1 Bangor Hydro s Local System Plan Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting November 17, 2011 Bangor Hydro Representative: Jeffrey Fenn, P.E., SGC Engineering

2 Purpose of Local System Plan (LSP) Per Attachment K - The LSP is an annual report that: 1. Describes non PTF transmission system reliability needs 2. Reflects 1. System planning studies 2. Proposed solutions 3. Identifies 1. Local planning process 2. Criteria, Data and Assumptions 2

3 LSP Communication 1. LSP is communicated via Local Planning Advisory Committee (LPAC) meeting for stakeholders convenience, this is being done following an ISO-NE PAC meeting 2. The material is posted prior to the LPAC meeting (via the ISO- NE PAC posting system) 3. Transmission Customers and Stakeholders have 30 days after posting to provide written comments for consideration by BHE 3

4 LSP Communication (cont.) 1. BHE Contact: Lisa Martin PO Box Illinois Avenue Bangor, Maine (207) BHE LSP is located at: 4

5 Local System Planning Process The process is Needs Assessment followed by Solutions Proposals Local System needs can result from: Load Growth Sub-area reliability assessments Point of delivery request from customers Generation interconnection requests (in accordance with appropriate generator interconnection procedures) Local System Plan consists of: Summary of needs assessment results Listing of criteria, data and study assumptions Identification of proposed alternatives Solution study results and selection of preferred alternative 5

6 Criteria, Data and Assumptions Loads based on CELT Report forecasts for the New England area, BHE specific forecasts and local customer needs Studies based on the ISO-NE library base cases and short circuit database Studies use relevant assumptions regarding transmission, generation and demand resources found in the latest ISO-NE Regional System Plan 6

7 LSP Project List 1. The LSP project list is a cumulative listing of proposed regulated transmission solutions intended to meet local needs 2. Similar to the ISO-NE PTF RSP, the LSP contains the status of each project Concept Project is under consideration as a solution to a partial needs assessment Proposed Needs assessment completed and project proposed as a solution, but not formally budgeted Planned Formally budgeted and if necessary, approved by ISO- NE Under Construction Significant engineering and internal approvals in process and project is being implemented In-Service Project used and useful 7

8 Bangor Hydro Detailed System 8

9 LSP Concept Status Need Needs Assessment Service Area Project Name Status Solutions Project In- Service Month/Year Reliability Chester T1 and T2 Overloading Northern Chester T1/T2 OL Concept Possible solution as part of BHE Annual Transmission Needs and Solutions Assessment 12/2013 9

10 LSP Proposed Status Need Needs Assessment Service Area Project Name Status Solutions Project In- Service Reliability Support of area loads, eliminate overload of L22 and improve ability to maintain transmission circuits Eastern Bar Harbor support Proposed Additional 34.5kV circuit with diverse route. Part of area looping 12/2012 Reliability Line 87 from Chester to Lincoln Overload Northern Line 87 Overload Proposed Rebuild 12/

11 LSP Planned Status Need Needs Assessment Service Area Project Name Status Solutions Project In- Service Reliability Existing regulation is overloaded under first contingency Eastern Harrington LTC Planned Replace regulators and transformer with LTC including transformer swap from Ellsworth Falls Q2/2012 Reliability Line overload/rating Bangor Line 8 Reconductor Planned Reconductor 3.3 miles 46kV 12/2012 Reliability Need determined during MPRP study Eastern Trenton Cap Planned Cap addition to 34.5kV 12/2012 Reliability Transformer overload/rating Eastern Ellsworth Falls T2 replacement Planned Install new transformer, freeing old transformer to be redeployed at Harrington Q2/

12 LSP Under Construction Status Need Project In- Service Service Area Project Name Status Reliability Q1/2012 Eastern MDI Causeway Circuit Addition Under Construction Reliability Q1/2012 Bangor Line 7 Reconductor Under Construction Reliability 12/2012 Eastern Tunk Substation Under Construction Reliability 12/2011 Eastern Line 13 Franklin to Unionville Under Construction 12

13 LSP In- Service Need Project In- Service Month/Year Service Area Project Name Status Solutions None n/a 13

14 Maine and BHE Major Transmission System 14

15 Bangor Hydro Detailed System 15

16 Project Descriptions - Proposed 1 Bar Harbor capacity support 2 L87 Overload 16

17 Project Descriptions Proposed 17

18 1 Bar Harbor Capacity 18

19 2 Line 87 Overload 19

20 Project Descriptions - Planned 1- Harrington LTC 2 Line 8 Reconductor 3 Trenton Cap Bank Addition 4 Ellsworth Falls T2 Replacement 20

21 Project Descriptions - Planned 21

22 1 Harrington LTC 22

23 2 Line 8 Reconductor 23

24 3 Trenton Cap Addition 24

25 4 Ellsworth Falls T2 25

26 LSP Under Construction Status 1 MDI Causeway Circuit Addition 2 - Line 7 Reconductor 3 Tunk Substation 4 Line 13 Franklin to Unionville 26

27 Project Descriptions Under Const. 27

28 1 - MDI Causeway Circuit 28

29 2 Line 7 Support 29

30 3 Tunk Sub 30

31 4 Line 13 Rebuild 31

32 Local System Planning Criteria The transmission system for purposes of this study is defined as those system facilities that are operated at 34.5 kv and above and are not considered to be under ISO-NE planning (in general non PTF). The standard of service to be provided dictates the need for changes to the existing system. It is necessary to consider the capability of transmission system elements, possible equipment failures, and the impact of failures on the ability to serve area loads. Transmission equipment is designed to operate within certain capabilities. The power that may be transferred over transmission lines depends upon the current carrying capacity of the wire and/or the required clearances of lines above ground. Transformers are limited by their heat dissipation capability. Circuit breakers or switches are designed to sustain a certain continuous amount of current. Also, the operation of customer electrical equipment requires that voltage be maintained within a certain acceptable range. Transmission system facilities are capable of regulating voltage within a limited range by varying reactive power and changing transformer tap settings. 32

33 Local System Planning Criteria Since all equipment is subject to breakdown, it is necessary to consider the consequence of such failures. One possible outcome could be the overload of other equipment that remains in service. For example, if one of two parallel lines trips, the remaining line may become overloaded. Overload beyond emergency ratings must be avoided due to possible permanent damage to the equipment or for public safety. Another consequence of equipment failure is the loss of power supply to customer load. This could occur with the loss of a radial transmission line or as the result of the cascaded outage of a looped transmission system. The loss of supply is critical to loads such as industrial processing, home heating, and hospitals, and must be considered in the design of the transmission system. 33

34 Local System Planning Criteria CAPACITY CRITERION No facility is to be loaded in excess of its normal rating for any expected dispatch of system generation at any load level. For any single contingency, no facility is to be loaded in excess of its normal rating for the following load cycle or in excess of its emergency rating immediately following the contingency. Uneconomic generation dispatch may be utilized to maintain power flows within ratings following a contingency. VOLTAGE CRITERION Transmission system voltages are to be maintained between 95% and 105% of operating base voltage under normal system conditions and for any single contingency. Further, voltages on the regulated side of load serving buses are to be maintained between 100% and 105% of operating base voltage under normal system conditions. 34

35 Local System Planning Criteria LOSS OF LOAD CRITERION No loss of load in excess of 25 MW is to occur for any single contingency. Loss of load less than 25 MW should be resupplied within 24 hours, except under very adverse conditions. MAINTENANCE CRITERION Transmission system planned maintenance is to be possible without exceeding normal voltage and capacity limits and without loss of load. 35

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC OCTOBER 19, 2017 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC

More information

Maine Public Service Transmission System Reliability

Maine Public Service Transmission System Reliability Maine Public Service Transmission System Reliability Presentation at the Northern Maine Planning Advisory Group 5/15/13 Today s Presentation will cover: Part I Assumptions & Methodology Assumptions used

More information

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability

More information

Eastside Solution Study Executive Summary

Eastside Solution Study Executive Summary Attachment 2 - Eastside Solution Study PO BOX 97034, EST06W Bellevue, WA 98004 1-800-548-2614 Attachment 2 - The planning analysis discussed in this report has identified five alternative solutions to

More information

Wholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission

Wholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission Wholesale Electricity Markets and New England Independent System Operator Commissioner Mark Vannoy Maine Public Utilities Commission March 26, 2014 Overview and Background 2 Wholesale Electricity Markets

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Stanly County, NC Total Output Requested By Customer: 30 MW Commercial Operation Date Requested By Customer: 12/1/2019 Feasibility

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date Description

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

SRRTEP Meeting 2019 Annual Assumptions for Pepco

SRRTEP Meeting 2019 Annual Assumptions for Pepco SRRTEP Meeting 2019 Annual Assumptions for Pepco December 7, 2019 1 Agenda Base Case Power Flow Model PJM Baseline Analysis FERC 715 Analysis Supplemental Project Drivers Asset Management Drivers Retirement

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee January 6, 2011 Issues Tracking Issues Tracking Open Issues: None New Issues: 3 Baseline Reliability Update Remaining 2015 Analysis 2015 N-1-1 voltage study Results

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper April 2018 EXECUTIVE SUMMARY On February 13, 2018, the PJM Board of Managers approved changes to the

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

The State of Wind Energy in New England

The State of Wind Energy in New England JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New

More information

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite

More information

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403 AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination

More information

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

A separate notification will be provided to NPCC Members announcing the start of the formal 10 day ballot period.

A separate notification will be provided to NPCC Members announcing the start of the formal 10 day ballot period. October 3, 2011 NPCC Full and General Members; Please find attached a draft of the NPCC Regional Standard PRC-006-NPCC-1 Automatic Underfrequency Load Shedding which has been posted to the NPCC Website

More information

Grid Integration of Renewable Energy. Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO)

Grid Integration of Renewable Energy. Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO) Grid Integration of Renewable Energy Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO) October 2012 Contents HELCO System Overview Challenges of integrating

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

Transmission Expansion Advisory Committee. December 15, 2011

Transmission Expansion Advisory Committee. December 15, 2011 Transmission Expansion Advisory Committee December 15, 2011 Issues Tracking Issues Tracking Open Issues None New Issues 3 Backbone Transmission Project Status Susquehanna to Roseland Project Required June

More information

Overview of the Sheffield-Highgate Export Interface (SHEI)

Overview of the Sheffield-Highgate Export Interface (SHEI) Overview of the Sheffield-Highgate Export Interface (SHEI) Draft June 29, 2017 DRAFT Public VELCO Table of Contents Page Introduction... 1 Transmission reinforcements are driven by reliability, not economics...

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

TPL 001 AB 0 System Performance Under Normal Conditions

TPL 001 AB 0 System Performance Under Normal Conditions Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure

More information

Reliability Coordinator Area System Operating Limit Methodology

Reliability Coordinator Area System Operating Limit Methodology Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power

More information

Electric Transmission in Northern NH

Electric Transmission in Northern NH Electric Transmission in Northern NH What it takes to upgrade, replace or build new transmission needed to support new generation NHPUC Forum in Groveton 8/7/07 Agenda Purpose of meeting PUC The existing

More information

2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development

2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development 2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development New England Governors Adopt Long-term Renewable Energy Vision States

More information

Standard TPL (i) System Performance Under Normal Conditions

Standard TPL (i) System Performance Under Normal Conditions Standard TPL-001-0.1(i) System Performance Under rmal Conditions A. Introduction 1. Title: System Performance Under rmal ( Contingency) Conditions (Category A) 2. Number: TPL-001-0.1(i) 3. Purpose: System

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Plant Load Factor: 50%

Plant Load Factor: 50% Current power sector scenario that also includes: Percentage of growth in generation: 6% (Energy) Percentage of growth in load demand: 10% Plant Load Factor: 50% Outage rate to assess the reliability of

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

Year Assessment Preliminary Study Design

Year Assessment Preliminary Study Design 2018 10-Year Assessment Preliminary Study Design October 24, 2017 Stakeholder and Customer Webcast Jeremy Voigt, System Planning atcllc.com Purpose Summarize ATC s project development processes Solicit

More information

New England Electricity Outlook

New England Electricity Outlook O C T O B E R 2 1, 2 0 1 6 S O U T H P O R T L A N D, M E New England Electricity Outlook Environmental and Energy Technology Council of Maine (E2Tech) Eric Johnson D I R E C T O R, E X T E R N A L A F

More information

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Transmission Expansion Advisory Committee April 14, 2010 2010 RTEP Sensitivity Analysis Assumptions Renewable Portfolio Standards RPS Methodology Renewable portfolio standards by state Typically a target

More information

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. SEVEN-YEAR OUTLOOK: AN ASSESSMENT OF THE ADEQUACY OF GENERATION AND TRANSMISSION FACILITIES ON THE NORTHERN MAINE TRANSMISSION SYSTEM April 2017 INTRODUCTION

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu, Engineer Transmission Contracts December 9, 2010 Content Attachment K Review Primary Contacts Economic Studies Process PSE Planning

More information

Wide-Area Trans-Regional Northeast Reliability Assessment

Wide-Area Trans-Regional Northeast Reliability Assessment Wide-Area Trans-Regional Northeast Reliability Assessment Philip A. Fedora Kollin Patten Northeast Power Coordinating Council PowerWorld Corporation 1515 Broadway 43 rd Floor 1816 South Oak Street New

More information

Microgrids in New England Technical Challenges & Opportunities

Microgrids in New England Technical Challenges & Opportunities Microgrids in New England Technical Challenges & Opportunities October 10, 2012 Agenda I. What is a Microgrid? Examples Elements to Consider II. Why a Microgrid? Improved Reliability Utility Guiding Principals

More information

Western Colorado Transmission Study Report

Western Colorado Transmission Study Report Submitted to Colorado Coordinated Planning Group Studies Performed By: Western Slope Study Group November 6, 2013 Updated February 11, 2014 Executive Summary Loads and transfer obligations on the Western

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards

Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Draft for Planning Committee Review 3353 Peachtree Road

More information

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments

More information

5.4 Post Contingency Local Load Relief Warning

5.4 Post Contingency Local Load Relief Warning 5.4 Post Contingency Local Load Relief Warning Post Contingency Local Load Relief Warning Non-Market Post Contingency Local Load Relief Warning The purpose of the Post Contingency Local Load Relief Warning

More information

PSE&G Assumptions Overview. November 2018

PSE&G Assumptions Overview. November 2018 PSE&G Assumptions Overview November 2018 1 Base Case Models Base Case Model will includes PSE&G 69kV network PJM RTEP models shall be for assessments of RTEP years Multi-regional Modeling Working Group

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

EIPC Roll-Up Powerflow Model

EIPC Roll-Up Powerflow Model EIPC Roll-Up Powerflow Model Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG Meeting November 25, 2013 2013 New York Independent System Operator, Inc. All Rights

More information

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011 Decision 2011-496 December 15, 2011 The Alberta Utilities Commission Decision 2011-496: Application No. 1607774 Proceeding ID No. 1505 December 15, 2011 Published by The Alberta Utilities Commission Fifth

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions Seminar on African Electrical Interconnection Module 8 - Interconnected Systems Operating Conditions Module 8 - Interconnected Systems Operating Conditions Contents 1) Technical Operating Agreements 2)

More information

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS Reliability Coordinator Processes and Tools Objectives Describe how the FRCC Security Process addresses planning/coordination of the Bulk Electric System Describe

More information

NU Guidance on ISO-NE Proposed Plan Application (PPA) Process for Generators Connecting to the NU Distribution System

NU Guidance on ISO-NE Proposed Plan Application (PPA) Process for Generators Connecting to the NU Distribution System NU Guidance on ISO-NE Proposed Plan Application (PPA) Process for Generators Connecting to the NU Distribution System Introduction This Proposed Plan Application (PPA) primer will assist Interconnection

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

Transmission Expansion Advisory Committee. October 11, 2012

Transmission Expansion Advisory Committee. October 11, 2012 Transmission Expansion Advisory Committee October 11, 2012 Issues Tracking Issues Tracking Open Issues None New Issues 3 2012 RTEP - Renewable Portfolio Standards Scenarios Progress Update Scenario #1

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

Impact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc.

Impact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc. Impact of Variable Generation on the Vermont Transmission Grid Chris Root Vermont Electric Power Company, Inc. croot@velco.com VELCO-managed assets 738 miles of transmission lines, 115kV to 450kV, predominantly

More information

AEP Transmission Local Planning Assumptions, Models, and Criteria

AEP Transmission Local Planning Assumptions, Models, and Criteria AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States

More information

Feasibility Study Report

Feasibility Study Report Generator Interconnection Request Feasibility Study Report For: Click here to enter text. 2x1 Combined Cycle Plant Service Location: Anderson, SC Total Output: 754 MW Commercial Operation Date: 5/1/2016

More information

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard TPL-002-0b System Performance Following Loss of a Single BES Element A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed

More information

SSR STUDY REPORT FINAL

SSR STUDY REPORT FINAL System Support Resource Study Escanaba 1 & 2: 25 MW Coal 36 Month Suspension 6/15/2012 6/15/2015 SSR STUDY REPORT FINAL June 21, 2012 Redacted version for January 3, 2013 filing EXECUTIVE SUMMARY An Attachment

More information

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO Proposed Facility Study Report Project: A380_A383_A415_A414_A413 MISO # F088 Prepared for Midwest ISO January 15 th, 2010 Great River Energy Contact: Greg Schutte, Project Manager Great River Energy 1

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

Technical Analysis of Operational Events and Market Impacts During the September 2013 Heat Wave

Technical Analysis of Operational Events and Market Impacts During the September 2013 Heat Wave During the September 2013 Heat Wave PJM Interconnection December 23, 2013 Contents 1 Executive Summary... 4 2 Introduction... 7 3 Load Shed Event Assessments... 11 3.1 Pigeon River 1 Load Shed Event (September

More information

ISO New England Available Transfer Capability. Implementation Document. Version 1.0

ISO New England Available Transfer Capability. Implementation Document. Version 1.0 ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6

More information

March 3, Submitted to: CAISO

March 3, Submitted to: CAISO March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING

More information

Limon 100 MW Wind Farm System Interconnection Study

Limon 100 MW Wind Farm System Interconnection Study Limon 100 MW Wind Farm System Interconnection Study October 27, 2004 Studies Conducted By: Garrett Durland Limon Wind Farm Impact Study I. Introduction In April 2004, Western Area Power Administration

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

Moorpark-Pardee 230 kv No. 4 Circuit Project

Moorpark-Pardee 230 kv No. 4 Circuit Project Moorpark-Pardee 230 kv No. 4 Circuit Project Nebiyu Yimer Regional Transmission Engineer Lead 2017-2018 Transmission Planning Process Stakeholder Call January 11, 2018 This review is taking place in light

More information

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Business Operations, Engineering & Process, has primary responsibility for the overall planning, operations and control

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. SEVEN-YEAR OUTLOOK: AN ASSESSMENT OF THE ADEQUACY OF GENERATION AND TRANSMISSION FACILITIES ON THE NORTHERN MAINE TRANSMISSION SYSTEM April 2019 ME1

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038 Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction

More information

Standard TPL-004-0a System Performance Following Extreme BES Events

Standard TPL-004-0a System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-0a 3. Purpose: System simulations

More information

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating ALR1-1 Generator Reactive Limit Metric:Voltage schedules How many times did generators encounter var limits associated with holding voltage schedule. 10 3 2 1 1 3 1 Initial pilot effort completed, reaching

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

Transmission System Security and Planning Standards

Transmission System Security and Planning Standards ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2

More information

SPP RTO Compliance Forum TPL Jason Terhune

SPP RTO Compliance Forum TPL Jason Terhune SPP RTO Compliance Forum TPL-001-4 Jason Terhune 501-688-8261 jterhune@spp.org 1 TPL Standards have been Consolidated TPL-001-0.1 TPL-002-0b TPL-003-0b TPL-004-0a TPL-001-4 R1 R2 R3 R4 R5 R6 R7 R8 2 Overview

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue L-ENT-17A New Orleans, LA 70113 Rev Issue

More information

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 884 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE

More information

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households

More information

New England East-West Solution (NEEWS): Interstate Reliability Project Component Updated Needs Assessment

New England East-West Solution (NEEWS): Interstate Reliability Project Component Updated Needs Assessment New England East-West Solution (NEEWS): Interstate Reliability Project Component Updated Needs Assessment Southern New England Regional Working Group (ISO New England, National Grid, Northeast Utilities,

More information

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM

Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM 1. Administrative A. Introductions... All B. SPP Antitrust Guidelines...

More information

Transmission Expansion Advisory Committee. Reliability Analysis Update

Transmission Expansion Advisory Committee. Reliability Analysis Update Transmission Expansion Advisory Committee Reliability Analysis Update June 11, 2015 Deactivation Update Generation Deactivations 3 Deactivation Status Unit(s) FPL MH50 (50.8MWs) - UPDATED AES Beaver Valley

More information