Re: Proposed Decision on Electricity Network Connection Policy CER 09/072
|
|
- Erick Webb
- 6 years ago
- Views:
Transcription
1 John Orme Electricity Distribution Commission for Energy Regulation The Exchange Belgard Square North Tallaght Dublin 24 Friday, 15 May 2009 Re: Proposed Decision on Electricity Network Connection Policy CER 09/072 John, SWS Energy (SWS) welcomes the decision to consult on Electricity Network Connection Policy and the opportunity to respond to the Commissions proposed decision. However we see this as an ongoing process to resolve the limitations of the current connection policy. You have identified a number of consultations required to reach a conclusion on this consultation, we would also request that you set in place a regular review process that would allow developers to feed into the continuing development and improvement of the connection policy. In the remainder of this letter we respond to the consultation separately; on any additional comments we have in relation to the issues detailed in section 2; on the planning/design phase of connection assets; on the level of certainty within standard contracts for connection to the network and on the proposed changes to the Capacity Bond. With reference to Section 2 of the proposal, SWS have the following observations: SWS welcomes the identification of a number of consultations that the commission intend to facilitate on some of the issues raised during this consultation process. SWS will respond to these consultations separately in turn. With regard to points #1 to #31, SWS welcomes the improvements listed for most points, but we have the following specific detailed comments:
2 Planning and consents Point #4: SWS proposes that CER also consider requiring timelines to achieve necessary consents (i.e. road opening licenses etc.) would be included in modified offers (where modification is for connection from overhead line to underground cable). Point #5: SWS proposes that the system operators provide a breakdown and expected milestones related to the current generic timelines included in the offers specifically identifying the packages of work within and outside their control. Timetables Point #8: SWS proposes that TSO provide programme meets the same level of detail as that described in the DSO response (e.g. highlighting critical path items). The current TSO approach of providing programme within 30 days of CID is too late in the process; SWS proposes that it should be provided at most 30 days following execution of our connection agreement, even if detail needs to be added later. SWS proposes further breakdown of programmes to identify packages of work and expected milestone dates particularly those that are within and outside the system operator s control. Acceleration of Programme Point #9: SWS welcomes the option to purchase long lead-time equipment once planning permission has been lodged. However it should be clarified that this can be achieved with a 5%/10% down-payment from the developer(s), which are normal commercial terms for the initial phases of procurement. SWS proposes that if delay is due to the System Operator, the risk/cost would be applied to the System Operator rather than the developer. Cost Certainty Point #11: SWS welcomes the DSOs proposal to provide estimates of pass through costs at offer stage. SWS proposes that these pass through cost estimates would also be provided by the TSO at offer stage. SWS proposes that the list of pass through costs detailed in the consultation is confirmed as the complete and final list of possible pass through costs. SWS proposes that a breakdown of the TSO costs is provided in the connection agreement similar to the breakdown that DSO currently provide. The benefit of
3 this is to provide developers with further understanding of the implications of offer modifications to their connection costs. SWS also proposes that it be clarified (as we believe to the current process) that the pass through volume changes costs are updated with the actual outturn volumes (i.e. if removing some or all of the 25% (TSO) and 10% (DSO) margin applied to overhead lines distances in offers). Non acceptance of Offers Point #14: Part A - SWS suggests that there may be value in identifying in offers or connection method meetings the minimum threshold of connections that need to be accepted for the group shared assets connection method not to change. This would allow the majority of the group to proceed (once this threshold was reached) even if some offers had been disputed or delayed for some reason. Point #14: Part D While SWS welcomes the CER and system operator s endeavours to meet the Gate 3 timelines as advised, we urge that they do not lose sight of the importance of offer modifications within this time crucially for pre-gate 3 offers and also Gate 3 offers to ensure that we meet out renewable targets. Payment of Charges Point #16: SWS welcomes the DSO s proposal as detailed in the draft direction and propose that the TSO would adapt a policy inline with this. Commissioning Point #17: Contrary to the DSO s assertion that there are significant and adequate commissioning resources available, we have experienced a delay on every wind farm we have commissioned to date due to the shortage of commissioners. With reference to Section 3.0 the Planning/design phase of connection assets within the proposal, SWS have the following observations: SWS welcome the introduction of landowner consultation at pre-construction stage by DSO, SWS request that TSO also include this consultation in their process. SWS also welcome the more collaborative approach between developers and the system operators at the pre-
4 construction stage in the process, developers have valuable knowledge in local areas that would identify if wayleaves for certain routes are achievable or not. SWS welcomes the option, in the collaborative approach, and in consultation with the system operators, to put in place wayleave agreements in advance of seeking planning permission for an overhead line. We agree that this should be optional, and may not be appropriate in all cases. With reference to Section 4.0 the timelines of connection assets within the proposal, SWS have the following observations: SWS welcome the further consideration that is to be applied to providing a fixed date with a payment if the connection assets are not completed by the stated date. SWS have the following initial comments for consideration by the commission in developing the consultation on this: - CER propose that if this is to be implemented by decision of the developer then a margin would be applied to the standard costs. As detailed in our response to your consultation CER/08/167 on Standard Transmission Charges & Timelines we believe that the costs are already inflated and to apply further additional costs to these is an untenable situation. As an alternative to a risk price premium the commission could consider applying a margin to the fixed date (i.e. 3 months). - More detail is required on what level the payment is likely to be. It could take the form of a deemed firm date mechanism, or a fixed day penalty rate related to the wind farm output, but the rate only has any value if it is equal or close to the loss incurred due to the system operators default. - Fixing the date only once consents are achieved is too late in the process. There should be a fixed date within connection offer, and extensions of time only allowed to the extent of any delays outside the control of the system operators such as delays in securing planning permission, consents and wayleaves. - While the deep reinforcements are not being paid for directly by developers, the consequence of their delay to the constraints applied to projects is expected to be significant from Gate 2 connection onwards and so payments/incentives should equally apply to the delivery of deep reinforcements, since the impact could be of a similar magnitude.
5 We look forward to receiving and responding to your consultation on this topic.
6 With reference to the Capacity Bond proposal, we have the following observations: Placement of Bond SWS propose that the commission include a caveat on Capacity Bond placement 2 years from CID, failure to meet MEC or operational certificate within 12 months of connection to cover the situation where the delay/failure is due to reasons outside a developer s control (i.e. that placement of the Bond is as defined provided construction has commenced and is progressing to meet stated connection date) Drawdown of Capacity Bond SWS understand the aim to create an escalating penalty. However we believe in practice that a developer is unlikely to be able to develop proportionate mitigation. He will either lose 3 turbines in planning or he won t, and an escalating penalty based on some arbitrary 1.5 exponent won t have any effect. We propose that a much simpler penalty directly pro-rata to the shortfall in MW will have practically identical effect, but is much more transparent. We suggest the following wording: Condition 1 - Drawdown of the bond for not achieving an MEC greater than or equal to ninety-five percent of the contracted MEC within twelve months from connection of a generation scheme will result in a drawdown of the bond equal to twice the percentage MEC not achieved and an amendment of the contracted MEC to the MEC achieved. Drawdown of the bond under this condition will not be invoked if failure to meet the MEC is due to reasons outside the developer s control. Comparison of the CER proposal for % drawdown = 0.5*[(% MEC not achieved)^1.5] and the SWS proposal = 2*(% MEC not achieved) are both displayed in the following graph.
7 Drawdown % of Bond % of Bond Drawndown % MEC not achieved Drawdown of Bond CER Proposal Drawdown of Bond SWS Proposal Graph 1: Drawdown of bond comparison of SWS and CER proposals - MEC SWS also proposes that rather than tying both requirements of MEC and Operational certificate into the one calculation that they would be 2 standalone conditions for release of the bond. The second related to the achievement of an operational certificate within 12 months being: Condition 2 - Drawdown of the bond for not achieving an operational certificate within twelve months from connection of a generation scheme will result in a drawdown of the bond equal to three times the number of months, twelve months post connection date that operational certificate has not been achieved. Drawdown of the bond under this condition will not be invoked if failure to obtain the operational certificate is due to reasons outside the developer s control Comparison of the CER proposal for % drawdown = 0.5*[(no of months post connection date - 12)^1.5] and the SWS proposal = 3*(no of months post connection date - 12) are both displayed in the following graph.
8 Drawdown % of Bond % of Bond Drawndown # Months OP Cert not achieved 12 months after conection date Drawdown of Bond CER Proposal Drawdown of Bond SWS Proposal Graph 2: Drawdown of bond comparison of SWS and CER proposals OP Cert
9 Payment on Offer Acceptance Again in the interests of simplicity SWS proposes that you require all applicants with a connection charge less than or equal to 100,000/MW to pay 10,000/MW on offer acceptance and all applicants with a connection cost greater than 100,000/MW to pay 10% of the connection cost on offer acceptance. There is no reason to single out developers with connection costs less than 20,000/MW, and indeed there is an argument that you should give equal incentive to discourage hoarding and minimise disruption in groups. This is a more straightforward approach that ensures developers with cheap grid connections are treated equitably. Your current proposed calculation is displayed graphically in Figure 1; the only difference to our proposal is projects with a connection charge less than 20,000/MW would pay 10,000/MW rather than 50% of cost of connection on offer acceptance. Payment at Offer Acceptance (,000/MW) Connection Cost (,000/MW) 10% of Connection Cost Payment at Offer Acceptance X Figure 1: Payment on offer acceptance X = lesser of (50% of cost of Connection & 10,000/MW) Payment at Offer Acceptance = Greater of (10% of Cost of Connection & X) SWS request the CER to caveat slightly the proposal that the initial payment be nonrefundable, SWS would envisage that a refund of the initial payment less costs incurred on progressing the application should remain refundable to the customer, when failure of a project is for reasons outside the developer s control (i.e. system operator failure to get planning permission/necessary consents to deliver the grid connection).
10 An additional point that was not raised in the consultation to date is as follows; SWS see the constraints that the infrastructure agreement (IA) places on EirGrid as a major obstacle to successful project delivery. SWS have recent experience of 2 projects that were substantially delayed due to the limitations placed on EirGrid by the IA. SWS request that the CER look to have the processes within the IA reviewed and proposals from the industry received in an effort to resolve this as a matter of urgency. Finally, we note that Eirgrid made the following statement in their input to this consultation: EirGrid has drafted an enhanced business process for monitoring and reporting on the deep reinforcement works associated with transmission and distribution connecting projects. EirGrid hopes to reach agreement on the process with ESB Networks during Q This process is designed to ensure that all connecting parties are kept regularly informed on progress and current status of deep reinforcement works. Given that SWS has over 200MW of operational wind farms in the south west, all of which are non-firm to varying degrees, this issue is very significant for us, and we will certainly be awaiting further details with interest. Once again we thank the CER for the opportunity to respond to this consultation. We are available to discuss or further develop any of the points raised in this response. Regards, Peter Harte SWS Energy w: t: m:
1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:
1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call
More informationGroup Processing Approach for Renewable Generator Connection Applications. Connection and Pricing Rules
Group Processing Approach for Renewable Generator Connection Applications Connection and Pricing Rules DIRECTION TO SYSTEM OPERATORS 6 th April 2005 CER/05/049 Table of Contents 1 Introduction... 3 2 Background...
More informationEnduring Connection Policy Stage 1 (ECP-1)
An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Enduring Connection Policy Stage 1 (ECP-1) Decision ECP-1 Decision Reference: CRU/18/058 Date Published: 27/03/2018 0 Executive Summary
More informationSTATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 1 st October 2017 Version 1.
STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM Effective from 1 st October 2017 Version 1.3 DOCUMENT CHANGE CONTROL SHEET Document Control Document Version
More informationThe Voice of the Networks Energy Networks Association
The Voice of the Networks Energy Networks Association Fair and Effective Management of DNO Connection Queues: Progression Milestones Best Practice Guide 3 November 2016 1. Purpose and Objective 1.1. The
More informationIWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015
IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 By e-mail to: ress@dcenr.gov.ie Introduction IWEA welcomes the opportunity to respond to the
More informationPerformance Reporting Criteria
Revision Date: February 2012 Revision No.: 2 Document No.: DOC-131102-ADV Status: Approved by CER Date: 01/03/2012 ESB Networks Ltd. Contents 1. Background... 3 2. Report Headings... 4 3. Criteria... 5
More informationConsultation on DS3 System Services Contracts for Interim Arrangements. DS3 System Services Implementation Project
Consultation on DS3 System Services Contracts for Interim Arrangements DS3 System Services Implementation Project 21 April 2016 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland,
More informationESB Networks - Service Level Agreements. Decision Paper
ESB Networks - Service Level Agreements Decision Paper CER 04/345 11 November 2004 Introduction On the 21 st June 2004 the Commission published a draft decision on the Service Level Agreements (SLAs) relating
More informationCapacity Performance FAQ Response
PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum
More informationINDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati
INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati Introduction Indonesian power sector is one of the business sectors in Indonesia which is strictly regulated. For the
More informationGEODE S POSITION ON THE EC DIRECTIVE PROPOSAL
GEODE S POSITION ON THE EC DIRECTIVE PROPOSAL Christian Held, Deputy Chairman of GEODE GEODE Autumn Conference 21 st October 2011 Wien Energie Stromnetz GmbH Mariannengasse 4-6 Vienna 2 Summary I. Introduction
More informationPolicy for determining capital contributions on Vector s electricity distribution networks. From 1 December 2017
Policy for determining capital contributions on Vector s electricity distribution networks From 1 December 2017 Pursuant to: Electricity Distribution Information Disclosure Determination 2012 1 Table of
More informationHaving regard to Section 14(2), Section 23(1), (3) and (4) and Section 24(3) of the Offshore Wind Energy Act (Wet windenergie op zee);
Ministerial Order issued by the Minister of Economic Affairs dated 3 October 27 No. WJZ / 722295, containing specific rules for permitting offshore wind energy permits for Wind Farm Sites I and II of the
More informationConsultation on DS3 System Services Scalar Design
Consultation on DS3 System Services Scalar Design DS3 System Services Implementation Project 11 March 2015 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationNETWORK USE OF SYSTEM CHARGES FOR CHP GENERATORS AND AUTOPRODUCERS PROPOSED DIRECTION BY COMMISSION FOR ENERGY REGULATION
NETWORK USE OF SYSTEM CHARGES FOR CHP GENERATORS AND AUTOPRODUCERS PROPOSED DIRECTION BY COMMISSION FOR ENERGY REGULATION CER/03/167 July 2003 Background: Autoproducers Direction 1. On 17 April 2002 the
More informationCapacity Market: proposals to simplify and improve accessibility in future capacity auctions
Department for Business, Energy & Industrial Strategy 3 Whitehall Place, London SW1A 2AW E: energy.security@beis.gov.uk www.gov.uk/beis Our ref: Government response to Capacity Market consultation letter
More informationI-SEM Testing Tariff High Level Options Consultation
I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on
More informationConnect and Manage Guidance March 2013
Connect and Manage Guidance March 2013 Version 2.0 page 1 of 16 Contents Introduction...3 Enabling and Wider Works...4 Connect and Manage Derogations...9 Connection Applications...10 User Commitment...11
More informationDeveloper Constructed Headworks Process. Information Guide. 1. watercorporation.com.
Developer Constructed Headworks Process 1. watercorporation.com. Contents Developer Constructed Headworks Process... 1... 1 Contents... 2 1. Introduction... 3 1.1. Purpose and Objectives... 3 1.2. The
More informationNew revenue guidance Implementation in the technology sector
No. US2017-08 April 25, 2017 What s inside: Overview..1 Identify the contract.2 Identify performance obligations..6 Determine transaction price 9 Allocate transaction price 12 Recognize revenue. 14 Principal
More informationWind Power in Denmark. Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy
Wind Power in Denmark Steffen Nielsen Head of Section Danish Energy Authority Ministry of Climate and Energy Outline Status on wind power deployment and large scale integration Support system and consent
More informationRENEWABLES TRENDS IN SCOTLAND STATISTICS & ANALYSIS. Scottish Natural Heritage June 2007
RENEWABLES TRENDS IN SCOTLAND STATISTICS & ANALYSIS Scottish Natural Heritage June 2007 Scottish Natural Heritage 2007 1 Table of Contents List of Tables & Figures...3 1 Background...4 1.1 SNH s Renewable
More informationConsultation on Connecting Further Generation in Northern Ireland. Call for Evidence
Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection
More informationRetail Contracts Scheme Benchmarks
Retail Contracts Scheme s 1 - Clear supply commencement 1.1. The gas supply arrangements must state when the supply of gas is to commence, either by stating a specific commencement date or the circumstances
More informationWIND ENERGY AND YOUR LAND
WIND ENERGY AND YOUR LAND WIND FARMS & your land Wind turbines and farmland can work very well together, but choosing the right partner is critical. RES works with landowners, farmers and estate managers
More informationSEMOpx Day-ahead Market Products Stage 3 Progress Report. May 2017
SEMOpx Day-ahead Market Products Stage 3 Progress Report May 2017 Contents 1 Introduction... 3 2 Purpose of the Document... 4 3 IAT STAGES... 4 4 Scope of IAT... 6 5 Structure of IAT... 6 5.1 Creation
More informationBalancing Market Principles Statement
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements Version 1.0 8 September 2017 Version Control Version No. Date Notes 1.0
More informationAnnual Renewable Energy Constraint and Curtailment Report 2016
Annual Renewable Energy Constraint and Curtailment Report 2016 07/04/2017 Contents Executive Summary... 3 1 Introduction... 5 1.1 Context... 5 1.2 Reasons for Dispatch-Down... 5 1.3 Reporting Methodology...
More information28/09/16 1. Challenges for wind energy projects in. World Wind Energy Association. Legal Working Group. Eoin Cassidy. Ireland. Mason Hayes & Curran
Challenges for wind energy projects in Ireland World Wind Energy Association Legal Working Group Eoin Cassidy Partner Mason Hayes & Curran 28/09/16 1 Wind Energy Positives Ireland In July 2016 there are
More informationDate of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017
Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of
More informationCURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA.
CURRENT STATUS AND PERSPECTIVES OF RES DEVELOPMENT IN THE REPUBLIC OF MOLDOVA. National Energy Regulatory Agency ANRE Kiev, Jun 2013 Sector challenges Lack of own energy resources (natural gas, oil, coal);
More informationAssessment of Load Shed Service for Import (LSSi) Product
Assessment of Load Shed Service for Import (LSSi) Product Date: March 27, 2014 Prepared by: Prepared for: Mike Law Jenny Chen Senior Market Design Specialist Vice President, Market Services Table of Contents
More informationGB regulatory approach RIIO price controls and distributed generation
GB regulatory approach RIIO price controls and distributed generation October 2016 James Veaney Head of Connections and Constraints Management Background Much of network installed in 1950s and 60s with
More informationINCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS. Activities carried out and further guidelines
CONSULTATION DOCUMENT 645/2017/R/EEL INCREASING THE RESILIENCE OF ELECTRICITY TRANSMISSION AND DISTRIBUTION NETWORKS Activities carried out and further guidelines Consultation document as part of the proceeding
More informationRole of the Public Electricity Supplier and the Supplier of Last Resort in the De-regulated Electricity Market
Role of the Public Electricity Supplier and the Supplier of Last Resort in the De-regulated Electricity Market DOCUMENT Consultation Paper TYPE: REFERENCE: CER 11/039 DATE PUBLISHED: CLOSING DATE: RESPONSES
More informationDescription of the nature and purpose of the modification
160 th January 2014 Transportation Network Code Proposed Modifications No. 12 Congestion Management Procedures Final Modification Report BGE (NI) ( The Transporter ) has prepared this report in accordance
More informationNatural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).
Guidance Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA). March 2008 Table of Contents Page INTRODUCTION... 2 DEFINITIONS...
More informationCluster Study Process
Cluster Study Process This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution Tariff (WDT) and Appendix Y of CAISO
More informationDS3: System Services Review TSO Recommendations
DS3: System Services Review TSO Recommendations A Synopsis for the SEM Committee EirGrid and SONI, 2012 Page 1 1. Executive Summary 1.1 Introduction The power system of Ireland and Northern Ireland is
More informationBusiness Practice Manual for Reliability Requirements. Version 34
Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM
More informationDispatching Variable Generation Resources
Dispatching Variable Generation Resources A Discussion Paper for Stakeholder Engagement 91 (Renewable Integration) Table of Contents Introduction... 3 IESO Dispatch Processes... 5 Registration... 5 Dispatch
More information15 January FCR Cooperation Draft Proposal
Proposal for the establishment of common and harmonised rules and processes for the exchange and procurement of Frequency Containment Reserve (FCR) in accordance with Art. 33 of COMMISSION REGULATION (EU)
More information(To be published in the Gazette of India, Part I, Section 1) RESOLUTION. Tariff based Competitive-bidding Guidelines for Transmission Service
(To be published in the Gazette of India, Part I, Section 1) No. 11/5/2005-PG(i) GOVERNMENT OF INDIA Ministry of Power. RESOLUTION New Delhi, Date: 17th April, 2006 Tariff based Competitive-bidding Guidelines
More informationGenerator Interconnection Procedures Overview
Generator Procedures Overview For questions, please email gen@pge.com This presentation is a tool to supplement the FERC approved Generator Procedures (GIP) found in Attachment I of PG&E s Wholesale Distribution
More informationELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION
ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION A National Framework for Electricity Distribution Networks MCE Standing Committee of Officials Policy Response 15 December 2008 Stakeholder consultation
More informationConsultation on DS3 System Services Market Ruleset. DS3 System Services Implementation Project
Consultation on DS3 System Services Market Ruleset DS3 System Services Implementation Project 15 March 2018 Disclaimer EirGrid as the Transmission System Operator (TSO) for Ireland, and SONI as the TSO
More informationA Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority
A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority The evolution of Israel s Renewable Energy Scheme 2017-2020: Solar
More informationInstalled power by end 2015, depending on connection point and technology
Europe s power system is undergoing a profound change. Most of the new generation capacity is being connected to distribution networks. Distributed generation could provide valuable services today to the
More informationInstitutional Arrangements for Virtual Reverse Flow at Moffat
Institutional Arrangements for Virtual Reverse Flow at Moffat DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: FURTHER INFORMATION: Decision Paper CER/11/113 4 th July 2011 cjohnston@cer.ie The Commission for
More informationImproving the way we price our network services. Consultation paper
Improving the way we price our network services Consultation paper October 2015 Table of Contents 1 Overview... 4 2 Background... 6 3 Purpose... 7 4 Network tariff strategy... 7 4.1 Network tariff reform
More informationDECC CONSULTATION RESPONSE: RO Grace periods consultation
DECC CONSULTATION RESPONSE: RO Grace periods consultation Introduction RenewableUK represents 610 organisations in the field of wind, wave and tidal stream energy. Scottish Renewables represents the renewable
More informationConsulting Newsletter
Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME
More informationDumfries and Galloway Developer Forum. Welcome and Introduction. Pearse Murray
8 TH June 2017 Dumfries and Galloway Developer Forum Welcome and Introduction Pearse Murray Agenda Introduction Pearse Murray NGET Update Julian Leslie KTR Project Update Colin Brown Q&A www.spenergynetworks.co.uk
More informationGermany: Energy Briefing
Germany: Energy Briefing February 2014 Contents Introduction 01 1. Amended Remuneration 02 2. Compulsory Direct Marketing 03 3. Tender Procedures 04 4. Self Consumption, Support for 04 Energy Intensive
More informationPolicy Direction for Alberta s Capacity Market Framework
Policy Direction for Alberta s Capacity Market Framework August 15, 2017 Alberta Department of Energy Table of Contents Executive Summary... 1 1 Introduction... 2 2 Policy Direction for Alberta s Capacity
More informationBoard Staff Discussion Paper
Ontario Energy Board Board Staff Discussion Paper on Issues Related to the Connection of Micro-Embedded Generation Facilities EB-2012-0246 December 20, 2012 - 2 - INTRODUCTION Prior to the introduction
More informationCharging Arrangements for New Connection Services
Charging Arrangements for New Connection Services 2018-2019 About South East Water Developer Services Developer Services Department For any new connections requests or issues please contact our Developer
More informationSolution Terms for Customised Apps ( Customised No Apps )
1. Interpretation 1.1 This Solution is provided in accordance with the Customer s Agreement with EE. 1.2 Solution Description The Customised Apps Solution Description forms part of these Solution Terms.
More informationThe Plan would address seasonal planning and ensure that the Mill and growers work each season s production path.
Cane Supply and Processing Agreement 1. The Tully District has significant potential to grow the area that supplies the mill and sugar per hectare productivity. A whole of district Strategic plan developed
More informationModule 5. Farm Business Management
Module 5. Farm Business Management Standards 5.1 Legal obligations and clear title to resources Management does not keep up to date with relevant legal obligations. Management cannot demonstrate clear
More informationDCC Business Case for DCC activities during the Transitional Phase of the Switching Programme
DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme Version: V3.0 Date: 29 March 2017 Author: Classification: Aimi Hayman and Bryn Coles DCC Public Document Control
More informationSystem Services Industry Forum. 12 October 2017
System Services Industry Forum 12 October 2017 Agenda Topic Time Speaker Registration (Tea & Coffee) 09.30 Introduction 10.00 Ian Connaughton Regulatory Authority Update 10.15 CRU/URegNI Regulated Tariffs
More informationJLL Energy & Infrastructure Advisory. Corporate PPAs: The Devil s In The Detail
JLL Energy & Infrastructure Advisory Corporate PPAs: The Devil s In The Detail Description A volatile energy market and fluctuating wholesale power prices make the planning of future energy expenditure
More informationIncremental Black Start RFP Response Template & General Information
Revision 2: 7/28/2015 Incremental Black Start RFP Response Template & General Information Overview This document is divided into three sections: Section 1: An incremental RFP response template Section
More informationThames Water AMP6 Outcomes Reporting Policy Annex 3 Thames Tideway Tunnel. Performance Commitments March 2015
Thames Water AMP6 Outcomes Reporting Policy Annex 3 Thames Tideway Tunnel Performance Commitments March 2015 Published: 31 March 2015 Contents Introduction... 1 T1A Successful procurement of the Infrastructure
More informationBT s response to Ofcom consultation document. Price Rises in Fixed Term Contracts
BT s response to Ofcom consultation document Price Rises in Fixed Term Contracts 14 March 2013 1 Executive Summary We welcome the opportunity to comment on this consultation on Price Rises in Fixed Term
More informationSystem Management Action Flagging Methodology Statement
System Management Action Flagging Methodology Statement Effective Date: 01 April 20172018 Version Number: 910.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission
More informationNon Registered Embedded Generation Information Pack
Non Registered Embedded Generation Information Pack > 30 KW to 5 MW Ergon Energy Network Embedded Generator Information Pack With a focus on energising our diverse QLD communities, we are committed to
More information2018 I&M IRP Website Stakeholder Comment Summary. Stakeholder Comment I&M Response
1. Craig Smith, Beacon Heights Church of Brethren, Fort Wayne, IN. 1a. One suggestion concerns residential solar power and the other covers energy storage. During John Torpey s afternoon presentation covering
More informationWorked Examples for Category 5 Intertripping Service
Worked Examples for Category 5 Intertripping Service National Grid s industry consultations on the procurement 1 and utilisation 2 of category 5 intertripping service outline the proposed criteria which
More informationDISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION
DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION TO THE COMMISSION FOR ELECTRICITY REGULATION Document No: DOC-140105-AIL 7/02/2000 Introduction: The Commission for Electricity Regulation (CER) have
More information450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India
450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity
More informationSCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.
SCHEDULE 12 Transmission Enhancement Charges (a) Establishment of Transmission Enhancement Charges. (i) Establishment of Transmission Enhancement Charges by Transmission Owners and Entities That Will Become
More informationPJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department
PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7
More informationSix Steps to Reduce DSO.
Six Steps to Reduce DSO www.eulerhermes.us Six Steps to Reduce DSO 2 Six Steps to Reduce DSO Cash flow is the lifeblood of any business and a key measure to track for a healthy cash flow is Days Sales
More informationCost and Benefits of Embedded Generation in Ireland
Cost and Benefits of Embedded Generation in Ireland September 2004 Report prepared for Sustainable Energy Ireland by: PB Power CONTENTS 1. Executive Summary 1 1.1 Representative Networks 2 1.2 Costs and
More informationB. Stakeholder Guide: Infrastructure and utility providers
B. Stakeholder Guide: Infrastructure and utility providers Why is the Government proposing new legislation? As our population grows, the Government wants to accelerate the building of new communities and
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3
More informationNew revenue guidance Implementation in the software industry
No. US2017-13 July 25, 2017 What s inside: Overview 1 Step 1: Identify the contract. 2 Step 2: Identify performance obligations.6 Step 3: Determine transaction price 18 Step 4: Allocate transaction price.....21
More informationIncentives to Increase Renewable Energy. Linda M. Wagner Senior Legal and Policy Advisor Illinois Commerce Commission
Incentives to Increase Renewable Energy Linda M. Wagner Senior Legal and Policy Advisor Illinois Commerce Commission August 13, 2013 Overview Generally, how to encourage renewable energy Specifically,
More informationWindEurope considers that repowered projects could be further provided with a clear path-to-market via:
As every energy technology, wind energy assets have an end to their operational lifetime. A significant proportion of the installed EU wind fleet will come to the end of its lifetime between 2020 and 2030.
More informationRenewable sources of energy, dispatching priority and balancing the system, facts and options: Part I
Renewable sources of energy, dispatching priority and balancing the system, facts and options: Part I Matteo Leonardi 22 May 2013 Liberalized markets versus monopolies Production Transmission distribution
More informationThe North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison. NAFTA Chapter 10: Government Procurement
The North-Atlantic Free Trade Agreement and the Trans-Pacific Partnership: Side-by-Side Comparison NAFTA Chapter 10: Government Procurement Chapter Ten: Government Procurement Chapter Fifteen: Government
More informationWork will begin on the project when the Letter of Agreement has been signed.
isit2b Marketing, LLC Marketing Services Terms & Conditions is it 2B Marketing provides website & graphic design, copywriting, and related online marketing services. Clients are asked to read and agree
More informationTaking up the baton from the Taylor Review? Select Committees publish joint report and draft bill outlining a new framework for modern employment
Taking up the baton from the Taylor Review? Select Committees publish joint report and draft bill outlining a new framework for modern employment On 20 November 2017, the House of Commons Work and Pensions
More informationCauses of residential electricity bill changes in Victoria, 1995 to prepared for: Victorian Electricity Distribution Businesses
Causes of residential electricity bill changes in Victoria, 1995 to 2017 prepared for: Victorian Electricity Distribution Businesses DISCLAIMER This report has been prepared for the Victorian Electricity
More informationPUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR-34 A, CHANDIGARH
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-21, SECTOR-34 A, CHANDIGARH Petition No. 31 of 2016 Date of Order: 10.06.2016 Present: Shri D.S. Bains, Chairman Shri S.S. Sarna, Member In the
More informationThe Voice of the Networks
Guidance on the Presentation of Curtailment Associated with an Active Network Management Connection Offer Introduction The ENA Active Network Management (ANM) Working Group (WG) was formed in late 2013
More informationA GUIDE TO INDEPENDENT FINANCIAL ADVICE & OUR SERVICES
A GUIDE TO INDEPENDENT FINANCIAL ADVICE & OUR SERVICES All advisers are regulated by the Financial Conduct Authority (FCA). The FCA regulates financial firms providing services to consumers and maintains
More informationLocal Market Power Mitigation Enhancements
Local Market Power Mitigation Enhancements Draft Final Proposal May 6, 2011 CAISO/M&ID/CRH May 6, 2011 page 1 Draft Final Proposal Local Market Power Mitigation Enhancements Table of Contents 1. Introduction...
More informationNEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE. Provide a copy of the report to the Board concerning Newfoundland
NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE CA181 Provide a copy of the report to the Board concerning Newfoundland Power Company s Study of Innovative Approaches to
More informationBalancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements
Balancing Market Principles Statement A Guide to Scheduling and Dispatch under the Revised Single Electricity Market Arrangements CONSULTATION VERSION 7 April 2017 IMPORTANT INFORMATION This Balancing
More informationElectricity trading and transmission arrangements. Towards better electricity trading and transmission arrangements
Agenda Advancing economics in business Electricity trading and transmission arrangements Towards better electricity trading and transmission arrangements The UK is facing the significant challenge of integrating
More informationTransforming Rehabilitation
Report by the Comptroller and Auditor General Ministry of Justice Transforming Rehabilitation HC 951 SESSION 2015-16 28 APRIL 2016 4 Key facts Transforming Rehabilitation Key facts 21 Community rehabilitation
More informationWestern Power Distribution Workplan to Improve Connections Performance 2014/ Quotation and Acceptance
Western Power Distribution Workplan to Improve Connections Performance 2014/2015 - Quotation and Issue WPD initiative(s) Actions Status update Review and update Offer Letter following Consult on Offer
More informationOpen Networks Project
Open Networks Project Consultation on Phase 2 Work Programme 30 January 2018 Document Ref: ON-Phase 2 Programme T +44 (0) 20 7706 5100 W www.energynetworks.org.uk E info@energynetworks.org 1 Introduction
More informationCode of Practice Date of last update: 26th April 2017
Code of Practice Date of last update: 26 th April 2017 1 CODE OF PRACTICE The purpose of this code of practice is to inform you in clear and helpful terms about our products, services, customer care policies
More informationProcurement Department PROCUREMENT POLICY
Procurement Department PROCUREMENT POLICY Document Number: CR/QMS/PROC/POL/1101 Documentum Number: Document History: Revision: Date: Prepared by: Checked by: Authorised by: Reason for Issue: 8.0 15.04.10
More informationFast Tracking Hydro Infrastructure Build in Developing Economies. BJ Rochecouste Collet Technical Director Aurecon South Africa
Fast Tracking Hydro Infrastructure Build in Developing Economies BJ Rochecouste Collet Technical Director Aurecon South Africa Fast Tracking? Hydro is the cheapest power source in the Nordic market (Source:
More information