Reliability Performance Evaluation Work Group

Size: px
Start display at page:

Download "Reliability Performance Evaluation Work Group"

Transcription

1 Reliability Performance Evaluation Work Group Phase I Probabilistic Based Reliability Criteria Evaluation of Exceptions List Facilities February 2, 2001

2 Phase I Probabilistic Based Reliability Criteria Evaluation of Exceptions List Facilities Purpose The purpose of this report is to document and present to PCC the Reliability Performance Work Group (RPEWG) evaluation of the Criteria Exceptions List facilities using the Phase I Probabilistic based Reliability Criteria (PBRC) as required by the RPEWG s work scope. Criteria Exceptions List A list contain the exception facilities and their descriptions as provided in the original TSS documentation (Criteria Exceptions List, January 1996.) is given in Attachment 1. Two categories of exceptions are identified: (1) disturbances declared noncredible, and (2) credible disturbances that have been granted exceptions to the criteria. An Exceptions List developed for the Phase I PBRC test period application is given in Table 1 below. This list was developed using Attachment 1. In developing this list several considerations were made: Develop more encompassing description of the exceptions, provide appropriate means for collocating sufficient data to assess outage frequencies, and combine the two categories of the original exception lists since their outage credibility will be re-evaluated using Phase I PBRC. Exceptions List Outage Data The RPEWG requested outage data of all Exceptions List facilities and provided outage data submittal templates. Transmission facility multiple element outage data resulting form simultaneous outages of dependent events are considered. Outages or system impacts caused due to RAS failure or system wide disturbance that are caused outside the facility are not subject for performance evaluation by the RPEWG. The utilities that submitted outage data associated with the Exceptions List are indicated in Table 1. Data for all of the Exceptions List items except No. 2 and 3 have been provided. MJB 2/2/01 1

3 Table 1: Exception List Facilities for Phase 1 PBRC Evaluation (The description of the Exceptions List Facilities is given in Attachment 1.) No. Description RAS Available Data Submitted Data Submitted by 1 Laramie River fault with loss of 2 circuits No Yes WAPA & BEPC 2 NE/SE Separation Scheme Misoperation Yes No 3 Bridger fault with loss of 2 circuits and RAS failure Yes No 4 Taft fault with loss of 2 circuits and RAS failure Yes Yes BPA 5 Navajo fault with loss of 1 circuit with 1 circuit already out and system unadjusted 6 Malin fault with loss of 2 circuits and RAS failure 7 Ingledow fault with loss of 2 circuits and RAS failure No Yes APS Yes Yes PG&E Yes Yes BCH 8 IPP Bipole outage and RAS failure Yes Yes LADWP 9 Palo Verde fault with loss of 2 circuits No Yes APS 10 Navajo fault with loss of 2 circuits No Yes APS 11 Lugo fault with loss of 2 circuits No Yes SCE 12 a) Navajo fault with loss of 2 circuits No Yes APS b) Eldorado fault with loss of 2 circuits No Yes APS WSCC Reliability Criteria for Transmission Planning Application To perform reliability performance evaluation of the Exceptions List facilities, general reliability criteria principles with regard to the application of the WSCC Disturbance Table, and definitions of the multiple element outages, two circuit outages, and Remedial Action Scheme are utilized. Some of the pertinent requirements and definitions from the WSCC criteria are given in Attachment 2. MJB 2/2/01 2

4 Phase I PBRC Performance Table and Data Interpretation Given below are the Phase I PBRC Performance Table and some conceptual diagrams for interpretations of the criteria. Performance Level Disturbance Outage Class Outage Frequency (outages/year) Mean-Time- Between-Failure (year) V 1 (%) t (cycle) V 2 (%) f min (Hz) A Single Element >0 B Bus Section >0 C Two Element >0 D More than Two NO CASCADING PERMITTED Elements (I)* E More than Two Elements (II)** < < EVALUATE FOR RISKS & CONSEQUENCES * Three or more circuits on common ROW ** Other multi-circuit outages identified in the March 1999 Reliability Criteria. Damp. (%) Probability of Occurrence A B/C D E V V = Variance Logarithmic Scale MTBF, years A B C D E Logarithmic Scale MTBF, years MJB 2/2/01 3

5 Remedial Action Scheme Issues The Exceptions List facilities that contain RAS are indicated in Table 1. Six out of the twelve Exceptions List facilities include RAS failures. RPEWG is not mandated to evaluate the reliability of these RASs or the credibility of their failures. Only the outage data related to the transmission equipment is analyzed. Information on RAS failures that are obtained during the performance evaluation will be forwarded to the WSCC Remedial Action Scheme Reliability Task Force (RASRTF) for their review and consideration. Criteria Exception in the PBRC Table By definition, the WSCC Criteria Exceptions List facilities are not required to meet any of the WSCC Criteria. (See Attachment 1 and 2.) From the PBRC application, the criteria for the Exception List facilities is Level E or better with MTBF greater than 300 years, or outage frequency of less than outages per year. Performance Evaluation Considerations As outlined in the Phase I PBRC report of June 25, 2000: Performance level evaluation (PLE) includes event probability assessment of facility taking into consideration the facility s physical characteristics, design considerations, operational history, geographic location, environmental surrounding, or other appropriate factors. (Section 4.1) A facility in the Exceptions List that is projected to have higher outage frequency than the class in which it is placed due to the exception may be downgraded 1 in its performance level following PLE. (Section 4.1) When considering performance level upgrade or downgrade of a facility, the facility s outage impact should be part of the consideration. (Section 4.1) To be consistent, as much as practicable, with the requirements of the new NERC Planning Standards and existing WSCC Reliability Criteria, no cascading or voltage collapse will be allowed for "loss of a single component" or "single system element disturbances," respectively 2. Outside the existing NERC and WSCC criteria, planned loss of load or loss of generation may be allowed for single element outage disturbance for less probable outages. (Section 4.1) 1 Downgrade = Making the performance level requirement more stringent; for example changing requirement from Level D to C, or B to A. 2 NERC Planning Standards, Page 14, Table I, Column 1; WSCC Reliability Criteria for Transmission System Planning Page 2, Paragraph 5. MJB 2/2/01 4

6 [R]PEWG may reasonably request additional information or data associated with its performance level evaluation and determination and the entity(s) involved should furnish the data to the extent it is available. (Section 4.3.5) Upon consensus agreement by [R]PEWG members, performance level adjustment recommendations are made to the appropriate WSCC group or committee for consideration and further actions. (Section 4.3.5) RPEWG Evaluation Guideline In evaluation of outage data, one outage occurrence is considered statistically insignificant regardless of the outage data time period. However, two or more are considered significant and are used in the reliability performance evaluation. Outage data time period should cover not less than ten years. If data greater than 10 year is available, it can be used in the evaluation at the facility owner s discretion. For facilities that has been in operation less than ten years, data for the operational period will be used. For Performance Level C, D and E, forced automatic 3 common-mode 4 outages are considered in outage counting. This will include: 1. Right-of-way or corridor outages. 2. Relay or other failures of unknown nature. 3. Human or relay failures that cause system outages. For Performance Level A and B, all forced automatic outages are considered in outage counting. Outages not considered in the counting include: 1. System wide outages that are initiated outside the facility in question. 2. Scheduled outages. 3. Major natural disasters or malicious misconduct such as earthquakes or sabotage. Only outage event probabilities are considered in the RPEWG evaluations of the Exceptions List facilities. Outage impacts or the overall performance risk due to outages are not considerations in this RPEWG evaluation. (This is in contrary to the recommendation of Phase I PBRC implementation plan Section 4.1.) Until the WSCC Reliability Subcommittee (RS) develops impact probabilities (Phase II PBRC), RS will be assisting RPEWG in the evaluation of facility outage impacts. As a general guide, RPEWG recommends that a single outage occurrence that results in cascading system impact is sufficient to disqualify an Exceptions List facility. 3 An outage which results from automatic operation of switching devices. 4 A related multiple outage event consisting of two or more primary outage occurrences initiated by a single incident where the outage occurrences are not consequences of each other. MJB 2/2/01 5

7 Exception List Facilities Evaluation and Recommendations Detailed evaluation sheet for each of the Exceptions List facilities is given in Attachment 3. The assessment is strictly based on the data submitted by the facility owners/operators as indicated in Table 1. If different data are made available in the future, the evaluations may be different. Some of the key considerations used in the reliability performance evaluation of the Exceptions List facilities included: Whether the facility is equipped with RAS or not? Whether the outage statistics show one or more outages in ten years? Based on the ten-year data submitted. Is there sufficient data to make the proper evaluation and reliability determination? Conclusions and recommendations are given below: RAS Equipped Facilities: Four facilities (No. 4, 6, 7 and 8) were assessed and the data of each of these facilities did indicate proper operation of their respective RASs. Because, the facilities are equipped with RAS, and the RASs were found to operate properly, these facility are recommend for maintaining their Exceptions status. Facilities Recommended for Keeping their Exceptions Status: Six Exceptions List items (No. 1, 5, 9, 10, 11 and 12) were assessed and found to meet the requirement for keeping their Exceptions status. According to the data submitted, in all of these cases except item 11, the facilities did not experience any outages in the ten-year evaluation period, and the two circuits under evaluation do not have common mode failure conditions. For Exception List Item 11, there was one multi-circuit outage (caused by a plan hitting the lines) that resulted in loss of load in areas outside the initiating utility. Nevertheless, according to the RPEWG Evaluation Guideline, the single event is considered statistically insignificant and thus not counted in the determination of evaluation performance. Furthermore, since the impact did not result in cascading outage, there is no compelling evidence to disqualify the facility from the Exception List. Facilities that have not Provided Data: Evaluation of two Exceptions List items (No. 2 and 3) was not done because no data was provided. Exceptions List No 2, is related with RAS only and no transmission line equipment is involved. Thus, it is recommended that no further evaluation is needed. Exceptions List facility No. 3 is also equipped with RAS. However, it is recommended that the owners of the facilities provide the necessary information to complete the assessment. Mo Beshir MJB 2/2/01 6

8 2/2/01 MJB 2/2/01 7

9 ATTACHMENT 1 Excerpts from: Criteria Exceptions List By System Review Work Group January DISTURBANCE DECLARED NON-CREDIBLE The following is a list of disturbances declared non-credible by the TSS. If any of these outages occur in real life, the subject of their credibility will be re-evaluated by the TSS. Until that time, they will not be formally studied by the WSCC staff as part of the Annual Study Program. DISTURBANCE D2.1: Laramie River 345-kV three-phase fault, loss of the Laramie River-Ault and Laramie River-Beaver Creek 345-kV lines. DISTURBANCE D2.2: False operation of the NE/SE separation scheme RAS malfunction. DISTURBANCE D2.3: Bridger 345-kV three-phase fault, loss of the Bridger-Borah and Bridger-Kinport 345-kV lines with failure of Bridger generator tripping RAS malfunction. DISTURBANCE D2.4: Taft 500-kV three-phase fault, loss of both Taft-Garrison 500- kv lines with total failure of Colstrip generator tripping RAS malfunction. DISTURBANCE D2.5: Navajo 500-kV three-phase fault, loss of the Navajo- McCullough 500-kV line, prior outage of the Navajo-Meonkopi 500-kV line with system unadjusted. DISTURBANCE D2.6: Malin 500-kV three-phase fault, loss of both Malin-Round Mountain 500-kV lines with failure of Chief Joseph brake insertion and Northwest generator tripping remedial action RAS malfunction. DISTURBANCE D2.7: Ingledow 500-kV three-phase fault, loss of both Ingledow- Custer 500-kV lines with failure of Mica generator tripping remedial action RAS malfunction. DISTURBANCE D2.8: Bipole loss of the Intermountain-Adelanto 500-kV DC line, with failure of one of the two Intermountain generators to trip RAS malfunction. MJB 2/2/01 8

10 3.0 CREDIBLE EXCEPTIONS TO THE WSCC RELIABILITY CRITERIA FOR TRANSMISSION SYSTEM PLANNING The following is a list of disturbances found credible by the Reliability Subcommittee but later declared exceptions to the WSCC Reliability Criteria for Transmission system Planning by the Planning Coordination Committee and the Executive Committee. DISTURBANCE D3.1: Palo Verde 500-kV three-phase fault, loss of the Palo Verde- Devers and Palo Verde-North Gila 500-kV lines. DISTURBANCE D3.2: Navajo 500-kV three-phase fault, loss of the Navajo-Moenkopi and Navajo-Westwing 500-kV lines. DISTURBANCE D3.3: Lugo 500-kV three-phase fault, loss of the Lugo-Eldorado and Lugo-Mohave 500 kv lines. DISTURBANCE D3.4: Loss of the Navajo-McCullough and Moenkopi-Eldorado 500- kv lines. MJB 2/2/01 9

11 ATTACHMENT 2 Excerpts from: Western Systems Coordinating Council Reliability Criteria for Transmission System Planning March APPLICATION TO MULTIPLE ELEMENT OUTAGES When experience proves that an outage involving multiple system elements, AC or DC, occurs more than once during the previous three years (sliding three-year scale) and causes (on another system) loss of load or loss of a thermal unit rated greater than 100 MW, then the intent of the Criteria is not achieved. In such event, the owner(s) of the facilities experiencing the disturbance should take the following actions expeditiously: 1. Implement measures to reduce the frequency of occurrence of the disturbance to meet the Criteria, and/or 2. Take steps to reduce the effects of the disturbance; specifically, the owner(s) should make all reasonable efforts to insure that loss of load or loss of a thermal unit rated greater than 100 MW are confined to their own system(s). Historical records of all multiple system element outages are to be maintained by the owners of the facilities experiencing the outages regardless of the effects of the outages. This information is to be made available to other WSCC members upon request. 7.0 APPLICATION TO REMEDIAL ACTION AND SPECIAL CONTROL SCHEMES Remedial Action Schemes (RAS) are allowed as a way to comply with the WSCC Reliability Criteria For Transmission System Planning. If studies show that the RAS failure (i.e., operation when not required or non-operation when required) will result in voltage collapse or cascading, then the RAS failure must be proven to be a non-credible event to the WSCC. Such RAS reliability determinations are made by the WSCC Remedial Action Scheme Reliability Task Force. If RAS failure occurs, the failure is considered credible until the owners of the facilities have demonstrated that the cause of the failure has been corrected and it is no longer credible. The Performance Level associated with accidental RAS operation is the more stringent Performance Level of the following: (1) the disturbance that would correctly initiate RAS operation or (2) the action initiated by the RAS. For example, if the RAS is intended to operate for a double-line outage and the remedial action initiated is the tripping of a single generator, then its accidental operation would be required to meet Performance Level A. However, if the RAS is intended to operate for a double-line outage and the remedial action initiated is the tripping of six lines, then its accidental operation would be required to meet Performance Level C. In general, high-speed control systems, such as MJB 2/2/01 10

12 used in a DC link, DC line, or a Static Var Control system, are not considered to be RAS. However, they are subject to the reliability philosophies contained in these criteria as is any other proposed or existing facility. If a control malfunction does not directly result in removal from service of the controlled facility, it should not expose other systems to loss of load, generation, or equipment damage or line outages. TERMS USED IN THE DISTURBANCE-PERFORMANCE TABLE Three or More Circuits in a Right-of-Way In the application of the Disturbance-Performance Table, this category is intended to cover those situations where the separation between circuits is such that a common mode failure could result in the simultaneous outage of multiple circuits. The credibility of such an outage depends on the credibility of the common mode failure. Considerations in the determination of credibility should include line design; length; location, whether forested, agricultural, mountainous, etc.; outage history; operational guidelines; and separation between circuits. For example, some organizations use separation by more than the span length as adequate to designate the circuits as being in separate corridors. Two Circuits In the application of the Disturbance-Performance Table, this category is intended to cover those situations where a common mode failure could result in the simultaneous loss of two circuits. The credibility of such an outage depends upon the credibility of the common mode failure. The credible outage of two circuits could result from a lightning storm or forest fire. Loss of two circuits does not require the same tower or right-of-way to be credible. Considerations in the determination of credibility should include line design; length; location, whether forested, agricultural, mountainous, etc.; outage history; operational guidelines; and separation between circuits. Common mode failures of substation terminal equipment, such as a breaker failure, are covered under the Bus Section category in the Disturbance-Performance Table. MJB 2/2/01 11

13 ATTACHMENT 3 Detailed Reliability Performance Evaluation of the Exceptions List Facilities MJB 2/2/01 12

14 1. Laramie River fault with loss of 2 circuits WAPA & BEPC Discussion: On the initial data request, both WAPA and Basin Electric had reported on this Exceptions List item. The data submitted were inconsistent and also some key information was missing. Both WAPA and Basin Electric subsequently provided clarifications. Based on the clarifications, there was no countable multi-element outage on the last 10 years. Assumptions: None Performance Evaluation: Facility: Laramie River Station (LRS) Ault, and LRS Story; the lines do not share common corridor Facility Outage Class: More than two elements Criteria Performance Level Specified: C Class Outage Frequency: outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.0 outages/year Criteria Performance Level based on Outage History: C System Impact of Reported Outage(s): Not Applicable Remedial Action: None Recommended Performance Level Adjustment: None Reason for the Recommendation: There were no multi-circuit outages in the facilities in the last ten years. MJB 2/2/01 13

15 4. Taft fault with loss of 2 circuits and RAS failure - BPA Discussion: PBA data clearly shows that there were four multi-element outages in the last 10 years. This results in outage frequency of 0.4 outages/year or MTBF = 2.5 years. The Phase I PBRC Performance Table specifies Level A performance for facilities with outage history grater or equal to 0.33 outages per year. Assumptions: None Performance Evaluation: Facility: Taft-Garrison lines 1 and 2 sharing the common corridor Facility Outage Class: Two elements Criteria Performance Level Specified: C Class Outage Frequency: outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.40 outages/year Criteria Performance Level based on Outage History: A System Impact of Reported Outage(s): No adverse effect Remedial Action: Yes (not armed, would not activate for momentary, no action) Recommended Performance Level Adjustment: none Reason for the Recommendation: The Phase I PBRC Performance Table is not applicable when the facility is equipped with RAS that mitigates the otherwise adverse impact of the disturbances. Furthermore, the RAS worked as designed and no information will be forwarded to the RASRTF for the RAS reliability evaluation. MJB 2/2/01 14

16 5. Navajo fault with loss of 1 circuit with 1 circuit already out & system unadjusted; 10. Navajo fault with loss of 2 circuits; and 12 (a). Navajo fault with loss of 2 circuits 12 (b). Eldorado fault with loss of 2 circuits APS Discussion: There was no multi-circuit outage reported. Assumptions: None Performance Evaluation: Facility: Navajo-Crystal (McCullough) and Navajo-Moenkopi lines (no common corridor), Navajo-Moenkopi and Navajo-Westwing (with common corridor), Navajo- Crystal (McCullough) and Navajo-Moenkopi lines (no common corridor), or Eldorado-Moenkopi and Crystal (McCullough)-Navajo (no common corridor) Facility Outage Class: Two elements (with or without common mode) Criteria Performance Level Specified: C or E Class Outage Frequency: or < outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.00 outages/year Criteria Performance Level based on Outage History: E System Impact of Reported Outage(s): Not Applicable Remedial Action: None Recommended Performance Level Adjustment: none Reason for the Recommendation: There were no multi-circuit outages in the facilities in the last ten years. MJB 2/2/01 15

17 6. Malin fault with loss of 2 circuits and RAS failure PG&E Discussion: PG&E data clearly shows that there were three multi-element outages in the last ten years. The outages frequency is 0.3 outages/year or MTBF = 3.33 years. This indicates a Performance Level C event. Assumptions: None Performance Evaluation: Facility: Malin-Round Mountain lines 1 and 2 sharing the common corridor Facility Outage Class: Two elements Criteria Performance Level Specified: C Class Outage Frequency: outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.30 outages/year Criteria Performance Level based on Outage History: C System Impact: Loss of interconnections Remedial Action of Reported Outage(s): Yes (not armed, no action) Recommended Performance Level Adjustment: none Reason for the Recommendation: The Phase I PBRC Performance Table is not applicable when the facility is equipped with RAS that mitigates the otherwise adverse impact of the disturbances. Furthermore, the RAS worked as designed and no information will be forwarded to the RASRTF for the RAS reliability evaluation. MJB 2/2/01 16

18 7. Ingledow fault with loss of 2 circuits and RAS failure - BCH Discussion: There was no multi-circuit outage reported. Assumptions: None Performance Evaluation: Facility: Ingledow-Custer line 1 and 2 sharing common corridor Facility Outage Class: Two elements Criteria Performance Level Specified: C Class Outage Frequency: outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.00 outages/year Criteria Performance Level based on Outage History: E System Impact of Reported Outage(s): Not applicable Remedial Action: Yes (not armed, would not activate for momentary, no action) Recommended Performance Level Adjustment: none Reason for the Recommendation: The Phase I PBRC Performance Table is not applicable when the facility is equipped with RAS that mitigates the otherwise adverse impact of the disturbances. Furthermore, the RAS worked as designed and no information will be forwarded to the RASRTF for the RAS reliability evaluation. (The reason that there were no multi-circuit outages in the last ten years in the facility provides additional support to the recommendation.) MJB 2/2/01 17

19 8. Intermountain Power Project (IPP) Bipole outage with RAS failure - LADWP Discussion: There was one bipole (multi-circuit) outage reported. Assumptions: None Performance Evaluation: Facility: IPP bipole pole 1 and 2 sharing common corridor (tower) Facility Outage Class: Two elements Criteria Performance Level Specified: C Class Outage Frequency: outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.10 outages/year Criteria Performance Level based on Outage History: C System Impact of Reported Outage(s): No adverse effect Remedial Action: Yes (was armed and activated correctly and tripped an IPP unit) Recommended Performance Level Adjustment: none Reason for the Recommendation: The Phase I PBRC Performance Table is not applicable when the facility is equipped with RAS that mitigates the otherwise adverse impact of the disturbances. Furthermore, the RAS worked as designed and no information will be forwarded to the RASRTF for the RAS reliability evaluation. MJB 2/2/01 18

20 9. Palo Verde fault with loss of 2 circuits - APS Discussion: There was no multi-circuit outage reported. Assumptions: None Performance Evaluation: Facility: Palo Verde-Davers and Palo Verde-North Gila lines (no common corridor) Facility Outage Class: Two elements (with or without common mode) Criteria Performance Level Specified: C or E Class Outage Frequency: or < outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.00 outages/year Criteria Performance Level based on Outage History: E System Impact of Reported Outage(s): Not applicable Remedial Action: None Recommended Performance Level Adjustment: none Reason for the Recommendation: There were no multi-circuit outages in the facility in the ten years evaluation period. MJB 2/2/01 19

21 11. Lugo fault with loss of 2 circuit - SCE Discussion: In the initial data request, SCE had reported data on five multi-circuit corridor facilities and several lines with line crossing exposures. Three of the multicircuit corridors from Lugo are 500 kv systems. One multi-element outage on each of these three different 500 kv corridors were reported. According to the original 10 year data, the frequency of multi-element outage on each of the three corridors is 1 in 10 years (i.e., f = 0.1 outage/year or MTBF of 1 in 10 years). Additional clarifications were subsequently provided by SCE where they recommended to disregard all other data and only to consider the corridor outage data of Lugo-Eldorado and Lugo-Mojave lines. There is no RAS consideration with this facility. The Lugo-Eldorado and Lugo-Mojave outage event resulted in loss of load. Assumptions: None Performance Evaluation: Facility: Lugo-Eldorado and Lugo-Mohave lines (sharing the same corridor) Facility Outage Class: Two elements Criteria Performance Level Specified: C Class Outage Frequency: outages/year Criteria Performance Level Granted: E or higher (Exceptions List) Historical Performance: 0.10 outages/year Criteria Performance Level based on Outage History: C System Impact of Reported Outage(s): Loss of load Remedial Action: None Recommended Performance Level Adjustment: None Reason for the Recommendation: According to the RPEWG Evaluation Guideline, the following issues are taking into consideration: (1) One event does not constitute statistically significant event, thus it is not used in the reliability performance determination of a facility. (2) The impact of the event did not result in cascading outage, thus does not warrant RS review of the impact. Mo Beshir MJB 2/2/01 20

22 February 2, 2001 MJB 2/2/01 21

Board of Directors. H:\Dept\Sec\Pcc\2013\Seven_Step_Process Web URL:

Board of Directors. H:\Dept\Sec\Pcc\2013\Seven_Step_Process Web URL: Document name Category Seven Step Process for Performance Category Upgrade Request ( ) Regional reliability standard ( ) Regional criteria ( ) Policy (X) Guideline () Report or other ( ) Charter Document

More information

Standard TPL-004-0a System Performance Following Extreme BES Events

Standard TPL-004-0a System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-0a 3. Purpose: System simulations

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements Page 220 of 257 A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments

More information

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements A. Introduction 1. Title: System Performance Following Loss of Two or More Bulk Electric System (Category C) 2. Number: TPL-003-0b 3. Purpose: System simulations and associated assessments are needed periodically

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Standard TPL (i) System Performance Under Normal Conditions

Standard TPL (i) System Performance Under Normal Conditions Standard TPL-001-0.1(i) System Performance Under rmal Conditions A. Introduction 1. Title: System Performance Under rmal ( Contingency) Conditions (Category A) 2. Number: TPL-001-0.1(i) 3. Purpose: System

More information

WECC Standard PRC-STD Transmission Maintenance

WECC Standard PRC-STD Transmission Maintenance A. Introduction 1. Title: Transmission Maintenance 2. Number: PRC-STD-005-1 3. Purpose: Regional Reliability Standard to ensure the Transmission Operator or Owner of a transmission path identified in Attachment

More information

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Standard TPL-002-0b System Performance Following Loss of a Single BES Element A. Introduction 1. Title: System Performance Following Loss of a Single Bulk Electric System Element (Category B) 2. Number: TPL-002-0b 3. Purpose: System simulations and associated assessments are needed

More information

Standard TPL System Performance Following Extreme BES Events

Standard TPL System Performance Following Extreme BES Events A. Introduction 1. Title: System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D) 2. Number: TPL-004-1 3. Purpose: System simulations

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project WECC 2011 Annual Progress Report Submitted by SouthWestern Power Group February 25, 2011 Table of Contents I. Introduction -----------------------------------------------------------

More information

TPL 001 AB 0 System Performance Under Normal Conditions

TPL 001 AB 0 System Performance Under Normal Conditions Alberta Reliability Standard System Performance Under rmal Conditions TPL-001-AB-0 TPL 001 AB 0 System Performance Under rmal Conditions 1. Purpose The purpose of this reliability standard is to ensure

More information

Assess Transmission Future Needs Standard Drafting Team. August 6, Conference Call Notes

Assess Transmission Future Needs Standard Drafting Team. August 6, Conference Call Notes Assess Transmission Future Needs Standard Drafting Team 1. Administrative Items a. Introductions and Quorum August 6, 2007 Conference Call Notes John Odom, Chair, brought the call to order at noon on August

More information

Standard TPL System Performance Under Normal Conditions

Standard TPL System Performance Under Normal Conditions Standard TPL-001-0.1 System Performance Under rmal Conditions Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities These definitions will be posted and balloted along with the standard, but will not be restated in the standard. Instead, they will be included in a separate Definitions section containing definitions

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998

Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 Western Electricity Coordinating Council Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 VOLTAGE STABILITY CRITERIA, UNDERVOLTAGE

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed:

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated

July 15 July 31. August First ballot September 1 10, Drafting Team considers comments and makes any revisions indicated Standard FAC-008-1 Facility Ratings Methodology Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS Draft 7/15/14 rev7 1 B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS A. Reliability Rule NYCA transmission facilities in the NYS Bulk Power System shall be planned to operate reliably over a

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

DOCUMENT A-11 DU NPCC

DOCUMENT A-11 DU NPCC Requête R-3498-2002 DOCUMENT A-11 DU NPCC Original : 2003-02-12 HQT-8, Document 2 (en liasse) Document A-11 1515 BROADWAY, NEW YORK, NY 10036-8901 TELEPHONE: (212) 840-1070 FAX: (212) 302-2782 Special

More information

Standard FAC System Operating Limits Methodology for the Planning Horizon

Standard FAC System Operating Limits Methodology for the Planning Horizon Standard FAC-010-1 System Operating Limits Methodology for the Planning Horizon Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will

More information

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS APPENDIX G AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS Transmission Planning Criteria - Basis and Assumptions Version 1.0 1. Introduction This document presents the reliability standards,

More information

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO. Table of Contents Purpose... 1 Applicable Reliability Standard(s)... 1 Applicability to California ISO... 1 SOLs and IROLs... 1 Study Methodology... 2 Supporting Information... 6 Responsibilities... 6

More information

Load Shed Philosophy

Load Shed Philosophy APPLICABILITY: Reliability Coordinator I. Background While time limits exist for mitigation of the exceedance of certain types of system operating limits, events can occur quickly necessitating a responsive

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Security Guideline for the Electricity Sector: Identifying Critical Assets

Security Guideline for the Electricity Sector: Identifying Critical Assets Note: The guideline was developed for CIP-002-1 but is also applicable to CIP- 002-2 and CIP-002-3. Security Guideline for the Electricity Sector: Identifying Critical Assets Disclaimer: This supporting

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Overview of Common Mode Outages In Power Systems

Overview of Common Mode Outages In Power Systems Overview of Common Mode Outages In Power Systems Paper Prepared by Task Force of RRPA Subcommittee Presented by Chanan Singh Texas A&M University Defintions A common mode outage refers to simultaneous

More information

FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting

FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting FRCC - PROC - RC PRC-003 FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting Effective Date: December 2, 2010 Revisions Rev. No. Date Description Developed by: Approved

More information

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation Transmission System Planning Methodology, Criteria and Process Business Practice December 07, 2007 Table of Contents

More information

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite

More information

March 3, Submitted to: CAISO

March 3, Submitted to: CAISO March 3, 2016 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2015-2016 TRANSMISSION PLANNING

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating

Approved RMWG Discussion was held. ??? John Simpson need to assign SMART rating ALR1-1 Generator Reactive Limit Metric:Voltage schedules How many times did generators encounter var limits associated with holding voltage schedule. 10 3 2 1 1 3 1 Initial pilot effort completed, reaching

More information

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING Operating Policies and Procedures Reporting OPP 1304 Issued: 2016-08-30 Supersedes: 2007-12-03 1. Purpose 1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING To establish processes for reporting AIES

More information

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING

1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING Operating Policies and Procedures Reporting OPP 1304 Issued: 2016-08-30 Supersedes: 2007-12-03 1. Purpose 1304 SYSTEM EVENT MONITORING AND DISTURBANCE REPORTING To establish processes for reporting AIES

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

FRCC - PROC - RC - EOP-004. FRCC Disturbance Reporting Procedure

FRCC - PROC - RC - EOP-004. FRCC Disturbance Reporting Procedure FRCC - PROC - RC - EOP-004 FRCC Disturbance Reporting Procedure Revisions Rev. No. Date Description Developed by: Approved by: 1 September 2, 2009 Conversion of RRO Legacy document FRCC Disturbance Reporting

More information

Proposed Resource Loss Protection Criteria

Proposed Resource Loss Protection Criteria Proposed Resource Loss Protection Criteria Background and Current Methodologies The Resource Loss Protection Criteria (RLPC) is the respective Interconnection design resource loss in MW, which is used

More information

TTC/ATC 1.0 DEFINITIONS

TTC/ATC 1.0 DEFINITIONS TTC/ATC In this section: Definitions Total Transfer Capability (TTC) Methodology Available Transmission Transfer Capability (ATC) Calculation Counterflow ATC Release of Unused Transmission in Pre- schedule

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

2015 Operational Practices Survey Questions

2015 Operational Practices Survey Questions 2015 Operational Practices Survey Questions This document of survey questions has been provided as a courtesy. It is not the actual survey, which will be completed electronically and only by a designated

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. NEW HARQUAHALA ) Docket No. RC GENERATING COMPANY, LLC )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. NEW HARQUAHALA ) Docket No. RC GENERATING COMPANY, LLC ) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION NEW HARQUAHALA ) Docket No. RC08-4-002 GENERATING COMPANY, LLC ) COMPLIANCE FILING OF THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION

More information

CAISO View of Smart Grid

CAISO View of Smart Grid CAISO View of Smart Grid David Hawkins Lead Renewables Power Engineer March 17, 2010 Slide 2 Slide 2 1 Generation Grid Operators View Leverage smart grid policies to: Increase demand-side participation

More information

Reliability Standard Audit Worksheet 1

Reliability Standard Audit Worksheet 1 Reliability Standard Audit Worksheet 1 TOP-009-1 Knowledge of Composite Protection Systems and Remedial Action Schemes and Their Effects This section to be completed by the Compliance Enforcement Authority.

More information

INTERPRETATION REQUEST FORM

INTERPRETATION REQUEST FORM INTERPRETATION REQUEST FORM When completed, email this form to: laura.hussey@nerc.net For questions about this form or for assistance in completing the form, call Laura Hussey at 404-446-2579. Note: A

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic Load shedding (UFLS) to support

More information

The RMATS footprint covers the States of Colorado, Idaho, Montana, Utah and Wyoming.

The RMATS footprint covers the States of Colorado, Idaho, Montana, Utah and Wyoming. On August 22, 2003, Wyoming Governor Dave Freudenthal and Utah Governor Michael Leavitt announced the formation of the Rocky Mountain Area Transmission Study (RMATS). They did so because the electric power

More information

by the Transmission Planner or Planning Coordinator.

by the Transmission Planner or Planning Coordinator. A. Introduction 1. Title: Undervoltage Load Shedding 2. Number: PRC 010 2 3. Purpose: To establish an integrated and coordinated approach to the design, evaluation, and reliable operation of Undervoltage

More information

PRC Under Voltage Load Shedding

PRC Under Voltage Load Shedding A. Introduction 1. Title: Undervoltage Load Shedding 2. Number: PRC-010-2 3. Purpose: To establish an integrated and coordinated approach to the design, evaluation, and reliable operation of Undervoltage

More information

Technical Report Supporting Definition of Adequate Level of Reliability

Technical Report Supporting Definition of Adequate Level of Reliability Technical Report Supporting Definition of Adequate Level of Reliability 1.0 Introduction The Adequate Level of Reliability Task Force (ALRTF or Task Force) was formed in May 2011 under the auspices of

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

Definition of Adequate Level of Reliability. Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET

Definition of Adequate Level of Reliability. Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET Definition of Adequate Level of Reliability Industry Webinar May 23, 2012, 1:00-3:00 p.m. ET Outline Background Definition and Reliability Objectives Supporting Documents Industry Feedback Next Steps Questions

More information

Definition of Adequate Level of Reliability

Definition of Adequate Level of Reliability Definition approved by Operating Committee and Planning Committee at their December 2007 OC and PC meetings Definition of Adequate Level of Reliability 116-390 Village Boulevard, Princeton, New Jersey

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

Overview of Issues at the Western Electricity Coordinating Council (WECC)

Overview of Issues at the Western Electricity Coordinating Council (WECC) energy strategies Overview of Issues at the Western Electricity Coordinating Council (WECC) Focusing on those Issues Impacting Independent Generators Presented to The California Independent Energy Producers

More information

Peak West-wide System Model Validation Activities

Peak West-wide System Model Validation Activities Peak West-wide System Model Validation Activities 10/24/2016 Brett Wangen Hongming Zhang Gareth Lim Purpose of This Discussion Provide West-wide System Model (WSM) overview Give insight into ongoing model

More information

Note This form is to comment on Version 2 of the Assess Transmission Future Needs and Develop Transmission Plans SAR.

Note This form is to comment on Version 2 of the Assess Transmission Future Needs and Develop Transmission Plans SAR. Transmission Plans SAR (2 nd Posting) te This form is to comment on Version 2 of the Assess Transmission Future Needs and Develop Transmission Plans SAR. The latest version of this SAR (TRNS_NDS_&_PLNS_01_02)

More information

Meeting Agenda Adequate Level of Reliability Task Force

Meeting Agenda Adequate Level of Reliability Task Force Meeting Agenda Adequate Level of Reliability Task Force June 28, 2012 8:00 a.m. to 3:00 p.m. ET APPA Offices (in the Universal North Building) 1875 Connecticut Avenue NW 12th Floor Main Conference Room

More information

ERO Reliability Performance Update

ERO Reliability Performance Update ERO Reliability Performance Update Sam Chanoski, NERC Director of Situation Awareness and Event Analysis Fall 2017 NPCC Compliance and Standards Workshop November 9, 2017 Daily Severity Risk Index 2 RELIABILITY

More information

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013 NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:

More information

SPP RTO Compliance Forum TPL Jason Terhune

SPP RTO Compliance Forum TPL Jason Terhune SPP RTO Compliance Forum TPL-001-4 Jason Terhune 501-688-8261 jterhune@spp.org 1 TPL Standards have been Consolidated TPL-001-0.1 TPL-002-0b TPL-003-0b TPL-004-0a TPL-001-4 R1 R2 R3 R4 R5 R6 R7 R8 2 Overview

More information

Stakeholder Comments. 2012/2013 Transmission Planning Process. Presentations from December 11 and 12 meetings

Stakeholder Comments. 2012/2013 Transmission Planning Process. Presentations from December 11 and 12 meetings Stakeholder Comments 2012/2013 Transmission Planning Process Presentations from December 11 and 12 meetings Submitted by Company Date Submitted Karen Shea Garry Chinn Rabiindra Kiran Southern California

More information

May 5, Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

May 5, Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 May 5, 2008 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 RE: Definition of Adequate Level of Reliability Dear Secretary Bose: The

More information

Conceptual Statewide Transmission Plan Update. California ISO Regional Transmission Planning Process.

Conceptual Statewide Transmission Plan Update. California ISO Regional Transmission Planning Process. 2014-2015 Conceptual Statewide Transmission Plan Update California ISO 2015-2016 Regional ning Process August 31, 2015 Prepared by Market & Infrastructure Development California Independent System Operator

More information

Mapping Document for FAC-010-3

Mapping Document for FAC-010-3 Mapping Document for FAC-010-3 The Project 2015 09 standard drafting team (SDT) is proposing the retirement of the NERC FAC 010 3 Reliability Standard. The SDT further proposes a new paradigm regarding

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

October 6, Submitted to: CAISO

October 6, Submitted to: CAISO October 6, 2017 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2017-2018 TRANSMISSION

More information

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0

Western Interconnection Seasonal Operations Planning Coordination Process Rev. 3.0 Western Interconnection Seasonal Operations Planning Rev. 3.0 Issued March 26, 2019 Effective May 1, 2019 PEAK RELIABILITY RELIABILITY COORDINATION 7600 NE 41 st STREET SUITE 201 VANCOUVER WASHINGTON 98662-6772

More information

WECC Board of Directors. Standards. Approved Regional Criteria (if any) NA. Final. Final

WECC Board of Directors. Standards. Approved Regional Criteria (if any) NA. Final. Final Document name Category Document date Adopted/approved by Date adopted/approved Custodian (entity responsible for maintenance and upkeep) Stored/filed Previous name/number Analysis, Reporting, and Mitigation

More information

Interconnection Feasibility Study

Interconnection Feasibility Study XXXXX Campbell River Power Enterprises Project April 5, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2011. All rights reserved. DISCLAIMER OF WARRANTY, LIMITATION

More information

GUIDE. Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria PUBLIC

GUIDE. Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria PUBLIC PUBLIC IESO_GDE_0364 GUIDE Market Manual 11: Reliability Compliance Part 11.1: Applicability Criteria for Compliance with NERC Reliability Standards and NPCC Criteria Issue 6.0 Public Disclaimer The posting

More information

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements 2. Number: PRC 006 RFC 01 3. Purpose: To establish ReliabilityFirst requirements for automatic underfrequency Load shedding

More information

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004 Glossary of Terms Used in Standards Preliminary Draft Version 0 Standards September 1, 2004 Source References (Noted in draft only will not be part of final glossary) Functional Model () Glossary (GL)

More information

EAPP interconnection readiness workshop

EAPP interconnection readiness workshop 1 EAPP interconnection readiness workshop Self-Assessment for EAPP/IC -Compliance Rwandan-Grid Gap Analysis & Proposed mitigations GENERATION, TRANSMISSION & DISTRIBUTION 01 st October, 2018 INTRODUCTION

More information

Distribution System Operating Code

Distribution System Operating Code Distribution System Operating Code Draft Rev 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System

More information

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION Operating Policies and Procedures Emergency System Operations OPP 804 Issued:2008-11-13 Supersedes Interim OPP Effective:2008-05-01 804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION 1. Purpose To

More information

DECISIONS on operating transfer limits and transmission

DECISIONS on operating transfer limits and transmission 1144 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 2, MAY 2004 Hydro Turbine-Governor Model Validation in Pacific Northwest Dmitry Kosterev Abstract This paper presents an approach for generator model

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent

More information

Limon 100 MW Wind Farm System Interconnection Study

Limon 100 MW Wind Farm System Interconnection Study Limon 100 MW Wind Farm System Interconnection Study October 27, 2004 Studies Conducted By: Garrett Durland Limon Wind Farm Impact Study I. Introduction In April 2004, Western Area Power Administration

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Stanly County, NC Total Output Requested By Customer: 30 MW Commercial Operation Date Requested By Customer: 12/1/2019 Feasibility

More information

2020 Local Capacity Area Technical Study. Final

2020 Local Capacity Area Technical Study. Final 2020 Local Capacity Area Technical Study Final November 23, 2018 2020 Local Capacity Area Technical Study Manual Table of Contents INTRODUCTION... 3 STUDY OBJECTIVES... 4 TECHNICAL STUDY ASSESSMENT AND

More information

Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results

Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results Written comments with CAISO reply Submitted after the April 10 Stakeholder Meeting regarding the 2009 Local Capacity Requirement (LCR) Results COMMENTS OF THE ALLIANCE FOR RETAIL ENERGY MARKETS ON THE

More information

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects System Protection Subgroup For any substation facility included in the scope of a transmission

More information

FirstEnergy Verification Team. Report on the Implementation of Recommendations from the FirstEnergy Readiness Audit of February 26 27, 2004

FirstEnergy Verification Team. Report on the Implementation of Recommendations from the FirstEnergy Readiness Audit of February 26 27, 2004 FirstEnergy Verification Team Report on the Implementation of Recommendations from the FirstEnergy Readiness Audit of February 26 27, 2004 June 22 23, 2005 North American Electric Reliability Council Table

More information

2020 Local Capacity Area Technical Study. Draft

2020 Local Capacity Area Technical Study. Draft 2020 Local Capacity Area Technical Study Draft October 23, 2018 2020 Local Capacity Area Technical Study Manual Table of Contents INTRODUCTION... 3 STUDY OBJECTIVES... 4 TECHNICAL STUDY ASSESSMENT AND

More information

Performance Standards Issues. Donald Lamontagne Principal Engineer Arizona Public Service

Performance Standards Issues. Donald Lamontagne Principal Engineer Arizona Public Service Performance Standards Issues Donald Lamontagne Principal Engineer Arizona Public Service Free Template from www.brainybetty.com 2 Regulatory Entities FERC Energy Policy Act of 2005 NERC Designated Electric

More information