Distributed Energy Resources (DER) Queue Management
|
|
- Ariel Day
- 6 years ago
- Views:
Transcription
1 Distributed Energy Resources (DER) Queue Management FortisAlberta s Distributed Energy Resource (DER) Queue Management stages are applicable to every DER Customer project, whether the project is the only one connecting generation capacity, or if there are multiple projects waiting to connect at a substation feeder. These stages are intended to ensure that active DER Customer projects in the queue continue to move forward and do not prevent access to other DER Customers. DER projects include Distributed Generation (DG) and Micro-Generation (MG). In order to remain active in the queue and not re-start a project, DER Customers must complete all of the requirements in each stage within the allotted time frames in the FortisAlberta DER Process. Any changes to the approved scope (for example, physical location; size of generator; or type of DER being connected) of a DER Customer s project will result in the need for the DER Customer to re-apply and the potential loss of queue position. If requirements are not met, the project request is Stale-Dated or Cancelled and is no longer considered in the FortisAlberta DER Queue. When a customer is removed from the DER Queue and there are other DER projects with contingencies on the removed DER project, the Key Account Manager notifies the customer with contingencies (also known as next-in-line ) with their updated High Level Study details. Timing extension circumstances There may be situations where FortisAlberta reserves the right to extend or limit the amount of response time required to keep a Customer s DER application in the FortisAlberta Queue. The following are two possible scenarios: A DER project is next-in-line at the High Level Study stage and the previous DER project has stale-dated or been cancelled. The High Level Study will be revised for this next-inline customer. Normally, a customer has a maximum of 60 calendar days to sign and return the High Level Study letter. With a change in the DER Queue Management occurring within 14 calendar days of the 60 calendar day expiry, the customer may be awarded a timing extension of 14 calendar days from the revised High Level Study date. The Key Account Manager will ensure that if the project automatically changed its status during the timing extension to Stale-Dated, the status will be changed back to High level Study Sent to Customer. Sep 25, 2017 Version 1 1
2 If the High Level Study was revised within 46 calendar days of the original High Level Study, the maximum 60 calendar days to reply remains unchanged. A customer wishes to delay the construction or connection of their DER project. The full Customer Contribution costs are required up front and the DER project will be held for up to one year. After one year, FortisAlberta reserves the right to cancel the DER project and any distribution and transmission construction costs, minus cancellation fees, will be refunded. High Level Study Stage Preliminary (pre-entry to DER queue) DER Customer reviews Get Connected: Distributed Generation or Get Connected: Micro-Generation and the Frequently Asked Questions (FAQs) located on FortisAlberta s website fortisalberta.com. DER Customer consults with FortisAlberta about any additional questions DER Customer completes and submits the Distributed Generation Service Application or Micro-Generation Service Application on fortisalberta.com. Application and Payment (pre-entry to DER queue) Once FortisAlberta receives payment for the HLS, the DER Customer project enters the queue. If the invoice is not paid by the due date of 30 calendar days, the invoice and the project are cancelled. System Capacity Review (enter DER queue) The Project is sent to Distribution Planning for system capacity review. The FortisAlberta Distribution Planner completes the study for the DER Customer project and the generator is assigned to the best available feeder capable of accommodating the proposed generation. This secures the capacity to the feeder at the originating substation. FortisAlberta sends the HLS proposal to the DER customer for review (valid for 60 calendar days). FortisAlberta may provide multiple options depending on queuing, for example, if there is a project contingent on the same capacity at the feeder or substation, this information will be provided to the customer in the HLS to allow additional discussion around future options or contingencies. Sep 25, 2017 Version 1 2
3 The HLS includes the distribution ballpark cost estimate and the anticipated Transmission Facility Owner (TFO) and Alberta Electric System Operator (AESO) upgrade requirements (without costs). FortisAlberta must receive the DER Customer s signed HLS acceptance letter for the location and/or option specified in the HLS within 60 calendar days or the project staledates, is cancelled, and removed from the queue. FortisAlberta sends invoices for the full Distribution and Transmission Detail Study costs required for the project to advance. The available capacity is secured for a further 30 calendar days from the date of invoice. FortisAlberta s Detailed Study cost starts at $7,500 and; TFO Study Protection and Power flow Studies as required. Note: If multiple TFOs are involved, additional fees will be required as each has their own fees FortisAlberta will advance the project to the Detail Study Stage upon full payment of all required Detail Study costs. If payment is not received by the invoice due date, the project will be removed from the queue. Milestone Completed High Level Study Stage is now complete or the project is cancelled Detailed Study Stage Detailed Study System Capacity Review (queue position maintained) FortisAlberta continues to hold the capacity for the DER Customer s defined project scope as specified in the accepted HLS. Any change to the HLS scope (generator size, location, type, etc.) may result in a new HLS being required or a new project to be initiated by the DER Customer (Stage 0). This decision is determined by the Distribution Planner and Key Account Manager. The DER Customer must provide some technical information as identified in the FortisAlberta DER Process within the 30 calendar days of the invoice. FortisAlberta and the Customer now enter into the AESO Behind The Fence (BTF) gating process. Typically this stage for the Detailed Study takes 6 to 12 months. (Note: During this stage, AESO has their own timing restrictions and requirements for projects. Failure to meet these required timelines can result in removal from the AESO queue. FortisAlberta reserves the right to remove the project from FortisAlberta s DER queue). Sep 25, 2017 Version 1 3
4 Completed Detailed Study Issue Quote (queue position maintained) FortisAlberta sends the quotation letter package (detailed distribution interconnection cost, pre-paid Operating and Maintenance (O&M) cost, and TFO Proposal to Provide Service (PPS) costs) to the DER Customer for review and acceptance (valid for 60 calendar days). FortisAlberta must receive the DER Customer s signed Quote letter with approval to proceed within 60 calendar days or the project stale-dates, is cancelled, and removed from the queue. FortisAlberta sends invoices for the full Distribution and Transmission costs required for the project to advance to the DER Customer. The available capacity is secured for a further 30 calendar days from the date of invoice. FortisAlberta will advance the project to the Construction Stage upon full payment of all required construction costs (distribution and transmission). If payment is not received by the invoice due date, the project will be removed from the queue. Milestone Completed Detailed Study Stage Complete Construction Stage Construction (queue position maintained) To allow some flexibility, the Customer may request deferring the construction for a maximum of one year. Should the construction be deferred, FortisAlberta reserves the right to re-quote the project to ensure costs are still relevant. The cost of requoting shall be included in the new quote package. If there are changes in DER standards during this period, the DER Customer shall comply with these new requirements. Commissioning Stage Commissioning (queue position maintained) A Key Account Manager works with internal FortisAlberta groups to coordinate the DER project integration. Sep 25, 2017 Version 1 4
5 Questions Please contact a Key Account Manager with any questions regarding the FortisAlberta Distributed Energy Resources Queue Management stages. Monique Soboren Monique.Soboren@FortisAlberta.com Leandro Tomei Leandro.Tomei@FortisAlberta.com Jack Wojciechowski Jack.Wojciechowski@FortisAlberta.com generation@fortisalberta.com Sep 25, 2017 Version 1 5
AESO Practices for System Access Service. May 31, 2013
AESO Practices for System Access Service May 31, 2013 Table of Contents 1 Purpose... 3 2 Introduction... 3 3 Practices for System Access Service... 4 3.1 Conditions for System Access Service... 4 3.2 Rationale
More informationWork will begin on the project when the Letter of Agreement has been signed.
isit2b Marketing, LLC Marketing Services Terms & Conditions is it 2B Marketing provides website & graphic design, copywriting, and related online marketing services. Clients are asked to read and agree
More informationONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES
ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES 2016 Commercial and Residential Solar Programs Kickoff Meeting November 11-12, 2015 Ken Brunkenhoefer Oncor Asset Planning OVERVIEW
More informationCluster Study Process
Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO
More informationThis issue is simultaneously being sent to USPS Supply Management employees for their information.
Issue 16 November 4, 2013 CONTENTS USPS Financial System Upgrade Supplier-Focused Q & As Regarding the Financial System Upgrade USPS Suppliers, You are receiving this newsletter from the Postal Service
More informationGenerator Interconnection Procedures Overview
Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution
More informationQueue Management. A look at queue reform and. Jennifer Heintz and Janet Wheeler June 12, 2012
Queue Management A look at queue reform and the queue process Jennifer Heintz and Janet Wheeler June 12, 2012 1a What is a queue? The interconnection queue (queue) refers to the process of getting a new
More informationLong Island Power Authority Seventh Revised Leaf No. 16
Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that
More informationAlberta Capacity Market
Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 4: Forward Capacity Auction Prepared by: Alberta Electric System Operator Date: January 26, 2018 Table of Contents
More informationINTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION
PLATEAU ELECTRIC COOPERATIVE INTERCONNECTION PROCEDURES FOR DISTRIBUTED GENERATION Policy B32 1 P a g e TABLE OF CONTENTS PAGE 1. GENERAL PROCEDURES & STANDARDS 3 1.1 Scope 1.2 Application for Interconnection
More informationRATE 665 RENEWABLE FEED-IN TARIFF
NORTHERN INDIANA PUBLIC SERVICE COMPANY Third Revised Sheet No. 104 Superseding Second Revised Sheet No. 104 TO WHOM AVAILABLE No. 1 of 11 Sheets This is a rate that is a voluntary offer available to any
More informationLong Island Power Authority Seventh Revised Leaf No. 16
Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that
More informationWestern Power Distribution Workplan to Improve Connections Performance 2014/ Quotation and Acceptance
Western Power Distribution Workplan to Improve Connections Performance 2014/2015 - Quotation and Issue WPD initiative(s) Actions Status update Review and update Offer Letter following Consult on Offer
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS What is Monumental Sports Account Manager? The Monumental Sports Account Manager is an extension to the box office available to you 24 hours a day, 7 days a week. By logging
More informationPROCURE-TO-PAY INVENTORY MANAGEMENT
RSM TECHNOLOGY ACADEMY Syllabus and Agenda PROCURE-TO-PAY INVENTORY MANAGEMENT FOR MICROSOFT DYNAMICS AX Course Details 3 Audience 3 At Course Completion 3 Course Cancellation Policy 5 Guaranteed to Run
More informationESB Networks - Service Level Agreements. Decision Paper
ESB Networks - Service Level Agreements Decision Paper CER 04/345 11 November 2004 Introduction On the 21 st June 2004 the Commission published a draft decision on the Service Level Agreements (SLAs) relating
More informationTerms & Conditions Lucas Bols INTRODUCTION
Terms & Conditions Lucas Bols INTRODUCTION This website is operated by Lucas Bols Amsterdam B.V. ("Lucas Bols") is a company incorporated in the Netherlands and registered at the Chamber of Commerce under
More informationP U B L I C T R A I N I N G
P U B L I C TRAINING HAZARDOUS AREA IN ELECTRICAL INSTALLATION OVERVIEW Hazardous area in electric installation are places where accidents could mostly happen. Types of accidents in electric installations
More informationYOUR CERTIFICATION PROCESS EXPLAINED
ISO 22000 FOOD SAFETY MANAGEMENT SYSTEMS FSSC 22000 FOOD SAFETY SYSTEM CERTIFICATION This document outlines the audit process for the above referenced standard. It outlines the stages to audit and gives
More informationInterconnection Specialists ensure all projects are treated in accordance with the current applicable tariff provisions
After the study process, main contact becomes your ISO contract negotiator Reports will be issued using Resource Interconnection Management System database (RIMS). It is imperative that project owners
More informationRetail Contracts Scheme Benchmarks
Retail Contracts Scheme s 1 - Clear supply commencement 1.1. The gas supply arrangements must state when the supply of gas is to commence, either by stating a specific commencement date or the circumstances
More informationSwan Purchase Order Acceptance Policy
Swan Purchase Order Acceptance Policy Purchase orders should be submitted via: Email swanezpo@swanstone.com or Fax (800) 342-7926 To ensure accurate and timely processing and shipping of orders, all purchase
More informationWelcome to the topic on customers and customer groups.
Welcome to the topic on customers and customer groups. In this topic, we will define a new customer group and a new customer belonging to this group. We will create a lead and then convert the lead into
More informationTerms & Conditions Case Study:
EDUCATION & RESEARCH FOUNDATION Terms & Conditions Case Study: The Tale of TED Electric Supply This research study has been generously sponsored by the NAED Education & Research Foundation s Channel Advantage
More informationRoyal Mail Group Ltd. Specific Terms for Response Services
Royal Mail Group Ltd Specific Terms for Response Services June 2014 Royal Mail and the Cruciform are registered trade marks of Royal Mail Group Ltd. All rights reserved. Royal Mail Group Ltd, registered
More informationContract Management from Principles to Action
Contract Management from Principles to Action Developing Core Competencies for Contract Success from Start to Finish 16-20 October 2016 08-12 October 2017 Qatar This course is Designed, Developed, and
More informationWes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED
Ramapo Phase Angle Regulator Cost Recovery Wes Yeomans Vice President Operations Management Committee May 31, 2017 Agenda Background Benefits of Two Ramapo Phase Angle Regulators Annual Cost Projections
More informationSTATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 1 st October 2017 Version 1.
STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM Effective from 1 st October 2017 Version 1.3 DOCUMENT CHANGE CONTROL SHEET Document Control Document Version
More informationSchedule 2 TECHNICAL INFORMATION
Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity
More informationTPP-GIP Integration Proposal November 30, 2011
TPP-GIP Integration Proposal November 30, 2011 Major Elements of Proposal Demand-Based Planning of Network Upgrades in the TPP Synchronize GIP, TPP and the LSE Procurement Processes Allocation of Deliverability
More information(To be published in the Gazette of India, Part I, Section 1) RESOLUTION. Tariff based Competitive-bidding Guidelines for Transmission Service
(To be published in the Gazette of India, Part I, Section 1) No. 11/5/2005-PG(i) GOVERNMENT OF INDIA Ministry of Power. RESOLUTION New Delhi, Date: 17th April, 2006 Tariff based Competitive-bidding Guidelines
More informationReview of Purchasing Guidelines
Review of Purchasing Guidelines Board Policy CH Local Persons making unauthorized purchases shall assume full responsibility for all such debts. All purchase commitments shall be made by the Superintendent
More informationTable of Contents. 6.1 Importing Exporting Documentation Retention... 6
Table of Contents 1.0 Completing the Internal Requisition Form... 2 2.0 Internal Requisition Attachments... 3 3.0 Processing the Internal Requisition Form... 3 4.0 Types of Purchase Orders... 4 5.0 Purchase
More informationRequest for Proposal: Controlled System Separation Feasibility Study
Request for Proposal: Controlled System Separation Feasibility Study I. INTRODUCTION A. Overview The New York Independent System Operator ( NYISO ) is requesting proposals for professional services from
More informationIBM Business Partner Operations Guide for Solution Provider for IBM Software as a Service
IBM Business Partner Operations Guide for Solution Provider for IBM Software as a Service Europe, Middle East and Africa Version 1.12 This Operations Guide and updated versions will be posted on the IBM
More informationExternal Project Management & Integrated Services Approach to Well Construction
External Project Management & Integrated Services Approach to Well Construction 17-21 September 2017 Dubai, United Arab Emirates 19-DEC-16 This course is Designed, Developed, and will be Delivered under
More informationZebra s Repair Order Portal for Partners COURSE CODE: RPE01
Zebra s Repair Order Portal for Partners COURSE CODE: RPE01 April 2017 Introduction Welcome to the Zebra s Repair Order Portal for Partners course. This course explains how to navigate the Repair Order
More informationMarket Procedure: Network Control Services
ELECTRICITY INDUSTRY ACT 2004 ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES Market Procedure: Network Control Services Version 2 Commencement:
More informationSAI Global Full Service Team
General information regarding elements of the certification process is described below. A degree of flexibility and options in the certification process are available so please feel free to contact us
More informationCOMMUNICATIONS WITH THE INTERNATIONAL BUREAU
GUIDE TO THE INTERNATIONAL REGISTRATION OF MARKS B.I. 1 PART B PROCEDURE CHAPTER I: GENERAL INTRODUCTION This Chapter is concerned with procedural matters which are of interest both to applicants and holders
More informationFocus on Energy s Biogas Feasibility Study Grants for Anaerobic Pretreatment and Anaerobic Digester Facilities
Focus on Energy s Biogas Feasibility Study Grants for Anaerobic Pretreatment and Anaerobic Digester Facilities Customer and Study Provider Guidelines For more information, Call 800.762.7077 or visit focusonenergy.com
More informationPCAT FAQs What are the important PCAT test dates for ? Registration Opens 3/1/2017. o July o September
PCAT FAQs 2017 2018 1. What are the important PCAT test dates for 2017 2018? Registration Opens 3/1/2017 o July 2017 18 19 o September 2017 7 8 o January 2018 3 4 Registration Opens 9/5/2017 (Limited Seating
More informationBC Eggs for Processing Program
BC Eggs for Processing Program Project Description September 8, 2015 Background: Historically, the industrial egg market has been used to remove surplus eggs from the market in order to maintain stability,
More informationSmall Generator Interconnection Procedures (SGIP) Customer Guide
Customer Guide SCE&G utilizes a FERC mandated and approved process, known as the Small Generator Interconnection Procedure (SGIP), to evaluate the interconnection of small generators to the SCE&G transmission
More informationNEW YORK CITY HOUSING DEVELOPMENT CORPORATION PURCHASING PROCEDURES. Updated as of November 19, 2015 (Reaffirmed on March 10, 2017)
NEW YORK CITY HOUSING DEVELOPMENT CORRATION I. ORDERING ITEMS PURCHASING PROCEDURES Updated as of November 19, 2015 (Reaffirmed on March 10, 2017) All requests for purchases are to be coordinated through
More informationIncremental Black Start RFP Response Template & General Information
Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section
More information1236 These conditions of sale supersede all previous selling policies. Prices, discounts, lead-times and product offerings are subject to change without notice. Order Placement Great Openings requires
More informationQuickbooks /Quickbooks Pro Data Conversion Information Sheet
Quickbooks /Quickbooks Pro Data Conversion Information Sheet Thank you for selecting PCLaw please review the following information regarding your data conversion. Are you using Timeslips for your time
More informationAVANTUS TRAINING PTE LTD
Service Industries in Microsoft Dynamics AX 2012 Course 80311A: 2 Days; Instructor-Led About this Course This two-day instructor-led course provides students with an overview of the Project management
More informationFLEXIBLE TRAINING OPPORTUNITIES APPLICATION FORM
FLEXIBLE TRAINING OPPORTUNITIES APPLICATION FORM Instructions for completing this form: To help you complete the application form please read the rules and guidance section and the help notes. Please use
More informationDSIWM Disposal Fees ebiz.epa.ohio.gov User Guide
DSIWM Disposal Fees ebiz.epa.ohio.gov User Guide 1 TABLE OF CONTENTS Contents 1. Introduction. 3 2. Glossary.. 3 3. Using the ebusiness Center 4 Obtaining an Account (User ID) and Password. 4 Obtaining
More informationPREPARED BY ORGANIZATION DATE
Process for Authorizing Use of Consultants NRAO Doc. #: Richard Sakshaug, Joyce Johnson May 18, 2015 Version: New Process for Authorizing Use of Consultants PREPARED BY ORGANIZATION DATE Richard Sakshaug,
More informationLIGHTING. TERMS & CONDITIONS Oct. 24, Tegan Lighting, Inc. 25 Pelican Way San Rafael CA (415) teganlighting.
TERMS & CONDITIONS Oct. 24, 2017 Tegan Lighting, Inc. 25 Pelican Way San Rafael CA 94901 (415) 504-3536 teganlighting.com revised 10/24/2017 TERMS and CONDITIONS How We Do Business Payment All orders will
More informationIBM Business Partner Operations Guide for Solution Provider for IBM Software as a Service
IBM Business Partner Operations Guide for Solution Provider for IBM Software as a Service Europe, Middle East and Africa Version 2.0 This Operations Guide and updated versions will be posted on the IBM
More informationRequirements for the Provision of Load Shedding Service for Import Version 4.0
LOAD SHED SERVICE for IMPORT (LSSi) Requirements Requirements for the Provision of Load Shedding Service for Import Version 4.0 This document outlines the eligibility criteria and requirements that an
More informationSystem Impact Study and Facilities Study Process Manual For Cleco Power LLC
System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2
More informationQuick Start Guide. Creating A Bill & Printing An Invoice
i Quick Start Guide Table of Contents Key Terms...3 Billing Types... 3 Premium Sent.. 3 Financing.. 3 Agency Fees....3 Create A Bill.. 4 By Issuing A Policy. 4 Agency Bill Policies... 4 Direct Bill Policies...
More informationCalifornia Independent System Operator Corporation. California ISO. Invoicing WECC NERC/ERO Costs. March 29, Prepared by: Michael Epstein
California Independent System Operator Corporation California ISO Invoicing WECC NERC/ERO Costs March 29, 2007 Prepared by: Michael Epstein Table of Contents 1. Executive Summary 2. Background 3. Overview
More informationCertificate Course in Maintenance Planning
Certificate Course in Maintenance Planning This course is Designed, Developed, and will be Delivered under ISO Quality Standards 26-30 March 2017 Muscat, Oman 15-JAN-17 Certificate Course in Maintenance
More informationPUBLIC WIFI FROM EE SOLUTION TERMS
1. Interpretation 1.1 The Public WiFi from EE Solution (referred to in these Solution Terms as "Public WiFi" or the "Solution") is provided in accordance with the Customer s Agreement with EE. 1.2 Solution
More informationCustomer Service in Microsoft Dynamics CRM 2013
Course 80545A: Customer Service in Microsoft Dynamics CRM 2013 Course Details Course Outline Module 1: Introduction Microsoft Dynamics CRM includes a comprehensive set of features that increases the efficiency
More informationLower Rio Grande Valley Development Council. Invitation to Bid (ITB): Online Training System for the Department. office.
The Lower Rio Grande Valley Development Council (LRGVDC) Invitation to Bid (ITB): Online Training System for the 9-1-1 Department Quotes Due Not Later than: Issuing Office: Monday, April 18 th, 2016 at
More informationPanther Mart Shopper Training Guide
Panther Mart Shopper Training Guide Shopper Guide Panther Mart Training Manual Table of Content Chapter 1 Introduction.. 2 Overview and Contact Information.... 2 Roles in Panther Mart..... 3 Workflow Rules....
More informationAriba Network Invoice Guide
Ariba Network Invoice Guide Content 1. Introduction 2. Invoice Practices 3. Before you Begin Invoicing I. Viewing Customer Invoice Rules II. Electronic Invoice Routing and notifications III. Account Configuration
More informationBINGO POLICY & PROCEDURES HANDBOOK
BINGO POLICY & PROCEDURES HANDBOOK TABLE OF CONTENTS Background 2 Bingo Policy 3 Qualifications Application Volunteer Requirement Late Attendance Penalties Appeals Accountability Bingo Allocation Volunteer
More informationKraft Heinz Accounts Payable Update Electronic Invoicing
Kraft Heinz Accounts Payable Update Electronic Invoicing Overview As you may be aware from previous communications, Kraft Heinz is implementing several changes in our Procurement and Accounts Payable areas.
More informationHP DesignJet Cash In & Trade Up April 2016 promotion
HP DesignJet Cash In & Trade Up April 2016 promotion Terms and conditions A. HP DesignJet Cash In & Trade Up April 2016 program structure Within the framework of the HP DesignJet Cash In & Trade Up April
More informationDIRECTORATE-GENERAL FOR COMMUNICATION DIRECTORATE FOR MEDIA CONDITIONS FOR SUBMITTING A TENDER INVITATION TO TENDER NEGOCIATED PROCEDURE
Directorate General for Communication Directorate for Media The Director DIRECTORATE-GENERAL FOR COMMUNICATION DIRECTORATE FOR MEDIA CONDITIONS FOR SUBMITTING A TENDER INVITATION TO TENDER NEGOCIATED PROCEDURE
More informationFAMILY AND MEDICAL LEAVE
(Combine: 3354:1-41-02.7 & 3354:1-41-02.6) Procedure for Family and Medical Leave of Absence (FMLA) and Other Leaves of Absence for Non-Bargaining Employees. FAMILY AND MEDICAL LEAVE The Family and Medical
More informationSAP Transportation Management 9.1, Support Package 2 Enterprise Services
SAP Transportation Management 9.1, Support Package 2 Enterprise Services CUSTOMER Document Version: 1.0 May 2014 SAP TM 9.1 SP02 Enterprise Services 1 Copyright Copyright 2014 SAP AG. All rights reserved.
More informationProficiency Test Request Form. Name of Laboratorium. Address. : No.Fax:
Proficiency Test Request Form We are ready to assist you in meeting the needs of the laboratory test program proficiency. To perform proficiency test in the query execution in accordance with the test
More informationGuide to Procurement. Ministry of Central Services Procurement Services. Last updated: April 2014 Page 1 of 11
Ministry of Central Services Procurement Services Last updated: April 2014 Page 1 of 11 Table of Contents Purpose of guide... 3 Authority for procurement... 3 Applicability - Who is covered by The Purchasing
More informationega Frequently Asked Questions (FAQ)
ega Frequently Asked Questions (FAQ) 1. How do I supersede an appointment? Login to ega using your NinerNet credentials. Click on the Supersede Assistantship link from the ega left navigation pane. Search
More informationPurchase flow. From the launch of a tender until payment
Purchase flow - From the launch of a tender until payment This flow requires the installation of Purchases / Stocks / Invoicing / Accounting / Supply Chain applications. You need to activate for this flow
More informationObtaining water supplies for new developments
Obtaining water supplies for new developments Guidance notes for developers Issue 1.0 - April 2015 life fow smoothly helping helpin life f ow smoothly hel ping helping life fow smoothly life fow smoothly
More informationInformation Document Service Proposals and Cost Estimating ID # R
Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document
More informationPJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department
PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7
More informationService Level Agreement For Interconnect Paths
Service Level Agreement For Interconnect Paths 21/06/17 Version 3.0 - Final 1 Version Control Version Status Update Effective Date 2.7 Document rebranded to open eir 16 th September 2015 V3.0 Final This
More informationSupplier Policies & Procedures
20.0 PERFORMANCE REQUIREMENTS Supplier Policies & Procedures True Value is committed to providing its Retailers with products that consistently meet or exceed their expectations for value and merchandise
More informationGeneral Terms and Conditions
General Terms and Conditions Standard Visit These are the General Terms and Conditions that apply to each visitor or group of visitors of the Standard Visit. We would ask that you read these through carefully,
More informationPurchase Request. Bizagi Suite. Copyright 2016 Bizagi
Purchase Request Bizagi Suite Purchase Request 1 Table of Contents Purchase Request... 3 Data model... Error! Bookmark not defined. Process Elements... Error! Bookmark not defined. Create Purchase Request...
More informationOpen Access Transmission Tariff ATTACHMENT K
ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct
More informationEngine Oil Licensing and Certification System (EOLCS) Online System User Guide
Engine Oil Licensing and Certification System (EOLCS) Online System User Guide Managing Contact and Company Information o Contact Registration o Company Registration o Add Contacts To Company o Password
More informationApplication Help for SAP TM Document version: SAP TM 9.2 SP CUSTOMER. Enterprise Services
Application Help for SAP TM Document version: SAP TM 9.2 SP02 2015-04-30 Document History The following table provides an overview of the most important document changes. Table 1 Version Date Description
More informationExacTrac and eprocurement Catalog Orders
ExacTrac and eprocurement Catalog Orders ExacTrac is a way for the University to pay for eprocurement Catalog orders using a one-time use virtual credit card number. The vendor receives the electronic
More informationCash Management Procedure
Office of Research and Sponsored Programs Issued: January, 2008 Implemented: March, 2008 BACKGROUND Payments for sponsored projects are typically received by the Cashier s Office, by the Office of Research
More informationArtisan Vendor Handbook
Artisan Vendor Handbook 2018 Rochester Downtown Alliance. All Rights Reserved. Thursdays on First & 3 rd Artisan Vendor Handbook Section 1 Event Information Thursdays on First & 3 rd is a summer market
More informationBusiness Practice Manual for the Transmission Planning Process
Business Practice Manual for the Transmission Planning Process Order 890 Compliance Version 76.0 September 15,February 11, 2010 TABLE OF CONTENTS Order 890 Compliance... i 1. Introduction... 6 1.1 Purpose
More informationNo. Finding Recommendation Previous Management Response(s) Six-Month Status Update
1 MAR Collection Efforts Are In order to send notification letters timely, we recommend the MAR unit clarify circumstances that are acceptable exceptions to their policy of sending late payment notification
More informationREQUEST FOR PROPOSAL. For Technical Contractor CanGym Revitalization City Park Drive, Suite 120 Ottawa, ON K1J 1A3
REQUEST FOR PROPOSAL For Technical Contractor CanGym Revitalization 1900 City Park Drive, Suite 120 Ottawa, ON K1J 1A3 Request for Proposal For Technical Contractor CanGym Revitalization Gymnastics Canada
More informationEDITORIAL CALENDAR ISSUE ON SALE AD CLOSE EDITORIAL THEMES DIGITAL HIGHLIGHTS. Body Reboot Love Your Strength Challenge
EDITORIAL CALENDAR 2017 ISSUE ON SALE AD CLOSE EDITORIAL THEMES DIGITAL HIGHLIGHTS JAN/FEB 12/23/2016 10/28/2016 Body Reboot Body Reboot Love Your Strength Challenge MARCH 2/10/2017 12/16/2016 Body Positive
More informationMRP I SYSTEMS AND MRP II SYSTEMS
MRP I SYSTEMS AND MRP II SYSTEMS 2.PLANNING THE MANUFACTURING RESOURCES. MRP II SYSTEMS At the end of the 70s, the computing systems based on the idea that as it is possible to use computing systems to
More informationForest Stewardship Council
Introduction Frequently Asked Questions (FAQs) FSC-STD-40-004 V3-0 and FSC-STD-20-011 V4-0 27 March 2017 On 1 January 2017, the FSC Board of Directors approved the revised FSC chain-ofcustody standards
More informationAmadeus Hotel Store. User guide 16 March Taking hotel consolidator content to a new level with Transhotel
Amadeus Hotel Store User guide 16 March 2009 Taking hotel consolidator content to a new level with Transhotel Index Amadeus Hotel Store is now open for business!...3 Technical requirements...3 Log-in...4
More informationMilano Worldwide Corporation
Milano Worldwide Corporation TERMS AND CONDITIONS Product Order Upon placing an order for a Custom Milano Worldwide concept and prototype, Customer will pay specified set-up charge and receive: Line drawing
More informationMETER UPGRADE MANUAL
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 METER UPGRADE MANUAL Version 4 EFFECTIVE DATE 5/01/2016 Meter Upgrade Manual This manual describes the process and the rules
More informationREFRIGERANT RECOVERY/RECYCLING EQUIPMENT CERTIFICATION PROGRAM
REFRIGERANT RECOVERY/RECYCLING EQUIPMENT CERTIFICATION PROGRAM AHRI RRRE OM JANUARY 2018 2111 Wilson Blvd, Suite 500 Arlington, Virginia 22201 (703) 524-8800 Sponsored and administered by: PREFACE The
More informationJob Aid. ESS - Create Entitlement Travel (UN Paid ticket)
ESS - Create Entitlement Travel (UN Paid ticket) Table of Contents Overview... 3 Objectives... 3 Enterprise Roles... 3 Create an Entitlement Travel (UN Paid ticket)... 4 Important Information Page... 5
More informationClassification: Public. ANZ TRANSACTIVE GLOBAL Nostro Account Management FAQs
Classification: Public ANZ TRANSACTIVE GLOBAL Nostro Account Management FAQs 06 2015 CONTENTS 1. USE OF ANZ TRANSACTIVE - GLOBAL 3 1.1 How do I view the current balance of an account? 3 1.2 How do I view
More informationMODIFICATIONS TO THE CASE MANAGEMENT, INFORMATION AND PAYROLLING SYSTEM (CMIPS) TO IMPLEMENT AND MANAGE WORKWEEK
REASON FOR THIS TRANSMITTAL April XX, 2016 ALL-COUNTY LETTER NO.: XXXXXX [X] State Law Change [X] Federal Law or Regulation Change [ ] Court Order [ ] Clarification Requested by One or More Counties [
More information