow rate, q, between two flow lines can be expressed using the Darcy law as q = The total flow rate, q h KAi = K D L Kh q = N N K: the hydraulic conductivity i : the hydraulic gradient h: head loss (h/n) N : number of equipotential drops N : the number of stream tubes CVE 471 Water Resources Engineering 86/101

87 Embankment (Fill) Dams Earth-fill Dams Drainage systems in an earth-fill dam. Chimney drains, in the embankment as well as enlarged toe drains are effective in controlling the seepage through the dam. CVE 471 Water Resources Engineering 87/101

88 Embankment (Fill) Dams Rock-fill Dams Having relatively high pore space Can be adopted to weaker foundations where a gravity dam cannot be constructed. Cross-sections of typical rock-fill dams CVE 471 Water Resources Engineering 88/101

89 Embankment (Fill) Dams Rock-fill Dams (Ataturk Dam) Largest dam in Turkey Reservoir Volume: 48.7 x 10 9 m 3 Installed capacity: 2400 MW Annual energy production: 8.9 x 10 9 kwh Irrigated land: ha (with the completion of the project) A cross-sections of the Ataturk Dam CVE 471 Water Resources Engineering 89/101

90 Embankment (Fill) Dams Rock-fill Dams (Ataturk Dam) A cross-sections of the Ataturk Dam CVE 471 Water Resources Engineering 90/101

91 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 91/101

92 Cross-sectional Layout Design of Dams A suitable dam cross-section should be provided such that both safety and desired functionality concerning service requirement are attained. Sufficient crest width, t c must be provided. a width of two lane traffic may be selected. For small embankment dams up to H f =15 m. t c =0.2H f +3 For large embankment dams up to H f =150 m. t c =3.6 (H f ) 1/3 where t c and H f are in meter. CVE 471 Water Resources Engineering 92/101

93 Cross-sectional Layout Design of Dams By examining some existing muti-purpose concrete gravity dams throughout the world, Yanmaz et al. (1999) proposed the following regression equations to define the shape of a gravity dam. H * = H t t c = H t where all variables are in meter CVE 471 Water Resources Engineering 93/101

94 Cross-sectional Layout Design of Dams United States Bureau of Reclamation (USBR) propose the following formulas for cross-sectional layout of arch dams: t t t c b 0.45H t = 0.01 = 3 = 0.95t ( H + 1.2B ) H b t t B a a B 0.15 Ht 400 H t / 400 All the dimensions are in ft where B a : the span width at the crest B 0.15 : the span width at 15% of the dam height above the base t 0.45Ht : the dam thickness at 45% of the dam height above the base. CVE 471 Water Resources Engineering 94/101

95 Cross-sectional Layout Design of Dams The crest elevation of a dam is to be determined such that there is almost no overtopping danger of the flood wave during the occurance of the design flood. Freeboards on flood levels for concrete and embankment dams Greater freeboards are required for embankment dams since they are susceptible to erosion at the downstream face due to overtopping from their crest. The required side slopes of concrete gravity dams are determined from stability analyses. The maximum downstream slope of gravity dams is 45. Side slopes of embankment dams are determined on the basis of seepage and slope stability analyses. CVE 471 Water Resources Engineering 95/101

96 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 96/101

97 Local Scour at the Downstream of Dams Excessive kinetic energy of the flowing water at the downstream of outlet works (spillways, sluiceways etc.) should be dissipated in order to prevent the erosion of the streambed and the banks below the dam. Local scour at the downstream of the dam and sluice gates Excessive scours at the downstream of Keban Dam have resulted in serious foundation stability problems (depth of approx 30 m). CVE 471 Water Resources Engineering 97/101

98 Local Scour at the Downstream of Dams Some of the scour prediction equations are given in the table. Scour prediction equations for the downstream of dams. d s : the maximum depth of scour hole in m. b: the thickness of the jet in m. Φ: the side inclination for the scour hole, Fr: Jet Froude number. U: the velocity of the jet in m/s =(γ s - γ)/γ, γ s: : specific weight of sediment in kn/m 3 γ : specific weight of water in kn/m 3. W f : Fall velocity in m/s q: unit discharge in m 3 /s/m H g : gross head in m h: tailwater depth in m D 50 : median size of bed material in m. CVE 471 Water Resources Engineering 98/101

99 Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Buttress Dams Embankment (Fill Dams) Cross-sectional Layout Design of Dams Local Scour at the Downstream of Dams Dam Safety and Rehabilitation CVE 471 Water Resources Engineering 99/101

100 Dam Safety and Rehabilitation Excessive care must be taken in planning, design, and construction stages of a dam. Major causes for a dam break: Inadequate spillway capacity, Improper construction of any type of dam, Insufficient compaction of embankment dams or compaction with undesirable water content, Improper protective measures, Excessive settlements, etc Continuous inspection and monitoring are required to assess the safety level of the dam throughout the lifetime. CVE 471 Water Resources Engineering 100/101

101 Dam Safety and Rehabilitation Upon periodic inspection, the following deficiencies may be observed that are indicators of problems: Large horizontal and vertical movements of crest, Tilting of the roadway along the crest, Deformation of embankment slope, Higher than usual pore water pressure in embankment dams, Unusual seepage at the toe or edges of an embankment dam, Seepage flows with not decreasing with low flow conditions, Turbit outflow through the embankment, Tilting of the spillway crest Increased leakage into inspection galleries in concrete dams, etc. CVE 471 Water Resources Engineering 101/101

WATER RESOURCES ENGINEERING DAMS

WATER RESOURCES ENGINEERING DAMS WATER RESOURCES ENGINEERING DAMS Overview Classification of Dams Parts of Dams Planning of Dams Construction of Dams Concrete Gravity Dams Arch Dams Cross-sectional Layout Design of Dams Local Scour at

More information

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Created by Simpo PDF Creator Pro (unregistered version)  Asst.Prof.Dr. Jaafar S. Maatooq Lect.No.9 2 nd Semester Barrages, Regulators, Dams 1 of 15 In order to harness the water potential of a river optimally, it is necessary to construct two types of hydraulic structures, as shown in Figure

More information

PE Exam Review - Geotechnical

PE Exam Review - Geotechnical PE Exam Review - Geotechnical Resources and Visual Aids Item Page I. Glossary... 11 II. Parameters... 9 III. Equations....11 IV. Tables, Charts & Diagrams... 14 1. Module 1 - Soil Classification... 14

More information

Lecture Retaining Wall Week 12

Lecture Retaining Wall Week 12 Lecture Retaining Wall Week 12 Retaining walls which provide lateral support to earth fill embankment or any other form of material which they retain them in vertical position. These walls are also usually

More information

A dam and a reservoir are complements of each other.

A dam and a reservoir are complements of each other. A dam is a hydraulic structure of fairly impervious material built across a river to create a reservoir on its upstream side for impounding water for various purposes. A dam and a reservoir are complements

More information

DESIGN AND DETAILING OF RETAINING WALLS

DESIGN AND DETAILING OF RETAINING WALLS DESIGN AND DETAILING OF RETAINING WALLS (For class held from nd April 07) Dr. M. C. Nataraja, Professor, Civil Engineering Department, Sri Jayachamarajendra Collge of Engineering, Mysore-5a70 006 Phone:

More information

Chapter 13: Retaining Walls

Chapter 13: Retaining Walls Chapter 13: Retaining Walls Introduction In general, retaining walls can be divided into two major categories: (a) conventional retaining walls and (b) mechanically stabilized earth walls Conventional

More information

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction Ö. Özen, H. Küsmez, A. Akman Dam and Tunnel Projects Director, İLCİ Holding & TR COLD Member, Ankara, Turkey

More information

Design of Semi gravity Retaining Walls

Design of Semi gravity Retaining Walls Design of Semi gravity Retaining Walls Example 13.1 A semi gravity retaining wall consisting of plain concrete (weight = 145 lb/ft³) is shown in Figure 13.9. The bank of supported earth is assumed to weigh

More information

Retaining Wall Design

Retaining Wall Design SIL 211 MEKANIKA TANAH Retaining Wall Design DR. IR. ERIZAL, MAGR DEPARTEMEN TEKNIK SIPIL DAN LINGKUNGAN FAKULTAS TEKNOLOGI PERTANIAN IPB 1 Conventional Retaining Walls Gravity Retaining Structures Stability

More information

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water The diversion works for the Cua Dat CFRD in Vietnam Michel Ho Ta Khanh, Dinh Sy Quat, Prof Pham Hong Giang VNCOLD No 95/10 Chua Boc Street Dong Da District Hanoi Vietnam Abstract The Cua Dat CFRD is constructed

More information

Earthquake Design of Flexible Soil Retaining Structures

Earthquake Design of Flexible Soil Retaining Structures Earthquake Design of Flexible Soil Retaining Structures J.H. Wood John Wood Consulting, Lower Hutt 207 NZSEE Conference ABSTRACT: Many soil retaining wall structures are restrained from outward sliding

More information

TUG - Institute of Hydraulic Engineering and Water Resources Management 1

TUG - Institute of Hydraulic Engineering and Water Resources Management 1 Large Dams Design, Construction and Performance Gerald Zenz Graz - University of Technology 1 Dam Structures & Geotechnique Design Construction / Observation Operation / Monitoring Cooperation & Transfer

More information

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d

Design Data 6. Loads and Supporting Strengths Elliptical and Arch Pipe. Values of B d Design Data 6 Loads and Supporting Strengths Elliptical and Arch Pipe The hydraulic and structural characteristics of elliptical and arch shapes offer advantages, under certain conditions, over the circular

More information

WATER STORAGE, TRANSPORT, AND DISTRIBUTION Selection of Type of Dams and Reservoirs - Osamu Arai, Kyohei Baba,and Tosho Hirose

WATER STORAGE, TRANSPORT, AND DISTRIBUTION Selection of Type of Dams and Reservoirs - Osamu Arai, Kyohei Baba,and Tosho Hirose SELECTION OF TYPE OF DAMS AND RESERVOIRS Osamu Arai Vice President of Konoike Construction Co., Ltd., Japan Kyohei Baba K. Baba Engineering Consultants Co., Japan Tosho Hirose Japan Commission on Large

More information

New innovative technique for strengthening old buttress dams and multiple arch dams

New innovative technique for strengthening old buttress dams and multiple arch dams New innovative technique for strengthening old buttress dams and multiple arch dams Thomas Konow Consultant engineer Dam safety E-mail: thomas.konow@gmail.com ABSTRACT: This article presents a new method

More information

DESIGN OF RETAINING WALLS

DESIGN OF RETAINING WALLS DESIGN OF RETAINING WALLS Dr. Izni Syahrizal bin Ibrahim Faculty of Civil Engineering Universiti Teknologi Malaysia Email: iznisyahrizal@utm.my Introduction Retaining wall is used to retain earth or other

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Fig: Alignment of a ridge or watershed canal (Head reach of a main canal in plains)

Fig: Alignment of a ridge or watershed canal (Head reach of a main canal in plains) SYSTEM OF IRRIGATION CANAL CHAPTER 6 Alluvial Soil and Non-Alluvial Soil The soil which is formed by transportation and deposition of silt through the agency of water, over a course of time, is called

More information

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination

Highway Drainage 1- Storm Frequency and Runoff 1.1- Runoff Determination Highway Drainage Proper drainage is a very important consideration in design of a highway. Inadequate drainage facilities can lead to premature deterioration of the highway and the development of adverse

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 Alberta Transportation Water Control Structures Selected Design Guidelines Alberta Environment Page 17-1 17.0 MAIN CANAL CONVEYANCE STRUCTURES 17.1 General Conveyance structures typically employed on main

More information

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment. POND SITE SELECTION AND CONSTRUCTION Uses, Planning, & Design David Krietemeyer Area Engineer USDA-NRCS June 20, 2008 Uses Considerations for Location of Commonly Used Terms Pond A water impoundment made

More information

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08 (b) Discuss in brief shaft spillway with neat sketches. Marks 04 OR Q (2) Explain in brief USBR stilling basin. Marks 08 Stilling Basins The basins are usually provided with special appurtenances including

More information

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL SLI Doc. No. 505573-3000-40EC-0003 01 5-Dec-2013 ii TABLE OF CONTENTS Page No. 1 INTRODUCTION... 1 2 CREST ELEVATIONS... 2 2.1 Cofferdams... 2 2.2 North Spur... 3 3 STABILITY ANALYSIS LOADING CASES AND

More information

APPENDIX G HYDRAULIC GRADE LINE

APPENDIX G HYDRAULIC GRADE LINE Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm

More information

5.4 Analysis for Torsion

5.4 Analysis for Torsion 5.4 Analysis for Torsion This section covers the following topics. Stresses in an Uncracked Beam Crack Pattern Under Pure Torsion Components of Resistance for Pure Torsion Modes of Failure Effect of Prestressing

More information

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall SWM MD-378 Pond Checklist Training 10/17/07 Ken Wolfe Warren Johnson USDA, NRCS Frederick, Maryland ROLES AND RESPONSIBILITIES Small Pond Approval MDE, WMA, Dam Safety Division Authority (COMAR 26.17.04.03)

More information

A Case Study: Foundation Design in Liquefiable Site

A Case Study: Foundation Design in Liquefiable Site RESEARCH ARTICLE OPEN ACCESS A Case Study: Foundation Design in Liquefiable Site Tahar Ayadat* *(Department of Civil Engineering, College of Engineering, PMU University, P.O. Box 1664, Al-Khobar, 31952,

More information

Design of Rigid Pavements

Design of Rigid Pavements Traffic and Highway Engineering (ІІ) CVL 4324 Chapter 20 Design of Rigid Pavements Dr. Sari Abusharar Assistant Professor Civil Engineering Department Faculty of Applied Engineering and Urban Planning

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA Overview Romania has built 2,617 dams out of which 246 are large and medium dams and 1260 are small dams, as per

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

River management in Japan With focus on river levee

River management in Japan With focus on river levee River management in Japan With focus on river levee January 2009 Masahiro Atsumi River Bureau, Ministry of Land, Infrastructure, Transport and Tourism, Japan Objectives of river management Article 1 of

More information

BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS

BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS Slide No. 1 Bending of In the previous discussion, we have considered only those beams that are fabricated from a single material such as steel. However, in

More information

Topic: Site Formation

Topic: Site Formation Topic: Site Formation Presentation prepared by Raymond Wong February 2006 Purpose of site formation is to prepare a piece of land in order to: Accommodate building/s or other facilities which will be placed

More information

Types of Foundations

Types of Foundations Shallow Foundations Types of Foundations Foundations can be classified to two major categories: Shallow. Deep. 1 Introduction If the soil stratum is suitable for supporting the structural loads from the

More information

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND AND Introduction to Structural Analysis TYPES OF STRUCTURES LOADS INTRODUCTION What is the role of structural analysis in structural engineering projects? Structural engineering is the science and art

More information

Homework # 4 - Solutions Fluid Flow (5 problems)

Homework # 4 - Solutions Fluid Flow (5 problems) Homework # 4 - Solutions Fluid Flow (5 problems) 1. An open-ended cylindrical standpipe contains a soil specimen as shown below. The soil is saturated with void ratio = 0.75 and specific gravity = 2.7.

More information

Prepared for Urban Drainage and Flood Control District

Prepared for Urban Drainage and Flood Control District BERM FAILURE TECHNICAL ANALYSES SOUTH PLATTE GRAVEL PIT EVALUATION CRITERIA Prepared for Urban Drainage and Flood Control District Wright Water Engineers, Inc. January 2013 121-030.000 TABLE OF CONTENTS

More information

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams

Types of Inspections. Prior to Inspection. Types of Inspections. Typical Inspection Equipment. Embankment Dams BIA Summer Water Resources Training Dam Safety Inspections Part 4 - Inspections July 28, 2012 Presented by Michael Johnson, Ph.D., P.E. Types of Inspections Periodic Inspections A comprehensive visual

More information

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016 SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri September 21, 2016 CONTENT Introduction Potential in Southeast Asia Challenges in Small Hydro Main Design Steps (Bad) Examples

More information

Lecture 20: Groundwater Introduction

Lecture 20: Groundwater Introduction Lecture 20: Groundwater Introduction Key Questions for Groundwater 1. What is an aquifer? 2. What is an unconfined aquifer? 3. What is groundwater recharge? 4. What is porosity? What determines the magnitude

More information

WEEK 9 ACTIVITY. Lecture (3 hours) Self Assessment. 34 slides

WEEK 9 ACTIVITY. Lecture (3 hours) Self Assessment. 34 slides WEEK 9 ACTIVITY Lecture (3 hours) 34 slides Self Assessment Site Investigation (ECG513) ARM - 2009 LEARNING OUTCOMES Week 9 : (3H) Coverage : Geophysical Methods, Permeability and Ground Stress measurement.

More information

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp Geneva Dam Design of a Steep, Temporary, Riprap Ramp A Run-of of-river Dam Analysis for Geneva Dam Credit to: Yu-Chun Su, Ph.D., P.E., CFM David T. Williams. Ph.D., P.E, CFM Presentation Purpose History

More information

Dam Safety Inspection Checklist

Dam Safety Inspection Checklist Dam Safety Inspection Checklist Complete All Portions of This Section (Pre-inspection) Date of Inspection: Name of Dam: EAP: (yes, no) OM&I: (yes, no) File Number: Review Inventory - Highlight missing

More information

Advance Design of RC Structure Retaining Wall

Advance Design of RC Structure Retaining Wall 1 Retaining Wall Retaining Walls What are retaining walls Retaining walls are soil-structure systems intended to support earth backfills. Type of retaining walls Gravity retaining wall gravity walls rely

More information

Drop Height For Channel Erosion Control

Drop Height For Channel Erosion Control Drop Height For Channel Erosion Control James C.Y. Guo, Professor and Director Department of Civil Engineering, U. of Colorado at Denver, Denver, Colorado 8017 E-mail: James.Guo@cudenver.edu Introduction

More information

CHAPTER 13 OUTLINE The Hydrologic Cycle and Groundwater. Hydrologic cycle. Hydrologic cycle cont.

CHAPTER 13 OUTLINE The Hydrologic Cycle and Groundwater. Hydrologic cycle. Hydrologic cycle cont. CHAPTER 13 OUTLINE The Hydrologic Cycle and Groundwater Does not contain complete lecture notes. To be used to help organize lecture notes and home/test studies. Hydrologic cycle The hydrologic cycle is

More information

A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures

A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures CFA Technical Note: 008-2010 A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures CFA Technical This CFA Technical Note is intended to serve as a guide to assist

More information

Sabah Shawkat Cabinet of Structural Engineering 2017

Sabah Shawkat Cabinet of Structural Engineering 2017 3.1-1 Continuous beams Every building, whether it is large or small, must have a structural system capable of carrying all kinds of loads - vertical, horizontal, temperature, etc. In principle, the entire

More information

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams by James K. Mitchell, Sc.D., P.E., Dist. M.ASCE University of Alberta, Edmonton, Alberta October 6, 2010 1 SCOPE OF THE LECTURE

More information

THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS

THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS Ninth International Water Technology Conference, IWTC9 2005, Sharm El-Sheikh, Egypt 355 THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS Yasser Shawky ( 1), Hala Badawy ( 2) (1) Researcher,

More information

Chapter A-15. CID-MO Structural Analysis

Chapter A-15. CID-MO Structural Analysis Kansas Citys, Missouri and Kansas Flood Risk Management Feasibility Study Engineering Appendix to the Final Feasibility Study Chapter A-15 CID-MO Structural Analysis Chapter A-15 CID-MO Structural Analysis

More information

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011 APPENDIX A EARTHEN EMBANKMENT VERSION 1.0 March 1, 2011 SECTION A-1: DESCRIPTION OF PRACTICE An earthen embankment is a raised impounding structure made from compacted soil. The embankment is the feature

More information

Characteristic study on seepage field of dam under cutoff wall construction defects and freeze in winter

Characteristic study on seepage field of dam under cutoff wall construction defects and freeze in winter Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(6):1094-1098 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 Characteristic study on seepage field of dam under

More information

Outlet Flow Velocity in Circular Culvert

Outlet Flow Velocity in Circular Culvert Archives of Hydro-Engineering and Environmental Mechanics Vol. 61 (2014), No. 3 4, pp. 193 203 DOI: 10.1515/heem-2015-0013 IBW PAN, ISSN 1231 3726 Outlet Flow Velocity in Circular Culvert Wojciech Szpakowski

More information

THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM

THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM 6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, 23 25 October 2012 THE USE OF 400 MM RCC LIFTS IN THE ENLARGED COTTER DAM Peter BUCHANAN Principal Dams Engineer, Bulk Water

More information

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM T. C. NEEL and K.BOZKURT ABSTRACT This work shall consist of the design, manufacture

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR RIPRAP. Conditions Where Practice Applies STANDARD FOR RIPRAP Definition A layer of loose rock, aggregate, bagged concrete, gabions, or concrete revetment blocks placed over an erodible soil surface. Purpose The purpose of riprap is to protect

More information

Chapter. Masonry Design

Chapter. Masonry Design Chapter Masonry Design The masonry design section contains modules for the analysis of reinforced masonry beams subjected to pure bending and unreinforced masonry walls subjected to axial compression and

More information

CHAPTER 11: PRESTRESSED CONCRETE

CHAPTER 11: PRESTRESSED CONCRETE CHAPTER 11: PRESTRESSED CONCRETE 11.1 GENERAL (1) This chapter gives general guidelines required for the design of prestressed concrete structures or members with CFRM tendons or CFRM tendons in conjunction

More information

SECTION2 Drainage Control for Surface Mines

SECTION2 Drainage Control for Surface Mines SECTION2 Drainage Control for Surface Mines 11 Horizontal Drains-Their Use in Open Pit Mine Dewatering by Ben L. Seegmiller, Principal, Seegmiller Associates, Salt Lake City, Utah, USA INTRODUCTION Horizontal

More information

Irrigation Structures 2. Dr. M. R. Kabir

Irrigation Structures 2. Dr. M. R. Kabir CHAPTER 9 Irrigation Structures 2 Dr. M. R. Kabir Professor and Head, Department of Civil Engineering University of Asia Pacific (UAP), Dhaka LECTURE 22 What is Cross Drainage Works? In an irrigation project,

More information

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT CHAPTER Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 19 By Dr. Ibrahim

More information

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS Dipl.-Wirt.Ing. Oliver Freudenreich Friedr. Ischebeck GmbH phone: ++49 2333 8305-0 Loher Str. 31 79 fax: ++49 2333 8305-55 e-mail: freudenreich@ischebeck.de D-58256 Ennepetal www.ischebeck.com INNOVATIVE

More information

LIGHTWEIGHT FILL DESIGN GUIDANCE

LIGHTWEIGHT FILL DESIGN GUIDANCE Preferred Design Procedure LIGHTWEIGHT FILL The Federal Highway Administration (FHWA) and National Cooperative Highway Research Program (NCHRP) have two documents for this technology that contain design

More information

Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles

Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles by 1 Dennes T. Bergado and 2 Glen A. Lorenzo 1 Professor and 2 Doctoral Candidate, respectively Geotechnical

More information

Preview of LEAME Computer Software

Preview of LEAME Computer Software Appendix Preview of LEAME Computer Software Thus far, this book has focused on the fundamental principles and methods for analyzing slope stability using the limit equilibrium method. The computer software

More information

TENSILE STRESSES IN CONCRETE DAMS

TENSILE STRESSES IN CONCRETE DAMS Water Power and Dam Construction, April, 2005 TENSILE STRESSES IN CONCRETE DAMS Dr. Martin Wieland Chairman, ICOLD Committee on Seismic Aspects of Dam Design, c/o Electrowatt-Ekono Ltd. (Jaakko Pöyry Group),

More information

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geotechnical Engineering Office Civil Engineering Department The Government of the Hong Kong Special Administrative Region

More information

APPENDIX B ABC STRUCTURES DESIGN GUIDE

APPENDIX B ABC STRUCTURES DESIGN GUIDE APPENDIX B ABC STRUCTURES DESIGN GUIDE The Cohos Evamy Partners TABLE OF CONTENTS Page No. DISCLAIMER... I 1. STRUCTURAL DESIGN GUIDELINES... 1 2. GENERAL REQUIREMENTS (FIGURE B.2, STEP 1)... 1 3. GENERAL

More information

In-plane testing of precast concrete wall panels with grouted sleeve

In-plane testing of precast concrete wall panels with grouted sleeve In-plane testing of precast concrete wall panels with grouted sleeve P. Seifi, R.S. Henry & J.M. Ingham Department of Civil Engineering, University of Auckland, Auckland. 2017 NZSEE Conference ABSTRACT:

More information

Modelling of RC moment resisting frames with precast-prestressed flooring system

Modelling of RC moment resisting frames with precast-prestressed flooring system Modelling of RC moment resisting frames with precast-prestressed flooring system B.H.H. Peng, R.P. Dhakal, R.C. Fenwick & A.J. Carr Department of Civil Engineering, University of Canterbury, Christchurch.

More information

PAPERWORK REDUCTION ACT A. GENERAL

PAPERWORK REDUCTION ACT A. GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY - FEDERAL EMERGENCY MANAGEMENT AGENCY RIVERINE STRUCTURES FORM O.M.B No. 1660-0016 Expires: 12/31/2010 PAPERWORK REDUCTION ACT Public reporting burden for this form

More information

LOW WATER CROSSINGS, fords, or drifts, as they

LOW WATER CROSSINGS, fords, or drifts, as they Chapter 9 For ords and Low-Water Crossings Keep the ford profile low, armor the driving surface, and protect against scour. LOW WATER CROSSINGS, fords, or drifts, as they are commonly called, can offer

More information

Mitigation Measures Evaluation for Concrete Faced Rockfill Dams. Juan E. Quiroz Mehdi Modares REC Conference - IIT

Mitigation Measures Evaluation for Concrete Faced Rockfill Dams. Juan E. Quiroz Mehdi Modares REC Conference - IIT 1 Mitigation Measures Evaluation for Concrete Faced Rockfill Dams Juan E. Quiroz Mehdi Modares REC Conference - IIT INTRODUCTION 2 Dams for water impoundment can be: Gravity Arch Masonry Roller Compacted

More information

Design of Geofoam Embankment for the. Steven F. Bartlett, Ph.D., P.E. Research Project Manager, UDOT

Design of Geofoam Embankment for the. Steven F. Bartlett, Ph.D., P.E. Research Project Manager, UDOT Design of Geofoam Embankment for the I-15 Reconstruction Steven F. Bartlett, Ph.D., P.E. Research Project Manager, UDOT I-15 Reconstruction - Quick Facts Single Largest Highway Contract t in U.S. 17 Miles

More information

Geotechnical Design and Factors of Safety

Geotechnical Design and Factors of Safety Geotechnical Design and Factors of Safety Technical Bulletin Ontario Ministry of Natural Resources This publication is available online at: Ontario.ca/dams Ces documents sont offerts en anglais seulement

More information

This material was downloaded from the website Please contact the PhillyH2O webmaster for more information about this material.

This material was downloaded from the website  Please contact the PhillyH2O webmaster for more information about this material. This material was downloaded from the website www.phillyh2o.org Please contact the PhillyH2O webmaster for more information about this material. Modernization and Optimization of Existing Dams and Reservoirs

More information

Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION

Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION The selection of a wall type and appropriate connection details is one of the most important

More information

Chapter 14 Lateral Earth Pressure

Chapter 14 Lateral Earth Pressure Page 14 1 Chapter 14 Lateral Earth Pressure 1. Which of the following is not a retaining structure? (a) Retaining wall (b) Basement wall (c) Raft (d) Bulkhead 2. When a retaining structure does not move

More information

Karkheh Storage Dam Cutoff Wall Analysis and Design

Karkheh Storage Dam Cutoff Wall Analysis and Design Missouri University of Science and Technology Scholars' Mine International Conference on Case Histories in Geotechnical Engineering (2004) - Fifth International Conference on Case Histories in Geotechnical

More information

Visual Inspection Checklist

Visual Inspection Checklist APPENDIX Q. Visual Inspection Checklist Thispageintentionallyleftblank. VISUAL INSPECTION CHECKLIST CITY OF AUBURN PUBLIC WORKS DEPARTMENT INSPECTION YEAR: TYPE OF INSPECTION: (Informal, Regular, Formal):

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

Parapet/railing terminal walls shall be located on the superstructure.

Parapet/railing terminal walls shall be located on the superstructure. GENERAL INFORMATION: This section of the chapter establishes the practices and requirements necessary for the design and detailing of deck slab extensions at abutments. For general requirements and guidelines

More information

Post-tensioned prestressed concrete bridge - assignment

Post-tensioned prestressed concrete bridge - assignment Post-tensioned prestressed concrete bridge - assignment Design a post-tensioned prestressed concrete bridge of a three-span arrangement. The construction is prestressed at the age of 7 days and put into

More information

Numerical Modeling of Slab-On-Grade Foundations

Numerical Modeling of Slab-On-Grade Foundations Numerical Modeling of Slab-On-Grade Foundations M. D. Fredlund 1, J. R. Stianson 2, D. G. Fredlund 3, H. Vu 4, and R. C. Thode 5 1 SoilVision Systems Ltd., 2109 McKinnon Ave S., Saskatoon, SK S7J 1N3;

More information

DATA SHEET 3 Concrete Masonry Lintels MARCH 2013

DATA SHEET 3 Concrete Masonry Lintels MARCH 2013 Concrete Masonry Association Australia PO Box, P: Artarmon F: NSW www.cmaa.com.au Disclaimer: The Concrete Masonry Association of Australia Limited is a non-profit organisation sponsored by the concrete

More information

Underground Construction Technology

Underground Construction Technology Underground Construction Technology Course Lectures Part 4.2 Permanent support Dr Ákos TÓTH 1 Segmental Lining in TBM Tunnelling Segmental lining is the support system for shield TBM excavated tunnels.

More information

RETAINING WALLS CHAPTER 13. Omitted parts: Section

RETAINING WALLS CHAPTER 13. Omitted parts: Section RETAINING WALLS CHAPTER 13 Omitted parts: Section 13.9 13.15-13.17 INTRODUCTION Retaining walls are structures that restrain soil or other materials at locations having an abrupt change in elevation. In

More information

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania

Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Supplemental Watershed Plan Agreement No. 10 for Neshaminy Creek Watershed Core Creek Dam (PA-620) Bucks County, Pennsylvania Project Authorization USDA's Small Watershed Program is carried out under the

More information

Types of Hydropower Facilities

Types of Hydropower Facilities Types of Hydropower Facilities 1 Impoundment Hydropower- uses a dam to store water. Water may be released either to meet changing electricity needs or to maintain a constant water level. 2 Run-of-River

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

Chapter A-8 GEOTECHNICAL ANALYSIS FAIRFAX-JERSEY CREEK (JERSEY CREEK SHEET PILE WALL)

Chapter A-8 GEOTECHNICAL ANALYSIS FAIRFAX-JERSEY CREEK (JERSEY CREEK SHEET PILE WALL) Kansas Citys, Missouri and Kansas Flood Damage Reduction Feasibility Study (Section 216 Review of Completed Civil Works Projects) Engineering Appendix to the Interim Feasibility Report Chapter A-8 GEOTECHNICAL

More information

Long-term stress measurements in the clay cores of storage reservoir embankments

Long-term stress measurements in the clay cores of storage reservoir embankments Long-term stress measurements in the clay cores of storage reservoir embankments K S WATTS, Building Research Establishment Ltd, Watford, UK. A KILBY, Thames Water plc, London, UK J A CHARLES, Building

More information

SEISMIC CRACKING AND STRENGTHENING OF CONCRETE GRAVITY DAMS

SEISMIC CRACKING AND STRENGTHENING OF CONCRETE GRAVITY DAMS SEISMIC CRACKING AND STRENGTHENING OF CONCRETE GRAVITY DAMS Hongyuan ZHANG 1 And Tatsuo OHMACHI 2 SUMMARY Concrete gravity dams designed in compliance with the present specification are likely to experience

More information

7.1 Transmission of Prestress (Part I)

7.1 Transmission of Prestress (Part I) 7.1 Transmission of Prestress (Part I) This section covers the following topics. Pre-tensioned Members 7.1.1 Pre-tensioned Members The stretched tendons transfer the prestress to the concrete leading to

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information