DECOMMISSIONING THE BELGONUCLEAIRE DESSEL MOX PLANT: PRESENTATION OF THE PROJECT AND SITUATION on 30/06/2011
|
|
- Kellie Hart
- 6 years ago
- Views:
Transcription
1 Proceedings Proceedings of The ASME of 2011 the 14th ASME International th International Conference Conference Environmental Environmental Remediation Remediation and Radioactive and Radioactive Waste Management ICEM2011 September 25-29, 2011, Reims, France ICEM DECOMMISSIONING THE BELGONUCLEAIRE DESSEL MOX PLANT: PRESENTATION OF THE PROJECT AND SITUATION on 30/06/2011 J.M. CUCHET, H. LIBON and C. VERHEYEN BELGONUCLEAIRE S.A. / N.V. Europalaan, 20 B2480 Dessel, Belgium J.BILY STUDSVIK GmbH Karlsruher Strae, 20 D75179 Pforzheim, Germany J.CUSTERS TECNUBEL N.V. Zandbergen, 1 B2480 Dessel, Belgium R.WALTHÉRY THV BELGOPROCESS / SCK CEN Gravenstraat, 73 B2480 Dessel, Belgium ABSTRACT BELGONUCLEAIRE has been operating the Dessel MOX plant at industrial scale between 1986 and In this period, 40 metric tons of plutonium (HM) has been processed into 90 reloads of MOX fuel for commercial light water reactors. The decision to stop the production in 2006 and to decommission the MOX plant was the result of the shrinkage of the MOX fuel market owing to political and customer s factors. As a significant part of the decommissioning project of the Dessel MOX plant, about 170 medium-sized glove boxes and about metric tons of structure and equipment outside the glove boxes are planned for decommissioning. The license for the decommissioning of the MOX plant was granted by Royal Decree in 2008 and the decommissioning works started in March 2009; the decommissioning works are executed by an integrated organization under leadership and responsibility of BELGONUCLEAIRE with 3 specialized contractors, namely TECNUBEL N.V., the joint venture (THV) BELGOPROCESS / SCK CEN and STUDSVIK GmbH In this paper, after having described the main characteristics of the project, the authors introduce the different organisational and technical options considered for the decommissioning of the glove boxes, and the main decision criteria (qualification of personnel and of processes, confinement, cutting techniques & radiation protection, safety aspects, alpha-bearing waste management) are analyzed as well. The progress, the feedback and the lessons learned mid 2011 are presented, giving the principal s and contractors point of view as well. GENERAL DESCRIPTION Situation of the BELGONUCLEAIRE MOX-Plant / Legal Context The BELGONUCLEAIRE (BN) production plant was commissioned in the early 70 s. In the mid-80 s, the industrial stage was reached. During the last two decades, 35 metric tons of plutonium were processed into about 650 tons of LWR fuel. The Dessel MOX plant is erected on a single floor and is arranged in an intricate network of interconnected glove-boxes with volumes ranging from 0.5 m³ up to 15 m³ and arranged on two levels. The decision to stop the production was taken in december 2005 and the conditioning and evacuation of the remaining production scrap was organized up to the point where the glove-boxes (GB s) are empty of reusable fissile materials. 1 Copyright 2011 by ASME
2 After cleaning, the radioactive material remaining in the glove-boxes as contaminant is limited to uranium and plutonium with following typical isotopic composition aged 5 years (wt% Pu-Am): 238 Pu 3.2% 239 Pu 50.2% 240 Pu 26.9% 241 Pu 7.6% 242 Pu 8.6% 241 Am 3.5%. According to the Belgian legislation, ONDRAF is the organization entrusted for the management (treatment/conditioning of the non conditioned radwaste, interim storage and final disposal of the conditioned ones) of the radioactive waste. The requirements for the acceptance of the non conditioned radioactive waste are provided in specifications elaborated by this organization. They describe (besides the required physico-chemical and radiological characterization) the waste packages leaving the BN plant to BELGOPROCESS (BP) for further processing and conditioning, before interim storage and final disposal. The waste classification, according to the ONDRAF specifications, is defined in TABLE I. TABLE I. Solid Waste Classification. Waste ID -Activity Range A1x < 40 MBq/m³ A2x Between 40 and 4000 MBq/m³ A3x > 4000 MBq/m³ The Belgian Royal Decree dated July 20 th, 2001 (ARBIS) provides with the legal frame for the protection of the population, workers and environment against the ionizing radiation hazards. To perform this decommissioning, BN needs to be granted a license from the Federal Agency for Nuclear Control (FANC). Moreover, the IAEA and EURATOM organizations continue to be in charge of the safeguards of the fissile materials remaining after cleaning. BELGONUCLEAIRE Plant Inventory For project management and obtaining the decommissioning authorizations, the full plant inventory for contaminated objects, including a radiological survey, was prepared based on samplings and measurements performed by an independent organization. This survey also includes ground samplings around the plant and building structure samples. The inventory, which includes 170 glove-boxes and their internal equipment and the infrastructures as well, is summarized in TABLE II, assuming a decommissioning of the glove-boxes in situ and a classification of the waste resulting from the decommissioning of the glove-boxes into the A3X category. Fig. 1. Typical Glove boxes Installation The waste volume includes the secondary wastes such as the disposable tents used for the decommissioning as well as waste resulting from cleaning and decommissioning process (steel, bags, ). TABLE II. Material Inventory. m³ Tons Free release / 1104 A1x A2x A3x (*) (*) Glove boxes, internals and secondary wastes DECOMMISSIONING STRATEGY BN decided performing the decommissioning as soon as possible because the activity results from long live radioelements and there is no activation. In addition, care has to be taken for some 241 Am build-up with time. All reusable fissile materials have been removed from the plant and the fissile materials remaining in the installation are treated as wastes. The cleaning of the glove-boxes and internal equipment is meant for reducing the contamination risk, the personnel exposure and the source term in the waste. The waste selection, volume or size reduction, characterization of the material to be wasted, waste adequate 2 Copyright 2011 by ASME
3 categorization and release up to the technical and economical possible extent will minimize the waste volume. Except for some particular cases, BN decided performing the glove-box disassembling and packing the resulting non conditioned waste into drums in its own plant to minimize contamination spreading risk during off-site transports. Because decommissioning is a specialized activity and because of the undetermined duration of the licensing process, it was early decided to subcontract the decommissioning work to specialized contractors. Selection of well-mastered techniques is crucial with respect to the safety and to the control of costs. Close relationship with Waste and Safety Authorities is also a key factor. Accurate estimation of primary and secondary waste helps the waste flow management. The waste will be transferred regularly to the final conditioning plant during the decommissioning period in containers and packaging close to the ones already used for the previous operations. Fig. 2. Simplified material flow diagram DECOMMISSIONING PROCESS list: Buildings + Site (for nuclear of non-nuclear re-use) R E L E A S E (*) Industrial dumpling place inert (*) According to RP113 and/or StrSchV BN MOX-Plant Unconditional release according to ARBIS Industrial recycling A1 A2 A3 The steps of the process are summarized in the following Removal of fissile material to the possible extent from the plant, Partial disassembly of unnecessary and non-contaminated equipment in the lobbies, Partial disassembly of the GB s in some workshops and laboratories, partial disassembly of equipment in the rod control workshop, to increase the available work floor space and drum storage capacity, Installation of additional equipment for waste management (NDA and size reduction equipment), Preparation of work areas for glove-tent installation, Process room by process room: H K + N C W Treatment by third parties (outside the plant) before release e.g. Melting in nuclear T/C facility Release according to RP89 Industrial recycling ingot ONDRAF T&C Interim Storage Disposal Empty the glove-box of most of its internal equipment (in situ), Isolate and separate GB s, Transfer GB in tent, GB decommissioning and waste processing under disposable glove-tent, Removing all remaining equipment from the rooms (platforms, stairs, lighting, ducts, etc), Installation of a temporary building ventilation system to back-up the existing one, Room decontamination (floor covering removal; floor, walls, ceilings shaving, etc), Remove of all equipment in the lobbies, Decommissioning of common utilities including glove box and building ventilation and filtering systems, Decommissioning of the additional equipment for waste processing and NDA, Free release of the buildings and site. The transfer to ONDRAF of waste drums containing non conditioned waste, for final processing and disposal, takes place continuously during the decommissioning. GLOVE BOX DECOMMISSIONING OPTIONS The first operation is a cleaning of the glove-boxes interior with residue removal. Then, the decommissioning and evacuation of the glove-box internal equipment is performed so far possible, except for what is necessary to maintain the confinement and glove-box ventilation or for some heavy or out of dimensions equipment parts. This takes place in situ using conventional tooling and installing so far possible additional evacuation bag-ports, if not already available on the glove-box or in the close neighborhood on other connected glove-boxes. The equipment is dismantled in components able to be handled by hand or by light handling devices and loaded in 200-liter drums. Performing this disassembling in situ also takes advantage of the existing radiation shielding. Materials are sorted as far as possible to optimize the drum filling. Several materials may be filled together, provided the drum load is characterized in weight percentage estimates for each physico-chemical type of waste (organic -plastic, PVC,.. -, metal, aluminium, ) according to the ONDRAF specifications. Equipment part size reduction is minimal due to their original design for easy maintenance purpose. Nevertheless, some size reduction operations are still needed. Next, the different glove-boxes are separated from the line, as necessary, in sub-units able to be moved together (most of the time in separate glove-boxes). A PVC bellows is secured on both sides of the intended separation, the existing link is disassembled, and the boxes slightly moved away. Then, the bellows is seal-welded on itself and cut to separate the boxes. Steel panel protections are placed over the sealed bellows on 3 Copyright 2011 by ASME
4 each side of the cut to cover them. If required to mitigate contamination spreading risks, this separation work can take place within a light tent erected around the work place. Contamination fixation at the internal face around the separation using varnish is also anticipated. For the in situ size reduction of the glove-boxes themselves and the remaining internal equipment, the Disposable glove-tent solution has been selected : the glovebox is introduced into a clean containment glove-tent fitted to the glove-box dimensions or the tent is erected around the glove-box itself: the latter tent undergoes specific commissioning tests before being put in operation. The tent features gloves and windows allow personnel to disassemble and cut the glove-box structure with cutting tools. The tent is ventilated and maintained in negative pressure with regard to the room. Ventilation system features the pressure controls, alarms and filters as for any glove-box. A port is managed to dock the drum wherein waste is loaded. PVC bag sealing technique, similar to bag-in/bag-out process, is used to replace full drums by empty ones. When the tent is empty, the tent is varnished to fix contamination and fold-down, rolled on it self, and wasted after sherdding. Cutting technologies Waste size reduction to fill as much as possible the drums is important to minimize final waste volume and cost. BN tested several cutting methods, which are compared in TABLE III. TABLE III. Comparison of Cutting Techniques. Abrasive Plasma Sawing Nibbling Grinding Not Generally Part Clamping Needed Needed necessary needed Temp C Room Temp. Tool Speed to N/A m/sec 0.01 Low up to Cut Capacity High Medium Medium 7mm thick Contaminatio n spread risk Very high High Low Low Fire Risk Very high High Low Low Hands-off Needed Possible No No Typical BN glove-box design features a 5 mm welded shell type box made of bended profiles with wide corner radius (rounded edge corners). The window panels are clamped on the 5 mm plates or profiles Few glove-boxes (around 10% of the glove-boxes) feature a very heavy base plate (10-38 mm) on which a 5 mm shell structure is attached (screws and tightness welds). In conclusion, except for some particularities, most of those structures are 5 mm thick, thus accessible for sawing or nibbling. Benefits of the best available techniques BN considers the disposable glove-tent and the cold cutting techniques as the best available technique at the present time as depicted in the previous paragraphs. The benefits using these techniques are summarized below: 1. Allow elaborating and presenting to the Waste Authorities a decommissioning plan supported by experience and operational records of activities in a similar plant (primary and secondary waste volumes, costs, time schedule, etc); 2. Allow elaborating and presenting to the Safety and Licensing Authorities a comprehensive safety file based on existing experience and operational records; 3. Allow implementation of decommissioning options to be operated by different actors (such as third parties specialized in decommissioning services) under different contractual schemes (lump sum and/or costreimbursed / incentivized contracts); 4. Allow parallel processing in different workshops and mastering of overall time-schedule; 5. Allow elaborating and presenting to the BN s board a manageable decommissioning project with time schedule, cost, and reduced uncertainties. Furthermore, the flexibility of operation allowed by the glove-tent allows to control precisely the content in weight or in fissile materials of the waste drums, which is a strategic condition for waste acceptance and transport. DECOMMISSIONING OF EQUIPMENT OUTSIDE THE GLOVE BOXES AND RELEASE STRATEGY The strategy for the decommissioning of equipment outside the glove boxes has been chosen in view of free release of material as much as possible. The basis of the release strategy is described in the paragraphs below. Traceability and classification On one hand, regulations request traceability of operations and of released material; this leads to a batch-based material management. On the other hand, the following applies for solids that qualify for free release: They occur in different physical forms (depending on the composing material; shape and size of the component, bulk or separate components, real or 4 Copyright 2011 by ASME
5 apparent density, coating and state of the surface (corrosion/porosity), total amount in similar physical form). Subsequently, they exhibit different suitability to mass- and/or surface-based free release. So, they imply the use of specific inspection methods. They have a different operational historical record: during their lifetime, they have established a different exposure to contamination. There are differences for materials having spent shorter or longer periods in controlled area rooms with or without risks of contamination, materials that have contained liquids or that have been transported with or without risk of contamination. Therefore, it seems logical to use the similar free release schemes to materials and substances with identical physical form, identical suitability to inspection and identical operational historical record. The operational organization, the treatment and storage of material are substantially simplified by splitting large amounts into smaller amounts and to select a number of well adapted standard carriers (drums, pallets, sampling cans ) Finally, when (nuclear or non-nuclear) material is to be recycled, recycling companies like to receive a characterization of the material. For all these reasons, free release management will be organized in batches, while the treatment (e.g. shredding in situ) will based on 200-L drums. When material is divided into batches, care has to be taken that the subsequent treatment and inspection is corresponding to the operational historical records. According to Article 23.1 of ARBIS, a log book is maintained by Control services. Homogenization The possibility of homogenization of material to be free released offers a number of advantages: It simplifies the application of mass-based concentration criteria on materials that have been subject to surface contamination It offers the possibility in the laboratory to measure samples (in stead of total amounts), with more sensitive methods and under better circumstances. When necessary, small amounts of similar materials with different historical records can be offered a new historical record. Consequently, a homogenous batch can be composed (e.g. secondary paint stripping waste) Homogenization can be carried out in a number of ways. Some examples: Blending of powder or granular waste Melting of metals in an induction furnace Crushing of rubble generated by shaving and scabbling operations, followed by blending Shredding of cables Qualification processes are still going on for the following ways: Shredding of organic substance (piping, linoleum, various PVC-components, ), followed by blending Shredding of switchboard material and computer parts, followed by blending Sample-taking must be carried out, the number of samples per batch being to be previously approved by the Belgian control body. Final destination As a reminder, regulation requests the following: The destination must be guaranteed and proven. A removal register has to be kept of the material that was free released. The possibility of reuse of the material in other nuclear applications has to be examined. Regional legislation After the unconditional free release according to federal legislation, the material and waste will receive a destination compliant with Flemish regional legislation. This means they have to be either industrially recycled or disposed as industrial waste on an licensed repository by a qualified recycler or operator. A number of toxic waste materials, mentioned in the table beneath, have to comply with regional regulation (VLAREM). Material Asbestos or asbestos contaminated material Heavy metal (Lead and Cadmium) Examples of foreseen techniques Destination Removal to repositories of Class 1 Industrial recycling of removal to repositories of Class 2 Recycling by melting: large amounts of steel material will be recycled by melting. This way, the material can be unconditionally or conditionally recycled. The melting is carried out by companies that operate such an installation,. Two companies have been qualified. Apart from the volume reduction, melting has a decontaminating effect in case of uranium or plutonium contamination; melting causes plutonium and uranium to be concentrated in the slag and the dust while the metal has been decontaminated. 5 Copyright 2011 by ASME
6 Examples of material to be recycled by melting are the difficult to measure, and externally non-contaminated tubular structures. They have been used in support for glove boxes, beams and in fluid piping. The advantage is a substantial reduction of free release on site measurements. Decontamination: various decontamination techniques can be applied, depending on the nature and size of the object or material. Decontamination will only be carried out if the cost of the operation is compensated by the profit that is made by declassification. Technique Ultra sound baths with Saxin Cleaning by brush (with Saxin) Mobile pickling installation with needle scabbler (and dust collection) Cleaning by washing and/or mechanical polishing Material suited for the technique small and medium sized pieces in stainless steel, plastic, anodized aluminum Medium sized and large pieces in painted carbon steel (tables, beams, platforms, rod bins...) Lead glas shielding panels Decontamination of the rooms in the controlled area: in view of the free release of the buildings in the controlled area, following techniques can be used for decontamination of the floors, walls and ceiling. Scabbling Shaving (using rotary tools and dust collection), as illustrated in Figure 3. PROJECT ORGANIZATION March 2008, BN examined the possibility of fixed price contract with a qualified contractor; this option has not been finalized, the risk being judged too big. End of 2008 Because decommissioning is a specialized activity and not part of BN s past core business, and because of the undetermined duration of the license process, it was early decided to subcontract the decommissioning work to specialized companies. Starting, BN decided to take the lead of an integrated decommissioning organization with qualified contractors. Contracts were signed in 2009 with: STUDSVIK GmbH (D) The joint venture THV BELGOPROCESS & SCK CEN (B) TECNUBEL N.V. (B) Fig. 4 describes the integrated organization which is operational since the start of the decommissioning works.. Waste Control Nuclear Waste Release on site Security Officer Security Decommissioning Managing Director Methods Decommissioni ng GB THV BP- Studsvik Tecnubel Decommissioni ng Utilities Strategy, Contracts and Planning Safety, Quality and Environment Health Physics Radiation P t ti Radiation Industrial Safety Quality and Environment Safeguards Personnel, Adm. & Communication Personnel & Purchasing Secretary Office BN ti BN safety contractors Fig. 3. Shaving of a concrete wall 1 (during process qualification) Fig. 4. Integrated organization The planning of the decommissioning project is the following: 2009 : training and qualification of the personnel; 2010 : decommissioning glove-boxes; 2011 : decommissioning glove-boxes; 2012 : decommissioning glove-boxes; 2013 : decommissioning infrastructures; 2014 : free release of the buildings and of the site. 1 BOLERO system (with the courtesy of STUDSVIK) 6 Copyright 2011 by ASME
7 SAFETY STRATEGY Actions have been undertaken by BN on 3 levels: level 1 : selection of the contractors : only specialized and qualified companies have been considered; level 2 : qualification and training of the operators training center; mentorship principle for each new operator; continuous evaluation; level 3 : work organization and decommissioning work sequences (e.g. emptying the internals in the glove-boxes themselves, when starting the work); work protection (e.g. use of shielding panels - see beneath -). In the frame of the training of the contractors, a training center has been developed (see Fig.5); its main functions and objectives are the following: Simulation of activities in cold conditions use of glove boxes (GB); use of individual protection equipment; bringing material in and out of GB; welding of plastics and bags; docking of waste drums, filling and disconnecting; setting up decommissioning tent with its infrastructure; working in GB s and tents: sawing, cutting, nibbling. (Training in mockups: 4 GB s and 2 tents) Qualification of decommissioning techniques (e.g. for handling and decommissioning of ball mills, sinterfurnaces,...) RADIATION PROTECTION / RISK ANALYSIS Radiation protection One of the main concerns of BN is to limit, up to a possible extent, the personnel s radiation exposure. The target is below the limits defined in the State Regulations and is according to the ALARA principles. The main exposure is coming from radiation generated by 241 Am and neutron irradiation. For this reason, BN developed reusable modular transparent shielding panels being placed between the glovetent and the workers. The panel is attached to the external tent supporting structure, as shown on Fig.6. Fig. 6. Example of modular shielding panels mounted o n a glove tent Before starting a decommissioning operation the radiation level is measured and the need for possible additional shielding is checked. Risk analysis Risk prevention and mitigation mainly concern criticality, fire risk and loss of containment, in addition to the common risk of industrial activities (load drops, injuries, etc). Fig. 5. Training in cold conditions for working in glove boxes and in tents Criticality Criticality risk is greatly reduced because most of fissile material is removed from the plant before beginning the decommissioning operations. Nevertheless, simplified criticality prevention rules remain applicable during the glovebox decommissioning period until the total amount of fissile materials is less than 805 g. For example, any contaminated material transfer within the plant needs to be declared and only takes place after approval of the Health and Physics Department. All transfers are recorded as to assess the fissile 7 Copyright 2011 by ASME
8 material and to comply with the international rules of safeguards. Fire Fire risk is controlled in the following ways: Flammable materials such as hydraulic fluids and process gases (Ar + H 2 ) have been completely evacuated well before the decommissioning operation begins. There is no operation anticipated on flammable material. The tent sheets are made of materials that do not propagate flames. No thermal process or thermal equipment is used for the decommissioning operation. BN selected cold and dry cutting processes; furthermore, no flammable solvent is used. Electric power supply to the glove-box equipment is shutdown before decommissioning and controlled by a consignation process under the Health and Physics Department s responsibility. Electric devices used during the whole decommissioning period are verified for their conformity to the general regulations (AREI and CE stamp). This includes both existing and new devices. Periodical thermographic survey is foreseen. Work organization and preparation are also key factors. All cutting processes have been qualified in inactive and active conditions. Any decommissioning activities are sequenced, described in writing, debated and approved by the Health and Physics Department before engaging any action. Operators will be selected, educated and trained for these glove-box activities. Shop floor verifications for tidiness, cleanness, escape paths free access, fire fighting devices location and markings will be systematically performed. Each tent features fire detection linked to local alarms (visual and audible) and to the general plant alarm network. Additional fire suppression sources will be provided on the working area as required for use in the tent or in the room. Personnel will be trained to use them. Compartmentalization of the process rooms is maintained operational during decommissioning works. preventing tent overstressing. Each tent is tested for strength and tightness when fabricated; tightness is verified again just before the decommissioning operation begins and before the tent inside becomes contaminated. Fixing the contamination in the tent After cutting of the glove-box, the use of water-based varnish for fixing the contamination at the inner surface of the tent improves the safety of the tent fold-down operation. PROCESS VALIDATIONS In support to the license filing documentation, several demonstrations of the cutting techniques took place with noncontaminated and contaminated material assessing their safety and efficiency. Tent configurations were developed and improved. As examples, several contaminated glove-boxes representative of the plant s glove-boxes stock were wasted using the selected processes, after having taught the staff with size reduction on dummy GB s. WASTE MANAGEMENT / PACKAGING DRUMS Drums used for the safe transport (in a dedicated transport overpack) of the non conditioned waste feature a 200-liter capacity with standardized shape. The internal faces are protected by a polyethylene sheet to receive falling parts without damaging the drum coating. At the upper part of the drum, a vinyl skirt clamped on the inner side of the drum by an expendable ring provides the α-tight connection with the docking station. When the drum is full, this skirt is seal-welded to confine the drum content to ensure the tightness of the final product according to ISO standard. A steel lid with seal is then clamped on the top. The drums are qualified to withstand a fall of 1 m with full load. An absolute filter prevents any drum pressure increase resulting from potential radiolysis gas release during storage. Loss of containment Containment is maintained by the glove-box ventilation system (high depression extraction and HEPA filters) on which the glove-tents will be coupled. Each tent will be equipped, as a production glove-box, with a normal extraction flow able to maintain the tent differential pressure in case of a breach (glove tear-out) with an adequate flow speed through the expected breach (for prevention of contamination spreading), and a vacuum breaker valve to limit the differential negative pressure Fig. 7. Drum during preparation (in cold conditions) 8 Copyright 2011 by ASME
9 The drum loading limits are as follows: Total maximum gross weight : 300kg Presence of organic material : no limit CONCLUSIONS / PROGRESS OF THE WORKS On 30/06/2011, it means ~28 months after start of the decommissioning works, the following conclusions can be drawn: The integration and qualification of the different contractors has been achieved by end Safety results : No labour accidents in the controlled area; No labour incidents with nuclear impact; The individual yearly exposure does not exceed the dose limit of 12 msv. Turnover of personnel : < 10 % Progress of the work : 45% of glove boxes are dismantled, conform to the expectations; 40% of the equipment outside the glove boxes have been treated ; 70 T metal scraps have been sent to a melting facility; Fillings rate of the radwaste drums: conform to the expectations. REFERENCES 1. R.BAUMANN, P.FABER, Decommissioning Techniques for Plutonium-Contaminated Gloveboxes: Experience from First Year of Decommissioning, 6 th International Symposium of Radioactive and Decommissioning Wastes, Kontec 2003, Berlin, Germany, March A.VANDERGHEYNST, J.M. CUCHET, Strategy For Decommissioning of Glove-Boxes in the Belgonucleaire Dessel Mox Fuel Fabrication Plant, 11th International Conference on Environmental Remediation and Radioactive Waste Management, ICEM`07, September 2-6, 2007, Bruges, Belgium. 3. A.VANDERGHEYNST, J.M. CUCHET, An Evolutionary Approach For the Decommissioning of the Glove Boxes in the Belgonucleaire Dessel Plant, SFEN International Conference Decommissioning Challenges: an Industrial Reality?, September 28 to October 2, 2008, Avignon, France. ACRONYMS AND ABBREVIATIONS Definition ARBIS Algemeen Reglement voor de Bescherming van de bevolking en van de werknemers tegen het gevaar van de Ioniserende Straling (= Belgian Regulation for Radiation Control, as per Royal Decree d.d. July 20, 2001) BEL-V Filiale van het FANC (= Supervisory Body) AREI Algemene Reglement voor Elektrische Installaties (= Belgian General Regulation for Electrical Installations), as per Royal Decree d.d. June 2, 2008) FANC Belgian Federal Agency for Nuclear Controls ONDRAF Organisme Fédéral des Déchets Radioactifs et des Matières Fissiles Enrichies (= Belgian Radwaste Administration) VLAREM Vlaams Reglement op de Milieuvergunningen (= Flemish regional regulatory frame for environment) StrSchV Strahlenschutzverordnung (= German Regulation for Radiation Control) 9 Copyright 2011 by ASME
C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant
C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant Content Regulatory framework Strategy Status of the project Role
More informationBest practices for preparing vessel internals segmentation projects
Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: 20 February 2015 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 12 For submission to CSS Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle
More informationIAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities
DS447 Date: September 2014 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 11 MS comments incorporated Review Committee Member comments due 31 Oct Predisposal Management
More informationMOX Fabrication: External Communication at BELGONUCLEAIRE Dessel Plant in Belgium
MOX Fabrication: External Communication at BELGONUCLEAIRE Dessel Plant in Belgium Achilles De Backer, BELGONUCLEAIRE N.V. International Seminar for MOX Utilisation Tokyo Japan 18-19 February 2002 2 CONTENTS
More informationWM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA
Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1
More informationRECYCLING OF URANIUM- AND PLUTONIUM-CONTAMINATED METALS FROM DECOMMISSIONING OF THE HANAU FUEL FABRICATION PLANT
RECYCLING OF URANIUM- AND PLUTONIUM-CONTAMINATED METALS FROM DECOMMISSIONING OF THE HANAU FUEL FABRICATION PLANT T. Kluth, U. Quade Siempelkamp Nukleartechnik GmbH Siempelkampstrasse 45, 47803 Krefeld,
More informationDirk Wegener*, Thomas Kluth** GNS Gesellschaft für Nuklear-Service mbh, Essen, Germany* Siempelkamp Nukleartechnik GmbH, Krefeld, Germany**
Treatment of Radioactive Metallic Waste from Operation of Nuclear Power Plants by Melting - The German Way for a Consistent Recycling to Minimize the Quantity of Radioactive Waste from Operation and Dismantling
More informationRESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED
RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED B. Stahn, R. Printz, K. Matela, C. Zehbe Forschungszentrum Jülich GmbH 52425 Jülich, Germany J. Pöppinghaus Gesellschaft
More informationRadioactive Waste Management Agency. and. Nuclear Safety Authority. in Belgium
Radioactive Waste Management Agency and Nuclear Safety Authority in Belgium Luc Baekelandt, FANC, Belgium LB/IAEA/2010-06-08/00 Contents 1. Institutional framework 2.The actors FANC ONDRAF/NIRAS 3. Co-operation
More informationWM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA
An Integrated Equipment for Massive Segmentation and Packaging of Control Rod Guide Tubes 15161 Joseph Boucau*, Patrick Gobert** Sébastien Bonne *** * Westinghouse Electric Company, 43 rue de l Industrie,
More informationRenovating a Medical Radiosotope Production Hot Cell T. GROCHOWSKI ROBATEL Technologies
Renovating a Medical Radiosotope Production Hot Cell - 11337 T. GROCHOWSKI ROBATEL Technologies D. SANCHETTE & S. COLLONGE ROBATEL Industries Rue de Genève, 69740 Genas - France P. Van boxem National Institute
More informationDECOMMISSIONING AND SITE RESTORATION IN BELGIUM
DECOMMISSIONING AND SITE RESTORATION IN BELGIUM Jean-Paul Minon, general manager ONDRAF/NIRAS Origin and Development of Nuclear Applications in Belgium The very beginning of the Belgian nuclear industry
More informationRadioactive Waste Management at the NCSR Demokritos - Greece
Radioactive Waste Management at the NCSR Demokritos - Greece Anastasia Savidou Radioactive Materials Management Laboratory Institute of Nuclear & Radiological Sciences & Technology, Energy & Safety, National
More informationDECOMMISSIONING PROGRAMS AND TECHNOLOGY DEVELOPMENT IN JAPAN ATOMIC ENERGY RESEARCH INSTITUTE
DECOMMISSIONING PROGRAMS AND TECHNOLOGY DEVELOPMENT IN JAPAN ATOMIC ENERGY RESEARCH INSTITUTE Mitsugu Tanaka, Mimori Takeo, Takakuni Hirabayashi and Satoshi Yanagihara Japan Atomic Energy Research Institute
More informationWM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA
Modular Design of Processing and Storage Facilities for Small Volumes of Low and Intermediate Level Radioactive Waste including Disused Sealed Sources - 12372 David R. Keene*, Susanta Kumar Samanta** and
More informationNew Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN
New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN Abstract The Swedish Radiation Safety Authority (SSM) has developed
More informationDECOMISSIONING OF THE FORMER GERMAN REPROCESSING SITE WAK STATUS OF VITRIFICATION PLANT AND DISMANTLING OF THE HLLW STORAGE TANKS
DECOMISSIONING OF THE FORMER GERMAN REPROCESSING SITE WAK STATUS OF VITRIFICATION PLANT AND DISMANTLING OF THE HLLW STORAGE TANKS - 9023 J. Fleisch, M. Weishaupt, W. Pfeifer Wiederaufarbeitungsanlage Karlsruhe,
More informationGerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany
861 REMOTELY-OPERATED DISMANTLING OF THE REACTOR INTERNALS AT NIEDERAICHBACH POWER PLANT USING MANIPULATORS Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany ABSTRACT The joint venture
More informationWM'00 Conference, February 27 - March 2, 2000, Tucson, AZ DECOMMISSIONING OF FOUR GERMAN FUEL CYCLE FACILITIES
DECOMMISSIONING OF FOUR GERMAN FUEL CYCLE FACILITIES Dr. Helmut Rupar, Roland Baumann, Peter Faber, Dr. Manfred Ruhbaum, Helmut Schmitt Siemens AG, Power Generation Group (KWU), Germany ABSTRACT The decommissioning
More informationDecommissioning of Nuclear Facilities. Waste Management
Decommissioning of Nuclear Facilities Waste Management Lesson Objectives Describe the requirements and methods for managing waste from decommissioning Review IAEA and US waste classification systems Review
More informationWM2011 Conference, February 27-March 3, 2011, Phoenix, AZ. The DN30 Package for the Transport of Enriched Reprocessed Uranium
The DN30 Package for the Transport of Enriched Reprocessed Uranium - 11111 Franz Hilbert, Wolfgang Bergmann Nuclear Cargo + Service GmbH, 63457 Hanau, Germany ABSTRACT In the last few years the volume
More informationWaste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report
Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report Rich McGrath (Presenter) - EPRI Consulting Employee Rick Reid, PhD - Senior Technical Leader Symposium
More informationManufacture of Nuclear Fuel Elements in Chile Fabricación de Combustible Nuclear en Chile
Manufacture of Nuclear Fuel Elements in Chile Fabricación de Combustible Nuclear en Chile Luis Olivares, Jorge Marin, Jaime Lisboa, Eric Alcorta Nuclear Fuel Section Chilean Nuclear Energy Commission Workshop
More informationDecommissioning Planning
Decommissioning Planning Ingemar Lund - Swedish Radiation Protection Authority, SSI, Sweden IAEA Regional Workshop: Legal and Regulatory Aspects of Decommissioning of Research Reactors Manila, Philippines,
More informationDECONTAMINATION-MELTING OF URANIUM- CONTAMINATED METAL
DECONTAMINATION-MELTING OF URANIUM- CONTAMINATED METAL Joachim Lorenzen and Maria Lindberg, Project Managers, Studsvik RadWaste AB, SE-611 82 Nyköping, SWEDEN ABSTRACT Studsvik RadWaste AB (SRW) has since
More informationEuropean Experience In Transport / Storage Cask for Vitrified Residues
ABSTRACT European Experience In Transport / Storage Cask for Vitrified Residues L. Blachet, C. Otton, D. Sicard AREVA TN International Because of the evolution of burnup of spent fuel to be reprocessed,
More informationSPENT FUEL STORAGE IN BELGIUM
SPENT FUEL STORAGE IN BELGIUM R. Vermeyen Tractebel Energy Engineering Belgatom 1. Introduction The Belgian utility Electrabel presently operates 7 PWR nuclear power plants, distributed over two sites
More informationMFC CH-TRU Waste Certification Plan
Document ID: Revision ID: 06//0 Plan MFC CH-TRU Waste Certification Plan The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance. 06//0 Page: ii of v Materials and
More informationWM2008 Conference, February 24-28, 2008, Phoenix, AZ Abstract #8216. Thermal Pretreatment For TRU Waste Sorting
ABSTRACT Thermal Pretreatment For TRU Waste Sorting T. Sasaki, Y. Aoyama, Y. Miyamoto, and H. Yamaguchi Japan Atomic Energy Agency 4-33, Muramatsu, Tokai-mura, Ibaraki 319-1194 Japan Japan Atomic Energy
More informationDry storage systems and aging management
Dry storage systems and aging management H.Issard, AREVA TN, France IAEA TM 47934 LESSONS LEARNED IN SPENT FUEL MANAGEMENT Vienna, 8-10 July 2014 AREVA TN Summary Dry storage systems and AREVA Experience
More informationJoint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria
2473-9 Joint ICTP-IAEA School on Nuclear Energy Management 15 July - 3 August, 2013 Lecture Notes I. Mele IAEA, Vienna, Austria The IAEA Nuclear Energy Management School ICTP, Trieste, 15-2 August 2013
More informationBenefits from R&D for D&D Projects Preparation
Benefits from R&D for D&D Projects Preparation Christine GEORGES 17th February 2016 Titre du document ~ February 2016 ~ 1 SPECIAL FEATURES OF CEA D&D PROJECTS 500 M /year 800 CEA employees and about 2500
More informationDecommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M
Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M Giorgi Nabakhtiani Grigol Kiknadze Nuclear and Radiation Safety Service Ministry of Environment Protection and Natural
More informationAREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals
AREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals Jan Hendrik Bruhn GmbH/ IBRZ-G Varna, June 10 th 2010 Content General Requirements for Dismantling Projects Stade NPP
More informationDecommissioning Waste Handling and Storage Challenges
Decommissioning Waste Handling and Storage Challenges Part of the Sellafield Ltd Game Changers Series How to use this document This document introduces the challenges associated with the dismantling, size
More informationSTRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY
GUIDE YVL C.1 / 15 November 2013 STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 General design requirements 3 4 Radiation safety aspects in the layout design
More informationPRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.
TECHNICAL MEETING ON THE RESEARCH REACTOR DECOMMISSIONING DEMONSTRATION PROJECT: CHARACTERIZATION SURVEY PHILIPPINES, 3 7 DECEMBER 2007 PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING
More informationTRANSPORT OF NUCLEAR MATERIAL AND NUCLEAR WASTE
GUIDE YVL 6.5 / 4 APRIL 2005 TRANSPORT OF NUCLEAR MATERIAL AND NUCLEAR WASTE 1 GENERAL 3 2 DEFINITIONS 3 3 REGULATIONS AND RESPONSIBILITIES CONCERNING TRANSPORTS 4 3.1 General transport regulations for
More informationOccupational Radiation Protection in Radioactive Waste Management
ISOE 2014 Asian ALARA Symposium The-K Hotel Gyeongju, Republic of Korea, 23-25 September 2014 Occupational Radiation Protection in Radioactive Waste Management 24 Sept., 2014 Byeongsoo KIM KINS 1 Contents
More informationRadiation Protection Challenges associated with the dismantling of Nuclear Power Plant
Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant Ludovic Vaillant ISOE International Symposium Rio de Janeiro, May 2015 Context (1/2) For various reasons - economical,
More informationTopical Aspects of Waste Container Approval for the Upcoming KONRAD Repository
Topical Aspects of Waste Container Approval for the Upcoming KONRAD Repository ABSTRACT H. Völzke, M. Ellouz, V. Noack BAM Federal Institute for Materials Research and Testing 12200 Berlin, Germany - 10012
More informationWGFCS Workshop Periodic safety review of French fuel cycle facilities Martine BAUDOIN and Jean-Pierre CARRETON
WGFCS Workshop Periodic safety review of French fuel cycle facilities 18 th October 2007 Martine BAUDOIN and Jean-Pierre CARRETON 1 Safety assessments through a facility s life Construction License Operation
More informationPRODUCT HSE: Clauses HSE Technological purchase
REFERENCE SYSTEM PRODUCT HSE: Clauses HSE Technological purchase Reference : 83570258-HSE-ITA-EN Revision : 001 Date of revision : 05 Nov 2012 Group revision Page 1 / 13 APPLICABILITY COUNTRY - SITE COMPANY
More informationDecommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment
: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment Dr. M Knaack TÜV NORD GmbH, Hamburg / Germany Overwiew Decommissioning when and why? Law, regulations and guidelines Three main
More informationNitroJet. Able to be operated remotely in high. As the liquid nitrogen rapidly changes state
CE Certified NitroJet N4 System NitroJet The NitroJet system creates and applies an ultra high-pressure (UHP) stream of liquid nitrogen for material coatings removal, cutting and cleaning without adding
More informationNUCLEAR SAFETY REQUIREMENTS BSR
NUCLEAR SAFETY REQUIREMENTS BSR-1.8.2-2015 APPROVED BY Order No. 22.3-99 of The Head of State Nuclear Power Safety Inspectorate, of 7 October 2011 (as amended by Order No. 22.3-57 of the Head of State
More informationGerman contribution on the safety assessment of research reactors
German contribution on the safety assessment of research reactors S. Langenbuch J. Rodríguez Gesellschaft für Anlagen- und Reaktorsicherheit (GRS) mh. Schwertnergasse 1, D-50667 Köln, Federal Republic
More informationEnvironmental Protection Control Standard for Solid Waste Imported as Raw Materials - Waste and Scraps of Iron and Steel
ICS 13.030.50 Z 70 National Standard of the People's Republic of China GB 16487.6-201_ Superseding GB 16487.6-2005 Environmental Protection Control Standard for Solid Waste Imported as Raw Materials -
More informationApplicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects
Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Leo Lessard Manager, Commercial Decommissioning Operations, AREVA Inc. 16th February 2016 International
More informationRADIOACTIVE CONTAMINATED SCRAP IN METAL RECYCLING FACILITIES
Health and Safety Executive Policy Group Manufacturing Sector Information Minute SIM 03/2005/08 Cancellation Date 23/05/2009 Open Government Status Fully Open Version No & Date 1: 23/05/2005 Author Unit/Section
More informationDecommissioning Group Ketut Kamajaya
Decommissioning Group Ketut Kamajaya Contents of presentation Briefly history of Bandung TRIGA reactor Location of the facility Decommissioning options Characterization of System, Structure and Component
More informationMOX fuel fabrication and its external communication in France. Roland JACQUET, Director of the MELOX plant
MOX fuel fabrication and its external communication in France Roland JACQUET, Director of the MELOX plant MOX fuel fabrication Nuclear material recycling solution > Recycling plutonium as MOX fuel permits
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION REPORT Docket No. 72-1040 HI-STORM UMAX Canister Storage System Holtec International, Inc. Certificate of Compliance
More informationMETHODS FOR MOUNTING RADIOACTIVE POWDERS FOR XRD ANALYSIS
54 METHODS FOR MOUNTING RADIOACTIVE POWDERS FOR XRD ANALYSIS Leah N. Squires, Robert D. Mariani, Thomas Hartmann* and J. Rory Kennedy Idaho National Laboratory, Fuel Fabrication and Characterization Department,
More informationPackaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517
Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517 Aurélie Brasch-Serres*, Mathias Chazot** * EDF-DP2D, 154 avenue Thiers, CS 60018, 69458 LYON CEDEX 06, FRANCE
More informationCONDITIONING OF INTERMEDIATE-LEVEL WASTE AT FORSCHUNGSZENTRUM JÜLICH GMBH. H. Krumbach Forschungszentrum Jülich GmbH (FZJ) Jülich, Germany
WM 03 Conference, February 23-27, 2003, Tucson, AZ CONDITIONING OF INTERMEDIATE-LEVEL WASTE AT FORSCHUNGSZENTRUM JÜLICH GMBH H. Krumbach Forschungszentrum Jülich GmbH (FZJ) 52425 Jülich, Germany ABSTRACT
More informationConcepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant
8 Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant KOZO TABUCHI *1 MASAYUKI TAKEDA *2 KAZUO TANAKA *2 JUNICHI IMAIZUMI *2 TAKASHI KANAGAWA *3 ATMEA1 TM is a 3-loop 1100
More informationABSTRACT. The Guidelines Section C is related to the classification and grading approach of NSQ100 (Chapters & 4.1.3).
Page 1 / 11 ABSTRACT This document is the Section C to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions
More informationSTURGIS Barge Decommissioning Project
STURGIS Barge Decommissioning Project U.S. Army Corps of Engineers Nov. 17, 2014 US Army Corps of Engineers Today s Presentation History of the STURGIS Environmental Assessment Decommissioning Waste Segregation
More informationReactor Technology: Materials, Fuel and Safety. Dr. Tony Williams
Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear
More informationDismantling of nuclear facilities in France: what is at stake?
Decommissioning of nuclear facilities Feedback from France L. Vaillant ISPRA, Italy, 16 th September 2015 Content Dismantling of nuclear facilities in France: what is at stake? Radioactive Waste Management
More informationDecommissioning, Radioactive Waste and Spent Nuclear Fuel Management in Slovakia
Decommissioning, Radioactive Waste and Spent Nuclear Fuel Management in Slovakia Presented by Mr. Vladimir Michal Division for Radiation Safety, NPP Decommissioning and RAW Management GSV, Trnava, 11 October
More informationSafety Assessment for Decommissioning of a Nuclear Laboratory
SAFETY ASSESSMENT FOR DECOMMISSIONING Annex I, Part C Safety Assessment for Decommissioning of a Nuclear Laboratory INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA CONTENTS 1. INTRODUCTION... 1 1.1. Background...
More informationBOMA BEST Sustainable Buildings 3.0 Waste Auditing Requirements
BOMA BEST Sustainable Buildings 3.0 Waste Auditing Requirements This document provides the requirements for completing an audit compliant with the BEST Practice. For a more comprehensive description of
More informationThe exchange of experience from a global fuel cycle operator point of view
The exchange of experience from a global fuel cycle operator point of view Workshop on Fuel Cycle Safety Wilmington, NC October 2007 Philippe BOSQUET Deputy VP Safety, Health & Security AREVA Introduction
More informationSpanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero
Spanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero Senior Researcher Head of CIEMAT Quality Management CYTED- Energy Area Technical Secretary of Spanish
More informationWM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA
The D&D program of GB1 Gaseous Diffusion Plant 14452 F. CHAMBON *, J. BONNETAUD **, P. SEURAT **, R. VINOCHE ***, S. DUMOND **** * AREVA Federal Services, Columbia, MD21045, USA; frederic.chambon@areva.com
More informationAbcite 585 EF. Technical Data and Application Guide. Product description. Typical applications. Product range. Product certifications.
Product description is a single layer, primer-free, halogen-free, high strength adhesive thermoplastic powder coating which provides shattering protection for glass pieces and preserves the original glass
More informationNON-REACTOR ALTERNATIVES FOR PLUTONIUM DISPOSITION
NON-REACTOR ALTERNATIVES FOR PLUTONIUM DISPOSITION Edwin S. Lyman Senior Scientist Union of Concerned Scientists Presentation at the AAAS Washington, DC June 10, 2014 SPENT FUEL STANDARD Spent fuel standard
More informationWälischmiller Engineering
Wälischmiller Engineering Cutting-Edge Technology with Tradition Wälischmiller Engineering is a specialist manufacturer of remote-handling, robotics and radiation-protection solutions for environments
More informationThe "Réacteur Jules Horowitz" : The preliminary design
The "Réacteur Jules Horowitz" : The preliminary design A. BALLAGNY - S. FRACHET CEA Direction des Réacteurs Nucléaires 31, 33 Rue de la Fédération 75752 PARIS Cédex 15 J.L. MINGUET - C. LEYDIER TECHNICATOME
More informationA Radiation Protection Perspective- Decommissioning of the Moata Reactor. Biological Shield Dismantling
A Radiation Protection Perspective- Decommissioning of the Moata Reactor Biological Shield Dismantling Australian Nuclear Science & Technology Organisation IAEA Workshop (R2D2) Sydney Australia 7 th -11
More informationBerkeley Boilers Project. Studsvik Symposium April 2014
Berkeley Boilers Project Studsvik Symposium April 2014 Berkeley NPP Twin Magnox Reactors Operating 1962 1989 First UK commercial reactor to enter decommissioning Currently managed on behalf of the Nuclear
More informationTransporting radioactive material - Guidance on radiation and contamination monitoring requirements, and determining a Transport Index
Transporting radioactive material - Guidance on radiation and contamination monitoring requirements, and determining a Transport Index Who is this guide for? This guide has been prepared primarily to help
More informationFABRICATED HOT-ROLLED STRUCTURAL SECTIONS
ENVIRONMENTAL PRODUCT DECLARATION FABRICATED HOT-ROLLED STRUCTURAL SECTIONS Hot rolled structural steel sections complying with the definition of structural steel in AISC 303-10 produced in the United
More informationACCESS CONTROL AND WORK AREA SETUP RCT STUDY GUIDE State responsibilities in using or initiating a RWP.
LEARNING OBJECTIVES: 2.10.01 State the purpose of and information found on a Radiological Work Permit (RWP) including the different classifications at your site. 2.10.02 State responsibilities in using
More informationCommercial in Confidence COPYRIGHT 2010
PNSI Overview Commercial in Confidence COPYRIGHT 2010 1 PNSI Background www.pdsgrp.com Pacific Nuclear Systems was originally formed as a Washington Corporation in 1983.The company built up a reputation
More informationWM2013 Conference, February 24-28, 2013, Phoenix, Arizona, USA
Development and Application of an Oversize Reusable DOT 7A Type A Overpack Container at the Y-12 National Security Complex - 13150 Tim Tharp*, David Martin**, and Paul Franco*** *B&W Technical Services
More informationRADIOACTIVE WASTE TREATMENT FROM MO-99 P RODUCTION FACILITY IN THE NETHERLANDS
RADIOACTIVE WASTE TREATMENT FROM MO-99 P RODUCTION FACILITY IN THE NETHERLANDS ABSTRACT Rozé.M. van Kleef, COVRA NV E-mail: rvkcovra@zeelandnet.nl Klaas.A. Duijves, NRG Hans.D.K. Codée, COVRA NV In Petten,
More informationConsiderations for Disposition of Dry Cask Storage System Materials at End of Storage System Life
Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life Nuclear Fuels Storage & Transportation Planning Project Office of Fuel Cycle Technologies Nuclear Energy
More informationMission Statement. State Steel strives to provide quality products and services at competitive
Mission Statement State Steel strives to provide quality products and services at competitive prices. This commitment is demonstrated with several branch locations all offering large, diverse inventories
More information1 Introduction and object of the statement Request of advice of the BMU Consultations Assessment basis Statement...
Note: This is a translation of the statement entitled Anforderungen an bestrahlte Brennelemente aus entsorgungstechnischer Sicht. In case of discrepancies between the English translation and the German
More informationExperiences on a Regulatory Clearance of the Radioactive Wastes at KAERI
Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI - 8323 D.S. Hong, Y. Y. Ji, J. S. Shon, S. B. Hong Korea Atomic Energy Research Institute 1045 Daedeokdaero, Yuseong, Daejeon, Korea
More informationSafety principles of radioactive waste management activities and supportive IAEA documents
Safety principles of radioactive waste management activities and supportive IAEA documents Eric K. Howell, Ph.D. Facilia Projects GmbH Joint ICTP/IAEA Workshop on Radioactive waste management solutions
More informationDRAFT UGANDA STANDARD
DRAFT UGANDA STANDARD DUS1910-2 First Edition 2017-10-20 Metal Chairs for 0ffice Purposes Part. 2: Revolving and Tilting- Specification Reference number DUS 1910-2:2017 UNBS 2017 DUS 1910-2:2017 Compliance
More informationAlec Kimber Australian Nuclear Science & Technology Organisation
Decommissioning and Dismantling of the Moata Reactor Alec Kimber Australian Nuclear Science & Technology Organisation A History of Moata Constructed at ANSTO in 1961 ARGONAUT type reactor Built as a 10
More informationROMANIA National Commission for Nuclear Activities Control (CNCAN) Report. on in Decommissioning Activities. Dr. Lucian BIRO Director General
ROMANIA National Commission for Nuclear Activities Control (CNCAN) Progress in Report on in Decommissioning Activities Dr. Lucian BIRO Director General IAEA R²D²P Workshop on Cost Estimates Manila, 30
More informationCASE STUDY: RH-TRU WASTE TRANSPORTATION FROM BATTELLE COLUMBUS LABORATORIES. James H. Eide Battelle Columbus Laboratories
CASE STUDY: RH-TRU WASTE TRANSPORTATION FROM BATTELLE COLUMBUS LABORATORIES James H. Eide Battelle Columbus Laboratories Jennifer Griffin, Murthy Devarakonda IT Corporation Mark Whittaker GTS Duratek Tod
More informationType II Environmental Declaration according ISO 14021:2001/A1:2011
Type II Environmental Declaration according ISO 14021:2001/A1:2011 Product: Hunter Douglas Panels Module 200-600mm Product code: 26005 Module 601-900mm Product code: 26025 Module 901-1200mm Product code:
More informationSika KAB combination joint waterbars waterstopping systems
PRODUCT DATA SHEET Sika KAB combination joint waterbars Waterbars for waterproofing construction and crack induced shrinkage joints in new reinforced concrete structures PRODUCT- DESCRIPTION KAB 125/KAB
More informationSAFE WORK PROCEDURE LOCATION WRITTEN BY: APPROVED BY: DATE CREATED LAST REVISION. Schools in PTSD Lorie Carriere School Principal August 30, 2011 New
Page 1 of 6 LOCATION WRITTEN BY: APPROVED BY: DATE CREATED LAST REVISION Schools in PTSD Lorie Carriere School Principal August 30, 2011 New PERSONAL PROTECTION EQUIPMENT (PPE) Safety glasses or face shield
More informationP. Brennecke, S. Steyer Bundesamt für Strahlenschutz Willy-Brandt-Strasse 5, D Salzgitter, Germany
WASTE CERTIFICATION, ACCEPTANCE AND DISPOSAL FOR LLW/ILW/MW/HW MANAGEMENT OF RADIOACTIVE WASTE IN GERMANY: QUALITY ASSURANCE OF WASTE PACKAGES WITH RESPECT TO IAEA RECOMMENDATIONS P. Brennecke, S. Steyer
More informationPreparation of Natural Uranium Samples for Shipment in an Excepted Package
WNTI W O R L D N U C L E A R T R A N S P O RT I N S T I T U T E FACT SHEET Preparation of Natural Uranium Samples for Shipment in an Excepted Package Dedicated to the safe, efficient and reliable transport
More informationTreatment, volume reduction and recycling of large components such as heat exchanges, steam generators and boilers
Treatment, volume reduction and recycling of large components such as heat exchanges, steam generators and boilers INTERNATIONAL NUCLEAR FORUM BULGARIAN NUCLEAR ENERGY NATIONAL, REGIONAL AND WORLD ENERGY
More informationDecommissioning of Nuclear Facilities: The Work Ahead and How to Succeed
Decommissioning of Nuclear Facilities: The Work Ahead and How to Succeed William D. Magwood, IV Director General Nuclear Energy Agency International Workshop on Decommissioning of Nuclear Power Plants
More informationDose and Risk Calculations for Decontamination of a Hot Cell
Dose and Risk Calculations for Decontamination of a Hot Cell Amr Abdelhady and T. Mongy Reactors dept., Nuclear Research Center, Atomic Energy Authority, Cairo, Egypt Received: 1 /2/ 2014 Accepted: 6 /3/
More informationSECTION HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
Page 220529-1 SECTION 220529 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationDismantling Techniques applied at MZFR
Wiederaufarbeitungsanlage Karlsruhe Rückbau- und Entsorgungs- GmbH The Decommissioning Project Multi-Purpose Research Reactor ( MZFR ) Dismantling Techniques applied at MZFR E. Prechtl Projekt MZFR WAK
More informationAPPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES
APPE NDIX F TY PE 2 ASBE STOS WORK PROCEDURES TY PE 2 WOR K PR OCE DUR ES These procedures are to be followed by all maintenance personnel and contractors performing the following work at KPDSB buildings.
More information