New Construction Change Order Negotiation Process. In-Service Training September 2007
|
|
- Camron Sherman
- 6 years ago
- Views:
Transcription
1 New Construction Change Order Negotiation Process In-Service Training September 2007
2 Change Order Negotiation Process Negotiating change orders is a process. Well negotiated change orders result from up-front preparation and documentation. Today we are going to discuss the process to effectively negotiate change orders.
3 Topics Covered The Major Steps in the Process Events leading up to a COP from the contractor the origin and initiation of a change. Analyzing a COP. Negotiating the change. When negotiations fail to fully resolve the issue. 3
4 Topics Covered Cont: o Why is good documentation important? o Example of a well documented negotiation process. 10 most important things to do. 10 things that hinder negotiations. What our negotiators have to say. Questions. 4
5 Events Leading to a COP Be event oriented! As discussed under claims avoidance training, follow the contract. If LAUSD initiates a change, issue an RFP. If an RFC response is a clear change, issue an RFP. For both of the above, determine if the work must proceed immediately or can it wait for a negotiated change order issue a CD as appropriate. If time permits the preferred action is to issue an RFP per GC If time is critical issue a CD with a not to exceed amount per GC , and instruct contractor to issue a COP within a defined time. New GCs change this to 10 days unless the COP says otherwise. Otherwise, make contractor issue Notice of Event Form and respond as appropriate. 5
6 Analyzing a COP Scope determination. Cost determination. Impact determination. Review of contractor COP. LAUSD documentation. 6
7 Scope Determination Is the COP complete and reviewable? Contractors position on why a change occurred clear? Sufficient backup for quantities and costs? Time impact analysis? If not complete, return it to the contractor. Consider if a CD needs to be issued to get the work moving while contractor is preparing a proper COP. Analyze the scope of work and prepare LAUSD s position while the revised COP is being prepared. 7
8 Scope Determination Cont. Question, did an event change the scope of work? Considerations: What was supposed to be constructed? Order of precedence in the contract, specifications vs. drawings vs. details. Submittals, manufacturer s instructions. Supplemental information, geotech reports, building codes, etc. Owner implied warranty - construe ambiguity against the drafter. What would a prudent bidder have priced on bid day? 8
9 Scope Determination Cont. What is now being constructed? Is it different from what was supposed to be constructed? How is it different? Change in material type. Change in quantity. Change in method of construction. Other. Why is it different; who caused the change? Contractor defective work correction. DSA required change. LAUSD desired change. Architect change; RFC, ASI, etc. Be on the lookout for credits. 9
10 Scope Determination Cont. Define the scope in your own words, use photos, sketches, etc. Make sure you understand the scope as well as implications of ancillary work. Get input from contractor. Get input from A/E. Get input from Inspector. Do your homework. Make up your own mind. Always discuss big issues with supervisor Review examples of contract language when preparing correspondence to contractors. 10
11 Cost Determination Perform a detailed take-off of the scope change, assess delta of what was to be constructed vs. what is now being instructed. Consider method of construction and equipment needed. Determine if unit prices in contract apply. Develop cost estimate based on applicable rates, see contract. Keep very detailed records and notes to refresh your memory for negotiations. 11
12 Impact Determination Has contractor requested a time extension? If so, require a detailed time impact analysis from the contractor. Make the contractor take a contemporaneous position on the extent of the delay. Has contractor put LAUSD on notice of additional impacts, or ripple effects, e.g. lost productivity, wage and material price increases, etc.? If so, require a detailed cost proposal from the contractor. Never consider, Time extension or impacts to be determined later. Contract requires time extension and impacts to be part of the COP. 12
13 Reviewing the Contractor s COP Is all the scope covered? Credits accounted for? Are all required trades represented. Identify differences in quantities between COP and Fair Cost Estimate. Assess labor hours and crew make-ups. Are costs acceptable; labor, material, equipment, etc. Is every thing in line with the ground rules established a the first negotiation meeting, see below. If acceptable issue a CO. No need to negotiate. If unacceptable, list in writing queries on portions of disagreement and call a meeting. 13
14 Negotiating the Change Negotiation Preparation. Setting the initial ground rules with the contractor. Negotiation Meeting. 14
15 Negotiation Preparation Review your detailed notes in advance. Have key documents at hand. Determine LAUSD participants. The fewer the better. You as the OAR want to be known by the contractor as the decision maker. Consider having estimator present. 15
16 Setting the Initial Ground Rules The first negotiation with the contractor is the most important. It establishes processes, expectations and cost standards. Be personable but contractual; do not involve personalities. Enforce the requirements of the contract. Make the contractor aware of the standards of documentation and backup required if it expects to be paid. 16
17 Setting the Initial Ground Rules, Cont. Develop agreement on cost standards. Follow the contract, but set specifics about; Labor rates Equipment rates Standard material Crew make-up Unit prices, etc. Remember, whatever you do or agree to in the very first meeting will set the contractor s expectation from that point on. 17
18 Negotiation Meeting First, give the contractor it s say. Have it walk through why there is a change from its perspective. Take notes. Be personable but contractual. Discuss LAUSD position after contractor establishes its position. Have contractor rebut LAUSD position, not the other way around. This causes the contractor to recognize the weaknesses in its position and make it more likely to negotiate. If and only if a scope change is agreed to, discuss quantities, labor hours, etc., save costs until the end. 18
19 Negotiation Meeting, Cont. Have a computer handy with the fair cost estimate spreadsheet; fill it in as you negotiate and the final number will calculate. Try to find points of agreement early on in the discussion, focus on discrepancies after that builds credibility with the contractor. Document agreements made and why on record of negotiation form. Work to reach resolution on all items, remember the intent is to close the issue. 19
20 When Negotiations Fail to Fully Resolve the Issue If issue fully resolved follow the contract, get the change order out timely. May need to issue an expedited change order for that portion of change agreed to or for LAUSD fair cost estimate. Make the contractor fill in the blank as to the disputed amount of the change order on the change order form. Document LAUSD position on the issue in correspondence. 20
21 Why is good documentation important? Facilitates approvals easier from upper management & Inspector General audits. Demonstrates and records that LAUSD is following contractual procedures. Becomes an official record of what transpired for future reference. Documents the contractor s and LAUSD s contemporaneous position important if there is a later claim. Document, who, what, when, where & why. 21
22 When Contractor s Pricing is Late Contractors do not always respond to requests in a timely manner. Remind contractor at weekly meetings of outstanding COPs. Record in minutes. Issue dunning letters to contractor. Instruct contractor that failure to submit a COP by required date will precipitate issuance of a CO per Deny the COP as untimely when necessary. 22
23 Well Documented Change Orders include: Change Order Checklist CO generated from the CO Workbook CO logged in Expedition CO signed by all required parties Justification included Record of negotiation included OAR estimate / Fair Cost Estimate COP submitted RFC submitted, if applicable 23
24 Example of a Well Documented Negotiation Process 24
25 Example 25
26 Example 26
27 Example 27
28 Example 28
29 Example 29
30 Example 30
31 Example 31
32 10 most important things to consider 1. Do your homework & prepare a complete folder. 2. Research the issue to ensure it is a real CO item. 3. Be fair, courteous & professional throughout process. 4. Avoid the blame game; e.g. A/E mistake. 5. Expedite the process to meet the 60 day billable metric. 6. Understand Contractors means and methods both original and changed. 7. Bring related documentation to meeting for reference; e.g. RFC, drawings, etc. 8. Be prepared to compromise. 9. Deal with all the issues & not just the easy items INSIST on submission of time extension requests and impact costs with the COP if applicable. 10.Take care in the preparation of documentation and make it simple for others to understand on review. 32
33 10 most things that hinder process 1. Failure to establish proposal standards to be met by contractor at the beginning; even if you join a project underway set your own standards. 2. Participant opinions not based on the contract documents and GCs. 3. Having an adversarial attitude towards contractor. 4. Attitude to prove you are right. 5. Contractor not submitting the COP in a timely manner. 6. Proposal not based on GC guidelines. 7. Quibbling with the Contractor on small items and not focusing on the larger issues. 8. Getting upset when feelings are hurt. 9. OAR unwilling to make up own mind on differing positions. 10.Poor documentation, including conflicting or overly complex explanations. 33
34 What our Negotiators have to say! Input from: Marcy Szarama Issue Support Group Steven Ross Close-out Phillip Cotton Central Region 34
35 QUESTIONS 35
APPENDIX D CONSTRUCTION PHASE CRITERIA
A. GENERAL REQUIREMENTS CONSTRUCTION PHASE CRITERIA For the Construction Phase of the Project, the Architect/Engineer (A/E) is responsible for providing project administration for the Owner in accordance
More informationMinistry of Transportation. WBCMS Manual. Item Postings & Reconciliation Guide. Contract Management and Operations Branch
WBCMS Manual Item Postings & Reconciliation Contract Management and Operations Branch Table of Contents Introduction... 2 Item Postings... 3 Item Postings... 3 Reconciliation Item Postings... 9 Support...
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationATTACHMENT D SCOPE OF SERVICES
ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.
More informationROLES AND RESPONSIBILITIES
Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationConstruction Documents Education Program
PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected
More informationA Failure to Communicate
A Failure to Communicate Professional liability insurers agree: the most effective step design firms can take to lessen the chances of a claim is to improve client communications. In fact, a study of more
More informationPre-Construction Conference Discussion Guide
Pre-Construction Conference Discussion Guide This guide is a summary of the topics normally required at the Pre-Construction Conference based upon the Tennessee Board of Regents Designers Manual standard
More informationA62 PRE-CONSTRUCTION MEETING AGENDA
Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:
More informationDesign Build: CCDC
Ontario Association of Architects Practice Tip PT.23.6 Version 2.0 August 14, 2018 Design Build: CCDC 14-2013 2018, 2015 Ontario Association of Architects (OAA). OAA members in good standing may reproduce
More informationA62 UT PRE-CONSTRUCTION MEETING AGENDA
Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:
More informationEJCDC Contract Documents for America s Infrastructure Buy online at
EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationLessons Learned Impacting Bridget Malinowski and John Stevens
Lessons Learned Impacting 2015 Bridget Malinowski and John Stevens Agenda Review lessons learned Maintain the schedule Potential change orders Agency coordination Claims process Design and construction
More informationContract Interpretation The grievance alleges that a provision of the contract, other than the just cause provision, was violated.
HANDLING GRIEVANCES 1. What is a Grievance? Grievances are defined under the contract. Be sure to know your timelines for filing a grievance and moving the grievance to the next step, if necessary. Generally,
More informationQ&A from the PSMJ Resources, Inc. / XL Group Webinar on September 18, 2012: Developing Satisfied Clients: 6 Steps That Can Save Your Assets
Q&A from the PSMJ Resources, Inc. / XL Group Webinar on September 18, 2012: Developing Satisfied Clients: 6 Steps That Can Save Your Assets Q: Can you give us examples of how to set up a procedure to ID
More informationConstruction Family of Documents
Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications
More informationCONSTRUCTION DOCUMENTS Part 1
Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org
More informationEJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center
EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction
More informationPartnering for Alternative Delivery Projects
Partnering for Alternative Delivery Projects Presented by: Renee L. Hoekstra, CVS Managing Partner RHA, LLC Julie Kliewer, PhD, P.E. State Construction & Materials Engineer - ADOT Training Objectives Understanding
More informationSounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build
When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits
More informationExamples of solicitation provisions and contract clauses that grant audit access to representatives of the Federal government include:
Most folks reading this blog understand that when you contract with the Federal government indeed, when you merely submit a proposal in an attempt to win a contract award from the Federal government you
More informationGENERAL REQUIREMENTS
CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 01001-1 PART 1 GENERAL 1.1 Work Covered By Contract Documents.1 Work covers, in general terms: demolition, removals, site preparation and complete construction
More informationAPWA Public Works Construction Management Seminar. March 22, 2018
APWA Public Works Construction Management Seminar March 22, 2018 Seminar Objectives Exchange of Ideas CM - Definition & Purpose Relationship to Overall Effort Your Expectations Working with Contractors
More informationOwner's Representative Scope Matrix - D/B Rev 10/28/2013
Ecluded Owner's Representative Scope Matri - D/B Rev 10/28/2013 The following matri is a worksheet to identify required and optional scope for Owner's Representative services. Please identify the scope
More informationEXHIBIT 6 Preconstruction Work
EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements
More informationUser Guide. Version 1.1 9/10/2015
BILLING SOLUTION User Guide Version 1.1 9/10/2015 TABLE OF CONTENTS ABOUT THIS DOCUMENT... 2 REPORT CODE DEFINITIONS...2 BILLING SOLUTION OVERVIEW... 2 ROCK-POND REPORTS DIVE IN... 2 IS MY PRICING CORRECT?...2
More informationECI: Two-Stage Contracts
ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /
More informationSuccessful Security Consulting
Successful Security Consulting Extended Consulting Services: Assessing, Designing and Implementing Integrated Management and Technical Solutions Frank Pisciotta, CSC President & Principal Consultant Business
More informationAudio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program
Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications
More informationCode of Conduct for Members of The Federation of Master Builders Limited
Code of Conduct for Members of The Federation of Master Builders Limited Code of Conduct for Members Members of the Federation of Master Builders (FMB) agree to comply with the requirements of the Code
More informationCONSTRUCTION MANAGEMENT CORE COMPETENCIES
CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...
More informationDesign and Build the NEC3 Way Getting the right results. 05/11/2015 NEC Contracts 1
Design and Build the NEC3 Way Getting the right results 05/11/2015 NEC Contracts 1 Design and Build with NEC3 Interactive Collaborative Informative Useful 2 Design and Build with NEC3 What is Design and
More information3. After a STPA, MPSA, or VSA is completed and signed, what is needed to receive a PO from CA for work to begin?
Partner On-Boarding 1. What is needed to become a CA Services partner contractually? All vendors, prior to working with CA are required to have a Vendor Services Agreement (VSA) or Single Transaction Partner
More informationPrime Contractor and Subcontractor Requirements for Web-based Certified Payroll Reporting
CHAPTER 6 ONLINE TOOLS Prime Contractor and Subcontractor Requirements for Web-based Certified Payroll Reporting S ubcontractors must know the terms of the contracts they enter with Prime Contractors in
More informationChoosing an External Auditor: A Guide to Making a Sound Decision, Developed by the Mid-America Intergovernmental Audit Forum
Choosing an External Auditor: A Guide to Making a Sound Decision, Developed by the Mid-America Intergovernmental Audit Forum Introduction Regardless of the type or size of public entity you are affiliated
More informationDoing the Footwork: Preparing for Arbitration
Doing the Footwork: Preparing for Arbitration By Ginger Staton, PHR Your agency has a grievance that is going to arbitration... now what? Even the inexperienced can do the footwork necessary to prepare
More informationSECTION 50 CONTROL OF WORK
SECTION 50 CONTROL OF WORK 50-01 AUTHORITY OF THE ENGINEER. The Engineer shall decide any and all questions which may arise as to the quality and acceptability of materials furnished, work performed, and
More information12: Unemployment Services
12: Chapter Contents Menu... 12-2 Unemployment Benefit Overview... 12-4 File a Claim... 12-4 File for Weekly Benefits... 12-4 Claim Summary... 12-5 Benefit Rights Information... 12-5 Claimant Details...
More informationETHICS PANEL. Panelists: John Baron, P.E. Gary DiPippo, P.E. Thomas Gonnella, ESQ Victoria Schmitt, P.E. Moderator: Mark A. Swyka, P.E.
ETHICS PANEL Panelists: John Baron, P.E. Gary DiPippo, P.E. Thomas Gonnella, ESQ Victoria Schmitt, P.E. Moderator: Mark A. Swyka, P.E. The Code is the Law Code of Ethics for Engineers Engineering is an
More informationCHAPTER 12: LABOR STANDARDS
CHAPTER 12: LABOR STANDARDS CHAPTER PURPOSE & CONTENTS This chapter provides states with general information on labor standards as these requirements apply to CDBG-funded construction work. The following
More information7 top tips for successful credit managers
Smarter Receivables 2011 Moreton Smith Ltd. All trademarks, service marks and trade names referenced in this material are the property of their respective owners. Following our recent webinar with Bill
More informationProcurement & Contracting
Procurement & Contracting Overview The procurement of goods and services and executing related contracts is a major function of transit management. In addition to seeking to obtain the highest quality
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September
More informationENTELEN Design-Build, LLC June 29, 2015 SUBJECT: JOB DESCRIPTION PROJECT MANAGER Page 1 of 6
SUBJECT: JOB DESCRIPTION PROJECT MANAGER Page 1 of 6 1.0 JOB DESCRIPTION SUMMARY The primary role of the Project Manager (PM) is to manage projects to insure that work is done according to specifications
More informationConnoisseur Solutions Project Procurement Management
Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes
More informationLawful Terminations Checklist
Lawful Terminations Checklist 2 6 STEPS TO CONDUCT SAFE TERMINATIONS We all know employees are generally at-will, meaning anyone can leave with or without reason or notice and conversely, an employer can
More informationFebruary Significant reduction in delays, unexpected costs and disputes between the parties arising during construction.
February 2014 The major benefits to the Owner in a design and construction program carried out by employing the Bridging method are listed and discussed below along with the benefits to the Owner s Design
More informationChoosing Delivery Method
Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing
More informationThe construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.
L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally
More informationBID PHASE GUIDELINES
Chapter 7 BID PHASE GUIDELINES A. INTRODUCTION 1. The Bid Phase starts once the project has been accepted by the OGS D&C Office of Project Control (OPC) and passed on to the OGS D&C Office of Contract
More informationProject Management Information System
Project Management Information System a UNIFIER TM deployment The Project Controls Group Mission Analyze the organization structure and information needs and configure UNIFIER TM to suit that organization
More informationAuditing Timeline. Top-Line Version
Auditing Timeline Top-Line Version As a complement to their book Agency Audits: How to Achieve Success, Joanne Davis and Jane Twyon have created a timeline that takes marketers through the auditing journey.
More informationTHE ROLE OF A BRIDGE INSPECTOR
C.1 The Role of a Bridge Inspector - General The Contractor is responsible for constructing the bridge in full accordance with the Plans and Specifications. The Bridge Inspector s role is that of ensuring
More informationBOROUGH OF BERLIN. Municipal Planning Board Engineer. Term: January 1, 2018 to December 31, 2018.
BOROUGH OF BERLIN REQUEST FOR QUALIFICATIONS FOR MUNICIPAL ATTORNEY, MUNICIPAL AUDITOR, MUNICIPAL BOND COUNSEL, MUNICIPAL ENGINEER, MUNICIPAL WATER & SEWER ENGINEER, MUNICIPAL PROSECUTOR, MUNICIPAL PUBLIC
More informationPOSITION DESCRIPTION September 2017
POSITION DESCRIPTION September 2017 Classification: Team / Section: Bureau / Division: Position Number: CONSTRUCTION REPRESENTATIVE - JOURNEY Construction Quality Control / Construction Oversight Architecture
More informationBuy The Complete Version of This Book at Booklocker.com:
This book is about commercial and government audit principles. What Makes a Good Audit? Buy The Complete Version of This Book at Booklocker.com: http://www.booklocker.com/p/books/4335.html?s=pdf What Makes
More informationNATIONAL ARBITRATION BEFORE IMPARTIAL ARBITRATOR STEPHEN B. GOLDBERG. ) UNITED STATES POSTAL SERVICE ) Case No. Q10T-4Q-C
NATIONAL ARBITRATION BEFORE IMPARTIAL ARBITRATOR STEPHEN B. GOLDBERG In the Matter of Arbitration ) between ) ) ) UNITED STATES POSTAL SERVICE ) Case No. Q10T-4Q-C -13332310 and ) AMERICAN POSTAL WORKERS
More informationCOMMERCIAL MANAGEMENT. Construction Law Competencies
COMMERCIAL MANAGEMENT Construction Law Competencies To exhibit an understanding of contract and civil engineering construction law, to support and recommend appropriate strategies to other members of the
More informationA Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E.
A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E. Last Planners prepare assignments for people who do work. Last Planners can be found throughout construction
More informationSTATE OF NORTH CAROLINA Office of the State Auditor
STATE OF NORTH CAROLINA Office of the State Auditor Ralph Campbell, Jr. State Auditor 2 S. Salisbury Street 20601 Mail Service Center Raleigh, NC 27699-0601 Telephone: (919) 807-7500 Fax: (919) 807-7647
More informationBY BETYE BAILEY, INTOXIMETERS, INC.
BY BETYE BAILEY, INTOXIMETERS, INC. A DEFENSIBLE BREATH hallenges or objections are going to arise after positive tests, not negative ones. In law enforcement, the most litigated offense in the United
More information13. Contract Changes General Change Order Process
13. Contract Changes 13.1. General 13.2. Change Order Process 13.3. Equitable Adjustments 13.4. Interim Work Authorization 13.5. Requirements for Professional Seals 13.6. Supplemental Agreements 13.1.
More informationChapter 2 Parties to the Contract
Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,
More informationREQUEST FOR PROPOSAL. HRIS Human Resources Information Software Fort Morgan, Colorado
REQUEST FOR PROPOSAL HRIS Human Resources Information Software Fort Morgan, Colorado October 7, 2014 Michael Boyer Director, Human Resources and Risk Management CITY OF FORT MORGAN P.O. BOX 100 FORT MORGAN,
More informationContracting 3 rd Party Major Maintenance Field Services K Pope & W Davis. 6/16/2010 6F Conference SA, Texas
Contracting 3 rd Party Major Maintenance Field Services K Pope & W Davis 1 Contracting 3 rd Party Field Services Pros and Cons of using 3 rd Party Field Services Developing a Bidders List Developing a
More informationRecord your conversation with a Tradesman
Record your conversation with a Tradesman In 11 simple steps you will have the right conversation with a tradesman. This checklist will help you ask the right questions of any tradesman you are asking
More informationCONSTRUCTION PROCEDURES MANUAL PROJECT
CONSTRUCTION PROCEDURES MANUAL ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS (DATE) Page 1 ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS TABLE OF CONTENTS CONTENTS PAGE: 1.0
More informationImprove Your Bottom Line - Increase Your Modeling Return On Investment Axis Software Designs, Inc. All Rights Reserved
Improve Your Bottom Line - Increase Your Modeling Return On Investment All Rights Reserved Welcome! Let Me Introduce Myself Marcie Barkin Goodwin President & CEO Axis Software Designs mbg@axisboulder.com
More informationAttachment 1 Architectural Services
A. Phase 1, Programming and Schematic Design: 1. Ascertain the requirements for each project through a meeting with the COUNTY, and a review of an existing schematic layout of each project, if such layout
More informationCHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS
CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical
More informationCity of Seattle Request for Proposal # FAS-4261 Addendum
The following is additional information regarding Request for Proposal # FAS-4261, titled Online Public Surplus Auction, released on 10/17/13 The due date and time for responses remains as 11/08/13 at
More informationAlbany Unified School District Contractor Prequalification
Albany Unified School District Contractor Prequalification The Albany Unified School District ( District ) has determined that contractors providing construction services ( Contractor(s) or Firm(s) ) must
More informationPrime Contractor and Subcontractor Requirements for Web-based Certified Payroll Reporting
CHAPTER 6 ONLINE TOOLS Prime Contractor and Subcontractor Requirements for Web-based Certified Payroll Reporting S ubcontractors must know the terms of the contracts they enter with Prime Contractors in
More informationCh 7 - Account for Differences
Ch 7 - Account for Differences 7.0 - Chapter Introduction 7.1 - Identifying Vendor-Related Differences o 7.1.1 - Responsibility o 7.1.2 - Understanding Of Requirements o 7.1.3 - Technology o 7.1.4 - Efficiency
More informationG , Request for Proposal Land Survey
G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994
More informationPresenting Audit Results
Presenting Audit Results Presenters: Lori Carmichael, CPA Rafael Guijarro, CPA Florida Michigan North Carolina Texas Insight. Oversight. Foresight. Overview 2 Insight. Oversight. Foresight. Overview Standards
More informationCOMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202
COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning
More informationARD OPERATIONAL PROCEDURE 6.- Audit Reporting
1. Purpose The purpose of this procedure is to provide guidance and authority to internal auditors in the reporting of their work and to ensure consistency and completeness of the reporting function. 2.
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationHow to protect your school against employment claims
How to protect your school against employment claims It goes without saying that employment disputes can be both disruptive and costly. This short guide provides some useful advice to help your school
More informationDESIGN IS GOOD BUSINESS
PROJECT DELIVERY: AN INTRODUCTION A profound design process eventually makes the patron, the architect, and every occasional visitor in the building a slightly better human being. JUHANI PALLASMAA The
More informationCHAPTER 6: MARKER FOR UT CONSTRUCTION CHANGES
CHAPTER 6: MARKER FOR UT CONSTRUCTION CHANGES The following designations have been supplemented to reflect requirements by UT. Changes are noted in Owner Information Section of this Manual unless noted
More informationSTUDENT GUIDE. CON 170 Fundamentals of Cost & Price Analysis. Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems
STUDENT GUIDE CON 170 Fundamentals of Cost & Price Analysis Unit 5, Lesson 1 Cost Analysis Process, Players, and Business Systems January 2017 CON170, Unit 5 Lesson 1 Cost Analysis Process and Players
More informationFlorida Institute of Technology
Florida Institute of Technology Procurement Policy POLICY SOURCE: Procurement Services POLICY NO.: 5383 SUPERCEDES: 5382 TITLE: Procurement Policy SUBMITTED BY: Purchasing REVISED DATE: May 1, 2017 APPROVED
More informationPerformance Skills Leader. Individual Feedback Report
Performance Skills Leader Individual Feedback Report Jon Sample Date Printed: /6/ Introduction REPORT OVERVIEW Recently, you completed the PS Leader assessment. You may recall that you were asked to provide
More informationRequirements Validation and Negotiation
REQUIREMENTS ENGINEERING LECTURE 2014/2015 Dr. Sebastian Adam Requirements Validation and Negotiation AGENDA Fundamentals of Requirements Validation Fundamentals of Requirements Negotiation Quality Aspects
More informationDesign Build - Project Delivery Model Trends
Drag picture to placeholder or click icon to add Drag picture to placeholder or click icon to add Drag picture to placeholder or click icon to add Design Build - Project Delivery Model Trends Sean M. Collins,
More informationAMERICAN FEDERATION OF GOVERNMENT EMPLOYEES AFL-CIO, LOCAL 1145
In the matter of Arbitration between.................................... AMERICAN FEDERATION OF GOVERNMENT EMPLOYEES AFL-CIO, LOCAL 1145 AND FEDERAL BUREAU OF PRISONS U. S. PENITENTIARY, ATLANTA, GEORGIA
More informationNW Region Tribal Transportation Symposium March 6-9, PROJECT DOCUMENTATION for Tribes Administering Construction Projects
NW Region Tribal Transportation Symposium March 6-9, 2017 PROJECT DOCUMENTATION for Tribes Administering Construction Projects Slides adopted from Karl Gleason, FHWA - Senior Tribal Coordinator, presentation
More informationAppendix D University of Maine System. Supplementary Requirements to AIA Document B Standard Form of Architect s Services
Appendix D University of Maine System Supplementary Requirements to AIA Document B201-2007 Standard Form of Architect s Services This document provides the Architect s scope of services only and must be
More information1/12/2015. Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach
Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach DRAFT for AIA CCA Knowledge Community 2015 Dale Munhall, AIA not a sign of teamwork Director of Construction
More informationNegotiation Skills. Copyright 2018 The Seller-Doer Academy 1. How to Test Your Value Proposition
Negotiation Skills How to Test Your Value Proposition The Seller Doer Academy for Civil Engineers has met the standards and requirements of the Registered Continuing Education Program. Credit earned on
More informationSuperintendent Job Description:
Superintendent Job Description: General Summary: Responsible for the overall onsite management of a project from inception to final acceptance. This includes, but is not limited to; all onsite planning,
More informationUniform Guidance Purchasing Updates. What University Administrators and PIs Need to Know
Uniform Guidance Purchasing Updates What University Administrators and PIs Need to Know Executive Summary The Uniform Guidance (UG) governs the management of federally funded sponsored projects across
More informationREPORT 2014/010 INTERNAL AUDIT DIVISION. Audit of contract administration at the United Nations Office at Geneva
INTERNAL AUDIT DIVISION REPORT 2014/010 Audit of contract administration at the United Nations Office at Geneva Overall results relating to administration of contracts at the United Nations Office at Geneva
More informationBEFORE: Joshua M. Javits, ARBITRATOR. APPEARANCES: For the Agency: Loretta Burke. For the Union: Jeffrey Roberts
) In the Matter of the Arbitration ) Grievance: National Grievance ) (Arbitrability) Between ) ) FMCS No. 13-51599 FEDERAL BUREAU OF PRISONS ) ) Agency ) ) And ) ) AMERICAN FEDERATION OF ) GOVERNMENT EMPOYEES,
More informationCONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationWhich Documents Govern when they Differ? Precedence of the Contract Documents By Arthur F. O'Leary, FAIA, MRIAI
Page 1 of 7 ABOUT DCD THE MAGAZINE D4COST CONTACT HOME Current Issue Click here to read the issue. Click Here To Access The DCD Archives Content/Departments Current Issue Issue Archive Specifiers Spotlights
More informationManaging Conflict & Difficult People/Situations
Managing Conflict & Difficult People/Situations SANDRA PLENSKI ASSOCIATE DIRECTOR OF BUSINESS OPERATIONS UC Hastings College of the Law Bursar s Conference-April 2017 Ponte Vedra Beach, Florida Does it
More information4/23/2014. Hot Button Topics. Other Issues. Wage and Hour Audits: What to Do When the Department Comes Knocking and Related Hot Buttons in Audits
Wage and Hour Audits: What to Do When the Department Comes Knocking and Related Hot Buttons in Audits Thomas Kennedy Karla Sanchez 480.624.2725 303.299.8418 tkennedy@shermanhoward.com ksanchez@shermanhoward.com
More information