1 Bangor Hydro s Local System Plan Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting November 17, 2011 Bangor Hydro Representative: Jeffrey Fenn, P.E., SGC Engineering
2 Purpose of Local System Plan (LSP) Per Attachment K - The LSP is an annual report that: 1. Describes non PTF transmission system reliability needs 2. Reflects 1. System planning studies 2. Proposed solutions 3. Identifies 1. Local planning process 2. Criteria, Data and Assumptions 2
3 LSP Communication 1. LSP is communicated via Local Planning Advisory Committee (LPAC) meeting for stakeholders convenience, this is being done following an ISO-NE PAC meeting 2. The material is posted prior to the LPAC meeting (via the ISO- NE PAC posting system) 3. Transmission Customers and Stakeholders have 30 days after posting to provide written comments for consideration by BHE 3
4 LSP Communication (cont.) 1. BHE Contact: Lisa Martin PO Box Illinois Avenue Bangor, Maine (207) BHE LSP is located at: 4
5 Local System Planning Process The process is Needs Assessment followed by Solutions Proposals Local System needs can result from: Load Growth Sub-area reliability assessments Point of delivery request from customers Generation interconnection requests (in accordance with appropriate generator interconnection procedures) Local System Plan consists of: Summary of needs assessment results Listing of criteria, data and study assumptions Identification of proposed alternatives Solution study results and selection of preferred alternative 5
6 Criteria, Data and Assumptions Loads based on CELT Report forecasts for the New England area, BHE specific forecasts and local customer needs Studies based on the ISO-NE library base cases and short circuit database Studies use relevant assumptions regarding transmission, generation and demand resources found in the latest ISO-NE Regional System Plan 6
7 LSP Project List 1. The LSP project list is a cumulative listing of proposed regulated transmission solutions intended to meet local needs 2. Similar to the ISO-NE PTF RSP, the LSP contains the status of each project Concept Project is under consideration as a solution to a partial needs assessment Proposed Needs assessment completed and project proposed as a solution, but not formally budgeted Planned Formally budgeted and if necessary, approved by ISO- NE Under Construction Significant engineering and internal approvals in process and project is being implemented In-Service Project used and useful 7
8 Bangor Hydro Detailed System 8
9 LSP Concept Status Need Needs Assessment Service Area Project Name Status Solutions Project In- Service Month/Year Reliability Chester T1 and T2 Overloading Northern Chester T1/T2 OL Concept Possible solution as part of BHE Annual Transmission Needs and Solutions Assessment 12/2013 9
10 LSP Proposed Status Need Needs Assessment Service Area Project Name Status Solutions Project In- Service Reliability Support of area loads, eliminate overload of L22 and improve ability to maintain transmission circuits Eastern Bar Harbor support Proposed Additional 34.5kV circuit with diverse route. Part of area looping 12/2012 Reliability Line 87 from Chester to Lincoln Overload Northern Line 87 Overload Proposed Rebuild 12/
11 LSP Planned Status Need Needs Assessment Service Area Project Name Status Solutions Project In- Service Reliability Existing regulation is overloaded under first contingency Eastern Harrington LTC Planned Replace regulators and transformer with LTC including transformer swap from Ellsworth Falls Q2/2012 Reliability Line overload/rating Bangor Line 8 Reconductor Planned Reconductor 3.3 miles 46kV 12/2012 Reliability Need determined during MPRP study Eastern Trenton Cap Planned Cap addition to 34.5kV 12/2012 Reliability Transformer overload/rating Eastern Ellsworth Falls T2 replacement Planned Install new transformer, freeing old transformer to be redeployed at Harrington Q2/
12 LSP Under Construction Status Need Project In- Service Service Area Project Name Status Reliability Q1/2012 Eastern MDI Causeway Circuit Addition Under Construction Reliability Q1/2012 Bangor Line 7 Reconductor Under Construction Reliability 12/2012 Eastern Tunk Substation Under Construction Reliability 12/2011 Eastern Line 13 Franklin to Unionville Under Construction 12
13 LSP In- Service Need Project In- Service Month/Year Service Area Project Name Status Solutions None n/a 13
14 Maine and BHE Major Transmission System 14
15 Bangor Hydro Detailed System 15
16 Project Descriptions - Proposed 1 Bar Harbor capacity support 2 L87 Overload 16
17 Project Descriptions Proposed 17
18 1 Bar Harbor Capacity 18
19 2 Line 87 Overload 19
20 Project Descriptions - Planned 1- Harrington LTC 2 Line 8 Reconductor 3 Trenton Cap Bank Addition 4 Ellsworth Falls T2 Replacement 20
21 Project Descriptions - Planned 21
22 1 Harrington LTC 22
23 2 Line 8 Reconductor 23
24 3 Trenton Cap Addition 24
25 4 Ellsworth Falls T2 25
26 LSP Under Construction Status 1 MDI Causeway Circuit Addition 2 - Line 7 Reconductor 3 Tunk Substation 4 Line 13 Franklin to Unionville 26
27 Project Descriptions Under Const. 27
28 1 - MDI Causeway Circuit 28
29 2 Line 7 Support 29
30 3 Tunk Sub 30
31 4 Line 13 Rebuild 31
32 Local System Planning Criteria The transmission system for purposes of this study is defined as those system facilities that are operated at 34.5 kv and above and are not considered to be under ISO-NE planning (in general non PTF). The standard of service to be provided dictates the need for changes to the existing system. It is necessary to consider the capability of transmission system elements, possible equipment failures, and the impact of failures on the ability to serve area loads. Transmission equipment is designed to operate within certain capabilities. The power that may be transferred over transmission lines depends upon the current carrying capacity of the wire and/or the required clearances of lines above ground. Transformers are limited by their heat dissipation capability. Circuit breakers or switches are designed to sustain a certain continuous amount of current. Also, the operation of customer electrical equipment requires that voltage be maintained within a certain acceptable range. Transmission system facilities are capable of regulating voltage within a limited range by varying reactive power and changing transformer tap settings. 32
33 Local System Planning Criteria Since all equipment is subject to breakdown, it is necessary to consider the consequence of such failures. One possible outcome could be the overload of other equipment that remains in service. For example, if one of two parallel lines trips, the remaining line may become overloaded. Overload beyond emergency ratings must be avoided due to possible permanent damage to the equipment or for public safety. Another consequence of equipment failure is the loss of power supply to customer load. This could occur with the loss of a radial transmission line or as the result of the cascaded outage of a looped transmission system. The loss of supply is critical to loads such as industrial processing, home heating, and hospitals, and must be considered in the design of the transmission system. 33
34 Local System Planning Criteria CAPACITY CRITERION No facility is to be loaded in excess of its normal rating for any expected dispatch of system generation at any load level. For any single contingency, no facility is to be loaded in excess of its normal rating for the following load cycle or in excess of its emergency rating immediately following the contingency. Uneconomic generation dispatch may be utilized to maintain power flows within ratings following a contingency. VOLTAGE CRITERION Transmission system voltages are to be maintained between 95% and 105% of operating base voltage under normal system conditions and for any single contingency. Further, voltages on the regulated side of load serving buses are to be maintained between 100% and 105% of operating base voltage under normal system conditions. 34
35 Local System Planning Criteria LOSS OF LOAD CRITERION No loss of load in excess of 25 MW is to occur for any single contingency. Loss of load less than 25 MW should be resupplied within 24 hours, except under very adverse conditions. MAINTENANCE CRITERION Transmission system planned maintenance is to be possible without exceeding normal voltage and capacity limits and without loss of load. 35
Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC
OCTOBER 19, 2017 Emera Maine s Local System Plan Bangor Hydro District Needs Assessment/Potential Solutions Local Planning Advisory Committee Meeting Emera Maine Representative: Jeffrey Fenn, P.E., SGC
More informationMaine Public Service Transmission System Reliability
Maine Public Service Transmission System Reliability Presentation at the Northern Maine Planning Advisory Group 5/15/13 Today s Presentation will cover: Part I Assumptions & Methodology Assumptions used
More informationPJM White Paper. Transource Independence Energy Connection Market Efficiency Project
PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability
More informationEastside Solution Study Executive Summary
Attachment 2 - Eastside Solution Study PO BOX 97034, EST06W Bellevue, WA 98004 1-800-548-2614 Attachment 2 - The planning analysis discussed in this report has identified five alternative solutions to
More informationWholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission
Wholesale Electricity Markets and New England Independent System Operator Commissioner Mark Vannoy Maine Public Utilities Commission March 26, 2014 Overview and Background 2 Wholesale Electricity Markets
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More informationTRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA
TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014
No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide
More informationFeasibility Study Report
Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Stanly County, NC Total Output Requested By Customer: 30 MW Commercial Operation Date Requested By Customer: 12/1/2019 Feasibility
More informationPOTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More informationPID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation
PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date Description
More informationPlatte River Power Authority. Ten-Year Transmission Plan ( )
Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.
More informationSRRTEP Meeting 2019 Annual Assumptions for Pepco
SRRTEP Meeting 2019 Annual Assumptions for Pepco December 7, 2019 1 Agenda Base Case Power Flow Model PJM Baseline Analysis FERC 715 Analysis Supplemental Project Drivers Asset Management Drivers Retirement
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee January 6, 2011 Issues Tracking Issues Tracking Open Issues: None New Issues: 3 Baseline Reliability Update Remaining 2015 Analysis 2015 N-1-1 voltage study Results
More informationASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.
ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates
More informationStandard MH-TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationTransmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board
Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board PJM Staff Whitepaper April 2018 EXECUTIVE SUMMARY On February 13, 2018, the PJM Board of Managers approved changes to the
More informationEast Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria
East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission
More informationThe State of Wind Energy in New England
JUNE 9, 2017 PORTLAND, MAINE The State of Wind Energy in New England Everyone Knows Its Windy The State of Wind Energy Alan McBride DIRECTOR TRANSMISSION STRATEGY & SERVICES Wind Power Has Emerged in New
More informationCOLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN
COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite
More informationApril 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403
AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination
More informationGenerator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report
Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent
More informationStandard TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationA separate notification will be provided to NPCC Members announcing the start of the formal 10 day ballot period.
October 3, 2011 NPCC Full and General Members; Please find attached a draft of the NPCC Regional Standard PRC-006-NPCC-1 Automatic Underfrequency Load Shedding which has been posted to the NPCC Website
More informationGrid Integration of Renewable Energy. Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO)
Grid Integration of Renewable Energy Robert S. Kaneshiro, P.E. Operations Assistant Superintendent Hawaii Electric Light Company (HELCO) October 2012 Contents HELCO System Overview Challenges of integrating
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationStakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5
Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods
More informationStandard Development Timeline
Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be
More informationTransmission Expansion Advisory Committee. December 15, 2011
Transmission Expansion Advisory Committee December 15, 2011 Issues Tracking Issues Tracking Open Issues None New Issues 3 Backbone Transmission Project Status Susquehanna to Roseland Project Required June
More informationOverview of the Sheffield-Highgate Export Interface (SHEI)
Overview of the Sheffield-Highgate Export Interface (SHEI) Draft June 29, 2017 DRAFT Public VELCO Table of Contents Page Introduction... 1 Transmission reinforcements are driven by reliability, not economics...
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationTPL 001 AB 0 System Performance Under Normal Conditions
Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure
More informationReliability Coordinator Area System Operating Limit Methodology
Reliability Coordinator Area System Operating Limit Methodology Revision 1.0 MAINTAINED BY SPP Operations Staff PUBLISHED: 10/19/2018 LATEST REVISION: Effective 10/19/2018 Copyright 2018 by Southwest Power
More informationElectric Transmission in Northern NH
Electric Transmission in Northern NH What it takes to upgrade, replace or build new transmission needed to support new generation NHPUC Forum in Groveton 8/7/07 Agenda Purpose of meeting PUC The existing
More information2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development
2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development New England Governors Adopt Long-term Renewable Energy Vision States
More informationStandard TPL (i) System Performance Under Normal Conditions
Standard TPL-001-0.1(i) System Performance Under rmal Conditions A. Introduction 1. Title: System Performance Under rmal ( Contingency) Conditions (Category A) 2. Number: TPL-001-0.1(i) 3. Purpose: System
More information2015 Operational Practices Survey Questions
2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated
More informationMapping Document for FAC-010-3
Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding
More information1.3 Planning Assumptions and Model Development
Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission
More informationPlant Load Factor: 50%
Current power sector scenario that also includes: Percentage of growth in generation: 6% (Energy) Percentage of growth in load demand: 10% Plant Load Factor: 50% Outage rate to assess the reliability of
More informationLOCAL PLANNING REPORT
Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared
More informationEIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015
EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be
More informationYear Assessment Preliminary Study Design
2018 10-Year Assessment Preliminary Study Design October 24, 2017 Stakeholder and Customer Webcast Jeremy Voigt, System Planning atcllc.com Purpose Summarize ATC s project development processes Solicit
More informationNew England Electricity Outlook
O C T O B E R 2 1, 2 0 1 6 S O U T H P O R T L A N D, M E New England Electricity Outlook Environmental and Energy Technology Council of Maine (E2Tech) Eric Johnson D I R E C T O R, E X T E R N A L A F
More informationTransmission Expansion Advisory Committee
Transmission Expansion Advisory Committee April 14, 2010 2010 RTEP Sensitivity Analysis Assumptions Renewable Portfolio Standards RPS Methodology Renewable portfolio standards by state Typically a target
More informationNORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.
NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. SEVEN-YEAR OUTLOOK: AN ASSESSMENT OF THE ADEQUACY OF GENERATION AND TRANSMISSION FACILITIES ON THE NORTHERN MAINE TRANSMISSION SYSTEM April 2017 INTRODUCTION
More informationStandard TPL System Performance Following Extreme BES Events
A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations
More informationStandard TPL-003-0b System Performance Following Loss of Two or More BES Elements
A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically
More informationPSE Attachment K Puget Sound Area Transmission Meeting
PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu, Engineer Transmission Contracts December 9, 2010 Content Attachment K Review Primary Contacts Economic Studies Process PSE Planning
More informationWide-Area Trans-Regional Northeast Reliability Assessment
Wide-Area Trans-Regional Northeast Reliability Assessment Philip A. Fedora Kollin Patten Northeast Power Coordinating Council PowerWorld Corporation 1515 Broadway 43 rd Floor 1816 South Oak Street New
More informationMicrogrids in New England Technical Challenges & Opportunities
Microgrids in New England Technical Challenges & Opportunities October 10, 2012 Agenda I. What is a Microgrid? Examples Elements to Consider II. Why a Microgrid? Improved Reliability Utility Guiding Principals
More informationWestern Colorado Transmission Study Report
Submitted to Colorado Coordinated Planning Group Studies Performed By: Western Slope Study Group November 6, 2013 Updated February 11, 2014 Executive Summary Loads and transfer obligations on the Western
More informationAESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS
APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,
More informationSpecial Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards
Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Draft for Planning Committee Review 3353 Peachtree Road
More informationSYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE
SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More informationStandard TPL-003-0b System Performance Following Loss of Two or More BES Elements
Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments
More information5.4 Post Contingency Local Load Relief Warning
5.4 Post Contingency Local Load Relief Warning Post Contingency Local Load Relief Warning Non-Market Post Contingency Local Load Relief Warning The purpose of the Post Contingency Local Load Relief Warning
More informationPSE&G Assumptions Overview. November 2018
PSE&G Assumptions Overview November 2018 1 Base Case Models Base Case Model will includes PSE&G 69kV network PJM RTEP models shall be for assessments of RTEP years Multi-regional Modeling Working Group
More informationAESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)
(R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric
More informationCAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)
Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC
More informationEIPC Roll-Up Powerflow Model
EIPC Roll-Up Powerflow Model Zach Smith Director, Transmission Planning New York Independent System Operator IPTF/EGCWG Meeting November 25, 2013 2013 New York Independent System Operator, Inc. All Rights
More informationDecision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011
Decision 2011-496 December 15, 2011 The Alberta Utilities Commission Decision 2011-496: Application No. 1607774 Proceeding ID No. 1505 December 15, 2011 Published by The Alberta Utilities Commission Fifth
More informationNERC PLANNING STANDARDS
NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation
More informationSeminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions
Seminar on African Electrical Interconnection Module 8 - Interconnected Systems Operating Conditions Module 8 - Interconnected Systems Operating Conditions Contents 1) Technical Operating Agreements 2)
More informationFRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools
FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS Reliability Coordinator Processes and Tools Objectives Describe how the FRCC Security Process addresses planning/coordination of the Bulk Electric System Describe
More informationNU Guidance on ISO-NE Proposed Plan Application (PPA) Process for Generators Connecting to the NU Distribution System
NU Guidance on ISO-NE Proposed Plan Application (PPA) Process for Generators Connecting to the NU Distribution System Introduction This Proposed Plan Application (PPA) primer will assist Interconnection
More informationTable of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.
Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6
More informationTransmission Expansion Advisory Committee. October 11, 2012
Transmission Expansion Advisory Committee October 11, 2012 Issues Tracking Issues Tracking Open Issues None New Issues 3 2012 RTEP - Renewable Portfolio Standards Scenarios Progress Update Scenario #1
More informationStandards de planification du NERC
Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council
More informationImpact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc.
Impact of Variable Generation on the Vermont Transmission Grid Chris Root Vermont Electric Power Company, Inc. croot@velco.com VELCO-managed assets 738 miles of transmission lines, 115kV to 450kV, predominantly
More informationAEP Transmission Local Planning Assumptions, Models, and Criteria
AEP Transmission Local Planning Assumptions, Models, and Criteria PJM Sub-Regional RTEP Western Meeting December 5, 2018 Introduction to AEP AEP is among the largest electric utilities in the United States
More informationFeasibility Study Report
Generator Interconnection Request Feasibility Study Report For: Click here to enter text. 2x1 Combined Cycle Plant Service Location: Anderson, SC Total Output: 754 MW Commercial Operation Date: 5/1/2016
More informationStandard TPL-002-0b System Performance Following Loss of a Single BES Element
A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed
More informationSSR STUDY REPORT FINAL
System Support Resource Study Escanaba 1 & 2: 25 MW Coal 36 Month Suspension 6/15/2012 6/15/2015 SSR STUDY REPORT FINAL June 21, 2012 Redacted version for January 3, 2013 filing EXECUTIVE SUMMARY An Attachment
More informationProposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO
Proposed Facility Study Report Project: A380_A383_A415_A414_A413 MISO # F088 Prepared for Midwest ISO January 15 th, 2010 Great River Energy Contact: Greg Schutte, Project Manager Great River Energy 1
More informationDRAFT STUDY PLAN FOR 2018
DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure
More informationTechnical Analysis of Operational Events and Market Impacts During the September 2013 Heat Wave
During the September 2013 Heat Wave PJM Interconnection December 23, 2013 Contents 1 Executive Summary... 4 2 Introduction... 7 3 Load Shed Event Assessments... 11 3.1 Pigeon River 1 Load Shed Event (September
More informationISO New England Available Transfer Capability. Implementation Document. Version 1.0
ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6
More informationMarch 3, Submitted to: CAISO
March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING
More informationLimon 100 MW Wind Farm System Interconnection Study
Limon 100 MW Wind Farm System Interconnection Study October 27, 2004 Studies Conducted By: Garrett Durland Limon Wind Farm Impact Study I. Introduction In April 2004, Western Area Power Administration
More informationTTC/ATC 1.0 DEFINITIONS
TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule
More informationMoorpark-Pardee 230 kv No. 4 Circuit Project
Moorpark-Pardee 230 kv No. 4 Circuit Project Nebiyu Yimer Regional Transmission Engineer Lead 2017-2018 Transmission Planning Process Stakeholder Call January 11, 2018 This review is taking place in light
More informationLast revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS
Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Business Operations, Engineering & Process, has primary responsibility for the overall planning, operations and control
More informationInterconnection Feasibility Study
XXXXX Ditni Yoh Green Energy April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION OF LIABILITY
More informationInterconnection Feasibility Study
XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION
More informationNORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.
NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC. SEVEN-YEAR OUTLOOK: AN ASSESSMENT OF THE ADEQUACY OF GENERATION AND TRANSMISSION FACILITIES ON THE NORTHERN MAINE TRANSMISSION SYSTEM April 2019 ME1
More informationGeneration Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038
Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position AA1-038 Lexington Low Moor 230kV 10.1MW Capacity / 78.2MW Energy September / 2015 Introduction
More informationStandard TPL-004-0a System Performance Following Extreme BES Events
A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-0a 3. Purpose: System simulations
More informationApproved RMWG Discussion was held. ??? John Simpson need to assign SMART rating
ALR1-1 Generator Reactive Limit Metric:Voltage schedules How many times did generators encounter var limits associated with holding voltage schedule. 10 3 2 1 1 3 1 Initial pilot effort completed, reaching
More informationConnection Study Requirements
Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.
More informationTransmission System Security and Planning Standards
ver. 1.4 page 1 from 13 Transmission System Security and Planning Standards April 2014 ver. 1.4 page 2 from 13 TABLE OF CONTENTS 1 Introduction... 4 2 Definitions... 4 2.1 Transmission System... 4 2.2
More informationSPP RTO Compliance Forum TPL Jason Terhune
SPP RTO Compliance Forum TPL-001-4 Jason Terhune 501-688-8261 jterhune@spp.org 1 TPL Standards have been Consolidated TPL-001-0.1 TPL-002-0b TPL-003-0b TPL-004-0a TPL-001-4 R1 R2 R3 R4 R5 R6 R7 R8 2 Overview
More informationAEP Guidelines for Transmission Owner Identified Needs
AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal
More informationPID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation
PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation Prepared by: Entergy Services, Inc. T & D Planning 639 Loyola Avenue L-ENT-17A New Orleans, LA 70113 Rev Issue
More informationSERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION
Southern California Edison Company Tariff Title: Wholesale Distribution Access Tariff Tariff Record Title: Service Agreement No. 884 Title Page FERC FPA Electric Tariff SERVICE AGREEMENT FOR WHOLESALE
More informationAddressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015
Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households
More informationNew England East-West Solution (NEEWS): Interstate Reliability Project Component Updated Needs Assessment
New England East-West Solution (NEEWS): Interstate Reliability Project Component Updated Needs Assessment Southern New England Regional Working Group (ISO New England, National Grid, Northeast Utilities,
More informationSouthwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM
Southwest Power Pool, Inc. Entergy ENTERGY SPP RTO REGIONAL PLANNING PROCESS MEETING June 16, 2011 NET CONFERENCE AGENDA 1:30 3:00 PM 1. Administrative A. Introductions... All B. SPP Antitrust Guidelines...
More informationTransmission Expansion Advisory Committee. Reliability Analysis Update
Transmission Expansion Advisory Committee Reliability Analysis Update June 11, 2015 Deactivation Update Generation Deactivations 3 Deactivation Status Unit(s) FPL MH50 (50.8MWs) - UPDATED AES Beaver Valley