COMPLIANCE MONITORING REPORT OF BLUE CRANE ROUTE MUNICIPALITY

Size: px
Start display at page:

Download "COMPLIANCE MONITORING REPORT OF BLUE CRANE ROUTE MUNICIPALITY"

Transcription

1 COMPLIANCE MONITORING REPORT OF BLUE CRANE ROUTE MUNICIPALITY Monitoring Date: 05 July 2016

2 All enquiries and correspondence to be directed to the Head of Department unless indicated otherwise by means of a formal letter signed by the head of department: Electricity Licensing, Compliance and Dispute Resolution. Tel: National Energy Regulator of South Africa Kulawula House 526 Madiba Street Arcadia Pretoria PO Box Arcadia 0007 Tel: +27 (0) Fax: +27 (0) DISCLAIMER This is a final report considered a true reflection of the implementation of the CAP based on information and evidence obtained from both the licensee and site verification of plant condition conducted during the monitoring process. Page 2 of 19

3 TABLE OF CONTENTS EXECUTIVE SUMMARY INTRODUCTION OVERVIEW MONITORING AND ENFORCEMENT OBJECTIVES METHODOLOGY NERSA AND BLUE CRANE ROUTE MUNICIPALITY DELEGATES GENERAL INFORMATION ON BLUE CRANE ROUTE MUNICIPALITY AUDIT FINDINGS BLUE CRANE ROUTE MUNICIPALITY S PERFORMANCE ON NERSA COMMUNICATION PROGRESS ON THE IMPLEMENTATION OF THE CORRECTIVE ACTION PLAN PLANT CONDITION DURING AUDIT VS. MONITORING TIME CONCLUSIONS RECOMMENDATIONS NEXT STEP Page 3 of 19

4 EXECUTIVE SUMMARY The National Energy Regulator (NERSA) conducted a compliance audit on Blue Crane Route Municipality ( the Licensee ) from 19 to 20 August 2014 to determine its level of compliance with the licence conditions. The objective was to determine the compliance of Blue Crane Route Municipality with the legal, financial and technical conditions of the electricity distribution licence. During the audit, Blue Crane Route Municipality representatives gave an overview, which addressed, among others, the staff complement, asset management, infrastructure development, the maintenance strategy and infrastructure projects done to date. After the audit, findings were recorded in a draft report and forwarded to the Licensee for management comments with regard to the correctness of the findings in order to make the report final. On 17 October 2014, Blue Crane Route Municipality sent the management comments to NERSA. These were received well within the prescribed time frame. The report was then considered final by NERSA and Blue Crane Route Municipality was then requested to send NERSA a signed, time-bound corrective action plan (CAP) to address the highlighted instances of non-compliance. On 19 July 2016, Blue Crane Route Municipality sent a CAP for NERSA s perusal and this was found to be acceptable as it addressed the issues highlighted by the audit. The National Energy Regulator instituted a monitoring regime to ensure and enforce the implementation of the CAP. On 05 July 2016, the National Energy Regulator conducted a monitoring exercise on the implementation of the CAP at Blue Crane Route Municipality. The monitoring exercise was conducted in order to determine the progress made in the implementation of the CAP. The National Energy Regulator is of the view that addressing issues raised during an audit will help Blue Crane Route Municipality to be a more efficient and effective licensee. This report depicts all the findings as per the audit and presents the status quo in terms of the progress that has been made at the time of the monitoring to address the instances of non-compliance highlighted during the audit. During the monitoring exercise, NERSA conducted site inspections to verify progress made in the implementation of the CAP. The level of improvement is depicted in detail in Section 7 of the report. Page 4 of 19

5 1. INTRODUCTION 1.1 Overview The National Energy Regulator (NERSA) is required to monitor and assess whether the electricity suppliers comply with the conditions of their licences. The Energy Regulator approved a compliance monitoring framework for electricity distributors in 2011, which acts as a guide on how compliance audits and monitoring must be conducted. The framework is also supported by the Electricity Regulation Act, 2006 (Act No. 4 of 2006), Chapter 4 (a) (vii), which states that the Regulator must enforce performance and compliance; and take appropriate steps in the case of non-performance. The National Energy Regulator conducts the compliance audits on licensed electricity distributors annually. The National Energy Regulator regulates the energy industry in accordance with Government laws and policies, standards and international best practices in support of sustainable development. The organisation issues licences to electricity distributors and therefore requires audits to be conducted against key licence obligations. It is the National Energy Regulator s mandate to monitor and enforce compliance with the licence conditions as per the Act. This monitoring process enforces and ensures improvement and sustainability of the licensees for the betterment of the Electricity Supply Industry (ESI), which will lead to improved quality of supply and service to customers. 1.2 Monitoring and Enforcement Objectives The key objectives of the compliance monitoring and enforcement of the corrective action plans are to: a) enforce implementation of the corrective action plans; b) help the licensee not to lose sight of critical matters that need to be corrected; c) help the licensee to start doing self-monitoring in terms of their performance against licence conditions; d) help the licensee to ensure that the quality of service and supply does not decline; and e) inform the Energy Regulator of the progress made by the licensee in the implementation of the corrective action plans. Page 5 of 19

6 2. METHODOLOGY A corrective action plan template was developed and sent to Blue Crane Route Municipality ( the Licensee ) to populate all the instances of non-compliance highlighted during the audit, together with the intended corrective action plan (CAP) with target dates of implementation. This is to be used by the National Energy Regulator to monitor the progress made and to establish whether the timelines on the CAP were realistic and addressing the issues highlighted during the audit. The CAP was sent to the National Energy Regulator after being signed by the relevant officials of the Licensee. The National Energy Regulator agreed on the CAP and instigated a monitoring process that robustly monitors progress. Progress is checked against target dates and remedial actions are implemented on an ongoing basis. Proof and supporting documents are requested and presented to the National Energy Regulator s officials during the monitoring process. Site verification was also done to compare the current plant condition against the plant condition during the audit. 3. NERSA AND BLUE CRANE ROUTE MUNICIPALITY DELEGATES NERSA was represented by the following officials: Mr Bongani Nhlabathi Compliance Monitoring Engineer Ms Basentjeng Malatji Compliance Monitoring Technician Ms Vuyelwa Poswa Dispute Resolution Officer Mr Morris Mafuyeka Compliance Monitoring Technician Blue Crane Route Municipality was represented by the following: Mr Vuyani Appolis Technical Service Manager Mr Gerard Goliath Chief Officer Page 6 of 19

7 4. GENERAL INFORMATION ON BLUE CRANE ROUTE MUNICIPALITY Blue Crane Route Municipality is the electricity distribution licence holder for the supply area with licence number NER/D/EC102 and supplies electricity to Somerset East, Cookhouse and Pearston. It has one bulk supply point with an installed capacity of 18 MVA and a maximum demand of 17.2 MVA. The network consists of 28km of medium voltage (MV) underground cable, 928km of low voltage (LV) underground cable, 2600km of MV overhead lines and 128km of LV overhead lines. It has 36,002 customers, which are categorised as follows: 6,696 prepaid domestic; 768 domestic credit meters; 354 commercial; 572 agricultural and 21 industrial customers. The total geographical area of Blue Crane Route Municipality is approximately 11,068.65km². At the time of the monitoring, it was highlighted that some instances of non-compliance that were noted during the initial audit have been addressed. These include the appointment of a Head Electromechanical, two linesmen, one electrician and six general workers. However, all the findings pertaining to the electricity network have not been addressed. 5. AUDIT FINDINGS At the time of the audit, the following was highlighted to the Licensee as areas that need attention and improvement: a) The critical vacancies must be filled. b) There was a shortage of working/field vehicles that must be included in the budget. c) The contract issued to trainees should include a retention strategy as the Licensee is faced with serious staff shortages in two critical departments. d) The electricity affairs of Blue Crane Route Municipality must be ringfenced from other activities of the Municipality. e) Blue Crane Route Municipality should budget sufficient funds (6%) for maintenance of the electricity network as required by the NERSA tariff guideline. f) The stores strategic spare equipment need to be replenish accordingly. g) The Licensee should replace all rotten wooden distribution poles as they pose a threat to the continuous supply of power to their customers. Page 7 of 19

8 h) The Electricity Department should procure a GIS system to enable them to track the condition of all electrical assets. i) The Licensee should apply to NERSA to amend their Electricity Distribution Licence as TLCs were phased out in j) Post mortems of the network incidents need to be conducted formally and must be recorded accordingly. 6. BLUE CRANE ROUTE MUNICIPALITY S PERFORMANCE ON NERSA COMMUNICATION In August 2014, the National Energy Regulator conducted a compliance audit on Blue Crane Route Municipality to determine its level of compliance with its licence conditions. This audit was followed by a number of s from the National Energy Regulator to Blue Crane Route Municipality. This communication was sent directly to Blue Crane Route Municipality s Electricity Manager. In all this communication, Blue Crane Route Municipality s Electricity Manager cooperated and responded in a satisfactory manner as indicated below. Table 1: BCRM s response record NERSA REQUEST DATE OF REQUEST LICENSEE RESPONSE DATE OF RESPONSE Request of Management 18/09/2014 Management 17/10/2014 comments on draft report comments sent Request for Corrective Action 26/11/2014 CAP sent 08/12/2014 Plan Monitoring notification 27/06/2016 Positive response 28/06/2016 Monitoring exercise 05/07/2016 Positive response 19/07/ PROGRESS ON THE IMPLEMENTATION OF THE CORRECTIVE ACTION PLAN At the time of the monitoring, it was noted that some instances of non-compliance that were highlighted during the audit have been addressed. These include the appointment of Head Electromechanical, two linesmen, one electrician, and six general workers, as well as the purchasing of field vehicles. However all findings pertaining to the electricity network have not been addressed. The table below depicts the progress made at the time of the monitoring of the implementation of the CAP that was submitted to NERSA. Page 8 of 19

9 Table 2: CAP Implementation Progress Non-compliance Corrective action Target date Target date for completion Critical Vacancies: The Critical vacancies must be filled. Progress Condition during monitoring day The Head Electromechanical Head Electromechanical Services was appointed on 01/09/2014. N/A 2014 Completed Appointed Assistant Head Rural Distribution Linesman BCRM is looking for a suitable candidate who resides in the area and knows the area very well. 3x Linesmen have been appointed and one has resigned. BCRM is looking for an internal candidate to fill the post. 2015/16 year 2014/15 (November) year 2017/18 Moved to 2017/18 year Organogram still to be reviewed and approved by Council 1x Linesman resigned in October 2015 and the post still vacant. Not filled Still vacant Page 0 of 19

10 Electrician Linesman Assistant General Worker Electrician who was employed resigned in September BCRM will advertise the post and look for a candidate residing in the area. The 2x Linesmen Assistant posts depend on the approval of the organogram in 2016/17 year. 6x General Workers were appointed February /16 year November 2014 Moved to 2017/18 year 2017/18 year 1x Electrician resigned in September 2015 and the post still vacant. Job tittle and description to be aligned with other municipalities of the same category. Still vacant Still vacant Completed Completed Compliant Shortage of working vehicles: There were a shortage of working/field vehicles Trainees: Contract issued to trainees should include a retention strategy. Two vehicles (LDV) have been purchased and delivered to BCRM. 6 x Vehicles (LDV) will be procured soon. BCRM is in the process of writing specifications for the vehicles. Policy on the retention of trainees will be developed by Corporate Services. 2015/16 year November /18 year 2017/18 Only five LDVs were purchased due to budget constraints. It was still to be raised in the training Committee to stipulate the condition and the policy. Noncompliant Noncompliant Page 1 of 19

11 Ring-Fencing: Electricity affairs of BCRM must be ring fenced from other activities of the Municipality Partially ring-fenced June /19 The Licensee does not prepare separate financial accounts but have different ledgers. Noncompliant Insufficient Budget: BCRM should budget sufficient funds (6%) for maintenance of the electricity network as required by NERSA tariff guidelines. Stores: Stores strategic spare equipment need to be replenished. Rotten wooded poles: Licensee should replace rotten wooded poles. BCRM maintenance budget is at 1.3% and will increase by 1% yearly. Supply Chain Management is in the process of replenishing spare equipment for the Electrical Services Department. The Licensee applied to DoE for funding to refurbish the BCRM substation and the accompanying backbone infrastructure for the BCRM area of supply. 2016/17 July 2015/16 August 2016/ / /19 November 2018/19 year BCRM maintenance budget is at 1.3% and will increase by 1% yearly starting from 2015/16 financial year. The BCRM is focusing on reducing distribution losses which will greatly improve the Licensee s revenue collection. The process is not yet completed. The Suurberg line needs to be replaced. DoE is funding approximately R30 Million for a substation and the accompanying backbone infrastructure. This will be done in phases until the 2018/19 financial year. Noncompliant Noncompliant Noncompliant Page 2 of 19

12 Geographic Information System (GIS): Electricity Department should procure a GIS system. The GIS system is still under discussion by the relevant departments and will be put in place. 2015/16 July 2017/18 The licensee reported that in 2017/18 there will be a fullyfunctional GIS system in the department. Noncompliant Amendment of Electricity Distribution Licence: The Licensee should apply to NERSA to amend their Electricity Distribution Licence. Network incident: Post Mortems of the network incidents need to be conducted formally and recorded accordingly. Application forwarded to NERSA and is being attended to. Conducting post mortems is done monthly as part of Safety Meetings. 23 July 2015 Ongoing 2015/16 Ongoing as part of Safety Awareness. Completed It is done and recorded in monthly meetings Compliant Compliant Page 3 of 19

13 The management of Blue Crane Route Municipality has filled some of the vacant positions in the organisational structure that were noted during the audit. At the time of the monitoring, nine positions had been filled. However, four positions were still vacant and the Licensee did not meet the initial target dates of 2016/17 as indicated in the CAP. The Licensee has moved the target dates to 2017/18. Five vehicles as opposed to six as indicated in the CAP had been procured at the time of monitoring. According to the Licensee, these were adequate for the Department to deliver on its mandate. However, once the vacant electrician position has been filled, the Department will be in need of another vehicle. The target date for this non-compliance was October 2015, and it has been partially addressed since the Licensee have already purchased five out of six LDVs. The Licensee did not address the non-compliance regarding contracts issued to trainees at the time of monitoring. However the Licensee mentioned that the Corporate Services Department will develop a retention policy, which will be finalised in the 2016/17 financial year. The electricity affairs of the Licensee are not yet ring-fenced. The Licensee s maintenance budget is at 1.3% and will increase by 1% yearly starting from the 2015/16 financial year. The BCRM Licensee is focusing on reducing distribution losses, which will greatly improve the Licensee s revenue collection. During the monitoring it was mentioned that the Supply Chain Management Department is in the process of replenishing spare equipment for the Electrical Department. It was reported that this will be finalised in 2018/19. The Suurberg line needs to be replaced. The Department of Energy (DoE) is funding approximately R30 million for a substation and the accompanying backbone infrastructure. This will be done in phases until the 2018/19 financial year. The Licensee applied to NERSA to amend its Electricity Distribution Licence to reflect the exact areas that the Licensee is supplying with electricity. The polygons were supplied to NERSA using Google Maps and Google Earth as opposed to GIS data sets as the Licensee did not have a fully functional GIS in place at the time. During the monitoring exercise, the Licensee indicated that the GIS is still under discussion with the relevant departments and will be budgeted for in the 2017/18 financial year. Page 4 of 19

14 Post mortems of network incidents are done on a monthly basis as part of the Safety Meetings. It was also mentioned that it is an ongoing programme as part of Safety Awareness. 8. PLANT CONDITION DURING AUDIT VS. MONITORING TIME The photos below depict the condition of the network equipment during the audit compared to the condition during the monitoring process. Poor vegetation management in HV yard and no yard stones. In 2016, vegetation was well managed, but no yard stones, no proper plinth and oil catchments. Oil leaks due to lack of maintenance and repairs on transformers with cable laid on the surface. In 2016 there are still signs of oil leaks on the transformer. Page 5 of 19

15 Melting terminations, possibility from overheating due to hot spot. In 2016, the conditions are still the same. Open cable trench with safety/first aid sign inside. Still no cable trench covers in Old repaired transformer in service. In 2016, the pole-mounted transformer has been replaced. Page 6 of 19

16 Old repaired transformer in service. In 2016, the condition of the transformer was still the same. Surge arrestors and drop out fuses missing. Surge arrestors and drop out fuses still missing in Drop out fuses and surge arrestors missing. In 2016, the transformer has been replaced but drop out fuses and surge arrestors are still not installed. Page 7 of 19

17 Evidence of old fuses that are no longer in stock. Evidence that old fuses that are no longer in stock were not replaced by Evidence of rust on the battery terminals indicating lack of proper maintenance. Old batteries have been replaced and well maintained in Panel cover missing. Panel cover still missing in Page 8 of 19

18 Evidence of poor maintenance. Maintenance still not done in Plinth submerged below ground level for the MSS. In 2016, still no change for the MSS. 9. CONCLUSIONS Blue Crane Route Municipality made some progress in addressing the noncompliances highlighted by the audit. This is confirmed by the filling of some vacancies, procuring of field vehicles and amendment of the electricity distribution licence. However, no significant progress was observed on the network conditions as some equipment had deteriorated. This was evident at the Licensee s substation, as transformers had signs of oil leaks, there were melted terminations and cable trench covers had still not been installed inside the switching stations. The non-compliance that had been highlighted relating to the Municipality s network being old and obsolete has not been addressed. This was confirmed by transformers that had blown up due to being in service for prolonged periods of time without proper repairs and maintenance. The industrial mini-substation is also Page 9 of 19

19 still operating with obsolete fuses that are dangerous to operate. The Suurberg line is worse than before the audit, as the poles are leaning more than the allowable limits. This is due to the fact that the line has exceeded its lifespan and should be replaced with immediate effect. 10. RECOMMENDATIONS It is recommended that Blue Crane Route Municipality should prioritise the addressing of the CAP to improve the level of compliance with licence conditions and impose a self-monitoring regime to ensure that it does not deteriorate back to non-compliance. 11. NEXT STEP There are still instances of non-compliance that need to be addressed by the Licensee. As a result, the Energy Regulator expects the Licensee to implement the corrective action plan until all the instances of non-compliance have been fully addressed in order to improve the Licensee s level of compliance. The National Energy Regulator will continue to monitor the Licensee s implementation of the corrective action plan on an ongoing basis to ensure that all the findings are addressed. Once the remaining projects in the CAP have been concluded, the Licensee must send a closeout report to the National Energy Regulator. It is expected that the Licensee will then implement a self-monitoring regime to ensure that the improved areas do not deteriorate back to a situation of non-compliance. Further monitoring exercises to be conducted by the Energy Regulator on the Licensee will be communicated to the Licensee in due course. All communication should be forwarded to the Head of Department unless indicated otherwise by means of a formal letter signed by the head of department: The Head of Department Licensing, Compliance and Dispute Resolution: Electricity National Energy Regulator of South Africa PO Box Arcadia 0007 Fax: +27 (0) Page 10 of 19

COMPLIANCE MONITORING REPORT OF UMHLATHUZE LOCAL MUNICIPALITY

COMPLIANCE MONITORING REPORT OF UMHLATHUZE LOCAL MUNICIPALITY COMPLIANCE MONITORING REPORT OF UMHLATHUZE LOCAL MUNICIPALITY Monitoring Date: 08 September 2014 All enquiries and correspondence to be directed to the Head of Department unless indicated otherwise by

More information

COMPLIANCE MONITORING REPORT OF PHUMELELA LOCAL MUNICIPALITY

COMPLIANCE MONITORING REPORT OF PHUMELELA LOCAL MUNICIPALITY COMPLIANCE MONITORING REPORT OF PHUMELELA LOCAL MUNICIPALITY Monitoring Date: 27 October 2015 All enquiries and correspondence to be directed to the Head of Department, unless indicated otherwise, by means

More information

COMPLIANCE MONITORING REPORT OF NKOMAZI LOCAL MUNICIPALITY

COMPLIANCE MONITORING REPORT OF NKOMAZI LOCAL MUNICIPALITY COMPLIANCE MONITORING REPORT OF NKOMAZI LOCAL MUNICIPALITY Monitoring Date: 12 August 2015 Page 1 of 18 All enquiries and correspondence to be directed to the Head of Department, unless indicated otherwise,

More information

COMPLIANCE MONITORING REPORT OF MOOKGOPHONG LOCAL MUNICIPALITY

COMPLIANCE MONITORING REPORT OF MOOKGOPHONG LOCAL MUNICIPALITY COMPLIANCE MONITORING REPORT OF MOOKGOPHONG LOCAL MUNICIPALITY Monitoring Date: 13 May 2014 All enquiries and correspondence to be directed to the Head of Department unless indicated otherwise by means

More information

COMPLIANCE MONITORING REPORT OF MAFUBE LOCAL MUNICIPALITY

COMPLIANCE MONITORING REPORT OF MAFUBE LOCAL MUNICIPALITY COMPLIANCE MONITORING REPORT OF MAFUBE LOCAL MUNICIPALITY Monitoring Date: 06 May 2014 All enquiries and correspondence to be directed to the Head of Department unless indicated otherwise by means of a

More information

CONSOLIDATED REPORT ON THE FINDINGS OF THE ELECTRICITY DISTRIBUTION INDUSTRY COMPLIANCE AUDITS CONDUCTED IN 2016/17

CONSOLIDATED REPORT ON THE FINDINGS OF THE ELECTRICITY DISTRIBUTION INDUSTRY COMPLIANCE AUDITS CONDUCTED IN 2016/17 CONSOLIDATED REPORT ON THE FINDINGS OF THE ELECTRICITY DISTRIBUTION INDUSTRY COMPLIANCE AUDITS CONDUCTED IN 2016/17 MARCH 2017 All inquiries and correspondence should be directed to the Head of Department:

More information

CONSOLIDATED REPORT ON THE FINDINGS OF THE ELECTRICITY DISTRIBUTION INDUSTRY COMPLIANCE AUDITS CONDUCTED IN 2013/14

CONSOLIDATED REPORT ON THE FINDINGS OF THE ELECTRICITY DISTRIBUTION INDUSTRY COMPLIANCE AUDITS CONDUCTED IN 2013/14 CONSOLIDATED REPORT ON THE FINDINGS OF THE ELECTRICITY DISTRIBUTION INDUSTRY COMPLIANCE AUDITS CONDUCTED IN 2013/14 FEBRUARY 2014 1 All inquiries and correspondence should be directed to the Head of Department:

More information

Alan Tait Managing Director Pragma Africa

Alan Tait Managing Director Pragma Africa Alan Tait Managing Director Pragma Africa Ekurhuleni Energy Department A Model for Electricity Distribution Infrastructure Asset Management Ekurhuleni Metropolitan Municipality Energy Department The Energy

More information

Consolidated Report on the Findings of the Electricity Generation Industry Compliance Audits Conducted in 2016/17 Financial Year

Consolidated Report on the Findings of the Electricity Generation Industry Compliance Audits Conducted in 2016/17 Financial Year Consolidated Report on the Findings of the Electricity Generation Industry Compliance Audits Conducted in 2016/17 Financial Year I All enquiries and correspondence to be directed to the Head of Department

More information

TRANSMISSION COMPLIANCE MONITORING FRAMEWORK FOR THE SOUTH AFRICAN ELECTRICITY INDUSTRY

TRANSMISSION COMPLIANCE MONITORING FRAMEWORK FOR THE SOUTH AFRICAN ELECTRICITY INDUSTRY TRANSMISSION COMPLIANCE MONITORING FRAMEWORK FOR THE SOUTH AFRICAN ELECTRICITY INDUSTRY TABLE OF CONTENTS 1. PURPOSE...2 2. OBJECTIVE...2 3. BACKGROUND...2 3.1 REGULATORY INTERFACE AND COMMUNICATION CHANNELS...2

More information

Consolidated Report on the Audit Findings of the Electricity Generation Industry Compliance Audits Conducted in 2013

Consolidated Report on the Audit Findings of the Electricity Generation Industry Compliance Audits Conducted in 2013 Consolidated Report on the Audit Findings of the Electricity Generation Industry Compliance Audits Conducted in 2013 Audit date: Year 2013 All enquiries and correspondence to be directed to the Head of

More information

NERSA. National Energy Regulator of South Africa

NERSA. National Energy Regulator of South Africa NERSA National Energy Regulator of South Africa 1 Making Regulation Work 2 AGENDA Regulatory Framework From Law to Grid Code From Experience Concluding Remarks 3 Understanding Regulation as an Activity

More information

GUIDELINES ON ELECTRICITY RESALE

GUIDELINES ON ELECTRICITY RESALE GUIDELINES ON ELECTRICITY RESALE Issued by The National Energy Regulator 526 Madiba Street Arcadia, Pretoria 0007 Contact Details: Tel: +27 (0)12 401 4600 Fax: +27 (0)12 401 4700 www.nersa.org.za Contents

More information

Performance Reporting Criteria

Performance Reporting Criteria Revision Date: February 2012 Revision No.: 2 Document No.: DOC-131102-ADV Status: Approved by CER Date: 01/03/2012 ESB Networks Ltd. Contents 1. Background... 3 2. Report Headings... 4 3. Criteria... 5

More information

TECHNICAL INDICATOR DESCRIPTIONS 2012/ /15

TECHNICAL INDICATOR DESCRIPTIONS 2012/ /15 TECHNICAL INDICATOR DESCRIPTIONS 2012/13 2014/15 INDEX Page 1. Executive Summary 1 2. Electricity Industry Regulation 3 3. Piped-Gas Industry Regulation 17 4. Petroleum Pipelines Industry Regulation 30

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

Distribution Tradesperson (Jobsplus Permit No. 706/2017)

Distribution Tradesperson (Jobsplus Permit No. 706/2017) CAREER OPPORTUNITIES Enemalta plc is the leading energy service provider in the Maltese Islands, entrusted with the generation and distribution of electricity and the development of the national electricity

More information

Distribution System Operating Code

Distribution System Operating Code Distribution System Operating Code Draft Rev 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System

More information

Section 3 Company Organisation and Certification Procedures

Section 3 Company Organisation and Certification Procedures OF&G ORGANIC STANDARDS AND CERTIFICATION MANUAL 3.0 Contents Page The describe how the company is structured and administered, and explains the certification procedures, the complaints procedures and the

More information

THE LESOTHO ELECTRICITY AUTHORITY. Presentation by the LEA Chief Executive on the occasion of the Launch 04 May 2006

THE LESOTHO ELECTRICITY AUTHORITY. Presentation by the LEA Chief Executive on the occasion of the Launch 04 May 2006 THE LESOTHO ELECTRICITY AUTHORITY Presentation by the LEA Chief Executive on the occasion of the Launch 04 May 2006 1 Structure of the Presentation Issues concerning the Power Sector of Lesotho Power Sector

More information

Supervision Guideline for Electrician to Lineworker Apprentices

Supervision Guideline for Electrician to Lineworker Apprentices Supervision Guideline for Electrician to Lineworker Apprentices This Guideline has been developed by the Victorian Electricity Supply Industry (VESI) Skills and Training Reference Committee to provide

More information

Distribution Code Definitions

Distribution Code Definitions Distribution Code Definitions Version 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System Operator

More information

Customer Capital Contributions Policy

Customer Capital Contributions Policy TasNetworks Customer Capital Contributions Policy Effective 1 July 2014 Tasmanian Networks Pty Ltd ABN 24 167 357 29 Page 1 of 25 Tasmanian Networks Pty Ltd ABN 24 167 357 299 1-7 Maria Street Lenah Valley

More information

STATUTORY AUTHORITY: ACT no. 50 of 29 June 1990, section 7-6

STATUTORY AUTHORITY: ACT no. 50 of 29 June 1990, section 7-6 NOTE: Unofficial translation - for information only REG. no. 959 of 7 December 1990: Regulations concerning the generation, conversion, transmission, trading, distribution and use of energy etc. (The Energy

More information

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control

More information

Site Quality Assurance Inspection Regime for Connections Extension Assets

Site Quality Assurance Inspection Regime for Connections Extension Assets Site Quality Assurance Inspection Regime for Connections Extension Assets Background Northern Powergrid undertakes sample quality assurance inspections of assets installed by Independent Connection Providers

More information

NERSA Consultation Paper

NERSA Consultation Paper NERSA Consultation Paper Renewable Energy Feed - In Tariff December 2008 Page 1 of 14 TABLE OF CONTENTS ABBREVIATIONS...3 1. INTRODUCTION AND BACKGROUND...4 2. SOUTH AFRICAN RENEWABLE ENERGY FEED IN TARIFF

More information

Supervision of Persons who are not Limited Certificate Holders

Supervision of Persons who are not Limited Certificate Holders Supervision of Persons who are not Limited Certificate Holders EWRB Reference Number Document Category: Board/Legislative/Operational Document Type: Rule/Policy/Procedure/Reference Responsible: Board/Registrar

More information

Pre-Qualification Submittal for Designated Transmission Entity Status Submitted to PJM September 5, 2013 Updated September 12, 2018

Pre-Qualification Submittal for Designated Transmission Entity Status Submitted to PJM September 5, 2013 Updated September 12, 2018 Pre-Qualification Submittal for Designated Transmission Entity Status Submitted to PJM September 5, 2013 Updated September 12, 2018 1. Name and address of the entity including a point of contact Duke Energy

More information

Audit Follow-Up. Water Infrastructure (Report #0919 issued September 30, 2009) As of March 31, Summary

Audit Follow-Up. Water Infrastructure (Report #0919 issued September 30, 2009) As of March 31, Summary Audit Follow-Up As of March 31, 2010 Sam M. McCall, Ph.D., CPA, CGFM, CIA, CGAP City Auditor Water Infrastructure (Report #0919 issued September 30, 2009) Report #1018 June 7, 2010 Summary Thirteen of

More information

OVERALL EXTERNAL SERVICES COSTS

OVERALL EXTERNAL SERVICES COSTS EB-00-00 Tab Schedule Filed: 00 Aug Page of OVERALL EXTERNAL SERVICES COSTS INTRODUCTION THESL uses external services to complement its internal capacity to execute work programs. External services represent

More information

ANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance

ANNEX THREE. Regime for Monitoring of Separation of Batelco and NBN Compliance ANNEX THREE Regime for Monitoring of Separation of Batelco and NBN Compliance Compliance Monitoring Regime Draft for Discussion Purpose: To establish a regime for monitoring Batelco s compliance with the

More information

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification

More information

Water NSW Reporting Manual

Water NSW Reporting Manual Water NSW Reporting Manual Operating Licence 2017-2022 Reporting Manual Water July 2017 Independent Pricing and Regulatory Tribunal of New South Wales 2017 This work is copyright. The Copyright Act 1968

More information

PETROLEUM PIPELINES REGULATION

PETROLEUM PIPELINES REGULATION PETROLEUM PIPELINES REGULATION Information to assist licence applicants to file licence applications in terms of the Petroleum Pipelines Act, 2003 (Act No. 60 of 2003) Version 1 November 2013 DISCLAIMER:

More information

The expected outcomes known as what must go right will be that: DWGs will be established and / or reviewed within the RMIT organisation structure

The expected outcomes known as what must go right will be that: DWGs will be established and / or reviewed within the RMIT organisation structure 1.0 Objective To set out the requirements for the establishment and maintenance of Health and Safety Committees (s), Designated Work Groups (DWGs) and Health and Safety Representatives (HSRs) at RMIT.

More information

Electricity Networks Corporation (t/a Western Power)

Electricity Networks Corporation (t/a Western Power) Networks Corporation (t/a Western Power) Transmission Licence (ETL 2) Performance Audit Report January 2013 Grant Thornton Australia Ltd. All rights reserved. Contents Acronym List 2 1. Introduction 5

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

on supervision of significant branches

on supervision of significant branches EBA/GL/2017/14 16/02/2018 Guidelines on supervision of significant branches 1. Compliance and reporting obligations Status of these guidelines 1. This document contains guidelines issued pursuant to Article

More information

MORETELE LOCAL MUNICIPALITY

MORETELE LOCAL MUNICIPALITY MORETELE LOCAL MUNICIPALITY OCCUPATIONAL HEALTH AND SAFETY POLICY Policy Adoption Date: Policy Number: Resolution Number: Expected review Date: Version control number: Authorized signature: Page 1 of 10

More information

CONSULTATION PAPER COST OF SUPPLY FRAMEWORK FOR LICENSED ELECTRICITY DISTRIBUTORSIN SOUTH AFRICA

CONSULTATION PAPER COST OF SUPPLY FRAMEWORK FOR LICENSED ELECTRICITY DISTRIBUTORSIN SOUTH AFRICA CONSULTATION PAPER COST OF SUPPLY FRAMEWORK FOR LICENSED ELECTRICITY DISTRIBUTORSIN SOUTH AFRICA Issued by: The National Energy Regulator 526 Madiba Street Arcadia,Pretoria 0007 Contact Details: Tel: +27(0)12

More information

Office for Nuclear Regulation

Office for Nuclear Regulation ONR GUIDE FLEXIBLE PERMISSIONING INCLUDING THE USE OF DERIVED POWERS Document Type: ONR Nuclear Safety Permissioning Guide Unique Document ID and Revision No: NS-PER-GD-001 Revision 0 Date Issued: April

More information

Inspection and Monitoring of Networks Constructed by Independent Connection Providers

Inspection and Monitoring of Networks Constructed by Independent Connection Providers 1. SCOPE This document details SP Energy Networks (SPEN) inspection and escalation regime for contestable works constructed (ICPs) that will be adopted by SPEN. 2. ISSUE RECORD This is a Controlled document.

More information

Contact Person Manager Technical Regulation - Water Lesotho Electricity Authority 7 th Floor, Moposo House Kingsway Maseru Lesotho Tel:

Contact Person Manager Technical Regulation - Water Lesotho Electricity Authority 7 th Floor, Moposo House Kingsway Maseru Lesotho Tel: URBAN WATER QUALITY OF SERVICE AND SUPPLY STANDARDS 01 MAY 2013 Contact Person Manager Technical Regulation - Water Lesotho Electricity Authority 7 th Floor, Moposo House Kingsway Maseru Lesotho Tel: 2231

More information

ASSET VALUATION A PRACTICAL APPROACH TO VALUING MUNICIPAL POWER SYSTEM ASSETS

ASSET VALUATION A PRACTICAL APPROACH TO VALUING MUNICIPAL POWER SYSTEM ASSETS ASSET VALUATION A PRACTICAL APPROACH TO VALUING MUNICIPAL POWER SYSTEM ASSETS M A FISH (B.Sc. Elec Eng, MSAIEE) Abstract. This paper describes a practical and cost-effective approach to valuing municipal

More information

PIPED-GAS REGULATION FEBRUARY 2017

PIPED-GAS REGULATION FEBRUARY 2017 PIPED-GAS REGULATION FEBRUARY 2017 Disclaimer This frequently asked questions document (FAQ) is developed in the context of the liquefied natural gas (LNG) to Power IPP Procurement Programme currently

More information

Supervision Guideline for Apprentice Lineworkers (Distribution)

Supervision Guideline for Apprentice Lineworkers (Distribution) Supervision Guideline for Apprentice Lineworkers (Distribution) This Guideline has been developed by the Victorian Electricity Supply Industry (VESI) Skills and Training Reference Committee to provide

More information

WORK IN THE VICINITY OF UNDERGROUND ASSETS

WORK IN THE VICINITY OF UNDERGROUND ASSETS CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF UNDERGROUND ASSETS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD

More information

Technical Guideline for. Section 8. Inspection and Approval of Construction

Technical Guideline for. Section 8. Inspection and Approval of Construction Technical Guideline for Section 8. Inspection and Approval of Construction Ontario Regulation 22/04 Electrical Distribution Safety January 12, 2005 Technical Guideline Section 8 General Legal Disclaimer

More information

The Auditor of an Authorized Political Party

The Auditor of an Authorized Political Party QUICK REFERENCE The Auditor of an Authorized Political Party Financing of Municipal Political Parties and Independent Candidates, and Control of Election Expenses Chapter XIII of the Act respecting elections

More information

Title of presentation

Title of presentation Title of presentation Dr Willie de Beer Chief Operations Officer EDI Holdings Are the REDs Dead? Presentation Outline Current Electricity Supply Industry Structure Current Situation Supply / Demand : In

More information

Small Enterprise Finance Agency

Small Enterprise Finance Agency Small Enterprise Finance Agency Title: Procedure ID No.: Relevant to: Purpose: sefa sefa-finance-2015-fpr0002 All Staff The purpose of the petty cash procedure is to support the implementation of the petty

More information

Service Quality and Reliability Performance Monitoring and Reporting for Owners of Electric Distribution Systems and for Gas Distributors

Service Quality and Reliability Performance Monitoring and Reporting for Owners of Electric Distribution Systems and for Gas Distributors C5-16-1 Rule 002 Service Quality and Reliability Performance Monitoring and Reporting for Owners of Electric Distribution Systems and for Gas Distributors This rule as amended was approved by the Alberta

More information

Document B Specification

Document B Specification Tender for The Provision of a Communal Cleaning & Window Cleaning Service Reference: PDT 18-035 Document B Specification Dated: February 2019 General Scope This specification defines the quality and standards

More information

Corporate Policy and Procedure

Corporate Policy and Procedure Page Page 1 of 13 TAB: SECTION: SUBJECT: CORPORATE ADMINISTRATION ACQUISITION/DISPOSAL OF GOODS AND SERVICES BID AWARDS AND BID PROTESTS POLICY STATEMENT PURPOSE SCOPE Bidders may receive Awards for the

More information

Bluewaters Power 1 Pty Ltd

Bluewaters Power 1 Pty Ltd Bluewaters Power 1 Pty Ltd Electricity Generation Licence (EGL 4) 2014 Performance Audit (Independent Assurance) Report June 2014 Deloitte Touche Tohmatsu ABN 74 490 121 060 Woodside Plaza Level 14 240

More information

LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS. Article 1. The Purpose of the Law

LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS. Article 1. The Purpose of the Law LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS Article 1. The Purpose of the Law 1.1. The purpose of this law is to regulate matters relating to energy generation, transmission, distribution,

More information

ROLE OF THE NATIONAL ENERGY REGULATOR (SOUTH AFRICA) Lambert du Plessis: Senior Regulatory Specialist

ROLE OF THE NATIONAL ENERGY REGULATOR (SOUTH AFRICA) Lambert du Plessis: Senior Regulatory Specialist ROLE OF THE NATIONAL ENERGY REGULATOR (SOUTH AFRICA) Lambert du Plessis: Senior Regulatory Specialist OUTLINE OF PRESENTATION Regulatory Principles South African Energy Regulation Legal framework NERSA

More information

MSP 50 CONTROL OF CONTRACTORS

MSP 50 CONTROL OF CONTRACTORS CONTROL OF CONTRACTORS AUTHORISED BY: PURCHASING MANAGER DATE: 14/03/2011 THIS DOCUMENT WILL FORM PART OF THE PRE-TENDER, TENDER AND CONTRACT PROCESSES FOR EACH CONTRACT AND AS SUCH SHALL BE REQUIRED TO

More information

Framework for Action for the management of small drinking water supplies

Framework for Action for the management of small drinking water supplies Framework for Action for the management of small drinking water supplies Environment Europe Direct is a service to help you find answers to your questions about the European Union Freephone number (*):

More information

Corporate. Emergency Standby Generator SOP. Document Control Summary

Corporate. Emergency Standby Generator SOP. Document Control Summary Corporate Emergency Standby Generator SOP Document Control Summary Status: Version: Author/Title: Owner/Title: Approved by: Ratified: Related Trust Strategy and/or Strategic Aims Implementation Date: Review

More information

CUSC Amendment Proposal Form CAP: 162

CUSC Amendment Proposal Form CAP: 162 CUSC Amendment Proposal Form CAP: 162 Title of Amendment Proposal: Transmission Access - Entry Overrun Description of the Proposed Amendment (mandatory by proposer): Creation of a commercial mechanism

More information

POWER QUALITY MANAGEMENT FRAMEWORK FOR THE ELECTRICITY SUPPLY INDUSTRY IN ZAMBIA

POWER QUALITY MANAGEMENT FRAMEWORK FOR THE ELECTRICITY SUPPLY INDUSTRY IN ZAMBIA POWER QUALITY MANAGEMENT FRAMEWORK FOR THE ELECTRICITY SUPPLY INDUSTRY IN ZAMBIA JUNE 2014 CONTENTS EXECUTIVE SUMMARY... ii 1. INTRODUCTION...1 1.1 Overview...1 1.2 Aims of Power Quality Management System...1

More information

EUROPEAN PARLIAMENT AND COUNCIL

EUROPEAN PARLIAMENT AND COUNCIL 27.4.2001 EN Official Journal of the European Communities L 118/41 II (Acts whose publication is not obligatory) EUROPEAN PARLIAMENT AND COUNCIL RECOMMENDATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

More information

Service Apparatus Connection Scheme. Information for Electrical Contractors

Service Apparatus Connection Scheme. Information for Electrical Contractors Service Apparatus Connection Scheme Information for Electrical Contractors Document release information Document number 34113854 Document title Revision status Service Apparatus Connection Scheme Version

More information

Construction Audit Process

Construction Audit Process Construction Audit Process Underground Developments Record Number: R0000389952 Version Number: 5.0 Date: September 2016 Authorisations Action Name and title Date Prepared by Project Management Works and

More information

Request for Electricity Connection Works at: xx Street Name, District, County, Postcode

Request for Electricity Connection Works at: xx Street Name, District, County, Postcode The Customer, xx, Street Name District County Postcode WPD Reference: 29xxxxx WPD Scheme No: 11xxxxx/1 Herald Way Pegasus Business Park CASTLE DONINGTON DE74 2TU WPD Telephone No 01332 xxxxxx 15/12/2017

More information

7. WATER SERVICES INSTITUTIONAL ARRANGEMENTS PROFILE

7. WATER SERVICES INSTITUTIONAL ARRANGEMENTS PROFILE 7. WATER SERVICES INSTITUTIONAL ARRANGEMENTS PROFILE 7.1 Water Services Authority assessment The WSA has a number of functions and outputs that are mainly associated with governance and regulation. The

More information

AUDIT REPORT. Audit of Offi cial Controls carried out by the Local Authority Veterinary Service Cavan County Council

AUDIT REPORT. Audit of Offi cial Controls carried out by the Local Authority Veterinary Service Cavan County Council AUDIT REPORT Audit of Offi cial Controls carried out by the Local Authority Veterinary Service AUDIT REPORT Audit of Official Controls carried out by the Local Authority Veterinary Service TABLE OF CONTENTS

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2014 Start Date (first day) 1 April 2014 Templates for Schedules 11a 13 (Asset Management Plan)

More information

Customer charter for electricity networks.

Customer charter for electricity networks. Customer charter for electricity networks. MAINTAINING OUR ELECTRICITY NETWORK IN SUMMER. Who does this Customer Charter cover? This ActewAGL Customer Charter covers customers who are connected to the

More information

SCHEDULE SS STANDBY SERVICE

SCHEDULE SS STANDBY SERVICE SCHEDULE SS STANDBY SERVICE SHEET NO. 69 A. APPLICABILITY: Applicable to customers with alternate regular source(s) of energy other than electricity from the Company when such sources are connected to

More information

Prequalification of Electrical Contractors

Prequalification of Electrical Contractors Prequalification of Electrical Contractors \\ 2018 Application Instructions & Forms Prequalified Electrical Contractors Application Checklist To apply for prequalification of utility type work for Tacoma

More information

Test Results & Conditional Pass Cover Letter sent to Manufacturer

Test Results & Conditional Pass Cover Letter sent to Manufacturer Conditional Pass Policy Version 2 January 2018 Introduction This document outlines the treatment of products that do not fully meet the Lighting Global Quality Standards due to easy-to-fix issues that

More information

CODE OF PRACTICE FOR RESPONSIBLE DISTRIBUTION

CODE OF PRACTICE FOR RESPONSIBLE DISTRIBUTION CODE OF PRACTICE FOR RESPONSIBLE DISTRIBUTION As a condition of membership, the member companies of the Responsible Distribution Canada are committed to Responsible Distribution 1. This Code of Practice

More information

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES

WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES CONTRACTOR WHS HAZARD STANDARD WORK IN THE VICINITY OF POWER POLES AND OVERHEAD LINES EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES

More information

Lesotho Electricity Authority. Rural Electricity Quality of Service and Supply Standards

Lesotho Electricity Authority. Rural Electricity Quality of Service and Supply Standards Lesotho Electricity Authority Rural Electricity Quality of Service and Supply Standards First Edition: 2008 Table of Contents 0 Abbreviations... 3 1 Definitions...3 Background and Scope...4 3 Quality of

More information

Price Application Policy ABN

Price Application Policy ABN Price Application Policy ABN 38 362 983 875 Table of Contents 1. Interpretation 4 1.1 Definitions 4 1.2 Access Code definitions apply 5 1.3 Interpretation 5 2. National Market Identifiers (NMIs) 6 2.1

More information

General Terms of Orders, Deliveries and Warranties (GTODW)

General Terms of Orders, Deliveries and Warranties (GTODW) General Terms of Orders, Deliveries and Warranties (GTODW) 1. General provisions and definitions 1.1 General Terms of Orders, Deliveries and Warranties (of 31st December 2015), hereinafter referred to

More information

Corporate Governance Statement

Corporate Governance Statement Corporate Governance Statement The Board of Directors of Frontier Digital Venture Limited (FDV or the Company) is responsible for the corporate governance of the Company and its subsidiaries. The Board

More information

FSA 2.1 Third Party Verification Audit Guide for Farm Management Groups FINAL for publication 1 June 2018 (1)

FSA 2.1 Third Party Verification Audit Guide for Farm Management Groups FINAL for publication 1 June 2018 (1) FARM SUSTAINABILITY ASSESSMENT (FSA) 2.1 THIRD PARTY VERIFICATION AUDIT GUIDE FOR FARM MANAGEMENT GROUP CLAIMS FOR USE WITH SAI FSA IMPLEMENTATION FRAMEWORK VERSION 2 (ALL CROPS EXCEPT WILD HARVEST) FINAL

More information

APPLICATION NUMBER: STV. Application for a Stevedoring licence issued in terms of section 57 of the National Ports Act No.

APPLICATION NUMBER: STV. Application for a Stevedoring licence issued in terms of section 57 of the National Ports Act No. APPLICATION NUMBER: STV Stevedoring Application for a Stevedoring licence issued in terms of section 57 of the National Ports Act No. 12 of 2005 Trading name of Applicant: Port in which stevedoring service

More information

TSGB Rules. Job description for the TSGB General Manager and Assistant (Administrative Regulatory Services) STAR project deliverable 9

TSGB Rules. Job description for the TSGB General Manager and Assistant (Administrative Regulatory Services) STAR project deliverable 9 TSGB Rules Job description for the TSGB General Manager and Assistant (Administrative Regulatory Services) STAR project deliverable 9 Date: 20 June 2014 Author: Dr Christopher Querée Owner: TAP Phase Two

More information

Part 2 - Audit and Monitoring. Operational Policy

Part 2 - Audit and Monitoring. Operational Policy Part 2 - Audit and Monitoring Operational Policy Although all reasonable steps have been taken to ensure the accuracy of the information contained in this document, the Ministry of Justice disclaims any

More information

Application of King III Corporate Governance Principles

Application of King III Corporate Governance Principles Application of Corporate Governance Principles / 1 This table is a useful reference to each of the principles and how, in broad terms, they have been applied by the Group. The information should be read

More information

Utility Licence Annual Technical Report

Utility Licence Annual Technical Report Utility Licence Annual Technical Report 2016-17 This compliance report is required to be completed by Distribution and approved by the General Manager Networks or the Chief Executive Officer of Distribution

More information

Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C.

Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule , F.A.C. Kissimmee Utility Authority Storm Hardening Report to the Florida Public Service Commission Pursuant to Rule 25-6.0343, F.A.C. 1) Introduction This report is filed in response to the above referenced rule

More information

Scorecard - Midland Power Utility Corporation 9/28/2018

Scorecard - Midland Power Utility Corporation 9/28/2018 Scorecard - Midland Power Utility Corporation 9/28/218 Performance Outcomes Performance Categories Measures 213 214 215 216 217 Trend Industry Distributor Target Customer Focus Services are provided in

More information

LICENCE FOR THE CONSTRUCTION OF A PETROLEUM STORAGE FACILITY AND AN AUXILIARY PIPELINE

LICENCE FOR THE CONSTRUCTION OF A PETROLEUM STORAGE FACILITY AND AN AUXILIARY PIPELINE Licence Number: PPL.sf.F1/175/2014 LICENCE FOR THE CONSTRUCTION OF A PETROLEUM STORAGE FACILITY AND AN AUXILIARY PIPELINE This licence is issued by the National Energy Regulator, hereinafter referred to

More information

RAINBOW COMMUNICATIONS CODE OF PRACTICE. Including our Basic Code of Practice and our Code of Practice for Premium Rate Services and NTS calls

RAINBOW COMMUNICATIONS CODE OF PRACTICE. Including our Basic Code of Practice and our Code of Practice for Premium Rate Services and NTS calls RAINBOW COMMUNICATIONS CODE OF PRACTICE Including our Basic Code of Practice and our Code of Practice for Premium Rate Services and NTS calls Part 1 - Rainbow Communications Basic Code of Practice on for

More information

9.1 Introduction Legislative requirements for JOHS Committees Composition of JOHS Committee and Safety Sub-committees...

9.1 Introduction Legislative requirements for JOHS Committees Composition of JOHS Committee and Safety Sub-committees... Table of Contents 9.1 Introduction... 2 9.2 Legislative requirements for JOHS Committees... 2 9.3 Composition of JOHS Committee and Safety Sub-committees... 2 9.4 Functions of JOHS Committee... 3 9.5 Roles

More information

Ergon Energy Corporation Limited. Specification for UDC Design RSD01. Specification RSD01 Ver 7. Ergon Energy Corporation Limited ABN

Ergon Energy Corporation Limited. Specification for UDC Design RSD01. Specification RSD01 Ver 7. Ergon Energy Corporation Limited ABN Ergon Energy Corporation Limited Specification for UDC Design RSD01 Specification RSD01 Ver 7 Contents 1. PURPOSE AND SCOPE... 1 2. REFERENCES... 1 2.1 ERGON ENERGY CONTROLLED DOCUMENTS... 1 3. DEFINITIONS,

More information

Pre-commissioning Requirements for Independent Connection Providers Requiring New Assets to be Connected to the 11/6.6kV Network

Pre-commissioning Requirements for Independent Connection Providers Requiring New Assets to be Connected to the 11/6.6kV Network Electricity Specification 220 Issue 3 December 2016 Pre-commissioning Requirements for Independent Connection Providers Requiring New Assets to be Connected to the 11/6.6kV Network Contents 1 Introduction

More information

Scheduled maintenance and rectification works. Systems integration and comprehensive reporting

Scheduled maintenance and rectification works. Systems integration and comprehensive reporting Distribution We have significant experience in asset management, maintenance and construction for overhead and underground electricity distribution networks. This enables us to consistently add-value,

More information

REQUEST FOR QUOTATION (RFQ)

REQUEST FOR QUOTATION (RFQ) 1 June 2018 RFQ No. 10957 REQUEST FOR QUOTATION (RFQ) RFQ Description Closing Date and Time Briefing Session Date and Time Site Inspection : Shuttle and Transport Services for Sasria staff for the period

More information

A Proposed Framework for a Waste-Free Ontario Ministry of the Environment and Climate Change Technical Briefing

A Proposed Framework for a Waste-Free Ontario Ministry of the Environment and Climate Change Technical Briefing A Proposed Framework for a Waste-Free Ontario Ministry of the Environment and Climate Change Technical Briefing Fall 2015 Purpose Overview: Background Proposed Legislation: Waste-Free Ontario Act, including:

More information

Rottnest Island Authority. ERA Electricity Licence Performance Audit and Asset Management System Review Audit Report

Rottnest Island Authority. ERA Electricity Licence Performance Audit and Asset Management System Review Audit Report Rottnest Island Authority ERA Electricity Licence Performance Audit and Asset Management System Review Audit Report November 2017 Executive summary The Rottnest Island Authority (RIA or the licensee) holds

More information

Regulatory Approach to Maintaining Local Security of Supply in Electricity

Regulatory Approach to Maintaining Local Security of Supply in Electricity An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017

More information

PRA RULEBOOK: CRR FIRMS NON-CRR FIRMS: INDIVIDUAL ACCOUNTABILITY INSTRUMENT 2015

PRA RULEBOOK: CRR FIRMS NON-CRR FIRMS: INDIVIDUAL ACCOUNTABILITY INSTRUMENT 2015 PRA 2015/6 PRA RULEBOOK: CRR FIRMS NON-CRR FIRMS: INDIVIDUAL ACCOUNTABILITY INSTRUMENT 2015 Powers exercised A. The Prudential Regulation Authority ( PRA ) makes this instrument in the exercise of the

More information