I-91 Viaduct Public Information Briefing
|
|
- Luke Conley
- 6 years ago
- Views:
Transcription
1 I-91 Viaduct Public Information Briefing Project File No MassDOT Contract No Briefing no. 9 September 13, 2017
2 Agenda Welcome and Presenter Introductions Update on Construction and Demolition Activities (St age 2) Next: Completion of Stage 2B / start of Stage 3 Traffic Management & Mitigation Continued Public Involvement and Outreach
3 The Joint Venture Constructing the Project J.F. White Contracting Co. A General Contractor performing heavy civil work in Massachusetts for over 90 years. Schiavone Construction Co. A General Contractor performing heavy civil work in the northeast region for over 50 years.
4 Project Limits
5 Project Scope Rehabilitation includes the following: Complete deck replacement Painting of structural steel, replacement of bearings, structural steel repairs, concrete substructure repairs Improved bridge drainage and highway lighting (on the highway, surface streets under the viaduct, upper levels of the north and south garage, and the Columbus Avenue railroad underpass) Other safety improvements, such as at the I-291/I-91 merge Comprehensive Traffic Management
6 Fast Facts Viaduct length is approximately ¾ mile Over 22,350 cubic yards of concrete for bridge deck and barriers over 18,500 cubic yards placed to date Over 7.2 million pounds of reinforcing steel nearly 7 million pounds placed to date Over 450 bearing replacements over 362 replaced to date 27 subcontractors to date In excess of 100 workers per day on average of whom over 20 are from Springfield and over 80 are from the Greater Springfield area and Western Mass.
7 Fast Facts (continued) 246 separate concrete deck placements required. 230 completed to date Approximately 21,000 feet (4 miles) of concrete barrier required. over 14,000 feet installed to date 12,500 feet of snow fence required feet installed to date 65 highway lighting fixtures required. 6 installed to date
8 Construction Schedule
9 Definition of Full Beneficial Use I-91, I-291 & Assoc. Ramps The majority of the contract work has been completed and the asset(s) has been opened for full multi-modal transportation use, except for limited contract work items that do not materially impair or hinder the intended public use of the transportation facility. All anticipated lane takings have been completed. This includes completion of superstructure work, bridge barrier, permanent guardrail, removal of temporary concrete barriers, final paving, permanent traffic markings and signage, permanent lighting.
10 Definition of Substantial Completion The majority the roadway and utility work is complete on the municipal streets and the remaining work not directly requiring lanes taken on the I-91, I-291, and the associated lanes is complete. Completed work includes all structural steel repairs, painting of structural steel, bearing replacements, installation of municipal street lighting, final paving and traffic markings at the municipal street level, Restoration of all disturbed areas.
11 Definition of Field Completion All physical contract Work is complete including punchlist. The Contractor has fully demobilized from field operations.
12 Stage 2 Deck Demolition and Reconstruction Began in All deck demolition is COMPLETE. Southbound deck concrete placements completed on all spans. Northbound - all but 3 spans have had concrete placements completed. Exit/entrance ramps all ramps have completed concrete deck placements except for exit 8 which will be completed this month. Exit 9 reopened in June 2017.
13 Stage 2B Progress Photos
14 Photo: Courtesy of White-Schiavone J.V.
15 I-91 NORTH I-91 SOUTH Photo: Courtesy of White-Schiavone J.V.
16 I-91 SOUTH Photo: Courtesy of White-Schiavone J.V.
17 Finalizing rebar installation for the last two decks on I-91 Southbound
18 Wetted burlap waiting to be placed on the new deck concrete. I-91 Southbound
19 Completed rebar installation deck placement underway I-91 Sout h.
20 Deck placement underway I-91 North.
21 Deck placement underway I-91 North.
22 Continuing pier repairs - Ramp M (Exit 8 t o I- 291).
23 Projec t Progress
24 Next Steps (3 month look-ahead) Complete remaining concrete deck placements. Complete remaining concrete barrier placements Complete highway lighting and snow fence installations. Complete all northbound paving, striping and signage. Continue pier repairs and bearing replacements. Continue painting of steel beams. Complete Stage 2B and reopen all northbound lanes and ramps. Reopen Exit 6 southbound.
25 Traffic Mitigation Police details are provided at critical intersections during peak periods, if needed. Comprehensive monitoring program of key corridors/intersections traffic plan is updated when needed, based on impacts. Real Time Traffic Management System (RTTM) continuously updated message boards to deliver information in real-time. RTTM cameras are monitored at the project, district and municipal levels. Dynamic Merge pilot program in use at the I-91 SB merge. (Due to the current lane configuration, it is continually set in the late merge mode). Incident Response Operations (IRO) plan in effect.
26 Incident Response Operations Contract requires 3 light duty tow trucks and one heavy duty tow truck available at all times. There is a required response time of 10 minutes or less (20 minutes for the heavy duty tow truck). Incident response area covers I-91 from the South End Bridge to I-391. Also includes East Columbus, West Columbus and Hall of Fame Avenues. Hookup and removal of the vehicle from the scene carries no charge to the operator. To dat e, 86 light-duty and 5 heavy-duty tows have been made under the IRO plan.
27 Speed Limits Speed reduced from 50 to 45 MPH approaching the work zone, with 40 mph limit in the zone Double fines in the work zone State Police enforcement for driver and construction team safety
28 MassRIDES Programs Online Ride Matching Commuter Incentives Emergency Ride Home NuRide.com/MassRIDES
29 Encouraging Mode Shift MassRIDES = Statewide Travel Options Program Carpool, vanpool, transit, bike, walk, telework Reduce traffic congestion Reduce emissions Employers - outreach and worksite services Commuters - ridematching, incentives, promotions and marketing
30 MassRIDES Outreach 325+ partner organizations, including: MassMutual, Baystate Medical Center, American International College, City of Springfield, Peter Pan Bus Company, Pioneer Valley Planning Commission, Pioneer Valley Transit Authority, Springfield Technical Community College, United Personnel- Springfield, Western New England University, Westfield State University 465,000+ commuters Worksite focus commute travel
31 Taylor Rock
32 Public Involvement Additional public meetings, as needed Regularly updated project website: Project fact sheets & community briefings Frequent notices and e-blasts on traffic changes during construction and responses to inquiries Project updates on social media English and translated materials and interpreters available upon request
33 THANK YOU! Contact Us S ign up on the project website for information and updates: Send questions or concerns to: i91viaduct@state.ma.us Questions?
I-91 Viaduct Public Information Briefing
I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:
More informationWhittier Bridge/I-95 Improvement Project. Public Information Meeting
Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project
More informationSafety. Introduction. Total System
Safety Introduction Ohio is the 35 th largest state in the nation based on geographic size, however it carries the 5 th largest total traffic volume and the 4 th largest truck traffic volume. With such
More informationMaine Turnpike Authority FINAL 4-year Capital Investment Plan ( )
Total preliminary Value for Project shown in initial year is for project duration. Projects have been listed in each year there are major Preliminary 4.8 Beech Ridge Road Underpass Repairs York $410,000
More informationDISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS
DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS Construction Impact Mitigation Strategy Guidelines for Major Developments The District of North Vancouver
More informationProject Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce
Project Team D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce D6 Design Project Manager Ali Toghiani, P.E. CEI: AIM Engineering and Surveying Francis Chin,
More informationAREAWIDE BRIDGE REPLACEMENT AND REHABILITATION
CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally
More informationIn Service Replacement of Box Girder Bottom Slab
In Service Replacement of Box Girder Bottom Slab WSDOT Bridge No. 5/537S - Span 11 Craig R. Boone, P.E., S.E. Lynn Peterson Secretary of Transportation 2015 Western Bridge Engineers Seminar Reno, Nevada
More informationPROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT
PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform
More informationRAIL-HWY PROJECT DEVELOPMENT GUIDE AND
RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT
More informationThe Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges
The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges I. ABSTRACT Keith A. Riniker, PE, PTOE This paper presents the Folded Interchange design and compares
More informationODOT Asset Management Plan 0
ODOT Asset Management Plan 0 Table of Contents Executive Summary... 1 ODOT s Experience with Asset Management... 1 A New Way of Doing Business... 2 ODOT s Investment Plans... 3 Moving Forward... 5 1.0
More informationTHE KOSCIUSZKO BRIDGE PROJECT. The New York State Department of Transportation. Page 1
THE KOSCIUSZKO BRIDGE PROJECT The New York State Department of Transportation Page 1 THE KOSCIUSZKO BRIDGE PROJECT Constructed 70 years ago, the existing Kosciusko Bridge serves more than 160,000 vehicles
More informationBusiness Plan for FY14 FY15
Business Plan for FY14 FY15 Commissioner s Message May 2013 The Executive Team and I are pleased to present the new Business Plan for FY 2014-15. This plan builds on the key priorities to deliver our mission:
More informationThe Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.
4 Goals & Objectives INTRODUCTION The 2015-2040 MTP preserves and promotes the quality of life and economic prosperity of the MAB by providing a transportation system consistent with the regional goals.
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)
FY 2018-2027 WIDE TRANSPORTATION IMPROVEMENT PROGRAM NY Susquehanna and Western Rail Line Bicycle/Pedestrian Path DBNUM: NS9803 / UPC: 058018 The 4.8 mile New York, Susquehanna, and Western Railway (NYS&W)
More informationTCATS October 12-Michigan Works 5:30-7pm. NATS October 19-Niles District Library 6-7:30pm
Goal Development Workshop TCATS October 12- Works 5:30-7pm NATS October 19-Niles District Library 6-7:30pm SAFETEA-LU Goals 2035 TwinCATS Goals 2030 TwinCATS Goals 1. Support the economic vitality of the
More informationTable of Contents. List of Appendices
Table of Contents Page Executive Summary 3 Description of Project 3 TMP Roles and Responsibilities 3 Area Engineer 3 Communications Office 4 TMP Monitoring 4 Existing and Future Conditions 4 Traffic Counts
More informationELANA D. FREEDMAN, P.E. Structural Engineer
, P.E. EDUCATION Bachelor of Science, Civil Engineering (L.C. Smith College of Engineering), Syracuse University, 2007 Bachelor of Arts, Philosophy (College of Arts & Sciences), Syracuse University, 2007
More informationState Route 8 Bridge Replacement Project
OPEN HOUSE PUBLIC INVOLVEMENT MEETING Celebration Church 688 Dan Street, Akron, Ohio Tuesday, July 14, 2015 5:00 PM to 7:00 PM State Route 8 Bridge Replacement Project Existing Bridge Future Bridges: Steel
More informationSuccessful Incident Management on a Major Reconstruction Project
Transportation Research Board 81 st Annual Meeting January 13-17, 2002 Washington, DC Successful Incident Management on a Major Reconstruction Project Pacific Motorway Project, Queensland Australia Professor
More informationAnalytical Tools and Decision Support Systems SANDAG I-15 ICM. ITS PA January 30 th, 2014
Analytical Tools and Decision Support Systems SANDAG I-15 ICM ITS PA January 30 th, 2014 Project Partners/Stakeholders National ICM Evaluator National AMS Contractor 2 San Diego I-15 Corridor 21 mile corridor
More informationScarborough Fire Department Scarborough, Maine Standard Operating Procedures
Scarborough Fire Department Scarborough, Maine Standard Operating Procedures Book: Emergency Operations Chapter: Alarm & Response Procedures Subject: 3020 - Safe Vehicle Positioning Revision Date: 7/31/2007;
More informationJANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25
General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO
More informationGLX Project AUGUST 2 4 FMCB MEETING
GLX Project Green Line Extension Project AUGUST 2 4 FMCB MEETING Presentation Overview 1) Project Essentials 2) Funding the Green Line Extension Project 3) The Construction Manager/General Contractor Procurement
More informationATHABASCA RIVER BRIDGE REHABILITATION PROJECT
ATHABASCA RIVER BRIDGE REHABILITATION PROJECT PROJECT INFORMATION Project Name Athabasca River Bridge Rehabilitation Project Location Highway 40 (over the Athabasca River), Entrance, Alberta Year Completed
More informationThe Cost Savings Potential of Sustainability Practices
The Cost Savings Potential of Sustainability Practices The Sustainability Triple Bottom Line The Triple Bottom Line (TBL) means addressing Environmental, Economic and Social Equity dimensions of a project
More informationI-35W Retaining Wall Design Exhibit A - Draft Scope of Work
Background MnDOT, Metro Transit, Hennepin County, and the City of Minneapolis are in the process of developing a project for Interstate 35W between 43 rd Street in Minneapolis and 15 th Street in Minneapolis.
More informationSECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS
SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS Section Page 26-1 GENERAL... 26.1 26-2 PAVEMENT KEYCUTTING... 26.1 26-3 PAVEMENT PLANING... 26.2 26-4 PLANED PAVEMENT CONFORMS... 26.3
More informationMaintenance, Construction & Secondary Roads. Terry Gibson, PE Chief Engineer February 20, 2013
Maintenance, Construction & Secondary Roads Terry Gibson, PE Chief Engineer February 20, 2013 State versus local responsibility Division structure Allocations Flexibility in funding Implications of not
More informationMONITORING IMPLEMENTATION AND PERFORMANCE
12 MONITORING IMPLEMENTATION AND PERFORMANCE The FAST Act continues the legislation authorized under MAP-21, which created a data-driven, performance-based multimodal program to address the many challenges
More informationAIR QUALITY AND CLIMATE CHANGE EVALUATION GUIDANCE
AIR QUALITY AND CLIMATE CHANGE EVALUATION GUIDANCE The following guidance provides additional details regarding the process followed by PSRC to evaluate projects for potential air quality benefits. As
More informationI-495 HOT LANES PROJECT VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY. Dan Staron, P.E. HNTB Corporation MARCH 4, 2010
VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY Dan Staron, P.E. HNTB Corporation MARCH 4, 2010 PRESENTATION OVERVIEW Project Background/Highlights Design Challenges Technical Details Concrete Applications/Details
More informationHUDSON TUNNEL PROJECT
HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen
More information12 Oct Virama Karya presentation on South Coast Highway. Therefore require a new route expressway
in association with Design 151.66 Km (Existing Road Apr. 180 km) 2 OBJECTIVE: The Government of Timor Lestewishes to Engage Consultant to carry out the Preliminary, Detailed Engineering Design and Environment
More informationExposition Light Rail Transit Project
Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009 Phase 1 Project Description 8.6 mile corridor from Downtown
More informationStaff Priority and UPWP Committee Priority List 3/25/2016. ID Proposed Study Name Project Category Tentative Project Cost
Staff and UPWP Committee List 3/25/2016 Projects with Only (No Bottom Non- ) C-2 Safety and Operations at Selected Intersections: FFY 2017 Roadway Network Performance $65,000 Purpose: The purpose of this
More informationDESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION
DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION Vireak Hinh, P.Eng. R.V. Anderson Associates Ltd., Toronto, Canada Jennifer Trimble Region of Halton, Oakville, Canada
More informationAgenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014
Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend
More informationIronton Russell Bridge Project
Construction Update October 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2014
More informationGREENE COUNTY - SR 221(J10) # PROPOSAL:$11.76 PLANS:$ X18:$ X36:$47.10
ASSOCIATED PENNSYLVANIA CONSTRUCTORS Update January 3, 2018 GREENE COUNTY - SR 221(J10) #105392 PROPOSAL:$11.76 PLANS:$4.18 12X18:$5.13 24X36:$47.10 The description and location of the project is as follows:
More informationBridge Preventative Maintenance.Act now before this happens to you! Keith Cooper, P.E. Local Bridge Program Manager
Bridge Preventative Maintenance.Act now before this happens to you! Keith Cooper, P.E. Local Bridge Program Manager 1 Local Bridge Program Asset Management for Local Bridges 2008 started approving Rehabilitation
More informationBenefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway
Benefits of Ultra-High Performance Concrete for the Rehabilitation of the Pulaski Skyway Michael D. McDonagh, P.E., P.Eng., WSP Parsons Brinckerhoff Andrew J. Foden, Ph.D., P.E., WSP Parsons Brinckerhoff
More informationfor Law Enforcement KVE Developed by the Kentucky Transportation Center University of Kentucky in cooperation with the
A Checklist for Law Enforcement Fire & Rescue EMS CRASH SITE Towing KYTC KVE Emergency Management Developed by the Kentucky Transportation Center University of Kentucky in cooperation with the Kentucky
More informationPreferred Elevated Tank Site
Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access
More informationCHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES
CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES 4.0 INTRODUCTION The ability to accommodate high volumes of intersecting traffic safely and efficiently through the arrangement of one or more interconnecting
More information2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement
2 Purpose and Need 2.1 Study Area Interstate 81 (I-81) is relied upon for local and regional travel and interstate travel in the eastern United States. It extends 855 miles from Tennessee to New York at
More informationI-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA
15th International Conference on Managed Lanes I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA Case Study for Funding of Transit Service and Transportation Demand Management
More information2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014
2040 Transportation Policy Plan Conversion to Performance Based Planning Basis 25 th Annual CTS Transportation Research Conference May 21, 2014 1 About the plan Long-range transportation plan for the Twin
More informationMaster RFI List: March 22, 2013 Version # 1, 2 & 3
Master RFI List: March 22, 2013 Version # 1, 2 & 3 1. Can the City confirm the completion and occupancy dates for the Main Street Garage (February 2003?) and Transit Center Garage facilities? Main Street
More informationTOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:
TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be
More informationTRANSPORTATION FACTS. OUR CUSTOMERS: Travel Patterns
OUR CUSTOMERS: Travel Patterns TRANSPORTATION FACTS The more than 6.5 million people in the Commonwealth have many reasons to travel and several ways to get to their destinations. A recent statewide survey
More informationFLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT
FLORIDA DEPARTMENT OF TRANSPORTATION Planning and Environmental Management Office INTERCHANGE MODIFICATION REPORT District 2 1109 South Marion Avenue Lake City, FL 32025-5874 INTERSTATE 10 (SR 8) / SR
More informationRAPID INCIDENT SCENE CLEARANCE (RISC)
Approved: Effective: September 18, 2008 Traffic Engineering and Operations Topic No. 750-030-020-a RAPID INCIDENT SCENE CLEARANCE (RISC) PURPOSE: Rapid Incident Scene Clearance (RISC) is a highly innovative
More informationPima County Travel Reduction Ordinance
Pima County Travel Reduction Ordinance Source: http://www.municode.com/resources/gateway.asp?pid=16119&sid=3 Chapter 17.40 TRAVEL REDUCTION ORDINANCE Sections: Article I. General Provisions 17.40.010 Short
More informationDesign and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.
Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on
More informationCONTINUOUSLY REINFORCED CONCRETE AND UNPAVED ROADS CONDITION SURVEY FIELD MANUAL PUBLICATION 343 APRIL 2017 PUB 343 (4-17)
CONTINUOUSLY REINFORCED CONCRETE AND UNPAVED ROADS CONDITION SURVEY FIELD MANUAL PUBLICATION 343 APRIL 2017 PREPARED BY: BUREAU OF MAINTENANCE AND OPERATIONS ASSET MANAGEMENT DIVISION P.O. Box 3437 HARRISBURG,
More informationRe: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy
Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy Presentation to Executive Committee September 21, 2015 1 Overview Project Background Procurement Options Analysis
More informationDowntown Estes Loop Project Frequently Asked Questions
May 15 th, 2015 Project Status 1) Has Alternative 1 already been selected? Is it a done deal? Response: The NEPA process will proceed with environmental analysis of both the No Action and Alternative 1.
More informationCarpinteria Avenue Bridge Replacement Project Description Introduction
Carpinteria Avenue Bridge Replacement Project Description Introduction The City of Carpinteria is proposing to replace the existing Carpinteria Avenue Bridge over Carpinteria Creek (Br. No. 51C 0172) with
More informationextent feasible. Per the and low constructability,
RELEVANT PUBLIC PROJECTS AND REFERENCES TranTech is proud of its accomplishments in structural engineering. Our staff members have provided design servicess to numerous public agencies on very successful
More informationDynamic Lane Merge Systems
Dynamic Lane Merge Systems Acknowledgements Maryland State Highway Administration University of Maryland, College Park Michigan Department of Transportation Wayne State University Lane Merging Issues Merging
More informationWELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017
WELCOME IL 47 Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017 MEETING PURPOSE MEETING AGENDA 1. Welcome/Introduction 2. Review Previous Public Involvement 3. Process/Schedule
More informationCHAPTER 1 COMMUTE TRIP REDUCTION BASIC INFORMATION
CHAPTER 1 COMMUTE TRIP REDUCTION BASIC INFORMATION COMMUTE TRIP REDUCTION (CTR) OVERVIEW In 1991, the Washington State Legislature passed the Commute Trip Reduction (CTR) Law requiring employers to work
More informationBids JANUARY 25, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $3,600,000)
General Info Number: PROJECT NO. 43-7-05 Description: BRIDGE DECK REPAIR AND REHABILITATION, BOSTON MILLS ROAD OVER OHIO TURNPIKE M.P. 78.0, OLDE EIGHT ROAD OVER OHIO TURNPIKE M.P. 79.5, NICHOLS ROAD OVER
More informationSR 99 Incident Response After- Action Plan
SR 99 Incident Response After- Action Plan Background On June 10, 2014 at 1:52 PM, a pickup truck and a passenger car collided on southbound SR 99 (E Marginal Way S), just south of S Spokane St. The SDOT
More informationWoodburn Interchange Project Transportation Technical Report
Final Report Woodburn Interchange Project Transportation Technical Report Prepared for Oregon Department of Transportation April 212 Prepared by DKS Associates Contents Methodologies... 4 Volume Development...
More informationManagement and Integration of Data and Modeling at Santa Clara County Congestion Management Agency
Management and Integration of Data and Modeling at Santa Clara County Congestion Management Agency VTA Modeling and GIS Group Peter Chen ITE SF Bay Area Annual Modeling Workshop April 29, 2015 Outlines
More informationMAINE MEDICAL CENTER
MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban
More informationOhio Department of Transportation
Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 Ted Strickland, Governor Jolene M. Molitoris, Director THE DEPARTMENT UTILIZES BID EXPRESS (http://www.bidx.com)
More informationApplication of Accelerated Bridge Construction for Local Agencies
Application of Accelerated Bridge Construction for Local Agencies APWA Public Works Conference November 9, 2017 Dorie Mellon Senior Bridge Engineer, Caltrans Matt Randall Senior Engineer, County of Placer
More information5 Recommendations 5.1 LONG-TERM ALTERNATIVES CONSIDERED
5 Recommendations The purpose of the New Bedford-Fairhaven Bridge Corridor Study is to evaluate multi-modal transportation and associated land use issues, develop potential solutions, and to recommend
More informationChapter URBAN & RURAL FREEWAY DESIGN
Chapter 5 URBAN & RURAL FREEWAY DESIGN 5.1 INTRODUCTION This chapter provides standards and guidance for urban and rural freeways on new construction/reconstruction projects. The chapter also provides
More informationI-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010
I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD
More informationADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012
ADOT Yuma District Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012 Active Construction Projects SR 95@ Bill Williams River NWR Rd CAP Intersection US 95, Castle
More informationExecutive Summary October 2017
Executive Summary The King of Prussia Rail Draft Environmental Impact Statement/Draft Section 4(f) Evaluation (DEIS) describes and summarizes the transportation and environmental benefits and impacts of
More informationStructural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options
Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements
More informationSeveral intersection improvements, bicycle-pedestrian improvements, and ITS/signage improvements are recommended for the short- and medium-term.
5 Recommendations 5.1 SUMMARY OF RECOMMENDATIONS The purpose of the New Bedford-Fairhaven Bridge Corridor Study is to evaluate multi-modal transportation and associated land use issues, develop potential
More informationIronton Russell Bridge Project
Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014
More informationDistrict Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016
District Department of Transportation ABC in DC (Accelerated Bridge Construction in Washington, DC) Paul Hoffman October 26, 2016 Ohio Transportation Engineering Conference 2016 Columbus, Ohio Agenda About
More informationConcept of Operations prepared for Minnesota Department of Transportation (MnDOT) for Rural Intersection Conflict Warning Systems II Deployment
Concept of Operations prepared for Minnesota Department of (MnDOT) for Rural Intersection Conflict Warning Systems II Deployment December 22, 2014 Table of Contents 1. Introduction and Concept Overview...1
More informationCOMPANY OFFICER SAFE VEHICLE PRACTICES DURING ON-HIGHWAY INCIDENTS. 3 hours TIME FRAME: LEVEL OF INSTRUCTION: AUTHORITY: BEHAVIORAL OBJECTIVE:
TOPIC: TIME FRAME: LEVEL OF INSTRUCTION: SAFE VEHICLE PRACTICES DURING ON-HIGHWAY INCIDENTS 3 hours II AUTHORITY: BEHAVIORAL OBJECTIVE: Condition: Behavior: Standard: A written quiz The student will confirm
More informationSustainability Strategies for Highway Construction: A Case Study of ADOT s Piestewa SR51 HOV Widening Project
Sustainability Strategies for Highway Construction: A Case Study of ADOT s Piestewa SR51 HOV Widening Project Jacqueline D. Thompson, M.U.E.P. and Howard H. Bashford, Ph.D., P.E. Arizona State University
More informationCITY OF JACKSONVILLE 2030 MOBILITY PLAN STUDY UPDATE GOALS, OBJECTIVES, AND PERFORMANCE MEASURES PREPARED FOR: CITY OF JACKSONVILLE
CITY OF JACKSONVILLE 2030 MOBILITY PLAN STUDY UPDATE GOALS, OBJECTIVES, AND PERFORMANCE MEASURES 3.20.2017 PREPARED FOR: CITY OF JACKSONVILLE 55 Railroad Row White River Junction, VT 05001 802.295.4999
More informationTransform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016
Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016 The Memorandum of Agreement (MOA) for the Transform 66: Inside the Beltway Project directs NVTC to
More informationGENERAL NOTES FOR WORK ZONE SAFETY SET UP GUIDE
FORWARD It shall be the responsibility of the person in charge to institute the placing of all appropriate cautionary devices and controls as may be required for the particular job. Traffic protection
More informationFunding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.
FACT SHEET GENERAL INFORMATION The project extends the existing No.7 Line subway service via a 1.5 mile extension from Times Square to the new 34 Street Hudson Yards station located at West 34th Street
More informationAlder Drive / Blair Road Bridge Replacement Projects
Alder Drive / Blair Road Bridge Replacement Projects Presented By: County of El Dorado Community Development Agency Transportation Division Matthew Smeltzer, P.E. Deputy Director of Engineering Paul Hom,
More informationRehabilitation of Prater junction
Dominik Rabl Introduction Linking the A23 Südosttangente motorway and the A4 Ost Autobahn motorway, Prater junction is one of the most important traffic junctions in the primary Austrian road network.
More informationTHE NEW BUCK O'NEIL (U.S. 169) CROSSING
THE NEW BUCK O'NEIL (U.S. 169) CROSSING A crossroads connecting the nation. TIGER Discretionary Grant Application FY 2017 National Infrastructure Investments The City of Kansas City, Missouri TIGER9-FY17
More informationPLAN 2040 Regional Transportation Plan Update. Final Recommendations. Transportation and Air Quality Committee March 13, 2014
PLAN 2040 Regional Transportation Plan Update Final Recommendations Transportation and Air Quality Committee March 13, 2014 TIP/RTP Update Milestones Official public comment period closed February 21 Final
More informationCITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way
CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY Guidance on restoration of City Rights-of-Way Public Works Department Directors Office 747 Market Street Suite 408 Tacoma, WA 98402 253-591-5525 Right-of-Way
More informationEMERGENCY OPERATIONS Educational Series
EMERGENCY OPERATIONS 2017 Educational Series TXDOT DISASTER AND EMERGENCY PREPAREDNESS, RESPONSE AND RECOVERY OVERVIEW The importance of safe and reliable transportation solutions is heightened during
More informationGreenDOT Advisory Group
GreenDOT Advisory Group Massachusetts Department of Transportation Kick-Off Meeting 1 Leading the Nation in Transportation Excellence www.mass.gov/massdot GreenDOT Policy Development and Implementation
More informationTECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &
TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed
More informationManagement. VA SITE Annual Meeting June 27, 2013 Jay Styles Performance and Strategic t Planning Manager, Business Transformation Office
VDOT and MAP-21 Performance Management VA SITE Annual Meeting June 27, 2013 Jay Styles Performance and Strategic t Planning Manager, Business Transformation Office Overview Map-21- How is VDOT Preparing?
More informationTech Brief PRECAST CONCRETE PAVEMENT IMPLEMENTATION BY U.S. HIGHWAY AGENCIES
OCTOBER 2015 FHWA-HIF-16-007 Tech Brief PRECAST CONCRETE PAVEMENT IMPLEMENTATION BY U.S. HIGHWAY AGENCIES INTRODUCTION Precast concrete pavement (PCP) technology is gaining wider acceptance in the U.S.
More informationTRANSPORTATION IMPACT STUDIES
January 28, 2009 POLICIES AND PROCEDURES FOR TRANSPORTATION IMPACT STUDIES Related to Highway Occupancy Permits Pennsylvania Department of Transportation Bureau of Highway Safety and Traffic Engineering
More informationSUPPLEMENTAL ECMS ADVANCED INFORMATION JULY 14, 2016 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)
Updated June 27, 2016 BEAVER COUNTY SR 7446(LBB) #92912 PROPOSAL:$54.72 PLANS:$42.46 12X18:$52.11 24X36:$752.70 EXSTRUCT:$48.62 12X18:$59.67 24X36:$861.90 The description and location of the project is
More information