A New Connection Concept to Connect an Offshore Wind Park to an Onshore Grid

Size: px
Start display at page:

Download "A New Connection Concept to Connect an Offshore Wind Park to an Onshore Grid"

Transcription

1 A New Connection Concept to Connect an Offshore Wind Park to an Onshore Grid Marc VAN DYCK, Shantanu DASTIDAR and Kristof VAN BRUSSELEN CG Holdings Belgium NV Systems Division, Mechelen, Belgium Tel: +32 (0) Fax: +32 (0) Topics: Wind Power, Transportation and distribution Power System Abstract The rapid increase of power generation from renewable energy sources, in particular wind energy, is posing considerable challenges to the power utility grids. Previously when smaller wind turbines and wind parks were built and connected to a local grid, a fault on the network resulted in the disconnection of these wind turbines. However, as the size of these wind parks are getting bigger and bigger, any disconnection of these wind parks would cause serious stability problems in the grid. This necessitates the transmission system operator (TSO) to impose certain connection conditions for connecting these large wind parks to the grid. These conditions, amongst others shall be: supply of reactive power, limiting the voltage fluctuation and the fault ride through capability. In this paper a new connection method, used for the offshore wind park Belwind, in the North-Sea, in front of the Belgian coast, will be presented. Index Terms grid code, grid connection, reactive power, voltage control, offshore wind farm 1. Introduction Over the past few years, the amount of installed electricity generation capacity from wind energy is rapidly increasing. Previously, there were small, single onshore turbines connected to the distribution grid at different locations. Presently, the large wind parks, mostly offshore, are being connected at one point in the transmission grid. The installation of these offshore wind parks, with the aggregate output power of a single offshore wind park comparable to the output of a conventional electricity generation plant, necessitated strict connection requirements [1] in order to maintain the stability of the grid. This paper will give a short description of presently used technique to do the interconnection of an offshore wind park to an onshore grid and compare this technique with the new connection technique used in the Belwind project. The focus of the new technique will be on the reactive power requirements and switch-in transients. Some information about reactive power compensation and grid requirements for various wind turbine types is given in [2], [3] and [4]. 2. Presently used connection method The standard concept to connect offshore wind turbines to the onshore transmission grid is shown in Fig. 1. All turbines are connected in a few strings on a medium voltage level, between 20 and 33 kv (depending on the size of the turbines and the wind park), to the offshore high voltage substation (OHVS). In this OHVS the medium voltage is transformed to a high voltage level between 132 and 220 kv. The step-up transformer is equipped with an on-load tap changer and is responsible for the voltage regulation. The offshore substation also contains high voltage switchgear for the outgoing export cable. At the connection point of the high voltage switchgear with the export cable, the short-circuit current is almost equal to the short-circuit current in the transmission grid. The reactive power regulation (as required by the grid code for large wind parks), is done onshore. Onshore reactors, capacitor banks and Static VAR Compensators are connected to the high voltage level so that the generating plant (wind park) capability curve meets the requirements of the grid code. Fig. 1. Basic concept to connect an offshore wind park to the onshore grid for the Belwind project. To compensate the voltage and current transients when switching in the export cable, onshore high voltage resistors along with high voltage switchgear are used. The resistors are switched in to temporary raise the impedance thereby limiting the inrush current. 3. Belwind The new connection concept was developed for 1

2 the Belwind wind farm. In the following paragraphs a short description of the project and the most important grid code requirements are given Short project description The Belwind wind park is located in the North Sea, in front of the Belgian coast. The total output power of the first phase of the park is 165 MW. It consists of 55 turbines of 3 MW, of type VESTAS type V90. These wind turbines are equipped with doubly-fed induction generators. All turbines are connected at 33 kv level to the offshore high voltage substation (OHVS) by means of 33kV array cables. In this substation a 3-winding transformer steps up the voltage to 150 kv. The offshore substation is located at a distance of around 45 km from the landing point at the beach in Zeebrugge, Belgium. and not the total output power of the wind farm. In case the network operator does not ask a strong capacitive reactive power delivery, the wind farm is allowed to absorb a small amount of inductive reactive power. When all turbines are out of service, the wind park is treated as a consumer and the reactive power should be between and of the total maximum output power of the wind farm. Fig. 3 shows the required and allowed reactive power delivery in function of the output power. The curve is shifted to the capacitive side in order to make the inductive compensation of the export cable as small as possible and still meeting the grid requirements. The wind farm must be able to meet these reactive power requirements for grid voltages between 90 % and 105 % of the operating voltage (which is 155 kv for 150 kv lines). In Zeebrugge the wind farm will finally be connected to the Belgian 150 kv transmission system, operated by Elia the TSO. Construction and commissioning of this wind farms was completed in December Fig. 2 shows a picture of the OHVS after offshore installation on its monopole foundation. Fig. 3. Minimum reactive power requirements in function of the total output power of the wind turbines in service [ELIA] Fig. 2. Picture of the installed offshore high voltage substation 3.2. Elia grid code requirements The Belwind wind farm is connected to the Belgian grid, so all connection requirements stated by the Belgian grid operator, Elia, have to be fulfilled. The full grid code can be found in [5]. In this section the most important requirements are highlighted. A production plant with the size of the Belwind wind park is treated by Elia like a regulating unit (or conventional power plant). The Belgian grid code states that a regulating production unit should always be able to absorb or deliver a minimum reactive power between -0.1 P nom and 0.45 P nom. The nominal power (P nom ) is equal to the maximum output power of the number of turbines in service, 4. The Belwind connection principle The concept for the new connection technique used for the Belwind project is shown in Fig. 4. In this concept, there is no static VAR compensator onshore. The required plant capability curve, given by the transmission system operator is met by using: a) the reactive power of the export cable, b) the regulating capabilities of the wind turbines and c) the installation of offshore reactors. However, compared to the basic concept of Fig. 2, the changes are described in the following paragraphs. An onshore booster transformer is added. This transformer is a series-compensated autotransformer 150/150 kv and has 2 main functions. The most important function is the voltage regulation of the 33 kv offshore grid. In order to benefit from the reactive power capabilities of the wind turbines, this voltage needs to be constant with only small deviations (+/-1 %) of the nominal voltage. To limit the switch-in current (from the export cable capacitive loading / transformer inrush) and voltage transients occurring when the onshore high voltage 2

3 breaker is closed, this transformer is also equipped with a soft-closing device. This device will be connected to an internal circuit on medium voltage. different reactors connection states is necessary. For this reason the two reactors (one on each medium voltage winding of the 3-winding step-up transformer) can be switched in in two steps. The main controller also controls the tap changer of the onshore booster transformer in order to keep the medium voltage level constant. A simplified version of the control system architecture is shown in Fig. 5. Fig. 4. New concept to connect an offshore wind park to the onshore grid used for the Belwind project. The offshore step-up transformer has a fixed transformation ratio. This makes the transformer more reliable and lowers the need for maintenance because there is no on-load tap changer. There is no offshore high voltage switchgear / circuit breaker. The onshore booster transformer with soft-closing feature makes it possible to switch in the export cable and offshore step-up transformer at the same time without causing excessive transients. With the conventional connection method this has to be done separately and even then, the charging of the export cable still causes larger disturbances compared to this new concept. The onshore compensation equipment (SVC, reactors, capacitors) is moved to the offshore high voltage substation. However, only reactors are needed. When the grid requests an amount of capacitive reactive power, this will be supplied by the export cable by disconnecting the reactors. Smaller reactive power changes will be compensated by the doubly fed induction generator inside the wind turbines. The reactors will not be connected at 150kV level but at 33kV. This reduces their size and their noise production. 6. Advantages The new connection concept used for the Belwind wind farm has a number of advantages compared with the standard connection principle. This section describes the most important advantages Reduction of short circuit current The use of a booster transformer in the onshore substation gives a large reduction in short circuit current on the export cable and on the high voltage offshore substation (up to one fourth of the initial current). This makes it possible to use cables and switchgear with a lower rating. For the export cable, the lower earth fault current could, for example, result in a cable with a smaller metallic screen section Use of offshore reactors The placement of the reactors offshore has the advantage that these reactors can be connected on medium voltage level. This makes them smaller.. Another advantage is that switching phenomena will be damped by the export cable and less visible for the onshore grid. 5. Control philosophy To control the wind park, the grid operator, Elia gives a reference voltage and reference reactive power output to the operator of the wind park. With these values and the actually measured voltage a reference MVAR value for the whole wind park is calculated. The wind park control system uses this value to control the reactive power of the individual wind turbines and to switch in or disconnect the reactors. The reactive power regulating capability of the doubly fed induction generators of the wind turbines will be used first. When these generators reach the limit of their control range, the control range is shifted into the opposite direction by switching in or disconnecting the reactors. To avoid a lot of switching of the reactors, enough overlap between the regulating range of the turbines and the Fig. 5. Belwind wind farm control system for reactive power and voltage control 6.3. Soft-closing The soft-closing feature has the dual advantage of minimizing the transients during switching in of the export cable and offshore transformer but also makes some part of the offshore high voltage switchgear not necessary. Because the export cable and the offshore step-up can be energized at the same time, there is no need to install a high voltage circuit breaker on the 3

4 offshore platform. This results in an easier platform design and a lower maintenance cost Onshore voltage regulation The regulation of the system voltage by means of the onshore booster transformer has also some advantages compared to offshore voltage regulation. The voltage on the export cable will remain constant, resulting in a constant production of reactive power. This simplifies the control logic. The maintenance cost will be lower as well. Because the offshore step-up transformer has a fixed turn ratio and no moving parts this transformer needs less maintenance. Off course the booster transformer (and especially the on-load tap changer) will need maintenance, but it is much cheaper to do this on an onshore location. When the grid voltage is different from the export cable voltage, an onshore transformer substation is always needed. In this case the transformer can be upgraded to a booster transformer with soft closing without a large extra cost. As can be seen from Fig. 6, the grid code requirements are completely covered when a different amount of reactors is in service. Even without reactor switching and with all reactors in service, the requirements are almost met by the regulating capabilities of the turbines. In this case, reactor switching will only be necessary for high output power. However, absorbing inductive power becomes increasingly difficult because of the limitations of the voltage regulation by the booster transformer. The numbers on the curve indicate the tap changer position of the booster transformer. For the lowest yellow curve the tap changer will be on his lowest tap ratio but the voltage on 33kV will not remain between +/- 1 % of the nominal value. Because of this deviation, the wind turbines can absorb less inductive power. This effect is shown in the light blue curve CAP-LIM of Fig Simulation and calculation results This section shows some simulation and calculation results obtained for some scenarios that could occur when the wind farm is in service. In all simulated situations is shown that the connection complies with grid code requirements Capability curves The capability curves for the wind park where calculated for 3 different grid voltages: kv, 155 kv and kv (or 90, 100 and 105%). Fig. 6 and 7 give the curves for the low and high voltage case respectively. For each case the capability curve is calculated for the 3 reactors positions (switched off, half power and fully active) and displayed in yellow. The grid code requirements are indicated in deep blue and turquoise. Fig. 7. Calculated capability curves for the Belwind project at high grid voltage for different reactors in operation compared with the grid code requirements For the high grid voltage, grid code requirements will be met except at high output power and a high demand to deliver inductive power. Again the voltage regulation of the booster transformer will run into its limits (tap position 115), resulting in smaller capabilities of the turbines, as shown in the light blue line of Fig. 7. Because this is only a small deviation it will be accepted by the grid operator. Fig. 6. Calculated capability curves for the Belwind project at low grid voltage for different reactors in operation compared with the grid code requirements At nominal operating voltage of 155 kv, the voltage regulation of the booster transformer will be able to keep the 33 kv voltage constant. This makes it easier to comply with the grid code requirements. As can be seen from previous figures, at active power output levels between 20 and 80%, the wind park will be able to deliver or absorb more reactive power than the grid code requires. In this output power range, it can also be seen that there is a large overlap between the curves for different amounts of reactors in service. The chance that reactors will continuously switch in and out will be very small. 4

5 7.2. Active power variation Simulations show that changes in active power output will only have a small effect on the tap changer position of the booster and the switching of reactors. A variation of the output power from 160 MW to 0 MW was simulated for different amount of reactive power output. Fig. 8 gives an example of this calculation for 0 MVAR reactive power output. No reactors are switched and the tap changer only moves three steps. Other simulations give the same result. It can be concluded that active power variations will not have a large influence on the switching behavior. power rates of the wind farm. Fig. 9 gives the result of the first case at a 100 % active power output. In the beginning of the simulation the two reactors (4 parts) are in service. When the voltage starts to drop, the requested amount of capacitive reactive power delivery to grid rises. First this will be compensated by the wind turbines but after a certain time the turbines will reach their limit and the first part of the two reactors will be switched off. When the voltage keeps on dropping, some time later also the second part of the two reactors will be switched off. At that time the reactive power delivery to the Elia grid will be around 75 MVAR, which is a little bit more than required. When the voltage rises again, the first part of the reactors will be switched in again. It is important to see that the second part will not be switched in again, because of the overlap between the different reactor quantities in service. This result confirms that the number of switching operations will be limited. Fig. 8. Voltage and reactive power variation when active power drops from 160 MW to 0 MW (including tap changer position changes of booster) with no delivery of reactive power to the grid 7.3. Reactor switching In order to fully comply with the grid code requirements some reactor switching will be necessary. It is important to know the voltage variations this switching will cause. Simulations done in the case of a low short circuit power in the grid have shown that when 2 reactors are fully tripped, the 150 kv grid voltage will only change with a value of around 0.7 %. The temporary variations on the 33kV level will be a bit higher (+/- 3.5 %), but will have no effect on the booster tap changer positions because this tap changer action is delayed. The voltage variations due to reactors switching will be small Voltage regulation To test the reaction of the new connection type to voltage variations different simulations were done: Slow voltage drop to minimal voltage followed by a low voltage rise back to nominal voltage Slow voltage rise to maximal voltage followed by a slow voltage drop back to nominal voltage Voltage step drop of 4 % Voltage step rise of 4 % Each simulation was done for different output Fig. 9. Reaction of the MVAr regulation (reactors and WTG) on a slow voltage drop of the grid with output power equal to 100% For other percentages of the output power, results will be equivalent. The reactive power delivered to support the voltage in these cases will be much higher than the minimum requirement from the grid code. In the case of a voltage slope to the maximal voltage, results are comparable as well, but here in all cases the reactive power support will be higher than requested. It can also be noticed that in the simulated cases reactor switching will not be necessary, as the wind turbines will be able to adjust the reactive power output. In Fig. 10, results are presented for a step voltage rise of 4 % with an output power of the wind park of 50 % and all reactors in service. In this case the reactors remain in service and the wind turbines will absorb the reactive power. The voltage support to the grid will again be much larger than the minimum requirements stated in the grid code. 5

6 requires a strong voltage support from wind farms, simulations done on the connection technique prove it will be able to comply with these requirements. The proposed technique makes it possible to connect a relatively high amount of wind power with an AC-connection to shore. Fig. 10. Reaction of the MVAr regulation (reactors and WTG) on a step voltage rise of the grid of 4 % with output power of the wind farm equal to 50% 8. Conclusion The new (patent pending) connection technique used to connect an offshore wind park to an onshore grid, which has been used for the Belwind project, has advantages compared to the standard connection techniques. The need for an extra onshore transformer is compensated by more standard, less maintenance requiring equipment that will be used offshore. There is no need for a high voltage circuit breaker and a tap changer in the offshore transformer. This makes the installation more reliable and needing less maintenance offshore, which is expensive. In cases where the export cable will be operated at a different voltage than the grid voltage, the onshore transformer only needs to be upgraded with soft closing. This can be done without large additional cost. Especially in countries where the grid code 9. References [1] A. Arulampalam, G. Ramtharan, N. Jenkins, V.K. Ramachandaramurthy, J.B. Ekanayake and G. Strbac, Trends in Wind Power Technology and Grid Code Requirements, International Conference on Industrial and Information Systems, ICIIS, Aug 9-11, 2007, pp [2] E.H. Camm, M.R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling, M. Edds, W.J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S.V. Pasupulati, N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke and R. Walling, "Reactive Power Compensation for Wind Power Plants," IEEE Power & Energy Society General Meeting, 2009 [3] E.H. Camm, M.R. Behnke, O. Bolado, M. Bollen, M. Bradt, C. Brooks, W. Dilling, M. Edds, W.J. Hejdak, D. Houseman, S. Klein, F. Li, J. Li, P. Maibach, T. Nicolai, J. Patiño, S.V. Pasupulati, N. Samaan, S. Saylors, T. Siebert, T. Smith, M. Starke and R. Walling, "Characteristics of Wind Turbine Generators for Wind Power Plants," IEEE Power & Energy Society General Meeting, 2009 [4] I. Erlich, W. Winter and A. Dittrich, Advanced Grid Requirements for the Integration of Wind Turbines into the German Transmission System, IEEE Power Engineering Society General Meeting 2006 [5] Belgian Royal Decree of concerning the technical rules for the operation and access to the Belgian transmission network, Belgisch staatblad/moniteur Belge, Ed. 6

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE CHENNAI INDIAN WIND GRID CODE Rajesh Katyal Unit Chief, R&D Centre for Wind Energy Technology OVERVIEW NEED FOR INDIAN WIND GRID CODE Wind energy constitutes 6% of the installed capacity in the power scenario

More information

Transmission Losses Report 2015

Transmission Losses Report 2015 SP Energy Networks October 2015 Transmission Losses Report 2015 1. INTRODUCTION Special condition 2K of SPT s transmission licence requires SPT to publish an annual transmission losses report detailing

More information

ISSN Vol.07,Issue.16, November-2015, Pages:

ISSN Vol.07,Issue.16, November-2015, Pages: ISSN 2348 2370 Vol.07,Issue.16, November-2015, Pages:3181-3185 www.ijatir.org Improvement of Power Quality in A Grid Connected Induction Generator Based Wind Farm using Static Compensator K. YOSHMA 1,

More information

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm SYNOPSIS OF THE THESIS Enhanced Power Quality Management of Grid Connected Wind Farm INTRODUCTION OF THE THESIS Faster depletion of fossil fuels and environmental damage has resulted into increased use

More information

DECISION 1 SCOPE AND CONSIDERATIONS... 2

DECISION 1 SCOPE AND CONSIDERATIONS... 2 MEMORANDUM TO Windfarm developers DATE November 02, 2018 FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) v2 DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed:

More information

Daniel Feltes Phone: Fax:

Daniel Feltes Phone: Fax: Coordination of Controls of Renewable Power Plants to Meet Steady State and Dynamic Response Requirements for Voltage Control and Reactive Power Supply Dinemayer Silva Phone: 518-395-5169 Fax: 518-346-2777

More information

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 1 Presentation Overview Joint Working Group The Issue Structure of the Report Wind Plant Configuration Wind Turbine Generators

More information

DECISION 1 SCOPE AND CONSIDERATIONS... 2

DECISION 1 SCOPE AND CONSIDERATIONS... 2 MEMORANDUM TO Windfarm developers FROM TenneT TSO SUBJECT Overplanting - version: Hollandse Kust (zuid) DECISION FOR INFORMATION ONLY QUALITY CONTROL Prepared: Daniël Vree Reviewed: Frank de Vries 19.09.2017

More information

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms In 2010, offshore wind farms accounted for 9.5% of the overall

More information

Technical and economical analysis of the wind turbines interconnection with the windfarm substation

Technical and economical analysis of the wind turbines interconnection with the windfarm substation Technical and economical analysis of the wind turbines interconnection with the windfarm substation NICOLAE COROIU Faculty of Electrical Engineering and Industrial Management University of Oradea Oradea,

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

End-to-end electrical solutions for the biggest challenges involved with connecting wind energy to the grid. Solutions for Wind Energy Integration

End-to-end electrical solutions for the biggest challenges involved with connecting wind energy to the grid. Solutions for Wind Energy Integration End-to-end electrical solutions for the biggest challenges involved with connecting wind energy to the grid Solutions for Wind Energy Integration There are lots of challenges involved in harnessing the

More information

Wind Farm Performance on the Grid: Perception and Reality

Wind Farm Performance on the Grid: Perception and Reality Wind Farm Performance on the Grid: Perception and Reality WindVAR and LVRT Data and Graphs provided by Nicholas W. Miller GE Energy, Energy Consulting 1 GE Energy Wind Energy Grid Performance: A Perception

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.1 Voltage level Filename ONL15-058-T1_Voltage level_pp_v1 Version 1 - release for Expert

More information

Impacts of the Decentralized Wind Energy Resources on the Grid

Impacts of the Decentralized Wind Energy Resources on the Grid 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Impacts of the Decentralized Wind Energy Resources on the Grid Babak Enayati, PhD, Senior

More information

Transmission Losses Report 2017

Transmission Losses Report 2017 SP Energy Networks October 2017 Transmission Losses Report 2017 1. INTRODUCTION Special condition 2K of the SP Transmission plc (SPT) transmission licence requires SPT to publish an annual transmission

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

Electric Power Systems An Overview

Electric Power Systems An Overview Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

Large-scale Integration of Distributed Energy Resources within Electric Power Systems. Danish Cell Controller Project Brief

Large-scale Integration of Distributed Energy Resources within Electric Power Systems. Danish Cell Controller Project Brief Large-scale Integration of Distributed Energy Resources within Electric Power Systems Danish Cell Controller Project Brief Project Introduction Energinet.dk Owns/Operates High Voltage Electric Power System

More information

Reactive power and voltage control interaction and optimization in the Danish largest wind power plant at Kriegers Flak

Reactive power and voltage control interaction and optimization in the Danish largest wind power plant at Kriegers Flak Journal of Physics: Conference Series PAPER OPEN ACCESS Reactive power and voltage control interaction and optimization in the Danish largest wind power plant at Kriegers Flak To cite this article: Vladislav

More information

FRT-Testing and Direct TSO-Control of Reactive Power Output of Large Wind Farms

FRT-Testing and Direct TSO-Control of Reactive Power Output of Large Wind Farms FRT-Testing and Direct TSO-Control of Reactive Power Output of Large Wind Farms Peter Van Roy, H. Lemmens, T. Springuel, A. Dabin (Elia) Eckard Quitman (Enercon), Jaap-Jan Ferweda (WindVision) Background

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

Transmission System Security and Planning Standards

Transmission System Security and Planning Standards ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2

More information

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403 AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination

More information

GOLDEN VALLEY ELECTRIC ASSOCIATION

GOLDEN VALLEY ELECTRIC ASSOCIATION October 13, 2008 GOLDEN VALLEY ELECTRIC ASSOCIATION Eva Creek Wind Farm-Limited Study Doubly Fed Asynchronous Generators Power Flow, Reactive Compensation, Transient Stability Revision 0 PROJECT NUMBER:

More information

Principles of modeling large wind parks

Principles of modeling large wind parks Doctoral school of energy- and geo-technology January 16 1 006. Kuressaare Estonia Principles of modeling large wind parks Raivo Attikas doctoral student.c. Tallinn University of Technology Department

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Grid Connection and Power Quality Optimization of Wind Power Plants

Grid Connection and Power Quality Optimization of Wind Power Plants Grid Connection and Power Quality Optimization of Wind Power Plants Fikri Baris UZUNLAR 1, Onder GULER 2, Ozcan KALENDERLI 3 1, 2 Istanbul Technical University, Energy Institute, Istanbul, Turkey barisuzunlar@hotmail.com,

More information

Reactive power and voltage control interaction and optimization in the Danish largest wind power plant at Kriegers Flak

Reactive power and voltage control interaction and optimization in the Danish largest wind power plant at Kriegers Flak Downloaded from orbit.dtu.dk on: Nov 08, 2018 Reactive power and voltage control interaction and optimization in the Danish largest wind power plant at Kriegers Flak Akhmatov, Vladislav; Wu, Qiuwei; Takarics,

More information

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection 7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej

More information

What makes a Wind Plant Grid Friendly?

What makes a Wind Plant Grid Friendly? Stable Renewable Plant Voltage and Reactive Power Control NERC ERSTF June 11-12, 2014 Sebastian Achilles Nicholas Miller Einar Larsen Jason MacDowell GE Energy Consulting 1 / Topics Features of modern

More information

The strongest link. Captive power plant-smelter interface for increased power plant efficiency. Reprint from ABB Review 4/2007

The strongest link. Captive power plant-smelter interface for increased power plant efficiency. Reprint from ABB Review 4/2007 The strongest link Captive power plant-smelter interface for increased power plant efficiency Reprint from ABB Review 4/2007 Power Plant Picture Courtesy by Alstom The strongest link Captive power plant-smelter

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Grid Interconnection Issues for Wind Generation

Grid Interconnection Issues for Wind Generation Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical

More information

Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function

Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function Mariana B. Pereira 1, Sebastian A. Achilles 2, Nath Venkit 2 Energy Consulting General

More information

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO Renewable Energy Impact to Distribution Network Performance and Reliability ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO Presentation Outline 1. RE Integration and changes in the Electric

More information

Integration of Renewable Energy Sources in the Electricity System - Grid Issues -

Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Integration of Renewable Energy Sources in the Electricity System - Grid Issues - Brussels, 30 March 2005 Background At European and national level mid-term plans exist to increase the share of electricity

More information

Mitigation of Voltage Fluctuations in Power System Using STATCOM

Mitigation of Voltage Fluctuations in Power System Using STATCOM RESEARCH ARTICLE OPEN ACCESS Mitigation of Voltage Fluctuations in Power System Using STATCOM M. Venkatesh & Ramakrishna Raghutu Assistant Professors, Dept. of Electrical & Electronics Engineering, GMRIT,

More information

Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks

Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks 1 Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks Linwei Chen, Haiyu Li, Steve Cox, and Kieran Bailey Presented by Dr Haiyu Li haiyu.li@manchester.ac.uk Senior

More information

BASIC CONCEPTS. Yahia Baghzouz Electrical & Computer Engineering Department

BASIC CONCEPTS. Yahia Baghzouz Electrical & Computer Engineering Department BASIC CONCEPTS Yahia Baghzouz Electrical & Computer Engineering Department INSTANTANEOUS VOLTAGE, CURRENT AND POWER, RMS VALUES AVERAGE (REAL) POWER, REACTIVE POWER, APPARENT POWER, POWER FACTOR INSTANTANEOUS

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

Comparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM

Comparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM International Journal of Energy and Power Engineering 2014; 3(6-2): 21-26 Published online November 27, 2014 (http://www.sciencepublishinggroup.com/j/ijepe) doi: 10.11648/j.ijepe.s.2014030602.14 ISSN:

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility Power Quality ssessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility Cheng-Ting Hsu, Member, IEEE Department of Electrical Engineering Southern Taiwan University

More information

TSOs, taking into account the following: Whereas

TSOs, taking into account the following: Whereas All TSOs proposal for a common grid model methodology in accordance with Articles 67(1) and 70(1) of Commission Regulation (EU) 2017/1485 of 02 August 2017 establishing a guideline on electricity transmission

More information

WIND ENERGY GENERATION

WIND ENERGY GENERATION WIND ENERGY GENERATION Modelling and Control Olimpo Anaya-Lara, University of Strathclyde, Glasgow, UK Nick Jenkins, Cardiff University, UK Janaka Ekanayake, Cardiff University, UK Phill Cartwright, Rolls-Royce

More information

VOLTAGE STABILITY LIMITS FOR WEAK POWER SYSTEMS WITH HIGH WIND PENETRATION ALA TAMIMI AN ABSTRACT OF A DISSERTATION

VOLTAGE STABILITY LIMITS FOR WEAK POWER SYSTEMS WITH HIGH WIND PENETRATION ALA TAMIMI AN ABSTRACT OF A DISSERTATION VOLTAGE STABILITY LIMITS FOR WEAK POWER SYSTEMS WITH HIGH WIND PENETRATION by ALA TAMIMI B.S., Jordan University of Science and Technology, 1990 M.S., Wichita State University, Wichita, Kansas, 1993 AN

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Power System Study for Renewable Energy Interconnection in Malaysia

Power System Study for Renewable Energy Interconnection in Malaysia IOP Conference Series: Earth and Environmental Science OPEN ACCESS Power System Study for Renewable Energy Interconnection in Malaysia To cite this article: O F Askar and V K Ramachandaramurthy 2013 IOP

More information

Proposal for categorization of Significant Users

Proposal for categorization of Significant Users Proposal for categorization of Significant Users First step of the iterative process Experts Group - Implementation NCs (session 3) Jonathan Sprooten Power System Operation and Security, Elia 25/02/2016

More information

Enhanced Features of DFIG Wind Energy Converters regarding new Grid Code Requirements

Enhanced Features of DFIG Wind Energy Converters regarding new Grid Code Requirements Enhanced Features of DFIG Wind Energy Converters regarding new Grid Code Requirements Roman Bluhm, Jens Fortmann Repower España S.L., P Castellana 141 - pta 20, 28046 Madrid, Tel.: 0034917893463 E-mail:

More information

Operation of Power Systems with High Shares of Variable Renewables. Manuel Coxe. Progarmme Officer - Grid Integration

Operation of Power Systems with High Shares of Variable Renewables. Manuel Coxe. Progarmme Officer - Grid Integration Operation of Power Systems with High Shares of Variable Renewables Manuel Coxe Progarmme Officer - Grid Integration IRENA Innovation and Technology Centre Similar or Different? STORK STORM AGENDA 1. Transforming

More information

Wind Farms in Weak Grids Compensated with STATCOM

Wind Farms in Weak Grids Compensated with STATCOM Nordic PhD course on Wind Power (June 5-11, 2005) Final Examination Report Ph.D. Candidate: Akarin Suwannarat Supervisors: Birgitte Bak-Jensen Institute of Energy Technology, Aalborg University Pontoppidantstraede

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network Insu Kim, Ronald G. Harley, and Raeey Regassa Georgia Institute of Technology,

More information

CHAPTER 1 OFFSHORE RENEWABLE ENERGY DEVELOPMENT IN THE BELGIAN PART OF THE NORTH SEA

CHAPTER 1 OFFSHORE RENEWABLE ENERGY DEVELOPMENT IN THE BELGIAN PART OF THE NORTH SEA CHAPTER 1 OFFSHORE RENEWABLE ENERGY DEVELOPMENT IN THE BELGIAN PART OF THE NORTH SEA RUMES Bob 1 & BRABANT Robin 2 Royal Belgian Institute of Natural Sciences (RBINS), Operational Directorate Natural Environment

More information

8 th Annual Electric Power Industry Conference

8 th Annual Electric Power Industry Conference 8 th Annual Electric Power Industry Conference STATCOM Application to Address Grid Stability and Reliability: Part I November 11 th, 2013 Authors: Donald Shoup, P.E. and Dr. Gregory Reed Support: Nick

More information

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS Christos KALOUDAS The University of Manchester UK christos.kaloudas@manchester.ac.uk Ben MARSHALL National Grid UK ben.marshall@nationalgrid.com

More information

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs RE integration workshop, Chennai January 23, 2018 Zakir H Rather, IIT Bombay Email: zakir.rather@iitb.ac.in Wind

More information

ELG4126 Distributed Generation and Renewables

ELG4126 Distributed Generation and Renewables ELG4126 Distributed Generation and Renewables Case Study of Renewable Energy and Smart Grid of Three Phases Phase One: Wind Farm Conduct a feasibility study for initiating a profitable wind energy farm

More information

LARGE WIND FARM AGGREGATION AND MODEL VALIDATION MULUMBA PROSPER PANUMPABI THESIS

LARGE WIND FARM AGGREGATION AND MODEL VALIDATION MULUMBA PROSPER PANUMPABI THESIS LARGE WIND FARM AGGREGATION AND MODEL VALIDATION BY MULUMBA PROSPER PANUMPABI THESIS Submitted in partial fulfillment of the requirements for the degree of Master of Science in Electrical and Computer

More information

Power Quality Improvement in Distribution System Using Distribution Static Compensator

Power Quality Improvement in Distribution System Using Distribution Static Compensator Power Quality Improvement in Distribution System Using Distribution Static Compensator Jay Kumar Sharma 1, Om Prakash Mahela 2 and Sunil Agarwal 1 1 Department of Electrical Engineering, Apex Institute

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor(SJIF): 3.3 International Journal of Advance Engineering and Research Development Volume,Issue, January -5 e-issn(o): 3-7 p-issn(p): 3- Performance Analysis of SCIG Coupled

More information

Cluster Design Toolbox. Cluster Design Workshop, 15/04/2016

Cluster Design Toolbox. Cluster Design Workshop, 15/04/2016 Cluster Design Toolbox Cluster Design Workshop, 15/04/2016 Layout 1 Idea and Concept Integrated approach 2 3 Architecture Toolbox compartments Architecture of the toolbox Interaction with computation models

More information

Power Quality and Voltage Stability of Power Systems with a large share of Distributed Energy Resources

Power Quality and Voltage Stability of Power Systems with a large share of Distributed Energy Resources University of Texas at Tyler Scholar Works at UT Tyler Electrical Engineering Theses Electrical Engineering Spring 4-30-2012 Power Quality and Voltage Stability of Power Systems with a large share of Distributed

More information

Technical Aspects of Status and Expected Future Trends for Wind Power in Denmark

Technical Aspects of Status and Expected Future Trends for Wind Power in Denmark WIND ENERGY Wind Energ. 2007; 10:31 49 Published online 4 September 2006 in Wiley Interscience (www.interscience.wiley.com).206 Research Article Technical Aspects of Status and Expected Future Trends for

More information

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS Shadab Shakeel 1, Ameenuddin Ahmed 2 1 Student, M.Tech, 2 Asst. Prof., Department

More information

Capacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability

Capacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability International Journal on Power Engineering and Energy (IJPEE) Vol. (4) No. () ISSN Print (234 738) and Online (234 73X) January 23 Capacity and Location Effects of Wind Turbine Energy Systems on Power

More information

POWER QUALITY ASPECTS IN A WIND POWER PLANT IMAMHUSEN M PATIL. MASTER OF TECHNOLOGY IN ELECTRICAL ENGINEERING (Computer Controlled Industrial Power)

POWER QUALITY ASPECTS IN A WIND POWER PLANT IMAMHUSEN M PATIL. MASTER OF TECHNOLOGY IN ELECTRICAL ENGINEERING (Computer Controlled Industrial Power) POWER QUALITY ASPECTS IN A WIND POWER PLANT A THESIS Submitted by IMAMHUSEN M PATIL In partial fulfillment for the award of the Degree of MASTER OF TECHNOLOGY IN ELECTRICAL ENGINEERING (Computer Controlled

More information

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks Magni Þ. Pálsson, Trond Toftevaag, Member IEEE, Kjetil Uhlen, Member IEEE, John Olav Giæver Tande SINTEF Energy Research

More information

STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid

STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid International OPEN ACCESS Journal Of Modern Engineering Research (IJMER) STATCOM for Improved Dynamic Performance of Wind Farms in Power Grid Mohammad Ilyas 1, Mohammad Ubaid Soherwardi 2 1, 2 (Department

More information

Kentish Flats Offshore Wind Farm

Kentish Flats Offshore Wind Farm Kentish Flats Offshore Wind Farm A pure spot on the Map of the World Kentish Flats Offshore Wind Farm features 30 wind-powered turbines each with a nominal rated capacity of 3 MW making a net capacity

More information

ISSN Vol.09,Issue.04, March-2017, Pages:

ISSN Vol.09,Issue.04, March-2017, Pages: ISSN 2348 2370 Vol.09,Issue.04, March-2017, Pages:0558-0562 www.ijatir.org Simulation Exhibition of 220KW Wind Power Generation with PMSG Using Matlab Simulink K. INDRANI 1, DR. K. RAVI 2, S. SENTHIL 3

More information

Generation Application Part B: Technical Form

Generation Application Part B: Technical Form Generation Connections Generation Application Part B: Technical Form For all applications with total installed generation capacity greater than 16A per phase (>4). 01 May 2018 How to fill out this application

More information

Electrical Networks and Integration of Wind Energy

Electrical Networks and Integration of Wind Energy Electrical Networks and Content: 1. Wind energy in Germany Dr. Boris Valov Institut für Solare Energieversorgungstechnik - ISET Division Engineering and Power Electronics 2. Change in operation of electrical

More information

DISTRIBUTED GENERATION AND POWER QUALITY

DISTRIBUTED GENERATION AND POWER QUALITY DISTRIBUTED GENERATION AND POWER QUALITY Arindam Ghosh Department of Electrical Engineering IIT Kanpur DISTRIBUTED GENERATION Distributed Generation (DG) employs smaller-size size generators. The electricity

More information

European Maritime Day - Renewable marine energy and infrastructures

European Maritime Day - Renewable marine energy and infrastructures European Maritime Day - Renewable marine energy and infrastructures Julien D Hollander Monday 21 May 2012 Gothenburg, Västra Götaland, Sweden 1 Agenda 1. Elia in a nutshell 2. European challenges 3. Elia

More information

Dynamic Compensation of Reactive Power for Integration of Wind Power in a Weak Distribution Network

Dynamic Compensation of Reactive Power for Integration of Wind Power in a Weak Distribution Network INTERNTIONL ONFERENE ON ONTROL, UTOMTION, OMMUNITION ND ENERGY ONSERVTION -2009, 4th-6 th June 2009 Dynamic ompensation of Reactive Power for Integration of Wind Power in a Weak Distribution Network 1

More information

2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications

2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications , rue d Artois, F78 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications

More information

Analysis of Wind Power Integration for Power System Transient Stability

Analysis of Wind Power Integration for Power System Transient Stability Analysis of Wind Power Integration for Power System Transient Stability J. K. Muriuki, C. M. Muriithi and L. M. Ngoo Abstract Many developing nations are currently undertaking huge electric power generation

More information

Interconnection of Distributed Generators and Their Influences on Power System

Interconnection of Distributed Generators and Their Influences on Power System International Energy Journal: Vol. 6, No. 1, Part 3, June 2005 3-127 Interconnection of Distributed Generators and Their Influences on Power System www.serd.ait.ac.th/reric Vu Van Thong, Johan Driesen,

More information

Orkney Active Network Management system Technical Session 1 Accessing capacity in a constrained network Active Network Management

Orkney Active Network Management system Technical Session 1 Accessing capacity in a constrained network Active Network Management Orkney Active Network Management system Technical Session 1 Active Network Management David MacLeman Distribution R&D Manager 1 Learning Outcomes Understand the concept of ANM Identify and assess opportunities

More information

Member Service Electric Wiring Guidelines

Member Service Electric Wiring Guidelines Member Service Electric Wiring Guidelines Table of Contents A. Definitions... 2 B. Member Service Wiring Guidelines... 2 C: Meter located on the house from an underground source - pad transformer or j-box....

More information

Distributed Renewable Energy Generation Interconnection Policy

Distributed Renewable Energy Generation Interconnection Policy Distributed Renewable Energy Generation Interconnection Policy Dominica Electricity Services 2010 Version Table of Contents Executive Summary... 2 1. Interconnection Policy... 6 1.1 Introduction... 6 1.2

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

Summary of the Tutorial on Fundamentals of Wind Energy IEEE PES 2010 T&D Conference New Orleans, Louisana

Summary of the Tutorial on Fundamentals of Wind Energy IEEE PES 2010 T&D Conference New Orleans, Louisana Summary of the Tutorial on Fundamentals of Wind Energy IEEE PES 2010 T&D Conference New Orleans, Louisana Sponsorship This tutorial is sponsored by (WPCC). Cosponsors include PSDP Committee, T&D Committee,

More information

Control of a Microgrid in Islanded Mode

Control of a Microgrid in Islanded Mode Faculty of Science & Engineering School of Engineering and Energy Control of a Microgrid in Islanded Mode A thesis submitted in partial fulfillment of the requirements for the degree of Bachelor of Engineering

More information

STUDY SUMMARY (F) CDC-1319

STUDY SUMMARY (F) CDC-1319 Commission for Electricity and Gas Regulation Rue de l Industrie 26-28 1040 Brussels Tel.: 02/289.76.11 Fax: 02/289.76.09 COMMISSION FOR ELECTRICITY AND GAS REGULATION STUDY SUMMARY (F)140430-CDC-1319

More information

CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS

CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS 108 CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS 6.1 INTRODUCTION Planning and development of power system infrastructure to cater to the needs of the people is

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers

Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers Economical and stable grid operation Shunt and series reactors for medium- and high-voltage grids siemens.com/transformers Reactors enhance grid stability and economic efficiency Shunt reactor from Siemens

More information

Operational Characteristics of Wind Windfarms

Operational Characteristics of Wind Windfarms Operational Characteristics of Wind Windfarms Panel sponsored by Energy Development and Power Generation Committee PES General Meeting, Montreal, Canada June 19, 2006 Badrul H. Chowdhury (Panel Chair)

More information

500 MW Wind Farm Technical System Impact Study

500 MW Wind Farm Technical System Impact Study FINAL REPORT Report to: El Paso Electric for 500 MW Wind Farm Technical System Impact Study Prepared by: Goran Drobnjak Sang Lee Emad Ahmed Reigh Walling Einar Larsen February 19, 2008 EPE_TechSIS_Final.doc

More information

OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH

OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH SUSTAINABLE EUROPEAN INFRASTRUCTURE FINANCING UNDER THE CONDITIONS OF COMPETITION, ENVIRONMENTAL

More information