1 US EPA Roundtable Research Triangle Park By: Richard A. Hovan Sr., QEP Date: December 05, 2016

2 SPECIFICATIONS AND TEST PROCEDURES FOR PREDICTIVE EMISSION MONITORING SYSTEMS IN STATIONARY SOURCES Major Sources most effected by PS-16 Stationary Gas Turbines Industrial, Commercial, Institutional Steam Generating Units Performance Specification 16 will neither apply to existing PEMS nor those covered under Subpart E of 40 CFR part 75. Part 75 is the Acid Rain Market trading program monitoring requirements Subpart E is the monitoring criteria for Alternative Monitoring Systems

3 Harmonization of Part 75; Subpart-E Part 75 is the Acid Rain Market trading program monitoring requirements Subpart E is the monitoring criteria for Alternative Monitoring Systems (AMS) Currently (until 3/15) required that all AMS applications perform monthly CGAs or equivalent tests to provide acceptable system validation of accuracy March 2015 ruling by CAMD specific to PEMS PEMS are to be able to provide validation testing for Part 75 applications according to PS-16 standards This was approved for a facility in Arkansas with 7 Combined Cycle GTs

4 Initial Relative Accuracy Test Audit (RATA) Third Party Testing Company Quarterly Relative Accuracy Audit (RA) Portable Analyzer Test Yearly Relative Accuracy Test Audit (RATA) Third Party Testing Company

5 Initial Relative Accuracy Test Audit (RATA) Measurand >100ppm = 10% RA Measurand 10ppm 100ppm = 20% Measurand < 10ppm = +/- 2ppm Quarterly Relative Accuracy Audit (RAA) Measurand >100ppm = 10% RA Measurand 10ppm 100ppm = 20% Measurand < 10ppm = +/- 2ppm Yearly Relative Accuracy Test Audit (RATA) Measurand >100ppm = 10% RA Measurand 10ppm 100ppm = 20% Measurand < 10ppm = +/- 2ppm

6 PS-16 has been written for NO X and O 2 only PEMS has evolved and now does SO 2 CO 2 CO H X C Y (specific) and THC States have been imposing standard Part 60 analyzer accuracies on tester analyzers and PEMS for emissions other than NO X

7 States have been imposing standard Part 60 analyzer accuracies on tester analyzers and PEMS for emissions other than NO X CO is the issue and needs harmonization A little History Late 90s to early 2000s tests where run by CARB on low level CO sample-line absorption ~1ppm absorption and random off-gas occurred Final results was Low level testing limitations CO for 5ppm and less; the analyzer only has to be +1ppm

8 States have been imposing standard Part 60 analyzer accuracies on tester analyzers and PEMS for emissions other than NO X CO is the issue and needs harmonization Final results was Low level testing limitations CO for 5ppm and less; the analyzer only has to be +1ppm PEMS required to meet 20% for all gases (NO X to follow PS-16) If CO is 2ppm then PEMS CO would have to meet an RATA of 0.4ppm Certifying with a tester instrument that only has to meet a +1ppm on a 2ppm reading Doable but difficult PS-16 must be changed to include all primary pollutants for the same test accuracies

9 8.3 Statistical Tests for PEMS that are Used for Continual Compliance. In addition to the RA determination, evaluate the paired RA and PEMS data using the following statistical tests Bias Test. From the RA data taken at the mid-level, determine if a bias exists between the RM and PEMS. (Use the equations in PS-16,Section ) F-test. Perform a separate F-test for the RA paired data from each operating level to determine if the RM and PEMS variances differ by more than might be expected from chance. (Use the equations in PS-16, Section ) Correlation Analysis. Perform a correlation analysis using the RA paired data from all operating levels combined to determine how well the RM and PEMS correlate. (Use the equations in PS-16, Section The correlation is waived if the process cannot be varied to produce a concentration change sufficient for a successful correlation Correlation Analysis. Calculate the correlation coefficient either manually (as per PS-16 Eq.16-8) or by computing all of the paired data points from all operating levels. The PEMS correlation must be 0.8% or greater to be acceptable If Auto-correlation is determined during initial certification test then the correlation analysis is permanently waived Auto-correlated according to 40CFR 75.41(b)(2) procedures If signal-to-noise ratio of the data is less than 4.

10 Initial RATA Once at initial system certification Quarterly RAA 3 consecutive Quarterly Audits (1 st year) If 1 st year RAAs and Yearly RATA pass then RAAs can be reduced to 6 month intervals. Yearly RATA Yearly at the completion of the 4 th Quarter

11 RM Tests for Excess Emission PEMS. For PEMS used for excess emission reporting, conduct at least 3, 21 minute runs of RM tests at the following key parameter operating levels: Low Load (minimum - 50%) Mid Load (50% - 80%) High Load (80% - 100%) RM Tests for Continual Compliance PEMS. For PEMS used to determine compliance, conduct at least 9, 21 minute runs of RM tests at the following key parameter operating levels: Low Load (minimum - 50%) Mid Load (50% - 80%) High Load (80% - 100%)

12 RM for Quarterly RA 3, 21 minute runs with portable analyzer Each run at 3 equidistant traverse points across measurement point Each traverse point averaged for 7 minutes Simultaneously record PEMS data and calculate RAA

13 RM Tests for Excess Emission PEMS. For PEMS used for excess emission reporting, conduct at least 3, 21 minute runs of RM tests at the following key parameter operating levels: Normal Operating Load RM Tests for Continual Compliance PEMS. For PEMS used to determine compliance, conduct at least 9, 21 minute runs of RM tests at the following key parameter operating levels: Normal Operating Load

14 PS-16RM Tests for Excess Emission PEMS For PEMS used for excess emission reporting, conduct at least 3, 21 minute runs of RM tests at the following key parameter operating levels: Normal Operating Load RM Tests for Continual Compliance PEMS. For PEMS used to determine compliance, conduct at least 9, 21 minute runs of RM tests at the following key parameter operating levels: Normal Operating Load

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2025

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2025 SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT COMPLIANCE DEPARTMENT COM 2025 APPROVED: SIGNED DATE: June 14, 2007 Jon Adams Director of Compliance TITLE: SUBJECT: RULE 1080 STACK MONITORING

More information

CEM Istanbul, 14 th May 2014

CEM Istanbul, 14 th May 2014 Predictive Emission Monitoring (PEM): Suitability and Application in View of U.S. EPA and European Regulatory Frameworks CEM 2014 - Istanbul, 14 th May 2014 Thomas Eisenmann Dr. Roland Bianchin David Triebel

More information

Part 60 vs. Part 75 RATA Testing Requirements. Bob Finken President Delta Air Quality Services, Inc. Orange, California

Part 60 vs. Part 75 RATA Testing Requirements. Bob Finken President Delta Air Quality Services, Inc. Orange, California Part 60 vs. Part 75 RATA Testing Requirements Bob Finken President Delta Air Quality Services, Inc. Orange, California RATA IS.. Relative Accuracy is the absolute mean difference between the CEMS and the

More information

Predictive Emissions Monitoring Systems (PEMS) What You Need to Know

Predictive Emissions Monitoring Systems (PEMS) What You Need to Know Predictive Emissions Monitoring Systems (PEMS) What You Need to Know Council of Industrial Boiler Owners March 8, 2017 Lauren Laabs Mostardi Platt Purpose of the Presentation What are PEMS? How are PEMS

More information

Advanced Monitoring Solution. Monitoring System (PEMS) as a Complete. Cogeneration Facility in the U.S.

Advanced Monitoring Solution. Monitoring System (PEMS) as a Complete. Cogeneration Facility in the U.S. Field Demonstration of a Cost-Effective Advanced Monitoring Solution Deployment of a Predictive Emissions Monitoring System (PEMS) as a Complete Compliance Solution for a Large Cogeneration Facility in

More information

Advanced Emission Monitoring for Compliance in the U.S.

Advanced Emission Monitoring for Compliance in the U.S. Advanced Emission Monitoring for Compliance in the U.S. A Cost-effective Advanced Monitoring Solution - Deployment of Predictive Emissions Monitoring System (PEMS) as a Compliance Solution for Gas Turbine

More information

data systems CEM International Conference and Exhibition on Emissions Monitoring

data systems CEM International Conference and Exhibition on Emissions Monitoring Predictive Emission Monitoring (PEM): Suitability and Application in View of U.S. EPA and European Regulatory Frameworks Thomas Eisenmann 1, Dr. Roland Bianchin 2 & David Triebel 1 Contents Abstract...

More information

DAILY LIFE of CEMS QA & PM

DAILY LIFE of CEMS QA & PM DAILY LIFE of CEMS QA & PM Presented at: ENVIRONMENTAL COMMITTEE TECHNICAL FOCUS GROUP December 8, 2015 DANIEL L. TODD, QEP, CHMM OVERALL CONCEPT To provide the perspective of the folks that are responsible

More information

ECMPS Reporting Instructions Quality Assurance and Certification

ECMPS Reporting Instructions Quality Assurance and Certification ECMPS Reporting Instructions Quality Assurance and Certification United States Environmental Protection Agency Office of Air and Radiation Clean Air Markets Division 1310 L Street, NW Washington, DC 20005

More information

Common CEMS RATA Failures and Risks. Paula Metz Alliance Source Testing, LLC Technical Services Assistant Manager

Common CEMS RATA Failures and Risks. Paula Metz Alliance Source Testing, LLC Technical Services Assistant Manager Common CEMS RATA Failures and Risks Paula Metz Alliance Source Testing, LLC Technical Services Assistant Manager Introduction Stack Testing is a labor and time intensive process and requires thorough planning

More information

Control Chart Methodology for Detecting Under-reported Emissions

Control Chart Methodology for Detecting Under-reported Emissions Control Chart Methodology for Detecting Under-reported Emissions Introduction: EPA uses the control chart methodology described in this paper to analyze the CO2 concentration data recorded at coal-fired

More information

ECMPS Reporting Instructions Quality Assurance and Certification

ECMPS Reporting Instructions Quality Assurance and Certification ECMPS Reporting Instructions Quality Assurance and Certification United States Environmental Protection Agency Office of Air and Radiation Clean Air Markets Division 1201 Constitution Ave, NW Washington,

More information

Review of ConocoPhillips Alaska Inc. Continuous Emissions Monitoring Data from a 2014 Drill Rig Study at Kuparuk Drill Site 2N

Review of ConocoPhillips Alaska Inc. Continuous Emissions Monitoring Data from a 2014 Drill Rig Study at Kuparuk Drill Site 2N Alaska Department of Environmental Conservation Air Quality Division Review of ConocoPhillips Alaska Inc. Continuous Emissions Monitoring Data from a 2014 Drill Rig Study at Kuparuk Drill Site 2N October

More information

TITLE V OPERATING PERMIT STATEMENT OF BASIS

TITLE V OPERATING PERMIT STATEMENT OF BASIS Facility Name: Title V Permit No.: Permit Application Nos.: Site ID: Equipment Address: Goal Line, L.P. APCD2016-TVP-00043 APCD2016-APP-004597 APCD1992-SITE-08447 555 North Tulip Street Escondido, CA 92025

More information

Lars K. Gram. FORCE Technology. The Danish EPA's Reference Laboratory for Air Emission Monitoring.

Lars K. Gram. FORCE Technology. The Danish EPA's Reference Laboratory for Air Emission Monitoring. Lars K. Gram FORCE Technology The Danish EPA's Reference Laboratory for Air Emission Monitoring LKG@Force.dk 1 Title: International regulation on emission monitoring Sub title: How to implement PEMS as

More information

REDUCE FLOW BIAS THROUGH AUTOMATED TESTING

REDUCE FLOW BIAS THROUGH AUTOMATED TESTING REDUCE FLOW BIAS THROUGH AUTOMATED TESTING PRESENTED AT: THE 20 TH ANNUAL ELECTRIC UTILITY CHEMISTRY WORKSHOP AT THE UNIVERSITY OF ILLINOIS MAY 9 11, 2000 CLARION HOTEL AND CONVENTION CENTER CHAMPAIGN,

More information

AIR EMISSION PERMIT NO IS ISSUED TO. LSP - Cottage Grove LP

AIR EMISSION PERMIT NO IS ISSUED TO. LSP - Cottage Grove LP AIR EMISSION PERMIT NO. 16300087-003 IS ISSUED TO LSP - Cottage Grove LP LSP COTTAGE GROVE COGENERATION FACILITY 9525 105th Street Court South Cottage Grove, Washington County, MN 55016 The emission units,

More information

Proposed Guidelines for the Reduction of Nitrogen Oxide Emissions from Natural Gas fuelled Stationary Combustion Turbines

Proposed Guidelines for the Reduction of Nitrogen Oxide Emissions from Natural Gas fuelled Stationary Combustion Turbines Proposed Guidelines for the Reduction of Nitrogen Oxide Emissions from Natural Gas fuelled Stationary Combustion Turbines Environment and Climate Change Canada May 2016 Table of Contents 1. Foreword...

More information

SANTA BARBARA COUNTY AIR POLLUTION CONTROL DISTRICT POLICIES AND PROCEDURES. Policy No Draft Div Pol Yr

SANTA BARBARA COUNTY AIR POLLUTION CONTROL DISTRICT POLICIES AND PROCEDURES. Policy No Draft Div Pol Yr SANTA BARBARA COUNTY AIR POLLUTION CONTROL DISTRICT POLICIES AND PROCEDURES Policy No. 6100.058.2016 Draft Div Pol Yr Supersedes No. 6100.058.2004 Final x Div Pol Yr Date: August 25, 2016 Pages 7 Topic:

More information

CEM. Continuous Emission Monitoring Systems NACT 221. Course Overview. National Air Compliance Training. CEM implementing regulations

CEM. Continuous Emission Monitoring Systems NACT 221. Course Overview. National Air Compliance Training. CEM implementing regulations National Air Compliance Training Continuous Emission Monitoring Systems NACT 221 Course Overview CEM implementing regulations CEM basic theory and operation CEM system components System certification requirements

More information

Best Practices Learned from Greenhouse Gas Reporting

Best Practices Learned from Greenhouse Gas Reporting Best Practices Learned from Greenhouse Gas Reporting A&WMA s 110 th Annual Conference & Exhibition Pittsburg, Pennsylvania June 5-8, 2017 Extended Abstract # 264587 Cassandra B. Drotman, Raymond H. Huff

More information

Nitric Acid Production Project Protocol Version 1.0 ERRATA AND CLARIFICATIONS

Nitric Acid Production Project Protocol Version 1.0 ERRATA AND CLARIFICATIONS Nitric Acid Production Project Protocol Version 1.0 ERRATA AND CLARIFICATIONS The Climate Action Reserve (Reserve) published its Nitric Acid Production Project Protocol Version 1.0 in December 2009. While

More information

09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural

09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural 09/30/2010 Waterside Power Redline Version: Matt Lydon Formatted: Font: Bold, Italic Formatted: Font: Bold, Italic Draft Model Rule Control of Natural Gas and Distillate Oil Fired HEDD Combustion Turbine

More information

Notice of Intent to Create

Notice of Intent to Create Notice of Intent to Create Date: November 9, 2004 Proponent: Proponent Contact: Standard Method: Project Location: Whitby Cogeneration 1550 Wentworth St. W. Whitby, Ontario L1N 7C1 Brent Gibson Chief Operation

More information

NSPS for Dc Boilers Burning Residual Oil

NSPS for Dc Boilers Burning Residual Oil Minnesota Pollution Control Agency AQ Doc. # 8.07 February 1998 Facts about NSPS for Dc Boilers Burning Residual Oil In an effort to regulate new sources of air pollution and ensure that those sources

More information

CONSTRUCTION PERMIT. Public Service Company

CONSTRUCTION PERMIT. Public Service Company COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT AIR POLLUTION CONTROL DIVISION TELEPHONE: (303) 692-3150 PERMIT NO: DATE ISSUED: ISSUED TO: CONSTRUCTION PERMIT 12AD2345 Public Service Company THE

More information

SHASTA COUNTY DEPARTMENT OF RESOURCE MANAGEMENT AIR QUALITY MANAGEMENT DISTRICT

SHASTA COUNTY DEPARTMENT OF RESOURCE MANAGEMENT AIR QUALITY MANAGEMENT DISTRICT EXPIRATION DATE: January 3, 2020 PERMIT NO: 03-TV-02 SHASTA COUNTY DEPARTMENT OF RESOURCE MANAGEMENT AIR QUALITY MANAGEMENT DISTRICT City of Redding, Redding Power Plant (Applicant) IS HEREBY GRANTED A

More information

Mercury and Air Toxics Standards (MATS) Completion of Electronic Reporting Requirements

Mercury and Air Toxics Standards (MATS) Completion of Electronic Reporting Requirements This document is scheduled to be published in the Federal Register on 09/29/2016 and available online at https://federalregister.gov/d/2016-21330, and on FDsys.gov 6560-50-P ENVIRONMENTAL PROTECTION AGENCY

More information

STATEMENT OF BASIS Mannington Mills, Inc. dba Mannington Wood Floors Epes, Sumter County, Alabama Facility/Permit No

STATEMENT OF BASIS Mannington Mills, Inc. dba Mannington Wood Floors Epes, Sumter County, Alabama Facility/Permit No STATEMENT OF BASIS Mannington Mills, Inc. dba Mannington Wood Floors Epes, Sumter County, Alabama Facility/Permit No. 412-0011 This draft initial Title V Major Source Operating Permit (MSOP) is issued

More information

Procedure Z: Quality Assurance Requirements for X-Ray-Fluorescence Based Multi-Metals Continuous Emission Monitoring Systems at Stationary Sources

Procedure Z: Quality Assurance Requirements for X-Ray-Fluorescence Based Multi-Metals Continuous Emission Monitoring Systems at Stationary Sources Procedure Z: Quality Assurance Requirements for X-Ray-Fluorescence Based Multi-Metals Continuous Emission Monitoring Systems at Stationary Sources June 9, 2005 Submitted to: The Environmental Protection

More information

ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR

ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR White paper WP/ANALYTICAL/002 EN ABB Measurement & Analytics Monitoring cement plant stack emissions using FTIR ABB FTIR CEMS analyzer successfully monitors cement plant stack emissions in extensive field

More information

PRELIMINARY AUTHORITY TO CONSTRUCT

PRELIMINARY AUTHORITY TO CONSTRUCT PRELIMINARY ISSUED BY: DATE ISSUED: SEPTEMBER XX, 2018 JORGE DeGUZMAN DATE EXPIRES: SEPTEMBER XX, 2020 ISSUED TO: SACRAMENTO MUNICIPAL UTILITY DISTRICT FINANCING AUTHORITY (SFA) COSUMNES POWER PLANT LOCATION:

More information

Part XXIII Stage 2 Disinfection Byproducts

Part XXIII Stage 2 Disinfection Byproducts Part XXIII Stage 2 Disinfection Byproducts 2301 GENERAL REQUIREMENTS A. General. The regulations in this part establish monitoring and other requirements for achieving compliance with maximum contaminant

More information

All Carbon All the Time

All Carbon All the Time All Carbon All the Time Ralph L. Roberson, P.E. RMB Consulting & Research, Inc. Two-Part Presentation Regulatory Overview and Update EPA s proposed new source performance standards Status of CO 2 rule

More information

Title V. Model General Permit Template SERIES 2 LOADING RACKS. Template # SJV-LR-2-1

Title V. Model General Permit Template SERIES 2 LOADING RACKS. Template # SJV-LR-2-1 Title V Model General Permit Template SERIES 2 LOADING RACKS Template # SJV-LR-2-1 Organic liquid loading racks Facilities loading 4,000 or more, but less than 20,000 gallons of an organic liquid on any

More information

Engineering Summary UNH Cogeneration Project Fall 2003, Durham, NH

Engineering Summary UNH Cogeneration Project Fall 2003, Durham, NH 1 Engineering Summary UNH Cogeneration Project Fall 2003, Durham, NH Application #: FY04-0148 AFS #: 3301700009 County: Strafford Engineer: Laughton Date: Late Fall 2003 The University of New Hampshire

More information

Final Essential Requirements of Mandatory Reporting Amendments for Harmonization of Reporting in Canadian Jurisdictions

Final Essential Requirements of Mandatory Reporting Amendments for Harmonization of Reporting in Canadian Jurisdictions Final Essential Requirements of Mandatory Reporting 2011 Amendments for Harmonization of Reporting in Canadian Jurisdictions Amended February 10, 2012 to include #7 in the list of errata changes 1 Introduction...

More information

ARKANSAS DEPARTMENT OF POLLUTION CONTROL AND ECOLOGY DIVISION OF AIR POLLUTION CONTROL. Summary Report Relative to Permit Application

ARKANSAS DEPARTMENT OF POLLUTION CONTROL AND ECOLOGY DIVISION OF AIR POLLUTION CONTROL. Summary Report Relative to Permit Application ARKANSAS DEPARTMENT OF POLLUTION CONTROL AND ECOLOGY DIVISION OF AIR POLLUTION CONTROL Summary Report Relative to Permit Application Submitted By: Ash Grove Cement Company Highway 108 West P.O. Box 130

More information

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT DRAFT STAFF REPORT

SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT DRAFT STAFF REPORT SAN JOAQUIN VALLEY UNIFIED AIR POLLUTION CONTROL DISTRICT DRAFT STAFF REPORT Proposed Revision to State Implementation Plan (SIP) to Address Federal Clean Air Act Requirements for Reasonably Available

More information

UPDATE ON NORTH AMERICAN EMISSIONS REGULATIONS FOR ELECTRIC POWER. Tim Cresswell Tier 4 Product Definition Manager Electric Power Division

UPDATE ON NORTH AMERICAN EMISSIONS REGULATIONS FOR ELECTRIC POWER. Tim Cresswell Tier 4 Product Definition Manager Electric Power Division Tim Cresswell Tier 4 Product Definition Manager Electric Power Division December 2011 INTRODUCTION In 2010, a number of changes and proposals influenced U.S. Environmental Protection Agency (EPA) regulations

More information

ECMPS Reporting Instructions Emissions

ECMPS Reporting Instructions Emissions ECMPS Reporting Instructions Emissions United States Environmental Protection Agency Office of Air and Radiation Clean Air Markets Division 1201 Constitution Ave, NW Washington, DC 20004 December 16September

More information

Final Mandatory Greenhouse Gases Reporting Rule. Overview

Final Mandatory Greenhouse Gases Reporting Rule. Overview Final Mandatory Greenhouse Gases Reporting Rule Overview 1 Agenda Outline Background Purpose of Rule Key Elements of Rule Assessing Applicability Special Provisions for 2010 Confidential Business Information

More information

LDAR Case Study Comparison of Conventional Method 21 vs Alternative Work Practice (Optical Gas Imaging) Terence Trefiak P.E.

LDAR Case Study Comparison of Conventional Method 21 vs Alternative Work Practice (Optical Gas Imaging) Terence Trefiak P.E. IMPROVING SAFETY MAXIMIZING PROFITS REDUCING EMISSIONS MAINTAINING COMPLIANCE LDAR Case Study Comparison of Conventional Method 21 vs Alternative Work Practice (Optical Gas Imaging) Terence Trefiak P.E.

More information

Chapter 9 Emission Measurement, Monitoring & Reporting

Chapter 9 Emission Measurement, Monitoring & Reporting Chapter 9 Emission Measurement, Monitoring & Reporting Editor s Note: Chapter 9 Emissions Measurement and Reporting - is most of Chapter 13 from the 2000 version of APTI 418 written by James A. Jahnke..

More information

Monitoring cement plant stack emissions using FTIR

Monitoring cement plant stack emissions using FTIR ABB MEASUREMENT & ANALYTICS WHITE PAPER Monitoring cement plant stack emissions using FTIR ABB FTIR CEMS analyzer successfully monitors cement plant stack emissions in extensive field study Measurement

More information

CGIAR Consortium Financial Governance Framework

CGIAR Consortium Financial Governance Framework , CB19 CGIAR Consortium Financial Governance Framework This Financial Governance Framework incorporates recommendations from Phase 1 of the CGIAR Governance Review 1 and is based on a recommendation made

More information

Building a Bigger, Better Zero Air Generator Certification Process

Building a Bigger, Better Zero Air Generator Certification Process Building a Bigger, Better Zero Air Generator Certification Process By: Dr. David Sodeman, Ph.D. and Mr. David Roque San Diego Air Pollution Control District 1 The Needs for a Zero Air Generator Certification

More information

Title V. Model General Permit Template SERIES 1 LOADING RACKS. Template # SJV-LR-1-1

Title V. Model General Permit Template SERIES 1 LOADING RACKS. Template # SJV-LR-1-1 Title V Model General Permit Template SERIES 1 LOADING RACKS Template # SJV-LR-1-1 facility which commenced construction or modification after December 17, 1980 loading racks at facility loading greater

More information

Ambient Air Quality Monitoring

Ambient Air Quality Monitoring Ambient Air Quality Monitoring Ambient Air Quality Division Air Quality and Noise Management Bureau Pollution Control Department 7/31/2012 2:09 PM 1 Carbon Monoxide (CO) Nitrogen Dioxide (NO 2 ) Ozone

More information

SANTA BARBARA COUNTY AIR POLLUTION CONTROL DISTRICT POLICIES AND PROCEDURES. Policy No Draft Div Pol Yr

SANTA BARBARA COUNTY AIR POLLUTION CONTROL DISTRICT POLICIES AND PROCEDURES. Policy No Draft Div Pol Yr SANTA BARBARA COUNTY AIR POLLUTION CONTROL DISTRICT POLICIES AND PROCEDURES Policy No. 6100.039.1993 Draft Div Pol Yr Supersedes No. Final x Div Pol Yr Date: May 28, 1993 Pages 14 Topic: Permit Requirements

More information

Compliance Measurements. Mike Klein & Robert Kettig BTS (609)

Compliance Measurements. Mike Klein & Robert Kettig BTS (609) Compliance Measurements Mike Klein & Robert Kettig BTS (609) 530-4140 BTS Emission Measurement Section Bureau Chief (vacant) 1 Section Chief 1 Supervisor 5* Staff Professionals + 1-2 part time Consultants

More information

Guidance for Portable Electrochemical Analyzer Testing Used for Compliance Monitoring

Guidance for Portable Electrochemical Analyzer Testing Used for Compliance Monitoring Guidance for Portable Electrochemical Analyzer Testing Used for Compliance Monitoring Section I. Introduction DEQ s Air Quality Division administers the provisions of 40 CFR Part 70 as well as the minor

More information

Measurement and Reporting of Vapor Phase Mercury Emissions, Using a Sorbent Trap Monitoring System (DRAFT 9/25/08)

Measurement and Reporting of Vapor Phase Mercury Emissions, Using a Sorbent Trap Monitoring System (DRAFT 9/25/08) Measurement and Reporting of Vapor Phase Mercury Emissions, Using a Sorbent Trap Monitoring System (DRAFT 9/25/08) 1. Scope and Application The purpose of this protocol is to establish procedures for the

More information

Attachment 2. Quality Assurance and Operating Procedures for Sorbent Trap Monitoring Systems

Attachment 2. Quality Assurance and Operating Procedures for Sorbent Trap Monitoring Systems Attachment 2 Quality Assurance and Operating Procedures for Sorbent Trap Monitoring Systems 1.0 Scope and Application This Attachment specifies sampling, analytical, and quality-assurance criteria and

More information

Method X: Determination of Metal Concentrations in Emissions from Stationary Sources (Instrumental Analyzer Procedure)

Method X: Determination of Metal Concentrations in Emissions from Stationary Sources (Instrumental Analyzer Procedure) Method X: Determination of Metal Concentrations in Emissions from Stationary Sources (Instrumental Analyzer Procedure) June 7, 2005 Submitted to: The Environmental Protection Agency Research Triangle Park,

More information

ENTERPRISE REFRIGERANT MANAGEMENT

ENTERPRISE REFRIGERANT MANAGEMENT ENTERPRISE REFRIGERANT MANAGEMENT A unified refrigerant management system can save you millions in regulatory fines and equipment upgrades. Commercial cooling equipment is critical to your business but

More information

EMISSION MEASUREMENT TECHNICAL INFORMATION CENTER NSPS TEST METHOD. Method 10 - Determination of Carbon Monoxide Emissions from Stationary Sources

EMISSION MEASUREMENT TECHNICAL INFORMATION CENTER NSPS TEST METHOD. Method 10 - Determination of Carbon Monoxide Emissions from Stationary Sources EMISSION MEASUREMENT TECHNICAL INFORMATION CENTER NSPS TEST METHOD Method 10 - Determination of Carbon Monoxide Emissions from Stationary Sources 1. PRINCIPLE AND APPLICABILITY 1.1 Principle. An integrated

More information

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company AIR EMISSION PERMIT NO. 05300015-002 ADMINISTRATIVE AMENDMENT IS ISSUED TO Northern States Power Company NSP - RIVERSIDE 3100 Marshall Street Northeast Minneapolis, Hennepin County, MN 554181826 The emission

More information

Data Certification Exercise

Data Certification Exercise Data Certification Exercise PQAO Training January 25 th, 2017 Objective: The data certification process involves certifying that ambient concentration data and quality assurance data for any given year

More information

EPA s Methane Agenda Will the Oil & Gas NSPS OOOOa Regulation Affect Other Sectors? Presented By: Jay Christopher Trihydro Corporation

EPA s Methane Agenda Will the Oil & Gas NSPS OOOOa Regulation Affect Other Sectors? Presented By: Jay Christopher Trihydro Corporation EPA s Methane Agenda Will the Oil & Gas NSPS OOOOa Presented By: Jay Christopher Trihydro Corporation Why Should Other Sectors Care About Oil & Gas NSPS Requirements? Methane is not a big issue to us,

More information

PC MACT Updates. Cemtek Environmental Emissions Monitoring Seminar Costa Mesa, CA September 28, Vineet Masuraha Trinity Consultants Irvine, CA

PC MACT Updates. Cemtek Environmental Emissions Monitoring Seminar Costa Mesa, CA September 28, Vineet Masuraha Trinity Consultants Irvine, CA PC MACT Updates Cemtek Environmental Emissions Monitoring Seminar Costa Mesa, CA September 28, 2016 Vineet Masuraha Trinity Consultants Irvine, CA Agenda 1. Introduction 2. Overview of the applicable AQ

More information

Guest Speaker: Bill Frietsche US EPA

Guest Speaker: Bill Frietsche US EPA Guest Speaker: Bill Frietsche US EPA 1 April 7: QA Systems, EPA definitions, PQAOs and common sense Mike Papp April 14: Routine Quality Control and Data Management (1-pt QC, flow rate, and instrument stability

More information

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company

AIR EMISSION PERMIT NO ADMINISTRATIVE AMENDMENT IS ISSUED TO. Northern States Power Company AIR EMISSION PERMIT NO. 16300005-003 ADMINISTRATIVE AMENDMENT IS ISSUED TO Northern States Power Company NSP - ALLEN S KING GENERATING PLANT 1103 King Plant Road Bayport, Washington County, MN 55003 The

More information

SANTA BARBARA COUNTY APCD GUIDANCE DOCUMENT FOR EMISSION VERIFICATION OF CONTAMINATED SOIL/GROUNDWATER CLEANUP (CSC) PROCESSES

SANTA BARBARA COUNTY APCD GUIDANCE DOCUMENT FOR EMISSION VERIFICATION OF CONTAMINATED SOIL/GROUNDWATER CLEANUP (CSC) PROCESSES SANTA BARBARA COUNTY APCD GUIDANCE DOCUMENT FOR EMISSION VERIFICATION OF CONTAMINATED SOIL/GROUNDWATER CLEANUP (CSC) PROCESSES I. INTRODUCTION To insure compliance, each "Contaminated Soil/Groundwater

More information

DEPARTMENT OF QUANTITATIVE METHODS & INFORMATION SYSTEMS

DEPARTMENT OF QUANTITATIVE METHODS & INFORMATION SYSTEMS DEPARTMENT OF QUANTITATIVE METHODS & INFORMATION SYSTEMS Time Series and Their Components QMIS 320 Chapter 5 Fall 2010 Dr. Mohammad Zainal 2 Time series are often recorded at fixed time intervals. For

More information

Implementation of EPA s Mandatory GHG Reporting Requirements

Implementation of EPA s Mandatory GHG Reporting Requirements Implementation of EPA s Mandatory GHG Reporting Requirements Rural Counties ESJPA Board and Technical Advisory Meeting March, 2010 Sacramento, CA Raymond H. Huff, R.E.A. SCS Engineers Speaker Bio Raymond

More information

Environmental Policies. Bruce Rising Siemens Westinghouse

Environmental Policies. Bruce Rising Siemens Westinghouse Environmental Policies Bruce Rising Siemens Westinghouse 12 Mar 2001 Overview Gas turbine technology will continue to be play a critical role in US energy needs. Air quality improvements have been substantial,

More information

Advances in NOx Compliance Testing with Portable Electrochemical Analyzers

Advances in NOx Compliance Testing with Portable Electrochemical Analyzers Advances in NOx Compliance Testing with Portable Electrochemical Analyzers LADCO Workshop: Emission Control and Measurement Technology for Industrial Sources March 24-25, 2009 Craig McKim, Emission Division

More information

Naughton Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by

Naughton Power Plant. Chapter 6, Section 2 Construction Permit Application. Submitted to the Wyoming Air Quality Division And Prepared by Naughton Power Plant Chapter 6, Section 2 Construction Permit Application Submitted to the Wyoming Air Quality Division And Prepared by 1407 West North Temple Salt Lake City, Utah 84116 March 2008 1.0

More information

Presented by: Danny Hintzman Luminant Power Company. Fall User Group 2015

Presented by: Danny Hintzman Luminant Power Company. Fall User Group 2015 Presented by: Danny Hintzman Luminant Power Company Fall User Group 2015 A good overall tool for determining what is recertification and what is Diagnostic: Recertification, Diagnostic, and Maintenance

More information

AIR EMISSION PERMIT NO IS ISSUED TO Minnesota Power & Light

AIR EMISSION PERMIT NO IS ISSUED TO Minnesota Power & Light AIR EMISSION PERMIT NO. 13700013-001 IS ISSUED TO Minnesota Power & Light MINNESOTA POWER AND LIGHT - LASKIN ENERGY County Road 110 and 633 Aurora, St. Louis County, Minnesota 55705 The emission units,

More information

Software CEM Advanced Emissions Monitoring

Software CEM Advanced Emissions Monitoring Software CEM Advanced Emissions Monitoring Pavilion8 Software CEM is a predictive emissions monitoring system (PEMS), developed on the Pavilion8 platform, which provides highly accurate measurements of

More information

Business Quantitative Analysis [QU1] Examination Blueprint

Business Quantitative Analysis [QU1] Examination Blueprint Business Quantitative Analysis [QU1] Examination Blueprint 2014-2015 Purpose The Business Quantitative Analysis [QU1] examination has been constructed using an examination blueprint. The blueprint, also

More information

Air Division. Emissions Test Protocol And Test Report Requirements

Air Division. Emissions Test Protocol And Test Report Requirements Air Division Emissions Test Protocol And Test Report Requirements May 18, 2018 Introduction The purpose of this document is to provide guidance for test protocols and reporting stack tests under the jurisdiction

More information

A2LA. R231 Specific Requirements: Threat Agent Testing Laboratory Accreditation Program. December 6, 2017

A2LA. R231 Specific Requirements: Threat Agent Testing Laboratory Accreditation Program. December 6, 2017 Laboratory Page 1 of 17 Laboratory December 6, 2017 2017 by A2LA All rights reserved. No part of this document may be reproduced in any form or by any means without the prior written permission of A2LA.

More information

A G. The Avogadro Group, LLC. Air Quality Consulting and Source Emissions Testing

A G. The Avogadro Group, LLC. Air Quality Consulting and Source Emissions Testing A G The Avogadro Group, LLC Air Quality Consulting and Source Emissions Testing ALL THESE TEST RESULTS ARE THE SAME POLLUTANT FROM THE SAME BOILER!! Different test methods CAN = different results! Recent

More information

SYCAMORE COGENERATION PROJECT (84-AFC-6C)

SYCAMORE COGENERATION PROJECT (84-AFC-6C) STATE OF CALIFORNIA NATURAL RESOURCES AGENCY EDMUND G. BROWN JR., Governor CALIFORNIA ENERGY COMMISSION 1516 NINTH STREET SACRAMENTO, CA 95814-5512 www.energy.ca.gov DATE: October 13, 2011 TO: FROM: Interested

More information

The Use of CAMD Data for Air Quality Modeling

The Use of CAMD Data for Air Quality Modeling The Use of CAMD Data for Air Quality Modeling David J. Long, PE American Electric Power Service Corporation Presented At 11 th USEPA Triennial Modeling Conference Research Triangle Park, NC August 13,

More information

Comparison Continuous Emission Monitoring Techniques

Comparison Continuous Emission Monitoring Techniques PRODUCT DATASHEET: Comparison Continuous Comparison Continuous Emission Monitoring Techniques Overview The requirements for continuous emission monitors has changed significantly over the last 30 years.

More information

UCSD DEPARTMENT KEY CONTROLS DOCUMENTATION All Control Activities Sorted by Frequency

UCSD DEPARTMENT KEY CONTROLS DOCUMENTATION All Control Activities Sorted by Frequency Accounting Period: Department/Division: Department Key Controls must be documented in such a fashion to demonstrate the review and follow-up activities were performed. Certain Financial Link tools can

More information

Author: Donald Pretty, Project Manager, Presenter: John Downs, Environmental Manager, B&W PGG, KVB-Enertec Products January 29, 2015

Author: Donald Pretty, Project Manager, Presenter: John Downs, Environmental Manager, B&W PGG, KVB-Enertec Products January 29, 2015 Author: Donald Pretty, Project Manager, Presenter: John Downs, Environmental Manager, B&W PGG, KVB-Enertec Products January 29, 2015 May 2007 Rule was proposed as an amendment to the NSPS Subpart J Rule

More information

RATA/Compliance Testing. Judith Aasland

RATA/Compliance Testing. Judith Aasland RATA/Compliance Testing Judith Aasland jaasland@montrose-env.com October 1, 2014 Overview RATAs/Compliance Tests ASTM D7036 Standard: Source Testing Accreditation Protocol Gas Verification Program (PGVP)

More information

TUV Certified FTIR CEM and Ultra Low Level HCl CEM for Combustion Facilities

TUV Certified FTIR CEM and Ultra Low Level HCl CEM for Combustion Facilities TUV Certified FTIR CEM and Ultra Low Level HCl CEM for Combustion Facilities CEM 2014 May 15-17, 2014 Istanbul, Turkey Peter G. Zemek MultiGas FT-IR Automated HCl CEM Systems MKS Instruments On-Line Product

More information

PRINTABLE VERSION. Quiz 11

PRINTABLE VERSION. Quiz 11 You scored 0 out of 100 Question 1 PRINTABLE VERSION Quiz 11 As the length of the confidence interval for the population mean decreases, the degree of confidence in the interval's actually containing the

More information

*** DRAFT - NOT YET FILED ***

*** DRAFT - NOT YET FILED *** *** DRAFT - NOT YET FILED *** 3745-36-10 Alternative conditions specific to categorical industrial users. [Comment: For dates of non-regulatory government publications, publications of recognized organizations

More information

Revision: 67. Prepared by

Revision: 67. Prepared by PJM Manual 11: Energy & Ancillary Services Market Revision: 67 Effective Date: June 1, 2014 Prepared by Forward Market PJM 2014 i Section 9: Hourly Scheduling Section 4: Overview of the PJM Synchronized

More information

TITLE V PERMIT APPLICATION APPLICATION COMPLETENESS CHECK LIST

TITLE V PERMIT APPLICATION APPLICATION COMPLETENESS CHECK LIST SHELBY COUNTY HEALTH DEPARTMENT POLLUTION CONTROL 814 JEFFERSON AVENUE MEMPHIS, TN 38105 Telephone: (901) 222-9599 FAX: (901) 222-9550 APC 35 TITLE V PERMIT APPLICATION APPLICATION COMPLETENESS CHECK LIST

More information

EPEA Approval Industrial Monitoring Documentation Submission Naming Guideline

EPEA Approval Industrial Monitoring Documentation Submission Naming Guideline EPEA Approval Industrial Monitoring Documentation Submission Naming Guideline Industrial Monitoring Submission Guideline Please note: Italicized words in the naming conventions are optional

More information

Lab 7 Measurement of Ozone

Lab 7 Measurement of Ozone Georgia Institute of Technology School of Earth and Atmospheric Sciences EAS 4641 Spring 2007 Lab 7 Measurement of Ozone Purpose of Lab 7: In this lab you will measure the ambient concentration of ozone

More information

FUNCTIONAL SAFETY CERTIFICATE

FUNCTIONAL SAFETY CERTIFICATE FUNCTIONAL SAFETY CERTIFICATE This is to certify that the 80 series proximity switch manufactured by Topworx, Inc. 3300 Fern Valley Road Louisville Kentucky 40213 USA has been assessed by with reference

More information

SUPPLEMENT TO PERMIT NO Connolly North America, Inc Oakland Park Boulevard Highland Park, Michigan August 10, 2000

SUPPLEMENT TO PERMIT NO Connolly North America, Inc Oakland Park Boulevard Highland Park, Michigan August 10, 2000 SUPPLEMENT TO PERMIT NO. 309-99 Connolly North America, Inc. 12225 Oakland Park Boulevard Highland Park, Michigan 48203 GENERAL CONDITIONS 1. Rule 201(1) - The process or process equipment covered by this

More information

Heat, cooling and power from a single unit

Heat, cooling and power from a single unit Heat, cooling and power from a single unit Simple. Economic. Environmentally Compatible. Heat, Cooling & Power. All in one. Is that possible? The Solution. A CHP Plant with a Micro Gas Turbine. Combined

More information

California s Revised Mandatory Greenhouse Gas Reporting Regulation

California s Revised Mandatory Greenhouse Gas Reporting Regulation California s Revised Mandatory Greenhouse Gas Reporting Regulation Extended Abstract #65 Y. Anny Huang, Doug Thompson, David Edwards, and Patrick Gaffney California Air Resources Board, 1001 I Street,

More information

Title 40 Code of Federal Regulations NSPS 60, Subpart WWW Checklist for Conditions and Requirements Municipal Solid Waste Landfills (MSWLF)

Title 40 Code of Federal Regulations NSPS 60, Subpart WWW Checklist for Conditions and Requirements Municipal Solid Waste Landfills (MSWLF) Check the most Appropriate Answer and fill in the blanks as appropriate. 40 CFR 60.750 Applicability, designation of affected facility, and delegation of authority see separate checklist for Applicability

More information

Measurement and Reporting of Vapor Phase Mercury Emissions from Low-Emitting Stationary Sources (DRAFT 9/25/08)

Measurement and Reporting of Vapor Phase Mercury Emissions from Low-Emitting Stationary Sources (DRAFT 9/25/08) Measurement and Reporting of Vapor Pase Mercury Emissions from Low-Emitting Stationary Sources (DRAFT 9/25/08) 1. Scope and Application Te purpose of tis protocol is to establis procedures for te measurement

More information

Balanced Scorecard Usage Survey 2010

Balanced Scorecard Usage Survey 2010 Balanced Scorecard Usage Survey 2010 Summary of findings 2GC Limited, 2010. All rights reserved. This document is licensed under a Creative Commons License. You are free to copy, distribute, display, and

More information

Chapter 10 Inspecting Combustion Sources

Chapter 10 Inspecting Combustion Sources Chapter 10 Inspecting Combustion Sources Editor s Note: Chapter 10 Inspecting Combustion Sources This section was written by Chuck Solt and is updated from material in the NOx Emissions course presented

More information

Inspecting Combustion Sources

Inspecting Combustion Sources Chapter 10 Inspecting Combustion Sources Editor s Note: Chapter 10 Inspecting Combustion Sources This section was written by Chuck Solt and is updated from material in the NOx Emissions course presented

More information

CHLORITE, BROMATE, AND CHLORINE DIOXIDE MONTHLY OPERATING REPORT

CHLORITE, BROMATE, AND CHLORINE DIOXIDE MONTHLY OPERATING REPORT CHLORITE, BROMATE, AND CHLORINE DIOXIDE MONTHLY OPERATING REPORT Division of Drinking and Ground Waters PUBLIC WATER SYSTEM INFORMATION PWS Name: STU Name: PWS #: STU #: LABORATORY INFORMATION Analytical

More information

RULE 344. PETROLEUM SUMPS, PITS AND WELL CELLARS. (Adopted 11/10/1994) 1. The provisions of this rule shall not apply to spill containments.

RULE 344. PETROLEUM SUMPS, PITS AND WELL CELLARS. (Adopted 11/10/1994) 1. The provisions of this rule shall not apply to spill containments. RULE 344. PETROLEUM SUMPS, PITS AND WELL CELLARS. (Adopted 11/10/1994) A. Applicability This rule applies to sumps, pits and well cellars at facilities where petroleum is produced, gathered, separated,

More information