IDAHO ARENA CM/GC Presubmittal Conference April 11, 2017

Size: px
Start display at page:

Download "IDAHO ARENA CM/GC Presubmittal Conference April 11, 2017"

Transcription

1

2 Background / History 1969 Athletic Study

3 Background / History 1970 Concept Construct Open Air Football Stadium Construct North Towers of New Basketball Pavilion

4 Background / History 1972 Pavilion Plans Law Building Events Pavilion ASUI Kibbie Activity Center

5 Background / History 1972 Pavilion Plans

6 Background / History 1972 Pavilion Plans

7 Background / History 1995 SRASE Master Plan

8 Background / History 2006 Master Plan

9 Wood Structural Heritage Kibbie Dome

10 Wood Structural Heritage Kibbie Dome

11 Wood Structural Heritage Student Recreation Center

12 Wood Products - Potential Gifts-In-Kind / Donated Material

13 Anticipated Project Schedule UI Board of Regents Approval to Proceed with Design: February 15, 2017 Architectural / Engineering Team Selection By: May 15, 2017 Construction Manager / General Contractor Selection By: May 30, 2017 Start of Programming & Design: June 2017 * Start of Construction: June 2018 * Substantial Completion / Certificate of Occupancy: July 2020 * Project schedule to be developed in detail with input from selected A/E Team and CM/GC Team

14 Anticipated Project Budget $30-million Total. To Include Design, Fees, Contingencies, etc * The University has current Board of Regents authorization to expend $3-million for programming and design. Additional Regents authorization to proceed with bidding and construction will be sought at some point after Design Development and Cost Confirmation process. Project budget to be developed in in coordination with selected A/E Team and CM/GC Team

15 Project Site Approximate Arena Location

16 Site Impacts Vehicular Must keep Stadium Drive open May be possible to close this section of Idaho Ave. Approximate Arena Location Must maintain fulltime access to Vandal Athletic Center / Kibbie East side Must maintain emergency / delivery access around Kibbie Dome

17 Site Impacts Pedestrian Heavily used pedestrian access from Lot 34 student parking to center of campus Approximate Arena Location Heavily used pedestrian access from Living Halls to Kibbie / Vandal Athletic Center

18 Site Impacts Parking Must maintain use of Lot 34 & 57 for duration of construction Must maintain use of Law Building parking lot for duration of construction Approximate Arena Location Maintain use and access to East Kibbie Services and Parking

19 Site Impacts Construction Staging Potential staging & delivery area in gravel RV Parking. Not available on Football weekends CM/GC will have use of entire north lawn area Approximate Arena Location Potential staging & delivery area gravel Lot 57. Not available on Football weekends

20 Site Impacts Utilities: Water Existing 12 PVC Domestic Water Main Existing reclaimed water (irrigation) main. Will need to be relocated. Existing parallel domestic water distribution mains

21 Site Impacts Utilities: Electrical & Data Existing main campus / west campus fiber pathway and fiber. Likely to require relocation Existing 13.2 kva Switchgear Existing 13.2kVA underground electrical distribution and switchgear Existing campus fiber pathway and fiber

22 Site Impacts Utilities: Sanitary Sewer Existing Kibbie sewer lines are above level of new arena and not sized to accommodate load. May be required to run new sanitary sewer line down Stadium Drive to Sixth Street Approximate Arena Location

23 Site Impacts Utilities: Central Campus Steam & Chilled Water Potential Option #1 Standalone Boiler / Chiller systems at New Arena. Potential Option #2 Extend existing utilidor and services from Law Building to New Arena. Potential Option #3 Extend full steam tunnel from Memorial Gym (to the east) to Kibbie and New Arena. Complete chilled water loop to both Kibbie Dome and New Arena. Approximate Arena Location Existing Chilled Water Distribution System

24 Site Impacts Potential Slope Stabilization Approximate Arena Location Potential soils stabilization issues on the north Kibbie slope will require attention and investigation depending on New Arena location and proximity to slope.

25 QUESTIONS?

West Campus Utilities Distribution Systems and Infrastructure Improvements / Expansion

West Campus Utilities Distribution Systems and Infrastructure Improvements / Expansion Request for Qualifications Engineering Services Programming, Planning & Design Phase Architectural & Engineering Services West Campus Utilities Distribution Systems and Infrastructure Improvements / Expansion

More information

FACILITY DESIGN PLAN

FACILITY DESIGN PLAN FACILITY DESIGN PLAN Sports Performance Enhancement Facility Arena and Outdoor Track and Soccer Complex Introduction: THE UNIVERSITY OF SOUTH DAKOTA The Facility Program Plan for the Sports Performance

More information

MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011

MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011 MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011 The Building Committee for the SDSU Central Heating Plant Boiler Replacement and Plant Upgrades met

More information

REQUEST FOR QUALIFICATIONS/PROPOSALS. For CONSTRUCTION MANAGER / GENERAL CONTRACTOR SERVICES. Idaho Arena. University of Idaho Moscow, Idaho

REQUEST FOR QUALIFICATIONS/PROPOSALS. For CONSTRUCTION MANAGER / GENERAL CONTRACTOR SERVICES. Idaho Arena. University of Idaho Moscow, Idaho REQUEST FOR QUALIFICATIONS/PROPOSALS For CONSTRUCTION MANAGER / GENERAL CONTRACTOR SERVICES Idaho Arena University of Idaho Moscow, Idaho March 27, 2017 UI PN CP170040 For additional information contact:

More information

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY

FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY FACILITY DESIGN PLAN FOR INDOOR PRACTICE AND HUMAN PERFORMANCE FACILITY SOUTH DAKOTA STATE UNIVERSITY DATE: November 20, 2012 SDSU requests approval of this Facility Design Plan to continue planning the

More information

BOARD OF TRUSTEES OCTOBER 13, 2014

BOARD OF TRUSTEES OCTOBER 13, 2014 Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 Y DATE: December 6-8, 2016 ****************************************************************************** SUBJECT: SDSU Student Wellness

More information

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017 Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.

More information

DEL MAR COLLEGE Capital Improvement Program for Proposed Southside Campus. Prepared by;

DEL MAR COLLEGE Capital Improvement Program for Proposed Southside Campus. Prepared by; DEL COLLEGE 2016 Capital Improvement Program for Proposed Southside Campus Prepared by; DEL COLLEGE 2016 Capital Improvement Program for Proposed Southside Campus GENSLER, UST 2, 2016 EXECUTIVE SUMY After

More information

Session: Date: Thursday, October 2, :00 am 11:00 am

Session: Date: Thursday, October 2, :00 am 11:00 am Session: 100205 Date: Thursday, October 2, 2014 Time: 10:00 am 11:00 am Serving a New Medical District The Utility Plant Challenge Presented by: Juan Ontiveros Executive Director Utilities and Energy Management

More information

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements

More information

Utilities Infrastructure Master Plan UK JANUARY 2016 FINAL DRAFT

Utilities Infrastructure Master Plan UK JANUARY 2016 FINAL DRAFT FINAL DRAFT Utilities Infrastructure Master Plan UK-1553-15 JANUARY 2016 Executive Summary Please contact Jeff Zumwalt (jeff.zumwalt@uky.edu) for more information 1. EXECUTIVE SUMMARY 1.1 Goals and Objectives

More information

UNIVERSITY OF COLORADO DENVER Anschutz Medical Campus. PROGRAM PLAN AND BUDGET FOR ENERGY EFFICINCY and SUSTAINABLILITY

UNIVERSITY OF COLORADO DENVER Anschutz Medical Campus. PROGRAM PLAN AND BUDGET FOR ENERGY EFFICINCY and SUSTAINABLILITY UNIVERSITY OF COLORADO DENVER Anschutz Medical Campus PROGRAM PLAN AND BUDGET FOR ENERGY EFFICINCY and SUSTAINABLILITY R1 North Tower Energy Savings Project FUNDING YEAR 2013-2014 August 12, 2013 i ACKNOWLEDGMENTS

More information

ECU Comprehensive Master Plan April 7, :00-12:30 01 PROJECT NAME DATE TIME MEETING NO. Kick Off meeting with Infrastructure Group

ECU Comprehensive Master Plan April 7, :00-12:30 01 PROJECT NAME DATE TIME MEETING NO. Kick Off meeting with Infrastructure Group ECU Comprehensive Master Plan April 7, 2009 11:00-12:30 01 PROJECT NAME DATE TIME MEETING NO. ECU Mendenhall #254 - MEETING LOCATION PROJECT NUMBER Brian Mitchell Kick Off meeting with Infrastructure Group

More information

Welcome Center, New Student Services, and Career and Employment Services

Welcome Center, New Student Services, and Career and Employment Services Architectural Program Welcome Center, New Student Services, and Career and Employment Services East Memorial Stadium Renovation May 2014 Prepared By Table of Contents Introduction.... 1 Competitive Market....

More information

Campus Energy Plant Tufts University

Campus Energy Plant Tufts University IDEA CampusEnergy2017 Combined Heat and Power to Provide Energy Efficiency to Medium Size Campus February 20-24, 2017 Campus Energy Plant Tufts University Overview Presentation Overview: Campus Introduction

More information

Appendix VI-A-3 Infrastructure Inventory

Appendix VI-A-3 Infrastructure Inventory Pennsylvania State System of Higher Education Facilities Manual Appendix VI-A-3 Infrastructure Inventory Form Format and Definitions Figure Column Headings Infrastructure means the communications, utility,

More information

APSU PROJECT REPORT. Client. Athletics REMAINING BUDGET STATUS. Client. Athletics

APSU PROJECT REPORT. Client. Athletics REMAINING BUDGET STATUS. Client. Athletics APSU PROJECT REPORT 373/003112018 Softball Field Improvements Athletics Rufus Johnson Installation of new foundation, ADA compliant stands and press box for the softball field. CONTRACTED PAID 01Approval\Planning

More information

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017 SDSU requests approval of this Facility Design Plan for renovation and addition to Harding

More information

Phone Joan Daniels. Line # Item Number Item/Description Category Co Item UOM Contract Price

Phone Joan Daniels. Line # Item Number Item/Description Category Co Item UOM Contract Price 1 of 12 1 000000000000031501 Construction Manager Services 81101513 EA 1.00 2 000000000000032537 CMH Roofing Restoration 81101513 EA 1.00 3 000000000000032538 CMH Wall Renovations 81101513 EA 1.00 4 000000000000032539

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 X DATE: December 6-8, 2016 ****************************************************************************** SUBJECT: South Dakota State University

More information

REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES

REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES REQUEST FOR ARCHITECTURAL & ENGINEERING DESIGN SERVICES CHILDREN S CENTER October 2008 Project No. 08L1J TABLE OF CONTENTS PAGE Background and Purpose... 1 Project Scope and Description... 1 Scope of Services...

More information

UNIVERSITY OF SOUTH ALABAMA 2015 UTILITIES MASTER PLAN SUMMARY REPORT

UNIVERSITY OF SOUTH ALABAMA 2015 UTILITIES MASTER PLAN SUMMARY REPORT UNIVERSITY OF SOUTH ALABAMA 2015 UTILITIES MASTER PLAN SUMMARY REPORT August 2015 Prepared by: Krebs Engineering, Inc. 2100 River Haven Drive, Suite 100 Birmingham, AL 35244 www.krebseng.com Page 1 TABLE

More information

Auburn University Construction Project Update March 2010

Auburn University Construction Project Update March 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena is currently 91% complete. Contract completion is July 25, 2010, but the project is on schedule to complete by May 2010. Interior finish

More information

BOARD OF REGENTS AGENDA ITEM 14 STATE OF IOWA APRIL 29-30, 2009 REGISTER OF UNIVERSITY OF IOWA CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS

BOARD OF REGENTS AGENDA ITEM 14 STATE OF IOWA APRIL 29-30, 2009 REGISTER OF UNIVERSITY OF IOWA CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS BOARD OF REGENTS AGENDA ITEM 14 STATE OF IOWA APRIL 29-30, 2009 Contact: Sheila Doyle REGISTER OF UNIVERSITY OF IOWA CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS Actions Requested: Consider approval of: 1.

More information

DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES. David Payne, P.E Interim Associate Director October 16, 2012

DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES. David Payne, P.E Interim Associate Director October 16, 2012 DIVISION OF ADMINISTRATION UTILITIES & ENERGY SERVICES David Payne, P.E Interim Associate Director October 16, 2012 Agenda - Production System Overview - Distributions Systems Overview - Recently Completed

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 6 O DATE: December 5-7, 2017 ****************************************************************************** SUBJECT USD Dakota Dome Renovation

More information

Texas State University System Telephonic Called Board of Regents Meeting

Texas State University System Telephonic Called Board of Regents Meeting Texas State University System Telephonic Called Board of Regents Meeting Monday, April 6, 2015 2:00 PM 1. Call Meeting to Order 2. Agenda Items 1. SHSU: Design Development Documents for South Dining...

More information

REQUEST FOR ARCHITECTURAL AND ENGINEERING DESIGN SERVICES DRUMLIN DINING HALL RENOVATION. University of Wisconsin-Whitewater.

REQUEST FOR ARCHITECTURAL AND ENGINEERING DESIGN SERVICES DRUMLIN DINING HALL RENOVATION. University of Wisconsin-Whitewater. REQUEST FOR ARCHITECTURAL AND ENGINEERING DESIGN SERVICES DRUMLIN DINING HALL RENOVATION University of Wisconsin-Whitewater March 2008 Project No. 08B21 TABLE OF CONTENTS PAGE Table of Contents... 2 Project

More information

STANFORD UNIVERSITY MEDICAL CENTER FACILITIES RENEWAL AND REPLACEMENT PROJECT UTILITIES AND SERVICES

STANFORD UNIVERSITY MEDICAL CENTER FACILITIES RENEWAL AND REPLACEMENT PROJECT UTILITIES AND SERVICES Revised 3/10 STANFORD UNIVERSITY MEDICAL CENTER FACILITIES RENEWAL AND REPLACEMENT PROJECT UTILITIES AND SERVICES This section contains the preliminary information for utility services to the following

More information

Project Information. Nominations of Artists. University of Houston

Project Information. Nominations of Artists. University of Houston UNIVERSITY OF HOUSTON SYSTEM SYSTEM WIDE ART ACQUISTION COMMITTEE AGENDA ITEM ITEM: UH University Center Transformation Project Artwork-Artists Nominations DATE PREVIOUSLY SUBMITTED: NA SUMMARY: Nominations

More information

Auburn University Construction Project Update June 2010

Auburn University Construction Project Update June 2010 New Basketball Arena: Construction Cost: $68.5 million. The Arena achieved the Substantial Completion project milestone as of June 4 th, 2010. Punch list item work is ongoing. Work related to the project,

More information

North Carolina State University Harrelson Hall Demolition. American Council of Engineering Companies of North Carolina. Engineering Excellence Awards

North Carolina State University Harrelson Hall Demolition. American Council of Engineering Companies of North Carolina. Engineering Excellence Awards American Council of Engineering Companies of North Carolina 2019 Submitted by: October 2018 Project Summary Harrelson Hall was a four-story reinforced concrete structure located in the central part of

More information

Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through June 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 I DATE: May 9-11, 2017 ****************************************************************************** SUBJECT: SDSU Harding Hall Renovation

More information

MIRACOSTA COMMUNITY COLLEGE DISTRICT

MIRACOSTA COMMUNITY COLLEGE DISTRICT MIRACOSTA COMMUNITY COLLEGE DISTRICT FACILITIES MASTER PLAN UPDATE MARCH 16, 2016 PHASE TWO: Board of Trustees Presentation 1 Facilities Master Plan Update: Cost Community Learning Center San Elijo Campus

More information

Texas A&M University Texas A&M University at Galveston. March 2001 Update

Texas A&M University Texas A&M University at Galveston. March 2001 Update Texas A&M University Texas A&M University at Galveston March 2001 Update THE TEXAS A&M UNIVERSITY SYSTEM Capital Plan Table of Contents Funding Codes 2 Texas A&M University Summary Information 4 Yearly

More information

LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN. APPENDIX N - Campus Utilities Assessment Findings

LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN. APPENDIX N - Campus Utilities Assessment Findings LOUISIANA STATE UNIVERSITY COMPREHENSIVE & STRATEGIC CAMPUS MASTER PLAN APPENDIX N - Campus Utilities Assessment Findings Louisiana State University Campus Master Plan Campus Utilities Introduction Based

More information

b) Ensure provision of sufficient potable water to meet anticipated University needs and to reuse water for irrigation purposes.

b) Ensure provision of sufficient potable water to meet anticipated University needs and to reuse water for irrigation purposes. 9.0 GENERAL INFRASTRUCTURE ELEMENT The purpose of this element is to ensure adequate provision of public facilities and services required to meet the future needs of the University, including the following:

More information

F 6 STANDING COMMITTEES. B. Finance and Asset Management Committee Campus Master Plan Update INFORMATION ITEM BACKGROUND

F 6 STANDING COMMITTEES. B. Finance and Asset Management Committee Campus Master Plan Update INFORMATION ITEM BACKGROUND F 6 VII. STANDING COMMITTEES B. Finance and Asset Management Committee 2018 Campus Master Plan Update INFORMATION ITEM BACKGROUND Each of the thirteen major institutions within the City of Seattle are

More information

Projects Currently in Planning, Design and Construction. April 12, 2017

Projects Currently in Planning, Design and Construction. April 12, 2017 Projects Currently in Planning, Design and Construction April 12, 2017 in Planning Programming, Space Planning, Site Design Review and Construction Support for Various Capital Projects Administrative Space

More information

GUIDELINES FOR PREPARING SECTION C: COSTS OF THE PROJECT CAPITAL IMPROVEMENT BUDGET (CIB) (Updated January 2008)

GUIDELINES FOR PREPARING SECTION C: COSTS OF THE PROJECT CAPITAL IMPROVEMENT BUDGET (CIB) (Updated January 2008) GUIDELINES FOR PREPARING SECTION C: COSTS OF THE PROJECT CAPITAL IMPROVEMENT BUDGET (CIB) (Updated January 2008) The following guidelines are to be used in the preparation of Section C: Costs of the project

More information

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by MONTHLY PROGRESS REPORT Through February 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive

More information

Complete / in Construction: $585M+

Complete / in Construction: $585M+ Complete / in Construction: $585M+ Complete Energy Services Performance Contract (ESCO) Steam Line Replacement portion In Closeout $115M Gampel Pavilion Dome Repair Engineering and Science Building Koons

More information

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements %

Overbrook Theater / Fruenthal Foundation Art Center. 1.0 Total Points % 2.1 Building Exterior Elements % 8/13/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 64 64% 2.2 Accessibility 0 66 66% 2.3 Structural 0 77 77% 2.4 Building Envelope 0 4 4% 2. Interior

More information

[THIS PAGE INTENTIONALLY LEFT BLANK]

[THIS PAGE INTENTIONALLY LEFT BLANK] I-1 IMPLEMENTATION [THIS PAGE INTENTIONALLY LEFT BLANK] In accordance with Chapter 163.3194 of the Florida Statutes, and following adoption of this update of the City of Oviedo Comprehensive Plan, all

More information

PROJECT UPDATES. Capital Planning and Space Management Office April 2015

PROJECT UPDATES. Capital Planning and Space Management Office April 2015 PROJECT UPDATES Capital Planning and Space Management Office April 2015 2 Completed Projects Stockton - Chan Family Hall Renovation 3 Chan Family Hall Renovation Audio-visual and security camera work in

More information

RFP Design and Field Improvements for Outdoor Track and Athletic Area Addendum #3 dated 02/8/2018

RFP Design and Field Improvements for Outdoor Track and Athletic Area Addendum #3 dated 02/8/2018 DATE: February 8, 2018 TO: FROM: RE: All Prospective Proposers Beth Kirk Director, Office of Procurement 301-546-0007 RFP 18-04 Design and Field Improvements for Outdoor Track and Athletic Area Addendum

More information

Requests Conditional Use Permits (Craft Brewery & Open Air Market) Staff Recommendation Approval. Staff Planner Kristine Gay

Requests Conditional Use Permits (Craft Brewery & Open Air Market) Staff Recommendation Approval. Staff Planner Kristine Gay Applicant Property Owner Derrick Borte Public Hearing October 11, 2017 City Council Election District Beach Agenda Item 11 Requests Conditional Use Permits (Craft Brewery & Open Air Market) Staff Recommendation

More information

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 1 ACTIVE PROJECTS Santa Ana College Chavez Hall Renovation Temporary Village Phase 2 Santiago Canyon College Orange Education Center

More information

TEMPLATE A P S S I T E M A S T E R P L A N N I N G

TEMPLATE A P S S I T E M A S T E R P L A N N I N G TEMPLATE A P S S I T E M A S T E R P L A N N I N G Albuquerque Public Schools Department of Facilities Design + Construction January 1, 2017 1 INTRODUCTION & OVERVIEW Albuquerque Public Schools develops

More information

Draft Feasibility Study for the Expansion of Southeast Library

Draft Feasibility Study for the Expansion of Southeast Library DC public Library KH KEAST & HOOD METROPOLITAN E N G I N E E R I N G I N C S H A P I RO-O BRIEN Draft Feasibility Study for the Expansion of Southeast Library Draft Submission: November 4, 2016 1 OVERVIEW

More information

Project Brief. Royal Columbian Hospital Redevelopment Project Phase One

Project Brief. Royal Columbian Hospital Redevelopment Project Phase One Royal Columbian Hospital Redevelopment Project Phase One Page i TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Purpose of this... 1 2 THE BUSINESS OPPORTUNITY... 2 3 FRASER HEALTH AUTHORITY... 4 4 THE PROJECT...

More information

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1300 CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT 15.1301 SECTION 13.01 STATEMENT OF PURPOSE To provide for manufactured home park development, of long-term duration of stay, in

More information

8 Infrastructure and Utilities Framework

8 Infrastructure and Utilities Framework 8 Infrastructure and Utilities Framework This section of the California State University East Bay, Hayward Campus Master Plan identifies the campus infrastructure and utility systems needed to accommodate

More information

UNCW Board of Trustees. Facilities Update. October 27, 2016

UNCW Board of Trustees. Facilities Update. October 27, 2016 UNCW Board of Trustees Facilities Update October 27, 2016 Hurricane Matthew Page 2 UNCW Allied Health Facility Page 3 Budget: $66M Status: Advance Planning in Progress Designer: EYP Architects Advance

More information

Meeting 6 December 14, 2016

Meeting 6 December 14, 2016 Meeting 6 December 14, 2016 TONIGHT'S AGENDA 6:00-6:30 6:30-6:35 6:35-6:40 6:40-6:45 6:45-7:00 7:00-7:15 7:15-7:25 7:25-7:35 7:35-7:50 7:50-7:55 Dinner Welcome / Agenda for tonight Review of scenarios

More information

CAPITAL OUTLAY APPROPRIATIONS SINCE as of December 7, 2017

CAPITAL OUTLAY APPROPRIATIONS SINCE as of December 7, 2017 Academic and Student Affairs Building 0 45,153,000 0 45,153,000 2010 0 45,153,000 0 45,153,000 Academic and Student Affairs Building Planning 0 0 0 0 2007 0 0 2,720,000 2,720,000 2010 0 0 (2,720,000) (2,720,000)

More information

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS AUGUST 1, 2018 Contact: John Nash REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS Actions Requested: Consider recommending to the Board approval of the: 1. Project Description

More information

Auburn Facilities Energy Reduction Plan

Auburn Facilities Energy Reduction Plan Auburn Facilities Energy Reduction Plan Revision 2: May 2012 Overall Plan: Auburn University Facilities will work to reduce energy usage, utility consumption, energy costs, and the University s carbon

More information

Field House Proposal

Field House Proposal Field House Proposal For Experienced Dependable Resourceful 5802 Akron Cleveland Rd. Hudson, OH 44236 Table Of Contents Cost Projection 3 Funding Summary 4 Site Plan 5 Field House Layout 6 Field House

More information

TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: ACTION ITEM CONSENT

TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: ACTION ITEM CONSENT Office of the President TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: For the Meeting of November 16, 2016 ACTION ITEM CONSENT APPROVAL OF THE NON-STATE BUDGET AND APPROVAL OF EXTERNAL FINANCING,

More information

Consolidating Systems for a Greener Future:

Consolidating Systems for a Greener Future: FEATURE Consolidating Systems for a Greener Future: Trinity University s thermal utility upgrade Bradley A. Pankow, PE, Principal Engineer and Project Manager, Stanley Consultants; and Jesse Cabrera, PE,

More information

The Florida State University Facility Program. for. Indoor Practice Facility FS-273

The Florida State University Facility Program. for. Indoor Practice Facility FS-273 The Florida State University Facility Program for Indoor Practice Facility FS-273 November 2010 Prepared by: The Facilities Department Facilities Planning Section ii Indoor Practice Facility (FS-273) Facility

More information

Capital Projects Update April 18, 2018 CALIFORNIA STATE UNIVERSITY, CHICO

Capital Projects Update April 18, 2018 CALIFORNIA STATE UNIVERSITY, CHICO Capital Projects Update April 18, 2018 CENTRAL PLANT MODIFICATIONS Scope o Expand existing building to add one new and one future chiller. o Replace original boilers. o New chiller, cooling tower and TES

More information

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Committee on Budget and Finance AGENDA ITEM: III E DATE: December 4-5, 2013 ****************************************************************************** SUBJECT: FY15 HEFF

More information

HEALTH AND WELLNESS CENTER

HEALTH AND WELLNESS CENTER HEALTH AND WELLNESS CENTER Draft Tiered Initial Study and Proposed Negative Declaration The following Initial Study has been prepared in compliance with CEQA. Prepared By: OFFICE OF RESOURCE MANAGEMENT

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance Consent ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance Consent ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance Consent AGENDA ITEM: 4 P DATE: December 5-7, 2017 ****************************************************************************** SUBJECT FY19 HEFF M&R Projects

More information

ORANGE VISTA HIGH SCHOOL PHASE I

ORANGE VISTA HIGH SCHOOL PHASE I 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description

More information

Report on Campus Construction Projects

Report on Campus Construction Projects Report on Campus Construction Projects May 8, 2015 Facilities Planning & Construction SUNY Geneseo Facilities Planning & Construction is pleased to present our summer construction report which details

More information

Quarterly Library Building Project Update. 13 December 2018

Quarterly Library Building Project Update. 13 December 2018 Quarterly Library Building Project Update 13 December 2018 Agenda A Recap Process Charges and Working Groups Consultants and Firms Communications Primer of Terms Status of Funding Feedback on Salons Discussion

More information

Architectural and Engineering Basic Services Fee Estimating Guidelines

Architectural and Engineering Basic Services Fee Estimating Guidelines Architectural and Engineering Basic Services Fee Estimating Guidelines Basic Services is the design work customary on a typical project to take an established building program, site, and budget, and then

More information

Heritage High School

Heritage High School Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery

More information

KIBBIE DOME WASTE CHARACTERIZATION STUDY September 27, 2014

KIBBIE DOME WASTE CHARACTERIZATION STUDY September 27, 2014 KIBBIE DOME WASTE CHARACTERIZATION STUDY September 27, 2014 Goals and Objectives The goals of this waste characterization study were to evaluate the efficiency of the Game Day Recycling program and measure

More information

APSU PROJECT REPORT 8/2/2018

APSU PROJECT REPORT 8/2/2018 373/003X92018 Harvill Hall Fan Coil & Controls Upgrade Housing Joe Mills (millsj@apsu.edu) LOI Replacement of Building Fan Coils & Controls 01Approval\Planning Construction Cost 320,000.00 Contingency

More information

Northwestern University Should We Move Our Central Plant? February 22, 2017

Northwestern University Should We Move Our Central Plant? February 22, 2017 Northwestern University Should We Move Our Central Plant? February 22, 2017 1 Agenda I. Introduction II. Capacity & Expansion III. Site Evaluation IV. Conclusions Introduction Facts about Northwestern

More information

other activities that cannot currently be supported due to the lack of this type of venue;

other activities that cannot currently be supported due to the lack of this type of venue; CLARK COUNTY AND BOARD OF REGENTS OF THE NEVADA SYSTEM OF HIGHER EDUCATION MEMORANDUM OF UNDERSTANDING RELATED TO THE DEVELOPMENT OF MEGA-EVENTS CENTER AND STUDENT VILLAGE AT THE UNIVERSITY OF NEVADA,

More information

Moving Toward Greater Sustainability: Oklahoma State University Builds a New Central Plant

Moving Toward Greater Sustainability: Oklahoma State University Builds a New Central Plant Moving Toward Greater Sustainability: Oklahoma State University Builds a New Central Plant June 21, 2016 Introductions James Rosner, PE, CEM (james.rosner@okstate.edu) - Director of Energy Services, Oklahoma

More information

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York

More information

Riverview Drive Sanitary Sewer and Water Main Extension Project CITY OF ANN ARBOR FILE NO

Riverview Drive Sanitary Sewer and Water Main Extension Project CITY OF ANN ARBOR FILE NO Riverview Drive Sanitary Sewer and Water Main Extension Project CITY OF ANN ARBOR FILE NO. 2017-031 WELCOME PUBLIC MEETING NO. 2 February 21, 2018 CITY OF ANN ARBOR RIVERVIEW DRIVE SANITARY SEWER AND WATER

More information

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural % 8/11/ Building Rating System Percent Site: 1.0 Total 0 9 8 Building: 2.1 Building Exterior Elements 0 82 82% 2.2 Accessibility 0 82 82% 2.3 Structural 0 7 7% 2.4 Building Envelope 0 47 47% 2. Interior

More information

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM AGENDA ITEM 23a To: From: Subject: Board of Regents Board Office Register

More information

City of Moscow University of Idaho Water Reclamation and Reuse Program

City of Moscow University of Idaho Water Reclamation and Reuse Program City of Moscow University of Idaho Water Reclamation and Reuse Program Association of Idaho Cities 2017 Annual Conference Les MacDonald, P.E. Moscow Director of Public Works HISTORY OF WWTP EFFLUENT REUSE

More information

SECTION 7: SCHEDULING/PLAYING SEASON/CONTRACTS

SECTION 7: SCHEDULING/PLAYING SEASON/CONTRACTS SECTION 7: SCHEDULING/PLAYING SEASON/CONTRACTS SCHEDULING GUIDELINES There are general guidelines which set the parameters for developing both an individual sport schedule and the overall athletic department

More information

CHILLED WATER SUB-ELEMENT Goal 1 To provide heating water and chilled water to satisfy the building demands to support the mission of the University.

CHILLED WATER SUB-ELEMENT Goal 1 To provide heating water and chilled water to satisfy the building demands to support the mission of the University. ELEMENT 10 UTILITIES ELEMENT INCLUDING SUB-ELEMENTS: Chilled Water and Reheat Water Electrical Power and Other Fuels Telecommunications Systems UTILITIES ELEMENT CHILLED WATER SUB-ELEMENT Goal 1 To provide

More information

FACILITY DESIGN PLAN FOR PHYSICAL EDUCATION COMPLEX FROST ARENA HVAC REPLACEMENT SOUTH DAKOTA STATE UNIVERSITY. May 17, 2013

FACILITY DESIGN PLAN FOR PHYSICAL EDUCATION COMPLEX FROST ARENA HVAC REPLACEMENT SOUTH DAKOTA STATE UNIVERSITY. May 17, 2013 FACILITY DESIGN PLAN FOR PHYSICAL EDUCATION COMPLEX FROST ARENA HVAC REPLACEMENT SOUTH DAKOTA STATE UNIVERSITY May 17, 2013 SDSU requests approval of this Facility Design Plan to continue design and implement

More information

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT. WORK IN PROGRESS August 2011

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT. WORK IN PROGRESS August 2011 AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS August 2011 Masonry and Concrete Improvements Status: Contractor: Pioneer Masonry Restoration Inc., Seattle WA. Construction

More information

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary A D D E N D U M 1 TO All Plan Holders ISSUE DATE 20 January 2017 PROJECT # 15-028 REGARDING Switchgear Replacement NARRATIVE PAGES 1 15-02812 KVa Switchgear Replacement Project SPECIFICATION PAGES 10 DRAWING

More information

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010

Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE. October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 28, 2010 Quarterly Report to the CITIZENS GENERAL OBLIGATION BOND OVERSIGHT COMMITTEE October 2010 update TABLE OF CONTENTS

More information

MILLBURY PARK MASTER PLAN AND VETERANS MEMORIAL

MILLBURY PARK MASTER PLAN AND VETERANS MEMORIAL Location Milbury, Ohio Planning, Site Engineering, Grantwriting and Surveying Project Cost $250,000 2010 2013 PDG Project Team David E. Saneholtz, Project Manager, P.E. MILLBURY PARK MASTER PLAN AND VETERANS

More information

KENTUCKY STATE UNIVERSITY

KENTUCKY STATE UNIVERSITY KENTUCKY STATE UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2004-2006 1 Hathaway Hall Renovation Phase II $11,200,000

More information

PLANNING THE 365-DAY VENUE

PLANNING THE 365-DAY VENUE PLANNING THE 365-DAY VENUE A white paper from L.R. Kimball March 2010 412.201.4900 www.lrkimball.com ARchitecture Engineering Communications technology aviation civil Construction services data systems

More information

I - 15 CORRIDOR CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT. Appendices

I - 15 CORRIDOR CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT. Appendices I - 15 CORRIDOR CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT Appendices Appendix J Utility Systems Data August 2017 I - 15 CORRIDOR CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO

More information

/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions

/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions Page 1 7-101 Definition A. Alternative Construction Delivery Methods: Building Delivery Processes that vary from the more standard Design-Bid-Build model. These may include Construction Manager-At-Risk

More information

College and University Design Services

College and University Design Services College and University Design Services Gannett Fleming helps college campuses evolve to meet the changing needs of students and programs. New Student Recreation Center, Shippensburg University Commitment

More information

University of Oregon 10 Year Capital Plan

University of Oregon 10 Year Capital Plan December 2018 University of Oregon 10 Year Capital Plan Prepared by Campus Planning and Facilities Management UNIVERSITY OF OREGON CAPITAL PLAN December 2018 Table of Contents Capital Plan Master Schedule

More information

MONTHLY PROGRESS REPORT

MONTHLY PROGRESS REPORT MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report

More information

RECOMMENDED CONCEPT COLLEGE COMMUNITY CAMPUS IMPROVEMENTS INTERNAL ROADWAY COST ANALYSIS MAY 9, 2014

RECOMMENDED CONCEPT COLLEGE COMMUNITY CAMPUS IMPROVEMENTS INTERNAL ROADWAY COST ANALYSIS MAY 9, 2014 8"' PCC CURB AND GUTTER KIRKWOOD BLVD SW 76TH AVENUE SW 76TH AVENUE SW PRAIRIE CREST ELEMENTARY 6' PRAIRIE PERFORMING ARTS CENTER PRAIRIE HIGH SCHOOL TIE INTO FROM PRAIRIE HILL FUTURE SITE OF PRAIRIE HILL

More information

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ****************************************************************************** SOUTH DAKOTA BOARD OF REGENTS Budget and Finance AGENDA ITEM: 7 X DATE: March 27-29, 2018 ****************************************************************************** SUBJECT USD North Commons Renovation

More information

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014

2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included

More information