Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Size: px
Start display at page:

Download "Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014"

Transcription

1

2 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend Work How to Stay Connected Q & A 2

3 Update on FTA Full Funding Grant Agreement Submit New Starts Update September 2013 New Starts Financial Plan October 2013 GLX Project in President s Budget Report March 2014 Submit FFGA Application September 2014 Full Funding Grant Agreement Winter

4 Project Phasing

5 GLX PHASE 1 CONSTRUCTION UPDATE 5

6 Phase 1: Early Bridge & Demolition Package Medford Street Rail Bridge Harvard Street Rail Bridge 21 Water Street Demolition 6

7 Phase 1 Update: 21 Water Street Demolition 7

8 Phase 1 Update: 21 Water Street Demolition 8

9 Medford Street Railroad Bridge, Somerville 9 #9

10 Medford Street Railroad Bridge Widening 10 #10

11 Balance of 2014 Medford Street Bridge Work as Planned: Continue concrete abutment modification work in advance of steel erection activities to widen the bridge structure: o 8/11 TBD (single lane closures) 3 to 4 weekend, full roadway closures planned for bridge widening steel erection (please note that dates are forecast and subject to change): o 9/13 9/14/14 - COMPLETED o 10/4 10/5/14 o 10/25 10/26/14 o Additional weekend to be determined (if necessary) Complete structural steel fit-up and final painting: o several weeks of single lane closures 11 #11

12 Medford Street Railroad Bridge Construction 12 #12

13 Harvard Street Railroad Bridge, Medford Future Track Location 13 #13

14 Harvard Street Railroad Bridge, Medford Work Includes: Widening Bridge Retaining & Noise Walls Moving Commuter Rail into Final Alignment Utility & Drainage Work 14 #14

15 Harvard Street Railroad Bridge, Medford 15 #15

16 Harvard Street Railroad Bridge, Medford Future contract will include corridor work on south side & build Green Line 16 #16

17 GLX Upcoming Milestones Submit FFGA Application Fall 2014 Begin Early Work Construction Fall 2014 o GMP#1-Procurement of Long Lead Items o GMP#2-Early Utilities Phases 2/2A & 4 o GMP#3-Miller s River & Fitchburg Line Full Funding Grant Agreement Winter Begin GMP#4 Phase 2/2A Construction Spring 2015 Service Begins: Lechmere, Washington St. & Union Sq.: December 2017 Gilman Sq., Lowell St., Ball Sq. & College Ave.: Summer

18 GLX EARLY CONSTRUCTION WORK 18

19 Long Lead Items Specialty trackwork Switch Machines Switch Heater Signal Bungalows Traction Power Equipment Washington Street Bridge Steel 19

20 Long Lead Items Specialty Track Work 20

21 Long Lead Items Switch Machines 21

22 Long Lead Items Signal Bungalow 22

23 Drainage 23

24 Utilities School St Utility Bridge 24

25 Utilities Medford St Utility Bridge 25

26 Utilities Broadway Utility Bridge 26

27 Union Square Branch Construction 27

28 Union Square Branch Construction 28

29 Accessing the Corridor 29

30 Construction Haul Road 30

31 Clearing & Grubbing 31

32 Clearing & Grubbing 32

33 Construction Mitigation Noise Mitigation Plan Will comply with local city & town noise ordinances Dust Control Plan Wheel Washers Street Sweeping Calcium Chloride Rodent Control Plan Preconstruction Surveys Soil Testing & Characterization 33

34 Night & Weekend Work Night Work at the MBTA Boston Engine Terminal 4:00 AM 1:30 PM Shift Weekend Work in 2015 &

35 GLX Upcoming Meetings GLX Working Group Meeting Oct. 2, PM, Center for the Arts Armory, Somerville Upcoming Station Design Public Meetings: o Lechmere October 2014 o Washington Street & Union Square October

36 How to Stay Informed and Follow the Progress of Construction MassDOT GLX Website: 3 Week Look Ahead Schedules Construction Progress Photos Traffic Updates Public Meetings Sign-up for Regular Blasts Contact Information: info@glxinfo.com Emergency Construction Hotline GLX-INFO 24/7 Coverage 36 #36

37

GREEN LINE EXTENSION PROJECT

GREEN LINE EXTENSION PROJECT GREEN LINE EXTENSION PROJECT RETAINING WALLS & NOISE BARRIERS AGENDA Upcoming Meeting Schedule Wall Aesthetics/ Design FTA Guidelines for Assessing & Mitigating Noise Impact Plans & Cross Sections Typical

More information

GLX Project AUGUST 2 4 FMCB MEETING

GLX Project AUGUST 2 4 FMCB MEETING GLX Project Green Line Extension Project AUGUST 2 4 FMCB MEETING Presentation Overview 1) Project Essentials 2) Funding the Green Line Extension Project 3) The Construction Manager/General Contractor Procurement

More information

Green Line Extension Project. March 28, 2018 Public Information Meeting

Green Line Extension Project. March 28, 2018 Public Information Meeting Green Line Extension Project 1 Agenda GLX Project-Wide Public Meeting March 7, 2018; 6:30 PM 8:00 PM 1. Welcome/Introductions Martin Nee (MBTA Stakeholder Support) 2. Project Update John Dalton (MBTA Program

More information

Somerville Public Meeting, October 23, Somerville High School October 23, 2017

Somerville Public Meeting, October 23, Somerville High School October 23, 2017 Somerville Public Meeting, 1 Agenda Somerville GLX Public Meeting ; 6:30 PM 8:00 PM 1. Welcome/Introductions Martin Nee 2. Project Update MBTA Program Manager John Dalton 3. Early Works Construction Overview

More information

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices DRFT ppendices MIS 8-05 - ppendices ppendices ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK] DRFT ppendix Tier Detailed Evaluation Tables MIS 8-05 - ppendix ppendix ugust 005 [THIS PGE INTENTIONLLY LEFT BLNK]

More information

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session

Green Line Extension EOT. Project Location. Project Purpose. Environmental Impact Report Public Scoping Session Green Line Extension Environmental Impact Report Public Scoping Session Somerville High School October 16, 2006 Project Location Green Line Extension Project Purpose Implement enhancements to transit services

More information

Miscellaneous Demolition & Concrete Removal Future Ball Square Station

Miscellaneous Demolition & Concrete Removal Future Ball Square Station Green Line Extension Project Construction Outlook (July 22 Aug. 17) Work schedule subject change based on weather or other factors = New information since last update Miscellaneous Demolition & Concrete

More information

14-Dec-2016 Public Meeting Medford City Hall

14-Dec-2016 Public Meeting Medford City Hall 1 Agenda December 14, 2016 1. Update on GLX Status a. New Program Manager, John Dalton b. Work of the Interim Program Management Team 2. Design Build (DB) contractor selection process and timeline 3. Latest

More information

Green Line extension Project Fall 2009

Green Line extension Project Fall 2009 Introduction The Massachusetts Department of Transportation (MassDOT) is proposing to extend the Green Line to improve transit service, mobility, and regional access for residents and visitors of Cambridge,

More information

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation Table of Contents Acronyms and Abbreviations Secretary s Certificate on the EENF Executive Summary 1 Introduction and Background... 1-1 1.1 Introduction... 1-1 1.2 Project Summary... 1-2 1.3 Permits and

More information

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting

Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY. November 20, 2017 Public Information Meeting Green Line COLLEGE AVENUE TO MYSTIC VALLEY PARKWAY Purpose of tonight s meeting A Notice of Project Change (NPC) has been published for a possible extension of the Green Line from College Avenue to Mystic

More information

Construction Manager / General Contractor CM/GC Procurement Case Study February 2016

Construction Manager / General Contractor CM/GC Procurement Case Study February 2016 Construction Manager / General Contractor CM/GC Procurement Case Study February 2016 WORLD TRADE CENTER PATH TERMINAL PROJECT MBTA GREEN LINE EXTENSION PROJECT Federal Transit Administration Wendy A. Lee,

More information

Massachusetts Bay Transportation Authority

Massachusetts Bay Transportation Authority Massachusetts Bay Transportation Authority Request for Qualifications For Construction Manager/General Contractor (CM/GC) Services Green Line Extension Project Cambridge, Somerville, Medford, Massachusetts

More information

View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019

View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019 View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019 AGENDA MBTA By The Numbers FY 2020-2024 Capital Investment Overview and Programs FY 2019 Major Program Highlights Doing Business

More information

CHAPTER FIVE. Determination of Air Quality Conformity BACKGROUND. Timely Implementation of Transportation Control Measures

CHAPTER FIVE. Determination of Air Quality Conformity BACKGROUND. Timely Implementation of Transportation Control Measures 5 CHAPTER FIVE Determination of Air Quality Conformity BACKGROUND The Commonwealth of Massachusetts is classified as unclassifiable/attainment for the ozone standard with the exception of Dukes County.

More information

Identification and Evaluation of Alternatives Tier 1

Identification and Evaluation of Alternatives Tier 1 Vanasse Hangen Brustlin, Inc. DRAFT 4 Identification and Evaluation of Alternatives Tier This chapter describes the initial set of alternatives that were identified to address the Purpose and Need of the

More information

Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No

Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No. 605287 25% Design Public Hearing Chelsea City Hall January 24, 2018 6:30 p.m. Introduction Welcome & Introductions by MassDOT PM

More information

6 Draft Section 61 Findings and Mitigation Commitments

6 Draft Section 61 Findings and Mitigation Commitments 6 Draft Section 61 Findings and Mitigation Commitments 6.1 Introduction This chapter presents the proposed mitigation program of the Executive Office of Transportation (EOT) to address adverse environmental

More information

June 30, Mr. Martin Suuberg Commissioner Department of Environmental Protection 1 Winter Street Boston, MA Dear Commissioner Suuberg:

June 30, Mr. Martin Suuberg Commissioner Department of Environmental Protection 1 Winter Street Boston, MA Dear Commissioner Suuberg: Charles D. Baker, Governor Karyn E. Polito, Lieutenant Governor Stephanie Pollack, MassDOT Secretary & CEO massdot Massachusetts Department of Transportation Mr. Martin Suuberg Commissioner Department

More information

REGION I. August 12, Re: Green Line Extension Project - Risk Assessment Review RepOli

REGION I. August 12, Re: Green Line Extension Project - Risk Assessment Review RepOli REGION I Volpe Cenler Connecticut, Maine, 55 Broadway Suile 904 Massachusetts, Cambridge, MA 02142-1093 U.S. Department of Transportation Federal Transit New Hampshire, 617-494-2055 Administration Rhode

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION MEMORANDUM. DATE January 21, 2010 BOSTON REGION METROPOLITAN PLANNING ORGANIZATION State Transportation Building Ten Park Plaza, Suite 2150 Boston, MA 02116-3968 Tel. (617) 973-7100 Fax (617) 973-8855 TTY (617) 973-7089 www.bostonmpo.org

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 10 December 18, 2017 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next:

More information

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction

Tonight s Agenda. 6:00 pm Open House 6:30 pm Presentation. 7:45 pm Return to Open House 8:30 pm Close. Introduction. Roosevelt Station Construction Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Roosevelt Station Construction Kristin Hoffman, Station Project Manager Next Steps

More information

Acton Parking Committee. Presented by:

Acton Parking Committee. Presented by: Presented to: Acton Parking Committee Presented by: The MBTA/HNTB Team MARCH 2009 Project Goals Improve Performance Increase Transit Reliability Decrease Travel Time Key Project Elements Engineering Work

More information

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018 Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day

More information

I-290 Construction Approach. April 2016

I-290 Construction Approach. April 2016 I-290 Construction Approach April 2016 1 AGENDA Project Process - Phase I, II, & III Overall guiding principles I-290 construction approach I-290 construction schedule Construction mitigation Best Practices

More information

Massachusetts Department of Transportation Massachusetts Bay Transportation Authority

Massachusetts Department of Transportation Massachusetts Bay Transportation Authority Massachusetts Department of Transportation Massachusetts Bay Transportation Authority State Implementation Plan Transit Commitments Monthly Status Report September 20, 2012 For questions on this document,

More information

Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116

Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments on this Environmental Assessment (EA) and may be submitted in writing to: Katherine S. Fichter MassDOT Office of Transportation Planning 10 Park Plaza, Room 4150 Boston, MA 02116 Comments must

More information

Impact Assessment Methodology for the. Somerville Public Library August 4, 2008 Jason Ross, P.E. Harris Miller Miller & Hanson Inc.

Impact Assessment Methodology for the. Somerville Public Library August 4, 2008 Jason Ross, P.E. Harris Miller Miller & Hanson Inc. Noise and Vibration Impact Assessment Methodology for the MBTA Green Line Extension P j t Project Presentation to the Advisory Group Meeting Meeting Somerville Public Library August 4, 2008 Jason Ross,

More information

9 Before and After Study Plan

9 Before and After Study Plan 9 Before and After Study Plan A Before and After Study Plan has been prepared, describing how the Massachusetts Bay Transportation Authority (MBTA), in cooperation with the Massachusetts Department of

More information

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010 I-405 Sepulveda Pass Widening Project Community Advisory Committee Meeting June 24, 2010 1 MWD LA-29 Project Drilling to install beams for shoring to support excavation at Sunset Bl and Church Ln 2 MWD

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting Regional Connector Transit Project Construction Update June 9, 2016 Project Wide Community Meeting 1 Agenda > Introductions & Project Overview > Tunnel Boring Machine Update > Construction Updates > Community

More information

LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION LONG-RANGE TRANSPORTATION PLAN OF THE BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Volume I September 22, 2011 The Boston Region Metropolitan Planning Organization (MPO) is composed of: Massachusetts

More information

Atlantic Street Bridge Project CTDOT Project Nos (Phase 1) & (Phase 2)

Atlantic Street Bridge Project CTDOT Project Nos (Phase 1) & (Phase 2) Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement City of Stamford www.atlanticstreetbridge.com

More information

Project Steering Committee April 14, 2015

Project Steering Committee April 14, 2015 Project Steering Committee April 14, 2015 Agenda Project Background and Schedule Agency Coordination Project Need and Purpose Alternatives Under Consideration Resources Stakeholder and Public Involvement

More information

Brooklyn Station Construction Open House

Brooklyn Station Construction Open House Brooklyn Station Construction Open House November 16, 2011 Tonight s Agenda 6:00 pm Open House 6:30 pm Presentation Introduction Ron Endlich, North Link Deputy Project Director Louise Little, Greater University

More information

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018 1 Agenda Project Overview Section 1 Construction Updates Wilshire/La Cienega Station Excavation Section 2 Pre-Construction

More information

METRO BOARD OF DIRECTORS Capital and Strategic Planning

METRO BOARD OF DIRECTORS Capital and Strategic Planning Thomas C. Lambert PRESIDENT & CEO METRO BOARD OF DIRECTORS Capital and Strategic Planning Working Committee Meeting METRO Board Room, 2 nd Floor August 22, 2016, 1:30 PM ACTION COMMITTEE MEMBERS Christof

More information

MassDOT Highway Presentation to ACEC October 7, 2017

MassDOT Highway Presentation to ACEC October 7, 2017 MassDOT Highway Presentation to ACEC October 7, 2017 Highway Administrator Jonathan Gulliver About MassDOT Highway Created in 2009 By a Special Act of the Legislature - An Act Modernizing the Transportation

More information

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016 Rt. 29 Solutions Project Delivery Advisory Panel February 18, 2016 Agenda item 1: Introductions Project Delivery Advisory Panel Technical Team 2 Agenda item 2: Interaction and Feedback Live Streaming Feb

More information

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016 Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations

More information

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening March 5, 2009 Nicholas J. Roper NOVA District Bridge Engineer Robert F. Price Resident Administrator of Loudoun/ Prince William Construction

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update October 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: October 1, 2015

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Expo Board Presentation Monthly Project Status Update May 1, 2008 PHASE 1 Phase 1 Project Status Design Design approximately 86% complete Construction Construction

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Downtown Corridor USC Galen Center November 13, 2007 Project Summary 8.6 mile corridor from 7th/Metro to Culver City 1.3 miles shared with Metro Blue Line 10 stations,

More information

Welcome! Overview Agenda: 6:00 pm 6:30 pm: Welcome & Sign-In. 6:30 pm 7:00 pm: Link US Presentation. 7:00 pm 8:00 pm: Open House

Welcome! Overview Agenda: 6:00 pm 6:30 pm: Welcome & Sign-In. 6:30 pm 7:00 pm: Link US Presentation. 7:00 pm 8:00 pm: Open House Welcome! Overview Agenda: 6:00 pm 6:30 pm: Welcome & Sign-In 6:30 pm 7:00 pm: Link US Presentation 7:00 pm 8:00 pm: Open House 1 Link Union Station (Link US) (formerly SCRIP) Scoping Meeting & Open House

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2015 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury

Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury EAE No. 14427 http://whittierbridge.mhd.state.ma.us/ Public Meeting 12.07.11 Whittier Bridge I-95 Improvement Project Newburyport/Amesbury/Salisbury

More information

HUDSON TUNNEL PROJECT

HUDSON TUNNEL PROJECT HUDSON TUNNEL PROJECT NORTH BERGEN COMMUNITY MEETING Lido Restaurant 2600 Tonnelle Avenue North Bergen, NJ January 30, 2018 6:00-8:00 PM Agenda Project Overview Construction Activities in North Bergen

More information

Safe, innovative, quality construction since Riding on the Strength

Safe, innovative, quality construction since Riding on the Strength Safe, innovative, quality construction since 1880 Riding on the Strength of EXPERIENCE The Expertise The Experience The People The Equipment The Work Ethic The quality To get your job done safely, on time

More information

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

UNION STATION RAIL CORRIDOR 2017 CONSTRUCTION LOOK-AHEAD

UNION STATION RAIL CORRIDOR 2017 CONSTRUCTION LOOK-AHEAD UNION STATION RAIL CORRIDOR 2017 CONSTRUCTION LOOK-AHEAD MANUEL PEDROSA, MANAGER COMMUNITY RELATIONS, ENVIRONMENTAL ASSESSMENTS (RER) - METROLINX TORONTO, ONTARIO, CANADA AGENDA Introductions Union Station

More information

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016 Purple Line Extension Beverly Hills Community Meeting August 22, 2016 1 3 Purple Line Extension Project Alignment 2 Section 2 and 3 Status Under Construction Forecasted Schedule Section 1 Section 2 Section

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017 VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident

More information

Organization. Project Management Institute, Olympia Chapter Date Nov. 20, 2012

Organization. Project Management Institute, Olympia Chapter Date Nov. 20, 2012 Organization Project Management Institute, Olympia Chapter Date Nov. 20, 2012 Program Overview The Alaskan Way Viaduct Replacement Program includes projects led by the Washington State Department of Transportation,

More information

Everett Transit Action Plan Open House and Community Meeting

Everett Transit Action Plan Open House and Community Meeting Everett Transit Action Plan Open House and Community Meeting Meeting Summary LOCATION OF MEETING: Edward G. Connolly Center, 90 Chelsea Street, Everett, MA DATE/TIME OF MEETING: February 11, 2016, Open

More information

Gold Line Environmental Impact Statement (EIS)

Gold Line Environmental Impact Statement (EIS) Gold Line Environmental Impact Statement (EIS) Workshop No. 3 Level 3, Detailed Evaluation February 5 and 7, 2007 1 Agenda Introduction Railroad (RR) Negotiations Update What is the Project? Mission of

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update January 1, 2016 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Project Overview The Ironton Russell Bridge Project entails

More information

Construction Project Briefing. November 14, 2012

Construction Project Briefing. November 14, 2012 Construction Project Briefing November 14, 2012 Today s Presentation Loop Track Purple Line Viaducts North Red Line Stations 2 Project Title: Loop Track Renewal Project Managing Department: Power & Way

More information

Greenbush Project FAQ's Last Updated: July 26, 2004

Greenbush Project FAQ's Last Updated: July 26, 2004 Greenbush Project FAQ's Last Updated: July 26, 2004 The Service Q: When will service start? A: Service is currently scheduled to start in mid-2006. The exact date has not yet been set. Q: What will the

More information

Winnipeg River Bridge on PR313 at Lac du Bonnet. June 2014

Winnipeg River Bridge on PR313 at Lac du Bonnet. June 2014 Winnipeg River Bridge on PR313 at Lac du Bonnet June 2014 Regional Context Local Area Purpose and Need The Winnipeg River Bridge on PR313 was originally constructed in 1930 as a trolley and vehicle bridge.

More information

Russell Street Design STPU M 8105(8) UPN

Russell Street Design STPU M 8105(8) UPN May 24, 2012 MORRISON MAIERLE,INC. Russell Street Design STPU M 8105(8) UPN 4128000 Missoula, Montana Project Understanding Key Project Elements Major urban arterial 1 of 5 river crossings over the Clark

More information

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013 Meeting Agenda Pre-Construction Meeting Meeting Purpose and Format Project Status Update Introduction of Construction Contractor

More information

Northern Branch Corridor CLC Meeting. June 30, 2008

Northern Branch Corridor CLC Meeting. June 30, 2008 Northern Branch Corridor CLC Meeting June 30, 2008 Agenda Introductions Project Status Environmental Process Technical Findings Capital Costs Next Steps Break Out Areas Introductions Project Status Preliminary

More information

Ironton Russell Bridge Project

Ironton Russell Bridge Project Construction Update March 1, 2014 Rendering by URS Responsible for Construction Inspection & Engineering Prepared by: Brian Davidson, P.E. Ironton Russell Bridge Project Project Summary: March 1, 2014

More information

MBTA Federal Capital Program Table 1: FFYs Draft TIP Amendment Two, REVISED Presented to the Boston MPO on 12/21/2017

MBTA Federal Capital Program Table 1: FFYs Draft TIP Amendment Two, REVISED Presented to the Boston MPO on 12/21/2017 MBTA Federal Capital Program Table 1: FFYs 2018-2022 Draft TIP Amendment Two, REVISED Presented to the Boston MPO on 12/21/2017 Project Information FY18-22 TIP (Federal Share Only) FFY18-22 FFY18-22 FFY18

More information

Overview of Construction Activities

Overview of Construction Activities Chapter 5.0 Overview of Construction Activities This chapter describes, to the extent feasible, how construction of the Preferred Alternative might be undertaken and summarizes the measures that have been

More information

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors Keith Couch Capital Rail Constructors January 2018 Agenda 1. Safety 2. Schedule

More information

Constructability Guidelines

Constructability Guidelines Constructability Guidelines The Constructability Guidelines offer a list of items that should be considered by Constructability function personnel during the Concept Development Phase through the Final

More information

Schuylkill Avenue Phase I Community Briefing Summary and Notes December 2, 2013

Schuylkill Avenue Phase I Community Briefing Summary and Notes December 2, 2013 Schuylkill Avenue Phase I Community Briefing Summary and Notes December 2, 2013 Representatives from The Children s Hospital of Philadelphia (CHOP), joined by design firm, Cooper Robertson & Partners,

More information

Willmar Wye Public Open House #4 and Public Hearing

Willmar Wye Public Open House #4 and Public Hearing Willmar Wye Public Open House #4 and Public Hearing February 23, 2017 www.dot.state.mn.us/d8/willmarwye Agenda Time Topic 5:00 pm Open House Opportunity for the public to ask questions of project staff

More information

Neptune Cargill Overpass Extension

Neptune Cargill Overpass Extension Project Environmental Review UPDATE November 23, 2017 Northshore Waterfront Liaison Committee Teck Agenda Project Objectives Project Description Project Discussion VFPA PER process Project Review Status

More information

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA)

DRAFT. Preliminary Evaluation. Analysis of Brownfields Cleanup Alternatives (ABCA) DRAFT Analysis of Brownfields Cleanup Alternatives (ABCA) Preliminary Evaluation Ball Square Station Site Boston Avenue and Broadway Somerville and Medford, Massachusetts Massachusetts DEP Release Tracking

More information

FOCUS40 MassDOT Board Presentation March 13, 2017

FOCUS40 MassDOT Board Presentation March 13, 2017 FOCUS40 MassDOT Board Presentation March 13, 2017 What is Focus40? A 25-year strategic plan for how the MBTA can meet the needs of the region in 2040. Focus40 is: Highlighting long-term performance, reliability,

More information

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017 Palo Alto Rail Committee Meeting November 29, 2017 Slide 1 Project Area Millbrae Station City Limits Existing Railroad Crossing at Broadway Caltrain Operational Constraint Major Constraints Millbrae Station

More information

Ohio Contractor Association Annual Work Forecast Program. John Picuri, District 4 Deputy Director Myron Pakush, District 12 Deputy Director

Ohio Contractor Association Annual Work Forecast Program. John Picuri, District 4 Deputy Director Myron Pakush, District 12 Deputy Director Ohio Contractor Association Annual Work Forecast Program John Picuri, District 4 Deputy Director Myron Pakush, District 12 Deputy Director John R. Kasich, Ohio Governor Jerry Wray, ODOT Director ODOT S

More information

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates November 29, 2017 Charles W. Stark Executive Project Director Silver Line: Phase 2 Station Tour Phase 1 Phase 1 Cost Summary Expenditures (May

More information

Maintains the status quo even though deteriorated. To keep at original condition or use.

Maintains the status quo even though deteriorated. To keep at original condition or use. Chapter 14 14.1 ROUTINE MAINTENANCE Maintains the status quo even though deteriorated. To keep at original condition or use. NOTE: All items include labor and material. Ma 1 Smoothing Surface - Strictly

More information

MAINE MEDICAL CENTER

MAINE MEDICAL CENTER MAINE MEDICAL CENTER Construction Projects at the East Tower, Visitor Garage, Central Utility Plant Construction Management Plan December 15, 2017 Prepared for: Portland Department of Planning & Urban

More information

Central 70 Project. American Association of Cost Engineers (AACE) Rocky Mountain Section (RMS) January 17, 2019

Central 70 Project. American Association of Cost Engineers (AACE) Rocky Mountain Section (RMS) January 17, 2019 Central 70 Project American Association of Cost Engineers (AACE) Rocky Mountain Section (RMS) January 17, 2019 Project Location Topics 1) Project Overview 2) P3 Partnership 3) Completed Work & Lowered

More information

8 AIR-QUALITY CONFORMITY

8 AIR-QUALITY CONFORMITY 8 AIR-QUALITY CONFORMITY DETERMINATION AND GREENHOUSE GAS ANALYSIS INTRODUCTION This chapter presents information about the air quality analyses that are required by both federal and state legislation.

More information

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017

UCSF Mission Bay & Dogpatch Construction Community Meeting 11/7/2017 UCSF Mission Bay & Dogpatch Construction Community Meeting Agenda Welcome Project Communications Construction Context Project Updates Minnesota Housing Center for Vision Neuroscience Precision Cancer Medicine

More information

Dulles Corridor Metrorail Project

Dulles Corridor Metrorail Project Dulles Corridor Metrorail Project MONTHLY COST AND SCHEDULE UPDATE FOR PHASES 1 AND 2 AS OF SEPTEMBER 30, 2014 November 2014 0 Phase 1 Cost Summary September Expenditures $ 2.5 Million Total Expenditures

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

WELCOME EAST LINK OVERLAKE MASTER PLANNED DEVELOPMENT

WELCOME EAST LINK OVERLAKE MASTER PLANNED DEVELOPMENT WELCOME The purpose of tonight s meeting is to: Educate the Overlake community about why Sound Transit is applying for a Master Planned Development Permit to build East Link within the City of Redmond

More information

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House May 22, 2018 1 Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House Rendering of Trail and Community Improvements at Project Completion 2

More information

CLA /10.54, PID Project Description:

CLA /10.54, PID Project Description: Project Description: The proposed project will consist of widening IR 70 to three lanes from Enon Road (SLM 06.75) to the US 68 interchange ramps (SLM 10.55). IR 70 is a component of the Strategic Highway

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

ALAMEDA CORRIDOR EAST San Gabriel Valley

ALAMEDA CORRIDOR EAST San Gabriel Valley ALAMEDA CORRIDOR EAST San Gabriel Valley San Pedro Bay ports: 40% of nation s imports; 30% of exports. ACE Trade Corridor: 21% of waterborne containers entering/exiting the U.S. 81 trains/day (2009) 141

More information

The compilation of these commitments reflects the project elements essential to those we ve engaged:

The compilation of these commitments reflects the project elements essential to those we ve engaged: Hon. Kemp Hannon NYS Senate, Capitol 420 Albany, NY 12247 Hon. Elaine Phillips NYS Senate, 848 LOB Albany, NY 12247 Dear Senator Hannon and Senator Phillips: I would like to share with you a summary of

More information

Engineering & Construction -- Transit Status Report. Significant Issues

Engineering & Construction -- Transit Status Report. Significant Issues ITEM XX Engineering & Construction -- Transit Status Report Significant Issues Presented By Bryan Pennington Executive Director Engineering and Construction 1 1 I-405 SEPULVEDA PASS IMPROVEMENTS PROJECT

More information

Metro Blue Line Improvements & Project Update

Metro Blue Line Improvements & Project Update Metro Blue Line Improvements & Project Update February 9, 2018 MBL Operational Improvements - External Metro & LADOT coordination to identify traffic signal and intersection treatments aimed at increasing

More information

VII. FREIGHT MANAGEMENT

VII. FREIGHT MANAGEMENT VII. FREIGHT MANAGEMENT The regional transportation network must not only move people safely and efficiently, but must also facilitate the safe and efficient transportation of goods as well. Local freight

More information

MBTA Green Line Extension Noise and Vibration Technical Report

MBTA Green Line Extension Noise and Vibration Technical Report MBTA Green Line Extension Noise and Vibration Technical Report Environmental Assessment HMMH Report No. 302580.000 January, 2011 Prepared for: Vanasse Hangen & Brustlin, Inc. 99 High Street Boston, MA

More information

Updating Sound Transit s Long-Range Plan. ITE November 12, 2013

Updating Sound Transit s Long-Range Plan. ITE November 12, 2013 Updating Sound Transit s Long-Range Plan ITE November 12, 2013 The Sound Transit district Today s regional transit system Serving more riders each year Millions of annual Boardings Responding to the recession

More information