Framework for Managing Dewatering and Accidental Artesian Aquifer Interception

Size: px
Start display at page:

Download "Framework for Managing Dewatering and Accidental Artesian Aquifer Interception"

Transcription

1 Northern Arterial Extension and Associated Stormwater Works - Resource Consents Application Appendix 12 Framework for Managing Dewatering and Accidental Artesian Aquifer Interception Beca // 13 August // NZ // page 118

2 Northern Arterial Extension and Associated Stormwater Works - Resource Consents Application Beca // 13 August // NZ // page 119

3 Report Northern Arterial Extension Consent Application Dewatering and Accidental Artesian Aquifer Interception Framework Prepared for Christchurch City Council (Client) By Beca Ltd (Beca) 19 August 2014 Beca 2014 (unless Beca has expressly agreed otherwise with the Client in writing). This report has been prepared by Beca on the specific instructions of our Client. It is solely for our Client s use for the purpose for which it is intended in accordance with the agreed scope of work. Any use or reliance by any person contrary to the above, to which Beca has not given its prior written consent, is at that person's own risk.

4 Revision History Revision Nº Prepared By Description Date A Mike Thorley Document Acceptance Action Name Signed Date Prepared by Mike Thorley Reviewed by Sian France Approved by Paul Whyte on behalf of Beca Ltd Beca // 19 August 2014

5 Table of Contents Introduction...1 Mitigation of Environmental Effects Dewatering Consents... 2 Discharge to the Environment... 2 Dewatering Discharge Quality... 2 Methods of Discharge Treatment... 3 Effects of Groundwater Drawdown on Surface Water Bodies... 5 Avoidance of Ground Settlement... 5 Dewatering Practice Method Selection... 7 Accidental Interception of Artesian Aquifers or Large Inflows Excavations Pile Holes Piling Current Estimate of Dewatering Required Across Christchurch Northern Arterial Extension...12 Current Estimate of Spring Monitoring Across Christchurch Northern Arterial Extension...12 References...12 Beca // 19 August 2014 // Page ii

6 1 Introduction The purpose of this framework is to set out the key issues associated with dewatering and the accidental interception of artesian conditions. Generally, the following items should be considered when managing dewatering activities: 1 Purpose of dewatering (i.e., an explanation of why dewatering is necessary) 2 Dewatering technique (i.e., well point, deep well, open hole, etc.) 3 Anticipated dewatering flow rate and total dewatering duration 4 Controls (i.e., settling tank, turbidity curtain, etc.) and method of discharge 5 Measures and techniques to manage noise, vibration and odour issues 6 Measures and techniques to manage geotechnical stability issues 7 Contingency plan in case of any emergency situation 8 A monitoring programme to ensure that discharge water will comply with applicable water quality standards 9 Baseline assessment of the existing environment (e.g. fauna, water quality) that will receive the discharge 10 A strategy for monitoring and managing effects during the life and after the closure of the project 11 The point of discharge to the stormwater system and to any waterway or water body. Dewatering across the Christchurch Northern Arterial Extension is not anticipated to be extensive. In particular some minor dewatering maybe required during the placement of culverts. The philosophy is to build on top of existing ground level and avoid excavations as much as possible. The following framework has largely been adapted from the Stronger Christchurch Infrastructure Recovery Team (SCIRT) DEWATERING GUIDELINE: Guideline for Dewatering Practice for Christchurch (SCIRT, 2013). Beca // 19 August 2014 // Page 1

7 2 Mitigation of Environmental Effects 2.1 Dewatering Consents Environment Canterbury consents are required for extracting groundwater for dewatering purposes and disposal of the discharge into water bodies or the stormwater system. The dewatering management plan needs to fully consider the conditions and ensure the required dewatering activities are conducted appropriately. Compliance with consent conditions will be demonstrated though the requirements of the dewatering management plan and associated QA records. 2.2 Discharge to the Environment Specific factors that need to be addressed are the siting of the discharge, the effects of the discharge on the discharge location and the ability of the discharge environment to accept the volume of discharge. The following mitigation options should be considered in the dewatering management plan: Determine the quality of the discharge water; Ensure appropriate treatment of the discharge prior to discharge; Minimise erosion and scour at the discharge point(s); Utilise the existing Christchurch City Council drainage network where possible; Ensure an appropriate mixing zone in the water body; Ensure the discharge does not have a detrimental impact on flora and fauna downstream of the discharge point; and Minimise the volume of dewatering water discharged to surface water bodies through reuse and land-based detention and soakage. 2.3 Dewatering Discharge Quality Suspended Solids Dewatering water shall pass through a sediment removal device prior to discharge. The TSS can be checked through a visual inspection of the water being released into the environment. Standard samples will be used for comparison to allow a rough instant field assessment of discharge quality (Figure 1). Beca // 19 August 2014 // Page 2

8 Figure 1: Example of comparative samples to visually assess approximate TSS within the discharge Because primary settlement tanks remove the solids that settle quickly, it is only particles with a long settling time that are usually discharged from the primary treatment. Therefore samples of discharge water that meet the consent conditions can be prepared in a laboratory based on the typical particle size expected to be discharged from the primary tanks. These can be compared with samples taken on site to allow approximation of the TSS value of the discharge. 2.4 Methods of Discharge Treatment Several options exist to treat dewatering water prior to it discharging to the environment. One or more of the following options will be used Sediment Control Tanks Examples of TSS <150 g/m 3 Sediment control tanks are the most common method of treatment of discharge water. The tank will be sized appropriately for the quantity of the discharge so that the flow velocity is lowered to promote sedimentation and that the retention time is sufficient. If there are concerns about settlement times, tanks can be used in series to increase discharge water withholding times and increase settlement of sediment. The overflow from the tank to the ground will be controlled through the use of a pipe or hose. This will avoid erosion and overland transport of entrained sediment resulting from the overflow. It will also allow the flow to be directed to the closest suitable discharge point. Regular (visual) monitoring of the clarity of the water exiting the sediment tank, especially during excavation, is likely to be required. Advantages Good gross settlement traps Sediment can be removed with suction trucks Allows incorporation of additional discharge water treatments, such as oil separators Ability of water to be accessed and used for other purposes (trench compaction, dust suppression) Can be used in conjunction with other methods of sediment capture. Disadvantages Not generally large enough to allow settlement times for clay particles Safety risk of water depth in public environment Large item to place in the road environment. Beca // 19 August 2014 // Page 3

9 2.4.2 Filtering Discharge Through Vegetation Filtering dewatering discharge through vegetation generally comprises the surface application of the discharge onto vegetated land, allowing water to soak through the soil and recharge the groundwater table. In general this requires a large area or an area of heavy/rank grass growth to capture the fines. Swales and coffer dams can also be used to collect the sediment and allow the water to drain away. Remediation of the land following its use in this way will be carried out by regrassing or aeration to avoid permanent clogging of the soil structure by the deposited fines. Filtering discharge though vegetation will only be used as a secondary treatment after the discharge has been passed through a sedimentation tank to remove larger particles. Advantages Discharge seeps into ground and not directly into a waterway Vegetation provides extended flow paths and captures sediment which is bound by grasses Not in road environment Disadvantages Needs grassed flow path Constant water flow can compromise grass health Pores in ground can become clogged and require remediation Some maintenance required if coffer dams in place Rain events can mobilise discharged site sediment Collection with sediment control bag / Flocculent impregnated sock A sediment control bag or flocculent impregnated sock comprises a geotextile bag attached to the pump outlet, filtering the larger sediments from the discharge water. There are a number of types of proprietary treatment devices available ranging from pore size sieving to flocculent impregnated fabric. These systems vary in size, efficiency and cost, but will be investigated and considered where appropriate. These systems may be used in series with other sediment treatment methods, such as filtering through vegetation. Advantages Small in size Gross silt contained in small area Easy to dispose of silt Disadvantages Unable to cope with large discharges or high pressure discharges Silt must be disposed of with the bag Fines/ silt weep out of the bag Connection of pump discharge hose to bag is a common point of failure ECan approval of the flocculent planned for use will be sought prior to implementation Opportunities for use of Dewatering discharge Opportunities to utilise dewatering water on site will be investigated. These include: Use for dust suppression Use for establishment of planting/berm areas Use for compaction or piling requirements Beca // 19 August 2014 // Page 4

10 2.5 Effects of Groundwater Drawdown on Surface Water Bodies There are no surface water bodies of significance in the Cranford Basin area. Management of dewatering across the Christchurch Northern Arterial Extension will consider the effects on the various drains that cross the alignment. Potential effects will depend on the depth of drawdown relative to the level of the watercourse, the period of drawdown, the rate of dewatering, the distance from the water body, and the permeability of the soil between the site and the watercourse. Measures which could be implemented on site to limit effects of groundwater drawdown on surface water bodies include: Recharge to the surface water body Installation of temporary cut-offs to lengthen flow paths (e.g. sheet pile wall, grout curtain, groundwater recharge) Modification of dewatering methodology to reduce influence beyond site. 2.6 Avoidance of Ground Settlement Dewatering activities can result in settlement of surrounding ground because: Drawdown of groundwater increases effective stress leading to both elastic (immediate) and consolidation settlement of soils. Settlement magnitude is dependent on the magnitude of groundwater drawdown, the soil profile and material properties at the site High flow velocities through the soil to dewatering wells and/or ineffective filters result in mobilisation and loss of fines, which can lead to local ground settlement Settlement of adjacent ground associated with instability of excavation sides, insufficient reduction of pore water pressures or seepage which compromises stability. Sands and gravels are comparatively permeable and stiff, so the settlements which result from changes in pore water pressure and effective stress occur rapidly during the period of construction and effects on the ground surface are generally small. However, softer and less permeable soils such as clay, silt and organic soils are prone to consolidation. Settlements in these materials may take some time to develop and have adverse effects on adjacent property Settlement Mitigation The dewatering management plan will identify methodologies to limit adverse dewatering settlement. The following points are key considerations in dewatering settlement: Settlement associated with loss of fines can be mitigated though appropriate design of the dewatering system to control flow velocity and provide screens and/ or filters matched to the grading of the in-situ soils. Entrainment of fines must be monitored during construction; actions are expected to include analysis of TSS in discharge water and/ or monitoring of accumulation of sediment in sedimentation tanks. Drawdown-induced ground settlement will be mitigated though estimation of groundwater drawdown and settlement coefficients to identify risk at the detailed design stage prior to drawing the groundwater down. Water level monitoring in monitoring boreholes and/or nearby springs will occur to check that larger drawdowns than anticipated at distance from the excavation are not occurring. Differential settlement is most problematic; this will be controlled by managing the rate of drawdown and understanding where clear changes in soil type occur. Should the potential for drawdown that could result in damaging settlement be indicated, this will be mitigated by installing groundwater cut-offs to stem or restrict groundwater flow and limit drawdown beyond the site. Beca // 19 August 2014 // Page 5

11 Provide sufficient temporary support to excavations to maintain stability, where seeps might otherwise induce progressive collapse of sides of the excavation. During dewatering implement staged drawdown (where appropriate) and monitor field settlement and water level changes beyond the immediate site, comparing against theoretical settlements and water levels to allow warning of potential dewatering settlement issues Assessment of Immediate and Consolidation Settlement Prior to commencing assessment of potential ground settlement associated with dewatering at a site, the following will be determined: sensitivity of adjacent structures to total and differential settlement, soil profile and material properties at the site (affecting magnitude of total and differential settlement and time for consolidation), groundwater conditions at the site and proposed drawdown, details of the dewatering methodologies being implemented, and temporary works design for the excavation Settlement Monitoring Details of proposed settlement monitoring will be set out in the dewatering management plan for sections of the project where there is a risk of settlement causing damage to surrounding structures or infrastructure. Prior to commencing dewatering, condition surveys of adjacent properties that could potentially be affected by dewatering will be carried out. The scope of settlement monitoring will be confirmed following detailed design, considering the risks and potential consequence of adverse settlement at the site or on adjacent property. It is anticipated that a settlement monitoring system will comprise a series of piezometers and settlement markers sited at various distances beyond and at the site, within the zone of influence of groundwater drawdown. Alert and Action settlement thresholds will be selected by theoretical assessment of anticipated settlements and review of sensitivity of adjacent structures and infrastructure. Beca // 19 August 2014 // Page 6

12 3 Dewatering Practice Whilst dewatering across the Christchurch Northern Arterial is not expected to be extensive, selection of a dewatering method will be made considering the factors set out in Figure 2. Table 1 summarises the common dewatering techniques used for different soils and identifies the key issues that will be considered in the management plan. 2.7 Method Selection Key factors that will control selection of a dewatering method are: Soil profile and soil type; permeability of each layer Extent of the area to be dewatered (excavation dimensions and depth) Existing depth to the groundwater table and the level to which it has to be lowered below this Proposed method of excavation and ground support Proximity of existing structures, water courses etc Conditions Favouring Sump Pumping Well-graded sandy gravel, clean gravel, firm to stiff clay Unconfined aquifer Modest drawdown required and there is no immediate source of recharge (e.g. no stream nearby) Shallow excavation slopes or deep driven sheet piles Excavation by backhoe or dragline Light foundation loads Low risk of contamination of discharge water Conditions Favouring Well-pointing Sandy or interlayered soils including sands (k = 10-3 to 10-5 m/s) Unconfined aquifer Drawdown of 5m or less required, or up to 10m where a large excavation area is available Conditions Favouring Wells Ground conditions too permeable for well-points to be viable Silty soils where correct filter grading design is needed Drawdown of more than 8m required or drawdown over a wide area for a long period Good understanding of ground conditions in and around the site and ideally, pumping test data Access to the excavation and top of batter slopes needed or congested sites (wells can be located away from working areas). Beca // 19 August 2014 // Page 7

13 Figure 2: Example dewatering methodology decision tree (from SCIRT, 2013) Beca // 19 August 2014 // Page 8

14 Table 1: Summary of the soils, possible issues and commonly used dewatering techniques Soil Type Grain Size (mm) GW Flow Rate Possible Issues Dewatering Methodology Gravels/ Cobbles >2 High Large flows of groundwater requiring wells if the excavation is to be deep and likely trench sumps if excavation is just into the water table wells and sumps Sand 0.06 to 2 Low to medium Trench stability low if sand allowed to run into excavation well pointing Silt to 0.06 low Clay <0.002 Very low Stability variable and yields could be low requiring close spacing of well points; localised perching possible Minimal trench stability issues; localised perching possible well pointing and sumps well pointing and sumps Peat variable Variable (low to high) Specialist requirements as dewatering peat can result in compression of the layers causing settlement and damage to surrounding land and infrastructure specialist advice required Mixed soils variable Variable (low to high) A majority of the conditions will be mixed and therefore the methodology is generally based on the predominant soil type depends on hydrogeology and highest yielding unit Beca // 19 August 2014 // Page 9

15 3 Accidental Interception of Artesian Aquifers or Large Inflows While it is not anticipated that artesian conditions will be intercepted in most dewatering activities carried out across Northern Arterial Extension, there is nevertheless the possibility of interception of artesian or high flow conditions which can rapidly lead to failure of embankments and founding layers if not responded to quickly and appropriately. This part of the framework sets out a plan for preparing for and responding to artesian or high inflow conditions. 3.1 Excavations In the case of uncontrolled aquifer inflows to excavations bound by sheet piles or similar, the following steps shall be taken: Assess the situation. Determine if the flow is constant or increasing. Determine if the turbidity is constant or increasing. Determine if the flow is confined to the well-point/ pumping well or excavation Notify project engineer and/or project manager. Be able to describe in detail the conditions and events prior to encountering artesian flow photographs and/or video, in real-time if possible. Consult with the Engineer and determine primary strategy and contingency plan should the primary strategy be insufficient to arrest the artesian flow Measure check any nearby groundwater levels in piezometers and drain/spring levels Notify. Inform project representative of the situation and planned action items Emergency actions may include: Backfill the excavation until the depth of backfill is sufficient to control material transport in the inflow; Extend pipe sections to allow measurement of the artesian pressure; Control any discharge of water by established site erosion and sediment control measures Refill the excavation with water to the original level; Reconsider the design of the excavation keeping in mind the level of artesian pressures; (consider caisson construction and tremie concreting a gravity compensated base slab); Design will need to be altered to allow a casing to be spun into the green concrete to allow control of the artesian pressures; If the aquifer pressures are modest and not above surrounding ground level, place a thickness of graded crushed aggregate on top to act as a controlled filtered exit. Design the thickness of the aggregate to avoid piping or heaving depending on the difference in height between the aquifer level and the depth to be excavated. 3.2 Pile Holes This section outlines steps that can be taken to control, stop, and seal groundwater flow during the construction of piles. 3.3 Piling Avoidance of interception of artesian aquifers in piling is desirable to: Avoid floating of piles Beca // 19 August 2014 // Page 10

16 Avoid depressurisation of the aquifer Avoid the potential for mixing of water from the Springston Formation with that found in the Riccarton Gravels if depressurisation of the aquifer occurs Driven Piles It is anticipated that most piles will be driven through the Springston Formation to the top of the Riccarton Gravels. Water pressure may rise around the pile for a time and mitigation measures may be required to remove any water that might emerge at land surface. In many areas of the Christchurch Northern Arterial the pressure will be transferred to more permeable layers within the Springston Formation and no remedial action would be needed Bored Piles In the event that bored piles are required, the management plan should consider following steps: Install a temporary or permanent casing around the pile; Complete the drilling of each pile hole using a high viscosity, dense polymer Once full depth is reached, complete the pile with concrete tremmied from the base up Recover and re-use the displaced polymer which will be pumped from the hole as the tremmie proceeds Have any remaining neutralized polymer removed from site and disposed of by an appropriate hazard substances carrier. The density of the polymer must be sufficient to exceed the artesian pressure of the Riccarton Gravels aquifer. The viscosity of the polymer will allow the hole to remain open until the tremmie is complete and avoid penetration of the concrete into the aquifer. The concrete will seal against the formation and/or the permanent casing. Beca // 19 August 2014 // Page 11

17 4 Current Estimate of Dewatering Required Across Christchurch Northern Arterial Extension Given the project is currently at Specimen Design phase, temporary works and dewatering methodologies that will be implemented during construction have not yet been determined. For the purposes of identifying potential effects for the resource consent application, the likely need for dewatering has been identified for the major structures across the project. Temporary dewatering is likely to be required mostly for the excavation and replacement of shallow materials for embankment construction at the following locations: Northern and Southern wetlands; Croziers Drain Culvert; and the Southern Culvert. Initial indications are that excavations will be at or just below the water table, and therefore only minor dewatering is expected. The quality of shallow groundwater should be monitored in relation to the soil contamination found in the vicinity of the alignment. If dewatering is undertaken, a sampling plan is prepared to verify the existing baseline groundwater quality and ensure dewatering activities do not significantly increase contaminant loads into the drain(s). This will ensure that the quality of the discharge water from dewatering will be similar to background levels. If groundwater quality is poorer than background levels, then mitigation measures will need to be employed to better treat the water, conduct further assessment on the impact of discharging the water and/or discharge the dewatering water to an alternative location such as the CCC sewer. 5 Current Estimate of Spring Monitoring Across Christchurch Northern Arterial Extension In order to monitor the potential effects on springs, the management plan should consider monitoring of three springs M35/8139, M35/8138 and M35/8136. Visual inspections and the level of the spring are considered sufficient to determine any potential change in spring condition. 6 References SCIRT, DEWATERING GUIDELINE: Guideline for Dewatering Practice for Christchurch. Prepared by Beca Ltd. Beca // 19 August 2014 // Page 12

A tank filtration and settling system set up to dewater groundwater for excavation work near the Upper Truckee River.

A tank filtration and settling system set up to dewater groundwater for excavation work near the Upper Truckee River. 4.5.1.3 DEWATERING DESCRIPTION Dewatering techniques are methods of addressing extracted ground or surface water encountered during construction. This temporary BMP addresses the installation and maintenance

More information

Dewatering Guideline. Theme: Construction

Dewatering Guideline. Theme: Construction Lessons learned from one of New Zealand s most challenging civil engineering projects: rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of Christchurch 2011-2016.

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01. Description. This work consists of installing and maintaining erosion and sedimentation controls to minimize soil erosion and control

More information

WAR Wairarapa Aggregates Ltd

WAR Wairarapa Aggregates Ltd WAR080518 Wairarapa Aggregates Ltd Supplementary report to Hearing Panel Deirdre Ross 1. Purpose of report The purpose of this report is to provide comments on the briefs of evidence provided by the applicant

More information

Temporary Watercourse Crossing: Fords

Temporary Watercourse Crossing: Fords Temporary Watercourse Crossing: Fords DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT

Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) DRAFT Shelbyville, Kentucky Stormwater Best Management Practices (BMPs) Stormwater Pollution Treatment Practices (Structural) Activity: Infiltration Systems PLANNING CONSIDERATIONS: Design Life: Short IS Acreage

More information

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering

More information

Inflow pipe. Drain. Drain

Inflow pipe. Drain. Drain Inflow pipe Screened overflow Drain Foul flush diverter Screened intake Manhole cover Maximum water level Seal Inspection cover Possible local drainage through screen Drain Bottom sloped Screened outlet

More information

Modular Sediment Barriers (Instream)

Modular Sediment Barriers (Instream) Modular Sediment Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

EXTRACT. MONITOR. CONTROL.

EXTRACT. MONITOR. CONTROL. GUIDANCE OF ABSTRACTION AND DISCHARGE PERMITS FOR OPERATIONS When considering any potential dewatering requirement, it is necessary to consider the following questions: Are we allowed to abstract groundwater,

More information

GRADING, EROSION AND SEDIMENTATION CONTROL

GRADING, EROSION AND SEDIMENTATION CONTROL SECTION 500 GRADING, EROSION AND SEDIMENTATION CONTROL 501 Erosion and Sedimentation Control Plan All engineering plans for projects that propose to construct new, or modify existing drainage facilities,

More information

Block & Aggregate Drop Inlet Protection

Block & Aggregate Drop Inlet Protection Block & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Culverts Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol

More information

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 The Institution of Engineers of Ireland Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 MODULE 4 RETAINING STRUCTURES DEEP EXCAVATIONS

More information

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B Oweninny Wind Farm Oweninny Environmental Impact Statement Appendix 5B Access Tracks, Hardstanding Areas, Electrical Compounds, Borrow Pit And Cable Laying Construction Method Statement Copyright ESB International

More information

WQ-08 ENHANCED DRY SWALE

WQ-08 ENHANCED DRY SWALE Greenville County Technical Specification for: WQ-08 ENHANCED DRY SWALE 1.0 Enhanced Dry Swale 1.1 Description An Enhanced Dry Swale is a shallow open-channel drainage way stabilized with turf grass or

More information

CONSTRUCTION SPECIFICATION FOR DEWATERING

CONSTRUCTION SPECIFICATION FOR DEWATERING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 517 NOVEMBER 2016 CONSTRUCTION SPECIFICATION FOR DEWATERING TABLE OF CONTENTS 517.01 SCOPE 517.02 REFERENCES 517.03 DEFINITIONS 517.04 DESIGN

More information

Scheduling Maintenance for Dry Ponds

Scheduling Maintenance for Dry Ponds Visual Inspection for Sedimentation Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections

More information

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) Tararua District Council Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP) NOTE: This is a draft ESCP in current preparation. Additional and updated information will

More information

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes. 1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

ACTIVITY: Dewatering Operations AM 12

ACTIVITY: Dewatering Operations AM 12 Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients Toxic Materials Oil & Grease Bacteria &

More information

2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS

2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS Section 2 Earthworks and Geotechnical Requirements 2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS CONTENTS 2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS... I 2.1 Introduction... 2-1 2.1.1 Objectives... 2-1 2.1.2

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring 14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring An effective monitoring program provides results to: indicate whether the facility is working as expected and that the assumptions used in the assessment

More information

Filter Tube Barriers (Instream)

Filter Tube Barriers (Instream) Filter Tube Barriers (Instream) INSTREAM PRACTICES Flow Control No Channel Flow Dry Channels Erosion Control Low Channel Flows Shallow Water Sediment Control High Channel Flows Deep Water Symbol Photo

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Black Butte Copper Project Mine Operating Permit Application (Revision 3) Water Management During Construction and Operations

Black Butte Copper Project Mine Operating Permit Application (Revision 3) Water Management During Construction and Operations Black Butte Copper Project Mine Operating Permit Application (Revision 3) APPENDIX K-2: Water Management During Construction and Operations Tintina Montana, Inc. July 2017 www.knightpiesold.com Mr. Bob

More information

Chapter 2: Selecting Best Management Practices (BMPs)

Chapter 2: Selecting Best Management Practices (BMPs) Chapter 2: Selecting Best Management Practices (BMPs) 2.1 - Temporary versus Permanent BMPs The same level of care should be taken to select both temporary BMPs and permanent BMPs. The same level of care

More information

ITEM 750 ROCK FILTER DAMS

ITEM 750 ROCK FILTER DAMS AFTER MARCH 1, 2012 ITEM 750 ROCK FILTER DAMS 750.1 Description. This work shall consist of the installation of temporary erosion protection and sediment control rock filter dams utilized during construction

More information

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP) SMP-11 PLANNING CONSIDERATIONS: Design Life: 1 yr Acreage

More information

Performance Standards Compliance Checklist

Performance Standards Compliance Checklist Truckee Meadows Regional Stormwater Quality Management Program Performance Standards Compliance Checklist The checklist that follows identifies the BMPs that can be used at construction sites to meet each

More information

Comparison of Liquefaction Mitigation Options: A Christchurch Case Study

Comparison of Liquefaction Mitigation Options: A Christchurch Case Study Comparison of Liquefaction Mitigation Options: A Christchurch Case Study 2013 NZSEE Conference D.P. Mahoney & J. Kupec Aurecon New Zealand Limited. ABSTRACT: Following the 4 September 2010 M w 7.1 Darfield

More information

Inlet Protection. Fe= (Depends on soil type)

Inlet Protection. Fe= (Depends on soil type) 3.4 DESIGN CRITERIA: KEY CONSIDERATIONS Evaluate drainage patterns to ensure inlet protection will not cause flooding of roadway, property or structures Never block entire inlet opening Size according

More information

Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging

Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging Ground Improvement of Titanium Dioxide Waste Spoils and Compressible Organics with In-Situ Mixing with Portland Cement and Surcharging James J. Serpico (&) Geotechnical Services, Maser Consulting P.A.,

More information

E2. Water quantity, allocation and use

E2. Water quantity, allocation and use E2. Water quantity, allocation and use E2.1. Introduction E2 Water quantity, allocation and use Demand for water already equals or exceeds availability in some surface waterbodies and aquifers. Future

More information

C-1. Infiltration System

C-1. Infiltration System C-1. Infiltration System Design Objective An infiltration system captures surface stormwater runoff and allows it to infiltrate into the soil. This SCM is typically the work horse of a runoff volume match

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

Assessment of Impacts from Groundwater Control Projects

Assessment of Impacts from Groundwater Control Projects Assessment of Impacts from Groundwater Control Projects Martin Preene Technical Development Director, Golder Associates Synopsis What is groundwater control? Potential impacts Case studies The future Conclusion

More information

Tools and methods to manage groundwater and settlement effects from the construction of an expressway on peat deposits

Tools and methods to manage groundwater and settlement effects from the construction of an expressway on peat deposits Avanidou T. & Alexander G.J. (2017) Tools and methods to manage groundwater and settlement effects from the construction of an expressway on peat deposits Proc. 20 th NZGS Geotechnical Symposium. Eds.

More information

COFFERDAM (no.) CODE 803

COFFERDAM (no.) CODE 803 ILLINOIS URBAN MANUAL PRACTICE STANDARD COFFERDAM (no.) CODE 803 Source: Kane-DuPage Soil and Water Conservation District DEFINITION A cofferdam is a temporary structure within a waterway or body of water

More information

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering) Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating

More information

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES

BLOCKING AND FILLING SURFACE DRAINAGE DITCHES MINNESOTA WETLAND RESTORATION GUIDE BLOCKING AND FILLING SURFACE DRAINAGE DITCHES TECHNICAL GUIDANCE DOCUMENT Document No.: WRG 4A-1 Publication Date: 10/14/2015 Table of Contents Introduction Application

More information

CNR Milton Mobility Hub Environmental Impact Statement (EIS) EXPERT REPORT ON GEOTECHNICAL ASPECTS

CNR Milton Mobility Hub Environmental Impact Statement (EIS) EXPERT REPORT ON GEOTECHNICAL ASPECTS CNR Milton Mobility Hub Environmental Impact Statement (EIS) EXPERT REPORT ON GEOTECHNICAL ASPECTS Prepared by: Mehdi Mostakhdemi and Dan Dimitriu of Amec Foster Wheeler Environment and Infrastructure

More information

GENERAL NOTES ENGINEERS OVERSIGHT 1. ALL ELEVATIONS, DIMENSIONS, ALIGNMENTS AND ORIENTATION OF ALL ELEMENTS SHOWN IN THE PLANS MUST BE APPROVED BY THE ENGINEER OR ENGINEER'S REPRESENTATIVE ( REP ENGINEER

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

105 - Control of Material

105 - Control of Material 105 - Control of Material 105.02_nat_us_05_11_2004 105.02 Material Sources. 105.02(a) Government Provided Sources. 105.02_nat us02_17_2005 (a) Government-provided sources. Add the following: Government-provided

More information

Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System [1] Supplementary Trap Dispersive Soils

Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System [1] Supplementary Trap Dispersive Soils Filter Tube Dams SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System [1] Supplementary Trap Dispersive Soils [1] Classification

More information

Groundwater Control for Design & Construction

Groundwater Control for Design & Construction PDH Course C587 (2 PDH) Groundwater Control for Design & Construction Instructor: T. E. McLaughlin, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088

More information

TEMPORARY SEDIMENT TRAP CODE

TEMPORARY SEDIMENT TRAP CODE ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY SEDIMENT TRAP CODE 960 Source: DEFINITION A small temporary stormwater storage structure designed to trap sediment. PURPOSE The purpose of this practice

More information

VOTR Site Assessment Victoria on the River

VOTR Site Assessment Victoria on the River i Executive Summary A. Introduction AECOM New Zealand Limited (AECOM) was engaged by Hamilton City Council (HCC) to undertake a geotechnical assessment of the (VOTR) site in Hamilton s central business

More information

SC-01 Surface Outlet and Baffle Sediment Basin

SC-01 Surface Outlet and Baffle Sediment Basin Greenville County Technical Specification for: SC-01 Surface Outlet and Baffle Sediment Basin 1.0 Surface Outlet and Baffle Sediment Basin This Specification contains requirements for the design and construction

More information

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166

City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 City of Doral 8401 NW 53 rd Ter. Doral, FL 33166 Project Address: (305) 593-6700 Permit Number: National Pollution Discharge Elimination System (NPDES) Construction Site Erosion and Sedimentation Control

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02

More information

D EROSION AND SEDIMENT CONTROL. Table of Contents

D EROSION AND SEDIMENT CONTROL. Table of Contents Table of Contents D1. GENERAL... 1 D2. OBJECTIVE... 1 D3. REFERENCE MATERIAL... 1 D4. REGULATORY REQUIREMENTS... 1 D5. EROSION AND SEDIMENT CONTROL (ESC) PLANS... 2 D5.1 Goals and Objectives:... 2 D5.2

More information

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2 Table of Contents 1. Introduction... 1 1.1 Site Information... 1 1.2 Site Characteristics... 1 1.3 Hydrogeologic Setting... 2 2. Closure Plan... 5 2.1 Closure Description... 5 2.2 Closure Timeframe...

More information

Lincoln Road Corridor Improvements Geotechnical Assessment Report

Lincoln Road Corridor Improvements Geotechnical Assessment Report Geotechnical Assessment Report Prepared for Auckland Transport December 2015 Status: Draft Project number: Page 1 Our ref: Word - Report Cover This document has been prepared for the benefit of Auckland

More information

E7. Taking, using, damming and diversion of water and drilling

E7. Taking, using, damming and diversion of water and drilling E7. Taking, using, damming and diversion of water and drilling E7.1. Introduction Taking, using, damming and diversion of surface water and groundwater provisions in this plan apply in accordance with

More information

Environmental Assessment Chapter 8 Surface Water

Environmental Assessment Chapter 8 Surface Water Environmental Assessment Chapter 8 Surface Water 8.2.7 Rainfall and Evaporation Based on recorded data for the area of interest, the mean annual rainfall is about 700mm, with maximum monthly rainfalls

More information

Single Family Residential Construction Erosion/Sediment Control Standards

Single Family Residential Construction Erosion/Sediment Control Standards Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended

More information

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies. The language provided in these specifications is meant to serve as a reminder and provide a generic example of the type of language that should be provided in final construction documents. This language

More information

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY 31 25 00 EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY A. Erosion and sedimentation control shall be provided by the Contractor for all areas of the site denuded or otherwise disturbed

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent

More information

(No. of pages excluding this page = 10)

(No. of pages excluding this page = 10) SPECIALIST CONSULTANT STUDIES 3-65 BIG ISLAND MINING PTY LTD (No. of pages excluding this page = 10) Ltd BIG ISLAND MINING PTY LTD 3-66 SPECIALIST CONSULTANT STUDIES This page has intentionally been left

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Division 15 Earthworks Code (including Lot Filling)

Division 15 Earthworks Code (including Lot Filling) Division 15 Earthworks Code (including Lot Filling) 12.15.1 Earthworks Code (1) The provisions in this division comprise the (2) They are compliance with the Earthworks Code (Section 12.15.2); overall

More information

Erosion Control Inspection Form

Erosion Control Inspection Form Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information

USING WSUD TO RESOLVE COMPETING OBJECTIVES: A CASE STUDY OF A SUSTAINABLE INDUSTRIAL DEVELOPMENT. Abstract

USING WSUD TO RESOLVE COMPETING OBJECTIVES: A CASE STUDY OF A SUSTAINABLE INDUSTRIAL DEVELOPMENT. Abstract USING WSUD TO RESOLVE COMPETING OBJECTIVES: A CASE STUDY OF A SUSTAINABLE INDUSTRIAL DEVELOPMENT R Wiese 1 M Brown 1,M Liebman 1 1 STORM_CONSULTING, rod@stormconsulting.com.au Abstract Located within the

More information

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014 MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341 Adopted April 24, 2014 Effective June 6, 2014 EROSION CONTROL RULE 1. POLICY. It is the policy of

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG.

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG. MEMORANDUM Levelton Consultants Ltd. 150-12791 Clarke Place Richmond, BC V6V 2H9 Canada Tel: 604 278-1411 Fax: 604 278-1042 E-Mail: rhillaby@levelton.com Web Site: www.levelton.com TO: STUART OLSON DOMINION

More information

ACTIVITY: Infiltration Systems and Methods ST 03

ACTIVITY: Infiltration Systems and Methods ST 03 Runoff Targeted Constituents Significant Benefit Partial Benefit Low or Unknown Benefit Sediment Heavy Metals Floatable Materials Oxygen Demanding Substances Nutrients Toxic Materials Oil & Grease Bacteria

More information

WASTE TREATMENT LAGOON

WASTE TREATMENT LAGOON 359-1 NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE STANDARD WASTE TREATMENT LAGOON (No.) CODE 359 DEFINITION A waste treatment impoundment made by constructing an embankment and/or excavating

More information

Appendix D. Erosion Management Sub- Plan

Appendix D. Erosion Management Sub- Plan Appendix D Erosion Management Sub- Plan DRENNAN SOLAR ENERGY FACILITY EROSION MANAGEMENT PLAN PRODUCED FOR ERM ON BEHALF OF SOLAIREDIRECT BY Simon.Todd@3foxes.co.za JUNE 2013 PURPOSE The purpose of the

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

Design Specifications & Requirements Manual

Design Specifications & Requirements Manual Design Specifications & Requirements Manual 10 SEDIMENT AND EROSION CONTROL 10.1 INTRODUCTION... 1 10.2 REFERENCE... 1 10.3 GENERAL INFORMATION REQUIREMENTS... 1 10.3.1 ESC Plan... 1 10.3.2 Servicing Drawings...

More information

AM-PR-003 Construction Environmental Management Plan (C-EMP)

AM-PR-003 Construction Environmental Management Plan (C-EMP) OMS Procedure AM-PR-003 Construction Environmental Management Plan (C-EMP) Revision: 1 Prepared by: Shannon Holroyd Authorised by: Marcus Manning Authorisation Date: 18th May 2015 This document has been

More information

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11 Appendix 11 Erosion and Sediment Control Management Plan Appendix 11 OTAIKA QUARRY - PROPOSED OVERBURDEN DISPOSAL AREA Application for Land Use Consent and Assessment of Environmental Effects Otaika Quarry

More information

SPECIFICATION FOR ENGINEERED FILLS

SPECIFICATION FOR ENGINEERED FILLS SPECIFICATION FOR ENGINEERED FILLS This specification is intended to be used for the engineered fill. The specification is suitable for most purposes but there may be special conditions existing at some

More information

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description. 7. WATER: HYDROGEOLOGY & HYDROLOGY 7.1 Introduction This chapter of the EIAR comprises of an assessment of the likely impact of the proposed development on the surrounding surface water and hydrogeological

More information

SECTION TRENCHING, BACKFILL AND COMPACTION

SECTION TRENCHING, BACKFILL AND COMPACTION SECTION 312333 TRENCHING, BACKFILL AND COMPACTION PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. Native Backfill Material 2. Crushed Stone Bedding 3. Select Backfill Material 4. Shoring and Bracing

More information

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER CHAPTER 3 Site Preparation In preparation for constructing buildings on a property, the builder must consider a number of factors related to code requirements. The buildings must be located according to

More information

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary

More information

Storm Water Standards 105

Storm Water Standards 105 Storm Water Standards 105 Schematic of Dry Swale 2006 S-13 (Source: Center for Watershed Protection, modified) 106 Edgewood - Public Works Schematic of Grass Channel 2006 S-13 Storm Water Standards 107

More information

Groundwater Monitoring Plan. Table of Contents

Groundwater Monitoring Plan. Table of Contents Table of Contents 1.0 Introduction... 3 2.0 Definitions and Acronyms... 5 3.0 Graving Dock Site... 6 3.1 Site Investigation... 6 3.2 Excavation... 7 4.0 Dewatering... 7 4.1 Deep Wells... 8 4.2 Cut-Off

More information

Building on small sites

Building on small sites BC5850 Building on small sites Doing it right Find out more: phone 09 301 0101 or visit aucklandcouncil.govt.nz Good building site management 3:41 Stabilising entranceways 2:32 How-to videos To view our

More information

Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance

Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance South Australia s Environment Protection Authority Environment Protection (Water Quality) Policy 2015, stormwater pollution prevention & dewatering guidance Clive Jenkins, Ruth Ward and Lara Settimio Outline

More information

DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES

DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES DESIGN PARAMETERS FOR MULTI-PHASE EXTRACTION SYSTEMS USING UNSATURATED AND SATURATED SOIL PROPERTIES Todd White, M.Sc., P.Geol. and Douglas A. Sweeney, M.Sc., P.Eng. SEACOR Environmental Inc. INTRODUCTION

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY

MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY MOUNT POLLEY MINING CORPORATION MOUNT POLLEY MINE TAILINGS STORAGE FACILITY REPORT ON STAGE 3C CONSTRUCTION (REF.NO. VA-101-1/5-1) Rev. No. Revision Date Approved 0 Issued in Final September 23, 2005 AMEC010485_0001

More information

Contents. Glossary 9. Foreword 10

Contents. Glossary 9. Foreword 10 Glossary 9 Foreword 10 1 Design considerations 11 1.1 Introduction 11 1.2 Client's general requirements 11 1.3 The ground 11 1.3.1 The concept of effective stress 11 1.3.2 Ground profile 13 1.3.3 Groundwater

More information

The discharge shall include stormwater generated during the construction phase of the subdivision.

The discharge shall include stormwater generated during the construction phase of the subdivision. Limits The discharge shall be only stormwater generated from: (a) Roofs, roads, hardstand areas, and pervious areas; and (b) Exposed areas during construction (optional); associated with the proposed [residential

More information

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT 06045-0191 HILLIARD S POND DAM REMOVAL AND BIGELOW BROOK STREAM CHANNEL RESTORATION BID NO. 14/15-74

More information

Part IV(b) Best Management Practices for Erosion, Sediment, and Velocity Control Continued. Good Housekeeping Practices

Part IV(b) Best Management Practices for Erosion, Sediment, and Velocity Control Continued. Good Housekeeping Practices Part IV(b) Best Management Practices for Erosion, Sediment, and Velocity Control Continued Good Housekeeping Practices Inlet Protection Consist of a variety of manufactured sediment barriers and products

More information

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture

More information

Permeable Pavement Facilities and Surfaces

Permeable Pavement Facilities and Surfaces Permeable Pavement Facilities and Surfaces This checklist is intended to highlight items critical to the performance of permeable pavement facilities and surfaces that need to be addressed in the design

More information