Re: Proposed Decision on Electricity Network Connection Policy CER 09/072

Size: px
Start display at page:

Download "Re: Proposed Decision on Electricity Network Connection Policy CER 09/072"

Transcription

1 John Orme Electricity Distribution Commission for Energy Regulation The Exchange Belgard Square North Tallaght Dublin 24 Friday, 15 May 2009 Re: Proposed Decision on Electricity Network Connection Policy CER 09/072 John, SWS Energy (SWS) welcomes the decision to consult on Electricity Network Connection Policy and the opportunity to respond to the Commissions proposed decision. However we see this as an ongoing process to resolve the limitations of the current connection policy. You have identified a number of consultations required to reach a conclusion on this consultation, we would also request that you set in place a regular review process that would allow developers to feed into the continuing development and improvement of the connection policy. In the remainder of this letter we respond to the consultation separately; on any additional comments we have in relation to the issues detailed in section 2; on the planning/design phase of connection assets; on the level of certainty within standard contracts for connection to the network and on the proposed changes to the Capacity Bond. With reference to Section 2 of the proposal, SWS have the following observations: SWS welcomes the identification of a number of consultations that the commission intend to facilitate on some of the issues raised during this consultation process. SWS will respond to these consultations separately in turn. With regard to points #1 to #31, SWS welcomes the improvements listed for most points, but we have the following specific detailed comments:

2 Planning and consents Point #4: SWS proposes that CER also consider requiring timelines to achieve necessary consents (i.e. road opening licenses etc.) would be included in modified offers (where modification is for connection from overhead line to underground cable). Point #5: SWS proposes that the system operators provide a breakdown and expected milestones related to the current generic timelines included in the offers specifically identifying the packages of work within and outside their control. Timetables Point #8: SWS proposes that TSO provide programme meets the same level of detail as that described in the DSO response (e.g. highlighting critical path items). The current TSO approach of providing programme within 30 days of CID is too late in the process; SWS proposes that it should be provided at most 30 days following execution of our connection agreement, even if detail needs to be added later. SWS proposes further breakdown of programmes to identify packages of work and expected milestone dates particularly those that are within and outside the system operator s control. Acceleration of Programme Point #9: SWS welcomes the option to purchase long lead-time equipment once planning permission has been lodged. However it should be clarified that this can be achieved with a 5%/10% down-payment from the developer(s), which are normal commercial terms for the initial phases of procurement. SWS proposes that if delay is due to the System Operator, the risk/cost would be applied to the System Operator rather than the developer. Cost Certainty Point #11: SWS welcomes the DSOs proposal to provide estimates of pass through costs at offer stage. SWS proposes that these pass through cost estimates would also be provided by the TSO at offer stage. SWS proposes that the list of pass through costs detailed in the consultation is confirmed as the complete and final list of possible pass through costs. SWS proposes that a breakdown of the TSO costs is provided in the connection agreement similar to the breakdown that DSO currently provide. The benefit of

3 this is to provide developers with further understanding of the implications of offer modifications to their connection costs. SWS also proposes that it be clarified (as we believe to the current process) that the pass through volume changes costs are updated with the actual outturn volumes (i.e. if removing some or all of the 25% (TSO) and 10% (DSO) margin applied to overhead lines distances in offers). Non acceptance of Offers Point #14: Part A - SWS suggests that there may be value in identifying in offers or connection method meetings the minimum threshold of connections that need to be accepted for the group shared assets connection method not to change. This would allow the majority of the group to proceed (once this threshold was reached) even if some offers had been disputed or delayed for some reason. Point #14: Part D While SWS welcomes the CER and system operator s endeavours to meet the Gate 3 timelines as advised, we urge that they do not lose sight of the importance of offer modifications within this time crucially for pre-gate 3 offers and also Gate 3 offers to ensure that we meet out renewable targets. Payment of Charges Point #16: SWS welcomes the DSO s proposal as detailed in the draft direction and propose that the TSO would adapt a policy inline with this. Commissioning Point #17: Contrary to the DSO s assertion that there are significant and adequate commissioning resources available, we have experienced a delay on every wind farm we have commissioned to date due to the shortage of commissioners. With reference to Section 3.0 the Planning/design phase of connection assets within the proposal, SWS have the following observations: SWS welcome the introduction of landowner consultation at pre-construction stage by DSO, SWS request that TSO also include this consultation in their process. SWS also welcome the more collaborative approach between developers and the system operators at the pre-

4 construction stage in the process, developers have valuable knowledge in local areas that would identify if wayleaves for certain routes are achievable or not. SWS welcomes the option, in the collaborative approach, and in consultation with the system operators, to put in place wayleave agreements in advance of seeking planning permission for an overhead line. We agree that this should be optional, and may not be appropriate in all cases. With reference to Section 4.0 the timelines of connection assets within the proposal, SWS have the following observations: SWS welcome the further consideration that is to be applied to providing a fixed date with a payment if the connection assets are not completed by the stated date. SWS have the following initial comments for consideration by the commission in developing the consultation on this: - CER propose that if this is to be implemented by decision of the developer then a margin would be applied to the standard costs. As detailed in our response to your consultation CER/08/167 on Standard Transmission Charges & Timelines we believe that the costs are already inflated and to apply further additional costs to these is an untenable situation. As an alternative to a risk price premium the commission could consider applying a margin to the fixed date (i.e. 3 months). - More detail is required on what level the payment is likely to be. It could take the form of a deemed firm date mechanism, or a fixed day penalty rate related to the wind farm output, but the rate only has any value if it is equal or close to the loss incurred due to the system operators default. - Fixing the date only once consents are achieved is too late in the process. There should be a fixed date within connection offer, and extensions of time only allowed to the extent of any delays outside the control of the system operators such as delays in securing planning permission, consents and wayleaves. - While the deep reinforcements are not being paid for directly by developers, the consequence of their delay to the constraints applied to projects is expected to be significant from Gate 2 connection onwards and so payments/incentives should equally apply to the delivery of deep reinforcements, since the impact could be of a similar magnitude.

5 We look forward to receiving and responding to your consultation on this topic.

6 With reference to the Capacity Bond proposal, we have the following observations: Placement of Bond SWS propose that the commission include a caveat on Capacity Bond placement 2 years from CID, failure to meet MEC or operational certificate within 12 months of connection to cover the situation where the delay/failure is due to reasons outside a developer s control (i.e. that placement of the Bond is as defined provided construction has commenced and is progressing to meet stated connection date) Drawdown of Capacity Bond SWS understand the aim to create an escalating penalty. However we believe in practice that a developer is unlikely to be able to develop proportionate mitigation. He will either lose 3 turbines in planning or he won t, and an escalating penalty based on some arbitrary 1.5 exponent won t have any effect. We propose that a much simpler penalty directly pro-rata to the shortfall in MW will have practically identical effect, but is much more transparent. We suggest the following wording: Condition 1 - Drawdown of the bond for not achieving an MEC greater than or equal to ninety-five percent of the contracted MEC within twelve months from connection of a generation scheme will result in a drawdown of the bond equal to twice the percentage MEC not achieved and an amendment of the contracted MEC to the MEC achieved. Drawdown of the bond under this condition will not be invoked if failure to meet the MEC is due to reasons outside the developer s control. Comparison of the CER proposal for % drawdown = 0.5*[(% MEC not achieved)^1.5] and the SWS proposal = 2*(% MEC not achieved) are both displayed in the following graph.

7 Drawdown % of Bond % of Bond Drawndown % MEC not achieved Drawdown of Bond CER Proposal Drawdown of Bond SWS Proposal Graph 1: Drawdown of bond comparison of SWS and CER proposals - MEC SWS also proposes that rather than tying both requirements of MEC and Operational certificate into the one calculation that they would be 2 standalone conditions for release of the bond. The second related to the achievement of an operational certificate within 12 months being: Condition 2 - Drawdown of the bond for not achieving an operational certificate within twelve months from connection of a generation scheme will result in a drawdown of the bond equal to three times the number of months, twelve months post connection date that operational certificate has not been achieved. Drawdown of the bond under this condition will not be invoked if failure to obtain the operational certificate is due to reasons outside the developer s control Comparison of the CER proposal for % drawdown = 0.5*[(no of months post connection date - 12)^1.5] and the SWS proposal = 3*(no of months post connection date - 12) are both displayed in the following graph.

8 Drawdown % of Bond % of Bond Drawndown # Months OP Cert not achieved 12 months after conection date Drawdown of Bond CER Proposal Drawdown of Bond SWS Proposal Graph 2: Drawdown of bond comparison of SWS and CER proposals OP Cert

9 Payment on Offer Acceptance Again in the interests of simplicity SWS proposes that you require all applicants with a connection charge less than or equal to 100,000/MW to pay 10,000/MW on offer acceptance and all applicants with a connection cost greater than 100,000/MW to pay 10% of the connection cost on offer acceptance. There is no reason to single out developers with connection costs less than 20,000/MW, and indeed there is an argument that you should give equal incentive to discourage hoarding and minimise disruption in groups. This is a more straightforward approach that ensures developers with cheap grid connections are treated equitably. Your current proposed calculation is displayed graphically in Figure 1; the only difference to our proposal is projects with a connection charge less than 20,000/MW would pay 10,000/MW rather than 50% of cost of connection on offer acceptance. Payment at Offer Acceptance (,000/MW) Connection Cost (,000/MW) 10% of Connection Cost Payment at Offer Acceptance X Figure 1: Payment on offer acceptance X = lesser of (50% of cost of Connection & 10,000/MW) Payment at Offer Acceptance = Greater of (10% of Cost of Connection & X) SWS request the CER to caveat slightly the proposal that the initial payment be nonrefundable, SWS would envisage that a refund of the initial payment less costs incurred on progressing the application should remain refundable to the customer, when failure of a project is for reasons outside the developer s control (i.e. system operator failure to get planning permission/necessary consents to deliver the grid connection).

10 An additional point that was not raised in the consultation to date is as follows; SWS see the constraints that the infrastructure agreement (IA) places on EirGrid as a major obstacle to successful project delivery. SWS have recent experience of 2 projects that were substantially delayed due to the limitations placed on EirGrid by the IA. SWS request that the CER look to have the processes within the IA reviewed and proposals from the industry received in an effort to resolve this as a matter of urgency. Finally, we note that Eirgrid made the following statement in their input to this consultation: EirGrid has drafted an enhanced business process for monitoring and reporting on the deep reinforcement works associated with transmission and distribution connecting projects. EirGrid hopes to reach agreement on the process with ESB Networks during Q This process is designed to ensure that all connecting parties are kept regularly informed on progress and current status of deep reinforcement works. Given that SWS has over 200MW of operational wind farms in the south west, all of which are non-firm to varying degrees, this issue is very significant for us, and we will certainly be awaiting further details with interest. Once again we thank the CER for the opportunity to respond to this consultation. We are available to discuss or further develop any of the points raised in this response. Regards, Peter Harte SWS Energy w: t: m:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: 1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call

More information

Group Processing Approach for Renewable Generator Connection Applications. Connection and Pricing Rules

Group Processing Approach for Renewable Generator Connection Applications. Connection and Pricing Rules Group Processing Approach for Renewable Generator Connection Applications Connection and Pricing Rules DIRECTION TO SYSTEM OPERATORS 6 th April 2005 CER/05/049 Table of Contents 1 Introduction... 3 2 Background...

More information

Enduring Connection Policy Stage 1 (ECP-1)

Enduring Connection Policy Stage 1 (ECP-1) An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Enduring Connection Policy Stage 1 (ECP-1) Decision ECP-1 Decision Reference: CRU/18/058 Date Published: 27/03/2018 0 Executive Summary

More information

STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 1 st October 2017 Version 1.

STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 1 st October 2017 Version 1. STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM Effective from 1 st October 2017 Version 1.3 DOCUMENT CHANGE CONTROL SHEET Document Control Document Version

More information

The Voice of the Networks Energy Networks Association

The Voice of the Networks Energy Networks Association The Voice of the Networks Energy Networks Association Fair and Effective Management of DNO Connection Queues: Progression Milestones Best Practice Guide 3 November 2016 1. Purpose and Objective 1.1. The

More information

IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015

IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 By e-mail to: ress@dcenr.gov.ie Introduction IWEA welcomes the opportunity to respond to the

More information

Performance Reporting Criteria

Performance Reporting Criteria Revision Date: February 2012 Revision No.: 2 Document No.: DOC-131102-ADV Status: Approved by CER Date: 01/03/2012 ESB Networks Ltd. Contents 1. Background... 3 2. Report Headings... 4 3. Criteria... 5

More information

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project

Consultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,

More information

ESB Networks - Service Level Agreements. Decision Paper

ESB Networks - Service Level Agreements. Decision Paper ESB Networks - Service Level Agreements Decision Paper CER 04/345 11 November 2004 Introduction On the 21 st June 2004 the Commission published a draft decision on the Service Level Agreements (SLAs) relating

More information

Capacity Performance FAQ Response

Capacity Performance FAQ Response PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum

More information

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati Introduction Indonesian power sector is one of the business sectors in Indonesia which is strictly regulated. For the

More information

GEODE S POSITION ON THE EC DIRECTIVE PROPOSAL

GEODE S POSITION ON THE EC DIRECTIVE PROPOSAL GEODE S POSITION ON THE EC DIRECTIVE PROPOSAL Christian Held, Deputy Chairman of GEODE GEODE Autumn Conference 21 st October 2011 Wien Energie Stromnetz GmbH Mariannengasse 4-6 Vienna 2 Summary I. Introduction

More information

Policy for determining capital contributions on Vector s electricity distribution networks. From 1 December 2017

Policy for determining capital contributions on Vector s electricity distribution networks. From 1 December 2017 Policy for determining capital contributions on Vector s electricity distribution networks From 1 December 2017 Pursuant to: Electricity Distribution Information Disclosure Determination 2012 1 Table of

More information

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee);

Having regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee); Ministerial Order issued by the Minister of Economic Affairs dated 3 October 27 No. WJZ / 722295, containing specific rules for permitting offshore wind energy permits for Wind Farm Sites I and II of the

More information

Consultation on DS3 System Services Scalar Design

Consultation on DS3 System Services Scalar Design Consultation on DS3 System Services Scalar Design DS3 System Services Implementation Project 11 March 2015 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO

More information

NETWORK USE OF SYSTEM CHARGES FOR CHP GENERATORS AND AUTOPRODUCERS PROPOSED DIRECTION BY COMMISSION FOR ENERGY REGULATION

NETWORK USE OF SYSTEM CHARGES FOR CHP GENERATORS AND AUTOPRODUCERS PROPOSED DIRECTION BY COMMISSION FOR ENERGY REGULATION NETWORK USE OF SYSTEM CHARGES FOR CHP GENERATORS AND AUTOPRODUCERS PROPOSED DIRECTION BY COMMISSION FOR ENERGY REGULATION CER/03/167 July 2003 Background: Autoproducers Direction 1. On 17 April 2002 the

More information

Capacity Market: proposals to simplify and improve accessibility in future capacity auctions

Capacity Market: proposals to simplify and improve accessibility in future capacity auctions Department for Business, Energy & Industrial Strategy 3 Whitehall Place, London SW1A 2AW E: energy.security@beis.gov.uk www.gov.uk/beis Our ref: Government response to Capacity Market consultation letter

More information

I-SEM Testing Tariff High Level Options Consultation

I-SEM Testing Tariff High Level Options Consultation I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on

More information

Connect and Manage Guidance March 2013

Connect and Manage Guidance March 2013 Connect and Manage Guidance March 2013 Version 2.0 page 1 of 16 Contents Introduction...3 Enabling and Wider Works...4 Connect and Manage Derogations...9 Connection Applications...10 User Commitment...11

More information

Developer Constructed Headworks Process. Information Guide. 1. watercorporation.com.

Developer Constructed Headworks Process. Information Guide. 1. watercorporation.com. Developer Constructed Headworks Process 1. watercorporation.com. Contents Developer Constructed Headworks Process... 1... 1 Contents... 2 1. Introduction... 3 1.1. Purpose and Objectives... 3 1.2. The

More information

New revenue guidance Implementation in the technology sector

New revenue guidance Implementation in the technology sector No. US2017-08 April 25, 2017 What s inside: Overview..1 Identify the contract.2 Identify performance obligations..6 Determine transaction price 9 Allocate transaction price 12 Recognize revenue. 14 Principal

More information

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy

Wind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Wind Power in Denmark Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Outline Status on wind power deployment and large scale integration Support system and consent

More information

RENEWABLES TRENDS IN SCOTLAND STATISTICS & ANALYSIS. Scottish Natural Heritage June 2007

RENEWABLES TRENDS IN SCOTLAND STATISTICS & ANALYSIS. Scottish Natural Heritage June 2007 RENEWABLES TRENDS IN SCOTLAND STATISTICS & ANALYSIS Scottish Natural Heritage June 2007 Scottish Natural Heritage 2007 1 Table of Contents List of Tables & Figures...3 1 Background...4 1.1 SNH s Renewable

More information

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection

More information

Retail Contracts Scheme Benchmarks

Retail Contracts Scheme Benchmarks Retail Contracts Scheme s 1 - Clear supply commencement 1.1. The gas supply arrangements must state when the supply of gas is to commence, either by stating a specific commencement date or the circumstances

More information

WIND ENERGY AND YOUR LAND

WIND ENERGY AND YOUR LAND WIND ENERGY AND YOUR LAND WIND FARMS & your land Wind turbines and farmland can work very well together, but choosing the right partner is critical. RES works with landowners, farmers and estate managers

More information

SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017

SEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017 SEMOpx Day-ahead Market Products Stage 3 Progress Report May 2017 Contents 1 Introduction... 3 2 Purpose of the Document... 4 3 IAT STAGES... 4 4 Scope of IAT... 6 5 Structure of IAT... 6 5.1 Creation

More information

Balancing Market Principles Statement

Balancing Market Principles Statement Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 1.0 8 September 2017 Version Control Version No. Date Notes 1.0

More information

Annual Renewable Energy Constraint and Curtailment Report 2016

Annual Renewable Energy Constraint and Curtailment Report 2016 Annual Renewable Energy Constraint and Curtailment Report 2016 07/04/2017 Contents Executive Summary... 3 1 Introduction... 5 1.1 Context... 5 1.2 Reasons for Dispatch-Down... 5 1.3 Reporting Methodology...

More information

28/09/16 1. Challenges for wind energy projects in. World Wind Energy Association. Legal Working Group. Eoin Cassidy. Ireland. Mason Hayes & Curran

28/09/16 1. Challenges for wind energy projects in. World Wind Energy Association. Legal Working Group. Eoin Cassidy. Ireland. Mason Hayes & Curran Challenges for wind energy projects in Ireland World Wind Energy Association Legal Working Group Eoin Cassidy Partner Mason Hayes & Curran 28/09/16 1 Wind Energy Positives Ireland In July 2016 there are

More information

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017

Date of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017 Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of

More information

CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA.

CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA. CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA. National Energy Regulatory Agency ANRE Kiev, Jun 2013 Sector challenges Lack of own energy resources (natural gas, oil, coal);

More information

Assessment of Load Shed Service for Import (LSSi) Product

Assessment of Load Shed Service for Import (LSSi) Product Assessment of Load Shed Service for Import (LSSi) Product Date: March 27, 2014 Prepared by: Prepared for: Mike Law Jenny Chen Senior Market Design Specialist Vice President, Market Services Table of Contents

More information

GB regulatory approach RIIO price controls and distributed generation

GB regulatory approach RIIO price controls and distributed generation GB regulatory approach RIIO price controls and distributed generation October 2016 James Veaney Head of Connections and Constraints Management Background Much of network installed in 1950s and 60s with

More information

INCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS. Activities carried out and further guidelines

INCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS. Activities carried out and further guidelines CONSULTATION DOCUMENT 645/2017/R/EEL INCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS Activities carried out and further guidelines Consultation document as part of the proceeding

More information

Role of the Public Electricity Supplier and the Supplier of Last Resort in the De-regulated Electricity Market

Role of the Public Electricity Supplier and the Supplier of Last Resort in the De-regulated Electricity Market Role of the Public Electricity Supplier and the Supplier of Last Resort in the De-regulated Electricity Market DOCUMENT Consultation Paper TYPE: REFERENCE: CER 11/039 DATE PUBLISHED: CLOSING DATE: RESPONSES

More information

Description of the nature and purpose of the modification

Description of the nature and purpose of the modification 160 th January 2014 Transportation Network Code Proposed Modifications No. 12 Congestion Management Procedures Final Modification Report BGE (NI) ( The Transporter ) has prepared this report in accordance

More information

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...

More information

Cluster Study Process

Cluster Study Process Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO

More information

DS3: System Services Review TSO Recommendations

DS3: System Services Review TSO Recommendations DS3: System Services Review TSO Recommendations A Synopsis for the SEM Committee EirGrid and SONI, 2012 Page 1 1. Executive Summary 1.1 Introduction The power system of Ireland and Northern Ireland is

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

Dispatching Variable Generation Resources

Dispatching Variable Generation Resources Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch

More information

15 January FCR Cooperation Draft Proposal

15 January FCR Cooperation Draft Proposal Proposal for the establishment of common and harmonised rules and processes for the exchange and procurement of Frequency Containment Reserve (FCR) in accordance with Art. 33 of COMMISSION REGULATION (EU)

More information

(To be published in the Gazette of India, Part I, Section 1) RESOLUTION. Tariff based Competitive-bidding Guidelines for Transmission Service

(To be published in the Gazette of India, Part I, Section 1) RESOLUTION. Tariff based Competitive-bidding Guidelines for Transmission Service (To be published in the Gazette of India, Part I, Section 1) No. 11/5/2005-PG(i) GOVERNMENT OF INDIA Ministry of Power. RESOLUTION New Delhi, Date: 17th April, 2006 Tariff based Competitive-bidding Guidelines

More information

Generator Interconnection Procedures Overview

Generator Interconnection Procedures Overview Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution

More information

ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION

ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION A National Framework for Electricity Distribution Networks MCE Standing Committee of Officials Policy Response 15 December 2008 Stakeholder consultation

More information

Consultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project

Consultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project Consultation on DS3 System Services Market Ruleset DS3 System Services Implementation Project 15 March 2018 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO

More information

A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority

A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority The evolution of Israel s Renewable Energy Scheme 2017-2020: Solar

More information

Installed power by end 2015, depending on connection point and technology

Installed power by end 2015, depending on connection point and technology Europe s power system is undergoing a profound change. Most of the new generation capacity is being connected to distribution networks. Distributed generation could provide valuable services today to the

More information

Institutional Arrangements for Virtual Reverse Flow at Moffat

Institutional Arrangements for Virtual Reverse Flow at Moffat Institutional Arrangements for Virtual Reverse Flow at Moffat DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: FURTHER INFORMATION: Decision Paper CER/11/113 4 th July 2011 cjohnston@cer.ie The Commission for

More information

Improving the way we price our network services. Consultation paper

Improving the way we price our network services. Consultation paper Improving the way we price our network services Consultation paper October 2015 Table of Contents 1 Overview... 4 2 Background... 6 3 Purpose... 7 4 Network tariff strategy... 7 4.1 Network tariff reform

More information

DECC CONSULTATION RESPONSE: RO Grace periods consultation

DECC CONSULTATION RESPONSE: RO Grace periods consultation DECC CONSULTATION RESPONSE: RO Grace periods consultation Introduction RenewableUK represents 610 organisations in the field of wind, wave and tidal stream energy. Scottish Renewables represents the renewable

More information

Consulting Newsletter

Consulting Newsletter Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME

More information

Dumfries and Galloway Developer Forum. Welcome and Introduction. Pearse Murray

Dumfries and Galloway Developer Forum. Welcome and Introduction. Pearse Murray 8 TH June 2017 Dumfries and Galloway Developer Forum Welcome and Introduction Pearse Murray Agenda Introduction Pearse Murray NGET Update Julian Leslie KTR Project Update Colin Brown Q&A www.spenergynetworks.co.uk

More information

Germany: Energy Briefing

Germany: Energy Briefing Germany: Energy Briefing February 2014 Contents Introduction 01 1. Amended Remuneration 02 2. Compulsory Direct Marketing 03 3. Tender Procedures 04 4. Self Consumption, Support for 04 Energy Intensive

More information

Policy Direction for Alberta s Capacity Market Framework

Policy Direction for Alberta s Capacity Market Framework Policy Direction for Alberta s Capacity Market Framework August 15, 2017 Alberta Department of Energy Table of Contents Executive Summary... 1 1 Introduction... 2 2 Policy Direction for Alberta s Capacity

More information

Board Staff Discussion Paper

Board Staff Discussion Paper Ontario Energy Board Board Staff Discussion Paper on Issues Related to the Connection of Micro-Embedded Generation Facilities EB-2012-0246 December 20, 2012 - 2 - INTRODUCTION Prior to the introduction

More information

Charging Arrangements for New Connection Services

Charging Arrangements for New Connection Services Charging Arrangements for New Connection Services 2018-2019 About South East Water Developer Services Developer Services Department For any new connections requests or issues please contact our Developer

More information

Solution Terms for Customised Apps ( Customised No Apps )

Solution Terms for Customised Apps ( Customised No Apps ) 1. Interpretation 1.1 This Solution is provided in accordance with the Customer s Agreement with EE. 1.2 Solution Description The Customised Apps Solution Description forms part of these Solution Terms.

More information

The Plan would address seasonal planning and ensure that the Mill and growers work each season s production path.

The Plan would address seasonal planning and ensure that the Mill and growers work each season s production path. Cane Supply and Processing Agreement 1. The Tully District has significant potential to grow the area that supplies the mill and sugar per hectare productivity. A whole of district Strategic plan developed

More information

Module 5. Farm Business Management

Module 5. Farm Business Management Module 5. Farm Business Management Standards 5.1 Legal obligations and clear title to resources Management does not keep up to date with relevant legal obligations. Management cannot demonstrate clear

More information

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme Version: V3.0 Date: 29 March 2017 Author: Classification: Aimi Hayman and Bryn Coles DCC Public Document Control

More information

System Services Industry Forum. 12 October 2017

System Services Industry Forum. 12 October 2017 System Services Industry Forum 12 October 2017 Agenda Topic Time Speaker Registration (Tea & Coffee) 09.30 Introduction 10.00 Ian Connaughton Regulatory Authority Update 10.15 CRU/URegNI Regulated Tariffs

More information

JLL Energy & Infrastructure Advisory. Corporate PPAs: The Devil s In The Detail

JLL Energy & Infrastructure Advisory. Corporate PPAs: The Devil s In The Detail JLL Energy & Infrastructure Advisory Corporate PPAs: The Devil s In The Detail Description A volatile energy market and fluctuating wholesale power prices make the planning of future energy expenditure

More information

Incremental Black Start RFP Response Template & General Information

Incremental Black Start RFP Response Template & General Information Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section

More information

Thames Water AMP6 Outcomes Reporting Policy Annex 3 Thames Tideway Tunnel. Performance Commitments March 2015

Thames Water AMP6 Outcomes Reporting Policy Annex 3 Thames Tideway Tunnel. Performance Commitments March 2015 Thames Water AMP6 Outcomes Reporting Policy Annex 3 Thames Tideway Tunnel Performance Commitments March 2015 Published: 31 March 2015 Contents Introduction... 1 T1A Successful procurement of the Infrastructure

More information

BT s response to Ofcom consultation document. Price Rises in Fixed Term Contracts

BT s response to Ofcom consultation document. Price Rises in Fixed Term Contracts BT s response to Ofcom consultation document Price Rises in Fixed Term Contracts 14 March 2013 1 Executive Summary We welcome the opportunity to comment on this consultation on Price Rises in Fixed Term

More information

System Management Action Flagging Methodology Statement

System Management Action Flagging Methodology Statement System Management Action Flagging Methodology Statement Effective Date: 01 April 20172018 Version Number: 910.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission

More information

Non Registered Embedded Generation Information Pack

Non Registered Embedded Generation Information Pack Non Registered Embedded Generation Information Pack > 30 KW to 5 MW Ergon Energy Network Embedded Generator Information Pack With a focus on energising our diverse QLD communities, we are committed to

More information

2018 I&M IRP Website Stakeholder Comment Summary. Stakeholder Comment I&M Response

2018 I&M IRP Website Stakeholder Comment Summary. Stakeholder Comment I&M Response 1. Craig Smith, Beacon Heights Church of Brethren, Fort Wayne, IN. 1a. One suggestion concerns residential solar power and the other covers energy storage. During John Torpey s afternoon presentation covering

More information

Worked Examples for Category 5 Intertripping Service

Worked Examples for Category 5 Intertripping Service Worked Examples for Category 5 Intertripping Service National Grid s industry consultations on the procurement 1 and utilisation 2 of category 5 intertripping service outline the proposed criteria which

More information

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION TO THE COMMISSION FOR ELECTRICITY REGULATION Document No: DOC-140105-AIL 7/02/2000 Introduction: The Commission for Electricity Regulation (CER) have

More information

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity

More information

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges. SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become

More information

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department

PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7

More information

Six Steps to Reduce DSO.

Six Steps to Reduce DSO. Six Steps to Reduce DSO www.eulerhermes.us Six Steps to Reduce DSO 2 Six Steps to Reduce DSO Cash flow is the lifeblood of any business and a key measure to track for a healthy cash flow is Days Sales

More information

Cost and Benefits of Embedded Generation in Ireland

Cost and Benefits of Embedded Generation in Ireland Cost and Benefits of Embedded Generation in Ireland September 2004 Report prepared for Sustainable Energy Ireland by: PB Power CONTENTS 1. Executive Summary 1 1.1 Representative Networks 2 1.2 Costs and

More information

B. Stakeholder Guide: Infrastructure and utility providers

B. Stakeholder Guide: Infrastructure and utility providers B. Stakeholder Guide: Infrastructure and utility providers Why is the Government proposing new legislation? As our population grows, the Government wants to accelerate the building of new communities and

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3

More information

New revenue guidance Implementation in the software industry

New revenue guidance Implementation in the software industry No. US2017-13 July 25, 2017 What s inside: Overview 1 Step 1: Identify the contract. 2 Step 2: Identify performance obligations.6 Step 3: Determine transaction price 18 Step 4: Allocate transaction price.....21

More information

Incentives to Increase Renewable Energy. Linda M. Wagner Senior Legal and Policy Advisor Illinois Commerce Commission

Incentives to Increase Renewable Energy. Linda M. Wagner Senior Legal and Policy Advisor Illinois Commerce Commission Incentives to Increase Renewable Energy Linda M. Wagner Senior Legal and Policy Advisor Illinois Commerce Commission August 13, 2013 Overview Generally, how to encourage renewable energy Specifically,

More information

WindEurope considers that repowered projects could be further provided with a clear path-to-market via:

WindEurope considers that repowered projects could be further provided with a clear path-to-market via: As every energy technology, wind energy assets have an end to their operational lifetime. A significant proportion of the installed EU wind fleet will come to the end of its lifetime between 2020 and 2030.

More information

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I

Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Matteo Leonardi 22 May 2013 Liberalized markets versus monopolies Production Transmission distribution

More information

The North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison. NAFTA Chapter 10: Government Procurement

The North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison. NAFTA Chapter 10: Government Procurement The North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison NAFTA Chapter 10: Government Procurement Chapter Ten: Government Procurement Chapter Fifteen: Government

More information

Work will begin on the project when the Letter of Agreement has been signed.

Work will begin on the project when the Letter of Agreement has been signed. isit2b Marketing, LLC Marketing Services Terms & Conditions is it 2B Marketing provides website & graphic design, copywriting, and related online marketing services. Clients are asked to read and agree

More information

Taking up the baton from the Taylor Review? Select Committees publish joint report and draft bill outlining a new framework for modern employment

Taking up the baton from the Taylor Review? Select Committees publish joint report and draft bill outlining a new framework for modern employment Taking up the baton from the Taylor Review? Select Committees publish joint report and draft bill outlining a new framework for modern employment On 20 November 2017, the House of Commons Work and Pensions

More information

Causes of residential electricity bill changes in Victoria, 1995 to prepared for: Victorian Electricity Distribution Businesses

Causes of residential electricity bill changes in Victoria, 1995 to prepared for: Victorian Electricity Distribution Businesses Causes of residential electricity bill changes in Victoria, 1995 to 2017 prepared for: Victorian Electricity Distribution Businesses DISCLAIMER This report has been prepared for the Victorian Electricity

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR-34 A, CHANDIGARH

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR-34 A, CHANDIGARH PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-21, SECTOR-34 A, CHANDIGARH Petition No. 31 of 2016 Date of Order: 10.06.2016 Present: Shri D.S. Bains, Chairman Shri S.S. Sarna, Member In the

More information

The Voice of the Networks

The Voice of the Networks Guidance on the Presentation of Curtailment Associated with an Active Network Management Connection Offer Introduction The ENA Active Network Management (ANM) Working Group (WG) was formed in late 2013

More information

A GUIDE TO INDEPENDENT FINANCIAL ADVICE & OUR SERVICES

A GUIDE TO INDEPENDENT FINANCIAL ADVICE & OUR SERVICES A GUIDE TO INDEPENDENT FINANCIAL ADVICE & OUR SERVICES All advisers are regulated by the Financial Conduct Authority (FCA). The FCA regulates financial firms providing services to consumers and maintains

More information

Local Market Power Mitigation Enhancements

Local Market Power Mitigation Enhancements Local Market Power Mitigation Enhancements Draft Final Proposal May 6, 2011 CAISO/M&ID/CRH May 6, 2011 page 1 Draft Final Proposal Local Market Power Mitigation Enhancements Table of Contents 1. Introduction...

More information

NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE. Provide a copy of the report to the Board concerning Newfoundland

NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE. Provide a copy of the report to the Board concerning Newfoundland NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE CA181 Provide a copy of the report to the Board concerning Newfoundland Power Company s Study of Innovative Approaches to

More information

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements

Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements CONSULTATION VERSION 7 April 2017 IMPORTANT INFORMATION This Balancing

More information

Electricity trading and transmission arrangements. Towards better electricity trading and transmission arrangements

Electricity trading and transmission arrangements. Towards better electricity trading and transmission arrangements Agenda Advancing economics in business Electricity trading and transmission arrangements Towards better electricity trading and transmission arrangements The UK is facing the significant challenge of integrating

More information

Transforming Rehabilitation

Transforming Rehabilitation Report by the Comptroller and Auditor General Ministry of Justice Transforming Rehabilitation HC 951 SESSION 2015-16 28 APRIL 2016 4 Key facts Transforming Rehabilitation Key facts 21 Community rehabilitation

More information

Western Power Distribution Workplan to Improve Connections Performance 2014/ Quotation and Acceptance

Western Power Distribution Workplan to Improve Connections Performance 2014/ Quotation and Acceptance Western Power Distribution Workplan to Improve Connections Performance 2014/2015 - Quotation and Issue WPD initiative(s) Actions Status update Review and update Offer Letter following Consult on Offer

More information

Open Networks Project

Open Networks Project Open Networks Project Consultation on Phase 2 Work Programme 30 January 2018 Document Ref: ON-Phase 2 Programme T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 1 Introduction

More information

Code of Practice Date of last update: 26th April 2017

Code of Practice Date of last update: 26th April 2017 Code of Practice Date of last update: 26 th April 2017 1 CODE OF PRACTICE The purpose of this code of practice is to inform you in clear and helpful terms about our products, services, customer care policies

More information

Procurement Department PROCUREMENT POLICY

Procurement Department PROCUREMENT POLICY Procurement Department PROCUREMENT POLICY Document Number: CR/QMS/PROC/POL/1101 Documentum Number: Document History: Revision: Date: Prepared by: Checked by: Authorised by: Reason for Issue: 8.0 15.04.10

More information

Fast Tracking Hydro Infrastructure Build in Developing Economies. BJ Rochecouste Collet Technical Director Aurecon South Africa

Fast Tracking Hydro Infrastructure Build in Developing Economies. BJ Rochecouste Collet Technical Director Aurecon South Africa Fast Tracking Hydro Infrastructure Build in Developing Economies BJ Rochecouste Collet Technical Director Aurecon South Africa Fast Tracking? Hydro is the cheapest power source in the Nordic market (Source:

More information