1 MONTHLY PROGRESS REPORT Through February 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company
2 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report Capital Projects Gunn High School New Classroom Buildings A & B page 6 Gunn High School Parking and Drop off Sitework Improvement page 7 Gunn High School New Gymnasium page 8 Palo Alto High School Athletic Stadium Improvements page 9 Palo Alto High School Project Classroom Building and Media Arts page 10 Palo Alto High School Performing Arts Center page 11 Jordan Middle School page 12 J.L. Stanford Middle School page 13 Terman Middle School page 14 Fairmeadow Elementary School page 15 Duveneck Elementary School page 16 Technology page 17 Completed Capital Projects Palo Alto High School Haymarket and Tower Building Boiler Replacement page 18 Ohlone Elementary School page 19 Property Acquisition 525 San Antonio Rd page 20 Jordan Middle School Interim Classrooms page 21 Gunn High School Air Conditioning of Existing Buildings page 22 J.L. Stanford Middle School Interim Classrooms page 23 Fairmeadow Elementary School Portable Relocation page 24 Elementary Classroom Improvements Interactive Whiteboard & Sound Assist System page 25 Palo Alto High School Multi use Field page 26 Gunn High School Industrial Arts Renovation page 27 Gunn High School Aquatic Center page 28 Middle School Pre Design page 29 Inactive Capital Projects Garland Elementary School page 30 Elementary School Teaching Walls Phase 1 Schools page 32 High School Master Plan page 33 Hoover Elementary School page 34 Elementary Classroom Improvements Phase 1 Schools Barron Park and El Carmelo page 35 Appendix Exhibit A Bond Project List Page 2
3 EXECUTIVE SUMMARY Gunn High School New Classroom Buildings A & B BRCO Constructors installed base rock for approximately 70% of the building pads. The electrical contractor continues to install under slab utilities. The contractor is preparing to pour concrete for the building slab and the stem walls. At building B, all under slab utilities are in and base rock for the pad is complete. The building slab was poured the last week of February Gunn High School Parking and Drop off Sitework Improvement Design for the parking and drop off improvements will recommence in conjunction with the planning of group 2 projects. Gunn High School New Gymnasium S.J. Amoroso completed building slab and stem walls, and continued to work on above slab electrical and plumbing piping. Steel began to arrive on site mid February 2012 and steel erection is anticipated to begin the last week of February. Palo Alto High School Athletics Stadium Improvements Taisei (TCC) surveyed and staked the building layout to begin the foundation work. Work continued on installation of under floor plumbing and electrical utilities. Due to a few rain days in February, the concrete pour is scheduled to occur in March Palo Alto High School Classroom Building and Media Arts Building TCC completed the installation of underground electrical and plumbing piping. They continue to work on the foundation system, where the floor slab preparation is 90% complete. The new pump was installed in the parking lot that connects to the new storm drainage system to the main line under El Camino Real. Palo Alto High School Performing Arts Center (PAC) Deems Lewis McKinley (DLM) met with facilities and maintenance staff on February 22, 2012 to review building systems, equipment and operations. DLM continues with design development, which is anticipated to be complete in March Jordan Middle School SJ Amoroso continued with site preparation for the new classroom building and cafetorium expansion. Both building pads are ready for foundation work to start, which will commence early March Interior improvements for the existing cafetorium space are underway. J.L. Stanford Middle School Additional constructability comments and coordination of bid documents are currently being incorporated prior to bidding in April The construction estimate will be updated to include recent revisions and to confirm the project s anticipated construction cost prior to going out for bid. Bids will be due in May Terman Middle School Hagensen Pacific continued site preparation, underground utility removal and relocation for the new drama classroom building and the library expansion. At the interior of the new administration building, the contractor completed demolition of the existing walls and started construction on improvements in the new space. Fairmeadow Elementary School New Classroom Building and Modernization Best Contracting Services (BCS) installed a temporary wall in the library so the library can remain occupied during the school year while construction occurs for the expansion. BCS commenced grading and excavation activities for the new two story building and the library addition on February 16, The building pad was certified on February 28, Page 3
4 Duveneck Elementary School New Classroom Buildings and Modernization Gelfand submitted construction documents to DSA on February 27, Gelfand continues to work on refinements to the construction documents and incorporation of constructability comments. Technology Implementation of the district wide Voice over IP (VoIP) telephone system has commenced and will continue throughout the school year. Also, bidding will occur in March 2012 to replace the district s wireless network. COMPLETED CAPITAL PROJECTS Palo Alto High School Haymarket and Tower Building Boiler Replacement Environmental Services Inc. (ESI) initiated project closeout. Staff continues to work on other improvements within the Tower building to improve the heating distribution and controls systems. 525 San Antonio Road Site Acquisition The advisory committee has recommended to the BOE on January 31, 2012 to lease the property on a short term basis to one or more tenants. Ohlone Elementary School New Classroom Building and Modernization Move in to the new building and other existing classrooms occurred during winter break. Students occupied the new building on January 3, Jordan Middle School Interim Classrooms The portables have been installed, and were cleaned and moved into on September 30, All documents were submitted to DSA for closeout November 2, Gunn High School Air Conditioning of Existing Buildings Best Contracting Services Inc. completed the installation of air conditioning units and the cool roof coating on most of Gunn s existing buildings. J.L. Stanford Middle School Interim Classrooms Coulter Construction completed the work on the relocated portables in August. Fairmeadow Elementary School Portable Relocation The work on the relocated portable was complete on August 8, All documents were submitted to DSA for closeout October 11, Elementary Classroom Improvements Installation of Interactive Whiteboards and Sound Assist Systems Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school classrooms and libraries in April Palo Alto High School Multi use Field The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9, Gunn High School Industrial Arts Addition & Renovation This facility was available for instruction in January DSA closeout received on July 18, Gunn High School Aquatic Center This facility was available for use in July 2009, and has been closed out with DSA. Page 4
5 Middle Schools Pre Design Jordan, J.L. Stanford and Terman AEDIS presented recommended concept plans for each campus to the Board of Education for approval on September 8, which became the program documents for the new projects at each campus. These projects for predesign work have been closed, and funds were transferred to the program contingency on June 14, INACTIVE CAPITAL PROJECTS Garland Elementary School Renovation The Board of Education has put new development for Garland on hold until a growth plan is established for the elementary schools. The board voted to terminate the lease with Stratford School in June Discussions with the Board on future plans for growth at the elementary schools will resume during a February 28, 2012 study session. Elementary School Teaching Walls Phase 1 Schools The district placed this project on hold after review of the implementation of other classroom improvements, as recommended by the elementary school principals. This project was renamed Elementary Classroom Improvements (see Capital Projects summary below). High School Master Plan The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed, with funds transferred to the respective campus reserve funds. Hoover Elementary School Pre Design This project has been put on hold until a growth plan is established for the elementary schools. Elementary Classroom Improvements Phase 1 Schools Barron Park and El Carmelo The project has been placed on hold pending further discussions with the BOE about elementary growth planning. Board Actions in February February 28, 2012 Action 14 Authorization to Bid Replacement of the District s Wireless Network Page 5
6 Palo Alto Unified School District Strong Schools Bond 2/29/2012 School Name - Project Name A B C C / A B - C C / B A - B Percent of Contract Percent of Committed Expenditures Balance Expended Balance Expended Gunn High School - High School Master Plan 142, , , % 18, % 6,381 Gunn High School 1 - Aquatic Center 4,865,423 4,862,530 4,862, % % 2,893 Gunn High School 2 - I.A Building 5,082,403 5,049,558 5,048, % 1, % 32,845 Gunn High School 3 - AD2- close out 5,777 5,777 5, % % 0 Gunn High School 4 - New classroom Buildings 25,035,200 23,864,062 5,960, % 17,903, % 1,171,138 Gunn High School 5 - Parking & Drop Off improvements 3,940, , , % 218, % 3,618,159 Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 11,046,148 2,937, % 8,108, % 1,868,652 Gunn High School 7- A/C 2,600,000 2,291,706 2,097, % 194, % 308,294 Gunn High School - Reserved 21,525, % % 21,525,081 Palo Alto High Schools - High School Master Plan 142, , , % 9, % 5,240 Palo Alto High School 1 - Stadium Field 4,940,000 4,493,342 1,060, % 3,432, % 446,658 Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609, % % 0 Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 33,678,487 8,404, % 25,274, % 3,461,513 Palo Alto High School 4 - New Theater 24,395,049 1,586, , % 1,343, % 22,808,808 Palo Alto High School 5 - Haymarket and Tower Admin. Building 800, , , % 109, % 350,718 Palo Alto High School - Reserved 28,765, % % 28,765,818 Jordan Middle School -Program Management- MS Pre-Design 18,890 18,890 17, % 1, % 0 Jordan Middle Schools 1- Interim Classrooms 600, , , % 37, % 134,079 Jordan Middle School 2- Improvements 19,891,564 18,469,796 1,753, % 16,716, % 1,421,768 J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,799 18, % % 0 J.L.S Middle School 1 - Interim Classrooms 446, , , % 26, % 49,236 J.L.S Middle School 2- Improvements 17,184,699 3,346,412 2,134, % 1,211, % 13,838,287 Terman Middle School - Program Management- MS Pre-Design 18,799 18,799 18, % % 0 Terman Middle School 1- Improvements 13,312,971 12,544,116 1,756, % 10,787, % 768,855 PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 85, % 13, % 46,520 Addison Elementary School 1-Phase I 21,267 21,267 21, % % 0 Duveneck Elementary School 1-Phase I 11,088,759 1,488, , % 1,070, % 9,599,833 Garland Elementary School 1- Phase I 22,178, , , % 1, % 21,897,265 Fairmeadow Elementary School 1- Phase I 9,543,750 8,947, , % 8,039, % 595,882 Hoover Elementary School 1-Phase I 70,550 70,550 57, % 13, % 0 Ohlone Elementary School 1- Phase I 11,667,965 10,744,981 9,277, % 1,467, % 922,984 Elementary Schools 1 - Elementary Classroom Improvements * 2,004,889 2,004,889 1,863, % 141, % 0 Elementary Schools - Reserved 33,457, % % 33,457,555 PAUSD - Program Management 6,652,006 5,112,403 4,349, % 763, % 1,539,603 PAUSD - Technology 8,238,257 6,424,319 6,055, % 368, % 1,813,938 PAUSD - Technology -Reserved 5,669, % % 5,669,108 PAUSD - Reserved 5,759, % % 5,759, San Antonio -Property Acquisition 8,500,000 8,500,000 8,500, % % 0 Bond Issuance Cost 1,840,700 1,840,700 1,840, % % 0 Total 353,234, ,348,764 74,074,364 97,274, ,886,181 Prepared by: Business Services Department based on QSS accounting System
7 Gunn High School New Classroom Buildings A & B BRCO Constructors installed base rock for approximately 70% of the building pads. The electrical contractor continues to install under slab utilities. The contractor is preparing to pour concrete for the building slab and the stem walls. At building B, all under slab utilities are in and base rock for the pad is complete. The building slab was poured the last week of February Strong Schools Bond Funds $25,035,200 Other $0 Total $25,035,200 Salaries and Benefits $13,253 Supplies $0 Contracts & Services $4,462,881 Construction & Equipment $20,482,302 Soft Costs Contingency $76,764 Total $25,035,200 Percent of Expended 23.8% Change Order Contingency Starting Contingency Balance $ 1,763,200 Remaining Contingency Balance $ 1,602,772 Percent of Changes 9.1% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) September 8, 2009 September 22, 2009 Schematic Design (2) January 12, 2010 January 26, 2010 Submit to DSA August 4, 2010 Authorize to Bid (2) March 8, 2011 March 22, 2011 Approval by DSA May 27, 2011 Bid Opening July 13, 2011 Award of Contract (1) July 22, 2011 Notice to Proceed August 24, 2011 Substantial Completion March 23, 2013* Planned Occupancy August 1, 2013* C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4 This project is proceeding on schedule and is within budget. Page 6
8 Gunn High School Parking and Drop off Sitework Improvement Design for the parking and drop off improvements will recommence in conjunction with the planning of group 2 projects in fall Strong Schools Bond Funds $3,940,000 Other $0 Total $3,940,000 Supplies $0 Contracts & Services $898,978 Construction & Equipment $2,919,840 Soft Costs Contingency $121,182 Total $3,940,000 Percent of Expended 2.6% Current Phase: Conceptual Design Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion C. BOND PROJECT LIST REFERENCE: 5.5 Design will recommence with the planning of group 2 projects. Page 7
9 Gunn High School New Gymnasium S.J. Amoroso completed building slab and stem walls, and continued to work on above slab electrical and plumbing piping. Steel began to arrive on site mid February 2012 and steel erection is anticipated to begin the last week of February. Strong Schools Bond Funds $12,914,800 Other $0 Total $12,914,800 Supplies $1,001 Contracts & Services $2,677,293 Construction & Equipment $10,158,210 Soft Costs Contingency $78,296 Total $12,914,800 Percent of Expended 22.7% Change Order Contingency Starting Contingency Balance $834,700 Remaining Contingency Balance $770,766 Percent of Changes 7.7% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) September 8, 2009 September 22, 2009 Schematic Design (2) January 12, 2010 January 26, 2010 Submit to DSA August 4, 2010 Authorize to Bid (2) March 8, 2011 March 22, 2011 Approval by DSA May 27, 2011 Bid Opening July 13, 2011 Award of Contract (1) July 20, 2011 Notice to Proceed August 1, 2011 Substantial Completion October 29, 2012* Planned Occupancy January 1, 2013* C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13 This project is proceeding on schedule and is within budget. Page 8
10 Palo Alto High School Athletic Stadium Improvements Taisei (TCC) surveyed and staked the building layout to begin the foundation work. Work continued on installation of under floor plumbing and electrical utilities. Due to a few rain days in February, the concrete pour is scheduled to occur in March Strong Schools Bond Funds $4,940,000 Other $0 Total $4,940,000 Salaries and Benefits $882 Supplies $0 Contracts & Services $829,025 Construction & Equipment $4,071,162 Soft Costs Contingency $38,931 Total $4,940,000 Percent of Expended 21.5% Change Order Contingency Starting Contingency Balance $310,200 Remaining Contingency Balance $269,816 Percent of Changes 4.3% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) January 26, 2010 February 9, 2010 Conceptual Design (2) June 1, 2010 June 22, 2010 Schematic Design (2) February 22, 2011 March 8, 2011 Submit to DSA April 4, 2011 Authorize to Bid (2) June 28, 2011 July 19, 2011 Approval by DSA July 26, 2011 Bid Opening December 1, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed January 4, 2012 Substantial Completion Concession August 15, 2012* Bleachers March 1, 2013* Planned Occupancy Concessions August 30, 2012* C. BOND PROJECT LIST REFERENCE: 4.13 The project is proceeding on schedule and within budget. Page 9
11 Palo Alto High School Classroom Building and Media Arts TCC completed the installation of underground electrical and plumbing piping. They continue to work on the foundation system, where the floor slab preparation is 90% complete. The new pump was installed in the parking lot that connects to the new storm drainage system to the main line under El Camino Real. Strong Schools Bond Funds $37,140,000 Other $0 Total $37,140,000 Salaries and Benefits $14,721 Supplies $0 Contracts & Services $7,056,446 Construction & Equipment $29,740,000 Soft Costs Contingency $328,833 Total $37,140,000 Percent of Expended 22.6% Change Order Contingency Starting Contingency Balance $2,515,000 Remaining Contingency Balance $2,245,983 Percent of Changes 10.7% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) September 8, 2009 September 22, 2009 Schematic Design (2) January 12, 2010 January 26, 2010 Submit to DSA August 4, 2010 Authorize to Bid (2) March 8, 2011 March 22, 2011 Approval by DSA April 28, 2011 Bid Opening June 30, 2011 Award of Contract (1) July 12, 2011 Notice to Proceed August 4, 2011 Substantial Completion August 5, 2013* Planned Occupancy August 20, 2013* C. BOND PROJECT LIST REFERENCE: This project is proceeding one month behind schedule occupancy and remains within budget. Page 10
12 Palo Alto High School Performing Arts Center (PAC) Deems Lewis McKinley (DLM) met with facilities and maintenance staff on February 22, 2012 to review building systems, equipment and operations. DLM continues with design development, which is anticipated to be complete in March Strong Schools Bond Funds $24,395,049 Other $0 Total $24,395,049 Supplies $0 Contracts & Services $4,481,640 Construction & Equipment $19,745,000 Soft Costs Contingency $168,409 Total $24,395,049 Percent of Expended 1.0% Current Phase: Design Development Architect Contract (2) March 31, 2009 April 14, 2009 Conceptual Design (2) June 1, 2010 June 22, 2010 Schematic Design (3) June 14, 2011 December 13, 2011 January 17, 2012 Submit to DSA January 3, 2013* Approval by DSA August 27, 2013* Authorize to Bid (2) August 20, 2013* September 9, 2013* Bid Opening October 22, 2013* Award of Contract (1) October 28, 2013* Notice to Proceed November 11, 2013* Substantial Completion May 13, 2015* Planned Occupancy August 17, 2015* C. BOND PROJECT LIST REFERENCE: 4.11 Design development continued. Project is proceeding on schedule and within budget. Page 11
13 Jordan Middle School SJ Amoroso continued with site preparation for the new classroom building and cafetorium expansion. Both building pads are ready for foundation work to start, which will commence early March Interior improvements for the existing cafetorium space are underway. Strong Schools Bond Funds $19,891,546 Other $0 Total $19,891,546 Supplies $0 Contracts & Services $3,552,716 Construction & Equipment $16,007,031 Soft Costs Contingency $331,817 Total $19,891,546 Percent of Expended 8.8% Change Order Contingency Starting Contingency Balance $1,389,700 Remaining Contingency Balance $1,389,700 Percent of Changes 0.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (2) March 23, 2010 April 27, 2010 Submit to DSA December 21, 2010 Authorize to Bid (2) June 28, 2011 July 19, 2011 Approval by DSA October 5, 2011 Bid Opening December 8, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed December 27, 2011 Substantial Completion August 1, 2013* Planned Occupancy August 26, 2013* C. BOND PROJECT LIST REFERENCE: , , , The project is proceeding on schedule and within budget. Page 12
14 J.L. Stanford Middle School Additional constructability comments and coordination of bid documents are currently being incorporated prior to bidding in April The construction estimate will be updated to include recent revisions and to confirm the project s anticipated construction cost prior to going out for bid. Bids will be due in May Strong Schools Bond Funds $17,184,699 Other $0 Total $17,184,699 Supplies $3,458 Contracts & Services $3,440,550 Construction & Equipment $13,421,500 Soft Costs Contingency $319,191 Total $17,184,699 Percent of Expended 12.4% Current Phase: DSA Review Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (3) June 1, 2010 June 22, 2010 (Sitework) September 28, 2010 Submit to DSA May 6, 2011 Authorize to Bid (2) November 29, 2011 December 13, 2011 Approval by DSA January 24, 2012 Bid Opening May 3, 2012* Award of Contract (1) May 8, 2012* Notice to Proceed May 21, 2012* Substantial Completion August 24, 2013* Planned Occupancy January 1, 2014* C. BOND PROJECT LIST REFERENCE: , , , 6.4, 6.5 DSA approval received on January 24, Anticipate project to bid in April Page 13
15 Terman Middle School Hagensen Pacific continued site preparation, underground utility removal and relocation for the new drama classroom building and the library expansion. At the interior of the new administration building, the contractor completed demolition of the existing walls and started construction on improvements in the new space. Strong Schools Bond Funds $13,312,971 Other $0 Total $13,312,971 Supplies $0 Contracts & Services $2,616,588 Construction & Equipment $10,517,515 Soft Costs Contingency $178,868 Total $13,312,971 Percent of Expended 13.2% Change Order Contingency Starting Contingency Balance $929,900 Remaining Contingency Balance $929,900 Percent of Changes 0.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (2) May 11, 2010 May 25, 2010 Submit to DSA December 21, 2010 Authorize to Bid (2) June 28, 2011 July 19, 2011 Approval by DSA September 1, 2011 Bid Opening December 6, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed December 27, 2011 Substantial Completion August 7, 2013* Planned Occupancy September 4, 2013* C. BOND PROJECT LIST REFERENCE: , The project proceeding on schedule and within budget. Page 14
16 Fairmeadow Elementary School New Classroom Building and Modernization Best Contracting Services (BCS) installed a temporary wall in the library so the library can remain occupied during the school year while construction occurs for the expansion. BCS commenced grading and excavation activities for the new two story building and the library addition on February 16, The building pad was certified on February 28, Strong Schools Bond Funds $9,543,750 Other $0 Total $9,543,750 Supplies $3,132 Contracts & Services $1,928,402 Construction & Equipment $7,500,180 Soft Costs Contingency $112,036 Total $9,543,750 Percent of Expended 9.5% Change Order Contingency Starting Contingency Balance $642,300 Remaining Contingency Balance $642,300 Percent of Changes 0.0% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Construction Architect Contract (2) October 13, 2009 October 27, 2009 Conceptual Design (2) March 23, 2010 April 6, 2010 Schematic Design (2) September 14, 2010 September 28, 2010 Submit to DSA April 18, 2011 Authorize to Bid (2) October 11, 2011 October 25, 2011 Approval by DSA November 14, 2011 Bid Opening December 5, 2011 Award of Contract (1) December 13, 2011 Notice to Proceed January 3, 2012 Substantial Completion August 5, 2013* Planned Occupancy August 20, 2013* C. BOND PROJECT LIST REFERENCE: , The project is proceeding on schedule and within budget. Page 15
17 Duveneck Elementary School New Classroom Buildings and Modernization Gelfand submitted construction documents to DSA on February 27, Gelfand continues to work on refinements to the construction documents and incorporation of constructability comments. Strong Schools Bond Funds $11,088,759 Other $0 Total $11,088,759 Supplies $0 Contracts & Services $2,159,389 Construction & Equipment $8,803,087 Soft Costs Contingency $126,283 Total $11,088,759 Percent of Expended 3.8% Current Phase: Construction Documents Architect Contract (2) April 27, 2010 May 11, 2010 Conceptual Design (2) December 14, 2010 January 11, 2011 Schematic Design (2) June 14, 2011 June 28, 2011 Submit to DSA February 27, 2012* Approval by DSA October 8, 2012* Authorize to Bid (2) October 28, 2012* November 9, 2012* Bid Opening December 22, 2012* Award of Contract (1) December 27, 2012* Notice to Proceed January 5, 2013* Substantial Completion May 16, 2014* Planned Occupancy August 1, 2014* C. BOND PROJECT LIST REFERENCE: , Project plans submitted to DSA on February 27, Project is on schedule and within budget. Page 16
18 Technology Improvements Implementation of the district wide Voice over IP (VoIP) telephone system has commenced and will continue throughout the school year. Also, bidding will occur in March 2012 to replace the district s wireless network. Strong Schools Bond Funds $8,238,257 Other $0 Total $8,238,257 Supplies & Computers $7,855,662 Contracts & Services $180,173 Construction & Equipment $202,422 Soft Costs Contingency $0 Total $8,238,257 Percent of Expended 73.5% Current Phase: Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: VOIP implementation on going. Page 17
19 Palo Alto High School Boiler Replacement System Environmental Services Inc. (ESI) initiated project closeout and a notice of completion has been filed. Staff continues to work on other improvements within the Tower building to improve the heating distribution and controls systems. Strong Schools Bond Funds $800,000 Other $0 Total $800,000 Supplies $400 Contracts & Services $119,000 Construction & Equipment $659,600 Soft Costs Contingency $21,000 Total $800,000 Percent of Expended 42.4% Change Order Contingency Starting Contingency Balance $39,200 Remaining Contingency Balance $33,930 Percent of Changes 1.2% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Close out Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA June 30, 2011 Authorize to Bid (2) May 10, 2011 May 24, 2011 Approval by DSA August 24, 2011 Bid Opening September 28, 2011 Award of Contract (1) October 11, 2011 Notice to Proceed November 7, 2011 Substantial Completion January 6, 2012 C. BOND PROJECT LIST REFERENCE: Project completed on schedule and within budget. Page 18
20 Ohlone Elementary School New Classroom Building and Modernization Move in to the new building and other existing classrooms occurred during winter break. Students occupied the new building on January 3, Strong Schools Bond Funds $11,667,965 Other $0 Total $11,667,965 Salaries and Benefits $7,196 Supplies $44,253 Contracts & Services $2,359,667 Construction & Equipment $9,139,461 Soft Costs Contingency $117,388 Total $11,667,965 Percent of Expended 79.5% Change Order Contingency Starting Contingency Balance $748,400 Remaining Contingency Balance $654,714 Percent of Changes 1.4% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy January 3, 2012 Architect Contract (2) September 30, 2008 October 14, 2008 Conceptual Design (2) March 3, 2009 March 17, 2009 Schematic Design (2) June 2, 2009 June 23, 2009 Submit to DSA November 24, 2009 Authorize to Bid (2) April 27, 2010 May 11, 2010 Approval by DSA May 18, 2010 Bid Opening July 13, 2010 Award of Contract (1) August 3, 2010 Notice to Proceed August 19, 2010 Substantial Completion November 18, 2011 Planned Occupancy January 3, 2012 C. BOND PROJECT LIST REFERENCE: , Occupancy occurred on January 3, Project completed on schedule and within budget. Page 19
21 Site Acquisition 525 San Antonio Rd The advisory committee has recommended to the BOE on January 31, 2012 to lease the property on a shortterm basis to one or more tenants. Strong Schools Bond Funds $8,500,000 Other $0 Total $8,500,000 Supplies $0 Contracts & Services $8,500,000 Construction & Equipment $0 Soft Costs Contingency $0 Total $8,500,000 Percent of Expended 100.0% Current Phase: Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: , BOE discussion on committee recommendation occurred on January 31, Page 20
22 Jordan Middle Schools Interim Classrooms The portables have been installed, and were cleaned and ready for occupancy a week ahead of schedule. School staff requested additional time for packing and moved in on September 30, DSA closeout has commenced. The project is funded with both bond funds and impact fees. Strong Schools Bond Funds $392,120 Other $208,222 Total $600,342 Supplies $0 Contracts & Services $180,286 Construction & Equipment $419,292 Soft Costs Contingency $764 Total $600,342 Percent of Expended 70.4%* * previously expended Current Phase: Move in Approval by DSA June 16, 2011 Authorize to Bid (2) June 14, 2011 June 28, 2011 Bid Opening July 14, 2011 Award of Contract (1) July 20, 2011 Notice to Proceed July 27, 2011 Substantial Completion September 20, 2011 Occupancy September 30, 2011 C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5 This project completed ahead of schedule and under budget. Move in occurred on September 30, Page 21
23 Gunn High School Air Conditioning of Existing Buildings Best Contracting Services Inc. completed the installation of air conditioning units and the cool roof coating on most of Gunn s existing buildings. Strong Schools Bond Funds $2,600,000 Other $0 Total $2,600,000 Salaries and Benefits $1,919 Supplies $0 Contracts & Services $454,160 Construction & Equipment $2,120,580 Soft Costs Contingency $22,891 Total $2,600,000 Percent of Expended 78.4% Current Phase: Close out Architect Contract (2) March 27, 2010 April 6, 2010 Conceptual Design (2) Schematic Design (2) Submit to DSA October 20, 2010 Approval by DSA February 10, 2011 Authorize to Bid (2) February 22, 2011 March 8, 2011 Bid Opening March 28, 2011 Award of Contract (1) April 8, 2011 Notice to Proceed April 11, 2011 Substantial Completion August 8, 2011 C. BOND PROJECT LIST REFERENCE: 3.7 Project in close out. Page 22
24 J.L. Stanford Middle School Interim Classrooms Coulter Construction completed the work on the relocated portables in August. Strong Schools Bond Funds $17,184,699 Other $0 Total $17,184,699 Supplies $3,458 Contracts & Services $3,440,550 Construction & Equipment $13,421,500 Soft Costs Contingency $319,191 Total $17,184,699 Percent of Expended 11.4% This portable relocation project funded by main JLS project. Current Phase: Occupancy August 11, 2011 Approval by DSA April 19, 2011 Jordan Project June 16, 2011 Authorize to Bid (2) May 10, 2011 May 24, 2011 Bid Opening June 1, 2011 Award of Contract (1) June 13, 2011 Notice to Proceed June 20, 2011 Substantial Completion August 8, 2011 Planned Occupancy August 15, 2011 C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5 Project completed on schedule and is currently in close out. Page 23
25 Fairmeadow Elementary School Portable Relocation Project Guerra Construction Group completed the work on the relocated portable on August 8, The JLS project is funding the relocation of this portable for the construction of JLS new 2 story classroom building. Project in close out. Strong Schools Bond Funds $17,184,699 Other $0 Total $17,184,699 Supplies $3,458 Contracts & Services $3,440,550 Construction & Equipment $13,421,500 Soft Costs Contingency $319,191 Total $17,184,699 Percent of Expended 11.4% This portable relocation project funded by main JLS project. Current Phase: Occupancy August 8, 2011 Architect Contract (2) February 15, 2011 Conceptual Design (2) Schematic Design (2) Submit to DSA March 3, 2011 Approval by DSA March 3, 2011 Authorize to Bid (2) May 11, 2011 May 24, 2011 Bid Opening June 14, 2011 Award of Contract (1) June 14, 2011 Notice to Proceed June 20, 2011 Substantial Completion August 1, 2011 Planned Occupancy August 8, 2011 C. BOND PROJECT LIST REFERENCE: 6.4 Project completed ahead of schedule on August 8, Page 24
26 Elementary Classroom Improvements Interactive Whiteboards and Sound Assist System Installation Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the installation April 29, Phase 4 and 5 schools were the final elementary schools to receive interactive whiteboards and sound assist systems. Strong Schools Bond Funds $2,004,889 Other $0 Total $2,004,889 Supplies $0 Contracts & Services $325,488 Construction & Equipment $1,679,401 Soft Costs Contingency $0 Total $2,004,889 Percent of Expended 93.0% Current Phase: Complete May 15, 2011 Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) November 9, 2010 November 23, 2010 Bid Opening February 25, 2011 Award of Contract (1) March 8, 2011 Notice to Proceed March 9, 2011 Completion May 15, 2011 C. BOND PROJECT LIST REFERENCE: All SmartBoards and Lightspeed sound systems installed. Page 25
27 Palo Alto High School Multi Use Field The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9, Strong Schools Bond Funds $2,609,680 Other $1,007,255 Total $3,616,935 Supplies $1,506 Contracts & Services $698,293 Construction & Equipment $2,916,682 Soft Costs Contingency $454 Total $3,616,935 Percent of Expended 100.0% Change Order Contingency Starting Contingency Balance $269,300 Remaining Contingency Balance $230,579 Percent of Changes 1.7% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy February 1, 2011 Architect Contract (2) September 30, 2008 October 14, 2008 Conceptual Design (2) Schematic Design (2) November 18, 2008 December 09, 2008 Submit to DSA March 19, 2009 Approval by DSA September 30, 2009 Authorize to Bid (2) February 24, 2009 March 17, 2009 Bid Opening March 16, 2010 Award of Contract (1) April 7, 2010 Notice to Proceed June 1, 2010 Substantial Completion January 31, 2011 Planned Occupancy February 1, 2011 C. BOND PROJECT LIST REFERENCE: 4.14 Field was open for use on February 1, Page 26
28 Gunn High School Industrial Arts Addition and Renovation This facility was available for instruction in January DSA closeout received on July 18, Strong Schools Bond Funds $5,082,402 Other $0 Total $5,082,402 Salaries and Benefits $1,061 Supplies $88,985 Contracts & Services $1,000,861 Construction & Equipment $3,991,495 Soft Costs Contingency $0 Total $5,082,402 Percent of Expended 99.3% Change Order Contingency Starting Contingency Balance $349,000 Remaining Contingency Balance $141,967 Percent of Changes 41.6% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy January 4, 2010 Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA June 17, 2008 Approval by DSA December 24, 2008 Authorize to Bid (2) October 14, 2008 October 28, 2008 Bid Opening December 16, 2008 Award of Contract (1) December 24, 2008 Notice to Proceed January 6, 2009 Substantial Completion November 25, 2009 Planned Occupancy January 4, 2010 C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11 The building occupied as scheduled, and the project completed within budget. Page 27
29 Gunn High School Aquatic Center This facility was available for use in July 2009, and has been closed out with DSA. Strong Schools Bond Funds $4,865,423 Other $0 Total $4,865,423 Supplies $0 Contracts & Services $647,169 Construction & Equipment $4,218,253 Soft Costs Contingency $0 Total $4,865,423 Percent of Expended 99.9% Change Order Contingency Starting Contingency Balance $389,887 Remaining Contingency Balance $195,148 Percent of Changes 49.9% (Change Orders + Construction Change Directives vs. Original Contract) Current Phase: Occupancy June 15, 2009 Architect Contract (2) Conceptual Design (2) Schematic Design (2) Submit to DSA December 11, 2007 Approval by DSA April 24, 2008 Authorize to Bid (2) April 8, 2008 April 22, 2008 Bid Opening May 28, 2008 Award of Contract (1) June 4, 2008 Notice to Proceed December 6, 2008 Substantial Completion June 15, 2009 Planned Occupancy June 15, 2009 C. BOND PROJECT LIST REFERENCE: 3.12 This project completed within budget. Page 28
30 Middle School Pre Design Jordan, J.L. Stanford and Terman AEDIS presented recommended concept plans for each campus to the Board of Education for approval on September 8, which became the program documents for the new projects at each campus. These projects for pre design work have been closed, and funds will be transferred to the program contingency on June 14, Strong Schools Bond Funds $56,488 Other $0 Total $56,488 Supplies $0 Contracts & Services $56,488 Construction & Equipment $0 Soft Costs Contingency $0 Total $56,488 Percent of Expended 96.8% Current Phase: Complete Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) June 23, 2009 September 8, 2009 Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: This project has been completed. Board approval received on September 8, Page 29
31 Garland Elementary School Campus Modernization The Board of Education has put new development for Garland on hold until a growth plan is established for the elementary schools. The board voted to terminate the lease with Stratford School in June 2011, so that future plans for growth at the elementary schools can begin on this campus as early as June Strong Schools Bond Funds $22,178,544 Other $0 Total $22,178,544 Supplies $0 Contracts & Services $3,915,789 Construction & Equipment $17,400,000 Soft Costs Contingency $862,755 Total $22,178,544 Percent of Expended 1.3% Current Phase: On Hold Architect Contract (2) October 28, 2008 October 30, 2008 Conceptual Design (2) February 10, 2009 February 24, 2009 Schematic Design (2) June 2, 2009 June 23, 2009 Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: 1.1, This project has been placed on hold. Page 30
32 Elementary School Teaching Walls Phase 1 Schools The district placed this project on hold after review of the implementation of other classroom improvements, as recommended by the elementary school principals. This project has been renamed Elementary Classroom Improvements (see Capital Projects summary below). Strong Schools Bond Funds $0 Other $0 Total $0 Supplies $0 Contracts & Services $0 Construction & Equipment $0 Soft Costs Contingency $0 Total $0 Percent of Expended 0% Current Phase: Project Renamed. See Classroom Improvements Project Architect Contract (2) September 30, 2008 October 14, 2008 Conceptual Design (2) Schematic Design (2) Submit to DSA Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: 1.9 This project has been renamed Elementary Classroom Improvements (see Capital Projects summary above). Page 31
33 High School Master Plan Palo Alto HS and Gunn HS The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed, with funds transferred to the respective campus reserve funds. Strong Schools Bond Funds $285,387 Other $0 Total $285,387 Supplies $0 Contracts & Services $285,387 Construction & Equipment $0 Soft Costs Contingency $0 Total $285,387 Percent of Expended 86.2% Current Phase: Master Planning Architect Contract (2) March 31, 2009 April 14, 2009 Initial Master Plan Approval (2) September 8, 2009 September 22, 2009 Paly CEQA Approval (2) February 9, 2010 February 23, 2010 Gunn Master Plan Update (2) March 23, 2010 April 6, 2010 Gunn CEQA Approval (2) April 27, 2010 May 11, 2010 Master Plan Revision Approval (2) September 14, 2010 Paly MP Revision Approval (2) October 9, 2010 Gunn MP Revision Approval (2) October 12, 2010 C. BOND PROJECT LIST REFERENCE: , Group 2 project planning at the high schools will re commence in fall Page 32
34 Hoover Elementary School Pre Design This project has been put on hold until a growth plan is established for the elementary schools. Strong Schools Bond Funds $70,550 Other $0 Total $70,550 Supplies $0 Contracts & Services $70,550 Construction & Equipment $60 Soft Costs Contingency $0 Total $70,550 Current Phase: On Hold Architect Contract (2) April 27, 2010 May 11, 2010 Conceptual Design (2) November 9, 2010 Schematic Design (2) Submit to DSA Approval by DSA Percent of Expended 100.0% Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: , Project is currently on hold. Page 33
35 Elementary Classroom Improvements Phase 1 Barron Park and El Carmelo DSA comments were returned to Gelfand for Phase 1 plans that include new lighting, adding operable windows and coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary schools. The authorization to bid has been placed on hold pending further discussions with the BOE about elementary growth planning. Strong Schools Bond Funds $2,004,889 Other $0 Total $2,004,889 Supplies $0 Contracts & Services $325,488 Construction & Equipment $1,679,401 Soft Costs Contingency $0 Total $2,004,889 Percent of Expended 93.0% Phase 1 Schools: Barron Park and El Carmelo Current Phase: On Hold Architect Contract (2) June 8, 2010 June 22, 2010 Conceptual Design (2) Schematic Design (2) November 9, 2010 December 7, 2010 Submit to DSA December 23, 2010 Approval by DSA Authorize to Bid (2) Bid Opening Award of Contract (1) Notice to Proceed Substantial Completion Planned Occupancy C. BOND PROJECT LIST REFERENCE: This project has been placed on hold. Page 34
36 Numbers Added EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. OHS WEST: A-1
37 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. OHS WEST: A-2
38 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. OHS WEST: A-3
39 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. OHS WEST: A-4
Through. June Current Strong Schools Bond Capital Improvement Projects. Prepared by
MONTHLY PROGRESS REPORT Through June 2012 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive
More informationThrough. November Current Strong Schools Bond Capital Improvement Projects. Prepared by
MONTHLY PROGRESS REPORT Through November 2010 Current Strong Schools Bond Capital Improvement Projects Prepared by O Connor Construction Management, Inc. & Gilbane Building Company TABLE OF CONTENTS Executive
More informationMONTHLY PROGRESS REPORT
MONTHLY PROGRESS REPORT Through May 2018 Strong Schools Bond Capital Improvement Projects Prepared by fs3 Hodges 1 TABLE OF CONTENTS Executive Summary page 3 Attachment 1 Consolidated Expenditure Report
More informationDEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION
DEL MAR UNION SCHOOL DISTRICT TECHNOLOGY & 21 ST -CENTURY LEARNING INITIATIVE BOND PROJECT DESCRIPTION The Board of Trustees of Del Mar Union School District ("District") has evaluated the need to acquire,
More informationBoynton High School & Blackford Site
Boynton High School & Blackford Site Balance (E- D) 980075 Blackford Campus Repairs (Asphalt, Plaster, Complete 100% 07/16/18 10/05/18 $725,367.67 $735,233.50 $352,463.56 -$9,865.83 $382,769.94 4 980066
More informationCompleted. Project. Melbourne High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project
More informationCupertino Union School District
Cupertino Union School District Update For Citizens Bond Oversight Committee September 21, 2016 WORK IN PROGRESS 1 STEVENS CREEK KINDERGARTEN CLASSROOM STEVENS CREEK KINDERGARTEN CLASSROOM 2 STEVENS CREEK
More informationIndependence Adult Center
Campus Master Plan March 15, 2004 Master Plan Contents Volume I: District Master Plan Andrew P. Hill High School Campus Master Plan Foothill High School Campus Master Plan Independence High School Campus
More informationMeasure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014
Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014 Measure T DEFINED: Measure T is a local ballot measure on the November 2014 ballot seeking voter authorization
More informationSanta Teresa High School
Santa Teresa High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan Santa Teresa High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew
More informationSCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA
SCHEDULE PALO ALTO HS MEETING SCHEDULE AND AGENDA 25 August 2009 All meetings are at 3:15 p.m. unless otherwise noted. Meeting dates are scheduled in advance and dates without agendas may or may not be
More informationJames Lick High School
James Lick High School Campus Master Plan March 15, 2004 Volume II: Campus Master Plan James Lick High School Master Plan Contents Volume I: District Master Plan Volume II: Campus Master Plan Andrew P.
More informationBOARD OF TRUSTEES OCTOBER 13, 2014
Measure E BOARD OF TRUSTEES OCTOBER 13, 2014 FACILITIES UPDATE Measure Q 1 RECENTLY COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements Building G Renovation Artesia Street Improvements Property
More informationAZUSA UNIFIED SCHOOL DISTRICT
AZUSA UNIFIED SCHOOL DISTRICT BOARD STUDY SESSION June 9, 2014 EVALUATION OF STATUS OF FACILITES AND FUTURE NEEDS NEEDS vs. FUNDING SETTING PRIORITIES 5) OTHER ADDITIONAL IMPROVEMENTS 4) OTHER ARCHITECTURAL
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction March 2010 Installation of exterior masonry and siding panels continues on the classroom wings. Library windows are complete. Window and storefront
More informationEL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN
EL CAMINO COLLEGE Facilities Master Plan Report November 2008 PROJECTS IN DESIGN I. Math, Business & Allied Health Building (MBA) The scope of this building is the construction of a new building at the
More informationFrost Technical Center
Frost Technical Center 1955 Greenhouses Addition Various other additions and renovations Provide site security improvements Provide improved Admin area field of view to site entrance Provide security camera
More informationELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015
ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015 TABLE OF CONTENTS PROGRAM SUMMARY DESIGN EXPLORATION EXISTING SITE PLAN - ANALYSIS DEMOLITION SITE PLAN PROPOSED SITE PLAN PROPOSED FLOOR PLANS DEMOLITION
More informationChino Valley Unified School District Monthly Construction Update
h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start:
More informationLong Term School Funding Program Measure M Component: Citizen s Oversight Committee Report
Moreno Valley Unified School District Long Term School Funding Program Measure M Component: Citizen s Oversight Committee Report November 19, 2015 District Long Term School Funding Program Revenue Sources
More informationGREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015
GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015 TABLE OF CONTENTS Bid Package 1 Crockett Elementary School Additions and Renovations 3 L.P. Waters Early Childhood Center Renovations
More information*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.
SECONDARY SCHOOLS Kirby Middle School Demolish 300, 400, and 500 buildings partial Change in total rebuild design New academic building - 33 classrooms *Rent portables for temporary classrooms partial
More information27 January 2011, 3:30 pm-5:00 pm
PALO ALTO HIGH SCHOOL Palo Alto Unified School District MEETING NOTES DATE: SUBJECT: ATTENDEES: 27 January 2011, 3:30 pm-5:00 pm ATHLETIC FIELD IMPROVEMENTS SUBCOMMITTEE MEETING NO. 6 Sign-in sheet (attached)
More informationN o v e m b e r
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE N o v e m b e r 2 0 1 7 Agenda Overview of the Bond 2017 Update 2018 Work 2 Agenda Overview of the Bond 2017 Update 2018 Work 3 Overview of Bond Why
More informationPROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations
Project Update Project Update September 8, 2006 November 6, 2009 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Ed Schwartz Project Budget Project
More informationScripps Ranch High School
Scripps Ranch High School 10410 Treena St. San Diego, CA 92131 Sub-district: B Cluster: Scripps Ranch Year School Opened: 1993 Grades: 9-12 4 3 1 2 1 2 3 4 Sustainable Technologies Buildings Synthetic
More informationSANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016
FACILITIES COMMITTEE MEETING OCTOBER 18, 2016 1 ACTIVE PROJECTS Santa Ana College Central Plant, Infrastructure and Mechanical Upgrades 2 COMPLETED PROJECTS Santa Ana College Perimeter Site Improvements
More informationOhlone Community College District
Bond Measure G March 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Closeout Progress
More information2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:
MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, 2007 North Medford High School: Project Summary: Renovate and add new addition based on facility evaluation and design.
More informationCompleted projects. Projects in progress. Program developments
1 Completed projects Projects in progress Program developments 2 Relocation of District administrative offices Interim housing (classrooms and PE facilities) at Cupertino and Lawson Middle Schools Site
More informationWissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017
Wissahickon School District Natatorium & Central Plant Project Project Update March 27, 2017 Project Features 1. New central plant and receiving area to serve current High School and future Master Plan.
More informationMCER Study for Little Powder K-8
MCER Study for Little Powder K-8 CCSD #1 Little Powder K-8 Weston, WY Wyoming School Facilities Department Cheyenne, WY TSP, Inc. Sheridan, WY May 16, 2016 Table of Contents Introduction 3 Goals and Objectives
More informationWARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y
WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y 2 0 1 8 Agenda Overview of the Bond 2018 Work 2 Agenda Overview of the Bond 2018 Work 3 Overview of Bond Why Now? Interest rates remain at historic
More informationGrossmont-Cuyamaca Community College District Facilities Construction Update
Grossmont-Cuyamaca Community College District Facilities Construction Update September 13, 2016 Presented by Penny McGrew Program Manager Gafcon, Inc. Bond Program Update Agenda Districtwide Energy Conservation
More informationOhlone Community College District
Bond Measure G February 2014 Prepared by: Contents Section 1 Section 2 Section 3 Section 4 Section 5 Executive Summary Project Summary Design Progress Construction Progress Quick Fix Projects Schedule
More informationMerritt Island High School
Project Project Update Update September April July 02, 8, 2010 2008 8, 2006 Project Project Manager Manager Anibal Gary Caussade Geiser Field Field Coordinator Bud Paul Mike Ball Friel Henry Mike Henry
More information2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014
2014 MASTER PLANNING PORT ARTHUR INDEPENDENT SCHOOL DISTRICT Revised, August 5, 2014 PROPOSED IMPROVEMENTS A. Replace Sam Houston Elementary School with a new facility to house 750 students. (Included
More informationPROJECT LIST ALTERNATIVE #1
PROJECT LIST ALTERNATIVE #1 TEMECULA VALLEY UNIFIED SCHOOL DISTRICT BOND PROJECT LIST To protect the quality of education in schools within the Temecula Valley Unified School District ( School District
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationSeattle Public Schools Building Excellence IV Projects Under Construction
Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee
More informationORANGE VISTA HIGH SCHOOL PHASE I
975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report February 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730 I. Project Location and Description
More informationRevised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi
Original Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 75% Three Story Academic Addition with CTE Gymnasium Addition: Multi-court gym 3 courts
More informationSchool Assessment Report
School Assessment Report School: Morningside Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:29:07 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationSANTA ROSA JUNIOR COLLEGE
EXPENDITURES Eligible Bond Program Costs 1,363,848 451,690 622,090 74,757 10,295 85,053 2,522,681 RENOVATION AND MODERNIZATION Upgrade classrooms, laboratories, support service space at all locations 298,139
More informationRepair & Replacement Study
Donald Lum Elementary School Repair & Replacement Study 23 January 2018 ALAMEDA UNIFIED SCHOOL DISTRICT 1495.05 1 PROJECT BACKGROUND Overview of Engineering Studies Miller Pacific Geotechnical Report -
More informationHealth Life Safety Survey and Master Facilities Plan
Health Life Safety Survey and Master Facilities Plan Community Presentation Board Meeting June 22, 2015 June 22, 2014 Board Presentation Overview and Summary of the Health Life Safety Survey and Master
More informationJanuary 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT
January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationHeritage High School
Project Update April 10, 2010 Project Manager Dennis Bonny Field Coordinator Halsey Chandler Project Budget $64,665,000 - GMP $80,000,000 Total Budget Design Criteria Professional Schenkel Shultz Delivery
More informationBLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS
BLIND BROOK-RYE UFSD SCHOOL FACILITIES PLANNING SECOND UPDATE ON RECOMMENDED PROJECTS January 9, 2017 SUMMARY OF OCTOBER 17 TH PRESENTATION 1. Five-Year Capital Facilities Plans & 15-year History 2. 2016-2020
More informationFacilities and Planning Department Measure E Update March 2017
State Seismic Mitigation Program (SSMP) The District s application for SSMP funds for Horace Mann Building A will be reviewed for approval by the State Allocation Board at its next scheduled meeting on
More informationFULL TEXT BALLOT PROPOSITION OF THE AMADOR COUNTY UNIFIED SCHOOL DISTRICT BOND MEASURE ELECTION NOVEMBER 6, 2018
FULL TEXT BALLOT PROPOSITION OF THE AMADOR COUNTY UNIFIED SCHOOL DISTRICT BOND MEASURE ELECTION NOVEMBER 6, 2018 The following is the full proposition presented to the voters by the Amador County Unified
More informationGrossmont-Cuyamaca Community College District Facilities Construction Update
Grossmont-Cuyamaca Community College District Facilities Construction Update April 17, 2018 Presented by Fred Parker Program Manager Gafcon, Inc. Agenda Grossmont College Update Cuyamaca College Update
More informationBARNARD ELEMENTARY SCHOOL
INITIAL YEAR BUILT 2002 BUILDING AREA 67,000 SF CURRENT PROGRAM CAPACITY 520 ENROLLMENT 2008 329 WARD 4 PROPOSED PROGRAM CAPACITY 450 Site Plan BARNARD - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationUpdate on FCPS Construction/Renovation Projects. June 2016
Update on FCPS Construction/Renovation Projects Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000
More informationHIDDEN VALLEY ELEMENTARY SCHOOL
SCHOOL DATA Address: 3435 Bonita Vista Santa Rosa, CA 95404 Established: 975 Permanent Classrooms: 29 Portable Classrooms: 8 Building Area: Site Area: Satellite Building Area: Satellite Site Area: 48,802
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationSchool Assessment Report
School Assessment Report School: Sutton Middle School (Powers Ferry) Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:32:59 AM FOR OFFICIAL USE ONLY Final School
More informationCapital Projects Report
Capital Projects Report t o t h e Board of Trustees of the Sierra Sands Unified School District December 11, 2014 1 BURROUGHS HIGH SCHOOL Address 500 E. French Ave. Ridgecrest, CA 93555 Project Maas Steve
More informationNALLE ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1950 BUILDING AREA 83,900 SF CURRENT PROGRAM CAPACITY 460 ENROLLMENT 2008 372 WARD 7 PROPOSED PROGRAM CAPACITY 400 Site Plan NALLE - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More information10 Year Plan. Facilities Planning Guide. December 15, 2014
10 Year Plan Facilities Planning Guide December 15, 2014 October 21, 2014 Facilities Study Session o Existing funding sources established relating to facilities Routine Restricted Maintenance Account (RRMA)
More informationGuam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY
Guam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY 2010-2011 October 1, 2010 to September 30, 2011 On August 3, 2011, the US Department of Education
More informationCazenovia Central Schools Proposed Building Project Information Session December 17, 2013
Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013 Information Session Agenda Background. Scope of work and why these renovations are important. Project cost. How
More informationArchitectural Services Consultant Registration Form
Architectural Services Consultant Registration Form Send three copies of the completed registration form to: San Bernardino Community College District, Facilities Project Management, Attn: Scott Stark,
More informationFREMONT UNIFIED. Thornton Middle School Conversion S C H O O L D I S T R I C T. Quattrocchi Kwok Architects. Sept 26, 2018
FREMONT UNIFIED S C H O O L D I S T R I C T Thornton Middle School Conversion Quattrocchi Kwok Architects Sept 26, 2018 1 Transforming Thornton Incoming 6 th graders in year 2021/22 Student population
More informationCEFPI Monthly Meeting
CEFPI Monthly Meeting LISD School Construction Cost Information Background Information School Cost Information How Does LISD Compare? Other District Comparisons Background Information Cost Discussion Type
More informationSYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community.
SYLVAN MIDDLE SCHOOL The mission of Sylvan Middle School is consistent with that of the San Juan Unified School District, which is to inspire each student tosucceed and responsibly contribute to a radically
More informationCONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO
CONSTRUCTION REPORT TSC NO. 21319.1 October 2014 Zionsville Community Schools Zionsville, Indiana The SKILLMAN Corporation Project Administration Construction Management Zionsville Community Schools 2005
More informationSchool Assessment Report
School Assessment Report School: Carver High School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:23 AM FOR OFFICIAL USE ONLY Final School Assessment Report
More information(Continued on next page)
FULL TEXT OF BALLOT MEASURE E LONG BEACH UNIFIED SCHOOL DISTRICT REPAIR AND SAFETY MEASURE. To improve outdated classrooms/neighborhood schools by: improving technology/labs/career education classrooms/electrical
More informationFACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015
FACILITIES PROJECTS UPDATE BOARD OF EDUCATION August 11, 2015 AGENDA Measure R Bond Projects Fund 40 Capital Projects Maintenance Projects MEASURE R BOND PROJECTS KINDERGARTEN MODERNIZATIONS PROGRAM BUDGET:
More informationProgram Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement
Projects under Construction Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders:
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationPrepared By Construction Manager September 2011
Prepared By: Construction Manager September 2011 INTRODUCTION P.J. Dick Incorporated is pleased to present the Upper St. Clair Board of School Directors with the following Construction Report for the Fort
More informationUpdate on FCPS Construction/Renovation Projects. August 2016
Update on FCPS Construction/Renovation Projects New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost:
More informationBerryessa Union School District Measure L Bond Construction Program
Berryessa Union School District Measure L Bond Construction Program Board of Trustees Update December 8, 2015 Introduction The following presentation is intended to provide the Board of Trustees with an
More informationPHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016
PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016 1 ACTIVE PROJECTS Santa Ana College Chavez Hall Renovation Temporary Village Phase 2 Santiago Canyon College Orange Education Center
More informationCapital Projects Update
Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being
More informationSafety Update Crossing study is in final review stages. Facilities Update Construction Progress
Major Projects Update September 2017 Prepared by Business and Operations September 11, 2017 Transportation Update As of 9/6/17 we have 4,803 students registered for busing, up 643 from last month s update.
More informationCapital Projects Progress Report. January Presented by
Capital Projects Progress Report January 2019 Presented by February 8, 2018 Loretta Orologio District Superintendent Churchville-Chili Central School District 139 Fairbanks Road Churchville, New York 14428
More informationUpper Adams School District Facility Study Presentation Part 2 November 17, 2016
Upper Adams School District Facility Study Presentation Part 2 November 17, 2016 Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects Agenda Part 1 Current
More informationBiddeford School Department
Biddeford School Department 5 Plan Buildings, Grounds & Equipment Table of Contents: John F Kennedy Memorial School Page: 1-2 Biddeford Primary School Page: 3-4 Biddeford Intermediate School Page: 5-6
More informationJanuary 2017 Project Update
January 2017 Project Update Overall Referendum Project Status: ON SCHEDULE/ON BUDGET All elements of the project completed to date have been completed on or ahead of schedule and final costs were under
More informationCORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting
CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan Community Information Meeting October 2017 AGENDA Meeting Objectives Draft Plan Overview School Improvements for specific site Feedback/Listening
More informationDENNIS TOWNSHIP FEASIBILITY STUDY
DENNIS TOWNSHIP FEASIBILITY STUDY October 29, 2015 TABLE OF CONTENTS I. INTRODUCTION II. EXECUTIVE SUMMARY III. GENERAL FACILITY DATA A. Primary School B. Elementary / Middle School IV. FACILITIES ASSESSMENT
More informationfacilities plan community input session Transylvania County Schools
facilities plan community input session Transylvania County Schools Facilities Plan community input session Where We ve Been Are Transylvania County Schools Facilities Plan community input session Where
More informationMINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011
MINUTES OF THE MEETING SDSU CENTRAL HEATING PLANT BOILER REPLACEMENT AND PLANT UPGRADES June 17, 2011 The Building Committee for the SDSU Central Heating Plant Boiler Replacement and Plant Upgrades met
More informationRAYMOND EDUCATION CAMPUS
INITIAL YEAR BUILT 1924 BUILDING AREA 73,600 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 302 WARD 1 PROPOSED PROGRAM CAPACITY 600 Site Plan RAYMOND - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationProgram Update. Chino Health Science Parking Lot
Projects under Construction Chino Health Science Parking Lot Architect: MDA Johnson Favaro Contract Amount: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction
More informationReport No F Meeting Date: June 22, 2017 REVISED ATTACHMENT BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA
Report No. 1203-F Meeting Date: June 22, 2017 REVISED ATTACHMENT BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA Topic: APPROVAL OF MTT PRIORITY LIST OF PROJECTS RECOMMENDATION:
More informationSchool Assessment Report
School Assessment Report School: Cascade Elementary School Report: Nov 17, 2015 Condition Assessment: Suitability Assessment: Generated: 11/17/2015 10:37:55 AM FOR OFFICIAL USE ONLY Final School Assessment
More informationStephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018
Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018 TABLE OF CONTENTS Description Page Construction Summary 1 1 - Residence Life Operations
More informationInspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.
Purpose 355 West Queens Road Single Family New Construction Required Inspection Stages Master Requirement GEN 110 Building Department: 604-990-2480, building@dnv.org, fax: 604-984-9683 The following procedure
More informationBALLOU SENIOR HIGH SCHOOL
INITIAL YEAR BUILT 1960 BUILDING AREA 271,300 SF CURRENT PROGRAM CAPACITY 1565 ENROLLMENT 2008 9-12 (1,252) STAY (753) WARD 8 PROPOSED PROGRAM CAPACITY 1200 Site Plan BALLOU - 1 PROPOSED PROGRAM PROFILE
More informationCapital Improvement Program Monthly Status Report
Santa Teresa High School New Concession Building 2300 Located in the ball fields zone of the Santa Teresa campus, Concession Building 2300 will be sited around the concept of central collective use, being
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationProject Update Prop M Bond Series A & B
Update Prop M Bond Series A & B Name Independent Citizen s Oversight Committee Report March 2012 Construction Scope Status 2071001 Natural Science Bldg. Completion & Equipment 2102002 PC North Education
More informationPROPOSITION R Citizen s Bond Oversight Committee
PROPOSITION R Citizen s Bond Oversight Committee June 15, 2011 Southwestern Community College District 900 Otay Lakes Road, Room L246 Chula Vista, CA 91910 Proposition R AGENDA 1. Call to Order / Roll
More informationCapital Improvement Program Monthly Status Report
Santa Teresa High School New Concession Building 2300 Located in the ball fields zone of the Santa Teresa campus, Concession Building 2300 will be sited around the concept of central collective use, being
More informationCoos Bay Best Bond Cost Breakdowns
Coos Bay Best Bond Cost Breakdowns Overview [For itemized breakdown by school, see following pages.] Harding: New 7 th /8 th grade school on Harding site, including second gym: $18,440,000 Demotion of
More information