TAROOM COAL PTY LTD ACN ELIMATTA MINE PROJECT MINING LEASE APPLICATIONS MLA OVER EPC 650 MLA OVER EPC 1171 AND MLA 50271

Size: px
Start display at page:

Download "TAROOM COAL PTY LTD ACN ELIMATTA MINE PROJECT MINING LEASE APPLICATIONS MLA OVER EPC 650 MLA OVER EPC 1171 AND MLA 50271"

Transcription

1 TAROOM COAL PTY LTD ABN: TAROOM COAL PTY LTD ACN ELIMATTA MINE PROJECT MINING LEASE APPLICATIONS MLA OVER EPC 650 MLA OVER EPC 1171 AND MLA AMENDED INITIAL DEVELOPMENT PLAN or IDP 1 PART 15.3 OF THE APPLICATION SECTIONS 318DT, 318DU, 318DV AND 318DW OF THE MINERAL RESOURCES ACT 1989 (QLD) JULY This document contains only the Initial Development Plan required under s 318DT of the Mineral Resources Act 1989 (Qld) and also addresses certain requirements of sections 318DU, 318DV and 318DW of the Mineral Resources Act 1989 (Qld). It does not provide for the CSG Statement or CSG Assessment Criteria, which are subject to a different set of rules and are located in part 15.3B of this application.

2 CHECKLIST OF LEGISLATIVE REQUIREMENTS Document Section (MR Act) Requirement Section ref Initial Development Plan 318DT(1)(a) an overview of the activities proposed to be carried out under the proposed mining lease during all of its proposed term DT(1)(b) for each year of the plan period: 1.2 the nature and extent of activities to be carried out under the proposed mining lease during the year; and where the activities are proposed to be carried out 318DT(1)(c) for each mineral the applicant proposed to mine under the proposed mining lease, each of the following: the location and estimate of the resources of the mineral in the area, or proposed area, of the mining lease 2 the standards and procedures used to make the estimate 3 the rate and amount of the proposed mining 4 approximately when the proposed mining is to start DT(1)(d) 318DT(1)(e) a schedule for the proposed mining during the plan period maps that show the matters mentioned in paragraphs (b) and (c)(i), (iii) and (iv) any other information relevant to the criteria mentioned in s 318EF for matters relevant to the CSG statement and CSG assessment criteria see part 15.3B of the Mining Lease Applications 318DT(1)(f) reasons why the plan is considered appropriate 6 318DT(1)(g) another matter prescribed under a regulation none identified 218DU state the period of the proposed plan DV 318DW statement of how the effects on, and the interests of, any relevant overlapping or adjacent petroleum tenure holder have, or have not, been considered having regard to: the main purposes of this part; and the CSG assessment criteria, other than the initial development plan requirements requirement that the activities provided for under the proposed plan must seek to optimise the use of incidental 7 8 Page 2 of 27

3 Document Section (MR Act) Requirement coal seam gas in a safe and efficient way, if it is commercially and technically feasible to do so Section ref Nb: In this part of this mining lease application, MR Act means Mineral Resources Act 1989 (Qld). Page 3 of 27

4 1. Overview of the Activities Proposed to be Carried Out 1.1 Overview This section addresses sections 318DT(1)(a) and (b) of the MR Act. Taroom Coal Pty Ltd ACN (Taroom Coal) has made three contiguous mining lease applications (MLAs) for the Elimatta Mine Project (Project) that this Amended Initial Development Plan (Amended IDP) describes. The MLAs were each made in This Amended IDP is being lodged in July This Amended IDP replaces the individual Initial Development Plans (IDPs) included in the 2009 MLAs. The term of this Amended IDP is proposed as three years from the date of grant of the Project MLAs on the assumption that the Project MLAs will be granted from a common date. Notionally, the term is from 1 January 2017 to 31 December 2019 to allow for site preparation, construction of infrastructure and commencement of production operations at the Project. MLA Elimatta Mining, is made over all of the area of EPC 650 and is intended for mining activities and related infrastructure. MLA Elimatta Infrastructure, was made in 2009 over the greater part of Exploration Permit for Coal (EPC) 1171 and Prospecting Permit (PP) However, EPC 1603 was subsequently granted over the area of PP to another party. Taroom Coal and the other party were unable to reach a commercial arrangement to maintain the area of PP within the MLA boundary. Consequently this part of the application area was abandoned in This MLA is intended for infrastructure associated with mining on MLA 50254, but not for mining purposes. MLA and MLA are each an application for a mining lease under section 234(1) of the MR Act. MLA Elimatta Transport is an application for a transport and services corridor to connect MLA and MLA areas. MLA is an application under section 316 of the MR Act. The MLAs cover a combined area of ~3,975 hectares (ha). In March 2015 Taroom Coal entered into a Co-Development Agreement (CDA) with BG International (AUS) Pty Ltd ABN , CNOOC Coal Seam Gas Company Pty Ltd ABN and Tokyo Gas QCLNG Pty Ltd ABN collectively the Gas Party, for purposes of the CDA. The CDA records the commercial (and confidential) arrangements between Taroom Coal and the Gas Party for the development of the resources in the Overlap Area effectively the area of the Taroom Coal MLAs. This Amended IDP aligns its activities with those of the CDA and the Co-Development Plan made as part of the CDA. The Project is located in the Western Downs Regional Council area in southern Queensland, approximately 45 km south-west of Taroom and 380 km north-west of Brisbane. Access to the Project site is from the Leichhardt Highway, the Yuleba Taroom Road and the local Perretts Road. The general location of the project is as shown in Figure 1. Page 4 of 27

5 Figure 1: Elimatta Project Location Page 5 of 27

6 The Elimatta Project is based on the development of a 259 million-tonne (Mt) thermal coal resource (JORC 2004 compliant) of the Juandah formation in the Surat Basin. The Project is planned to mine up to 8.2 Mtpa of ROM coal (average 7.5 Mtpa) to produce an average 5.0 Mtpa of product coal for export. The target commencement date for production is 2019 with this timing dependent on date of grant of the leases, the state of the international market for thermal coals, the availability of services and infrastructure required for power and water supply and product coal transportation and shipping. The mining leases term applied for is forty (40) years, to allow for construction time prior to commencing production activities, the period of production activities extending to more than 30 years and final rehabilitation of the site at the end of mining operations to the condition required in the Environmental Authority for the Project. The Project construction period on site prior to start of full scale coal production is anticipated to be months with first mine excavation activities site preparation and drainage management commencing after 13 months. The Project s operational phase will involve open-cut mining using truck and excavator methods within MLA Overburden and interburden will be disposed of both in-pit and in out-of-pit spoils dumps located on site and contiguous with the pit excavation. ROM coal will be hauled from the pit area to the Coal Handling and Processing Plant (CHPP) located on MLA for processing via a dedicated private haul road within MLA Processing will involve crushing, screening and washing to separate coal from waste materials. Fine waste rejects will be partially dewatered, with water recycled to the processing plant, and pumped to dedicated tailings storage facilities. Coarse rejects will be dewatered and disposed of within spoil dumps. Product coal is intended to be transported by rail to Gladstone Port for export through the Wiggins Island Coal Export Terminal (or the R G Tanna Coal Terminal). During construction the number of on-site personnel is estimated to peak at more than 500 (erection of CHPP structure) and during operations at about 300 people, rising over time to more than 350. Mine operations are planned to be all day, all year. The Elimatta Transport MLA overlaps MDL 449, MDL 411 and MLA lodged by Glencore Coal Queensland Pty Ltd. Because MLA is an application for a mining lease for transportation and services (and not for mining), Taroom Coal was not required to hold an underlying mining tenure upon which to base the application. Taroom Coal has an agreement with Glencore Coal Queensland Pty Ltd (formerly Xstrata Coal Queensland Pty Ltd) whereby the Wandoan Project proponents consent to, and undertake not to object to, the grant of Taroom Coal s MLA for transportation and services. In return, Taroom Coal will consent to, and undertake not to object to, the grant of a coal mining lease (ML) over MLA Regional petroleum tenements that underlie or are adjacent to the Elimatta Project are shown in Table 1 (as at 19 May 2015). Page 6 of 27

7 Table 1: Underlying & Adjacent Petroleum Tenements MLA Areas Tenement Holder Status Status Date Expiry ATP 852 PLA 299 BG International (AUS) Pty Ltd (73.5%), CNOOC Coal Seam Gas Company Pty Ltd (25%) Tokyo Gas QCLNG Pty Ltd (1.25%) BG International (AUS) Pty Ltd (73.5%), CNOOC Coal Seam Gas Company Pty Ltd (25%) Tokyo Gas QCLNG Pty Ltd (1.25%) Granted 20 th April th April 2019 Application 22 nd May BG International (AUS) Pty Ltd (73.5%), CNOOC Coal Seam Gas Company Pty Ltd (25%) Tokyo Gas QCLNG Pty Ltd (1.25%) PL 498 Granted 19 th December th December 2043 BG International (AUS) Pty Ltd (73.5%), CNOOC Coal Seam Gas Company Pty Ltd (25%) Tokyo Gas QCLNG Pty Ltd (1.25%) PL 464 Granted 15 th October th October 2043 PLA 397 BG International (AUS) Pty Ltd (73.5%), CNOOC Coal Seam Gas Company Pty Ltd (25%) Tokyo Gas QCLNG Pty Ltd (1.25%) Application 26 th July The Elimatta Mining MLA overlaps Petroleum Lease Application (PLA) 299 made by the Gas Party. PLA 299 was made over part of Authority to Prospect (ATP) 852. Where a MLA is made over a granted ATP, then the coal seam gas provisions of the MR Act apply. The MLA must include additional components, such as a CSG statement, that give consideration to the development of petroleum (including coal seam gas) from the same area. The ML applicant must use reasonable attempts to consult with the ATP holder and enter into a coordination arrangement that facilitates the coordinated future development of both coal and petroleum resources. The Elimatta Infrastructure MLA overlaps PLA 397 made by the Gas Party. PLA 397 was made over ATP 852. Despite the fact that no actual coal mining will be undertaken on this ML, the coal seam gas provisions of the MR Act still apply. The provisions apply to a coal mining lease which includes a Page 7 of 27

8 specific purpose mining lease for a purpose associated with, arising from or promoting the activity of coal mining, whether or not it is also granted for a purpose other than coal mining. The Elimatta Transport MLA also overlaps PLA 299 and ATP 852. The coal seam gas provisions discussed above will not apply to MLA as the MLA is for a transportation ML under s 316 of the MR Act. As noted above, Taroom Coal and the Gas Party have a Co-Development Agreement and as at the date of this Amended IDP, are working together to make a Coordination Arrangement for the overlap area the co-development area for the Minister s consideration. There are no Greenhouse Gas tenures or geothermal tenures within the immediate Project area. Figure 2: Elimatta Project Mining and Petroleum Tenures Project Proponent Taroom Coal is the proponent for the Elimatta Project and applicant for the project MLs and Environmental Authority. At the time of the MLAs were lodged in 2009, Taroom Coal was a wholly owned subsidiary of Northern Energy Corporation Limited (NEC). In 2011 NEC was taken over by New Hope Corporation Limited (New Hope) such that, now, Taroom Coal is a wholly owned subsidiary of New Hope. New Hope is an Australian publicly listed company with a long history dating to the early 1950s of coal mine development and operation in Queensland and overseas. At the time of making this Amended IDP New Hope s office is located at: 3/22 Magnolia Drive Via Tournament Drive Brookwater Qld 4300 Page 8 of 27

9 1.2 Description of proposed activities This section also addresses section 318DT(1)(b) of the MR Act. The construction of the mining operation and the CHPP, stockpiling and transportation facilities, maintenance workshops and servicing plant and administration buildings within the Project MLA areas are all part of the proposal to develop the Project. The main elements of the proposed development to be constructed and operated are: Open pit coal mining excavations; Haul road from mine area and ROM coal receiving area and stockpile; ROM dump hopper and primary sizing station; Secondary sizing station and linking conveyors; Coal processing plant comprising a single module of 350tph capacity; Product coal conveyors and stockpile; Train loading area (or alternatively, truck loading if road haulage is part of the transport solution); Rail balloon loop; Plant reject material storage areas; Heavy equipment workshop and vehicle servicing areas; Warehouse; Administration building and change rooms; Fuel, lubricants and tyre stores; Light and heavy vehicle parking hard stands; Access roads; Raw water storage and water management dams and pipelines; and Electrical power substation and distribution network. The following table outlines the nature and extent of the activities proposed to be carried out, including the proposed location of activities during the term of this IDP. Table 2: Nature and Extent of Activities Amended IDP Year Nature and Extent of Activities Location of Activities Year 1 Site preparation and construction See Figure 3 for General Project layout Year 2 Year 3 Construction and start excavation activities Production activities (finalise construction) See Figure 4 for Infrastructure Area Layout See Figure 5 for proposed mine excavation activities at the end of mine year 01 The general layout of the main infrastructure is shown in Figures 3 and 4 and the mine operation as it is planned to be at the end of Year 3 of this IDP (Mine Project Year 01) is show in Figure 5. Mining activities are currently planned within the Elimatta Mining MLA area with the coal processing and related tasks, including train loading, located within the Elimatta Infrastructure MLA area. Page 9 of 27

10 Figure 3: Project Major Infrastructure General Layout Page 10 of 27

11 Figure 4: Mine Infrastructure Area General Layout Page 11 of 27

12 Figure 5: Mining Operations - End of Mine Project Year 01 (Amended IDP Year 3) Page 12 of 27

13 2. Location and Estimate of the Resources in the MLA Area This section addresses section 318DT(1)(c)(i) of the MR Act. 2.1 Location and Estimate MLA The coal resource within the MLA area has been classified into measured, indicated and inferred categories in accordance with the 2004 JORC Code. The estimated total resource at 259 Mt of in-situ coal, is shown in Table 3. Table 3: Coal Resources within MLA Horizon Total Resource Area (ha) In-Situ Density (g/cc) Thickness Range (m) Measured Tonnage (x 106) Indicated Tonnage (x 106) Inferred Tonnage (x 106) UG 1, Y 2, A 2, B 2, BC C Sub Total Mt Mt 50 Mt Grand Total (rounded) 259 Mt An extensive exploration drilling program in the period 2007 to 2012 has been conducted by Taroom Coal in order to define the resource and provide for mine planning. The drill hole location plan for MLA is as shown in Figure 6. The deposit is situated over a broad north-south trending anticline which plunges to the south. The coal seams dip to the south over most of the deposit, generally at less than one and a half degrees as shown in Figure 7.Forty individual coal seams have been correlated and modelled. The individual seams have been assigned to eight separate groups, based largely on historic seam nomenclature. In decreasing stratigraphical order, the seam groups are T, UG, Y, A, B, BC, C and LG. The seams are often interbanded with siltstone and mudstones but there are also thick sections of clean, low ash coal with very few stone bands. Typical stratigraphic column is as shown in Figure 8. The seams split and coalesce, but are thicker and more consistent towards the centre of the deposit (underlying the Horse Creek flow area), while thinning and splitting towards the margins. East-west and north-south sections show the A and B seams coalesced in the central part of the deposit and splitting to the east, west and south. The A seams sub-crop in the north and reach depths of greater than 70 m in the south. The lowest strip ratios are in a large zone in the central area of MLA where the merged A and B seams are thick and shallow. Although the A and B seam groups contain the main seams of economic interest, further down dip (to the south), the Y and then the UG seam groups occur above the A seams, and these seams also make a significant contribution to the low strip ratio coal inventory. In the northern part of MLA 50254, mining efforts will target the coal resources through to the C seam group. Page 13 of 27

14 Figure 6: Drill Hole Location Plan and Current Resource Limits Page 14 of 27

15 Figure 7: Elimatta Mining - Cross Sections at Locations shown in Figure 6 Page 15 of 27

16 Figure 8: Typical Elimatta Project Stratigraphy Page 16 of 27

17 MLA Taroom Coal has undertaken exploration activities within EPC This work comprised firstly undertaking a review of regional geological information available on public record from exploration carried out by previous tenure holders. This reporting described the area as having low potential for usable resources within the Juandah Coal Measures. As Taroom Coal was proposing to utilise the area of EPC 1171 for Elimatta project infrastructure and not for coal mining purposes, it carried out additional exploration in order to confirm the previous asessments and to be satisified that the infrastructure was not likely to steralise a coal resource opportunity. Taroom Coal has added eight exploration drill holes to the knowledge base see Figure 9 for locations. The coal seams identified are generally less than 1m thick as indicated by geophysical logging and have been correlated with those of the lower Juandah Coal Measures within EPC 650/MLA The seams in EPC 1171 are generally dominated by dull coal with occasional bright bands. Lithic seam partings are prevalent and comprised of siltstone, mudstone and reworked tuffaceous sediments. Theoretical strip ratios, assuming open pit mining of overburden and interburden are typically greater than 20. No seam intersected at the depths covered in the exploration less than 100 metres were considered suitable for underground extraction being too shallow and too thin. A typical graphic log is shown in Figure 10. Therefore, no coal resource has been delineated within ML MLA MLA is an application for transport and services, not for mining purposes. Any coal resource within the area of MLA is for the benefit of the Glencore Project proponents. Page 17 of 27

18 Figure 9: EPC 1171 Drill Hole Location Plan Page 18 of 27

19 Figure 10: EPC 1171 Typical Drill Hole Graphic Log 3. Standards and Procedures Used to Make the Estimate This section addresses section 318DT(1)(c)(ii) of the MR Act. The estimates of coal resources have been prepared in accordance with the guidelines of the Australian Code for Reporting of Exploration Results, Mineral resources and Ore Resources the 2004 JORC Code. A stratigraphic column of the modelled seams is given at Figure 8. The seam structure has been defined in terms of seam groups, parent seams and seam splits, as recorded in the drill hole logs. Modelling has been performed on a compound unit basis that is, seam groups, parent seams and their splits have all been modelled. Key parameters used for creating the geological model are given below: Schema name: ELI_1109 Topography surface: Topo_all_10m Interpolator: finite element method (fem) Extrapolation distance: 2000m Grid cell size: 50m The grid limits are (GDA94): Easting to Northing to Page 19 of 27

20 The geological database used to construct the geological model was contained within Mincom s GDB system. The geological model was built using Mincom s Minescape software. The integration between the two modules is considered an appropriate system for coal exploration data storage and coal deposit modelling. A rigorous review of the geological database was carried out in This review was part of a study on the feasibility of the Elimatta Project. The review included interrogation of interval depths, sample depths and sample validity. Coal seam correlation and structural review were also carried out. Following the 2010 review, the database was loaded into the Vulcan system for geological modelling. Prior to construction of the geological model, the Minescape database was validated against the exported Vulcan database to ensure they were aligned. The validation included coal seam assignment and correlation as well as sample boundaries. The comparison was generally acceptable, although some minor changes were made to interval and sample depths to better align the sampled intervals with the coal seam roof and floors. The geological database contained 361 drill holes. All drill hole collar locations have been recorded in GDA94. Most drill holes have been logged using geophysical techniques. This includes density, natural gamma, calliper and sonic velocity. The proximate analysis table contains 1,391 records for raw coal analysis. Of these records, 1,372 were deemed valid. The samples excluded were done so on the basis of invalid sampling techniques. A count of coal quality records for each parameter is as shown in Table 4. Table 4: Coal Quality Records Count by Parameter PARAMETER RAW Ash % (ad) 1372 Moisture % (ad) 1173 Volatile Matter % (ad) 1087 Fixed Carbon % (ad) 1092 Specific Energy (Mj/kg) 1096 Relative Density (g/cc) 1348 Structural Modelling Of the 361 drill holes contained in the geological database, 277 were used for constructing the structural model. The drill holes excluded were either not within the project area, contained unreliable data or were abandoned and redrilled with a new hole number. Drill hole statistics are illustrated in Table 5. Page 20 of 27

21 Table 5: Drill Hole Statistics INTERVAL NUMBER OF INTERSECTIONS AVERAGE THICKNESS MINIMUM THICKNESS (m) MAXIMUM THICKNESS (m) UG UG UG UG Y Y Y Y Y A A A A A B B B B BC BC BC C C C C C C C C LG LG LG LG LG LG Coal Quality Modelling A total of 112 drill holes contained valid coal quality data obtained from core samples. These holes were used to construct the coal quality model. Where values did not exist for some of the raw coal quality parameters, they were substituted using a number of methods. A new column was developed for each of the parameters that were substituted. The methods are given in Table 6. Page 21 of 27

22 Table 6: Substitution Methods and Equations PARAMETER METHOD REVISED COLUMN NAME Default moisture value of 8% (ad) where moisture was missing Moisture % and ash was <75% (ad) Default moisture value of 4% (ad) where moisture was missing PRIMDEF and ash was >75% RD g/cc (ad) Regression using inverse ash % (ad) RD (ad) = 1/( *Ash % (ad) ) PRRDDEF Volatile Matter % (ad) Specific Energy Mj/kg (ad) Fixed Carbon % (ad) Regression using raw ash % (db) *Ash% (db) Then adjusted back to air-dried basis Regression using raw ash % (db) *Ash% (db) Then adjusted back to air-dried basis Regression using raw ash % (db) * Ash% (db) Then adjusted back to air-dried basis PRVMDEF PRSEDEF PRFCDEF Mincom s GDB compositing tools were used to combine the sampled increments and apply the analysed coal quality parameters to the designated plies. Due to the nature of the coal measures concerned, coal sequences intersected in drill holes have not always been sampled at the ply boundaries. In most cases, sample increment boundaries were determined by lithological changes e.g. stone bands. Such lithological changes often mark the ply boundaries and in most cases plies have been sampled with respect to these boundaries. There are many instances where plies have been sampled in multiple increments; the compositing tool has weighted the parameters for the incremental samples against their thickness to produce a single value per parameter per ply. Where sampled sections extended outside the interval range, they were excluded from the coal quality model unless the lithology of the sampled interval was at minimum 50% coal. This allowed capture of points of observation where bulk sampling of a parent interval had occurred. This sampling methodology was considered appropriate in some of the earlier exploration programs that occurred prior to the development of the ply model. Plies were also rejected from the quality composite table if the total thickness of the samples applied was less than 95% of the ply thickness. The following coal quality parameters were composited and subsequently modelled: Ash % (ad) Moisture % (ad) Volatile Matter %(ad) Fixed Carbon % (ad) Relative Density g/cc (ad) Specific Energy Mj/kg (ad) Total Sulphur % (ad) Ash % (db) Volatile Matter % (db) Fixed Carbon % (db) Specific Energy Mj/Kg (db) Volatile Matter % (daf) Coal quality statistics, at air-dried basis, from the composited coal quality table are given at Table 7. Page 22 of 27

23 Table 7: Coal Quality Data SEAM No. of Samples Ash % (ad) Moisture % (ad) Volatile Matter % (ad) Fixed Carbon % (ad) RD g/cc (ad) Specific Energy mj/kg (ad) Total Sulphur % (ad) UG UG UG UG Y Y Y Y Y A A A A A B B B B BC BC BC C C C C C Rate and Amount of the Proposed Mining This section addresses section 318DT(1)(c)(iii) of the MR Act. A detailed mine production schedule was revised and updated in The mine design, waste volume, coal tonnage and coal quality are based on the geological model used to estimate the resource. The mine schedule was based on a 24 hour day / 7 days per week operation with a targeted production capacity of 5.0 Mt of product coal per annum for a period of up to 32 years. Table 8 gives key production statistics for the period of this Amended IDP (full production statistics are found in the Elimatta Project - Environmental Impact Statement 2014, published in May 2014). Page 23 of 27

24 Table 8: Key Production Statistics Amended IDP Year 1 Year 2 Year 3 Schedule Quantities Units Waste Mining M bcm Waste Mining Ex5500A M bcm Waste Mining Ex5500B M bcm Waste Mining Ex2500A M bcm Waste Mining Loader 994A M bcm ROM Coal Quantities Total ROM Tonnes (ROM moisture) Mt (ROM) Infrastructures and construction Infrastructure and construction continues - start mine activities Rom Ash (rom moisture) % Rom Ash (AD) %(ad) Closing ROM inventory Washed Product Mt (ROM) Washplant Yield (wet/wet) %(w/w) Washed Product tonnes Mt (prod) Other items Topsoil Area '000 m Reject Tonnage Mt (prod) Mining Schedule This section addresses section 318DT(1)(c)(vi)-(v) of the MR Act. 5.1 When the Proposed Mining is to Start Site clearing, establishment of drainage and then overburden removal is scheduled to commence from month 13 of the project construction schedule notionally in February 2018 on the basis of the MLs having been granted by January 2017 with general site preparation and construction activities commencing shortly thereafter. 5.2 Schedule for Proposed Mining during the Plan Period Refer to Table 8 above. Page 24 of 27

25 6. Reasons why the Plan is Considered Appropriate This section addresses section 318DT(1)(f) of the MR Act. The Project scope and objectives are to: Extract an open cut coal Resource of ~250 Mt at shallower than 100m below surface. At a production rate of up to 8.2 Mtpa ROM coal average 7.5 Mtpa for + 30 years (current assessment actual production duration will be dependent on coal prices for the product prevailing at the time of production). Establish and operate a conventional open cut mining operation using trucks and excavators. Construct and operate mine related infrastructure including workshop, offices and CHPP. Have product transported to Gladstone for export. The Project is considered by Taroom Coal to be viable given the following: Total Resource measured, Indicated and Inferred of 259 Mt (reported to JORC standard). Mining resource is suitable for low cost open pit extraction. Thermal Coal product is suitable for use in the power generating industry. As there is no infrastructure suitable for mine processing activities, heavy equipment maintenance, coal stockpiling, waste storage and rail transportation located within the area of or near to the MLA areas, Taroom Coal will be responsible for the construction of the full suite of infrastructure at the Project site, including the CHPP, stockpiling, administration and maintenance facilities and train loading at an estimated capital cost of some $400 - $500 million. Coal is one of Queensland s highest value exports and the coal industry provides significant value to the State by way of direct and indirect employment, purchase of goods and services and payment of taxes and royalties. The Project provides an opportunity to add to the contribution the industry makes to the State with its development in a region not currently directly benefiting from the continued growth of the coal and other resource sectors. The Project will also provide a benefit to the country on a national scale. This is achieved through increased foreign revenue from the export of coal and general economic stimulus through increased employment and the purchase of goods and services. Taroom Coal has identified a resource of +250 Mt within the Project area, of which up to 170 Mt can be economically extracted using today s evaluation standards by efficient open cut mining methods to generate 5.0 Mtpa product coal suitable for the international market for thermal coals. The project is anticipated to have a production life in excess of 30 years. The value of infrastructure construction is estimated to be $400 - $500 million (2013 dollars). Although many of the mining inputs will be imported into the regional economy, the workforce is expected to be recruited locally where available and/or provided as FIFO or DIDO/BIBO. As the project is now following on from the CSG industry construction boom, rather than competing with CSG for resources and labour a local workforce is expected to be available. It is expected that about $250 million of construction expenditures will be sourced from domestic suppliers and $ million will be spent on imports. The wage costs during construction are estimated to be $40-45 million, most of which will be Queensland based. Annual employee payroll in the operating phase is expected to be more than $36 million per year. Page 25 of 27

26 A range of operational expenditures will be sourced from Queensland based firms including rail services, port services, power and water supplies and plant maintenance. Full year expenditures on rail and port services are expected to exceed $125 million per annum. The Project will pay significant on-going revenue to the State Government through royalty and payroll tax obligations. Without the mine these payments will not be received. The annual royalty payment to the State resulting from sales of the product from mining operations, based on 5.0 Mtpa sales and a price of A$100 is in the order of $35 million. The Project will directly generate approximately up to 500 full time equivalent jobs during construction and 300 for early production to generate spending potential in the regional area where the workforce is located of approximately $18 million each year. The Project will have a positive impact on the economy of the region and the State through ongoing expenditures for materials and services, payment of rates, purchase of infrastructure, plant and consumables, use of service industries and payment of taxes. 7. How the effect on, and the interests of, any relevant overlapping or adjacent petroleum tenure holders have, or have not, been considered, having regard to the main purposes of this part and the CSG assessment criteria This section addresses section 318DV of the MR Act. Overlapping Petroleum Tenements: Taroom Coal and the Gas Party entered into a Co-Development Agreement in March 2015 which provides for the arrangements for each party to utilise the resource the subject of its production tenures (when granted) and which provides for a mechanism to make a Coordination Arrangement for consideration for acceptance by the Minister. Taroom Coal confirms that it has, in preparing this Amended IDP, had regard to the main purposes of part 7AA of the MR Act including the CSG assessment criteria. Taroom Coal has in preparing the Elimatta Project MLAs considered: the principal objectives of the MR Act in s 2; and the main purposes of Part 7AA of the MR Act in s 318A. For the reasons set out in the MLAs, including in this Amended IDP, the Elimatta Project MLAs are consistent with and promote the objectives of the MR Act and the main purposes of Part 7AA of the MR Act, particularly in respect of: the minimisation of land use conflicts (s 2(c)) as described in this application; ensuring an appropriate financial return to the State from mining (s 2(e), see part 15.1 Supporting Information to the MLAs and the CSG statement for the Project); addressing issues arising for coal seam gas mining under the MR Act (s 318A(b), see the CSG statement and material relating to the CSG assessment criteria in this application and comments above in this section); providing certainty of tenure for future investments relating to coal, oil shale and petroleum (s 318A(d), see the CSG statement and material relating to the CSG assessment criteria in this application and comments above in this section); optimising the development and use of the State s coal, oil shale and petroleum resources to maximise the benefit for all Queenslanders (s 318A(e), see the CSG statement and material relating to the CSG assessment criteria in the application and comments above in this section). Page 26 of 27

27 8. How the activities will seek to optimise the use of incidental coal seam gas in a safe and efficient way This section addresses section 318DW of the MR Act. Taroom Coal has conducted a test program to determine the likelihood of the availability of incidental coal seam gas occurring at the shallow depths that will be part of the open pit mine operation. Twenty core samples from four sites across the mine area (MLA 50254) were tested. Initial desorption measurements in the field were carried out using gas canisters and desorption apparatus. On completion of the field test component the samples were sent to a commercial laboratory where the fast method of gas content testing was used. Due to the low gas content encountered, generally <0.3m3/t, the test program was modified to increase the precision of the measurements and to provide a more accurate assessment of the gas content and composition. Infrastructure construction on MLA and are anticipated to require excavations no deeper than 15 metres at most and to not intersect coal seams. No gas release is anticipated as a result of the mining (construction) activities on these tenures. Therefore, Taroom Coal anticipates that its open pit mining activities will not access commercial quantities of incidental coal seam gas. Page 27 of 27

TAROOM COAL PROPRIETARY LIMITED (ABN ) ELIMATTA PROJECT UPDATE TO THE PROJECT APPLICATIONS SUPPORTING INFORMATION.

TAROOM COAL PROPRIETARY LIMITED (ABN ) ELIMATTA PROJECT UPDATE TO THE PROJECT APPLICATIONS SUPPORTING INFORMATION. TAROOM COAL PTY LTD ABN: 16 079 251 442 TAROOM COAL PROPRIETARY LIMITED (ABN 16 079 251 442) ELIMATTA PROJECT UPDATE TO THE PROJECT APPLICATIONS SUPPORTING INFORMATION September 2015 1.0 INTRODUCTION 1.1

More information

TAROOM COAL PROPRIETARY LIMITED ELIMATTA PROJECT - MINING LEASE APPLICATION. Section 15 - Accompaniments 1.0 INTRODUCTION.

TAROOM COAL PROPRIETARY LIMITED ELIMATTA PROJECT - MINING LEASE APPLICATION. Section 15 - Accompaniments 1.0 INTRODUCTION. 28 May, 2009 TAROOM COAL PROPRIETARY LIMITED ELIMATTA PROJECT - MINING LEASE APPLICATION Section 15 - Accompaniments 1.0 INTRODUCTION 1.1 PROJECT OVERVIEW This Mining Lease Application (MLA) is made over

More information

PREFEASIBILITY STUDY COMPLETED FOR MMAMABULA WEST

PREFEASIBILITY STUDY COMPLETED FOR MMAMABULA WEST For electronic distribution 12 th May 2014 Highlights PREFEASIBILITY STUDY COMPLETED FOR MMAMABULA WEST A Prefeasibility Study for an underground coal mine based on a 200Mt portion of the A Seam within

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 30th September, 2014 ABM s Development Plan & Production Guidance for Old Pirate High-Grade Gold Deposit Highlights: 50,000 to 60,000 ounces of gold production

More information

QUARTERLY REPORT March 2011

QUARTERLY REPORT March 2011 QUARTERLY REPORT March 2011 Australian energy company, Blackham Resources Ltd (Blackham) ( ASX: BLK ) continues to advance the development of the Scaddan and Zanthus Coal to Liquids ( CTL ) projects. The

More information

For personal use only

For personal use only 24 August 2015 PROPOSED COAL SEAM ACCESS AT BUCK CREEK NO.2 MINE CONFIRMS LOW CAPITAL COST HIGHLIGHTS: Shallow depth of coal seam (100 to 125 feet / 30 to 38 metres) at proposed Buck Creek No. 2 Mine allows

More information

Estimating and Reporting of

Estimating and Reporting of AUSTRALIAN GUIDELINES FOR Estimating and Reporting of Inventory Coal, Coal Resources and Coal Reserves 2003 EDITION PREPARED BY THE COALFIELDS GEOLOGY COUNCIL OF NEW SOUTH WALES AND THE QUEENSLAND MINING

More information

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum ASX ANNOUNCEMENT 29 March 2010 Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum PanAust is pleased to announce that the Board of Directors

More information

MAIDEN RESOURCE STATEMENT FOR TCM COAL PROJECT, INDONESIA

MAIDEN RESOURCE STATEMENT FOR TCM COAL PROJECT, INDONESIA 311 313 Hay Street SUBIACO WA 6008 P: + 61 8 9381 5819 F: + 61 8 9388 3701 ABN: 45 098 448 269 www.panasiacorp.com.au 11 May 2010 The Manager Company Announcements Platform Australian Securities Exchange

More information

5 th Asian Bauxite & Alumina Conference

5 th Asian Bauxite & Alumina Conference 5 th Asian Bauxite & Alumina Conference October 2015 Bauxite Hills Project Deliberate Focus ASX : MMI CORPORATE SNAPSHOT Shareholders 0.140 0.120 MMI Share Price (A$) Other 47% NetWealth Investments 5%

More information

ASX RELEASE BY METROCOAL LIMITED (ASX-MTE) $30 MILLION JOINT VENTURE SIGNED WITH CHINA COAL

ASX RELEASE BY METROCOAL LIMITED (ASX-MTE) $30 MILLION JOINT VENTURE SIGNED WITH CHINA COAL ASX ANNOUNCEMENT Thursday 8 April 2010 ASX RELEASE BY METROCOAL LIMITED (ASX-MTE) $30 MILLION JOINT VENTURE SIGNED WITH CHINA COAL Metallica Minerals Limited (ASX-MLM) advises that it s 56% owned subsidiary,

More information

DRILLING INTERSECTS SIGNIFICANT COAL SEAMS AT TCM COAL PROJECT, KALIMANTAN, INDONESIA

DRILLING INTERSECTS SIGNIFICANT COAL SEAMS AT TCM COAL PROJECT, KALIMANTAN, INDONESIA 311 313 Hay Street SUBIACO WA 6008 P: + 61 8 9381 5819 F: + 61 8 9388 3701 ABN: 45 098 448 269 www.panasiacorp.com.au 1 February 2010 The Manager Company Announcements Platform Australian Securities Exchange

More information

Postal Address: PO Box Brisbane Adelaide Street QLD 4000

Postal Address: PO Box Brisbane Adelaide Street QLD 4000 1.0 INTRODUCTION 1.1 PROJECT PROPONENT The proponent for the Elimatta Project (the Project) is Taroom Coal Proprietary Limited (Taroom Coal) which is a wholly owned subsidiary of Northern Energy Corporation

More information

Arrow Energy. Surat operational update. July 2016

Arrow Energy. Surat operational update. July 2016 Surat operational July 2016 Why we are here today Provide an to the community on Arrow s operational activities over the past 24 months Approval stages for the Surat Gas Project Upcoming survey activities

More information

For personal use only

For personal use only TALGA RESOURCES Talga Resources Ltd ABN 32 138 405 419 1st Floor, 2 Richardson St, West Perth, WA 6005 T: +61 8 9481 6667 F: +61 8 9322 1935 www.talgaresources.com Corporate Information ASX Code TLG Shares

More information

Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements

Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements 1 Development Potential of the Wara Coal Deposit to meet Indonesia s Future Power Requirements 2 COAL RESOURCE Indonesia has large resources of lower heating value subbituminous coal the resources are

More information

COAL RESOURCES INCREASE TO 79Mt AT KATINGAN RIA, INDONESIA

COAL RESOURCES INCREASE TO 79Mt AT KATINGAN RIA, INDONESIA ASX/Media Release 18 January 2012 COAL RESOURCES INCREASE TO 79Mt AT KATINGAN RIA, INDONESIA Highlights Phase 2 drilling work commenced and will continue through to mid February Inferred Resources estimate

More information

2.0 Description of Existing Mine Operations

2.0 Description of Existing Mine Operations 2.0 2.1 Mine History Austar Coal Mine is an amalgamation of several older mines and operates within a number of mining leases under 12 separate development consents issued by Cessnock City Council between

More information

For personal use only

For personal use only NEW HOPE CORPORATION LIMITED ABN: 38 010 653 844 QUARTERLY ACTIVITIES REPORT 30 APRIL 2016 30 May 2016 Quarter Ended 9 Months Ended Apr 16 Apr 15 Change (%) Apr 16 Apr 15 Change (%) Raw Coal Production

More information

Windimurra Vanadium Plant Project Update. Investor Presentation August 2011

Windimurra Vanadium Plant Project Update. Investor Presentation August 2011 Windimurra Vanadium Plant Project Update Investor Presentation August 2011 Disclaimer The material in this presentation ( material ) is not and does not constitute an offer, invitation or recommendation

More information

For personal use only

For personal use only ASX Code: MRP MacPhersons Resources Ltd ABN 98 139 357 967 ACN 139 357 967 Contact Details PO Box 10977 109 Maritana Street Kalgoorlie WA 6430 T +61 (0) 8 9091 7515 F +61 (0) 8 9091 7610 E info@mrpresources.com.au

More information

BUILDING AN EMERGING RESOURCE COMPANY UPDATE ON ACQUISITION OF COAL AND MANGANESE ASSETS IN INDONESIA

BUILDING AN EMERGING RESOURCE COMPANY UPDATE ON ACQUISITION OF COAL AND MANGANESE ASSETS IN INDONESIA 16 December 2009 The Manager Company Announcements Platform Australian Securities Exchange Exchange Plaza, 2 The Esplanade PERTH WA 6000 311 313 Hay Street SUBIACO WA 6008 P: + 61 8 9381 5819 F: + 61 8

More information

June 2009 quarterly report

June 2009 quarterly report June 2009 quarterly report HIGHLIGHTS Canning Basin Coal Projects, WA Resource at Duchess-Paradise upgraded to over 500Mt thermal coal Pre feasibility study on coal export project underway Myroodah Underground

More information

Activities Report Quarter Ended 31 st March 2015

Activities Report Quarter Ended 31 st March 2015 ASX & Media Release ASX Code AZM 30 th April 2015 www.azumahresources.com.au Investment Highlights: Wa Project: 2.0Moz Mineral Resource including 1.3Moz Measured & Indicated 624,000oz Ore Reserves at 2.14

More information

DEVELOPMENT CONSENT MODIFICATION Statement of Environmental Effects

DEVELOPMENT CONSENT MODIFICATION Statement of Environmental Effects BENGALLA MINE DEVELOPMENT CONSENT MODIFICATION for Bengalla Mining Company Pty Limited August 2015 BENGALLA MINE DEVELOPMENT CONSENT MODIFICATION STATEMENT OF ENVIRONMENTAL EFFECTS Prepared by: HANSEN

More information

2. Project Justification and Feasible Alternatives

2. Project Justification and Feasible Alternatives 2. Project Justification and Feasible Alternatives 2.1 Project Justification Energy intensive industries associated with the coal and gas sectors in the Surat region continue to drive electricity demand

More information

Industrial land demand forecasting for supply chain business supporting Queensland s resources sector

Industrial land demand forecasting for supply chain business supporting Queensland s resources sector Industrial land demand forecasting for supply chain business supporting Queensland s resources sector Queensland is the focus of major developments in the resources sector, creating huge potential for

More information

Mining Update - Mongolia

Mining Update - Mongolia Suite C1, 1 Honeysuckle Drive, The Boardwalk Newcastle NSW 2300 PO Box 509, Newcastle NSW 2300 Telephone: 02 4914 5910 Facsimile: 02 4925 3505 www.guildfordcoal.com.au 15 October 2012 Company Announcements

More information

GUIDELINES to the MINING ACT

GUIDELINES to the MINING ACT GUIDELINES to the MINING ACT PART I Format Requirements Reports 1. All reports required to be submitted to the minister by the Mining Act or regulations shall (a) be bound in a folder; (b) be a typewritten

More information

For personal use only

For personal use only 1 SCOPING STUDY CONFIRMS PROFITABLE POTENTIAL OF HASTINGS HEAVY RARE EARTH PROJECT The Manager Company Announcements Office Australian Securities Exchange 4th Floor, 20 Bridge Street SYDNEY NSW 2000 Hastings

More information

For personal use only

For personal use only 4 APRIL 2013 D Zone Mineral Resource Increases by 34% to 20.7 million tonnes with a significant increase in contained Cu and Fe Highlights Overall D Zone Mineral Resource tonnage has increased by 5.2 million

More information

For personal use only

For personal use only ASX Announcement 25 February 2016 Mulga Rock Project Definitive Feasibility Study Update Vimy Resources Limited ( Vimy ASX: VMY) is pleased to provide the following operational update on the Mulga Rock

More information

MINERAL RESOURCES LIMITED

MINERAL RESOURCES LIMITED MINERAL RESOURCES LIMITED QUARTERLY EXPLORATION AND MINING ACTIVITIES REPORT OCTOBER TO DECEMBER Q2 FY2017 MINERAL RESOURCES LIMITED QUARTERLY EXPLORATION AND MINING ACTIVITIES REPORT OCTOBER TO DECEMBER,

More information

EXCO S PROJECT PIPELINE

EXCO S PROJECT PIPELINE EXCO S PROJECT PIPELINE INVESTOR UPDATE EXCO RESOURCES N.L. MAY 2010 Presented by Michael Anderson Managing Director DISCLAIMER This presentation contains forward looking statements that are subject to

More information

CARBON ENERGY. Surat Basin Coal & Energy Conference 23 MAY 2012

CARBON ENERGY. Surat Basin Coal & Energy Conference 23 MAY 2012 CARBON ENERGY Surat Basin Coal & Energy Conference 23 MAY 2012 IMPORTANT STATEMENTS Disclaimer The information contained in this presentation is given without any liability whatsoever to Carbon Energy

More information

For personal use only

For personal use only ` 28 September 2011 ASX ANNOUNCEMENT CAZALY RESOURCES LIMITED COMPANY PRESENTATION Mr Clive Jones joint Managing Director of Cazaly Resources Limited (ASX: CAZ) ( Cazaly ) will be presenting the attached

More information

ASX ANNOUNCEMENT. Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA. Mt Stuart Joint Venture MAIDEN ORE RESERVE STATEMENT

ASX ANNOUNCEMENT. Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA. Mt Stuart Joint Venture MAIDEN ORE RESERVE STATEMENT ABN 46 006 045 790 14 th December 2010 ASX ANNOUNCEMENT Maiden Reserve for Catho Well Channel Iron Deposit, West Pilbara WA Cullen Resources Limited (ASX:CUL) (Cullen) is pleased to report the maiden JORC

More information

QUARTERLY ACTIVITIES REPORT 30 APRIL 2015

QUARTERLY ACTIVITIES REPORT 30 APRIL 2015 NEW HOPE CORPORATION LIMITED ABN: 38 010 653 844 QUARTERLY ACTIVITIES REPORT 30 APRIL 2015 28 May 2015 Quarter Ended 9 Months Ended Apr 15 Apr 14 Change (%) Apr 15 Apr 14 Change (%) Raw Coal Production

More information

metallurgical coal Anglo American plc Fact Book 2011/12 37 Metallurgical Coal

metallurgical coal Anglo American plc Fact Book 2011/12 37 Metallurgical Coal metallurgical coal is the second biggest n metallurgical coal producer and the No. 3 global exporter of metallurgical coal. Anglo American is an active partner in diverse clean coal energy initiatives.

More information

REGUIBAT URANIUM PROJECT SCOPING STUDY COMPLETE

REGUIBAT URANIUM PROJECT SCOPING STUDY COMPLETE 16 July 2014 REGUIBAT URANIUM PROJECT SCOPING STUDY COMPLETE STUDY HIGHLIGHTS STRONGLY POSITIVE ECONOMICS LOW CAPEX, LOW OPEX PROJECT PRODUCING UP TO 1 MLBS PER ANNUM PROJECT PRODUCES OVER A$350 MILLION

More information

Atlantic Ltd (ASX: ATI; Atlantic or the Company) is pleased to present its report for the quarter ended 30 June 2011.

Atlantic Ltd (ASX: ATI; Atlantic or the Company) is pleased to present its report for the quarter ended 30 June 2011. 1 2 QUARTERLY REPORT Atlantic Ltd (ASX: ATI; Atlantic or the Company) is pleased to present its report for the quarter ended 30 June 2011. HIGHLIGHTS Windimurra vanadium project remains on track for first

More information

Carbon Energy Presentation Surat Basin Coal & Energy Conference

Carbon Energy Presentation Surat Basin Coal & Energy Conference ASX/Media Announcement 23 May 2012 Level 12, 301 Coronation Drive, Milton QLD 4064 Australia PO Box 2118, Toowong DC QLD 4066 Australia phone + 61 (0) 7 3337 9944 fax + 61 (0) 7 3337 9945 www.carbonenergy.com.au

More information

For personal use only

For personal use only Arrium Mining Quarterly Production Report For the quarter ended 30 June 2015 Summary Sales and shipments 2.85Mt (dmt) and 2.74Mt (dmt) respectively Average Platts market index price (62% Fe CFR) US$58/dmt,

More information

Consultation Regulatory Impact Statement

Consultation Regulatory Impact Statement Consultation Regulatory Impact Statement Post Implementation Review of the Industry Levy to fund the petroleum and gas water functions of the Office of Groundwater Impact Assessment December 2016 This

More information

A1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871

A1 Australian and South Australian Government Guidelines 813. A2 South Australian Government Guidelines 871 Appendix A EIS Guidelines CONTENTS A1 Australian and South Australian Government Guidelines 813 A2 South Australian Government Guidelines 871 A3 Northern Territory Government Guidelines 929 Olympic Dam

More information

For personal use only

For personal use only T +61 7 3001 4100 E info@cokal.com.au Level 34 Riverside Centre, 123 Eagle Street Brisbane QLD 4000 PO Box 7122, Brisbane QLD 4001 ABN 55 082 541 437 (ASX: CKA) www.cokal.com.au 30 January 2015 QUARTERLY

More information

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002

(18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002 (18 April 2011 to date) MINERAL AND PETROLEUM RESOURCES DEVELOPMENT ACT 28 OF 2002 (Gazette No. 23922, Notice No. 1273 dated 10 October 2002. Commencement date: 1 May 2004 [Proc. No. R25, Gazette No. 26264])

More information

Environmental Monitoring Results Summary

Environmental Monitoring Results Summary Environmental Monitoring Results Summary Quarter 1 2016 Name of Mine: CSA Mine Environment Protection Licence: EPL 1864 Licensee Name and Operator: Cobar Management Pty Ltd Licensee Address: PO Box 31,

More information

Cristal Australia Pty Ltd

Cristal Australia Pty Ltd ENERGY EFFICIENCY OPPORTUNITIES PUBLIC REPORT 2013 Cristal Australia Pty Ltd is a wholly owned subsidiary of The National Titanium Dioxide Company Limited (Cristal), a private company with headquarters

More information

Open Cut Coal Solutions

Open Cut Coal Solutions Open Cut Coal Solutions INTEGRATED MINE PLANNING TOOLS FOR OPEN CUT COAL OPERATIONS Strong technical solutions tailored to specialized industry needs Deswik has developed a fresh and innovative range of

More information

For personal use only

For personal use only 13 APRIL 2018 AUTHIER PROJECT PRESENTATION TO KEY STAKEHOLDERS & PERMITTING UPDATE Sayona Mining Limited (ASX: SYA) ("Sayona" or the "Company") is pleased to announce that the Company held information

More information

Pit to Port Infrastructure in SA

Pit to Port Infrastructure in SA Pit to Port Infrastructure in SA An Explorer s Perspective Dr A. John Parker Managing Director SA Mining and Energy Infrastructure Conference 2011 12-13 April 2011 Disclaimer & Competent Person s Statement

More information

NEWS RELEASE. Post Tax NPV 10%) Post Tax IRR (100% equity) 17.6% Probable Reserves Project Life (based on Probable Reserves)

NEWS RELEASE. Post Tax NPV 10%) Post Tax IRR (100% equity) 17.6% Probable Reserves Project Life (based on Probable Reserves) June 18, 2015 NEWS RELEASE Symbol: TSX-V: FBX FWB/BER: FBI FIRST BAUXITE CORPORATION ANNOUNCES PROPPANT FEASIBILITY STUDY RESULTS Toronto, ON - First Bauxite Corporation ( First Bauxite or the Company

More information

209 million 36.1% Fe

209 million 36.1% Fe ASX ANNOUNCEMENT 29 August 2011 ASX Code: BDR MAIDEN IRON ORE RESOURCE ON BEADELL S MINING CONCESSION - BRAZIL 209 million tonnes @ 36.1 Fe Beadell Resources Limited ( Beadell ) is pleased to announce

More information

Gum Creek Gold Project Free Milling Scoping Study

Gum Creek Gold Project Free Milling Scoping Study 18 March 2016 ASX: PAN Highlights Gum Creek Gold Project Free Milling Scoping Study Mining Inventory of 4.9Mt at 1.94g/t Au for 309koz gold based on material from Swan, Swift and Howards Resources Average

More information

Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations

Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 2014 Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations Daniel

More information

ABM Hits 3000 Ounce Target from Trial Mining

ABM Hits 3000 Ounce Target from Trial Mining ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 12 th December 2013 ABM Hits 3000 Ounce Target from Trial Mining ABM Resources NL ( ABM or The Company ) presents an update on the Trial Mining and Processing at

More information

Environmental Assessment Chapter 8 Surface Water

Environmental Assessment Chapter 8 Surface Water Environmental Assessment Chapter 8 Surface Water 8.2.7 Rainfall and Evaporation Based on recorded data for the area of interest, the mean annual rainfall is about 700mm, with maximum monthly rainfalls

More information

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves LA ARENA GOLD OXIDE RESERVES INCREASED TO 1.28MM OZ AT AU PRICE OF $1,200 COMPLETION OF THE PRE-FEASIBILITY STUDY FOR THE PHASE II SULPHIDE Cu-Au PROJECT Drilling, metallurgical test work and a new resource

More information

TABLE OF CONTENTS LIST OF FIGURES. Mt Arthur Coal Open Cut Modification Environmental Assessment

TABLE OF CONTENTS LIST OF FIGURES. Mt Arthur Coal Open Cut Modification Environmental Assessment Executive Summary TABLE OF CONTENTS ES1 BACKGROUND ES-1 ES2 EXISTING OPERATIONS ES-1 ES3 MODIFICATION OVERVIEW ES-1 ES4 CONSULTATION ES-1 ES5 COMMUNITY INITIATIVES AND INVOLVEMENT ES-3 ES6 ENVIRONMENTAL

More information

For personal use only

For personal use only ACN 097 088 689 01 DEFINITIVE FEASIBILITY STUDY SUPPORTS A MAJOR EXPANSION OF THE SYAMA GOLD MINE Definitive Feasibility Study completed for multifaceted expansion of Syama operation confirms its technical

More information

Georgian Mining Corporation / EPIC: GEO / Sector: Natural Resources

Georgian Mining Corporation / EPIC: GEO / Sector: Natural Resources 24 October 2017 Georgian Mining Corporation / EPIC: GEO / Sector: Natural Resources Georgian Mining Corporation Drilling Update from KB Gold Zone 2 and New Gold Discovery Georgian Mining Corporation (

More information

For personal use only

For personal use only 9 August 2012 PRAIRIE DOWNS SECURES A LARGE COAL PROJECT IN POLAND Prairie Downs Metals Limited ( Prairie or Company ) is pleased to advise that the Company has secured a highly prospective and potentially

More information

MCINTOSH STAGE 1 PRE-FEASIBILITY STUDY UPDATE

MCINTOSH STAGE 1 PRE-FEASIBILITY STUDY UPDATE ASX ANNOUNCEMENT 8 June 2016 MCINTOSH STAGE 1 PRE-FEASIBILITY STUDY UPDATE Open pit mining optimisation results demonstrate the potential for multiple low strip ratio, open pit operations across a range

More information

Developing mining options at the Sese coal project in Botswana

Developing mining options at the Sese coal project in Botswana Developing mining options at the Sese coal project in Botswana Results from the Concept Study, September 2011 Disclaimer This presentation has been prepared by and issued by African Energy Resources Limited

More information

Section 2 Proposal Description

Section 2 Proposal Description Section 2 Proposal Description 2. PROPOSAL DESCRIPTION 2.1 Overview The Proposal comprises the construction, operation and closure of mining at the J5 and Bungalbin East iron ore deposits and associated

More information

ASX Release ASX Code: YTC

ASX Release ASX Code: YTC HERA DEFINITIVE FEASIBILITY STUDY TO BE EXPANDED Hera DFS scope to be expanded to include the assessment of mining and treatment of high grade copper ores from the Nymagee Copper Mine together with additional

More information

Nullagine Gold Project Life of Mine Update

Nullagine Gold Project Life of Mine Update 19 March 2014 Manager Company Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 ABN 85 003 257 556 Dear Sir/Madam Via Electronic

More information

Arrow Energy. Surat development update. December 2017

Arrow Energy. Surat development update. December 2017 Surat development update December 2017 Why we are here today Arrow has agreed one of the largest gas supply deals on Australia s east coast: - 27-year deal between Arrow and QCLNG to commercialise the

More information

Grange Resources Australia s leading magnetite producer

Grange Resources Australia s leading magnetite producer Grange Resources Australia s leading magnetite producer Grange Resources Limited (GRR) Level 11, 200 St Georges Terrace Perth, WA 6000, Australia Phone + 61 8 9321 1118 Fax + 61 8 9321 1523 www.grangeresources.com.au

More information

Updated JORC Statement of Coal Resources and Reserves for PT Katingan Ria Thermal Coal Project, Indonesia

Updated JORC Statement of Coal Resources and Reserves for PT Katingan Ria Thermal Coal Project, Indonesia Company Announcements ASX Limited By Electronic Lodgement 9 May 2017 Updated JORC Statement of Coal Resources and Reserves for PT Katingan Ria Thermal Coal Project, Indonesia Highlights Coal Resources

More information

Maiden Inferred Iron Ore Resources for Gum Flat

Maiden Inferred Iron Ore Resources for Gum Flat 30 April 2009 The Manager ASX Announcements Maiden Inferred Iron Ore s for Gum Flat Lincoln Minerals Limited ( LML ) is pleased to announce Inferred s for its Gum Flat Iron Ore Project on southern Eyre

More information

Grange Resources. Diggers & Dealers 4 August Russell Clark Managing Director & CEO

Grange Resources. Diggers & Dealers 4 August Russell Clark Managing Director & CEO Grange Resources Australia s leading magnetite producer Grange Resources Limited (GRR) Level 11, 200 St Georges Terrace Perth, WA 6000, Australia Phone + 61 8 9321 1118 Fax + 61 8 9321 1523 www.grangeresources.com.au

More information

Community Information Session Surat Basin

Community Information Session Surat Basin Community Consultation June 2010 Community Information Session Surat Basin May 2011 1 INTRODUCTION OF PRESENTERS Tony Knight, Vice President, Exploration St John Herbert, Groundwater Modelling Coordinator

More information

For personal use only

For personal use only 25 May 2012 AMENDED PERKOA JOINT VENTURE PROJECT MINERAL RESOURCE UPGRADE Please find attached an amended version of the Perkoa Joint Venture Project Mineral Resource Upgrade announcement released yesterday.

More information

PATRICK SCOTT - DIRECTOR TIN CONFERENCE BEER & CO - SECOND ANNUAL WEDNESDAY, 5 NOVEMBER, 2014

PATRICK SCOTT - DIRECTOR TIN CONFERENCE BEER & CO - SECOND ANNUAL WEDNESDAY, 5 NOVEMBER, 2014 BEER & CO - SECOND ANNUAL TIN CONFERENCE WEDNESDAY, 5 NOVEMBER, 2014 PATRICK SCOTT - DIRECTOR SCOTT@AUSTRALIA.ROHSTOFF.DE Disclaimer This presentation has been prepared by and issued by Tin International

More information

WAMBO COAL MINE MINING OPERATIONS PLAN

WAMBO COAL MINE MINING OPERATIONS PLAN WAMBO COAL MINE MINING OPERATIONS PLAN 2015 2020 PREPARED BY WAMBO COAL PTY LTD May 2017 MOP Amendment F Wambo Coal Mine Mining Plan Wambo Coal Pty Limited Mining Plan Name of Mine: Wambo Coal Pty Ltd

More information

SECTION 1 SAMPLING TECHNIQUES AND DATA

SECTION 1 SAMPLING TECHNIQUES AND DATA Silvergrass East Table 1 The following table provides a summary of important assessment and reporting criteria used at Silvergrass East for the reporting of Mineral Resources and Ore Reserves in accordance

More information

AGM - Lorena Gold Project

AGM - Lorena Gold Project AGM - Lorena Gold Project For personal use onlynovember 2015 Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk factors

More information

GUIDELINES FOR THE INTEGRATED PLANNING AND DESIGN OF UNDERGROUND COAL MINES. Prof. G A Fourie Mr D J van Niekerk

GUIDELINES FOR THE INTEGRATED PLANNING AND DESIGN OF UNDERGROUND COAL MINES. Prof. G A Fourie Mr D J van Niekerk GUIDELINES FOR THE INTEGRATED PLANNING AND DESIGN OF UNDERGROUND COAL MINES Prof. G A Fourie Mr D J van Niekerk Project No : COL 814 Date : November 2001 i) Foreword Mine planning and design involves the

More information

RESOURCE GOLD PTY. LTD.

RESOURCE GOLD PTY. LTD. Copyright RESOURCE GOLD PTY. LTD. Gold Recovery From Processing Of - Mill Site Materials - Alluvial Gold Deposits - Hard Rock Resources NOVEMBER, 2009 REVISION 3 1 Disclaimer! This presentation contains

More information

EXCO S PROJECT PIPELINE. Unlocking the Value

EXCO S PROJECT PIPELINE. Unlocking the Value EXCO S PROJECT PIPELINE Unlocking the Value EXCO RESOURCES N.L. 20 AUGUST 2010 Wholesale Investors Forum Presented by Michael Anderson Managing Director DISCLAIMER This presentation contains forward looking

More information

IMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION. Marc Johnson, Regional Manager - South America

IMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION. Marc Johnson, Regional Manager - South America IMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION Marc Johnson, Regional Manager - South America Abstract In Pit Crushing and Conveying (IPCC) systems have matured as a technology to the

More information

Estimation of Open Cut Mining Recovery and Mining Dilution. Summary. Introduction. Estimation Techniques. AusIMM JORC Code Edition.

Estimation of Open Cut Mining Recovery and Mining Dilution. Summary. Introduction. Estimation Techniques. AusIMM JORC Code Edition. Estimation of Open Cut Mining Recovery and Mining Dilution By Kent Bannister, ARMIT, FAusIMM (CP), CEO Kent Bannister Pty Ltd, (KBPL) Summary Loss and dilution of Mineral Resource grade occurs during mining

More information

WPG TO ENTER THE IRON ORE INDUSTRY

WPG TO ENTER THE IRON ORE INDUSTRY Western Plains Gold Ltd ABN 51 109 426 502 PO Box N239, Grosvenor Place NSW 1220, Australia Level 11, Kyle House, 27-31 Macquarie Place, Sydney, NSW Australia Telephone (+612) 9251 1044 Facsimile (+612)

More information

Bengalla Mining Company Pty Limited. Particulate Matter Control Best Practice Implementation Monitoring Programs

Bengalla Mining Company Pty Limited. Particulate Matter Control Best Practice Implementation Monitoring Programs Bengalla Mining Company Pty Limited Particulate Matter Control Best Practice Implementation Monitoring Programs U3. Wheel Generated Dust U4. Disturbing and Handling Overburden Under Adverse Weather Conditions

More information

For personal use only

For personal use only 27 April 2017 ASX Announcement March 2017 Quarterly Activities Report Summary Chelkar - Assay High Grade Potash Mineralisation Present Bankable Feasibility Study Advances for Satimola Project JV with Chongqing

More information

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY 10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3

More information

Coal Seam Gas Water Management

Coal Seam Gas Water Management Coal Seam Gas Water Management Response to 2012 Draft Policy 30 November 2012 AgForce Queensland Industrial Union of Employers ABN 21 241 679 171 First Floor, 183 North Quay, Brisbane, Qld, 4000 PO Box

More information

Advice to decision maker on coal mining project

Advice to decision maker on coal mining project . Advice to decision maker on coal mining project IESC 2015-063: West Muswellbrook Project New Development Requesting agency The New South Wales Mining and Petroleum Gateway Panel Date of request 27 January

More information

DEVELOPING A WORLD-CLASS VANADIUM-TITANIUM-IRON PROJECT MOUNT PEAKE, NORTHERN TERRITORY. INFORMATION MEMOR ANDUM

DEVELOPING A WORLD-CLASS VANADIUM-TITANIUM-IRON PROJECT MOUNT PEAKE, NORTHERN TERRITORY.  INFORMATION MEMOR ANDUM DEVELOPING A WORLD-CLASS VANADIUM-TITANIUM-IRON PROJECT MOUNT PEAKE, NORTHERN TERRITORY www.tngltd.com.au INFORMATION MEMOR ANDUM 2 MOUNT PEAKE: A WORLD-CLASS VANADIUM-TITANIUM-IRON DEPOSIT The Mount Peake

More information

For personal use only

For personal use only 19 October 2015 PARINGA CONTRACTS FUTURE COAL SALES TOTALING US$220 MILLION WITH A MAJOR UTILITY HIGHLIGHTS: Paringa has executed its cornerstone coal sales agreement with LG&E and KU, two of the largest

More information

Australian Tailings Group Pty Ltd Synergy (SNR) Investor Presentation

Australian Tailings Group Pty Ltd Synergy (SNR) Investor Presentation Australian Tailings Group Pty Ltd Synergy (SNR) Investor Presentation Disclaimer Forward-Looking Statements This presentation contains forward looking statements concerning the projects owned by Australian

More information

North River Resources plc / Ticker: NRRP / Index: AIM / Sector: Mining 30 June 2014 North River Resources plc ( North River or the Company )

North River Resources plc / Ticker: NRRP / Index: AIM / Sector: Mining 30 June 2014 North River Resources plc ( North River or the Company ) North River Resources plc / Ticker: NRRP / Index: AIM / Sector: Mining 30 June 2014 North River Resources plc ( North River or the Company ) Namib Project - Mine Development Plan North River is pleased

More information

GLADSTONE LNG leads the way with its first LNG shipment in 2012

GLADSTONE LNG leads the way with its first LNG shipment in 2012 GLADSTONE LNG leads the way with its first LNG shipment in 2012 LNG Business Model Development of mid-scale LNG projects of up to 1.5 million tonne per annum (Mtpa) production capacity per LNG train, based

More information

For personal use only

For personal use only ABN 28 009 174 761 www.regisresources.com Level 1 1 Alvan Street Subiaco WA 6008 Australia P 08 9442 2200 F 08 9442 2290 20 February 2013 Manager Announcements Company Announcements Office Australian Securities

More information

For personal use only

For personal use only ASX ASX ANNOUNCEMENT ANNOUNCEMENT th 15 15th January January 2018 2018 For personal use only PACIFIC BAUXITE ACQUIRES NEW BAUXITE PROJECT IN WESTERN AUSTRALIA HIGHLIGHTS Pacific Bauxite has acquired the

More information

Strong open pit drilling results boost plan to grow Paulsens' production to 100,000ozpa

Strong open pit drilling results boost plan to grow Paulsens' production to 100,000ozpa ASX ANNOUNCEMENT 21 DECEMBER 2011 Australian Securities Exchange Code: NST Strong open pit drilling results boost plan to grow Paulsens' production to 100,000ozpa Highlights High-grade results of up to

More information

Mining in a Day Seminar Balikpapan. 2 nd September 2015

Mining in a Day Seminar Balikpapan. 2 nd September 2015 Mining in a Day Seminar Balikpapan 2 nd September 2015 Exploration Test Program Design Page 2 Exploration Test Program Design Factors to be considered when designing test program Existing databases. Little

More information