COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

Size: px
Start display at page:

Download "COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN"

Transcription

1 COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR (503)

2 8338 NE Alderwood Road, Suite 140 Portland, OR Disclaimer: The data and analyses contained in this report are not warranted by ColumbiaGrid or any other party, nor does ColumbiaGrid accept delegation of responsibility for compliance with any industry compliance or reliability requirement, including any reliability standard. Any reliance on this data or analyses is done so at the user s own risk.

3 Table of Contents Introduction... 1 System Assessment Timeline... 1 Base Case Development Process... 3 Study Years & Base Cases... 3 Determining Study Years... 4 Selecting Base Cases... 4 Major Assumptions Base Topology & Ten-Year Plan... 5 Loads... 5 Resources... 6 Interchanges... 6 Contingencies... 7 TPL Contingencies & Automatic Actions... 7 Processing Contingencies... 7 Limit Monitoring... 7 Post Contingency Solution Settings... 7 Results Review Methodology... 8 Identify Order 1000 Needs... 8 Transient Stability Studies... 9 Other Studies... 9

4 Introduction The foundation for the Biennial Transmission Expansion Plan (BTEP) is the ColumbiaGrid System Assessment. The System Assessment study effort focuses on an evaluation of whether or not the Northwest planned transmission grid meets established reliability standards; primarily from North American Electric Reliability Corporation (NERC) and Western Electricity Coordinating Council (WECC) Transmission Planning. It also includes a study to identify Order 1000 Needs, a re-evaluation of previous year Order 1000 projects, and other various planning activities. The ColumbiaGrid System Assessment report is issued in July of each year. The draft 2018 System Assessment Study Plan includes several sections that describe the activities required to complete the major elements of the assessment. These activities include (1) Reliability Assessment Study, (2) Order 1000 Related Activities, (3) Transient Stability Study, and (4) Other Activities. Among these, the first section of the plan details key elements and associated timelines of each activity. The second section describes the process of which ColumbiaGrid develops the base cases and base case content. Followed by the details of major assumptions in each base case (transmission projects that will be built within the 10 year planning horizon); anticipated electricity demand (load levels); resources; and target power flow on key transmission interchanges. The remaining section elaborates on how the contingency descriptions are established for Reliability Studies. Furthermore, the end of this document provides the descriptions of other activities in addition to the Reliability Assessment that may be conducted by ColumbiaGrid as part of System Assessment. These include part of FERC Order 1000 activities which require ColumbiaGrid to evaluate Potential Order 1000 Needs suggestions as part of the System Assessment, Transient Stability, and other studies that may be conducted by ColumbiaGrid. System Assessment Timeline Table 1 provides an approximate timeline and lists the key activities for the 2018 System Assessment.; with a launch date of November 2017 and an intended completion date by the 3rd quarter of

5 Study Plan Meeting: Select Base Planning / Stability Cases Review and Update Modeling Assumptions Review TPl / Stability Contingency & Automatic Action File Assumptions to be requested Develop Base Study and Discuss Sensitivity Study Plans Provide Available WECC Approved Base Cases & Dynamics Files for Updates (Group A) Distribute Ten-Year Plan for Review Solicit Order 1000 Potential Needs suggestions Finalize Ten-Year Plan Provide Any Remaining Base Cases & Dynamics Files Approved by WECC after the Initial Set of Cases for Updates (Group B) Review and Finalize Group A Study Cases & Dynamics Files (Due by End of Month) Review and Finalize Group B Study Cases & Dynamics Files (Due by End of Month) Load 2017 Contingency & Automatic Action Models into Finalized Cases and Note Consistency Issues Reaffirm base and sensitivity study plan Provide Initial Contingency & Automatic Action Models for Review and Updates (Due by End of Month) Process & Review Contingency Results for Light Load Case, One 5 Year Case, and Both 10 Year Cases Evaluate Order 1000 Potential Needs Process & Review Transient Stability Study Contingency Results Prepare System Assessment Identify Order 1000 Needs Prepare Needs Statement Finalize System Assessment Recommend Study Teams for Proposed & Order 1000 Needs Build Additional Near Term and 5 Year Study Cases for Members (Start After Finalizing Initial Cases) Table 1: System Assessment Timeline 2

6 Base Case Development Process ColumbiaGrid members identified coordinated base case development as a valuable process in order to provide a common starting point to use for their own assessments. The goal is to provide base cases, which can be used as the starting points for technical studies that are required by applicable reliability standards (Transmission Planning (TPL) standard TPL and others). The assessment work performed by ColumbiaGrid will be done on a subset of these cases. Additional cases may be produced, as a result of the study work that cannot be accommodated. ColumbiaGrid completes this activity by the first quarter of every year. This section provides descriptions and background of the cases that will be created by ColumbiaGrid. Study Years & Base Cases NERC TPL standard requires analysis to be done on base assumption cases for several scenarios where high electricity demands are anticipated. These include year one or year two peak load, short-term year five peak load, one to five year off-peak load, and long-term peak load. To meet the case requirements, ColumbiaGrid will develop at least seven base cases in These include two base assumption cases for each of the peak load cases (heavy summer 1, 5, and 10 year cases and heavy winter 1, 5, and 10 year cases) and one 5 year off-peak case. Such cases would be a starting point to accommodate all steady state and transient study scenarios required by TPL Typically, applicable approved WECC cases are selected as a starting point to create these cases. The process starts by determining the study years and selecting base cases. Other cases may be developed based on study needs for planned sensitivities, Order 1000 work, or to provide members with studies for their use. The information regarding these study scenarios as required by TPL is listed in Table 2 below. Additional cases may be created later, upon request from members. Study Timeframe Year One or Year Two Short-Term Long-Term Loading Condition Peak Load Table 2: Base Case Study Timeframe Needs for Loading Conditions Off-Peak Load After the cases are finalized, they may be used in several technical studies performed by ColumbiaGrid and other entities. Table 3 summarizes potential utilization of these cases. X X X X 3

7 Study Scenarios Study Timeframe Steady State Base Steady State Sensitivity Short Circuit Transient & Voltage Stability Year One or Year Two X X Short-Term X X X X Long-Term X X Table 3: Base Case Possible Scenario Uses for Study Timeframe DETERMINING STUDY YEARS For each timeframe, study years are determined by the projected end of the System Assessment process; which is mid-summer of the current Assessment year. All case study years were determined and discussed with the members. Additional cases may be developed for member use to account for different interpretations of required study years and study schedules. SELECTING BASE CASES The strategy for selecting base cases is to utilize recent approved WECC cases that closely represent current system topology and desired seasonal system conditions. Alternatively, previous year s System Assessment cases may be selected if WECC case availability is limited. The topology and resources for these cases are adjusted to create the study cases. Table 4 lists the study years that were selected as the base cases for the 2018 System Assessment. Initial WECC Case Study Year Study Case Study Plan 18HW3-OP yr Heavy Winter Member Use 21LSP1-S 2021 Near Term Light Load Study 23HS yr Heavy Summer Study 23HW yr Heavy Winter Member Use 28HS yr Heavy Summer Study 28HW yr Heavy Winter Study Table 4: WECC seed cases and System Assessment Base Case Study Years 4

8 Major Assumptions After the base cases are selected, the study cases are developed with the intent to complete them prior to building the contingency lists. This section describes a summary of key assumptions that will be used to create the base cases. However, additional adjustments may be made after the issuance of this document. In such incident, a summary of these adjustments will be reported in the 2018 System Assessment and made available upon request after the cases are finalized. Base Topology & Ten-Year Plan As outlined in Table 1, the base case development process starts with ColumbiaGrid issuing the initial cases for the members to provide updates to case topologies. Updates should include corrections to case errors and project adjustments to match the Ten-Year Plan. The ColumbiaGrid Ten-Year Plan comprises a list of projects which planning participants are committed to build (in the permitting, design, or construction phases) within the coming years, to address known transmission deficiencies. The projects in the Ten-Year Plan fill a variety of needs such as serving load, integrating new resources, or facilitating economic transfers. The projects may have been generated in a variety of forums such as earlier System Assessments, studies completed by the study teams, or individual planning participant studies. A summary of the Ten-Year plan is summarized in Appendix A that will be included in the final version of this Study Plan. To maintain data quality, the Ten-Year Plan will not be adjusted after it has been finalized unless the changes are determined as critical elements that would invalidate the System Assessment. This determination may be made by ColumbiaGrid participating parties. Loads Similar to topology modeling; members will direct ColumbiaGrid on load adjustments in their areas, for the System Assessment cases from the starting WECC cases. Members should provide (1) a file that updates the loads for each of the cases to the desired levels or (2) provide specific levels for ColumbiaGrid to scale their loads. Unless directed otherwise; ColumbiaGrid would adjust a participant s designated scalable load in the base case, until all of the participant s loads reach the desired level. A constant P/Q ratio would be maintained. Any expected changes to block loads for scaling should also be provided. A summary of the load levels that were modeled in ColumbiaGrid base cases after the adjustment will be included in the final version of this Study Plan. 5

9 Resources Generation patterns for the System Assessment cases will initially be set to the associated seasonal WECC base case. Adjustments to this pattern would include corrections to better represent expected generation patterns (such as adjusting wind generation output levels) or justified changes such as a new resources or the retirement of an existing resource. Balancing of the area will be done via interchange adjustments; typically from California for winter cases and the Columbia River hydro for summer cases. Interchanges Interchanges are used to balance and stress the case. This is primarily done with California and Canadian interchanges, whereas the remaining interchanges are typically untouched. The California interchange is used to balance the system in winter cases and the Columbia River hydro system is used for summer cases. The Canadian interchange is used to stress the system and is set to 2300 MW North-to-South for summer peak cases and 1500 MW South-to- North for winter peak cases, reflecting current firm transmission service commitments on the Westside Northern Intertie (Path 3). After the loads, resources and interchanges are adjusted; the study cases will be sent out for final review. If the cases are accepted by the members, they will be used to build the contingency. Table 5 details the initial study case resource and interchange assumptions to be used for the 2018 System Assessment. Initial WECC Case Study Year Generation Wind Hydro Remaining Idaho/ Montana Interchange Adjustments BC COI/PDCI Loads 18HS4-OP 2019 Off Balance Typical Maintain 2300 NS Maintain 18HW3-OP 2019 Off Typical Typical Maintain 1500 SN Balance 50% not exceed 50% not exceed 21LSP1-S 2021 Cap Factor (30-40%) Balance Typical Maintain Maintain Maintain typical 23HS Off Balance Typical Maintain 2300 NS Maintain 23HW Off Typical Typical Maintain 1500 SN Balance 28HS Off Balance Typical Maintain 2300 NS Maintain 28HW Off Typical Typical Maintain 1500 SN Balance 50% not exceed 50% not exceed 50% not exceed 50% not exceed Table 5: 2018 System Assessment Initial Base Case Assumptions 6

10 Contingencies TPL Contingencies & Automatic Actions After the study cases are finalized; ColumbiaGrid and the members will jointly develop contingency files, in compliance with TPL and WECC criterion TPL-001- WECC-CRT-2.1. A detailed description of what needs to be submitted is described in the ColumbiaGrid System Assessment Contingency Methodology paper. By suggestion, a base list will be created for the One-Year cases and then provide individual change files for each Ten-Year Plan project or each of the 5 year and the 10 year cases. The previous year s contingency may be used as a starting point for this list. Processing Contingencies This section describes the method used to process contingency lists. LIMIT MONITORING The following limit monitoring settings are used for System Assessment contingencies: Seasonal normal and post contingency/ emergency branch thermal limits are monitored based on WECC s convention (i.e. summer normal = limit A, summer emergency = limit B, winter normal = limit C, winter emergency = limit D, etc.). Radial lines and buses are not monitored. Only elements in Area 40 (Northwest) are monitored. Branch violations are only flagged if branch flow increases by more than 1%. Bus violations are only flagged if bus voltages change by more than 0.02 per unit. Bus voltage monitoring settings are supplied by participants. Bus voltage change of greater than 5% (based on WECC criteria). Voltage angle change of more than 5 degrees across branches opened in a contingency. Only angles more than 30 degrees are reported. POST CONTINGENCY SOLUTION SETTINGS The post contingency solution settings differ from the default pre-solution settings by not allowing most Switched Shunts, Load Tap Changing Transformers (LTCs), and Phase Shifters from mimicking the system conditions right after the contingency occurs. Static Var Compensator (SVC) devices and automatically controlled shunts are allowed to operate. Participants must provide which shunts are automatically controlled to properly model the post contingency system condition. Post contingency solution settings are used for any contingency that has a solution embedded into the contingency definition. This allows participants to document the system condition for PRC-023 for N-1-1 conditions. 7

11 RESULTS REVIEW METHODOLOGY All study cases are initially reviewed for violations without outages (N-0 conditions). Any voltage violations or facility overloads that could not be resolved through tuning the cases are provided to the participants and reported in the System Assessment. The provided TPL and WECC criterion TPL-001-WECC-CRT-2.1 contingencies are then processed. All results are reviewed for accuracy and provided to participants for review. The results are pared down for additional study by the following criteria: N-1-X: All contingencies results with initial outage conditions (i.e. P3 or P6) are studied for informational purposes only. Results are sorted to identify contingency combinations that have more than one participant. Additional study work may be done if requested by the participants. Single System: The System Assessment focuses on joint issues where the outages and associated violations are owned by multiple participant utilities and where joint transmission planning may be needed. Instances where the outage and overloaded facilities are owned by the same utility (and are assumed to be the responsibility of that utility to mitigate); will not be reported in the System Assessment. Identify Order 1000 Needs Order 1000 Potential Needs that are submitted to ColumbiaGrid, will be evaluated with the option to be included in the System Assessment. In this planning cycle, the process kicks-off in January 2018 with notification to solicit suggestions regarding Order 1000 Needs. Suggestions are due prior to the Order 1000 Needs Meeting and will be discussed during that time. Following the Order 1000 Needs Meeting, the process continues with the evaluation of the submissions to identify Order 1000 Needs that are vetted during the System Assessment process. ColumbiaGrid will implement applicable screening studies of the Order 1000 ColumbiaGrid Planning Region using the Order 1000 Planning criteria and Order 1000 Needs Factors. The results of the validation are reported in the System Assessment and Needs Statement documents that are developed as part of the System Assessment. The remaining violations and any unsolved outages are further explored for validity. All confirmed and valid violations are reported in the System Assessment. 8

12 Transient Stability Studies or possible future issues caused by policy changes. In conjunction with building the study cases; the WECC transient stability data will be updated allowing the ability to run studies on the developed cases. The data for the cases will be reviewed and test simulations (such as no fault run, Chief Joseph Braking test, and Double Palo Verde tests) are performed to verify satisfactory dynamic performance. Modeling data errors and potential problems are identified and fixed. The proposed changes to the base case will be discussed in the planning meeting as basic assumptions for performing the transient stability study. With the base case ready, contingencies submitted by members will be simulated and results will be discussed with members, if unexpected issues are identified. As discussed in the transient stability workshops; unstable contingencies, WECC transient limit violations, and generation tripping are reported in the System Assessment. Other Studies Other studies may be included in the System Assessment report from sensitivities requested by ColumbiaGrid members or from work done outside the process. The scope of these studies is determined by the members and typically addresses identified issues in the system, studies associated with new planning standards, 9

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

DRAFT STUDY PLAN FOR 2018

DRAFT STUDY PLAN FOR 2018 DRAFT STUDY PLAN FOR 2018 Introduction The Ten-year transmission planning process is intended to facilitate a timely, coordinated and transparent process that fosters the development of electric infrastructure

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon Transfer Capability Methodology for the Near-Term Transmission Planning FAC-013-2 Version 2.2 June 30, 2018 Table of Contents 1 PURPOSE... 3 2 DEFINITION... 3 3 APPLICABILITY... 3 4 TRANSFER CAPABILITY

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013 NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018

WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018 WECC Guideline 2019 Base Case Compilation Schedule Date: January 16, 2018 Introduction The Data Subcommittee compiles eleven steady state and dynamic base cases (base cases) to meet WECC s requirements

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

2019 Biennial Transmission Expansion Plan (BTEP)

2019 Biennial Transmission Expansion Plan (BTEP) 2019 Biennial Transmission Expansion Plan (BTEP) 8338 NE Alderwood Rd., Suite 140 Portland, OR 97220 1 This page intentionally left blank 2 Acknowledgements ColumbiaGrid Members & Participants Avista Corporation

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent

More information

Northwest Power Pool Processes

Northwest Power Pool Processes Northwest Power Pool Processes Background The Northwest Power Pool membership (NWPP) was founded in 1941 to promote efficient production of electrical energy. The NWPP is the geographic area encompassed

More information

WECC Guideline 2018 Base Case Compilation Schedule Date: DRAFT

WECC Guideline 2018 Base Case Compilation Schedule Date: DRAFT WECC Guideline 2018 Base Case Compilation Schedule Date: DRAFT Introduction The Data Subcommittee compiles eleven steady state and dynamic base cases (base cases) to meet WECC s requirements to compile

More information

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology Executive Summary Deliverability is an essential element of any resource adequacy requirement. Specifically, Load

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

PSE Attachment K Puget Sound Area Transmission Meeting

PSE Attachment K Puget Sound Area Transmission Meeting PSE Attachment K Puget Sound Area Transmission Meeting Stephanie Lu, Engineer Transmission Contracts December 9, 2010 Content Attachment K Review Primary Contacts Economic Studies Process PSE Planning

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

Performance Standards Issues. Donald Lamontagne Principal Engineer Arizona Public Service

Performance Standards Issues. Donald Lamontagne Principal Engineer Arizona Public Service Performance Standards Issues Donald Lamontagne Principal Engineer Arizona Public Service Free Template from www.brainybetty.com 2 Regulatory Entities FERC Energy Policy Act of 2005 NERC Designated Electric

More information

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated Standard FAC-008-1 Facility Ratings Methodology Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

Post SAR July day Formal Comment Period with Parallel Ballot July 2013

Post SAR July day Formal Comment Period with Parallel Ballot July 2013 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0 No. RC0610 SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 1.0 By California Independent System Operator (CAISO RC) No. RC0610 Table of Contents A. Conventions... 5 B. Introduction

More information

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities These definitions will be posted and balloted along with the standard, but will not be restated in the standard. Instead, they will be included in a separate Definitions section containing definitions

More information

SSR STUDY REPORT FINAL

SSR STUDY REPORT FINAL System Support Resource Study Escanaba 1 & 2: 25 MW Coal 36 Month Suspension 6/15/2012 6/15/2015 SSR STUDY REPORT FINAL June 21, 2012 Redacted version for January 3, 2013 filing EXECUTIVE SUMMARY An Attachment

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 8.1 By Peak Reliability February 24, 2017 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015 EIPC Interconnection-wide Webinar and Stakeholder Discussion November 17, 2015 Webinar Outline Presentation on 2025 Summer Peak (2025S) and 2025 Winter Peak (2025W) Roll-up Case Development Report to be

More information

OUTAGE COORDINATION PROCESS

OUTAGE COORDINATION PROCESS OUTAGE COORDINATION PROCESS March 13, 2017 www.peakrc.com. Classification: Public Page 0 of 68 Effective Date: Apr 01, 2017 Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

WECC Guideline 2016 Base Case Compilation Schedule Date: TSS Approved Meeting 170

WECC Guideline 2016 Base Case Compilation Schedule Date: TSS Approved Meeting 170 WECC Guideline 2016 Base Case Compilation Schedule Date: TSS Approved Meeting 170 Introduction The System Review Work Group (SRWG) compiles eleven steady state and dynamic base cases (base cases) to meet

More information

SPP RTO Compliance Forum TPL Jason Terhune

SPP RTO Compliance Forum TPL Jason Terhune SPP RTO Compliance Forum TPL-001-4 Jason Terhune 501-688-8261 jterhune@spp.org 1 TPL Standards have been Consolidated TPL-001-0.1 TPL-002-0b TPL-003-0b TPL-004-0a TPL-001-4 R1 R2 R3 R4 R5 R6 R7 R8 2 Overview

More information

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0 Western Interconnection Seasonal Operations Planning Rev. 3.0 Issued March 26, 2019 Effective May 1, 2019 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON 98662-6772

More information

MOD Steady-State and Dynamic System Model Validation

MOD Steady-State and Dynamic System Model Validation MOD-033-1 Steady-State and Dynamic System Model Validation A. Introduction 1. Title: Steady-State and Dynamic System Model Validation 2. Number: MOD-033-1 3. Purpose: To establish consistent validation

More information

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th 2016 DRAFT Proposal only Formal stakeholder review will begin August 24 th and remain open through September 12

More information

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering

I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e. June 15, 2016 Engineering 2017 ITPNT 2 0 1 7 I n t e g r a t e d T r a n s m i s s i o n P l a n n i n g N e a r - T e r m S c o p e June 15, 2016 Engineering Revision History Date or Version Number Author Change Description Comments

More information

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL Case s 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality s FINAL Introduction Powerflow and dynamics cases are the foundation of virtually all power system studies. Calculations

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

Open Access Transmission Tariff ATTACHMENT K

Open Access Transmission Tariff ATTACHMENT K ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study

Point to Point US to BC, BC to Alberta. and wheel through US to Alberta. System Impact Study Point to Point US to BC, BC to Alberta and wheel through US to Alberta System Impact Study Report No. SPA 2007-85 November 2007 Transmission System Planning British Columbia Transmission Corporation British

More information

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014 Background In April 2012, the Federal Energy Regulatory Commission (FERC) and the

More information

Reliability Coordinator Seasonal Operations Planning Coordination Process Rev. 2.0

Reliability Coordinator Seasonal Operations Planning Coordination Process Rev. 2.0 Reliability Coordinator Seasonal Operations Planning Rev. 2.0 By Peak Reliability Month XX, 2018 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON 98662-6772

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

OUTAGE COORDINATION PROCESS

OUTAGE COORDINATION PROCESS OUTAGE COORDINATION PROCESS October 3, 2016 www.peakrc.com. Classification: Public Page 0 of 67 Effective Date: Apr 01, 2017 Contents 1. Conventions... 2 2. Introduction... 2 3. Purpose... 2 4. Applicability...

More information

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE

SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE SYSTEM OPERATING LIMITS IN THE PLANNING HORIZON FAC-010 COMPLIANCE System Operating Limits (SOLs) in the planning horizon are required to be identified by FAC-010. This guideline describes how Duke Energy

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

Project System Operating Limits

Project System Operating Limits Project 2015-09 System Operating Limits Technical Conference Background Materials These background materials were prepared by members of the Standard Drafting Team solely for use in conjunction with the

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80487374, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #80439788, under the SaskPower Open Access Transmission Tariff (OATT). The purpose of

More information

System Impact Study for. 1 January January 2016

System Impact Study for. 1 January January 2016 System Impact Study for OASIS 72401305 Long-term Point to Point Transmission Service Request On the LM BPAT Path 1 January 2011 1 January 2016 Report No: SPPA2009-113 May 2009 System Planning & Performance

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

March 3, Submitted to: CAISO

March 3, Submitted to: CAISO March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING

More information

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview Owner Initiated projects from past RTEP cycles that are yet to be placed in-service.) This website will provide tracking information about the status of listed projects and

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

2018 GridLiance High Plains Planning Study Scope. Transmission Planning

2018 GridLiance High Plains Planning Study Scope. Transmission Planning 2018 GridLiance High Plains Planning Study Scope Transmission Planning July 16, 2018 Overview GridLiance and its subsidiary GridLiance High Plains LLC (GridLiance High Plains) will perform an annual system

More information

Standard TPL-004-0a System Performance Following Extreme BES Events

Standard TPL-004-0a System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-0a 3. Purpose: System simulations

More information

SOL Methodology Revision Kick-off

SOL Methodology Revision Kick-off SOL Methodology Revision Kick-off Welcome - the webinar will begin shortly All participants will be muted during the webinar Peak will unmute phones at the end to take questions Peak will be recording

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments

More information

S P P T P L S t e a d y S t a t e A s s e s s m e n t

S P P T P L S t e a d y S t a t e A s s e s s m e n t S P P 2 0 1 4 T P L S t e a d y S t a t e A s s e s s m e n t December 2014 SPP Engineering Revision History Revision History Date Author Change Description 11/11/2014 SPP staff Initial Draft 12/3/2014

More information

REDACTED. Supplemental Eastside Needs Assessment Report. Transmission System King County. April Puget Sound Energy

REDACTED. Supplemental Eastside Needs Assessment Report. Transmission System King County. April Puget Sound Energy Supplemental Eastside Needs Assessment Report Transmission System King County April 2015 Puget Sound Energy Report prepared by: Thomas J Gentile, PE Quanta Technology Donald J Morrow, PE Quanta Technology

More information

Operating Procedure PURPOSE... 2

Operating Procedure PURPOSE... 2 No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS RAMU

More information

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation Observations and Information Sharing Date: June, 2015 Prepared by: AESO Table of Contents Executive Summary...

More information

Standard FAC System Operating Limits Methodology for the Planning Horizon

Standard FAC System Operating Limits Methodology for the Planning Horizon Standard FAC-010-1 System Operating Limits Methodology for the Planning Horizon Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will

More information

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard TPL-002-0b System Performance Following Loss of a Single BES Element A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed

More information

Standard TPL (i) System Performance Under Normal Conditions

Standard TPL (i) System Performance Under Normal Conditions Standard TPL-001-0.1(i) System Performance Under rmal Conditions A. Introduction 1. Title: System Performance Under rmal ( Contingency) Conditions (Category A) 2. Number: TPL-001-0.1(i) 3. Purpose: System

More information

Methodology PLG-METH-0002-V1

Methodology PLG-METH-0002-V1 Methodology Department: Document No: System Planning and Strategic Projects PLG-METH-0002-V1 Title: Transmission Planning Assessment Practices Issue Date: September 27, 2012 Previous Date: Nov. 18, 2011

More information

Victorian reactive power support May 2018

Victorian reactive power support May 2018 Victorian reactive power support May 2018 Regulatory Investment Test For Transmission Project Specification Consultation Report Important notice PURPOSE AEMO has prepared this document to provide information

More information

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

Criteria. C~/v~ ~ ~ ~ G!  A1A ~ Tg'~10N COr'P''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria A1A "~"" T"""g"'~10N COr'P""''~ Criteria Department: Document No: System Planning and Strategic Projects P LG -C R-0001-V 19.2 T~c~e: Transmission System Planning Criteria issue gate: Previous Date: February

More information

Wide-Area Trans-Regional Northeast Reliability Assessment

Wide-Area Trans-Regional Northeast Reliability Assessment Wide-Area Trans-Regional Northeast Reliability Assessment Philip A. Fedora Kollin Patten Northeast Power Coordinating Council PowerWorld Corporation 1515 Broadway 43 rd Floor 1816 South Oak Street New

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: March 20, 2019 Re: Decision on ISO 2018-19 transmission plan This memorandum requires

More information

Agenda Unified Planning Assumptions & Study Plan

Agenda Unified Planning Assumptions & Study Plan Agenda Unified Planning Assumptions & Study Plan Jody Cross Stakeholder Engagement and Policy Specialist 2018-2019 Transmission Planning Process Stakeholder Meeting February 28, 2018 2018-2019 Transmission

More information

What makes a Wind Plant Grid Friendly?

What makes a Wind Plant Grid Friendly? Stable Renewable Plant Voltage and Reactive Power Control NERC ERSTF June 11-12, 2014 Sebastian Achilles Nicholas Miller Einar Larsen Jason MacDowell GE Energy Consulting 1 / Topics Features of modern

More information

WECC Board of Directors. Standards. Approved Regional Criteria (if any) NA. Final. Final

WECC Board of Directors. Standards. Approved Regional Criteria (if any) NA. Final. Final Document name Category Document date Adopted/approved by Date adopted/approved Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number Analysis, Reporting, and Mitigation

More information

Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1

Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1 Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1 Proposed Draft Standard The drafting team proposes to revise existing standard EOP-005 to incorporate IV.A.M2 and IV.A.M3. IV.A.M2 is translated into requirements

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically

More information

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403 AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination

More information

MOD Data for Power System Modeling and Analysis

MOD Data for Power System Modeling and Analysis MOD-032-1 Data for Power System Modeling and Analysis A. Introduction 1. Title: Data for Power System Modeling and Analysis 2. Number: MOD-032-1 3. Purpose: To establish consistent modeling data requirements

More information

Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards

Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Special Protection Systems (SPS) / Remedial Action Schemes (RAS): Assessment of Definition, Regional Practices, and Application of Related Standards Draft for Planning Committee Review 3353 Peachtree Road

More information

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - CAISO 2008-2013 Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - Purpose The purpose of this document is to provide an initial high-level scoping and program plan for the CAISO

More information

TPL 001 AB 0 System Performance Under Normal Conditions

TPL 001 AB 0 System Performance Under Normal Conditions Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure

More information

2013 Economic Study Report

2013 Economic Study Report 2013 Economic Study Report PPL EnergyPlus, LLC December 19, 2013 Electric Transmission Planning Table of Contents Executive Summary... 3 Study Constraints and Conditions... 4 Study Parameters... 5 Steady-State

More information

I Department: System Planning and Strategic Projects. Methodology

I Department: System Planning and Strategic Projects. Methodology ~, I Department: System Planning and Strategic Projects AMENICAN TIIANSMISSION CONPANY~~ Methodology Document No: P LG -M ETH'OOO?'V7 T~cie: Transmission Planning Assessment Practices issue gate: January

More information

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas

2012 NCTPC PJM Joint Interregional Reliability Study. PJM Interconnection. Duke Energy Carolinas. Progress Energy Carolinas 2012 NCTPC PJM Joint Interregional Reliability Study PJM Interconnection Duke Energy Carolinas Progress Energy Carolinas January 2013 1 Executive Summary The joint study consisted of a reliability analysis

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

Loads and Resources Methods and Assumptions

Loads and Resources Methods and Assumptions Loads and Resources Methods and Assumptions WECC Staff September 2014 155 North 400 West, Suite 200 Salt Lake City, Utah 84103-1114 Loads and Resources Methods and Assumptions ii Contents Purpose... 1

More information

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Transmission System Planning Methodology, Criteria and Process Business Practice December 07, 2007 Table of Contents

More information