1 BEFORE THE PUBLIC SERVICE COMMISSION OF WISCONSIN APPLICATION OF WISCONSIN PUBLIC SERVICE CORPORATION FOR AUTHORITY TO ADJUST ELECTRIC AND NATURAL GAS RATES DOCKET 6690-UR-124 Ex.-WPSC-Beyer-1
2 Ex.-WPSC-Beyer-1 Page 1 of 9 WISCONSIN PUBLIC SERVICE CORPORATION 2016 ELECTRIC EXTENSION ALLOWANCE CALCULATIONS The proposed 2016 distribution system investment extension allowances for the "Electric Extension Rules" were calculated using the methodologies described below cost of service data was used based on the commission Staff s preferred method of allocating plant costs by 70% group coincident demand and by 30% customer count. Page 4 contains the embedded cost allowances based upon the 70/30 split. 1. RESIDENTIAL CUSTOMERS The net distribution plant investments for accounts 364, 365, 366, and 367 were divided by the total number of 383,293 residential customers (see Exhibit WPSC-Beyer-1, page 4). See Page 4 for the calculated allowance value of $ DEMAND AND ENERGY COMMERCIAL AND INDUSTRIAL CUSTOMERS The net distribution plant investments for accounts 364, 365, 366, and 367 were divided by the total maximum customer non-coincident peak demands that occurred in the year multiplied by 12 to arrive at a dollar per kw allowance. See Page 4 for the calculated allowance value of $36.80/kW. 3. ENERGY-ONLY COMMERCIAL AND INDUSTRIAL CUSTOMERS a. Interval Data: To obtain needed customer load information, the interval data for energy only customers on the Cg rate schedules was used. The data from three representative months during the period of January 2014 to July 2014 was accumulated. One month from each of the following periods were chosen: Summer Peak (July) Winter Peak (January) Fall/Spring Off-Peak (April) Data from 1,627 customers was available in January 2014, 1,621 customers in April 2014, and 1,763 customers in July During the year, sample groups of customers were in the process of change resulting in more or less customers. b. Data Analysis: The individual customer load information utilized in this study was: Monthly usage Monthly customer maximum demand Monthly customer group coincident demand
3 This customer data was grouped into three categories by monthly usage. 0-3,000 kwh 3,001-15,000 kwh 15,001 and over kwh Ex.-WPSC-Beyer-1 Page 2 of 9 The usage and demand data was totaled for all customers in each of the three categories. These totals were then used as follows: 1) Usage and customer maximum demand was used in load factor calculation to determine customer demand range corresponding to the breakpoint between the three categories. 2) Customer group demand was used along with customer count to allocate net plant to the two highest demand ranges. The totals are shown on Page 5 while the calculated load factors and calculated demand ranges are displayed on Page 6. The demand range limits were calculated as follows: 3,000 kwh Hrs Ave Load Factor 744 mo. X = 17.4 kwh/mo. 15 kwh will continue to be used as the breakpoint. 15,000 kwh Hrs Ave Load Factor 744 mo. X = 49.3 kwh/mo. 50 kwh will continue to be used as the breakpoint. c. Customer Calculation: Average customer counts for the period January 2014 through December 2014, bill summaries by usage range were used to calculate the number of customers in the demand ranges determined above. Page 7 shows the bill summaries for the energy-only Cg rate schedules. The calculation of the number of customers is shown on Page 8. d. Net Plant Allocation: The net plant in accounts for the Cg-1 under 100 kwh (energy only) customers was allocated by weighting the group coincident demand by 70% and the customer counts by 30%. This allocation method is consistent with "cost of service" studies preferred by the commission Staff. See below for calculation of the net plant totals used in this study: 364, 365, 366, Cg-1 & Cg-2 Energy Only & 367 Plant Net Plant per Cust 1 x No. of Cust 2 = Net Plant Cg: $ x 52,443 = $33,151, From Ex.-WPSC-Beyer-1, page 4) 2. From Ex.-WPSC-Beyer-1, page 8) The net plant totals are then allocated to the three demand ranges above by using the same 70%/30% allocation method mentioned above. The allocation percentages for
4 Ex.-WPSC-Beyer-1 Page 3 of 9 the two higher demand ranges were calculated on Page 8, Sections A and B. The customer counts were taken from Page 8, Section B. The group demand allocators were calculated on Page 8, Section A. The allocation for the 0-15 kwh group was made assuming the $ per customer that is used for residential customers. The remaining net plant was divided between the other two groups using the above allocators. The calculation is shown on Page 8, Section C. e. Allowance calculation: The net distribution plant allocations from d. above are divided by the customer counts from c. above, to arrive at the allowances. They are on Page 8, Section D.
5 Wisconsin Public Service Corporation Year Ending December 31, 2016 Electric Extension Allowance Calculation Ex.-WPSC-Beyer-1 Page 4 of 9 Energy Only Billed Demand Billed Residential C & I C & I Lighting Description Account Cost / Customer Cost / Customer Cost / KW Cost / Lamp GROSS PLANT 3640 $ $ $16.55 $ GROSS PLANT 3650 $ $ $20.81 $39.11 GROSS PLANT 3660 $8.30 $25.19 $3.52 $0.86 GROSS PLANT 3670 $ $ $32.57 $ ACCUM DEPRECIATION $ $ $ $ ACCUM DEPRECIATION $ $ $ $23.85 ACCUM DEPRECIATION $3.98 -$ $1.69 -$0.41 ACCUM DEPRECIATION $ $ $ $51.85 $ $ $36.80 $192.49
6
7
8 Ex.-WPSC-Beyer-1 Page 7 of 9 Wisconsin Public Service Corporation Year Ending December 31, 2014 Customer Bills 2014 Bills For Rate Classes: Cg-1 < 50 Cg Cg-3 OTOU kwh 2014 Bills , , , , , , , , , , , , , , ,000 15,919 1,001-1,500 59,292 1,501-2,000 39,288 2,001-3,000 47, ,547 3,001-4,000 30,109 4,001-5,000 20,083 5,001-10,000 43,031 10,001-15,000 5,746 98,969 15,001-20, ,001-25, ,001-30, ,001-50, ,001-70, , , , , , , ,001-1,000, ,000,001-2,000, ,000,001-6,000, ,000,001-10,000,000 0 >10,000, , ,424 / Adjustment 0-3,000 kwh \ Adj Pct Range Bills Adjustment Original Adjusted less: 50% 2,001-3,000 47,601-23,801 less: 25% 1,501-2,000 39,288-9,822 less: 10% 1,001-1,500 59,292-5,929 plus: 25% 3,001-4,000 30,109 7,527 plus: 10% 4,001-5,000 20,083 2,008-30, , ,531 / Adjustment 3,001-15,000 kwh \ Adj Pct Range Bills Adjustment Original Adjusted Diff Between End and Beginnig ,016 Diff Between End and Beginnig & Over -12,027 17,989 98, ,958 / Adjustment >15,000 kwh \ Adj Pct Range Bills Adjustment Original Adjusted Less 25% 15,001-20, Less 10% 20,001-25, Plus 25% 4,001-5,000 20,083 5,021 Plus 10% 5,001-10,000 43,031 4,303 Plus 50% 10,001-15,000 5,746 2,873 12, ,935 Total 0 593, ,424
9 Ex.-WPSC-Beyer-1 Page 8 of 9 Wisconsin Public Service Corporation Year Ending December 31, 2014 Customer Bills A. Calculation of Group Demand Allocators Total Group Demand No. of Cust Group X in Demand Range = Demand Range Demand No. of Customers (From Sect B.) Group Demand Allocators 21, kw , ,904 kw ,479 13, & >kw ,143 43,545 kw Total 192,450 kw B. Calculation of Customer Allocators 2016 / Bills \ 2016 Customers Demand Bills Customer PCT Customers Allocated To Customer Range From Page 7. Customers By Demand Range (Section C Below) Demand Range Allocators 463, kw , X 52,443 = 40, , kw , X 52,443 = 10, , & >kw , X 52,443 = 1, Customers 49, , Note: Forecasted customers for these rate schedules are allocated to demand ranges C. Net Plant Allocation Total Net Plant To Reallocate /-- From Section D of Write Up --\ Net Plant 2016 Total Per Customer Customers Net Plant Cg-1, Cg-2, Cg-3, ,443 33,151,563 Cg-4,Cg-5 52,443 33,151,563 Reallocation of Net Plant 0-15 kw Total Net Plant 0-15 kw Net Plant To / Customer \ /----- Group Demand \ Customer & Demand Customers Per Customer Net Plant Be Reallocated Allocator Allocator PCT Allocator Allocator PCT Demand Net Plant Range (Sect B.) (Page 4) Allocated to kw (Sect. B) 30% (Sect. A) 70% Allocator Re Allocated 0-15 kw 40, ,256,604 18,256, kw 14,894, ,090, & >kw 14,894, ,804, ,151,563 D. Allowance Calculation Calculated Proposed Demand Range Calculation Allowance Allowance 0-15 kw Same as Residential $446 $450 Net Plant Allocated 12,090, kw = $1,170 $1,170 Customers 10,336 Net Plant Allocated 2,804, & >kw = $2,454 $2,455 Customers 1,143 Residential From Page 1 $446 $450 Billed Demand C&I Per kw From Page 1 $37 $37
10 Wisconsin Public Service Corporation History of Electric Extension Rule Allowances Ex.-WPSC-Beyer-1 Page 9 of 9 Customer Proposed Class Effective: kw $118 $145 $170 $195 $185 $180 $205 $205 $360 $425 $ kw $475 $570 $645 $750 $865 $940 $1,130 $1,130 $1,065 $1,060 $1, & > kw $1,645 $1,840 $2,280 $2,265 $2,215 $2,095 $2,640 $2,640 $2,280 $2,470 $2,455 Per kw $36 $41 $38 $33 $31 $33 $33 $33 $27 $27 $37
11 Ex.-WPSC-Beyer-1 Schedule 2 Page 1 of 1 Wisconsin Public Service Corporation Derivation of NatureWise Incremental Costs Proposed WPSC-WI Rate Case 6690-UR-124 Power Supply Costs Renewable Power Generation (kwh) Forecast Ave Cost % of Total ($/kwh) WTD Ave Cost ($/kwh) Ag/Bio/Landfill 144,496,560 50% $ $ Wind 118,651,260 50% $ $ Average Renewable Power ($/kwh) $ Non Renewable Power Rate Hours Cost Capacity On Peak Energy $ , Off Peak Energy $ , Total 8, Total Non Renewable Power ($/kwh) $ Incremental Power Supply Costs ($/kwh) $ Non Power Supply Costs Program Administration $4,900 Total Non Power Supply Costs $4,900 Forecasted kwh Renewable Sales 8,917,200 Non Power Supply Costs/kWh $ Total Incremental Costs/kWh $0.026 Total Incremental Cost/ 100kWh Block $2.60
12 WISCONSIN PUBLIC SERVICE CORPORATION Ex.-WPSC-Beyer-1 Schedule 3 Page 1 of 1 P.S.C.W. Volume No. 7 4th Rev. Sheet No. E4.42 Replaces 3rd Rev. Sheet No. E4.42 Amendment XXX Schedule Ls-1 Outdoor Overhead Lighting Service Company-Owned EFFECTIVE IN All territory served. AVAILABILITY Facilities in this section are available to all classes of customers who desire company owned lighting service. MONTHLY RATE Fixture Type Lamp Type Lumens Watts $/Month R R R Post Top Sodium Vapor 5, $17.00 Cobra Head (closed) Sodium Vapor 9, $17.52 Cobra Head (closed) Sodium Vapor 14, $20.00 Cobra Head (closed) Sodium Vapor 27, $24.65 Cobra Head Sodium Vapor 45, $33.06 Cobra Head Metal Halide 8, $23.55 Cobra Head Metal Halide 26, $29.88 Cobra Head (closed) Metal Halide 36, $33.06 LED LED 9,000* 100* $14.47 LED LED 14,000* 150* $18.23 LED LED 27,000* 250* $23.83 Area-Power Bracket Sodium Vapor 9, $14.65 Area-Power Bracket Sodium Vapor 14, $17.96 Directional-Flood Sodium Vapor 27, $29.90 Directional-Flood Sodium Vapor 45, $36.56 Directional-Flood Metal Halide 26, $31.91 Directional-Flood (closed) Metal Halide 36, $36.30 Directional-Flood Metal Halide 110,000 1,000 $55.00 The above charges are for lighting standard facilities on existing company-owned distribution poles. The company will own and install the standard facilities Monthly charges for LED are based on all night burning hours and will be the only option for this rate. * The wattages and lumens listed under the LED lamps are wattages and lumens of sodium vapor lamps to which the LED lamps are considered equivalent. Actual wattages and lumens of LED lamps may vary. Continued to Sheet No. E4.43 Issued XX-XX-XX Effective for Service Rendered On and After XX-XX-XX PSCW Authorization By Order 6690-UR-124 Dated XX-XX-XX
DIRECT TESTIMONY OF HETHIE S. PARMESANO
BEFORE THE NEW YORK STATE PUBLIC SERVICE COMMISSION ----------------------------------------------------------------------------x Proceeding on Motion of the Commission as to the Rates, Charges, Rules
More informationEMBEDDED COST OF SERVICE Kim Wissman Executive Director Ohio Power Siting Board On behalf of NARUC
NARUC Partnership Program Public Utilities Commission of Ohio Ministry of Energy of Ghana Energy Commission of Ghana and Public Utilities Regulatory Commission of Ghana sponsored by United States Agency
More informationWISCONSIN PUBLIC SERVICE CORPORATION. P.S.C.W. Volume No. 7 1st Rev. Sheet No. E7.00 Replaces Original Sheet No. E7.00
WISCONSIN PUBLIC SEVICE COPOATION P.S.C.W. Volume No. 7 1st ev. Sheet No. E7.00 eplaces Original Sheet No. E7.00 Amendment 756 EFFECTIVE IN All territory served. AVAILABILITY This schedule is available
More informationModeling Customer Response to Xcel Energy s RD-TOU Rate
Page 1 of 21 Modeling Customer Response to Xcel Energy s RD-TOU Rate P R E S E N T E D T O Xcel Energy P R E S E N T E D B Y Ahmad Faruqui Ryan Hledik Ap r i l 2 1, 2 0 1 6 Copyright 2016 The Brattle Group,
More informationSCHEDULE OF RATES. For Electric Service in Allegheny and Beaver Counties. Issued By DUQUESNE LIGHT COMPANY
SUPPLEMENT NO. 155 DUQUESNE LIGHT CO. SCHEDULE OF RATES For Electric Service in Allegheny and Beaver Counties (For List of Communities Served, see Pages No. 4 and 5) Issued By DUQUESNE LIGHT COMPANY 411
More informationTexas CREZ Policy and Transmission Expansion Update. Mark Dreyfus December 2, 2010
Texas CREZ Policy and Transmission Expansion Update Mark Dreyfus December 2, 2010 1 Texas Establishes a Renewable Energy Policy Senate Bill 7 (1999) comprehensive restructuring of the electric industry.
More informationWISCONSIN ELECTRIC POWER COMPANY Volume 19 Electric Rates Revision 4 Sheet 71.1 Amendment No. 759 Effective In All Areas Served In Wisconsin
WISCONSIN ELECTIC POWE COMPANY Volume 19 Electric ates evision 4 Sheet 71.1 Amendment No. 759 ate Schedule TMP GENEAL PIMAY SEVICE EAL-TIME MAKET PICING IDE AVAILABILITY This rate is a rider to primary
More informationFocus on Energy Evaluated Deemed Savings Changes
Focus on Energy Evaluated Deemed Savings Changes November 14, 2014 Public Service Commission of Wisconsin This page left blank. Prepared by: Cadmus This page left blank. Table of Contents Deemed Savings
More informationUniversity City MO Street Lighting Study SUMMARY. Funded by the Energy Efficiency and Conservation Block Grant. Authored by.
University City MO Street Lighting Study SUMMARY Funded by the Energy Efficiency and Conservation Block Grant Authored by Jennifer Wendt April 2011 Table of Contents 1. INTRODUCTION... 4 2. DATA RESULTS...
More informationEnergy Forecasting Group, May 10-11, 2012 Las Vegas, Nevada. Terry Baxter, NV Energy
NV Energy Integrating DSM Into The Forecast Energy Forecasting Group, May 10-11, 2012 Las Vegas, Nevada Terry Baxter, NV Energy 2 NV Energy Service Territory NVE Statistics ti ti Mixed results for 2011
More informationHow Have Regulators and Utilities Responded to Revenue Erosion?
June 2017 1 How Have Regulators and Utilities Responded to Revenue Erosion? Dan Hansen Christensen Associates Energy Consulting June 2017 June 2017 2 Utility Fixed Cost Recovery Issues Traditional regulated
More informationMASSACHUSETTS ELECTRIC COMPANY STREET AND AREA LIGHTING HIGH PRESSURE SODIUM VAPOR CONVERSION COMPANY OWNED EQUIPMENT S-20 RETAIL DELIVERY SERVICE
Sheet 1 Canceling M.D.P.U. No. 1145 AVAILABILITY 1. This rate is available to any Customer receiving service on the Street and Area Lighting Company Owned Equipment S-1 rate which agrees to convert all
More informationTHE NARRAGANSETT ELECTRIC COMPANY GENERAL STREET AND AREA LIGHTING SERVICE (S-14) RETAIL DELIVERY SERVICE
Sheet 1 AVAILABILITY General Street and Area Lighting Service is available under this rate to any city, town, governmental entity, or other public authority hereinafter referred to as the Customer, in
More informationUtilities Used in Production
www.taxes.state.mn.us Utilities Used in Production 129 Sales Tax Fact Sheet 129 Fact Sheet Utility exemption Electricity, gas or steam used or consumed in agricultural or industrial production is exempt
More informationSchool Outdoor Lighting Audit Guide
School Outdoor Lighting Audit Guide Adapted with permission from the National Optical Astronomy Observatory. Overview: You will conduct an audit of the types of outdoor lights on one building at your school
More informationReview of SaskPower s Cost Allocation and Rate Design Methodologies. John Todd, Michael Roger May 15, 2017
Review of SaskPower s Cost Allocation and Rate Design Methodologies John Todd, Michael Roger May 15, 2017 5/11/2017 Agenda 1. Project Description 2. Background on Cost Allocation Methodology 3. Elenchus
More informationUtilities Used in Production 129
www.revenue.state.mn.us Utilities Used in Production 129 Sales Tax Fact Sheet 129 Fact Sheet What s New in 2017 We added information on different methods to calculate exempt utility percentages. Utility
More informationBEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION
BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION IN THE MATTER OF THE APPLICATION OF ) OKLAHOMA GAS AND ELECTRIC COMPANY ) FOR APPROVAL OF A GENERAL CHANGE IN ) DOCKET NO. -0-U RATES AND TARIFFS ) Direct
More informationDark Skies Rangers Program
Grades: 5 8 (and 9 12) Overview: Students will be auditing the types of outdoor lights on one building at their school to determine how much energy those lights are using. Students will ultimately be making
More informationCity of Manchester Phase one HPS Cobra Head Replacement With LED Cobra Heads
ATTACHMENT A City of Manchester Phase one HPS Cobra Head Replacement With LED Cobra Heads 10 27 of 34 4/29/2014 City of Manchester HPS Cobra Head Replacement With LED Cobra Heads Streetlight Conversion
More informationATTACHMENT M-2 (PECO) Determination of Capacity Peak Load Contributions, Network Service Peak Load and Hourly Load Obligations PURPOSE
ATTACHMENT M-2 (PECO) Determination of Capacity Peak Load Contributions, Network Service Peak Load and Hourly Load Obligations PURPOSE This document outlines the process by which PECO determines Capacity
More informationWISCONSIN PUBLIC SERVICE CORPORATION
WISCONSIN PUBLIC SEVICE COPOATION P.S.C.W. Volume No. 8 13th ev. Sheet No. G8.00 eplaces 12th ev. Sheet No. G8.00 Amendment 739 Schedule PGAC 1. EFFECTIVE IN: All Territory Served. 2. APPLICABILITY: To
More informationLighting Commercial Spaces 101. An Introduction to LED and Lighting Controls
Lighting Commercial Spaces 101 An Introduction to LED and Lighting Controls 1 Free technology Smart Networked Thermostats Free equipment and installation Centralized Management of Heating and Cooling Equipment
More informationA Brighter Idea Than Fluorescent
A Brighter Idea Than Fluorescent Venture s Uni-Form pulse start metal halide lighting systems are the brighter solution: Greater energy savings! More light: Higher system lumens per watt Lower dirt depreciation
More informationDuke Energy Corporation
Commercial Audit for Account: 12345-56789 Thank you for completing the Duke Energy Corporation Business Energy Check. We hope the information and recommendations provided will assist you in managing your
More informationCost-benefit Analysis of the New Jersey Clean Energy Program Energy Efficiency Programs
Cost-benefit Analysis of the New Jersey Clean Energy Program Energy Efficiency Programs January 9, 2008 Table of Contents I. Summary...3 II. Methodology...4 III. Cost-Benefit Analysis Assumptions...6 IV.
More informationExhibit No. JM-1 Updated Vol.II, pages 2-98 through ELECTRIC ENERGY AND DEMAND FORECASTS
2.6 ELECTRIC ENERGY AND DEMAND FORECASTS Updated Vol.II, pages 2-98 through 2-148 Introduction Projections of future energy and peak demand are fundamental inputs into Public Service s resource need assessment.
More informationRenewable Energy Plan 2013 Biennial Review Lansing Board of Water & Light MSCP Case No. U-16619
Renewable Energy Plan 2013 Biennial Review Lansing Board of Water & Light MSCP Case No. U-16619 This Biennial Review filing by the Lansing Board of Water & Light (LBWL) complies with State of Michigan
More informationUnits. Lighting quantity is primarily expressed in three types of units.
Lighting Efficiency Units Lighting quantity is primarily expressed in three types of units. Watts measure of electrical power that defines the rate of energy consumption. Lumens output of a lamp, how much
More informationLOADS, CUSTOMERS AND REVENUE
Page of LOADS, CUSTOMERS AND REVENUE The purpose of this evidence is to present the Company s load, customer and distribution revenue forecast for the test years. The detailed test year forecasts are shown
More informationEnergy-efficient Lighting for Florida Homes
Energy-efficient Lighting for Florida Homes Authors Parker, Danny Drake, Nick Publication Number FSEC-EN-18-91 Copyright Copyright Florida Solar Energy Center/University of Central Florida 1679 Clearlake
More informationProspective Cost of Service Study. For Fiscal Year Ending March 31, 2011
Prospective Cost of Service Study For Fiscal Year Ending March 31, 2011 Cost of Service Department May 25, 2010 MANITOBA HYDRO PROSPECTIVE COST OF SERVICE STUDY FOR FISCAL YEAR ENDING MARCH 31, 2011 TABLE
More informationENERGY INITIATIVE ENERGY EFFICIENCY PROGRAM Impact Evaluation of Prescriptive and Custom Lighting Installations. National Grid. Prepared by DNV GL
ENERGY INITIATIVE ENERGY EFFICIENCY PROGRAM Impact Evaluation of Prescriptive and Custom Lighting Installations National Grid Prepared by DNV GL Date: September 25, 2015 DNV GL www.dnvgl.com September,
More informationResidential Technical Reference Manual
Residential Technical Reference Manual Version 2013.1 Effective Date: January 1, 2013 Efficiency Maine Trust 151 Capitol Street Augusta, ME 04333 866-376-2463 efficiencymaine.com INTRODUCTION... 3 RESIDENTIAL
More informationATTACHMENT M-2 (BGE) Determination of Capacity Peak Load Contributions, Network Service Peak Load and Hourly Load Obligations PURPOSE
ATTACHMENT M-2 (BGE) Determination of Capacity Peak Load Contributions, Network Service Peak Load and Hourly Load Obligations PURPOSE This document outlines the process by which BGE determines Capacity
More information2015 Energy Efficiency Program for Business
ENERGY EFFICIENCY PROGRAM FOR BUSINESS 2015 Energy Efficiency Program for Business Custom Project Training May 20, 2015 1 ENERGY EFFICIENCY PROGRAM FOR BUSINESS Safety First 2 ENERGY EFFICIENCY PROGRAM
More informationMASSACHUSETTS ELECTRIC COMPANY STREET AND AREA LIGHTING COMPANY OWNED EQUIPMENT S-1 RETAIL DELIVERY SERVICE
Sheet 1 Canceling M.D.P.U. No. 1311 AVAILABILITY Service is available under this rate for street and area lighting full service applications owned by the Company to any Customer, inclusive of municipalities,
More informationEVOENERGY 2017/18 STATEMENT OF TARIFF CLASSES AND TARIFFS
EVOENERGY 2017/18 STATEMENT OF TARIFF CLASSES AND TARIFFS Effective date: May 2017 List of tables... 3 Overview... 4 1. Introduction... 5 1.1 Purpose and scope of the document... 5 1.2 Background... 5
More informationSCE and AVCE JOINT RATE COMPARISONS
and JOINT RATE COMPARISONS As part of our mutual commitment to better serve customers, Southern California Edison () and Apple Valley Choice Energy () have jointly created a comparison of our common electric
More informationSeattle City Light LED Streetlight Program Case Study
Seattle City Light LED Streetlight Program Case Study July 15, 2011 Edward Smalley, LC Manager, Streetlight Engineering Seattle City Light Lok M. Chan, PE Senior Associate Civil Engineer 2011 Northwest
More informationUnits. Lighting quantity is primarily expressed in three types of units.
Lighting Efficiency Units Lighting quantity is primarily expressed in three types of units. Watts measure of electrical power that defines the rate of energy consumption. Lumens output of a lamp, how much
More informationPeterborough Distribution Incorporated TARIFF OF RATES AND CHARGES Effective and Implementation Date May 1, 2015
Page 1 of 11 RESIDENTIAL SERVICE CLASSIFICATION Residential class customers are defined as single-family dwelling units for domestic or household purposes. Semi-detached and row town-housing will be considered
More information. Incandescent. . Operating Table - 2,000 foot-candles. . Storerooms - 5 foot-candles. Lighting and E. - Metal Halide
Lighting and E 1 R Paul Crumpler Pol u t io n Prevent ion Ass is ta n ce Division 404-651 -51 20 or 800-685-2443 Lighting Choices. ncandescent Fluorescent High ntensity Discharge Mercury High Pressure
More informationFederal Regulations and State Compliance for Energy Efficiency
Federal Regulations and State Compliance for Energy Efficiency A Plan B Paper In Partial Fulfillment of the Master of Science in Science, Technology and Environmental Policy Degree Requirements The Hubert
More information411 Seventh Avenue Mail drop 15 7 Pittsburgh, PA 15219
-DUQUESNE LIGHT CO. - Michael Zimmerman Counsel, Regulatory 411 Seventh Avenue Mail drop 15 7 Pittsburgh, PA 15219 Tel: 412T393-6268 mzimmermnn@duqli,hc.com September 17, 2018 Via Electronic Filing Rosemary
More informationEL PASO ELECTRIC COMPANY SECTION 3 LINE EXTENSION POLICY AND CONSTRUCTION CHARGES
SECTION 3 LINE EXTENSION POLICY AND CONSTRUCTION CHARGES SECTION 3 LINE EXTENSION POLICY AND CONSTRUCTION CHARGES TABLE OF CONTENTS Title Sheet Number Page Number Table of Contents 1 1 State of Texas Service
More informationApproved Material and Methods of Installation
CHAPTER 19 OUTDOOR LIGHTING Article 19-1 ADMINISTRATION 19-1-1 Purpose 19-1-2 Conformance with Applicable Codes 19-1-3 Approved Material and Methods of Installation Section 19-1-1 Purpose This ordinance
More informationSTUDY OF INDUCTION TECHNOLOGY BASED NEXT GENERATION INDUSTRIAL LIGHTING SYSTEM
STUDY OF INDUCTION TECHNOLOGY BASED NEXT GENERATION INDUSTRIAL LIGHTING SYSTEM Piyush Verma 1, Mrinal Saurabh Bhaskar 2 & Alka Verma 3 1, 2 Bureau of Energy Efficiency, (India) 3 Graphic Era University,
More informationEnergy Trust Electric and Gas Avoided Cost Update for Oregon for 2018 Measure and Program Planning
Energy Trust Electric and Gas Avoided Cost Update for Oregon for 2018 Measure and Program Planning August 8, 2017 Energy Trust s estimates of future electric and gas avoided costs are critical assumptions
More informationEnergy Auditing for Schools. Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007
Energy Auditing for Schools Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007 Schools Consumption breakdown 19% 6% 9% Space Heating 46% Water Heating Lighting Cooling 20%
More informationRESIDENTIAL SERVICE CLASSIFICATION
Page 1 of 9 RESIDENTIAL SERVICE CLASSIFICATION This classification refers to the supply of electrical energy to residential customers residing in detached, semi detached, townhouse (freehold or condominium)
More informationWakulla Chamber of Commerce July Place your cover photo here. Size and crop it to 4 high x 9.6 wide. Presented by Derick Farfan
Wakulla Chamber of Commerce July 2017 Commercial Energy Efficiency Programs Place your cover photo here. Size and crop it to 4 high x 9.6 wide. Presented by Derick Farfan Energy Efficiency Incentives Question:
More informationRocky Mountain Power Docket No Witness: Joelle R. Steward BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER
Rocky Mountain Power Docket No. 13-035-184 Witness: Joelle R. Steward BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Direct Testimony of Joelle R. Steward Cost of Service
More informationPublic disclosure of WEL Networks 1 April 2012 pricing methodology
Public disclosure of WEL s 1 April 2012 pricing methodology This document relates to WEL s Limited s (WEL) obligations under the Electricity (Information Disclosure) Regulations of the Commerce Commission
More informationSTREET LIGHTING SERVICE SCHEDULE SLR-45 (RESIDENTIAL SUBDIVISIONS)
STREET LIGHTING SERVICE SCHEDULE SLR-45 (RESIDENTIAL SUBDIVISIONS) AVAILABILITY This Schedule is available for service supplied in the lighting of residential dedicated public streets by means of mercury
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM-Engineering and Operations. From: Juan M. Ulloa Approved by: /s/
AGENDA ITEM NO.: 4.E.1 MEETING DATE: 02/24/2014 ADMINISTRATIVE REPORT NO.: 2014-44 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM-Engineering and Operations From: Juan M. Ulloa
More informationCalculations of Peak Load Contribution (PLC) AND Network Service Peak Load (NSPL) As of 1/1/2015
Calculations of Peak Load Contribution (PLC) AND Network Service Peak Load (NSPL) As of 1/1/2015 Overview PLC = Peak Load Contribution (aka ICAP ) Capacity-related Individual customer ticket representing
More informationResidential Real-Time Pricing: Bringing Home the Potential
Residential Real-Time Pricing: Bringing Home the Potential Kathryn Tholin Assessing the Potential for Demand Response Programs The Institute for Regulatory Policy Studies, Illinois State University May
More informationThe ESP Handbook. Chapter 15 Obtaining Consumer Usage and Metering Information. Version 7.0 February 1, 2017
The ESP Handbook Chapter 15 Obtaining Consumer Usage and Metering Information Version 7.0 February 1, 2017 SCE is committed to providing timely and accurate information to its customers or their authorized
More informationRATE DS-4 LARGE GENERAL DELIVERY SERVICE
d/b/a Ameren Illinois 5 th Revised Sheet No. 14 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 14) AVAILABILITY Service under this Rate is available for any eligible non-residential
More informationNewfoundland Power Marginal Cost of Electricity Service Study
12. Marginal Cost Study Newfoundland Power Marginal Cost of Electricity Service Study Newfoundland Power 2008 General Rate Application Newfoundland Power Marginal Cost of Electricity Service Study Prepared
More informationLED Lighting and Retrofit Design
LED Lighting and Retrofit Design 0 Marcus Gioe Senior Project Manager Lighting Division an Energy Efficiency Provider Lighting Solar Thermal Systems Capital Roadmap 1 Lighting Retrofit Process: Audit,
More informationPower Options. For Oregon Customers. Choosing an Electricity Service Supplier About transition adjustments... 7
P A C I F I C P O W E R Power Options 2011 For Oregon Customers Power Options At a Glance... 1 Direct Access... 3 10 Getting started... 4 Important dates... 4 The enrollment process... 5 Choosing an Electricity
More informationBill Fehrman President and CEO
Bill Fehrman President and CEO A graduate of the University of Nebraska in Lincoln and with a master s degree in business administration from Regis University, Bill joined MidAmerican Energy in 2007 after
More informationILL. C. C. No. 10 Commonwealth ELECTRICITY 5th Revised Sheet No. 189 Edison Company (Canceling 4th Revised Sheet No. 189) GENERAL TERMS AND CONDITIONS
Commonwealth ELECTRICITY 5th Revised Sheet No. 189 Edison Company (Canceling 4th Revised Sheet No. 189) (Continued from Sheet No. 188.1) METERING (CONTINUED) STANDARD METERING (CONTINUED). Other Metering
More informationASSESSING ONTARIO S REGULATED PRICE PLAN: A White Paper
The Brattle Group ASSESSING ONTARIO S REGULATED PRICE PLAN: A White Paper Ahmad Faruqui Phil Hanser Ryan Hledik Jenny Palmer December 8, 2010 The views expressed in this report are those of The Brattle
More informationBEFORE THE PUBLIC SERVICE COMMISSION OF WISCONSIN
BEFORE THE PUBLIC SERVICE COMMISSION OF WISCONSIN APPLICATION OF WISCONSIN PUBLIC SERVICE CORPORATION FOR AUTHORITY TO ADJUST ELECTRIC AND NATURAL GAS RATES DOCKET 6690-UR-124 Ex.-WPSC-Kage-1 Integrys
More informationUnits. Lighting quantity is primarily expressed in three types of units.
Lighting Efficiency Units Lighting quantity is primarily expressed in three types of units. Watts measure of electrical power that defines the rate of energy consumption. Lumens output of a lamp, how much
More informationOverview of Price Regulation and Basic Ratemaking Process: Perspectives from Illinois. Commissioner Sherman J. Elliott Illinois Commerce Commission
National Association of Regulatory Utility Commissioners Energy Regulatory Partnership Program, The Energy Regulatory Office of Kosovo and The Illinois Commerce Commission Overview of Price Regulation
More informationDEEMED SAVINGS TECHNICAL ASSUMPTIONS
Product: Description: Prescriptive rebates will be offered for replacement lighting equipment. New Construction rebates will be offered for new facilities or spaces overhauled for a new purpose. Custom
More informationStructuring the Solar Deal
The 26 th Annual Energy Fair June 19, 2015 Structuring the Solar Deal Presented By: Arthur J. Harrington Godfrey & Kahn, S.C. aharrington@gklaw.com 414-287-9414 13993876 Three Important Facts About Electrical
More informationTom Ledyard, RLW Analytics, Inc. and Lynn Hoefgen, Nexus Market Research Subject: Extended residential logging results Date: May 2, 2005
To: Angela Li, National Grid USA From: Tom Ledyard, RLW Analytics, Inc. and Lynn Hoefgen, Nexus Market Research Subject: Extended residential logging results Date: May 2, 2005 We have recently removed
More informationEPB Retail Rate Summary Effective October 1, 2017
EPB Retail Summary Effective October 1, 2017 Customer Class Residential Residential TakeCharge Time of Use Small Commercial (GSA1) Demand of 50 kw or less Metered Accounts Non-Metered Accounts Commercial
More informationILL. C. C. No. 10 Commonwealth ELECTRICITY 3rd Revised Sheet No. 29 Edison Company (Canceling 2nd Revised Sheet No. 29)
Commonwealth ELECTRICITY 3rd Revised Sheet No. 29 Edison Company (Canceling 2nd Revised Sheet No. 29) APPLICABILITY. This tariff is applicable to any retail customer (a) for which the Company is providing
More informationProgram Cost-benefit Analysis of 2003 New Jersey Clean Energy Council Energy Efficiency Programs. July 28, 2005
Program Cost-benefit Analysis of 2003 New Jersey Clean Energy Council Energy Efficiency Programs July 28, 2005 Section 1- Summary The Center for Energy, Economic and Environmental Policy (CEEEP) presents
More information2/17/2017. Energy Accounting & Education. Topics (Electricity) Creating Electricity
Energy Accounting & Education Energy Managers Kermit King School District of La Crosse John Daily School District of Holmen 1 Topics (Electricity) Creating electricity Defining degree days Customer charges
More informationISO New England 2003 Demand Response Programs
ISO New England 2003 Demand Response Programs Presented at: National Accounts Demand Response Seminar August 19, 2003 Bob Laurita Sr. Program Administrator, Demand Response ISO New England, Inc. New England
More informationFocus on Energy Evaluated Deemed Savings Changes
Focus on Energy Evaluated Deemed Savings Changes September 12, 2016 Updated February 17, 2017 Public Service Commission of Wisconsin This page left blank. Table of Contents Deemed Savings Analysis... 1
More informationTariff Advice Filing to Amend Tariff RIPUC No Street and Area Lighting Customer Owned Equipment S-05 Docket No.
Robert J. Humm Senior Counsel December 29, 2016 VIA HAND DELIVERY & ELECTRONIC MAIL Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick, RI 02888 RE:
More information2014 Nonresidential Downstream Deemed ESPI Lighting Impact Evaluation Report
2014 Nonresidential Downstream Deemed ESPI Lighting Impact Evaluation Report Prepared for California Public Utilities Commission Itron, Inc. 1111 Broadway, Suite 1800 Oakland, CA 94607 (510) 844-2800 March
More informationSummary of 60-Day Notice: Smart Thermostat Optimization
Summary of 60-Day Notice: Smart Thermostat Optimization Public Service Company of Colorado ( Public Service or the Company ) posts this 60- Day Notice to add a Smart Thermostat Optimization Pilot to the
More informationAMI Billing Regression Study Final Report. February 23, 2016
AMI Billing Regression Study Final Report February 23, 2016 Table of Contents Executive Summary... i 1 Introduction... 1 2 Random Coefficients Model... 5 2.1 RANDOM COEFFICIENTS MODEL DEVELOPMENT PROCESS...
More informationPenn Power Load Profile Application
Penn Power Load Profile Application I. General The Company presents the raw equations utilized in process of determining customer hourly loads. These equations may be utilized by Electric Generation Suppliers
More informationEvan Berger Director of Energy Solutions CALMAC Manufacturing Corp. Fair Lawn, NJ November 2014 CALMAC Mfg. Corp.
Evan Berger Director of Energy Solutions CALMAC Manufacturing Corp. Fair Lawn, NJ November 2014 eberger@calmac.com 1 Conclusions 1. There are three ways to lower electric costs: a) Buy fewer units of energy.
More informationUNDERSTAND THE REASONS TO BELIEVE THE RESULTS... pg.4 4 5
WHAT IS A NOESIS PLAYBOOK?/ INTRODUCTION... pg. 1 1 UNDERSTAND THE DIRECT COST SAVING... pg.2 2 3 COMPARE APPLES TO APPLES... pg.3 UNDERSTAND THE REASONS TO BELIEVE THE RESULTS... pg.4 4 5 DON T FORGET:
More informationSUMMARY OF SERVICES & INCENTIVES
SMALL BUSINESS PROGRAM 2017 SUMMARY OF SERVICES & INCENTIVES Effective through December 31, 2017 Last updated February 1, 2017 EFFICIENCY INCENTIVES SUMMARY The Focus on Energy Small Business Program offers
More informationLED Street Light Conversion Report Bruce Trivellini, Peter Flynn, Mark Mitch, Mike French, Bill Marko and Dan. Goodenough
LED STREET LIGHT CONVERSION REPORT 2018 1 LED Street Light Conversion Report 2018 Bruce Trivellini, Peter Flynn, Mark Mitch, Mike French, Bill Marko and Dan Goodenough The Town of Henniker, New Hampshire
More informationEnergy Efficiency & Customer Research & Development Technology Brief: LED Canopy Lighting
Exploring the Future Together Energy Efficiency & Customer Research & Development Technology Brief: LED Canopy Lighting Executive Summary During 2009, SMUD conducted several research projects to explore
More informationBEFORE THE L "L:"LJ ARKANSAS PUBLIC SERVICE COMMISSION DIRECT TESTIMONY GORDON D. MEYER ON BEHALF OF ENTERGY ARKANSAS, INC.
ir '- I*-:! BEFORE THE L "L:"LJ ARKANSAS PUBLIC SERVICE COMMISSION IN THE MAlTER OF THE APPLICATION OF ENTERGY ARKANSAS, INC. FOR ) APPROVAL OF CHANGES IN RATES FOR ) RETAIL ELECTRIC SERVICE ) DOCKET NO.
More informationEnergy Efficiency on the Farm
Energy Efficiency on the Farm June 14, 2017 Josh Ludgate (Exact Energy Inc.) and Erin Puryear (ODEC) How do farms use electricity? Water heating, space heating Grain Drying, Aeration Feed augers, manure
More informationMISSOURI SERVICE AREA
MO.P.S.C. SCHEDULE NO. 6 3rd Revised SHEET NO. 56 CANCELLING MO.P.S.C. SCHEDULE NO. 6 2nd Revised SHEET NO. 56 *RATE BASED ON MONTHLY METER READINGS LARGE GENERAL SERVICE RATE Summer Rate (Applicable during
More informationRenewable Energy Plan 2011 Biennial Review Lansing Board of Water & Light MSCP Case No. U-16619
Renewable Energy Plan 2011 Biennial Review Lansing Board of Water & Light MSCP Case No. U-16619 This Biennial Review filing by the Lansing Board of Water & Light (LBWL) complies with Public Act 295 of
More informationSolar System Analysis
Preliminary Analysis of an Industrial Photovoltaic System and Comparison of Its Performance with a Wind Energy System and a Fuel Cell Power System Amal Kabalan, LEED A.P. Consulting Engineer The purpose
More informationIntroduction to Efficient Pricing
Introduction to Efficient Pricing Presented to: Edison Electric Institute s Advanced Rates Course University of Wisconsin, Madison Presented by: Philip Q Hanser Copyright 2012 The Brattle Group, Inc. July
More informationState of Hawaii. Public Utilities Commission The Hawaii Public Utilities Commission Acknowledges Receipt of Your Submittal.
2015-04-28 HECO ECAC - May 2015.pdf State of Hawaii Public Utilities Commission The Hawaii Public Utilities Commission Acknowledges Receipt of Your Submittal. Form: Hawaii PUC efile Non-Docketed Entity:
More informationUNRIVALED. green technology. the STERNBERG advantage
UNRIVALED green technology the STERNBERG advantage Typical HID DELIVERED Lumens Lamp Mean Fixture Typical Downward DELIVERED Lumens Watts Lumens 1 CRI Watts 2 Acorn 3 L / W 6 Lantern 4 L / W 6 Down Light
More informationEnergy-efficient street lighting Experiences from Melaka, Malaysia
Energy-efficient street lighting Experiences from Melaka, Malaysia Parallel Session C3: Tools & Resources - Renewable Energy/EE Implementation December 6, 2017, Ho Chi Minh Asia LEDS Partnership Forum
More informationEvolution LED High Bay Flood Light Series
Evolution LED High Bay Flood Light Series Instant On/ Instant Off No Restart Delay Ultra-Energy Efficient Eco Friendly Durable Construction Zero UV Emissions Ultra Long Life Zero Maintenance Evolution
More informationDEEMED SAVINGS TECHNICAL ASSUMPTIONS
Product: Description: Prescriptive rebates will be offered for replacement lighting equipment. New Construction rebates will be offered for new facilities or spaces overhauled for a new purpose. Custom