COST TRENDS OF MBR SYSTEMS FOR MUNICIPAL WASTEWATER TREATMENT

Size: px
Start display at page:

Download "COST TRENDS OF MBR SYSTEMS FOR MUNICIPAL WASTEWATER TREATMENT"

Transcription

1 COST TRENDS OF MBR SYSTEMS FOR MUNICIPAL WASTEWATER TREATMENT James DeCarolis*, Samer Adham **, William R. Pearce***, Zakir Hirani**, Stephen Lacy**, Roger Stephenson** *MWH Americas, Inc Farnham Street, Suite 300 San Diego, CA **MWH Americas, Inc. ***City of San Diego ABSTRACT Cost estimates were developed for full-scale (1 and 5 MGD) MBR facilities designed to treat municipal wastewater. These estimates included both capital and operational / maintenance (O&M) costs related to the headworks, MBR process (biological process and membrane system), chlorine disinfection and effluent storage. The costs associated with the membrane systems were developed from budgetary cost quotes provided by suppliers which have recently introduced newly developed MBR products into the U.S. market. Each of these products offer unique design features aimed towards the reduction of capital and/or operation costs. All other costs associated with the MBR facilities were developed from previous conceptual designs performed by the project team and updated using current standard engineering cost indices. Total estimated capital plus annual costs ($/1000 gal treated) for the newly developed MBR systems (1-MGD capacity) ranged from $2.02-$2.58. The range in costs directly reflects the range in membrane system and membrane replacement costs provided by the participating MBR suppliers. Evaluation of cost estimates for 1 and 5 MGD capacity MBR facilities revealed an average economy of scale of 16.5% for the non-membrane components (i.e. headworks, process basins, buildings etc.) of the MBR facility and 23.6% for the membrane system only. Comparison of the current MBR cost estimates to historical costs estimates (adjusted for inflation) suggest that a steady decrease has occurred in the membrane system cost of MBRs between However, an opposite trend was observed over the same time period for costs associated with the non-membrane components of the MBR facility. The drop in membrane system costs are attributed to advancements in manufacturing and increased competition in the market place while the increased costs of facility components are attributed to the increased cost of concrete and other raw materials used for plant construction. Results from this analysis shows these opposing trends have resulted in the overall total cost of MBR facilities to be fairly level (i.e. < 10% increase) between 2000 and KEYWORDS Membrane Bioreactor, MBR, Wastewater Reclamation, Water Reuse, Wastewater Treatment 3407

2 INTRODUCTION Membrane bioreactors (MBR) are a leading-edge technology being applied worldwide for municipal wastewater treatment. The municipal MBR market has grown dramatically over the past decade with facilities increasing in number and capacity. During this time, the number of suppliers offering MBR systems within the municipal wastewater market has also sky rocketed. Though the technology has become established within the municipal wastewater treatment sector, little published information exists related to the cost of MBR systems (Churchhouse and Wildgoose, 1999; Davies et al., 1998). Due to the vast growing nature of the MBR market, it is important for the industry to have current cost information of these systems for budgeting and planning purposes. An evaluation of the historical cost trends of MBR systems would also provide useful information on how technological advancements and increased competition are impacting costs. Lastly, insight on specific applications where the implementation of MBR may be economically favorable over conventional treatment alternatives would be valuable for those considering the technology to meet their wastewater treatment goals. The project team has been evaluating MBR technology related to municipal wastewater treatment for nearly a decade. This included the completion of four consecutive projects focused on the development of various MBR systems (Adham et al., 1998, 2000, 2004; DeCarolis et al., 2007). The scope of each project also included rough order cost estimates of MBR technology based on various scenarios. Upon completion of the most recent project, focused on newly developed MBR products, the project team thought it would be useful to compare the cost information from the four projects to identify possible general trends in MBR costs for the given time period. It should be emphasized the cost estimates provided in this paper represent budgetary estimates for municipal MBR facilities based on certain assumptions; however site specific factors can significantly alter MBR costs and must be considered when performing budgetary planning. The objectives of this evaluation were: Perform total cost estimates (capital and annual) of new developed MBR systems recently introduced in the U.S. market for various capacities (1 and 5 MGD). Assess the economy of scale of associated with 1 and 5 MGD MBR facilities. Compare cost estimates of MBR facilities prepared between to identify possible cost trends related to the membrane component as compared to other facility system components (i.e. biological basins, pre and post treatment). METHODOLOGY Costing Approach Cost analyses were performed to estimate the capital and operational costs of full-scale MBR water reclamation facilities for treatment capacities of 1 and 5 MGD (4,000-20,000 m 3 /day). Costs were estimated for MBR facilities consisting of headworks, process basins, membrane system, mechanical equipment, blower and pump building, chlorination system and effluent storage. All costs except those related to the membrane systems were derived from previous estimates (Adham et al., 2004) and updated using current Engineering News Record 3408

3 Construction Cost Index (ENRCCI) and Chemical Engineering Plant Cost Index (CEPCI). Costs associated with the membrane systems (i.e. membranes, pumps, blowers and miscellaneous equipment along with installation) were based on recent budgetary costs estimates provided by suppliers of the newly developed MBR systems including Koch Membrane Systems, Huber Technologies Inc., Kruger Inc. and Parkson Corporation. Table 1 provides a brief description of each of these MBR products including their unique design features which may impact capital and/or operation and maintenance (O&M) costs. In order to get comparable quotes from all suppliers, a memo was created and given to each supplier, which provided specific information related to the cost request. The cost estimates of the newly developed systems were compared to historical MBR cost estimates prepared from budgetary estimates provided by establsihed MBR suppliers including Zenon, Kubota and Memcor (Adham et al., 1998, 2000, 2004). Conceptual Design Criteria Table 2 provides the MBR design criteria used for all cost estimates. The raw water quality was assumed typical of medium strength municipal wastewater with BOD 5, ammonia, and TSS of 290 mg/l, 30 mg-n/l and 320 mg/l, respectively. The membrane operating conditions and reactor design criteria were based on previous conceptual MBR designs and pilot testing conducted by the project team (Adham et al., 2004; DeCarolis et al., 2007) and consultation with participating MBR manufacturers. As indicated, the instaneuous membrane flux rates ranged from gfd for submerged systems and 30 gfd for external systems. The higher flux value used for external systems is due to membrane scouring which results from high recirculation of MLSS across the membrane surface which prevents accumulation of solids on the membrane surface. As shown in Table 2, cost estimates were based on MBR systems designed for complete oxidation of biodegradable organic matter (BOD 5 <2 mg/l), complete nitrification (ammonia<1.0 mg-n/l), partial denitrification (nitrate<10 mg-n/l) and biological phosphorus removal (total phosphorus <0.2 mg-p/l). For costing purposes, it was also assumed that all MBR facilities were sewer mining or scalping plants built on a clean plot of land. Such facilities differ from end-of-pipe systems because raw wastewater is withdrawn at a controlled rate from the collection system and all residuals (screenings, grit, WAS, etc.) are returned to the same pipe which eliminates the need for sludge handling and disposal. In addition, MBR scalping plants require much less (or no) redundancy compared to end of pipe facilities. The participating manufacturers were requested to provide membrane system cost estimates based on the ability to operate at average conditions with two filter units out of service (OOS). One OOS to accommodate routine relaxation / backwashing and an additional membrane filter OOS for chemical cleaning. Lastly, costs were based on the design capacity without peaking. 3409

4 Table 1 Description of Newly MBR Systems used in Cost Analysis Supplier Membrane Type / Configuration Key Design Feature(s) Description Intended Purpose Potential Cost Impact Koch Membrane Systems hollow fiber / submerged Sealed fibers (one end) Prevent loss of membrane active area; minimize fiber breakage lower membrane replacement costs Huber Technologies Inc. flat sheet / submerged Rotating membranes, universal air scour Reduce membrane air scour lower energy costs Parkson Corporation tubular/external Side stream external membranes; Airlift System Reduce membrane air scour / increase operating flux lower energy costs; reduce capital cost of membranes for given production capacity Kruger Inc. flat sheet / submerged Uniform membrane pore size Enhance effectiveness of membrane cleaning reduce cleaning costs / lower membrane replacement costs 3410

5 Table 2 MBR Design Criteria used in Cost Analysis Desgin Criteria Units Value Raw Water Quality BOD 5 mg/l 290 COD mg/l 630 TSS mg/l 320 VSS mg/l 260 Ammonia-N mg/l 30 TKN mg/l 60 Total Phosphorus-P mg/l 2 TDS mg/l 1200 Alkalinty mg/l 245 Temperature Deg C 20 Membrane and Reactor Design Conditions Flux 25 Deg C (submerged) 30 (external) MLSS g/l 8 F/M day HRT hr 6 SRT days 10 Effluent Water Quality BOD 5 mg/l <2 Ammonia-N mg/l <1.0 Nitrate-N mg/l <10 Total Phosphorus-P mg/l <2.0 RESULTS AND DISCUSSION Cost Estimates of Newly Developed MBRs Captial Costs. Table 3 provides capital cost estimates for the various MBR facilites designed for 1 and 5 MGD capacities. The table includes total capital costs ($K) and amortized capital costs ($K/year) assuming a 5% interest rate over a 30 year period. As shown, the total capital cost estimate for the 1.0-MGD installations ranged from $7,990,000 $9,850,000, while the amortized cost ranged from $520,000-$641,000. The range in capital costs directly reflects the range of membrane system costs acquired from the four participating MBR suppliers. Each supplier was requested to provide membrane costs to include a 5-yr non-prorated warranty. In addition, the suppliers were requested that the costs include adequate membranes to produce the desired capacities at flux rates demonstrated during pilot testing. The values of instantaneous flux during pilot testing ranged from gfd for the submerged MBR systems and 30 gfd for the external MBR system. Net flux differs from instantaneous flux as it accounts for downtime due to relaxation/backwashing and product water used for backwashing/maintenance cleans. In general such losses amount to about 10% of daily production. Each supplier was requested to account for these losses when estimating membrane costs. Operation & Maitenance Costs. Table 4 provides the estimated annual and total O & M costs (5% interest rate over a 30-year period) for all MBR installations considered. As shown key O&M costs included labor, equipment repair and replacement parts, chemicals 3411

6 (membrane cleaning and disinfection), membrane replacement, and electricity. Membrane replacement costs were provided by the participating suppliers and are based on an 8-yr membrane life. All other unit cost assumptions are provided elsewhere (DeCarolis et al., 2007). As provided in Table 4, the annually O&M cost ($K/yr) for the 1-MGD ranged from $218-$302. The range in values is reflective of differences in membrane replacement costs ($K/yr) provided by the participating MBR suppliers, which ranged from $40-$106. Table 3: Capital Cost Estimates of MBR Facilities Item 1.0 MGD Capital Costs, $K 5.0 MGD Headworks $516 $2,064 Basins $503 $2,346 5-ton bridge crane $56 $69 1 Membrane System $1,419-$2,330 $5,803-$7,750 Mechanical $480 $2,766 Blower and Pump building $274 $962 Chlorine Dosing System $248 $1,242 Subtotal $3,441-$4,352 $15,183-$17,130 Electrical, 15% $525-$661 $2,222-$2,700 Mechanical/ Plumbing/HVAC, 13% $455-$573 $1,926-$2,340 Sitework, 9% $315-$397 $1,333-$1,620 Subtotal $4,791-$6,039 $20,295-$24,659 Contractor Overhead and Profit, 15% $719-$906 $3,044-$3,699 Subtotal-Construction Cost $5,509-$6,945 $23,339-$28,357 Land $825 $1,925 Contingency, 15% $826-$1,042 $3,501-$4,254 Engineering/Legal/Administration, 15% $826-$1,042 $3,501-$4,254 Total Capital Cost, $ $7,990-$9,850 $32,270-$38,790 Interest Rate 5% 5% Number of Years P/A Factor Amortized Capital Cost, $/yr $520-$641 $2,099-$2,523 1 Costs based on proposals received from MBR vendors in July/August

7 Table 4: O&M Cost Estimates of MBR Facilities Item O & M Costs, $K/yr 1.0 MGD 5.0 MGD Electrical power for process/miscellaneous $88 $438 Equipment repairs/lubricants/replacement $38-$57 $159-$223 Chemical Cleaning $9 $46 Chemical Cost for Disinfection $5 $26 Diffuser Replacement $3 $14 1, 2 Membrane Replacement $40-$106 $193-$478 Labor $35 $98 Total O&M Costs in First Year, $ $218-$302 $974-$1,323 Interest rate 5% 5% Number of Years P/A Factor Total Estimated O&M Costs, $ $3,350-$4,649 $14,974-$20,344 1 Membrane Replacement cost estimates based on 8-yr life; annual costs shown would fund account annually. 2 Costs based on proposals received from MBR vendors in July/August Figure 1 provides a visual representation of the percent contribution each O&M component has on the total annual cost associated with a 1-MGD MBR facility. These costs were based on average membrane replacement costs provided by the participating suppliers. As shown the two largest components of the O&M cost includes membrane replacement (28%) and energy (34%). The two main energy demands of the MBR system include that required by air blowers to provide process air and scour the membranes. Judd, 2006 reported that these demands make up 35% and 38%, respectively of the total energy demand associated with a 1.5 MGD MBR system. 13% MBR O & M Costs Energy 34% Equipment Repair / Replacement Chemicals Membrane Replacement 28% Labor 6% 19% Figure 1: Breakdown for O&M Costs for 1-MGD MBR Facility 3413

8 Interestingly, pilot data collected from 10 different MBR systems between at the Aqua 2030 Research Center (San Diego CA) suggests that the membrane air scour requirement for MBR systems has shown improvement in recent years. A summary of this data is provided in Table 5. As shown the specific air demand per membrane area (SADm) and specific air demand per permeate volume produced (SADp) requirements (as defined by Judd 2006) for System A and B were lower duirng testing conducted in 2003 as opposed to testing conducted in In additon, due to its high flux rate, the external membrane tested in 2006 had the lowest SADp (with the exception of System A which used cyclic aeration) of all systems tested. Though this data is useful to make general comparisons of air scour requirements from different types of MBR systems it is important to also consider the required cleaning frequencies of the systems. For example a system operating with lower SADp or SADm value may require more frequent membrane cleaning and therefore increased costs associated with chemicals and possible reduced membrane life. The project team is currently incorporating this information into a more detailed cost model to compare the energy costs of the various MBR systems. Table 5: Membrane Air Scour used for MBR Systems MBR System ID Year Tested Configuration Instantaneous Target Permeate Flux (gfd) SADm (scfm/ f 2 ) SADp (ft 3 air / ft 3 permeate) 1 A 1998 immersed HF B 1998 immersed HF C 2002 immersed FP D 2002 immersed HF A 2003 immersed HF B 2003 immersed HF E 2006 immersed HF F 2006 side stream MT G 2006 immersed FP H 2006 immersed FP ) used cyclic aeration 2) required pumping energy for MLSS recirculation. Total Costs / Economy of Scale. Table 6 provides a summary of the capital and O&M cost estimates for complete MBR facilities based on 1 and 5 MGD capacities. The total capital costs and estimated O&M costs were summed to provide present worth values of each installation. The present worth values shown are based on a 5% interest rate over a 30-year period. The present worth ($K) for the 1-MGD and 5 MGD was estimated between $11,260- $14,429 and $47,064-$58,954, respectively. Table 7 provides total costs ($/1000 gal) for each capacity. These costs were derived from the amortized capital cost and the annual O&M cost associated with each capacity. The table shows the total cost ($/1000 gal) for the 1-MGD capacity ranged from $2.02-$2.58. An economy of scale analysis of the costs associated with the MBR facility components (excluding membrane system costs) and the membrane system only was conducted for 1 and 5 MGD capacities. The total costs ($K/MGD) (based on the average values of the four systems analyzed) associated with these two capacities was determined to be $12,844 and $10,602 respectively. A comparison of 3414

9 these estimates reveals an economy of scale exists for both the MBR facility components (16.5%) and the membrane system only component (23.6%). The former would be expected as the cost of construction and raw material decreases with size and bulk quantity. The latter would indicate savings associated with purchasing larger quantities of membranes. Table 6: Summary of Capital and O&M Cost for MBR Facilities Capacity (MGD) Capital Costs, $K Total O&M Costs, $K Present Worth Value, $K 1 5 $7,990-$9,850 $3,350-$4,649 $11,260-$14,429 $32,270-$38,790 $14,974-$20,344 $47,064-$58,954 Table 7: Summary of Costs, $/kgal for MBR Facilities Capacity (MGD) Amortized Capital Costs, $K/yr O&M Costs, $K/yr Total Cost, $K/yr Total Cost, $/1000 gal 1 5 $520-$641 $218-$302 $738-$943 $2.02-$2.58 $2,099-$2,523 $974-$1,323 $3,073-$3,846 $1.68-$2.11 MBR COST TRENDS The capital cost estimates of the newly developed MBR facilities were compared with previous cost estimates made by the project team in 2000 and The estimates of the membrane systems were obtained from original budget proposals provided by Zenon and Kubota, in the given years (Adham et al., 2000 & 2003) and budget proposals received from the suppliers of the newly developed MBR systems in All previous budgetary cost estimates of the membrane systems were adjusted to current dollars using the consumer price index (CPI) published by the U.S. Department of Labor (U.S. Department of Labor, Bureau of Labor Statistics Data, 2006). Membrane system costs include costs associated with the membranes, pumps, blowers and miscellaneous equipment along with installation. Capital costs for all other MBR facility components (i.e. headworks, process basins, blower/pump building, chlorine dosing system and effluent storage) were based on original estimates (Adham et al., 2003) and adjusted using ENRCCI and CEPCI for the desired years. As shown in Figure 2 there has been a steady increase (~24%) in costs associated with MBR process components (excluding membrane system) between Interestingly, as shown in Figure 3 the opposite trend was observed for membrane system costs, which actually have decreased by approximately 33% over the same time period. The rise in nonmembrane costs associated with the MBR facilities is due to the increased cost of concrete and other raw materials used for plant construction. The drop in membrane system costs maybe attributed to advancements in manufacturing and increased competition in the market place. These trends have resulted in the overall total cost for 1-MGD MBR systems to be fairly level (i.e. < 10% increase) between 2000 and

10 MBR Process Components Cost $8,000 1-MGD capacity $6,000 Capital Cost, $K $4,000 $2,000 $ Membrane system costs not included in estimates Year Figure 2: Capital Cost Estimates of 1-MGD MBR Facility Components ( ) Membrane System Cost Capital Cost, $K (2006 Dollars) $4,000 $3,000 $2,000 $1,000 $0 1-MGD capacity Costs for 2000 and 2003 were determined by adjusting Year orginal estimates using 2006 Consumer Price Index Figure 3: Capital Cost Estimates of 1-MGD MBR Membrane Systems 3416

11 CONCLUSIONS The following conclusions were made from this evaluation: Capital cost ($K) estimates of 1 MGD capacity MBR systems (membrane systems only) varied from $1,419-$2,330 based on budgetary proposals received from the four participating suppliers. Total cost estimates ($/1000 gal) for 1 MGD MBR facilities (headworks, biological process, membrane system, chlorine disinfection and effluent storage) ranged from ranged from $2.02-$2.58. Membrane replacement (28%) and energy costs (34%) were the largest components of the O&M cost estimates associated with the MBR systems. Cost estimates of 1 and 5 MGD MBR systems showed an economy of scale for both the MBR process components (16.5%) and the membrane system only component (23.6%). Comparison of the current cost estimates of the newly developed MBR systems to historical costs estimates (adjusted for inflation) suggests a steady decrease (total decrease ~33%) in the membrane system component cost has occurred between Comparison of the current cost estimates of the newly developed MBR systems to historical costs estimates (adjusted for inflation) suggests a steady increase (total increase ~ 24%) in the MBR process components costs (not including membrane systems costs) has increased by ~24% between Results from this evaluation has shown the overall total cost for 1-MGD MBR facilities has been fairly level (i.e. < 10% increase) between ACKNOWLEDGMENTS The project team would thanks the following groups for making this project possible. United States Bureau of Reclamation (USBR) Technical Service Center Water Treatment Engineering and Research Group for funding Agreement No. 01-FC Larry Wassermann and Neil Tran of the City of San Diego Metropolitan Wastewater Department for assisting with MBR evaluations. 3417

12 Participating Vendors for supplying budgetary cost estimates of their MBR systems: Koch Membrane Systems, Huber Technologies Inc., Kruger Inc. and Parkson Corporation. Dr. Simon Judd (Cranfield University) for providing information on normalizing MBR energy requirements. REFERENCES Adham, S., et al., (1998) Membrane Bioreactors for Water Repurification- Phase I, Desalination Research and Development Program Report No. 34; Bureau of Reclamation. Adham, S., et al., (2000) Membrane Bioreactors for Water Reclamation - Phase II, Desalination Research and Development Program Report No. 60; Bureau of Reclamation. Adham, S., and DeCarolis, J., (2004) Optimization of Various MBR Systems for Water Reclamation-Phase III, Final Report Project No. 103; Bureau of Reclamation. Churchhouse, S.J., Wildgoose, D., (1999) Membrane Bioreactors hit the big time from lab to full-scale installation. Inlt Meeting on Membrane Bioreactors for Wastewater Treatment, University, Cranfield, UK. Pg. 14. Davies, W.J., Le, M.S., and Heath, C.R., (1998) Intensified activated sludge process with submerged microfiltration. Wat. Sci. Technology. 38 (4-5), DeCarolis, J., Adham, S., Hirani Z., (in-print 2007) Evaluation of Newly Developed Membrane Bioreactor Systems for Water Reclamation Phase 4. Final Report, Project No. 01-FC , United States Department of Interior, Bureau of Reclamation. Judd, S., (2006) The MBR Book. Elsevier Publishing. U.S. Department of Labor Bureau of Labor Statistics Data (2006),

EVALUATION OF NEWLY DEVELOPED MEMBRANE BIOREACTORS FOR WASTEWATER RECLAMATION

EVALUATION OF NEWLY DEVELOPED MEMBRANE BIOREACTORS FOR WASTEWATER RECLAMATION EVALUATION OF NEWLY DEVELOPED MEMBRANE BIOREACTORS FOR WASTEWATER RECLAMATION ABSTRACT Zakir Hirani 1, James DeCarolis 1, Samer Adham 1, Larry Wasserman 2 1 MWH, 31 North Lake Ave, Suite 12, Pasadena,

More information

Membrane BioReactor: Technology for Waste Water Reclamation

Membrane BioReactor: Technology for Waste Water Reclamation Membrane BioReactor: Technology for Waste Water Reclamation Sachin Malekar - Senior Manager, Technology & Nilesh Tantak - Executive, Technology Ion Exchange (India) Ltd. BACKGROUND Due to diminishing water

More information

Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor

Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor J. Komorita 1, P. Burke 2, B. Youker 2, and G. Crawford 2 1 King County, 2 CH2M HILL ABSTRACT Many Membrane Bioreactor (MBR)

More information

DEVELOPMENT OF THE. Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc.

DEVELOPMENT OF THE. Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc. DEVELOPMENT OF THE AquaMB PROCESS Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc. Aqua-Aerobic Systems, Inc. 6306 N. Alpine Road Rockford, IL 61111 Copyright 2003 Aqua-Aerobic

More information

The Effect of Organic Loading on Membrane Fouling in a Submerged Membrane Bioreactor Treating Municipal Wastewater

The Effect of Organic Loading on Membrane Fouling in a Submerged Membrane Bioreactor Treating Municipal Wastewater The Effect of Organic Loading on Membrane Fouling in a Submerged Membrane Bioreactor Treating Municipal Wastewater R. Shane Trussell, P.E., Rion P. Merlo, Slawomir W. Hermanowicz,, and David Jenkins Department

More information

There Is Another Flat Plate MBR

There Is Another Flat Plate MBR There Is Another Flat Plate MBR Evaluation of Huber's VRM Membrane Bioreactor Technology Henryk Melcer Background VRM Technology Pilot plant Review of Investigation Preliminary conclusions Outline Membrane

More information

MBRs Don t Have to Break the Bank

MBRs Don t Have to Break the Bank MBRs Don t Have to Break the Bank Kimberly Mathis Business Development Manager MBR Systems Ovivo USA, LLC P : 512.834.6035 F : 512.834.6039 Kimberly.Mathis@ovivowater.com www.ovivowater.com Membrane Bioreactors

More information

Evaluation of Conventional Activated Sludge Compared to Membrane Bioreactors

Evaluation of Conventional Activated Sludge Compared to Membrane Bioreactors Evaluation of Conventional Activated Sludge Compared to Membrane Bioreactors Short Course on Membrane Bioreactors 3/22/06 R. Shane Trussell, Ph.D., P.E. shane@trusselltech.com Outline Introduction Process

More information

Is membrane filtration worth it?

Is membrane filtration worth it? Is membrane filtration worth it? A case study of 3 municipal MBR s in Michigan and their operational experiences. Joe Hebert - Ottawa County Public Utilities 1 Who are these MBR s? North Kent Sewer Authority,

More information

SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION

SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION Analytical Environmental Services 2-1 Jamul Indian Village Wastewater Treatment Plant Analytical Environmental Services 2-2 Jamul

More information

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL Alvin C. Firmin CDM Jefferson Mill, 670 North Commercial Street Suite 201 Manchester, New Hampshire 03101 ABSTRACT Sequencing

More information

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND Brett T. Messner, PE, Tetra Tech, Inc., 201 E Pine St, Suite 1000, Orlando, FL 32801 Brett.Messner@tetratech.com, Ph: 239-851-1225 Fred

More information

A Battle to Be the Best: A Comparison of Two Powerful Sidestream Treatment Technologies: Post Aerobic Digestion and Anammox

A Battle to Be the Best: A Comparison of Two Powerful Sidestream Treatment Technologies: Post Aerobic Digestion and Anammox A Battle to Be the Best: A Comparison of Two Powerful Treatment Technologies: Post Aerobic Digestion and Anammox David Oerke/CH2M Tom Johnson/CH2M Bruce Johnson/CH2M Heidi Bauer/CH2M Steve Graziano/CH2M

More information

Characteristics of Nutrient Removal in Vertical Membrane Bioreactors

Characteristics of Nutrient Removal in Vertical Membrane Bioreactors The 2 nd MBR workshop at Hokkaido University Characteristics of Nutrient Removal in Vertical Membrane Bioreactors Prof. Hang-Sik Shin Dept. of Civil and Environmental Engineering Korea Advanced Institute

More information

COMPARISON STUDY BETWEEN INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS), MEMBRANE BIOREACTOR (MBR) AND CONVENTIONAL ACTIVATED SLUDGE (AS) PROCESSES

COMPARISON STUDY BETWEEN INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS), MEMBRANE BIOREACTOR (MBR) AND CONVENTIONAL ACTIVATED SLUDGE (AS) PROCESSES Sixteenth International Water Technology Conference, IWTC 16 2012, Istanbul, Turkey 1 COMPARISON STUDY BETWEEN INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS), MEMBRANE BIOREACTOR (MBR) AND CONVENTIONAL

More information

Membrane Bioreactor. Highest level of effluent standards

Membrane Bioreactor. Highest level of effluent standards Membrane Bioreactor Highest level of effluent standards The effluent produced by Ecoprocess MBR meet the strictest quality requirements for the discharge of treated wastewater, including disinfection,

More information

Appendix D JWPCP Background and NDN

Appendix D JWPCP Background and NDN Appendix D JWPCP Background and NDN JWPCP Background JWPCP Water Quality Primary Clarifiers HPO Reactors Final Clarifiers Unit Influent Primary Effluent Secondary Effluent BOD mg/l 460 240

More information

Palmer Wastewater Treatment Plant Environmental Impacts. A summary of the impacts of this treatment alternative are listed below:

Palmer Wastewater Treatment Plant Environmental Impacts. A summary of the impacts of this treatment alternative are listed below: 6.1.3 Environmental Impacts A summary of the impacts of this treatment alternative are listed below: 1. The Matanuska River will receive treated effluent as it currently does. 2. Effluent quality would

More information

membrane bioreactors MBR vs. Conventional Activated Sludge Systems CAS

membrane bioreactors MBR vs. Conventional Activated Sludge Systems CAS membrane bioreactors MBR vs. Conventional Activated Sludge Systems CAS Features What of MBR is a Membrane technology Bioreactor? compared to conventional processes Membrane Bioreactors MBR, combine fine

More information

ASSESSMENT OF AN MBR SYSTEM FOR SEGREGATED HOUSEHOLD WASTEWATER BY USING SIMULATION MATHEMATICAL MODEL

ASSESSMENT OF AN MBR SYSTEM FOR SEGREGATED HOUSEHOLD WASTEWATER BY USING SIMULATION MATHEMATICAL MODEL Proceedings of the 13 th International Conference of Environmental Science and Technology Athens, Greece, 5-7 September 213 ASSESSMENT OF AN SYSTEM FOR SEGREGATED HOUSEHOLD WASTEWATER BY USING SIMULATION

More information

Air Connection on Rack. Filtrate Connection on Rack

Air Connection on Rack. Filtrate Connection on Rack What is a membrane? Module with Flow holes Air Connection on Rack Filtrate Connection on Rack 1 module 1rack Goal is to use membranes to separate or filter solids, organisms, and molecules from the liquid

More information

Basic Design Concepts of MBR

Basic Design Concepts of MBR Basic Design Concepts of MBR Class III & Class IV OTCO Workshop Wednesday August 15, 2007 Terry M. Gellner, P.E CT Consultants, Inc Outline Types of Membranes MBR WWTP and General Sizing Criteria Common

More information

Nutrient Removal Optimization at the Fairview WWTP

Nutrient Removal Optimization at the Fairview WWTP Alyssa Mayer, PE Principal Engineer Nutrient Removal Optimization at the Fairview WWTP Mark Strahota, PE Associate Presentation Overview Project Background Process Model Development BNR Design Considerations

More information

KUBOTA Submerged Membrane Unit for MBR Technologies

KUBOTA Submerged Membrane Unit for MBR Technologies KUBOTA Submerged Membrane Unit for MBR Technologies February 2017 Kubota Corporation Kubota was established in 1890. We are globally challenging problems on Water, Food and Environment. Combine Corporate

More information

OPTIMIZATION OF AN INTERMITTENTLY AERATED AND FED SUBMERGED MEMBRANE BIOREACTOR

OPTIMIZATION OF AN INTERMITTENTLY AERATED AND FED SUBMERGED MEMBRANE BIOREACTOR OPTIMIZATION OF AN INTERMITTENTLY AERATED AND FED SUBMERGED MEMBRANE BIOREACTOR P. MELIDIS, S. NTOUGIAS, V. VASILATOU, V. DIAMANTIS and A. ALEXANDRIDIS Laboratory of Wastewater Management and Treatment

More information

Membrane Biofilm Reactor (MBfR): A New Approach to Denitrification in Wastewater Setting

Membrane Biofilm Reactor (MBfR): A New Approach to Denitrification in Wastewater Setting Membrane Biofilm Reactor (MBfR): A New Approach to Denitrification in Wastewater Setting Ramesh Sharma, Ph.D. Shane Trussell, Ph.D., P.E. Trussell Technologies, Inc. Pasadena, CA April 2007 Outline Understanding

More information

APPLICATION OF FLAT SHEET CERAMIC MEMBRANE TECHNOLOGY FOR WATER REUSE. Abstract. Introduction

APPLICATION OF FLAT SHEET CERAMIC MEMBRANE TECHNOLOGY FOR WATER REUSE. Abstract. Introduction APPLICATION OF FLAT SHEET CERAMIC MEMBRANE TECHNOLOGY FOR WATER REUSE James F. DeCarolis, P.E., Black & Veatch, 300 Rancheros Drive, Suite 250, San Marcos, CA, 92069, decarolisjf@bv.com, Ph: 619-204-2537

More information

ISAM SBR with Blower Assisted Jet Aeration Design Calculations For Lyons, CO WWTP Upgrade

ISAM SBR with Blower Assisted Jet Aeration Design Calculations For Lyons, CO WWTP Upgrade ISAM SBR with Blower Assisted Jet Aeration Design Calculations For Lyons, CO WWTP Upgrade May. 28, 2013 A. Site Conditions 1. Site elevation = 5,322 ft MSL 2. Average barometric pressure = 12.07 psia 3.

More information

MEMBRANE BIOREACTORS (MBR)

MEMBRANE BIOREACTORS (MBR) MEMBRANE BIOREACTORS (MBR) MEMBRANE CLASSIFICATION Microfiltration (MF) Ultrafiltration (UF) Nanofiltration (NF) Reverse Osmosis (RO) COMPARISON OF MEMBRANE FILTRATION PROCESSES CONTAMINANTS REJECTED GENERAL

More information

Japan U.S. Joint Conference on Drinking Water Quality Management and Wastewater Control, March 2-5, 2009

Japan U.S. Joint Conference on Drinking Water Quality Management and Wastewater Control, March 2-5, 2009 Japan-U.S. Joint Conference Abstract Investigation of Membrane Bioreactor Effluent Water Quality and Technology Japan U.S. Joint Conference on Drinking Water Quality Management and Wastewater Control,

More information

MEMBRANE BIOREACTORS (MBR) AND REVERSE OSMOSIS (RO) FOR LEACHATE TREATMENT. Abstract

MEMBRANE BIOREACTORS (MBR) AND REVERSE OSMOSIS (RO) FOR LEACHATE TREATMENT. Abstract MEMBRANE BIOREACTORS (MBR) AND REVERSE OSMOSIS (RO) FOR LEACHATE TREATMENT Kevin D. Torrens, BCEEM, Brown and Caldwell, 2 Park Way, Suite 2A, Upper Saddle River, NJ 07458 KTorrens@Brwncald.com, Ph: 201-574-4700

More information

Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects

Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects Glen T. Daigger, Ph.D., P.E., DEE, NAE Senior Vice President and Chief Technology Officer CH2M HILL Presented

More information

EVALUATION OF CERAMNIC MBR TECHNOLOGY FOR WATER REUSE. Abstract. Introduction

EVALUATION OF CERAMNIC MBR TECHNOLOGY FOR WATER REUSE. Abstract. Introduction EVALUATION OF CERAMNIC MBR TECHNOLOGY FOR WATER REUSE James F. DeCarolis, P.E., Black & Veatch, 300 Rancheros Drive, Suite 250, San Marcos, CA, 92069, decarolisjf@bv.com, Ph: 619-204-2537 Scott Freeman,

More information

Aqua-Aerobic MBR Topics

Aqua-Aerobic MBR Topics Aqua-Aerobic MBR Topics Aqua-Aerobic Systems KMS Partnership Traditional MBR Approach Aqua-Aerobic Time-managed Biological Approach Bioreactor Operation & Membrane Integration Traditional Membrane Issues

More information

THE USE OF MEMBRANE BIOREACTOR FOR WASTEWATER TREATMENT

THE USE OF MEMBRANE BIOREACTOR FOR WASTEWATER TREATMENT 1 2 THE USE OF MEMBRANE BIOREACTOR FOR WASTEWATER TREATMENT 1. R. NAGY, 2. W. SCHMIDT, 1. A. NEGREA, 2. M. BELCEA 1. POLITEHNICA UNIVERSITY OF TIMIŞOARA, FACULTY OF INDUSTRIAL CHEMISTRY AND ENVIRONMENTAL

More information

Operation of a small scale MBR system for wastewater reuse

Operation of a small scale MBR system for wastewater reuse Operation of a small scale MBR system for wastewater reuse K. Azis, Ch. Vardalachakis, P. Melidis and S. Ntougias Laboratory of Wastewater Management and Treatment Technologies, Department of Environmental

More information

No-Holds-Barred Match: RBC vs. MBR

No-Holds-Barred Match: RBC vs. MBR No-Holds-Barred Match: RBC vs. MBR Northeast Onsite Wastewater Short Course & Exhibition April 6 th, 2016 Erin K. Moore, PE Services provided in NY as T&B Engineering, PC Overview Evaluation target Historic

More information

Application of MBR for the treatment of textile wastewater

Application of MBR for the treatment of textile wastewater Application of MBR for the treatment of textile wastewater P. Damala, E. Katsou, J. Novakovic, K. Chatzikonstantinou, G. Karathanasi, A. Patsia, S. Malamis International Conference on Industrial Waste

More information

A Critical New Look at Nutrient Removal Processes

A Critical New Look at Nutrient Removal Processes A Critical New Look at Nutrient Removal Processes Thomas E. Wilson,* John McGettigan* *Earth Tech, Inc. 675 North Washington Street Alexandria, Virginia 22314 ABSTRACT This paper questions the basic practice

More information

Membrane Bioreactors for Wastewater Treatment

Membrane Bioreactors for Wastewater Treatment PDH-Pro.com Membrane Bioreactors for Wastewater Treatment Course Number: CH-02-212 PDH: 4 Approved for: AK, AL, AR, GA, IA, IL, IN, KS, KY, MD, ME, MI, MN, MO, MS, MT, NC, ND, NE, NH, NJ, NM, NV, OH, OK,

More information

Membrane Thickening Aerobic Digestion Processes

Membrane Thickening Aerobic Digestion Processes Membrane Thickening Aerobic Digestion Processes 2013 NESOWEA Operator Seminar Bryen Woo, PE Membrane Thickening Digestion Aerobic digestion process using a Flat Sheet Membrane Unit Ideal for: Facilities

More information

Submerged Membrane Technology for MBR

Submerged Membrane Technology for MBR Submerged Membrane Technology for MBR Who we are newterra GmbH - a subsidiary of Newterra Ltd., of Ontario, Canada - is the Technology and Competence Centre for the MicroClear filtration system for our

More information

Recycling of Food Processing Wastewater to Potable Water Standards

Recycling of Food Processing Wastewater to Potable Water Standards Recycling of Food Processing Wastewater to Potable Water Standards The issues surrounding wastewater recycling in the food and drinks sector are generally well known. Over the past ten years a UK owned

More information

Introduction of Kubota Corporation and its capability in Water Market

Introduction of Kubota Corporation and its capability in Water Market Introduction of Kubota Corporation and its capability in Water Market 6 th October, 2016 KUBOTA Corporation http://www.kubota-global.net/ 1 Contents 1. Introduction of Kubota and its Water Related Products

More information

ENHANCED BIOLOGICAL PHOSPHORUS REMOVAL WITHIN MEMBRANE BIOREACTORS. 255 Consumers Road Toronto, ON, Canada, M2J 5B6

ENHANCED BIOLOGICAL PHOSPHORUS REMOVAL WITHIN MEMBRANE BIOREACTORS. 255 Consumers Road Toronto, ON, Canada, M2J 5B6 ENHANCED BIOLOGICAL PHOSPHORUS REMOVAL WITHIN MEMBRANE BIOREACTORS G. Crawford 1,2, G. Daigger 1, and Z. Erdal 1 1 CH2M HILL 2 CH2M HILL 255 Consumers Road Toronto, ON, Canada, M2J 5B6 ABSTRACT Several

More information

Improved Membrane Design Addresses Integrity Issues for the City of Yuba City Water Treatment Plant

Improved Membrane Design Addresses Integrity Issues for the City of Yuba City Water Treatment Plant Improved Membrane Design Addresses Integrity Issues for the City of Yuba City Water Treatment Plant Richard Stratton, PE HDR Engineering Acknowledgements City of Yuba City - John Westhouse, Plant Supervisor

More information

Membrane Bioreactors (MBR) for Water Reclamation

Membrane Bioreactors (MBR) for Water Reclamation Membrane Bioreactors (MBR) for Water Reclamation Course No: C07-003 Credit: 7 PDH Raymond Ehrhard, P.E., B.C.E.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980

More information

Fifteen Years of Progressive Membrane Bioreactor Experience in the Pacific Northwest Patrick Roe April 27, HDR, Inc., all rights reserved.

Fifteen Years of Progressive Membrane Bioreactor Experience in the Pacific Northwest Patrick Roe April 27, HDR, Inc., all rights reserved. Cover Slide 2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. Fifteen Years of Progressive Membrane Bioreactor Experience in the Pacific Northwest Patrick Roe April 27, 2018 2017 HDR, Inc., all

More information

Feasibility Report on Sewage Treatment Plant (STP)

Feasibility Report on Sewage Treatment Plant (STP) Feasibility Report on Sewage Treatment Plant (STP) FOR Proposed Commercial Building project Commercial Office Building by M/s. Bhagavath Sannidhi Estates Pvt Ltd.at Sy No 55/1 of Devarabeesanahalli Village,

More information

FEASIBILITY REPORT OF 250 KLD SEWAGE TREATMENT PLANT

FEASIBILITY REPORT OF 250 KLD SEWAGE TREATMENT PLANT FEASIBILITY REPORT OF 250 KLD SEWAGE TREATMENT PLANT FOR Proposed Residential Apartment project by M/s. DS-Max Properties Pvt Ltd, at Sy No. 27/2 & 27/3 at Valagerahalli Village, Kengeri Hobli, Bangalore

More information

Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation

Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation Pennsylvania Water Environment Federation PennTEC Annual Technical Conference June 4, 2013 Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation Presented by: Jim

More information

MEMBRANE BIOREACTORS FOR RO PRETREATMENT

MEMBRANE BIOREACTORS FOR RO PRETREATMENT ABSTRACT MEMBRANE BIOREACTORS FOR RO PRETREATMENT Simon Dukes, Antonia von Gottberg Koch Membrane Systems, 850 Main Street, Wilmington, MA 01887 Currently, treated municipal wastewater is typically discharged

More information

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W Facility Overview The recently upgraded and expanded Henry N. Wochholz Regional Water Reclamation Facility (WRWRF) treats domestic wastewater generated from the Yucaipa-Calimesa service area. The WRWRF

More information

Recent Advances in Membrane Technologies Peter D Adamo, Ph.D., P.E Spring Conference Wilmington, NC April 13, 2015

Recent Advances in Membrane Technologies Peter D Adamo, Ph.D., P.E Spring Conference Wilmington, NC April 13, 2015 2015 Spring Conference Wilmington, NC April 13, 2015 Recent Advances in Membrane Technologies Peter D Adamo, Ph.D., P.E. 2014 HDR, Inc., all rights reserved. Membrane Filtration Basics Recent Membrane

More information

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010 Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21

More information

Review of WEFTEC 2016 Challenge & Overview of 2017 Event. Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng

Review of WEFTEC 2016 Challenge & Overview of 2017 Event. Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng Review of WEFTEC 2016 Challenge & Overview of 2017 Event Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng Agenda Review 2016 Challenge Provide overview of updates to 2017 event Frequency WEFTEC Scores

More information

Description. Development

Description. Development Description Aquatec Maxcon is the exclusive agent for Kubota membrane bioreactors (MBRs) modules in Australia and New Zealand. Our company designed and constructed the first commercial scale MBR in Australasia

More information

CSR Process Simulations Can Help Municipalities Meet Stringent Nutrient Removal Requirements

CSR Process Simulations Can Help Municipalities Meet Stringent Nutrient Removal Requirements CSR Process Simulations Can Help Municipalities Meet Stringent Nutrient Removal Requirements Continuous Flow Sequencing Reactor (CSR) Basin with Moving Bridge, Submerged Diffusers, and Stationary Diffusers

More information

Factors Affecting Filtration Characteristics in Submerged Membrane Bioreactor for Wastewater Treatment

Factors Affecting Filtration Characteristics in Submerged Membrane Bioreactor for Wastewater Treatment Factors Affecting Filtration Characteristics in Submerged Membrane Bioreactor for Wastewater Treatment Dr V S SAPKAL 1 ; D J GARKAL 2 ; Dr R S SAPKAL 3 ; P V SAPKAL 4 1 Vice Chancellor, RTM Nagpur University,

More information

EVW 2 Hynds Commercial Wastewater Systems April 2013

EVW 2 Hynds Commercial Wastewater Systems April 2013 Hynds Commercial Wastewater Systems High quality sewage treatment systems Fully designed by qualified engineers Small footprint EVW 2 Hynds Commercial Wastewater Systems April 2013 0800 425 433 www.hyndsenv.co.nz

More information

Energy Use Impacts of Flow Conveyance Alternatives for Membrane Bioreactor (MBR) Facilities

Energy Use Impacts of Flow Conveyance Alternatives for Membrane Bioreactor (MBR) Facilities Energy Use Impacts of Flow Conveyance Alternatives for Membrane Bioreactor (MBR) Facilities Thor Young 1* and Kristi Perri 1 1 GHD Inc., Bowie, Maryland * Email: thor.young@ghd.com ABSTRACT Flow conveyance

More information

Application of MBR Technology in Municipal Wastewater Treatment

Application of MBR Technology in Municipal Wastewater Treatment Arab J Sci Eng (20) 36:3 DOI.7/s3369-0-0007-7 RESEARCH ARTICLE - CHEMISTRY A. Naghizadeh A. H. Mahvi A. R. Mesdaghinia M. Alimohammadi Application of MBR Technology in Municipal Wastewater Treatment Received:

More information

A Submerged Attached Growth Bioreactor (SAGB) And Membrane Filtration For Water Reuse

A Submerged Attached Growth Bioreactor (SAGB) And Membrane Filtration For Water Reuse A Submerged Attached Growth Bioreactor (SAGB) And Membrane Filtration For Water Reuse Philip B. Pedros, Ph.D., P.E. Andrew R. McBrearty, P.E. Wallace W. Bruce Agenda Introduction Description of Process

More information

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES A range of potential ammonia limits were identified for alternatives evaluation, as discussed in Section 2.2.5. This chapter

More information

Sulaibiya world s largest membrane water reuse project

Sulaibiya world s largest membrane water reuse project Water Technologies & Solutions technical paper Sulaibiya world s largest membrane water reuse project background In May 2001, a consortium including Mohammed Abdulmohsin Al-Kharafi and Sons (The Kharafi

More information

MEMBRANE AERATED BIOFILM REACTORS OXYGENATED FUN WITH LESS CARBON COST KELLY MARTIN AND SANDEEP SATHYAMOORTHY

MEMBRANE AERATED BIOFILM REACTORS OXYGENATED FUN WITH LESS CARBON COST KELLY MARTIN AND SANDEEP SATHYAMOORTHY MEMBRANE AERATED BIOFILM REACTORS OXYGENATED FUN WITH LESS CARBON COST KELLY MARTIN AND SANDEEP SATHYAMOORTHY AGENDA Background Commercialized Technology Concept Evaluation 2 BACKGROUND 3 THE MABR PROVIDES

More information

DISCUSSION PAPER. 1 Objective. 2 Design Flows and Loads. Capital Regional District Core Area Wastewater Management Program

DISCUSSION PAPER. 1 Objective. 2 Design Flows and Loads. Capital Regional District Core Area Wastewater Management Program DISCUSSION PAPER Capital Regional District Core Area Wastewater Management Program Macaulay/McLoughlin Point Wastewater Treatment Plant Discussion Paper Liquid Process Alternatives Evaluation 034-DP-1

More information

2015 Spring Conference

2015 Spring Conference 2015 Spring Conference Meeting Strict Summer Permit Requirements on Day One: Start-up of the Western Wake Regional Water Reclamation Facility Chris White, PE April 13, 2015 Acknowledgements Town of Cary

More information

Onsite treatment of higher-load graywater by membrane bioreactor

Onsite treatment of higher-load graywater by membrane bioreactor Onsite treatment of higher-load graywater by membrane bioreactor Aileen HUELGAS Candidate for the Degree of Doctor of Philosophy in Engineering Supervisor: Professor Naoyuki Funamizu Division of Built

More information

MBRs The Future of Wastewater Treatment PURON MBR. Tim Jordan KMS Midwest RSM

MBRs The Future of Wastewater Treatment PURON MBR. Tim Jordan KMS Midwest RSM MBRs The Future of Wastewater Treatment PURON MBR Tim Jordan KMS Midwest RSM Koch Membrane Systems We are a global leader in membrane filtration technology We have been in business for half a century,

More information

Pilot Studies on Performance of Membrane Bio-Reactor in Treating Hong Kong Freshwater and Saline Sewage and Its Virus Rejection Ability and Mechanism

Pilot Studies on Performance of Membrane Bio-Reactor in Treating Hong Kong Freshwater and Saline Sewage and Its Virus Rejection Ability and Mechanism Pilot Studies on Performance of Membrane Bio-Reactor in Treating Hong Kong Freshwater and Saline Sewage and Its Virus Rejection Ability and Mechanism G. H. Chen and C. Shang The Hong Kong University of

More information

2015 HDR, Inc., all rights reserved.

2015 HDR, Inc., all rights reserved. 2015 HDR, Inc., all rights reserved. Hastings Utilities Water Pollution Control Facility Improvements Brian Bakke, HDR ASCE Environmental Conference 4/6/2017 Review Existing Facilities Need for the Project

More information

FURTHER EXPANDED FLOWS AND LOADS R3 INDUSTRIAL WWTP PROCESS ENGINEERING EVALUATION

FURTHER EXPANDED FLOWS AND LOADS R3 INDUSTRIAL WWTP PROCESS ENGINEERING EVALUATION FURTHER EXPANDED FLOWS AND LOADS R3 INDUSTRIAL WWTP PROCESS ENGINEERING EVALUATION Prepared For: HyLife Foods Neepawa, Manitoba, Canada Prepared By: Pharmer Engineering 1998 West Judith Lane Boise, ID

More information

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS:

City of Redlands Wastewater Treatment Plant. Redlands, CA LOCATION: Carollo Engineers; CH2M HILL MBR MANUFACTURER: COMMENTS: FACILITY: City of Redlands Wastewater Treatment Plant LOCATION: Redlands, CA GEO. AREA: Southern California STATUS 07/14: Operational CONSTRUCTION: ENGINEERING: Carollo Engineers; CH2M HILL MBR MANUFACTURER:

More information

UDWQ POTW Nutrient Removal Cost Impact Study: Analysis of Tremonton City Wastewater Treatment Plant

UDWQ POTW Nutrient Removal Cost Impact Study: Analysis of Tremonton City Wastewater Treatment Plant TECHNICAL MEMORANDUM UDWQ POTW Nutrient Removal Cost Impact Study: Analysis of Tremonton City Wastewater Treatment Plant PREPARED FOR: PREPARED BY: COPIES: Utah Division of Water Quality CH2M HILL DATE:

More information

Choices to Address Filamentous Growth

Choices to Address Filamentous Growth Michigan Water Environment Association Process Seminar November 12, 2015 Choices to Address Filamentous Growth Richard Beardslee City of Battle Creek Nathan Cassity Donohue & Associates Outline Battle

More information

The Application of Low Energy MBR in Landfill Leachate Treatment

The Application of Low Energy MBR in Landfill Leachate Treatment The Application of Low Energy MBR in Landfill Leachate Treatment Antony Robinson, Wehrle Environmental Abstract Cross-flow Membrane Bioreactor (MBR) is a leachate treatment technology that has seen widespread

More information

Energy efficient submerged UF/MF system utilizing reciprocating inertia for wastewater treatment

Energy efficient submerged UF/MF system utilizing reciprocating inertia for wastewater treatment Energy efficient submerged UF/MF system utilizing reciprocating inertia for wastewater treatment Jaeho Ho, Shaleena Smith, Gyu Dong Kim and Hyung Keun Roh Doosan Hydro Technology, Tampa, USA Why Membrane

More information

We Know Water. NEOSEP Membrane Bioreactor (MBR) WATER TECHNOLOGIES

We Know Water. NEOSEP Membrane Bioreactor (MBR) WATER TECHNOLOGIES We Know Water NEOSEP Membrane Bioreactor (MBR) WATER TECHNOLOGIES Veolia s NEOSEP MBR NEOSEP combines the best attributes of hollow fiber and flat sheet membranes with the use of hybrid FibrePlate membranes

More information

SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES

SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES Oxidation ditches are very popular wastewater treatment processes for small to medium sized municipalities that

More information

Commissioning and Operation of a 50 mgd Ultrafiltration Advanced Reclamation Facility for Gwinnett County, Georgia

Commissioning and Operation of a 50 mgd Ultrafiltration Advanced Reclamation Facility for Gwinnett County, Georgia Commissioning and Operation of a 50 mgd Ultrafiltration Advanced Reclamation Facility for Gwinnett County, Georgia ABSTRACT Robert A. Bergman*, Richard Porter**, Don Joffe***, Ed Minchew**** * CH2M HILL

More information

APPENDIX D.1 IFAS PRELIMINARY COST ESTIMATE

APPENDIX D.1 IFAS PRELIMINARY COST ESTIMATE APPENDIX D.1 IFAS PRELIMINARY COST ESTIMATE IFAS Treatment Process Alternative Opinion of Probable Construction Cost Opinion of Probable Construction Costs VTSV WWTF IFAS Treatment Process Division Description

More information

Membrane Bioreactor and High Flow Biological Treatment System for the Cox Creek WRF

Membrane Bioreactor and High Flow Biological Treatment System for the Cox Creek WRF Membrane Bioreactor and High Flow Biological Treatment System for the Cox Creek WRF Thor Young, GHD With Contributions from Vince Maillard, Rip Copithorn, Kristi Perri, and Jeff Sturdevant, GHD Dimitrios

More information

Long-Term Activated Sludge Treatment in MBR for Industrial Wastewater Treatment

Long-Term Activated Sludge Treatment in MBR for Industrial Wastewater Treatment International Journal of Engineering and Applied Sciences (IJEAS) Long-Term Activated Sludge Treatment in MBR for Industrial Wastewater Treatment AL-Saadi Anmar Joudah, Gabriel Racoviteanu Abstract Membrane

More information

INTEGRITY AND PERFORMANCE EVALUATION OF NEW GENERATION DESALTING MEMBRANES DURING MUNICIPAL WASTEWATER RECLAMATION

INTEGRITY AND PERFORMANCE EVALUATION OF NEW GENERATION DESALTING MEMBRANES DURING MUNICIPAL WASTEWATER RECLAMATION INTEGRITY AND PERFORMANCE EVALUATION OF NEW GENERATION DESALTING MEMBRANES DURING MUNICIPAL WASTEWATER RECLAMATION ABSTRACT James DeCarolis*, Samer Adham, Manish Kumar, Bill Pearce, Larry Wasserman *MWH

More information

Dr Martin Peter *, Joachim Scholz & Victor Ferre. Contents

Dr Martin Peter *, Joachim Scholz & Victor Ferre. Contents Feedback from a metal processing industry MBR Plant in its 3rd Year of Operation:- An Analysis of the Flux, Effluent Quality and Membrane Lifetime Data to date Authors: Dr Martin Peter *, Joachim Scholz

More information

Comparative study of MBR and activated sludge in the treatment of paper mill wastewater

Comparative study of MBR and activated sludge in the treatment of paper mill wastewater Comparative study of MBR and activated sludge in the treatment of paper mill wastewater M. Lerner*, N. Stahl** and N.I. Galil* *Department of Civil and Environmental Engineering, Technion Israel Institute

More information

BIOSPHERE MOVING BED BIOLOGICAL SYSTEMS

BIOSPHERE MOVING BED BIOLOGICAL SYSTEMS REACTION TANKS BIOSPHERE MOVING BED BIOLOGICAL SYSTEMS PROVEN FIXED-FILM TECHNOLOGY IDEAL FOR BNR UPGRADES AND CAPACITY EXPANSIONS. SAME FOOTPRINT, BETTER TREATMENT AT NEPTUNE BEACH, FL WWTP Without adding

More information

MEMBRANE BIOREACTOR NIHAR DOCTOR. Director

MEMBRANE BIOREACTOR NIHAR DOCTOR. Director TM MEMBRANE BIOREACTOR NIHAR DOCTOR Director en-vısı n Enviro Technologies Pvt. Ltd. (Pollution Control Consultants & Engineers) Shree Ram Complex, 2 nd Floor, Above Bank Of India, Near Kargil Chowk, Surat

More information

Facilities Plan. Volume 2 Wastewater Facilities Assessment Report Executive Summary

Facilities Plan. Volume 2 Wastewater Facilities Assessment Report Executive Summary City of St. Joseph, Missouri Volume 2 Wastewater Facilities Assessment Report Executive Summary By Work Order No. 09-001 B&V Project 163509 October 29, 2010 Table of Contents 1.0 Introduction...1 2.0 TM-WW-1:

More information

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ENHANCING THE PERFORMANCE OF OXIDATION DITCHES Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ABSTRACT Oxidation ditches are very popular wastewater treatment

More information

AQUASMART - Water and Wastewater Treatment Solutions

AQUASMART - Water and Wastewater Treatment Solutions AQUASMART - Water and Wastewater Treatment Solutions A Reconversão de ETAR existentes em Unidades Geradoras de Recursos The Conversion of existing WWTPs to Resource Generating Units Luís Marinheiro DI(FH)

More information

Integrated Fixed Film Activated Sludge (IFAS) System for Additional Nitrification at the Coldwater WWTP

Integrated Fixed Film Activated Sludge (IFAS) System for Additional Nitrification at the Coldwater WWTP Fishbeck, Thompson, Carr & Huber, Inc. Integrated Fixed Film Activated Sludge (IFAS) System for Additional Nitrification at the Coldwater WWTP Jim Flamming, P.E., Senior Process Engineer, FTC&H Dave Woodman,

More information

Domestic wastewater reclamation by submerged membrane bioreactor with high concentration powdered activated carbon for stream restoration

Domestic wastewater reclamation by submerged membrane bioreactor with high concentration powdered activated carbon for stream restoration Domestic wastewater reclamation by submerged membrane bioreactor with high concentration powdered activated carbon for stream restoration G.T. Seo*, H.I. Ahan*, J.T. Kim*, Y.J. Lee* and I.S. Kim** * Department

More information

Can MBR Eliminate Additional Disinfection? A Case Study. Ufuk Erdal, PhD, PE, CH2M Jonathan Vorheis, PE, CH2M July 17, 2015

Can MBR Eliminate Additional Disinfection? A Case Study. Ufuk Erdal, PhD, PE, CH2M Jonathan Vorheis, PE, CH2M July 17, 2015 Can MBR Eliminate Additional Disinfection? A Case Study Ufuk Erdal, PhD, PE, CH2M Jonathan Vorheis, PE, CH2M July 17, 2015 2 Acknowledgement We sincerely thank to co-authors for their valuable contribution

More information

1/11/2016. Types and Characteristics of Microorganisms. Topic VI: Biological Treatment Processes. Learning Objectives:

1/11/2016. Types and Characteristics of Microorganisms. Topic VI: Biological Treatment Processes. Learning Objectives: Topic VI: Biological Treatment Processes Learning Objectives: 1. Discuss microbiology and relate it to wastewater treatment. 2. Describe growth kinetics of pure bacterial culture with Monod expression

More information

OBG WASTE MANAGEMENT PRESENTS: 18 th Annual New England Pretreatment Coordinators Workshop (October 27, 2016) Landfill Leachate Overview Mark Greene,

OBG WASTE MANAGEMENT PRESENTS: 18 th Annual New England Pretreatment Coordinators Workshop (October 27, 2016) Landfill Leachate Overview Mark Greene, OBG WASTE MANAGEMENT PRESENTS: 18 th Annual New England Pretreatment Coordinators Workshop (October 27, 2016) Landfill Leachate Overview Mark Greene, Ph.D., P.E. OBG Anne Reichert, P.E. WM AGENDA Leachate

More information

UPGRADING FOR TOTAL NITROGEN REMOVAL WITH A POROUS MEDIA IFAS SYSTEM

UPGRADING FOR TOTAL NITROGEN REMOVAL WITH A POROUS MEDIA IFAS SYSTEM UPGRADING FOR TOTAL NITROGEN REMOVAL WITH A POROUS MEDIA IFAS SYSTEM T. Masterson, J. Federico, G. Hedman, S. Duerr BETA Group, Inc. 6 Blackstone Valley Place Lincoln, Rhode Island 02865 ABSTRACT The Westerly,

More information

Reclaimed Waste Water for Power Plant Cooling Tower Water & Boiler Feed Make-up. Richard Coniglio, Business Product Manager

Reclaimed Waste Water for Power Plant Cooling Tower Water & Boiler Feed Make-up. Richard Coniglio, Business Product Manager Reclaimed Waste Water for Power Plant Cooling Tower Water & Boiler Feed Make-up Richard Coniglio, Business Product Manager 70% Covered with Water 3% is Fresh Water 1% of the Fresh Water is only accessible.

More information

Increasing Denitrification in Sequencing Batch Reactors with Continuous Influent Feed

Increasing Denitrification in Sequencing Batch Reactors with Continuous Influent Feed Increasing Denitrification in Sequencing Batch Reactors with Continuous Influent Feed ABSTRACT In this study, the denitrification capacity of a continuous influent feed sequencing batch reactor (SBR) was

More information