Overview of the NSIAC Initiative in the US for Buried and Underground Piping & Tanks

Size: px
Start display at page:

Download "Overview of the NSIAC Initiative in the US for Buried and Underground Piping & Tanks"

Transcription

1 Overview of the NSIAC Initiative in the US for Buried and Underground Piping & Tanks David Smith EPRI IAEA Technical Meeting on Ageing Management of Buried and Underground Piping and Tanks for NPPs October 13-15, 2014 Charlotte, NC

2 Focus on Buried Pipe in the US In May 2007, EPRI sponsored a workshop related to piping integrity issues Buried pipe was rated #1 issue Resulted in: Formation of Buried Pipe Integrity Group (BPIG) in 2008 Development of recommendations for buried pipe program - Dec 2008; current version is report Development of risk ranking software for buried pipe (BPWORKS Version 1.0) - Dec 2008 BP101: Training for the Buried Pipe Program Owner First class June

3 Operating Experiences In 2009 there were several well publicized leaks of radioactive material from buried and underground pipe: The US Congress got involved Feb 2009 Indian Point April 2009 Oyster Creek Industry looked at other significant leaks of radioactive material: Hatch 1986 Palo Verde 1993 Seabrook 1999 Salem 2002 Dresden 2004 Brunswick 2007 Quad Cities 2008 Vermont Yankee

4 NSIAC Initiative An NSIAC (Nuclear Strategic Issues Advisory Committee) Initiative was approved in Nov 2009 to address buried 1 pipe NSIAC is composed of CEOs / CNOs of all US nuclear plants Industry commitment, not regulation Goal was to provide Reasonable Assurance of structural and leak integrity of buried pipe with special emphasis on piping that contained radioactive materials 1 Buried - Piping that is below grade and in direct contact with the soil. 4

5 NSIAC Initiative (continued) Based on additional operating experience, in September 2010 the initiative was revised to include: Underground 2 piping and tanks that are outside of a building if they are safety related or contain radioactive materials Now called the Underground Piping and Tanks Integrity Initiative Additional elements or milestones were added for new scope 2 Underground - piping that is below grade, not accessible, and outside of buildings (e.g., in tunnels, trenches, vaults). 5

6 NSIAC Initiative (continued) In January 2013, NSIAC approved another revision to the initiative based on: Progress of the industry s implementation Tier 1 Fukushima related requirements Cumulative impact of industry and regulatory activities The latest revision includes: Scope changes to focus inspections on the most important components and align the buried and underground initiatives Allows more time to complete the first round of inspections and the associated asset management plans 6

7 Current Initiative Scope All buried and underground piping and tanks that are outside of a building and below grade (whether or not they are in direct contact with the soil) if they: Are safety related, OR Changes are highlighted! Contain licensed material or are known to be contaminated with licensed materials, OR 7

8 Current Initiative Milestones Buried Piping Changes are highlighted! Procedures and Oversight: June 30 th, 2010 Risk Ranking: Dec. 31 st, 2010 Inspection Plans: June 30 th, 2011 Inspection Implementation Start: June 30 th, 2012 Licensed Material Condition Assessment Complete: Asset Management Plan: Underground Piping and Tanks Procedures and Oversight: Dec. 31 st, 2011 Prioritization: June 30 th, 2012 Condition Assessment Plans: Dec. 31 st, 2012 Assessment Plan Implementation: June 30 th, 2013 Licensed Material Condition Assessment Complete: Asset Management Plan: Dec. 31 st,

9 NEI The Nuclear Energy Institute is the regulatory and legislative interface of the US nuclear industry Sister organization to EPRI and INPO NEI issued NEI in Dec 2009, Guideline for the Management of Buried Piping Integrity A Buried Piping Integrity Task Force was formed to provide input and direction Referenced EPRI report , Recommendations for an Effective Program to Control the Degradation of Buried Pipe ( , Revision 1) for details 9

10 Purpose of NEI Guideline for the Management of Buried Piping Integrity Document the text of the Buried Piping Integrity Initiative Describe the intent of the Initiative Communicate roles and responsibilities of industry participants Utilities, EPRI, INPO, NEI Facilitate Implementation Describe industry reporting of implementation 10

11 NEI Revision 1 NEI Revision1- Guideline for the Management of Underground Piping and Tank Integrity was issued in January of Revision 1: Adds text of the revised Initiative Clarifies the intent of the Initiative through shall statements Clarifies Initiative scope Adds definitions Enhances the process for justifying deviations Adds expectations for communication of OE and deviations New BPITF responsibilities 11

12 NEI Revision 2 NEI Revision 2- Guideline for the Management of Underground Piping and Tank Integrity was issued in January of Revision 2: Inspection Planning Guidance incorporated as Appendix C All approved initiative interpretations have been reflected where the information was appropriate. This includes: The definition of licensed material Components that are within the scope of the initiative Implementation of inspection plans Start of inspections The meaning of condition assessment Recognition of INPO s ICES database as the means for collecting adverse inspection findings. 12

13 NEI Revision 3 NEI Revision 3- Guideline for the Management of Underground Piping and Tank Integrity was issued in May of Revision 3: Revises the Initiative scope and milestones in accordance with the January 2013 changes Adds guidance for crediting inspections performed in other programs Moves the description of the deviation process into its own section Restates that the content of reports to EPRI (BPIRD) and INPO (ICES) on inspection findings and leaks includes all buried and underground piping and tanks even though the scope of the initiative changed. Adds an expectation for performing periodic self assessments 13

14 NEI Inspection Planning Guidance or Reasonable Assurance Document Purpose was to develop an approach to meet the intent of the Industry Initiative Reasonable Assurance Technical Advisory Group Subgroup of NEI BPITF Approach had been developed by 2 Utilities Draft reviews, webcast and conference calls Several levels of review and approval Incorporated into NEI Revision 2 as an appendix 14

15 Inspection Planning- Overall Approach Reasonable Assurance / Inspection Planning Guidance is a Graded Process that involves: Inventory and Risk Ranking Create Line Groupings Indirect inspection samples Direct examinations Feedback for overall program Effective use of resources through graded process, focused and quality inspections 15

16 Programmatic Guidance Consensus document of what to do is contained in EPRI report , Recommendations for an Effective Program to Control the Degradation of Buried and Underground Piping and Tanks ( , Revision 1) Considered to be a living document, to be periodically revised as technology and experience evolve Download from EPRIweb Risk based approach 16

17 US Regulatory Requirements US regulatory requirements are mostly coming through the license renewal process NUREG-1801, Generic Aging Lessons Learned (GALL report) Each revision of GALL has increased the inspection requirements (not retroactive) Buried pipe is considered to be within scope of aging management 10 CFR 50.65, Maintenance Rule 10 CFR 54, License renewal LR-ISG , which supplements/replaces the guidance in rev 2 of the GALL report NRC Inspection Manual NUREG/CR-6679, Assessment of Age-Related Degradation. NUREG/CR-6786, Risk Informed Assessment of Degraded Buried Pipes. NRR Action Plan for Buried Piping; TAC No. ME

18 INPO Assessments INPO has been conducting assessments at many plants of their buried pipe program How-to document Questions the evaluators will ask the plants Many sites have received Areas for Improvement (AFIs) or Performance Deficiencies (PDs) Common AFIs or PDs Deficiencies in the CP system The CP system is not tested and maintained Equipment problems reduce the protection of buried piping Monitoring has not received high priority Predictive inspections are not performed and analyses are not based on current information Long-term strategies do not address known vulnerabilities 18

19 Together Shaping the Future of Electricity 19

20 Why Was a Special Initiative Required - What Makes Underground Pipe Unique? Not readily accessible for inspection and leak detection Are subject to degradation mechanisms from the outside (soil side) as well as from the inside (fluid side) Also subject to occlusions Burial conditions can have chemical, geotechnical and civil-structural considerations that can be unique to each installation and/or site Backfill materials vary by their nature and degree of inspection or verification during the installation process 20

21 What Makes Underground Pipe Unique? Encompass a variety of services such as raw, treated and demin water; gases; chemicals; fuel oil; lube oil May contain radioactive fluids Encompass a wide range of materials: steel, cast iron, copper alloys, stainless, concrete, asbestos, PVC, polyethylene, FRP, etc. Encompass a wide range of sizes, from over 10 ft diameter to small bore piping Wide range of connection types: butt-welded, socket welded, flanged, threaded, bell & spigot, victaulic couplings, etc. 21

22 What Makes Underground Pipe Unique? Pipes may be bare or they may have a variety of external coatings and internal linings May or may not be cathodically protected Different types of CP systems Because the pipes are not readily accessible, buried pipe inspections have not been as common as above-ground inspections The design formulas and corresponding design margins for soil and surface loads are not defined in US codes such as ASME Loads for aboveground, buried, and underground are all different 22

23 Systems that often Contain Underground Pipes Active Drainage Auxiliary Feedwater Auxiliary Gas Building Drains Chemical Injection Chlorination Circulating Water CO2 Condensate and Feedwater Control room air supply/ventilation Cooling Oil Demineralized Water Diesel Generator Fuel Oil Domestic Water 23

24 Systems that often Contain Underground Pipes (continued) Emergency Coolant Injection Emergency Storage Water Essential Service Water Fire Protection Frazil Ice Protection Fuel Oil High Pressure Coolant Injection (HPCI) Hydrogen Instrument Air Liquid Effluent Sampling and Monitoring Lubrication Oil Lubrication Oil Waste Disposal Make-up Water 24

25 Systems that Often Contain Underground Pipes (continued) Non-essential Service Water Off-gas Pipe Trench Inactive Drainage Radwaste Reactor Core Isolation Cooling (RCIC) Refueling Water Roof Drainage Service Air Sewage System Steam Generator Blowdown Tempering Water Trash Removal Turbine bearing cooling Yard Fire Protection 25

26 Other Buried Commodities that may be Susceptible to Degradation Intake structure Traveling screens Tanks Electrical cables Phone cables Manways Abandoned lines Grounding grid Security equipment 26

INPO Perspective Groundwater Protection and RETS/REMP Meeting June 2014

INPO Perspective Groundwater Protection and RETS/REMP Meeting June 2014 Institute of Nuclear Power Operations INPO Perspective Groundwater Protection and RETS/REMP Meeting June 2014 Joe Sears Manager, Nuclear Asset Protection Key Topics Groundwater protection Underground piping

More information

Appendix B. Aging Management Programs and Activities

Appendix B. Aging Management Programs and Activities Appendix B Aging Management Programs and Activities This page is intentionally blank. TABLE OF CONTENTS Table of Contents...i Appendix B: Aging Management Programs and Activities... B.1-1 B.1 INTRODUCTION...

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 1316 - SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 22 PLUMBING

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 22 PLUMBING SECTION 221316 - SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following soil and waste, sanitary drainage and vent piping inside the building: 1. Pipe, tube,

More information

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as

More information

6.1 General. This chapter shall provide requirements for correct use of sprinkler system components and hardware.

6.1 General. This chapter shall provide requirements for correct use of sprinkler system components and hardware. NFPA 13-Proposed 2013 Edition Standard for the Installation of Sprinkler Systems TIA Log No.: 1054 Reference: Chapter 6 Comment Closing Date: June 1, 2012 Submitter: Bob Caputo, Fire & Life Safety America

More information

The Materials Initiative NEI Overview

The Materials Initiative NEI Overview The Materials Initiative NEI 03-08 Overview Robin Dyle EPRI Annual Materials/NRC Technical Exchange June 2, 2015 Overview Primary system materials integrity is vital to plant performance and reliability

More information

Daytona Beach Pier Building Renovation Jun 2010

Daytona Beach Pier Building Renovation Jun 2010 SECTION 15150 - SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

Efficiency Bulletin: Maximizing the Benefit of Portable Equipment

Efficiency Bulletin: Maximizing the Benefit of Portable Equipment March 23, 2017 Color Code: Green Efficiency Bulletin: 17-10 Maximizing the Benefit of Portable Equipment Utilize portable equipment, including equipment procured as a part of the B.5.b and FLEX programs,

More information

July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC

July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC July 29, 2011 R. William Borchardt, Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 SUBJECT: Petition Pursuant to 10 CFR 2.206 Demand For Information Regarding

More information

NuScale SMR Technology

NuScale SMR Technology NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by

More information

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,

More information

P Boiling Water Reactor Vessel and Internals Program (BWRVIP)

P Boiling Water Reactor Vessel and Internals Program (BWRVIP) 2018 Research Portfolio P41.01.03 - Boiling Water Reactor Vessel and Internals Program (BWRVIP) Program Description As boiling water reactors (BWRs) age, various types of materials degradation mechanisms

More information

Plant Engineering. Program Overview

Plant Engineering. Program Overview Plant Engineering Program Description Program Overview Safe, reliable, cost-effective nuclear plant operation is supported by detailed, technically sound engineering practices. Engineering analysis, for

More information

Low-Level Waste and Radiation Management

Low-Level Waste and Radiation Management Low-Level Waste and Radiation Management Program Description Program Overview Nuclear power plants face significant regulatory, economic, environmental, and public perception pressures with respect to

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

www.flexonics.com 1 800 854 2553 Senior Flexonics Pathway Division 2400 Longhorn Industrial Dr. New Braunfels, Texas 78130 Tel Int: 1 830 629 8080 Fax Int: 1 830 629 6899 E-mail: sales@pathway.flexonics.com

More information

Nuclear Industry Support System

Nuclear Industry Support System Nuclear Industry Support System Vince Gilbert Chief Knowledge Officer December 9, 2010 Objectives Background for nuclear industry support Overview Unique Nuclear Industry Support features back Highlight

More information

Claude FAIDY, EDF (France) Overview of EDF ageing management program of safety class components

Claude FAIDY, EDF (France) Overview of EDF ageing management program of safety class components program of safety class components Claude Faidy, Electricité de France - SEPTEN 12-14 Avenue Dutrievoz - 69628 Villeurbanne Cedex - France Tel: +33 4 7282 7279, Fax: +33 4 7282 7697 E-mail: claude.faidy@edf.fr

More information

192GasCatalog.

192GasCatalog. 192GasCatalog www.energyu.org www.midwestenergy.org 192-Abnormal Operating Conditions... 4 192-0101 Characteristics and Hazards of Natural Gas... 4 192-0201 Gas Detection and Alarm System Maintenance...

More information

ASME B31.3 Process Piping. 19. What s Different in B31.1

ASME B31.3 Process Piping. 19. What s Different in B31.1 ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. What s Different in B31.1-1 19. What s Different in B31.1 Scope Organization of the Code

More information

ASME B31.3 Process Piping

ASME B31.3 Process Piping ASME B31.3 Process Piping Charles Becht IV, PhD, PE Don Frikken, PE Instructors BECHT ENGINEERING COMPANY, INC. Nonmetallic Piping - 1 Piping Development Process 1. Establish applicable system standard(s)

More information

Graded approach practices for the mechanical components of French research reactor projects

Graded approach practices for the mechanical components of French research reactor projects Graded approach practices for the mechanical components of French research reactor projects Claude PASCAL RMR/RR Rabat IAEA conference, november 2011 Content Context Classification of SSCs Associated Requirements

More information

Long Term Operation of Nuclear Power Plants in Spain: Preparing for the Future

Long Term Operation of Nuclear Power Plants in Spain: Preparing for the Future XXVIII Congreso Anual de la Sociedad Nuclear Mexicana - 2017 LAS/ANS Symposium Long Term Operation of Nuclear Power Plants in Spain: Preparing for the Future Ignacio Marcelles, Eva Frutos, Xavier Jardí

More information

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water

More information

INDUSTRIAL PIPE FITTINGS, LLC

INDUSTRIAL PIPE FITTINGS, LLC Page 1 of 9 SPIROLITE MUNICIPAL AND INDUSTRIAL ODOR CONTROL PIPING Municipal wastewater treatment plants, industrial processes and composting facilities can be assured of trouble free transport of foul

More information

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated.

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated. SECTION 221316 SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

2017 Water Reactor Fuel Performance Meeting September 10 (Sun) 14 (Thu), 2017 Ramada Plaza Jeju Jeju Island, Korea

2017 Water Reactor Fuel Performance Meeting September 10 (Sun) 14 (Thu), 2017 Ramada Plaza Jeju Jeju Island, Korea Extended Storage Collaboration Program for Addressing Long-Term Dry Storage Issues Hatice Akkurt 1 1 Electric Power Research Institute (EPRI), 1300 W WT Harris Blvd, Charlotte, NC 28262, hakkurt@epri.com

More information

DRAFT REGULATORY GUIDE

DRAFT REGULATORY GUIDE Purpose vb U.S. NUCLEAR REGULATORY COMMISSION November 2015 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 4 DRAFT REGULATORY GUIDE DRAFT REGULATORY GUIDE DG-4025 (Proposed New Regulatory Guide) Technical

More information

Westinghouse AP1000. Reactor

Westinghouse AP1000. Reactor Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment

More information

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS - June 2013 Addendum GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS SUBSECTION "A" : GENERAL RULES SUBSECTION "B" : CLASS 1 COMPONENTS SUBSECTION "C" : CLASS 2 COMPONENTS SUBSECTION "D" : CLASS

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 1313 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Furnish and install soil, waste, and vent piping systems within building and connect with outside

More information

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS

SECTION STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY 1.2 SUBMITTALS 1.3 PROJECT CONDITIONS SECTION 334100 - STORM UTILITY DRAINAGE PIPING PART 1 - GENERAL 1.1 SUMMARY Section Includes: 1. Pipe and fittings. 2. Drain Basin. 3. De-chlorination tablet feeder. 4. Non-pressure transition couplings.

More information

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant

More information

Transition to Flexible Plant Operations U.S.A. Update

Transition to Flexible Plant Operations U.S.A. Update Transition to Flexible Plant Operations U.S.A. Update Sherry Bernhoft EPRI Program Manager IAEA EDF Technical Meeting on NPP Flexible Operations Paris, France September 2013 EPRI Our History Founded in

More information

INL/EXT Key Design Requirements for the High Temperature Gascooled Reactor Nuclear Heat Supply System

INL/EXT Key Design Requirements for the High Temperature Gascooled Reactor Nuclear Heat Supply System INL/EXT-10-19887 Key Design Requirements for the High Temperature Gascooled Reactor Nuclear Heat Supply System September 2010 DISCLAIMER This information was prepared as an account of work sponsored by

More information

NRC Inspection Report / September 21, Staff Exhibit 5

NRC Inspection Report / September 21, Staff Exhibit 5 NRC Inspection Report 05000219/2006007 September 21, 2006 Staff Exhibit 5 September 21, 2006 Mr. Christopher M. Crane President and CEO AmerGen Energy Company, LLC 200 Exelon Way, KSA 3-E Kennett Square,

More information

STATE UNIVERPROGRAM DIRECTIVES

STATE UNIVERPROGRAM DIRECTIVES DIRECTIVE 15H-10 PIPING TYPES AND MATERIALS Issue date: September 2017 Steam & Condensate Piping Service & Location Pipe Size Pipe Material & Weight Joint Type Fitting Material Insulation Material Low

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

SECTION PLUMBING PIPING SYSTEMS

SECTION PLUMBING PIPING SYSTEMS SECTION 15300 PLUMBING PIPING SYSTEMS PART 1 - GENERAL 1.01 SPECIAL NOTICE A. Each contractor shall read all relevant documents, become familiar with the job, the scope of work, type of general construction,

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment

More information

PWROG Reactor Internals Projects

PWROG Reactor Internals Projects PWROG Reactor Internals Projects Industry/NRC Exchange Meeting June 2015 Glenn Gardner, Mike Burke, Heather Malikowski Topics Integrated Industry Approach, Processes and Tools Materials Applications Fleet-wide

More information

FATIGUE MONITORING FOR DEMONSTRATING FATIGUE DESIGN BASIS COMPLIANCE

FATIGUE MONITORING FOR DEMONSTRATING FATIGUE DESIGN BASIS COMPLIANCE FATIGUE MONITORING FOR DEMONSTRATING FATIGUE DESIGN BASIS COMPLIANCE D. Gerber, G. Stevens, T. Gilman, J. Zhang Structural Integrity Associates,San Jose,USA Structural Integrity Associates,San Jose,USA

More information

Class III Pipes Fittings (Dy 500 mm)

Class III Pipes Fittings (Dy 500 mm) p pproval roramms for U rcos orasato Mutual coto (M)No. 2.9 STANDARD FOR CERTIFICATION Approval Programmes Type Approval Programmes for EU recognised organisation Mutual Recognition (MR) No. MR-P003 Class

More information

Accepting Supplier ISO 9000 Quality Programs

Accepting Supplier ISO 9000 Quality Programs Accepting Supplier ISO 9000 Quality Programs IEEE Subcommittee on Qualification October 7-8, 2004 Leigh A. Aparicio PSE Technical Leader aparicio@epri.com Project Overview ISO 9000 Phase I Initiated in

More information

Sargent & Lundy LLC April 8, 2014

Sargent & Lundy LLC April 8, 2014 Farid M. Berry Vice President & Project Director Sargent & Lundy LLC April 8, 2014 Role of the OWNER S ENGINEER Technical Meeting on Becoming a Knowledgeable Customer Obninsk and Novovoronezh, Russian

More information

SECTION PIPE & PIPE FITTINGS PART 1 GENERAL

SECTION PIPE & PIPE FITTINGS PART 1 GENERAL SECTION 02610 PIPE & PIPE FITTINGS PART 1 GENERAL 1.01 DESCRIPTION A. This Section includes the material and bedding requirements for all pipe and pipe fittings for underground pressure and non-pressure

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Eleventh Quarterly Update to the Estimate to Complete November - January 2015 Published April 2015 Table of Contents Section 1 - Executive Summary... 3

More information

TECHNICAL PROCEDURE TABLE OF CONTENTS

TECHNICAL PROCEDURE TABLE OF CONTENTS TECHNICAL PROCEDURE No. Page DATE: 07/3/5 CATEGORY UNDERGROUND STRUCTURES SUBJECT OF SMUD s UNDERGROUND TRANSMISSION TABLE OF CONTENTS PURPOSE... 2 2 REFERENCES... 2 3 MINIMUM REQUIREMENTS... 2 4 RELATED

More information

SECTION FOUNDATION DRAINAGE

SECTION FOUNDATION DRAINAGE SECTION 33 41 13 SPEC WRITER NOTES: Use this section only for NCA projects. Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section

More information

NUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S.

NUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S. NUPIC General Membership and Vendor Meetings June 2014 Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S. NRC 1 Insights from the Fukushima Event 2014 NRC Vendor Inspections Recent

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE GRANT NO: UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA The following standard specification is intended to be edited according to the specifics of the project. Brackets [ ] and areas shaded in gray [e.g. format] indicate requirements that are optional depending

More information

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 Classification requirements 3 3.1 Principles of safety classification 3 3.2 Classification

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

Palo Verde Generating Station NEI Lessons Learned. Michael Wittas September 28, 2017

Palo Verde Generating Station NEI Lessons Learned. Michael Wittas September 28, 2017 Palo Verde Generating Station NEI 16-06 Lessons Learned Michael Wittas September 28, 2017 Overview Background & History Pre-FLEX Temporary Equipment Fukushima Daiichi Response NRC RIS 2008-15 Palo Verde

More information

Nuclear Service Valves

Nuclear Service Valves GE Energy Consolidated* Pressure Relief Valves Nuclear Service Valves Pressure relief solutions for the nuclear industry Safety Relief Valves Safety Valves Advanced Technology and Equipment Manufactured

More information

Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station

Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station November 26, 2015 The Kansai Electric Power Co., Inc. Application for Permission to Extend the Operating Period and Application for Approval of Construction Plans of Unit 3 at Mihama Nuclear Power Station

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

Protective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc.

Protective Coatings for Underground Utility Concrete Structures. By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc. Protective Coatings for Underground Utility Concrete Structures By: John E. Davis Inside Sales & Marketing Specialist: Sauereisen, Inc. As our cities and municipalities grow older, the utility and wastewater

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications

More information

Gasketed Sewer Pipe. Storm and Sanitary pipe for use with Gasketed Sewer Fittings.

Gasketed Sewer Pipe. Storm and Sanitary pipe for use with Gasketed Sewer Fittings. Gasketed Sewer Pipe Storm and Sanitary pipe for use with Gasketed Sewer Fittings. Gasketed Sewer Pipe Installation Royal Municipal Solutions Gasketed Sewer Pipe weighs a fraction of the weight of traditional

More information

Kozloduy NPP units 5&6

Kozloduy NPP units 5&6 Kozloduy NPP units 5&6 Ageing management of Buried and Underground Piping and Tanks at NPPs Technical Meeting 621-I2-TM-47031 IAEA / EPRI, Charlotte 13-15.10.2014 Daniel Genov Agenda 1. Kozloduy NPP Plc

More information

SECTION LAYING AND JOINTING BURIED PIPELINES

SECTION LAYING AND JOINTING BURIED PIPELINES SECTION 02650 LINES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Installation of all underground pipelines. Provide pipeline materials, coatings and linings as specified and pipe of the types, sizes

More information

195LiquidsCatalog.

195LiquidsCatalog. 195LiquidsCatalog www.energyu.org www.midwestenergy.org 195 Abnormal Operating Conditions... 3 195-0060 General Abnormal Operating Conditions (CT60)... 3 195-0000 Documentation & Reporting... 3 195-0403

More information

FS-DUO. Wastewater Flow Distributor Technical Data. Submittal Special Precautions Specifications Installation. (62.2 cm) (62.2 cm)

FS-DUO. Wastewater Flow Distributor Technical Data. Submittal Special Precautions Specifications Installation. (62.2 cm) (62.2 cm) Wastewater Flow Distributor Technical Data Submittal Special Precautions Specifications Installation 24½" (62.2 cm) 12½" (31.8 cm) 24½" (62.2 cm) (30.5 cm) SUBMITTAL STANDARD: 4" plain end inlet/outlet

More information

September 19, Mr. Biff Bradley, Director Risk Assessment Nuclear Energy Institute Suite I Street, NW Washington, DC

September 19, Mr. Biff Bradley, Director Risk Assessment Nuclear Energy Institute Suite I Street, NW Washington, DC September 19, 2007 Mr. Biff Bradley, Director Risk Assessment Suite 400 1776 I Street, NW SUBJECT: FINAL SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE (NEI) TOPICAL REPORT (TR) 04-10, REVISION 1, RISK-INFORMED

More information

NUCLEAR PLANT WITH VK-300 BOILING WATER REACTORS FOR POWER AND DISTRICT HEATING GRIDS

NUCLEAR PLANT WITH VK-300 BOILING WATER REACTORS FOR POWER AND DISTRICT HEATING GRIDS 7th International Conference on Nuclear Engineering Tokyo, Japan, April 19-23, 1999 ICONE-7335 NUCLEAR PLANT WITH VK-300 BOILING WATER REACTORS FOR POWER AND DISTRICT HEATING GRIDS Yu.N. Kuznetsov*, F.D.

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section DUCTILE IRON PIPE AND FITTINGS Section 02501 PART 1 GENERAL 1.01 SUMMARY This Section includes ductile iron pipe and fittings for water lines, wastewater force mains, gravity sanitary sewers, and storm sewers. 1.02 MEASUREMENT AND PAYMENT

More information

Plant Life Management Canada

Plant Life Management Canada 2017/02/22 TWG on LM for NPP Plant Life Management Canada - Copyright - General Utility Focus/Concerns Expanded focus last few years: Still driven primarily by desire to improve Equipment Reliability Index

More information

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012 NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012 AP1000 IN FEBRUARY 2012, THE FIRST NUCLEAR POWER PLANTS IN THE US IN 35 YEARS WERE LICENSCED TO BEGIN CONSTRUCTION. TWO WESTINGHOUSE AP1000 NUCEAR REACTOR

More information

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT

A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT A DYNAMIC ASSESSMENT OF AUXILIARY BUILDING CONTAMINATION AND FAILURE DUE TO A CYBER-INDUCED INTERFACING SYSTEM LOSS OF COOLANT ACCIDENT Z.K. Jankovsky The Ohio State University Columbus, USA Email: jankovsky.3@osu.edu

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Plastic (PVC) Pressure Water Pipe & Fittings C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Plastic (PVC) Pressure Water Pipe & Fittings C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 15064 - Plastic (PVC) Pressure Water Pipe & Fittings C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 DELIVERY... 1 1.03 QUALITY ASSURANCE...

More information

Draft for comments only Not to be cited as East African Standard

Draft for comments only Not to be cited as East African Standard CD/K/055-5:2009 ICS 23.040.20; 23.040.45; 91.140.60; 93.025 EAST AFRICAN STANDARD Plastics piping systems Polyethylene (PE) pipes and fittings for water supply Part 5: Fitness purpose of the system EAST

More information

STANDARD SPECIFICATIONS SECTION JACKED CASING

STANDARD SPECIFICATIONS SECTION JACKED CASING STANDARD SPECIFICATIONS SECTION 02315 JACKED CASING PART 1 - GENERAL A. Description Tunneling method by jacked casing, directional drilling, or a tunnel boring machine, for highway, railroad, creek, and

More information

SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL)

SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL) h~i:! SECTION I FLEXIBLE PIPE VS. RIGID PIPE (GENERAL) Generally, rigid pipes have the following characteristics: made in discrete lengths use gaskets in joints to form a water-tight seal often produced

More information

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 8

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 8 September 2013 Page 1 of 8 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described hereunder shall consist of the construction of sewer and/or water pipeline or watermain crossings of rivers and other

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe Design and Installation Guide PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar

More information

DAVID J. HOLLER DETAILED EXPERIENCE

DAVID J. HOLLER DETAILED EXPERIENCE DAVID J. HOLLER EXPERIENCE SUMMARY QA Professional and Technical Specialist with 33 years of nuclear power-related experience. Experience and capabilities include quality program assessment, management

More information

NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS

NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS James K. (Jim) Liming ABSG Consulting Inc. (ABS Consulting) 300

More information

PipelineCompass : Pipeline Corrosion Modeling, Prediction, Assessment & Solutions Version 9.17

PipelineCompass : Pipeline Corrosion Modeling, Prediction, Assessment & Solutions Version 9.17 Page 1 of 7 Advisory Consultancy Training Expert Witness FA Diagnosis Design Review Corrosion Test Inspection Coatings + More >>> PipelineCompass : Pipeline Corrosion Modeling, Prediction, Assessment &

More information

BSR GPTC Z TR x GM Referenced Standards Page 1 of 12

BSR GPTC Z TR x GM Referenced Standards Page 1 of 12 Page 1 of 12 PURPOSE: Review existing GM and modify as appropriate in light of Amendment 192 119. Regulations Section 192.620 To address increased risk of a maximum allowable operating pressure based on

More information

Radioactive Materials from U.S. Nuclear Plants

Radioactive Materials from U.S. Nuclear Plants Routine Releases of Radioactive Materials from U.S. Nuclear Plants Dave Lochbaum Union of Concerned Scientists August 2014 Revision i 1 1 The idea for this material came during a November 2013 workshop

More information

AGEING MANAGEMENT ASSESSMENT

AGEING MANAGEMENT ASSESSMENT AGEING MANAGEMENT ASSESSMENT Module 9 Session 9 Resource document: AMAT Guidelines, Reference document for Ageing Management Assessment Teams, Services Series No. 4, (1999) International Atomic Energy

More information

Managing I&C Obsolescence for Plant Life Extension

Managing I&C Obsolescence for Plant Life Extension Managing I&C Obsolescence for Plant Life Extension IAEA-CN-155/075 Larry Chi Consulting Engineer Bin Zhang Senior Engineer GE-Hitachi Nuclear Energy October 2007 1 Managing I&C Obsolescence for Plant Life

More information

SEWER FORCE MAIN HDPE PIPE

SEWER FORCE MAIN HDPE PIPE SECTION 15150 SEWER FORCE MAIN HDPE PIPE PART 1: GENERAL 1-1 DESCRIPTION: This specification governs the material, pipe, fittings, joining methods and general construction practice for High Density Polyethylene

More information

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the Council of the European Union declared

More information

APR1400 Safe, Reliable Technology

APR1400 Safe, Reliable Technology APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics

More information

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft) TROJAN DECOMMISSIONING STATUS OPUC Meeting March 8, 2005 (draft) 1 Meeting Agenda Trojan Decommissioning Overview History Major Projects Overall Performance Remaining Major Activities Current Issues USDOE

More information

STORM DRAINAGE CHAPTER 11

STORM DRAINAGE CHAPTER 11 CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,

More information

CONSTRUCTION SPECIFICATION FOR SEWAGE FORCEMAIN INSTALLATION IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR SEWAGE FORCEMAIN INSTALLATION IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 412 NOVEMBER 2009 CONSTRUCTION SPECIFICATION FOR SEWAGE FORCEMAIN INSTALLATION IN OPEN CUT TABLE OF CONTENTS 412.01 SCOPE 412.02 REFERENCES 412.03

More information

C. ASSE 1013 Performance Requirements for Reduced Pressure Principle Backflow Preventers.

C. ASSE 1013 Performance Requirements for Reduced Pressure Principle Backflow Preventers. PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

NRC LIAISON REPORT NRC SIGNS NUCLEAR SAFETY COOPERATION AGREEMENTS WITH SEVEN NATIONS

NRC LIAISON REPORT NRC SIGNS NUCLEAR SAFETY COOPERATION AGREEMENTS WITH SEVEN NATIONS NRC LIAISON REPORT NRC SIGNS NUCLEAR SAFETY COOPERATION AGREEMENTS WITH SEVEN NATIONS The U.S. Nuclear Regulatory Commission Chairman Gregory B. Jaczko signed agreements with representatives of seven countries

More information

A Comparison: ASME B31.1 Power Piping versus ASME B31.3 Process Piping

A Comparison: ASME B31.1 Power Piping versus ASME B31.3 Process Piping A Comparison: ASME B31.1 Power Piping versus ASME B31.3 Process Piping Don Frikken, PE BECHT ENGINEERING COMPANY, INC. 1 Topics Discussed B31 History Scopes Organization of the Codes Bases for Allowable

More information

SPECIAL SPECIFICATION 3504 Septic Tank System

SPECIAL SPECIFICATION 3504 Septic Tank System 1993 Specifications CSJ s 3136-01-126, etc. & 0683-01-070, etc. SPECIAL SPECIFICATION 3504 Septic Tank System 1. Description. This Item shall govern for all materials, equipment and labor necessary for

More information

The Risk of Nuclear Power

The Risk of Nuclear Power 13 th International Conference on Probabilistic Safety Assessment and Management [PSAM13] The Risk of Nuclear Power Soon Heung Chang Handong Global University Oct 4, 2016 Contents 1 2 3 4 Introduction:

More information